PEMERINTAH KABUPATEN BANYUMAS

DINAS CIPTA KARYA KEBERSIHAN DAN TATA RUANG DAFTAR HARGA SATUAN
Jl.Gerilya Barat No. 05 Telp. (0281) 640359 UPAH , BAHAN & ALAT
PURWOKERTO TAHUN 2008 (Perubahan)
HARGA SATUAN UPAH (Rp)
NO. SATUAN KODE JENIS UPAH PEK. SWAKELOLA PEK. DIBORONGKAN
Rp / OH Rp / OH Rp / Jam
A. UPAH
1 OH L.001 Tukang Batu 29,000.00 32,500.00 4,642.86
2 OH L.002 Tukang Kayu 29,000.00 32,500.00 4,642.86
3 OH L.003 Tukang Besi 29,000.00 32,500.00 4,642.86
4 OH L.004 Tukang Cat 29,000.00 32,500.00 4,642.86
5 OH L.005 Tukang Dempul 29,000.00 32,500.00 4,642.86
6 OH L.006 Tukang Plistur 29,000.00 32,500.00 4,642.86
7 OH L.007 Kepala Tukang 31,500.00 35,000.00 5,000.00
8 OH L.008 Pekerja 24,500.00 27,000.00 3,857.14
9 OH L.009 Pekerja Bongkar / Siram 24,500.00 27,000.00 3,857.14
10 OH L.010 Mandor 31,500.00 35,000.00 5,000.00
11 OH L.011 Tukang Batu Ahli 35,000.00 ### 5,000.00
12 OH L.012 Operator Mesin Poles 50,000.00 ### 5,000.00
11 OH L.021 Operator Alat Berat 31,500.00 35,000.00 5,000.00
12 OH L.022 Pembantu Operator 28,500.00 31,500.00 4,500.00
13 OH L.023 Sopir 28,500.00 31,500.00 4,500.00
14 OH L.024 Pembantu Sopir 25,500.00 28,000.00 4,000.00

HARGA SATUAN BAHAN (Rp)


NO. SATUAN KODE JENIS BAHAN KATAGORI I (Mudah) KATAGORI II (Sulit)
1 2 3 4 5 6
B. BAHAN
100 M3 M.100 Agregat Kasar Beton 146,500.00 152,500.00
M3 M.101 Agregat Kasar Klas A 148,600.00 154,900.00
M3 M.102 Agregat Halus Klas A 136,600.00 139,800.00
M3 M.103 Agregat Kasar Klas B 145,400.00 151,300.00
M3 M.104 Agregat Halus Klas B 135,060.00 138,125.00
M3 M.105 Agregat Kasar Klas ATB 146,500.00 152,450.00
M3 M.106 Agregat Halus Klas ATB 123,300.00 125,875.00
M3 M.107 Agregat Kasar Klas AC (Laston) 149,600.00 155,150.00
M3 M.108 Agregat Halus Klas AC (Laston) 125,700.00 128,500.00
M3 M.109 Agregat Kasar Klas HRS (Lataston) 149,600.00 155,150.00
M3 M.110 Agregat Halus Klas HRS (Lataston) 125,700.00 128,500.00
M3 M.111 Agregat Pokok Lapen 140,000.00 146,000.00
M3 M.112 Agregat Pengunci Lapen 149,825.00 154,880.00
M3 M.112a Agregat Penutup Lapen 125,650.00 128,500.00

001 M3 M.001 Pasir Beton 92,500.00 100,000.00


M3 M.001a Pasir Pasang 85,000.00 92,500.00
M3 M.001b Pasir Urug / Timbun 55,000.00 62,500.00
M3 M.001c Tanah Urug 50,000.00 55,000.00
M3 M.001d Kapur Pasang 135,000.00 140,000.00
M3 M.001e Sirtu 62,500.00 67,500.00
M3 M.001e1 Agregat Klas C 62,500.00 67,500.00
M3 M.001f Batu Kali Belah 93,000.00 95,000.00
M3 M.001f1 Batu belah 15 / 20 cm 95,000.00 100,000.00
M3 M.001f2 Batu belah 10 / 15 cm 100,000.00 105,000.00
M3 M.001f3 Batu pecah 5 / 7 cm 106,000.00 111,000.00

halaman 1 / 128
HARGA SATUAN BAHAN (Rp)
NO. SATUAN KODE JENIS BAHAN KATAGORI I (Mudah) KATAGORI II (Sulit)
1 2 3 4 5 6
M3 M.001f4 Batu pecah 3 / 5 cm 137,000.00 142,000.00
M3 M.001g Batu Pecah 2/3 cm (Koral beton) 140,000.00 150,000.00
M3 M.001h Batu Pecah Mesin 2/3 cm 143,000.00 150,000.00
M3 M.001i Batu Pecah Mesin 1/2 cm 150,000.00 155,000.00
M3 M.001i1 Batu pecah 0,5 - 1 cm 152,000.00 160,000.00
M3 M.001i2 Batu pecah 0,2 - 0,50 cm 156,000.00 160,000.00
M3 M.001i3 Abu Batu 122,500.00 125,000.00
Kg M.001i4 Filler 200.00 250.00
Bh M.001j Batu Bata 360.00 380.00
M3 M.001k Batu Blonos 70,000.00 75,000.00
Kg M.001l Tali Ijuk 5,500.00 6,000.00

halaman 2 / 128
HARGA SATUAN BAHAN (Rp)
NO. SATUAN KODE JENIS BAHAN KATAGORI I (Mudah) KATAGORI II (Sulit)
1 2 3 4 5 6

M3 M.001m Batu Bata 216,000.00 228,000.00


M3 M.001n Batu Kerikil 40,000.00 50,000.00
M3 M.001o Ijuk 270,000.00 290,000.00
Bh M.001p Sikat Kawat / Plastik 6,500.00 ###

002 Zak M.002 Portland Cement 50 Kg 60,000.00 60,350.00


Kg M.002a Portland Cement 1,200.00 1,207.00
Kg M.002b PC Warna 1,500.00 1,550.00

003 Kg M.003 Besi Beton ( Polos ) (sek.KS) 15,000.00 16,000.00


Kg M.003.1 Besi Beton ( Polos ) (sek.Non KS) 14,000.00 15,000.00
Kg M.003a Bindrat 17,300.00 18,300.00
Kg M.003b Besi Siku / Propil 14,000.00 15,000.00
Kg M.003c Besi Beton ( Ulir ) 15,000.00 16,000.00
Bh M.003d Begel ( Besi Strip ) 21,000.00 22,000.00
Kg M.003e Kawat Bronjong 4 mm 18,500.00 21,500.00
Kg M.003f Mur, baud 20,650.00 21,000.00

004 Bh M.004 Keramik Lantai 20 x 20 cm (klas A : mulia, arwana) 1,630.00 1,730.00


Bh M.004a Keramik Lantai 20 x 20 cm (klas B : Asia tile, picaso) 1,800.00 1,900.00
Bh M.004b Keramik Lantai 20 x 20 cm (klas C : Roman) 2,400.00 ###
Bh M.004c Keramik Lantai 33 x 33 cm (klas C : Roman) 7,000.00 7,200.00
Bh M.004d Keramik Lantai 40 x 40 cm (klas A : mulia,arwana, garuda,venesia) 6,670.00 6,870.00
Bh M.004e Keramik Lantai 40 x 40 cm (klas B : Asia tile, picaso) 7,420.00 7,620.00
Bh M.004e.1 Keramik Lantai 40 x 40 cm (klas C : platinum) 9,400.00 9,500.00
Bh M.004e.2 Keramik Lantai 40 x 40 cm (klas D : Roman) 12,600.00 12,745.00
Bh M.004f Keramik Lantai 30 x 30 cm (klas A : mulia,arwana) 3,000.00 3,155.00
Bh M.004g Keramik Lantai 30 x 30 cm (klas B : Asia tile, picaso) 3,445.00 3,645.00
Bh M.004g.1 Keramik Lantai 30 x 30 cm (klas C : KIA, impreso, masterina) 4,150.00 4,350.00
Bh M.004g.2 Keramik Lantai 30 x 30 cm (klas D : Roman) 5,850.00 5,909.00
Bh M.004h Keramik Lantai 33x33 cm Anti Slip (klas C : Roman) 7,100.00 7,200.00
Bh M.004i Keramik Lantai 40x40 cm Anti Slip (klas A:mulia,arwana,garuda,venesia) 7,335.00 7,535.00
Bh M.004j Keramik Lantai 40x40 cm Anti Slip (klas B : Asia tile, picaso) 8,500.00 8,650.00
Bh M.004j.1 Keramik Lantai 40x40 cm Anti Slip (klas C : platinum) 9,500.00 9,600.00
Bh M.004j.2 Keramik Lantai 40x40 cm Anti Slip (klas D : Roman) 13,100.00 13,220.00
Bh M.004k Keramik Lantai 30x30 cm Anti Slip (klas A : mulia, arwana) 3,275.00 3,475.00
Bh M.004l Keramik Lantai 30x30 cm Anti Slip (klas B : Asia tile, picaso) 3,820.00 4,020.00
Bh M.004l.1 Keramik Lantai 30 x 30 cm Anti Slip (klas C : KIA, impreso, masterina) 4,275.00 4,475.00
Bh M.004l.2 Keramik Lantai 30 x 30 cm Anti Slip (klas D : Roman) 5,950.00 6,060.00
Bh M.004m Keramik Dinding 20 x 20 cm (Klas A : mulia) 1,560.00 1,660.00
Bh M.004n Keramik Dinding 20 x 20 cm (Klas B : roman) 2,400.00 2,438.00
Bh M.004o Keramik Dinding 20 x 25 cm (Klas A : mulia,asia tile,picasso,arwana, 2,300.00 2,400.00
masterina)
Bh M.004o.1 Keramik Dinding 20 x 25 cm (Klas B : KIA impresso) 2,610.00 2,710.00
Bh M.004o.2 Keramik Dinding 20 x 25 cm (Klas C : platinum) 2,700.00 2,800.00
Bh M.004o.3 Keramik Dinding 20 x 25 cm (Klas D : roman) 2,945.00 3,045.00
Bh M.004p Ubin Abu-abu 20 x 20 cm 700.00 800.00
Bh M.004q Ubin Abu-abu 30 x 30 cm 2,000.00 2,250.00
M2 M.004r Lembaran Granit lokal 250,000.00 300,000.00
M2 M.004s Lembaran Granit Import 1,125,000.00 1,500,000.00
M2 M.004t Batu Candi 171,500.00 190,000.00
M2 M.004u Batu Koral Hitam 112,500.00 130,000.00
M2 M.004v Lembaran Granit Import 750,000.00 ###

005 M3 M.005 Glugu Tua 1,350,000.00 1,400,000.00

halaman 3 / 128
HARGA SATUAN BAHAN (Rp)
NO. SATUAN KODE JENIS BAHAN KATAGORI I (Mudah) KATAGORI II (Sulit)
1 2 3 4 5 6
M3 M.005a Kayu Tahun 1,350,000.00 1,400,000.00
M3 M.005b Kayu Meranti Balok 4,010,000.00 4,035,000.00
M3 M.005c Kayu Kruing Balok 5,520,000.00 5,595,000.00
M3 M.005d Kayu Bangkir Balok 7,745,000.00 7,820,000.00
Kayu Bangkir Balok uk. Khusus 30/30, 18/25, 20/20, 14/20, 16/16,
M3 M.005d1 14/14, 12/12 P : 5-8 m' 9,720,000.00 9,795,000.00
M3 M.005d2 Kayu Bangkir Balok uk. Khusus 8/15, 8/12, 6/15, 6/12, 5/10 P : 5-8 m' 10,325,000.00 10,400,000.00
M3 M.005e Kayu Kamper Balok 7,599,000.00 7,674,000.00
M3 M.005f Kayu Jati Balok (lokal) 14,500,000.00 14,575,000.00
Kayu Jati Balok (Kw. Eksport) uk. Khusus 30/30, 18/25, 20/20, 14/20,
M3 M.005f1 16/16, 14/14, 12/12 P : 5-8 m' 48,000,000.00 48,075,000.00

halaman 4 / 128
HARGA SATUAN BAHAN (Rp)
NO. SATUAN KODE JENIS BAHAN KATAGORI I (Mudah) KATAGORI II (Sulit)
1 2 3 4 5 6

Kayu Jati Balok (Kw. Eksport) uk. Khusus 8/15, 8/12, 6/15, 6/12, 5/10
M3 M.005f2 P : 5-8 m' 30,375,000.00 30,450,000.00
M3 M.005f3 Kayu Jati Balok (Kw. Eksport) Bukan Khusus P : 2-4 m' 25,000,000.00 25,075,000.00
M3 M.005g Usuk Meranti 5/7 3,900,000.00 3,975,000.00
M3 M.005h Usuk Kruing 5/7 4,900,000.00 4,975,000.00
M3 M.005i Usuk Bangkir 5/7 6,500,000.00 6,575,000.00
M3 M.005j Usuk Kamper 5/7 5,800,000.00 5,875,000.00
M3 M.005k Usuk Jati 5/7 9,900,000.00 9,975,000.00
M3 M.005l Papan Meranti 4,275,000.00 4,350,000.00
M3 M.005m Papan Kruing 6,100,000.00 6,175,000.00
M3 M.005n Papan Bangkir 9,000,000.00 9,075,000.00
M3 M.005o Papan Kamper 8,500,000.00 8,575,000.00
M3 M.005p Papan Jati (lokal) 12,800,000.00 12,875,000.00
M3 M.005p1 Papan Jati (Kw. Eksport) 39,300,000.00 39,375,000.00
M' M.005q Lis kayu propil ( kayu kruing ) 5,500.00 6,000.00
M' M.005r Lis kayu kruing 3,500.00 4,000.00
Btg M.005s Dolken kayu dim. 8 - 10 P : 4m 30,000.00 35,000.00
Btg M.005t Usuk 5/7 kayu tahun 17,500.00 18,000.00
M3 M.005u Kayu Perancah 975,000.00 1,000,000.00

006 Kg M.006 Paku Biasa ( 2" - 5") usuk,reng,plafon 18,000.00 ###


Kg M.006a Paku Eternit, Lis 21,850.00 ###
Kg M.006b Paku Kait 28,000.00 ###
Kg M.006c Paku Seng ( 1/2" - 1") 24,000.00 ###
Bj M.006d Paku Payung 500.00 ###
Bj M.006e Paku Sumbat 500.00 ###
Btg M.006f Bambu 7,500.00 8,000.00
Bj M.006g Skrup 3.5" 600.00 ###
Kg M.006h Skrup 36,000.00 ###
Kg M.006i Paku beton 5 cm 29,000.00 ###

007 Lbr M.007 Eternit Kerang Super 7,000.00 7,200.00


M2 M.007a Harplek 4 mm 17,000.00 17,500.00
Lbr M.007b Gypsum board tb. 9 mm 53,000.00 55,000.00
008 M2 M.008 Kaca Bening 3 mm 51,000.00 55,000.00
M2 M.008a Kaca Bening 5 mm 75,000.00 76,500.00
M2 M.008b Kaca Polos 8 mm 180,000.00 182,000.00
M2 M.008c Kaca Cermin 5 mm 170,000.00 172,000.00
M2 M.008d Kawat burung 14,000.00 15,000.00

009 M2 M.009 Triplek 3 mm 25,650.00 26,000.00


Lbr M.009a Triplek 3 mm 0,9 x 2,1 m 48,500.00 50,000.00
M2 M.009b Multiplek 9 mm 74,000.00 75,600.00
Lbr M.009c Multiplek 9 mm 0,9 x 2,1 m 140,000.00 143,000.00
M2 M.009d Teakwood 3 mm 40,740.00 41,000.00
Lbr M.009e Teakwood 3 mm 0,9 x 2,1 m 77,000.00 78,000.00

010 Bj M.010 Genteng Vlams Sokka 800.00 850.00


Bj M.010a Genteng Pres Plentong 1,090.00 1,140.00
Bj M.010b Genteng Pres Kodok 1,300.00 1,350.00
Bj M.010c Genteng Nok Pres Sokka 2,500.00 2,750.00
Bj M.010d Genteng Margase 1,350.00 1,400.00
Bj M.010e Genteng Morando 2,050.00 2,100.00
Bj M.010f Genteng Nok Morando / Margase 4,000.00 4,100.00
Bj M.010g Genteng Paris Sokka 1,500.00 1,650.00

halaman 5 / 128
HARGA SATUAN BAHAN (Rp)
NO. SATUAN KODE JENIS BAHAN KATAGORI I (Mudah) KATAGORI II (Sulit)
1 2 3 4 5 6
Bj M.010h Genteng Nok Paris Sokka 4,500.00 4,550.00
Bj M.010i Genteng Nok Beton 4,000.00 4,050.00
Bj M.010j Genteng Beton 3,800.00 3,850.00
Bj M.010k Genteng Keramik natural 5,500.00 5,600.00
Lbr M.010l Seng Gelombang BJLS 20 ( 0,90 x 1,80 ) 47,000.00 48,000.00
Lbr M.010m Seng Gelombang BJLS 30 ( 0,90 x 1,80 ) 50,000.00 51,000.00
Lbr M.010n Seng Plat BJLS 30 ( 0,90 x 1,80 ) 24,000.00 25,000.00
Lbr M.010o Fiber semen Gelombang 4 mm ( 3,00 x 1,05 ) x 4 mm 85,000.00 86,000.00
Lbr M.010p Fiber semen Gelombang 4 mm ( 2,70 x 1,05 ) x 4 mm 77,000.00 78,000.00
Lbr M.010q Fiber semen Gelombang 4 mm ( 2,40 x 1,05 ) x 4 mm 69,000.00 70,000.00
Lbr M.010r Fiber semen Gelombang 4 mm ( 2,10 x 1,05 ) x 4 mm 60,000.00 61,000.00

halaman 6 / 128
HARGA SATUAN BAHAN (Rp)
NO. SATUAN KODE JENIS BAHAN KATAGORI I (Mudah) KATAGORI II (Sulit)
1 2 3 4 5 6

Lbr M.010s Fiber semen Gelombang 4 mm ( 1,50 x 1,05 ) x 4 mm 43,000.00 44,000.00


Psg M.010t Nok Still Asbes Gelombang 23,000.00 24,000.00
M2 M.010u Aluminium Foil / Sisalation 13,000.00 13,500.00
Lbr M.010v Seng Galvalum 290,000.00 300,000.00

011 Kg M.011 Cat Kayu setingkat AVIAN 37,700.00 38,500.00


Kg M.011a Cat Kayu setingkat DULUX 70,000.00 71,000.00
Kg M.011a.1 Cat Tembok untuk interior (sekualitas Mowilex) 44,500.00 45,000.00
Kg M.011a.2 Cat Tembok untuk exterior (sekualitas Mowilex) 66,000.00 ###
Kg M.011b Cat Tembok (sekualitas Catylac) 15,550.00 16,050.00
Kg M.011c Cat Tembok (sekualitas Decolith) 12,750.00 13,250.00
Kg M.011d Cat Tembok (sekualitas Maxilite) 10,450.00 10,950.00
Kg M.011e Cat Genteng (sekualitas Tamitex) 26,000.00 26,500.00
Kg M.011f Cat Meni 11,000.00 12,000.00
Kg M.011g Minyak Cat 5,000.00 6,000.00
Kg M.011h Meni Besi 11,000.00 12,000.00
Ltr M.011i Thinner 15,000.00 ###
Kg M.011j Cat minyak 35,000.00 ###
Kg M.011k Cat Marka Jalan 20,000.00 ###
Kg M.011l Glass Bit 15,000.00 ###
Ltr M.011m Curing Compund 7,500.00 ###

012 Kg M.012 Batu Kambang / Apung 6,275.00 6,500.00


Kg M.012a Plamir Tembok 7,500.00 ###
Kg M.012b Plamir Kayu 16,000.00 16,500.00
Lbr M.012c Amp l a s 3,000.00 ###
Kg M.012d Dempul Lilin 30,000.00 30,500.00
Kg M.012e Dempul Kayu 16,000.00 16,500.00
Kg M.012f Kapur sirih / Labur / Gamping 2,000.00 ###
Kg M.012g Lem Kayu 17,000.00 ###
Kg M.012h Politur 36,000.00 ###
Ikat M.012i Alang-alang 2,000.00 2,200.00
ltr M.012j Tir Kayu 8,000.00 ###
ltr M.012k OlI 37,000.00 ###
Kg M.012l Soda api 19,000.00 ###
Kg M.012m Politur sek. Mowilex 60,000.00 ###
Bh M.012n Kuas 3,800.00 4,000.00
Ltr M.012o Resin warna 47,000.00 ###
Ltr M.012p Cairan coating 19,000.00 ###
set M.012q Batu grenda poles 380,000.00 ###
Kg M.012r Obat poles 120,000.00 ###
Glg M.012s Kain poles 9,000.00 ###
Bh M.012t Kain pel 9,500.00 ###
Kg M.012u Semir lantai sek. MAA 17,000.00 ###

013 M2 M.013 Paving Blok Natural 6 cm 37,000.00 38,000.00


M2 M.013a Paving Blok Warna 6 cm 60,000.00 61,000.00
M2 M.013b Paving Blok Aldas t : 8 cm K - 400 105,000.00 107,000.00
M2 M.013c Paving Blok Aldas t : 6 cm K - 300 65,000.00 66,000.00
M2 M.013d Batu Andesit 20/20 cm (ex. Baseh) 275,000.00 ###

014 Bh M.014 Kunci tanam antik 300,000.00 ###


Bh M.014a Kunci tanam biasa sek. Yalle 90,000.00 85,000.00
Bh M.014b Kunci tanam kamar mandi 35,000.00 32,000.00

halaman 7 / 128
HARGA SATUAN BAHAN (Rp)
NO. SATUAN KODE JENIS BAHAN KATAGORI I (Mudah) KATAGORI II (Sulit)
1 2 3 4 5 6
Bh M.014c Engsel pintu 7,500.00 ###
Bh M.014d Engsel jendela kupu-kupu 5,000.00 ###
Bh M.014e Engsel angin 20,000.00 ###
Bh M.014f Kait Angin model lipat 5,000.00 ###
Bh M.014f.1 Kait Angin model antik 16,500.00 ###
Bh M.014g Door Closer 200,000.00 ###
Bh M.014h Kunci slot 85,000.00 ###
Bh M.014i Pegangan Pintu / Door Holder 175,500.00 ###
Bh M.014j Door Stop 37,000.00 ###
Bh M.014k Rel Pintu Dorong 300,000.00 ###

015 Bh M.015 Kloset duduk sek. Toto (lengkap asesories) 1,400,000.00 1,425,000.00
Bh M.015a Kloset jongkok sek. Toto 158,000.00 155,000.00

halaman 8 / 128
HARGA SATUAN BAHAN (Rp)
NO. SATUAN KODE JENIS BAHAN KATAGORI I (Mudah) KATAGORI II (Sulit)
1 2 3 4 5 6

Bh M.015b U r i n o i r sek. Toto 400,000.00 420,000.00


Bh M.015c W a s t a f e l sek. Toto 475,000.00 480,000.00
Bh M.015d Bak Mandi Fiberglass 175,000.00 157,000.00
Bh M.015d.1 Bak tangki air Fiberglass kap 500 ltr 796,000.00 552,000.00
Bh M.015e Bath tube 3,861,000.00 4,000,000.00
Bh M.015f Bak Cuci Piring Stainless 1 ruang 224,000.00 215,000.00
Bh M.015g Water drain + asesories 29,000.00 ###
Bh M.015h Kran air 3/4" (stainless steel ) 35,000.00 ###
Bh M.015h.1 Kran air 1/2" (stainless steel ) 15,000.00 ###
Bh M.015i Seal tape 2,500.00 ###
Bh M.015j Floor Drain (stainless steel ) 20,000.00 ###

016 M' M.016 Pipa Galvanis 1/2" med. B 17,500.00 18,000.00


M' M.016a Pipa Galvanis 3/4" med. B 23,500.00 24,000.00
M' M.016b Pipa Galvanis 1" med. B 30,500.00 31,000.00
M' M.016c Pipa Galvanis 1 1/2" med. B 43,000.00 43,500.00
M' M.016d Pipa Galvanis 2" med. B 54,000.00 54,500.00
M' M.016e Pipa Galvanis 3" med. B 96,500.00 97,000.00
M' M.016f Pipa Galvanis 4" med. B 130,500.00 131,000.00
M' M.016g Pipa PVC 1/2" type AW 4,000.00 4,500.00
M' M.016h Pipa PVC 3/4" type AW 5,450.00 5,950.00
M' M.016i Pipa PVC 1" type AW 7,000.00 7,500.00
M' M.016j Pipa PVC 1 1/2" type AW 10,800.00 11,500.00
M' M.016k Pipa PVC 2" type AW 13,850.00 14,000.00
M' M.016l Pipa PVC 3" type AW 27,250.00 28,000.00
M' M.016m Pipa PVC 4" type AW 45,000.00 46,000.00

HARGA SATUAN BAHAN (Rp)


NO. SATUAN KODE JENIS BAHAN
KATAGORI I (Mudah) KATAGORI II (Sulit)
1 2 3 4 5 6
017 Kg M.017 Aspal penetrasi 60/70 9,700.00 9,850.00
Ltr M.017a Bensin 6,000.00 6,500.00
Ltr M.017b Solar 5,500.00 6,000.00
Ltr M.017c Minyak Pelumas / Olie 37,500.00 38,500.00
Ltr M.017d Kerosene / Minyak tanah 2,700.00 3,200.00
M3 M.017e Kayu bakar 74,500.00 89,500.00
018 Bh M.018 Plat Rambu 350,000.00 ###
Bh M.018a Reflector 25,000.00 ###
M' M.018b Rel Pengaman (Guard Rail) 279,000.00 ###
m' M.018c Expantion Joint KW 1 650,000.00 ###
cm3 M.018d Karet Elastomer Bearing 200.00 ###
M' M.018e Karet delatasi 200,000.00 ###
kg M.018f Kawat las 20,000.00 ###
M' M.018g Tiang Pancang 310,000.00 ###

NO. SATUAN KODE JENIS ALAT HARGA SATUAN ALAT (Rp)


1 2 3 4 5
E Jam E.01 Asphalt Mixing Plant 3,086,729.33
Jam E.02 Asphalt Finisher 380,393.80
Jam E.03 Asphalt Sprayer 47,048.56
Jam E.04 Buldozer 100 - 150 HP 334,775.96

halaman 9 / 128
HARGA SATUAN BAHAN (Rp)
NO. SATUAN KODE JENIS BAHAN KATAGORI I (Mudah) KATAGORI II (Sulit)
1 2 3 4 5 6
Jam E.05 Compresor 4000 - 6500 L\M 126,595.63
Jam E.06 Concrete Mixer 0,125 M3 27,217.48
Jam E.07 Crane 10 - 15 Ton 286,558.98
Jam E.08 Stone Cruisher 419,775.96
Jam E.09 Motor Grader > 100 HP 271,764.87
Jam E.10 Excavator 80 - 140 HP 247,489.17
Jam E.11 Track Loader 75 - 100 HP 281,650.96
Jam E.12 Wheel Loader 1,0 - 1,6 m3 274,051.67
Jam E.13 Three Wheel Roller 6 - 8 T 197,389.87
Jam E.14 Tandem Roller 6 - 8 Ton 203,845.77
Jam E.15 Pneumatic. Tired Roller 501,191.73

halaman 10 / 128
HARGA SATUAN BAHAN (Rp)
NO. SATUAN KODE JENIS BAHAN KATAGORI I (Mudah) KATAGORI II (Sulit)
1 2 3 4 5 6

Jam E.16 Vibratory Roller 5 - 8 Ton 284,984.84


Jam E.17 Pedestrian Roller 25,103.45
Jam E.18 Water Tank Truck 2000-4500 L 146,845.63
Jam E.19 Dump Truck 3 - 4 M3 157,544.17
Jam E.20 Dump Truck 194,805.22
Jam E.21 Flat Bad Truck 3 - 4M3 153,585.71
Jam E.22 Generator Set 205,842.46
Jam E.23 Jack Hammer 47,346.97
Jam E.24 Concrete Vibrator 16,143.45
Jam E.25 Stamper 13,872.45
Jam E.26 Water Pump 70 - 100 mm 12,917.48
Jam E.27 Concrete Paver 50,000.00
Jam E.28 Concrete Cutting Machine 65,000.00
Jam E.29 Pile Hammer 50,000.00
Jam E.30 Mesin Las 60,000.00
Hr E.31 Sewa Mesin Poles 50,000.00

Purwokerto, September 2008

KEPALA DINAS CIPTA KARYA, KEBERSIHAN


DAN TATA RUANG KAB. BANYUMAS

Ir. ANDRIE SUBANDRIO, MT


Pembina Tk.I
NIP. 500 097 810

halaman 11 / 128
12 / 128
PEMERINTAH KABUPATEN BANYUMAS ANALISA HARGA SATUAN PEKERJAAN
DINAS CIPTA KARYA KEBERSIHAN DAN TATA RUANG
Jl.Gerilya Barat No. 05 Telp. (0281) 640359
PURWOKERTO
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
A. PEKERJAAN PERSIAPAN
Pengukuran dan Pemasangan Bouwplank (Kayu
SNI - A.6.4 M' 83,560.00 84,460.00 82,907.50
Meranti)
M.005g Usuk Meranti 5/7 0.0120 M3 3,900,000.00 46,800.00 3,975,000.00 47,700.00 3,900,000.00 46,800.00
M.006 Paku Biasa ( 2" - 5" ) 0.0200 Kg 18,000.00 360.00 18,000.00 360.00 18,000.00 360.00
M.005l Papan Meranti 0.0070 M3 4,275,000.00 29,925.00 4,275,000.00 29,925.00 4,275,000.00 29,925.00
L.008 Pekerja 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.002 Tukang Kayu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
Pengukuran dan Pemasangan Bouwplank (Kayu
SNI - A.6.4a M' 32,485.00 33,435.00 31,832.50
Tahun)
M.005a Usuk 5/7 kayu Tahun 0.0120 M3 1,350,000.00 16,200.00 1,400,000.00 16,800.00 1,350,000.00 16,200.00
M.006 Paku Biasa ( 2" - 5" ) 0.0200 Kg 18,000.00 360.00 18,000.00 360.00 18,000.00 360.00
M.005a Papan kayu Tahun 3/20 0.0070 M3 1,350,000.00 9,450.00 1,400,000.00 9,800.00 1,350,000.00 9,450.00
L.008 Pekerja 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.002 Tukang Kayu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
Pembuatan Gudang Semen dan Alat-alat (Kayu
SNI - A.6.6 M2 1,147,775.00 1,174,323.50 1,137,400.00
Meranti )
M.005s Dolken kayu diam. 8-10 / 4 m 1.7000 Btg 30,000.00 51,000.00 35,000.00 59,500.00 30,000.00 51,000.00
M.005l Papan Meranti 0.2100 M3 4,275,000.00 897,750.00 4,350,000.00 913,500.00 4,275,000.00 897,750.00
M.006 Paku Biasa ( 2" - 5" ) 0.3000 Kg 18,000.00 5,400.00 18,000.00 5,400.00 18,000.00 5,400.00
M.002a Portland Cement 10.5000 Kg 1,200.00 12,600.00 1,207.00 12,673.50 1,200.00 12,600.00
M.001 Pasir Beton 0.0300 M3 92,500.00 2,775.00 100,000.00 3,000.00 92,500.00 2,775.00
M.001g Koral Beton ( Batu Pecah 2/3 ) 0.0500 M3 140,000.00 7,000.00 150,000.00 7,500.00 140,000.00 7,000.00
M.010l Seng Gelombang BJLS 20 1.5000 Lbr 47,000.00 70,500.00 48,000.00 72,000.00 47,000.00 70,500.00
L.008 Pekerja 1.0000 OH 27,000.00 27,000.00 27,000.00 27,000.00 24,500.00 24,500.00
L.002 Tukang Kayu 2.0000 OH 32,500.00 65,000.00 32,500.00 65,000.00 29,000.00 58,000.00
L.007 Kepala Tukang 0.2000 OH 35,000.00 7,000.00 35,000.00 7,000.00 31,500.00 6,300.00
L.010 Mandor 0.0500 OH 35,000.00 1,750.00 35,000.00 1,750.00 31,500.00 1,575.00
Pembuatan Gudang Semen dan Alat-alat (Kayu
SNI - A.6.6a M2 533,525.00 554,823.50 523,150.00
Tahun )
M.005s Dolken kayu diam. 8-10 / 4 m 1.7000 Btg 30,000.00 51,000.00 35,000.00 59,500.00 30,000.00 51,000.00
M.005a Papan kayu Tahun 3/20 0.2100 M3 1,350,000.00 283,500.00 1,400,000.00 294,000.00 1,350,000.00 283,500.00
M.006 Paku Biasa ( 2" - 5" ) 0.3000 Kg 18,000.00 5,400.00 18,000.00 5,400.00 18,000.00 5,400.00
M.002a Portland Cement 10.5000 Kg 1,200.00 12,600.00 1,207.00 12,673.50 1,200.00 12,600.00
M.001 Pasir Beton 0.0300 M3 92,500.00 2,775.00 100,000.00 3,000.00 92,500.00 2,775.00
M.001g Koral Beton ( Batu Pecah 2/3 ) 0.0500 M3 140,000.00 7,000.00 150,000.00 7,500.00 140,000.00 7,000.00
M.010l Seng Gelombang BJLS 20 1.5000 Lbr 47,000.00 70,500.00 48,000.00 72,000.00 47,000.00 70,500.00
L.008 Pekerja 1.0000 OH 27,000.00 27,000.00 27,000.00 27,000.00 24,500.00 24,500.00
L.002 Tukang Kayu 2.0000 OH 32,500.00 65,000.00 32,500.00 65,000.00 29,000.00 58,000.00
L.007 Kepala Tukang 0.2000 OH 35,000.00 7,000.00 35,000.00 7,000.00 31,500.00 6,300.00
L.010 Mandor 0.0500 OH 35,000.00 1,750.00 35,000.00 1,750.00 31,500.00 1,575.00
Pembuatan Rumah Jaga / Konstruksi Kayu (Kayu
SNI - A.6.7 M2 1,435,750.00 1,472,950.00 1,427,300.00
Meranti )
M.005s Dolken kayu diam. 8-10 / 4 m 3.0000 Btg 30,000.00 90,000.00 35,000.00 105,000.00 30,000.00 90,000.00
M.005l Papan Meranti 0.2760 M3 4,275,000.00 1,179,900.00 4,350,000.00 1,200,600.00 4,275,000.00 1,179,900.00
M.006 Paku Biasa ( 2" - 5" ) 0.7000 Kg 18,000.00 12,600.00 18,000.00 12,600.00 18,000.00 12,600.00
M.010l Seng Gelombang BJLS 20 1.5000 Lbr 47,000.00 70,500.00 48,000.00 72,000.00 47,000.00 70,500.00
L.008 Pekerja 1.0000 OH 27,000.00 27,000.00 27,000.00 27,000.00 24,500.00 24,500.00
L.002 Tukang Kayu 1.5000 OH 32,500.00 48,750.00 32,500.00 48,750.00 29,000.00 43,500.00
L.007 Kepala Tukang 0.1500 OH 35,000.00 5,250.00 35,000.00 5,250.00 31,500.00 4,725.00
L.010 Mandor 0.0500 OH 35,000.00 1,750.00 35,000.00 1,750.00 31,500.00 1,575.00
Pembuatan Rumah Jaga / Konstruksi Kayu (Kayu
SNI - A.6.7a M2 SNIA.6.7a 628,450.00 SN2A.6.7a 658,750.00 SNSA.6.7a 620,000.00
Tahun )
M.005s Dolken kayu diam. 8-10 / 4 m 3.0000 Btg 30,000.00 90,000.00 35,000.00 105,000.00 30,000.00 90,000.00
M.005a Papan kayu Tahun 3/20 0.2760 M3 1,350,000.00 372,600.00 1,400,000.00 386,400.00 1,350,000.00 372,600.00
M.006 Paku Biasa ( 2" - 5" ) 0.7000 Kg 18,000.00 12,600.00 18,000.00 12,600.00 18,000.00 12,600.00
M.010l Seng Gelombang BJLS 20 1.5000 Lbr 47,000.00 70,500.00 48,000.00 72,000.00 47,000.00 70,500.00
L.008 Pekerja 1.0000 OH 27,000.00 27,000.00 27,000.00 27,000.00 24,500.00 24,500.00
L.002 Tukang Kayu 1.5000 OH 32,500.00 48,750.00 32,500.00 48,750.00 29,000.00 43,500.00
L.007 Kepala Tukang 0.1500 OH 35,000.00 5,250.00 35,000.00 5,250.00 31,500.00 4,725.00
L.010 Mandor 0.0500 OH 35,000.00 1,750.00 35,000.00 1,750.00 31,500.00 1,575.00

SNI - A.6.8 Membersihkan Lapangan dan Perataan M2 SNIA.6.8 4,450.00 SN2A.6.8 4,450.00 SNSA.6.8 4,025.00
L.008 Pekerja 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.010 Mandor 0.0500 OH 35,000.00 1,750.00 35,000.00 1,750.00 31,500.00 1,575.00
Pembuatan Bak Adukan Uk. ( 40x50x20 ) cm Kayu
SNI - A.6.10 BH SNIA.6.10 77,342.50 SN2A.6.10 79,642.50 SNSA.6.10 76,287.25
Tahun
M.005a Kayu Tahun 0.0360 M3 1,350,000.00 48,600.00 1,400,000.00 50,400.00 1,350,000.00 48,600.00
M.006 Paku Biasa ( 2" - 5" ) 0.0800 Kg 18,000.00 1,440.00 18,000.00 1,440.00 18,000.00 1,440.00
M.005t Usuk 5/7 1.0000 Btg 17,500.00 17,500.00 18,000.00 18,000.00 17,500.00 17,500.00
L.001 Tukang Batu 0.3000 OH 32,500.00 9,750.00 32,500.00 9,750.00 29,000.00 8,700.00
L.010 Mandor 0.0015 OH 35,000.00 52.50 35,000.00 52.50 31,500.00 47.25
SNI - A.6.11 Pembuatan Steger dari Bambu M2 SNIA.6.11 16,702.50 SN2A.6.11 17,327.50 SNSA.6.11 15,965.50
M.006f Bambu diam. 6-8 / 6 m 1.0000 Btg 7,500.00 7,500.00 8,000.00 8,000.00 7,500.00 7,500.00
M.001l Tali Ijuk 0.2500 Kg 5,500.00 1,375.00 6,000.00 1,500.00 5,500.00 1,375.00
L.008 Pekerja 0.2500 OH 27,000.00 6,750.00 27,000.00 6,750.00 24,500.00 6,125.00
L.002 Tukang Kayu 0.0170 OH 32,500.00 552.50 32,500.00 552.50 29,000.00 493.00
L.007 Kepala Tukang 0.0020 OH 35,000.00 70.00 35,000.00 70.00 31,500.00 63.00
L.010 Mandor 0.0130 OH 35,000.00 455.00 35,000.00 455.00 31,500.00 409.50
SNI - A.6.13 Bongkaran Beton Bertulang M3 SNIA.6.13 191,664.00 SN2A.6.13 191,664.00 SNSA.6.13 173,831.00
L.008 Pekerja 6.6670 OH 27,000.00 180,009.00 27,000.00 180,009.00 24,500.00 163,341.50
L.010 Mandor 0.3330 OH 35,000.00 11,655.00 35,000.00 11,655.00 31,500.00 10,489.50
13 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
SNI - A.6.14 Bongkaran dinding Tembok Bata Merah M3 SNIA.6.14 181,164.00 SN2A.6.14 181,164.00 SNSA.6.14 164,381.00
L.008 Pekerja 6.6670 OH 27,000.00 180,009.00 27,000.00 180,009.00 24,500.00 163,341.50
L.010 Mandor 0.0330 OH 35,000.00 1,155.00 35,000.00 1,155.00 31,500.00 1,039.50
B. PEKERJAAN TANAH

SNI - B.6.1 Galian Tanah Biasa Sedalam 1 meter M3 SNIB.6.1 12,200.00 SN2B.6.1 12,200.00 SNSB.6.1 11,060.00
L.008 Pekerja 0.4000 OH 27,000.00 10,800.00 27,000.00 10,800.00 24,500.00 9,800.00
L.010 Mandor 0.0400 OH 35,000.00 1,400.00 35,000.00 1,400.00 31,500.00 1,260.00
SNI - B.6.2 Galian Tanah Biasa Sedalam 2 meter M3 SNIB.6.2 16,022.00 SN2B.6.2 16,022.00 SNSB.6.2 14,525.00
L.008 Pekerja 0.5260 OH 27,000.00 14,202.00 27,000.00 14,202.00 24,500.00 12,887.00
L.010 Mandor 0.0520 OH 35,000.00 1,820.00 35,000.00 1,820.00 31,500.00 1,638.00
SNI - B.6.3 Galian Tanah Biasa Sedalam 3 meter M3 SNIB.6.3 22,400.00 SN2B.6.3 22,400.00 SNSB.6.3 20,307.00
L.008 Pekerja 0.7350 OH 27,000.00 19,845.00 27,000.00 19,845.00 24,500.00 18,007.50
L.010 Mandor 0.0730 OH 35,000.00 2,555.00 35,000.00 2,555.00 31,500.00 2,299.50
SNI - B.6.4 Galian Tanah Keras Sedalam 1 meter M3 SNIB.6.4 19,045.00 SN2B.6.4 19,045.00 SNSB.6.4 17,265.50
L.008 Pekerja 0.6250 OH 27,000.00 16,875.00 27,000.00 16,875.00 24,500.00 15,312.50
L.010 Mandor 0.0620 OH 35,000.00 2,170.00 35,000.00 2,170.00 31,500.00 1,953.00
SNI - B.6.7 Pekerjaan Striping Setinggi 1 meter M3 SNIB.6.7 1,525.00 SN2B.6.7 1,525.00 SNSB.6.7 1,382.50
L.008 Pekerja 0.0500 OH 27,000.00 1,350.00 27,000.00 1,350.00 24,500.00 1,225.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
SNI - B.6.8 Pembuangan Tanah Sejauh 150 meter M3 SNIB.6.8 15,682.00 SN2B.6.8 15,682.00 SNSB.6.8 14,217.00
L.008 Pekerja 0.5160 OH 27,000.00 13,932.00 27,000.00 13,932.00 24,500.00 12,642.00
L.010 Mandor 0.0500 OH 35,000.00 1,750.00 35,000.00 1,750.00 31,500.00 1,575.00
SNI - B.6.9 Urugan Kembali M3 SNIB.6.9 5,849.00 SN2B.6.9 5,849.00 SNSB.6.9 5,302.50
L.008 Pekerja 0.1920 OH 27,000.00 5,184.00 27,000.00 5,184.00 24,500.00 4,704.00
L.010 Mandor 0.0190 OH 35,000.00 665.00 35,000.00 665.00 31,500.00 598.50
SNI - B.6.10 Pemadatan Tanah M3 SNIB.6.10 15,250.00 SN2B.6.10 15,250.00 SNSB.6.10 13,825.00
L.008 Pekerja 0.5000 OH 27,000.00 13,500.00 27,000.00 13,500.00 24,500.00 12,250.00
L.010 Mandor 0.0500 OH 35,000.00 1,750.00 35,000.00 1,750.00 31,500.00 1,575.00
SNI - B.6.11 Urugan Pasir M3 SNIB.6.11 74,450.00 SN2B.6.11 83,450.00 SNSB.6.11 73,665.00
M.001b Pasir urug 1.2000 M3 55,000.00 66,000.00 62,500.00 75,000.00 55,000.00 66,000.00
L.008 Pekerja 0.3000 OH 27,000.00 8,100.00 27,000.00 8,100.00 24,500.00 7,350.00
L.010 Mandor 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
SNI - B.6.14 Pemasangan Lapisan Ijuk M3 SNIB.6.14 328,575.00 SN2B.6.14 352,575.00 SNSB.6.14 328,147.50
M.001o Ijuk 1.2000 M3 270,000.00 324,000.00 290,000.00 348,000.00 270,000.00 324,000.00
L.008 Pekerja 0.1500 OH 27,000.00 4,050.00 27,000.00 4,050.00 24,500.00 3,675.00
L.010 Mandor 0.0150 OH 35,000.00 525.00 35,000.00 525.00 31,500.00 472.50
SNI - B.6.15 Urugan Sirtu M3 SNIB.6.15 82,625.00 SN2B.6.15 88,625.00 SNSB.6.15 81,912.50
M.001e Sirtu 1.2000 M3 62,500.00 75,000.00 67,500.00 81,000.00 62,500.00 75,000.00
L.008 Pekerja 0.2500 OH 27,000.00 6,750.00 27,000.00 6,750.00 24,500.00 6,125.00
L.010 Mandor 0.0250 OH 35,000.00 875.00 35,000.00 875.00 31,500.00 787.50
C. PEKERJAAN PONDASI BATU KALI

SNI - C.6.5 Pas. Pondasi Batu Kali 1 PC : 4 Psr M3 SNIC.6.5 409,025.00 SN2C.6.5 419,566.00 SNSC.6.5 402,702.50
M.001f1 Batu Belah 15/20 cm 1.1000 M3 95,000.00 104,500.00 100,000.00 110,000.00 95,000.00 104,500.00
M.002a Portland Cement 163.00 Kg 1,200.00 195,600.00 1,207.00 196,741.00 1,200.00 195,600.00
M.001a Pasir Pasang 0.5200 M3 85,000.00 44,200.00 92,500.00 48,100.00 85,000.00 44,200.00
L.008 Pekerja 1.5000 OH 27,000.00 40,500.00 27,000.00 40,500.00 24,500.00 36,750.00
L.001 Tukang Batu 0.6000 OH 32,500.00 19,500.00 32,500.00 19,500.00 29,000.00 17,400.00
L.007 Kepala Tukang 0.0600 OH 35,000.00 2,100.00 35,000.00 2,100.00 31,500.00 1,890.00
L.010 Mandor 0.0750 OH 35,000.00 2,625.00 35,000.00 2,625.00 31,500.00 2,362.50
SNI - C.6.6 Pas. Pondasi Batu Kali 1 PC : 5 Psr M3 SNIC.6.6 378,665.00 SN2C.6.6 389,197.00 SNSC.6.6 372,342.50
M.001f1 Batu Belah 15/20 cm 1.1000 M3 95,000.00 104,500.00 100,000.00 110,000.00 95,000.00 104,500.00
M.002a Portland Cement 136.00 Kg 1,200.00 163,200.00 1,207.00 164,152.00 1,200.00 163,200.00
M.001a Pasir Pasang 0.5440 M3 85,000.00 46,240.00 92,500.00 50,320.00 85,000.00 46,240.00
L.008 Pekerja 1.5000 OH 27,000.00 40,500.00 27,000.00 40,500.00 24,500.00 36,750.00
L.001 Tukang Batu 0.6000 OH 32,500.00 19,500.00 32,500.00 19,500.00 29,000.00 17,400.00
L.007 Kepala Tukang 0.0600 OH 35,000.00 2,100.00 35,000.00 2,100.00 31,500.00 1,890.00
L.010 Mandor 0.0750 OH 35,000.00 2,625.00 35,000.00 2,625.00 31,500.00 2,362.50
SNI - C.6.12 Pas. Pondasi Batu Kali 1 PC : 3 Kp : 10 Psr M3 SNIC.6.12 304,090.00 SN2C.6.12 314,442.00 SNSC.6.12 297,767.50
M.001f1 Batu Belah 15/20 cm 1.1000 M3 95,000.00 104,500.00 100,000.00 110,000.00 95,000.00 104,500.00
M.002a Portland Cement 61.000 Kg 1,200.00 73,200.00 1,207.00 73,627.00 1,200.00 73,200.00
M.001d Kapur Pasang 0.1470 M3 135,000.00 19,845.00 140,000.00 20,580.00 135,000.00 19,845.00
M.001a Pasir Pasang 0.4920 M3 85,000.00 41,820.00 92,500.00 45,510.00 85,000.00 41,820.00
L.008 Pekerja 1.5000 OH 27,000.00 40,500.00 27,000.00 40,500.00 24,500.00 36,750.00
L.001 Tukang Batu 0.6000 OH 32,500.00 19,500.00 32,500.00 19,500.00 29,000.00 17,400.00
L.007 Kepala Tukang 0.0600 OH 35,000.00 2,100.00 35,000.00 2,100.00 31,500.00 1,890.00
L.010 Mandor 0.0750 OH 35,000.00 2,625.00 35,000.00 2,625.00 31,500.00 2,362.50
SNI - C.6.14 Pas. Pondasi Batu Kosong M3 SNIC.6.14 166,965.00 SN2C.6.14 175,215.00 SNSC.6.14 163,377.00
M.001f1 Batu Belah 15/20 cm 1.2000 M3 95,000.00 114,000.00 100,000.00 120,000.00 95,000.00 114,000.00
M.001b Pasir Urug 0.3000 M3 55,000.00 16,500.00 62,500.00 18,750.00 55,000.00 16,500.00
L.008 Pekerja 0.7800 OH 27,000.00 21,060.00 27,000.00 21,060.00 24,500.00 19,110.00
L.001 Tukang Batu 0.3900 OH 32,500.00 12,675.00 32,500.00 12,675.00 29,000.00 11,310.00
L.007 Kepala Tukang 0.0390 OH 35,000.00 1,365.00 35,000.00 1,365.00 31,500.00 1,228.50
L.010 Mandor 0.0390 OH 35,000.00 1,365.00 35,000.00 1,365.00 31,500.00 1,228.50
14 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
D. PEKERJAAN DINDING

SNI - D.6.3 Pas. Batu Merah tb. 1 bata 1 PC : 3 Psr M2 SNID.6.3 123,475.00 SN2D.6.3 127,188.15 SNSD.6.3 120,975.00
M.001j Batu Merah (5x11x22cm) 140.00 Bh 360.00 50,400.00 380.00 53,200.00 360.00 50,400.00
M.002a Portland Cement 32.9500 Kg 1,200.00 39,540.00 1,207.00 39,770.65 1,200.00 39,540.00
M.001a Pasir Pasang 0.0910 M3 85,000.00 7,735.00 92,500.00 8,417.50 85,000.00 7,735.00
L.008 Pekerja 0.6500 OH 27,000.00 17,550.00 27,000.00 17,550.00 24,500.00 15,925.00
L.001 Tukang Batu 0.2000 OH 32,500.00 6,500.00 32,500.00 6,500.00 29,000.00 5,800.00
L.007 Kepala Tukang 0.0200 OH 35,000.00 700.00 35,000.00 700.00 31,500.00 630.00
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
SNI - D.6.5 Pas. Batu Merah tb. 1 bata 1 PC : 5 Psr M2 SNID.6.5 111,510.00 SN2D.6.5 115,230.40 SNSD.6.5 109,010.00
M.001j Batu Merah (5x11x22cm) 140.00 Bh 360.00 50,400.00 380.00 53,200.00 360.00 50,400.00
M.002a Portland Cement 22.2000 Kg 1,200.00 26,640.00 1,207.00 26,795.40 1,200.00 26,640.00
M.001a Pasir Pasang 0.1020 M3 85,000.00 8,670.00 92,500.00 9,435.00 85,000.00 8,670.00
L.008 Pekerja 0.6500 OH 27,000.00 17,550.00 27,000.00 17,550.00 24,500.00 15,925.00
L.001 Tukang Batu 0.2000 OH 32,500.00 6,500.00 32,500.00 6,500.00 29,000.00 5,800.00
L.007 Kepala Tukang 0.0200 OH 35,000.00 700.00 35,000.00 700.00 31,500.00 630.00
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
SNI - D.6.7 Pas. Batu Merah tb. 1 bata 1 PC : 3 Kp : 10 Psr M2 SNID.6.7 99,871.00 SN2D.6.7 103,572.81 SNSD.6.7 97,371.00
M.001j Batu Merah (5x11x22cm) 140.0 Bh 360.00 50,400.00 380.00 53,200.00 360.00 50,400.00
M.002a Portland Cement 10.0800 Kg 1,200.00 12,096.00 1,207.00 12,166.56 1,200.00 12,096.00
M.001a Pasir Pasang 0.0925 M3 85,000.00 7,862.50 92,500.00 8,556.25 85,000.00 7,862.50
M.001d Kapur pasang 0.0275 M3 135,000.00 3,712.50 140,000.00 3,850.00 135,000.00 3,712.50
L.008 Pekerja 0.6500 OH 27,000.00 17,550.00 27,000.00 17,550.00 24,500.00 15,925.00
L.001 Tukang Batu 0.2000 OH 32,500.00 6,500.00 32,500.00 6,500.00 29,000.00 5,800.00
L.007 Kepala Tukang 0.0200 OH 35,000.00 700.00 35,000.00 700.00 31,500.00 630.00
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
SNI - D.6.10 Pas. Batu Merah tb. 1/2 bata 1 PC : 3 Psr M2 SNID.6.10 58,609.00 SN2D.6.10 60,409.59 SNSD.6.10 57,371.50
M.001j Batu Merah (5x11x22cm) 70.0000 Bh 360.00 25,200.00 380.00 26,600.00 360.00 25,200.00
M.002a Portland Cement 14.3700 Kg 1,200.00 17,244.00 1,207.00 17,344.59 1,200.00 17,244.00
M.001a Pasir Pasang 0.0400 M3 85,000.00 3,400.00 92,500.00 3,700.00 85,000.00 3,400.00
L.008 Pekerja 0.3200 OH 27,000.00 8,640.00 27,000.00 8,640.00 24,500.00 7,840.00
L.001 Tukang Batu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0150 OH 35,000.00 525.00 35,000.00 525.00 31,500.00 472.50
SNI - D.6.12 Pas. Batu Merah tb. 1/2 bata 1 PC : 5 Psr M2 SNID.6.12 53,406.00 SN2D.6.12 55,211.26 SNSD.6.12 52,168.50
M.001j Batu Merah (5x11x22cm) 70.0000 Bh 360.00 25,200.00 380.00 26,600.00 360.00 25,200.00
M.002a Portland Cement 9.6800 Kg 1,200.00 11,616.00 1,207.00 11,683.76 1,200.00 11,616.00
M.001a Pasir Pasang 0.0450 M3 85,000.00 3,825.00 92,500.00 4,162.50 85,000.00 3,825.00
L.008 Pekerja 0.3200 OH 27,000.00 8,640.00 27,000.00 8,640.00 24,500.00 7,840.00
L.001 Tukang Batu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0150 OH 35,000.00 525.00 35,000.00 525.00 31,500.00 472.50
SNI - D.6.15 Pas. Batu Merah tb. 1/2 bata 1 PC : 3 Kp ; 10 Psr M2 SNID.6.15 49,640.00 SN2D.6.15 51,521.50 SNSD.6.15 48,402.50
M.001j Batu Merah (5x11x22cm) 70.0000 Bh 360.00 25,200.00 380.00 26,600.00 360.00 25,200.00
M.002a Portland Cement 4.5000 Kg 1,200.00 5,400.00 1,207.00 5,431.50 1,200.00 5,400.00
M.001a Pasir Pasang 0.0500 M3 85,000.00 4,250.00 92,500.00 4,625.00 85,000.00 4,250.00
M.001d Kapur pasang 0.0150 M3 135,000.00 2,025.00 140,000.00 2,100.00 135,000.00 2,025.00
L.008 Pekerja 0.3200 OH 27,000.00 8,640.00 27,000.00 8,640.00 24,500.00 7,840.00
L.001 Tukang Batu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0150 OH 35,000.00 525.00 35,000.00 525.00 31,500.00 472.50
E. PEKERJAAN PLESTERAN

SNI - E.6.3 Plesteran 1 PC : 3 Psr tb. 1,5 cm M2 SNIE.6.3 20,541.00 SN2E.6.3 20,728.86 SNSE.6.3 19,428.50
M.002a Portland Cement 6.4800 Kg 1,200.00 7,776.00 1,207.00 7,821.36 1,200.00 7,776.00
M.001a Pasir Pasang 0.0190 M3 85,000.00 1,615.00 92,500.00 1,757.50 85,000.00 1,615.00
L.008 Pekerja 0.2000 OH 27,000.00 5,400.00 27,000.00 5,400.00 24,500.00 4,900.00
L.001 Tukang Batu 0.1500 OH 32,500.00 4,875.00 32,500.00 4,875.00 29,000.00 4,350.00
L.007 Kepala Tukang 0.0150 OH 35,000.00 525.00 35,000.00 525.00 31,500.00 472.50
L.010 Mandor 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
SNI - E.6.5 Plesteran 1 PC : 5 Psr tb. 1,5 cm M2 SNIE.6.5 18,204.00 SN2E.6.5 18,399.24 SNSE.6.5 17,091.50
M.002a Portland Cement 4.3200 Kg 1,200.00 5,184.00 1,207.00 5,214.24 1,200.00 5,184.00
M.001a Pasir Pasang 0.0220 M3 85,000.00 1,870.00 92,500.00 2,035.00 85,000.00 1,870.00
L.008 Pekerja 0.2000 OH 27,000.00 5,400.00 27,000.00 5,400.00 24,500.00 4,900.00
L.001 Tukang Batu 0.1500 OH 32,500.00 4,875.00 32,500.00 4,875.00 29,000.00 4,350.00
L.007 Kepala Tukang 0.0150 OH 35,000.00 525.00 35,000.00 525.00 31,500.00 472.50
L.010 Mandor 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
SNI - E.6.9 Plesteran 1 PC : 3 Kp : 10 Psr tb. 1,5 cm M2 SNIE.6.9 15,358.00 SN2E.6.9 15,505.88 SNSE.6.9 14,245.50
M.002a Portland Cement 1.8400 Kg 1,200.00 2,208.00 1,207.00 2,220.88 1,200.00 2,208.00
M.001d Kapur Padam 0.0060 M3 135,000.00 810.00 140,000.00 840.00 135,000.00 810.00
M.001a Pasir Pasang 0.0140 M3 85,000.00 1,190.00 92,500.00 1,295.00 85,000.00 1,190.00
L.008 Pekerja 0.2000 OH 27,000.00 5,400.00 27,000.00 5,400.00 24,500.00 4,900.00
L.001 Tukang Batu 0.1500 OH 32,500.00 4,875.00 32,500.00 4,875.00 29,000.00 4,350.00
L.007 Kepala Tukang 0.0150 OH 35,000.00 525.00 35,000.00 525.00 31,500.00 472.50
L.010 Mandor 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
SNI - E.6.14 Plesteran 1 PC : 3 Psr tb. 2 cm M2 SNIE.6.14 29,557.50 SN2E.6.14 29,828.10 SNSE.6.14 28,118.75
M.002a Portland Cement 10.8000 Kg 1,200.00 12,960.00 1,207.00 13,035.60 1,200.00 12,960.00
M.001a Pasir Pasang 0.0260 M3 85,000.00 2,210.00 92,500.00 2,405.00 85,000.00 2,210.00
L.008 Pekerja 0.2500 OH 27,000.00 6,750.00 27,000.00 6,750.00 24,500.00 6,125.00
L.001 Tukang Batu 0.2000 OH 32,500.00 6,500.00 32,500.00 6,500.00 29,000.00 5,800.00
L.007 Kepala Tukang 0.0200 OH 35,000.00 700.00 35,000.00 700.00 31,500.00 630.00
L.010 Mandor 0.0125 OH 35,000.00 437.50 35,000.00 437.50 31,500.00 393.75
15 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
SNI - E.6.16 Plesteran 1 PC : 5 Psr tb. 2 cm M2 SNIE.6.16 25,515.50 SN2E.6.16 25,776.53 SNSE.6.16 24,076.75
M.002a Portland Cement 7.2900 Kg 1,200.00 8,748.00 1,207.00 8,799.03 1,200.00 8,748.00
M.001a Pasir Pasang 0.0280 M3 85,000.00 2,380.00 92,500.00 2,590.00 85,000.00 2,380.00
L.008 Pekerja 0.2500 OH 27,000.00 6,750.00 27,000.00 6,750.00 24,500.00 6,125.00
L.001 Tukang Batu 0.2000 OH 32,500.00 6,500.00 32,500.00 6,500.00 29,000.00 5,800.00
L.007 Kepala Tukang 0.0200 OH 35,000.00 700.00 35,000.00 700.00 31,500.00 630.00
L.010 Mandor 0.0125 OH 35,000.00 437.50 35,000.00 437.50 31,500.00 393.75
SNI - E.6.28 Berapen 1 PC : 5 Psr tb. 1,5 cm M2 SNIE.6.28 15,609.00 SN2E.6.28 15,821.19 SNSE.6.28 14,936.50
M.002a Portland Cement 5.6700 Kg 1,200.00 6,804.00 1,207.00 6,843.69 1,200.00 6,804.00
M.001a Pasir Pasang 0.0230 M3 85,000.00 1,955.00 92,500.00 2,127.50 85,000.00 1,955.00
L.008 Pekerja 0.1500 OH 27,000.00 4,050.00 27,000.00 4,050.00 24,500.00 3,675.00
L.001 Tukang Batu 0.0700 OH 32,500.00 2,275.00 32,500.00 2,275.00 29,000.00 2,030.00
L.007 Kepala Tukang 0.0070 OH 35,000.00 245.00 35,000.00 245.00 31,500.00 220.50
L.010 Mandor 0.0080 OH 35,000.00 280.00 35,000.00 280.00 31,500.00 252.00
SNI - E.6.30 Plesteran Beton 1 PC : 5 Psr tb. 1,5 cm M2 SNIE.6.30 24,944.00 SN2E.6.30 25,150.99 SNSE.6.30 23,478.50
M.002a Portland Cement 7.0700 Kg 1,200.00 8,484.00 1,207.00 8,533.49 1,200.00 8,484.00
M.001a Pasir Pasang 0.0210 M3 85,000.00 1,785.00 92,500.00 1,942.50 85,000.00 1,785.00
L.008 Pekerja 0.2600 OH 27,000.00 7,020.00 27,000.00 7,020.00 24,500.00 6,370.00
L.001 Tukang Batu 0.2000 OH 32,500.00 6,500.00 32,500.00 6,500.00 29,000.00 5,800.00
L.007 Kepala Tukang 0.0200 OH 35,000.00 700.00 35,000.00 700.00 31,500.00 630.00
L.010 Mandor 0.0130 OH 35,000.00 455.00 35,000.00 455.00 31,500.00 409.50
SNI - E.6.31 Plesteran Skoning 1 PC : 2 Psr M2 SNIE.6.31 4,944.00 SN2E.6.31 4,962.50 SNSE.6.31 4,528.50
M.002a Portland Cement 0.5000 Kg 1,200.00 600.00 1,207.00 603.50 1,200.00 600.00
M.001a Pasir Pasang 0.0020 M3 85,000.00 170.00 92,500.00 185.00 85,000.00 170.00
L.008 Pekerja 0.0570 OH 27,000.00 1,539.00 27,000.00 1,539.00 24,500.00 1,396.50
L.001 Tukang Batu 0.0380 OH 32,500.00 1,235.00 32,500.00 1,235.00 29,000.00 1,102.00
L.007 Kepala Tukang 0.0380 OH 35,000.00 1,330.00 35,000.00 1,330.00 31,500.00 1,197.00
L.010 Mandor 0.0020 OH 35,000.00 70.00 35,000.00 70.00 31,500.00 63.00
SNI - E.6.35 Plesteran Siar Adukan 1 PC : 2 Psr M2 SNIE.6.35 13,394.00 SN2E.6.35 13,544.24 SNSE.6.35 12,721.50
M.002a Portland Cement 4.3200 Kg 1,200.00 5,184.00 1,207.00 5,214.24 1,200.00 5,184.00
M.001a Pasir Pasang 0.0160 M3 85,000.00 1,360.00 92,500.00 1,480.00 85,000.00 1,360.00
L.008 Pekerja 0.1500 OH 27,000.00 4,050.00 27,000.00 4,050.00 24,500.00 3,675.00
L.001 Tukang Batu 0.0700 OH 32,500.00 2,275.00 32,500.00 2,275.00 29,000.00 2,030.00
L.007 Kepala Tukang 0.0070 OH 35,000.00 245.00 35,000.00 245.00 31,500.00 220.50
L.010 Mandor 0.0080 OH 35,000.00 280.00 35,000.00 280.00 31,500.00 252.00
F. PEKERJAAN KAYU

SNI - F.6.1 Pas. Kusen Pintu dan Jendela Kayu Jati M3 SNIF.6.1 16,842,500.00 SN2F.6.1 16,925,000.00 SNSF.6.1 16,749,450.00
M.005f Kayu Jati Balok (lokal) 1.1000 M3 14,500,000 15,950,000.00 14,575,000 16,032,500.00 14,500,000 15,950,000.00
L.008 Pekerja 6.0000 OH 27,000 162,000.00 27,000 162,000.00 24,500 147,000.00
L.002 Tukang Kayu 20.0000 OH 32,500 650,000.00 32,500 650,000.00 29,000 580,000.00
L.007 Kepala Tukang 2.0000 OH 35,000 70,000.00 35,000 70,000.00 31,500 63,000.00
L.010 Mandor 0.3000 OH 35,000 10,500.00 35,000 10,500.00 31,500 9,450.00
SNI - F.6.2 Pas. Kusen Pintu dan Jendela Kayu Kamper M3 SNIF.6.2 9,946,300.00 SN2F.6.2 10,036,300.00 SNSF.6.2 9,860,250.00
M.005e Kayu Kamper Balok 1.2000 M3 7,599,000.00 9,118,800.00 7,674,000.00 9,208,800.00 7,599,000.00 9,118,800.00
L.008 Pekerja 6.0000 OH 27,000.00 162,000.00 27,000.00 162,000.00 24,500.00 147,000.00
L.002 Tukang Kayu 18.0000 OH 32,500.00 585,000.00 32,500.00 585,000.00 29,000.00 522,000.00
L.007 Kepala Tukang 2.0000 OH 35,000.00 70,000.00 35,000.00 70,000.00 31,500.00 63,000.00
L.010 Mandor 0.3000 OH 35,000.00 10,500.00 35,000.00 10,500.00 31,500.00 9,450.00
SNI - F.6.2a Pas. Kusen Pintu dan Jendela Kayu Bangkir M3 SNIF.6.2a 10,121,500.00 SN2F.6.2a 10,211,500.00 SNSF.6.2a 10,035,450.00
M.005d Kayu Bangkir Balok 1.2000 M3 7,745,000.00 9,294,000.00 7,820,000.00 9,384,000.00 7,745,000.00 9,294,000.00
L.008 Pekerja 6.0000 OH 27,000.00 162,000.00 27,000.00 162,000.00 24,500.00 147,000.00
L.002 Tukang Kayu 18.0000 OH 32,500.00 585,000.00 32,500.00 585,000.00 29,000.00 522,000.00
L.007 Kepala Tukang 2.0000 OH 35,000.00 70,000.00 35,000.00 70,000.00 31,500.00 63,000.00
L.010 Mandor 0.3000 OH 35,000.00 10,500.00 35,000.00 10,500.00 31,500.00 9,450.00
SNI - F.6.2b Pas. Kusen Pintu dan Jendela Kayu Kruing M3 SNIF.6.2b 7,451,500.00 SN2F.6.2b 7,541,500.00 SNSF.6.2b 7,365,450.00
M.005c Kayu Kruing Balok 1.2000 M3 5,520,000.00 6,624,000.00 5,595,000.00 6,714,000.00 5,520,000.00 6,624,000.00
L.008 Pekerja 6.0000 OH 27,000.00 162,000.00 27,000.00 162,000.00 24,500.00 147,000.00
L.002 Tukang Kayu 18.0000 OH 32,500.00 585,000.00 32,500.00 585,000.00 29,000.00 522,000.00
L.007 Kepala Tukang 2.0000 OH 35,000.00 70,000.00 35,000.00 70,000.00 31,500.00 63,000.00
L.010 Mandor 0.3000 OH 35,000.00 10,500.00 35,000.00 10,500.00 31,500.00 9,450.00

