SAFETY
1
METHOD STATEMENT FOR Excavation
Safety Arrangements:
Underground utilities like sewers, water pipe lines, electric cables, etc. shall be
located and
Adequate precautions shall be taken
The excavation trenches shall be properly shored/timbered if necessary and
excavated material shall be placed 1 m from the edge of the trench
Heavy equipments such as cranes, dumpers shall not work near the edge of
excavation area and be away by at least 6 meters.
Excavated areas shall be barricaded properly.
Aluminum Ladder shall be used for access and aggress.
All workers and staff shall be provided with appropriate PPE.
Toolbox talk will be conducted to labors and staff.
Work permit shall be obtained before taken up work.
Proper adequate lighting will be provided during working at nights.
Safety Arrangements:
Description of works:
2. Visual inspection of chemical shall be done to ensure the chemical is approved for
use.
3. Measure the proportion of chemical and water by using measuring cans and Jars.
4. Ensure the quantity prepared will be utilized within the defined area and the area
to be measured
Before commencing the work to get the required quantity of the chemical.
6. The chemical applied shall be uniform and as per manufacturer's specification and
good
Construction practice.
2
7. The unused chemical shall be taken back to the storage area and protect.
3
METHOD STATEMENT FOR PCC WORKS
Safety Arrangements:
Description of works:
1. Ensure that the Ant termite treatment carried out for the area where PCC will be
carried out.
2. Lay out shall be carried out with the help of total station and mark on the pits
where PCC Shall be carried out. Ensure that the instrument shall be calibrated as
per standard.
3. Provide shuttering for sides for PCC works.
4. Mark Levels by using leveling instrument either with the nails on sides of form
work or put level pads on ground. Ensure that the Instrument shall be calibrated
as per standard.
5. Ensure the raw materials available in sufficient quantity to complete the pour.
6. The concrete shall be produced after obtaining the Pour card approved by the
Clients representative.
7. Transport the concrete produced by the RMC plant by suitable transport like
dumper, concrete pump or other means.
8. The concrete dispatched from the RMC Mixer shall be consumed with in the
prescribed time limit and not to withhold the concrete for long time.
9. Ensure that no extra water added in the concrete which affects the quality of the
concrete.
10.The concrete shall be unloaded into the chute or others.
11.Pour the concrete in the correct location and in sequence to avoid the double
handling and save the time and thus increase the productivity.
12.Compact the concrete to the required level and proper surface finish shall be
done.
13.Clean out all loose concrete and keep the concreted area neat and clean.
14.Remove the sides of PCC and the stripping time will be as per specifications.
15.Curing shall be carried out as per the methodology of curing.
Safety Arrangements:
4
Walkways shall be provided for movement of workers and staff to avoid trap in
the reinforcement
All workers and staff shall be provided with appropriate PPE
Toolbox talk will be conducted to labors and staff
Proper adequate lighting will be provided during working at nights.
Traffic control shall be done for movement of transit mixers, mini dumpers and
trucks.
Adequate support shall be provided for chute.
Description of works:
Reinforcement Works:
Shuttering:
Concreting works:
5
Design the concrete mix and take trials.
Test for the acceptance criteria as per requirements.
Estimate the quantity of pour to be taken and requirement shall be submitted
to clients for approval.
The area of concreting shall be properly cleaned with loose materials before
pouring and check for the rigidity of supports.
Arrangement shall be made before arrival of concrete like concrete lifting and
placing equipments, labor, mason, chute etc.
After receiving concrete at site, check the batch sheet whether the concrete
brought as per the requirement.
Check for concrete for quality with respect to temperature, workability.
Safety Arrangements:
Description of works:
1. The earth shall be selected from the approved location before starting the work
6
2. Remove all loose materials, debris, steel scraps, and wooden materials from the
area where the
Filling shall be taken up. Also dewatering shall be done by using pumps and
dispose of water.
3. Protect all permanent structure by hitting the hard material and damage the
members.
4. Filling shall be done in layers of 200mm and apply water and compact the earth by
using
Earth compactor.
5. Take core sample of each and every layer at defined area and the no. of samples
shall be as
Per requirements decided between MAGUS. Compare with the OMC and MDD
derived
6. The next layer can be filled only after the layer below has approved by the clients.
7. The stone of size more than 150mm shall not be used for filling and stones filled
shall be
8. Complete the compaction and testing report shall be submitted to clients for their
approval.
