1. Introduction
2. Scope
5. Schedule / Programme
6. Materials
1. Introduction
The documentation describes the Procedure which shall be followed by M/s
German Steel Contracting WLL(GSC) for the Installation of Stainless Steel
Shelters for the Qatar Integrated Railway, Doha Metro Major Stations/Mushreib
project in accordance with project specification, Contract Drawings & Standards
by ensuring the Health, Safety of Employees at work and Environmental
Responsibilities in order to eliminate or reduce the hazards identified.
The erection methods cover the methodology for Anchor Bolts, Column Frame,
Rafters, and Purlins & Bracings etc.
2. Scope of Work
The scope shall include all labour, material, equipment, permits ad services
necessary for the installation of Stainless Steel Secondary Shelters 2, 3, 4 & 5 and
related works complete in accordance with the Approved drawings.
The following are the scope of work to be carried out by German Steel
a) Delivery & Storage of Stainless Steel Members
b) Supply of Stainless Steel Cast in Place Anchors
c) Transit of Members to the Work Premise
d) Erection of Stainless Steel Shelter
e) Polishing (To Restore the finishes damaged during Erection)
f) Final Inspection and Handing Over
Project Specifications
o MOO7-ONW-ARC-SPE-11303 Section 05 12 05
Contract Input Drawings (IFC)
o M007-ONW-ARC-DWG-UCST000-AA-11305 to 11340
Approved Shop Drawings
o M007-CCC-STR-DWG-UCST000-AG-GS100 to 111
NFPA 130, 101
Qatar Construction Specification QCS 2014 Section 16 & 17
Material Approvals
o MAR: M007-CCC-STR-MAR-00035 to 00038
ITP Inspection & Test Plan for Installation of Stainless Steel Structure
o M007-CCC-ARC-ITP-00003
PQP Project Quality Plan
o M007-CCC-QMS-PLN-00002
Project HSE Plan
o M007-CCC-HSE-PLN-00006
Construction drawings for Architectural works Room Data Schedule
o For MUS M007-MML-ARC-DWG-UCSTMUS-AA-00010 up to 00016
AWS D10.4 for Stainless Steel Welding
ASTM Standards for Non-Destructive Tests
Approved WPS, PQR & WQT
Others
Latest revisions of the above documents should be used
The following are the list permits & Licences required and are not limited to
All the materials which shall be fixed permanently on site are made of 316 L grade
stainless steel and the list shall be as listed below:
SS Anchor Bolts
SS Columns Made of 15mm thick Plate SC1
SS Beams Made of 15mm Thick Plate SB1
SS Rafters Made of 15mm Thick Plate - SB2
SS Purlins Made of RHS 100x60x5mm SB3
SS Connection Bolts
SS GUTTERS
The parties with roles and responsibilities at the various stages of the projects are as
follows:
Plan, check and get the design manager sign-off the Sequence/Method of
Erection
Ensure the adequate plans and actions to solve out all the complaints from the
clients.
Sign-off or get the authorized sign-off for all the non-conformance.
Check and record all the required test and inspection documents.
Design Co-ordinator
The Design coordinator is in charge of the proper coordination with construction team
and technical team in Main office.
Responsible to provide all the approved documents to the erection team.
Responsible for any technical clarification arises from construction site.
Responsible for collecting and inquiring technical information with CCC technical
team.
Responsible for BIM coordination with CCC.
Site Supervisor
QA/QC Engineer
Safety Officer/Engineer
Prepare toolbox meeting, safety training course to train team members about
safety.
Employee in General
Be responsible for own safety.
Follow the safe working procedures and erection method statement.
Report hazards, near miss, injuries and accidents to his supervisor/HSE
personnel.
Be physically fit and mentally alert.
Use the tools and tackles in safe manner.
Make sure there is space and firmed pathway for truck delivery, crane truck
erection operation. The suitable truck & crane capacity must be clarified (and
listed in the equipment register).
Survey the wind direction to have plan for roof material storage and installation
direction.
Decide the plan for unloading and material storage. Choose a firm and dry
location. Materials shall be stored in designated areas for each building and
clearly identified for their location in that area.
Make sure that materials supply and storage schedule is appropriate and not
conflict with the installation schedule and other sub-contractors schedules.
Register the available power & water supply source locations at the site. Make
sure there is a safe method to lead the supply to the working area.
Provide the required quantity of Cast in place anchors prior to the pouring of
concrete with all necessary templates, drawing co-ordinates and other
installation procedures..
Site layout and Access Preparation
The supervision team at site shall make sure that access roads shall have
adequate sight lines and be kept clear from parked vehicles and other
obstructions
The supervision team shall enforce the application of mounted crackdown for
controlling traffic flow inside the construction areas consisting of deploying
directive signs at potentially hazardous locations, safety boards and notices,
flagmen, and the necessary staff to pull out the job safely without compromising
the welfare of personnel, property, and material.
In the event that work requires an extension of a day shift which would result in
working in dusk, dim and/or dark conditions, an assessment shall be conducted
prior to these conditions. The assessment shall identify the time required to
supply and install suitable and sufficient lighting prior to these conditions.
Fire Control
Fire extinguishers shall be placed at all gates, storage areas, electrical areas,
areas where welding works to be performed etc.
Further Provisions
Communication at site shall be effected through GSM lines and Radios.