SNI - F.6.2c Pas. Kusen Pintu dan Jendela Kayu Jati (lokal) M3 SNIF.6.2c 16,777,500.00 SN2F.6.2c 16,860,000.00 SNSF.6.2c 16,691,450.00
M.005f Kayu Jati balok lokal 1.1000 M3 14,500,000.00 15,950,000.00 14,575,000.00 16,032,500.00 14,500,000.00 15,950,000.00
L.008 Pekerja 6.0000 OH 27,000.00 162,000.00 27,000.00 162,000.00 24,500.00 147,000.00
L.002 Tukang Kayu 18.0000 OH 32,500.00 585,000.00 32,500.00 585,000.00 29,000.00 522,000.00
L.007 Kepala Tukang 2.0000 OH 35,000.00 70,000.00 35,000.00 70,000.00 31,500.00 63,000.00
L.010 Mandor 0.3000 OH 35,000.00 10,500.00 35,000.00 10,500.00 31,500.00 9,450.00
Pas. Soko / Tiang kayu Jati (uk. Khusus 30/30-
SNI - F.6.2d 12/12 P : 5-8 m' ) Diketam halus dan di Propil (Kw. M3 SNIF.6.2d 58,427,860.00 SN2F.6.2d 58,517,860.00 SNSF.6.2d 58,341,810.00
Eksport)
M.005f1 Kayu Jati Balok Uk. Khusus (Kw. Eksport 1.2000 M3 48,000,000.00 57,600,000.00 48,075,000.00 57,690,000.00 48,000,000.00 57,600,000.00
M.006 Paku biasa ( 5" ) 0.0200 Kg 18,000.00 360.00 18,000.00 360.00 18,000.00 360.00
L.008 Pekerja 6.0000 OH 27,000.00 162,000.00 27,000.00 162,000.00 24,500.00 147,000.00
L.002 Tukang Kayu 18.0000 OH 32,500.00 585,000.00 32,500.00 585,000.00 29,000.00 522,000.00
L.007 Kepala Tukang 2.0000 OH 35,000.00 70,000.00 35,000.00 70,000.00 31,500.00 63,000.00
L.010 Mandor 0.3000 OH 35,000.00 10,500.00 35,000.00 10,500.00 31,500.00 9,450.00
Pas. Soko / Tiang kayu Jati uk. Khusus Diketam
SNI - F.6.2e M3 SNIF.6.2e 30,827,860.00 SN2F.6.2e 30,917,860.00 SNSF.6.2e 30,741,810.00
halus dan di Propil (Kw. Eksport)
M.005f3 Kayu Jati Balok Uk.Bukan Khusus 1.2000 M3 25,000,000.00 30,000,000.00 25,075,000.00 30,090,000.00 25,000,000.00 30,000,000.00
M.006 Paku biasa ( 5" ) 0.0200 Kg 18,000.00 360.00 18,000.00 360.00 18,000.00 360.00
L.008 Pekerja 6.0000 OH 27,000.00 162,000.00 27,000.00 162,000.00 24,500.00 147,000.00
L.002 Tukang Kayu 18.0000 OH 32,500.00 585,000.00 32,500.00 585,000.00 29,000.00 522,000.00
L.007 Kepala Tukang 2.0000 OH 35,000.00 70,000.00 35,000.00 70,000.00 31,500.00 63,000.00
L.010 Mandor 0.3000 OH 35,000.00 10,500.00 35,000.00 10,500.00 31,500.00 9,450.00
16 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
Pas. Soko / Tiang kayu Bangkir uk. Khusus
SNI - F.6.2f M3 SNIF.6.2f 12,491,860.00 SN2F.6.2f 12,581,860.00 SNSF.6.2f 12,405,810.00
Diketam halus dan di Propil
M.005d1 Kayu Bangkir Balok Uk. Khusus 1.2000 M3 9,720,000.00 11,664,000.00 9,795,000.00 11,754,000.00 9,720,000.00 11,664,000.00
M.006 Paku biasa ( 5" ) 0.0200 Kg 18,000.00 360.00 18,000.00 360.00 18,000.00 360.00
L.008 Pekerja 6.0000 OH 27,000.00 162,000.00 27,000.00 162,000.00 24,500.00 147,000.00
L.002 Tukang Kayu 18.0000 OH 32,500.00 585,000.00 32,500.00 585,000.00 29,000.00 522,000.00
L.007 Kepala Tukang 2.0000 OH 35,000.00 70,000.00 35,000.00 70,000.00 31,500.00 63,000.00
L.010 Mandor 0.3000 OH 35,000.00 10,500.00 35,000.00 10,500.00 31,500.00 9,450.00
SNI - F.6.7 Pas. Pintu Panil Kayu Jati M2 SNIF.6.7 630,750.00 SN2F.6.7 633,750.00 SNSF.6.7 618,450.00
M.005p Papan Jati (lokal) 0.0400 M3 12,800,000 512,000.00 12,875,000 515,000.00 12,800,000 512,000.00
L.008 Pekerja 1.0000 OH 27,000 27,000.00 27,000 27,000.00 24,500 24,500.00
L.002 Tukang Kayu 2.5000 OH 32,500 81,250.00 32,500 81,250.00 29,000 72,500.00
L.007 Kepala Tukang 0.2500 OH 35,000 8,750.00 35,000 8,750.00 31,500 7,875.00
L.010 Mandor 0.0500 OH 35,000 1,750.00 35,000 1,750.00 31,500 1,575.00
SNI - F.6.8 Pas. Pintu Panil Kayu Kamper M2 SNIF.6.8 458,750.00 SN2F.6.8 461,750.00 SNSF.6.8 446,450.00
M.005o Papan Kamper 0.0400 M3 8,500,000.00 340,000.00 8,575,000.00 343,000.00 8,500,000.00 340,000.00
L.008 Pekerja 1.0000 OH 27,000.00 27,000.00 27,000.00 27,000.00 24,500.00 24,500.00
L.002 Tukang Kayu 2.5000 OH 32,500.00 81,250.00 32,500.00 81,250.00 29,000.00 72,500.00
L.007 Kepala Tukang 0.2500 OH 35,000.00 8,750.00 35,000.00 8,750.00 31,500.00 7,875.00
L.010 Mandor 0.0500 OH 35,000.00 1,750.00 35,000.00 1,750.00 31,500.00 1,575.00
SNI - F.6.8a Pas. Pintu Panil Kayu Bangkir M2 SNIF.6.8a 478,750.00 SN2F.6.8a 481,750.00 SNSF.6.8a 466,450.00
M.005n Papan Bangkir 0.0400 M3 9,000,000.00 360,000.00 9,075,000.00 363,000.00 9,000,000.00 360,000.00
L.008 Pekerja 1.0000 OH 27,000.00 27,000.00 27,000.00 27,000.00 24,500.00 24,500.00
L.002 Tukang Kayu 2.5000 OH 32,500.00 81,250.00 32,500.00 81,250.00 29,000.00 72,500.00
L.007 Kepala Tukang 0.2500 OH 35,000.00 8,750.00 35,000.00 8,750.00 31,500.00 7,875.00
L.010 Mandor 0.0500 OH 35,000.00 1,750.00 35,000.00 1,750.00 31,500.00 1,575.00
SNI - F.6.8b Pas. Pintu Panil Kayu Kruing M2 SNIF.6.8b 362,750.00 SN2F.6.8b 365,750.00 SNSF.6.8b 350,450.00
M.005m Papan Kruing 0.0400 M3 6,100,000.00 244,000.00 6,175,000.00 247,000.00 6,100,000.00 244,000.00
L.008 Pekerja 1.0000 OH 27,000.00 27,000.00 27,000.00 27,000.00 24,500.00 24,500.00
L.002 Tukang Kayu 2.5000 OH 32,500.00 81,250.00 32,500.00 81,250.00 29,000.00 72,500.00
L.007 Kepala Tukang 0.2500 OH 35,000.00 8,750.00 35,000.00 8,750.00 31,500.00 7,875.00
L.010 Mandor 0.0500 OH 35,000.00 1,750.00 35,000.00 1,750.00 31,500.00 1,575.00
SNI - F.6.9 Pas. Pintu dan Jendela Kaca Kayu Jati M2 SNIF.6.9 543,000.00 SN2F.6.9 545,625.00 SNSF.6.9 533,160.00
M.005p Papan Jati (lokal) 0.0350 M3 12,800,000 448,000.00 12,875,000 450,625.00 12,800,000 448,000.00
L.008 Pekerja 0.8000 OH 27,000 21,600.00 27,000 21,600.00 24,500 19,600.00
L.002 Tukang Kayu 2.0000 OH 32,500 65,000.00 32,500 65,000.00 29,000 58,000.00
L.007 Kepala Tukang 0.2000 OH 35,000 7,000.00 35,000 7,000.00 31,500 6,300.00
L.010 Mandor 0.0400 OH 35,000 1,400.00 35,000 1,400.00 31,500 1,260.00
SNI - F.6.10 Pas. Pintu dan Jendela Kaca Kayu Kamper M2 SNIF.6.10 392,500.00 SN2F.6.10 395,125.00 SNSF.6.10 382,660.00
M.005o Papan Kamper 0.0350 M3 8,500,000.00 297,500.00 8,575,000.00 300,125.00 8,500,000.00 297,500.00
L.008 Pekerja 0.8000 OH 27,000.00 21,600.00 27,000.00 21,600.00 24,500.00 19,600.00
L.002 Tukang Kayu 2.0000 OH 32,500.00 65,000.00 32,500.00 65,000.00 29,000.00 58,000.00
L.007 Kepala Tukang 0.2000 OH 35,000.00 7,000.00 35,000.00 7,000.00 31,500.00 6,300.00
L.010 Mandor 0.0400 OH 35,000.00 1,400.00 35,000.00 1,400.00 31,500.00 1,260.00
SNI - F.6.10a Pas. Pintu dan Jendela Kaca Kayu Bangkir M2 SNIF.6.10a 410,000.00 SN2F.6.10a 412,625.00 SNSF.6.10a 400,160.00
M.005n Papan Bangkir 0.0350 M3 9,000,000.00 315,000.00 9,075,000.00 317,625.00 9,000,000.00 315,000.00
L.008 Pekerja 0.8000 OH 27,000.00 21,600.00 27,000.00 21,600.00 24,500.00 19,600.00
L.002 Tukang Kayu 2.0000 OH 32,500.00 65,000.00 32,500.00 65,000.00 29,000.00 58,000.00
L.007 Kepala Tukang 0.2000 OH 35,000.00 7,000.00 35,000.00 7,000.00 31,500.00 6,300.00
L.010 Mandor 0.0400 OH 35,000.00 1,400.00 35,000.00 1,400.00 31,500.00 1,260.00
SNI - F.6.10b Pas. Pintu dan Jendela Kaca Kayu Kruing M2 SNIF.6.10b 308,500.00 SN2F.6.10b 311,125.00 SNSF.6.10b 298,660.00
M.005m Papan Kruing 0.0350 M3 6,100,000.00 213,500.00 6,175,000.00 216,125.00 6,100,000.00 213,500.00
L.008 Pekerja 0.8000 OH 27,000.00 21,600.00 27,000.00 21,600.00 24,500.00 19,600.00
L.002 Tukang Kayu 2.0000 OH 32,500.00 65,000.00 32,500.00 65,000.00 29,000.00 58,000.00
L.007 Kepala Tukang 0.2000 OH 35,000.00 7,000.00 35,000.00 7,000.00 31,500.00 6,300.00
L.010 Mandor 0.0400 OH 35,000.00 1,400.00 35,000.00 1,400.00 31,500.00 1,260.00
SNI - F.6.12 Pas. Pintu dan Jendela Jalusi Kayu Jati M2 SNIF.6.12 964,700.00 SN2F.6.12 969,500.00 SNSF.6.12 949,600.00
M.005p Papan Jati (lokal) 0.0640 M3 12,800,000.00 819,200.00 12,875,000.00 824,000.00 12,800,000.00 819,200.00
L.008 Pekerja 1.0000 OH 27,000.00 27,000.00 27,000.00 27,000.00 24,500.00 24,500.00
L.002 Tukang Kayu 3.0000 OH 32,500.00 97,500.00 32,500.00 97,500.00 29,000.00 87,000.00
L.007 Kepala Tukang 0.3000 OH 35,000.00 10,500.00 35,000.00 10,500.00 31,500.00 9,450.00
L.010 Mandor 0.3000 OH 35,000.00 10,500.00 35,000.00 10,500.00 31,500.00 9,450.00
SNI - F.6.13 Pas. Pintu dan Jendela Jalusi Kayu Kamper M2 SNIF.6.13 696,500.00 SN2F.6.13 701,300.00 SNSF.6.13 680,700.00
M.005o Papan Kamper 0.0640 M3 8,500,000.00 544,000.00 8,575,000.00 548,800.00 8,500,000.00 544,000.00
L.008 Pekerja 1.0000 OH 27,000.00 27,000.00 27,000.00 27,000.00 24,500.00 24,500.00
L.002 Tukang Kayu 3.0000 OH 32,500.00 97,500.00 32,500.00 97,500.00 29,000.00 87,000.00
L.007 Kepala Tukang 0.3000 OH 35,000.00 10,500.00 35,000.00 10,500.00 31,500.00 9,450.00
L.010 Mandor 0.5000 OH 35,000.00 17,500.00 35,000.00 17,500.00 31,500.00 15,750.00
SNI - F.6.13a Pas. Pintu dan Jendela Jalusi Kayu Bangkir M2 SNIF.6.13a 728,500.00 SN2F.6.13a 733,300.00 SNSF.6.13a 712,700.00
M.005n Papan Bangkir 0.0640 M3 9,000,000.00 576,000.00 9,075,000.00 580,800.00 9,000,000.00 576,000.00
L.008 Pekerja 1.0000 OH 27,000.00 27,000.00 27,000.00 27,000.00 24,500.00 24,500.00
L.002 Tukang Kayu 3.0000 OH 32,500.00 97,500.00 32,500.00 97,500.00 29,000.00 87,000.00
L.007 Kepala Tukang 0.3000 OH 35,000.00 10,500.00 35,000.00 10,500.00 31,500.00 9,450.00
L.010 Mandor 0.5000 OH 35,000.00 17,500.00 35,000.00 17,500.00 31,500.00 15,750.00
SNI - F.6.13b Pas. Pintu dan Jendela Jalusi Kayu Kruing M2 SNIF.6.13b 542,900.00 SN2F.6.13b 547,700.00 SNSF.6.13b 527,100.00
M.005m Papan Kruing 0.0640 M3 6,100,000.00 390,400.00 6,175,000.00 395,200.00 6,100,000.00 390,400.00
L.008 Pekerja 1.0000 OH 27,000.00 27,000.00 27,000.00 27,000.00 24,500.00 24,500.00
L.002 Tukang Kayu 3.0000 OH 32,500.00 97,500.00 32,500.00 97,500.00 29,000.00 87,000.00
L.007 Kepala Tukang 0.3000 OH 35,000.00 10,500.00 35,000.00 10,500.00 31,500.00 9,450.00
L.010 Mandor 0.5000 OH 35,000.00 17,500.00 35,000.00 17,500.00 31,500.00 15,750.00
17 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
SNI - F.6.16 Pas. Jalusi Mati Kusen Kayu Jati M2 SNIF.6.16 857,652.50 SN2F.6.16 862,152.50 SNSF.6.16 848,615.00
M.005p Papan Jati (lokal) 0.0600 M3 12,800,000.00 768,000.00 12,875,000.00 772,500.00 12,800,000.00 768,000.00
M.006a Paku Biasa ( 1/2" - 1") 0.1500 Kg 21,850.00 3,277.50 21,850.00 3,277.50 21,850.00 3,277.50
L.008 Pekerja 0.5000 OH 27,000.00 13,500.00 27,000.00 13,500.00 24,500.00 12,250.00
L.002 Tukang Kayu 2.0000 OH 32,500.00 65,000.00 32,500.00 65,000.00 29,000.00 58,000.00
L.007 Kepala Tukang 0.2000 OH 35,000.00 7,000.00 35,000.00 7,000.00 31,500.00 6,300.00
L.010 Mandor 0.0250 OH 35,000.00 875.00 35,000.00 875.00 31,500.00 787.50
SNI - F.6.17 Pas. Jalusi Mati Kusen Kayu Kamper M2 SNIF.6.17 599,652.50 SN2F.6.17 604,152.50 SNSF.6.17 590,615.00
M.005o Papan Kamper 0.0600 M3 8,500,000.00 510,000.00 8,575,000.00 514,500.00 8,500,000.00 510,000.00
M.006a Paku Biasa ( 1/2" - 1") 0.1500 Kg 21,850.00 3,277.50 21,850.00 3,277.50 21,850.00 3,277.50
L.008 Pekerja 0.5000 OH 27,000.00 13,500.00 27,000.00 13,500.00 24,500.00 12,250.00
L.002 Tukang Kayu 2.0000 OH 32,500.00 65,000.00 32,500.00 65,000.00 29,000.00 58,000.00
L.007 Kepala Tukang 0.2000 OH 35,000.00 7,000.00 35,000.00 7,000.00 31,500.00 6,300.00
L.010 Mandor 0.0250 OH 35,000.00 875.00 35,000.00 875.00 31,500.00 787.50
SNI - F.6.17a Pas. Jalusi Mati Kusen Kayu Bangkir M2 SNIF.6.17a 629,652.50 SN2F.6.17a 634,152.50 SNSF.6.17a 620,615.00
M.005n Papan Bangkir 0.0600 M3 9,000,000.00 540,000.00 9,075,000.00 544,500.00 9,000,000.00 540,000.00
M.006a Paku Biasa ( 1/2" - 1") 0.1500 Kg 21,850.00 3,277.50 21,850.00 3,277.50 21,850.00 3,277.50
L.008 Pekerja 0.5000 OH 27,000.00 13,500.00 27,000.00 13,500.00 24,500.00 12,250.00
L.002 Tukang Kayu 2.0000 OH 32,500.00 65,000.00 32,500.00 65,000.00 29,000.00 58,000.00
L.007 Kepala Tukang 0.2000 OH 35,000.00 7,000.00 35,000.00 7,000.00 31,500.00 6,300.00
L.010 Mandor 0.0250 OH 35,000.00 875.00 35,000.00 875.00 31,500.00 787.50
SNI - F.6.17b Pas. Jalusi Mati Kusen Kayu Kruing M2 SNIF.6.17b 455,652.50 SN2F.6.17b 460,152.50 SNSF.6.17b 446,615.00
M.005m Papan Kruing 0.0600 M3 6,100,000.00 366,000.00 6,175,000.00 370,500.00 6,100,000.00 366,000.00
M.006a Paku Biasa ( 1/2" - 1") 0.1500 Kg 21,850.00 3,277.50 21,850.00 3,277.50 21,850.00 3,277.50
L.008 Pekerja 0.5000 OH 27,000.00 13,500.00 27,000.00 13,500.00 24,500.00 12,250.00
L.002 Tukang Kayu 2.0000 OH 32,500.00 65,000.00 32,500.00 65,000.00 29,000.00 58,000.00
L.007 Kepala Tukang 0.2000 OH 35,000.00 7,000.00 35,000.00 7,000.00 31,500.00 6,300.00
L.010 Mandor 0.0250 OH 35,000.00 875.00 35,000.00 875.00 31,500.00 787.50
SNI - F.6.19 Pas. Pintu Teakwood rangkap, rangka Kayu Jati M2 SNIF.6.19 428,785.00 SN2F.6.19 431,255.00 SNSF.6.19 419,480.00
M.005p Papan Jati (lokal) 0.0196 M3 12,800,000.00 250,880.00 12,875,000.00 252,350.00 12,800,000.00 250,880.00
M.006a Paku Biasa ( 1/2" - 1") 0.3000 Kg 21,850.00 6,555.00 21,850.00 6,555.00 21,850.00 6,555.00
M.012g Lem Kayu 0.3000 Kg 17,000.00 5,100.00 17,000.00 5,100.00 17,000.00 5,100.00
M.009e Teakwood 3' x 7' x 3mm 1.0000 Lbr 77,000.00 77,000.00 78,000.00 78,000.00 77,000.00 77,000.00
L.008 Pekerja 0.6000 OH 27,000.00 16,200.00 27,000.00 16,200.00 24,500.00 14,700.00
L.002 Tukang Kayu 2.0000 OH 32,500.00 65,000.00 32,500.00 65,000.00 29,000.00 58,000.00
L.007 Kepala Tukang 0.2000 OH 35,000.00 7,000.00 35,000.00 7,000.00 31,500.00 6,300.00
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
Pas. Pintu Teakwood rangkap, rangka Kayu
SNI - F.6.20 M2 SNIF.6.20 344,505.00 SN2F.6.20 346,975.00 SNSF.6.20 335,200.00
Kamper
M.005o Papan Kamper 0.0196 M3 8,500,000.00 166,600.00 8,575,000.00 168,070.00 8,500,000.00 166,600.00
M.006a Paku Biasa ( 1/2" - 1") 0.3000 Kg 21,850.00 6,555.00 21,850.00 6,555.00 21,850.00 6,555.00
M.012g Lem Kayu 0.3000 Kg 17,000.00 5,100.00 17,000.00 5,100.00 17,000.00 5,100.00
M.009e Teakwood 3' x 7' x 3mm 1.0000 Lbr 77,000.00 77,000.00 78,000.00 78,000.00 77,000.00 77,000.00
L.008 Pekerja 0.6000 OH 27,000.00 16,200.00 27,000.00 16,200.00 24,500.00 14,700.00
L.002 Tukang Kayu 2.0000 OH 32,500.00 65,000.00 32,500.00 65,000.00 29,000.00 58,000.00
L.007 Kepala Tukang 0.2000 OH 35,000.00 7,000.00 35,000.00 7,000.00 31,500.00 6,300.00
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
Pas. Pintu Teakwood rangkap, rangka Kayu
SNI - F.6.20a M2 SNIF.6.20a 354,305.00 SN2F.6.20a 356,775.00 SNSF.6.20a 345,000.00
Bangkir
M.005n Papan Bangkir 0.0196 M3 9,000,000.00 176,400.00 9,075,000.00 177,870.00 9,000,000.00 176,400.00
M.006a Paku Biasa ( 1/2" - 1") 0.3000 Kg 21,850.00 6,555.00 21,850.00 6,555.00 21,850.00 6,555.00
M.012g Lem Kayu 0.3000 Kg 17,000.00 5,100.00 17,000.00 5,100.00 17,000.00 5,100.00
M.009e Teakwood 3' x 7' x 3mm 1.0000 Lbr 77,000.00 77,000.00 78,000.00 78,000.00 77,000.00 77,000.00
L.008 Pekerja 0.6000 OH 27,000.00 16,200.00 27,000.00 16,200.00 24,500.00 14,700.00
L.002 Tukang Kayu 2.0000 OH 32,500.00 65,000.00 32,500.00 65,000.00 29,000.00 58,000.00
L.007 Kepala Tukang 0.2000 OH 35,000.00 7,000.00 35,000.00 7,000.00 31,500.00 6,300.00
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
Pas. Pintu Teakwood rangkap, rangka Kayu
SNI - F.6.20b M2 SNIF.6.20b 297,465.00 SN2F.6.20b 299,935.00 SNSF.6.20b 288,160.00
Kruing
M.005m Papan Kruing 0.0196 M3 6,100,000.00 119,560.00 6,175,000.00 121,030.00 6,100,000.00 119,560.00
M.006a Paku Biasa ( 1/2" - 1") 0.3000 Kg 21,850.00 6,555.00 21,850.00 6,555.00 21,850.00 6,555.00
M.012g Lem Kayu 0.3000 Kg 17,000.00 5,100.00 17,000.00 5,100.00 17,000.00 5,100.00
M.009e Teakwood 3' x 7' x 3mm 1.0000 Lbr 77,000.00 77,000.00 78,000.00 78,000.00 77,000.00 77,000.00
L.008 Pekerja 0.6000 OH 27,000.00 16,200.00 27,000.00 16,200.00 24,500.00 14,700.00
L.002 Tukang Kayu 2.0000 OH 32,500.00 65,000.00 32,500.00 65,000.00 29,000.00 58,000.00
L.007 Kepala Tukang 0.2000 OH 35,000.00 7,000.00 35,000.00 7,000.00 31,500.00 6,300.00
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
Pas. Pintu Triplek 3mm rangkap, rangka Kayu
SNI - F.6.20c M2 SNIF.6.20c 316,005.00 SN2F.6.20c 318,975.00 SNSF.6.20c 306,700.00
Kamper
M.005o Papan Kamper 0.0196 M3 8,500,000.00 166,600.00 8,575,000.00 168,070.00 8,500,000.00 166,600.00
M.006a Paku Biasa ( 1/2" - 1") 0.3000 Kg 21,850.00 6,555.00 21,850.00 6,555.00 21,850.00 6,555.00
M.012g Lem Kayu 0.3000 Kg 17,000.00 5,100.00 17,000.00 5,100.00 17,000.00 5,100.00
M.009a Triplek 3mm ( 3' x 7' ) 1.0000 Lbr 48,500.00 48,500.00 50,000.00 50,000.00 48,500.00 48,500.00
L.008 Pekerja 0.6000 OH 27,000.00 16,200.00 27,000.00 16,200.00 24,500.00 14,700.00
L.002 Tukang Kayu 2.0000 OH 32,500.00 65,000.00 32,500.00 65,000.00 29,000.00 58,000.00
L.007 Kepala Tukang 0.2000 OH 35,000.00 7,000.00 35,000.00 7,000.00 31,500.00 6,300.00
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
Pas. Pintu Triplek 3mm rangkap, rangka Kayu
SNI - F.6.20d M2 SNIF.6.20d 325,805.00 SN2F.6.20d 328,775.00 SNSF.6.20d 316,500.00
Bangkir
M.005n Papan Bangkir 0.0196 M3 9,000,000.00 176,400.00 9,075,000.00 177,870.00 9,000,000.00 176,400.00
M.006a Paku Biasa ( 1/2" - 1") 0.3000 Kg 21,850.00 6,555.00 21,850.00 6,555.00 21,850.00 6,555.00
M.012g Lem Kayu 0.3000 Kg 17,000.00 5,100.00 17,000.00 5,100.00 17,000.00 5,100.00
M.009a Triplek 3mm ( 3' x 7' ) 1.0000 Lbr 48,500.00 48,500.00 50,000.00 50,000.00 48,500.00 48,500.00
L.008 Pekerja 0.6000 OH 27,000.00 16,200.00 27,000.00 16,200.00 24,500.00 14,700.00
L.002 Tukang Kayu 2.0000 OH 32,500.00 65,000.00 32,500.00 65,000.00 29,000.00 58,000.00
L.007 Kepala Tukang 0.2000 OH 35,000.00 7,000.00 35,000.00 7,000.00 31,500.00 6,300.00
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
18 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
Pas. Pintu Triplek 3mm rangkap, rangka Kayu
SNI - F.6.20e M2 SNIF.6.20e 268,965.00 SN2F.6.20e 271,935.00 SNSF.6.20e 259,660.00
Kruing
M.005m Papan Kruing 0.0196 M3 6,100,000.00 119,560.00 6,175,000.00 121,030.00 6,100,000.00 119,560.00
M.006a Paku Biasa ( 1/2" - 1") 0.3000 Kg 21,850.00 6,555.00 21,850.00 6,555.00 21,850.00 6,555.00
M.012g Lem Kayu 0.3000 Kg 17,000.00 5,100.00 17,000.00 5,100.00 17,000.00 5,100.00
M.009a Triplek 3mm ( 3' x 7' ) 1.0000 Lbr 48,500.00 48,500.00 50,000.00 50,000.00 48,500.00 48,500.00
L.008 Pekerja 0.6000 OH 27,000.00 16,200.00 27,000.00 16,200.00 24,500.00 14,700.00
L.002 Tukang Kayu 2.0000 OH 32,500.00 65,000.00 32,500.00 65,000.00 29,000.00 58,000.00
L.007 Kepala Tukang 0.2000 OH 35,000.00 7,000.00 35,000.00 7,000.00 31,500.00 6,300.00
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
SNI - F.6.27 Pas. Konstruksi Kuda-kuda Kayu Jati M3 SNIF.6.27 16,826,400.00 SN2F.6.27 16,923,900.00 SNSF.6.27 16,769,500.00
M.005f Kayu Jati Balok (lokal) 1.1000 M3 14,500,000.00 15,950,000.00 14,575,000.00 16,032,500.00 14,500,000.00 15,950,000.00
M.003d Begel 15.0000 Kg 21,000.00 315,000.00 22,000.00 330,000.00 21,000.00 315,000.00
M.006 Paku Biasa ( 2" - 5") 0.8000 Kg 18,000.00 14,400.00 18,000.00 14,400.00 18,000.00 14,400.00
L.008 Pekerja 4.0000 OH 27,000.00 108,000.00 27,000.00 108,000.00 24,500.00 98,000.00
L.002 Tukang Kayu 12.0000 OH 32,500.00 390,000.00 32,500.00 390,000.00 29,000.00 348,000.00
L.007 Kepala Tukang 1.2000 OH 35,000.00 42,000.00 35,000.00 42,000.00 31,500.00 37,800.00
L.010 Mandor 0.2000 OH 35,000.00 7,000.00 35,000.00 7,000.00 31,500.00 6,300.00
Pas. Rangka Atap diketam halus dan di propil
SNI - F.6.27a M3 SNIF.6.27a 53,925,400.00 SN2F.6.27a 54,022,900.00 SNSF.6.27a 53,842,500.00
Kayu Jati (Kw.Eksport) uk. Khusus
M.005f1 Kayu Jati Balok (Kw. Eksport) uk.Khusus 1.1000 M3 48,000,000.00 52,800,000.00 48,075,000.00 52,882,500.00 48,000,000.00 52,800,000.00
M.003d Begel 15.0000 Kg 21,000.00 315,000.00 22,000.00 330,000.00 21,000.00 315,000.00
M.006 Paku Biasa ( 2" - 5") 0.8000 Kg 18,000.00 14,400.00 18,000.00 14,400.00 18,000.00 14,400.00
L.008 Pekerja 6.0000 OH 27,000.00 162,000.00 27,000.00 162,000.00 24,500.00 147,000.00
L.002 Tukang Kayu 18.0000 OH 32,500.00 585,000.00 32,500.00 585,000.00 29,000.00 522,000.00
L.007 Kepala Tukang 1.2000 OH 35,000.00 42,000.00 35,000.00 42,000.00 31,500.00 37,800.00
L.010 Mandor 0.2000 OH 35,000.00 7,000.00 35,000.00 7,000.00 31,500.00 6,300.00
Pas. Rangka Atap diketam halus dan di propil
SNI - F.6.27b M3 SNIF.6.27b 34,537,900.00 SN2F.6.27b 34,635,400.00 SNSF.6.27b 34,455,000.00
Kayu Jati (Kw. Eksport) uk. Khusus
Kayu Jati Balok (Kw. Eksport)
M.005f3 1.1000 M3 30,375,000.00 33,412,500.00 30,450,000.00 33,495,000.00 30,375,000.00 33,412,500.00
uk.Khusus
M.003d Begel 15.0000 Kg 21,000.00 315,000.00 22,000.00 330,000.00 21,000.00 315,000.00
M.006 Paku Biasa ( 2" - 5") 0.8000 Kg 18,000.00 14,400.00 18,000.00 14,400.00 18,000.00 14,400.00
L.008 Pekerja 6.0000 OH 27,000.00 162,000.00 27,000.00 162,000.00 24,500.00 147,000.00
L.002 Tukang Kayu 18.0000 OH 32,500.00 585,000.00 32,500.00 585,000.00 29,000.00 522,000.00
L.007 Kepala Tukang 1.2000 OH 35,000.00 42,000.00 35,000.00 42,000.00 31,500.00 37,800.00
L.010 Mandor 0.2000 OH 35,000.00 7,000.00 35,000.00 7,000.00 31,500.00 6,300.00
Pas. Rangka Atap diketam halus dan di propil
SNI - F.6.27c M3 SNIF.6.27c 28,625,400.00 SN2F.6.27c 28,722,900.00 SNSF.6.27c 28,542,500.00
Kayu Jati (Kw.Eksport) uk. Bukan Khusus
Kayu Jati Balok (Kw. Eksport) uk.bukan
M.005f3 1.1000 M3 25,000,000.00 27,500,000.00 25,075,000.00 27,582,500.00 25,000,000.00 27,500,000.00
Khusus
M.003d Begel 15.0000 Kg 21,000.00 315,000.00 22,000.00 330,000.00 21,000.00 315,000.00
M.006 Paku Biasa ( 2" - 5") 0.8000 Kg 18,000.00 14,400.00 18,000.00 14,400.00 18,000.00 14,400.00
L.008 Pekerja 6.0000 OH 27,000.00 162,000.00 27,000.00 162,000.00 24,500.00 147,000.00
L.002 Tukang Kayu 18.0000 OH 32,500.00 585,000.00 32,500.00 585,000.00 29,000.00 522,000.00
L.007 Kepala Tukang 1.2000 OH 35,000.00 42,000.00 35,000.00 42,000.00 31,500.00 37,800.00
L.010 Mandor 0.2000 OH 35,000.00 7,000.00 35,000.00 7,000.00 31,500.00 6,300.00
SNI - F.6.28 Pas. Konstruksi Kuda-kuda Kayu Kamper M3 SNIF.6.28 9,235,300.00 SN2F.6.28 9,332,800.00 SNSF.6.28 9,178,400.00
M.005e Kayu Kamper Balok 1.1000 M3 7,599,000.00 8,358,900.00 7,674,000.00 8,441,400.00 7,599,000.00 8,358,900.00
M.003d Begel 15.0000 Kg 21,000.00 315,000.00 22,000.00 330,000.00 21,000.00 315,000.00
M.006 Paku Biasa ( 2" - 5") 0.8000 Kg 18,000.00 14,400.00 18,000.00 14,400.00 18,000.00 14,400.00
L.008 Pekerja 4.0000 OH 27,000.00 108,000.00 27,000.00 108,000.00 24,500.00 98,000.00
L.002 Tukang Kayu 12.0000 OH 32,500.00 390,000.00 32,500.00 390,000.00 29,000.00 348,000.00
L.007 Kepala Tukang 1.2000 OH 35,000.00 42,000.00 35,000.00 42,000.00 31,500.00 37,800.00
L.010 Mandor 0.2000 OH 35,000.00 7,000.00 35,000.00 7,000.00 31,500.00 6,300.00
SNI - F.6.28a Pas. Konstruksi Kuda-kuda Kayu Bangkir M3 SNIF.6.28a 9,395,900.00 SN2F.6.28a 9,493,400.00 SNSF.6.28a 9,339,000.00
M.005d Kayu Bangkir Balok 1.1000 M3 7,745,000.00 8,519,500.00 7,820,000.00 8,602,000.00 7,745,000.00 8,519,500.00
M.003d Begel 15.0000 Kg 21,000.00 315,000.00 22,000.00 330,000.00 21,000.00 315,000.00
M.006 Paku Biasa ( 2" - 5") 0.8000 Kg 18,000.00 14,400.00 18,000.00 14,400.00 18,000.00 14,400.00
L.008 Pekerja 4.0000 OH 27,000.00 108,000.00 27,000.00 108,000.00 24,500.00 98,000.00
L.002 Tukang Kayu 12.0000 OH 32,500.00 390,000.00 32,500.00 390,000.00 29,000.00 348,000.00
L.007 Kepala Tukang 1.2000 OH 35,000.00 42,000.00 35,000.00 42,000.00 31,500.00 37,800.00
L.010 Mandor 0.2000 OH 35,000.00 7,000.00 35,000.00 7,000.00 31,500.00 6,300.00
Pas. Rk. Atap diketam halus & di propil
SNI - F.6.28b M3 SNIF.6.28b 11,810,400.00 SN2F.6.28b 11,907,900.00 SNSF.6.28b 11,728,200.00
Ky.Bangkir uk. Khusus (30/30 - 12/12 P:5-8m')
M.005d1 Kayu Bangkir Balok uk.Khusus 1.1000 M3 9,720,000.00 10,692,000.00 9,795,000.00 10,774,500.00 9,720,000.00 10,692,000.00
M.003d Begel 15.0000 Kg 21,000.00 315,000.00 22,000.00 330,000.00 21,000.00 315,000.00
M.006 Paku Biasa ( 2" - 5") 0.8000 Kg 18,000.00 14,400.00 18,000.00 14,400.00 18,000.00 14,400.00
L.008 Pekerja 6.0000 OH 27,000.00 162,000.00 27,000.00 162,000.00 24,500.00 147,000.00
L.002 Tukang Kayu 18.0000 OH 32,500.00 585,000.00 32,500.00 585,000.00 29,000.00 522,000.00
L.007 Kepala Tukang 1.2000 OH 35,000.00 42,000.00 35,000.00 42,000.00 31,500.00 37,800.00
L.010 Mandor 0.2000 OH 35,000.00 7,000.00 35,000.00 7,000.00 31,500.00 6,300.00
Pas. Rk. Atap diketam halus & di propil
SNI - F.6.28c M3 SNIF.6.28c 12,482,900.00 SN2F.6.28c 12,580,400.00 SNSF.6.28c 12,400,000.00
Ky.Bangkir uk. Khusus (8/15 - 5/10 P:5-8m')
M.005d2 Kayu Bangkir Balok uk.Khusus 1.1000 M3 10,325,000.00 11,357,500.00 10,400,000.00 11,440,000.00 10,325,000.00 11,357,500.00
M.003d Begel 15.0000 Kg 21,000.00 315,000.00 22,000.00 330,000.00 21,000.00 315,000.00
M.006 Paku Biasa ( 2" - 5") 0.8000 Kg 18,000.00 14,400.00 18,000.00 14,400.00 18,000.00 14,400.00
L.008 Pekerja 6.0000 OH 27,000.00 162,000.00 27,000.00 162,000.00 24,500.00 147,000.00
L.002 Tukang Kayu 18.0000 OH 32,500.00 585,000.00 32,500.00 585,000.00 29,000.00 522,000.00
L.007 Kepala Tukang 1.2000 OH 35,000.00 42,000.00 35,000.00 42,000.00 31,500.00 37,800.00
L.010 Mandor 0.2000 OH 35,000.00 7,000.00 35,000.00 7,000.00 31,500.00 6,300.00
SNI - F.6.30 Pas. Konstruksi Kuda-kuda Kayu Kruing M3 SNIF.6.30 6,948,400.00 SN2F.6.30 7,045,900.00 SNSF.6.30 6,891,500.00
M.005c Kayu Kruing Balok 1.1000 M3 5,520,000.00 6,072,000.00 5,595,000.00 6,154,500.00 5,520,000.00 6,072,000.00
M.003d Begel 15.0000 Kg 21,000.00 315,000.00 22,000.00 330,000.00 21,000.00 315,000.00
M.006 Paku Biasa ( 2" - 5") 0.8000 Kg 18,000.00 14,400.00 18,000.00 14,400.00 18,000.00 14,400.00
L.008 Pekerja 4.0000 OH 27,000.00 108,000.00 27,000.00 108,000.00 24,500.00 98,000.00
L.002 Tukang Kayu 12.0000 OH 32,500.00 390,000.00 32,500.00 390,000.00 29,000.00 348,000.00
L.007 Kepala Tukang 1.2000 OH 35,000.00 42,000.00 35,000.00 42,000.00 31,500.00 37,800.00
L.010 Mandor 0.2000 OH 35,000.00 7,000.00 35,000.00 7,000.00 31,500.00 6,300.00
19 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
Pas. Kaso dan Reng genteng (kodok, plentong,
SNI - F.6.31 M2 SNIF.6.31 78,775.00 SN2F.6.31 79,675.00 SNSF.6.31 78,122.50
vlams dan sejenisnya) Kayu Kamper
M.005j Usuk Kamper 5/7 0.0120 M3 5,800,000.00 69,600.00 5,875,000.00 70,500.00 5,800,000.00 69,600.00
M.006 Paku Biasa ( 2" - 5") 0.1500 Kg 18,000.00 2,700.00 18,000.00 2,700.00 18,000.00 2,700.00
L.008 Pekerja 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.002 Tukang Kayu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
Pas. Kaso dan Reng genteng (kodok, plentong,
SNI - F.6.31a M2 SNIF.6.31a 87,175.00 SN2F.6.31a 88,075.00 SNSF.6.31a 86,522.50
vlams dan sejenisnya) Kayu Bangkir
M.005i Usuk Bangkir 5/7 0.0120 M3 6,500,000.00 78,000.00 6,575,000.00 78,900.00 6,500,000.00 78,000.00
M.006 Paku Biasa ( 2" - 5") 0.1500 Kg 18,000.00 2,700.00 18,000.00 2,700.00 18,000.00 2,700.00
L.008 Pekerja 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.002 Tukang Kayu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
Pas. Kaso dan Reng genteng (kodok, plentong,
SNI - F.6.31b M2 SNIF.6.31b 67,975.00 SN2F.6.31b 68,875.00 SNSF.6.31b 67,322.50
vlams dan sejenisnya) Kayu Kruing
M.005h Usuk Kruing 5/7 0.0120 M3 4,900,000.00 58,800.00 4,975,000.00 59,700.00 4,900,000.00 58,800.00
M.006 Paku Biasa ( 2" - 5") 0.1500 Kg 18,000.00 2,700.00 18,000.00 2,700.00 18,000.00 2,700.00
L.008 Pekerja 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.002 Tukang Kayu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
Pas. Kaso dan Reng genteng (kodok, plentong,
SNI - F.6.31c M2 SNIF.6.31c 55,975.00 SN2F.6.31c 56,875.00 SNSF.6.31c 55,322.50
vlams dan sejenisnya) Kayu Meranti
M.005g Usuk Meranti 5/7 0.0120 M3 3,900,000.00 46,800.00 3,975,000.00 47,700.00 3,900,000.00 46,800.00
M.006 Paku Biasa ( 2" - 5") 0.1500 Kg 18,000.00 2,700.00 18,000.00 2,700.00 18,000.00 2,700.00
L.008 Pekerja 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.002 Tukang Kayu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
Pas. Kaso dan Reng genteng (kodok, plentong,
SNI - F.6.31d M2 SNIF.6.31d 125,815.00 SN2F.6.31d 126,715.00 SNSF.6.31d 125,162.50
vlams dan sejenisnya) Kayu Bangkir uk.5/10

M.005d1 Usuk Bangkir 5/10 0.0120 M3 9,720,000.00 116,640.00 9,795,000.00 117,540.00 9,720,000.00 116,640.00
M.006 Paku Biasa ( 2" - 5") 0.1500 Kg 18,000.00 2,700.00 18,000.00 2,700.00 18,000.00 2,700.00
L.008 Pekerja 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.002 Tukang Kayu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
Pas. Kaso dan Reng genteng (monier dan
SNI - F.6.35 M2 SNIF.6.35 90,375.00 SN2F.6.35 91,425.00 SNSF.6.35 89,722.50
sejenisnya) Kayu Kamper
M.005j Usuk Kamper 5/7 0.0140 M3 5,800,000.00 81,200.00 5,875,000.00 82,250.00 5,800,000.00 81,200.00
M.006 Paku Biasa ( 2" - 5") 0.1500 Kg 18,000.00 2,700.00 18,000.00 2,700.00 18,000.00 2,700.00
L.008 Pekerja 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.002 Tukang Kayu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
Pas. Kaso dan Reng genteng (monier dan
SNI - F.6.35a M2 SNIF.6.35a 100,175.00 SN2F.6.35a 101,225.00 SNSF.6.35a 99,522.50
sejenisnya) Kayu Bangkir
M.005i Usuk Bangkir 5/7 0.0140 M3 6,500,000.00 91,000.00 6,575,000.00 92,050.00 6,500,000.00 91,000.00
M.006 Paku Biasa ( 2" - 5") 0.1500 Kg 18,000.00 2,700.00 18,000.00 2,700.00 18,000.00 2,700.00
L.008 Pekerja 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.002 Tukang Kayu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
Pas. Kaso dan Reng genteng (monier dan
SNI - F.6.35b M2 SNIF.6.35b 77,775.00 SN2F.6.35b 78,825.00 SNSF.6.35b 77,122.50
sejenisnya) Kayu Kruing
M.005h Usuk Kruing 5/7 0.0140 M3 4,900,000.00 68,600.00 4,975,000.00 69,650.00 4,900,000.00 68,600.00
M.006 Paku Biasa ( 2" - 5") 0.1500 Kg 18,000.00 2,700.00 18,000.00 2,700.00 18,000.00 2,700.00
L.008 Pekerja 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.002 Tukang Kayu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
Pas. Usuk 5/10 P : 5 - 8 m Kayu Bangkir diketam
SNI - F.6.35c M3 SNIF.6.35c 12,988,656.00 SN2F.6.35c 13,078,705.00 SNSF.6.35c 12,943,621.00
halus dan dipropil
M.005d2 Kayu Bangkir Balok Uk.Khusus 1.2000 M3 10,325,000.00 12,390,000.00 10,400,000.00 12,480,000.00 10,325,000.00 12,390,000.00
M.003f Mur, baud 0.1400 M3 20,650.00 2,891.00 21,000.00 2,940.00 20,650.00 2,891.00
M.006 Paku biasa ( 5" ) 0.0800 M3 18,000.00 1,440.00 18,000.00 1,440.00 18,000.00 1,440.00
L.008 Pekerja 6.0000 OH 18,000.00 108,000.00 18,000.00 108,000.00 18,000.00 108,000.00
L.002 Tukang Kayu 18.0000 OH 27,000.00 486,000.00 27,000.00 486,000.00 24,500.00 441,000.00
L.007 Kepala Tukang 0.0100 OH 32,500.00 325.00 32,500.00 325.00 29,000.00 290.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
Pas. Usuk 5/10 P : 2 - 4 m Kayu Bangkir diketam
SNI - F.6.35d M3 SNIF.6.35d 9,892,656.00 SN2F.6.35d 9,982,705.00 SNSF.6.35d 9,847,621.00
halus dan dipropil
M.005d Kayu Jati Balok 1.2000 M3 7,745,000.00 9,294,000.00 7,820,000.00 9,384,000.00 7,745,000.00 9,294,000.00
M.003f Mur, baud 0.1400 M3 20,650.00 2,891.00 21,000.00 2,940.00 20,650.00 2,891.00
M.006 Paku biasa ( 5" ) 0.0800 M3 18,000.00 1,440.00 18,000.00 1,440.00 18,000.00 1,440.00
L.008 Pekerja 6.0000 OH 18,000.00 108,000.00 18,000.00 108,000.00 18,000.00 108,000.00
L.002 Tukang Kayu 18.0000 OH 27,000.00 486,000.00 27,000.00 486,000.00 24,500.00 441,000.00
L.007 Kepala Tukang 0.0100 OH 32,500.00 325.00 32,500.00 325.00 29,000.00 290.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
20 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
Pas. Usuk 5/10 P : 5 - 8 m Kayu Jati diketam halus
SNI - F.6.35e M3 SNIF.6.35e 37,048,831.00 SN2F.6.35e 37,138,880.00 SNSF.6.35e 37,003,778.50
dan dipropil (Kw. Eksport)
M.005f2 Kayu Jati Balok Uk.Khusus (Kw. Eksport) 1.2000 M3 30,375,000.00 36,450,000.00 30,450,000.00 36,540,000.00 30,375,000.00 36,450,000.00
M.003f Mur, baud 0.1400 M3 20,650.00 2,891.00 21,000.00 2,940.00 20,650.00 2,891.00
M.006 Paku biasa ( 5" ) 0.0800 M3 18,000.00 1,440.00 18,000.00 1,440.00 18,000.00 1,440.00
L.008 Pekerja 6.0000 OH 18,000.00 108,000.00 18,000.00 108,000.00 18,000.00 108,000.00
L.002 Tukang Kayu 18.0000 OH 27,000.00 486,000.00 27,000.00 486,000.00 24,500.00 441,000.00
L.007 Kepala Tukang 0.0100 OH 32,500.00 325.00 32,500.00 325.00 29,000.00 290.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
Pas. Usuk 5/10 P : 2 - 4 m Kayu Jati diketam halus
SNI - F.6.35f M3 SNIF.6.35f 30,598,831.00 SN2F.6.35f 30,688,880.00 SNSF.6.35f 30,553,778.50
dan dipropil (Kw. Eksport)
M.005f3 Kayu Jati Balok Uk.Khusus (Kw. Eksport) 1.2000 M3 25,000,000.00 30,000,000.00 25,075,000.00 30,090,000.00 25,000,000.00 30,000,000.00
M.003f Mur, baud 0.1400 M3 20,650.00 2,891.00 21,000.00 2,940.00 20,650.00 2,891.00
M.006 Paku biasa ( 5" ) 0.0800 M3 18,000.00 1,440.00 18,000.00 1,440.00 18,000.00 1,440.00
L.008 Pekerja 6.0000 OH 18,000.00 108,000.00 18,000.00 108,000.00 18,000.00 108,000.00
L.002 Tukang Kayu 18.0000 OH 27,000.00 486,000.00 27,000.00 486,000.00 24,500.00 441,000.00
L.007 Kepala Tukang 0.0100 OH 32,500.00 325.00 32,500.00 325.00 29,000.00 290.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
SNI - F.6.38 Pas. Rangka langit-langit Kayu Jati Uk. 1 x 1 m M2 SNIF.6.38 136,275.00 SN2F.6.38 137,175.00 SNSF.6.38 134,675.00
M.005k Usuk Jati 5/7 0.0120 M3 9,900,000.00 118,800.00 9,975,000.00 119,700.00 9,900,000.00 118,800.00
M.006 Paku Biasa ( 2" - 5") 0.1000 Kg 18,000.00 1,800.00 18,000.00 1,800.00 18,000.00 1,800.00
L.008 Pekerja 0.1500 OH 27,000.00 4,050.00 27,000.00 4,050.00 24,500.00 3,675.00
L.002 Tukang Kayu 0.2500 OH 32,500.00 8,125.00 32,500.00 8,125.00 29,000.00 7,250.00
L.007 Kepala Tukang 0.0250 OH 35,000.00 875.00 35,000.00 875.00 31,500.00 787.50
L.010 Mandor 0.0750 OH 35,000.00 2,625.00 35,000.00 2,625.00 31,500.00 2,362.50
Pas. Lambersering uk. 1/20 Kayu Jati diketam
SNI - F.6.38a M' SNIF.6.38a 402,130.00 SN2F.6.38a 402,880.00 SNSF.6.38a 401,320.00
halus dan dipropil (Kw.Eksport)
M.005p1 Papan Jati (Kw. Eksport) 0.0100 M3 39,300,000.00 393,000.00 39,375,000.00 393,750.00 39,300,000.00 393,000.00
M.006 Paku Biasa ( 1" - 2") 0.0600 Kg 18,000.00 1,080.00 18,000.00 1,080.00 18,000.00 1,080.00
L.008 Pekerja 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.002 Tukang Kayu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0500 OH 35,000.00 1,750.00 35,000.00 1,750.00 31,500.00 1,575.00
Pas. Rangka langit-langit Kayu Kamper Uk. 1 x 1
SNI - F.6.39 M2 SNIF.6.39 87,075.00 SN2F.6.39 87,975.00 SNSF.6.39 85,475.00
m
M.005j Usuk Kamper 5/7 0.0120 M3 5,800,000.00 69,600.00 5,875,000.00 70,500.00 5,800,000.00 69,600.00
M.006 Paku Biasa ( 2" - 5") 0.1000 Kg 18,000.00 1,800.00 18,000.00 1,800.00 18,000.00 1,800.00
L.008 Pekerja 0.1500 OH 27,000.00 4,050.00 27,000.00 4,050.00 24,500.00 3,675.00
L.002 Tukang Kayu 0.2500 OH 32,500.00 8,125.00 32,500.00 8,125.00 29,000.00 7,250.00
L.007 Kepala Tukang 0.0250 OH 35,000.00 875.00 35,000.00 875.00 31,500.00 787.50
L.010 Mandor 0.0750 OH 35,000.00 2,625.00 35,000.00 2,625.00 31,500.00 2,362.50
SNI - F.6.39a Pas. Rangka langit-langit Ky Bangkir Uk. 1x1 m M2 SNIF.6.39a 95,475.00 SN2F.6.39a 96,375.00 SNSF.6.39a 93,875.00
M.005i Usuk Bangkir 5/7 0.0120 M3 6,500,000.00 78,000.00 6,575,000.00 78,900.00 6,500,000.00 78,000.00
M.006 Paku Biasa ( 2" - 5") 0.1000 Kg 18,000.00 1,800.00 18,000.00 1,800.00 18,000.00 1,800.00
L.008 Pekerja 0.1500 OH 27,000.00 4,050.00 27,000.00 4,050.00 24,500.00 3,675.00
L.002 Tukang Kayu 0.2500 OH 32,500.00 8,125.00 32,500.00 8,125.00 29,000.00 7,250.00
L.007 Kepala Tukang 0.0250 OH 35,000.00 875.00 35,000.00 875.00 31,500.00 787.50
L.010 Mandor 0.0750 OH 35,000.00 2,625.00 35,000.00 2,625.00 31,500.00 2,362.50
SNI - F.6.39b Pas. Rangka langit-langit Ky Kruing Uk. 1 x 1 m M2 SNIF.6.39b 76,275.00 SN2F.6.39b 77,175.00 SNSF.6.39b 74,675.00
M.005h Usuk Kruing 5/7 0.0120 M3 4,900,000.00 58,800.00 4,975,000.00 59,700.00 4,900,000.00 58,800.00
M.006 Paku Biasa ( 2" - 5") 0.1000 Kg 18,000.00 1,800.00 18,000.00 1,800.00 18,000.00 1,800.00
L.008 Pekerja 0.1500 OH 27,000.00 4,050.00 27,000.00 4,050.00 24,500.00 3,675.00
L.002 Tukang Kayu 0.2500 OH 32,500.00 8,125.00 32,500.00 8,125.00 29,000.00 7,250.00
L.007 Kepala Tukang 0.0250 OH 35,000.00 875.00 35,000.00 875.00 31,500.00 787.50
L.010 Mandor 0.0750 OH 35,000.00 2,625.00 35,000.00 2,625.00 31,500.00 2,362.50
SNI - F.6.39c Pas. Rangka langit-langit Ky Meranti Uk. 1x1 m M2 SNIF.6.39c 64,275.00 SN2F.6.39c 65,175.00 SNSF.6.39c 62,675.00
M.005g Usuk Meranti 5/7 0.0120 M3 3,900,000.00 46,800.00 3,975,000.00 47,700.00 3,900,000.00 46,800.00
M.006 Paku Biasa ( 2" - 5") 0.1000 Kg 18,000.00 1,800.00 18,000.00 1,800.00 18,000.00 1,800.00
L.008 Pekerja 0.1500 OH 27,000.00 4,050.00 27,000.00 4,050.00 24,500.00 3,675.00
L.002 Tukang Kayu 0.2500 OH 32,500.00 8,125.00 32,500.00 8,125.00 29,000.00 7,250.00
L.007 Kepala Tukang 0.0250 OH 35,000.00 875.00 35,000.00 875.00 31,500.00 787.50
L.010 Mandor 0.0750 OH 35,000.00 2,625.00 35,000.00 2,625.00 31,500.00 2,362.50
Pas. Lambersering uk. 1/20 Kayu Bangkir diketam
SNI - F.6.39d M' SNIF.6.39d 99,130.00 SN2F.6.39d 99,880.00 SNSF.6.39d 98,320.00
halus dan dipropil
M.005n Papan Bangkir 0.0100 M3 9,000,000.00 90,000.00 9,075,000.00 90,750.00 9,000,000.00 90,000.00
M.006 Paku Biasa ( 1" - 2") 0.0600 Kg 18,000.00 1,080.00 18,000.00 1,080.00 18,000.00 1,080.00
L.008 Pekerja 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.002 Tukang Kayu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0500 OH 35,000.00 1,750.00 35,000.00 1,750.00 31,500.00 1,575.00
Pas. Rangka langit-langit Kayu Kamper Uk. 0.30 x
SNI - F.6.44 M2 SNIF.6.44 179,987.50 SN2F.6.44 182,012.50 SNSF.6.44 177,971.25
0.30 m
M.005j Usuk Kamper 5/7 0.0270 M3 5,800,000.00 156,600.00 5,875,000.00 158,625.00 5,800,000.00 156,600.00
M.006 Paku Biasa ( 2" - 5") 0.2000 Kg 18,000.00 3,600.00 18,000.00 3,600.00 18,000.00 3,600.00
L.008 Pekerja 0.2500 OH 27,000.00 6,750.00 27,000.00 6,750.00 24,500.00 6,125.00
L.002 Tukang Kayu 0.3500 OH 32,500.00 11,375.00 32,500.00 11,375.00 29,000.00 10,150.00
L.007 Kepala Tukang 0.0350 OH 35,000.00 1,225.00 35,000.00 1,225.00 31,500.00 1,102.50
L.010 Mandor 0.0125 OH 35,000.00 437.50 35,000.00 437.50 31,500.00 393.75
Pas. Rangka langit-langit Kayu Bangkir Uk. 0.30 x
SNI - F.6.44a M2 SNIF.6.44a 198,887.50 SN2F.6.44a 200,912.50 SNSF.6.44a 196,871.25
0.30 m
M.005i Usuk Bangkir 5/7 0.0270 M3 6,500,000.00 175,500.00 6,575,000.00 177,525.00 6,500,000.00 175,500.00
M.006 Paku Biasa ( 2" - 5") 0.2000 Kg 18,000.00 3,600.00 18,000.00 3,600.00 18,000.00 3,600.00
L.008 Pekerja 0.2500 OH 27,000.00 6,750.00 27,000.00 6,750.00 24,500.00 6,125.00
L.002 Tukang Kayu 0.3500 OH 32,500.00 11,375.00 32,500.00 11,375.00 29,000.00 10,150.00
L.007 Kepala Tukang 0.0350 OH 35,000.00 1,225.00 35,000.00 1,225.00 31,500.00 1,102.50
L.010 Mandor 0.0125 OH 35,000.00 437.50 35,000.00 437.50 31,500.00 393.75
21 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
Pas. Rangka langit-langit Kayu Kruing Uk. 0.30 x
SNI - F.6.44b M2 SNIF.6.44b 155,687.50 SN2F.6.44b 157,712.50 SNSF.6.44b 153,671.25
0.30 m
M.005h Usuk Kruing 5/7 0.0270 M3 4,900,000.00 132,300.00 4,975,000.00 134,325.00 4,900,000.00 132,300.00
M.006 Paku Biasa ( 2" - 5") 0.2000 Kg 18,000.00 3,600.00 18,000.00 3,600.00 18,000.00 3,600.00
L.008 Pekerja 0.2500 OH 27,000.00 6,750.00 27,000.00 6,750.00 24,500.00 6,125.00
L.002 Tukang Kayu 0.3500 OH 32,500.00 11,375.00 32,500.00 11,375.00 29,000.00 10,150.00
L.007 Kepala Tukang 0.0350 OH 35,000.00 1,225.00 35,000.00 1,225.00 31,500.00 1,102.50
L.010 Mandor 0.0125 OH 35,000.00 437.50 35,000.00 437.50 31,500.00 393.75
Pas. Rangka langit-langit Kayu Meranti Uk. 0.30 x
SNI - F.6.44c M2 SNIF.6.44c 128,687.50 SN2F.6.44c 130,712.50 SNSF.6.44c 126,671.25
0.30 m
M.005g Usuk Meranti 5/7 0.0270 M3 3,900,000.00 105,300.00 3,975,000.00 107,325.00 3,900,000.00 105,300.00
M.006 Paku Biasa ( 2" - 5") 0.2000 Kg 18,000.00 3,600.00 18,000.00 3,600.00 18,000.00 3,600.00
L.008 Pekerja 0.2500 OH 27,000.00 6,750.00 27,000.00 6,750.00 24,500.00 6,125.00
L.002 Tukang Kayu 0.3500 OH 32,500.00 11,375.00 32,500.00 11,375.00 29,000.00 10,150.00
L.007 Kepala Tukang 0.0350 OH 35,000.00 1,225.00 35,000.00 1,225.00 31,500.00 1,102.50
L.010 Mandor 0.0125 OH 35,000.00 437.50 35,000.00 437.50 31,500.00 393.75
SNI - F.6.47 Pas. Lisplank Kayu Jati Uk. 3 x 20 cm M' SNIF.6.47 103,310.00 SN2F.6.47 103,850.00 SNSF.6.47 102,255.00
M.005p Papan Jati (lokal) 0.0072 M3 12,800,000.00 92,160.00 12,875,000.00 92,700.00 12,800,000.00 92,160.00
M.006 Paku Biasa ( 2" - 5") 0.0500 Kg 18,000.00 900.00 18,000.00 900.00 18,000.00 900.00
L.008 Pekerja 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.002 Tukang Kayu 0.2000 OH 32,500.00 6,500.00 32,500.00 6,500.00 29,000.00 5,800.00
L.007 Kepala Tukang 0.0250 OH 35,000.00 875.00 35,000.00 875.00 31,500.00 787.50
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
Pas. Lisplank dipropil dan divariasi uk. 3x30
SNI - F.6.47a M' SNIF.6.47 375,280.00 SN2F.6.47 375,955.00 SNSF.6.47 373,170.00
Kayu Jati (Kw.Eksport)
M.005p1 Papan Jati (Kw. Eksport) 0.0090 M3 39,300,000.00 353,700.00 39,375,000.00 354,375.00 39,300,000.00 353,700.00
M.006 Paku Biasa ( 1" - 2") 0.0600 Kg 18,000.00 1,080.00 18,000.00 1,080.00 18,000.00 1,080.00
L.008 Pekerja 0.2000 OH 27,000.00 5,400.00 27,000.00 5,400.00 24,500.00 4,900.00
L.002 Tukang Kayu 0.4000 OH 32,500.00 13,000.00 32,500.00 13,000.00 29,000.00 11,600.00
L.007 Kepala Tukang 0.0500 OH 35,000.00 1,750.00 35,000.00 1,750.00 31,500.00 1,575.00
L.010 Mandor 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
SNI - F.6.48 Pas. Lisplank Kayu Kamper Uk. 3 x 20 cm M' SNIF.6.48 72,175.00 SN2F.6.48 72,715.00 SNSF.6.48 71,137.50
M.005o Papan Kamper 0.0072 M3 8,500,000.00 61,200.00 8,575,000.00 61,740.00 8,500,000.00 61,200.00
M.006 Paku Biasa ( 2" - 5") 0.0500 Kg 18,000.00 900.00 18,000.00 900.00 18,000.00 900.00
L.008 Pekerja 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.002 Tukang Kayu 0.2000 OH 32,500.00 6,500.00 32,500.00 6,500.00 29,000.00 5,800.00
L.007 Kepala Tukang 0.0200 OH 35,000.00 700.00 35,000.00 700.00 31,500.00 630.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
SNI - F.6.48a Pas. Lisplank Kayu Bangkir Uk. 3 x 20 cm M' SNIF.6.48a 75,775.00 SN2F.6.48a 76,315.00 SNSF.6.48a 74,737.50
M.005n Papan Bangkir 0.0072 M3 9,000,000.00 64,800.00 9,075,000.00 65,340.00 9,000,000.00 64,800.00
M.006 Paku Biasa ( 2" - 5") 0.0500 Kg 18,000.00 900.00 18,000.00 900.00 18,000.00 900.00
L.008 Pekerja 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.002 Tukang Kayu 0.2000 OH 32,500.00 6,500.00 32,500.00 6,500.00 29,000.00 5,800.00
L.007 Kepala Tukang 0.0200 OH 35,000.00 700.00 35,000.00 700.00 31,500.00 630.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
SNI - F.6.48b Pas. Lisplank Kayu Kruing Uk. 3 x 20 cm M' SNIF.6.48b 54,895.00 SN2F.6.48b 55,435.00 SNSF.6.48b 53,857.50
M.005m Papan Kruing 0.0072 M3 6,100,000.00 43,920.00 6,175,000.00 44,460.00 6,100,000.00 43,920.00
M.006 Paku Biasa ( 2" - 5") 0.0500 Kg 18,000.00 900.00 18,000.00 900.00 18,000.00 900.00
L.008 Pekerja 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.002 Tukang Kayu 0.2000 OH 32,500.00 6,500.00 32,500.00 6,500.00 29,000.00 5,800.00
L.007 Kepala Tukang 0.0200 OH 35,000.00 700.00 35,000.00 700.00 31,500.00 630.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
Pas. Lisplank dipropil dan divariasi uk. 3x30
SNI - F.6.48c M' SNIF.6.48c 102,580.00 SN2F.6.48c 103,255.00 SNSF.6.48c 100,470.00
Kayu Bangkir
M.005n Papan Bangkir 0.0090 M3 9,000,000.00 81,000.00 9,075,000.00 81,675.00 9,000,000.00 81,000.00
M.006 Paku Biasa ( 2" - 5") 0.0600 Kg 18,000.00 1,080.00 18,000.00 1,080.00 18,000.00 1,080.00
L.008 Pekerja 0.2000 OH 27,000.00 5,400.00 27,000.00 5,400.00 24,500.00 4,900.00
L.002 Tukang Kayu 0.4000 OH 32,500.00 13,000.00 32,500.00 13,000.00 29,000.00 11,600.00
L.007 Kepala Tukang 0.0500 OH 35,000.00 1,750.00 35,000.00 1,750.00 31,500.00 1,575.00
L.010 Mandor 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
SNI - F.6.52 Pas. Lisplank Kayu Jati Uk. 2 ( 2 x 20 ) cm M' SNIF.6.52 119,210.00 SN2F.6.52 119,855.00 SNSF.6.52 118,400.00
M.005p Papan Jati (lokal) 0.0086 M3 12,800,000 110,080.00 12,875,000 110,725.00 12,800,000 110,080.00
M.006 Paku Biasa ( 2" - 5") 0.0600 Kg 18,000 1,080.00 18,000 1,080.00 18,000 1,080.00
L.008 Pekerja 0.1000 OH 27,000 2,700.00 27,000 2,700.00 24,500 2,450.00
L.002 Tukang Kayu 0.1000 OH 32,500 3,250.00 32,500 3,250.00 29,000 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000 350.00 35,000 350.00 31,500 315.00
L.010 Mandor 0.0500 OH 35,000 1,750.00 35,000 1,750.00 31,500 1,575.00
SNI - F.6.52a Pas. Lisplank Kayu Kamper Uk. 2 ( 2 x 20 ) cm M' SNIF.6.52a 82,230.00 SN2F.6.52a 82,875.00 SNSF.6.52a 81,420.00
M.005o Papan Kamper 0.0086 M3 8,500,000.00 73,100.00 8,575,000.00 73,745.00 8,500,000.00 73,100.00
M.006 Paku Biasa ( 2" - 5") 0.0600 Kg 18,000.00 1,080.00 18,000.00 1,080.00 18,000.00 1,080.00
L.008 Pekerja 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.002 Tukang Kayu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0500 OH 35,000.00 1,750.00 35,000.00 1,750.00 31,500.00 1,575.00
SNI - F.6.52b Pas. Lisplank Kayu Bangkir Uk. 2 ( 2 x 20 ) cm M' SNIF.6.52b 86,530.00 SN2F.6.52b 87,175.00 SNSF.6.52b 85,720.00
M.005n Papan Bangkir 0.0086 M3 9,000,000.00 77,400.00 9,075,000.00 78,045.00 9,000,000.00 77,400.00
M.006 Paku Biasa ( 2" - 5") 0.0600 Kg 18,000.00 1,080.00 18,000.00 1,080.00 18,000.00 1,080.00
L.008 Pekerja 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.002 Tukang Kayu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0500 OH 35,000.00 1,750.00 35,000.00 1,750.00 31,500.00 1,575.00
22 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
SNI - F.6.52c Pas. Lisplank Kayu Kruing Uk. 2 ( 2 x 20 ) cm M' SNIF.6.52c 61,590.00 SN2F.6.52c 62,235.00 SNSF.6.52c 60,780.00
M.005m Papan Kruing 0.0086 M3 6,100,000.00 52,460.00 6,175,000.00 53,105.00 6,100,000.00 52,460.00
M.006 Paku Biasa ( 2" - 5") 0.0600 Kg 18,000.00 1,080.00 18,000.00 1,080.00 18,000.00 1,080.00
L.008 Pekerja 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.002 Tukang Kayu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0500 OH 35,000.00 1,750.00 35,000.00 1,750.00 31,500.00 1,575.00
SNI - F.6.52d Pas. Lisplank Kayu Jati Uk. 2 ( 2 x 20 ) cm M' SNIF.6.52d 119,210.00 SN2F.6.52d 119,855.00 SNSF.6.52d 118,400.00
M.005p Papan Jati (lokal) 0.0086 M3 12,800,000 110,080.00 12,875,000 110,725.00 12,800,000 110,080.00
M.006 Paku Biasa ( 2" - 5") 0.0600 Kg 18,000 1,080.00 18,000 1,080.00 18,000 1,080.00
L.008 Pekerja 0.1000 OH 27,000 2,700.00 27,000 2,700.00 24,500 2,450.00
L.002 Tukang Kayu 0.1000 OH 32,500 3,250.00 32,500 3,250.00 29,000 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000 350.00 35,000 350.00 31,500 315.00
L.010 Mandor 0.0500 OH 35,000 1,750.00 35,000 1,750.00 31,500 1,575.00
G. PEKERJAAN BETON

SNI - G.6.1 Membuat Beton Tumbuk 1 PC : 3 Ps : 5 Kr M3 SNIG.6.1 487,850.00 SN2G.6.1 501,976.00 SNSG.6.1 482,482.50
M.002a Portland Cement 218.00 Kg 1,200.00 261,600.00 1,207.00 263,126.00 1,200.00 261,600.00
M.001 Pasir Beton 0.5200 M3 92,500.00 48,100.00 100,000.00 52,000.00 92,500.00 48,100.00
M.001g Koral Beton ( Batu pecah 2/3 cm ) 0.8700 M3 140,000.00 121,800.00 150,000.00 130,500.00 140,000.00 121,800.00
L.008 Pekerja 1.6500 OH 27,000.00 44,550.00 27,000.00 44,550.00 24,500.00 40,425.00
L.001 Tukang Batu 0.2500 OH 32,500.00 8,125.00 32,500.00 8,125.00 29,000.00 7,250.00
L.007 Kepala Tukang 0.0250 OH 35,000.00 875.00 35,000.00 875.00 31,500.00 787.50
L.010 Mandor 0.0800 OH 35,000.00 2,800.00 35,000.00 2,800.00 31,500.00 2,520.00
Membuat Lantai Kerja Beton Tumbuk 1 PC : 3 Ps :
SNI - G.6.4 M3 SNIG.6.4 52,545.00 SN2G.6.4 53,250.00 SNSG.6.4 49,572.00
5 Kr tb. 5 cm
M.002a Portland Cement 10.0000 Kg 1,200.00 12,000.00 1,207.00 12,070.00 1,200.00 12,000.00
M.001 Pasir Beton 0.0260 M3 92,500.00 2,405.00 100,000.00 2,600.00 92,500.00 2,405.00
M.001g Koral Beton ( Batu pecah 2/3 cm ) 0.0440 M3 140,000.00 6,160.00 150,000.00 6,600.00 140,000.00 6,160.00
L.008 Pekerja 1.1500 OH 27,000.00 31,050.00 27,000.00 31,050.00 24,500.00 28,175.00
L.001 Tukang Batu 0.0200 OH 32,500.00 650.00 32,500.00 650.00 29,000.00 580.00
L.007 Kepala Tukang 0.0020 OH 35,000.00 70.00 35,000.00 70.00 31,500.00 63.00
L.010 Mandor 0.0060 OH 35,000.00 210.00 35,000.00 210.00 31,500.00 189.00
SNI - G.6.7 Membuat Beton Cor 1 PC : 2 Ps : 2,5 Kr M3 SNIG.6.7 628,550.00 SN2G.6.7 642,214.00 SNSG.6.7 623,182.50
M.002a Portland Cement 352.00 Kg 1,200.00 422,400.00 1,207.00 424,864.00 1,200.00 422,400.00
M.001 Pasir Beton 0.5600 M3 92,500.00 51,800.00 100,000.00 56,000.00 92,500.00 51,800.00
M.001g Koral Beton ( Batu pecah 2/3 cm ) 0.7000 M3 140,000.00 98,000.00 150,000.00 105,000.00 140,000.00 98,000.00
L.008 Pekerja 1.6500 OH 27,000.00 44,550.00 27,000.00 44,550.00 24,500.00 40,425.00
L.001 Tukang Batu 0.2500 OH 32,500.00 8,125.00 32,500.00 8,125.00 29,000.00 7,250.00
L.007 Kepala Tukang 0.0250 OH 35,000.00 875.00 35,000.00 875.00 31,500.00 787.50
L.010 Mandor 0.0800 OH 35,000.00 2,800.00 35,000.00 2,800.00 31,500.00 2,520.00
SNI - G.6.13 Membuat Beton Cor 1 PC : 2 Ps : 3 Kr M3 SNIG.6.13 668,150.00 SN2G.6.13 682,652.00 SNSG.6.13 658,302.50
M.002a Portland Cement 336.00 Kg 1,200.00 403,200.00 1,207.00 405,552.00 1,200.00 403,200.00
M.001 Pasir Beton 0.5400 M3 92,500.00 49,950.00 100,000.00 54,000.00 92,500.00 49,950.00
M.001g Koral Beton ( Batu pecah 2/3 cm ) 0.8100 M3 140,000.00 113,400.00 150,000.00 121,500.00 140,000.00 113,400.00
L.008 Pekerja 2.0000 OH 27,000.00 54,000.00 27,000.00 54,000.00 24,500.00 49,000.00
L.001 Tukang Batu 0.3500 OH 32,500.00 11,375.00 32,500.00 11,375.00 29,000.00 10,150.00
L.007 Kepala Tukang 0.0350 OH 35,000.00 1,225.00 35,000.00 1,225.00 31,500.00 1,102.50
L.010 Mandor 1.0000 OH 35,000.00 35,000.00 35,000.00 35,000.00 31,500.00 31,500.00
SNI - G.6.25 Pembesian dengan Besi Beton Polos (sek.KS) Kg SNIG.6.25 16,461.00 SN2G.6.25 17,526.00 SNSG.6.25 16,415.50
M.003 Besi Beton Polos 1.0500 Kg 15,000.00 15,750.00 16,000.00 16,800.00 15,000.00 15,750.00
M.003a Kawat Beton ( Bindrat ) 0.0150 Kg 17,300.00 259.50 18,300.00 274.50 17,300.00 259.50
L.008 Pekerja 0.0070 OH 27,000.00 189.00 27,000.00 189.00 24,500.00 171.50
L.003 Tukang Besi 0.0070 OH 32,500.00 227.50 32,500.00 227.50 29,000.00 203.00
L.007 Kepala Tukang 0.0007 OH 35,000.00 24.50 35,000.00 24.50 31,500.00 22.05
L.010 Mandor 0.0003 OH 35,000.00 10.50 35,000.00 10.50 31,500.00 9.45
SNI - G.6.25a Pembesian dengan Besi Beton Ulir Kg SNIG.6.25a 16,461.00 SN2G.6.25a 17,526.00 SNSG.6.25a 16,415.50
M.003c Besi Beton Ulir 1.0500 Kg 15,000.00 15,750.00 16,000.00 16,800.00 15,000.00 15,750.00
M.003a Kawat Beton ( Bindrat ) 0.0150 Kg 17,300.00 259.50 18,300.00 274.50 17,300.00 259.50
L.008 Pekerja 0.0070 OH 27,000.00 189.00 27,000.00 189.00 24,500.00 171.50
L.003 Tukang Besi 0.0070 OH 32,500.00 227.50 32,500.00 227.50 29,000.00 203.00
L.007 Kepala Tukang 0.0007 OH 35,000.00 24.50 35,000.00 24.50 31,500.00 22.05
L.010 Mandor 0.0003 OH 35,000.00 10.50 35,000.00 10.50 31,500.00 9.45
Pembesian dengan Besi Beton Polos (sek.Non
SNI - G.6.25b Kg SNIG.6.25 15,411.00 SN2G.6.25 16,476.00 SNSG.6.25 15,365.50
KS)
M.003.1 Besi Beton Polos 1.0500 Kg 14,000.00 14,700.00 15,000.00 15,750.00 14,000.00 14,700.00
M.003a Kawat Beton ( Bindrat ) 0.0150 Kg 17,300.00 259.50 18,300.00 274.50 17,300.00 259.50
L.008 Pekerja 0.0070 OH 27,000.00 189.00 27,000.00 189.00 24,500.00 171.50
L.003 Tukang Besi 0.0070 OH 32,500.00 227.50 32,500.00 227.50 29,000.00 203.00
L.007 Kepala Tukang 0.0007 OH 35,000.00 24.50 35,000.00 24.50 31,500.00 22.05
L.010 Mandor 0.0003 OH 35,000.00 10.50 35,000.00 10.50 31,500.00 9.45
SNI - G.6.28 Pas. Bekisting untuk Pondasi M2 SNIG.6.28 77,035.00 SN2G.6.28 79,035.00 SNSG.6.28 75,266.50
M.005a Kayu Tahun 0.0400 M3 1,350,000.00 54,000.00 1,400,000.00 56,000.00 1,350,000.00 54,000.00
M.006 Paku Biasa (2" - 5") 0.3000 Kg 18,000.00 5,400.00 18,000.00 5,400.00 18,000.00 5,400.00
L.008 Pekerja 0.3000 OH 27,000.00 8,100.00 27,000.00 8,100.00 24,500.00 7,350.00
L.002 Tukang Kayu 0.2600 OH 32,500.00 8,450.00 32,500.00 8,450.00 29,000.00 7,540.00
L.007 Kepala Tukang 0.0260 OH 35,000.00 910.00 35,000.00 910.00 31,500.00 819.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
23 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
SNI - G.6.29 Pas. Bekisting untuk Sloof M2 SNIG.6.29 83,785.00 SN2G.6.29 86,035.00 SNSG.6.29 82,016.50
M.005a Kayu Tahun 0.0450 M3 1,350,000.00 60,750.00 1,400,000.00 63,000.00 1,350,000.00 60,750.00
M.006 Paku Biasa (2" - 5") 0.3000 Kg 18,000.00 5,400.00 18,000.00 5,400.00 18,000.00 5,400.00
L.008 Pekerja 0.3000 OH 27,000.00 8,100.00 27,000.00 8,100.00 24,500.00 7,350.00
L.002 Tukang Kayu 0.2600 OH 32,500.00 8,450.00 32,500.00 8,450.00 29,000.00 7,540.00
L.007 Kepala Tukang 0.0260 OH 35,000.00 910.00 35,000.00 910.00 31,500.00 819.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
SNI - G.6.30 Pas. Bekisting untuk Kolom M2 SNIG.6.30 248,890.00 SN2G.6.30 263,065.00 SNSG.6.30 246,848.50
M.005a Kayu Tahun 0.0400 M3 1,350,000.00 54,000.00 1,400,000.00 56,000.00 1,350,000.00 54,000.00
M.006 Paku Biasa (2" - 5") 0.4000 Kg 18,000.00 7,200.00 18,000.00 7,200.00 18,000.00 7,200.00
M.005g Usuk Meranti 5/7 0.0150 M3 3,900,000.00 58,500.00 3,975,000.00 59,625.00 3,900,000.00 58,500.00
M.009c Multiplek 9mm 0.3500 Lbr 140,000.00 49,000.00 143,000.00 50,050.00 140,000.00 49,000.00
M.005s Dolken kayu galam diam.8-10/4m 2.0000 Btg 30,000.00 60,000.00 35,000.00 70,000.00 30,000.00 60,000.00
L.008 Pekerja 0.3000 OH 27,000.00 8,100.00 27,000.00 8,100.00 24,500.00 7,350.00
L.002 Tukang Kayu 0.3300 OH 32,500.00 10,725.00 32,500.00 10,725.00 29,000.00 9,570.00
L.007 Kepala Tukang 0.0330 OH 35,000.00 1,155.00 35,000.00 1,155.00 31,500.00 1,039.50
L.010 Mandor 0.0060 OH 35,000.00 210.00 35,000.00 210.00 31,500.00 189.00
SNI - G.6.31 Pas. Bekisting untuk Balok M2 SNIG.6.31 261,130.00 SN2G.6.31 275,530.00 SNSG.6.31 259,038.50
M.005a Kayu Tahun 0.0400 M3 1,350,000.00 54,000.00 1,400,000.00 56,000.00 1,350,000.00 54,000.00
M.006 Paku Biasa (2" - 5") 0.4000 Kg 18,000.00 7,200.00 18,000.00 7,200.00 18,000.00 7,200.00
M.005g Usuk Meranti 5/7 0.0180 M3 3,900,000.00 70,200.00 3,975,000.00 71,550.00 3,900,000.00 70,200.00
M.009c Multiplek 9mm 0.3500 Lbr 140,000.00 49,000.00 143,000.00 50,050.00 140,000.00 49,000.00
M.005s Dolken kayu galam diam.8-10/4m 2.0000 Btg 30,000.00 60,000.00 35,000.00 70,000.00 30,000.00 60,000.00
L.008 Pekerja 0.3200 OH 27,000.00 8,640.00 27,000.00 8,640.00 24,500.00 7,840.00
L.002 Tukang Kayu 0.3300 OH 32,500.00 10,725.00 32,500.00 10,725.00 29,000.00 9,570.00
L.007 Kepala Tukang 0.0330 OH 35,000.00 1,155.00 35,000.00 1,155.00 31,500.00 1,039.50
L.010 Mandor 0.0060 OH 35,000.00 210.00 35,000.00 210.00 31,500.00 189.00
SNI - G.6.32 Pas. Bekisting untuk Lantai M2 SNIG.6.32 369,430.00 SN2G.6.32 403,605.00 SNSG.6.32 367,338.50
M.005a Kayu Tahun 0.0400 M3 1,350,000.00 54,000.00 1,400,000.00 56,000.00 1,350,000.00 54,000.00
M.006 Paku Biasa (2" - 5") 0.4000 Kg 18,000.00 7,200.00 18,000.00 7,200.00 18,000.00 7,200.00
M.005g Usuk Meranti 5/7 0.0150 M3 3,900,000.00 58,500.00 3,975,000.00 59,625.00 3,900,000.00 58,500.00
M.009c Multiplek 9mm 0.3500 Lbr 140,000.00 49,000.00 143,000.00 50,050.00 140,000.00 49,000.00
M.005s Dolken kayu galam diam.8-10/4m 6.0000 Btg 30,000.00 180,000.00 35,000.00 210,000.00 30,000.00 180,000.00
L.008 Pekerja 0.3200 OH 27,000.00 8,640.00 27,000.00 8,640.00 24,500.00 7,840.00
L.002 Tukang Kayu 0.3300 OH 32,500.00 10,725.00 32,500.00 10,725.00 29,000.00 9,570.00
L.007 Kepala Tukang 0.0330 OH 35,000.00 1,155.00 35,000.00 1,155.00 31,500.00 1,039.50
L.010 Mandor 0.0060 OH 35,000.00 210.00 35,000.00 210.00 31,500.00 189.00
SNI - G.6.33 Pas. Bekisting untuk Dinding M2 SNIG.6.33 355,430.00 SN2G.6.33 376,480.00 SNSG.6.33 353,338.50
M.005a Kayu Tahun 0.0300 M3 1,350,000.00 40,500.00 1,400,000.00 42,000.00 1,350,000.00 40,500.00
M.006 Paku Biasa (2" - 5") 0.4000 Kg 18,000.00 7,200.00 18,000.00 7,200.00 18,000.00 7,200.00
M.005g Usuk Meranti 5/7 0.0200 M3 3,900,000.00 78,000.00 3,975,000.00 79,500.00 3,900,000.00 78,000.00
M.009c Multiplek 9mm 0.3500 Lbr 140,000.00 49,000.00 143,000.00 50,050.00 140,000.00 49,000.00
M.005s Dolken kayu galam diam.8-10/4m 3.0000 Btg 30,000.00 90,000.00 35,000.00 105,000.00 30,000.00 90,000.00
M.005t Formite/Penjaga Jarak Bekisting/Spacer 4.0000 Btg 17,500.00 70,000.00 18,000.00 72,000.00 17,500.00 70,000.00
L.008 Pekerja 0.3200 OH 27,000.00 8,640.00 27,000.00 8,640.00 24,500.00 7,840.00
L.002 Tukang Kayu 0.3300 OH 32,500.00 10,725.00 32,500.00 10,725.00 29,000.00 9,570.00
L.007 Kepala Tukang 0.0330 OH 35,000.00 1,155.00 35,000.00 1,155.00 31,500.00 1,039.50
L.010 Mandor 0.0060 OH 35,000.00 210.00 35,000.00 210.00 31,500.00 189.00
SNI - G.6.34 Pas. Bekisting untuk Tangga M2 SNIG.6.34 235,930.00 SN2G.6.34 249,605.00 SNSG.6.34 233,838.50
M.005a Kayu Tahun 0.0300 M3 1,350,000.00 40,500.00 1,400,000.00 42,000.00 1,350,000.00 40,500.00
M.006 Paku Biasa (2" - 5") 0.4000 Kg 18,000.00 7,200.00 18,000.00 7,200.00 18,000.00 7,200.00
M.005g Kayu Meranti ( Balok ) 0.0150 M3 3,900,000.00 58,500.00 3,975,000.00 59,625.00 3,900,000.00 58,500.00
M.009c Plywood 9mm 0.3500 Lbr 140,000.00 49,000.00 143,000.00 50,050.00 140,000.00 49,000.00
M.005s Dolken kayu galam diam.8-10/4m 2.0000 Btg 30,000.00 60,000.00 35,000.00 70,000.00 30,000.00 60,000.00
L.008 Pekerja 0.3200 OH 27,000.00 8,640.00 27,000.00 8,640.00 24,500.00 7,840.00
L.002 Tukang Kayu 0.3300 OH 32,500.00 10,725.00 32,500.00 10,725.00 29,000.00 9,570.00
L.007 Kepala Tukang 0.0330 OH 35,000.00 1,155.00 35,000.00 1,155.00 31,500.00 1,039.50
L.010 Mandor 0.0060 OH 35,000.00 210.00 35,000.00 210.00 31,500.00 189.00
Membuat Kolom Penguat Beton Bertulang ( 11 x
SNI - G.6.45 M' SNIG.6.45 66,165.00 SN2G.6.45 69,878.00 SNSG.6.45 65,773.50
11 ) cm
M.005a Kayu Tahun 0.0020 M3 1,350,000.00 2,700.00 1,400,000.00 2,800.00 1,350,000.00 2,700.00
M.006 Paku Biasa (2" - 5") 0.0100 Kg 18,000.00 180.00 18,000.00 180.00 18,000.00 180.00
M.003 Besi Beton Polos 3.0000 Kg 15,000.00 45,000.00 16,000.00 48,000.00 15,000.00 45,000.00
M.003a Kawat Beton ( Bindrat ) 0.4500 Kg 17,300.00 7,785.00 18,300.00 8,235.00 17,300.00 7,785.00
M.002a Portland Cement 4.0000 Kg 1,200.00 4,800.00 1,207.00 4,828.00 1,200.00 4,800.00
M.001 Pasir Beton 0.0060 M3 92,500.00 555.00 100,000.00 600.00 92,500.00 555.00
M.001g Koral Beton ( Batu Pecah 2/3 ) 0.0090 M3 140,000.00 1,260.00 150,000.00 1,350.00 140,000.00 1,260.00
L.008 Pekerja 0.0600 OH 27,000.00 1,620.00 27,000.00 1,620.00 24,500.00 1,470.00
L.001 Tukang Batu 0.0200 OH 32,500.00 650.00 32,500.00 650.00 29,000.00 580.00
L.002 Tukang Kayu 0.0200 OH 32,500.00 650.00 32,500.00 650.00 29,000.00 580.00
L.003 Tukang Besi 0.0200 OH 32,500.00 650.00 32,500.00 650.00 29,000.00 580.00
L.007 Kepala Tukang 0.0060 OH 35,000.00 210.00 35,000.00 210.00 31,500.00 189.00
L.010 Mandor 0.0030 OH 35,000.00 105.00 35,000.00 105.00 31,500.00 94.50
24 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
SNI - G.6.46 Membuat Ring Balok Beton ( 10 x 15 ) cm M' SNIG.6.46 75,250.00 SN2G.6.46 79,306.00 SNSG.6.46 74,601.00
M.005a Kayu Tahun 0.0030 M3 1,350,000.00 4,050.00 1,400,000.00 4,200.00 1,350,000.00 4,050.00
M.006 Paku Biasa (2" - 5") 0.0200 Kg 18,000.00 360.00 18,000.00 360.00 18,000.00 360.00
M.003 Besi Beton Polos 3.6000 Kg 15,000.00 54,000.00 16,000.00 57,600.00 15,000.00 54,000.00
M.003a Kawat Beton ( Bindrat ) 0.0500 Kg 17,300.00 865.00 18,300.00 915.00 17,300.00 865.00
M.002a Portland Cement 5.5000 Kg 1,200.00 6,600.00 1,207.00 6,638.50 1,200.00 6,600.00
M.001 Pasir Beton 0.0090 M3 92,500.00 832.50 100,000.00 900.00 92,500.00 832.50
M.001g Koral Beton ( Batu Pecah 2/3 ) 0.0150 M3 140,000.00 2,100.00 150,000.00 2,250.00 140,000.00 2,100.00
L.008 Pekerja 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.001 Tukang Batu 0.0330 OH 32,500.00 1,072.50 32,500.00 1,072.50 29,000.00 957.00
L.002 Tukang Kayu 0.0330 OH 32,500.00 1,072.50 32,500.00 1,072.50 29,000.00 957.00
L.003 Tukang Besi 0.0330 OH 32,500.00 1,072.50 32,500.00 1,072.50 29,000.00 957.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
H. PEKERJAAN ATAP

