Abstract of Cost
Project :- Namuna Ekikrit Basti Bikash Karyakram Gatlang, Goljung F/Y:- 2073/074
Site: Gatlang, Goljung V. D. C, Rasuwa
S.N. Description of Work Quantity Unit Rate Rs. Unit Amount Remarks
A. Civil Works
1 Earthwork and Earthfilling
Site preparation work with cleaning and disposal of
1.1 debrises, uprooting roots, solid wastes etc. all 227.50 Sqm 15.34 Sqm 3489.85
complete as per instruction.
Earthwork in excavation in hard/boulder mix soils in
1.2 foundation including 10m hauling distance and 1.5 1559.66 Cum 549.60 Cum 857189.13
m. lift all complete.
Earth filling in 150/150 mm thick layer, watering,
1.3 ramming including supply of filling materials within 150.41 Cum 619.62 Cum 93197.04
10 m distance all complete.
3 Stone Work
Rubble masonry in 1:6 C/S mortar in perfect line
3.1 level finish including, racking the joints and curing 404.43 Cum 11545.62 Cum 4669395.09
the work for at least 7 days all complete.
3.2 Rubble stone filling work in foundation and in floor. 603.71 Cum 2587.50 Cum 1562099.62
Government Of Nepal
Ministry of Urban Development
Department of Urban Development and Building Construction
Division Office, Rasuwa
Abstract of Cost
Project :- Namuna Ekikrit Basti Bikash Karyakram Gatlang, Goljung F/Y:- 2073/074
Site: Gatlang, Goljung V. D. C, Rasuwa
S.N. Description of Work Quantity Unit Rate Rs. Unit Amount Remarks
7 Plastering Work
8 Painting works
Government Of Nepal
Ministry of Urban Development
Department of Urban Development and Building Construction
Division Office, Rasuwa
Abstract of Cost
Project :- Namuna Ekikrit Basti Bikash Karyakram Gatlang, Goljung F/Y:- 2073/074
Site: Gatlang, Goljung V. D. C, Rasuwa
S.N. Description of Work Quantity Unit Rate Rs. Unit Amount Remarks
Supplying and painting two coat distemper paint
8.2 with one coat primer as per specification and 86.06 Sqm 157.02 Sqm 13513.14
instruction, all complete
9 Door, window & wooden work
Fixing of aluminium Casement door section
9.1 (100x38x1.5)mm of naturally anodized colour with 12.38 Sqm 6637.4 Sqm 82171.01
5mm glass.
Supplying and fitting 2 track aluminium sliding
9.2 window in naturally anodized colour of 5.79 Sqm 7040.88 Sqm 40766.69
section(88x38x1.5)mm with 5 mm glass.
Supplying and fitting Aluminium swing door section
9.3 2.35 Sqm 10334.76 Sqm 24286.68
of (101 x45 x1.5)mm & 5mm glass.
10 Steel & Iron Works
M.S.black pipe roof truss with I.S. or B.S. section
including jointing, fixing, erection and primer
painting with all necessary M.S. bed plates, shoe
10.1 895.51 Kg 181.73 Kg 162741.03
angles anchor bolts leas sheeting or cement
grouting as per drawing and instructions, all
complete .
11.0 Roofing Works
Government Of Nepal
Ministry of Urban Development
Department of Urban Development and Building Construction
Division Office, Rasuwa
Abstract of Cost
Project :- Namuna Ekikrit Basti Bikash Karyakram Gatlang, Goljung F/Y:- 2073/074
Site: Gatlang, Goljung V. D. C, Rasuwa
S.N. Description of Work Quantity Unit Rate Rs. Unit Amount Remarks
Supplying and fixing White glaze Indian Pattern
Porcelain clay wash basin/Oval with brackets
32mm dia. Pvc bottle trap, 32mm CP waste
coupling , 15mmx450mm long c.p. pipe connector
etc all complete.Sanitaryware:-.(
Parryware,Hindware, or equivalent ) .