Toolboxes and safety awareness talks shall be observed at site before initiating
critical activities to properly communicate to the working level all the hazards
involved. All permits and certificates required shall be prepared, submitted in due
course and received before commencing the work at site.
Project Conditions
Weather Limitations: Carry out all the works only when existing and forecasted
weather conditions permit. The Safety Manager will stop all activities on-site
when the weather conditions endanger the safety of workers.
Coordination
Coordination is to be performed with all disciplines, sub-contractors and other
interfacing contractors prior to commencement of works to ensure a safe working
environment and avoid damaging the works.
component with the right no. of points and position so that the load of component itself
do not damaged or broken.
Always attach a tag line to the lifting component.
All materials receipt at site shall be visually inspected by QA/QC engr. for any damage.
Remedial works to the damage shall be taken immediately, if possible, to avoid any
delay to erection.
Materials shall be shipped to job site separately or on the skid put in trailer. They are
unloaded y crane. The average load of trucks carried out materials is about 15ton.
Therefore the temporary road in the job site must be prepared properly for crane and
trucks.
Before unloading materials out of trucks or containers, it is required to take pictures of
real material status delivered to job site.
Material Arrangement
To avoid materials being moved so much on jobsite that might cause unexpected
damages of shapes. when material delved to job site, they must be unloaded and arranged
closed to the designed erection point.Up to The materials shall be stacked in locations
according to the building/areas, should be near to the lifting position adjacent to the area
to be erected. This is to facilitate the sorting and delivery during the erection.
The materials will be arranged as following principle to ease moving, combination and
erection after later.
- Members should be checked part mark as packing list enclosed before unloading for
best unloaded positions.
- W shaped canopy Column (SC1) Frame should be arranged closed to their anchor
bolt position.
- Beams (SB1) & Rafters (SB2) members should be arranged to ensure easy assembly,
movement.
- Nested parts (Purlins SB3) shall be stacked on timber frames near to the installation
area.
- Small components (nuts, bolts, clips, fasteners etc.) are stored in a given area
convenient to all parts of the building.
With purpose of preventing and protecting material damages during storage out of
environment factors such as storm water, dust, etc which cause rusty, stain, etc. Including
below tasks:
Choose firmed and dry area for storage.
The material shall be stored above ground level with timber packing.
The materials or component or member shall be stored separately, above ground on
timber dun age. They shall not be stacked directly on top of each other but must be
separated by 50mm thick timber, and shall not stack in contact with other steel member
but must be separated by a minimum 250mm gap.
Particular care shall be taken to stiffen free ends at 200mm distance from ends, prevent
permanent distortion.
Setting Out
As built(Anchor Bolts) survey inspections shall be carried out.
This Section specifies the erection procedure and sequence of activities, which shall be
carried out for the erection of Secondary Shelters by considering the conceivable risks.
General principle
Do not conduct erection without last Erection drawings issued for Erection.
Permits shall be obtained prior to commence any activities.
Adequately bracing before releasing lifting equipments or temporarily stop working.
All connection joints must be completed bolt tightening before releasing lifting
equipment.
Survey the cast in place anchors to ensure it has placed on exact coordinates as per
drawing.
All lifting operation involving Lifting Equipment shall be properly planned by a
competent person appropriately supervised and carried out as per the erection sequence
method statement in coordination with CCC site safety engineers. Lifting Equips/Tackles
periodic inspection shall be conducted by competent person
The person planning the operation shall have adequate practical, theoretical knowledge,
experience of planning in lifting operations and shall conduct a tool Box with the
persons who are involving in the lifting operation.
A Risk Assessment shall be carried out to identify all potential risks associated with the
lifting operation.
c:
Weight of Each Member
SC1 Max < 2T
SB1 Max < 1T
SB2 Max < 1T
SB3 Max < 20 Kg
A sketch of the lifting operation showing a plan & elevation view of the lift.
Details of the equipment being utilized including capacities.
Ensure the availability of survey equipment with Operator shall be provided by CCC.
Ensure all the dimensions of the delivered fabricated members are not exceeding the
allowed tolerances.
Leveling with steel packers to the design elevation to ensure the base plate remains in
level.
The column frame after erection is aligned to design location with fix jacks, wire & Lever
according to site surveyors instruction.
Tighten Anchor bolts to the required torque after aligned the frame to the right position.
Repeat the same step to install all the remaining W frames.
Workers standing on scaffolding/MEWP will adjust to fix the beam correctly in the
groove provided in W frame.
Adjust the beam to seat rigidly in the groove by align at right design level.
Follow the same procedure to erect all the remaining beams.
Workers standing on scaffolding/MEWP will adjust to fix the Rafter correctly over the
holes provided on the installed beam (SB1.
Contractual Requirement
Quality Assurance requirements in the contract specification shall have been verified and
presented in the form of Inspection and Test Plan. Complying the standard & codes as
mentioned in section 3 of this document.
All erection works compliance with international standards and code of practice operating to as
approved Quality Management System certified in accordance with ISO 9001-2008/ contract
specification
Inspection & Approving parties as per ITP shall ensure the quality of work at every level.
GSC shall follow the submitted GSC HSE Plan in line with Project HSE requirements.
Information to Personnel
o Prior to start the work daily/shift the following pre-task briefings to be carried
out in STARRT meeting.
Emergency Procedure
During emergency situations CCC procedure shall be followed.