SNI - H.6.1 Pas. Atap Genteng Plentong Kecil M2 SNIH.6.1 34,297.50 SN2H.6.1 35,547.50 SNSH.6.1 33,604.00
M.010a Genteng plentong 25.0000 Bh 1,090.00 27,250.00 1,140.00 28,500.00 1,090.00 27,250.00
L.008 Pekerja 0.1500 OH 27,000.00 4,050.00 27,000.00 4,050.00 24,500.00 3,675.00
L.002 Tukang Kayu 0.0750 OH 32,500.00 2,437.50 32,500.00 2,437.50 29,000.00 2,175.00
L.007 Kepala Tukang 0.0080 OH 35,000.00 280.00 35,000.00 280.00 31,500.00 252.00
L.010 Mandor 0.0080 OH 35,000.00 280.00 35,000.00 280.00 31,500.00 252.00
SNI - H.6.2 Pas. Atap Genteng Kodok M2 SNIH.6.2 39,547.50 SN2H.6.2 40,797.50 SNSH.6.2 38,854.00
M.010b Genteng Kodok 25.0000 Bh 1,300.00 32,500.00 1,350.00 33,750.00 1,300.00 32,500.00
L.008 Pekerja 0.1500 OH 27,000.00 4,050.00 27,000.00 4,050.00 24,500.00 3,675.00
L.002 Tukang Kayu 0.0750 OH 32,500.00 2,437.50 32,500.00 2,437.50 29,000.00 2,175.00
L.007 Kepala Tukang 0.0080 OH 35,000.00 280.00 35,000.00 280.00 31,500.00 252.00
L.010 Mandor 0.0080 OH 35,000.00 280.00 35,000.00 280.00 31,500.00 252.00
SNI - H.6.4 Pas. Atap Genteng Bubung Plentong M' SNIH.6.4 42,890.00 SN2H.6.4 44,436.00 SNSH.6.4 41,113.00
M.010c Genteng Bubung Plentong/Kodok 5.0000 Bh 2,500.00 12,500.00 2,750.00 13,750.00 2,500.00 12,500.00
M.002a Portland Cement 8.0000 Kg 1,200.00 9,600.00 1,207.00 9,656.00 1,200.00 9,600.00
M.001a Pasir Pasang 0.0320 M3 85,000.00 2,720.00 92,500.00 2,960.00 85,000.00 2,720.00
L.008 Pekerja 0.4000 OH 27,000.00 10,800.00 27,000.00 10,800.00 24,500.00 9,800.00
L.002 Tukang Kayu 0.2000 OH 32,500.00 6,500.00 32,500.00 6,500.00 29,000.00 5,800.00
L.007 Kepala Tukang 0.0200 OH 35,000.00 700.00 35,000.00 700.00 31,500.00 630.00
L.010 Mandor 0.0020 OH 35,000.00 70.00 35,000.00 70.00 31,500.00 63.00
Pas. Atap fiber semen Gelombang Uk. ( 3,00 x
SNI - H.6.12 M2 SNIH.6.12 39,655.00 SN2H.6.12 40,005.00 SNSH.6.12 39,011.00
1,05 m ) x 4mm
M.010o Asbes Gelombang 0.3500 Lbr 85,000.00 29,750.00 86,000.00 30,100.00 85,000.00 29,750.00
M.006b Paku Kait 0.1200 Kg 28,000.00 3,360.00 28,000.00 3,360.00 28,000.00 3,360.00
L.008 Pekerja 0.1400 OH 27,000.00 3,780.00 27,000.00 3,780.00 24,500.00 3,430.00
L.002 Tukang Kayu 0.0700 OH 32,500.00 2,275.00 32,500.00 2,275.00 29,000.00 2,030.00
L.007 Kepala Tukang 0.0070 OH 35,000.00 245.00 35,000.00 245.00 31,500.00 220.50
L.010 Mandor 0.0070 OH 35,000.00 245.00 35,000.00 245.00 31,500.00 220.50
Pas. Atap fiber semen Gelombang Uk. ( 2,70 x
SNI - H.6.13 M2 SNIH.6.13 42,245.00 SN2H.6.13 42,665.00 SNSH.6.13 41,601.00
1,05 m ) x 4mm
M.010p Asbes Gelombang 0.4200 Lbr 77,000.00 32,340.00 78,000.00 32,760.00 77,000.00 32,340.00
M.006b Paku Kait 0.1200 Kg 28,000.00 3,360.00 28,000.00 3,360.00 28,000.00 3,360.00
L.008 Pekerja 0.1400 OH 27,000.00 3,780.00 27,000.00 3,780.00 24,500.00 3,430.00
L.002 Tukang Kayu 0.0700 OH 32,500.00 2,275.00 32,500.00 2,275.00 29,000.00 2,030.00
L.007 Kepala Tukang 0.0070 OH 35,000.00 245.00 35,000.00 245.00 31,500.00 220.50
L.010 Mandor 0.0070 OH 35,000.00 245.00 35,000.00 245.00 31,500.00 220.50
Pas. Atap fiber semen Gelombang Uk. ( 2,40 x
SNI - H.6.14 M2 SNIH.6.14 40,167.50 SN2H.6.14 40,607.50 SNSH.6.14 39,534.00
1,05 m ) x 4mm
M.010q Asbes Gelombang 0.4400 Lbr 69,000.00 30,360.00 70,000.00 30,800.00 69,000.00 30,360.00
M.006b Paku Kait 0.1200 Kg 28,000.00 3,360.00 28,000.00 3,360.00 28,000.00 3,360.00
L.008 Pekerja 0.1400 OH 27,000.00 3,780.00 27,000.00 3,780.00 24,500.00 3,430.00
L.002 Tukang Kayu 0.0670 OH 32,500.00 2,177.50 32,500.00 2,177.50 29,000.00 1,943.00
L.007 Kepala Tukang 0.0070 OH 35,000.00 245.00 35,000.00 245.00 31,500.00 220.50
L.010 Mandor 0.0070 OH 35,000.00 245.00 35,000.00 245.00 31,500.00 220.50
Pas. Atap fiber semen Gelombang Uk. ( 2,10 x
SNI - H.6.15 M2 SNIH.6.15 40,407.50 SN2H.6.15 40,917.50 SNSH.6.15 39,774.00
1,05 m ) x 4mm
M.010r Asbes Gelombang 0.5100 Lbr 60,000.00 30,600.00 61,000.00 31,110.00 60,000.00 30,600.00
M.006b Paku Kait 0.1200 Kg 28,000.00 3,360.00 28,000.00 3,360.00 28,000.00 3,360.00
L.008 Pekerja 0.1400 OH 27,000.00 3,780.00 27,000.00 3,780.00 24,500.00 3,430.00
L.002 Tukang Kayu 0.0670 OH 32,500.00 2,177.50 32,500.00 2,177.50 29,000.00 1,943.00
L.007 Kepala Tukang 0.0070 OH 35,000.00 245.00 35,000.00 245.00 31,500.00 220.50
L.010 Mandor 0.0070 OH 35,000.00 245.00 35,000.00 245.00 31,500.00 220.50
Pas. Atap fiber semen Gelombang Uk. ( 1,50 x
SNI - H.6.16 M2 SNIH.6.16 44,207.50 SN2H.6.16 45,007.50 SNSH.6.16 43,574.00
1,05 m ) x 4mm
M.010s Asbes Gelombang 0.8000 Lbr 43,000.00 34,400.00 44,000.00 35,200.00 43,000.00 34,400.00
M.006b Paku Kait 0.1200 Kg 28,000.00 3,360.00 28,000.00 3,360.00 28,000.00 3,360.00
L.008 Pekerja 0.1400 OH 27,000.00 3,780.00 27,000.00 3,780.00 24,500.00 3,430.00
L.002 Tukang Kayu 0.0670 OH 32,500.00 2,177.50 32,500.00 2,177.50 29,000.00 1,943.00
L.007 Kepala Tukang 0.0070 OH 35,000.00 245.00 35,000.00 245.00 31,500.00 220.50
L.010 Mandor 0.0070 OH 35,000.00 245.00 35,000.00 245.00 31,500.00 220.50
25 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
SNI-H.6.16.a Pasang Atap Seng Galvalum M2 SNIH.6.16a 79,407.50 SN2H.6.16a 81,807.50 SNSH.6.16a 78,774.00
M.010v Seng Galvalum 0.2400 Lbr 290,000.00 69,600.00 300,000.00 72,000.00 290,000.00 69,600.00
M.006b Paku Kait 0.1200 Kg 28,000.00 3,360.00 28,000.00 3,360.00 28,000.00 3,360.00
L.008 Pekerja 0.1400 OH 27,000.00 3,780.00 27,000.00 3,780.00 24,500.00 3,430.00
L.002 Tukang Kayu 0.0670 OH 32,500.00 2,177.50 32,500.00 2,177.50 29,000.00 1,943.00
L.007 Kepala Tukang 0.0070 OH 35,000.00 245.00 35,000.00 245.00 31,500.00 220.50
L.010 Mandor 0.0070 OH 35,000.00 245.00 35,000.00 245.00 31,500.00 220.50
SNI - H.6.23 Pas. Nok Stel fiber semen Gelombang Uk. 1,50 m M' SNIH.6.23 58,825.50 SN2H.6.23 60,925.50 SNSH.6.23 58,118.50
M.010t Nok Stel Asbes Gelombang 2.1000 Lbr 23,000.00 48,300.00 24,000.00 50,400.00 23,000.00 48,300.00
M.006g Paku Skrup 3,5" 6.0000 Bh 600.00 3,600.00 600.00 3,600.00 600.00 3,600.00
L.008 Pekerja 0.0840 OH 27,000.00 2,268.00 27,000.00 2,268.00 24,500.00 2,058.00
L.002 Tukang Kayu 0.1250 OH 32,500.00 4,062.50 32,500.00 4,062.50 29,000.00 3,625.00
L.007 Kepala Tukang 0.0130 OH 35,000.00 455.00 35,000.00 455.00 31,500.00 409.50
L.010 Mandor 0.0040 OH 35,000.00 140.00 35,000.00 140.00 31,500.00 126.00
SNI - H.6.30 1 M2 Pas. Atap Genteng Beton M2 SNIH.6.30 51,690.00 SN2H.6.30 52,240.00 SNSH.6.30 50,770.00
M.010j Genteng Beton 11.0000 Bh 3,800.00 41,800.00 3,850.00 42,350.00 3,800.00 41,800.00
M.006 Paku Biasa ( 2" - 5") 0.0300 Kg 18,000.00 540.00 18,000.00 540.00 18,000.00 540.00
L.008 Pekerja 0.2000 OH 27,000.00 5,400.00 27,000.00 5,400.00 24,500.00 4,900.00
L.002 Tukang Kayu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
SNI - H.6.30a 1 M2 Pas. Atap Genteng Morando M2 SNIH.6.30a 46,790.00 SN2H.6.30a 47,690.00 SNSH.6.30a 45,870.00
M.010e Genteng Morando 18.0000 Bh 2,050.00 36,900.00 2,100.00 37,800.00 2,050.00 36,900.00
M.006 Paku Biasa ( 2" - 5") 0.0300 Kg 18,000.00 540.00 18,000.00 540.00 18,000.00 540.00
L.008 Pekerja 0.2000 OH 27,000.00 5,400.00 27,000.00 5,400.00 24,500.00 4,900.00
L.002 Tukang Kayu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
SNI - H.6.34 Pas. Atap Nok Genteng Beton M' SNIH.6.34 50,780.00 SN2H.6.34 51,320.60 SNSH.6.34 48,940.00
M.010i Genteng Nok Beton 3.5000 Bh 4,000.00 14,000.00 4,050.00 14,175.00 4,000.00 14,000.00
M.006 Paku Biasa ( 2" - 5") 0.0500 Kg 18,000.00 900.00 18,000.00 900.00 18,000.00 900.00
M.002a Portland Cement 10.8000 Kg 1,200.00 12,960.00 1,207.00 13,035.60 1,200.00 12,960.00
M.001a Pasir Pasang 0.0320 M3 85,000.00 2,720.00 92,500.00 2,960.00 85,000.00 2,720.00
M.002b PC Warna 1.0000 Kg 1,500.00 1,500.00 1,550.00 1,550.00 1,500.00 1,500.00
L.008 Pekerja 0.4000 OH 27,000.00 10,800.00 27,000.00 10,800.00 24,500.00 9,800.00
L.002 Tukang Kayu 0.2000 OH 32,500.00 6,500.00 32,500.00 6,500.00 29,000.00 5,800.00
L.007 Kepala Tukang 0.0200 OH 35,000.00 700.00 35,000.00 700.00 31,500.00 630.00
L.010 Mandor 0.0200 OH 35,000.00 700.00 35,000.00 700.00 31,500.00 630.00
SNI - H.6.34a Pas. Atap Nok Genteng Morando M' SNIH.6.34a 50,780.00 SN2H.6.34a 51,495.60 SNSH.6.34a 48,940.00
M.010f Genteng Nok Morando 3.5000 Bh 4,000.00 14,000.00 4,100.00 14,350.00 4,000.00 14,000.00
M.006 Paku Biasa ( 2" - 5") 0.0500 Kg 18,000.00 900.00 18,000.00 900.00 18,000.00 900.00
M.002a Portland Cement 10.8000 Kg 1,200.00 12,960.00 1,207.00 13,035.60 1,200.00 12,960.00
M.001a Pasir Pasang 0.0320 M3 85,000.00 2,720.00 92,500.00 2,960.00 85,000.00 2,720.00
M.002b PC Warna 1.0000 Kg 1,500.00 1,500.00 1,550.00 1,550.00 1,500.00 1,500.00
L.008 Pekerja 0.4000 OH 27,000.00 10,800.00 27,000.00 10,800.00 24,500.00 9,800.00
L.002 Tukang Kayu 0.2000 OH 32,500.00 6,500.00 32,500.00 6,500.00 29,000.00 5,800.00
L.007 Kepala Tukang 0.0200 OH 35,000.00 700.00 35,000.00 700.00 31,500.00 630.00
L.010 Mandor 0.0200 OH 35,000.00 700.00 35,000.00 700.00 31,500.00 630.00
SNI - H.6.38 Pas. Atap Seng Gelombang BJLS 30 M' SNIH.6.38 38,990.00 SN2H.6.38 39,690.00 SNSH.6.38 38,438.00
M.010l Seng Gelombang 3" x 6 " BJLS 30 0.7000 Lbr 47,000.00 32,900.00 48,000.00 33,600.00 47,000.00 32,900.00
M.006c Paku Seng ( 1/2" - 1") 0.0200 Kg 24,000.00 480.00 24,000.00 480.00 24,000.00 480.00
L.008 Pekerja 0.1200 OH 27,000.00 3,240.00 27,000.00 3,240.00 24,500.00 2,940.00
L.002 Tukang Kayu 0.0600 OH 32,500.00 1,950.00 32,500.00 1,950.00 29,000.00 1,740.00
L.007 Kepala Tukang 0.0060 OH 35,000.00 210.00 35,000.00 210.00 31,500.00 189.00
L.010 Mandor 0.0060 OH 35,000.00 210.00 35,000.00 210.00 31,500.00 189.00
SNI - H.6.39 Pas. Atap Nok Seng M2 SNIH.6.39 14,975.00 SN2H.6.39 15,275.00 SNSH.6.39 14,306.00
M.010n Seng Plat 3" x 6 " BJLS 30 0.3000 Lbr 24,000.00 7,200.00 25,000.00 7,500.00 24,000.00 7,200.00
M.006c Paku Seng ( 1/2" - 1") 0.0400 Kg 24,000.00 960.00 24,000.00 960.00 24,000.00 960.00
L.008 Pekerja 0.1500 OH 27,000.00 4,050.00 27,000.00 4,050.00 24,500.00 3,675.00
L.002 Tukang Kayu 0.0700 OH 32,500.00 2,275.00 32,500.00 2,275.00 29,000.00 2,030.00
L.007 Kepala Tukang 0.0080 OH 35,000.00 280.00 35,000.00 280.00 31,500.00 252.00
L.010 Mandor 0.0060 OH 35,000.00 210.00 35,000.00 210.00 31,500.00 189.00
SNI - H.6.40 Pas. Talang Datar Seng BJLS 30 ( Kayu Meranti ) M' SNIH.6.40 74,118.75 SN2H.6.40 75,588.75 SNSH.6.40 72,251.88
M.010n Seng Plat 3" x 6 " BJLS 30 0.5000 Lbr 24,000.00 12,000.00 25,000.00 12,500.00 24,000.00 12,000.00
M.006c Paku Seng ( 1/2" - 1") 0.0150 Kg 24,000.00 360.00 24,000.00 360.00 24,000.00 360.00
M.005l Papan Meranti 0.0096 m3 4,275,000.00 41,040.00 4,350,000.00 41,760.00 4,275,000.00 41,040.00
M.011h Meni Besi 0.2500 Kg 11,000.00 2,750.00 12,000.00 3,000.00 11,000.00 2,750.00
L.008 Pekerja 0.1500 OH 27,000.00 4,050.00 27,000.00 4,050.00 24,500.00 3,675.00
L.002 Tukang Kayu 0.4000 OH 32,500.00 13,000.00 32,500.00 13,000.00 29,000.00 11,600.00
L.007 Kepala Tukang 0.0250 OH 35,000.00 875.00 35,000.00 875.00 31,500.00 787.50
L.010 Mandor 0.00125 OH 35,000.00 43.75 35,000.00 43.75 31,500.00 39.38
26 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
SNI - H.6.40a Pas. Talang Datar Seng BJLS 30 (Kayu Kruing) M' SNIH.6.40a 146,558.75 SN2H.6.40a 148,783.75 SNSH.6.40a 144,966.88
M.010n Seng Plat 3" x 6 " BJLS 30 0.5000 Lbr 24,000.00 12,000.00 25,000.00 12,500.00 24,000.00 12,000.00
M.006c Paku Seng ( 1/2" - 1") 0.0150 Kg 24,000.00 360.00 24,000.00 360.00 24,000.00 360.00
M.005m Papan Kruing 0.0190 m3 6,100,000.00 115,900.00 6,175,000.00 117,325.00 6,100,000.00 115,900.00
M.011h Meni Besi 0.3000 Kg 11,000.00 3,300.00 12,000.00 3,600.00 11,000.00 3,300.00
L.008 Pekerja 0.0400 OH 27,000.00 1,080.00 27,000.00 1,080.00 24,500.00 980.00
L.002 Tukang Kayu 0.4000 OH 32,500.00 13,000.00 32,500.00 13,000.00 29,000.00 11,600.00
L.007 Kepala Tukang 0.0250 OH 35,000.00 875.00 35,000.00 875.00 31,500.00 787.50
L.010 Mandor 0.00125 OH 35,000.00 43.75 35,000.00 43.75 31,500.00 39.38
SNI - H.6.41 Pas. Talang Miring Seng BJLS 30 ( Kayu Meranti ) M' SNIH.6.41 111,883.75 SN2H.6.41 114,108.75 SNSH.6.41 110,291.88
M.010n Seng Plat 3" x 6 " BJLS 30 0.5000 Lbr 24,000.00 12,000.00 25,000.00 12,500.00 24,000.00 12,000.00
M.006c Paku Seng ( 1/2" - 1") 0.0150 Kg 24,000.00 360.00 24,000.00 360.00 24,000.00 360.00
M.005l Papan Meranti 0.0190 m3 4,275,000.00 81,225.00 4,350,000.00 82,650.00 4,275,000.00 81,225.00
M.011h Meni Besi 0.3000 Kg 11,000.00 3,300.00 12,000.00 3,600.00 11,000.00 3,300.00
L.008 Pekerja 0.0400 OH 27,000.00 1,080.00 27,000.00 1,080.00 24,500.00 980.00
L.002 Tukang Kayu 0.4000 OH 32,500.00 13,000.00 32,500.00 13,000.00 29,000.00 11,600.00
L.007 Kepala Tukang 0.0250 OH 35,000.00 875.00 35,000.00 875.00 31,500.00 787.50
L.010 Mandor 0.0013 OH 35,000.00 43.75 35,000.00 43.75 31,500.00 39.38
SNI - H.6.41a Pas. Talang Miring Seng BJLS 30 ( Kayu Kruing ) M' SNIH.6.41a 146,558.75 SN2H.6.41a 148,783.75 SNSH.6.41a 144,966.88
M.010n Seng Plat 3" x 6 " BJLS 30 0.5000 Lbr 24,000.00 12,000.00 25,000.00 12,500.00 24,000.00 12,000.00
M.006c Paku Seng ( 1/2" - 1") 0.0150 Kg 24,000.00 360.00 24,000.00 360.00 24,000.00 360.00
M.005m Papan Kruing 0.0190 m3 6,100,000.00 115,900.00 6,175,000.00 117,325.00 6,100,000.00 115,900.00
M.011h Meni Besi 0.3000 Kg 11,000.00 3,300.00 12,000.00 3,600.00 11,000.00 3,300.00
L.008 Pekerja 0.0400 OH 27,000.00 1,080.00 27,000.00 1,080.00 24,500.00 980.00
L.002 Tukang Kayu 0.4000 OH 32,500.00 13,000.00 32,500.00 13,000.00 29,000.00 11,600.00
L.007 Kepala Tukang 0.0250 OH 35,000.00 875.00 35,000.00 875.00 31,500.00 787.50
L.010 Mandor 0.0013 OH 35,000.00 43.75 35,000.00 43.75 31,500.00 39.38
SNI - H.6.42 Pas. Aluminium Foil /Sisalation M2 SNIH.6.42 19,780.00 SN2H.6.42 20,305.00 SNSH.6.42 19,184.50
M.010u Aluminium Foil / Sisalation 1.0500 M2 13,000.00 13,650.00 13,500.00 14,175.00 13,000.00 13,650.00
L.008 Pekerja 0.1500 OH 27,000.00 4,050.00 27,000.00 4,050.00 24,500.00 3,675.00
L.002 Tukang Kayu 0.0500 OH 32,500.00 1,625.00 32,500.00 1,625.00 29,000.00 1,450.00
L.007 Kepala Tukang 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
L.010 Mandor 0.0080 OH 35,000.00 280.00 35,000.00 280.00 31,500.00 252.00
SNI - H.6.43 Pas. Kawat Burung ( Kayu Meranti ) M2 SNIH.6.43 29,849.50 SN2H.6.43 31,084.50 SNSH.6.43 29,212.75
M.008d Kawat Burung 1.1000 M2 14,000.00 15,400.00 15,000.00 16,500.00 14,000.00 15,400.00
M.006a Paku Eternit lis ( 1/2" - 1") 0.0200 Kg 21,850.00 437.00 21,850.00 437.00 21,850.00 437.00
M.005l Papan Meranti 0.0018 M3 4,275,000.00 7,695.00 4,350,000.00 7,830.00 4,275,000.00 7,695.00
L.008 Pekerja 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.002 Tukang Kayu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0005 OH 35,000.00 17.50 35,000.00 17.50 31,500.00 15.75
SNI - H.6.43a Pas. Kawat Burung ( Kayu Kruing ) M2 SNIH.6.43a 33,134.50 SN2H.6.43a 34,369.50 SNSH.6.43a 32,497.75
M.008d Kawat Burung 1.1000 M2 14,000.00 15,400.00 15,000.00 16,500.00 14,000.00 15,400.00
M.006a Paku Eternit lis ( 1/2" - 1") 0.0200 Kg 21,850.00 437.00 21,850.00 437.00 21,850.00 437.00
M.005m Papan Kruing 0.0018 M3 6,100,000.00 10,980.00 6,175,000.00 11,115.00 6,100,000.00 10,980.00
L.008 Pekerja 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.002 Tukang Kayu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0005 OH 35,000.00 17.50 35,000.00 17.50 31,500.00 15.75
I. PEKERJAAN LANGIT - LANGIT

SNI - I.6.19 Pas. Lis Langit-langit Kayu Propil ( Kayu Meranti ) M' SNII.6.19 9,523.50 SN2I.6.19 10,073.50 SNSI.6.19 9,195.50
M.005q Lis Kayu Propil 1.1000 M' 5,500.00 6,050.00 6,000.00 6,600.00 5,500.00 6,050.00
M.006a Paku Eternit, Lis 0.0100 Kg 21,850.00 218.50 21,850.00 218.50 21,850.00 218.50
L.008 Pekerja 0.0500 OH 27,000.00 1,350.00 27,000.00 1,350.00 24,500.00 1,225.00
L.002 Tukang Kayu 0.0500 OH 32,500.00 1,625.00 32,500.00 1,625.00 29,000.00 1,450.00
L.007 Kepala Tukang 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
L.010 Mandor 0.0030 OH 35,000.00 105.00 35,000.00 105.00 31,500.00 94.50
SNI - I.6.19a Pas. Lis Langit-langit Kayu ( Kayu Kruing ) M' SNII.6.19a 7,323.50 SN2I.6.19a 7,873.50 SNSI.6.19a 6,995.50
M.005r Lis Kayu 1.1000 M' 3,500.00 3,850.00 4,000.00 4,400.00 3,500.00 3,850.00
M.006a Paku Eternit, Lis 0.0100 Kg 21,850.00 218.50 21,850.00 218.50 21,850.00 218.50
L.008 Pekerja 0.0500 OH 27,000.00 1,350.00 27,000.00 1,350.00 24,500.00 1,225.00
L.002 Tukang Kayu 0.0500 OH 32,500.00 1,625.00 32,500.00 1,625.00 29,000.00 1,450.00
L.007 Kepala Tukang 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
L.010 Mandor 0.0030 OH 35,000.00 105.00 35,000.00 105.00 31,500.00 94.50
Pas. Langit-langit Eternit ( 1,00 x 1,00 ) m Rangka
SNI - I.6.20 M2 SNII.6.20 95,293.50 SN2I.6.20 96,413.50 SNSI.6.20 93,580.00
Kayu Kamper
M.005j Usuk Kamper 5/7 0.0120 M3 5,800,000.00 69,600.00 5,875,000.00 70,500.00 5,800,000.00 69,600.00
M.006 Paku Plafond 0.0600 Kg 18,000.00 1,080.00 18,000.00 1,080.00 18,000.00 1,080.00
M.006a Paku Eternit, Lis 0.0100 Kg 21,850.00 218.50 21,850.00 218.50 21,850.00 218.50
M.007 Eternit ( 1,00 x 1,00 ) m 1.1000 Lbr 7,000.00 7,700.00 7,200.00 7,920.00 7,000.00 7,700.00
L.008 Pekerja 0.1800 OH 27,000.00 4,860.00 27,000.00 4,860.00 24,500.00 4,410.00
L.002 Tukang Kayu 0.3200 OH 32,500.00 10,400.00 32,500.00 10,400.00 29,000.00 9,280.00
L.007 Kepala Tukang 0.0320 OH 35,000.00 1,120.00 35,000.00 1,120.00 31,500.00 1,008.00
L.010 Mandor 0.0090 OH 35,000.00 315.00 35,000.00 315.00 31,500.00 283.50
27 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
Pas. Langit-langit Eternit ( 1,00 x 1,00 ) m Rangka
SNI - I.6.20a M2 SNII.6.20a 103,693.50 SN2I.6.20a 104,813.50 SNSI.6.20a 101,980.00
Kayu Bangkir
M.005i Usuk Bangkir 5/7 0.0120 M3 6,500,000.00 78,000.00 6,575,000.00 78,900.00 6,500,000.00 78,000.00
M.006 Paku Plafond 0.0600 Kg 18,000.00 1,080.00 18,000.00 1,080.00 18,000.00 1,080.00
M.006a Paku Eternit, Lis 0.0100 Kg 21,850.00 218.50 21,850.00 218.50 21,850.00 218.50
M.007 Eternit ( 1,00 x 1,00 ) m 1.1000 Lbr 7,000.00 7,700.00 7,200.00 7,920.00 7,000.00 7,700.00
L.008 Pekerja 0.1800 OH 27,000.00 4,860.00 27,000.00 4,860.00 24,500.00 4,410.00
L.002 Tukang Kayu 0.3200 OH 32,500.00 10,400.00 32,500.00 10,400.00 29,000.00 9,280.00
L.007 Kepala Tukang 0.0320 OH 35,000.00 1,120.00 35,000.00 1,120.00 31,500.00 1,008.00
L.010 Mandor 0.0090 OH 35,000.00 315.00 35,000.00 315.00 31,500.00 283.50
Pas. Langit-langit Eternit ( 1,00 x 1,00 ) m Rangka
SNI - I.6.20b M2 SNII.6.20b 84,493.50 SN2I.6.20b 85,613.50 SNSI.6.20b 82,780.00
Kayu Kruing
M.005h Usuk Kruing 5/7 0.0120 M3 4,900,000.00 58,800.00 4,975,000.00 59,700.00 4,900,000.00 58,800.00
M.006 Paku Plafond 0.0600 Kg 18,000.00 1,080.00 18,000.00 1,080.00 18,000.00 1,080.00
M.006a Paku Eternit, Lis 0.0100 Kg 21,850.00 218.50 21,850.00 218.50 21,850.00 218.50
M.007 Eternit ( 1,00 x 1,00 ) m 1.1000 Lbr 7,000.00 7,700.00 7,200.00 7,920.00 7,000.00 7,700.00
L.008 Pekerja 0.1800 OH 27,000.00 4,860.00 27,000.00 4,860.00 24,500.00 4,410.00
L.002 Tukang Kayu 0.3200 OH 32,500.00 10,400.00 32,500.00 10,400.00 29,000.00 9,280.00
L.007 Kepala Tukang 0.0320 OH 35,000.00 1,120.00 35,000.00 1,120.00 31,500.00 1,008.00
L.010 Mandor 0.0090 OH 35,000.00 315.00 35,000.00 315.00 31,500.00 283.50
Pas. Langit-langit Eternit ( 1,00 x 1,00 ) m Rangka
SNI - I.6.20c M2 SNII.6.20c 72,178.50 SN2I.6.20c 73,298.50 SNSI.6.20c 70,496.50
Kayu Meranti
M.005g Usuk Meranti 5/7 0.0120 M3 3,900,000.00 46,800.00 3,975,000.00 47,700.00 3,900,000.00 46,800.00
M.006 Paku Plafond 0.0600 Kg 18,000.00 1,080.00 18,000.00 1,080.00 18,000.00 1,080.00
M.006a Paku Eternit, Lis 0.0100 Kg 21,850.00 218.50 21,850.00 218.50 21,850.00 218.50
M.007 Eternit ( 1,00 x 1,00 ) m 1.1000 Lbr 7,000.00 7,700.00 7,200.00 7,920.00 7,000.00 7,700.00
L.008 Pekerja 0.1800 OH 27,000.00 4,860.00 27,000.00 4,860.00 24,500.00 4,410.00
L.002 Tukang Kayu 0.3200 OH 32,500.00 10,400.00 32,500.00 10,400.00 29,000.00 9,280.00
L.007 Kepala Tukang 0.0320 OH 35,000.00 1,120.00 35,000.00 1,120.00 31,500.00 1,008.00
L.010 Mandor 0.0090 OH 35,000.00 315.00 35,000.00 315.00 31,500.00 283.50
Pas. Langit-langit Harplek 4 mm ( 1,00 x 1,00 ) m
SNI - I.6.20d M2 SNII.6.20d 102,933.50 SN2I.6.20d 104,383.50 SNSI.6.20d 101,220.00
Rangka Kayu Kruing
M.005c Kayu Kruing Balok 0.0120 M3 5,520,000.00 66,240.00 5,595,000.00 67,140.00 5,520,000.00 66,240.00
M.006 Paku Plafond 0.0600 Kg 18,000.00 1,080.00 18,000.00 1,080.00 18,000.00 1,080.00
M.006a Paku Eternit, Lis 0.0100 Kg 21,850.00 218.50 21,850.00 218.50 21,850.00 218.50
M.007a Harplek 4mm ( 1,00 x 1,00 ) m 1.1000 Lbr 17,000.00 18,700.00 17,500.00 19,250.00 17,000.00 18,700.00
L.008 Pekerja 0.1800 OH 27,000.00 4,860.00 27,000.00 4,860.00 24,500.00 4,410.00
L.002 Tukang Kayu 0.3200 OH 32,500.00 10,400.00 32,500.00 10,400.00 29,000.00 9,280.00
L.007 Kepala Tukang 0.0320 OH 35,000.00 1,120.00 35,000.00 1,120.00 31,500.00 1,008.00
L.010 Mandor 0.0090 OH 35,000.00 315.00 35,000.00 315.00 31,500.00 283.50
Pas. Langit-langit Harplek 4 mm ( 1,00 x 1,00 ) m
SNI - I.6.20e M2 SNII.6.20e 84,813.50 SN2I.6.20e 85,663.50 SNSI.6.20e 83,100.00
Rangka Kayu Meranti
M.005b Kayu Meranti Balok 0.0120 M3 4,010,000.00 48,120.00 4,035,000.00 48,420.00 4,010,000.00 48,120.00
M.006 Paku Plafond 0.0600 Kg 18,000.00 1,080.00 18,000.00 1,080.00 18,000.00 1,080.00
M.006a Paku Eternit, Lis 0.0100 Kg 21,850.00 218.50 21,850.00 218.50 21,850.00 218.50
M.007a Harplek 4mm ( 1,00 x 1,00 ) m 1.1000 Lbr 17,000.00 18,700.00 17,500.00 19,250.00 17,000.00 18,700.00
L.008 Pekerja 0.1800 OH 27,000.00 4,860.00 27,000.00 4,860.00 24,500.00 4,410.00
L.002 Tukang Kayu 0.3200 OH 32,500.00 10,400.00 32,500.00 10,400.00 29,000.00 9,280.00
L.007 Kepala Tukang 0.0320 OH 35,000.00 1,120.00 35,000.00 1,120.00 31,500.00 1,008.00
L.010 Mandor 0.0090 OH 35,000.00 315.00 35,000.00 315.00 31,500.00 283.50
SNI - I.6.24 Pas. Langit-langit Gypsum Board Tb. 9mm M2 SNII.6.24 27,927.00 SN2I.6.24 28,655.00 SNSI.6.24 27,467.00
M.007b Gypsum Board (120x240)cmx9mm 0.3640 Lbr 53,000.00 19,292.00 55,000.00 20,020.00 53,000.00 19,292.00
M.006h Paku Skrup 0.1100 Kg 36,000.00 3,960.00 36,000.00 3,960.00 36,000.00 3,960.00
L.008 Pekerja 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.002 Tukang Kayu 0.0500 OH 32,500.00 1,625.00 32,500.00 1,625.00 29,000.00 1,450.00
L.007 Kepala Tukang 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
J. PEKERJAAN SANITASI

SNI - J.6.1 Pasang Kloset Duduk / Monoblok BH SNIJ.6.1 1,614,485.00 SN2J.6.1 1,640,985.00 SNSJ.6.1 1,601,821.50
M.015 Kloset duduk / Monoblok 1.0000 Bh 1,400,000.00 1,400,000.00 1,425,000.00 1,425,000.00 1,400,000.00 1,400,000.00
- Perlengkapan 6% x hrg kloset 84,000.00 84,000.00 85,500.00 85,500.00 84,000.00 84,000.00
L.008 Pekerja 3.3000 OH 27,000.00 89,100.00 27,000.00 89,100.00 24,500.00 80,850.00
L.001 Tukang Batu 1.1000 OH 32,500.00 35,750.00 32,500.00 35,750.00 29,000.00 31,900.00
L.007 Kepala Tukang 0.0010 OH 35,000.00 35.00 35,000.00 35.00 31,500.00 31.50
L.010 Mandor 0.1600 OH 35,000.00 5,600.00 35,000.00 5,600.00 31,500.00 5,040.00
SNI - J.6.2 Pasang Kloset Jongkok Porselen BH SNIJ.6.2 299,900.00 SN2J.6.2 297,017.00 SNSJ.6.2 286,340.00
M.015a Kloset Jongkok Porselen 1.0000 Bh 158,000.00 158,000.00 155,000.00 155,000.00 158,000.00 158,000.00
M.002a Portland Cement 6.0000 Kg 1,200.00 7,200.00 1,207.00 7,242.00 1,200.00 7,200.00
M.001a Pasir Pasang 0.0100 M3 85,000.00 850.00 92,500.00 925.00 85,000.00 850.00
L.008 Pekerja 1.0000 OH 27,000.00 27,000.00 27,000.00 27,000.00 24,500.00 24,500.00
L.001 Tukang Batu 1.5000 OH 32,500.00 48,750.00 32,500.00 48,750.00 29,000.00 43,500.00
L.007 Kepala Tukang 1.5000 OH 35,000.00 52,500.00 35,000.00 52,500.00 31,500.00 47,250.00
L.010 Mandor 0.1600 OH 35,000.00 5,600.00 35,000.00 5,600.00 31,500.00 5,040.00
SNI - J.6.4 Pasang Urinoir BH SNIJ.6.4 594,550.00 SN2J.6.4 620,667.00 SNSJ.6.4 587,850.00
M.015b Urinoir 1.0000 Bh 400,000.00 400,000.00 420,000.00 420,000.00 400,000.00 400,000.00
- Perlengkapan 30% x hrg Urinoir 120,000.00 120,000.00 126,000.00 126,000.00 120,000.00 120,000.00
M.002a Portland Cement 6.0000 Kg 1,200.00 7,200.00 1,207.00 7,242.00 1,200.00 7,200.00
M.001a Pasir Pasang 0.0100 M3 85,000.00 850.00 92,500.00 925.00 85,000.00 850.00
L.008 Pekerja 1.0000 OH 27,000.00 27,000.00 27,000.00 27,000.00 24,500.00 24,500.00
L.001 Tukang Batu 1.0000 OH 32,500.00 32,500.00 32,500.00 32,500.00 29,000.00 29,000.00
L.007 Kepala Tukang 0.1000 OH 35,000.00 3,500.00 35,000.00 3,500.00 31,500.00 3,150.00
L.010 Mandor 0.1000 OH 35,000.00 3,500.00 35,000.00 3,500.00 31,500.00 3,150.00
28 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
SNI - J.6.5 Pasang Wastafel BH SNIJ.6.5 628,325.00 SN2J.6.5 634,042.00 SNSJ.6.5 619,375.00
M.015c Wastafel 1.0000 Bh 475,000.00 475,000.00 480,000.00 480,000.00 475,000.00 475,000.00
- Perlengkapan 12% x hrg Wastafel 57,000.00 57,000.00 57,600.00 57,600.00 57,000.00 57,000.00
M.002a Portland Cement 6.0000 Kg 1,200.00 7,200.00 1,207.00 7,242.00 1,200.00 7,200.00
M.001a Pasir Pasang 0.0100 M3 85,000.00 850.00 92,500.00 925.00 85,000.00 850.00
L.008 Pekerja 1.2000 OH 27,000.00 32,400.00 27,000.00 32,400.00 24,500.00 29,400.00
L.001 Tukang Batu 1.4500 OH 32,500.00 47,125.00 32,500.00 47,125.00 29,000.00 42,050.00
L.007 Kepala Tukang 0.1500 OH 35,000.00 5,250.00 35,000.00 5,250.00 31,500.00 4,725.00
L.010 Mandor 0.1000 OH 35,000.00 3,500.00 35,000.00 3,500.00 31,500.00 3,150.00
SNI - J.6.7 Pasang Bak Mandi Fiber Glass Vol. 0,30 m3 BH SNIJ.6.7 365,600.00 SN2J.6.7 344,360.00 SNSJ.6.7 349,375.00
M.015d Bk Fiberglass 1.0000 Bh 175,000.00 175,000.00 157,000.00 157,000.00 175,000.00 175,000.00
- Perlengkapan 18% x hrg Bak Fg 31,500.00 31,500.00 28,260.00 28,260.00 31,500.00 31,500.00
L.008 Pekerja 1.8000 OH 27,000.00 48,600.00 27,000.00 48,600.00 24,500.00 44,100.00
L.001 Tukang Batu 2.7000 OH 32,500.00 87,750.00 32,500.00 87,750.00 29,000.00 78,300.00
L.007 Kepala Tukang 0.5400 OH 35,000.00 18,900.00 35,000.00 18,900.00 31,500.00 17,010.00
L.010 Mandor 0.1100 OH 35,000.00 3,850.00 35,000.00 3,850.00 31,500.00 3,465.00
SNI - J.6.8 Pasang Bak Mandi Batu Bata Vol. 0,30 m3 BH SNIJ.6.8 741,600.00 SN2J.6.8 760,690.00 SNSJ.6.8 714,000.00
M.001m Batu Bata 0.4000 M3 216,000.00 86,400.00 228,000.00 91,200.00 216,000.00 86,400.00
M.002a Portland Cement 120.00 Kg 1,200.00 144,000.00 1,207.00 144,840.00 1,200.00 144,000.00
M.001a Pasir Pasang 0.3000 M3 85,000.00 25,500.00 92,500.00 27,750.00 85,000.00 25,500.00
M.004a Keramik 20/20 cm 109 Bh 1,800.00 196,200.00 1,900.00 207,100.00 1,800.00 196,200.00
M.002b PC Warna / Nat 6.0000 Kg 1,500.00 9,000.00 1,550.00 9,300.00 1,500.00 9,000.00
L.008 Pekerja 6.0000 OH 27,000.00 162,000.00 27,000.00 162,000.00 24,500.00 147,000.00
L.001 Tukang Batu 3.0000 OH 32,500.00 97,500.00 32,500.00 97,500.00 29,000.00 87,000.00
L.007 Kepala Tukang 0.3000 OH 35,000.00 10,500.00 35,000.00 10,500.00 31,500.00 9,450.00
L.010 Mandor 0.3000 OH 35,000.00 10,500.00 35,000.00 10,500.00 31,500.00 9,450.00
SNI - J.6.9 Pasang Bath Tub Porselen BH SNIJ.6.9 4,670,637.50 SN2J.6.9 4,837,437.50 SNSJ.6.9 4,666,875.00
M.015e Bath tubh 1.0000 Bh 3,861,000.00 3,861,000.00 4,000,000.00 4,000,000.00 3,861,000.00 3,861,000.00
- Perlengkapan 20% x hrg B.tubh 772,200.00 772,200.00 800,000.00 800,000.00 772,200.00 772,200.00
L.001 Tukang Batu 0.0750 OH 32,500.00 2,437.50 32,500.00 2,437.50 29,000.00 2,175.00
L.007 Kepala Tukang 0.7500 OH 35,000.00 26,250.00 35,000.00 26,250.00 31,500.00 23,625.00
L.010 Mandor 0.2500 OH 35,000.00 8,750.00 35,000.00 8,750.00 31,500.00 7,875.00
SNI - J.6.11 Pasang Bak Fiber glass vol. 1 m3 air BH SNIJ.6.11 1,181,770.00 SN2J.6.11 908,490.00 SNSJ.6.11 1,152,220.00
M.015d.1 Bak Fiber glass 1.0000 Bh 796,000.00 796,000.00 552,000.00 552,000.00 796,000.00 796,000.00
- Perlengkapan 12% x hrg Bak Fg 95,520.00 95,520.00 66,240.00 66,240.00 95,520.00 95,520.00
L.008 Pekerja 3.0000 OH 27,000.00 81,000.00 27,000.00 81,000.00 24,500.00 73,500.00
L.001 Tukang Batu 4.5000 OH 32,500.00 146,250.00 32,500.00 146,250.00 29,000.00 130,500.00
L.007 Kepala Tukang 0.9000 OH 35,000.00 31,500.00 35,000.00 31,500.00 31,500.00 28,350.00
L.010 Mandor 0.9000 OH 35,000.00 31,500.00 35,000.00 31,500.00 31,500.00 28,350.00
Pasang Bak Kontrol Pasang Batu Bata Uk. (30x30)
SNI - J.6.16 BH SNIJ.6.16 242,420.00 SN2J.6.16 247,743.00 SNSJ.6.16 230,806.25
cm tinggi 35 cm
M.001m Batu Bata 0.1450 M3 216,000.00 31,320.00 228,000.00 33,060.00 216,000.00 31,320.00
M.002a Portland Cement 44.00 Kg 1,200.00 52,800.00 1,207.00 53,108.00 1,200.00 52,800.00
M.001a Pasir Pasang 0.0700 M3 85,000.00 5,950.00 92,500.00 6,475.00 85,000.00 5,950.00
M.001n Batu Kerikil 0.0700 M3 40,000.00 2,800.00 50,000.00 3,500.00 40,000.00 2,800.00
M.003 Besi Beton 1.6000 Kg 15,000.00 24,000.00 16,000.00 25,600.00 15,000.00 24,000.00
M.001 Pasir Beton 0.0600 M3 92,500.00 5,550.00 100,000.00 6,000.00 92,500.00 5,550.00
L.008 Pekerja 3.2000 OH 27,000.00 86,400.00 27,000.00 86,400.00 24,500.00 78,400.00
L.001 Tukang Batu 1.0150 OH 32,500.00 32,987.50 32,500.00 32,987.50 29,000.00 29,435.00
L.007 Kepala Tukang 0.0015 OH 35,000.00 52.50 35,000.00 52.50 31,500.00 47.25
L.010 Mandor 0.0160 OH 35,000.00 560.00 35,000.00 560.00 31,500.00 504.00
Pasang Bak Kontrol Pasang Batu Bata Uk. (45x45)
SNI - J.6.17 BH SNIJ.6.17 263,417.50 SN2J.6.17 271,406.50 SNSJ.6.17 257,799.00
cm tinggi 50 cm
M.001m Batu Bata 0.2500 M3 216,000.00 54,000.00 228,000.00 57,000.00 216,000.00 54,000.00
M.002a Portland Cement 77.00 Kg 1,200.00 92,400.00 1,207.00 92,939.00 1,200.00 92,400.00
M.001a Pasir Pasang 0.1300 M3 85,000.00 11,050.00 92,500.00 12,025.00 85,000.00 11,050.00
M.001n Batu Kerikil 0.0200 M3 40,000.00 800.00 50,000.00 1,000.00 40,000.00 800.00
M.003 Besi Beton 2.6000 Kg 15,000.00 39,000.00 16,000.00 41,600.00 15,000.00 39,000.00
M.001 Pasir Beton 0.0900 M3 92,500.00 8,325.00 100,000.00 9,000.00 92,500.00 8,325.00
L.008 Pekerja 1.4200 OH 27,000.00 38,340.00 27,000.00 38,340.00 24,500.00 34,790.00
L.001 Tukang Batu 0.4730 OH 32,500.00 15,372.50 32,500.00 15,372.50 29,000.00 13,717.00
L.007 Kepala Tukang 0.0470 OH 35,000.00 1,645.00 35,000.00 1,645.00 31,500.00 1,480.50
L.010 Mandor 0.0710 OH 35,000.00 2,485.00 35,000.00 2,485.00 31,500.00 2,236.50
Pasang Bak Kontrol Pasang Batu Bata Uk. (60x60)
SNI - J.6.18 BH SNIJ.6.18 408,466.00 SN2J.6.18 421,176.00 SNSJ.6.18 399,666.00
cm tinggi 65 cm
M.001m Batu Bata 0.3710 M3 216,000.00 80,136.00 228,000.00 84,588.00 216,000.00 80,136.00
M.002a Portland Cement 114.00 Kg 1,200.00 136,800.00 1,207.00 137,598.00 1,200.00 136,800.00
M.001a Pasir Pasang 0.1840 M3 85,000.00 15,640.00 92,500.00 17,020.00 85,000.00 15,640.00
M.001n Batu Kerikil 0.0330 M3 40,000.00 1,320.00 50,000.00 1,650.00 40,000.00 1,320.00
M.003 Besi Beton 4.8500 Kg 15,000.00 72,750.00 16,000.00 77,600.00 15,000.00 72,750.00
M.001 Pasir Beton 0.1200 M3 92,500.00 11,100.00 100,000.00 12,000.00 92,500.00 11,100.00
L.009 Tukang Gali 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.008 Pekerja 2.1600 OH 27,000.00 58,320.00 27,000.00 58,320.00 24,500.00 52,920.00
L.001 Tukang Batu 0.7200 OH 32,500.00 23,400.00 32,500.00 23,400.00 29,000.00 20,880.00
L.007 Kepala Tukang 0.0720 OH 35,000.00 2,520.00 35,000.00 2,520.00 31,500.00 2,268.00
L.010 Mandor 0.1080 OH 35,000.00 3,780.00 35,000.00 3,780.00 31,500.00 3,402.00
SNI - J.6.19 Pasang Pipa Galvanis dia 1/2" med. B M' SNIJ.6.19 32,768.00 SN2J.6.19 33,543.00 SNSJ.6.19 32,192.00
M.016 Pipa Galvanis 1/2" med. B 1.2000 M' 17,500.00 21,000.00 18,000.00 21,600.00 17,500.00 21,000.00
- Perlengkapan 35% x hrg pipa 6,125.00 6,125.00 6,300.00 6,300.00 6,125.00 6,125.00
L.008 Pekerja 0.0540 OH 27,000.00 1,458.00 27,000.00 1,458.00 24,500.00 1,323.00
L.001 Tukang Batu 0.0900 OH 32,500.00 2,925.00 32,500.00 2,925.00 29,000.00 2,610.00
L.007 Kepala Tukang 0.0090 OH 35,000.00 315.00 35,000.00 315.00 31,500.00 283.50
L.010 Mandor 0.0270 OH 35,000.00 945.00 35,000.00 945.00 31,500.00 850.50
29 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
SNI - J.6.20 Pasang Pipa Galvanis dia 3/4" med. B M' SNIJ.6.20 42,068.00 SN2J.6.20 42,843.00 SNSJ.6.20 41,492.00
M.016a Pipa Galvanis 3/4" med. B 1.2000 M' 23,500.00 28,200.00 24,000.00 28,800.00 23,500.00 28,200.00
- Perlengkapan 35% x hrg pipa 8,225.00 8,225.00 8,400.00 8,400.00 8,225.00 8,225.00
L.008 Pekerja 0.0540 OH 27,000.00 1,458.00 27,000.00 1,458.00 24,500.00 1,323.00
L.001 Tukang Batu 0.0900 OH 32,500.00 2,925.00 32,500.00 2,925.00 29,000.00 2,610.00
L.007 Kepala Tukang 0.0090 OH 35,000.00 315.00 35,000.00 315.00 31,500.00 283.50
L.010 Mandor 0.0270 OH 35,000.00 945.00 35,000.00 945.00 31,500.00 850.50
SNI - J.6.21 Pasang Pipa Galvanis dia 1" med. B M' SNIJ.6.21 52,918.00 SN2J.6.21 53,693.00 SNSJ.6.21 52,342.00
M.016b Pipa Galvanis 1" med. B 1.2000 M' 30,500.00 36,600.00 31,000.00 37,200.00 30,500.00 36,600.00
- Perlengkapan 35% x hrg pipa 10,675.00 10,675.00 10,850.00 10,850.00 10,675.00 10,675.00
L.008 Pekerja 0.0540 OH 27,000.00 1,458.00 27,000.00 1,458.00 24,500.00 1,323.00
L.001 Tukang Batu 0.0900 OH 32,500.00 2,925.00 32,500.00 2,925.00 29,000.00 2,610.00
L.007 Kepala Tukang 0.0090 OH 35,000.00 315.00 35,000.00 315.00 31,500.00 283.50
L.010 Mandor 0.0270 OH 35,000.00 945.00 35,000.00 945.00 31,500.00 850.50
SNI - J.6.22 Pasang Pipa Galvanis dia 1 1/2" med. B M' SNIJ.6.22 76,235.00 SN2J.6.22 77,010.00 SNSJ.6.22 75,253.10
M.016c Pipa Galvanis 1 1/2" med. B 1.2000 M' 43,000.00 51,600.00 43,500.00 52,200.00 43,000.00 51,600.00
- Perlengkapan 35% x hrg pipa 15,050.00 15,050.00 15,225.00 15,225.00 15,050.00 15,050.00
L.008 Pekerja 0.1080 OH 27,000.00 2,916.00 27,000.00 2,916.00 24,500.00 2,646.00
L.001 Tukang Batu 0.1800 OH 32,500.00 5,850.00 32,500.00 5,850.00 29,000.00 5,220.00
L.007 Kepala Tukang 0.0180 OH 35,000.00 630.00 35,000.00 630.00 31,500.00 567.00
L.010 Mandor 0.0054 OH 35,000.00 189.00 35,000.00 189.00 31,500.00 170.10
SNI - J.6.22a Pasang Pipa Galvanis dia. 2" med. B M' SNIJ.6.22a 93,285.00 SN2J.6.22a 94,060.00 SNSJ.6.22a 92,303.10
M.016d Pipa Galvanis 2" med. B 1.2000 M' 54,000.00 64,800.00 54,500.00 65,400.00 54,000.00 64,800.00
- Perlengkapan 35% x hrg pipa 18,900.00 18,900.00 19,075.00 19,075.00 18,900.00 18,900.00
L.008 Pekerja 0.1080 OH 27,000.00 2,916.00 27,000.00 2,916.00 24,500.00 2,646.00
L.001 Tukang Batu 0.1800 OH 32,500.00 5,850.00 32,500.00 5,850.00 29,000.00 5,220.00
L.007 Kepala Tukang 0.0180 OH 35,000.00 630.00 35,000.00 630.00 31,500.00 567.00
L.010 Mandor 0.0054 OH 35,000.00 189.00 35,000.00 189.00 31,500.00 170.10
SNI - J.6.23 Pasang Pipa Galvanis dia. 3" med. B M' SNIJ.6.23 159,160.00 SN2J.6.23 159,935.00 SNSJ.6.23 158,178.10
M.016e Pipa Galvanis 3" med. B 1.2000 M' 96,500.00 115,800.00 97,000.00 116,400.00 96,500.00 115,800.00
- Perlengkapan 35% x hrg pipa 33,775.00 33,775.00 33,950.00 33,950.00 33,775.00 33,775.00
L.008 Pekerja 0.1080 OH 27,000.00 2,916.00 27,000.00 2,916.00 24,500.00 2,646.00
L.001 Tukang Batu 0.1800 OH 32,500.00 5,850.00 32,500.00 5,850.00 29,000.00 5,220.00
L.007 Kepala Tukang 0.0180 OH 35,000.00 630.00 35,000.00 630.00 31,500.00 567.00
L.010 Mandor 0.0054 OH 35,000.00 189.00 35,000.00 189.00 31,500.00 170.10
SNI - J.6.24 Pasang Pipa Galvanis dia 4" med. B M' SNIJ.6.24 214,258.00 SN2J.6.24 215,033.00 SNSJ.6.24 213,030.45
M.016f Pipa Galvanis 4" med. B 1.2000 M' 130,500.00 156,600.00 131,000.00 157,200.00 130,500.00 156,600.00
- Perlengkapan 35% x hrg pipa 45,675.00 45,675.00 45,850.00 45,850.00 45,675.00 45,675.00
L.008 Pekerja 0.1350 OH 27,000.00 3,645.00 27,000.00 3,645.00 24,500.00 3,307.50
L.001 Tukang Batu 0.2250 OH 32,500.00 7,312.50 32,500.00 7,312.50 29,000.00 6,525.00
L.007 Kepala Tukang 0.0225 OH 35,000.00 787.50 35,000.00 787.50 31,500.00 708.75
L.010 Mandor 0.0068 OH 35,000.00 238.00 35,000.00 238.00 31,500.00 214.20
SNI - J.6.25 Pasang Pipa PVC diameter 1/2" type AW M' SNIJ.6.25 9,395.00 SN2J.6.25 10,170.00 SNSJ.6.25 9,067.70
M.016g Pipa PVC 1/2" 1.2000 M' 4,000.00 4,800.00 4,500.00 5,400.00 4,000.00 4,800.00
- Perlengkapan 35% x hrg pipa 1,400.00 1,400.00 1,575.00 1,575.00 1,400.00 1,400.00
L.008 Pekerja 0.0360 OH 27,000.00 972.00 27,000.00 972.00 24,500.00 882.00
L.001 Tukang Batu 0.0600 OH 32,500.00 1,950.00 32,500.00 1,950.00 29,000.00 1,740.00
L.007 Kepala Tukang 0.0060 OH 35,000.00 210.00 35,000.00 210.00 31,500.00 189.00
L.010 Mandor 0.0018 OH 35,000.00 63.00 35,000.00 63.00 31,500.00 56.70
SNI - J.6.26 Pasang Pipa PVC diameter 3/4" type AW M' SNIJ.6.26 11,642.50 SN2J.6.26 12,417.50 SNSJ.6.26 11,315.20
M.016h Pipa PVC diam. 3/4" 1.2000 M' 5,450.00 6,540.00 5,950.00 7,140.00 5,450.00 6,540.00
- Perlengkapan 35% x hrg pipa 1,907.50 1,907.50 2,082.50 2,082.50 1,907.50 1,907.50
L.008 Pekerja 0.0360 OH 27,000.00 972.00 27,000.00 972.00 24,500.00 882.00
L.001 Tukang Batu 0.0600 OH 32,500.00 1,950.00 32,500.00 1,950.00 29,000.00 1,740.00
L.007 Kepala Tukang 0.0060 OH 35,000.00 210.00 35,000.00 210.00 31,500.00 189.00
L.010 Mandor 0.0018 OH 35,000.00 63.00 35,000.00 63.00 31,500.00 56.70
SNI - J.6.27 Pasang Pipa PVC diameter 1" type AW M' SNIJ.6.27 14,045.00 SN2J.6.27 14,820.00 SNSJ.6.27 13,717.70
M.016i Pipa PVC diam. 1" 1.2000 M' 7,000.00 8,400.00 7,500.00 9,000.00 7,000.00 8,400.00
- Perlengkapan 35% x hrg pipa 2,450.00 2,450.00 2,625.00 2,625.00 2,450.00 2,450.00
L.008 Pekerja 0.0360 OH 27,000.00 972.00 27,000.00 972.00 24,500.00 882.00
L.001 Tukang Batu 0.0600 OH 32,500.00 1,950.00 32,500.00 1,950.00 29,000.00 1,740.00
L.007 Kepala Tukang 0.0060 OH 35,000.00 210.00 35,000.00 210.00 31,500.00 189.00
L.010 Mandor 0.0018 OH 35,000.00 63.00 35,000.00 63.00 31,500.00 56.70
SNI - J.6.28 Pasang Pipa PVC diameter 1 1/2" type AW M' SNIJ.6.28 19,935.00 SN2J.6.28 21,020.00 SNSJ.6.28 19,607.70
M.016j Pipa PVC diam. 1 1/2" 1.2000 M' 10,800.00 12,960.00 11,500.00 13,800.00 10,800.00 12,960.00
- Perlengkapan 35% x hrg pipa 3,780.00 3,780.00 4,025.00 4,025.00 3,780.00 3,780.00
L.008 Pekerja 0.0360 OH 27,000.00 972.00 27,000.00 972.00 24,500.00 882.00
L.001 Tukang Batu 0.0600 OH 32,500.00 1,950.00 32,500.00 1,950.00 29,000.00 1,740.00
L.007 Kepala Tukang 0.0060 OH 35,000.00 210.00 35,000.00 210.00 31,500.00 189.00
L.010 Mandor 0.0018 OH 35,000.00 63.00 35,000.00 63.00 31,500.00 56.70
30 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
SNI - J.6.29 Pasang Pipa PVC diameter 2" type AW M' SNIJ.6.29 26,260.00 SN2J.6.29 26,492.50 SNSJ.6.29 25,769.05
M.016k Pipa PVC diam. 2" 1.2000 M' 13,850.00 16,620.00 14,000.00 16,800.00 13,850.00 16,620.00
- Perlengkapan 35% x hrg pipa 4,847.50 4,847.50 4,900.00 4,900.00 4,847.50 4,847.50
L.008 Pekerja 0.0540 OH 27,000.00 1,458.00 27,000.00 1,458.00 24,500.00 1,323.00
L.001 Tukang Batu 0.0900 OH 32,500.00 2,925.00 32,500.00 2,925.00 29,000.00 2,610.00
L.007 Kepala Tukang 0.0090 OH 35,000.00 315.00 35,000.00 315.00 31,500.00 283.50
L.010 Mandor 0.0027 OH 35,000.00 94.50 35,000.00 94.50 31,500.00 85.05
SNI - J.6.31 Pasang Pipa PVC diameter 3" type AW M' SNIJ.6.31 47,030.00 SN2J.6.31 48,192.50 SNSJ.6.31 46,539.05
M.016l Pipa PVC diam. 3" 1.2000 M' 27,250.00 32,700.00 28,000.00 33,600.00 27,250.00 32,700.00
- Perlengkapan 35% x hrg pipa 9,537.50 9,537.50 9,800.00 9,800.00 9,537.50 9,537.50
L.008 Pekerja 0.0540 OH 27,000.00 1,458.00 27,000.00 1,458.00 24,500.00 1,323.00
L.001 Tukang Batu 0.0900 OH 32,500.00 2,925.00 32,500.00 2,925.00 29,000.00 2,610.00
L.007 Kepala Tukang 0.0090 OH 35,000.00 315.00 35,000.00 315.00 31,500.00 283.50
L.010 Mandor 0.0027 OH 35,000.00 94.50 35,000.00 94.50 31,500.00 85.05
SNI - J.6.32 Memasang 1 m' Pipa PVC diameter 4" type AW M' SNIJ.6.32 76,940.50 SN2J.6.32 78,490.50 SNSJ.6.32 76,203.90
M.016m Pipa PVC diam. 4" 1.2000 M' 45,000.00 54,000.00 46,000.00 55,200.00 45,000.00 54,000.00
- Perlengkapan 35% x hrg pipa 15,750.00 15,750.00 16,100.00 16,100.00 15,750.00 15,750.00
L.008 Pekerja 0.0810 OH 27,000.00 2,187.00 27,000.00 2,187.00 24,500.00 1,984.50
L.001 Tukang Batu 0.1350 OH 32,500.00 4,387.50 32,500.00 4,387.50 29,000.00 3,915.00
L.007 Kepala Tukang 0.0135 OH 35,000.00 472.50 35,000.00 472.50 31,500.00 425.25
L.010 Mandor 0.0041 OH 35,000.00 143.50 35,000.00 143.50 31,500.00 129.15
SNI - J.6.33 Memasang 1 Buah Bak Cuci Piring Stainless Steel BH SNIJ.6.33 264,662.50 SN2J.6.33 255,662.50 SNSJ.6.33 263,427.25
M.015f Bak Cuci piring Stainless stell 1.0000 Bh 224,000.00 224,000.00 215,000.00 215,000.00 224,000.00 224,000.00
M.015g Water drain + Asesories 1.0000 Set 29,000.00 29,000.00 29,000.00 29,000.00 29,000.00 29,000.00
L.008 Pekerja 0.0300 OH 27,000.00 810.00 27,000.00 810.00 24,500.00 735.00
L.001 Tukang Batu 0.3000 OH 32,500.00 9,750.00 32,500.00 9,750.00 29,000.00 8,700.00
L.007 Kepala Tukang 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
L.010 Mandor 0.0015 OH 35,000.00 52.50 35,000.00 52.50 31,500.00 47.25
SNI - J.6.35 Memasang 1 Buah Kran diameter 3/4" BH SNIJ.6.35 39,107.50 SN2J.6.35 39,107.50 SNSJ.6.35 38,680.00
M.015h Kran air 3/4" 1.0000 Bh 35,000.00 35,000.00 35,000.00 35,000.00 35,000.00 35,000.00
M.015i Seal tape 0.0250 Bh 2,500.00 62.50 2,500.00 62.50 2,500.00 62.50
L.008 Pekerja 0.0100 OH 27,000.00 270.00 27,000.00 270.00 24,500.00 245.00
L.001 Tukang Batu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
SNI - J.6.35a Memasang 1 Buah Kran diameter 1/2" BH SNIJ.6.35a 19,107.50 SN2J.6.35a 19,107.50 SNSJ.6.35a 18,680.00
M.015h.1 Kran air 1/2" 1.0000 Bh 15,000.00 15,000.00 15,000.00 15,000.00 15,000.00 15,000.00
M.015i Seal tape 0.0250 Bh 2,500.00 62.50 2,500.00 62.50 2,500.00 62.50
L.008 Pekerja 0.0100 OH 27,000.00 270.00 27,000.00 270.00 24,500.00 245.00
L.001 Tukang Batu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
SNI - J.6.36 Memasang 1 Buah Floor Drain BH SNIJ.6.36 24,045.00 SN2J.6.36 24,045.00 SNSJ.6.36 23,617.50
M.015j Floor Drain 1.0000 Bh 20,000.00 20,000.00 20,000.00 20,000.00 20,000.00 20,000.00
L.008 Pekerja 0.0100 OH 27,000.00 270.00 27,000.00 270.00 24,500.00 245.00
L.001 Tukang Batu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
K. PEKERJAAN KUNCI DAN KACA

SNI - K.6.1 Pasang Kunci Tanam Antik BH SNIK.6.1 323,325.00 SN2K.6.1 323,325.00 SNSK.6.1 320,854.50
M.014 Kunci Tanam Antik 1.0000 Bh 300,000.00 300,000.00 300,000.00 300,000.00 300,000.00 300,000.00
L.008 Pekerja 0.0600 OH 27,000.00 1,620.00 27,000.00 1,620.00 24,500.00 1,470.00
L.002 Tukang Kayu 0.6000 OH 32,500.00 19,500.00 32,500.00 19,500.00 29,000.00 17,400.00
L.007 Kepala Tukang 0.0600 OH 35,000.00 2,100.00 35,000.00 2,100.00 31,500.00 1,890.00
L.010 Mandor 0.0030 OH 35,000.00 105.00 35,000.00 105.00 31,500.00 94.50
SNI - K.6.2 Pasang Kunci Tanam Biasa BH SNIK.6.2 107,045.00 SN2K.6.2 102,045.00 SNSK.6.2 105,217.50
M.014a Kunci Tanam Biasa 1.0000 Bh 90,000.00 90,000.00 85,000.00 85,000.00 90,000.00 90,000.00
L.008 Pekerja 0.0100 OH 27,000.00 270.00 27,000.00 270.00 24,500.00 245.00
L.002 Tukang Kayu 0.5000 OH 32,500.00 16,250.00 32,500.00 16,250.00 29,000.00 14,500.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
SNI - K.6.3 Pasang Kunci Tanam Kamar Mandi BH SNIK.6.3 52,045.00 SN2K.6.3 49,045.00 SNSK.6.3 50,217.50
M.014b Kunci Tanam Kamar Mandi 1.0000 Bh 35,000.00 35,000.00 32,000.00 32,000.00 35,000.00 35,000.00
L.008 Pekerja 0.0100 OH 27,000.00 270.00 27,000.00 270.00 24,500.00 245.00
L.002 Tukang Kayu 0.5000 OH 32,500.00 16,250.00 32,500.00 16,250.00 29,000.00 14,500.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
SNI - K.6.5 Pasang Engsel Pintu BH SNIK.6.5 13,331.25 SN2K.6.5 13,331.25 SNSK.6.5 12,713.63
M.014c Engsel pintu 1.0000 Bh 7,500.00 7,500.00 7,500.00 7,500.00 7,500.00 7,500.00
L.008 Pekerja 0.0150 OH 27,000.00 405.00 27,000.00 405.00 24,500.00 367.50
L.002 Tukang Kayu 0.1500 OH 32,500.00 4,875.00 32,500.00 4,875.00 29,000.00 4,350.00
L.007 Kepala Tukang 0.0150 OH 35,000.00 525.00 35,000.00 525.00 31,500.00 472.50
L.010 Mandor 0.00075 OH 35,000.00 26.25 35,000.00 26.25 31,500.00 23.63
31 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
SNI - K.6.6 Pasang Engsel Jendela Kupu-kupu BH SNIK.6.6 10,831.25 SN2K.6.6 10,831.25 SNSK.6.6 10,213.63
M.014d Engsel Jendela kupu-kupu 1.0000 Bh 5,000.00 5,000.00 5,000.00 5,000.00 5,000.00 5,000.00
L.008 Pekerja 0.0150 OH 27,000.00 405.00 27,000.00 405.00 24,500.00 367.50
L.002 Tukang Kayu 0.1500 OH 32,500.00 4,875.00 32,500.00 4,875.00 29,000.00 4,350.00
L.007 Kepala Tukang 0.0150 OH 35,000.00 525.00 35,000.00 525.00 31,500.00 472.50
L.010 Mandor 0.00075 OH 35,000.00 26.25 35,000.00 26.25 31,500.00 23.63
SNI - K.6.7 Pasang Engsel Angin BH SNIK.6.7 28,090.00 SN2K.6.7 28,090.00 SNSK.6.7 27,235.00
M.014e Engsel angin 1.0000 Bh 20,000.00 20,000.00 20,000.00 20,000.00 20,000.00 20,000.00
L.008 Pekerja 0.0200 OH 27,000.00 540.00 27,000.00 540.00 24,500.00 490.00
L.002 Tukang Kayu 0.2000 OH 32,500.00 6,500.00 32,500.00 6,500.00 29,000.00 5,800.00
L.007 Kepala Tukang 0.0200 OH 35,000.00 700.00 35,000.00 700.00 31,500.00 630.00
L.010 Mandor 0.01000 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
SNI - K.6.9 Pasang Kait Angin model lipat BH SNIK.6.9 10,831.25 SN2K.6.9 10,831.25 SNSK.6.9 10,213.63
M.014f Kait Angin model lipat 1.0000 Bh 5,000.00 5,000.00 5,000.00 5,000.00 5,000.00 5,000.00
L.008 Pekerja 0.0150 OH 27,000.00 405.00 27,000.00 405.00 24,500.00 367.50
L.002 Tukang Kayu 0.1500 OH 32,500.00 4,875.00 32,500.00 4,875.00 29,000.00 4,350.00
L.007 Kepala Tukang 0.0150 OH 35,000.00 525.00 35,000.00 525.00 31,500.00 472.50
L.010 Mandor 0.00075 OH 35,000.00 26.25 35,000.00 26.25 31,500.00 23.63
SNI - K.6.9a Pasang Kait Angin model antik BH SNIK.6.9a 22,331.25 SN2K.6.9a 22,331.25 SNSK.6.9a 21,713.63
M.014f.1 Kait Angin model antik 1.0000 Bh 16,500.00 16,500.00 16,500.00 16,500.00 16,500.00 16,500.00
L.008 Pekerja 0.0150 OH 27,000.00 405.00 27,000.00 405.00 24,500.00 367.50
L.002 Tukang Kayu 0.1500 OH 32,500.00 4,875.00 32,500.00 4,875.00 29,000.00 4,350.00
L.007 Kepala Tukang 0.0150 OH 35,000.00 525.00 35,000.00 525.00 31,500.00 472.50
L.010 Mandor 0.00075 OH 35,000.00 26.25 35,000.00 26.25 31,500.00 23.63
SNI - K.6.10 Pasang Door Closer BH SNIK.6.10 219,437.50 SN2K.6.10 219,437.50 SNSK.6.10 217,378.75
M.014g Door Closer 1.0000 Bh 200,000.00 200,000.00 200,000.00 200,000.00 200,000.00 200,000.00
L.008 Pekerja 0.0500 OH 27,000.00 1,350.00 27,000.00 1,350.00 24,500.00 1,225.00
L.002 Tukang Kayu 0.5000 OH 32,500.00 16,250.00 32,500.00 16,250.00 29,000.00 14,500.00
L.007 Kepala Tukang 0.0500 OH 35,000.00 1,750.00 35,000.00 1,750.00 31,500.00 1,575.00
L.010 Mandor 0.00250 OH 35,000.00 87.50 35,000.00 87.50 31,500.00 78.75
SNI - K.6.11 Pasang Kunci Slot BH SNIK.6.11 92,775.00 SN2K.6.11 92,775.00 SNSK.6.11 91,951.50
M.014h Kunci Slot 1.0000 Bh 85,000.00 85,000.00 85,000.00 85,000.00 85,000.00 85,000.00
L.008 Pekerja 0.0200 OH 27,000.00 540.00 27,000.00 540.00 24,500.00 490.00
L.002 Tukang Kayu 0.2000 OH 32,500.00 6,500.00 32,500.00 6,500.00 29,000.00 5,800.00
L.007 Kepala Tukang 0.0200 OH 35,000.00 700.00 35,000.00 700.00 31,500.00 630.00
L.010 Mandor 0.00100 OH 35,000.00 35.00 35,000.00 35.00 31,500.00 31.50
SNI - K.6.12 Pasang Pegangan Pintu / Door Holder BH SNIK.6.12 194,937.50 SN2K.6.12 194,937.50 SNSK.6.12 192,878.75
M.014i Pegangan Pintu / Door Holder 1.0000 Bh 175,500.00 175,500.00 175,500.00 175,500.00 175,500.00 175,500.00
L.008 Pekerja 0.0500 OH 27,000.00 1,350.00 27,000.00 1,350.00 24,500.00 1,225.00
L.002 Tukang Kayu 0.5000 OH 32,500.00 16,250.00 32,500.00 16,250.00 29,000.00 14,500.00
L.007 Kepala Tukang 0.0500 OH 35,000.00 1,750.00 35,000.00 1,750.00 31,500.00 1,575.00
L.010 Mandor 0.00250 OH 35,000.00 87.50 35,000.00 87.50 31,500.00 78.75
SNI - K.6.13 Pasang Door Stop BH SNIK.6.13 40,887.50 SN2K.6.13 40,887.50 SNSK.6.13 40,475.75
M.014j Door Stop 1.0000 Bh 37,000.00 37,000.00 37,000.00 37,000.00 37,000.00 37,000.00
L.008 Pekerja 0.0100 OH 27,000.00 270.00 27,000.00 270.00 24,500.00 245.00
L.002 Tukang Kayu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.00050 OH 35,000.00 17.50 35,000.00 17.50 31,500.00 15.75
SNI - K.6.14 Pasang Rel Pintu Dorong BH SNIK.6.14 323,325.00 SN2K.6.14 323,325.00 SNSK.6.14 320,854.50
M.014k Rel Pintu Dorong 1.0000 Bh 300,000.00 300,000.00 300,000.00 300,000.00 300,000.00 300,000.00
L.008 Pekerja 0.0600 OH 27,000.00 1,620.00 27,000.00 1,620.00 24,500.00 1,470.00
L.002 Tukang Kayu 0.6000 OH 32,500.00 19,500.00 32,500.00 19,500.00 29,000.00 17,400.00
L.007 Kepala Tukang 0.0600 OH 35,000.00 2,100.00 35,000.00 2,100.00 31,500.00 1,890.00
L.010 Mandor 0.00300 OH 35,000.00 105.00 35,000.00 105.00 31,500.00 94.50
SNI - K.6.16 Pasang Kaca tb. 3 mm M2 SNIK.6.16 61,931.25 SN2K.6.16 66,331.25 SNSK.6.16 61,313.63
M.008 Kaca bening tb. 3 mm 1.1000 M2 51,000.00 56,100.00 55,000.00 60,500.00 51,000.00 56,100.00
L.008 Pekerja 0.0150 OH 27,000.00 405.00 27,000.00 405.00 24,500.00 367.50
L.002 Tukang Kayu 0.1500 OH 32,500.00 4,875.00 32,500.00 4,875.00 29,000.00 4,350.00
L.007 Kepala Tukang 0.0150 OH 35,000.00 525.00 35,000.00 525.00 31,500.00 472.50
L.010 Mandor 0.00075 OH 35,000.00 26.25 35,000.00 26.25 31,500.00 23.63
SNI - K.6.17 Pasang Kaca tb. 5 mm M2 SNIK.6.17 88,331.25 SN2K.6.17 89,981.25 SNSK.6.17 87,713.63
M.008a Kaca bening tb. 5 mm 1.1000 M2 75,000.00 82,500.00 76,500.00 84,150.00 75,000.00 82,500.00
L.008 Pekerja 0.0150 OH 27,000.00 405.00 27,000.00 405.00 24,500.00 367.50
L.002 Tukang Kayu 0.1500 OH 32,500.00 4,875.00 32,500.00 4,875.00 29,000.00 4,350.00
L.007 Kepala Tukang 0.0150 OH 35,000.00 525.00 35,000.00 525.00 31,500.00 472.50
L.010 Mandor 0.00075 OH 35,000.00 26.25 35,000.00 26.25 31,500.00 23.63
SNI - K.6.18 Pasang Kaca tb. 8 mm M2 SNIK.6.18 204,413.50 SN2K.6.18 206,613.50 SNSK.6.18 203,734.20
M.008b Kaca bening tb. 8 mm 1.1000 M2 180,000.00 198,000.00 182,000.00 200,200.00 180,000.00 198,000.00
L.008 Pekerja 0.0165 OH 27,000.00 445.50 27,000.00 445.50 24,500.00 404.25
L.002 Tukang Kayu 0.1650 OH 32,500.00 5,362.50 32,500.00 5,362.50 29,000.00 4,785.00
L.007 Kepala Tukang 0.0165 OH 35,000.00 577.50 35,000.00 577.50 31,500.00 519.75
L.010 Mandor 0.00080 OH 35,000.00 28.00 35,000.00 28.00 31,500.00 25.20
32 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
SNI - K.6.20 Pasang Kaca Cermin tb. 5 mm M2 SNIK.6.20 192,831.25 SN2K.6.20 195,031.25 SNSK.6.20 192,213.63
M.008c Kaca Cermin tb. 5 mm 1.1000 M2 170,000.00 187,000.00 172,000.00 189,200.00 170,000.00 187,000.00
L.008 Pekerja 0.0150 OH 27,000.00 405.00 27,000.00 405.00 24,500.00 367.50
L.002 Tukang Kayu 0.1500 OH 32,500.00 4,875.00 32,500.00 4,875.00 29,000.00 4,350.00
L.007 Kepala Tukang 0.0150 OH 35,000.00 525.00 35,000.00 525.00 31,500.00 472.50
L.010 Mandor 0.00075 OH 35,000.00 26.25 35,000.00 26.25 31,500.00 23.63
L. PEKERJAAN LANTAI