3 Indian pattern Porcelain clay white glaze Oval
Wash Basin 50x40cm with inbuilt hole/over
5.00 set 11467.13 set 57335.65
counter/under counter and swan type piller cock
complete set.
4 Indian pattern White glazed porceline clay Urinal
46.5X31.5X26.5cm with necessary accessories all 2.00 Set 5325.69 Set 10651.38
complete set .
5
Porcelain clay white glaze Indian Pattern 68X30cm
1.00 Set 3285.21 Set 3285.21
size Urinal partation all complete set .
Government Of Nepal
Ministry of Urban Development
Department of Urban Development and Building Construction
Division Office, Rasuwa
Abstract of Cost
Project :- Namuna Ekikrit Basti Bikash Karyakram Gatlang, Goljung F/Y:- 2073/074
Site: Gatlang, Goljung V. D. C, Rasuwa
S.N. Description of Work Quantity Unit Rate Rs. Unit Amount Remarks
Supplying and Fixing Pipes all complete set as per
specification and instruction. (Panchakanya or
equivalent(N.S. )
20 40mm HDP pipe (4 kg/sqcm) 25.00 Rm 423.64 Rm 10591.00
25mm PPR pipe, PN-10 \SDR 11, Pachanya,
21 20.00 Rm 185.45 Rm 3709.00
Napatop or eqv,
20 mm PPR pipe, PN-10 \SDR 11, Pachanya,
22 20.00 Rm 134.26 Rm 2685.20
Napatop or eqv,
23 110 mm PVC Pipe 6 kg\cm2 20.00 Rm 975.22 Rm 19504.40
24 50 mm PVC Pipe 6 kg/cm2 10.00 Rm 297.95 Rm 2979.50
25 110 mm HDP pipe 4 kg/sqcm 15.00 Rm 810.27 Rm 12154.05
Sub-Total B ( Sum of Sanitary works ):- 337,140.10
C. ELECTRICAL WORKS
A. LUMINAIRES ( FIXTURES)
Accessories:screws, gripes, pvc tape, choke,
starter, Tube, bulbs, holder, flexible wire,GI pipe/
chain etc all complete.
Ceiling ligh/Dome light 8" heavy carrier with CFL
1 10.00 Set 338.85 Set 3388.50
etc all complete.
1x40 watt tube light box mirror optic Wipro/Ge or
2 2.00 Set 1442.92 Set 2885.84
eqvt.etc all complete.
Government Of Nepal
Ministry of Urban Development
Department of Urban Development and Building Construction
Division Office, Rasuwa
Abstract of Cost
Project :- Namuna Ekikrit Basti Bikash Karyakram Gatlang, Goljung F/Y:- 2073/074
Site: Gatlang, Goljung V. D. C, Rasuwa
S.N. Description of Work Quantity Unit Rate Rs. Unit Amount Remarks
Accessories: HDPE polythene pipe,PVC listy
screws,pvc tape, grips, circular box etc all
complete.
2x2.50 sq mm multi strand flexible cu .wire for light
9 & fan point in 1/2"HDPE polythene pipe /PVC listy 15.00 Point 1005.83 Point 15087.45
etc all complete.
2x4.0+1x1.50 sq.mm multi strand flexible cu wire
10 for power point in 3/4" HDPE polythene pipe/PVC 10.00 Point 1676.58 Point 16765.80
listy etc all complete.
Sub-Total C ( Sum of Electrical works ):- 56,887.17
Sub-Total ( A+B+C):- 16,684,882.85
D. Provisional sum
(a) Insurance Premium Amount Rs. 131,575.98
(b) Test Amount Rs. 37,866.00
Sub Total ( Provisional Sum): 169,441.98
E Total 3 ( A+B+C+D) 16,854,324.83
F Contingencies @ 5% 842,716.24
G Total 4(G+H) 17,697,041.07
H Vat @ 13% 2,300,615.33
I Total 5(I+J)) 19,997,656.40
J 10% of Total 3 for Physical contingencies 1,769,704.11
K 10% of Total 3 for Price Adjustment 1,769,704.11
L Grand Total 6 (K+L+M) 23,537,064.62