Response Level
o The response level is the initial step in the GSC/CCC effort to avert a disaster. At
this level, on site personnel must be prepared to follow CCC emergency
operations procedures immediately.
o In case of Emergency like fire, gas leak, structural collapse, personnel fall from
height, heart attack etc and emergency action will be immediately enforced
following the instruction on the time.
Control Measures
The following
Air Quality
All vehicles and plant on site must be regularly inspected and maintained to
ensure compliance with Qatar mobile emission standards.
Idling of vehicles has to be avoided when vehicles are not in use, although it is
accepted that occupied vehicles may need to be switched on to ensure air
conditioning is available, particularly during hotter periods of the year.
The combustion of any waste materials including waste oils on site will not
permitted under any circumstances.
When possible the use of mains powered electrical equipment shall be used in
preference to using generators to provide power.
Dust Control
Any vehicle with an open load carrying area used for moving potentially dust
producing material shall have properly fitting side and tail boards. Materials
having the potential to create dust shall not be loaded to a level higher than the
side and tail boards, and shall be covered by a clean tarpaulin in good condition.
The tarpaulin shall be properly secured.
Activities that potentially generate high dust levels shall be cur-tailed, suspended
or postponed in situations where the wind direction and speed is causing adverse
impacts on nearby sensitive receptors.
Use of dust-suppressed tools for all operations.
Ensuring that all construction plant and equipment is maintained in good working
order and not left running when not in use.
Hazardous Materials
To ensure the protection of the soil, hazardous materials must be managed
appropriately.
All minor or emergency refuelling/servicing that cannot be carried out offsite
should be carried out at a dedicated sealed, impermeable, drained and kerbed
concrete floor with wastewater and hydrocarbon/solvent collection and separation
facilities.
Rotating equipment and fan wheels should be appropriately stored, applied and
handled by trained personnel.
Noise Management
Personnel Protection
Proper PPE to be provided to all personnel working in high noise areas.
Appropriate breaks to be provided to personnel working in high noise areas.
A quiet area for personnel to take breaks, such as a lunch room.
Administration of an effective hearing conservation programme where the
sound levels exceed specified limits.
General Noise Control and Measure
Site hoardings must be provided around all surface construction and logistics
areas.
Noise and vibration monitoring is undertaken within close proximity of noise
vibration sensitive locations, especially if future works include activities which
are known to cause significant levels of noise.
Stationery machinery such as generators must be kept in enclosed structures
for noise control during the night.
Items of plant on site operating intermittently will be shut down in the
intervening periods between uses.
Electrically powered plant should be preferred, where practicable, to
mechanically powered alternatived.
All mechanically powered plant should also be fitted with suitable silencers.
Noisy equipment and machinery will be replaced with less noisy alternatives
or provide equipment that is specifically designed with noise inhibitors, such
as generators and compressors with silencers and muffled jackhammers.
All equipment must be regularly maintained and/or replaced as necessary.
Use of vibratory hammer rather than impact hammer to reduce noise levels.
Measures of Reduction
Appropriate measures to be implemented to ensure the health and safety risks
associated with extreme noise to staff are minimized. This must include
providing appropriate personal protective equipment as well as safe working
practices.
All necessary measures shall be taken in accordance with Qatari Standards to
ensure that the operation of all mechanical equipment and construction
processes on or off the site shall not cause excessive noise which may disturb
any occupant of any nearby dwellings, schools, hospitals or premises with
similar sensitivity to noise.
Methods of working to minimize noise impacts must be arranged and
experienced personnel must be provided with suitable training to ensure that
these methods are implemented.
If noise exceeds the required standards the use of acoustic screens or noise
attenuation measures has to be implemented.
Vibrations.
Where the EIA has identified potential vibration issues, CCC shall prepare a
detailed vibration assessment to accurately predict vibration levels and plan
appropriate management measures.
Waste Management
Wastes have the potential to cause severe environmental damages if not correctly managed. It is
vital that sites manage waste generated in a manner such that legislative requirements are fully
complied with breaches of legal obligations cab result in the prosecution of an organization
and /or individual employee.
o Waste is securely contained in a such a way as to avoid it escaping into the environment.
o Waste is transferred only to someone authorized to carry or manage it.
o Appropriate records and transfer notes are kept.
o Appropriate measures are taken to ensure that others involved in the handling and
disposal of waste the waste does so in accordance with the laws of Qatar..
o Waste is not kept in a corroded or worn container.
o The container is secure to prevent accidental spillage or leakage.
o Waste is kept in such a way as to prevent falling while in storage or while it is being
transported.
o Waste is to be protected from scavenging by people and animals.
Waste Minimization
Waste generation damages the environment, and for the business: the cost of waste includes all
the costs incurred in getting a material to the point at which it has become a waste. Waste
minimization is the reduction or avoidance of waste at source, and the adaptation of such
techniques on site is to be encouraged.
As the amount and type of waste generated depends on the stage of construction, it is important
that waste management practices adapt as the works progress. To facilitate site waste reduction,
quantities of raw material ordered shall be critically assessed and materials carefully managed
during delivery, storage and use. Wastes shall be segregated to encourage re-use and recycling,
and reclaimed materials used in new works whenever possible.
Stainless Steel
To reduce waste on site made to measure structural steels can be ordered from the supplier,
while good stock control ensures that the correct stainless steel are used on appropriate
structures. Oppertunities for reuse on site shall be investigated, as well as recycling srap metal.
Timber
Timber Waste can often be reused or recycled. For example pallets can be returned to the
supplier for reuse.
