Protective relaying
Numerical Breaker Management Protection 7VK61(Synchro Check Relay)
Commissioning certificate 8/2012
Customer : EETC
Plant : Maghagha 220 kV S/S Contract-No.:
Feeder : B00+D09

MLFB - No.: 7VK6101-6AB02-4YN0

Serial.-No.: In = A f= 50 Hz UH = 220 V Un = 100 V


dc
Voltage Transformers: V.T. UN=
Ratio: 220 000/100 UN= UN=

1. Relay Settings:
A printout of the relay settings is attached.

2. Secondary Injection Test Set Up:


Where secondary tests are to be performed, a three-phase test equipment providing
test voltage recommended (e.g. Omicron CMC 256 for manual and automatic testing).
The phase angle between voltage phases should be continuously controllable.
The frequency of each phase separately should be controllable.
Tester Connection:
Table-1: Injection Connection

Tester Points Function Test Switch Relay points


VR Feeder voltage (Phase R) 3B R15
VS Feeder voltage (Phase S) 4B R16
Voltage
VR Bus Bar voltage (Phase R) 1B R13
VS Bus Bar voltage (Phase S) 2B R14
BI1-red 2C,4C R7,R8
Bin.
Close order
Input-1 BI1- Blk

Tested by Witnessed by
Siemens S.A.E Client :EETC
Name: Ismail M. Mosaed Name: Ahmed Esmat
Date: 20 -11-2016 Date: 19-10-2016
Signature Signature
Page 2 / 4

3. Operational measured values

Relay Readings
Injected Voltage
Primary Secondary
Line VR -VS 100 V , 50 Hz 220 KV , 50 Hz 100V,50 Hz
BB VR -VS 100 V , 50 Hz 220 KV , 50 Hz 100V,50 Hz

4. Synchrocheck

Parameters Setting Measured Remarks

Dead. voltage limit 15 V 15 V


Max. voltage limit 110 V 110 V
On command at U1<and U2> OK
On command at U1>and U2< OK
On command at U1<andU2< N/A
Synchronisim From in to Out From Out to In

Max voltage difference 10 V 10.4 V 10V

Max Frequency difference 0.05 Hz 0.052 Hz 0.05 Hz

Max angle difference 10 o 10.5 o 10 o

Blocking By BB VT mcb No starting

Synchro Over Ride OK


Synchro Over Ride trigger
OK
internal Fault Recorder

Tested by Witnessed by
Siemens S.A.E Client :EETC
Name: Ismail M. Mosaed Name: Ahmed Esmat
Date: 20 -11-2016 Date: 19-10-2016
Signature Signature
Page 3 / 4

5. Function Test of the Relay:


Condition Description Voltage Values Expected Result
Live / Dead 100 / 9
DEAD / LIVE 9 / 100
Within Limits CB Cloesd
DEAD / DEAD N/A
LIVE / LIVE 100 / 100
Not Dead 100 / 30
Out Of Limits NOT LIVE 80 / 9
OK
MAX LIMIT 112 / 108
U >> 100 / 104
CB Not Closed
Out Of Synchronism F >> 50HZ / 50.12
>> 0 / 12
Synchro start request
Out of Time limit 100 / 100
lasts for > 30 Sec.

LEDs Operation Tested According to setting OK


B/I Operation Tested According to setting OK
B/O Operation Tested According to setting OK

Tested by Witnessed by
Siemens S.A.E Client :EETC
Name: Ismail M. Mosaed Name: Ahmed Esmat
Date: 20 -11-2016 Date: 19-10-2016
Signature Signature
Page 4 / 4

6. Circuit Breaker close Test as following:


Selected Voltage
Conditions Bay Expected Result
Voltages Value
- Start Synchro
BB l & Feeder - Q01 ON D01 100 V, 95 V CB Close (Synchronism) OK
- BB I VT mcb ON

- Start Synchro
BB lI & Feeder - Q01 ON D01 100 V, 95 V CB Close (Synchronism) OK
- BB II VT mcb ON

Tested by Witnessed by
Siemens S.A.E Client :EETC
Name: Ismail M. Mosaed Name: Ahmed Esmat
Date: 20 -11-2016 Date: 19-10-2016
Signature Signature