SNI - L.6.2 Pas. Lantai Ubin PC abu-abu uk. ( 30 x 30 ) cm M2 SNIL.6.2 49,542.50 SN2L.6.2 52,580.00 SNSL.6.2 48,365.75
M.004q Ubin Abu-abu 30 x 30 cm 11.8700 Bh 2,000.00 23,740.00 2,250.00 26,707.50 2,000.00 23,740.00
M.002a Portland Cement 10.0000 Kg 1,200.00 12,000.00 1,207.00 12,070.00 1,200.00 12,000.00
M.001a Pasir Pasang 0.0215 M3 85,000.00 1,827.50 85,000.00 1,827.50 85,000.00 1,827.50
L.008 Pekerja 0.2600 OH 27,000.00 7,020.00 27,000.00 7,020.00 24,500.00 6,370.00
L.001 Tukang Batu 0.1250 OH 32,500.00 4,062.50 32,500.00 4,062.50 29,000.00 3,625.00
L.007 Kepala Tukang 0.0125 OH 35,000.00 437.50 35,000.00 437.50 31,500.00 393.75
L.010 Mandor 0.0130 OH 35,000.00 455.00 35,000.00 455.00 31,500.00 409.50
SNI - L.6.3 Pas. Lantai Ubin PC abu-abu uk. ( 20 x 20 ) cm M2 SNIL.6.3 44,620.00 SN2L.6.3 47,444.05 SNSL.6.3 43,397.25
M.004p Ubin Abu-abu 20 x 20 cm 26.5000 Bh 700.00 18,550.00 800.00 21,200.00 700.00 18,550.00
M.002a Portland Cement 10.4000 Kg 1,200.00 12,480.00 1,207.00 12,552.80 1,200.00 12,480.00
M.001a Pasir Pasang 0.0135 M3 85,000.00 1,147.50 92,500.00 1,248.75 85,000.00 1,147.50
L.008 Pekerja 0.2700 OH 27,000.00 7,290.00 27,000.00 7,290.00 24,500.00 6,615.00
L.001 Tukang Batu 0.1300 OH 32,500.00 4,225.00 32,500.00 4,225.00 29,000.00 3,770.00
L.007 Kepala Tukang 0.0130 OH 35,000.00 455.00 35,000.00 455.00 31,500.00 409.50
L.010 Mandor 0.0135 OH 35,000.00 472.50 35,000.00 472.50 31,500.00 425.25
SNI - L.6.44 Pas. Lantai Keramik uk. ( 20 x 20 ) cm (Klas A) M2 SNIL.6.44 93,061.00 SN2L.6.44 96,180.66 SNSL.6.44 90,058.50
M.004 Ubin Keramik 20 x 20 cm (Klas A) 26.5000 Bh 1,630.00 43,195.00 1,730.00 45,845.00 1,630.00 43,195.00
M.002a Portland Cement 11.3800 Kg 1,200.00 13,656.00 1,207.00 13,735.66 1,200.00 13,656.00
M.001a Pasir Pasang 0.0420 M3 85,000.00 3,570.00 92,500.00 3,885.00 85,000.00 3,570.00
M.002b Semen Warna 1.5000 Kg 1,500.00 2,250.00 1,550.00 2,325.00 1,500.00 2,250.00
L.008 Pekerja 0.6200 OH 27,000.00 16,740.00 27,000.00 16,740.00 24,500.00 15,190.00
L.001 Tukang Batu 0.3500 OH 32,500.00 11,375.00 32,500.00 11,375.00 29,000.00 10,150.00
L.007 Kepala Tukang 0.0350 OH 35,000.00 1,225.00 35,000.00 1,225.00 31,500.00 1,102.50
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
SNI - L.6.44a Pas. Lantai Keramik uk. ( 20 x 20 ) cm (Klas B) M2 SNIL.6.44a 97,566.00 SN2L.6.44a 100,685.66 SNSL.6.44a 94,563.50
M.004a Ubin Keramik 20 x 20 cm (Klas B) 26.5000 Bh 1,800.00 47,700.00 1,900.00 50,350.00 1,800.00 47,700.00
M.002a Portland Cement 11.3800 Kg 1,200.00 13,656.00 1,207.00 13,735.66 1,200.00 13,656.00
M.001a Pasir Pasang 0.0420 M3 85,000.00 3,570.00 92,500.00 3,885.00 85,000.00 3,570.00
M.002b Semen Warna 1.5000 Kg 1,500.00 2,250.00 1,550.00 2,325.00 1,500.00 2,250.00
L.008 Pekerja 0.6200 OH 27,000.00 16,740.00 27,000.00 16,740.00 24,500.00 15,190.00
L.001 Tukang Batu 0.3500 OH 32,500.00 11,375.00 32,500.00 11,375.00 29,000.00 10,150.00
L.007 Kepala Tukang 0.0350 OH 35,000.00 1,225.00 35,000.00 1,225.00 31,500.00 1,102.50
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
SNI - L.6.44b Pas. Lantai Keramik uk. ( 20 x 20 ) cm (Klas C) M2 SNIL.6.44a 113,466.00 SN2L.6.44a 113,935.66 SNSL.6.44a 110,463.50
M.004b Ubin Keramik 20 x 20 cm (Klas C) 26.5000 Bh 2,400.00 63,600.00 2,400.00 63,600.00 2,400.00 63,600.00
M.002a Portland Cement 11.3800 Kg 1,200.00 13,656.00 1,207.00 13,735.66 1,200.00 13,656.00
M.001a Pasir Pasang 0.0420 M3 85,000.00 3,570.00 92,500.00 3,885.00 85,000.00 3,570.00
M.002b Semen Warna 1.5000 Kg 1,500.00 2,250.00 1,550.00 2,325.00 1,500.00 2,250.00
L.008 Pekerja 0.6200 OH 27,000.00 16,740.00 27,000.00 16,740.00 24,500.00 15,190.00
L.001 Tukang Batu 0.3500 OH 32,500.00 11,375.00 32,500.00 11,375.00 29,000.00 10,150.00
L.007 Kepala Tukang 0.0350 OH 35,000.00 1,225.00 35,000.00 1,225.00 31,500.00 1,102.50
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
SNI - L.6.47 Pas. Lantai Keramik uk. ( 33 x 33 ) cm (Klas C) M2 SNIL.6.47 119,866.00 SN2L.6.47 122,335.66 SNSL.6.47 116,863.50
M.004c Ubin Keramik 33 x 33 cm (Klas C) 10.0000 Bh 7,000.00 70,000.00 7,200.00 72,000.00 7,000.00 70,000.00
M.002a Portland Cement 11.3800 Kg 1,200.00 13,656.00 1,207.00 13,735.66 1,200.00 13,656.00
M.001a Pasir Pasang 0.0420 M3 85,000.00 3,570.00 92,500.00 3,885.00 85,000.00 3,570.00
M.002b Semen Warna 1.5000 Kg 1,500.00 2,250.00 1,550.00 2,325.00 1,500.00 2,250.00
L.008 Pekerja 0.6200 OH 27,000.00 16,740.00 27,000.00 16,740.00 24,500.00 15,190.00
L.001 Tukang Batu 0.3500 OH 32,500.00 11,375.00 32,500.00 11,375.00 29,000.00 10,150.00
L.007 Kepala Tukang 0.0350 OH 35,000.00 1,225.00 35,000.00 1,225.00 31,500.00 1,102.50
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
SNI - L.6.47a Pas. Lantai Keramik uk. ( 40 x 40 ) cm (Klas A) M2 SNIL.6.47a 96,556.00 SN2L.6.47a 98,425.66 SNSL.6.47a 93,553.50
M.004d Ubin Keramik 40 x 40 cm (Klas A) 7.0000 Bh 6,670.00 46,690.00 6,870.00 48,090.00 6,670.00 46,690.00
M.002a Portland Cement 11.3800 Kg 1,200.00 13,656.00 1,207.00 13,735.66 1,200.00 13,656.00
M.001a Pasir Pasang 0.0420 M3 85,000.00 3,570.00 92,500.00 3,885.00 85,000.00 3,570.00
M.002b Semen Warna 1.5000 Kg 1,500.00 2,250.00 1,550.00 2,325.00 1,500.00 2,250.00
L.008 Pekerja 0.6200 OH 27,000.00 16,740.00 27,000.00 16,740.00 24,500.00 15,190.00
L.001 Tukang Batu 0.3500 OH 32,500.00 11,375.00 32,500.00 11,375.00 29,000.00 10,150.00
L.007 Kepala Tukang 0.0350 OH 35,000.00 1,225.00 35,000.00 1,225.00 31,500.00 1,102.50
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
SNI - L.6.47b Pas. Lantai Keramik uk. ( 40 x 40 ) cm (Klas B) M2 SNIL.6.47b 101,806.00 SN2L.6.47b 103,675.66 SNSL.6.47b 98,803.50
M.004e Ubin Keramik 40 x 40 cm (Klas B) 7.0000 Bh 7,420.00 51,940.00 7,620.00 53,340.00 7,420.00 51,940.00
M.002a Portland Cement 11.3800 Kg 1,200.00 13,656.00 1,207.00 13,735.66 1,200.00 13,656.00
M.001a Pasir Pasang 0.0420 M3 85,000.00 3,570.00 92,500.00 3,885.00 85,000.00 3,570.00
M.002b Semen Warna 1.5000 Kg 1,500.00 2,250.00 1,550.00 2,325.00 1,500.00 2,250.00
L.008 Pekerja 0.6200 OH 27,000.00 16,740.00 27,000.00 16,740.00 24,500.00 15,190.00
L.001 Tukang Batu 0.3500 OH 32,500.00 11,375.00 32,500.00 11,375.00 29,000.00 10,150.00
L.007 Kepala Tukang 0.0350 OH 35,000.00 1,225.00 35,000.00 1,225.00 31,500.00 1,102.50
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
33 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
SNI - L.6.47c Pas. Lantai Keramik uk. ( 40 x 40 ) cm (Klas C) M2 SNIL.6.47c 115,666.00 SN2L.6.47c 116,835.66 SNSL.6.47c 112,663.50
M.004e.1 Ubin Keramik 40 x 40 cm (Klas C) 7.0000 Bh 9,400.00 65,800.00 9,500.00 66,500.00 9,400.00 65,800.00
M.002a Portland Cement 11.3800 Kg 1,200.00 13,656.00 1,207.00 13,735.66 1,200.00 13,656.00
M.001a Pasir Pasang 0.0420 M3 85,000.00 3,570.00 92,500.00 3,885.00 85,000.00 3,570.00
M.002b Semen Warna 1.5000 Kg 1,500.00 2,250.00 1,550.00 2,325.00 1,500.00 2,250.00
L.008 Pekerja 0.6200 OH 27,000.00 16,740.00 27,000.00 16,740.00 24,500.00 15,190.00
L.001 Tukang Batu 0.3500 OH 32,500.00 11,375.00 32,500.00 11,375.00 29,000.00 10,150.00
L.007 Kepala Tukang 0.0350 OH 35,000.00 1,225.00 35,000.00 1,225.00 31,500.00 1,102.50
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
SNI - L.6.47d Pas. Lantai Keramik uk. ( 40 x 40 ) cm (Klas D) M2 SNIL.6.47d 138,066.00 SN2L.6.47d 139,550.66 SNSL.6.47d 135,063.50
M.004e.2 Ubin Keramik 40 x 40 cm (Klas D) 7.0000 Bh 12,600.00 88,200.00 12,745.00 89,215.00 12,600.00 88,200.00
M.002a Portland Cement 11.3800 Kg 1,200.00 13,656.00 1,207.00 13,735.66 1,200.00 13,656.00
M.001a Pasir Pasang 0.0420 M3 85,000.00 3,570.00 92,500.00 3,885.00 85,000.00 3,570.00
M.002b Semen Warna 1.5000 Kg 1,500.00 2,250.00 1,550.00 2,325.00 1,500.00 2,250.00
L.008 Pekerja 0.6200 OH 27,000.00 16,740.00 27,000.00 16,740.00 24,500.00 15,190.00
L.001 Tukang Batu 0.3500 OH 32,500.00 11,375.00 32,500.00 11,375.00 29,000.00 10,150.00
L.007 Kepala Tukang 0.0350 OH 35,000.00 1,225.00 35,000.00 1,225.00 31,500.00 1,102.50
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
SNI - L.6.47e Pas. Lantai Keramik uk. ( 30 x 30 ) cm (Klas A) M2 SNIL.6.47e 85,866.00 SN2L.6.47e 88,195.66 SNSL.6.47e 82,863.50
M.004f Keramik lantai 30 x 30 cm (Klas A) 12.0000 Bh 3,000.00 36,000.00 3,155.00 37,860.00 3,000.00 36,000.00
M.002a Portland Cement 11.3800 Kg 1,200.00 13,656.00 1,207.00 13,735.66 1,200.00 13,656.00
M.001a Pasir Pasang 0.0420 M3 85,000.00 3,570.00 92,500.00 3,885.00 85,000.00 3,570.00
M.002b Semen Warna 1.5000 Kg 1,500.00 2,250.00 1,550.00 2,325.00 1,500.00 2,250.00
L.008 Pekerja 0.6200 OH 27,000.00 16,740.00 27,000.00 16,740.00 24,500.00 15,190.00
L.001 Tukang Batu 0.3500 OH 32,500.00 11,375.00 32,500.00 11,375.00 29,000.00 10,150.00
L.007 Kepala Tukang 0.0350 OH 35,000.00 1,225.00 35,000.00 1,225.00 31,500.00 1,102.50
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
SNI - L.6.47f Pas. Lantai Keramik uk. ( 30 x 30 ) cm (Klas B) M2 SNIL.6.47e 91,206.00 SN2L.6.47e 94,075.66 SNSL.6.47e 88,203.50
M.004g Keramik lantai 30 x 30 cm (Klas B) 12.0000 Bh 3,445.00 41,340.00 3,645.00 43,740.00 3,445.00 41,340.00
M.002a Portland Cement 11.3800 Kg 1,200.00 13,656.00 1,207.00 13,735.66 1,200.00 13,656.00
M.001a Pasir Pasang 0.0420 M3 85,000.00 3,570.00 92,500.00 3,885.00 85,000.00 3,570.00
M.002b Semen Warna 1.5000 Kg 1,500.00 2,250.00 1,550.00 2,325.00 1,500.00 2,250.00
L.008 Pekerja 0.6200 OH 27,000.00 16,740.00 27,000.00 16,740.00 24,500.00 15,190.00
L.001 Tukang Batu 0.3500 OH 32,500.00 11,375.00 32,500.00 11,375.00 29,000.00 10,150.00
L.007 Kepala Tukang 0.0350 OH 35,000.00 1,225.00 35,000.00 1,225.00 31,500.00 1,102.50
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
SNI - L.6.47g Pas. Lantai Keramik uk. ( 30 x 30 ) cm (Klas C) M2 SNIL.6.47e 99,666.00 SN2L.6.47e 102,535.66 SNSL.6.47e 96,663.50
M.004g.1 Keramik lantai 30 x 30 cm (Klas C) 12.0000 Bh 4,150.00 49,800.00 4,350.00 52,200.00 4,150.00 49,800.00
M.002a Portland Cement 11.3800 Kg 1,200.00 13,656.00 1,207.00 13,735.66 1,200.00 13,656.00
M.001a Pasir Pasang 0.0420 M3 85,000.00 3,570.00 92,500.00 3,885.00 85,000.00 3,570.00
M.002b Semen Warna 1.5000 Kg 1,500.00 2,250.00 1,550.00 2,325.00 1,500.00 2,250.00
L.008 Pekerja 0.6200 OH 27,000.00 16,740.00 27,000.00 16,740.00 24,500.00 15,190.00
L.001 Tukang Batu 0.3500 OH 32,500.00 11,375.00 32,500.00 11,375.00 29,000.00 10,150.00
L.007 Kepala Tukang 0.0350 OH 35,000.00 1,225.00 35,000.00 1,225.00 31,500.00 1,102.50
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
SNI - L.6.47h Pas. Lantai Keramik uk. ( 30 x 30 ) cm (Klas D) M2 SNIL.6.47e 120,066.00 SN2L.6.47e 121,243.66 SNSL.6.47e 117,063.50
M.004g.2 Keramik lantai 30 x 30 cm (Klas D) 12.0000 Bh 5,850.00 70,200.00 5,909.00 70,908.00 5,850.00 70,200.00
M.002a Portland Cement 11.3800 Kg 1,200.00 13,656.00 1,207.00 13,735.66 1,200.00 13,656.00
M.001a Pasir Pasang 0.0420 M3 85,000.00 3,570.00 92,500.00 3,885.00 85,000.00 3,570.00
M.002b Semen Warna 1.5000 Kg 1,500.00 2,250.00 1,550.00 2,325.00 1,500.00 2,250.00
L.008 Pekerja 0.6200 OH 27,000.00 16,740.00 27,000.00 16,740.00 24,500.00 15,190.00
L.001 Tukang Batu 0.3500 OH 32,500.00 11,375.00 32,500.00 11,375.00 29,000.00 10,150.00
L.007 Kepala Tukang 0.0350 OH 35,000.00 1,225.00 35,000.00 1,225.00 31,500.00 1,102.50
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
Pas. Lantai Keramik Anti Slip uk. ( 33 x 33 ) cm
SNI - L.6.48 M2 SNIL.6.48 120,866.00 SN2L.6.48 122,335.66 SNSL.6.48 117,863.50
(Klas C)
Keramik Lantai 33x33 cm Anti Slip
M.004h 10.0000 Bh 7,100.00 71,000.00 7,200.00 72,000.00 7,100.00 71,000.00
(Klas C)
M.002a Portland Cement 11.3800 Kg 1,200.00 13,656.00 1,207.00 13,735.66 1,200.00 13,656.00
M.001a Pasir Pasang 0.0420 M3 85,000.00 3,570.00 92,500.00 3,885.00 85,000.00 3,570.00
M.002b Semen Warna 1.5000 Kg 1,500.00 2,250.00 1,550.00 2,325.00 1,500.00 2,250.00
L.008 Pekerja 0.6200 OH 27,000.00 16,740.00 27,000.00 16,740.00 24,500.00 15,190.00
L.001 Tukang Batu 0.3500 OH 32,500.00 11,375.00 32,500.00 11,375.00 29,000.00 10,150.00
L.007 Kepala Tukang 0.0350 OH 35,000.00 1,225.00 35,000.00 1,225.00 31,500.00 1,102.50
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
Pas. Lantai Keramik Anti Slip uk. ( 40 x 40 ) cm
SNI - L.6.48a M2 SNIL.6.48a 101,211.00 SN2L.6.48a 103,080.66 SNSL.6.48a 98,208.50
(Klas A)
Keramik Lantai 40x40 cm Anti Slip
M.004i 7.0000 Bh 7,335.00 51,345.00 7,535.00 52,745.00 7,335.00 51,345.00
(Klas A)
M.002a Portland Cement 11.3800 Kg 1,200.00 13,656.00 1,207.00 13,735.66 1,200.00 13,656.00
M.001a Pasir Pasang 0.0420 M3 85,000.00 3,570.00 92,500.00 3,885.00 85,000.00 3,570.00
M.002b Semen Warna 1.5000 Kg 1,500.00 2,250.00 1,550.00 2,325.00 1,500.00 2,250.00
L.008 Pekerja 0.6200 OH 27,000.00 16,740.00 27,000.00 16,740.00 24,500.00 15,190.00
L.001 Tukang Batu 0.3500 OH 32,500.00 11,375.00 32,500.00 11,375.00 29,000.00 10,150.00
L.007 Kepala Tukang 0.0350 OH 35,000.00 1,225.00 35,000.00 1,225.00 31,500.00 1,102.50
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
Pas. Lantai Keramik Anti Slip uk. ( 40 x 40 ) cm
SNI - L.6.48b M2 SNIL.6.48b 109,366.00 SN2L.6.48b 110,885.66 SNSL.6.48b 106,363.50
(Klas B)
Keramik Lantai 40x40 cm Anti Slip
M.004j 7.0000 Bh 8,500.00 59,500.00 8,650.00 60,550.00 8,500.00 59,500.00
(Klas B)
M.002a Portland Cement 11.3800 Kg 1,200.00 13,656.00 1,207.00 13,735.66 1,200.00 13,656.00
M.001a Pasir Pasang 0.0420 M3 85,000.00 3,570.00 92,500.00 3,885.00 85,000.00 3,570.00
M.002b Semen Warna 1.5000 Kg 1,500.00 2,250.00 1,550.00 2,325.00 1,500.00 2,250.00
L.008 Pekerja 0.6200 OH 27,000.00 16,740.00 27,000.00 16,740.00 24,500.00 15,190.00
L.001 Tukang Batu 0.3500 OH 32,500.00 11,375.00 32,500.00 11,375.00 29,000.00 10,150.00
L.007 Kepala Tukang 0.0350 OH 35,000.00 1,225.00 35,000.00 1,225.00 31,500.00 1,102.50
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
34 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
Pas. Lantai Keramik Anti Slip uk. ( 40 x 40 ) cm
SNI - L.6.48c M2 SNIL.6.48c 116,366.00 SN2L.6.48c 117,535.66 SNSL.6.48c 113,363.50
(Klas C)
Keramik Lantai 40x40 cm Anti Slip
M.004j.1 7.0000 Bh 9,500.00 66,500.00 9,600.00 67,200.00 9,500.00 66,500.00
(Klas C)
M.002a Portland Cement 11.3800 Kg 1,200.00 13,656.00 1,207.00 13,735.66 1,200.00 13,656.00
M.001a Pasir Pasang 0.0420 M3 85,000.00 3,570.00 92,500.00 3,885.00 85,000.00 3,570.00
M.002b Semen Warna 1.5000 Kg 1,500.00 2,250.00 1,550.00 2,325.00 1,500.00 2,250.00
L.008 Pekerja 0.6200 OH 27,000.00 16,740.00 27,000.00 16,740.00 24,500.00 15,190.00
L.001 Tukang Batu 0.3500 OH 32,500.00 11,375.00 32,500.00 11,375.00 29,000.00 10,150.00
L.007 Kepala Tukang 0.0350 OH 35,000.00 1,225.00 35,000.00 1,225.00 31,500.00 1,102.50
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
Pas. Lantai Keramik Anti Slip uk. ( 40 x 40 ) cm
SNI - L.6.48d M2 SNIL.6.48c 141,566.00 SN2L.6.48c 142,875.66 SNSL.6.48c 138,563.50
(Klas D)
Keramik Lantai 40x40 cm Anti Slip
M.004j.2 7.0000 Bh 13,100.00 91,700.00 13,220.00 92,540.00 13,100.00 91,700.00
(Klas D)
M.002a Portland Cement 11.3800 Kg 1,200.00 13,656.00 1,207.00 13,735.66 1,200.00 13,656.00
M.001a Pasir Pasang 0.0420 M3 85,000.00 3,570.00 92,500.00 3,885.00 85,000.00 3,570.00
M.002b Semen Warna 1.5000 Kg 1,500.00 2,250.00 1,550.00 2,325.00 1,500.00 2,250.00
L.008 Pekerja 0.6200 OH 27,000.00 16,740.00 27,000.00 16,740.00 24,500.00 15,190.00
L.001 Tukang Batu 0.3500 OH 32,500.00 11,375.00 32,500.00 11,375.00 29,000.00 10,150.00
L.007 Kepala Tukang 0.0350 OH 35,000.00 1,225.00 35,000.00 1,225.00 31,500.00 1,102.50
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
Pas. Lantai Keramik Anti Slip uk. ( 30 x 30 ) cm
SNI - L.6.48e M2 SNIL.6.48d 89,166.00 SN2L.6.48d 92,035.66 SNSL.6.48d 86,163.50
(Klas A)
Keramik Lantai 30x30 cm Anti Slip
M.004k 12.0000 Bh 3,275.00 39,300.00 3,475.00 41,700.00 3,275.00 39,300.00
(Klas A)
M.002a Portland Cement 11.3800 Kg 1,200.00 13,656.00 1,207.00 13,735.66 1,200.00 13,656.00
M.001a Pasir Pasang 0.0420 M3 85,000.00 3,570.00 92,500.00 3,885.00 85,000.00 3,570.00
M.002b Semen Warna 1.5000 Kg 1,500.00 2,250.00 1,550.00 2,325.00 1,500.00 2,250.00
L.008 Pekerja 0.6200 OH 27,000.00 16,740.00 27,000.00 16,740.00 24,500.00 15,190.00
L.001 Tukang Batu 0.3500 OH 32,500.00 11,375.00 32,500.00 11,375.00 29,000.00 10,150.00
L.007 Kepala Tukang 0.0350 OH 35,000.00 1,225.00 35,000.00 1,225.00 31,500.00 1,102.50
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
Pas. Lantai Keramik Anti Slip uk. ( 30 x 30 ) cm
SNI - L.6.48f M2 SNIL.6.48e 95,706.00 SN2L.6.48e 98,575.66 SNSL.6.48e 92,703.50
(Klas B)
Keramik Lantai 30x30 cm Anti Slip
M.004l 12.0000 Bh 3,820.00 45,840.00 4,020.00 48,240.00 3,820.00 45,840.00
(Klas B)
M.002a Portland Cement 11.3800 Kg 1,200.00 13,656.00 1,207.00 13,735.66 1,200.00 13,656.00
M.001a Pasir Pasang 0.0420 M3 85,000.00 3,570.00 92,500.00 3,885.00 85,000.00 3,570.00
M.002b Semen Warna 1.5000 Kg 1,500.00 2,250.00 1,550.00 2,325.00 1,500.00 2,250.00
L.008 Pekerja 0.6200 OH 27,000.00 16,740.00 27,000.00 16,740.00 24,500.00 15,190.00
L.001 Tukang Batu 0.3500 OH 32,500.00 11,375.00 32,500.00 11,375.00 29,000.00 10,150.00
L.007 Kepala Tukang 0.0350 OH 35,000.00 1,225.00 35,000.00 1,225.00 31,500.00 1,102.50
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
Pas. Lantai Keramik Anti Slip uk. ( 30 x 30 ) cm
SNI - L.6.48g M2 SNIL.6.48d 101,166.00 SN2L.6.48d 104,035.66 SNSL.6.48d 98,163.50
(Klas C)
Keramik Lantai 30x30 cm Anti Slip
M.004l.1 12.0000 Bh 4,275.00 51,300.00 4,475.00 53,700.00 4,275.00 51,300.00
(Klas C)
M.002a Portland Cement 11.3800 Kg 1,200.00 13,656.00 1,207.00 13,735.66 1,200.00 13,656.00
M.001a Pasir Pasang 0.0420 M3 85,000.00 3,570.00 92,500.00 3,885.00 85,000.00 3,570.00
M.002b Semen Warna 1.5000 Kg 1,500.00 2,250.00 1,550.00 2,325.00 1,500.00 2,250.00
L.008 Pekerja 0.6200 OH 27,000.00 16,740.00 27,000.00 16,740.00 24,500.00 15,190.00
L.001 Tukang Batu 0.3500 OH 32,500.00 11,375.00 32,500.00 11,375.00 29,000.00 10,150.00
L.007 Kepala Tukang 0.0350 OH 35,000.00 1,225.00 35,000.00 1,225.00 31,500.00 1,102.50
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
Pas. Lantai Keramik Anti Slip uk. ( 30 x 30 ) cm
SNI - L.6.48h M2 SNIL.6.48e 121,266.00 SN2L.6.48e 123,055.66 SNSL.6.48e 118,263.50
(Klas D)
Keramik Lantai 30x30 cm Anti Slip
M.004l.2 12.0000 Bh 5,950.00 71,400.00 6,060.00 72,720.00 5,950.00 71,400.00
(Klas D)
M.002a Portland Cement 11.3800 Kg 1,200.00 13,656.00 1,207.00 13,735.66 1,200.00 13,656.00
M.001a Pasir Pasang 0.0420 M3 85,000.00 3,570.00 92,500.00 3,885.00 85,000.00 3,570.00
M.002b Semen Warna 1.5000 Kg 1,500.00 2,250.00 1,550.00 2,325.00 1,500.00 2,250.00
L.008 Pekerja 0.6200 OH 27,000.00 16,740.00 27,000.00 16,740.00 24,500.00 15,190.00
L.001 Tukang Batu 0.3500 OH 32,500.00 11,375.00 32,500.00 11,375.00 29,000.00 10,150.00
L.007 Kepala Tukang 0.0350 OH 35,000.00 1,225.00 35,000.00 1,225.00 31,500.00 1,102.50
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
SNI - L.6.68 Pas. Keramik Dinding uk. ( 20 x 20 ) cm (Klas A) M2 SNIL.6.68 78,355.00 SN2L.6.68 81,280.10 SNSL.6.68 76,242.50
M.004m Keramik Dinding 20 x 20 cm (Klas A) 26.5000 Bh 1,560.00 41,340.00 1,660.00 43,990.00 1,560.00 41,340.00
M.002a Portland Cement 9.3000 Kg 1,200.00 11,160.00 1,207.00 11,225.10 1,200.00 11,160.00
M.001a Pasir Pasang 0.0180 M3 85,000.00 1,530.00 92,500.00 1,665.00 85,000.00 1,530.00
M.002b Semen Warna 1.5000 Kg 1,500.00 2,250.00 1,550.00 2,325.00 1,500.00 2,250.00
L.008 Pekerja 0.6000 OH 27,000.00 16,200.00 27,000.00 16,200.00 24,500.00 14,700.00
L.001 Tukang Batu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0450 OH 35,000.00 1,575.00 35,000.00 1,575.00 31,500.00 1,417.50
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
SNI - L.6.68a Pas. Keramik Dinding uk. ( 20 x 20 ) cm (Klas B) M2 SNIL.6.68a 100,615.00 SN2L.6.68a 101,897.10 SNSL.6.68a 98,502.50
M.004n Keramik Dinding 20 x 20 cm (Klas B) 26.5000 Bh 2,400.00 63,600.00 2,438.00 64,607.00 2,400.00 63,600.00
M.002a Portland Cement 9.3000 Kg 1,200.00 11,160.00 1,207.00 11,225.10 1,200.00 11,160.00
M.001a Pasir Pasang 0.0180 M3 85,000.00 1,530.00 92,500.00 1,665.00 85,000.00 1,530.00
M.002b Semen Warna 1.5000 Kg 1,500.00 2,250.00 1,550.00 2,325.00 1,500.00 2,250.00
L.008 Pekerja 0.6000 OH 27,000.00 16,200.00 27,000.00 16,200.00 24,500.00 14,700.00
L.001 Tukang Batu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0450 OH 35,000.00 1,575.00 35,000.00 1,575.00 31,500.00 1,417.50
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
35 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
SNI - L.6.68b Pas. Keramik Dinding uk. ( 20 x 25 ) cm (Klas A) M2 SNIL.6.68a 85,315.00 SN2L.6.68a 87,690.10 SNSL.6.68a 83,202.50
M.004o Keramik Dinding 20 x 25 cm (Klas A) 21.0000 Bh 2,300.00 48,300.00 2,400.00 50,400.00 2,300.00 48,300.00
M.002a Portland Cement 9.3000 Kg 1,200.00 11,160.00 1,207.00 11,225.10 1,200.00 11,160.00
M.001a Pasir Pasang 0.0180 M3 85,000.00 1,530.00 92,500.00 1,665.00 85,000.00 1,530.00
M.002b Semen Warna 1.5000 Kg 1,500.00 2,250.00 1,550.00 2,325.00 1,500.00 2,250.00
L.008 Pekerja 0.6000 OH 27,000.00 16,200.00 27,000.00 16,200.00 24,500.00 14,700.00
L.001 Tukang Batu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0450 OH 35,000.00 1,575.00 35,000.00 1,575.00 31,500.00 1,417.50
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
SNI - L.6.68c Pas. Keramik Dinding uk. ( 20 x 25 ) cm (Klas B) M2 SNIL.6.68a 91,825.00 SN2L.6.68a 94,200.10 SNSL.6.68a 89,712.50
M.004o.1 Keramik Dinding 20 x 25 cm (Klas B) 21.0000 Bh 2,610.00 54,810.00 2,710.00 56,910.00 2,610.00 54,810.00
M.002a Portland Cement 9.3000 Kg 1,200.00 11,160.00 1,207.00 11,225.10 1,200.00 11,160.00
M.001a Pasir Pasang 0.0180 M3 85,000.00 1,530.00 92,500.00 1,665.00 85,000.00 1,530.00
M.002b Semen Warna 1.5000 Kg 1,500.00 2,250.00 1,550.00 2,325.00 1,500.00 2,250.00
L.008 Pekerja 0.6000 OH 27,000.00 16,200.00 27,000.00 16,200.00 24,500.00 14,700.00
L.001 Tukang Batu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0450 OH 35,000.00 1,575.00 35,000.00 1,575.00 31,500.00 1,417.50
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
SNI - L.6.68d Pas. Keramik Dinding uk. ( 20 x 25 ) cm (Klas C) M2 SNIL.6.68a 93,715.00 SN2L.6.68a 96,090.10 SNSL.6.68a 91,602.50
M.004o.2 Keramik Dinding 20 x 25 cm (Klas C) 21.0000 Bh 2,700.00 56,700.00 2,800.00 58,800.00 2,700.00 56,700.00
M.002a Portland Cement 9.3000 Kg 1,200.00 11,160.00 1,207.00 11,225.10 1,200.00 11,160.00
M.001a Pasir Pasang 0.0180 M3 85,000.00 1,530.00 92,500.00 1,665.00 85,000.00 1,530.00
M.002b Semen Warna 1.5000 Kg 1,500.00 2,250.00 1,550.00 2,325.00 1,500.00 2,250.00
L.008 Pekerja 0.6000 OH 27,000.00 16,200.00 27,000.00 16,200.00 24,500.00 14,700.00
L.001 Tukang Batu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0450 OH 35,000.00 1,575.00 35,000.00 1,575.00 31,500.00 1,417.50
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
SNI - L.6.68e Pas. Keramik Dinding uk. ( 20 x 25 ) cm (Klas D) M2 SNIL.6.68a 98,860.00 SN2L.6.68a 101,235.10 SNSL.6.68a 96,747.50
M.004o.3 Keramik Dinding 20 x 25 cm (Klas D) 21.0000 Bh 2,945.00 61,845.00 3,045.00 63,945.00 2,945.00 61,845.00
M.002a Portland Cement 9.3000 Kg 1,200.00 11,160.00 1,207.00 11,225.10 1,200.00 11,160.00
M.001a Pasir Pasang 0.0180 M3 85,000.00 1,530.00 92,500.00 1,665.00 85,000.00 1,530.00
M.002b Semen Warna 1.5000 Kg 1,500.00 2,250.00 1,550.00 2,325.00 1,500.00 2,250.00
L.008 Pekerja 0.6000 OH 27,000.00 16,200.00 27,000.00 16,200.00 24,500.00 14,700.00
L.001 Tukang Batu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0450 OH 35,000.00 1,575.00 35,000.00 1,575.00 31,500.00 1,417.50
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
M. PEKERJAAN PENGECATAN

SNI - M.6.1 Mengikis/Mengerok Permukaan Cat Tembok Lama M2 SNIM.6.1 5,087.50 SN2M.6.1 5,087.50 SNSM.6.1 4,703.75
M.012l Soda Api 0.0500 Kg 19,000.00 950.00 19,000.00 950.00 19,000.00 950.00
L.008 Pekerja 0.1500 OH 27,000.00 4,050.00 27,000.00 4,050.00 24,500.00 3,675.00
L.010 Mandor 0.0025 OH 35,000.00 87.50 35,000.00 87.50 31,500.00 78.75
SNI - M.6.6 Mendempul dan Menggosok Kayu M2 SNIM.6.6 4,050.25 SN2M.6.6 4,112.50 SNSM.6.6 3,787.50
M.012e Dempul Jadi 0.0800 Kg 16,000.00 1,280.00 16,500.00 1,320.00 16,000.00 1,280.00
M.011g Minyak Cat 0.0200 Kg 5,000.00 100.00 6,000.00 120.00 5,000.00 100.00
M.012 Batu Kambang / Apung 0.0100 Kg 6,275.00 62.75 6,500.00 65.00 6,275.00 62.75
L.008 Pekerja 0.0400 OH 27,000.00 1,080.00 27,000.00 1,080.00 24,500.00 980.00
L.004 Tukang Cat 0.0400 OH 32,500.00 1,300.00 32,500.00 1,300.00 29,000.00 1,160.00
L.007 Kepala Tukang 0.0040 OH 35,000.00 140.00 35,000.00 140.00 31,500.00 126.00
L.010 Mandor 0.0025 OH 35,000.00 87.50 35,000.00 87.50 31,500.00 78.75
SNI - M.6.7 Pengecatan Bidang Kayu Lama ( Sek. Avian ) M2 SNIM.6.7 19,895.50 SN2M.6.7 20,242.50 SNSM.6.7 19,423.00
M.012b Plamir Kayu 0.1500 Kg 16,000.00 2,400.00 16,500.00 2,475.00 16,000.00 2,400.00
M.011 Cat dasar ( sek. Avian ) 0.1700 Kg 37,700.00 6,409.00 38,500.00 6,545.00 37,700.00 6,409.00
M.011 Cat Penutup ( sek. Avian ) 0.1700 Kg 37,700.00 6,409.00 38,500.00 6,545.00 37,700.00 6,409.00
L.008 Pekerja 0.0700 OH 27,000.00 1,890.00 27,000.00 1,890.00 24,500.00 1,715.00
L.004 Tukang Cat 0.0750 OH 32,500.00 2,437.50 32,500.00 2,437.50 29,000.00 2,175.00
L.007 Kepala Tukang 0.0075 OH 35,000.00 262.50 35,000.00 262.50 31,500.00 236.25
L.010 Mandor 0.0025 OH 35,000.00 87.50 35,000.00 87.50 31,500.00 78.75
Pengecatan Bidang Kayu Baru( 1 lps plamir, 1 lps
SNI - M.6.8 M2 SNIM.6.8 23,291.00 SN2M.6.8 23,910.00 SNSM.6.8 23,054.75
cat dasar, 2 lps cat penutup ) Sek. Avian
M.011f Cat meni 0.2000 Kg 11,000.00 2,200.00 12,000.00 2,400.00 11,000.00 2,200.00
M.012b Plamir Kayu 0.1500 Kg 16,000.00 2,400.00 16,500.00 2,475.00 16,000.00 2,400.00
M.011 Cat dasar ( sek. Avian ) 0.1700 Kg 37,700.00 6,409.00 38,500.00 6,545.00 37,700.00 6,409.00
M.011 Cat Penutup ( sek. Avian ) 0.2600 Kg 37,700.00 9,802.00 38,500.00 10,010.00 37,700.00 9,802.00
L.008 Pekerja 0.0700 OH 27,000.00 1,890.00 27,000.00 1,890.00 24,500.00 1,715.00
L.004 Tukang Cat 0.0090 OH 32,500.00 292.50 32,500.00 292.50 29,000.00 261.00
L.007 Kepala Tukang 0.0060 OH 35,000.00 210.00 35,000.00 210.00 31,500.00 189.00
L.010 Mandor 0.0025 OH 35,000.00 87.50 35,000.00 87.50 31,500.00 78.75
Pengecatan Bidang Kayu Baru( 1 lps plamir, 1 lps
SNI - M.6.8a M2 SNIM.6.8 37,180.00 SN2M.6.8 37,885.00 SNSM.6.8 36,943.75
cat dasar, 2 lps cat penutup ) Sek. Dulux
M.011f Cat meni 0.2000 Kg 11,000.00 2,200.00 12,000.00 2,400.00 11,000.00 2,200.00
M.012b Plamir Kayu 0.1500 Kg 16,000.00 2,400.00 16,500.00 2,475.00 16,000.00 2,400.00
M.011 Cat dasar ( sek. Dulux ) 0.1700 Kg 70,000.00 11,900.00 71,000.00 12,070.00 70,000.00 11,900.00
M.011 Cat Penutup ( sek. Dulux ) 0.2600 Kg 70,000.00 18,200.00 71,000.00 18,460.00 70,000.00 18,200.00
L.008 Pekerja 0.0700 OH 27,000.00 1,890.00 27,000.00 1,890.00 24,500.00 1,715.00
L.004 Tukang Cat 0.0090 OH 32,500.00 292.50 32,500.00 292.50 29,000.00 261.00
L.007 Kepala Tukang 0.0060 OH 35,000.00 210.00 35,000.00 210.00 31,500.00 189.00
L.010 Mandor 0.0025 OH 35,000.00 87.50 35,000.00 87.50 31,500.00 78.75
36 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
Pengecatan Bidang Kayu Baru( 1 lps plamir, 1 lps
SNI - M.6.9 M2 SNIM.6.9 29,734.00 SN2M.6.9 30,425.00 SNSM.6.9 29,168.75
cat dasar, 3 lps cat penutup ) Sek. Avian
M.011f Cat meni 0.2000 Kg 11,000.00 2,200.00 12,000.00 2,400.00 11,000.00 2,200.00
M.012b Plamir Kayu 0.1500 Kg 16,000.00 2,400.00 16,500.00 2,475.00 16,000.00 2,400.00
M.011 Cat dasar ( sek. Avian ) 0.1700 Kg 37,700.00 6,409.00 38,500.00 6,545.00 37,700.00 6,409.00
M.011 Cat Penutup ( sek. Avian ) 0.3500 Kg 37,700.00 13,195.00 38,500.00 13,475.00 37,700.00 13,195.00
L.008 Pekerja 0.0700 OH 27,000.00 1,890.00 27,000.00 1,890.00 24,500.00 1,715.00
L.004 Tukang Cat 0.1050 OH 32,500.00 3,412.50 32,500.00 3,412.50 29,000.00 3,045.00
L.007 Kepala Tukang 0.0040 OH 35,000.00 140.00 35,000.00 140.00 31,500.00 126.00
L.010 Mandor 0.0025 OH 35,000.00 87.50 35,000.00 87.50 31,500.00 78.75
Pengecatan Bidang Kayu Baru( 1 lps plamir, 1 lps
SNI - M.6.9a M2 SNIM.6.9 46,530.00 SN2M.6.9 47,325.00 SNSM.6.9 45,964.75
cat dasar, 3 lps cat penutup ) Sek. Dulux
M.011f Cat meni 0.2000 Kg 11,000.00 2,200.00 12,000.00 2,400.00 11,000.00 2,200.00
M.012b Plamir Kayu 0.1500 Kg 16,000.00 2,400.00 16,500.00 2,475.00 16,000.00 2,400.00
M.011 Cat dasar ( sek. Dulux ) 0.1700 Kg 70,000.00 11,900.00 71,000.00 12,070.00 70,000.00 11,900.00
M.011 Cat Penutup ( sek. Dulux ) 0.3500 Kg 70,000.00 24,500.00 71,000.00 24,850.00 70,000.00 24,500.00
L.008 Pekerja 0.0700 OH 27,000.00 1,890.00 27,000.00 1,890.00 24,500.00 1,715.00
L.004 Tukang Cat 0.1050 OH 32,500.00 3,412.50 32,500.00 3,412.50 29,000.00 3,045.00
L.007 Kepala Tukang 0.0040 OH 35,000.00 140.00 35,000.00 140.00 31,500.00 126.00
L.010 Mandor 0.0025 OH 35,000.00 87.50 35,000.00 87.50 31,500.00 78.75
SNI - M.6.11 Pelaburan Bidang Kayu dengan Politur M2 SNIM.6.11 27,389.50 SN2M.6.11 27,389.50 SNSM.6.11 27,114.75
M.012h Politur 0.1500 Ltr 36,000.00 5,400.00 36,000.00 5,400.00 36,000.00 5,400.00
M.012h Politur Jadi 0.3720 Ltr 36,000.00 13,392.00 36,000.00 13,392.00 36,000.00 13,392.00
M.012c Amplas 2.0000 Lbr 3,000.00 6,000.00 3,000.00 6,000.00 3,000.00 6,000.00
L.004 Tukang Cat 0.0600 OH 32,500.00 1,950.00 32,500.00 1,950.00 29,000.00 1,740.00
L.007 Kepala Tukang 0.0160 OH 35,000.00 560.00 35,000.00 560.00 31,500.00 504.00
L.010 Mandor 0.0025 OH 35,000.00 87.50 35,000.00 87.50 31,500.00 78.75
Pelaburan Bidang Kayu dengan Politur sek.
SNI - M.6.11a M2 SNIM.6.11 39,917.50 SN2M.6.11 39,917.50 SNSM.6.11 39,642.75
Mowilex
M.012h Politur 0.1500 Ltr 60,000.00 9,000.00 60,000.00 9,000.00 60,000.00 9,000.00
M.012h Politur Jadi 0.3720 Ltr 60,000.00 22,320.00 60,000.00 22,320.00 60,000.00 22,320.00
M.012c Amplas 2.0000 Lbr 3,000.00 6,000.00 3,000.00 6,000.00 3,000.00 6,000.00
L.004 Tukang Cat 0.0600 OH 32,500.00 1,950.00 32,500.00 1,950.00 29,000.00 1,740.00
L.007 Kepala Tukang 0.0160 OH 35,000.00 560.00 35,000.00 560.00 31,500.00 504.00
L.010 Mandor 0.0025 OH 35,000.00 87.50 35,000.00 87.50 31,500.00 78.75
Pelaburan Bidang Kayu dengan Cat Residu dan
SNI - M.6.12 M2 SNIM.6.12 5,710.00 SN2M.6.12 5,710.00 SNSM.6.12 5,439.00
Teer
M.012j Residu dan Teer 0.3500 Ltr 8,000.00 2,800.00 8,000.00 2,800.00 8,000.00 2,800.00
L.008 Pekerja 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.010 Mandor 0.0060 OH 35,000.00 210.00 35,000.00 210.00 31,500.00 189.00
Pengecatan Tembok Baru( 1 lps plamir, 1 lps cat
SNI - M.6.14 dasar, 2 lps cat penutup ) Sek. Mowilex untuk M2 SNIM.6.14 19,665.50 SN2M.6.14 19,845.50 SNSM.6.14 19,364.20
interior
M.012a Plamir Tembok 0.1000 Kg 7,500.00 750.00 7,500.00 750.00 7,500.00 750.00
M.011a Cat dasar ( sek. Mowilex ) 0.1000 Kg 44,500.00 4,450.00 45,000.00 4,500.00 44,500.00 4,450.00
M.011a Cat Penutup 2 kali ( sek. Mowilex ) 0.2600 Kg 44,500.00 11,570.00 45,000.00 11,700.00 44,500.00 11,570.00
L.008 Pekerja 0.0200 OH 27,000.00 540.00 27,000.00 540.00 24,500.00 490.00
L.004 Tukang Cat 0.0630 OH 32,500.00 2,047.50 32,500.00 2,047.50 29,000.00 1,827.00
L.007 Kepala Tukang 0.0063 OH 35,000.00 220.50 35,000.00 220.50 31,500.00 198.45
L.010 Mandor 0.0025 OH 35,000.00 87.50 35,000.00 87.50 31,500.00 78.75
Pengecatan Tembok Baru( 1 lps plamir, 1 lps cat
SNI - M.6.14a dasar, 2 lps cat penutup ) Sek. Mowilex untuk M2 SNIM.6.14a 27,405.50 SN2M.6.14a 27,405.50 SNSM.6.14a 27,104.20
Exterior
M.012a Plamir Tembok 0.1000 Kg 7,500.00 750.00 7,500.00 750.00 7,500.00 750.00
M.011a.1 Cat dasar ( sek. Mowilex ) 0.1000 Kg 66,000.00 6,600.00 66,000.00 6,600.00 66,000.00 6,600.00
M.011a.1 Cat Penutup 2 kali ( sek. Mowilex ) 0.2600 Kg 66,000.00 17,160.00 66,000.00 17,160.00 66,000.00 17,160.00
L.008 Pekerja 0.0200 OH 27,000.00 540.00 27,000.00 540.00 24,500.00 490.00
L.004 Tukang Cat 0.0630 OH 32,500.00 2,047.50 32,500.00 2,047.50 29,000.00 1,827.00
L.007 Kepala Tukang 0.0063 OH 35,000.00 220.50 35,000.00 220.50 31,500.00 198.45
L.010 Mandor 0.0025 OH 35,000.00 87.50 35,000.00 87.50 31,500.00 78.75
Pengecatan Tembok Baru( 1 lps plamir, 1 lps cat
SNI - M.6.14b M2 SNIM.6.14b 9,243.50 SN2M.6.14b 9,423.50 SNSM.6.14b 8,942.20
dasar, 2 lps cat penutup ) Sek. Catylac
M.012a Plamir Tembok 0.1000 Kg 7,500.00 750.00 7,500.00 750.00 7,500.00 750.00
M.011b Cat dasar ( sek. Catylac ) 0.1000 Kg 15,550.00 1,555.00 16,050.00 1,605.00 15,550.00 1,555.00
M.011b Cat Penutup 2 kali ( sek. Catylac ) 0.2600 Kg 15,550.00 4,043.00 16,050.00 4,173.00 15,550.00 4,043.00
L.008 Pekerja 0.0200 OH 27,000.00 540.00 27,000.00 540.00 24,500.00 490.00
L.004 Tukang Cat 0.0630 OH 32,500.00 2,047.50 32,500.00 2,047.50 29,000.00 1,827.00
L.007 Kepala Tukang 0.0063 OH 35,000.00 220.50 35,000.00 220.50 31,500.00 198.45
L.010 Mandor 0.0025 OH 35,000.00 87.50 35,000.00 87.50 31,500.00 78.75
Pengecatan Tembok Baru( 1 lps plamir, 1 lps cat
SNI - M.6.14c M2 SNIM.6.14c 8,235.50 SN2M.6.14c 8,415.50 SNSM.6.14c 7,934.20
dasar, 2 lps cat penutup ) Sek. Decolith
M.012a Plamir Tembok 0.1000 Kg 7,500.00 750.00 7,500.00 750.00 7,500.00 750.00
M.011c Cat dasar ( sek. Decolith ) 0.1000 Kg 12,750.00 1,275.00 13,250.00 1,325.00 12,750.00 1,275.00
M.011c Cat Penutup 2 kali ( sek. Decolith ) 0.2600 Kg 12,750.00 3,315.00 13,250.00 3,445.00 12,750.00 3,315.00
L.008 Pekerja 0.0200 OH 27,000.00 540.00 27,000.00 540.00 24,500.00 490.00
L.004 Tukang Cat 0.0630 OH 32,500.00 2,047.50 32,500.00 2,047.50 29,000.00 1,827.00
L.007 Kepala Tukang 0.0063 OH 35,000.00 220.50 35,000.00 220.50 31,500.00 198.45
L.010 Mandor 0.0025 OH 35,000.00 87.50 35,000.00 87.50 31,500.00 78.75
Pengecatan Tembok Baru( 1 lps plamir, 1 lps cat
SNI - M.6.14d M2 SNIM.6.14d 7,407.50 SN2M.6.14d 7,587.50 SNSM.6.14d 7,106.20
dasar, 2 lps cat penutup ) Sek. Mollex
M.012a Plamir Tembok 0.1000 Kg 7,500.00 750.00 7,500.00 750.00 7,500.00 750.00
M.011d Cat dasar ( sek. Mollex ) 0.1000 Kg 10,450.00 1,045.00 10,950.00 1,095.00 10,450.00 1,045.00
M.011d Cat Penutup 2 kali ( sek. MOllex ) 0.2600 Kg 10,450.00 2,717.00 10,950.00 2,847.00 10,450.00 2,717.00
L.008 Pekerja 0.0200 OH 27,000.00 540.00 27,000.00 540.00 24,500.00 490.00
L.004 Tukang Cat 0.0630 OH 32,500.00 2,047.50 32,500.00 2,047.50 29,000.00 1,827.00
L.007 Kepala Tukang 0.0063 OH 35,000.00 220.50 35,000.00 220.50 31,500.00 198.45
L.010 Mandor 0.0025 OH 35,000.00 87.50 35,000.00 87.50 31,500.00 78.75
37 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
Pengecatan Tembok Lama ( 1 lps cat dasar, 2 lps
SNI - M.6.15 M2 SNIM.6.15 15,705.50 SN2M.6.15 15,855.50 SNSM.6.15 15,465.05
cat penutup ) Sek. Mowilex untuk interior
M.011a Cat dasar ( sek. Mowilex ) 0.1200 Kg 44,500.00 5,340.00 45,000.00 5,400.00 44,500.00 5,340.00
M.011a Cat Penutup 2 kali ( sek. Mowilex ) 0.1800 Kg 44,500.00 8,010.00 45,000.00 8,100.00 44,500.00 8,010.00
L.008 Pekerja 0.0280 OH 27,000.00 756.00 27,000.00 756.00 24,500.00 686.00
L.004 Tukang Cat 0.0420 OH 32,500.00 1,365.00 32,500.00 1,365.00 29,000.00 1,218.00
L.007 Kepala Tukang 0.0042 OH 35,000.00 147.00 35,000.00 147.00 31,500.00 132.30
L.010 Mandor 0.0025 OH 35,000.00 87.50 35,000.00 87.50 31,500.00 78.75
Pengecatan Tembok Lama ( 1 lps cat dasar, 2 lps
SNI - M.6.15a M2 SNIM.6.15a 22,155.50 SN2M.6.15a 22,155.50 SNSM.6.15a 21,915.05
cat penutup ) Sek. Mowilex untuk Exterior
M.011a.1 Cat dasar ( sek. Mowilex ) 0.1200 Kg 66,000.00 7,920.00 66,000.00 7,920.00 66,000.00 7,920.00
M.011a.1 Cat Penutup 2 kali ( sek. Mowilex ) 0.1800 Kg 66,000.00 11,880.00 66,000.00 11,880.00 66,000.00 11,880.00
L.008 Pekerja 0.0280 OH 27,000.00 756.00 27,000.00 756.00 24,500.00 686.00
L.004 Tukang Cat 0.0420 OH 32,500.00 1,365.00 32,500.00 1,365.00 29,000.00 1,218.00
L.007 Kepala Tukang 0.0042 OH 35,000.00 147.00 35,000.00 147.00 31,500.00 132.30
L.010 Mandor 0.0025 OH 35,000.00 87.50 35,000.00 87.50 31,500.00 78.75
Pengecatan Tembok Lama ( 1 lps cat dasar, 2 lps
SNI - M.6.15b M2 SNIM.6.15b 7,020.50 SN2M.6.15b 7,170.50 SNSM.6.15b 6,780.05
cat penutup ) Sek. Catylac
M.011b Cat dasar ( sek. Catylac ) 0.1200 Kg 15,550.00 1,866.00 16,050.00 1,926.00 15,550.00 1,866.00
M.011b Cat Penutup 2 kali ( sek. Catylac ) 0.1800 Kg 15,550.00 2,799.00 16,050.00 2,889.00 15,550.00 2,799.00
L.008 Pekerja 0.0280 OH 27,000.00 756.00 27,000.00 756.00 24,500.00 686.00
L.004 Tukang Cat 0.0420 OH 32,500.00 1,365.00 32,500.00 1,365.00 29,000.00 1,218.00
L.007 Kepala Tukang 0.0042 OH 35,000.00 147.00 35,000.00 147.00 31,500.00 132.30
L.010 Mandor 0.0025 OH 35,000.00 87.50 35,000.00 87.50 31,500.00 78.75
Pengecatan Tembok Lama ( 1 lps cat dasar, 2 lps
SNI - M.6.15c M2 SNIM.6.15c 6,180.50 SN2M.6.15c 6,330.50 SNSM.6.15c 5,940.05
cat penutup ) Sek. Decolith
M.011c Cat dasar ( sek. Decolith ) 0.1200 Kg 12,750.00 1,530.00 13,250.00 1,590.00 12,750.00 1,530.00
M.011c Cat Penutup 2 kali ( sek. Decolith ) 0.1800 Kg 12,750.00 2,295.00 13,250.00 2,385.00 12,750.00 2,295.00
L.008 Pekerja 0.0280 OH 27,000.00 756.00 27,000.00 756.00 24,500.00 686.00
L.004 Tukang Cat 0.0420 OH 32,500.00 1,365.00 32,500.00 1,365.00 29,000.00 1,218.00
L.007 Kepala Tukang 0.0042 OH 35,000.00 147.00 35,000.00 147.00 31,500.00 132.30
L.010 Mandor 0.0025 OH 35,000.00 87.50 35,000.00 87.50 31,500.00 78.75
Pengecatan Tembok Lama ( 1 lps cat dasar, 2 lps
SNI - M.6.15d M2 SNIM.6.15d 5,490.50 SN2M.6.15d 5,640.50 SNSM.6.15d 5,250.05
cat penutup ) Sek. Mollex
M.011d Cat dasar ( sek. Mollex ) 0.1200 Kg 10,450.00 1,254.00 10,950.00 1,314.00 10,450.00 1,254.00
M.011d Cat Penutup 2 kali ( sek. MOllex ) 0.1800 Kg 10,450.00 1,881.00 10,950.00 1,971.00 10,450.00 1,881.00
L.008 Pekerja 0.0280 OH 27,000.00 756.00 27,000.00 756.00 24,500.00 686.00
L.004 Tukang Cat 0.0420 OH 32,500.00 1,365.00 32,500.00 1,365.00 29,000.00 1,218.00
L.007 Kepala Tukang 0.0042 OH 35,000.00 147.00 35,000.00 147.00 31,500.00 132.30
L.010 Mandor 0.0025 OH 35,000.00 87.50 35,000.00 87.50 31,500.00 78.75
SNI - M.6.17 Melabur Tembok dengan Kapur Sirih M2 SNIM.6.17 5,393.50 SN2M.6.17 5,443.50 SNSM.6.17 5,005.90
M.012c Amplas 0.1000 Lbr 3,000.00 300.00 3,000.00 300.00 3,000.00 300.00
M.012i Alang-alang 0.2500 Ikat 2,000.00 500.00 2,200.00 550.00 2,000.00 500.00
M.012m Perancah kayu 0.0020 M3 60,000.00 120.00 60,000.00 120.00 60,000.00 120.00
M.012f Kapur sirih/ Labur 0.1500 Kg 2,000.00 300.00 2,000.00 300.00 2,000.00 300.00
L.008 Pekerja 0.1500 OH 27,000.00 4,050.00 27,000.00 4,050.00 24,500.00 3,675.00
L.004 Tukang Cat 0.0010 OH 32,500.00 32.50 32,500.00 32.50 29,000.00 29.00
L.007 Kepala Tukang 0.0001 OH 35,000.00 3.50 35,000.00 3.50 31,500.00 3.15
L.010 Mandor 0.0025 OH 35,000.00 87.50 35,000.00 87.50 31,500.00 78.75
Melabur Tembok Lama dengan Kapur Sirih
SNI - M.6.18 M2 SNIM.6.18 2,067.50 SN2M.6.18 2,067.50 SNSM.6.18 1,939.50
( Untuk Pemeliharaan )
M.012m Perancah kayu 0.0020 M3 60,000.00 120.00 60,000.00 120.00 60,000.00 120.00
M.012f Kapur sirih/ Labur 0.3000 Kg 2,000.00 600.00 2,000.00 600.00 2,000.00 600.00
L.008 Pekerja 0.0400 OH 27,000.00 1,080.00 27,000.00 1,080.00 24,500.00 980.00
L.004 Tukang Cat 0.0050 OH 32,500.00 162.50 32,500.00 162.50 29,000.00 145.00
L.007 Kepala Tukang 0.0005 OH 35,000.00 17.50 35,000.00 17.50 31,500.00 15.75
L.010 Mandor 0.0025 OH 35,000.00 87.50 35,000.00 87.50 31,500.00 78.75
SNI - M.6.20 Pengecatan Permukaan baja dengan meni besi M2 SNIM.6.20 9,228.00 SN2M.6.20 9,330.00 SNSM.6.20 8,373.00
M.011h Meni Besi 0.1000 Kg 11,000.00 1,100.00 12,000.00 1,200.00 11,000.00 1,100.00
M.012n Kuas 0.0100 Bh 3,800.00 38.00 4,000.00 40.00 3,800.00 38.00
L.008 Pekerja 0.0200 OH 27,000.00 540.00 27,000.00 540.00 24,500.00 490.00
L.004 Tukang Cat 0.2000 OH 32,500.00 6,500.00 32,500.00 6,500.00 29,000.00 5,800.00
L.007 Kepala Tukang 0.0200 OH 35,000.00 700.00 35,000.00 700.00 31,500.00 630.00
L.010 Mandor 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
Pengecatan Permukaan baja dengan meni besi
SNI - M.6.21 M2 SNIM.6.21 16,370.50 SN2M.6.21 16,472.50 SNSM.6.21 14,853.00
dan perancah
M.011h Meni Besi 0.1000 Kg 11,000.00 1,100.00 12,000.00 1,200.00 11,000.00 1,100.00
M.012n Kuas 0.0100 Bh 3,800.00 38.00 4,000.00 40.00 3,800.00 38.00
M.012m Perancah Kayu 0.0020 M3 60,000.00 120.00 60,000.00 120.00 60,000.00 120.00
L.008 Pekerja 0.2500 OH 27,000.00 6,750.00 27,000.00 6,750.00 24,500.00 6,125.00
L.004 Tukang Cat 0.2250 OH 32,500.00 7,312.50 32,500.00 7,312.50 29,000.00 6,525.00
L.007 Kepala Tukang 0.0225 OH 35,000.00 787.50 35,000.00 787.50 31,500.00 708.75
L.010 Mandor 0.0075 OH 35,000.00 262.50 35,000.00 262.50 31,500.00 236.25
Pengecatan Permukaan baja lps seng (galbani)
SNI - M.6.24 secara manual sistem 3 lapis cat konvensional M2 SNIM.6.24 70,572.00 SN2M.6.24 70,860.00 SNSM.6.24 64,772.00
dengan tb. 200 um
M.011 Cat dasar 0.1100 Kg 37,700.00 4,147.00 38,500.00 4,235.00 37,700.00 4,147.00
M.011 Cat antara 0.1700 Kg 37,700.00 6,409.00 38,500.00 6,545.00 37,700.00 6,409.00
M.011 Cat penutup 0.0800 Kg 37,700.00 3,016.00 38,500.00 3,080.00 37,700.00 3,016.00
L.008 Pekerja 0.5000 OH 27,000.00 13,500.00 27,000.00 13,500.00 24,500.00 12,250.00
L.004 Tukang Cat 0.8000 OH 32,500.00 26,000.00 32,500.00 26,000.00 29,000.00 23,200.00
L.007 Kepala Tukang 0.3000 OH 35,000.00 10,500.00 35,000.00 10,500.00 31,500.00 9,450.00
L.010 Mandor 0.2000 OH 35,000.00 7,000.00 35,000.00 7,000.00 31,500.00 6,300.00
38 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10

ANALISA BOW
A. PEKERJAAN PAVING ###
BOW - KPU.
Pasang Paving Blok Natural M2 BKPU. IVa 64,200.00 KPU2.4a 65,950.00 KPUS.4a 62,360.00
IVa
M.013 Paving Blok Natural 6 cm 1.0000 M2 37,000.00 37,000.00 38,000.00 38,000.00 37,000.00 37,000.00
M.001a Pasir Pasang 0.1000 M3 85,000.00 8,500.00 92,500.00 9,250.00 85,000.00 8,500.00
L.001 Tukang Batu 0.2000 OH 32,500.00 6,500.00 32,500.00 6,500.00 29,000.00 5,800.00
L.007 Kepala Tukang 0.0200 OH 35,000.00 700.00 35,000.00 700.00 31,500.00 630.00
L.008 Pekerja 0.4000 OH 27,000.00 10,800.00 27,000.00 10,800.00 24,500.00 9,800.00
L.010 Mandor 0.0200 OH 35,000.00 700.00 35,000.00 700.00 31,500.00 630.00
BOW - KPU.
Pasang Paving Blok Warna M2 BKPU. IVb 87,200.00 KPU2.4b 88,950.00 KPUS.4b 85,360.00
IVb
M.013a Paving Blok Warna 6 cm 1.0000 M2 60,000.00 60,000.00 61,000.00 61,000.00 60,000.00 60,000.00
M.001a Pasir Pasang 0.1000 M3 85,000.00 8,500.00 92,500.00 9,250.00 85,000.00 8,500.00
L.001 Tukang Batu 0.2000 OH 32,500.00 6,500.00 32,500.00 6,500.00 29,000.00 5,800.00
L.007 Kepala Tukang 0.0200 OH 35,000.00 700.00 35,000.00 700.00 31,500.00 630.00
L.008 Pekerja 0.4000 OH 27,000.00 10,800.00 27,000.00 10,800.00 24,500.00 9,800.00
L.010 Mandor 0.0200 OH 35,000.00 700.00 35,000.00 700.00 31,500.00 630.00
BOW - KPU.
Pasang Paving Blok T : 8 cm, K-400 M2 BKPU. IVc 132,200.00 KPU2.4c 134,950.00 KPUS.4c 130,360.00
IVc
M.013b Paving Blok t : 8 cm K-400 1.0000 M2 105,000.00 105,000.00 107,000.00 107,000.00 105,000.00 105,000.00
M.001a Pasir Pasang 0.1000 M3 85,000.00 8,500.00 92,500.00 9,250.00 85,000.00 8,500.00
L.001 Tukang Batu 0.2000 OH 32,500.00 6,500.00 32,500.00 6,500.00 29,000.00 5,800.00
L.007 Kepala Tukang 0.0200 OH 35,000.00 700.00 35,000.00 700.00 31,500.00 630.00
L.008 Pekerja 0.4000 OH 27,000.00 10,800.00 27,000.00 10,800.00 24,500.00 9,800.00
L.010 Mandor 0.0200 OH 35,000.00 700.00 35,000.00 700.00 31,500.00 630.00
BOW - KPU.
Pasang Paving Blok T : 6 cm, K-300 M2 BOWKPU. IVd 92,200.00 KPU2.4d 93,950.00 KPUS.4d 90,360.00
IVd
M.013c Paving Blok t : 6 cm K-300 1.0000 M2 65,000.00 65,000.00 66,000.00 66,000.00 65,000.00 65,000.00
M.001a Pasir Pasang 0.1000 M3 85,000.00 8,500.00 92,500.00 9,250.00 85,000.00 8,500.00
L.001 Tukang Batu 0.2000 OH 32,500.00 6,500.00 32,500.00 6,500.00 29,000.00 5,800.00
L.007 Kepala Tukang 0.0200 OH 35,000.00 700.00 35,000.00 700.00 31,500.00 630.00
L.008 Pekerja 0.4000 OH 27,000.00 10,800.00 27,000.00 10,800.00 24,500.00 9,800.00
L.010 Mandor 0.0200 OH 35,000.00 700.00 35,000.00 700.00 31,500.00 630.00
BOW - KPU. Pasang Batu Andesit 20/20 cm (ex. Baseh) T
M2 BOWKPU. IVd 302,200.00 KPU2.4d 302,950.00 KPUS.4d 300,360.00
IVe = 6 cm
M.013d Batu Andesit 20/20 cm 1.0000 M2 275,000.00 275,000.00 275,000.00 275,000.00 275,000.00 275,000.00
M.001a Pasir Pasang 0.1000 M3 85,000.00 8,500.00 92,500.00 9,250.00 85,000.00 8,500.00
L.001 Tukang Batu 0.2000 OH 32,500.00 6,500.00 32,500.00 6,500.00 29,000.00 5,800.00
L.007 Kepala Tukang 0.0200 OH 35,000.00 700.00 35,000.00 700.00 31,500.00 630.00
L.008 Pekerja 0.4000 OH 27,000.00 10,800.00 27,000.00 10,800.00 24,500.00 9,800.00
L.010 Mandor 0.0200 OH 35,000.00 700.00 35,000.00 700.00 31,500.00 630.00
B. PEKERJAAN KAP BESI

BOW - I.a Pekerjaan Kap Besi Kg BOW.Ia 21,805.00 BOW2.Ia 22,905.00 BOWS.Ia 21,160.00
M.003b Besi Siku/Propil 1.1000 Kg 14,000.00 15,400.00 15,000.00 16,500.00 14,000.00 15,400.00
L.003 Tukang Besi 0.0900 OH 32,500.00 2,925.00 32,500.00 2,925.00 29,000.00 2,610.00
L.007 Kepala Tukang 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
L.008 Pekerja 0.0900 OH 27,000.00 2,430.00 27,000.00 2,430.00 24,500.00 2,205.00
C. PEKERJAAN KAYU

BOW - F.16 Pasang Kembali Usuk dan Reng Bekas M2 BOWF.16 10,975.00 BOW2F.16 10,975.00 BOWSF.16 10,322.50
M.006 Paku Biasa ( 2" - 5") 0.2500 Kg 18,000.00 4,500.00 18,000.00 4,500.00 18,000.00 4,500.00
L.002 Tukang Kayu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.008 Pekerja 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
BOW - F.16a Pasang Reng Kayu Kruing M2 BOWF.16a 22,796.25 BOW2F.16a 23,021.25 BOWSF.16a 22,306.88
M.005h Kayu Kruing 0.0030 M3 4,900,000.00 14,700.00 4,975,000.00 14,925.00 4,900,000.00 14,700.00
M.006 Paku Biasa ( 2" - 5") 0.1800 Kg 18,000.00 3,240.00 18,000.00 3,240.00 18,000.00 3,240.00
L.002 Tukang Kayu 0.0750 OH 32,500.00 2,437.50 32,500.00 2,437.50 29,000.00 2,175.00
L.007 Kepala Tukang 0.0075 OH 35,000.00 262.50 35,000.00 262.50 31,500.00 236.25
L.008 Pekerja 0.0750 OH 27,000.00 2,025.00 27,000.00 2,025.00 24,500.00 1,837.50
L.010 Mandor 0.0038 OH 35,000.00 131.25 35,000.00 131.25 31,500.00 118.13
Pasang Usuk Diketam Halus dan Reng Kayu
BOW - F.16b M2 BOWF.16b 76,250.00 BOW2F.16b 77,150.00 BOWSF.16b 74,945.00
Kruing
M.005h Kayu Kruing 0.0120 M3 4,900,000.00 58,800.00 4,975,000.00 59,700.00 4,900,000.00 58,800.00
M.006 Paku Biasa ( 2" - 5") 0.2500 Kg 18,000.00 4,500.00 18,000.00 4,500.00 18,000.00 4,500.00
L.002 Tukang Kayu 0.2000 OH 32,500.00 6,500.00 32,500.00 6,500.00 29,000.00 5,800.00
L.007 Kepala Tukang 0.0200 OH 35,000.00 700.00 35,000.00 700.00 31,500.00 630.00
L.008 Pekerja 0.2000 OH 27,000.00 5,400.00 27,000.00 5,400.00 24,500.00 4,900.00
L.010 Mandor 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
Pasang Usuk Diketam Halus dan Reng Kayu
BOW - F.16c M2 BOWF.16c 95,450.00 BOW2F.16c 96,350.00 BOWSF.16c 94,145.00
Bangkir
M.005i Kayu Bangkir 0.0120 M3 6,500,000.00 78,000.00 6,575,000.00 78,900.00 6,500,000.00 78,000.00
M.006 Paku Biasa ( 2" - 5") 0.2500 Kg 18,000.00 4,500.00 18,000.00 4,500.00 18,000.00 4,500.00
L.002 Tukang Kayu 0.2000 OH 32,500.00 6,500.00 32,500.00 6,500.00 29,000.00 5,800.00
L.007 Kepala Tukang 0.0200 OH 35,000.00 700.00 35,000.00 700.00 31,500.00 630.00
L.008 Pekerja 0.2000 OH 27,000.00 5,400.00 27,000.00 5,400.00 24,500.00 4,900.00
L.010 Mandor 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
Pasang Usuk Diketam Halus dan Reng Kayu
BOW - F.16d M2 BOWF.16d 87,050.00 BOW2F.16d 87,950.00 BOWSF.16d 85,745.00
Kamper
M.005j Kayu Kamper 0.0120 M3 5,800,000.00 69,600.00 5,875,000.00 70,500.00 5,800,000.00 69,600.00
M.006 Paku Biasa ( 2" - 5") 0.2500 Kg 18,000.00 4,500.00 18,000.00 4,500.00 18,000.00 4,500.00
L.002 Tukang Kayu 0.2000 OH 32,500.00 6,500.00 32,500.00 6,500.00 29,000.00 5,800.00
L.007 Kepala Tukang 0.0200 OH 35,000.00 700.00 35,000.00 700.00 31,500.00 630.00
L.008 Pekerja 0.2000 OH 27,000.00 5,400.00 27,000.00 5,400.00 24,500.00 4,900.00
L.010 Mandor 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
39 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
BOW - F.16e Pasang Usuk Diketam Halus dan Reng Kayu Jati M2 BOWF.16e 136,250.00 BOW2F.16e 137,150.00 BOWSF.16e 134,945.00
M.005k Kayu Jati 0.0120 M3 9,900,000.00 118,800.00 9,975,000.00 119,700.00 9,900,000.00 118,800.00
M.006 Paku Biasa ( 2" - 5") 0.2500 Kg 18,000.00 4,500.00 18,000.00 4,500.00 18,000.00 4,500.00
L.002 Tukang Kayu 0.2000 OH 32,500.00 6,500.00 32,500.00 6,500.00 29,000.00 5,800.00
L.007 Kepala Tukang 0.0200 OH 35,000.00 700.00 35,000.00 700.00 31,500.00 630.00
L.008 Pekerja 0.2000 OH 27,000.00 5,400.00 27,000.00 5,400.00 24,500.00 4,900.00
L.010 Mandor 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
BOW - F.16f Pasang Usuk Kayu Kruing M2 BOWF.16f 67,031.25 BOW2F.16f 67,931.25 BOWSF.16f 66,541.88
M.005h Kayu Kruing 0.0120 M3 4,900,000.00 58,800.00 4,975,000.00 59,700.00 4,900,000.00 58,800.00
M.006 Paku Biasa ( 2" - 5") 0.1875 Kg 18,000.00 3,375.00 18,000.00 3,375.00 18,000.00 3,375.00
L.002 Tukang Kayu 0.0750 OH 32,500.00 2,437.50 32,500.00 2,437.50 29,000.00 2,175.00
L.007 Kepala Tukang 0.0075 OH 35,000.00 262.50 35,000.00 262.50 31,500.00 236.25
L.008 Pekerja 0.0750 OH 27,000.00 2,025.00 27,000.00 2,025.00 24,500.00 1,837.50
L.010 Mandor 0.0038 OH 35,000.00 131.25 35,000.00 131.25 31,500.00 118.13
BOW - F.16g Pasang Usuk Kayu Bangkir M2 BOWF.16g 86,231.25 BOW2F.16g 87,131.25 BOWSF.16g 85,741.88
M.005i Kayu Bangkir 0.0120 M3 6,500,000.00 78,000.00 6,575,000.00 78,900.00 6,500,000.00 78,000.00
M.006 Paku Biasa ( 2" - 5") 0.1875 Kg 18,000.00 3,375.00 18,000.00 3,375.00 18,000.00 3,375.00
L.002 Tukang Kayu 0.0750 OH 32,500.00 2,437.50 32,500.00 2,437.50 29,000.00 2,175.00
L.007 Kepala Tukang 0.0075 OH 35,000.00 262.50 35,000.00 262.50 31,500.00 236.25
L.008 Pekerja 0.0750 OH 27,000.00 2,025.00 27,000.00 2,025.00 24,500.00 1,837.50
L.010 Mandor 0.0038 OH 35,000.00 131.25 35,000.00 131.25 31,500.00 118.13
BOW - F.16h Pasang Reng Kayu Jati ( Kw.Eksport) M2 BOWF.16h 83,096.25 BOW2F.16h 83,321.25 BOWSF.16h 82,606.88
M.005f3 Kayu Jati ( Kw.Eksport) 0.0030 M3 25,000,000.00 75,000.00 25,075,000.00 75,225.00 25,000,000.00 75,000.00
M.006 Paku Biasa ( 2" - 5") 0.1800 Kg 18,000.00 3,240.00 18,000.00 3,240.00 18,000.00 3,240.00
L.002 Tukang Kayu 0.0750 OH 32,500.00 2,437.50 32,500.00 2,437.50 29,000.00 2,175.00
L.007 Kepala Tukang 0.0075 OH 35,000.00 262.50 35,000.00 262.50 31,500.00 236.25
L.008 Pekerja 0.0750 OH 27,000.00 2,025.00 27,000.00 2,025.00 24,500.00 1,837.50
L.010 Mandor 0.0038 OH 35,000.00 131.25 35,000.00 131.25 31,500.00 118.13
BOW - F.16i Pasang Reng Kayu Bangkir M2 BOWF.16i 27,596.25 BOW2F.16i 27,821.25 BOWSF.16i 27,106.88
M.005i Kayu Bangkir 0.0030 M3 6,500,000.00 19,500.00 6,575,000.00 19,725.00 6,500,000.00 19,500.00
M.006 Paku Biasa ( 2" - 5") 0.1800 Kg 18,000.00 3,240.00 18,000.00 3,240.00 18,000.00 3,240.00
L.002 Tukang Kayu 0.0750 OH 32,500.00 2,437.50 32,500.00 2,437.50 29,000.00 2,175.00
L.007 Kepala Tukang 0.0075 OH 35,000.00 262.50 35,000.00 262.50 31,500.00 236.25
L.008 Pekerja 0.0750 OH 27,000.00 2,025.00 27,000.00 2,025.00 24,500.00 1,837.50
L.010 Mandor 0.0038 OH 35,000.00 131.25 35,000.00 131.25 31,500.00 118.13
BOW -
Pasang Plapond Harplek Diatas usuk M2 BOWSupl.VIIIa 24,537.00 B2.Sup8a 25,087.00 BS.Sup8a 24,037.00
Supl.VIIIa
M.007a Harplek 4 mm 1.1000 M2 17,000.00 18,700.00 17,500.00 19,250.00 17,000.00 18,700.00
M.006a Paku Eternit, Lis 0.0200 Kg 21,850.00 437.00 21,850.00 437.00 21,850.00 437.00
L.008 Pekerja 0.2000 OH 27,000.00 5,400.00 27,000.00 5,400.00 24,500.00 4,900.00
L.010 Mandor 0.0200 OH 35,000.00 700.00 35,000.00 700.00 31,500.00 630.00
BOW -
Pasang Plapond Eternit Diatas usuk M2 BOWSupl.VIIIb 14,237.00 B2.Sup8b 14,457.00 BS.Sup8b 13,667.00
Supl.VIIIb
M.007 Eternit Kerang Super 1.1000 Lb 7,000.00 7,700.00 7,200.00 7,920.00 7,000.00 7,700.00
M.006a Paku Eternit, Lis 0.0200 Kg 21,850.00 437.00 21,850.00 437.00 21,850.00 437.00
L.008 Pekerja 0.2000 OH 27,000.00 5,400.00 27,000.00 5,400.00 24,500.00 4,900.00
L.010 Mandor 0.0200 OH 35,000.00 700.00 35,000.00 700.00 31,500.00 630.00
BOW - F.36a Pintu Kaca Kayu Kruing tb. 3,5 cm M2 BOWF.36a 436,237.00 BOW2F.36a 438,637.00 BOWSF.36a 407,787.00
M.005m Kayu Kruing 0.0180 M3 6,100,000.00 109,800.00 6,175,000.00 111,150.00 6,100,000.00 109,800.00
M.008a Kaca Bening 5 mm 0.7000 M2 75,000.00 52,500.00 76,500.00 53,550.00 75,000.00 52,500.00
M.006a Paku Eternit,Lis 0.0200 Kg 21,850.00 437.00 21,850.00 437.00 21,850.00 437.00
L.002 Tukang Kayu 6.0000 OH 32,500.00 195,000.00 32,500.00 195,000.00 29,000.00 174,000.00
L.007 Kepala Tukang 0.6000 OH 35,000.00 21,000.00 35,000.00 21,000.00 31,500.00 18,900.00
L.008 Pekerja 2.0000 OH 27,000.00 54,000.00 27,000.00 54,000.00 24,500.00 49,000.00
L.010 Mandor 0.1000 OH 35,000.00 3,500.00 35,000.00 3,500.00 31,500.00 3,150.00
BOW - F.36b Pintu Kaca Kayu Kruing Sederhana tb. 3,5 cm M2 BOWF.36b 332,547.00 BOW2F.36b 334,797.00 BOWSF.36b 313,612.00
M.005m Kayu Kruing 0.0160 M3 6,100,000.00 97,600.00 6,175,000.00 98,800.00 6,100,000.00 97,600.00
M.008a Kaca Bening 5 mm 0.7000 M2 75,000.00 52,500.00 76,500.00 53,550.00 75,000.00 52,500.00
M.006a Paku Eternit,Lis 0.0200 Kg 21,850.00 437.00 21,850.00 437.00 21,850.00 437.00
L.002 Tukang Kayu 4.0000 OH 32,500.00 130,000.00 32,500.00 130,000.00 29,000.00 116,000.00
L.007 Kepala Tukang 0.4000 OH 35,000.00 14,000.00 35,000.00 14,000.00 31,500.00 12,600.00
L.008 Pekerja 1.3300 OH 27,000.00 35,910.00 27,000.00 35,910.00 24,500.00 32,585.00
L.010 Mandor 0.0600 OH 35,000.00 2,100.00 35,000.00 2,100.00 31,500.00 1,890.00
BOW - F.36c Pintu Kaca Kayu Bangkir tb. 3,5 cm M2 BOWF.36c 488,437.00 BOW2F.36c 490,837.00 BOWSF.36c 459,987.00
M.005n Kayu Bangkir 0.0180 M3 9,000,000.00 162,000.00 9,075,000.00 163,350.00 9,000,000.00 162,000.00
M.008a Kaca Bening 5 mm 0.7000 M2 75,000.00 52,500.00 76,500.00 53,550.00 75,000.00 52,500.00
M.006a Paku Eternit,Lis 0.0200 Kg 21,850.00 437.00 21,850.00 437.00 21,850.00 437.00
L.002 Tukang Kayu 6.0000 OH 32,500.00 195,000.00 32,500.00 195,000.00 29,000.00 174,000.00
L.007 Kepala Tukang 0.6000 OH 35,000.00 21,000.00 35,000.00 21,000.00 31,500.00 18,900.00
L.008 Pekerja 2.0000 OH 27,000.00 54,000.00 27,000.00 54,000.00 24,500.00 49,000.00
L.010 Mandor 0.1000 OH 35,000.00 3,500.00 35,000.00 3,500.00 31,500.00 3,150.00
BOW - F.36d Pintu Kaca Kayu Kamper tb. 3,5 cm M2 BOWF.36d 479,437.00 BOW2F.36d 481,837.00 BOWSF.36d 450,987.00
M.005o Kayu Kamper 0.0180 M3 8,500,000.00 153,000.00 8,575,000.00 154,350.00 8,500,000.00 153,000.00
M.008a Kaca Bening 5 mm 0.7000 M2 75,000.00 52,500.00 76,500.00 53,550.00 75,000.00 52,500.00
M.006a Paku Eternit,Lis 0.0200 Kg 21,850.00 437.00 21,850.00 437.00 21,850.00 437.00
L.002 Tukang Kayu 6.0000 OH 32,500.00 195,000.00 32,500.00 195,000.00 29,000.00 174,000.00
L.007 Kepala Tukang 0.6000 OH 35,000.00 21,000.00 35,000.00 21,000.00 31,500.00 18,900.00
L.008 Pekerja 2.0000 OH 27,000.00 54,000.00 27,000.00 54,000.00 24,500.00 49,000.00
L.010 Mandor 0.1000 OH 35,000.00 3,500.00 35,000.00 3,500.00 31,500.00 3,150.00
40 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
BOW - F.36e Pintu Kaca Kayu Jati tb. 3,5 cm M2 BOWF.36e 540,037.00 BOW2F.36e 544,187.00 BOWSF.36e 511,587.00
M.005p Kayu Jati 0.0180 M3 12,800,000 230,400.00 12,875,000 231,750.00 12,800,000 230,400.00
M.008a Kaca Bening 5 mm 0.7000 M2 51,000 35,700.00 55,000 38,500.00 51,000 35,700.00
M.006a Paku Eternit,Lis 0.0200 Kg 21,850 437.00 21,850 437.00 21,850 437.00
L.002 Tukang Kayu 6.0000 OH 32,500 195,000.00 32,500 195,000.00 29,000 174,000.00
L.007 Kepala Tukang 0.6000 OH 35,000 21,000.00 35,000 21,000.00 31,500 18,900.00
L.008 Pekerja 2.0000 OH 27,000 54,000.00 27,000 54,000.00 24,500 49,000.00
L.010 Mandor 0.1000 OH 35,000 3,500.00 35,000 3,500.00 31,500 3,150.00
BOW - F.36f Jendela Kaca Kayu Kruing tb. 3 cm M2 BOWF.36f 314,462.00 BOW2F.36f 318,162.00 BOWSF.36f 293,124.50
M.005m Kayu Kruing 0.0120 M3 6,100,000.00 73,200.00 6,175,000 74,100.00 6,100,000.00 73,200.00
M.008 Kaca Bening 3 mm 0.7000 M2 51,000.00 35,700.00 55,000 38,500.00 51,000.00 35,700.00
M.006a Paku Eternit,Lis 0.0200 Kg 21,850.00 437.00 21,850 437.00 21,850.00 437.00
L.002 Tukang Kayu 4.5000 OH 32,500.00 146,250.00 32,500 146,250.00 29,000.00 130,500.00
L.007 Kepala Tukang 0.4500 OH 35,000.00 15,750.00 35,000 15,750.00 31,500.00 14,175.00
L.008 Pekerja 1.5000 OH 27,000.00 40,500.00 27,000 40,500.00 24,500.00 36,750.00
L.010 Mandor 0.0750 OH 35,000.00 2,625.00 35,000 2,625.00 31,500.00 2,362.50
BOW - F.36g Jendela Kaca Kayu Kruing Sederhana tb. 3 cm M2 BOWF.36g 246,087.00 BOW2F.36g 249,787.00 BOWSF.36g 231,862.00
M.005m Kayu Kruing 0.0120 M3 6,100,000.00 73,200.00 6,175,000.00 74,100.00 6,100,000.00 73,200.00
M.008 Kaca Bening 3 mm 0.7000 M2 51,000.00 35,700.00 55,000.00 38,500.00 51,000.00 35,700.00
M.006a Paku Eternit,Lis 0.0200 Kg 21,850.00 437.00 21,850.00 437.00 21,850.00 437.00
L.002 Tukang Kayu 3.0000 OH 32,500.00 97,500.00 32,500.00 97,500.00 29,000.00 87,000.00
L.007 Kepala Tukang 0.3000 OH 35,000.00 10,500.00 35,000.00 10,500.00 31,500.00 9,450.00
L.008 Pekerja 1.0000 OH 27,000.00 27,000.00 27,000.00 27,000.00 24,500.00 24,500.00
L.010 Mandor 0.0500 OH 35,000.00 1,750.00 35,000.00 1,750.00 31,500.00 1,575.00
BOW - F.36h Jendela Kaca Kayu Bangkir tb. 3 cm M2 BOWF.36h 349,262.00 BOW2F.36h 352,962.00 BOWSF.36h 327,924.50
M.005n Kayu Bangkir 0.0120 M3 9,000,000.00 108,000.00 9,075,000.00 108,900.00 9,000,000.00 108,000.00
M.008 Kaca Bening 3 mm 0.7000 M2 51,000.00 35,700.00 55,000.00 38,500.00 51,000.00 35,700.00
M.006a Paku Eternit,Lis 0.0200 Kg 21,850.00 437.00 21,850.00 437.00 21,850.00 437.00
L.002 Tukang Kayu 4.5000 OH 32,500.00 146,250.00 32,500.00 146,250.00 29,000.00 130,500.00
L.007 Kepala Tukang 0.4500 OH 35,000.00 15,750.00 35,000.00 15,750.00 31,500.00 14,175.00
L.008 Pekerja 1.5000 OH 27,000.00 40,500.00 27,000.00 40,500.00 24,500.00 36,750.00
L.010 Mandor 0.0750 OH 35,000.00 2,625.00 35,000.00 2,625.00 31,500.00 2,362.50
BOW - F.36i Jendela Kaca Kayu Kamper tb. 3 cm M2 BOWF.36i 343,262.00 BOW2F.36i 346,962.00 BOWSF.36i 321,924.50
M.005o Kayu Kamper 0.0120 M3 8,500,000.00 102,000.00 8,575,000.00 102,900.00 8,500,000.00 102,000.00
M.008 Kaca Bening 3 mm 0.7000 M2 51,000.00 35,700.00 55,000.00 38,500.00 51,000.00 35,700.00
M.006a Paku Eternit,Lis 0.0200 Kg 21,850.00 437.00 21,850.00 437.00 21,850.00 437.00
L.002 Tukang Kayu 4.5000 OH 32,500.00 146,250.00 32,500.00 146,250.00 29,000.00 130,500.00
L.007 Kepala Tukang 0.4500 OH 35,000.00 15,750.00 35,000.00 15,750.00 31,500.00 14,175.00
L.008 Pekerja 1.5000 OH 27,000.00 40,500.00 27,000.00 40,500.00 24,500.00 36,750.00
L.010 Mandor 0.0750 OH 35,000.00 2,625.00 35,000.00 2,625.00 31,500.00 2,362.50
BOW - F.36j Jendela Kaca Kayu Jati tb. 3 cm M2 BOWF.36j 394,862.00 BOW2F.36j 398,562.00 BOWSF.36j 373,524.50
M.005p Kayu Jati 0.0120 M3 12,800,000.00 153,600.00 12,875,000.00 154,500.00 12,800,000.00 153,600.00
M.008 Kaca Bening 3 mm 0.7000 M2 51,000.00 35,700.00 55,000.00 38,500.00 51,000.00 35,700.00
M.006a Paku Eternit,Lis 0.0200 Kg 21,850.00 437.00 21,850.00 437.00 21,850.00 437.00
L.002 Tukang Kayu 4.5000 OH 32,500.00 146,250.00 32,500.00 146,250.00 29,000.00 130,500.00
L.007 Kepala Tukang 0.4500 OH 35,000.00 15,750.00 35,000.00 15,750.00 31,500.00 14,175.00
L.008 Pekerja 1.5000 OH 27,000.00 40,500.00 27,000.00 40,500.00 24,500.00 36,750.00
L.010 Mandor 0.0750 OH 35,000.00 2,625.00 35,000.00 2,625.00 31,500.00 2,362.50
Pintu Panil Multiplek 9mm Rngka Kayu Jati ( tb.
BOW - F.36k M2 BOWF.36k 464,420.00 BOW2F.36k 466,890.00 BOWSF.36k 445,464.00
3,5 cm )
M.005p Kayu Jati 0.0180 M3 12,800,000.00 230,400.00 12,875,000.00 231,750.00 12,800,000.00 230,400.00
M.009b Multiplek 9 mm 0.7000 M2 74,000.00 51,800.00 75,600.00 52,920.00 74,000.00 51,800.00
L.002 Tukang Kayu 4.0000 OH 32,500.00 130,000.00 32,500.00 130,000.00 29,000.00 116,000.00
L.007 Kepala Tukang 0.4000 OH 35,000.00 14,000.00 35,000.00 14,000.00 31,500.00 12,600.00
L.008 Pekerja 1.3300 OH 27,000.00 35,910.00 27,000.00 35,910.00 24,500.00 32,585.00
L.010 Mandor 0.0660 OH 35,000.00 2,310.00 35,000.00 2,310.00 31,500.00 2,079.00
Pintu Panil Multiplek 9mm Rangka Kayu Kruing
BOW - F.36l M2 BOWF.36l 343,820.00 BOW2F.36l 346,290.00 BOWSF.36l 324,864.00
( tb. 3,5 cm )
M.005m Kayu Kruing 0.0180 M3 6,100,000.00 109,800.00 6,175,000.00 111,150.00 6,100,000.00 109,800.00
M.009b Multiplek 9 mm 0.7000 M2 74,000.00 51,800.00 75,600.00 52,920.00 74,000.00 51,800.00
L.002 Tukang Kayu 4.0000 OH 32,500.00 130,000.00 32,500.00 130,000.00 29,000.00 116,000.00
L.007 Kepala Tukang 0.4000 OH 35,000.00 14,000.00 35,000.00 14,000.00 31,500.00 12,600.00
L.008 Pekerja 1.3300 OH 27,000.00 35,910.00 27,000.00 35,910.00 24,500.00 32,585.00
L.010 Mandor 0.0660 OH 35,000.00 2,310.00 35,000.00 2,310.00 31,500.00 2,079.00
Pintu Panil Multiplek 9mm Rangka Kayu
BOW - F.36m M2 BOWF.36m 396,020.00 BOW2F.36m 398,490.00 BOWSF.36m 377,064.00
Bangkir( tb. 3,5 cm )
M.005n Kayu Bangkir 0.0180 M3 9,000,000.00 162,000.00 9,075,000.00 163,350.00 9,000,000.00 162,000.00
M.009b Multiplek 9 mm 0.7000 M2 74,000.00 51,800.00 75,600.00 52,920.00 74,000.00 51,800.00
L.002 Tukang Kayu 4.0000 OH 32,500.00 130,000.00 32,500.00 130,000.00 29,000.00 116,000.00
L.007 Kepala Tukang 0.4000 OH 35,000.00 14,000.00 35,000.00 14,000.00 31,500.00 12,600.00
L.008 Pekerja 1.3300 OH 27,000.00 35,910.00 27,000.00 35,910.00 24,500.00 32,585.00
L.010 Mandor 0.0660 OH 35,000.00 2,310.00 35,000.00 2,310.00 31,500.00 2,079.00
Pintu Panil Multiplek 9mm Rangka Kayu Kamper
BOW - F.36n M2 BOWF.36n 325,300.00 BOW2F.36n 326,420.00 BOWSF.36n 296,850.00
( tb. 3,5 cm )
M.005o Kayu Kamper 0.0180 M3 8,500,000.00 153,000.00 8,575,000.00 154,350.00 8,500,000.00 153,000.00
M.009b Multiplek 9 mm 0.7000 M2 74,000.00 51,800.00 75,600.00 52,920.00 74,000.00 51,800.00
L.002 Tukang Kayu 6.0000 OH 32,500.00 195,000.00 32,500.00 195,000.00 29,000.00 174,000.00
L.007 Kepala Tukang 0.6000 OH 35,000.00 21,000.00 35,000.00 21,000.00 31,500.00 18,900.00
L.008 Pekerja 2.0000 OH 27,000.00 54,000.00 27,000.00 54,000.00 24,500.00 49,000.00
L.010 Mandor 0.1000 OH 35,000.00 3,500.00 35,000.00 3,500.00 31,500.00 3,150.00
41 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
D. PEKERJAAN PENGECATAN