Damage to
material, - The hand toolss used by the operatives
must be in good condition.
Human causality
- The workers should have the awareness
Using hand tools Damage of 1-5 2 3 6 M about the safe usage of the hand tools
property
- Hand tools like grinders should have the
Loss of time safety guards.
Site Engineer to Ensure that all the lifting
devices that will be in use are tested and
certified by third party and he should inform
the working crew for lifting the steel. Workers
must be made aware of the risks involved on
this job and the area must be cordoned off to
prevent people entering in to this lifting zone.
MSRA to be communicated to all people
involved and report should be signed off.
Using /defective Should not cross the safe working load of
Lifting of tools/tackles. Crane (50 Tons) and chain block (2 ton).
Fabricated Falling load over
Only certified and experienced rigger should Conduct
Structure using people may lead
1-5 3 4 12 H give signals and he should ensure all lifting Tool Box
crane to serious injuries
appliance and the locking system are fit for Talks / DSTI
and damage to
work.
properties. L
Control the unauthorized entry to the work
area.
No. Exposed:
100 plus 6 6 5 4 3
50 to 100 6 5 4 3 3
25 to 50 6 4 3 2 2
15 to 25 6 3 3 2 1
5 to 15 6 3 2 1 1
1 to 5 6 2 1 1 1
Severity (S): Not Harmful (NH) = 1; Slightly Harmful (SH) = 2; Harmful (H) = 3; Extremely Harmful (EH) = 4; Multiple Casualties (M) = 5;
Catastrophic (C) =6
This method statement and risk assessment to be communicated to all the people involved and should be signed off and keep the copy of
the report at site
A'
N
X
148
80
Red Line
LA
QIB
10
150
130
00
50
Y
00
140
B'
9
130
00 SECONDARY SHELTER Green Line
Z 00
ENTRANCE 3 Blue Line
140
150
8
50
130
00
00
140
AA
C'
7
108
00
220
00
20
306
D'
AB
Gold Line
Legends:
100
00
6
E'
220
00
1A
100
20
00
306
AC
F'
5
130
00
100
00
AD
00
140
G'
4
130
00
00
140 AE
3
130
00
00
140
47 AF
2
1
130
80
BU
00
148
SECONDARY SHELTER 1 AG
SS
ENTRANCE 4
13
SECONDARY SHELTER
ENTRANCE 2
TO
105
00
12 AH
P
BU 3990
K'
SS
Notes:
6400
ALL DIMENSIONS ARE IN MILLIMETERS AND LEVELS ARE IN METERS
TO
M007-ONW-ARC-DWG-UCST000-AA-00019 (FOH)
EN M007-ONW-ARC-DWG-UCST000-AA-11002 (P1.1)
TR M007-ONW-ARC-DWG-UCST000-AA-11306 (P1.2)
J'
AN
CE AUXILIARY STRUCTURES OF FINISHES ARE INDICATIVE AND WILL BE
DEFINED FOR THE WORST CASE WHEN FINAL FINISH IS DEFINED,
FINAL DIMENSIONS AND CHARACTERISTICS WILL BE DEFINED BY
FINAL SUPPLIER IN COMPLIANCE WITH ER.
RESPONSABILITY TO INTEGRATE MSI DETAILS IS UP TO THE
CONTRACTOR
7'
6'
5'
NOTE:
A'
4'
FOR PAVEMENT DESIGN
PLEASE REFER TO
PACKAGE P3
3'
M007-ONW-ARC-MD3-UCST000-AG-11350_RVT_1.0 M007-MML-ARC-MD3-UCSTMUS-MX-00031_IFC_10.0
M007-ONW-ARC-MD3-UCST000-AG-11351_RVT_1.0 M007-MML-STR-MD3-UCSTMUS-MX-20000_IFC_2.1
M007-ONW-ARC-MD3-UCST000-AG-11352_RVT_1.0 M007-MML-STR-MD3-UCSTMUS-IL-01050_IFC_1.1
B'
58 M007-ONW-ARC-MD3-UCST000-MX-10007_RVT_2.0
M007-ONW-ARC-MD3-UCST000-MX-10006_RVT_2.0
M007-ONW-ARC-MD3-UCST000-AG-10300_RVT_2.0
2'
Reference Documents:
1'
C'
Project:
M007-ONW-ARC-DWG-UCST000-AG-11310 1.0
THE DRAWING AND ANY INFORMATION OR DESCRIPTIVE MATTER SET OUT HEREON IS LICENSED TO THE QATAR RAILWAYS COMPANY AND IS CONFIDENTIAL AND SUBJECT TO COPYRIGHT. IT MUST NOT BE DISCLOSED, LOANED, COPIED OR USED FOR MANUFACTURING, TENDERING OR FOR ANY OTHER PURPOSE WITHOUT WRITTEN PERMISSION. QATAR RAILWAYS COMPANY.
Key Plan:
N
Red Line
LA
QIB
Green Line
Blue Line
Gold Line
Legends:
Notes:
ALL DIMENSIONS ARE IN MILLIMETERS AND LEVELS ARE IN METERS
THE COMPLETE LIST OF MATERIALS IS DETAILED ON SHEETS:
M007-ONW-ARC-DWG-UCST000-AA-00019 (FOH)
M007-ONW-ARC-DWG-UCST000-AA-11002 (P1.1)
M007-ONW-ARC-DWG-UCST000-AA-11306 (P1.2)
AUXILIARY STRUCTURES OF FINISHES ARE INDICATIVE AND WILL BE
DEFINED FOR THE WORST CASE WHEN FINAL FINISH IS DEFINED,
FINAL DIMENSIONS AND CHARACTERISTICS WILL BE DEFINED BY
FINAL SUPPLIER IN COMPLIANCE WITH ER.
