S.N.

Mandatory Points before grid charging Category Remarks

1. Connectivity of grid to approach roads from both


Safety
main gates.
2. Provision of Electrical and mechanical interlock of
Safety
Isolator and CB.
3. Integration of Fire alarm and smoke detector system
Safety
with SCADA
4.
Provision of Rubber Mat at all required location. Safety

5. Provision of Clamps on yard light poles for safe


Safety
working.
Availability of Trench cover at all location and
6.
provision of handles after every 9th trench cover for Safety
lifting.
7.
Availability of Cable root marker for U/G cables Safety
8.
Door Earthing of all gates including MOM boxes Safety

9. Ladder/staircase to be provided for way to water


Safety
tank on roof.
10.
Yard light Switching Box to be provided outside yard Safety

11. Availability concertina wire on the boundary wall of


Safety
grid s/stn.
12. Availability of special tools related to grid equipment
Safety
operation and maintenance of equipments.
13.
Availability of water in Wash Basin in Battery Room. Safety

14. Availability of security arrangement with


Security
communication facilities.
15.
Availability of proper lighting in Yard and building. Security
16.
Availability of safety charts / Grid SLD. Operation

17. Interconnectivity of all trenches and sump pump


Operation
should be operational.
18. Vermin proofing of control cables pipes and control
Operation
panel should be done.
19.
Cleaning of all Earthing pits. Operation
20.
Dressing of wiring in control panels. Operation
All jumper and bus bar of 11 KV sides of PTRs ,
21.
local Transformer and capacitor bank should be Operation
insulated.
Availability of Exhaust fan with cross ventilation at
22.
all required places (ACDB, Battery , VCB, and Operation
control room) with auto change over relay
Availability of cable cleats and proper clamping
23.
structure on 33KV and 11KV on respective power Operation
cables.
24.
Availability substation name board. Operation
25.
All indication lamps should be in working condition. Operation
26.
Availability of duplicate supply source. Operation
27. As built Drawings and manuals availability at control
Operation
Room in Hard.
28. Provision of invertor for the AC supply arrangement
Operation
in case of local/duplicate Supply Failure.
One day on site (grid) operation training to all SMC
29.
and HMC (or at least concerned SMC and HMC) Operation
before Grid manger.
Parallel laying of 11 KV cables in 11 KV Panels by
30.
DP after approval of NEG and permission of Operation
concerned PO and Grid manager
31.
Cleaning of entire Trenches ( Power, Control) Operation
32. Earthing of lighting protection shield should be
Equipment Safety
connected to earth mat of grid.
33. No unwanted holes should be present in trench of
Equipment Safety
VCB room , main boundary wall
34. Availability bird caps on all capacitor bank cells
Equipment Safety
units.
35.
NIDS should be operation in PTRs. Equipment Safety
36. Proper sewage connection and wash rooms should
Equipment Safety
be in working condition.
37.
Availability of drinking water with water cooler Basic Amenities
38. Inspection of OLTC during erection by STS for auto
Basic Amenities
work.
39.
DC leakage should not be there. Equipment Safety
40.
Scrap and excess material disposal from site. Equipment Safety
41.
Fire barrier and Fire coating at power cables. Equipment Safety