APPROXIMATE ESTIMATE FOR THE CONSTRUCTION OF BORE HOLE AT

KOTOKROM

ITE DESCRIPTION QTY UNIT PRICE AMOUNT


M
1 Rambo poly tank(700) 1 nr 2,500.00 2,500.00
2 P. E. pipe(1) 80 mtr 400.00 450.00
3 1.5 hose power pump(1) 1 nr 900.00 900.00
4 P.E. Adopter (1) 2 nr 30.00 70.00
5 Fanket bend(1) 2 nr 5.00 10.00
6 P.m pipes (1) 18 nr 17.00 306.00
7 P.m pipes (3/4) 4 nr 12.00 48.00
8 Air valve (1) 30 nr 1.00 30.00
9 Water filter (1) 2 nr 50.00 100.00
10 British stop cock(1) 2 nr 75.00 150.00
11 Hose tap (3/4) 3 nr 25.00 75.00
13 Fanket bend (3/4) 3 nr 5.00 15.00
14 P.m reducer ( 13/4) 4 nr 3.00 12.00
15 P.M bend (1) 14 nr 3.00 42.00
16 P.m bend (3/4) 10 nr 3.00 30.00
17 P.m tee (1) 5 nr 3.00 15.00
18 Tangent glue 5 nr 12.00 60.00
19 Stop cock (3/4) 3 nr 30.00 90.00
20 Valve socket (1) 14 nr 3.00 42.00
21 Clean out (1) 1 nr 40.00 40.00
22 P.m union (1) 4 nr 12.00 48.00
23 P.m tee (3/4) 4 nr 3.00 12.00
24 Thread tape 10 nr 3.00 30.00
WORKMANSHIP FOR PLUMBING 1,500.00
TOTAL COST FOR PLUMBING 6,130.00
WORKS
25 Ordinary Portland cement 40 bags 32.00 1,280.00
26 12mm iron rods 12 nr 20.00 240.00
27 WORKMANSHIP FOR MASONERY 1,000.00
TOTAL MASONERY WORK 2,500.00
28 Tiles 30 boxes 24.00 600.00
29 Tile cement 10 bags 5.00 50.00
30 WORKMANSHIP FOR TILES 450.00
TOTAL COST FOR TILING 1,100.00
31 112wawa board 5 nr 20.00 100.00
32 WORKMANSHIP FOR 200.00
CARPENTARY
TOTAL COST FOR CARPENTARY 300.00
WORKS
33 COST OF DRILLING 7,500.00
COLLECT TO SUMMARY
PLUMBING 6,130.00
MASONERY 2,500.00
TILING 1,100.00
CARPENTARY 300.00
DRILLING 7,500.00
GRAND TOTAL 17,530.00