RESPONSABILITY TO INTEGRATE MSI DETAILS IS UP TO THE
CONTRACTOR
Reference Documents:
Project:
M007-ONW-ARC-DWG-UCST000-AA-11340 1.0
THE DRAWING AND ANY INFORMATION OR DESCRIPTIVE MATTER SET OUT HEREON IS LICENSED TO THE QATAR RAILWAYS COMPANY AND IS CONFIDENTIAL AND SUBJECT TO COPYRIGHT. IT MUST NOT BE DISCLOSED, LOANED, COPIED OR USED FOR MANUFACTURING, TENDERING OR FOR ANY OTHER PURPOSE WITHOUT WRITTEN PERMISSION. QATAR RAILWAYS COMPANY.
Key Plan:
Scala 1:50
01 32 03 04 05 06 07 08 09 12
02 10 13
13785 11 Green Line
SB3 SB2 SB3 Blue Line
200
200
5F
Model 3d
SB3
SB3
SB3
SB3
SB3
SB3
SB3
SB2 Scala 1:100
1019
SC1
SB3 SB2 SB3 SB3
5E
SB1
SB1
SB3
SB3
SB3
SB3
SB3
SB3
SB3
SB2
1019
SB2 SB3 SB1 Gold Line
SB3 SB3
Legends:
5D
SB3
SB3
SB3
SB3
SB3
SB3
SB3
SB2
1019
5095
5495
SB3 SB2 SB3
SB3
5C
SB3
SB3
SB3
SB3
SB3
SB3
SB3
SB2
1019
SB2 SB3
SB3 SB3
5B
SB3
SB3
SB3
SB3
SB3
SB3
SB3
SB2
1019
5A
113
153
200
60
47
Notes:
ALL DIMENSIONS ARE IN MILLIMETERS AND LEVELS ARE IN METERS
60 ALIGNMENT 13 THE COMPLETE LIST OF MATERIALS IS DETAILED ON SHEETS:
M007-ONW-ARC-DWG-UCST000-AA-00019 (FOH)
Scala 1:50 M007-ONW-ARC-DWG-UCST000-AA-11002 (P1.1)
ALIGNMENT 5A M007-ONW-ARC-DWG-UCST000-AA-11306 (P1.2)
Scala 1:50
5A 5B 5C 5D 5E 5F AUXILIARY STRUCTURES OF FINISHES ARE INDICATIVE AND WILL BE
DEFINED FOR THE WORST CASE WHEN FINAL FINISH IS DEFINED,
01 03 04 05 06 07 08 09 12 FINAL DIMENSIONS AND CHARACTERISTICS WILL BE DEFINED BY
FINAL SUPPLIER IN COMPLIANCE WITH ER.
300 10 13 5495 RESPONSABILITY TO INTEGRATE MSI DETAILS IS UP TO THE
1645 CONTRACTOR
02 1645
7693 11 153 1019 1019 1019 1019 1019 200
SB3
1645 15
SB3 1645 5948
SB3 1645
1645 1565 160 1565 200
SB3
SB3 SB2 SB3 SB3 SB3 SB3
DET. A
R=70050
M007-ONW-ARC-MD3-UCST000-AG-11350_RVT_1.0 M007-MML-ARC-MD3-UCSTMUS-MX-00031_IFC_10.0
SC1
M007-ONW-ARC-MD3-UCST000-AG-11351_RVT_1.0 M007-MML-STR-MD3-UCSTMUS-MX-20000_IFC_2.1
3441
SC1
M007-ONW-ARC-MD3-UCST000-AG-11352_RVT_1.0 M007-MML-STR-MD3-UCSTMUS-IL-01050_IFC_1.1
3208
3130
M007-ONW-ARC-MD3-UCST000-MX-10007_RVT_2.0
SC1
2980
M007-ONW-ARC-MD3-UCST000-MX-10006_RVT_2.0
M007-ONW-ARC-MD3-UCST000-AG-10300_RVT_2.0
R150
R150
Reference Documents:
BOS BOS
+7.000 +7.000
Client
50
4887 3297 2200 PL
15 ENTRANCE 5
*8 Qatar Railways Company
250
2
SB3
200
P.O. Box 29988
Structural materials Doha - Qatar
M20
CSK Profiles and plates: Stainless
300 steel satin finish - AISI 316L
SB2 Bolts: A4 - 80 Originator Name & Logo:
01 02
Structural sections
4880
4720
PL15*35
Doha Metro:Major Stations
RTC/193/2016
50
Discipline:
250
ARCHITECTURAL
PL
SC1
200
Drawing Title:
235
250
M007-ONW-ARC-DWG-UCST000-AA-11323 1.0
THE DRAWING AND ANY INFORMATION OR DESCRIPTIVE MATTER SET OUT HEREON IS LICENSED TO THE QATAR RAILWAYS COMPANY AND IS CONFIDENTIAL AND SUBJECT TO COPYRIGHT. IT MUST NOT BE DISCLOSED, LOANED, COPIED OR USED FOR MANUFACTURING, TENDERING OR FOR ANY OTHER PURPOSE WITHOUT WRITTEN PERMISSION. QATAR RAILWAYS COMPANY.