BOW - K.6+23 Pengecatan plapond 3x ( sek. Catylac ) M2 BOWK.623 16,563.75 BOW2K.623 16,763.75 BOWSK.623 15,507.50
M.011b Cat Tembok ( sek. Catylac ) 0.4000 Kg 15,550.00 6,220.00 16,050.00 6,420.00 15,550.00 6,220.00
L.004 Tukang Cat 0.1875 OH 32,500.00 6,093.75 32,500.00 6,093.75 29,000.00 5,437.50
L.007 Kepala Tukang 0.0188 OH 35,000.00 658.00 35,000.00 658.00 31,500.00 592.20
L.008 Pekerja 0.1250 OH 27,000.00 3,375.00 27,000.00 3,375.00 24,500.00 3,062.50
L.010 Mandor 0.0062 OH 35,000.00 217.00 35,000.00 217.00 31,500.00 195.30
BOW -
Pengecatan plapond 3x ( sek. Decolith ) M2 BOWK.623a 15,442.00 BOW2K.623a 15,642.00 BOWSK.623a 14,385.93
K.6+23a
M.011c Cat Tembok ( sek. Decolith) 0.4000 Kg 12,750.00 5,100.00 13,250.00 5,300.00 12,750.00 5,100.00
L.004 Tukang Cat 0.1875 OH 32,500.00 6,093.75 32,500.00 6,093.75 29,000.00 5,437.50
L.007 Kepala Tukang 0.0188 OH 35,000.00 656.25 35,000.00 656.25 31,500.00 590.63
L.008 Pekerja 0.1250 OH 27,000.00 3,375.00 27,000.00 3,375.00 24,500.00 3,062.50
L.010 Mandor 0.0062 OH 35,000.00 217.00 35,000.00 217.00 31,500.00 195.30
BOW -
Pengecatan plapond 3x ( sek. Mollex ) M2 BOWK.623b 14,522.00 BOW2K.623b 14,722.00 BOWSK.623b 13,465.93
K.6+23b
M.011d Cat Tembok ( sek. Mollex) 0.4000 Kg 10,450.00 4,180.00 10,950.00 4,380.00 10,450.00 4,180.00
L.004 Tukang Cat 0.1875 OH 32,500.00 6,093.75 32,500.00 6,093.75 29,000.00 5,437.50
L.007 Kepala Tukang 0.0188 OH 35,000.00 656.25 35,000.00 656.25 31,500.00 590.63
L.008 Pekerja 0.1250 OH 27,000.00 3,375.00 27,000.00 3,375.00 24,500.00 3,062.50
L.010 Mandor 0.0062 OH 35,000.00 217.00 35,000.00 217.00 31,500.00 195.30
BOW -
Pengecatan Genteng 3x M2 BOWK.623c 18,142.00 BOW2K.623c 18,292.00 BOWSK.623c 17,085.93
K.6+23c
M.011e Cat Genteng 0.3000 Kg 26,000.00 7,800.00 26,500.00 7,950.00 26,000.00 7,800.00
L.004 Tukang Cat 0.1875 OH 32,500.00 6,093.75 32,500.00 6,093.75 29,000.00 5,437.50
L.007 Kepala Tukang 0.0188 OH 35,000.00 656.25 35,000.00 656.25 31,500.00 590.63
L.008 Pekerja 0.1250 OH 27,000.00 3,375.00 27,000.00 3,375.00 24,500.00 3,062.50
L.010 Mandor 0.0062 OH 35,000.00 217.00 35,000.00 217.00 31,500.00 195.30
E. PEKERJAAN BETON

BOW - F.8 Cetakan Beton Kayu Tahun M2 BOWF.8 95,750.00 BOW2F.8 97,750.00 BOWSF.8 92,290.00
M.005a Kayu Tahun 0.0400 M3 1,350,000.00 54,000.00 1,400,000.00 56,000.00 1,350,000.00 54,000.00
M.006 Paku Biasa ( 2" - 5") 0.4000 Kg 18,000.00 7,200.00 18,000.00 7,200.00 18,000.00 7,200.00
L.002 Tukang Kayu 0.5000 OH 32,500.00 16,250.00 32,500.00 16,250.00 29,000.00 14,500.00
L.007 Kepala Tukang 0.0500 OH 35,000.00 1,750.00 35,000.00 1,750.00 31,500.00 1,575.00
L.008 Pekerja 0.2000 OH 27,000.00 5,400.00 27,000.00 5,400.00 24,500.00 4,900.00
L.010 Mandor 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.009 Pekerja Bongkar / Siram 0.4000 OH 27,000.00 10,800.00 27,000.00 10,800.00 24,500.00 9,800.00
BOW-G.14 Perekat camp. 1 PC : 2 Psr M3 BOWG.14 785,390.00 BOW2G.14 796,625.40 BOWSG.14 785,390.00
M.002a Portland Cement 587.2000 Kg 1,200.00 704,640.00 1,207.00 708,750.40 1,200.00 704,640.00
M.001a Pasir Pasang 0.9500 M3 85,000.00 80,750.00 92,500.00 87,875.00 85,000.00 80,750.00
BOW-G.13 Perekat camp. 1 PC : 2 Psr M3 BOWG.13 1,108,840.00 BOW2G.13 1,120,211.15 BOWSG.13 1,108,840.00
M.002a Portland Cement 874.4500 Kg 1,200.00 1,049,340.00 1,207.00 1,055,461.15 1,200.00 1,049,340.00
M.001a Pasir Pasang 0.7000 M3 85,000.00 59,500.00 92,500.00 64,750.00 85,000.00 59,500.00
BOW-G.77 Upah Pasang Lembaran Batu Granit OH BOWG.77 326,500.00 BOW2G.77 326,500.00 BOWSG.77 309,050.00
L.008 Pekerja 6.0000 OH 27,000.00 162,000.00 27,000.00 162,000.00 24,500.00 147,000.00
L.011 Tukang Batu Ahli 4.0000 OH 35,000.00 140,000.00 35,000.00 140,000.00 35,000.00 140,000.00
L.007 Kepala Tukang 0.4000 OH 35,000.00 14,000.00 35,000.00 14,000.00 31,500.00 12,600.00
L.010 Mandor 0.3000 OH 35,000.00 10,500.00 35,000.00 10,500.00 31,500.00 9,450.00
BOW-Supl.IV.a Pasang Lantai Batu Granit Lokal M2 B.Sup.4a 609,931.70 B2.Sup.4a 610,268.76 BS.Sup.4a 592,481.70
M.004r Lembaran Granit lokal 1.0000 M2 250,000.00 250,000.00 250,000.00 250,000.00 250,000.00 250,000.00
BOW-G.14 Perekat G.14 0.0300 M3 785,390.00 23,561.70 796,625.40 23,898.76 785,390.00 23,561.70
M.012o Resin warna 0.2100 Ltr 47,000.00 9,870.00 47,000.00 9,870.00 47,000.00 9,870.00
BOW-G.77 Upah Tenaga Kerja 1.0000 326,500.00 326,500.00 326,500.00 326,500.00 309,050.00 309,050.00
BOW-Supl.IV.b Pasang Pelapis Dinding Batu Granit Lokal M2 B.Sup.4b 1,189,596.80 B2.Sup.4b 1,239,894.22 BS.Sup.4b 1,172,146.80
M.004r Lembaran Granit lokal 1.0000 M2 250,000.00 250,000.00 300,000.00 300,000.00 250,000.00 250,000.00
BOW-G.13 Perekat G.13 0.0200 M3 1,108,840.00 22,176.80 1,120,211.15 22,404.22 1,108,840.00 22,176.80
M.012o Resin warna 0.2100 Ltr 47,000.00 9,870.00 47,000.00 9,870.00 47,000.00 9,870.00
M.003 Kawat bindrat 0.0700 Kg 15,000.00 1,050.00 16,000.00 1,120.00 15,000.00 1,050.00
M.006i Paku beton 5 cm 20.0000 Bh 29,000.00 580,000.00 29,000.00 580,000.00 29,000.00 580,000.00
BOW-G.77 Upah Tenaga Kerja 1.0000 326,500.00 326,500.00 326,500.00 326,500.00 309,050.00 309,050.00
BOW-Supl.IV.c Pelapisan Coating 3 x ( sebelum dipasang ) M2 B.Sup.4c 11,425.00 B2.Sup.4c 11,425.00 BS.Sup.4c 11,157.50
M.012p Cairan coating 0.4500 Ltr 19,000.00 8,550.00 19,000.00 8,550.00 19,000.00 8,550.00
L.008 Pekerja 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
BOW-Supl.IV.d Pelapisan Coating 2 x ( setelah dipoles ) M2 B.Sup.4d 7,120.00 B2.Sup.4d 7,120.00 BS.Sup.4d 6,988.00
M.012p Cairan coating 0.3000 Ltr 19,000.00 5,700.00 19,000.00 5,700.00 19,000.00 5,700.00
L.008 Pekerja 0.0500 OH 27,000.00 1,350.00 27,000.00 1,350.00 24,500.00 1,225.00
L.010 Mandor 0.0020 OH 35,000.00 70.00 35,000.00 70.00 31,500.00 63.00
Pemolesan Lantai Batu Granit ( sampai mengkilap
BOW-Supl.IV.e M2 B.Sup.4e 182,950.00 B2.Sup.4e 182,950.00 BS.Sup.4e 182,275.00
)
M.012q Batu grenda poles 0.0700 Set 380,000.00 26,600.00 380,000.00 26,600.00 380,000.00 26,600.00
M.012r Obat poles 5x 0.5600 Kg 120,000.00 67,200.00 120,000.00 67,200.00 120,000.00 67,200.00
M.012s Kain poles 5x 8.0000 Glg 9,000.00 72,000.00 9,000.00 72,000.00 9,000.00 72,000.00
L.008 Pekerja 0.2000 OH 27,000.00 5,400.00 27,000.00 5,400.00 24,500.00 4,900.00
L.010 Mandor 0.0500 OH 35,000.00 1,750.00 35,000.00 1,750.00 31,500.00 1,575.00
L.012 Operator mesin poles 0.1000 OH 50,000.00 5,000.00 50,000.00 5,000.00 50,000.00 5,000.00
L.013 Sewa mesin poles 0.1000 Hr 50,000.00 5,000.00 50,000.00 5,000.00 50,000.00 5,000.00
42 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
Pemolesan Lembaran Batu Granit ( Rata, halus,
BOW-Supl.IV.f M2 B.Sup.4f 27,220.00 B2.Sup.4f 27,220.00 BS.Sup.4f 26,750.00
tidak mengkilap )

M.012q Batu grenda poles 0.0400 Set 380,000.00 15,200.00 380,000.00 15,200.00 380,000.00 15,200.00
L.008 Pekerja 0.1600 OH 27,000.00 4,320.00 27,000.00 4,320.00 24,500.00 3,920.00
L.010 Mandor 0.0200 OH 35,000.00 700.00 35,000.00 700.00 31,500.00 630.00
L.012 Operator mesin poles 0.0700 OH 50,000.00 3,500.00 50,000.00 3,500.00 50,000.00 3,500.00
E.31 Sewa mesin poles 0.0700 Hr 50,000.00 3,500.00 50,000.00 3,500.00 50,000.00 3,500.00
BOW-Supl.IV.g Penyemiran Lantai M2 B.Sup.4g 8,865.00 B2.Sup.4g 8,865.00 BS.Sup.4g 8,530.00
M.012t Kain Pel 0.0900 Set 9,500.00 855.00 9,500.00 855.00 9,500.00 855.00
M.012u Semir Lantai sek. MAA 0.2600 Kg 17,000.00 4,420.00 17,000.00 4,420.00 17,000.00 4,420.00
L.008 Pekerja 0.1200 OH 27,000.00 3,240.00 27,000.00 3,240.00 24,500.00 2,940.00
L.010 Mandor 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
BOW-G.69 Upah Pasang Tegel M3 BOWG.69 23,375.00 BOW2G.69 23,375.00 BOWsG.69 21,075.00
L.001 Tukang Batu 0.2500 Hr 32,500.00 8,125.00 32,500.00 8,125.00 29,000.00 7,250.00
L.007 Kepala Tukang 0.0250 Hr 35,000.00 875.00 35,000.00 875.00 31,500.00 787.50
L.008 Pekerja 0.5000 Hr 27,000.00 13,500.00 27,000.00 13,500.00 24,500.00 12,250.00
L.010 Mandor 0.0250 Hr 35,000.00 875.00 35,000.00 875.00 31,500.00 787.50
BOW-Supl.IV.h Pasang Tegel Batu Candi M2 B.Sup.4h 242,533.95 B2.Sup.4h 261,375.08 BS.Sup.4h 239,658.95
171,500.00 Batu Candi 1.0000 M2 171,500.00 171,500.00 190,000.00 190,000.00 171,500.00 171,500.00
BOW-G.13 Perekat G.13 0.0300 M3 1,108,840.00 33,265.20 1,120,211.15 33,606.33 1,108,840.00 33,265.20
19,000.00 Cairan coating 0.4500 Ltr 19,000.00 8,550.00 19,000.00 8,550.00 19,000.00 8,550.00
BOW-G.69 Upah Pasang G.69 1.2500 M3 23,375.00 29,218.75 23,375.00 29,218.75 21,075.00 26,343.75
BOW-Supl.IV.h Pasang Tegel Batu Baseh M2 B.Sup.4h 171,033.95 B2.Sup.4h 261,375.08 BS.Sup.4h 239,658.95
171,500.00 Batu Granit 10/20 1.0000 M2 100,000.00 100,000.00 190,000.00 190,000.00 171,500.00 171,500.00
BOW-G.13 Perekat G.13 0.0300 M3 1,108,840.00 33,265.20 1,120,211.15 33,606.33 1,108,840.00 33,265.20
19,000.00 Cairan coating 0.4500 Ltr 19,000.00 8,550.00 19,000.00 8,550.00 19,000.00 8,550.00
BOW-G.69 Upah Pasang G.69 1.2500 M3 23,375.00 29,218.75 23,375.00 29,218.75 21,075.00 26,343.75
BOW-Supl.IV.h Pasang Tegel Batu Baseh M2 B.Sup.4h 166,033.95 B2.Sup.4h 261,375.08 BS.Sup.4h 239,658.95
171,500.00 Batu Granit 10/10 1.0000 M2 95,000.00 95,000.00 190,000.00 190,000.00 171,500.00 171,500.00
BOW-G.13 Perekat G.13 0.0300 M3 1,108,840.00 33,265.20 1,120,211.15 33,606.33 1,108,840.00 33,265.20
19,000.00 Cairan coating 0.4500 Ltr 19,000.00 8,550.00 19,000.00 8,550.00 19,000.00 8,550.00
BOW-G.69 Upah Pasang G.69 1.2500 M3 23,375.00 29,218.75 23,375.00 29,218.75 21,075.00 26,343.75
BOW-Supl.IV.i Pasang Koral Sikat M2 B.Sup.4i 192,840.20 B2.Sup.4i 210,681.33 BS.Sup.4i 188,240.20
M.004u Batu Koral Hitam 1.0000 M2 112,500.00 112,500.00 130,000.00 130,000.00 112,500.00 112,500.00
BOW-G.13 Perekat G.13 0.0300 M3 1,108,840.00 33,265.20 1,120,211.15 33,606.33 1,108,840.00 33,265.20
M.001p Sikat Kawat/ Plastik 0.0500 Bh 6,500.00 325.00 6,500.00 325.00 6,500.00 325.00
BOW-G.69 Upah Pasang G.69 2.0000 M3 23,375.00 46,750.00 23,375.00 46,750.00 21,075.00 42,150.00
BOW-Supl.IV.j Pasang Pelapis Dinding Batu Granit Import M2 B.Sup.4j 2,016,096.80 B2.Sup.4j 2,016,394.22 BS.Sup.4j 1,981,196.80
M.004v Lembaran Granit Import 1.0000 M2 750,000.00 750,000.00 750,000.00 750,000.00 750,000.00 750,000.00
BOW-G.13 Perekat G.13 0.0200 M3 1,108,840.00 22,176.80 1,120,211.15 22,404.22 1,108,840.00 22,176.80
M.012o Resin warna 0.2100 Ltr 47,000.00 9,870.00 47,000.00 9,870.00 47,000.00 9,870.00
M.003 Kawat bindrat 0.0700 Kg 15,000.00 1,050.00 16,000.00 1,120.00 15,000.00 1,050.00
M.006i Paku beton 5 cm 20.0000 Bh 29,000.00 580,000.00 29,000.00 580,000.00 29,000.00 580,000.00
BOW-G.77 Upah Pasang G.77 2.0000 326,500.00 653,000.00 326,500.00 653,000.00 309,050.00 618,100.00
Pembuatan Septictank 1 x 1 x 2 m +
Ls.08 UNIT Ls.08 4,677,160.75 Ls2.08 4,839,095.56 LsS.08 4,595,823.88
Peresapan
SNI-B.6.2 Galian Tanah Biasa Sedalam 2 M 10.00 m3 16,022.00 160,220.00 16,022.00 160,220.00 14,525.00 145,250.00
SNI-B.6.9 Urugan Kembali 2.50 m3 5,849.00 14,622.50 5,849.00 14,622.50 5,302.50 13,256.25
SNI-B.6.11 Urugan Pasir 1.50 m3 74,450.00 111,675.00 83,450.00 125,175.00 73,665.00 110,497.50
SNI-C.6.14 Pas. Pondasi Batu Kosong 0.60 m3 166,965.00 100,179.00 175,215.00 105,129.00 163,377.00 98,026.20
SNI-D.6.3 Pas. Batu Merah tb.1 bata 1Pc:3Ps 6.00 m2 123,475.00 740,850.00 127,188.15 763,128.90 120,975.00 725,850.00
SNI-D.6.10 Pas. Batu Merah tb.1/2 bata 1Pc:3Ps 3.00 m2 58,609.00 175,827.00 60,409.59 181,228.77 57,371.50 172,114.50
SNI-E.6.3 Plesteran 1Pc:3Ps tb.1,5 cm 10.00 m2 20,541.00 205,410.00 20,728.86 207,288.60 19,428.50 194,285.00
SNI-G.6.13 Membuat
PembesianBeton CorBesi
dengan 1Pc:2Ps:3Kr
Beton Polos (sek. 0.22 m3 668,150.00 146,993.00 682,652.00 150,183.44 658,302.50 144,826.55
SNI-G.6.25 KS) 16.50 kg 16,461.00 271,606.50 17,526.00 289,179.00 16,415.50 270,855.75
BOW-F.8 Cetakan Kayu Tahun 4.00 m2 95,750.00 383,000.00 97,750.00 391,000.00 92,290.00 369,160.00
SNI-J.6.32 Pasang Pipa PVC diam. 4" type AW 8.00 m' 76,940.50 615,524.00 78,490.50 627,924.00 76,203.90 609,631.20
SNI-J.6.31 Pasang Pipa PVC diam. 3" type AW 10.00 m' 47,030.00 470,300.00 48,192.50 481,925.00 46,539.05 465,390.50
SNI-J.6.22 Pasang Pipa Galvanis diam. 1 1/2" med. B 3.00 m' 76,235.00 228,705.00 77,010.00 231,030.00 75,253.10 225,759.30
Ls Kenie T 1.00 bh 7,500.00 7,500.00 7,500.00 7,500.00 7,500.00 7,500.00
M.001f3 Batu pecah 5/7 cm 2.60 m3 106,000.00 275,600.00 111,000.00 288,600.00 106,000.00 275,600.00
Ls Krosok 2.50 m3 45,000.00 112,500.00 45,000.00 112,500.00 45,000.00 112,500.00
SNI-B.6.14 Pemasangan Lapisan Ijuk 1.85 m3 328,575.00 607,863.75 352,575.00 652,263.75 328,147.50 607,072.88
SNI-G.6.1 Membuat Beton Tumbuk 1Pc:3Ps:5Kr 0.10 m3 487,850.00 48,785.00 501,976.00 50,197.60 482,482.50 48,248.25
43 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
Pembuatan Septictank 1.5 x 2 x 2 m +
Ls.09 Peresapan UNIT Ls.09 6,432,224.10 Ls2.09 6,643,590.25 LsS.09 6,297,947.93
SNI-B.6.2 Galian Tanah Biasa Sedalam 2 M 14.90 m3 16,022.00 238,727.80 16,022.00 238,727.80 14,525.00 216,422.50
SNI-B.6.9 Urugan Kembali 40.00 m3 5,849.00 233,960.00 5,849.00 233,960.00 5,302.50 212,100.00
SNI-B.6.11 Urugan Pasir 0.92 m3 74,450.00 68,494.00 83,450.00 76,774.00 73,665.00 67,771.80
SNI-C.6.14 Pas. Pondasi Batu Kosong 0.60 m3 166,965.00 100,179.00 175,215.00 105,129.00 163,377.00 98,026.20
SNI-D.6.3 Pas. Batu Merah tb.1 bata 1Pc:3Ps 10.50 m2 123,475.00 1,296,487.50 127,188.15 1,335,475.58 120,975.00 1,270,237.50
SNI-D.6.10 Pas. Batu Merah tb.1/2 bata 1Pc:3Ps 5.00 m2 58,609.00 293,045.00 60,409.59 302,047.95 57,371.50 286,857.50
SNI-E.6.3 Plesteran 1Pc:3Ps tb.1,5 cm 17.30 m2 20,541.00 355,359.30 20,728.86 358,609.28 19,428.50 336,113.05
SNI-G.6.13 Membuat Beton Cor 1Pc:2Ps:3Kr 0.55 m3 668,150.00 367,482.50 682,652.00 375,458.60 658,302.50 362,066.38
SNI-G.6.25 Pembesian dengan Besi Beton Polos (sek. KS 41.25 kg 16,461.00 679,016.25 17,526.00 722,947.50 16,415.50 677,139.38
BOW-F.8 Cetakan Kayu Tahun 3.50 m2 95,750.00 335,125.00 97,750.00 342,125.00 92,290.00 323,015.00
SNI-J.6.32 Pasang Pipa PVC diam. 4" type AW 8.00 m' 76,940.50 615,524.00 78,490.50 627,924.00 76,203.90 609,631.20
SNI-J.6.31 Pasang Pipa PVC diam. 3" type AW 10.00 m' 47,030.00 470,300.00 48,192.50 481,925.00 46,539.05 465,390.50
SNI-J.6.22 Pasang Pipa Galvanis diam. 1 1/2" med. B 3.00 m' 76,235.00 228,705.00 77,010.00 231,030.00 75,253.10 225,759.30
Ls Kenie T 1.00 bh 7,500.00 7,500.00 7,500.00 7,500.00 7,500.00 7,500.00
M.001f3 Batu pecah 5/7 cm 2.60 m3 106,000.00 275,600.00 111,000.00 288,600.00 106,000.00 275,600.00
Ls Krosok 2.50 m3 45,000.00 112,500.00 45,000.00 112,500.00 45,000.00 112,500.00
SNI-B.6.14 Pemasangan Lapisan Ijuk 1.85 m3 328,575.00 607,863.75 352,575.00 652,263.75 328,147.50 607,072.88
SNI-G.6.1 Membuat Beton Tumbuk 1Pc:3Ps:5Kr 0.30 m3 487,850.00 146,355.00 501,976.00 150,592.80 482,482.50 144,744.75

E1.30 PEMBERSIHAN DAMIJA M2 E1.30 656.37 E2.30 656.37


U.008 Pekerja 0.0933 Jam 3,857.14 359.87 3,857.14 359.87
U.010 Mandor 0.0093 Jam 5,000.00 46.50 5,000.00 46.50
Ls Alat bantu 0.0100 Ls 25,000.00 250.00 25,000.00 250.00
E1.33 PENYIAPAN BADAN JALAN M2 E1.33 1,722.04 E2.33 1,722.04
U.008 Pekerja 0.0161 Jam 3,857.14 62.10 3,857.14 62.10
U.010 Mandor 0.0040 Jam 5,000.00 20.00 5,000.00 20.00
E.16 Vibratory Roller 5 - 8 Ton 0.0040 Jam 284,984.84 1,139.94 284,984.84 1,139.94
Ls Alat bantu 1.0000 Ls 500.00 500.00 500.00 500.00
E1.311a GALIAN TANAH BIASA ( MANUAL) M3 E1.311a 21,625.00 E2.311a 21,625.00
U.008 Pekerja 5.2500 Jam 3,857.14 20,250.00 3,857.14 20,250.00
U.010 Mandor 0.1750 Jam 5,000.00 875.00 5,000.00 875.00
Ls Alat bantu 1.0000 Jam 500.00 500.00 500.00 500.00
E1.312a GALIAN PADAS / BATUAN (MANUAL) M3 E1.312a 43,750.00 E2.312a 43,750.00
U.008 Pekerja 10.5000 Jam 3,857.14 40,500.00 3,857.14 40,500.00
U.010 Mandor 0.3500 Jam 5,000.00 1,750.00 5,000.00 1,750.00
Ls Alat bantu 1.0000 Ls 1,500.00 1,500.00 1,500.00 1,500.00
E1.313 GALIAN PERKERASAN ASPAL(MANUAL) M3 E1.313 57,810.00 E2.313 57,810.00
U.008 Pekerja 14.0000 Jam 3,857.14 54,000.00 3,857.14 54,000.00
U.010 Mandor 0.4620 Jam 5,000.00 2,310.00 5,000.00 2,310.00
Ls Alat bantu 1.0000 Ls 1,500.00 1,500.00 1,500.00 1,500.00
E1.321a URUGAN TANAH BIASA DARI HASIL GALIAN M3 E1.321a 7,399.93 E2.321a 7,399.93
U.008 Pekerja 0.0714 Jam 3,857.14 275.40 3,857.14 275.40
U.010 Mandor 0.0178 Jam 5,000.00 89.00 5,000.00 89.00
E.09 Motor Grader 0.0061 Jam 271,764.87 1,657.77 271,764.87 1,657.77
E.16 Vibratory Roller 0.0100 Jam 284,984.84 2,849.85 284,984.84 2,849.85
E.18 Water Tank Truck 2000-4500L 0.0070 Jam 146,845.63 1,027.92 146,845.63 1,027.92
Ls Alat bantu 1.0000 Ls 1,500.00 1,500.00 1,500.00 1,500.00
E1.322 URUGAN SIRTU M3 E1.322 82,399.93 E2.322 88,399.93
U.008 Pekerja 0.0714 Jam 3,857.14 275.40 3,857.14 275.40
U.010 Mandor 0.0178 Jam 5,000.00 89.00 5,000.00 89.00
M.001e Sirtu 1.2000 M3 62,500.00 75,000.00 67,500.00 81,000.00
E.09 Motor Grader 0.0061 Jam 271,764.87 1,657.77 271,764.87 1,657.77
E.16 Vibratory Roller 0.0100 Jam 284,984.84 2,849.85 284,984.84 2,849.85
E.18 Water Tank Truck 2000-4500L 0.0070 Jam 146,845.63 1,027.92 146,845.63 1,027.92
Ls Alat bantu 1.0000 Ls 1,500.00 1,500.00 1,500.00 1,500.00
E1.321 URUGAN TANAH BIASA M3 E1.321 67,399.93 E2.321 73,399.93
U.008 Pekerja 0.0714 Jam 3,857.14 275.40 3,857.14 275.40
U.010 Mandor 0.0178 Jam 5,000.00 89.00 5,000.00 89.00
M.001c Tanah Urug 1.2000 M3 50,000.00 60,000.00 55,000.00 66,000.00
E.09 Motor Grader 0.0061 Jam 271,764.87 1,657.77 271,764.87 1,657.77
E.16 Vibratory Roller 0.0100 Jam 284,984.84 2,849.85 284,984.84 2,849.85
E.18 Water Tank Truck 2000-4500L 0.0070 Jam 146,845.63 1,027.92 146,845.63 1,027.92
Ls Alat bantu 1.0000 Ls 1,500.00 1,500.00 1,500.00 1,500.00
E1.511 LAPIS PONDASI AGREGAT KELAS A M3 E1.511 187,988.35 E2.511 193,874.35
U.008 Pekerja 0.2499 Jam 3,857.14 963.90 3,857.14 963.90
U.010 Mandor 0.0357 Jam 5,000.00 178.50 5,000.00 178.50
M.101 Agregat Kasar Klas A 0.6600 M3 148,600.00 98,076.00 154,900.00 102,234.00
M.102 Agregat Halus Klas A 0.5400 M3 136,600.00 73,764.00 139,800.00 75,492.00
E.09 Motor Grader 0.0117 Jam 271,764.87 3,179.65 271,764.87 3,179.65
E.16 Vibratory Roller 0.0178 Jam 284,984.84 5,072.73 284,984.84 5,072.73
E.15 Pneumatic. Tired Roller 0.0043 Jam 501,191.73 2,155.12 501,191.73 2,155.12
E.18 Water Tank Truck 2000-4500L 0.0211 Jam 146,845.63 3,098.44 146,845.63 3,098.44
Ls Alat bantu 1.0000 Ls 1,500.00 1,500.00 1,500.00 1,500.00
44 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
E1.512 LAPIS PONDASI AGREGAT KELAS B M3 E1.512 143,380.75 E2.512 149,294.35
U.008 Pekerja 0.2499 Jam 3,857.14 963.90 3,857.14 963.90
U.010 Mandor 0.0357 Jam 5,000.00 178.50 5,000.00 178.50
M.103 Agregat Kasar Klas B 0.4200 M3 145,400.00 61,068.00 151,300.00 63,546.00
M.104 Agregat Halus Klas B 0.2400 M3 135,060.00 32,414.40 138,125.00 33,150.00
M.001e Sirtu 0.5400 M3 62,500.00 33,750.00 67,500.00 36,450.00
E.09 Motor Grader 0.0117 Jam 271,764.87 3,179.65 271,764.87 3,179.65
E.19 Vibratory Roller 0.0178 Jam 284,984.84 5,072.73 284,984.84 5,072.73
E.15 Pneumatic. Tired Roller 0.0043 Jam 501,191.73 2,155.12 501,191.73 2,155.12
E.18 Water Tank Truck 2000-4500L 0.0211 Jam 146,845.63 3,098.44 146,845.63 3,098.44
Ls Alat bantu 1.0000 Ls 1,500.00 1,500.00 1,500.00 1,500.00
E1.521 LAPIS PONDASI AGREGAT KELAS C M3 E1.521 100,728.05 E2.521 107,478.05
U.008 Pekerja 0.0703 Jam 3,857.14 271.16 3,857.14 271.16
U.010 Mandor 0.0100 Jam 5,000.00 50.00 5,000.00 50.00
M.001e1 Agregat Klas C 1.3500 M3 62,500.00 84,375.00 67,500.00 91,125.00
E.09 Motor Grader 0.0117 Jam 271,764.87 3,179.65 271,764.87 3,179.65
E.16 Vibratory Roller 0.0214 Jam 284,984.84 6,098.68 284,984.84 6,098.68
E.15 Pneumatic. Tired Roller 0.0043 Jam 501,191.73 2,155.12 501,191.73 2,155.12
E.18 Water Tank Truck 2000-4500L 0.0211 Jam 146,845.63 3,098.44 146,845.63 3,098.44
Ls Alat bantu 1.0000 Ls 1,500.00 1,500.00 1,500.00 1,500.00
E1.611 LAPIS RESAP PENGIKAT LITER E1.611 8,577.53 E2.611 8,916.39
U.008 Pekerja 0.0301 Jam 3,857.14 116.10 3,857.14 116.10
U.010 Mandor 0.0060 Jam 5,000.00 30.00 5,000.00 30.00
M.017 Aspal Penetrasi 60/70 0.6294 Kg 9,700.00 6,105.18 9,850.00 6,199.59
M.017d Kerosene / Minyak Tanah 0.4889 Ltr 2,700.00 1,320.03 3,200.00 1,564.48
E.03 Aphalt Sprayer 0.0030 Jam 47,048.56 141.15 47,048.56 141.15
E.05 Compressor 4000-6000 L/M 0.0031 Jam 126,595.63 392.45 126,595.63 392.45
E.19 Dump Truck 3 - 4 M3 0.0030 Jam 157,544.17 472.63 157,544.17 472.63
E1.612 LAPIS PEREKAT LITER E1.612 10,702.81 E2.612 10,960.17
U.008 Pekerja 0.0301 Jam 3,857.14 116.10 3,857.14 116.10
U.010 Mandor 0.0060 Jam 5,000.00 30.00 5,000.00 30.00
M.017 Aspal Penetrasi 60/70 0.8724 Kg 9,700.00 8,462.28 9,850.00 8,593.14
M.017d Kerosene / Minyak Tanah 0.2530 Ltr 2,700.00 683.10 3,200.00 809.60
E.03 Aphalt Sprayer 0.0030 Jam 47,048.56 141.15 47,048.56 141.15
E.05 Compressor 4000-6000 L/M 0.0063 Jam 126,595.63 797.55 126,595.63 797.55
E.19 Dump Truck 3 - 4 M3 0.0030 Jam 157,544.17 472.63 157,544.17 472.63
E1.817a LAPIS PENETRASI MACADAM (Leveling) M3 E1.817a 1,087,879.76 E2.817a 1,115,313.13
U.008 Pekerja 0.7144 Jam 3,857.14 2,755.54 3,857.14 2,755.54
U.010 Mandor 0.0714 Jam 5,000.00 357.20 5,000.00 357.20
M.111 Agregat Kasar 1.8222 M3 140,000.00 255,112.05 146,000.00 266,045.42
M.017 Aspal Penetrasi 60/70 80.0000 Kg 9,700.00 776,000.00 9,850.00 788,000.00
M.017e Kayu Bakar 0.3000 M3 74,500.00 22,350.00 89,500.00 26,850.00
E.13 Three Wheel Roller 6-8 T 0.0459 Jam 197,389.87 9,050.33 197,389.87 9,050.33
E.03 Aphalt Sprayer 0.2924 Jam 47,048.56 13,754.65 47,048.56 13,754.65
Ls Alat bantu 1.0000 Ls 8,500.00 8,500.00 8,500.00 8,500.00
E1.631 LATASIR ( SAND SHEET ) M2 E1.631 34,498.98 E2.631 35,223.98
U.008 Pekerja 1.1662 Jam 3,857.14 4,498.20 3,857.14 4,498.20
U.010 Mandor 0.0560 Jam 5,000.00 280.00 5,000.00 280.00
M.017e Kayu Bakar 0.0180 M3 74,500.00 1,341.00 89,500.00 1,611.00
M.001i2 Batu pecah 02 - 0,5 cm 0.0200 M3 156,000.00 3,120.00 160,000.00 3,200.00
M.017 Aspal penetrasi 60/70 2.5000 Kg 9,700.00 24,250.00 9,850.00 24,625.00
E.13 Three Wheel Roller 6-8 T 0.0020 Jam 197,389.87 394.78 197,389.87 394.78
Ls Alat bantu 1.0000 Ls 615.00 615.00 615.00 615.00
E1.817b LAPIS PENETRASI MACADAM SHEET M2 E1.817b 64,109.71 E2.817b 65,945.29
U.008 Pekerja 1.0452 Jam 3,857.14 4,031.49 3,857.14 4,031.49
U.010 Mandor 0.0393 Jam 5,000.00 196.50 5,000.00 196.50
M.111 Agregat Pokok Lapen 0.0489 M3 140,000.00 6,844.60 146,000.00 7,137.94
M.112 Agregat Pengunci Lapen 0.0153 M3 149,825.00 2,289.33 154,880.00 2,366.57
M.001i2 Batu pecah 0,2 - 0,5 cm 0.0100 M3 156,000.00 1,560.00 160,000.00 1,600.00
M.017 Aspal Penetrasi 60/70 4.5000 Kg 9,700.00 43,650.00 9,850.00 44,325.00
M.017e Kayu Bakar 0.0500 M3 74,500.00 3,725.00 89,500.00 4,475.00
E.13 Three Wheel Roller 6-8 T 0.0027 Jam 197,389.87 527.92 197,389.87 527.92
E.03 Aphalt Sprayer 0.0119 Jam 47,048.56 559.88 47,048.56 559.88
Ls Alat bantu 1.0000 Ls 725.00 725.00 725.00 725.00
E1.635 ASPHALT TREATED BASE (ATB) M3 E1.635 2,033,039.45 E2.635 2,063,874.02
U.008 Pekerja 0.3880 Jam 3,857.14 1,496.57 3,857.14 1,496.57
U.010 Mandor 0.0554 Jam 5,000.00 277.00 5,000.00 277.00
M.105 Agregat Kasar ATB 0.7731 M3 146,500.00 113,265.01 152,450.00 117,865.19
M.106 Agregat Haslus ATB 0.5271 M3 123,300.00 64,996.36 125,875.00 66,353.75
M.001i4 Filler 25.3400 Kg 200.00 5,068.00 250.00 6,335.00
M.017 Aspal Penetrasi 60/70 157.40 Kg 9,700.00 1,526,780.00 9,850.00 1,550,390.00
E.12 Wheel Loader 1,0 - 1,6 m3 0.0380 Jam 274,051.67 10,413.96 274,051.67 10,413.96
E.01 Asphalt Mixing Plant 0.0554 Jam 3,086,729.33 171,004.81 3,086,729.33 171,004.81
E.22 Generator Set 0.0554 Jam 205,842.46 11,403.67 205,842.46 11,403.67
E.20 Dump Truck 0.3150 Jam 194,805.22 61,363.64 194,805.22 61,363.64
E.02 Asphalt Finisher 0.0767 Jam 380,393.80 29,176.20 380,393.80 29,176.20
E.14 Tandem Roller 6-8 Ton 0.0656 Jam 203,845.77 13,380.44 203,845.77 13,380.44
E.15 Pneumatic. Tired Roller 0.0367 Jam 501,191.73 18,413.78 501,191.73 18,413.78
Ls Alat bantu 1.0000 Ls 6,000.00 6,000.00 6,000.00 6,000.00
45 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
E1.635a ASPHALT TREATED BASE LEVELING (ATBL) TON E1.635a 882,321.57 E2.635a 895,727.90
U.008 Pekerja 0.1687 Jam 3,857.14 650.68 3,857.14 650.68
U.010 Mandor 0.0241 Jam 5,000.00 120.50 5,000.00 120.50
M.105 Agregat Kasar ATB 0.3361 M3 146,500.00 49,245.66 152,450.00 51,245.74
M.106 Agregat Haslus ATB 0.2292 M3 123,300.00 28,259.29 125,875.00 28,849.46
M.001i4 Filler 11.0174 Kg 200.00 2,203.48 250.00 2,754.35
M.017 Aspal Penetrasi 60/70 68.4348 Kg 9,700.00 663,817.39 9,850.00 674,082.61
E.12 Wheel Loader 1,0 - 1,6 m3 0.0165 Jam 274,051.67 4,527.81 274,051.67 4,527.81
E.01 Asphalt Mixing Plant 0.0241 Jam 3,086,729.33 74,349.92 3,086,729.33 74,349.92
E.22 Generator Set 0.0241 Jam 205,842.46 4,958.12 205,842.46 4,958.12
E.20 Dump Truck 0.1370 Jam 194,805.22 26,679.84 194,805.22 26,679.84
E.02 Asphalt Finisher 0.0333 Jam 380,393.80 12,685.31 380,393.80 12,685.31
E.14 Tandem Roller 6-8 Ton 0.0285 Jam 203,845.77 5,817.58 203,845.77 5,817.58
E.15 Pneumatic. Tired Roller 0.0160 Jam 501,191.73 8,005.99 501,191.73 8,005.99
Ls Alat bantu 1.0000 Ls 1,000.00 1,000.00 1,000.00 1,000.00
E1.633 LATASTON (HRS) M2 E1.633 65,112.7675 E2.633 66,078.3125
U.008 Pekerja 0.0113 Jam 3,857.14 43.59 3,857.14 43.59
U.010 Mandor 0.0016 Jam 5,000.00 8.00 5,000.00 8.00
M.105 Agregat Kasar HRS 0.0176 M3 146,500.00 2,578.40 152,450.00 2,683.12
M.106 Agregat Haslus HRS 0.0182 M3 123,300.00 2,244.06 125,875.00 2,290.93
M.001i4 Filler 0.7056 kg 200.00 141.12 250.00 176.40
M.017 Aspal Penetrasi 60/70 5.1912 kg 9,700.00 50,354.64 9,850.00 51,133.32
E.12 Wheel Loader 1,0 - 1,6 m3 0.0011 Jam 274,051.67 301.46 274,051.67 301.46
E.01 Asphalt Mixing Plant 0.0016 Jam 3,086,729.33 4,938.77 3,086,729.33 4,938.77
E.22 Generator Set 0.0016 Jam 205,842.46 329.35 205,842.46 329.35
E.20 Dump Truck 0.0092 Jam 194,805.22 1,792.21 194,805.22 1,792.21
E.02 Asphalt Finisher 0.0020 Jam 380,393.80 760.79 380,393.80 760.79
E.14 Tandem Roller 6-8 Ton 0.0023 Jam 203,845.77 468.85 203,845.77 468.85
E.15 Pneumatic. Tired Roller 0.0013 Jam 501,191.73 651.55 501,191.73 651.55
Ls Alat bantu 1.0000 Ls 500.00 500.00 500.00 500.00
E1.716 BETON K-125 M3 E1.716 510,602.14 E2.716 519,869.94
U.008 Pekerja 5.3012 Jam 3,857.14 20,447.49 3,857.14 20,447.49
U.001 Tukang 1.7671 Jam 4,642.86 8,204.39 4,642.86 8,204.39
U.010 Mandor 0.4418 Jam 5,000.00 2,209.00 5,000.00 2,209.00
M.002a Portland Cement 50 kg 256.2500 kg 1,200.00 307,500.00 1,207.00 309,293.75
M.001 Pasir Beton 0.4271 M3 92,500.00 39,506.75 100,000.00 42,710.00
M.100 Agregat Kasar Beton 0.7118 M3 146,500.00 104,278.70 152,500.00 108,549.50
E.06 Concrete Mixer 0,125 M3 0.4418 Jam 27,217.48 12,024.68 27,217.48 12,024.68
E.24 Concrete Vibrator 0.4418 Jam 16,143.45 7,132.18 16,143.45 7,132.18
E.18 Water Tank Truck 2000-4500L 0.0463 Jam 146,845.63 6,798.95 146,845.63 6,798.95
Ls Alat bantu 1.0000 Ls 2,500.00 2,500.00 2,500.00 2,500.00
E1.711 BETON K-250 M3 E1.711 621,000.18 E2.711 630,653.69
U.008 Pekerja 5.3012 Jam 3,857.14 20,447.49 3,857.14 20,447.49
U.001 Tukang 1.7671 Jam 4,642.86 8,204.39 4,642.86 8,204.39
U.010 Mandor 0.4418 Jam 5,000.00 2,209.00 5,000.00 2,209.00
M.002a Portland Cement 50 kg 354.8077 kg 1,200.00 425,769.24 1,207.00 428,252.89
M.001 Pasir Beton 0.4435 M3 92,500.00 41,023.75 100,000.00 44,350.00
M.100 Agregat Kasar Beton 0.6406 M3 146,500.00 93,847.90 152,500.00 97,691.50
E.06 Concrete Mixer 0,125 M3 0.4418 Jam 27,217.48 12,024.68 27,217.48 12,024.68
E.24 Concrete Vibrator 0.4418 Jam 16,143.45 7,132.18 16,143.45 7,132.18
E.18 Water Tank Truck 2000-4500L 0.0534 Jam 146,845.63 7,841.56 146,845.63 7,841.56
Ls Alat bantu 1.0000 Ls 2,500.00 2,500.00 2,500.00 2,500.00
E1.714b BETON K-350 M3 E1.714b 654,773.04 E2.714b 664,510.52
U.008 Pekerja 5.3012 Jam 3,857.14 20,447.49 3,857.14 20,447.49
U.001 Tukang 1.7671 Jam 4,642.86 8,204.39 4,642.86 8,204.39
U.010 Mandor 0.4418 Jam 5,000.00 2,209.00 5,000.00 2,209.00
M.002a Portland Cement 50 kg 384.3750 kg 1,200.00 461,250.00 1,207.00 463,940.63
M.001 Pasir Beton 0.4271 M3 92,500.00 39,506.75 100,000.00 42,710.00
M.100 Agregat Kasar Beton 0.6406 M3 146,500.00 93,847.90 152,500.00 97,691.50
E.06 Concrete Mixer 0,125 M3 0.4418 Jam 27,217.48 12,024.68 27,217.48 12,024.68
E.24 Concrete Vibrator 0.4418 Jam 16,143.45 7,132.18 16,143.45 7,132.18
E.18 Water Tank Truck 2000-4500L 0.0521 Jam 146,845.63 7,650.66 146,845.63 7,650.66
Ls Alat bantu 1.0000 Ls 2,500.00 2,500.00 2,500.00 2,500.00
E1.712a BETON CYCLOP M3 E1.712a 467,841.66 E2.712a 476,042.74
U.008 Pekerja 4.8192 Jam 3,857.14 18,588.34 3,857.14 18,588.34
U.001 Tukang 1.6064 Jam 4,642.86 7,458.29 4,642.86 7,458.29
U.010 Mandor 0.8032 Jam 5,000.00 4,016.00 5,000.00 4,016.00
M.002a Portland Cement 50 kg 187.6900 kg 1,200.00 225,228.00 1,207.00 226,541.83
M.001 Pasir Beton 0.2799 M3 92,500.00 25,890.75 100,000.00 27,990.00
M.100 Agregat Kasar Beton 0.6180 M3 146,500.00 90,537.00 152,500.00 94,245.00
M.001f Batu Belah 0.5400 M3 93,000.00 50,220.00 95,000.00 51,300.00
E.06 Concrete Mixer 0,125 M3 0.8032 Jam 27,217.48 21,861.08 27,217.48 21,861.08
E.24 Concrete Vibrator 0.8032 Jam 16,143.45 12,966.42 16,143.45 12,966.42
E.18 Water Tank Truck 2000-4500L 0.0584 Ls 146,845.63 8,575.78 146,845.63 8,575.78
Ls Alat bantu 1.0000 Ls 2,500.00 2,500.00 2,500.00 2,500.00
46 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
E1.713a BETON STRUKTUR K-225 KANSTIN (EKSPOS) M3 E1.713a 584,223.60 E2.713a 593,844.70
U.008 Pekerja 4.0963 Jam 3,857.14 15,800.01 3,857.14 15,800.01
U.001 Tukang 1.3654 Jam 4,642.86 6,339.36 4,642.86 6,339.36
U.010 Mandor 0.6827 Jam 5,000.00 3,413.50 5,000.00 3,413.50
M.002a Portland Cement 50 kg 300.0000 kg 1,200.00 360,000.00 1,207.00 362,100.00
M.001 Pasir Beton 0.3074 M3 92,500.00 28,434.50 100,000.00 30,740.00
M.100 Agregat Kasar Beton 0.8276 M3 146,500.00 121,243.40 152,500.00 126,209.00
M.001i3 Abu Batu 0.1000 M3 122,500.00 12,250.00 125,000.00 12,500.00
E.06 Concrete Mixer 0,125 M3 0.6827 Jam 27,217.48 18,581.37 27,217.48 18,581.37
E.24 Concrete Vibrator 0.6827 Jam 16,143.45 11,021.14 16,143.45 11,021.14
E.18 Water Tank Truck 2000-4500L 0.0316 Jam 146,845.63 4,640.32 146,845.63 4,640.32
Ls Alat bantu 1.0000 Ls 2,500.00 2,500.00 2,500.00 2,500.00
E1.72 PENULANGAN / PEMBESIAN Kg. E1.72 17,788.50 E2.72 18,908.50
U.008 Pekerja 0.1050 Jam 3,857.14 405.00 3,857.14 405.00
U.001 Tukang 0.0350 Jam 4,642.86 162.50 4,642.86 162.50
U.010 Mandor 0.0350 Jam 5,000.00 175.00 5,000.00 175.00
M.003 Baja Tulangan 1.1000 Kg 15,000.00 16,500.00 16,000.00 17,600.00
M.003a Kawat Beton ( Bindrat ) 0.0200 Kg 17,300.00 346.00 18,300.00 366.00
Ls Alat bantu 1.0000 Ls 200.00 200.00 200.00 200.00
E1.710 ACUAN (Begisting) utk Jbt / gorong-gorong M2 E1.710 52,200.00 E2.710 52,950.00
U.008 Pekerja 2.4500 Jam 3,857.14 9,450.00 3,857.14 9,450.00
U.001 Tukang 1.4000 Jam 4,642.86 6,500.00 4,642.86 6,500.00
U.010 Mandor 0.3500 Jam 5,000.00 1,750.00 5,000.00 1,750.00
M.005u Kayu Perancah 0.0300 M3 975,000.00 29,250.00 1,000,000.00 30,000.00
M.006 Paku Biasa ( 2" - 5") 0.2000 Kg 18,000.00 3,600.00 18,000.00 3,600.00
LS Alat bantu 1.0000 Set 1,650.00 1,650.00 1,650.00 1,650.00
E1.813 PENGECATAN KAYU / BESI M2 E1.813 19,035.50 E2.813 19,203.50
U.008 Pekerja 2.4500 Jam 3,857.14 9,450.00 3,857.14 9,450.00
U.001 Tukang 0.3500 Jam 4,642.86 1,625.00 4,642.86 1,625.00
U.010 Mandor 0.1225 Jam 5,000.00 612.50 5,000.00 612.50
M.011j Cat Minyak 0.1500 kg 35,000.00 5,250.00 35,000.00 5,250.00
M.011f Cat Meni 0.1680 kg 11,000.00 1,848.00 12,000.00 2,016.00
Ls Alat bantu 1.0000 Ls 250.00 250.00 250.00 250.00
E1.753 BRONJONG (GABIONS) M3 E1.753 392,812.50 E2.753 443,312.50
U.008 Pekerja 5.2500 Jam 3,857.14 20,250.00 3,857.14 20,250.00
U.001 Tukang 2.6250 Jam 4,642.86 12,187.50 4,642.86 12,187.50
U.010 Mandor 0.8750 Jam 5,000.00 4,375.00 5,000.00 4,375.00
M.003e Kawat Bronjong dia 4 mm 15.0000 Kg 18,500.00 277,500.00 21,500.00 322,500.00
M.001k Batu Kali Blonos 1.1000 M3 70,000.00 77,000.00 75,000.00 82,500.00
Ls Alat bantu 1.0000 Ls 1,500.00 1,500.00 1,500.00 1,500.00
PASANGAN BATU (MEKANIK) termasuk plesteran
E1.79 M3 E1.79 410,028.11 E2.79 416,570.86
/ siar
U.008 Pekerja 5.4618 Jam 3,857.14 21,066.94 3,857.14 21,066.94
U.001 Tukang 1.3655 Jam 4,642.86 6,339.82 4,642.86 6,339.82
U.010 Mandor 0.6827 Jam 5,000.00 3,413.50 5,000.00 3,413.50
M.001f Batu Belah 1.1700 M3 93,000.00 108,810.00 95,000.00 111,150.00
M.002a Portland Cement 50 kg 176.0000 kg 1,200.00 211,200.00 1,207.00 212,432.00
M.001a Pasir Pasang 0.3961 M3 85,000.00 33,668.50 92,500.00 36,639.25
E.06 Concrete Mixer 0,125 M3 0.6827 Jam 27,217.48 18,581.37 27,217.48 18,581.37
E.18 Water Tank Truck 2000-4500L 0.0371 Jam 146,845.63 5,447.97 146,845.63 5,447.97
Ls Alat bantu 1.0000 Ls 1,500.00 1,500.00 1,500.00 1,500.00
E1.715 GROOVING M2 E1.715 4,811.83 E2.715 4,811.83
U.008 Pekerja 0.7404 Jam 3,857.14 2,855.83 3,857.14 2,855.83
M.011m Curing Compound 0.0608 Ltr 7,500.00 456.00 7,500.00 456.00
Ls Alat bantu 1.0000 Ls 1,500.00 1,500.00 1,500.00 1,500.00
E1-716a SEALENT E1.716a 12,583.83 E2.716a 12,583.83
L.008 Pekerja 0.7404 Jam 3,857.14 2,855.83 3,857.14 2,855.83
M59 Joint sealer (Aspal Cut Back) 1.1000 M' 3,000.00 3,300.00 3,000.00 3,300.00
Cutter Machine 0.0912 Jam 65,000.00 5,928.00 65,000.00 5,928.00
Ls 1.0000 Ls 500.00 500.00 500.00 500.00

E1.847 PATOK KILOMETER BH E1.847 449,568.28 E2.847 470,736.28


U.008 Pekerja 0.5243 Jam 3,857.14 2,022.30 3,857.14 2,022.30
U.001 Tukang 0.2097 Jam 4,642.86 973.61 4,642.86 973.61
U.010 Mandor 0.1049 Jam 5,000.00 524.50 5,000.00 524.50
E1.711 Beton K-250 0.1512 M3 621,000.18 93,895.23 621,000.18 93,895.23
E1.72 Baja Tulangan 18.9000 Kg 17,788.50 336,202.65 18,908.50 357,370.65
Ls Cat dan Material Lainnya 1.0000 Ls 15,000.00 15,000.00 15,000.00 15,000.00
Ls Alat bantu 1.0000 Ls 950.00 950.00 950.00 950.00
47 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
E1.846 PATOK HEKTOMETER BH E1.846 125,742.06 E2.846 131,293.14
U.008 Pekerja 0.7380 Jam 3,857.14 2,846.57 3,857.14 2,846.57
U.001 Tukang 0.3690 Jam 4,642.86 1,713.21 4,642.86 1,713.21
U.010 Mandor 0.0922 Jam 5,000.00 461.00 5,000.00 461.00
E1.711 Beton K-250 0.0354 M3 621,000.18 21,983.41 630,653.69 22,325.14
E1.72 Pembesian 4.6512 Kg 17,788.50 82,737.87 18,908.50 87,947.22
Ls Cat dan Material Lainnya 1.0000 Ls 15,000.00 15,000.00 15,000.00 15,000.00
Ls Alat bantu 1.0000 Ls 1,000.00 1,000.00 1,000.00 1,000.00
E1.723.4 TIANG PANCANG BETON M' E1.723.4 366,350.04 E2.723.4 366,350.04
U.008 Pekerja 0.7500 Jam 3,857.14 2,892.86 3,857.14 2,892.86
U.010 Mandor 0.1250 Jam 5,000.00 625.00 5,000.00 625.00
M.018g Tiang pancang 1.0000 M 310,000.00 310,000.00 310,000.00 310,000.00
E.21 Flat Bed Truck 3-4 M3 0.1979 Jam 153,585.71 30,394.61 153,585.71 30,394.61
E.07 Crane 10 - 15 Ton 0.0783 Jam 286,558.98 22,437.57 286,558.98 22,437.57

W.4 Biaya Gilas


Untuk 1 mesin Gilas setiap hari diperlukan : 1 Operator, 1 Pemb. Operator, 6 Pekerja
1 Mesin gilas tiap bulan diperlukan 25 hari kerja
Biaya Operasional 1 mesin gilas/bulan :
W.4 Biaya Gilas 14,500,000.00 14,775,000.00
1 1 Sewa Mesin Gilas 25 Hari 200,000.00 5,000,000.00 200,000.00 5,000,000.00
1 1 Operator 25 Hari 35,000.00 875,000.00 35,000.00 875,000.00
1 1 Pemb.Operator 25 Hari 31,500.00 787,500.00 31,500.00 787,500.00
6 6 Pekerja 25 Hari 27,000.00 4,050,000.00 27,000.00 4,050,000.00
20 20 Ltr. Solar 25 Hari 5,500.00 2,750,000.00 6,000.00 3,000,000.00
1 1 Ltr. Olie 25 Hari 37,500.00 937,500.00 38,500.00 962,500.00
8 8 Kg. Vet/Bulan 1 Bln 12,500.00 100,000.00 12,500.00 100,000.00

W.4a = 1 M2 Biaya Gilas Onderlaag = 1 / 7500 14,500,000.00 1,933.33 14,775,000.00 1,970.00


W.4b = 1 M2 Biaya Gilas Stenslaag = 1 / 3750 14,500,000.00 3,866.67 14,775,000.00 3,940.00
W.4c = 1 M2 Biaya Gilas Aspalan = 1 / 15000 14,500,000.00 9,666.67 14,775,000.00 9,850.00

W.2 1 M2 Memasang Onderlaag tebal 15 cm W.2 35,773.33 W2.2 37,148.33


M.001f2 Batu pecah 8/15 cm 0.15 M3 100,000.00 15,000.00 105,000.00 15,750.00
M.001f3 Batu pecah 5/7 cm 0.05 M3 106,000.00 5,300.00 111,000.00 5,550.00
M.001b Pasir Urug 0.05 M3 55,000.00 2,750.00 62,500.00 3,125.00
L.008 Pekerja 0.375 Hr 27,000.00 10,125.00 27,000.00 10,125.00
L.010 Mandor 0.019 Hr 35,000.00 665.00 35,000.00 665.00
Biaya gilas W.4a 1,933.33 1,933.33 1,933.33 1,933.33
A.18 1 M3 Urugan pasir pasang A.18 110,450.00 A2.18 119,450.00
M.001a Pasir pasang 1.20 M3 85,000.00 102,000.00 92,500.00 111,000.00
L.008 Pekerja 0.30 OH 27,000.00 8,100.00 27,000.00 8,100.00
L.010 Mandor 0.01 OH 35,000.00 350.00 35,000.00 350.00
W.3 1 M2 Memasang Stenslaag tebal 6 cm W.3 12,359.03 W2.3 12,908.11
M.001f3 Batu pecah 5/7 cm 0.06 M3 106,000.00 6,360.00 111,000.00 6,660.00
M.001f4 Batu pecah 3/5 cm 0.02 M3 137,000.00 2,740.00 142,000.00 2,840.00
M.001b Pasir urug 0.02 M3 55,000.00 1,100.00 62,500.00 1,250.00
L.008 Pekerja 0.075 OH 27,000.00 2,025.00 27,000.00 2,025.00
L.010 Mandor 0.0038 OH 35,000.00 133.00 35,000.00 133.00
Biaya gilas/M2 W.4b 1.03 1.03 0.11 0.11
KPU.IVa Pasang Paving Blok Natural KPU.IVa 64,200.00 KPU2.IVa 65,950.00
M.013 Paving Blok Natural 6 cm 1 M2 37,000.00 37,000.00 38,000.00 38,000.00
M.001a Pasir Pasang 0.1 M3 85,000.00 8,500.00 92,500.00 9,250.00
L.001 Tukang batu 0.2 OH 32,500.00 6,500.00 32,500.00 6,500.00
L.007 Kepala Tukang 0.02 OH 35,000.00 700.00 35,000.00 700.00
L.008 Pekerja 0.4 OH 27,000.00 10,800.00 27,000.00 10,800.00
L.010 Mandor 0.02 OH 35,000.00 700.00 35,000.00 700.00
KPU.IVb 1 M2 Pasang Paving Blok Warna KPU.IVb 87,200.00 KPU2.IVb 88,950.00
M.013a Paving Blok Warna 6 cm 1 M2 60,000.00 60,000.00 61,000.00 61,000.00
M.001a Pasir pasang 0.1 M3 85,000.00 8,500.00 92,500.00 9,250.00
L.001 Tukang batu 0.2 OH 32,500.00 6,500.00 32,500.00 6,500.00
L.007 Kepala Tukang 0.02 OH 35,000.00 700.00 35,000.00 700.00
L.008 Pekerja 0.4 OH 27,000.00 10,800.00 27,000.00 10,800.00
L.010 Mandor 0.02 OH 35,000.00 700.00 35,000.00 700.00
48 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
W.3.a 1 M2 Memasang Stenslaag tebal 6 - 8 cm W.3a 19,084.67 W2.3a 19,774.67
M.001f3 Batu pecah 5/7 cm 0.06 M3 106,000.00 6,360.00 111,000.00 6,660.00
M.001f4 Batu pecah 3/5 cm 0.02 M3 137,000.00 2,740.00 142,000.00 2,840.00
M.001h Batu pecah 2/3 cm 0.02 M3 143,000.00 2,860.00 150,000.00 3,000.00
M.001b Pasir urug 0.02 M3 55,000.00 1,100.00 62,500.00 1,250.00
L.008 Pekerja 0.075 OH 27,000.00 2,025.00 27,000.00 2,025.00
L.010 Mandor 0.0038 OH 35,000.00 133.00 35,000.00 133.00
Biaya gilas/M2 W.4b 3,866.67 3,866.67 3,866.67 3,866.67
A.19 1 M3 Urugan pasir Urug A.19 74,450.00 A2.19 83,450.00
M.001b Pasir Urug 1.20 M3 55,000.00 66,000.00 62,500.00 75,000.00
L.008 Pekerja 0.30 OH 27,000.00 8,100.00 27,000.00 8,100.00
L.010 Mandor 0.01 OH 35,000.00 350.00 35,000.00 350.00

Pekerjaan sokongan untuk 1m3 beton tinggi 4 meter:


W.3.b 1 m2 Sokongon Jembatan (Bekisting) 1,551,105.77 1,557,836.54
M.005u Kayu dim 13 cm 0.26923 M3 975,000.00 262,500.00 1,000,000.00 269,230.77
L.007 Kep. Tukang 2.82692 jam 35,000.00 98,942.31 35,000.00 98,942.31
L.010 Mandor 0.47115 Jam 35,000.00 16,490.38 35,000.00 16,490.38
L.002 Tukang 28.26923 Jam 32,500.00 918,750.00 32,500.00 918,750.00
L.008 Pekerja 9.42308 Jam 27,000.00 254,423.08 27,000.00 254,423.08

Purwokerto, September 2008

KEPALA DINAS CIPTA KARYA, KEBERSIHAN


DAN TATA RUANG KAB. BANYUMAS

Ir. ANDRIE SUBANDRIO, MT


Pembina Tk.I
NIP. 500 097 810
PEMERINTAH KABUPATEN BANYUMAS
DINAS CIPTA KARYA KEBERSIHAN DAN TATA RUANG DAFTAR HARGA SATUAN PEKERJAAN
Jl.Gerilya Barat No. 05 Telp. (0281) 640359
PURWOKERTO HSP
TAHUN 2008 (Perubahan)
HRG SATUAN (Rp)
NO KODE ANALISSATUAN JENIS PEKERJAAN KATAGORI I KATAGORI II
(Mudah) (Sulit)
A. PEKERJAAN PERSIAPAN
1 SNI - A.6.4 M' Pengukuran & Pas.Bouwplank Kayu Meranti 83,560.00 84,460.00
2 SNI - A.6.4a M' Pengukuran & Pas.Bouwplank Kayu Tahun 32,485.00 33,435.00
3 SNI - A.6.6 M2 Pemb.Gudang Semen & Alat-alat Ky.Meranti 1,147,775.00 1,174,323.50
4 SNI - A.6.6a M2 Pemb.Gudang Semen & Alat-alat Ky.Tahun 533,525.00 554,823.50
5 SNI - A.6.7 M2 Pemb. Rumah Jaga / Konstruksi Kayu Meranti 1,435,750.00 1,472,950.00
6 SNI - A.6.7a M2 Pemb. Rumah Jaga / Konstruksi Kayu Tahun 628,450.00 658,750.00
7 SNI - A.6.8 M2 Membersihkan Lapangan dan Perataan 4,450.00 4,450.00
8 SNI - A.6.10 Bh Pemb. Bak Adukan Uk.(40x50x20)cm Ky.Tahun 77,342.50 79,642.50
9 SNI - A.6.11 M2 Pembuatan Steger dari Bambu 16,702.50 17,327.50
10 SNI - A.6.13 M3 Bongkaran Beton Bertulang 191,664.00 191,664.00
11 SNI - A.6.14 M3 Bongkaran Dinding Tembok Bt.Merah 181,164.00 181,164.00

B. PEKERJAAN TANAH
1 SNI - B.6.1 M3 Galian Tanah Biasa Sedalam 1 M 12,200.00 12,200.00
2 SNI - B.6.2 M3 Galian Tanah Biasa Sedalam 2 M 16,022.00 16,022.00
3 SNI - B.6.3 M3 Galian Tanah Biasa Sedalam 3 M 22,400.00 22,400.00
4 SNI - B.6.4 M3 Galian Tanah Keras Sedalam 1 M 19,045.00 19,045.00
5 SNI - B.6.7 M2 Pekerjaan Striping Setinggi 1 M 1,525.00 1,525.00
6 SNI - B.6.8 M3 Pembuangan Tanah Sejauh 150 M 15,682.00 15,682.00
7 SNI - B.6.9 M3 Urugan Kembali 5,849.00 5,849.00
8 SNI - B.6.10 M3 Pemadatan Tanah 15,250.00 15,250.00
9 SNI - B.6.11 M3 Urugan Pasir 74,450.00 83,450.00
10 SNI - B.6.14 M3 Pemasangan Lapisan Ijuk 328,575.00 352,575.00
11 SNI - B.6.15 M3 Urugan Sirtu 82,625.00 88,625.00

C. PEKERJAAN PONDASI BATU KALI


1 SNI - C.6.5 M3 Pas. Pondasi Batu Kali 1 PC : 4 Ps 409,025.00 419,566.00
2 SNI - C.6.6 M3 Pas. Pondasi Batu Kali 1 PC : 5 Ps 378,665.00 389,197.00
3 SNI - C.6.12 M3 Pas. Pondasi Bt.Kali 1 PC : 3 Kp : 10 Ps 304,090.00 314,442.00
4 SNI - C.6.14 M3 Pas. Pondasi Batu Kosong 166,965.00 175,215.00

D. PEKERJAAN DINDING
1 SNI - D.6.3 M2 Pas. Batu Merah tb.1 bata 1Pc:3Ps 123,475.00 127,188.15
2 SNI - D.6.5 M2 Pas. Batu Merah tb.1 bata 1Pc:5Ps 111,510.00 115,230.40
3 SNI - D.6.7 M2 Pas. Batu Merah tb.1 bata 1Pc:3Kp:10Ps 99,871.00 103,572.81
4 SNI - D.6.10 M2 Pas. Batu Merah tb.1/2 bata 1Pc:3Ps 58,609.00 60,409.59
5 SNI - D.6.12 M2 Pas. Batu Merah tb.1/2 bata 1Pc:5Ps 53,406.00 55,211.26
6 SNI - D.6.15 M2 Pas. Batu Merah tb.1/2 bata 1Pc:3Kp:10Ps 49,640.00 51,521.50

E. PEKERJAAN PLESTERAN
1 SNI - E.6.3 M2 Plesteran 1Pc:3Ps tb.1,5 cm 20,541.00 20,728.86
2 SNI - E.6.5 M2 Plesteran 1PC:5Ps tb.1,5 cm 18,204.00 18,399.24
49 / 128
HRG SATUAN (Rp)
NO KODE ANALISSATUAN JENIS PEKERJAAN KATAGORI I KATAGORI II
(Mudah) (Sulit)
3 SNI - E.6.9 M2 Plesteran 1Pc:3Kp:10Ps tb.1,5 cm 15,358.00 15,505.88
4 SNI - E.6.14 M2 Plesteran 1Pc:3Ps tb.2 cm 29,557.50 29,828.10
5 SNI - E.6.16 M2 Plesteran 1Pc:5Ps tb.2 cm 25,515.50 25,776.53
6 SNI - E.6.28 M2 Berapen 1Pc:5Ps tb.1,5 cm 15,609.00 15,821.19
7 SNI - E.6.30 M2 Plesteran Beton 1Pc:3 Ps tb.1,5 cm 24,944.00 25,150.99
8 SNI - E.6.31 M2 Plesteran Skoning 1Pc:2Ps 4,944.00 4,962.50
9 SNI - E.6.35 M2 Plesteran Siar Adukan 1Pc:2Ps 13,394.00 13,544.24

50 / 128
HRG SATUAN (Rp)
NO KODE ANALISSATUAN JENIS PEKERJAAN KATAGORI I KATAGORI II
(Mudah) (Sulit)

F. PEKERJAAN KAYU
1 SNI - F.6.1 M3 Pas. Kusen pintu dan Jendela Ky.Jati 16,842,500.00 16,925,000.00
2 SNI - F.6.2 M3 Pas. Kusen pintu dan Jendela Ky.Kamper 9,946,300.00 10,036,300.00
3 SNI - F.6.2a M3 Pas. Kusen pintu dan Jendela Ky.Bangkir 10,121,500.00 10,211,500.00
4 SNI - F.6.2b M3 Pas. Kusen pintu dan Jendela Ky.Kruing 7,451,500.00 7,541,500.00
5 SNI - F.6.2c M3 Pas. Kusen Pintu dan Jendela Ky Jati (lokal) 16,777,500.00 16,860,000.00
Pas. Soko/ Tiang Kayu Jati ( uk.Khusus 30/30-12/12P:5-8 m' ) diketam
6 SNI - F.6.2d M3 halus dan dipropil (Kw.Eksport) 58,427,860.00 58,517,860.00
Pas. Soko/ Tiang Kayu Jati ( uk.Khusus 8/15-5/10 P:5-8 m' ) diketam
7 SNI - F.6.2e M3 halus dan dipropil (Kw.Eksport) 30,827,860.00 30,917,860.00
Pas. Soko/ Tiang Kayu Bangkir( uk.Khusus 30/30-12/12P:5-8 m' )
8 SNI - F.6.2f M3 diketam halus dan dipropil 12,491,860.00 12,581,860.00
9 SNI - F.6.7 M2 Pas. Pintu Panil Kayu Jati 630,750.00 633,750.00
10 SNI - F.6.8 M2 Pas. Pintu Panil Kayu Kamper 458,750.00 461,750.00
11 SNI - F.6.8a M2 Pas. Pintu Panil Kayu Bangkir 478,750.00 481,750.00
12 SNI - F.6.8b M2 Pas. Pintu Panil Kayu Kruing 362,750.00 365,750.00
13 SNI - F.6.9 M2 Pas. Pintu dan Jendela Kaca Ky. Jati 543,000.00 545,625.00
14 SNI - F.6.10 M2 Pas. Pintu dan Jendela Kaca Ky.Kamper 392,500.00 395,125.00
15 SNI - F.6.10a M2 Pas. Pintu dan Jendela Kaca Ky.Bangkir 410,000.00 412,625.00
16 SNI - F.6.10b M2 Pas. Pintu dan Jendela Kaca Ky. Kruing 308,500.00 311,125.00
17 SNI - F.6.12 M2 Pas. Pintu dan Jendela Jalusi Ky. Jati 964,700.00 969,500.00
18 SNI - F.6.13 M2 Pas. Pintu dan Jendela Jalusi Ky. Kamper 696,500.00 701,300.00
19 SNI - F.6.13a M2 Pas. Pintu dan Jendela Jalusi Ky. Bangkir 728,500.00 733,300.00
20 SNI - F.6.13b M2 Pas. Pintu dan Jendela Jalusi Ky. Kruing 542,900.00 547,700.00
21 SNI - F.6.16 M2 Pas. Jalusi Mati Kusen Kayu Jati 857,652.50 862,152.50
22 SNI - F.6.17 M2 Pas. Jalusi Mati Kusen Kayu Kamper 599,652.50 604,152.50
23 SNI - F.6.17a M2 Pas. Jalusi Mati Kusen Kayu Bangkir 629,652.50 634,152.50
24 SNI - F.6.17b M2 Pas. Jalusi Mati Kusen Kayu Kruing 455,652.50 460,152.50
25 SNI - F.6.19 M2 Pas. Pintu Teakwood 3 mm rkp, rk.Ky. Jati 428,785.00 431,255.00
26 SNI - F.6.20 M2 Pas. Pintu Teakwood 3 mm rkp, rk.Ky. Kamper 344,505.00 346,975.00
27 SNI - F.6.20a M2 Pas. Pintu Teakwood 3 mm rkp, rk.Ky. Bangkir 354,305.00 356,775.00
28 SNI - F.6.20b M2 Pas. Pintu Teakwood 3 mm rkp, rk.Ky. Kruing 297,465.00 299,935.00
29 SNI - F.6.20c M2 Pas. Pintu Triplek 3mm rangkap, rk.Ky. Kamper 316,005.00 318,975.00
30 SNI - F.6.20d M2 Pas. Pintu Triplek 3mm rangkap, rk.Ky. Bangkir 325,805.00 328,775.00
31 SNI - F.6.20e M2 Pas. Pintu Triplek 3mm rangkap, rk.Ky. Kruing 268,965.00 271,935.00
32 SNI - F.6.27 M3 Pas. Konstruksi Kuda-kuda Kayu Jati 16,826,400.00 16,923,900.00
Pas. Rangka Atap diketam halus dan diPropil Kayu Jati (Kw.Eksport)
33 SNI - F.6.27a M3 uk.Khusus(30/30 - 12/12 P : 5-8) 53,925,400.00 54,022,900.00
Pas. Rangka Atap diketam halus dan diPropil Kayu Jati (Kw.Eksport)
34 SNI - F.6.27b M3 uk.Khusus (8/15 - 5/10 P : 5-8) 34,537,900.00 34,635,400.00
Pas. Rangka Atap diketam halus dan diPropil Kayu Jati (Kw.Eksport)
35 SNI - F.6.27c M3 uk.Bukan Khusus 28,625,400.00 28,722,900.00
36 SNI - F.6.28 M3 Pas. Konstruksi Kuda-kuda Kayu Kamper 9,235,300.00 9,332,800.00
37 SNI - F.6.28a M3 Pas. Konstruksi Kuda-kuda Kayu Bangkir 9,395,900.00 9,493,400.00
Pas. Rangka Atap diketam halus dan diPropil Ky.Bangkir uk.Khusus
38 SNI - F.6.28b M3 (30/30 - 12/12 P : 5-8) 11,810,400.00 11,907,900.00
Pas. Rangka Atap diketam halus dan diPropil Ky.Bangkir uk.Khusus
39 SNI - F.6.28c M3 (8/15 - 5/10 P : 5-8) 9,395,900.00 12,580,400.00