Safety Arrangements:
Traffic Control shall be done for transporting material within the site.
All workers and staff shall be provided with appropriate PPE
Toolbox talk will be conducted to labors and staff
Proper adequate lighting will be provided during working at nights.
Description of works:
2. The proper level shall be marked and a nylon stringe shall be tied from one end to
another end.
7
3. The stone shall be of proper size and the oversize stone shall be broken into the
suitable size by hammer.
4. The stone laid to the required level and compacted by using wooden rammer.
5. All gaps shall be blinded by using stone chips and crushed sand.
Safety Arrangements:
3. The area shall be cleaned of all loose materials and debris before work.
8
METHOD STATEMENT For Masonry:
Safety Arrangements:
Description of works:
1. The area shall be cleaned of loose materials and debris shall be cleaned before
starting work.
2. Lay out shall be made with reference to building outer line and as per
architectural drawings.
3. The concrete surface where the masonry is in contact shall be checked for
hacking of surfaces
and mortar shall be put on the vertical surface of RCC members a day before
taking of masonry.
4. The loading of materials shall not be stored at one location which affects the
structure by excess
dead load.
5. The mortar required for masonry shall be mixed on platform made of MS Sheet.
6. The batching of materials shall be volumetric and make adjust for bulkage in sand
and water content
8. The masonry work shall be laid in English bond. Proper queen closure shall be
adopted in the right
9. The RCC Band shall be provided at every one-meter height in half brick wall. And
the methodology
9
11. The curing shall be carried out for 7 days from the day of masonry done to ensure
the proper curing.
12. Clean out the area from loose mortar and keep the area as good as new one.
Dispose off the debris to
13. Signoff all checklists from the Clients for each lift of masonry.
Safety Arrangements:
Description of works:
1. The area where the plastering will be taken shall be cleared of all dust, oil,
smoke or any other
5. The mortar required for masonry shall be mixed on platform made of MS Sheet.
6. The batching of materials shall be volumetric and make adjust for bulkage in
sand and water
7. The plastering shall be done from top to bottom and mortar shall be properly
pressed with the help
10
8. The surface finish shall be as per specifications for each type.
9. Get checked the plastering works for line, level, bonding, undulation and
uniform texture.
10. Clean out the area from loose mortar and keep the area as good as new
one.Dispose off the debris
To defined location.
11. Curing shall be carried out as per methodology for atleast 7 days.
12. Signoff all checklists from the Clients for each day's and each location's work.
Safety Arrangements:
Description of works:
Safety Arrangements:
11
Safety belt should be provided.
Description of works:
3. The doors and windows are fixed firmly into the masonry
Safety Arrangements:
Description of works:
3. Clean the area and make the prepatory arrangement for painting work at site.
2. During execution of critical activities like demolition of R.C.C. structures / walls, str.
Steel works, heavy scaffolding, shuttering, etc. approval of all safety measures
12
from S.I.C. / V.P. (Operation) / Clients are taken and all such jobs carried out under
strict and constant supervision.
3. Hazards works like cleaning of chemical / ETP Tank, gutters, vessels etc. and
shifting of vessels, pipeline, machines, chemical drum, other party jobs, etc. not
allowed even in case of special request from anybody / urgency etc. to us or
our sub contractors, labourer.
4. Quality Safety shoes, belts, helmets, goggles are enforced before work
commencement.
5. All night works if required are done with proper lighting and Engineer / Supervisor
& Electrician present till job completion.
6. Overloading of floors / passage / walkways with materials like cement, str. steel,
Blocks, sintex water tanks etc. is prevented.
7. Work area is protected / restricted for man movement while heavy erection,
scaffolding, shuttering, or material movement.
8. Diesel / Petrol Drums, cans, chemicals, paint materials, etc. are well protected,
covered and only authorized persons are allowed for its use / handling.
9. All service cut outs, open tanks, deep gutters, etc. are covered firmly with suitable
framework / Jali followed by old plates, plywood (without any gaps / holes) etc. so
as to work above and below it.
11.Cables / floodlights erected on wooden poles & tied with katha (no binding wire to
be used)
14.Electrical D.B.'s & cables are protected from water / material movement.
15.All debris / material movement is from defined area and in defined manner. This
will be covered from outside.
16.All vehicles movements & steel, shuttering, shifting etc. is controlled by signal
man on the sides of vehicles / material movements.