Key Plan:
N
Red Line
LA
QIB
01 * 03 04 05 09 12 Gold Line
08
02 06 07 10 13 Legends:
11
58 1170
80
SC1 SB2 SB3
200
50
125
4F
SB3
SB3
SB3
SB3
SB3
SB3
SB3
SB2
1019
SB3
SB3 SB2 SB3 SB3
4E
SB1
SB1
SB3
SB3
SB3
SB3
SB3
SB3
SB3
SB2
1019
SB3
SB3
SB3
SB3
SB3
SB3
SB2
1019
5095
5495
SB3 SB2 SB3
SB3
4C
SB3
SB3
SB3
SB3
SB3
SB3
SB3
SB2
1019
SB2 SB3
SB3 SB3
4B
SB3
SB3
SB3
SB3
SB3
SB3
SB3
SB2
1019
ALIGNMENT 13
01 * 03 04 05 06 07 08 09 12 Scala 1:50
300 10 13 4A 4B 4C 4D 4E 4F
1645 5495
02 1645
7693 11 200 1019 1019 1019 1019 1019 200
SB3
1645 15
SB3 1645 5948
SB3 1645
1645 1565 160 1565 200
SB3
SB3 SB2 SB3 SB3 SB3 SB3
DET. A
R=70050
SB1 SB3 SB2 THIS DRAWING IS AN EXTRACTION FROM THE FOLLOWING MODEL FILES
SB1 SB1
+8.080 m M007-ONW-ARC-MD3-UCST000-AG-11350_RVT_1.0 M007-MML-ARC-MD3-UCSTMUS-MX-00031_IFC_10.0
DET. B M007-ONW-ARC-MD3-UCST000-AG-11351_RVT_1.0
M007-ONW-ARC-MD3-UCST000-AG-11352_RVT_1.0
M007-MML-STR-MD3-UCSTMUS-MX-20000_IFC_2.1
M007-MML-STR-MD3-UCSTMUS-IL-01050_IFC_1.1
433 4325 15 M007-ONW-ARC-MD3-UCST000-MX-10007_RVT_2.0
15 433 M007-ONW-ARC-MD3-UCST000-MX-10006_RVT_2.0
M007-ONW-ARC-MD3-UCST000-AG-10300_RVT_2.0
Reference Documents:
3441
3208
3130
SC1
2980
R150
R150
5040 180
522 4665 1620 3303 3490
BOS BOS
+5.100 +5.100
Drawing Revision History:
Rev Description App. Date
1.0 ISSUED FOR SONO G. DE CARLI 18/10/16
Purpose of Issue:
340
160
160
50
35
4720
4720
MSHEIREB STATION
*8
15
250
PL
200
M20 1220 800 2497 800 1800 METRO ENTRANCE 4 - CANOPY - STRUCTURE FRAMING
CSK
P1.2 SECONDARY SHELTERS DETAIL DESIGN
35
160
250
SB2 200
Originator: Contractor:
12 13 SC1 Drawn C. MICONO 18/10/16 Checked
Checked S. CORNEGLIANI 18/10/16
Approved G. DE CARLI 18/10/16 Approved
M007-ONW-ARC-DWG-UCST000-AA-11322 1.0
THE DRAWING AND ANY INFORMATION OR DESCRIPTIVE MATTER SET OUT HEREON IS LICENSED TO THE QATAR RAILWAYS COMPANY AND IS CONFIDENTIAL AND SUBJECT TO COPYRIGHT. IT MUST NOT BE DISCLOSED, LOANED, COPIED OR USED FOR MANUFACTURING, TENDERING OR FOR ANY OTHER PURPOSE WITHOUT WRITTEN PERMISSION. QATAR RAILWAYS COMPANY.
Key Plan:
N
Plan canopy structure Red Line
50 03 Scala 1:50 QIB
LA
01 04 06 07 08 09 10 11 12
02 05 13
Green Line
2980
3734 13785 Blue Line
SB2 SB2
200
200
3I
500
3H
1000
SB2 SB3 SB3 SB2 SB3
SB3
SB3
SB3
SB3
SB3
SB3
SB3
SC1
3G
Gold Line
1000
SB2 SB3 SB3 SB2 SB3 Legends:
SB3
SB3
SB3
SB3
SB3
SB3
SB3
Structural materials 3F
ENTRANCE 3 Profiles and plates: Stainless steel
1000
satin finish - AISI 316L SB2 SB3 SB3 SB2 SB3
SB3
SB3
SB3
SB3
SB3
SB3
SB3
Bolts: A4 - 80
ENTRANCE 2
5400
6000
6400
Structural sections 3E
ENTRANCE 4
MAIN SHELTER
1000
SB1: Section 150x75x300x15.0t SB2 SB3 SB3 SB2 SB3
SB3
SB3
SB3
SB3
SB3
SB3
SB3
6060
ENTRANCE 5
SB2: Section 125x62.5x250x15.0t 3D
SB1 SB1
1000
SB3: Section RHS-100x60x5.0t SB2 SB3 SB3 SB2 SB3
SB3
SB3
SB3
SB3
SB3
SB3
SB3
SB1
keymap
SC1: Section 150x300x150x15.0t 3C
1000
SB2 SC1 SB3
SB3
SB3
SB3
SB3
SB3
SB3
SB3
To ensure good technical and 3B
aesthetic success of the welds in the
500
project, it will be request the 3A
200
200
realization of all the mock up
necessary to properly define the SB3 SB3 SB2
600
correct degree of finish.