51 / 128
HRG SATUAN (Rp)
NO KODE ANALISSATUAN JENIS PEKERJAAN KATAGORI I KATAGORI II
(Mudah) (Sulit)
40 SNI - F.6.30 M3 Pas. Konstruksi Kuda-kuda Kayu Kruing 6,948,400.00 7,045,900.00
Pas. Kaso dan Reng genteng (kodok, plentong, vlams dan sejenisnya)
41 SNI - F.6.31 M2 78,775.00 79,675.00
Kayu Kamper
Pas. Kaso dan Reng genteng (kodok, plentong, vlams dan sejenisnya)
42 SNI - F.6.31a M2 87,175.00 88,075.00
Kayu Bangkir
Pas. Kaso dan Reng genteng (kodok, plentong, vlams dan sejenisnya)
43 SNI - F.6.31b M2 67,975.00 68,875.00
Kayu Kruing
Pas. Kaso dan Reng genteng (kodok, plentong, vlams dan sejenisnya)
44 SNI - F.6.31c M2 55,975.00 56,875.00
Kayu Meranti

52 / 128
HRG SATUAN (Rp)
NO KODE ANALISSATUAN JENIS PEKERJAAN KATAGORI I KATAGORI II
(Mudah) (Sulit)
Pas. Kaso dan Reng genteng (kodok, plentong, vlams dan sejenisnya)
45 SNI - F.6.31d M2 125,815.00 126,715.00
Kayu Bangkir uk. 5/10

46 SNI - F.6.35 M2 Pas. Kaso dan Reng genteng (monier dan sejenisnya) Kayu Kamper 90,375.00 91,425.00

47 SNI - F.6.35a M2 Pas. Kaso dan Reng genteng (monier dan sejenisnya) Kayu Bangkir 100,175.00 101,225.00

48 SNI - F.6.35b M2 Pas. Kaso dan Reng genteng (monier dan sejenisnya) Kayu Kruing 77,775.00 78,825.00

49 SNI - F.6.35c M3 Pas. Usuk 5/10 P : 5 - 8 m Kayu Bangkir diketam halus dan dipropil 12,988,656.00 13,078,705.00

50 SNI - F.6.35d M3 Pas. Usuk 5/10 P : 2 - 4 m Kayu Bangkir diketam halus dan dipropil 9,892,656.00 9,982,705.00
Pas. Usuk 5/10 P : 5 - 8 m Kayu Jati diketam halus dan dipropil (Kw.
51 SNI - F.6.35e M3 37,048,831.00 37,138,880.00
Eksport)
Pas. Usuk 5/10 P : 2 - 4 m Kayu Jati diketam halus dan dipropil (Kw.
52 SNI - F.6.35f M3 30,598,831.00 30,688,880.00
Eksport)
53 SNI - F.6.38 M2 Pas. Rangka Langit-Langit Uk.(1x1)m Ky.Jati 136,275.00 137,175.00
Pas. Lambersering uk. 1/20 Kayu Jati diketam halus dan dipropil
54 SNI - F.6.38a M2 (Kw.Eksport) 402,130.00 402,880.00
55 SNI - F.6.39 M2 Pas. Rangka Langit-Langit Uk.(1x1)m Ky.Kamper 87,075.00 87,975.00
56 SNI - F.6.39a M2 Pas. Rangka Langit-Langit Uk.(1x1)m Ky.Bangkir 95,475.00 96,375.00
57 SNI - F.6.39b M2 Pas. Rangka Langit-Langit Uk.(1x1)m Ky.Kruing 76,275.00 77,175.00
58 SNI - F.6.39c M2 Pas. Rangka Langit-Langit Uk.(1x1)m Ky.Meranti 64,275.00 65,175.00

59 SNI - F.6.39d M2 Pas. Lambersering uk. 1/20 Kayu Bangkir diketam halus dan dipropil 99,130.00 99,880.00
60 SNI - F.6.44 M2 Pas. Rangka Langit-Langit Uk.(0.3x0.3)m Ky.Kamper 179,987.50 182,012.50
61 SNI - F.6.44a M2 Pas. Rangka Langit-Langit Uk.(0.3x0.3)m Ky.Bangkir 198,887.50 200,912.50
62 SNI - F.6.44b M2 Pas. Rangka Langit-Langit Uk.(0.3x0.3)m Ky.Kruing 155,687.50 157,712.50
63 SNI - F.6.44c M2 Pas. Rangka Langit-Langit Uk.(0.3x0.3)m Ky.Meranti 128,687.50 130,712.50
64 SNI - F.6.47 M' Pas. Lisplank Uk. (3 x 20) cm Kayu Jati 103,310.00 103,850.00

65 SNI - F.6.47a M' Pas. Lisplank dipropil dan divariasi uk. 3x30 Kayu Jati (Kw.Eksport) 375,280.00 375,955.00
66 SNI - F.6.48 M' Pas. Lisplank Uk. (3 x 20) cm Kayu Kamper 72,175.00 72,715.00
67 SNI - F.6.48a M' Pas. Lisplank Uk. (3 x 20) cm Kayu Bangkir 75,775.00 76,315.00
68 SNI - F.6.48b M' Pas. Lisplank Uk. (3 x 20) cm Kayu Kruing 54,895.00 55,435.00

69 SNI - F.6.48c M' Pas. Lisplank dipropil dan divariasi uk. 3x30 Kayu Bangkir 102,580.00 103,255.00
70 SNI - F.6.52 M' Pas. Lisplank Uk. 2 (2 x 20) cm Kayu Jati 119,210.00 119,855.00
71 SNI - F.6.52a M' Pas. Lisplank Uk. 2 (2 x 20) cm Kayu Kamper 82,230.00 82,875.00
72 SNI - F.6.52b M' Pas. Lisplank Uk. 2 (2 x 20) cm Kayu Bangkir 86,530.00 87,175.00
73 SNI - F.6.52c M' Pas. Lisplank Uk. 2 (2 x 20) cm Kayu Kruing 61,590.00 62,235.00

G. PEKERJAAN BETON
1 SNI - G.6.1 M3 Membuat Beton Tumbuk 1Pc:3Ps:5Kr 487,850.00 501,976.00
2 SNI - G.6.4 M3 Lantai Kerja Beton Tumbuk 1Pc:3Ps:5Kr tb.5cm 52,545.00 53,250.00
3 SNI - G.6.7 M3 Membuat Beton Cor 1Pc:2Ps:2,5Kr 628,550.00 642,214.00
4 SNI - G.6.13 M3 Membuat Beton Cor 1Pc:2Ps:3Kr 668,150.00 682,652.00
5 SNI - G.6.25 Kg Pembesian dengan Besi Beton Polos (sek. KS) 16,461.00 17,526.00
6 SNI - G.6.25a Kg Pembesian dengan Besi Beton Ulir 16,461.00 17,526.00
7 SNI - G.6.25b Kg Pembesian dengan Besi Beton Polos (sek.Non KS) 15,411.00 16,476.00
8 SNI - G.6.28 M2 Pas. Bekisting untuk Pondasi 77,035.00 79,035.00

53 / 128
HRG SATUAN (Rp)
NO KODE ANALISSATUAN JENIS PEKERJAAN KATAGORI I KATAGORI II
(Mudah) (Sulit)
9 SNI - G.6.29 M2 Pas. Bekisting untuk Sloof 83,785.00 86,035.00
10 SNI - G.6.30 M2 Pas. Bekisting untuk Kolom 248,890.00 263,065.00
11 SNI - G.6.31 M2 Pas. Bekisting untuk Balok 261,130.00 275,530.00
12 SNI - G.6.32 M2 Pas. Bekisting untuk Lantai 369,430.00 403,605.00
13 SNI - G.6.33 M2 Pas. Bekisting untuk Dinding 355,430.00 376,480.00
14 SNI - G.6.34 M2 Pas. Bekisting untuk Tangga 235,930.00 249,605.00
15 SNI - G.6.45 M' Memb. Kolom Penguat Beton Bertulang (11x11)cm 66,165.00 69,878.00
16 SNI - G.6.46 M' Membuat Ring Balok Beton Bertulang (10x15)cm 75,250.00 79,306.00

54 / 128
HRG SATUAN (Rp)
NO KODE ANALISSATUAN JENIS PEKERJAAN KATAGORI I KATAGORI II
(Mudah) (Sulit)

H. PEKERJAAN ATAP
1 SNI - H.6.1 M2 Pas. Atap Genteng Plentong Kecil 34,297.50 35,547.50
2 SNI - H.6.2 M2 Pas. Atap Genteng Kodok 39,547.50 40,797.50
3 SNI - H.6.4 M' Pas. Atap Genteng Bubung Plentong 42,890.00 44,436.00
4 SNI - H.6.12 M2 Pas. Fiber semen Gelombang Uk.(3,00x1,05m)x4mm 39,655.00 40,005.00
5 SNI - H.6.13 M2 Pas. Fiber semen Gelombang Uk.(2,70x1,05m)x4mm 42,245.00 42,665.00
6 SNI - H.6.14 M2 Pas. Fiber semen Gelombang Uk.(2,40x1,05m)x4mm 40,167.50 40,607.50
7 SNI - H.6.15 M2 Pas. Fiber semen Gelombang Uk.(2,10x1,05m)x4mm 40,407.50 40,917.50
8 SNI - H.6.16 M2 Pas. Fiber semen Gelombang Uk.(1,50x1,05m)x4mm 44,207.50 45,007.50
9 SNI - H.6.16.a M2 Pas. Atap seng Galvalum 79,407.50 81,807.50
10 SNI - H.6.23 M' Pas. Nok Stel Fiber semen Gelombang Uk. 1,05m 58,825.50 60,925.50
11 SNI - H.6.30 M2 Pas. Atap Genteng Beton 51,690.00 52,240.00
12 SNI - H.6.30a M2 Pas. Atap Genteng Morando 46,790.00 47,690.00
13 SNI - H.6.34 M' Pas. Atap Nok Genteng Beton 50,780.00 51,320.60
14 SNI - H.6.34a M' Pas. Atap Nok Genteng Morando 50,780.00 51,495.60
15 SNI - H.6.38 M2 Pas. Atap Seng Gelombang BJLS 20 38,990.00 39,690.00
16 SNI - H.6.39 M2 Pas. Atap Nok Seng 14,975.00 15,275.00
17 SNI - H.6.40 M' Pas. Talang Datar Seng BJLS 30 Ky.Meranti 74,118.75 75,588.75
18 SNI - H.6.40a M' Pas. Talang Datar Seng BJLS 30 Ky.Kruing 146,558.75 148,783.75
19 SNI - H.6.41 M' Pas. Talang Miring Seng BJLS 30 Ky.Meranti 111,883.75 114,108.75
20 SNI - H.6.41a M' Pas. Talang Miring Seng BJLS 30 Ky.Kruing 146,558.75 148,783.75
21 SNI - H.6.42 M2 Pas. Aluminium Foil / Sisalation 19,780.00 20,305.00
22 SNI - H.6.43 M2 Pas. Kawat Burung Kayu Meranti 29,849.50 31,084.50
23 SNI - H.6.43a M2 Pas. Kawat Burung Kayu Kruing 33,134.50 34,369.50

I. PEKERJAAN LANGIT - LANGIT


1 SNI - I.6.19 M' Lis Langit-langit Kayu Propil Kayu Kruing 9,523.50 10,073.50
2 SNI - I.6.19a M' Lis Langit-langgit Kayu Kruing 7,323.50 7,873.50
3 SNI - I.6.20 M2 Langit-langit Eternit Rk.Ky.Kamper Uk.(1x1)m 95,293.50 96,413.50
4 SNI - I.6.20a M2 Langit-langit Eternit Rk.Ky.Bangkir Uk. (1x1)m 103,693.50 104,813.50
5 SNI - I.6.20b M2 Langit-langit Eternit Rk.Ky.Kruing Uk. (1x1)m 84,493.50 85,613.50
6 SNI - I.6.20c M2 Langit-langit Eternit Rk.Ky.Meranti Uk. (1x1)m 72,178.50 73,298.50
7 SNI - I.6.20d M2 Langit-langit Harplek 4mm Rk.Ky.Kruing Uk. (1x1)m 102,933.50 104,383.50
8 SNI - I.6.20e M2 Langit-langit Harplek 4mm Rk.Ky.Meranti Uk. (1x1)m 84,813.50 85,663.50
9 SNI - I.6.24 M2 Langit-langit Gypsum board tb.9mm 27,927.00 28,655.00

J. PEKERJAAN SANITASI
1 SNI - J.6.1 Bh Pasang Kloset Duduk / Monoblok 1,614,485.00 1,640,985.00
2 SNI - J.6.2 Bh Pasang Kloset Jongkok Porselen 299,900.00 297,017.00
3 SNI - J.6.4 Bh Pasang Urinoir 594,550.00 620,667.00
4 SNI - J.6.5 Bh Pasang Wastafel 628,325.00 634,042.00
5 SNI - J.6.7 Bh Pasang Bak Mandi Fiberglass vol. 0,30 m3 air 365,600.00 344,360.00
6 SNI - J.6.8 Bh Pasang Bak Mandi Batu Bata vol. 0,30 m3 air. 741,600.00 760,690.00
7 SNI - J.6.9 Bh Pasang Bath tubh Porselen 4,670,637.50 4,837,437.50
8 SNI - J.6.11 Bh Pasang Bak Fiberglass vol. 1 m3 air 1,181,770.00 908,490.00
9 SNI - J.6.16 Bh Pas. Bak Kontrol pas.Bt.Bata uk.(35x35)cm T:35 cm 242,420.00 247,743.00
10 SNI - J.6.17 Bh Pas. Bak Kontrol pas.Bt.Bata uk.(45x45)cm T:50 cm 263,417.50 271,406.50
11 SNI - J.6.18 Bh Pas. Bak Kontrol pas.Bt.Bata uk.(60x60)cm T:65 cm 408,466.00 421,176.00
12 SNI - J.6.19 M' Pasang Pipa Galvanis diam. 1/2" med. B 32,768.00 33,543.00

55 / 128
HRG SATUAN (Rp)
NO KODE ANALISSATUAN JENIS PEKERJAAN KATAGORI I KATAGORI II
(Mudah) (Sulit)
13 SNI - J.6.20 M' Pasang Pipa Galvanis diam. 3/4" med. B 42,068.00 42,843.00
14 SNI - J.6.21 M' Pasang Pipa Galvanis diam. 1" med. B 52,918.00 53,693.00
15 SNI - J.6.22 M' Pasang Pipa Galvanis diam. 1 1/2" med. B 76,235.00 77,010.00
16 SNI - J.6.22a M' Pasang Pipa Galvanis diam. 2" med. B 93,285.00 94,060.00
17 SNI - J.6.23 M' Pasang Pipa Galvanis diam. 3" med. B 159,160.00 159,935.00
18 SNI - J.6.24 M' Pasang Pipa Galvanis diam. 4" med. B 214,258.00 215,033.00
19 SNI - J.6.25 M' Pasang Pipa PVC diam. 1/2" type AW 9,395.00 10,170.00
20 SNI - J.6.26 M' Pasang Pipa PVC diam. 3/4" type AW 11,642.50 12,417.50
21 SNI - J.6.27 M' Pasang Pipa PVC diam. 1" type AW 14,045.00 14,820.00

56 / 128
HRG SATUAN (Rp)
NO KODE ANALISSATUAN JENIS PEKERJAAN KATAGORI I KATAGORI II
(Mudah) (Sulit)

22 SNI - J.6.28 M' Pasang Pipa PVC diam. 1 1/2" type AW 19,935.00 21,020.00
23 SNI - J.6.29 M' Pasang Pipa PVC diam. 2" type AW 26,260.00 26,492.50
24 SNI - J.6.31 M' Pasang Pipa PVC diam. 3" type AW 47,030.00 48,192.50
25 SNI - J.6.32 M' Pasang Pipa PVC diam. 4" type AW 76,940.50 78,490.50
26 SNI - J.6.33 Bh Pasang Bak Cuci Piring Stainless Steel 264,662.50 255,662.50
27 SNI - J.6.35 Bh Pasang Kran diameter 3/4". 39,107.50 39,107.50
28 SNI - J.6.35a Bh Pasang Kran diameter 1/2" 19,107.50 19,107.50
29 SNI - J.6.36 Bh Pasang Floor Drain 24,045.00 24,045.00

K. PEKERJAAN KUNCI DAN KACA


1 SNI - K.6.1 Bh Pasang Kunci tanam antik 323,325.00 323,325.00
2 SNI - K.6.2 Bh Pasang Kunci Tanam Biasa 107,045.00 102,045.00
3 SNI - K.6.3 Bh Pasang Kunci Tanam Kamar Mandi 52,045.00 49,045.00
4 SNI - K.6.5 Bh Pasang Engsel Pintu 13,331.25 13,331.25
5 SNI - K.6.6 Bh Pasang Engsel Jendela Kupu-kupu 10,831.25 10,831.25
6 SNI - K.6.7 Bh Pasang Engsel Angin 28,090.00 28,090.00
7 SNI - K.6.9 Bh Pasang Kait Angin model lipat 10,831.25 10,831.25
8 SNI - K.6.9.a Bh Pasang Kait Angin model antik 22,331.25 22,331.25
9 SNI - K.6.10 Bh Pasang Door Closer 219,437.50 219,437.50
10 SNI - K.6.11 Bh Pasang Kunci Selot 92,775.00 92,775.00
11 SNI - K.6.12 Bh Pasang Pegangan pintu/Door Holder 194,937.50 194,937.50
12 SNI - K.6.13 Bh Pasang Door Stop 40,887.50 40,887.50
13 SNI - K.6.14 Bh Pasang Rel Pintu Dorong 323,325.00 323,325.00
14 SNI - K.6.16 Bh Pasang Kaca tb. 3mm 61,931.25 66,331.25
15 SNI - K.6.17 Bh Pasang Kaca tb. 5mm 88,331.25 89,981.25
16 SNI - K.6.18 Bh Pasang Kaca tb. 8mm 204,413.50 206,613.50
17 SNI - K.6.20 Bh Pasang Kaca Cermin tb. 5mm 192,831.25 195,031.25

L. PEKERJAAN LANTAI
1 SNI - L.6.2 M2 Pas. Lantai Ubin PC Abu-abu 30 x 30 cm 49,542.50 52,580.00
2 SNI - L.6.3 M2 Pas. Lantai Ubin PC Abu-abu 20 x 20 cm 44,620.00 47,444.05
3 SNI - L.6.44 M2 Pas. Lantai Keramik 20 x 20 cm (Klas A) 93,061.00 96,180.66
4 SNI - L.6.44a M2 Pas. Lantai Keramik 20 x 20 cm (Klas B) 97,566.00 100,685.66
5 SNI - L.6.44b M2 Pas. Lantai Keramik 20 x 20 cm (Klas C) 113,466.00 113,935.66
6 SNI - L.6.47 M2 Pas. Lantai Keramik 33 x 33 cm (Klas C) 119,866.00 122,335.66
7 SNI - L.6.47a M2 Pas. Lantai Keramik 40 x 40 cm (Klas A) 96,556.00 98,425.66
8 SNI - L.6.47b M2 Pas. Lantai Keramik 40 x 40 cm (Klas B) 101,806.00 103,675.66
9 SNI - L.6.47c M2 Pas. Lantai Keramik 40 x 40 cm (Klas C) 115,666.00 116,835.66
10 SNI - L.6.47d M2 Pas. Lantai Keramik 40 x 40 cm (Klas D) 138,066.00 139,550.66
11 SNI - L.6.47e M2 Pas. Lantai Keramik 30 x 30 cm (Klas A) 85,866.00 88,195.66
12 SNI - L.6.47f M2 Pas. Lantai Keramik 30 x 30 cm (Klas B) 91,206.00 94,075.66
13 SNI - L.6.47g M2 Pas. Lantai Keramik 30 x 30 cm (Klas C) 99,666.00 102,535.66
14 SNI - L.6.47h M2 Pas. Lantai Keramik 30 x 30 cm (Klas D) 120,066.00 121,243.66
15 SNI - L.6.48 M2 Pas. Lt. Keramik Anti Slip 33x33 cm (Klas C) 120,866.00 122,335.66
16 SNI - L.6.48a M2 Pas. Lt.Keramik Anti Slip 40x40 cm (Klas A) 101,211.00 103,080.66
17 SNI - L.6.48b M2 Pas. Lt.Keramik Anti Slip 40x40 cm (Klas B) 109,366.00 110,885.66
18 SNI - L.6.48c M2 Pas. Lt.Keramik Anti Slip 40x40 cm (Klas C) 116,366.00 117,535.66
19 SNI - L.6.48d M2 Pas. Lt.Keramik Anti Slip 40x40 cm (Klas D) 141,566.00 142,875.66
20 SNI - L.6.48e M2 Pas. Lt.Keramik Anti Slip 30x30 cm (Klas A) 89,166.00 92,035.66
57 / 128
HRG SATUAN (Rp)
NO KODE ANALISSATUAN JENIS PEKERJAAN KATAGORI I KATAGORI II
(Mudah) (Sulit)
21 SNI - L.6.48f M2 Pas. Lt.Keramik Anti Slip 30x30 cm (Klas B) 95,706.00 98,575.66
22 SNI - L.6.48g M2 Pas. Lt.Keramik Anti Slip 30x30 cm (Klas C) 101,166.00 104,035.66
23 SNI - L.6.48h M2 Pas. Lt.Keramik Anti Slip 30x30 cm (Klas D) 121,266.00 123,055.66
24 SNI - L.6.68 M2 Pas. Dinding Keramik 20x20 cm (Klas A) 78,355.00 81,280.10
25 SNI - L.6.68a M2 Pas. Dinding Keramik 20x20 cm (Klas B) 100,615.00 101,897.10
26 SNI - L.6.68b M2 Pas. Dinding Keramik 20x25 cm (Klas A) 85,315.00 87,690.10
27 SNI - L.6.68c M2 Pas. Dinding Keramik 20x25 cm (Klas B) 91,825.00 94,200.10
28 SNI - L.6.68d M2 Pas. Dinding Keramik 20x25 cm (Klas C) 93,715.00 96,090.10
29 SNI - L.6.68e M2 Pas. Dinding Keramik 20x25 cm (Klas D) 98,860.00 101,235.10

58 / 128
HRG SATUAN (Rp)
NO KODE ANALISSATUAN JENIS PEKERJAAN KATAGORI I KATAGORI II
(Mudah) (Sulit)

M. PEKERJAAN PENGECATAN
1 SNI - M.6.1 M2 Mengerok Permukaan Cat Tembok Lama 5,087.50 5,087.50
2 SNI - M.6.6 M2 Mendempul dan Menggosok Kayu 4,050.25 4,112.50
3 SNI - M.6.7 M2 Mengecat kayu Lama 19,895.50 20,242.50
4 SNI - M.6.8 M2 Mengecat kayu 2 x jadi (Sek. Avian) 23,291.00 23,910.00
5 SNI - M.6.8a M2 Mengecat kayu 2 x jadi (Sek. Dulux) 37,180.00 37,885.00
6 SNI - M.6.9 M2 Mengecat kayu 3 x jadi (Sek. Avian) 29,734.00 30,425.00
7 SNI - M.6.9a M2 Mengecat kayu 3 x jadi (Sek. Dulux) 46,530.00 47,325.00
8 SNI - M.6.11 M2 Pelaburan Kayu dgn Politur 27,389.50 27,389.50
9 SNI - M.6.11a M2 Pelaburan Kayu dgn Politur sek. Mowilex 39,917.50 39,917.50
10 SNI - M.6.12 M2 Pelaburan Kayu dgn Cat Residu dan Ter 5,710.00 5,710.00
11 SNI - M.6.14 M2 Mengecat Tembok Baru utk interior(sek.Mowilex) 19,665.50 19,845.50
12 SNI - M.6.14a M2 Mengecat Tembok Baru utk exterior (sek.Mowilex) 27,405.50 27,405.50
13 SNI - M.6.14b M2 Mengecat Tembok Baru (sek.Catylac) 9,243.50 9,423.50
14 SNI - M.6.14c M2 Mengecat Tembok Baru (sek.Decolith) 8,235.50 8,415.50
15 SNI - M.6.14d M2 Mengecat Tembok Baru (sek.Maxilite) 7,407.50 7,587.50
16 SNI - M.6.15 M2 Mengecat Tembok Lama utk interior(sek.Mowilex) 15,705.50 15,855.50
17 SNI - M.6.15a M2 Mengecat Tembok Lama utk exterior(sek.Mowilex) 22,155.50 22,155.50
18 SNI - M.6.15b M2 Mengecat Tembok Lama (sek.Catylac) 7,020.50 7,170.50
19 SNI - M.6.15c M2 Mengecat Tembok Lama (sek.Decolith) 6,180.50 6,330.50
20 SNI - M.6.15d M2 Mengecat Tembok Lama (sek.Maxilite) 5,490.50 5,640.50
21 SNI - M.6.17 M2 Melabur Tembok dengan Kapur Sirih 5,393.50 5,443.50
22 SNI - M.6.18 M2 Melabur Tembok Lama dgn Kapur Sirih 2,067.50 2,067.50
23 SNI - M.6.20 M2 Mengecat Baja dengan Meni Besi 9,228.00 9,330.00
24 SNI - M.6.21 M2 Mengecat Baja dgn Meni Besi & Perancah 16,370.50 16,472.50
25 SNI - M.6.24 M2 Mengecat Baja 3x cat konvensional 70,572.00 70,860.00
ANALISA BOW
A. PEKERJAAN PAVING
1 BOW - KPU.IVa M2 Pas. Paving Blok Natural 6 cm 64,200.00 65,950.00
2 BOW - KPU.IVb M2 Pas. Paving Blok Warna 6 cm 87,200.00 88,950.00
3 BOW - KPU.IVc M2 Pas. Paving Blok T = 8cm K-400 132,200.00 134,950.00
4 BOW - KPU.IVd M2 Pas. Paving Blok T = 6cm K-300 92,200.00 93,950.00
5 BOW - KPU.Ive M2 Pas. Batu Andesit 20/20 cm (ex. Baseh) T= 6 cm 302,200.00 302,950.00

B. PEKERJAAN KAP BESI


1 BOW - I.a Kg Pekerjaan Kap Besi 21,805.00 22,905.00

C. PEKERJAAN KAYU
1 BOW - F.16 M2 Pas. Kembali Usuk dan Reng Bekas 10,975.00 10,975.00
2 BOW - F.16a M2 Pas. Reng Kayu Kruing 22,796.25 23,021.25
3 BOW - F.16b M2 Usuk Diketam Halus dan Reng Ky.Kruing 76,250.00 77,150.00
4 BOW - F.16c M2 Usuk Diketam Halus dan Reng Ky.Bangkir 95,450.00 96,350.00
5 BOW - F.16d M2 Usuk Diketam Halus dan Reng Ky.Kamper 87,050.00 87,950.00
6 BOW - F.16e M2 Usuk Diketam Halus dan Reng Ky.Jati 136,250.00 137,150.00
7 BOW - F.16f M2 Pas. Usuk Kayu Kruing 67,031.25 67,931.25
8 BOW - F.16g M2 Pas. Usuk Kayu Bangkir 86,231.25 87,131.25
9 BOW - F.16h M2 Pas. Reng Kayu Jati ( Kw. Eksport ) 83,096.25 83,321.25
59 / 128
HRG SATUAN (Rp)
NO KODE ANALISSATUAN JENIS PEKERJAAN KATAGORI I KATAGORI II
(Mudah) (Sulit)
10 BOW - F.16i M2 Pas. Reng Kayu Bangkir 27,596.25 27,821.25
11 BOW - Supl.VIIIa M2 Plafond Harplek Diatas Usuk 24,537.00 25,087.00
12 BOW - Supl.VIIIb M2 PlaFond Eternit Diatas Usuk 14,237.00 14,457.00
13 BOW - F.36a M2 Pintu Kaca Kayu Kruing tebal 3,5 cm 436,237.00 438,637.00
14 BOW - F.36b M2 Pintu Kaca Kayu Kruing Sederhana tebal 3,5 cm 332,547.00 334,797.00
15 BOW - F.36c M2 Pintu Kaca Kayu Bangkir tebal 3,5 cm 488,437.00 490,837.00
16 BOW - F.36d M2 Pintu Kaca Kayu Kamper tebal 3,5 cm 479,437.00 481,837.00
17 BOW - F.36e M2 Pintu Kaca Kayu Jati tebal 3,5 cm 540,037.00 544,187.00
18 BOW - F.36f M2 Jendela Kaca Kayu Kruing tebal 2,5 cm 314,462.00 318,162.00
19 BOW - F.36g M2 Jendela Kaca Kayu Kruing Sederhana tebal 3 cm 246,087.00 249,787.00
20 BOW - F.36h M2 Jendela Kaca Kayu Bangkir tebal 2,5 cm 349,262.00 352,962.00
21 BOW - F.36i M2 Jendela Kaca Kayu Kamper tebal 2,5 cm 343,262.00 346,962.00

60 / 128
HRG SATUAN (Rp)
NO KODE ANALISSATUAN JENIS PEKERJAAN KATAGORI I KATAGORI II
(Mudah) (Sulit)

22 BOW - F.36j M2 Jendela Kaca Kayu Jati tebal 2,5 cm 394,862.00 398,562.00
23 BOW - F.36k M2 Pintu Panil Multiplek 9 mm Rangka Kayu Jati tebal 3,5 cm 464,420.00 466,890.00
24 BOW - F.36l M2 Pintu Panil Multiplek 9 mm Rangka Kayu Kruing 343,820.00 346,290.00
25 BOW - F.36m M2 Pintu Panil Multiplek 9 mm Rangka Kayu Bangkir 396,020.00 398,490.00
26 BOW - F.36n M2 Pintu Panil Multiplek 9 mm Rangka Kayu Kamper 325,300.00 326,420.00

D. PEKERJAAN PENGECATAN
1 BOW - K.6+23 M2 Mengecat Plapond 3x jadi ( Sek. Catylac ) 16,563.75 16,763.75
2 BOW - K.6+23a M2 Mengecat Plapond 3x jadi ( Sek. Decolith ) 15,442.00 15,642.00
3 BOW - K.6+23b M2 Mengecat Plapond 3x jadi ( Sek. Maxilite ) 14,522.00 14,722.00
4 BOW - K.6+23c M2 Mengecat Genteng 3x jadi (Sek. Tamitex) 18,142.00 18,292.00
PEKERJAAN BETON
E. PEKERJAAN BETON
1 BOW - F.8 M2 Cetakan Kayu Tahun 95,750.00 97,750.00
PEKERJAAN PASANGAN BATU GRANIT
F. PEKERJAAN PEMASANGAN BATU GRANIT
1 BOW-G.14 M3 Perekat camp. 1 Pc : 2 Psr 785,390.00 796,625.40
2 BOW-G.13 M3 Perekat camp. 1 Pc : 1 Psr 1,108,840.00 1,120,211.15
3 BOW-G.77 M2 Upah Pasang Lembaran Batu Granit 326,500.00 326,500.00
4 BOW-Supl.IVa M2 Pasang lantai Batu Granit 609,931.70 610,268.76
5 BOW-Supl.IVb M2 Pasang Pelapis Dinding Batu Granit 1,189,596.80 1,239,894.22
6 BOW-Supl.IVc M2 Pelapisan Coating 3x ( sebelum dipasang ) 11,425.00 11,425.00
7 BOW-Supl.IVd M2 Pelapisan Coating 1x ( setelah dipasang ) 7,120.00 7,120.00
8 BOW-Supl.IVe M2 Pemolesan Lantai Batu Granit ( sampai mengkilap ) 182,950.00 182,950.00
9 BOW-Supl.IVf M2 Pemolesan Lembaran Batu Granit ( Rata, Halus tidak mengkilap ) 27,220.00 27,220.00
10 BOW-Supl.IVg M2 Penyemiran Lantai 8,865.00 8,865.00
11 BOW-G.69 M3 Upah Pasang Tegel 23,375.00 23,375.00
12 BOW-Supl.IVh M2 Pasang Tegel Batu Candi 242,533.95 261,375.08
13 BOW-Supl.IVi M2 Pasang Koral Sikat 192,840.20 210,681.33
14 BOW-Supl.IVj M2 Pasang Pelapis Dinding Batu Granit Import 2,016,096.80 2,016,394.22
PEKERJAAN LAIN - LAIN
1 Up.SNI-H.6.1 M2 Upah Pas. Genteng lama 7,047.50 7,047.50
2 Ls.01 Bh Pas. Grendel pintu 6,000.00 6,000.00
3 Ls.02 Bh Pas. Grendel jendela 4,000.00 4,000.00
4 Ls.03 Bh Pas. Tarikan jendela 4,500.00 4,500.00
5 Ls.04 Daun Pas. Kaca Nako 5 mm + Tralis 20,000.00 20,000.00
6 Ls.05 Kg Pas. Besi, Doog, Angkur 7,000.00 7,000.00
7 Ls.06 Kg Pas. Begel 7,000.00 7,000.00
8 Ls.07 M' Pas. Tutup Lisplank Kayu Kruing Lapis Seng 15,000.00 15,000.00
9 Ls.08 Unit Pembuatan Septictank 1 x 1 x 2 m + Peresapan 4,677,160.75 4,839,095.56
10 Ls.09 Unit Pembuatan Septictank 1.5 x 2 x 2 m + Peresapan 6,432,224.10 6,643,590.25
11 Ls.11 Titik Pas. Instalasi Titik Cahaya / Lampu 150,000.00 150,000.00
12 Ls.12 Titik Pas. Instalasi Stop Kontak 150,000.00 150,000.00
13 Ls.13 Titik Pas. A r d e 150,000.00 150,000.00
14 Ls.14 Unit Biaya Administrasi Sambungan Listrik ( PLN ) 900 watt 565,000.00 565,000.00
15 Ls.15 Unit Biaya Administrasi Sambungan Listrik ( PLN ) 450 watt 290,000.00 290,000.00

61 / 128
HRG SATUAN (Rp)
NO KODE ANALISSATUAN JENIS PEKERJAAN KATAGORI I KATAGORI II
(Mudah) (Sulit)
16 Ls.16 Unit Biaya Administrasi Sambungan Listrik ( PLN ) 1300 watt 808,000.00 808,000.00
17 Ls.16.a Unit Biaya Administrasi Sambungan Listrik ( PLN ) 2200 watt 1,357,000.00 1,357,000.00
18 Ls.17 Bh Pas. Shock 1/2" PVC 1,250.00 1,250.00
19 Ls.18 Bh Pas. Shock 3/4" PVC 1,750.00 1,750.00
20 Ls.19 Bh Pas. Shock 2" PVC 4,000.00 4,000.00
21 Ls.20 Bh Pas. Shock 3" PVC 7,000.00 7,000.00
22 Ls.21 Bh Pas. Shock 4" PVC 12,500.00 12,500.00
23 Ls.22 Bh Pas. Kenie 1/2" PVC 2,000.00 2,000.00

62 / 128
HRG SATUAN (Rp)
NO KODE ANALISSATUAN JENIS PEKERJAAN KATAGORI I KATAGORI II
(Mudah) (Sulit)

24 Ls.23 Bh Pas. Kenie 3/4" PVC 2,500.00 2,500.00


25 Ls.24 Bh Pas. Kenie 2" PVC 5,000.00 5,000.00
26 Ls.25 Bh Pas. Kenie 3" PVC 12,500.00 12,500.00
27 Ls.26 Bh Pas. Kenie 4" PVC 25,000.00 25,000.00
28 Ls.27 M' Pas. Saluran U 20x25 dengan buis beton 80,000.00 80,000.00
29 Ls.31 M' Pas. Papan Sanggan Talang 2 x 20 cm kayu kruing 54,000.00 54,000.00
30 Ls.32 M' Pas. Papan Suri - suri 2 x 20 cm Kayu Kruing 27,000.00 27,000.00
31 Ls.33 M' Pas. Papan Suri - suri 2 / 20 cm Kayu Jati 65,000.00 65,000.00
32 Ls.34 M' Pas. Kawat Duri 3,500.00 3,500.00
33 Ls.35 M2 Pengrosokan Halaman tebal 7 cm 3,250.00 3,250.00
34 Ls.36 Unit Pas. Lampu TL 20 watt 50,000.00 50,000.00
35 Ls.37 Unit Pas. Lampu TL 40 watt 60,000.00 60,000.00
36 Ls.38 Bh Pas. Lampu Pijar 4,500.00 4,500.00
37 Ls.39 Bh Pas. Lampu SL 18 watt 27,500.00 27,500.00
38 Ls.40 Btg Pas. Talang PVC U 75,000.00 75,000.00
39 Ls.41 Bh Pas. Tutup Talang PVC U 3,000.00 3,000.00
40 Ls.42 Bh Pas. Hak Talang PVC U 6,500.00 6,500.00
41 Ls.43 Bh Pas. Kenie Talang PVC U 13,000.00 13,000.00
42 Ls.44 Bh Pas. Corong Talang PVC U 13,000.00 13,000.00
43 Ls.45 Bh Pas. Sarangan Stainless steel 25,000.00 25,000.00
44 Ls.46 Bh Step nosing/ plint tangga 12,000.00 12,000.00
45 Ls.47 m2 Pas. folding gate besi tb.0,30 mm 420,000.00 420,000.00
Ls.47.a m2 Pas. folding gate besi tb.0,40 mm 443,000.00 443,000.00
Ls.47.b m2 Pas. folding gate besi tb.0,50 mm 467,000.00 467,000.00
Ls.47.c m2 Pas. folding gate besi tb.0,80 mm 589,000.00 589,000.00
46 Ls.48 set Pas. pintu aluminium uk. 70 cm lengkap 276,000.00 276,000.00
47 Ls.49 set Pas. pintu PVC uk. 70 cm lengkap 325,000.00 325,000.00
Ls.51 Unit Bongkar pasang dastang 150,000.00 150,000.00

PEKERJAAN JALAN & JEMBATAN

1 E1.30 M2 PEMBERSIHAN DAMIJA 656.37 656.37


2 E1.33 M2 PENYIAPAN BADAN JALAN 1,722.04 1,722.04
3 E1.311a M3 GALIAN TANAH BIASA ( MANUAL) 21,625.00 21,625.00
4 E1.312a M3 GALIAN PADAS / BATUAN (MANUAL) 43,750.00 43,750.00
5 E1.313 M3 GALIAN PERKERASAN ASPAL(MANUAL) 57,810.00 57,810.00
6 E1.321a M3 URUGAN TANAH BIASA DARI HASIL GALIAN 7,399.93 7,399.93
7 E1.322 M3 URUGAN SIRTU 82,399.93 88,399.93
8 E1.321 M3 URUGAN TANAH BIASA 67,399.93 73,399.93
9 E1.511 M3 LAPIS PONDASI AGREGAT KELAS A 187,988.35 193,874.35
10 E1.512 M3 LAPIS PONDASI AGREGAT KELAS B 143,380.75 149,294.35
11 E1.521 M3 LAPIS PONDASI AGREGAT KELAS C 100,728.05 107,478.05
12 E1.611 LITER LAPIS RESAP PENGIKAT 8,577.53 8,916.39
13 E1.612 LITER LAPIS PEREKAT 10,702.81 10,960.17
14 E1.817a M3 LAPIS PENETRASI MACADAM (Leveling) 1,087,879.76 1,115,313.13
15 E1.631 M2 LATASIR ( SAND SHEET ) 34,498.98 35,223.98

63 / 128
HRG SATUAN (Rp)
NO KODE ANALISSATUAN JENIS PEKERJAAN KATAGORI I KATAGORI II
(Mudah) (Sulit)
16 E1.817b M2 LAPIS PENETRASI MACADAM SHEET 64,109.71 65,945.29
17 E1.635 M3 ASPHALT TREATED BASE (ATB) 2,033,039.45 2,063,874.02
18 E1.635a TON ASPHALT TREATED BASE LEVELING (ATBL) 882,321.57 895,727.90
19 E1.633 M2 LATASTON (HRS) 65,112.77 66,078.31
20 E1.716 M3 BETON K-125 510,602.14 519,869.94
21 E1.711 M3 BETON K-250 621,000.18 630,653.69
22 E1.714b M3 BETON K-350 654,773.04 664,510.52
23 E1.712a M3 BETON CYCLOP 467,841.66 476,042.74

64 / 128
HRG SATUAN (Rp)
NO KODE ANALISSATUAN JENIS PEKERJAAN KATAGORI I KATAGORI II
(Mudah) (Sulit)

24 E1.713a M3 BETON STRUKTUR K-225 KANSTIN ( EKSPOS ) 584,223.60 593,844.70


25 E1.72 Kg. PENULANGAN / PEMBESIAN 17,788.50 18,908.50
26 E1.710 M2 ACUAN (Begisting) utk Jbt / gorong-gorong 52,200.00 52,950.00
27 E1.813 M2 PENGECATAN KAYU / BESI 19,035.50 19,203.50
28 E1.753 M3 BRONJONG (GABIONS) 392,812.50 443,312.50
29 E1.79 M3 PASANGAN BATU (MEKANIK) 410,028.11 416,570.86
30 E1.841 M2 MARKA JALAN THERMOPLASTIC 75,000.00 ###
31 E1.715 M2 GROOVING 4,811.83 4,811.83
32 E1.847 BH PATOK KILOMETER 449,568.28 470,736.28
33 E1.846 BH PATOK HEKTOMETER 125,742.06 131,293.14
34 E1.723.4 M' TIANG PANCANG BETON 366,350.04 366,350.04
35 W.2 M2 Memasang Onderlaag tebal 15 cm 35,773.33 37,148.33
36 A.18 M3 Urugan pasir pasang 110,450.00 119,450.00
37 W.3 M2 Memasang Stenslaag tebal 6 cm 12,359.03 12,908.11
38 KPU.IVa M2 Pasang Paving Blok Natural 64,200.00 65,950.00
39 KPU.IVb M2 Pasang Paving Blok Warna 87,200.00 88,950.00
40 W.3.a M2 Memasang Stenslaag tebal 6 - 8 cm 19,084.67 19,774.67
41 A.19 M3 Urugan pasir Urug 74,450.00 83,450.00
42 W.3.b M2 Sokongon Jembatan (Bekisting) 1,551,105.77 1,557,836.54

Purwokerto, September 2008

KEPALA DINAS CIPTA KARYA, KEBERSIHAN


DAN TATA RUANG KAB. BANYUMAS

Ir. ANDRIE SUBANDRIO, MT


Pembina Tk.I
NIP. 500 097 810

65 / 128
DAFTAR HARGA SATUAN PEKERJAAN

HSP
TAHUN 2008 (Perubahan)
HRG SATUAN (Rp)
SWAKELOLA

82,907.50
31,832.50
1,137,400.00
523,150.00
1,427,300.00
620,000.00
4,025.00
76,287.25
15,965.50
173,831.00
164,381.00

11,060.00
14,525.00
20,307.00
17,265.50
1,382.50
14,217.00
5,302.50
13,825.00
73,665.00
328,147.50
81,912.50

402,702.50
372,342.50
297,767.50
163,377.00

120,975.00
109,010.00
97,371.00
57,371.50
52,168.50
48,402.50

19,428.50
17,091.50
66 / 128
HRG SATUAN (Rp)
SWAKELOLA
14,245.50
28,118.75
24,076.75
14,936.50
23,478.50
4,528.50
12,721.50

67 / 128
HRG SATUAN (Rp)
SWAKELOLA

16,749,450.00
9,860,250.00
10,035,450.00
7,365,450.00
16,691,450.00
58,341,810.00

30,741,810.00

12,405,810.00
618,450.00
446,450.00
466,450.00
350,450.00
533,160.00
382,660.00
400,160.00
298,660.00
949,600.00
680,700.00
712,700.00
527,100.00
848,615.00
590,615.00
620,615.00
446,615.00
419,480.00
335,200.00
345,000.00
288,160.00
306,700.00
316,500.00
259,660.00
16,769,500.00

53,842,500.00

34,455,000.00

28,542,500.00
9,178,400.00
9,339,000.00

11,728,200.00

12,400,000.00

68 / 128
HRG SATUAN (Rp)
SWAKELOLA
6,891,500.00
78,122.50

86,522.50

67,322.50

55,322.50

69 / 128
HRG SATUAN (Rp)
SWAKELOLA

125,162.50

89,722.50

99,522.50

77,122.50

12,943,621.00

9,847,621.00

37,003,778.50

30,553,778.50
134,675.00

401,320.00
85,475.00
93,875.00
74,675.00
62,675.00

98,320.00
177,971.25
196,871.25
153,671.25
126,671.25
102,255.00

373,170.00
71,137.50
74,737.50
53,857.50

100,470.00
118,400.00
81,420.00
85,720.00
60,780.00

482,482.50
49,572.00
623,182.50
658,302.50
16,415.50
16,415.50
15,365.50
75,266.50

70 / 128
HRG SATUAN (Rp)
SWAKELOLA
82,016.50
246,848.50
259,038.50
367,338.50
353,338.50
233,838.50
65,773.50
74,601.00

71 / 128
HRG SATUAN (Rp)
SWAKELOLA

33,604.00
38,854.00
41,113.00
39,011.00
41,601.00
39,534.00
39,774.00
43,574.00
78,774.00
58,118.50
50,770.00
45,870.00
48,940.00
48,940.00
38,438.00
14,306.00
72,251.88
144,966.88
110,291.88
144,966.88
19,184.50
29,212.75
32,497.75

9,195.50
6,995.50
93,580.00
101,980.00
82,780.00
70,496.50
101,220.00
83,100.00
27,467.00

1,601,821.50
286,340.00
587,850.00
619,375.00
349,375.00
714,000.00
4,666,875.00
1,152,220.00
230,806.25
257,799.00
399,666.00
32,192.00

72 / 128
HRG SATUAN (Rp)
SWAKELOLA
41,492.00
52,342.00
75,253.10
92,303.10
158,178.10
213,030.45
9,067.70
11,315.20
13,717.70

73 / 128
HRG SATUAN (Rp)
SWAKELOLA

19,607.70
25,769.05
46,539.05
76,203.90
263,427.25
38,680.00
18,680.00
23,617.50

320,854.50
105,217.50
50,217.50
12,713.63
10,213.63
27,235.00
10,213.63
21,713.63
217,378.75
91,951.50
192,878.75
40,475.75
320,854.50
61,313.63
87,713.63
203,734.20
192,213.63

48,365.75
43,397.25
90,058.50
94,563.50
110,463.50
116,863.50
93,553.50
98,803.50
112,663.50
135,063.50
82,863.50
88,203.50
96,663.50
117,063.50
117,863.50
98,208.50
106,363.50
113,363.50
138,563.50
86,163.50
74 / 128
HRG SATUAN (Rp)
SWAKELOLA
92,703.50
98,163.50
118,263.50
76,242.50
98,502.50
83,202.50
89,712.50
91,602.50
96,747.50

75 / 128
HRG SATUAN (Rp)
SWAKELOLA

4,703.75
3,787.50
19,423.00
23,054.75
36,943.75
29,168.75
45,964.75
27,114.75
39,642.75
5,439.00
19,364.20
27,104.20
8,942.20
7,934.20
7,106.20
15,465.05
21,915.05
6,780.05
5,940.05
5,250.05
5,005.90
1,939.50
8,373.00
14,853.00
64,772.00
ANALISA BOW
62,360.00
85,360.00
130,360.00
90,360.00
300,360.00

21,160.00

10,322.50
22,306.88
74,945.00
94,145.00
85,745.00
134,945.00
66,541.88
85,741.88
82,606.88
76 / 128
HRG SATUAN (Rp)
SWAKELOLA
27,106.88
24,037.00
13,667.00
407,787.00
313,612.00
459,987.00
450,987.00
511,587.00
293,124.50
231,862.00
327,924.50
321,924.50

77 / 128
HRG SATUAN (Rp)
SWAKELOLA

373,524.50
445,464.00
324,864.00
377,064.00
296,850.00

15,507.50
14,385.93
13,465.93
17,085.93
PEKERJAAN BETON

92,290.00
JAAN PASANGAN BATU GRANIT

785,390.00
1,108,840.00
309,050.00
592,481.70
1,172,146.80
11,157.50
6,988.00
182,275.00
26,750.00
8,530.00
21,075.00
239,658.95
188,240.20
1,981,196.80
PEKERJAAN LAIN - LAIN
6,354.00
6,000.00
4,000.00
4,500.00
20,000.00
7,000.00
7,000.00
15,000.00
4,595,823.88
6,297,947.93
150,000.00
150,000.00
150,000.00
565,000.00
290,000.00

78 / 128
HRG SATUAN (Rp)
SWAKELOLA
808,000.00
1,357,000.00
1,250.00
1,750.00
4,000.00
7,000.00
12,500.00
2,000.00

79 / 128
HRG SATUAN (Rp)
SWAKELOLA

2,500.00
5,000.00
12,500.00
25,000.00
80,000.00
54,000.00
27,000.00
65,000.00
3,500.00
3,250.00
50,000.00
60,000.00
4,500.00
27,500.00
75,000.00
3,000.00
6,500.00
13,000.00
13,000.00
25,000.00
12,000.00
420,000.00
443,000.00
467,000.00
589,000.00
276,000.00
325,000.00
150,000.00

80 / 128
HRG SATUAN (Rp)
SWAKELOLA

81 / 128
HRG SATUAN (Rp)
SWAKELOLA

Purwokerto, September 2008

KEPALA DINAS CIPTA KARYA, KEBERSIHAN


DAN TATA RUANG KAB. BANYUMAS

Ir. ANDRIE SUBANDRIO, MT

82 / 128
ANALISA BIAYA SEWA PERALATAN PER JAM KERJA

JAM Faktor Angsu- Biaya Pasti Per Jam BIAYA OPERASI PER JAM BIAYA /
NO KODE URAIAN HP KAPASITAS UMUR KERJA HARGA Nilai Sisa Alat ran Modal i = Biaya Peng Asuransi Jumlah Bahan BakaBahan Bakar Pelumas Perawatan & Operator Pembantu JUMLAH SEWA ALAT
ALAT 1 THN ALAT 10 % x B 20.00% balian Modal dll Biaya pasti Pemanasan(0,125-0,17 (0,01 - 0,02) Perbaikan OperatorBIAYA OPERASI PER JAM
i x ( 1 + i )^A' ( B'-C)*D 0,002 x B' per jam Material Pw x Ms Pw x Mp (12,5%-17,5%)xB' PER JAM
( 1 + i )^A'-1 W' W' 12x0,7xCpxMs W'
Pw Cp A W B C D E F G = (E+F) H2 H I K L M P=H+I+K+L+M S = G + P
1 E01 Asphalt Mixing Plant 150 40 Ton/Jam 5 1,500 3,750,000,000 375,000,000 0.3344 752,354 5,000 757,354 1,848,000 103,125 56,250 312,500 5,000 4,500 2,329,375 3,086,729
2 E02 Asphalt Finisher 47 6 Ton 5 2,000 1,500,000,000 150,000,000 0.3344 225,706 1,500 227,206 32,313 17,625 93,750 5,000 4,500 153,188 380,394
3 E03 Asphalt Sprayer 15 800 Ltr 5 2,000 101,000,000 10,100,000 0.3344 15,198 101 15,299 10,313 5,625 6,313 5,000 4,500 31,750 47,049
4 E04 Buldozer 100 - 150 HP 140 - 5 2,000 825,000,000 82,500,000 0.3344 124,138 825 124,963 96,250 52,500 51,563 5,000 4,500 209,813 334,776
5 E05 Compresor 4000 - 6500 L\M 80 - 5 2,000 150,000,000 15,000,000 0.3344 22,571 150 22,721 55,000 30,000 9,375 5,000 4,500 103,875 126,596
6 E06 Concrete Mixer 0,125 M3 15 250 Ltr 4 2,000 7,500,000 750,000 0.3863 1,304 8 1,311 10,313 5,625 469 5,000 4,500 25,906 27,217
7 E07 Crane 10 - 15 Ton 150 15 Ton 5 2,000 550,000,000 55,000,000 0.3344 82,759 550 83,309 103,125 56,250 34,375 5,000 4,500 203,250 286,559
8 E08 Stone Cruisher 220 50 Ton/Jam 5 2,000 825,000,000 82,500,000 0.3344 124,138 825 124,963 151,250 82,500 51,563 5,000 4,500 294,813 419,776
9 E09 Motor Grader > 100 HP 125 - 5 2,000 605,000,000 60,500,000 0.3344 91,035 605 91,640 85,938 46,875 37,813 5,000 4,500 180,125 271,765
10 E10 Excavator 80 - 140 HP 80 0.5 M3 5 2,000 715,000,000 71,500,000 0.3344 107,587 715 108,302 55,000 30,000 44,688 5,000 4,500 139,188 247,489
11 E11 Track Loader 75 - 100 HP 90 1.6 M3 5 2,000 825,000,000 82,500,000 0.3344 124,138 825 124,963 61,875 33,750 51,563 5,000 4,500 156,688 281,651
12 E12 Wheel Loader 1,0 - 1,6 m3 105 1.5 M3 5 2,000 715,000,000 71,500,000 0.3344 107,587 715 108,302 72,188 39,375 44,688 5,000 4,500 165,750 274,052
13 E13 Three Wheel Roller 6 - 8 T 55 8 Ton 5 2,000 605,000,000 60,500,000 0.3344 91,035 605 91,640 37,813 20,625 37,813 5,000 4,500 105,750 197,390
14 E14 Tandem Roller 6 - 8 Ton 50 8 Ton 5 2,000 660,000,000 66,000,000 0.3344 99,311 660 99,971 34,375 18,750 41,250 5,000 4,500 103,875 203,846
15 E15 Pneumatic Tired Roller 8-10 T 60 10 Ton 5 1,000 1,000,000,000 100,000,000 0.3344 300,942 2,000 302,942 41,250 22,500 125,000 5,000 4,500 198,250 501,192
16 E16 Vibratory Roller 5 - 8 Ton 75 7 Ton 4 2,000 825,000,000 82,500,000 0.3863 143,410 825 144,235 51,563 28,125 51,563 5,000 4,500 140,750 284,985
17 E17 Pedestrian Roller 11 0.98 Ton 4 2,000 16,500,000 1,650,000 0.3863 2,868 17 2,885 7,563 4,125 1,031 5,000 4,500 22,219 25,103
18 E18 Water Tank Truck 2000-4500 L 100 4000 5 2,000 150,000,000 15,000,000 0.3344 22,571 150 22,721 68,750 37,500 9,375 4,500 4,000 124,125 146,846
19 E19 Dump Truck 3 - 4 M3 100 6 Ton 5 2,000 200,000,000 20,000,000 0.3344 30,094 200 30,294 68,750 37,500 12,500 4,500 4,000 127,250 157,544
20 E20 Dump Truck 125 8 Ton 5 2,000 250,000,000 25,000,000 0.3344 37,618 250 37,868 85,938 46,875 15,625 4,500 4,000 156,938 194,805
21 E21 Flat Bed Truck 3 - 4M3 100 4 M3 5 2,000 181,500,000 18,150,000 0.3344 27,310 182 27,492 68,750 37,500 11,344 4,500 4,000 126,094 153,586
22 E22 Generator Set 175 125 KVA 5 2,000 75,000,000 7,500,000 0.3344 11,285 75 11,360 120,313 65,625 4,688 3,857 - 194,482 205,842
23 E23 Jack Hammer 3 - 4 1,000 82,500,000 8,250,000 0.3863 28,682 165 28,847 2,063 1,125 10,313 5,000 - 18,500 47,347
24 E24 Concrete Vibrator 10 - 4 1,000 3,500,000 350,000 0.3863 1,217 7 1,224 6,875 3,750 438 3,857 - 14,920 16,143
25 E25 Stamper 5 0.17 Ton 4 1,000 7,500,000 750,000 0.3863 2,607 15 2,622 3,438 1,875 938 5,000 - 11,250 13,872
26 E26 Water Pump 70 - 100 mm 6 - 2 2,000 7,500,000 750,000 0.6545 2,209 8 2,217 4,125 2,250 469 3,857 - 10,701 12,917
27 E27 Concrete Paver 3,857 - 50,000
28 E28 Concrete Cutting Machine 3,857 - 65,000
29 E29 Pile Hammer 5,000 - 50,000
30 E30 Mesin Las 3,857 - 60,000
31 E.31 Mesin Poles - 50,000
HARGA AGREGAT
KATEGORI - I ( Mudah )
AGREGAT KLAS A
Harga Agregat
Jenis batuan Ukuran KODE % Tertahan Bobot Harga Satuan Harga Faktor
Klas A per M3
M.101 2-3 M.001h 100-77 15 0.273 143,000.00 39,000.00
AGREGAT 1-2 M.001i 49-27 26 0.473 150,000.00 70,909.09
KASAR 0,5 - 1 M.001i1 58- 14 0.255 152,000.00 38,690.91
Jumlah 55 148,600.00
Dibulatkan 148,600.00 0.550 81,730.00
M.102 0,2 - 0,5 M.001i2 76-64 19 0.422 156,000.00 65,866.67
AGREGAT Abu batu M.001i3 100-76 26 0.578 122,500.00 70,777.78
HALUS Jumlah 45 136,644.44
Dibulatkan 136,600.00 0.450 61,470.00
143,200.00

AGREGAT KLAS B
Harga Agregat
Jenis batuan Ukuran KODE % Tertahan Bobot Harga Satuan Harga Faktor
Klas B per M3
M.103 3-5 M.001f4 100-85 11 0.262 137,000.00 35,880.95
AGREGAT 2-3 M.001h 85-72 9 0.214 143,000.00 30,642.86
KASAR 1-2 M.001i 72-52,5 15.5 0.369 150,000.00 55,357.14
0,5 - 1 M.001i1 52,5-41 6.5 0.155 152,000.00 23,523.81
Jumlah 42 1.000 145,404.76
Dibulatkan 145,400.00 0.42 61,068.00
M.104 0,2 - 0,5 M.001i2 76-64 9 0.375 156,000.00 58,500.00
AGREGAT Abu batu M.001i3 100-76 15 0.625 122,500.00 76,562.50
HALUS Jumlah 24 135,062.50
Dibulatkan 135,060.00 0.24 32,414.40
93,482.40

LAPEN MACADAM
Jenis batuan Ukuran KODE % Tertahan Bobot Harga Satuan Harga
M.111 3-5 M.001f4 100-50 50 0.500 137,000.00 68,500.00
AGREGAT 2-3 M.001h 100-50 50 0.500 143,000.00 71,500.00
POKOK 100 Jumlah 140,000.00
Dibulatkan 140,000.00
M.112
AGREGAT 2-3 M.001h 100-97,5 2.5 0.025 143,000.00 3,575.00
PENGUNCI 1-2 M.001i 97.5 97.5 0.975 150,000.00 146,250.00

100 Jumlah 149,825.00


Dibulatkan 149,825.00
M.112a 0,5-1 M.001i1 10-5 5 0.050 152,000.00 7,600.00
AGREGAT 0,2 - 0,5 M.001i2 10-5 5 0.050 156,000.00 7,800.00
PENUTUP Abu batu M.001i3 90 90 0.900 122,500.00 110,250.00
100 Jumlah 125,650.00
Dibulatkan 125,650.00

A T B ( M3)
Jenis batuan Ukuran KODE % Tertahan Bobot Harga Satuan Harga
M.105 1-2 M.001i 100-75 25 0.250 150,000.00 37,500.00
AGREGAT 0,5 - 1 M.001i1 75-25 50 0.500 152,000.00 76,000.00
KASAR 0,2 - 0,5 M.001i2 82-75 7 0.070 156,000.00 10,920.00
Abu batu M.001i3 18 0.180 122,500.00 22,050.00
100 Jumlah 146,470.00
Dibulatkan 146,500.00
M.106 0,5 - 1 M.001i1 100-99 1 0.010 152,000.00 1,520.00
AGREGAT 0,2 - 0,5 M.001i2 99-97,5 1.5 0.015 156,000.00 2,340.00
HALUS Abu batu M.001i3 97.5 0.975 122,500.00 119,437.50
100 Jumlah 123,297.50
Dibulatkan 123,300.00
HARGA AGREGAT
KATEGORI - I ( Mudah )
LASTON ( AC )
Jenis batuan Ukuran KODE % Tertahan Bobot Harga Satuan Harga
M.107 1-2 M.001i 100-27,5 72.5 0.725 150,000.00 108,750.00
AGREGAT 0,5 - 1 M.001i1 95-72,5 22.5 0.225 152,000.00 34,200.00
KASAR 0,2 - 0,5 M.001i2 96,5-95 1.5 0.015 156,000.00 2,340.00
Abu batu M.001i3 3.5 0.035 122,500.00 4,287.50
100 Jumlah 149,577.50
Dibulatkan 149,600.00
M.108 0,5 - 1 M.001i1 100-95 5 0.050 152,000.00 7,600.00
AGREGAT 0,2 - 0,5 M.001i2 10-5 5 0.050 156,000.00 7,800.00
HALUS Abu batu M.001i3 90 0.900 122,500.00 110,250.00
100 Jumlah 125,650.00
Dibulatkan 125,700.00

LATASTON ( HRS )
Jenis batuan Ukuran KODE % Tertahan Bobot Harga Satuan Harga
M.109 1-2 M.001i 100-27,5 72.5 0.725 150,000.00 108,750.00
AGREGAT 0,5 - 1 M.001i1 95-72,5 22.5 0.225 152,000.00 34,200.00
KASAR 0,2 - 0,5 M.001i2 96,5-95 1.5 0.015 156,000.00 2,340.00
Abu batu M.001i3 3.5 0.035 122,500.00 4,287.50
100 Jumlah 149,577.50
Dibulatkan 149,600.00
M.110 0,5 - 1 M.001i1 100-95 5 0.050 152,000.00 7,600.00
AGREGAT 0,2 - 0,5 M.001i2 10-5 5 0.050 156,000.00 7,800.00
HALUS Abu batu M.001i3 90 0.900 122,500.00 110,250.00
100 Jumlah 125,650.00
Dibulatkan 125,700.00

M.100 AGREGAT BETON


Jenis batuan Ukuran KODE % Tertahan Bobot Harga Satuan Harga
AGREGAT 2-3 M.001h 0.5 143,000.00 71,500.00
KASAR 1-2 M.001i 0.5 150,000.00 75,000.00
Jumlah 146,500.00
HARGA AGREGAT
KATEGORI - II ( Sulit )
AGREGAT KLAS A
Harga Agregat
Jenis batuan Ukuran KODE % Tertahan Bobot Harga Satuan Harga Faktor
Klas A per M3
B.101 2-3 M.001h 100-77 15 0.273 150,000.00 40,909.09
AGREGAT 1-2 M.001i 49-27 26 0.473 155,000.00 73,272.73
KASAR 0,5 - 1 M.001i1 58- 14 0.255 160,000.00 40,727.27
Jumlah 55 154,909.09
Dibulatkan 154,900.00 0.550 85,195.00
B.102 0,2 - 0,5 M.001i2 76-64 19 0.422 160,000.00 67,555.56
AGREGAT Abu batu M.001i3 100-76 26 0.578 125,000.00 72,222.22
HALUS Jumlah 45 139,777.78
Dibulatkan 139,800.00 0.450 62,910.00
148,105.00

AGREGAT KLAS B
Harga Agregat
Jenis batuan Ukuran KODE % Tertahan Bobot Harga Satuan Harga Faktor
Klas B per M3
B.103 3-5 M.001f4 100-85 11 0.262 142,000.00 37,190.48
AGREGAT 2-3 M.001h 85-72 9 0.214 150,000.00 32,142.86
KASAR 1-2 M.001i 72-52,5 15.5 0.369 155,000.00 57,202.38
0,5 - 1 M.001i1 52,5-41 6.5 0.155 160,000.00 24,761.90
Jumlah 42 1.000 151,297.62
Dibulatkan 151,300.00 0.42 63,546.00
B.104 0,2 - 0,5 M.001i2 76-64 9 0.375 160,000.00 60,000.00
AGREGAT Abu batu M.001i3 100-76 15 0.625 125,000.00 78,125.00
HALUS Jumlah 24 138,125.00
Dibulatkan 138,125.00 0.24 33,150.00
96,696.00

LAPEN MACADAM
Jenis batuan Ukuran KODE % Tertahan Bobot Harga Satuan Harga
B.111 3-5 M.001f4 100-50 50 0.500 142,000.00 71,000.00
AGREGAT 2-3 M.001h 100-50 50 0.500 150,000.00 75,000.00
POKOK 100 Jumlah 146,000.00
Dibulatkan 146,000.00
B.112
AGREGAT 2-3 M.001h 100-97,5 2.5 0.025 150,000.00 3,750.00
PENGUNCI 1-2 M.001i 97.5 97.5 0.975 155,000.00 151,125.00

100 Jumlah 154,875.00


Dibulatkan 154,880.00
B.112a 0,5-1 M.001i1 10-5 5 0.050 160,000.00 8,000.00
AGREGAT 0,2 - 0,5 M.001i2 10-5 5 0.050 160,000.00 8,000.00
PENUTUP Abu batu M.001i3 90 90 0.900 125,000.00 112,500.00
100 Jumlah 128,500.00
Dibulatkan 128,500.00

A T B ( M3)
Jenis batuan Ukuran KODE % Tertahan Bobot Harga Satuan Harga
B.105 1-2 M.001i 100-75 25 0.250 155,000.00 38,750.00
AGREGAT 0,5 - 1 M.001i1 75-25 50 0.500 160,000.00 80,000.00
KASAR 0,2 - 0,5 M.001i2 82-75 7 0.070 160,000.00 11,200.00
Abu batu M.001i3 18 0.180 125,000.00 22,500.00
100 Jumlah 152,450.00
Dibulatkan 152,450.00
B.106 0,5 - 1 M.001i1 100-99 1 0.010 160,000.00 1,600.00
AGREGAT 0,2 - 0,5 M.001i2 99-97,5 1.5 0.015 160,000.00 2,400.00
HALUS Abu batu M.001i3 97.5 0.975 125,000.00 121,875.00
100 Jumlah 125,875.00
Dibulatkan 125,875.00
HARGA AGREGAT
KATEGORI - II ( Sulit )
LASTON ( AC )
Jenis batuan Ukuran KODE % Tertahan Bobot Harga Satuan Harga
B.107 1-2 M.001i 100-27,5 72.5 0.725 155,000.00 112,375.00
AGREGAT 0,5 - 1 M.001i1 95-72,5 22.5 0.225 160,000.00 36,000.00
KASAR 0,2 - 0,5 M.001i2 96,5-95 1.5 0.015 160,000.00 2,400.00
Abu batu M.001i3 3.5 0.035 125,000.00 4,375.00
100 Jumlah 155,150.00
Dibulatkan 155,150.00
B.108 0,5 - 1 M.001i1 100-95 5 0.050 160,000.00 8,000.00
AGREGAT 0,2 - 0,5 M.001i2 10-5 5 0.050 160,000.00 8,000.00
HALUS Abu batu M.001i3 90 0.900 125,000.00 112,500.00
100 Jumlah 128,500.00
Dibulatkan 128,500.00

LATASTON ( HRS )
Jenis batuan Ukuran KODE % Tertahan Bobot Harga Satuan Harga
B.109 1-2 M.001i 100-27,5 72.5 0.725 155,000.00 112,375.00
AGREGAT 0,5 - 1 M.001i1 95-72,5 22.5 0.225 160,000.00 36,000.00
KASAR 0,2 - 0,5 M.001i2 96,5-95 1.5 0.015 160,000.00 2,400.00
Abu batu M.001i3 3.5 0.035 125,000.00 4,375.00
100 Jumlah 155,150.00
Dibulatkan 155,150.00
B.110 0,5 - 1 M.001i1 100-95 5 0.050 160,000.00 8,000.00
AGREGAT 0,2 - 0,5 M.001i2 10-5 5 0.050 160,000.00 8,000.00
HALUS Abu batu M.001i3 90 0.900 125,000.00 112,500.00
100 Jumlah 128,500.00
Dibulatkan 128,500.00

B.100 AGREGAT BETON


Jenis batuan Ukuran KODE % Tertahan Bobot Harga Satuan Harga
AGREGAT 2-3 M.001h 0.5 150,000.00 75,000.00
KASAR 1-2 M.001i 0.5 155,000.00 77,500.00
Jumlah 152,500.00
TAKSIRAN HARGA
89 / 128

PEMERINTAH KABUPATEN BANYUMAS ANALISA HARGA SATUAN PEKERJAAN


DINAS PEKERJAAN UMUM
Jl.Jend. Gatot Subroto No.III-5 Telp.(0281) 637038 TAHUN 2008

KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA


JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
A. PEKERJAAN PERSIAPAN
Pengukuran dan Pemasangan Bouwplank (Kayu
SNI - A.6.4 M' 83,560.00 84,460.00 82,907.50
Meranti)
M.005g Usuk Meranti 5/7 0.0120 M3 3,900,000.00 46,800.00 3,975,000.00 47,700.00 3,900,000.00 46,800.00
M.006 Paku Biasa ( 2" - 5" ) 0.0200 Kg 18,000.00 360.00 18,000.00 360.00 18,000.00 360.00
M.005l Papan Meranti 0.0070 M3 4,275,000.00 29,925.00 4,275,000.00 29,925.00 4,275,000.00 29,925.00
L.008 Pekerja 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.002 Tukang Kayu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
Pengukuran dan Pemasangan Bouwplank (Kayu
SNI - A.6.4a M' 32,485.00 33,435.00 31,832.50
Tahun)
M.005a Usuk 5/7 kayu Tahun 0.0120 M3 1,350,000.00 16,200.00 1,400,000.00 16,800.00 1,350,000.00 16,200.00
M.006 Paku Biasa ( 2" - 5" ) 0.0200 Kg 18,000.00 360.00 18,000.00 360.00 18,000.00 360.00
M.005a Papan kayu Tahun 3/20 0.0070 M3 1,350,000.00 9,450.00 1,400,000.00 9,800.00 1,350,000.00 9,450.00
L.008 Pekerja 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.002 Tukang Kayu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
Pembuatan Gudang Semen dan Alat-alat (Kayu
SNI - A.6.6 M2 1,147,775.00 1,174,323.50 1,137,400.00
Meranti )
M.005s Dolken kayu diam. 8-10 / 4 m 1.7000 Btg 30,000.00 51,000.00 35,000.00 59,500.00 30,000.00 51,000.00
M.005l Papan Meranti 0.2100 M3 4,275,000.00 897,750.00 4,350,000.00 913,500.00 4,275,000.00 897,750.00
M.006 Paku Biasa ( 2" - 5" ) 0.3000 Kg 18,000.00 5,400.00 18,000.00 5,400.00 18,000.00 5,400.00
M.002a Portland Cement 10.5000 Kg 1,200.00 12,600.00 1,207.00 12,673.50 1,200.00 12,600.00
M.001 Pasir Beton 0.0300 M3 92,500.00 2,775.00 100,000.00 3,000.00 92,500.00 2,775.00
M.001g Koral Beton ( Batu Pecah 2/3 ) 0.0500 M3 140,000.00 7,000.00 150,000.00 7,500.00 140,000.00 7,000.00
M.010l Seng Gelombang BJLS 20 1.5000 Lbr 47,000.00 70,500.00 48,000.00 72,000.00 47,000.00 70,500.00
L.008 Pekerja 1.0000 OH 27,000.00 27,000.00 27,000.00 27,000.00 24,500.00 24,500.00
L.002 Tukang Kayu 2.0000 OH 32,500.00 65,000.00 32,500.00 65,000.00 29,000.00 58,000.00
L.007 Kepala Tukang 0.2000 OH 35,000.00 7,000.00 35,000.00 7,000.00 31,500.00 6,300.00
L.010 Mandor 0.0500 OH 35,000.00 1,750.00 35,000.00 1,750.00 31,500.00 1,575.00
Pembuatan Gudang Semen dan Alat-alat (Kayu
SNI - A.6.6a M2 533,525.00 554,823.50 523,150.00
Tahun )
M.005s Dolken kayu diam. 8-10 / 4 m 1.7000 Btg 30,000.00 51,000.00 35,000.00 59,500.00 30,000.00 51,000.00
M.005a Papan kayu Tahun 3/20 0.2100 M3 1,350,000.00 283,500.00 1,400,000.00 294,000.00 1,350,000.00 283,500.00
M.006 Paku Biasa ( 2" - 5" ) 0.3000 Kg 18,000.00 5,400.00 18,000.00 5,400.00 18,000.00 5,400.00
M.002a Portland Cement 10.5000 Kg 1,200.00 12,600.00 1,207.00 12,673.50 1,200.00 12,600.00
M.001 Pasir Beton 0.0300 M3 92,500.00 2,775.00 100,000.00 3,000.00 92,500.00 2,775.00
M.001g Koral Beton ( Batu Pecah 2/3 ) 0.0500 M3 140,000.00 7,000.00 150,000.00 7,500.00 140,000.00 7,000.00
M.010l Seng Gelombang BJLS 20 1.5000 Lbr 47,000.00 70,500.00 48,000.00 72,000.00 47,000.00 70,500.00
L.008 Pekerja 1.0000 OH 27,000.00 27,000.00 27,000.00 27,000.00 24,500.00 24,500.00
L.002 Tukang Kayu 2.0000 OH 32,500.00 65,000.00 32,500.00 65,000.00 29,000.00 58,000.00
L.007 Kepala Tukang 0.2000 OH 35,000.00 7,000.00 35,000.00 7,000.00 31,500.00 6,300.00
L.010 Mandor 0.0500 OH 35,000.00 1,750.00 35,000.00 1,750.00 31,500.00 1,575.00
Pembuatan Rumah Jaga / Konstruksi Kayu (Kayu
SNI - A.6.7 M2 1,435,750.00 1,472,950.00 1,427,300.00
Meranti )
M.005s Dolken kayu diam. 8-10 / 4 m 3.0000 Btg 30,000.00 90,000.00 35,000.00 105,000.00 30,000.00 90,000.00
M.005l Papan Meranti 0.2760 M3 4,275,000.00 1,179,900.00 4,350,000.00 1,200,600.00 4,275,000.00 1,179,900.00
M.006 Paku Biasa ( 2" - 5" ) 0.7000 Kg 18,000.00 12,600.00 18,000.00 12,600.00 18,000.00 12,600.00
M.010l Seng Gelombang BJLS 20 1.5000 Lbr 47,000.00 70,500.00 48,000.00 72,000.00 47,000.00 70,500.00
L.008 Pekerja 1.0000 OH 27,000.00 27,000.00 27,000.00 27,000.00 24,500.00 24,500.00
L.002 Tukang Kayu 1.5000 OH 32,500.00 48,750.00 32,500.00 48,750.00 29,000.00 43,500.00
L.007 Kepala Tukang 0.1500 OH 35,000.00 5,250.00 35,000.00 5,250.00 31,500.00 4,725.00
L.010 Mandor 0.0500 OH 35,000.00 1,750.00 35,000.00 1,750.00 31,500.00 1,575.00
Pembuatan Rumah Jaga / Konstruksi Kayu (Kayu
SNI - A.6.7a M2 SNIA.6.7a 628,450.00 SN2A.6.7a 658,750.00 SNSA.6.7a 620,000.00
Tahun )
M.005s Dolken kayu diam. 8-10 / 4 m 3.0000 Btg 30,000.00 90,000.00 35,000.00 105,000.00 30,000.00 90,000.00
M.005a Papan kayu Tahun 3/20 0.2760 M3 1,350,000.00 372,600.00 1,400,000.00 386,400.00 1,350,000.00 372,600.00
M.006 Paku Biasa ( 2" - 5" ) 0.7000 Kg 18,000.00 12,600.00 18,000.00 12,600.00 18,000.00 12,600.00
M.010l Seng Gelombang BJLS 20 1.5000 Lbr 47,000.00 70,500.00 48,000.00 72,000.00 47,000.00 70,500.00
L.008 Pekerja 1.0000 OH 27,000.00 27,000.00 27,000.00 27,000.00 24,500.00 24,500.00
L.002 Tukang Kayu 1.5000 OH 32,500.00 48,750.00 32,500.00 48,750.00 29,000.00 43,500.00
L.007 Kepala Tukang 0.1500 OH 35,000.00 5,250.00 35,000.00 5,250.00 31,500.00 4,725.00
L.010 Mandor 0.0500 OH 35,000.00 1,750.00 35,000.00 1,750.00 31,500.00 1,575.00
90 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
SNI - A.6.8 Membersihkan Lapangan dan Perataan M2 SNIA.6.8 4,450.00 SN2A.6.8 4,450.00 SNSA.6.8 4,025.00
L.008 Pekerja 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.010 Mandor 0.0500 OH 35,000.00 1,750.00 35,000.00 1,750.00 31,500.00 1,575.00
Pembuatan Bak Adukan Uk. ( 40x50x20 ) cm Kayu
SNI - A.6.10 BH SNIA.6.10 77,342.50 SN2A.6.10 79,642.50 SNSA.6.10 76,287.25
Tahun
M.005a Kayu Tahun 0.0360 M3 1,350,000.00 48,600.00 1,400,000.00 50,400.00 1,350,000.00 48,600.00
M.006 Paku Biasa ( 2" - 5" ) 0.0800 Kg 18,000.00 1,440.00 18,000.00 1,440.00 18,000.00 1,440.00
M.005t Usuk 5/7 1.0000 Btg 17,500.00 17,500.00 18,000.00 18,000.00 17,500.00 17,500.00
L.001 Tukang Batu 0.3000 OH 32,500.00 9,750.00 32,500.00 9,750.00 29,000.00 8,700.00
L.010 Mandor 0.0015 OH 35,000.00 52.50 35,000.00 52.50 31,500.00 47.25
SNI - A.6.11 Pembuatan Steger dari Bambu M2 SNIA.6.11 16,702.50 SN2A.6.11 17,327.50 SNSA.6.11 15,965.50
M.006f Bambu diam. 6-8 / 6 m 1.0000 Btg 7,500.00 7,500.00 8,000.00 8,000.00 7,500.00 7,500.00
M.001l Tali Ijuk 0.2500 Kg 5,500.00 1,375.00 6,000.00 1,500.00 5,500.00 1,375.00
L.008 Pekerja 0.2500 OH 27,000.00 6,750.00 27,000.00 6,750.00 24,500.00 6,125.00
L.002 Tukang Kayu 0.0170 OH 32,500.00 552.50 32,500.00 552.50 29,000.00 493.00
L.007 Kepala Tukang 0.0020 OH 35,000.00 70.00 35,000.00 70.00 31,500.00 63.00
L.010 Mandor 0.0130 OH 35,000.00 455.00 35,000.00 455.00 31,500.00 409.50
SNI - A.6.13 Bongkaran Beton Bertulang M3 SNIA.6.13 191,664.00 SN2A.6.13 191,664.00 SNSA.6.13 173,831.00
L.008 Pekerja 6.6670 OH 27,000.00 180,009.00 27,000.00 180,009.00 24,500.00 163,341.50
L.010 Mandor 0.3330 OH 35,000.00 11,655.00 35,000.00 11,655.00 31,500.00 10,489.50
SNI - A.6.14 Bongkaran dinding Tembok Bata Merah M3 SNIA.6.14 181,164.00 SN2A.6.14 181,164.00 SNSA.6.14 164,381.00
L.008 Pekerja 6.6670 OH 27,000.00 180,009.00 27,000.00 180,009.00 24,500.00 163,341.50
L.010 Mandor 0.0330 OH 35,000.00 1,155.00 35,000.00 1,155.00 31,500.00 1,039.50
B. PEKERJAAN TANAH