17.All machinery electrical connections are checked, protected & well earthed.
18.Machine operators are well trained and machines are properly fixed and covered.
Their licenses are checked for experience.
19.All machines & materials are well maintained and are defect free for use.
13
20.Firm side rails / Railings are provided to stairs / area with open surface / sides with
toe board.
21.Important Phones Nos. of nearest Fire Brigade, Police, Hospitals, Ambulance are on
Site Communication Board.
22.First Aid box (cotton bandage, potassium permanganate, tincture iodine, dettol,
knife, blade, scissors & general medicine) with all requirements is in stores and
stock of material in it is checked every week by store keeper.
25.Site & Labour camp is clean and well maintained. Proper water connections,
sanitations facilities & drainage are provided.
27.All measures to protect Clients / Customer's property machines etc. are taken.
28.Necessary steps to be taken after notice of accidents and responsibility are fixed
by S.I.C.
30.Take precautions & alert like snake at the time of Site cleaning, excavation and in
Labour camp areas.
1. Cable routine layout for showing temporary cables laid under the ground for
construction work.
2. Temporary lines given to function boards are with proper supported on special
wooden / M.S. poles about a sufficient height for dumping of truck movement etc.
& other loading / unloading of material.
3. All cables are without joints or if needs the joint then it must be protected in
wooden junction box.
4. For all junction boards from which the cutter m/c, welding m/cs & all other m/cs to
be working are properly earthed with G.S. / cu wire.
5. The proper rating of ELCB / MCB is provided before giving the supply to any of the
function board / distribution board.
6. All main switches, busbars & other switch boards are properly earthed which is
fixed on distribution boards.
14
7. The Armored cables used for distribution network are earthed with their armour of
cable.
8. No. dumping of materials on camles which laid into underground for distribution
network.
9. The flexible cables / armored cables which are laid on the road side are through
proper protective pipes etc. & should be deeper as compared to other side lying.
10.All focus lighting for temporary work should be proper jointing or through pin top
on junction boards.
11.5A / 15A pin tops are used for all electrical m/cs like drilling, cutting, etc. with
proper earth wire.
12.Big. Polish m/c & tile cutting m/c should operate with proper earthling.
13.All main switches, ELCB / MCB'S & cables to be checked before using for
temporary work.
14.Proper specifications, makes, switches / ELCB's, Busbars & cables are to be used.
15.Proper size of cables are used for halogens of higher capacity & m/cs used for
cutting, welding, etc. & for mixer, lifts, pumps, etc.
16.Cable markers are used for locating the cables for maintenance.
17.Proper sizes Dor / Star-delta starters are used for mixer, lifts, pumps, etc.
18.All drilling, cutting, polishing & mixing machines & their mortars shall be checking
before connections for any shocks / leakage currents etc.
19.Open connections for any works should be avoided & it should be properly with
sockets / pins tops, switch, etc.
20.Temporary D.G. sets are maintained properly by checking, water level in battery
connections & other fuel level, oil level, etc.
1. Responsibilities: -
15
Supervision during erection & dismantling .
3. Material dedicated till job completion and no removal of any part of scaffolding
before total dismantling.
4. Base plates supported / rested on firm and leveled ground / timber & to prevent
sinking & slipping. (Don't use packing / supports like brick, wooden pipes, etc. to
base plate).
5. All scaffolding supported / suspended, sufficiently & properly braced, and rigidly
connected with building part which is strong enough. (Cross & Angular
supports @ every floor).
6. Planks / Platform are of good quality, of sufficient thickness (min. 50 mm for 8'
length) & width (min. 700 mm wide for workmen without any material).
7. Planks / Platform are firmly tied on both ends and are in level on both ends & not
projecting beyond end supports.
8. Gap between two planks not exceeds 25 mm & precautions to safeguard while
walking below scaffolding.
10.Gangway / ramp / area used for man movement shall be plated, planked, covered
(min. 2 m wide).
16
17.Precautions during setting up & dismantling of scaffolds, (warning signs, safety
cartons,) to ensure safety for the traffic.
18.Protection of scaffolding against accidental collisions with traffic. (keep min. 1.0 m
clear distance) & ht. 2.5 m for Pedestrians.
19.Access to fire alarms, & escape stairs, cable tunnels, hydrants etc. shall remain
free at all times.
20.Catching scaffold or Net (of min. 1.3 mtr. wide) shall be provided.
17