57
ALIGNMENT 3B Notes:
ALIGNMENT 01 Scala 1:50 ALL DIMENSIONS ARE IN MILLIMETERS AND LEVELS ARE IN METERS
Scala 1:50 THE COMPLETE LIST OF MATERIALS IS DETAILED ON SHEETS:
M007-ONW-ARC-DWG-UCST000-AA-00019 (FOH)
50 03 06 07 08 09 10 11 12
57 3A 3C 3D 3E 3F 3G 3H M007-ONW-ARC-DWG-UCST000-AA-11002 (P1.1)
M007-ONW-ARC-DWG-UCST000-AA-11306 (P1.2)
01 04 13
3B 3I 300
AUXILIARY STRUCTURES OF FINISHES ARE INDICATIVE AND WILL BE
05 DEFINED FOR THE WORST CASE WHEN FINAL FINISH IS DEFINED,
800 300 700 1000 1000 1000 1000 700 300 02 1645 SB3 FINAL DIMENSIONS AND CHARACTERISTICS WILL BE DEFINED BY
7693 1645 FINAL SUPPLIER IN COMPLIANCE WITH ER.
SB3
1645 RESPONSABILITY TO INTEGRATE MSI DETAILS IS UP TO THE
15 1645 SB3
5948 CONTRACTOR
1645 1644 SB3
200 1565 160 1565
SB2 SB3
SB3 SB3 SB3 SB3
DET. A
R=700
50
SB3 SB1
SB2
DET. B SB1 SB1
693 15
+7.830 m 4685 15 693
R50
6400
3441
3208
3130
2980
SC1
THIS DRAWING IS AN EXTRACTION FROM THE FOLLOWING MODEL FILES
R150
R150
1100 5400 M007-ONW-ARC-MD3-UCST000-AG-11350_RVT_1.0 M007-MML-ARC-MD3-UCSTMUS-MX-00031_IFC_10.0
M007-ONW-ARC-MD3-UCST000-AG-11351_RVT_1.0 M007-MML-STR-MD3-UCSTMUS-MX-20000_IFC_2.1
M007-ONW-ARC-MD3-UCST000-AG-11352_RVT_1.0 M007-MML-STR-MD3-UCSTMUS-IL-01050_IFC_1.1
M007-ONW-ARC-MD3-UCST000-MX-10007_RVT_2.0
M007-ONW-ARC-MD3-UCST000-MX-10006_RVT_2.0
M007-ONW-ARC-MD3-UCST000-AG-10300_RVT_2.0
3595 3297 6807
Reference Documents:
BOS BOS
+4.850 +4.850
3H
SONO Reference: Date:
340
100
215
50
1
PL
200
SB3
Qatar Railways Company
M20 P.O. Box 29988
CSK
Doha - Qatar
300
SB2
4720
5400
DET. B
1:10
100 Project:
200
ARCHITECTURAL
15
250
215
*8
200
340
Drawing Title:
250
M007-ONW-ARC-DWG-UCST000-AA-11321 1.0
THE DRAWING AND ANY INFORMATION OR DESCRIPTIVE MATTER SET OUT HEREON IS LICENSED TO THE QATAR RAILWAYS COMPANY AND IS CONFIDENTIAL AND SUBJECT TO COPYRIGHT. IT MUST NOT BE DISCLOSED, LOANED, COPIED OR USED FOR MANUFACTURING, TENDERING OR FOR ANY OTHER PURPOSE WITHOUT WRITTEN PERMISSION. QATAR RAILWAYS COMPANY.
Key Plan:
N
Plan canopy structure Red Line
Scale 1:50 QIB
LA
10
01 61 03 04 05 06 07 08 09 11 13
02 64 12 14
15400 Green Line
SB3 SB1 SB3 SB1 Blue Line
200
200
2H
300
2G
SB3
SB3
SB3
SB3
SB3
SB3
SB3
SB3
62 Model 3d
1000
SB3 SB1 SB3 SB3 SB1 Scala 1:100
SC1
2F
SB1
SB1
SB3
SB3
SB3
SB3
SB3
SB3
SB3
SB3
1000
SB3 SB1 SB3 SB3
SB1 SB1 Gold Line
4305
2E Legends:
SB3
SB3
SB3
SB3
SB3
SB3
SB3
SB3
4400
1000
5400
SB1 SB3 SB1
SB3 SB3
2D
SB3
SB3
SB3
SB3
SB3
SB3
SB3
SB3
1000
SB3 SB1 SB3 SB3 SB1
2C
SB3
SB3
SB3
SB3
SB3
SC1
1000
50 SB3
2B
300
2A
200
200
SB1
9080
63
Notes:
ALL DIMENSIONS ARE IN MILLIMETERS AND LEVELS ARE IN METERS
ALIGNMENT 14 ENTRANCE 3 THE COMPLETE LIST OF MATERIALS IS DETAILED ON SHEETS:
Scala 1:50 M007-ONW-ARC-DWG-UCST000-AA-00019 (FOH)
M007-ONW-ARC-DWG-UCST000-AA-11002 (P1.1)
ENTRANCE 2 M007-ONW-ARC-DWG-UCST000-AA-11306 (P1.2)
ALIGNMENT 2B AUXILIARY STRUCTURES OF FINISHES ARE INDICATIVE AND WILL BE
06 Scala 1:50 07 08 09 10 13 2C 2D 2E 2F 2G ENTRANCE 4
DEFINED FOR THE WORST CASE WHEN FINAL FINISH IS DEFINED,
63 2A 2B MAIN SHELTER
FINAL DIMENSIONS AND CHARACTERISTICS WILL BE DEFINED BY
11 14 2H FINAL SUPPLIER IN COMPLIANCE WITH ER.