SNI - B.6.1 Galian Tanah Biasa Sedalam 1 meter M3 SNIB.6.1 12,200.00 SN2B.6.1 12,200.00 SNSB.6.1 11,060.00
L.008 Pekerja 0.4000 OH 27,000.00 10,800.00 27,000.00 10,800.00 24,500.00 9,800.00
L.010 Mandor 0.0400 OH 35,000.00 1,400.00 35,000.00 1,400.00 31,500.00 1,260.00
SNI - B.6.2 Galian Tanah Biasa Sedalam 2 meter M3 SNIB.6.2 16,022.00 SN2B.6.2 16,022.00 SNSB.6.2 14,525.00
L.008 Pekerja 0.5260 OH 27,000.00 14,202.00 27,000.00 14,202.00 24,500.00 12,887.00
L.010 Mandor 0.0520 OH 35,000.00 1,820.00 35,000.00 1,820.00 31,500.00 1,638.00
SNI - B.6.3 Galian Tanah Biasa Sedalam 3 meter M3 SNIB.6.3 22,400.00 SN2B.6.3 22,400.00 SNSB.6.3 20,307.00
L.008 Pekerja 0.7350 OH 27,000.00 19,845.00 27,000.00 19,845.00 24,500.00 18,007.50
L.010 Mandor 0.0730 OH 35,000.00 2,555.00 35,000.00 2,555.00 31,500.00 2,299.50
SNI - B.6.4 Galian Tanah Keras Sedalam 1 meter M3 SNIB.6.4 19,045.00 SN2B.6.4 19,045.00 SNSB.6.4 17,265.50
L.008 Pekerja 0.6250 OH 27,000.00 16,875.00 27,000.00 16,875.00 24,500.00 15,312.50
L.010 Mandor 0.0620 OH 35,000.00 2,170.00 35,000.00 2,170.00 31,500.00 1,953.00
SNI - B.6.7 Pekerjaan Striping Setinggi 1 meter M3 SNIB.6.7 1,525.00 SN2B.6.7 1,525.00 SNSB.6.7 1,382.50
L.008 Pekerja 0.0500 OH 27,000.00 1,350.00 27,000.00 1,350.00 24,500.00 1,225.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
SNI - B.6.8 Pembuangan Tanah Sejauh 150 meter M3 SNIB.6.8 15,682.00 SN2B.6.8 15,682.00 SNSB.6.8 14,217.00
L.008 Pekerja 0.5160 OH 27,000.00 13,932.00 27,000.00 13,932.00 24,500.00 12,642.00
L.010 Mandor 0.0500 OH 35,000.00 1,750.00 35,000.00 1,750.00 31,500.00 1,575.00
SNI - B.6.9 Urugan Kembali M3 SNIB.6.9 5,849.00 SN2B.6.9 5,849.00 SNSB.6.9 5,302.50
L.008 Pekerja 0.1920 OH 27,000.00 5,184.00 27,000.00 5,184.00 24,500.00 4,704.00
L.010 Mandor 0.0190 OH 35,000.00 665.00 35,000.00 665.00 31,500.00 598.50
SNI - B.6.10 Pemadatan Tanah M3 SNIB.6.10 15,250.00 SN2B.6.10 15,250.00 SNSB.6.10 13,825.00
L.008 Pekerja 0.5000 OH 27,000.00 13,500.00 27,000.00 13,500.00 24,500.00 12,250.00
L.010 Mandor 0.0500 OH 35,000.00 1,750.00 35,000.00 1,750.00 31,500.00 1,575.00
SNI - B.6.11 Urugan Pasir M3 SNIB.6.11 74,450.00 SN2B.6.11 83,450.00 SNSB.6.11 73,665.00
M.001b Pasir urug 1.2000 M3 55,000.00 66,000.00 62,500.00 75,000.00 55,000.00 66,000.00
L.008 Pekerja 0.3000 OH 27,000.00 8,100.00 27,000.00 8,100.00 24,500.00 7,350.00
L.010 Mandor 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
SNI - B.6.14 Pemasangan Lapisan Ijuk M3 SNIB.6.14 328,575.00 SN2B.6.14 352,575.00 SNSB.6.14 328,147.50
M.001o Ijuk 1.2000 M3 270,000.00 324,000.00 290,000.00 348,000.00 270,000.00 324,000.00
L.008 Pekerja 0.1500 OH 27,000.00 4,050.00 27,000.00 4,050.00 24,500.00 3,675.00
91 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
L.010 Mandor 0.0150 OH 35,000.00 525.00 35,000.00 525.00 31,500.00 472.50
SNI - B.6.15 Urugan Sirtu M3 SNIB.6.15 82,625.00 SN2B.6.15 88,625.00 SNSB.6.15 81,912.50
M.001e Sirtu 1.2000 M3 62,500.00 75,000.00 67,500.00 81,000.00 62,500.00 75,000.00
L.008 Pekerja 0.2500 OH 27,000.00 6,750.00 27,000.00 6,750.00 24,500.00 6,125.00
L.010 Mandor 0.0250 OH 35,000.00 875.00 35,000.00 875.00 31,500.00 787.50
C. PEKERJAAN PONDASI BATU KALI

SNI - C.6.5 Pas. Pondasi Batu Kali 1 PC : 4 Psr M3 SNIC.6.5 409,025.00 SN2C.6.5 419,566.00 SNSC.6.5 402,702.50
M.001f1 Batu Belah 15/20 cm 1.1000 M3 95,000.00 104,500.00 100,000.00 110,000.00 95,000.00 104,500.00
M.002a Portland Cement 163.00 Kg 1,200.00 195,600.00 1,207.00 196,741.00 1,200.00 195,600.00
M.001a Pasir Pasang 0.5200 M3 85,000.00 44,200.00 92,500.00 48,100.00 85,000.00 44,200.00
L.008 Pekerja 1.5000 OH 27,000.00 40,500.00 27,000.00 40,500.00 24,500.00 36,750.00
L.001 Tukang Batu 0.6000 OH 32,500.00 19,500.00 32,500.00 19,500.00 29,000.00 17,400.00
L.007 Kepala Tukang 0.0600 OH 35,000.00 2,100.00 35,000.00 2,100.00 31,500.00 1,890.00
L.010 Mandor 0.0750 OH 35,000.00 2,625.00 35,000.00 2,625.00 31,500.00 2,362.50
92 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
SNI - C.6.6 Pas. Pondasi Batu Kali 1 PC : 5 Psr M3 SNIC.6.6 378,665.00 SN2C.6.6 389,197.00 SNSC.6.6 372,342.50
M.001f1 Batu Belah 15/20 cm 1.1000 M3 95,000.00 104,500.00 100,000.00 110,000.00 95,000.00 104,500.00
M.002a Portland Cement 136.00 Kg 1,200.00 163,200.00 1,207.00 164,152.00 1,200.00 163,200.00
M.001a Pasir Pasang 0.5440 M3 85,000.00 46,240.00 92,500.00 50,320.00 85,000.00 46,240.00
L.008 Pekerja 1.5000 OH 27,000.00 40,500.00 27,000.00 40,500.00 24,500.00 36,750.00
L.001 Tukang Batu 0.6000 OH 32,500.00 19,500.00 32,500.00 19,500.00 29,000.00 17,400.00
L.007 Kepala Tukang 0.0600 OH 35,000.00 2,100.00 35,000.00 2,100.00 31,500.00 1,890.00
L.010 Mandor 0.0750 OH 35,000.00 2,625.00 35,000.00 2,625.00 31,500.00 2,362.50
SNI - C.6.12 Pas. Pondasi Batu Kali 1 PC : 3 Kp : 10 Psr M3 SNIC.6.12 304,090.00 SN2C.6.12 314,442.00 SNSC.6.12 297,767.50
M.001f1 Batu Belah 15/20 cm 1.1000 M3 95,000.00 104,500.00 100,000.00 110,000.00 95,000.00 104,500.00
M.002a Portland Cement 61.000 Kg 1,200.00 73,200.00 1,207.00 73,627.00 1,200.00 73,200.00
M.001d Kapur Pasang 0.1470 M3 135,000.00 19,845.00 140,000.00 20,580.00 135,000.00 19,845.00
M.001a Pasir Pasang 0.4920 M3 85,000.00 41,820.00 92,500.00 45,510.00 85,000.00 41,820.00
L.008 Pekerja 1.5000 OH 27,000.00 40,500.00 27,000.00 40,500.00 24,500.00 36,750.00
L.001 Tukang Batu 0.6000 OH 32,500.00 19,500.00 32,500.00 19,500.00 29,000.00 17,400.00
L.007 Kepala Tukang 0.0600 OH 35,000.00 2,100.00 35,000.00 2,100.00 31,500.00 1,890.00
L.010 Mandor 0.0750 OH 35,000.00 2,625.00 35,000.00 2,625.00 31,500.00 2,362.50
SNI - C.6.14 Pas. Pondasi Batu Kosong M3 SNIC.6.14 166,965.00 SN2C.6.14 175,215.00 SNSC.6.14 163,377.00
M.001f1 Batu Belah 15/20 cm 1.2000 M3 95,000.00 114,000.00 100,000.00 120,000.00 95,000.00 114,000.00
M.001b Pasir Urug 0.3000 M3 55,000.00 16,500.00 62,500.00 18,750.00 55,000.00 16,500.00
L.008 Pekerja 0.7800 OH 27,000.00 21,060.00 27,000.00 21,060.00 24,500.00 19,110.00
L.001 Tukang Batu 0.3900 OH 32,500.00 12,675.00 32,500.00 12,675.00 29,000.00 11,310.00
L.007 Kepala Tukang 0.0390 OH 35,000.00 1,365.00 35,000.00 1,365.00 31,500.00 1,228.50
L.010 Mandor 0.0390 OH 35,000.00 1,365.00 35,000.00 1,365.00 31,500.00 1,228.50
D. PEKERJAAN DINDING

SNI - D.6.3 Pas. Batu Merah tb. 1 bata 1 PC : 3 Psr M2 SNID.6.3 123,475.00 SN2D.6.3 127,188.15 SNSD.6.3 120,975.00
M.001j Batu Merah (5x11x22cm) 140.00 Bh 360.00 50,400.00 380.00 53,200.00 360.00 50,400.00
M.002a Portland Cement 32.9500 Kg 1,200.00 39,540.00 1,207.00 39,770.65 1,200.00 39,540.00
M.001a Pasir Pasang 0.0910 M3 85,000.00 7,735.00 92,500.00 8,417.50 85,000.00 7,735.00
L.008 Pekerja 0.6500 OH 27,000.00 17,550.00 27,000.00 17,550.00 24,500.00 15,925.00
L.001 Tukang Batu 0.2000 OH 32,500.00 6,500.00 32,500.00 6,500.00 29,000.00 5,800.00
L.007 Kepala Tukang 0.0200 OH 35,000.00 700.00 35,000.00 700.00 31,500.00 630.00
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
SNI - D.6.5 Pas. Batu Merah tb. 1 bata 1 PC : 5 Psr M2 SNID.6.5 111,510.00 SN2D.6.5 115,230.40 SNSD.6.5 109,010.00
M.001j Batu Merah (5x11x22cm) 140.00 Bh 360.00 50,400.00 380.00 53,200.00 360.00 50,400.00
M.002a Portland Cement 22.2000 Kg 1,200.00 26,640.00 1,207.00 26,795.40 1,200.00 26,640.00
M.001a Pasir Pasang 0.1020 M3 85,000.00 8,670.00 92,500.00 9,435.00 85,000.00 8,670.00
L.008 Pekerja 0.6500 OH 27,000.00 17,550.00 27,000.00 17,550.00 24,500.00 15,925.00
L.001 Tukang Batu 0.2000 OH 32,500.00 6,500.00 32,500.00 6,500.00 29,000.00 5,800.00
L.007 Kepala Tukang 0.0200 OH 35,000.00 700.00 35,000.00 700.00 31,500.00 630.00
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
SNI - D.6.7 Pas. Batu Merah tb. 1 bata 1 PC : 3 Kp : 10 Psr M2 SNID.6.7 99,871.00 SN2D.6.7 103,572.81 SNSD.6.7 97,371.00
M.001j Batu Merah (5x11x22cm) 140.0 Bh 360.00 50,400.00 380.00 53,200.00 360.00 50,400.00
M.002a Portland Cement 10.0800 Kg 1,200.00 12,096.00 1,207.00 12,166.56 1,200.00 12,096.00
M.001a Pasir Pasang 0.0925 M3 85,000.00 7,862.50 92,500.00 8,556.25 85,000.00 7,862.50
M.001d Kapur pasang 0.0275 M3 135,000.00 3,712.50 140,000.00 3,850.00 135,000.00 3,712.50
L.008 Pekerja 0.6500 OH 27,000.00 17,550.00 27,000.00 17,550.00 24,500.00 15,925.00
L.001 Tukang Batu 0.2000 OH 32,500.00 6,500.00 32,500.00 6,500.00 29,000.00 5,800.00
L.007 Kepala Tukang 0.0200 OH 35,000.00 700.00 35,000.00 700.00 31,500.00 630.00
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
SNI - D.6.10 Pas. Batu Merah tb. 1/2 bata 1 PC : 3 Psr M2 SNID.6.10 58,609.00 SN2D.6.10 60,409.59 SNSD.6.10 57,371.50
M.001j Batu Merah (5x11x22cm) 70.0000 Bh 360.00 25,200.00 380.00 26,600.00 360.00 25,200.00
M.002a Portland Cement 14.3700 Kg 1,200.00 17,244.00 1,207.00 17,344.59 1,200.00 17,244.00
M.001a Pasir Pasang 0.0400 M3 85,000.00 3,400.00 92,500.00 3,700.00 85,000.00 3,400.00
L.008 Pekerja 0.3200 OH 27,000.00 8,640.00 27,000.00 8,640.00 24,500.00 7,840.00
L.001 Tukang Batu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0150 OH 35,000.00 525.00 35,000.00 525.00 31,500.00 472.50
SNI - D.6.12 Pas. Batu Merah tb. 1/2 bata 1 PC : 5 Psr M2 SNID.6.12 53,406.00 SN2D.6.12 55,211.26 SNSD.6.12 52,168.50
M.001j Batu Merah (5x11x22cm) 70.0000 Bh 360.00 25,200.00 380.00 26,600.00 360.00 25,200.00
M.002a Portland Cement 9.6800 Kg 1,200.00 11,616.00 1,207.00 11,683.76 1,200.00 11,616.00
M.001a Pasir Pasang 0.0450 M3 85,000.00 3,825.00 92,500.00 4,162.50 85,000.00 3,825.00
L.008 Pekerja 0.3200 OH 27,000.00 8,640.00 27,000.00 8,640.00 24,500.00 7,840.00
L.001 Tukang Batu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
93 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0150 OH 35,000.00 525.00 35,000.00 525.00 31,500.00 472.50
SNI - D.6.15 Pas. Batu Merah tb. 1/2 bata 1 PC : 3 Kp ; 10 Psr M2 SNID.6.15 49,640.00 SN2D.6.15 51,521.50 SNSD.6.15 48,402.50
M.001j Batu Merah (5x11x22cm) 70.0000 Bh 360.00 25,200.00 380.00 26,600.00 360.00 25,200.00
M.002a Portland Cement 4.5000 Kg 1,200.00 5,400.00 1,207.00 5,431.50 1,200.00 5,400.00
M.001a Pasir Pasang 0.0500 M3 85,000.00 4,250.00 92,500.00 4,625.00 85,000.00 4,250.00
M.001d Kapur pasang 0.0150 M3 135,000.00 2,025.00 140,000.00 2,100.00 135,000.00 2,025.00
L.008 Pekerja 0.3200 OH 27,000.00 8,640.00 27,000.00 8,640.00 24,500.00 7,840.00
L.001 Tukang Batu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0150 OH 35,000.00 525.00 35,000.00 525.00 31,500.00 472.50
E. PEKERJAAN PLESTERAN

SNI - E.6.3 Plesteran 1 PC : 3 Psr tb. 1,5 cm M2 SNIE.6.3 20,541.00 SN2E.6.3 20,728.86 SNSE.6.3 19,428.50
M.002a Portland Cement 6.4800 Kg 1,200.00 7,776.00 1,207.00 7,821.36 1,200.00 7,776.00
M.001a Pasir Pasang 0.0190 M3 85,000.00 1,615.00 92,500.00 1,757.50 85,000.00 1,615.00
L.008 Pekerja 0.2000 OH 27,000.00 5,400.00 27,000.00 5,400.00 24,500.00 4,900.00
L.001 Tukang Batu 0.1500 OH 32,500.00 4,875.00 32,500.00 4,875.00 29,000.00 4,350.00
L.007 Kepala Tukang 0.0150 OH 35,000.00 525.00 35,000.00 525.00 31,500.00 472.50
L.010 Mandor 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
SNI - E.6.5 Plesteran 1 PC : 5 Psr tb. 1,5 cm M2 SNIE.6.5 18,204.00 SN2E.6.5 18,399.24 SNSE.6.5 17,091.50
M.002a Portland Cement 4.3200 Kg 1,200.00 5,184.00 1,207.00 5,214.24 1,200.00 5,184.00
M.001a Pasir Pasang 0.0220 M3 85,000.00 1,870.00 92,500.00 2,035.00 85,000.00 1,870.00
L.008 Pekerja 0.2000 OH 27,000.00 5,400.00 27,000.00 5,400.00 24,500.00 4,900.00
L.001 Tukang Batu 0.1500 OH 32,500.00 4,875.00 32,500.00 4,875.00 29,000.00 4,350.00
L.007 Kepala Tukang 0.0150 OH 35,000.00 525.00 35,000.00 525.00 31,500.00 472.50
L.010 Mandor 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
SNI - E.6.9 Plesteran 1 PC : 3 Kp : 10 Psr tb. 1,5 cm M2 SNIE.6.9 15,358.00 SN2E.6.9 15,505.88 SNSE.6.9 14,245.50
M.002a Portland Cement 1.8400 Kg 1,200.00 2,208.00 1,207.00 2,220.88 1,200.00 2,208.00
M.001d Kapur Padam 0.0060 M3 135,000.00 810.00 140,000.00 840.00 135,000.00 810.00
M.001a Pasir Pasang 0.0140 M3 85,000.00 1,190.00 92,500.00 1,295.00 85,000.00 1,190.00
L.008 Pekerja 0.2000 OH 27,000.00 5,400.00 27,000.00 5,400.00 24,500.00 4,900.00
L.001 Tukang Batu 0.1500 OH 32,500.00 4,875.00 32,500.00 4,875.00 29,000.00 4,350.00
L.007 Kepala Tukang 0.0150 OH 35,000.00 525.00 35,000.00 525.00 31,500.00 472.50
L.010 Mandor 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
SNI - E.6.14 Plesteran 1 PC : 3 Psr tb. 2 cm M2 SNIE.6.14 29,557.50 SN2E.6.14 29,828.10 SNSE.6.14 28,118.75
M.002a Portland Cement 10.8000 Kg 1,200.00 12,960.00 1,207.00 13,035.60 1,200.00 12,960.00
M.001a Pasir Pasang 0.0260 M3 85,000.00 2,210.00 92,500.00 2,405.00 85,000.00 2,210.00
L.008 Pekerja 0.2500 OH 27,000.00 6,750.00 27,000.00 6,750.00 24,500.00 6,125.00
L.001 Tukang Batu 0.2000 OH 32,500.00 6,500.00 32,500.00 6,500.00 29,000.00 5,800.00
L.007 Kepala Tukang 0.0200 OH 35,000.00 700.00 35,000.00 700.00 31,500.00 630.00
L.010 Mandor 0.0125 OH 35,000.00 437.50 35,000.00 437.50 31,500.00 393.75
SNI - E.6.16 Plesteran 1 PC : 5 Psr tb. 2 cm M2 SNIE.6.16 25,515.50 SN2E.6.16 25,776.53 SNSE.6.16 24,076.75
M.002a Portland Cement 7.2900 Kg 1,200.00 8,748.00 1,207.00 8,799.03 1,200.00 8,748.00
M.001a Pasir Pasang 0.0280 M3 85,000.00 2,380.00 92,500.00 2,590.00 85,000.00 2,380.00
L.008 Pekerja 0.2500 OH 27,000.00 6,750.00 27,000.00 6,750.00 24,500.00 6,125.00
L.001 Tukang Batu 0.2000 OH 32,500.00 6,500.00 32,500.00 6,500.00 29,000.00 5,800.00
L.007 Kepala Tukang 0.0200 OH 35,000.00 700.00 35,000.00 700.00 31,500.00 630.00
L.010 Mandor 0.0125 OH 35,000.00 437.50 35,000.00 437.50 31,500.00 393.75
SNI - E.6.28 Berapen 1 PC : 5 Psr tb. 1,5 cm M2 SNIE.6.28 15,609.00 SN2E.6.28 15,821.19 SNSE.6.28 14,936.50
M.002a Portland Cement 5.6700 Kg 1,200.00 6,804.00 1,207.00 6,843.69 1,200.00 6,804.00
M.001a Pasir Pasang 0.0230 M3 85,000.00 1,955.00 92,500.00 2,127.50 85,000.00 1,955.00
L.008 Pekerja 0.1500 OH 27,000.00 4,050.00 27,000.00 4,050.00 24,500.00 3,675.00
L.001 Tukang Batu 0.0700 OH 32,500.00 2,275.00 32,500.00 2,275.00 29,000.00 2,030.00
L.007 Kepala Tukang 0.0070 OH 35,000.00 245.00 35,000.00 245.00 31,500.00 220.50
L.010 Mandor 0.0080 OH 35,000.00 280.00 35,000.00 280.00 31,500.00 252.00
SNI - E.6.30 Plesteran Beton 1 PC : 5 Psr tb. 1,5 cm M2 SNIE.6.30 24,944.00 SN2E.6.30 25,150.99 SNSE.6.30 23,478.50
M.002a Portland Cement 7.0700 Kg 1,200.00 8,484.00 1,207.00 8,533.49 1,200.00 8,484.00
M.001a Pasir Pasang 0.0210 M3 85,000.00 1,785.00 92,500.00 1,942.50 85,000.00 1,785.00
L.008 Pekerja 0.2600 OH 27,000.00 7,020.00 27,000.00 7,020.00 24,500.00 6,370.00
L.001 Tukang Batu 0.2000 OH 32,500.00 6,500.00 32,500.00 6,500.00 29,000.00 5,800.00
L.007 Kepala Tukang 0.0200 OH 35,000.00 700.00 35,000.00 700.00 31,500.00 630.00
L.010 Mandor 0.0130 OH 35,000.00 455.00 35,000.00 455.00 31,500.00 409.50
SNI - E.6.31 Plesteran Skoning 1 PC : 2 Psr M2 SNIE.6.31 4,944.00 SN2E.6.31 4,962.50 SNSE.6.31 4,528.50
94 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
M.002a Portland Cement 0.5000 Kg 1,200.00 600.00 1,207.00 603.50 1,200.00 600.00
M.001a Pasir Pasang 0.0020 M3 85,000.00 170.00 92,500.00 185.00 85,000.00 170.00
L.008 Pekerja 0.0570 OH 27,000.00 1,539.00 27,000.00 1,539.00 24,500.00 1,396.50
L.001 Tukang Batu 0.0380 OH 32,500.00 1,235.00 32,500.00 1,235.00 29,000.00 1,102.00
L.007 Kepala Tukang 0.0380 OH 35,000.00 1,330.00 35,000.00 1,330.00 31,500.00 1,197.00
L.010 Mandor 0.0020 OH 35,000.00 70.00 35,000.00 70.00 31,500.00 63.00
SNI - E.6.35 Plesteran Siar Adukan 1 PC : 2 Psr M2 SNIE.6.35 13,394.00 SN2E.6.35 13,544.24 SNSE.6.35 12,721.50
M.002a Portland Cement 4.3200 Kg 1,200.00 5,184.00 1,207.00 5,214.24 1,200.00 5,184.00
M.001a Pasir Pasang 0.0160 M3 85,000.00 1,360.00 92,500.00 1,480.00 85,000.00 1,360.00
L.008 Pekerja 0.1500 OH 27,000.00 4,050.00 27,000.00 4,050.00 24,500.00 3,675.00
L.001 Tukang Batu 0.0700 OH 32,500.00 2,275.00 32,500.00 2,275.00 29,000.00 2,030.00
L.007 Kepala Tukang 0.0070 OH 35,000.00 245.00 35,000.00 245.00 31,500.00 220.50
L.010 Mandor 0.0080 OH 35,000.00 280.00 35,000.00 280.00 31,500.00 252.00
F. PEKERJAAN KAYU

SNI - F.6.1 Pas. Kusen Pintu dan Jendela Kayu Jati M3 SNIF.6.1 16,842,500.00 SN2F.6.1 16,925,000.00 SNSF.6.1 16,749,450.00
M.005f Kayu Jati Balok (lokal) 1.1000 M3 14,500,000 15,950,000.00 14,575,000 16,032,500.00 14,500,000 15,950,000.00
L.008 Pekerja 6.0000 OH 27,000 162,000.00 27,000 162,000.00 24,500 147,000.00
L.002 Tukang Kayu 20.0000 OH 32,500 650,000.00 32,500 650,000.00 29,000 580,000.00
L.007 Kepala Tukang 2.0000 OH 35,000 70,000.00 35,000 70,000.00 31,500 63,000.00
L.010 Mandor 0.3000 OH 35,000 10,500.00 35,000 10,500.00 31,500 9,450.00
95 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
SNI - F.6.2 Pas. Kusen Pintu dan Jendela Kayu Kamper M3 SNIF.6.2 9,946,300.00 SN2F.6.2 10,036,300.00 SNSF.6.2 9,860,250.00
M.005e Kayu Kamper Balok 1.2000 M3 7,599,000.00 9,118,800.00 7,674,000.00 9,208,800.00 7,599,000.00 9,118,800.00
L.008 Pekerja 6.0000 OH 27,000.00 162,000.00 27,000.00 162,000.00 24,500.00 147,000.00
L.002 Tukang Kayu 18.0000 OH 32,500.00 585,000.00 32,500.00 585,000.00 29,000.00 522,000.00
L.007 Kepala Tukang 2.0000 OH 35,000.00 70,000.00 35,000.00 70,000.00 31,500.00 63,000.00
L.010 Mandor 0.3000 OH 35,000.00 10,500.00 35,000.00 10,500.00 31,500.00 9,450.00
SNI - F.6.2a Pas. Kusen Pintu dan Jendela Kayu Bangkir M3 SNIF.6.2a 10,121,500.00 SN2F.6.2a 10,211,500.00 SNSF.6.2a 10,035,450.00
M.005d Kayu Bangkir Balok 1.2000 M3 7,745,000.00 9,294,000.00 7,820,000.00 9,384,000.00 7,745,000.00 9,294,000.00
L.008 Pekerja 6.0000 OH 27,000.00 162,000.00 27,000.00 162,000.00 24,500.00 147,000.00
L.002 Tukang Kayu 18.0000 OH 32,500.00 585,000.00 32,500.00 585,000.00 29,000.00 522,000.00
L.007 Kepala Tukang 2.0000 OH 35,000.00 70,000.00 35,000.00 70,000.00 31,500.00 63,000.00
L.010 Mandor 0.3000 OH 35,000.00 10,500.00 35,000.00 10,500.00 31,500.00 9,450.00
SNI - F.6.2b Pas. Kusen Pintu dan Jendela Kayu Kruing M3 SNIF.6.2b 7,451,500.00 SN2F.6.2b 7,541,500.00 SNSF.6.2b 7,365,450.00
M.005c Kayu Kruing Balok 1.2000 M3 5,520,000.00 6,624,000.00 5,595,000.00 6,714,000.00 5,520,000.00 6,624,000.00
L.008 Pekerja 6.0000 OH 27,000.00 162,000.00 27,000.00 162,000.00 24,500.00 147,000.00
L.002 Tukang Kayu 18.0000 OH 32,500.00 585,000.00 32,500.00 585,000.00 29,000.00 522,000.00
L.007 Kepala Tukang 2.0000 OH 35,000.00 70,000.00 35,000.00 70,000.00 31,500.00 63,000.00
L.010 Mandor 0.3000 OH 35,000.00 10,500.00 35,000.00 10,500.00 31,500.00 9,450.00

SNI - F.6.2c Pas. Kusen Pintu dan Jendela Kayu Jati (lokal) M3 SNIF.6.2c 16,777,500.00 SN2F.6.2c 16,860,000.00 SNSF.6.2c 16,691,450.00
M.005f Kayu Jati balok lokal 1.1000 M3 14,500,000.00 15,950,000.00 14,575,000.00 16,032,500.00 14,500,000.00 15,950,000.00
L.008 Pekerja 6.0000 OH 27,000.00 162,000.00 27,000.00 162,000.00 24,500.00 147,000.00
L.002 Tukang Kayu 18.0000 OH 32,500.00 585,000.00 32,500.00 585,000.00 29,000.00 522,000.00
L.007 Kepala Tukang 2.0000 OH 35,000.00 70,000.00 35,000.00 70,000.00 31,500.00 63,000.00
L.010 Mandor 0.3000 OH 35,000.00 10,500.00 35,000.00 10,500.00 31,500.00 9,450.00
Pas. Soko / Tiang kayu Jati (uk. Khusus 30/30-
SNI - F.6.2d 12/12 P : 5-8 m' ) Diketam halus dan di Propil (Kw. M3 SNIF.6.2d 58,427,860.00 SN2F.6.2d 58,517,860.00 SNSF.6.2d 58,341,810.00
Eksport)
M.005f1 Kayu Jati Balok Uk. Khusus (Kw. Eksport 1.2000 M3 48,000,000.00 57,600,000.00 48,075,000.00 57,690,000.00 48,000,000.00 57,600,000.00
M.006 Paku biasa ( 5" ) 0.0200 Kg 18,000.00 360.00 18,000.00 360.00 18,000.00 360.00
L.008 Pekerja 6.0000 OH 27,000.00 162,000.00 27,000.00 162,000.00 24,500.00 147,000.00
L.002 Tukang Kayu 18.0000 OH 32,500.00 585,000.00 32,500.00 585,000.00 29,000.00 522,000.00
L.007 Kepala Tukang 2.0000 OH 35,000.00 70,000.00 35,000.00 70,000.00 31,500.00 63,000.00
L.010 Mandor 0.3000 OH 35,000.00 10,500.00 35,000.00 10,500.00 31,500.00 9,450.00
Pas. Soko / Tiang kayu Jati uk. Khusus Diketam
SNI - F.6.2e M3 SNIF.6.2e 30,827,860.00 SN2F.6.2e 30,917,860.00 SNSF.6.2e 30,741,810.00
halus dan di Propil (Kw. Eksport)
M.005f3 Kayu Jati Balok Uk.Bukan Khusus 1.2000 M3 25,000,000.00 30,000,000.00 25,075,000.00 30,090,000.00 25,000,000.00 30,000,000.00
M.006 Paku biasa ( 5" ) 0.0200 Kg 18,000.00 360.00 18,000.00 360.00 18,000.00 360.00
L.008 Pekerja 6.0000 OH 27,000.00 162,000.00 27,000.00 162,000.00 24,500.00 147,000.00
L.002 Tukang Kayu 18.0000 OH 32,500.00 585,000.00 32,500.00 585,000.00 29,000.00 522,000.00
L.007 Kepala Tukang 2.0000 OH 35,000.00 70,000.00 35,000.00 70,000.00 31,500.00 63,000.00
L.010 Mandor 0.3000 OH 35,000.00 10,500.00 35,000.00 10,500.00 31,500.00 9,450.00
Pas. Soko / Tiang kayu Bangkir uk. Khusus
SNI - F.6.2f M3 SNIF.6.2f 12,491,860.00 SN2F.6.2f 12,581,860.00 SNSF.6.2f 12,405,810.00
Diketam halus dan di Propil
M.005d1 Kayu Bangkir Balok Uk. Khusus 1.2000 M3 9,720,000.00 11,664,000.00 9,795,000.00 11,754,000.00 9,720,000.00 11,664,000.00
M.006 Paku biasa ( 5" ) 0.0200 Kg 18,000.00 360.00 18,000.00 360.00 18,000.00 360.00
L.008 Pekerja 6.0000 OH 27,000.00 162,000.00 27,000.00 162,000.00 24,500.00 147,000.00
L.002 Tukang Kayu 18.0000 OH 32,500.00 585,000.00 32,500.00 585,000.00 29,000.00 522,000.00
L.007 Kepala Tukang 2.0000 OH 35,000.00 70,000.00 35,000.00 70,000.00 31,500.00 63,000.00
L.010 Mandor 0.3000 OH 35,000.00 10,500.00 35,000.00 10,500.00 31,500.00 9,450.00
SNI - F.6.7 Pas. Pintu Panil Kayu Jati M2 SNIF.6.7 630,750.00 SN2F.6.7 633,750.00 SNSF.6.7 618,450.00
M.005p Papan Jati (lokal) 0.0400 M3 12,800,000 512,000.00 12,875,000 515,000.00 12,800,000 512,000.00
L.008 Pekerja 1.0000 OH 27,000 27,000.00 27,000 27,000.00 24,500 24,500.00
L.002 Tukang Kayu 2.5000 OH 32,500 81,250.00 32,500 81,250.00 29,000 72,500.00
L.007 Kepala Tukang 0.2500 OH 35,000 8,750.00 35,000 8,750.00 31,500 7,875.00
L.010 Mandor 0.0500 OH 35,000 1,750.00 35,000 1,750.00 31,500 1,575.00
SNI - F.6.8 Pas. Pintu Panil Kayu Kamper M2 SNIF.6.8 458,750.00 SN2F.6.8 461,750.00 SNSF.6.8 446,450.00
M.005o Papan Kamper 0.0400 M3 8,500,000.00 340,000.00 8,575,000.00 343,000.00 8,500,000.00 340,000.00
L.008 Pekerja 1.0000 OH 27,000.00 27,000.00 27,000.00 27,000.00 24,500.00 24,500.00
L.002 Tukang Kayu 2.5000 OH 32,500.00 81,250.00 32,500.00 81,250.00 29,000.00 72,500.00
L.007 Kepala Tukang 0.2500 OH 35,000.00 8,750.00 35,000.00 8,750.00 31,500.00 7,875.00
L.010 Mandor 0.0500 OH 35,000.00 1,750.00 35,000.00 1,750.00 31,500.00 1,575.00
SNI - F.6.8a Pas. Pintu Panil Kayu Bangkir M2 SNIF.6.8a 478,750.00 SN2F.6.8a 481,750.00 SNSF.6.8a 466,450.00
96 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
M.005n Papan Bangkir 0.0400 M3 9,000,000.00 360,000.00 9,075,000.00 363,000.00 9,000,000.00 360,000.00
L.008 Pekerja 1.0000 OH 27,000.00 27,000.00 27,000.00 27,000.00 24,500.00 24,500.00
L.002 Tukang Kayu 2.5000 OH 32,500.00 81,250.00 32,500.00 81,250.00 29,000.00 72,500.00
L.007 Kepala Tukang 0.2500 OH 35,000.00 8,750.00 35,000.00 8,750.00 31,500.00 7,875.00
L.010 Mandor 0.0500 OH 35,000.00 1,750.00 35,000.00 1,750.00 31,500.00 1,575.00
SNI - F.6.8b Pas. Pintu Panil Kayu Kruing M2 SNIF.6.8b 362,750.00 SN2F.6.8b 365,750.00 SNSF.6.8b 350,450.00
M.005m Papan Kruing 0.0400 M3 6,100,000.00 244,000.00 6,175,000.00 247,000.00 6,100,000.00 244,000.00
L.008 Pekerja 1.0000 OH 27,000.00 27,000.00 27,000.00 27,000.00 24,500.00 24,500.00
L.002 Tukang Kayu 2.5000 OH 32,500.00 81,250.00 32,500.00 81,250.00 29,000.00 72,500.00
97 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
L.007 Kepala Tukang 0.2500 OH 35,000.00 8,750.00 35,000.00 8,750.00 31,500.00 7,875.00
L.010 Mandor 0.0500 OH 35,000.00 1,750.00 35,000.00 1,750.00 31,500.00 1,575.00
SNI - F.6.9 Pas. Pintu dan Jendela Kaca Kayu Jati M2 SNIF.6.9 543,000.00 SN2F.6.9 545,625.00 SNSF.6.9 533,160.00
M.005p Papan Jati (lokal) 0.0350 M3 12,800,000 448,000.00 12,875,000 450,625.00 12,800,000 448,000.00
L.008 Pekerja 0.8000 OH 27,000 21,600.00 27,000 21,600.00 24,500 19,600.00
L.002 Tukang Kayu 2.0000 OH 32,500 65,000.00 32,500 65,000.00 29,000 58,000.00
L.007 Kepala Tukang 0.2000 OH 35,000 7,000.00 35,000 7,000.00 31,500 6,300.00
L.010 Mandor 0.0400 OH 35,000 1,400.00 35,000 1,400.00 31,500 1,260.00
SNI - F.6.10 Pas. Pintu dan Jendela Kaca Kayu Kamper M2 SNIF.6.10 392,500.00 SN2F.6.10 395,125.00 SNSF.6.10 382,660.00
M.005o Papan Kamper 0.0350 M3 8,500,000.00 297,500.00 8,575,000.00 300,125.00 8,500,000.00 297,500.00
L.008 Pekerja 0.8000 OH 27,000.00 21,600.00 27,000.00 21,600.00 24,500.00 19,600.00
L.002 Tukang Kayu 2.0000 OH 32,500.00 65,000.00 32,500.00 65,000.00 29,000.00 58,000.00
L.007 Kepala Tukang 0.2000 OH 35,000.00 7,000.00 35,000.00 7,000.00 31,500.00 6,300.00
L.010 Mandor 0.0400 OH 35,000.00 1,400.00 35,000.00 1,400.00 31,500.00 1,260.00
SNI - F.6.10a Pas. Pintu dan Jendela Kaca Kayu Bangkir M2 SNIF.6.10a 410,000.00 SN2F.6.10a 412,625.00 SNSF.6.10a 400,160.00
M.005n Papan Bangkir 0.0350 M3 9,000,000.00 315,000.00 9,075,000.00 317,625.00 9,000,000.00 315,000.00
L.008 Pekerja 0.8000 OH 27,000.00 21,600.00 27,000.00 21,600.00 24,500.00 19,600.00
L.002 Tukang Kayu 2.0000 OH 32,500.00 65,000.00 32,500.00 65,000.00 29,000.00 58,000.00
L.007 Kepala Tukang 0.2000 OH 35,000.00 7,000.00 35,000.00 7,000.00 31,500.00 6,300.00
L.010 Mandor 0.0400 OH 35,000.00 1,400.00 35,000.00 1,400.00 31,500.00 1,260.00
SNI - F.6.10b Pas. Pintu dan Jendela Kaca Kayu Kruing M2 SNIF.6.10b 308,500.00 SN2F.6.10b 311,125.00 SNSF.6.10b 298,660.00
M.005m Papan Kruing 0.0350 M3 6,100,000.00 213,500.00 6,175,000.00 216,125.00 6,100,000.00 213,500.00
L.008 Pekerja 0.8000 OH 27,000.00 21,600.00 27,000.00 21,600.00 24,500.00 19,600.00
L.002 Tukang Kayu 2.0000 OH 32,500.00 65,000.00 32,500.00 65,000.00 29,000.00 58,000.00
L.007 Kepala Tukang 0.2000 OH 35,000.00 7,000.00 35,000.00 7,000.00 31,500.00 6,300.00
L.010 Mandor 0.0400 OH 35,000.00 1,400.00 35,000.00 1,400.00 31,500.00 1,260.00
SNI - F.6.12 Pas. Pintu dan Jendela Jalusi Kayu Jati M2 SNIF.6.12 964,700.00 SN2F.6.12 969,500.00 SNSF.6.12 949,600.00
M.005p Papan Jati (lokal) 0.0640 M3 12,800,000.00 819,200.00 12,875,000.00 824,000.00 12,800,000.00 819,200.00
L.008 Pekerja 1.0000 OH 27,000.00 27,000.00 27,000.00 27,000.00 24,500.00 24,500.00
L.002 Tukang Kayu 3.0000 OH 32,500.00 97,500.00 32,500.00 97,500.00 29,000.00 87,000.00
L.007 Kepala Tukang 0.3000 OH 35,000.00 10,500.00 35,000.00 10,500.00 31,500.00 9,450.00
L.010 Mandor 0.3000 OH 35,000.00 10,500.00 35,000.00 10,500.00 31,500.00 9,450.00
SNI - F.6.13 Pas. Pintu dan Jendela Jalusi Kayu Kamper M2 SNIF.6.13 696,500.00 SN2F.6.13 701,300.00 SNSF.6.13 680,700.00
M.005o Papan Kamper 0.0640 M3 8,500,000.00 544,000.00 8,575,000.00 548,800.00 8,500,000.00 544,000.00
L.008 Pekerja 1.0000 OH 27,000.00 27,000.00 27,000.00 27,000.00 24,500.00 24,500.00
L.002 Tukang Kayu 3.0000 OH 32,500.00 97,500.00 32,500.00 97,500.00 29,000.00 87,000.00
L.007 Kepala Tukang 0.3000 OH 35,000.00 10,500.00 35,000.00 10,500.00 31,500.00 9,450.00
L.010 Mandor 0.5000 OH 35,000.00 17,500.00 35,000.00 17,500.00 31,500.00 15,750.00
SNI - F.6.13a Pas. Pintu dan Jendela Jalusi Kayu Bangkir M2 SNIF.6.13a 728,500.00 SN2F.6.13a 733,300.00 SNSF.6.13a 712,700.00
M.005n Papan Bangkir 0.0640 M3 9,000,000.00 576,000.00 9,075,000.00 580,800.00 9,000,000.00 576,000.00
L.008 Pekerja 1.0000 OH 27,000.00 27,000.00 27,000.00 27,000.00 24,500.00 24,500.00
L.002 Tukang Kayu 3.0000 OH 32,500.00 97,500.00 32,500.00 97,500.00 29,000.00 87,000.00
L.007 Kepala Tukang 0.3000 OH 35,000.00 10,500.00 35,000.00 10,500.00 31,500.00 9,450.00
L.010 Mandor 0.5000 OH 35,000.00 17,500.00 35,000.00 17,500.00 31,500.00 15,750.00
SNI - F.6.13b Pas. Pintu dan Jendela Jalusi Kayu Kruing M2 SNIF.6.13b 542,900.00 SN2F.6.13b 547,700.00 SNSF.6.13b 527,100.00
M.005m Papan Kruing 0.0640 M3 6,100,000.00 390,400.00 6,175,000.00 395,200.00 6,100,000.00 390,400.00
L.008 Pekerja 1.0000 OH 27,000.00 27,000.00 27,000.00 27,000.00 24,500.00 24,500.00
L.002 Tukang Kayu 3.0000 OH 32,500.00 97,500.00 32,500.00 97,500.00 29,000.00 87,000.00
L.007 Kepala Tukang 0.3000 OH 35,000.00 10,500.00 35,000.00 10,500.00 31,500.00 9,450.00
L.010 Mandor 0.5000 OH 35,000.00 17,500.00 35,000.00 17,500.00 31,500.00 15,750.00
SNI - F.6.16 Pas. Jalusi Mati Kusen Kayu Jati M2 SNIF.6.16 857,652.50 SN2F.6.16 862,152.50 SNSF.6.16 848,615.00
M.005p Papan Jati (lokal) 0.0600 M3 12,800,000.00 768,000.00 12,875,000.00 772,500.00 12,800,000.00 768,000.00
M.006a Paku Biasa ( 1/2" - 1") 0.1500 Kg 21,850.00 3,277.50 21,850.00 3,277.50 21,850.00 3,277.50
L.008 Pekerja 0.5000 OH 27,000.00 13,500.00 27,000.00 13,500.00 24,500.00 12,250.00
L.002 Tukang Kayu 2.0000 OH 32,500.00 65,000.00 32,500.00 65,000.00 29,000.00 58,000.00
L.007 Kepala Tukang 0.2000 OH 35,000.00 7,000.00 35,000.00 7,000.00 31,500.00 6,300.00
L.010 Mandor 0.0250 OH 35,000.00 875.00 35,000.00 875.00 31,500.00 787.50
SNI - F.6.17 Pas. Jalusi Mati Kusen Kayu Kamper M2 SNIF.6.17 599,652.50 SN2F.6.17 604,152.50 SNSF.6.17 590,615.00
M.005o Papan Kamper 0.0600 M3 8,500,000.00 510,000.00 8,575,000.00 514,500.00 8,500,000.00 510,000.00
M.006a Paku Biasa ( 1/2" - 1") 0.1500 Kg 21,850.00 3,277.50 21,850.00 3,277.50 21,850.00 3,277.50
L.008 Pekerja 0.5000 OH 27,000.00 13,500.00 27,000.00 13,500.00 24,500.00 12,250.00
98 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
L.002 Tukang Kayu 2.0000 OH 32,500.00 65,000.00 32,500.00 65,000.00 29,000.00 58,000.00
L.007 Kepala Tukang 0.2000 OH 35,000.00 7,000.00 35,000.00 7,000.00 31,500.00 6,300.00
L.010 Mandor 0.0250 OH 35,000.00 875.00 35,000.00 875.00 31,500.00 787.50
SNI - F.6.17a Pas. Jalusi Mati Kusen Kayu Bangkir M2 SNIF.6.17a 629,652.50 SN2F.6.17a 634,152.50 SNSF.6.17a 620,615.00
M.005n Papan Bangkir 0.0600 M3 9,000,000.00 540,000.00 9,075,000.00 544,500.00 9,000,000.00 540,000.00
M.006a Paku Biasa ( 1/2" - 1") 0.1500 Kg 21,850.00 3,277.50 21,850.00 3,277.50 21,850.00 3,277.50
L.008 Pekerja 0.5000 OH 27,000.00 13,500.00 27,000.00 13,500.00 24,500.00 12,250.00
L.002 Tukang Kayu 2.0000 OH 32,500.00 65,000.00 32,500.00 65,000.00 29,000.00 58,000.00
L.007 Kepala Tukang 0.2000 OH 35,000.00 7,000.00 35,000.00 7,000.00 31,500.00 6,300.00
L.010 Mandor 0.0250 OH 35,000.00 875.00 35,000.00 875.00 31,500.00 787.50
99 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
SNI - F.6.17b Pas. Jalusi Mati Kusen Kayu Kruing M2 SNIF.6.17b 455,652.50 SN2F.6.17b 460,152.50 SNSF.6.17b 446,615.00
M.005m Papan Kruing 0.0600 M3 6,100,000.00 366,000.00 6,175,000.00 370,500.00 6,100,000.00 366,000.00
M.006a Paku Biasa ( 1/2" - 1") 0.1500 Kg 21,850.00 3,277.50 21,850.00 3,277.50 21,850.00 3,277.50
L.008 Pekerja 0.5000 OH 27,000.00 13,500.00 27,000.00 13,500.00 24,500.00 12,250.00
L.002 Tukang Kayu 2.0000 OH 32,500.00 65,000.00 32,500.00 65,000.00 29,000.00 58,000.00
L.007 Kepala Tukang 0.2000 OH 35,000.00 7,000.00 35,000.00 7,000.00 31,500.00 6,300.00
L.010 Mandor 0.0250 OH 35,000.00 875.00 35,000.00 875.00 31,500.00 787.50
SNI - F.6.19 Pas. Pintu Teakwood rangkap, rangka Kayu Jati M2 SNIF.6.19 428,785.00 SN2F.6.19 431,255.00 SNSF.6.19 419,480.00
M.005p Papan Jati (lokal) 0.0196 M3 12,800,000.00 250,880.00 12,875,000.00 252,350.00 12,800,000.00 250,880.00
M.006a Paku Biasa ( 1/2" - 1") 0.3000 Kg 21,850.00 6,555.00 21,850.00 6,555.00 21,850.00 6,555.00
M.012g Lem Kayu 0.3000 Kg 17,000.00 5,100.00 17,000.00 5,100.00 17,000.00 5,100.00
M.009e Teakwood 3' x 7' x 3mm 1.0000 Lbr 77,000.00 77,000.00 78,000.00 78,000.00 77,000.00 77,000.00
L.008 Pekerja 0.6000 OH 27,000.00 16,200.00 27,000.00 16,200.00 24,500.00 14,700.00
L.002 Tukang Kayu 2.0000 OH 32,500.00 65,000.00 32,500.00 65,000.00 29,000.00 58,000.00
L.007 Kepala Tukang 0.2000 OH 35,000.00 7,000.00 35,000.00 7,000.00 31,500.00 6,300.00
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
Pas. Pintu Teakwood rangkap, rangka Kayu
SNI - F.6.20 M2 SNIF.6.20 344,505.00 SN2F.6.20 346,975.00 SNSF.6.20 335,200.00
Kamper
M.005o Papan Kamper 0.0196 M3 8,500,000.00 166,600.00 8,575,000.00 168,070.00 8,500,000.00 166,600.00
M.006a Paku Biasa ( 1/2" - 1") 0.3000 Kg 21,850.00 6,555.00 21,850.00 6,555.00 21,850.00 6,555.00
M.012g Lem Kayu 0.3000 Kg 17,000.00 5,100.00 17,000.00 5,100.00 17,000.00 5,100.00
M.009e Teakwood 3' x 7' x 3mm 1.0000 Lbr 77,000.00 77,000.00 78,000.00 78,000.00 77,000.00 77,000.00
L.008 Pekerja 0.6000 OH 27,000.00 16,200.00 27,000.00 16,200.00 24,500.00 14,700.00
L.002 Tukang Kayu 2.0000 OH 32,500.00 65,000.00 32,500.00 65,000.00 29,000.00 58,000.00
L.007 Kepala Tukang 0.2000 OH 35,000.00 7,000.00 35,000.00 7,000.00 31,500.00 6,300.00
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
Pas. Pintu Teakwood rangkap, rangka Kayu
SNI - F.6.20a M2 SNIF.6.20a 354,305.00 SN2F.6.20a 356,775.00 SNSF.6.20a 345,000.00
Bangkir
M.005n Papan Bangkir 0.0196 M3 9,000,000.00 176,400.00 9,075,000.00 177,870.00 9,000,000.00 176,400.00
M.006a Paku Biasa ( 1/2" - 1") 0.3000 Kg 21,850.00 6,555.00 21,850.00 6,555.00 21,850.00 6,555.00
M.012g Lem Kayu 0.3000 Kg 17,000.00 5,100.00 17,000.00 5,100.00 17,000.00 5,100.00
M.009e Teakwood 3' x 7' x 3mm 1.0000 Lbr 77,000.00 77,000.00 78,000.00 78,000.00 77,000.00 77,000.00
L.008 Pekerja 0.6000 OH 27,000.00 16,200.00 27,000.00 16,200.00 24,500.00 14,700.00
L.002 Tukang Kayu 2.0000 OH 32,500.00 65,000.00 32,500.00 65,000.00 29,000.00 58,000.00
L.007 Kepala Tukang 0.2000 OH 35,000.00 7,000.00 35,000.00 7,000.00 31,500.00 6,300.00
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
Pas. Pintu Teakwood rangkap, rangka Kayu
SNI - F.6.20b M2 SNIF.6.20b 297,465.00 SN2F.6.20b 299,935.00 SNSF.6.20b 288,160.00
Kruing
M.005m Papan Kruing 0.0196 M3 6,100,000.00 119,560.00 6,175,000.00 121,030.00 6,100,000.00 119,560.00
M.006a Paku Biasa ( 1/2" - 1") 0.3000 Kg 21,850.00 6,555.00 21,850.00 6,555.00 21,850.00 6,555.00
M.012g Lem Kayu 0.3000 Kg 17,000.00 5,100.00 17,000.00 5,100.00 17,000.00 5,100.00
M.009e Teakwood 3' x 7' x 3mm 1.0000 Lbr 77,000.00 77,000.00 78,000.00 78,000.00 77,000.00 77,000.00
L.008 Pekerja 0.6000 OH 27,000.00 16,200.00 27,000.00 16,200.00 24,500.00 14,700.00
L.002 Tukang Kayu 2.0000 OH 32,500.00 65,000.00 32,500.00 65,000.00 29,000.00 58,000.00
L.007 Kepala Tukang 0.2000 OH 35,000.00 7,000.00 35,000.00 7,000.00 31,500.00 6,300.00
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
Pas. Pintu Triplek 3mm rangkap, rangka Kayu
SNI - F.6.20c M2 SNIF.6.20c 316,005.00 SN2F.6.20c 318,975.00 SNSF.6.20c 306,700.00
Kamper
M.005o Papan Kamper 0.0196 M3 8,500,000.00 166,600.00 8,575,000.00 168,070.00 8,500,000.00 166,600.00
M.006a Paku Biasa ( 1/2" - 1") 0.3000 Kg 21,850.00 6,555.00 21,850.00 6,555.00 21,850.00 6,555.00
M.012g Lem Kayu 0.3000 Kg 17,000.00 5,100.00 17,000.00 5,100.00 17,000.00 5,100.00
M.009a Triplek 3mm ( 3' x 7' ) 1.0000 Lbr 48,500.00 48,500.00 50,000.00 50,000.00 48,500.00 48,500.00
L.008 Pekerja 0.6000 OH 27,000.00 16,200.00 27,000.00 16,200.00 24,500.00 14,700.00
L.002 Tukang Kayu 2.0000 OH 32,500.00 65,000.00 32,500.00 65,000.00 29,000.00 58,000.00
L.007 Kepala Tukang 0.2000 OH 35,000.00 7,000.00 35,000.00 7,000.00 31,500.00 6,300.00
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
Pas. Pintu Triplek 3mm rangkap, rangka Kayu
SNI - F.6.20d M2 SNIF.6.20d 325,805.00 SN2F.6.20d 328,775.00 SNSF.6.20d 316,500.00
Bangkir
M.005n Papan Bangkir 0.0196 M3 9,000,000.00 176,400.00 9,075,000.00 177,870.00 9,000,000.00 176,400.00
M.006a Paku Biasa ( 1/2" - 1") 0.3000 Kg 21,850.00 6,555.00 21,850.00 6,555.00 21,850.00 6,555.00
M.012g Lem Kayu 0.3000 Kg 17,000.00 5,100.00 17,000.00 5,100.00 17,000.00 5,100.00
M.009a Triplek 3mm ( 3' x 7' ) 1.0000 Lbr 48,500.00 48,500.00 50,000.00 50,000.00 48,500.00 48,500.00
L.008 Pekerja 0.6000 OH 27,000.00 16,200.00 27,000.00 16,200.00 24,500.00 14,700.00
L.002 Tukang Kayu 2.0000 OH 32,500.00 65,000.00 32,500.00 65,000.00 29,000.00 58,000.00
L.007 Kepala Tukang 0.2000 OH 35,000.00 7,000.00 35,000.00 7,000.00 31,500.00 6,300.00
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
100 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
Pas. Pintu Triplek 3mm rangkap, rangka Kayu
SNI - F.6.20e M2 SNIF.6.20e 268,965.00 SN2F.6.20e 271,935.00 SNSF.6.20e 259,660.00
Kruing
M.005m Papan Kruing 0.0196 M3 6,100,000.00 119,560.00 6,175,000.00 121,030.00 6,100,000.00 119,560.00
M.006a Paku Biasa ( 1/2" - 1") 0.3000 Kg 21,850.00 6,555.00 21,850.00 6,555.00 21,850.00 6,555.00
M.012g Lem Kayu 0.3000 Kg 17,000.00 5,100.00 17,000.00 5,100.00 17,000.00 5,100.00
M.009a Triplek 3mm ( 3' x 7' ) 1.0000 Lbr 48,500.00 48,500.00 50,000.00 50,000.00 48,500.00 48,500.00
L.008 Pekerja 0.6000 OH 27,000.00 16,200.00 27,000.00 16,200.00 24,500.00 14,700.00
L.002 Tukang Kayu 2.0000 OH 32,500.00 65,000.00 32,500.00 65,000.00 29,000.00 58,000.00
L.007 Kepala Tukang 0.2000 OH 35,000.00 7,000.00 35,000.00 7,000.00 31,500.00 6,300.00
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
101 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
SNI - F.6.27 Pas. Konstruksi Kuda-kuda Kayu Jati M3 SNIF.6.27 16,826,400.00 SN2F.6.27 16,923,900.00 SNSF.6.27 16,769,500.00
M.005f Kayu Jati Balok (lokal) 1.1000 M3 14,500,000.00 15,950,000.00 14,575,000.00 16,032,500.00 14,500,000.00 15,950,000.00
M.003d Begel 15.0000 Kg 21,000.00 315,000.00 22,000.00 330,000.00 21,000.00 315,000.00
M.006 Paku Biasa ( 2" - 5") 0.8000 Kg 18,000.00 14,400.00 18,000.00 14,400.00 18,000.00 14,400.00
L.008 Pekerja 4.0000 OH 27,000.00 108,000.00 27,000.00 108,000.00 24,500.00 98,000.00
L.002 Tukang Kayu 12.0000 OH 32,500.00 390,000.00 32,500.00 390,000.00 29,000.00 348,000.00
L.007 Kepala Tukang 1.2000 OH 35,000.00 42,000.00 35,000.00 42,000.00 31,500.00 37,800.00
L.010 Mandor 0.2000 OH 35,000.00 7,000.00 35,000.00 7,000.00 31,500.00 6,300.00
Pas. Rangka Atap diketam halus dan di propil
SNI - F.6.27a M3 SNIF.6.27a 53,925,400.00 SN2F.6.27a 54,022,900.00 SNSF.6.27a 53,842,500.00
Kayu Jati (Kw.Eksport) uk. Khusus
M.005f1 Kayu Jati Balok (Kw. Eksport) uk.Khusus 1.1000 M3 48,000,000.00 52,800,000.00 48,075,000.00 52,882,500.00 48,000,000.00 52,800,000.00
M.003d Begel 15.0000 Kg 21,000.00 315,000.00 22,000.00 330,000.00 21,000.00 315,000.00
M.006 Paku Biasa ( 2" - 5") 0.8000 Kg 18,000.00 14,400.00 18,000.00 14,400.00 18,000.00 14,400.00
L.008 Pekerja 6.0000 OH 27,000.00 162,000.00 27,000.00 162,000.00 24,500.00 147,000.00
L.002 Tukang Kayu 18.0000 OH 32,500.00 585,000.00 32,500.00 585,000.00 29,000.00 522,000.00
L.007 Kepala Tukang 1.2000 OH 35,000.00 42,000.00 35,000.00 42,000.00 31,500.00 37,800.00
L.010 Mandor 0.2000 OH 35,000.00 7,000.00 35,000.00 7,000.00 31,500.00 6,300.00
Pas. Rangka Atap diketam halus dan di propil
SNI - F.6.27b M3 SNIF.6.27b 34,537,900.00 SN2F.6.27b 34,635,400.00 SNSF.6.27b 34,455,000.00
Kayu Jati (Kw. Eksport) uk. Khusus
Kayu Jati Balok (Kw. Eksport)
M.005f3 1.1000 M3 30,375,000.00 33,412,500.00 30,450,000.00 33,495,000.00 30,375,000.00 33,412,500.00
uk.Khusus
M.003d Begel 15.0000 Kg 21,000.00 315,000.00 22,000.00 330,000.00 21,000.00 315,000.00
M.006 Paku Biasa ( 2" - 5") 0.8000 Kg 18,000.00 14,400.00 18,000.00 14,400.00 18,000.00 14,400.00
L.008 Pekerja 6.0000 OH 27,000.00 162,000.00 27,000.00 162,000.00 24,500.00 147,000.00
L.002 Tukang Kayu 18.0000 OH 32,500.00 585,000.00 32,500.00 585,000.00 29,000.00 522,000.00
L.007 Kepala Tukang 1.2000 OH 35,000.00 42,000.00 35,000.00 42,000.00 31,500.00 37,800.00
L.010 Mandor 0.2000 OH 35,000.00 7,000.00 35,000.00 7,000.00 31,500.00 6,300.00
Pas. Rangka Atap diketam halus dan di propil
SNI - F.6.27c M3 SNIF.6.27c 28,625,400.00 SN2F.6.27c 28,722,900.00 SNSF.6.27c 28,542,500.00
Kayu Jati (Kw.Eksport) uk. Bukan Khusus
Kayu Jati Balok (Kw. Eksport) uk.bukan
M.005f3 1.1000 M3 25,000,000.00 27,500,000.00 25,075,000.00 27,582,500.00 25,000,000.00 27,500,000.00
Khusus
M.003d Begel 15.0000 Kg 21,000.00 315,000.00 22,000.00 330,000.00 21,000.00 315,000.00
M.006 Paku Biasa ( 2" - 5") 0.8000 Kg 18,000.00 14,400.00 18,000.00 14,400.00 18,000.00 14,400.00
L.008 Pekerja 6.0000 OH 27,000.00 162,000.00 27,000.00 162,000.00 24,500.00 147,000.00
L.002 Tukang Kayu 18.0000 OH 32,500.00 585,000.00 32,500.00 585,000.00 29,000.00 522,000.00
L.007 Kepala Tukang 1.2000 OH 35,000.00 42,000.00 35,000.00 42,000.00 31,500.00 37,800.00
L.010 Mandor 0.2000 OH 35,000.00 7,000.00 35,000.00 7,000.00 31,500.00 6,300.00
SNI - F.6.28 Pas. Konstruksi Kuda-kuda Kayu Kamper M3 SNIF.6.28 9,235,300.00 SN2F.6.28 9,332,800.00 SNSF.6.28 9,178,400.00
M.005e Kayu Kamper Balok 1.1000 M3 7,599,000.00 8,358,900.00 7,674,000.00 8,441,400.00 7,599,000.00 8,358,900.00
M.003d Begel 15.0000 Kg 21,000.00 315,000.00 22,000.00 330,000.00 21,000.00 315,000.00
M.006 Paku Biasa ( 2" - 5") 0.8000 Kg 18,000.00 14,400.00 18,000.00 14,400.00 18,000.00 14,400.00
L.008 Pekerja 4.0000 OH 27,000.00 108,000.00 27,000.00 108,000.00 24,500.00 98,000.00
L.002 Tukang Kayu 12.0000 OH 32,500.00 390,000.00 32,500.00 390,000.00 29,000.00 348,000.00
L.007 Kepala Tukang 1.2000 OH 35,000.00 42,000.00 35,000.00 42,000.00 31,500.00 37,800.00
L.010 Mandor 0.2000 OH 35,000.00 7,000.00 35,000.00 7,000.00 31,500.00 6,300.00
SNI - F.6.28a Pas. Konstruksi Kuda-kuda Kayu Bangkir M3 SNIF.6.28a 9,395,900.00 SN2F.6.28a 9,493,400.00 SNSF.6.28a 9,339,000.00
M.005d Kayu Bangkir Balok 1.1000 M3 7,745,000.00 8,519,500.00 7,820,000.00 8,602,000.00 7,745,000.00 8,519,500.00
M.003d Begel 15.0000 Kg 21,000.00 315,000.00 22,000.00 330,000.00 21,000.00 315,000.00
M.006 Paku Biasa ( 2" - 5") 0.8000 Kg 18,000.00 14,400.00 18,000.00 14,400.00 18,000.00 14,400.00
L.008 Pekerja 4.0000 OH 27,000.00 108,000.00 27,000.00 108,000.00 24,500.00 98,000.00
L.002 Tukang Kayu 12.0000 OH 32,500.00 390,000.00 32,500.00 390,000.00 29,000.00 348,000.00
L.007 Kepala Tukang 1.2000 OH 35,000.00 42,000.00 35,000.00 42,000.00 31,500.00 37,800.00
L.010 Mandor 0.2000 OH 35,000.00 7,000.00 35,000.00 7,000.00 31,500.00 6,300.00
Pas. Rk. Atap diketam halus & di propil
SNI - F.6.28b M3 SNIF.6.28b 11,810,400.00 SN2F.6.28b 11,907,900.00 SNSF.6.28b 11,728,200.00
Ky.Bangkir uk. Khusus (30/30 - 12/12 P:5-8m')
M.005d1 Kayu Bangkir Balok uk.Khusus 1.1000 M3 9,720,000.00 10,692,000.00 9,795,000.00 10,774,500.00 9,720,000.00 10,692,000.00
M.003d Begel 15.0000 Kg 21,000.00 315,000.00 22,000.00 330,000.00 21,000.00 315,000.00
M.006 Paku Biasa ( 2" - 5") 0.8000 Kg 18,000.00 14,400.00 18,000.00 14,400.00 18,000.00 14,400.00
L.008 Pekerja 6.0000 OH 27,000.00 162,000.00 27,000.00 162,000.00 24,500.00 147,000.00
L.002 Tukang Kayu 18.0000 OH 32,500.00 585,000.00 32,500.00 585,000.00 29,000.00 522,000.00
L.007 Kepala Tukang 1.2000 OH 35,000.00 42,000.00 35,000.00 42,000.00 31,500.00 37,800.00
L.010 Mandor 0.2000 OH 35,000.00 7,000.00 35,000.00 7,000.00 31,500.00 6,300.00
Pas. Rk. Atap diketam halus & di propil
SNI - F.6.28c M3 SNIF.6.28c 12,482,900.00 SN2F.6.28c 12,580,400.00 SNSF.6.28c 12,400,000.00
Ky.Bangkir uk. Khusus (8/15 - 5/10 P:5-8m')
M.005d2 Kayu Bangkir Balok uk.Khusus 1.1000 M3 10,325,000.00 11,357,500.00 10,400,000.00 11,440,000.00 10,325,000.00 11,357,500.00
M.003d Begel 15.0000 Kg 21,000.00 315,000.00 22,000.00 330,000.00 21,000.00 315,000.00
M.006 Paku Biasa ( 2" - 5") 0.8000 Kg 18,000.00 14,400.00 18,000.00 14,400.00 18,000.00 14,400.00
L.008 Pekerja 6.0000 OH 27,000.00 162,000.00 27,000.00 162,000.00 24,500.00 147,000.00
102 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
L.002 Tukang Kayu 18.0000 OH 32,500.00 585,000.00 32,500.00 585,000.00 29,000.00 522,000.00
L.007 Kepala Tukang 1.2000 OH 35,000.00 42,000.00 35,000.00 42,000.00 31,500.00 37,800.00
L.010 Mandor 0.2000 OH 35,000.00 7,000.00 35,000.00 7,000.00 31,500.00 6,300.00
SNI - F.6.30 Pas. Konstruksi Kuda-kuda Kayu Kruing M3 SNIF.6.30 6,948,400.00 SN2F.6.30 7,045,900.00 SNSF.6.30 6,891,500.00
M.005c Kayu Kruing Balok 1.1000 M3 5,520,000.00 6,072,000.00 5,595,000.00 6,154,500.00 5,520,000.00 6,072,000.00
M.003d Begel 15.0000 Kg 21,000.00 315,000.00 22,000.00 330,000.00 21,000.00 315,000.00
M.006 Paku Biasa ( 2" - 5") 0.8000 Kg 18,000.00 14,400.00 18,000.00 14,400.00 18,000.00 14,400.00
L.008 Pekerja 4.0000 OH 27,000.00 108,000.00 27,000.00 108,000.00 24,500.00 98,000.00
L.002 Tukang Kayu 12.0000 OH 32,500.00 390,000.00 32,500.00 390,000.00 29,000.00 348,000.00
L.007 Kepala Tukang 1.2000 OH 35,000.00 42,000.00 35,000.00 42,000.00 31,500.00 37,800.00
L.010 Mandor 0.2000 OH 35,000.00 7,000.00 35,000.00 7,000.00 31,500.00 6,300.00
Pas. Kaso dan Reng genteng (kodok, plentong,
SNI - F.6.31 M2 SNIF.6.31 78,775.00 SN2F.6.31 79,675.00 SNSF.6.31 78,122.50
vlams dan sejenisnya) Kayu Kamper
M.005j Usuk Kamper 5/7 0.0120 M3 5,800,000.00 69,600.00 5,875,000.00 70,500.00 5,800,000.00 69,600.00
M.006 Paku Biasa ( 2" - 5") 0.1500 Kg 18,000.00 2,700.00 18,000.00 2,700.00 18,000.00 2,700.00
L.008 Pekerja 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.002 Tukang Kayu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
Pas. Kaso dan Reng genteng (kodok, plentong,
SNI - F.6.31a M2 SNIF.6.31a 87,175.00 SN2F.6.31a 88,075.00 SNSF.6.31a 86,522.50
vlams dan sejenisnya) Kayu Bangkir
M.005i Usuk Bangkir 5/7 0.0120 M3 6,500,000.00 78,000.00 6,575,000.00 78,900.00 6,500,000.00 78,000.00
M.006 Paku Biasa ( 2" - 5") 0.1500 Kg 18,000.00 2,700.00 18,000.00 2,700.00 18,000.00 2,700.00
L.008 Pekerja 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.002 Tukang Kayu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
Pas. Kaso dan Reng genteng (kodok, plentong,
SNI - F.6.31b M2 SNIF.6.31b 67,975.00 SN2F.6.31b 68,875.00 SNSF.6.31b 67,322.50
vlams dan sejenisnya) Kayu Kruing
M.005h Usuk Kruing 5/7 0.0120 M3 4,900,000.00 58,800.00 4,975,000.00 59,700.00 4,900,000.00 58,800.00
M.006 Paku Biasa ( 2" - 5") 0.1500 Kg 18,000.00 2,700.00 18,000.00 2,700.00 18,000.00 2,700.00
L.008 Pekerja 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.002 Tukang Kayu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
Pas. Kaso dan Reng genteng (kodok, plentong,
SNI - F.6.31c M2 SNIF.6.31c 55,975.00 SN2F.6.31c 56,875.00 SNSF.6.31c 55,322.50
vlams dan sejenisnya) Kayu Meranti
M.005g Usuk Meranti 5/7 0.0120 M3 3,900,000.00 46,800.00 3,975,000.00 47,700.00 3,900,000.00 46,800.00
M.006 Paku Biasa ( 2" - 5") 0.1500 Kg 18,000.00 2,700.00 18,000.00 2,700.00 18,000.00 2,700.00
L.008 Pekerja 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.002 Tukang Kayu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
SNI - F.6.31d Pas. Kaso dan Reng Kayu Bangkir uk.5/10 M2 SNIF.6.31d 125,815.00 SN2F.6.31d 126,715.00 SNSF.6.31d 125,162.50
M.005d1 Usuk Bangkir 5/10 0.0120 M3 9,720,000.00 116,640.00 9,795,000.00 117,540.00 9,720,000.00 116,640.00
M.006 Paku Biasa ( 2" - 5") 0.1500 Kg 18,000.00 2,700.00 18,000.00 2,700.00 18,000.00 2,700.00
L.008 Pekerja 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.002 Tukang Kayu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
Pas. Kaso dan Reng genteng (monier dan
SNI - F.6.35 M2 SNIF.6.35 90,375.00 SN2F.6.35 91,425.00 SNSF.6.35 89,722.50
sejenisnya) Kayu Kamper
M.005j Usuk Kamper 5/7 0.0140 M3 5,800,000.00 81,200.00 5,875,000.00 82,250.00 5,800,000.00 81,200.00
M.006 Paku Biasa ( 2" - 5") 0.1500 Kg 18,000.00 2,700.00 18,000.00 2,700.00 18,000.00 2,700.00
L.008 Pekerja 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.002 Tukang Kayu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
Pas. Kaso dan Reng genteng (monier dan
SNI - F.6.35a M2 SNIF.6.35a 100,175.00 SN2F.6.35a 101,225.00 SNSF.6.35a 99,522.50
sejenisnya) Kayu Bangkir
M.005i Usuk Bangkir 5/7 0.0140 M3 6,500,000.00 91,000.00 6,575,000.00 92,050.00 6,500,000.00 91,000.00
M.006 Paku Biasa ( 2" - 5") 0.1500 Kg 18,000.00 2,700.00 18,000.00 2,700.00 18,000.00 2,700.00
L.008 Pekerja 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.002 Tukang Kayu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
103 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
Pas. Kaso dan Reng genteng (monier dan
SNI - F.6.35b M2 SNIF.6.35b 77,775.00 SN2F.6.35b 78,825.00 SNSF.6.35b 77,122.50
sejenisnya) Kayu Kruing
M.005h Usuk Kruing 5/7 0.0140 M3 4,900,000.00 68,600.00 4,975,000.00 69,650.00 4,900,000.00 68,600.00
M.006 Paku Biasa ( 2" - 5") 0.1500 Kg 18,000.00 2,700.00 18,000.00 2,700.00 18,000.00 2,700.00
L.008 Pekerja 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.002 Tukang Kayu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
Pas. Usuk 5/10 P : 5 - 8 m Kayu Bangkir diketam
SNI - F.6.35c M3 SNIF.6.35c 12,988,656.00 SN2F.6.35c 13,078,705.00 SNSF.6.35c 12,943,621.00
halus dan dipropil
M.005d2 Kayu Bangkir Balok Uk.Khusus 1.2000 M3 10,325,000.00 12,390,000.00 10,400,000.00 12,480,000.00 10,325,000.00 12,390,000.00
M.003f Mur, baud 0.1400 M3 20,650.00 2,891.00 21,000.00 2,940.00 20,650.00 2,891.00
M.006 Paku biasa ( 5" ) 0.0800 M3 18,000.00 1,440.00 18,000.00 1,440.00 18,000.00 1,440.00
L.008 Pekerja 6.0000 OH 18,000.00 108,000.00 18,000.00 108,000.00 18,000.00 108,000.00
L.002 Tukang Kayu 18.0000 OH 27,000.00 486,000.00 27,000.00 486,000.00 24,500.00 441,000.00
L.007 Kepala Tukang 0.0100 OH 32,500.00 325.00 32,500.00 325.00 29,000.00 290.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
104 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
Pas. Usuk 5/10 P : 2 - 4 m Kayu Bangkir diketam
SNI - F.6.35d M3 SNIF.6.35d 9,892,656.00 SN2F.6.35d 9,982,705.00 SNSF.6.35d 9,847,621.00
halus dan dipropil
M.005d Kayu Jati Balok 1.2000 M3 7,745,000.00 9,294,000.00 7,820,000.00 9,384,000.00 7,745,000.00 9,294,000.00
M.003f Mur, baud 0.1400 M3 20,650.00 2,891.00 21,000.00 2,940.00 20,650.00 2,891.00
M.006 Paku biasa ( 5" ) 0.0800 M3 18,000.00 1,440.00 18,000.00 1,440.00 18,000.00 1,440.00
L.008 Pekerja 6.0000 OH 18,000.00 108,000.00 18,000.00 108,000.00 18,000.00 108,000.00
L.002 Tukang Kayu 18.0000 OH 27,000.00 486,000.00 27,000.00 486,000.00 24,500.00 441,000.00
L.007 Kepala Tukang 0.0100 OH 32,500.00 325.00 32,500.00 325.00 29,000.00 290.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
Pas. Usuk 5/10 P : 5 - 8 m Kayu Jati diketam halus
SNI - F.6.35e M3 SNIF.6.35e 37,048,831.00 SN2F.6.35e 37,138,880.00 SNSF.6.35e 37,003,778.50
dan dipropil (Kw. Eksport)
M.005f2 Kayu Jati Balok Uk.Khusus (Kw. Eksport) 1.2000 M3 30,375,000.00 36,450,000.00 30,450,000.00 36,540,000.00 30,375,000.00 36,450,000.00
M.003f Mur, baud 0.1400 M3 20,650.00 2,891.00 21,000.00 2,940.00 20,650.00 2,891.00
M.006 Paku biasa ( 5" ) 0.0800 M3 18,000.00 1,440.00 18,000.00 1,440.00 18,000.00 1,440.00
L.008 Pekerja 6.0000 OH 18,000.00 108,000.00 18,000.00 108,000.00 18,000.00 108,000.00
L.002 Tukang Kayu 18.0000 OH 27,000.00 486,000.00 27,000.00 486,000.00 24,500.00 441,000.00
L.007 Kepala Tukang 0.0100 OH 32,500.00 325.00 32,500.00 325.00 29,000.00 290.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
Pas. Usuk 5/10 P : 2 - 4 m Kayu Jati diketam halus
SNI - F.6.35f M3 SNIF.6.35f 30,598,831.00 SN2F.6.35f 30,688,880.00 SNSF.6.35f 30,553,778.50
dan dipropil (Kw. Eksport)
M.005f3 Kayu Jati Balok Uk.Khusus (Kw. Eksport) 1.2000 M3 25,000,000.00 30,000,000.00 25,075,000.00 30,090,000.00 25,000,000.00 30,000,000.00
M.003f Mur, baud 0.1400 M3 20,650.00 2,891.00 21,000.00 2,940.00 20,650.00 2,891.00
M.006 Paku biasa ( 5" ) 0.0800 M3 18,000.00 1,440.00 18,000.00 1,440.00 18,000.00 1,440.00
L.008 Pekerja 6.0000 OH 18,000.00 108,000.00 18,000.00 108,000.00 18,000.00 108,000.00
L.002 Tukang Kayu 18.0000 OH 27,000.00 486,000.00 27,000.00 486,000.00 24,500.00 441,000.00
L.007 Kepala Tukang 0.0100 OH 32,500.00 325.00 32,500.00 325.00 29,000.00 290.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
SNI - F.6.38 Pas. Rangka langit-langit Kayu Jati Uk. 1 x 1 m M2 SNIF.6.38 136,275.00 SN2F.6.38 137,175.00 SNSF.6.38 134,675.00
M.005k Usuk Jati 5/7 0.0120 M3 9,900,000.00 118,800.00 9,975,000.00 119,700.00 9,900,000.00 118,800.00
M.006 Paku Biasa ( 2" - 5") 0.1000 Kg 18,000.00 1,800.00 18,000.00 1,800.00 18,000.00 1,800.00
L.008 Pekerja 0.1500 OH 27,000.00 4,050.00 27,000.00 4,050.00 24,500.00 3,675.00
L.002 Tukang Kayu 0.2500 OH 32,500.00 8,125.00 32,500.00 8,125.00 29,000.00 7,250.00
L.007 Kepala Tukang 0.0250 OH 35,000.00 875.00 35,000.00 875.00 31,500.00 787.50
L.010 Mandor 0.0750 OH 35,000.00 2,625.00 35,000.00 2,625.00 31,500.00 2,362.50
Pas. Lambersering uk. 1/20 Kayu Jati diketam
SNI - F.6.38a M' SNIF.6.38a 402,130.00 SN2F.6.38a 402,880.00 SNSF.6.38a 401,320.00
halus dan dipropil (Kw.Eksport)
M.005p1 Papan Jati (Kw. Eksport) 0.0100 M3 39,300,000.00 393,000.00 39,375,000.00 393,750.00 39,300,000.00 393,000.00
M.006 Paku Biasa ( 1" - 2") 0.0600 Kg 18,000.00 1,080.00 18,000.00 1,080.00 18,000.00 1,080.00
L.008 Pekerja 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.002 Tukang Kayu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0500 OH 35,000.00 1,750.00 35,000.00 1,750.00 31,500.00 1,575.00
Pas. Rangka langit-langit Kayu Kamper Uk. 1 x 1
SNI - F.6.39 M2 SNIF.6.39 87,075.00 SN2F.6.39 87,975.00 SNSF.6.39 85,475.00
m
M.005j Usuk Kamper 5/7 0.0120 M3 5,800,000.00 69,600.00 5,875,000.00 70,500.00 5,800,000.00 69,600.00
M.006 Paku Biasa ( 2" - 5") 0.1000 Kg 18,000.00 1,800.00 18,000.00 1,800.00 18,000.00 1,800.00
L.008 Pekerja 0.1500 OH 27,000.00 4,050.00 27,000.00 4,050.00 24,500.00 3,675.00
L.002 Tukang Kayu 0.2500 OH 32,500.00 8,125.00 32,500.00 8,125.00 29,000.00 7,250.00
L.007 Kepala Tukang 0.0250 OH 35,000.00 875.00 35,000.00 875.00 31,500.00 787.50
L.010 Mandor 0.0750 OH 35,000.00 2,625.00 35,000.00 2,625.00 31,500.00 2,362.50
SNI - F.6.39a Pas. Rangka langit-langit Ky Bangkir Uk. 1x1 m M2 SNIF.6.39a 95,475.00 SN2F.6.39a 96,375.00 SNSF.6.39a 93,875.00
M.005i Usuk Bangkir 5/7 0.0120 M3 6,500,000.00 78,000.00 6,575,000.00 78,900.00 6,500,000.00 78,000.00
M.006 Paku Biasa ( 2" - 5") 0.1000 Kg 18,000.00 1,800.00 18,000.00 1,800.00 18,000.00 1,800.00
L.008 Pekerja 0.1500 OH 27,000.00 4,050.00 27,000.00 4,050.00 24,500.00 3,675.00
L.002 Tukang Kayu 0.2500 OH 32,500.00 8,125.00 32,500.00 8,125.00 29,000.00 7,250.00
L.007 Kepala Tukang 0.0250 OH 35,000.00 875.00 35,000.00 875.00 31,500.00 787.50
L.010 Mandor 0.0750 OH 35,000.00 2,625.00 35,000.00 2,625.00 31,500.00 2,362.50
SNI - F.6.39b Pas. Rangka langit-langit Ky Kruing Uk. 1 x 1 m M2 SNIF.6.39b 76,275.00 SN2F.6.39b 77,175.00 SNSF.6.39b 74,675.00
M.005h Usuk Kruing 5/7 0.0120 M3 4,900,000.00 58,800.00 4,975,000.00 59,700.00 4,900,000.00 58,800.00
M.006 Paku Biasa ( 2" - 5") 0.1000 Kg 18,000.00 1,800.00 18,000.00 1,800.00 18,000.00 1,800.00
L.008 Pekerja 0.1500 OH 27,000.00 4,050.00 27,000.00 4,050.00 24,500.00 3,675.00
L.002 Tukang Kayu 0.2500 OH 32,500.00 8,125.00 32,500.00 8,125.00 29,000.00 7,250.00
L.007 Kepala Tukang 0.0250 OH 35,000.00 875.00 35,000.00 875.00 31,500.00 787.50
L.010 Mandor 0.0750 OH 35,000.00 2,625.00 35,000.00 2,625.00 31,500.00 2,362.50
SNI - F.6.39c Pas. Rangka langit-langit Ky Meranti Uk. 1x1 m M2 SNIF.6.39c 64,275.00 SN2F.6.39c 65,175.00 SNSF.6.39c 62,675.00
M.005g Usuk Meranti 5/7 0.0120 M3 3,900,000.00 46,800.00 3,975,000.00 47,700.00 3,900,000.00 46,800.00
M.006 Paku Biasa ( 2" - 5") 0.1000 Kg 18,000.00 1,800.00 18,000.00 1,800.00 18,000.00 1,800.00
105 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
L.008 Pekerja 0.1500 OH 27,000.00 4,050.00 27,000.00 4,050.00 24,500.00 3,675.00
L.002 Tukang Kayu 0.2500 OH 32,500.00 8,125.00 32,500.00 8,125.00 29,000.00 7,250.00
L.007 Kepala Tukang 0.0250 OH 35,000.00 875.00 35,000.00 875.00 31,500.00 787.50
L.010 Mandor 0.0750 OH 35,000.00 2,625.00 35,000.00 2,625.00 31,500.00 2,362.50
Pas. Lambersering uk. 1/20 Kayu Bangkir diketam
SNI - F.6.39d M' SNIF.6.39d 99,130.00 SN2F.6.39d 99,880.00 SNSF.6.39d 98,320.00
halus dan dipropil
M.005n Papan Bangkir 0.0100 M3 9,000,000.00 90,000.00 9,075,000.00 90,750.00 9,000,000.00 90,000.00
M.006 Paku Biasa ( 1" - 2") 0.0600 Kg 18,000.00 1,080.00 18,000.00 1,080.00 18,000.00 1,080.00
L.008 Pekerja 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.002 Tukang Kayu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0500 OH 35,000.00 1,750.00 35,000.00 1,750.00 31,500.00 1,575.00
Pas. Rangka langit-langit Kayu Kamper Uk. 0.30 x
SNI - F.6.44 M2 SNIF.6.44 179,987.50 SN2F.6.44 182,012.50 SNSF.6.44 177,971.25
0.30 m
M.005j Usuk Kamper 5/7 0.0270 M3 5,800,000.00 156,600.00 5,875,000.00 158,625.00 5,800,000.00 156,600.00
M.006 Paku Biasa ( 2" - 5") 0.2000 Kg 18,000.00 3,600.00 18,000.00 3,600.00 18,000.00 3,600.00
L.008 Pekerja 0.2500 OH 27,000.00 6,750.00 27,000.00 6,750.00 24,500.00 6,125.00
L.002 Tukang Kayu 0.3500 OH 32,500.00 11,375.00 32,500.00 11,375.00 29,000.00 10,150.00
L.007 Kepala Tukang 0.0350 OH 35,000.00 1,225.00 35,000.00 1,225.00 31,500.00 1,102.50
L.010 Mandor 0.0125 OH 35,000.00 437.50 35,000.00 437.50 31,500.00 393.75
Pas. Rangka langit-langit Kayu Bangkir Uk. 0.30 x
SNI - F.6.44a M2 SNIF.6.44a 198,887.50 SN2F.6.44a 200,912.50 SNSF.6.44a 196,871.25
0.30 m
M.005i Usuk Bangkir 5/7 0.0270 M3 6,500,000.00 175,500.00 6,575,000.00 177,525.00 6,500,000.00 175,500.00
M.006 Paku Biasa ( 2" - 5") 0.2000 Kg 18,000.00 3,600.00 18,000.00 3,600.00 18,000.00 3,600.00
L.008 Pekerja 0.2500 OH 27,000.00 6,750.00 27,000.00 6,750.00 24,500.00 6,125.00
L.002 Tukang Kayu 0.3500 OH 32,500.00 11,375.00 32,500.00 11,375.00 29,000.00 10,150.00
L.007 Kepala Tukang 0.0350 OH 35,000.00 1,225.00 35,000.00 1,225.00 31,500.00 1,102.50
L.010 Mandor 0.0125 OH 35,000.00 437.50 35,000.00 437.50 31,500.00 393.75
Pas. Rangka langit-langit Kayu Kruing Uk. 0.30 x
SNI - F.6.44b M2 SNIF.6.44b 155,687.50 SN2F.6.44b 157,712.50 SNSF.6.44b 153,671.25
0.30 m
M.005h Usuk Kruing 5/7 0.0270 M3 4,900,000.00 132,300.00 4,975,000.00 134,325.00 4,900,000.00 132,300.00
M.006 Paku Biasa ( 2" - 5") 0.2000 Kg 18,000.00 3,600.00 18,000.00 3,600.00 18,000.00 3,600.00
L.008 Pekerja 0.2500 OH 27,000.00 6,750.00 27,000.00 6,750.00 24,500.00 6,125.00
L.002 Tukang Kayu 0.3500 OH 32,500.00 11,375.00 32,500.00 11,375.00 29,000.00 10,150.00
L.007 Kepala Tukang 0.0350 OH 35,000.00 1,225.00 35,000.00 1,225.00 31,500.00 1,102.50
L.010 Mandor 0.0125 OH 35,000.00 437.50 35,000.00 437.50 31,500.00 393.75
Pas. Rangka langit-langit Kayu Meranti Uk. 0.30 x
SNI - F.6.44c M2 SNIF.6.44c 128,687.50 SN2F.6.44c 130,712.50 SNSF.6.44c 126,671.25
0.30 m
M.005g Usuk Meranti 5/7 0.0270 M3 3,900,000.00 105,300.00 3,975,000.00 107,325.00 3,900,000.00 105,300.00
M.006 Paku Biasa ( 2" - 5") 0.2000 Kg 18,000.00 3,600.00 18,000.00 3,600.00 18,000.00 3,600.00
L.008 Pekerja 0.2500 OH 27,000.00 6,750.00 27,000.00 6,750.00 24,500.00 6,125.00
L.002 Tukang Kayu 0.3500 OH 32,500.00 11,375.00 32,500.00 11,375.00 29,000.00 10,150.00
L.007 Kepala Tukang 0.0350 OH 35,000.00 1,225.00 35,000.00 1,225.00 31,500.00 1,102.50
L.010 Mandor 0.0125 OH 35,000.00 437.50 35,000.00 437.50 31,500.00 393.75
SNI - F.6.47 Pas. Lisplank Kayu Jati Uk. 3 x 20 cm M' SNIF.6.47 103,310.00 SN2F.6.47 103,850.00 SNSF.6.47 102,255.00
M.005p Papan Jati (lokal) 0.0072 M3 12,800,000.00 92,160.00 12,875,000.00 92,700.00 12,800,000.00 92,160.00
M.006 Paku Biasa ( 2" - 5") 0.0500 Kg 18,000.00 900.00 18,000.00 900.00 18,000.00 900.00
L.008 Pekerja 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.002 Tukang Kayu 0.2000 OH 32,500.00 6,500.00 32,500.00 6,500.00 29,000.00 5,800.00
L.007 Kepala Tukang 0.0250 OH 35,000.00 875.00 35,000.00 875.00 31,500.00 787.50
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
Pas. Lisplank dipropil dan divariasi uk. 3x30
SNI - F.6.47a M' SNIF.6.47 375,280.00 SN2F.6.47 375,955.00 SNSF.6.47 373,170.00
Kayu Jati (Kw.Eksport)
M.005p1 Papan Jati (Kw. Eksport) 0.0090 M3 39,300,000.00 353,700.00 39,375,000.00 354,375.00 39,300,000.00 353,700.00
M.006 Paku Biasa ( 1" - 2") 0.0600 Kg 18,000.00 1,080.00 18,000.00 1,080.00 18,000.00 1,080.00
L.008 Pekerja 0.2000 OH 27,000.00 5,400.00 27,000.00 5,400.00 24,500.00 4,900.00
L.002 Tukang Kayu 0.4000 OH 32,500.00 13,000.00 32,500.00 13,000.00 29,000.00 11,600.00
L.007 Kepala Tukang 0.0500 OH 35,000.00 1,750.00 35,000.00 1,750.00 31,500.00 1,575.00
L.010 Mandor 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
SNI - F.6.48 Pas. Lisplank Kayu Kamper Uk. 3 x 20 cm M' SNIF.6.48 72,175.00 SN2F.6.48 72,715.00 SNSF.6.48 71,137.50
M.005o Papan Kamper 0.0072 M3 8,500,000.00 61,200.00 8,575,000.00 61,740.00 8,500,000.00 61,200.00
M.006 Paku Biasa ( 2" - 5") 0.0500 Kg 18,000.00 900.00 18,000.00 900.00 18,000.00 900.00
L.008 Pekerja 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.002 Tukang Kayu 0.2000 OH 32,500.00 6,500.00 32,500.00 6,500.00 29,000.00 5,800.00
L.007 Kepala Tukang 0.0200 OH 35,000.00 700.00 35,000.00 700.00 31,500.00 630.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
SNI - F.6.48a Pas. Lisplank Kayu Bangkir Uk. 3 x 20 cm M' SNIF.6.48a 75,775.00 SN2F.6.48a 76,315.00 SNSF.6.48a 74,737.50
106 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
M.005n Papan Bangkir 0.0072 M3 9,000,000.00 64,800.00 9,075,000.00 65,340.00 9,000,000.00 64,800.00
M.006 Paku Biasa ( 2" - 5") 0.0500 Kg 18,000.00 900.00 18,000.00 900.00 18,000.00 900.00
L.008 Pekerja 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.002 Tukang Kayu 0.2000 OH 32,500.00 6,500.00 32,500.00 6,500.00 29,000.00 5,800.00
L.007 Kepala Tukang 0.0200 OH 35,000.00 700.00 35,000.00 700.00 31,500.00 630.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
SNI - F.6.48b Pas. Lisplank Kayu Kruing Uk. 3 x 20 cm M' SNIF.6.48b 54,895.00 SN2F.6.48b 55,435.00 SNSF.6.48b 53,857.50
M.005m Papan Kruing 0.0072 M3 6,100,000.00 43,920.00 6,175,000.00 44,460.00 6,100,000.00 43,920.00
M.006 Paku Biasa ( 2" - 5") 0.0500 Kg 18,000.00 900.00 18,000.00 900.00 18,000.00 900.00
L.008 Pekerja 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.002 Tukang Kayu 0.2000 OH 32,500.00 6,500.00 32,500.00 6,500.00 29,000.00 5,800.00
L.007 Kepala Tukang 0.0200 OH 35,000.00 700.00 35,000.00 700.00 31,500.00 630.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
Pas. Lisplank dipropil dan divariasi uk. 3x30
SNI - F.6.48c M' SNIF.6.48c 102,580.00 SN2F.6.48c 103,255.00 SNSF.6.48c 100,470.00
Kayu Bangkir
M.005n Papan Bangkir 0.0090 M3 9,000,000.00 81,000.00 9,075,000.00 81,675.00 9,000,000.00 81,000.00
M.006 Paku Biasa ( 2" - 5") 0.0600 Kg 18,000.00 1,080.00 18,000.00 1,080.00 18,000.00 1,080.00
L.008 Pekerja 0.2000 OH 27,000.00 5,400.00 27,000.00 5,400.00 24,500.00 4,900.00
L.002 Tukang Kayu 0.4000 OH 32,500.00 13,000.00 32,500.00 13,000.00 29,000.00 11,600.00
L.007 Kepala Tukang 0.0500 OH 35,000.00 1,750.00 35,000.00 1,750.00 31,500.00 1,575.00
L.010 Mandor 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
107 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
SNI - F.6.52 Pas. Lisplank Kayu Jati Uk. 2 ( 2 x 20 ) cm M' SNIF.6.52 119,210.00 SN2F.6.52 119,855.00 SNSF.6.52 118,400.00
M.005p Papan Jati (lokal) 0.0086 M3 12,800,000 110,080.00 12,875,000 110,725.00 12,800,000 110,080.00
M.006 Paku Biasa ( 2" - 5") 0.0600 Kg 18,000 1,080.00 18,000 1,080.00 18,000 1,080.00
L.008 Pekerja 0.1000 OH 27,000 2,700.00 27,000 2,700.00 24,500 2,450.00
L.002 Tukang Kayu 0.1000 OH 32,500 3,250.00 32,500 3,250.00 29,000 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000 350.00 35,000 350.00 31,500 315.00
L.010 Mandor 0.0500 OH 35,000 1,750.00 35,000 1,750.00 31,500 1,575.00
SNI - F.6.52a Pas. Lisplank Kayu Kamper Uk. 2 ( 2 x 20 ) cm M' SNIF.6.52a 82,230.00 SN2F.6.52a 82,875.00 SNSF.6.52a 81,420.00
M.005o Papan Kamper 0.0086 M3 8,500,000.00 73,100.00 8,575,000.00 73,745.00 8,500,000.00 73,100.00
M.006 Paku Biasa ( 2" - 5") 0.0600 Kg 18,000.00 1,080.00 18,000.00 1,080.00 18,000.00 1,080.00
L.008 Pekerja 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.002 Tukang Kayu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0500 OH 35,000.00 1,750.00 35,000.00 1,750.00 31,500.00 1,575.00
SNI - F.6.52b Pas. Lisplank Kayu Bangkir Uk. 2 ( 2 x 20 ) cm M' SNIF.6.52b 86,530.00 SN2F.6.52b 87,175.00 SNSF.6.52b 85,720.00
M.005n Papan Bangkir 0.0086 M3 9,000,000.00 77,400.00 9,075,000.00 78,045.00 9,000,000.00 77,400.00
M.006 Paku Biasa ( 2" - 5") 0.0600 Kg 18,000.00 1,080.00 18,000.00 1,080.00 18,000.00 1,080.00
L.008 Pekerja 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.002 Tukang Kayu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0500 OH 35,000.00 1,750.00 35,000.00 1,750.00 31,500.00 1,575.00
SNI - F.6.52c Pas. Lisplank Kayu Kruing Uk. 2 ( 2 x 20 ) cm M' SNIF.6.52c 61,590.00 SN2F.6.52c 62,235.00 SNSF.6.52c 60,780.00
M.005m Papan Kruing 0.0086 M3 6,100,000.00 52,460.00 6,175,000.00 53,105.00 6,100,000.00 52,460.00
M.006 Paku Biasa ( 2" - 5") 0.0600 Kg 18,000.00 1,080.00 18,000.00 1,080.00 18,000.00 1,080.00
L.008 Pekerja 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.002 Tukang Kayu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0500 OH 35,000.00 1,750.00 35,000.00 1,750.00 31,500.00 1,575.00
SNI - F.6.52d Pas. Lisplank Kayu Jati Uk. 2 ( 2 x 20 ) cm M' SNIF.6.52d 119,210.00 SN2F.6.52d 119,855.00 SNSF.6.52d 118,400.00
M.005p Papan Jati (lokal) 0.0086 M3 12,800,000 110,080.00 12,875,000 110,725.00 12,800,000 110,080.00
M.006 Paku Biasa ( 2" - 5") 0.0600 Kg 18,000 1,080.00 18,000 1,080.00 18,000 1,080.00
L.008 Pekerja 0.1000 OH 27,000 2,700.00 27,000 2,700.00 24,500 2,450.00
L.002 Tukang Kayu 0.1000 OH 32,500 3,250.00 32,500 3,250.00 29,000 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000 350.00 35,000 350.00 31,500 315.00
L.010 Mandor 0.0500 OH 35,000 1,750.00 35,000 1,750.00 31,500 1,575.00
G. PEKERJAAN BETON

