Mandatory Points before grid charging Category Remarks
1. Connectivity of grid to approach roads from both
Safety main gates. 2. Provision of Electrical and mechanical interlock of Safety Isolator and CB. 3. Integration of Fire alarm and smoke detector system Safety with SCADA 4. Provision of Rubber Mat at all required location. Safety
5. Provision of Clamps on yard light poles for safe
Safety working. Availability of Trench cover at all location and 6. provision of handles after every 9th trench cover for Safety lifting. 7. Availability of Cable root marker for U/G cables Safety 8. Door Earthing of all gates including MOM boxes Safety
9. Ladder/staircase to be provided for way to water
Safety tank on roof. 10. Yard light Switching Box to be provided outside yard Safety
11. Availability concertina wire on the boundary wall of
Safety grid s/stn. 12. Availability of special tools related to grid equipment Safety operation and maintenance of equipments. 13. Availability of water in Wash Basin in Battery Room. Safety
14. Availability of security arrangement with
Security communication facilities. 15. Availability of proper lighting in Yard and building. Security 16. Availability of safety charts / Grid SLD. Operation
17. Interconnectivity of all trenches and sump pump
Operation should be operational. 18. Vermin proofing of control cables pipes and control Operation panel should be done. 19. Cleaning of all Earthing pits. Operation 20. Dressing of wiring in control panels. Operation All jumper and bus bar of 11 KV sides of PTRs , 21. local Transformer and capacitor bank should be Operation insulated. Availability of Exhaust fan with cross ventilation at 22. all required places (ACDB, Battery , VCB, and Operation control room) with auto change over relay Availability of cable cleats and proper clamping 23. structure on 33KV and 11KV on respective power Operation cables. 24. Availability substation name board. Operation 25. All indication lamps should be in working condition. Operation 26. Availability of duplicate supply source. Operation 27. As built Drawings and manuals availability at control Operation Room in Hard. 28. Provision of invertor for the AC supply arrangement Operation in case of local/duplicate Supply Failure. One day on site (grid) operation training to all SMC 29. and HMC (or at least concerned SMC and HMC) Operation before Grid manger. Parallel laying of 11 KV cables in 11 KV Panels by 30. DP after approval of NEG and permission of Operation concerned PO and Grid manager 31. Cleaning of entire Trenches ( Power, Control) Operation 32. Earthing of lighting protection shield should be Equipment Safety connected to earth mat of grid. 33. No unwanted holes should be present in trench of Equipment Safety VCB room , main boundary wall 34. Availability bird caps on all capacitor bank cells Equipment Safety units. 35. NIDS should be operation in PTRs. Equipment Safety 36. Proper sewage connection and wash rooms should Equipment Safety be in working condition. 37. Availability of drinking water with water cooler Basic Amenities 38. Inspection of OLTC during erection by STS for auto Basic Amenities work. 39. DC leakage should not be there. Equipment Safety 40. Scrap and excess material disposal from site. Equipment Safety 41. Fire barrier and Fire coating at power cables. Equipment Safety