320 8793
50 1645
1645
keymap
50 1645 1565 160 1565 200
SB3
SB3
SB3 SB3 SB3 SB3 SB1
Structural materials
250 Profiles and plates: Stainless steel
satin finish - AISI 316L
SB3 SB1 SB3 Bolts: A4 - 80
R=70050
M007-ONW-ARC-MD3-UCST000-AG-10300_RVT_2.0
3208
3130
SC1
2980
SC1: Section 150x300x150x15.0t Reference Documents:
SC1
SC1
300 4400 300 To ensure good technical and
646 1620 3297 3496 aesthetic success of the welds in the
2127 4274 126 project, it will be request the
BOS BOS realization of all the mock up
+4.85 +4.85 necessary to properly define the
correct degree of finish.
100
12 40 SC1 PL15*35
1645 9337
SB3 1645 64 Qatar Railways Company
50
250
2G P.O. Box 29988
450 125
SB3 1645
1645 15 62 SB3
SB3 5948 Doha - Qatar
450
1645
SB3 1645 160 199
300
1565 1565
SB3
250
DET. A SB1 SB3 SB1
7
SB3 SB3 SB3 SB3
0
M20
*1
47 3208 3297 820
15
CSK Originator Name & Logo:
PL
R=70050
SB1 250
10.48
SB1 DET. B 2E 13 14
SB1 SB1
DET. A
3250
4400
3250
1:10
R50
Project:
57 100
300 Qatar Integrated Railway Project
Doha Metro:Major Stations
3441
PL15*35
3208
3130
SC1 RTC/193/2016
100
50
R150
R150
Discipline:
ARCHITECTURAL
2808 800 2497 800 420
300
SB3 Drawing Title:
450
575
250
PL
5169 47 3208 3297 3496 M20 MSHEIREB STATION
15
250
2B CSK
*10
BOS METRO ENTRANCE 2 - CANOPY - STRUCTURE FRAMING
7
+4.85 SC1 NOTE: P1.2 SECONDARY SHELTERS DETAIL DESIGN
Baseplate detail 300
ref. M007-ONW-ARC-DWG-UCST000-AA-11324 Originator: Contractor:
SB1
Drawn C. MICONO 18/10/16 Checked
01 02 Checked S. CORNEGLIANI 18/10/16
Approved G. DE CARLI 18/10/16 Approved
M007-ONW-ARC-DWG-UCST000-AA-11320 1.0
THE DRAWING AND ANY INFORMATION OR DESCRIPTIVE MATTER SET OUT HEREON IS LICENSED TO THE QATAR RAILWAYS COMPANY AND IS CONFIDENTIAL AND SUBJECT TO COPYRIGHT. IT MUST NOT BE DISCLOSED, LOANED, COPIED OR USED FOR MANUFACTURING, TENDERING OR FOR ANY OTHER PURPOSE WITHOUT WRITTEN PERMISSION. QATAR RAILWAYS COMPANY.
SR.PROJECT ENGINEER
J. C NAIR
00971-556323740
QUANTITY SURVEYOR DESIGN COORDINATOR SITE SUPERVISOR QA/QC ENGINEER SAFETY OFFICER
RAMEESH MOHAMMED.S FRANCIS KOTTUNGAL. O CIJO. P
00971-564301273 00974-55172027 00971-564301272 00974-77394109 00971-551954609
OPERATIVES
DRAWING:
SPEC:
Method Statement:
Witness Point
Hold Point
Signature
Name
Date
PMC
Status
No Objection No Objection With Comments Rejected Cancelled
Notes:
1. This document shall not be used to specify acceptance of the Inspection / Test; this can only be achieved by sign off of an appropriate inspection
/ test report which shall be attached hereto, and does not relieve the Contractor of his obligations under the Contract .
2. PMC Inspection shall occur only after the Inspection / Test report is signed off by Contractor QC Representative confirming
approval of the work.
FRM-M007-005-0001 Rev 3
CONSOLIDATED CONTRACTORS GROUP S.A.L (OFFSHORE) (CCC)
Construction Management Services for Major Stations
Contract No.: RTC/176/2016
Station MUS
0B EDU
1B Document No.
Rev No.
Subject / Title
Date
Material
Quantity
Description
Material
Material Grade
Standard
Specification (MAR)Submittal
Ref. Ref.
Remarks:
Status
Party Not Name Signature Date
Approved
Approved
CCC Construction /
Procurement / Stores
CCC QA/QC
Subcontractor
Construction /
Procurement / Stores
Subcontractor QA/QC
Supervision Engineer
Status
Party Name Signature Date
No Objection Objection
PMC
Station MUS
0B EDU
1B Document No.
Rev No.
Subject / Title
Date
Remarks:
Note: If the member leans towards N/E the reading taken +ve, S/W the reading is taken -ve