SNI - G.6.1 Membuat Beton Tumbuk 1 PC : 3 Ps : 5 Kr M3 SNIG.6.1 487,850.00 SN2G.6.1 501,976.00 SNSG.6.1 482,482.50
M.002a Portland Cement 218.00 Kg 1,200.00 261,600.00 1,207.00 263,126.00 1,200.00 261,600.00
M.001 Pasir Beton 0.5200 M3 92,500.00 48,100.00 100,000.00 52,000.00 92,500.00 48,100.00
M.001g Koral Beton ( Batu pecah 2/3 cm ) 0.8700 M3 140,000.00 121,800.00 150,000.00 130,500.00 140,000.00 121,800.00
L.008 Pekerja 1.6500 OH 27,000.00 44,550.00 27,000.00 44,550.00 24,500.00 40,425.00
L.001 Tukang Batu 0.2500 OH 32,500.00 8,125.00 32,500.00 8,125.00 29,000.00 7,250.00
L.007 Kepala Tukang 0.0250 OH 35,000.00 875.00 35,000.00 875.00 31,500.00 787.50
L.010 Mandor 0.0800 OH 35,000.00 2,800.00 35,000.00 2,800.00 31,500.00 2,520.00
Membuat Lantai Kerja Beton Tumbuk 1 PC : 3 Ps :
SNI - G.6.4 M3 SNIG.6.4 52,545.00 SN2G.6.4 53,250.00 SNSG.6.4 49,572.00
5 Kr tb. 5 cm
M.002a Portland Cement 10.0000 Kg 1,200.00 12,000.00 1,207.00 12,070.00 1,200.00 12,000.00
M.001 Pasir Beton 0.0260 M3 92,500.00 2,405.00 100,000.00 2,600.00 92,500.00 2,405.00
M.001g Koral Beton ( Batu pecah 2/3 cm ) 0.0440 M3 140,000.00 6,160.00 150,000.00 6,600.00 140,000.00 6,160.00
L.008 Pekerja 1.1500 OH 27,000.00 31,050.00 27,000.00 31,050.00 24,500.00 28,175.00
L.001 Tukang Batu 0.0200 OH 32,500.00 650.00 32,500.00 650.00 29,000.00 580.00
L.007 Kepala Tukang 0.0020 OH 35,000.00 70.00 35,000.00 70.00 31,500.00 63.00
L.010 Mandor 0.0060 OH 35,000.00 210.00 35,000.00 210.00 31,500.00 189.00
SNI - G.6.7 Membuat Beton Cor 1 PC : 2 Ps : 2,5 Kr M3 SNIG.6.7 628,550.00 SN2G.6.7 642,214.00 SNSG.6.7 623,182.50
M.002a Portland Cement 352.00 Kg 1,200.00 422,400.00 1,207.00 424,864.00 1,200.00 422,400.00
M.001 Pasir Beton 0.5600 M3 92,500.00 51,800.00 100,000.00 56,000.00 92,500.00 51,800.00
M.001g Koral Beton ( Batu pecah 2/3 cm ) 0.7000 M3 140,000.00 98,000.00 150,000.00 105,000.00 140,000.00 98,000.00
L.008 Pekerja 1.6500 OH 27,000.00 44,550.00 27,000.00 44,550.00 24,500.00 40,425.00
L.001 Tukang Batu 0.2500 OH 32,500.00 8,125.00 32,500.00 8,125.00 29,000.00 7,250.00
L.007 Kepala Tukang 0.0250 OH 35,000.00 875.00 35,000.00 875.00 31,500.00 787.50
L.010 Mandor 0.0800 OH 35,000.00 2,800.00 35,000.00 2,800.00 31,500.00 2,520.00
108 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
SNI - G.6.13 Membuat Beton Cor 1 PC : 2 Ps : 3 Kr M3 SNIG.6.13 668,150.00 SN2G.6.13 682,652.00 SNSG.6.13 658,302.50
M.002a Portland Cement 336.00 Kg 1,200.00 403,200.00 1,207.00 405,552.00 1,200.00 403,200.00
M.001 Pasir Beton 0.5400 M3 92,500.00 49,950.00 100,000.00 54,000.00 92,500.00 49,950.00
M.001g Koral Beton ( Batu pecah 2/3 cm ) 0.8100 M3 140,000.00 113,400.00 150,000.00 121,500.00 140,000.00 113,400.00
L.008 Pekerja 2.0000 OH 27,000.00 54,000.00 27,000.00 54,000.00 24,500.00 49,000.00
L.001 Tukang Batu 0.3500 OH 32,500.00 11,375.00 32,500.00 11,375.00 29,000.00 10,150.00
L.007 Kepala Tukang 0.0350 OH 35,000.00 1,225.00 35,000.00 1,225.00 31,500.00 1,102.50
L.010 Mandor 1.0000 OH 35,000.00 35,000.00 35,000.00 35,000.00 31,500.00 31,500.00
109 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
SNI - G.6.25 Pembesian dengan Besi Beton Polos (sek.KS) Kg SNIG.6.25 16,461.00 SN2G.6.25 17,526.00 SNSG.6.25 16,415.50
M.003 Besi Beton Polos 1.0500 Kg 15,000.00 15,750.00 16,000.00 16,800.00 15,000.00 15,750.00
M.003a Kawat Beton ( Bindrat ) 0.0150 Kg 17,300.00 259.50 18,300.00 274.50 17,300.00 259.50
L.008 Pekerja 0.0070 OH 27,000.00 189.00 27,000.00 189.00 24,500.00 171.50
L.003 Tukang Besi 0.0070 OH 32,500.00 227.50 32,500.00 227.50 29,000.00 203.00
L.007 Kepala Tukang 0.0007 OH 35,000.00 24.50 35,000.00 24.50 31,500.00 22.05
L.010 Mandor 0.0003 OH 35,000.00 10.50 35,000.00 10.50 31,500.00 9.45
SNI - G.6.25a Pembesian dengan Besi Beton Ulir Kg SNIG.6.25a 16,461.00 SN2G.6.25a 17,526.00 SNSG.6.25a 16,415.50
M.003c Besi Beton Ulir 1.0500 Kg 15,000.00 15,750.00 16,000.00 16,800.00 15,000.00 15,750.00
M.003a Kawat Beton ( Bindrat ) 0.0150 Kg 17,300.00 259.50 18,300.00 274.50 17,300.00 259.50
L.008 Pekerja 0.0070 OH 27,000.00 189.00 27,000.00 189.00 24,500.00 171.50
L.003 Tukang Besi 0.0070 OH 32,500.00 227.50 32,500.00 227.50 29,000.00 203.00
L.007 Kepala Tukang 0.0007 OH 35,000.00 24.50 35,000.00 24.50 31,500.00 22.05
L.010 Mandor 0.0003 OH 35,000.00 10.50 35,000.00 10.50 31,500.00 9.45
Pembesian dengan Besi Beton Polos (sek.Non
SNI - G.6.25b Kg SNIG.6.25 15,411.00 SN2G.6.25 16,476.00 SNSG.6.25 15,365.50
KS)
M.003.1 Besi Beton Polos 1.0500 Kg 14,000.00 14,700.00 15,000.00 15,750.00 14,000.00 14,700.00
M.003a Kawat Beton ( Bindrat ) 0.0150 Kg 17,300.00 259.50 18,300.00 274.50 17,300.00 259.50
L.008 Pekerja 0.0070 OH 27,000.00 189.00 27,000.00 189.00 24,500.00 171.50
L.003 Tukang Besi 0.0070 OH 32,500.00 227.50 32,500.00 227.50 29,000.00 203.00
L.007 Kepala Tukang 0.0007 OH 35,000.00 24.50 35,000.00 24.50 31,500.00 22.05
L.010 Mandor 0.0003 OH 35,000.00 10.50 35,000.00 10.50 31,500.00 9.45
SNI - G.6.28 Pas. Bekisting untuk Pondasi M2 SNIG.6.28 77,035.00 SN2G.6.28 79,035.00 SNSG.6.28 75,266.50
M.005a Kayu Tahun 0.0400 M3 1,350,000.00 54,000.00 1,400,000.00 56,000.00 1,350,000.00 54,000.00
M.006 Paku Biasa (2" - 5") 0.3000 Kg 18,000.00 5,400.00 18,000.00 5,400.00 18,000.00 5,400.00
L.008 Pekerja 0.3000 OH 27,000.00 8,100.00 27,000.00 8,100.00 24,500.00 7,350.00
L.002 Tukang Kayu 0.2600 OH 32,500.00 8,450.00 32,500.00 8,450.00 29,000.00 7,540.00
L.007 Kepala Tukang 0.0260 OH 35,000.00 910.00 35,000.00 910.00 31,500.00 819.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
SNI - G.6.29 Pas. Bekisting untuk Sloof M2 SNIG.6.29 83,785.00 SN2G.6.29 86,035.00 SNSG.6.29 82,016.50
M.005a Kayu Tahun 0.0450 M3 1,350,000.00 60,750.00 1,400,000.00 63,000.00 1,350,000.00 60,750.00
M.006 Paku Biasa (2" - 5") 0.3000 Kg 18,000.00 5,400.00 18,000.00 5,400.00 18,000.00 5,400.00
L.008 Pekerja 0.3000 OH 27,000.00 8,100.00 27,000.00 8,100.00 24,500.00 7,350.00
L.002 Tukang Kayu 0.2600 OH 32,500.00 8,450.00 32,500.00 8,450.00 29,000.00 7,540.00
L.007 Kepala Tukang 0.0260 OH 35,000.00 910.00 35,000.00 910.00 31,500.00 819.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
SNI - G.6.30 Pas. Bekisting untuk Kolom M2 SNIG.6.30 248,890.00 SN2G.6.30 263,065.00 SNSG.6.30 246,848.50
M.005a Kayu Tahun 0.0400 M3 1,350,000.00 54,000.00 1,400,000.00 56,000.00 1,350,000.00 54,000.00
M.006 Paku Biasa (2" - 5") 0.4000 Kg 18,000.00 7,200.00 18,000.00 7,200.00 18,000.00 7,200.00
M.005g Usuk Meranti 5/7 0.0150 M3 3,900,000.00 58,500.00 3,975,000.00 59,625.00 3,900,000.00 58,500.00
M.009c Multiplek 9mm 0.3500 Lbr 140,000.00 49,000.00 143,000.00 50,050.00 140,000.00 49,000.00
M.005s Dolken kayu galam diam.8-10/4m 2.0000 Btg 30,000.00 60,000.00 35,000.00 70,000.00 30,000.00 60,000.00
L.008 Pekerja 0.3000 OH 27,000.00 8,100.00 27,000.00 8,100.00 24,500.00 7,350.00
L.002 Tukang Kayu 0.3300 OH 32,500.00 10,725.00 32,500.00 10,725.00 29,000.00 9,570.00
L.007 Kepala Tukang 0.0330 OH 35,000.00 1,155.00 35,000.00 1,155.00 31,500.00 1,039.50
L.010 Mandor 0.0060 OH 35,000.00 210.00 35,000.00 210.00 31,500.00 189.00
SNI - G.6.31 Pas. Bekisting untuk Balok M2 SNIG.6.31 261,130.00 SN2G.6.31 275,530.00 SNSG.6.31 259,038.50
M.005a Kayu Tahun 0.0400 M3 1,350,000.00 54,000.00 1,400,000.00 56,000.00 1,350,000.00 54,000.00
M.006 Paku Biasa (2" - 5") 0.4000 Kg 18,000.00 7,200.00 18,000.00 7,200.00 18,000.00 7,200.00
M.005g Usuk Meranti 5/7 0.0180 M3 3,900,000.00 70,200.00 3,975,000.00 71,550.00 3,900,000.00 70,200.00
M.009c Multiplek 9mm 0.3500 Lbr 140,000.00 49,000.00 143,000.00 50,050.00 140,000.00 49,000.00
M.005s Dolken kayu galam diam.8-10/4m 2.0000 Btg 30,000.00 60,000.00 35,000.00 70,000.00 30,000.00 60,000.00
L.008 Pekerja 0.3200 OH 27,000.00 8,640.00 27,000.00 8,640.00 24,500.00 7,840.00
L.002 Tukang Kayu 0.3300 OH 32,500.00 10,725.00 32,500.00 10,725.00 29,000.00 9,570.00
L.007 Kepala Tukang 0.0330 OH 35,000.00 1,155.00 35,000.00 1,155.00 31,500.00 1,039.50
L.010 Mandor 0.0060 OH 35,000.00 210.00 35,000.00 210.00 31,500.00 189.00
SNI - G.6.32 Pas. Bekisting untuk Lantai M2 SNIG.6.32 369,430.00 SN2G.6.32 403,605.00 SNSG.6.32 367,338.50
M.005a Kayu Tahun 0.0400 M3 1,350,000.00 54,000.00 1,400,000.00 56,000.00 1,350,000.00 54,000.00
M.006 Paku Biasa (2" - 5") 0.4000 Kg 18,000.00 7,200.00 18,000.00 7,200.00 18,000.00 7,200.00
M.005g Usuk Meranti 5/7 0.0150 M3 3,900,000.00 58,500.00 3,975,000.00 59,625.00 3,900,000.00 58,500.00
M.009c Multiplek 9mm 0.3500 Lbr 140,000.00 49,000.00 143,000.00 50,050.00 140,000.00 49,000.00
M.005s Dolken kayu galam diam.8-10/4m 6.0000 Btg 30,000.00 180,000.00 35,000.00 210,000.00 30,000.00 180,000.00
L.008 Pekerja 0.3200 OH 27,000.00 8,640.00 27,000.00 8,640.00 24,500.00 7,840.00
110 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
L.002 Tukang Kayu 0.3300 OH 32,500.00 10,725.00 32,500.00 10,725.00 29,000.00 9,570.00
L.007 Kepala Tukang 0.0330 OH 35,000.00 1,155.00 35,000.00 1,155.00 31,500.00 1,039.50
L.010 Mandor 0.0060 OH 35,000.00 210.00 35,000.00 210.00 31,500.00 189.00
SNI - G.6.33 Pas. Bekisting untuk Dinding M2 SNIG.6.33 355,430.00 SN2G.6.33 376,480.00 SNSG.6.33 353,338.50
M.005a Kayu Tahun 0.0300 M3 1,350,000.00 40,500.00 1,400,000.00 42,000.00 1,350,000.00 40,500.00
M.006 Paku Biasa (2" - 5") 0.4000 Kg 18,000.00 7,200.00 18,000.00 7,200.00 18,000.00 7,200.00
M.005g Usuk Meranti 5/7 0.0200 M3 3,900,000.00 78,000.00 3,975,000.00 79,500.00 3,900,000.00 78,000.00
M.009c Multiplek 9mm 0.3500 Lbr 140,000.00 49,000.00 143,000.00 50,050.00 140,000.00 49,000.00
M.005s Dolken kayu galam diam.8-10/4m 3.0000 Btg 30,000.00 90,000.00 35,000.00 105,000.00 30,000.00 90,000.00
M.005t Formite/Penjaga Jarak Bekisting/Spacer 4.0000 Btg 17,500.00 70,000.00 18,000.00 72,000.00 17,500.00 70,000.00
L.008 Pekerja 0.3200 OH 27,000.00 8,640.00 27,000.00 8,640.00 24,500.00 7,840.00
L.002 Tukang Kayu 0.3300 OH 32,500.00 10,725.00 32,500.00 10,725.00 29,000.00 9,570.00
L.007 Kepala Tukang 0.0330 OH 35,000.00 1,155.00 35,000.00 1,155.00 31,500.00 1,039.50
L.010 Mandor 0.0060 OH 35,000.00 210.00 35,000.00 210.00 31,500.00 189.00
111 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
SNI - G.6.34 Pas. Bekisting untuk Tangga M2 SNIG.6.34 235,930.00 SN2G.6.34 249,605.00 SNSG.6.34 233,838.50
M.005a Kayu Tahun 0.0300 M3 1,350,000.00 40,500.00 1,400,000.00 42,000.00 1,350,000.00 40,500.00
M.006 Paku Biasa (2" - 5") 0.4000 Kg 18,000.00 7,200.00 18,000.00 7,200.00 18,000.00 7,200.00
M.005g Kayu Meranti ( Balok ) 0.0150 M3 3,900,000.00 58,500.00 3,975,000.00 59,625.00 3,900,000.00 58,500.00
M.009c Plywood 9mm 0.3500 Lbr 140,000.00 49,000.00 143,000.00 50,050.00 140,000.00 49,000.00
M.005s Dolken kayu galam diam.8-10/4m 2.0000 Btg 30,000.00 60,000.00 35,000.00 70,000.00 30,000.00 60,000.00
L.008 Pekerja 0.3200 OH 27,000.00 8,640.00 27,000.00 8,640.00 24,500.00 7,840.00
L.002 Tukang Kayu 0.3300 OH 32,500.00 10,725.00 32,500.00 10,725.00 29,000.00 9,570.00
L.007 Kepala Tukang 0.0330 OH 35,000.00 1,155.00 35,000.00 1,155.00 31,500.00 1,039.50
L.010 Mandor 0.0060 OH 35,000.00 210.00 35,000.00 210.00 31,500.00 189.00
Membuat Kolom Penguat Beton Bertulang ( 11 x
SNI - G.6.45 M' SNIG.6.45 66,165.00 SN2G.6.45 69,878.00 SNSG.6.45 65,773.50
11 ) cm
M.005a Kayu Tahun 0.0020 M3 1,350,000.00 2,700.00 1,400,000.00 2,800.00 1,350,000.00 2,700.00
M.006 Paku Biasa (2" - 5") 0.0100 Kg 18,000.00 180.00 18,000.00 180.00 18,000.00 180.00
M.003 Besi Beton Polos 3.0000 Kg 15,000.00 45,000.00 16,000.00 48,000.00 15,000.00 45,000.00
M.003a Kawat Beton ( Bindrat ) 0.4500 Kg 17,300.00 7,785.00 18,300.00 8,235.00 17,300.00 7,785.00
M.002a Portland Cement 4.0000 Kg 1,200.00 4,800.00 1,207.00 4,828.00 1,200.00 4,800.00
M.001 Pasir Beton 0.0060 M3 92,500.00 555.00 100,000.00 600.00 92,500.00 555.00
M.001g Koral Beton ( Batu Pecah 2/3 ) 0.0090 M3 140,000.00 1,260.00 150,000.00 1,350.00 140,000.00 1,260.00
L.008 Pekerja 0.0600 OH 27,000.00 1,620.00 27,000.00 1,620.00 24,500.00 1,470.00
L.001 Tukang Batu 0.0200 OH 32,500.00 650.00 32,500.00 650.00 29,000.00 580.00
L.002 Tukang Kayu 0.0200 OH 32,500.00 650.00 32,500.00 650.00 29,000.00 580.00
L.003 Tukang Besi 0.0200 OH 32,500.00 650.00 32,500.00 650.00 29,000.00 580.00
L.007 Kepala Tukang 0.0060 OH 35,000.00 210.00 35,000.00 210.00 31,500.00 189.00
L.010 Mandor 0.0030 OH 35,000.00 105.00 35,000.00 105.00 31,500.00 94.50
SNI - G.6.46 Membuat Ring Balok Beton ( 10 x 15 ) cm M' SNIG.6.46 75,250.00 SN2G.6.46 79,306.00 SNSG.6.46 74,601.00
M.005a Kayu Tahun 0.0030 M3 1,350,000.00 4,050.00 1,400,000.00 4,200.00 1,350,000.00 4,050.00
M.006 Paku Biasa (2" - 5") 0.0200 Kg 18,000.00 360.00 18,000.00 360.00 18,000.00 360.00
M.003 Besi Beton Polos 3.6000 Kg 15,000.00 54,000.00 16,000.00 57,600.00 15,000.00 54,000.00
M.003a Kawat Beton ( Bindrat ) 0.0500 Kg 17,300.00 865.00 18,300.00 915.00 17,300.00 865.00
M.002a Portland Cement 5.5000 Kg 1,200.00 6,600.00 1,207.00 6,638.50 1,200.00 6,600.00
M.001 Pasir Beton 0.0090 M3 92,500.00 832.50 100,000.00 900.00 92,500.00 832.50
M.001g Koral Beton ( Batu Pecah 2/3 ) 0.0150 M3 140,000.00 2,100.00 150,000.00 2,250.00 140,000.00 2,100.00
L.008 Pekerja 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.001 Tukang Batu 0.0330 OH 32,500.00 1,072.50 32,500.00 1,072.50 29,000.00 957.00
L.002 Tukang Kayu 0.0330 OH 32,500.00 1,072.50 32,500.00 1,072.50 29,000.00 957.00
L.003 Tukang Besi 0.0330 OH 32,500.00 1,072.50 32,500.00 1,072.50 29,000.00 957.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
H. PEKERJAAN ATAP

SNI - H.6.1 Pas. Atap Genteng Plentong Kecil M2 SNIH.6.1 34,297.50 SN2H.6.1 35,547.50 SNSH.6.1 33,604.00
M.010a Genteng plentong 25.0000 Bh 1,090.00 27,250.00 1,140.00 28,500.00 1,090.00 27,250.00
L.008 Pekerja 0.1500 OH 27,000.00 4,050.00 27,000.00 4,050.00 24,500.00 3,675.00
L.002 Tukang Kayu 0.0750 OH 32,500.00 2,437.50 32,500.00 2,437.50 29,000.00 2,175.00
L.007 Kepala Tukang 0.0080 OH 35,000.00 280.00 35,000.00 280.00 31,500.00 252.00
L.010 Mandor 0.0080 OH 35,000.00 280.00 35,000.00 280.00 31,500.00 252.00
Pasang Atap Genteng Keramik Glazur sek. M
M2 SNIH.6.1 73,287.50 SN2H.6.1 22,779.50 SNSH.6.1 21,396.00
Class
Genteng Keramik Glazur 13.8000 Bh 4,800.00 66,240.00 1,140.00 15,732.00 1,090.00 15,042.00
L.008 Pekerja 0.1500 OH 27,000.00 4,050.00 27,000.00 4,050.00 24,500.00 3,675.00
L.002 Tukang Kayu 0.0750 OH 32,500.00 2,437.50 32,500.00 2,437.50 29,000.00 2,175.00
L.007 Kepala Tukang 0.0080 OH 35,000.00 280.00 35,000.00 280.00 31,500.00 252.00
L.010 Mandor 0.0080 OH 35,000.00 280.00 35,000.00 280.00 31,500.00 252.00

SNI - H.6.2 Pas. Atap Genteng Kodok M2 SNIH.6.2 39,547.50 SN2H.6.2 40,797.50 SNSH.6.2 38,854.00
M.010b Genteng Kodok 25.0000 Bh 1,300.00 32,500.00 1,350.00 33,750.00 1,300.00 32,500.00
L.008 Pekerja 0.1500 OH 27,000.00 4,050.00 27,000.00 4,050.00 24,500.00 3,675.00
L.002 Tukang Kayu 0.0750 OH 32,500.00 2,437.50 32,500.00 2,437.50 29,000.00 2,175.00
L.007 Kepala Tukang 0.0080 OH 35,000.00 280.00 35,000.00 280.00 31,500.00 252.00
L.010 Mandor 0.0080 OH 35,000.00 280.00 35,000.00 280.00 31,500.00 252.00
Pas. Atap Genteng Nok Keramik Glazur sek. M
M' SNIH.6.4 89,890.00 SN2H.6.4 40,311.00 SNSH.6.4 37,363.00
Class
M.010c Genteng Nok Keramik 3.5000 Bh 17,000.00 59,500.00 2,750.00 9,625.00 2,500.00 8,750.00
M.002a Portland Cement 8.0000 Kg 1,200.00 9,600.00 1,207.00 9,656.00 1,200.00 9,600.00
M.001a Pasir Pasang 0.0320 M3 85,000.00 2,720.00 92,500.00 2,960.00 85,000.00 2,720.00
L.008 Pekerja 0.4000 OH 27,000.00 10,800.00 27,000.00 10,800.00 24,500.00 9,800.00
112 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
L.002 Tukang Kayu 0.2000 OH 32,500.00 6,500.00 32,500.00 6,500.00 29,000.00 5,800.00
L.007 Kepala Tukang 0.0200 OH 35,000.00 700.00 35,000.00 700.00 31,500.00 630.00
L.010 Mandor 0.0020 OH 35,000.00 70.00 35,000.00 70.00 31,500.00 63.00
SNI - H.6.4 Pas. Atap Genteng Bubung Plentong M' SNIH.6.4 42,890.00 SN2H.6.4 44,436.00 SNSH.6.4 41,113.00
M.010c Genteng Bubung Plentong/Kodok 5.0000 Bh 2,500.00 12,500.00 2,750.00 13,750.00 2,500.00 12,500.00
M.002a Portland Cement 8.0000 Kg 1,200.00 9,600.00 1,207.00 9,656.00 1,200.00 9,600.00
M.001a Pasir Pasang 0.0320 M3 85,000.00 2,720.00 92,500.00 2,960.00 85,000.00 2,720.00
L.008 Pekerja 0.4000 OH 27,000.00 10,800.00 27,000.00 10,800.00 24,500.00 9,800.00
L.002 Tukang Kayu 0.2000 OH 32,500.00 6,500.00 32,500.00 6,500.00 29,000.00 5,800.00
L.007 Kepala Tukang 0.0200 OH 35,000.00 700.00 35,000.00 700.00 31,500.00 630.00
L.010 Mandor 0.0020 OH 35,000.00 70.00 35,000.00 70.00 31,500.00 63.00
Pas. Atap fiber semen Gelombang Uk. ( 3,00 x
SNI - H.6.12 M2 SNIH.6.12 39,655.00 SN2H.6.12 40,005.00 SNSH.6.12 39,011.00
1,05 m ) x 4mm
M.010o Asbes Gelombang 0.3500 Lbr 85,000.00 29,750.00 86,000.00 30,100.00 85,000.00 29,750.00
M.006b Paku Kait 0.1200 Kg 28,000.00 3,360.00 28,000.00 3,360.00 28,000.00 3,360.00
L.008 Pekerja 0.1400 OH 27,000.00 3,780.00 27,000.00 3,780.00 24,500.00 3,430.00
L.002 Tukang Kayu 0.0700 OH 32,500.00 2,275.00 32,500.00 2,275.00 29,000.00 2,030.00
L.007 Kepala Tukang 0.0070 OH 35,000.00 245.00 35,000.00 245.00 31,500.00 220.50
L.010 Mandor 0.0070 OH 35,000.00 245.00 35,000.00 245.00 31,500.00 220.50
Pas. Atap fiber semen Gelombang Uk. ( 2,70 x
SNI - H.6.13 M2 SNIH.6.13 42,245.00 SN2H.6.13 42,665.00 SNSH.6.13 41,601.00
1,05 m ) x 4mm
M.010p Asbes Gelombang 0.4200 Lbr 77,000.00 32,340.00 78,000.00 32,760.00 77,000.00 32,340.00
M.006b Paku Kait 0.1200 Kg 28,000.00 3,360.00 28,000.00 3,360.00 28,000.00 3,360.00
L.008 Pekerja 0.1400 OH 27,000.00 3,780.00 27,000.00 3,780.00 24,500.00 3,430.00
L.002 Tukang Kayu 0.0700 OH 32,500.00 2,275.00 32,500.00 2,275.00 29,000.00 2,030.00
L.007 Kepala Tukang 0.0070 OH 35,000.00 245.00 35,000.00 245.00 31,500.00 220.50
L.010 Mandor 0.0070 OH 35,000.00 245.00 35,000.00 245.00 31,500.00 220.50
Pas. Atap fiber semen Gelombang Uk. ( 2,40 x
SNI - H.6.14 M2 SNIH.6.14 40,167.50 SN2H.6.14 40,607.50 SNSH.6.14 39,534.00
1,05 m ) x 4mm
M.010q Asbes Gelombang 0.4400 Lbr 69,000.00 30,360.00 70,000.00 30,800.00 69,000.00 30,360.00
M.006b Paku Kait 0.1200 Kg 28,000.00 3,360.00 28,000.00 3,360.00 28,000.00 3,360.00
L.008 Pekerja 0.1400 OH 27,000.00 3,780.00 27,000.00 3,780.00 24,500.00 3,430.00
L.002 Tukang Kayu 0.0670 OH 32,500.00 2,177.50 32,500.00 2,177.50 29,000.00 1,943.00
L.007 Kepala Tukang 0.0070 OH 35,000.00 245.00 35,000.00 245.00 31,500.00 220.50
L.010 Mandor 0.0070 OH 35,000.00 245.00 35,000.00 245.00 31,500.00 220.50
Pas. Atap fiber semen Gelombang Uk. ( 2,10 x
SNI - H.6.15 M2 SNIH.6.15 40,407.50 SN2H.6.15 40,917.50 SNSH.6.15 39,774.00
1,05 m ) x 4mm
M.010r Asbes Gelombang 0.5100 Lbr 60,000.00 30,600.00 61,000.00 31,110.00 60,000.00 30,600.00
M.006b Paku Kait 0.1200 Kg 28,000.00 3,360.00 28,000.00 3,360.00 28,000.00 3,360.00
L.008 Pekerja 0.1400 OH 27,000.00 3,780.00 27,000.00 3,780.00 24,500.00 3,430.00
L.002 Tukang Kayu 0.0670 OH 32,500.00 2,177.50 32,500.00 2,177.50 29,000.00 1,943.00
L.007 Kepala Tukang 0.0070 OH 35,000.00 245.00 35,000.00 245.00 31,500.00 220.50
L.010 Mandor 0.0070 OH 35,000.00 245.00 35,000.00 245.00 31,500.00 220.50
Pas. Atap fiber semen Gelombang Uk. ( 1,50 x
SNI - H.6.16 M2 SNIH.6.16 44,207.50 SN2H.6.16 45,007.50 SNSH.6.16 43,574.00
1,05 m ) x 4mm
M.010s Asbes Gelombang 0.8000 Lbr 43,000.00 34,400.00 44,000.00 35,200.00 43,000.00 34,400.00
M.006b Paku Kait 0.1200 Kg 28,000.00 3,360.00 28,000.00 3,360.00 28,000.00 3,360.00
L.008 Pekerja 0.1400 OH 27,000.00 3,780.00 27,000.00 3,780.00 24,500.00 3,430.00
L.002 Tukang Kayu 0.0670 OH 32,500.00 2,177.50 32,500.00 2,177.50 29,000.00 1,943.00
L.007 Kepala Tukang 0.0070 OH 35,000.00 245.00 35,000.00 245.00 31,500.00 220.50
L.010 Mandor 0.0070 OH 35,000.00 245.00 35,000.00 245.00 31,500.00 220.50
SNI-H.6.16.a Pasang Atap Seng Galvalum M2 SNIH.6.16a 79,407.50 SN2H.6.16a 81,807.50 SNSH.6.16a 78,774.00
M.010v Seng Galvalum 0.2400 Lbr 290,000.00 69,600.00 300,000.00 72,000.00 290,000.00 69,600.00
M.006b Paku Kait 0.1200 Kg 28,000.00 3,360.00 28,000.00 3,360.00 28,000.00 3,360.00
L.008 Pekerja 0.1400 OH 27,000.00 3,780.00 27,000.00 3,780.00 24,500.00 3,430.00
L.002 Tukang Kayu 0.0670 OH 32,500.00 2,177.50 32,500.00 2,177.50 29,000.00 1,943.00
L.007 Kepala Tukang 0.0070 OH 35,000.00 245.00 35,000.00 245.00 31,500.00 220.50
L.010 Mandor 0.0070 OH 35,000.00 245.00 35,000.00 245.00 31,500.00 220.50
SNI - H.6.23 Pas. Nok Stel fiber semen Gelombang Uk. 1,50 m M' SNIH.6.23 58,825.50 SN2H.6.23 60,925.50 SNSH.6.23 58,118.50
M.010t Nok Stel Asbes Gelombang 2.1000 Lbr 23,000.00 48,300.00 24,000.00 50,400.00 23,000.00 48,300.00
M.006g Paku Skrup 3,5" 6.0000 Bh 600.00 3,600.00 600.00 3,600.00 600.00 3,600.00
L.008 Pekerja 0.0840 OH 27,000.00 2,268.00 27,000.00 2,268.00 24,500.00 2,058.00
L.002 Tukang Kayu 0.1250 OH 32,500.00 4,062.50 32,500.00 4,062.50 29,000.00 3,625.00
L.007 Kepala Tukang 0.0130 OH 35,000.00 455.00 35,000.00 455.00 31,500.00 409.50
L.010 Mandor 0.0040 OH 35,000.00 140.00 35,000.00 140.00 31,500.00 126.00
SNI - H.6.30 1 M2 Pas. Atap Genteng Beton M2 SNIH.6.30 51,690.00 SN2H.6.30 52,240.00 SNSH.6.30 50,770.00
M.010j Genteng Beton 11.0000 Bh 3,800.00 41,800.00 3,850.00 42,350.00 3,800.00 41,800.00
113 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
M.006 Paku Biasa ( 2" - 5") 0.0300 Kg 18,000.00 540.00 18,000.00 540.00 18,000.00 540.00
L.008 Pekerja 0.2000 OH 27,000.00 5,400.00 27,000.00 5,400.00 24,500.00 4,900.00
L.002 Tukang Kayu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
SNI - H.6.30a 1 M2 Pas. Atap Genteng Morando M2 SNIH.6.30a 46,790.00 SN2H.6.30a 47,690.00 SNSH.6.30a 45,870.00
M.010e Genteng Morando 18.0000 Bh 2,050.00 36,900.00 2,100.00 37,800.00 2,050.00 36,900.00
M.006 Paku Biasa ( 2" - 5") 0.0300 Kg 18,000.00 540.00 18,000.00 540.00 18,000.00 540.00
L.008 Pekerja 0.2000 OH 27,000.00 5,400.00 27,000.00 5,400.00 24,500.00 4,900.00
L.002 Tukang Kayu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
SNI - H.6.34 Pas. Atap Nok Genteng Beton M' SNIH.6.34 50,780.00 SN2H.6.34 51,320.60 SNSH.6.34 48,940.00
M.010i Genteng Nok Beton 3.5000 Bh 4,000.00 14,000.00 4,050.00 14,175.00 4,000.00 14,000.00
M.006 Paku Biasa ( 2" - 5") 0.0500 Kg 18,000.00 900.00 18,000.00 900.00 18,000.00 900.00
M.002a Portland Cement 10.8000 Kg 1,200.00 12,960.00 1,207.00 13,035.60 1,200.00 12,960.00
M.001a Pasir Pasang 0.0320 M3 85,000.00 2,720.00 92,500.00 2,960.00 85,000.00 2,720.00
M.002b PC Warna 1.0000 Kg 1,500.00 1,500.00 1,550.00 1,550.00 1,500.00 1,500.00
L.008 Pekerja 0.4000 OH 27,000.00 10,800.00 27,000.00 10,800.00 24,500.00 9,800.00
L.002 Tukang Kayu 0.2000 OH 32,500.00 6,500.00 32,500.00 6,500.00 29,000.00 5,800.00
L.007 Kepala Tukang 0.0200 OH 35,000.00 700.00 35,000.00 700.00 31,500.00 630.00
L.010 Mandor 0.0200 OH 35,000.00 700.00 35,000.00 700.00 31,500.00 630.00
SNI - H.6.34a Pas. Atap Nok Genteng Morando M' SNIH.6.34a 50,780.00 SN2H.6.34a 51,495.60 SNSH.6.34a 48,940.00
M.010f Genteng Nok Morando 3.5000 Bh 4,000.00 14,000.00 4,100.00 14,350.00 4,000.00 14,000.00
M.006 Paku Biasa ( 2" - 5") 0.0500 Kg 18,000.00 900.00 18,000.00 900.00 18,000.00 900.00
M.002a Portland Cement 10.8000 Kg 1,200.00 12,960.00 1,207.00 13,035.60 1,200.00 12,960.00
M.001a Pasir Pasang 0.0320 M3 85,000.00 2,720.00 92,500.00 2,960.00 85,000.00 2,720.00
M.002b PC Warna 1.0000 Kg 1,500.00 1,500.00 1,550.00 1,550.00 1,500.00 1,500.00
L.008 Pekerja 0.4000 OH 27,000.00 10,800.00 27,000.00 10,800.00 24,500.00 9,800.00
L.002 Tukang Kayu 0.2000 OH 32,500.00 6,500.00 32,500.00 6,500.00 29,000.00 5,800.00
L.007 Kepala Tukang 0.0200 OH 35,000.00 700.00 35,000.00 700.00 31,500.00 630.00
L.010 Mandor 0.0200 OH 35,000.00 700.00 35,000.00 700.00 31,500.00 630.00
114 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
SNI - H.6.38 Pas. Atap Seng Gelombang BJLS 20 M' SNIH.6.38 38,990.00 SN2H.6.38 39,690.00 SNSH.6.38 38,438.00
M.010l Seng Gelombang 3" x 6 " BJLS 20 0.7000 Lbr 47,000.00 32,900.00 48,000.00 33,600.00 47,000.00 32,900.00
M.006c Paku Seng ( 1/2" - 1") 0.0200 Kg 24,000.00 480.00 24,000.00 480.00 24,000.00 480.00
L.008 Pekerja 0.1200 OH 27,000.00 3,240.00 27,000.00 3,240.00 24,500.00 2,940.00
L.002 Tukang Kayu 0.0600 OH 32,500.00 1,950.00 32,500.00 1,950.00 29,000.00 1,740.00
L.007 Kepala Tukang 0.0060 OH 35,000.00 210.00 35,000.00 210.00 31,500.00 189.00
L.010 Mandor 0.0060 OH 35,000.00 210.00 35,000.00 210.00 31,500.00 189.00
SNI - H.6.39 Pas. Atap Nok Seng M2 SNIH.6.39 14,975.00 SN2H.6.39 15,275.00 SNSH.6.39 14,306.00
M.010n Seng Plat 3" x 6 " BJLS 20 0.3000 Lbr 24,000.00 7,200.00 25,000.00 7,500.00 24,000.00 7,200.00
M.006c Paku Seng ( 1/2" - 1") 0.0400 Kg 24,000.00 960.00 24,000.00 960.00 24,000.00 960.00
L.008 Pekerja 0.1500 OH 27,000.00 4,050.00 27,000.00 4,050.00 24,500.00 3,675.00
L.002 Tukang Kayu 0.0700 OH 32,500.00 2,275.00 32,500.00 2,275.00 29,000.00 2,030.00
L.007 Kepala Tukang 0.0080 OH 35,000.00 280.00 35,000.00 280.00 31,500.00 252.00
L.010 Mandor 0.0060 OH 35,000.00 210.00 35,000.00 210.00 31,500.00 189.00
SNI - H.6.40 Pas. Talang Datar Seng BJLS 20 ( Kayu Meranti ) M' SNIH.6.40 74,118.75 SN2H.6.40 75,588.75 SNSH.6.40 72,251.88
M.010n Seng Plat 3" x 6 " BJLS 20 0.5000 Lbr 24,000.00 12,000.00 25,000.00 12,500.00 24,000.00 12,000.00
M.006c Paku Seng ( 1/2" - 1") 0.0150 Kg 24,000.00 360.00 24,000.00 360.00 24,000.00 360.00
M.005l Papan Meranti 0.0096 m3 4,275,000.00 41,040.00 4,350,000.00 41,760.00 4,275,000.00 41,040.00
M.011h Meni Besi 0.2500 Kg 11,000.00 2,750.00 12,000.00 3,000.00 11,000.00 2,750.00
L.008 Pekerja 0.1500 OH 27,000.00 4,050.00 27,000.00 4,050.00 24,500.00 3,675.00
L.002 Tukang Kayu 0.4000 OH 32,500.00 13,000.00 32,500.00 13,000.00 29,000.00 11,600.00
L.007 Kepala Tukang 0.0250 OH 35,000.00 875.00 35,000.00 875.00 31,500.00 787.50
L.010 Mandor 0.00125 OH 35,000.00 43.75 35,000.00 43.75 31,500.00 39.38
SNI - H.6.40a Pas. Talang Datar Seng BJLS 20 (Kayu Kruing) M' SNIH.6.40a 146,558.75 SN2H.6.40a 148,783.75 SNSH.6.40a 144,966.88
M.010n Seng Plat 3" x 6 " BJLS 20 0.5000 Lbr 24,000.00 12,000.00 25,000.00 12,500.00 24,000.00 12,000.00
M.006c Paku Seng ( 1/2" - 1") 0.0150 Kg 24,000.00 360.00 24,000.00 360.00 24,000.00 360.00
M.005m Papan Kruing 0.0190 m3 6,100,000.00 115,900.00 6,175,000.00 117,325.00 6,100,000.00 115,900.00
M.011h Meni Besi 0.3000 Kg 11,000.00 3,300.00 12,000.00 3,600.00 11,000.00 3,300.00
L.008 Pekerja 0.0400 OH 27,000.00 1,080.00 27,000.00 1,080.00 24,500.00 980.00
L.002 Tukang Kayu 0.4000 OH 32,500.00 13,000.00 32,500.00 13,000.00 29,000.00 11,600.00
L.007 Kepala Tukang 0.0250 OH 35,000.00 875.00 35,000.00 875.00 31,500.00 787.50
L.010 Mandor 0.00125 OH 35,000.00 43.75 35,000.00 43.75 31,500.00 39.38
SNI - H.6.41 Pas. Talang Miring Seng BJLS 20 ( Kayu Meranti ) M' SNIH.6.41 111,883.75 SN2H.6.41 114,108.75 SNSH.6.41 110,291.88
M.010n Seng Plat 3" x 6 " BJLS 20 0.5000 Lbr 24,000.00 12,000.00 25,000.00 12,500.00 24,000.00 12,000.00
M.006c Paku Seng ( 1/2" - 1") 0.0150 Kg 24,000.00 360.00 24,000.00 360.00 24,000.00 360.00
M.005l Papan Meranti 0.0190 m3 4,275,000.00 81,225.00 4,350,000.00 82,650.00 4,275,000.00 81,225.00
M.011h Meni Besi 0.3000 Kg 11,000.00 3,300.00 12,000.00 3,600.00 11,000.00 3,300.00
L.008 Pekerja 0.0400 OH 27,000.00 1,080.00 27,000.00 1,080.00 24,500.00 980.00
L.002 Tukang Kayu 0.4000 OH 32,500.00 13,000.00 32,500.00 13,000.00 29,000.00 11,600.00
L.007 Kepala Tukang 0.0250 OH 35,000.00 875.00 35,000.00 875.00 31,500.00 787.50
L.010 Mandor 0.0013 OH 35,000.00 43.75 35,000.00 43.75 31,500.00 39.38
SNI - H.6.41a Pas. Talang Miring Seng BJLS 20 ( Kayu Kruing ) M' SNIH.6.41a 146,558.75 SN2H.6.41a 148,783.75 SNSH.6.41a 144,966.88
M.010n Seng Plat 3" x 6 " BJLS 20 0.5000 Lbr 24,000.00 12,000.00 25,000.00 12,500.00 24,000.00 12,000.00
M.006c Paku Seng ( 1/2" - 1") 0.0150 Kg 24,000.00 360.00 24,000.00 360.00 24,000.00 360.00
M.005m Papan Kruing 0.0190 m3 6,100,000.00 115,900.00 6,175,000.00 117,325.00 6,100,000.00 115,900.00
M.011h Meni Besi 0.3000 Kg 11,000.00 3,300.00 12,000.00 3,600.00 11,000.00 3,300.00
L.008 Pekerja 0.0400 OH 27,000.00 1,080.00 27,000.00 1,080.00 24,500.00 980.00
L.002 Tukang Kayu 0.4000 OH 32,500.00 13,000.00 32,500.00 13,000.00 29,000.00 11,600.00
L.007 Kepala Tukang 0.0250 OH 35,000.00 875.00 35,000.00 875.00 31,500.00 787.50
L.010 Mandor 0.0013 OH 35,000.00 43.75 35,000.00 43.75 31,500.00 39.38
SNI - H.6.42 Pas. Aluminium Foil /Sisalation M2 SNIH.6.42 19,780.00 SN2H.6.42 20,305.00 SNSH.6.42 19,184.50
M.010u Aluminium Foil / Sisalation 1.0500 M2 13,000.00 13,650.00 13,500.00 14,175.00 13,000.00 13,650.00
L.008 Pekerja 0.1500 OH 27,000.00 4,050.00 27,000.00 4,050.00 24,500.00 3,675.00
L.002 Tukang Kayu 0.0500 OH 32,500.00 1,625.00 32,500.00 1,625.00 29,000.00 1,450.00
L.007 Kepala Tukang 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
L.010 Mandor 0.0080 OH 35,000.00 280.00 35,000.00 280.00 31,500.00 252.00
SNI - H.6.43 Pas. Kawat Burung ( Kayu Meranti ) M2 SNIH.6.43 29,849.50 SN2H.6.43 31,084.50 SNSH.6.43 29,212.75
M.008d Kawat Burung 1.1000 M2 14,000.00 15,400.00 15,000.00 16,500.00 14,000.00 15,400.00
M.006a Paku Eternit lis ( 1/2" - 1") 0.0200 Kg 21,850.00 437.00 21,850.00 437.00 21,850.00 437.00
M.005l Papan Meranti 0.0018 M3 4,275,000.00 7,695.00 4,350,000.00 7,830.00 4,275,000.00 7,695.00
L.008 Pekerja 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.002 Tukang Kayu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
115 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
L.010 Mandor 0.0005 OH 35,000.00 17.50 35,000.00 17.50 31,500.00 15.75
SNI - H.6.43a Pas. Kawat Burung ( Kayu Kruing ) M2 SNIH.6.43a 33,134.50 SN2H.6.43a 34,369.50 SNSH.6.43a 32,497.75
M.008d Kawat Burung 1.1000 M2 14,000.00 15,400.00 15,000.00 16,500.00 14,000.00 15,400.00
M.006a Paku Eternit lis ( 1/2" - 1") 0.0200 Kg 21,850.00 437.00 21,850.00 437.00 21,850.00 437.00
M.005m Papan Kruing 0.0018 M3 6,100,000.00 10,980.00 6,175,000.00 11,115.00 6,100,000.00 10,980.00
L.008 Pekerja 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.002 Tukang Kayu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0005 OH 35,000.00 17.50 35,000.00 17.50 31,500.00 15.75
116 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
I. PEKERJAAN LANGIT - LANGIT

SNI - I.6.19 Pas. Lis Langit-langit Kayu Propil ( Kayu Meranti ) M' SNII.6.19 9,523.50 SN2I.6.19 10,073.50 SNSI.6.19 9,195.50
M.005q Lis Kayu Propil 1.1000 M' 5,500.00 6,050.00 6,000.00 6,600.00 5,500.00 6,050.00
M.006a Paku Eternit, Lis 0.0100 Kg 21,850.00 218.50 21,850.00 218.50 21,850.00 218.50
L.008 Pekerja 0.0500 OH 27,000.00 1,350.00 27,000.00 1,350.00 24,500.00 1,225.00
L.002 Tukang Kayu 0.0500 OH 32,500.00 1,625.00 32,500.00 1,625.00 29,000.00 1,450.00
L.007 Kepala Tukang 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
L.010 Mandor 0.0030 OH 35,000.00 105.00 35,000.00 105.00 31,500.00 94.50
SNI - I.6.19a Pas. Lis Langit-langit Kayu ( Kayu Kruing ) M' SNII.6.19a 7,323.50 SN2I.6.19a 7,873.50 SNSI.6.19a 6,995.50
M.005r Lis Kayu 1.1000 M' 3,500.00 3,850.00 4,000.00 4,400.00 3,500.00 3,850.00
M.006a Paku Eternit, Lis 0.0100 Kg 21,850.00 218.50 21,850.00 218.50 21,850.00 218.50
L.008 Pekerja 0.0500 OH 27,000.00 1,350.00 27,000.00 1,350.00 24,500.00 1,225.00
L.002 Tukang Kayu 0.0500 OH 32,500.00 1,625.00 32,500.00 1,625.00 29,000.00 1,450.00
L.007 Kepala Tukang 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
L.010 Mandor 0.0030 OH 35,000.00 105.00 35,000.00 105.00 31,500.00 94.50
Pas. Langit-langit Eternit ( 1,00 x 1,00 ) m Rangka
SNI - I.6.20 M2 SNII.6.20 95,306.00 SN2I.6.20 96,426.00 SNSI.6.20 93,592.50
Kayu Kamper
M.005j Usuk Kamper 5/7 0.0120 M3 5,800,000.00 69,600.00 5,875,000.00 70,500.00 5,800,000.00 69,600.00
M.006a Paku Eternit, Lis 0.0600 Kg 21,850.00 1,311.00 21,850.00 1,311.00 21,850.00 1,311.00
M.007 Eternit ( 1,00 x 1,00 ) m 1.1000 Lbr 7,000.00 7,700.00 7,200.00 7,920.00 7,000.00 7,700.00
L.008 Pekerja 0.1800 OH 27,000.00 4,860.00 27,000.00 4,860.00 24,500.00 4,410.00
L.002 Tukang Kayu 0.3200 OH 32,500.00 10,400.00 32,500.00 10,400.00 29,000.00 9,280.00
L.007 Kepala Tukang 0.0320 OH 35,000.00 1,120.00 35,000.00 1,120.00 31,500.00 1,008.00
L.010 Mandor 0.0090 OH 35,000.00 315.00 35,000.00 315.00 31,500.00 283.50
Pas. Langit-langit Eternit ( 1,00 x 1,00 ) m Rangka
SNI - I.6.20a M2 SNII.6.20a 103,706.00 SN2I.6.20a 104,826.00 SNSI.6.20a 101,992.50
Kayu Bangkir
M.005i Usuk Bangkir 5/7 0.0120 M3 6,500,000.00 78,000.00 6,575,000.00 78,900.00 6,500,000.00 78,000.00
M.006a Paku Eternit, Lis 0.0600 Kg 21,850.00 1,311.00 21,850.00 1,311.00 21,850.00 1,311.00
M.007 Eternit ( 1,00 x 1,00 ) m 1.1000 Lbr 7,000.00 7,700.00 7,200.00 7,920.00 7,000.00 7,700.00
L.008 Pekerja 0.1800 OH 27,000.00 4,860.00 27,000.00 4,860.00 24,500.00 4,410.00
L.002 Tukang Kayu 0.3200 OH 32,500.00 10,400.00 32,500.00 10,400.00 29,000.00 9,280.00
L.007 Kepala Tukang 0.0320 OH 35,000.00 1,120.00 35,000.00 1,120.00 31,500.00 1,008.00
L.010 Mandor 0.0090 OH 35,000.00 315.00 35,000.00 315.00 31,500.00 283.50
Langit-langit Kalsiboard 3,5 mm rangka kayu M2 SNII.6.20a 114,018.50 SN2I.6.20a 104,826.00 SNSI.6.20a 101,992.50
M.005i Usuk Bangkir 5/7 0.0120 M3 6,500,000.00 78,000.00 6,575,000.00 78,900.00 6,500,000.00 78,000.00
M.006a Paku Eternit, Lis 0.0600 Kg 21,850.00 1,311.00 21,850.00 1,311.00 21,850.00 1,311.00
M.007 Kalsiboard ( 1,00 x 1,00 ) m 1.1000 Lbr 16,375.00 18,012.50 7,200.00 7,920.00 7,000.00 7,700.00
L.008 Pekerja 0.1800 OH 27,000.00 4,860.00 27,000.00 4,860.00 24,500.00 4,410.00
L.002 Tukang Kayu 0.3200 OH 32,500.00 10,400.00 32,500.00 10,400.00 29,000.00 9,280.00
L.007 Kepala Tukang 0.0320 OH 35,000.00 1,120.00 35,000.00 1,120.00 31,500.00 1,008.00
L.010 Mandor 0.0090 OH 35,000.00 315.00 35,000.00 315.00 31,500.00 283.50
Pas. Langit-langit Eternit ( 1,00 x 1,00 ) m Rangka
SNI - I.6.20b M2 SNII.6.20b 84,506.00 SN2I.6.20b 85,626.00 SNSI.6.20b 82,792.50
Kayu Kruing
M.005h Usuk Kruing 5/7 0.0120 M3 4,900,000.00 58,800.00 4,975,000.00 59,700.00 4,900,000.00 58,800.00
M.006a Paku Eternit, Lis 0.0600 Kg 21,850.00 1,311.00 21,850.00 1,311.00 21,850.00 1,311.00
M.007 Eternit ( 1,00 x 1,00 ) m 1.1000 Lbr 7,000.00 7,700.00 7,200.00 7,920.00 7,000.00 7,700.00
L.008 Pekerja 0.1800 OH 27,000.00 4,860.00 27,000.00 4,860.00 24,500.00 4,410.00
L.002 Tukang Kayu 0.3200 OH 32,500.00 10,400.00 32,500.00 10,400.00 29,000.00 9,280.00
L.007 Kepala Tukang 0.0320 OH 35,000.00 1,120.00 35,000.00 1,120.00 31,500.00 1,008.00
L.010 Mandor 0.0090 OH 35,000.00 315.00 35,000.00 315.00 31,500.00 283.50
Pas. Langit-langit Eternit ( 1,00 x 1,00 ) m Rangka
SNI - I.6.20c M2 SNII.6.20c 72,191.00 SN2I.6.20c 73,311.00 SNSI.6.20c 70,509.00
Kayu Meranti
M.005g Usuk Meranti 5/7 0.0120 M3 3,900,000.00 46,800.00 3,975,000.00 47,700.00 3,900,000.00 46,800.00
M.006a Paku Eternit, Lis 0.0600 Kg 21,850.00 1,311.00 21,850.00 1,311.00 21,850.00 1,311.00
M.007 Eternit ( 1,00 x 1,00 ) m 1.1000 Lbr 7,000.00 7,700.00 7,200.00 7,920.00 7,000.00 7,700.00
L.008 Pekerja 0.1800 OH 27,000.00 4,860.00 27,000.00 4,860.00 24,500.00 4,410.00
L.002 Tukang Kayu 0.3200 OH 32,500.00 10,400.00 32,500.00 10,400.00 29,000.00 9,280.00
L.007 Kepala Tukang 0.0320 OH 35,000.00 1,120.00 35,000.00 1,120.00 31,500.00 1,008.00
L.010 Mandor 0.0090 OH 35,000.00 315.00 35,000.00 315.00 31,500.00 283.50
Pas. Langit-langit Harplek 4 mm ( 1,00 x 1,00 ) m
SNI - I.6.20d M2 SNII.6.20d 102,946.00 SN2I.6.20d 104,396.00 SNSI.6.20d 101,232.50
Rangka Kayu Kruing
M.005c Kayu Kruing Balok 0.0120 M3 5,520,000.00 66,240.00 5,595,000.00 67,140.00 5,520,000.00 66,240.00
M.006a Paku Eternit, Lis 0.0600 Kg 21,850.00 1,311.00 21,850.00 1,311.00 21,850.00 1,311.00
M.007a Harplek 4mm ( 1,00 x 1,00 ) m 1.1000 Lbr 17,000.00 18,700.00 17,500.00 19,250.00 17,000.00 18,700.00
L.008 Pekerja 0.1800 OH 27,000.00 4,860.00 27,000.00 4,860.00 24,500.00 4,410.00
L.002 Tukang Kayu 0.3200 OH 32,500.00 10,400.00 32,500.00 10,400.00 29,000.00 9,280.00
L.007 Kepala Tukang 0.0320 OH 35,000.00 1,120.00 35,000.00 1,120.00 31,500.00 1,008.00
117 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
L.010 Mandor 0.0090 OH 35,000.00 315.00 35,000.00 315.00 31,500.00 283.50
Pas. Langit-langit Harplek 4 mm ( 1,00 x 1,00 ) m
SNI - I.6.20e M2 SNII.6.20e 84,826.00 SN2I.6.20e 85,676.00 SNSI.6.20e 83,112.50
Rangka Kayu Meranti
M.005b Kayu Meranti Balok 0.0120 M3 4,010,000.00 48,120.00 4,035,000.00 48,420.00 4,010,000.00 48,120.00
M.006a Paku Eternit, Lis 0.0600 Kg 21,850.00 1,311.00 21,850.00 1,311.00 21,850.00 1,311.00
M.007a Harplek 4mm ( 1,00 x 1,00 ) m 1.1000 Lbr 17,000.00 18,700.00 17,500.00 19,250.00 17,000.00 18,700.00
L.008 Pekerja 0.1800 OH 27,000.00 4,860.00 27,000.00 4,860.00 24,500.00 4,410.00
L.002 Tukang Kayu 0.3200 OH 32,500.00 10,400.00 32,500.00 10,400.00 29,000.00 9,280.00
L.007 Kepala Tukang 0.0320 OH 35,000.00 1,120.00 35,000.00 1,120.00 31,500.00 1,008.00
L.010 Mandor 0.0090 OH 35,000.00 315.00 35,000.00 315.00 31,500.00 283.50
SNI - I.6.24 Pas. Langit-langit Gypsum Board Tb. 9mm M2 SNII.6.24 27,927.00 SN2I.6.24 28,655.00 SNSI.6.24 27,467.00
M.007b Gypsum Board (120x240)cmx9mm 0.3640 Lbr 53,000.00 19,292.00 55,000.00 20,020.00 53,000.00 19,292.00
M.006h Paku Skrup 0.1100 Kg 36,000.00 3,960.00 36,000.00 3,960.00 36,000.00 3,960.00
L.008 Pekerja 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.002 Tukang Kayu 0.0500 OH 32,500.00 1,625.00 32,500.00 1,625.00 29,000.00 1,450.00
L.007 Kepala Tukang 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
118 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
J. PEKERJAAN SANITASI

SNI - J.6.1 Pasang Kloset Duduk / Monoblok BH SNIJ.6.1 1,614,485.00 SN2J.6.1 1,640,985.00 SNSJ.6.1 1,601,821.50
M.015 Kloset duduk / Monoblok 1.0000 Bh 1,400,000.00 1,400,000.00 1,425,000.00 1,425,000.00 1,400,000.00 1,400,000.00
- Perlengkapan 6% x hrg kloset 84,000.00 84,000.00 85,500.00 85,500.00 84,000.00 84,000.00
L.008 Pekerja 3.3000 OH 27,000.00 89,100.00 27,000.00 89,100.00 24,500.00 80,850.00
L.001 Tukang Batu 1.1000 OH 32,500.00 35,750.00 32,500.00 35,750.00 29,000.00 31,900.00
L.007 Kepala Tukang 0.0010 OH 35,000.00 35.00 35,000.00 35.00 31,500.00 31.50
L.010 Mandor 0.1600 OH 35,000.00 5,600.00 35,000.00 5,600.00 31,500.00 5,040.00
SNI - J.6.2 Pasang Kloset Jongkok Porselen BH SNIJ.6.2 299,900.00 SN2J.6.2 297,017.00 SNSJ.6.2 286,340.00
M.015a Kloset Jongkok Porselen 1.0000 Bh 158,000.00 158,000.00 155,000.00 155,000.00 158,000.00 158,000.00
M.002a Portland Cement 6.0000 Kg 1,200.00 7,200.00 1,207.00 7,242.00 1,200.00 7,200.00
M.001a Pasir Pasang 0.0100 M3 85,000.00 850.00 92,500.00 925.00 85,000.00 850.00
L.008 Pekerja 1.0000 OH 27,000.00 27,000.00 27,000.00 27,000.00 24,500.00 24,500.00
L.001 Tukang Batu 1.5000 OH 32,500.00 48,750.00 32,500.00 48,750.00 29,000.00 43,500.00
L.007 Kepala Tukang 1.5000 OH 35,000.00 52,500.00 35,000.00 52,500.00 31,500.00 47,250.00
L.010 Mandor 0.1600 OH 35,000.00 5,600.00 35,000.00 5,600.00 31,500.00 5,040.00
SNI - J.6.4 Pasang Urinoir BH SNIJ.6.4 594,550.00 SN2J.6.4 620,667.00 SNSJ.6.4 587,850.00
M.015b Urinoir 1.0000 Bh 400,000.00 400,000.00 420,000.00 420,000.00 400,000.00 400,000.00
- Perlengkapan 30% x hrg Urinoir 120,000.00 120,000.00 126,000.00 126,000.00 120,000.00 120,000.00
M.002a Portland Cement 6.0000 Kg 1,200.00 7,200.00 1,207.00 7,242.00 1,200.00 7,200.00
M.001a Pasir Pasang 0.0100 M3 85,000.00 850.00 92,500.00 925.00 85,000.00 850.00
L.008 Pekerja 1.0000 OH 27,000.00 27,000.00 27,000.00 27,000.00 24,500.00 24,500.00
L.001 Tukang Batu 1.0000 OH 32,500.00 32,500.00 32,500.00 32,500.00 29,000.00 29,000.00
L.007 Kepala Tukang 0.1000 OH 35,000.00 3,500.00 35,000.00 3,500.00 31,500.00 3,150.00
L.010 Mandor 0.1000 OH 35,000.00 3,500.00 35,000.00 3,500.00 31,500.00 3,150.00
SNI - J.6.5 Pasang Wastafel BH SNIJ.6.5 628,325.00 SN2J.6.5 634,042.00 SNSJ.6.5 619,375.00
M.015c Wastafel 1.0000 Bh 475,000.00 475,000.00 480,000.00 480,000.00 475,000.00 475,000.00
- Perlengkapan 12% x hrg Wastafel 57,000.00 57,000.00 57,600.00 57,600.00 57,000.00 57,000.00
M.002a Portland Cement 6.0000 Kg 1,200.00 7,200.00 1,207.00 7,242.00 1,200.00 7,200.00
M.001a Pasir Pasang 0.0100 M3 85,000.00 850.00 92,500.00 925.00 85,000.00 850.00
L.008 Pekerja 1.2000 OH 27,000.00 32,400.00 27,000.00 32,400.00 24,500.00 29,400.00
L.001 Tukang Batu 1.4500 OH 32,500.00 47,125.00 32,500.00 47,125.00 29,000.00 42,050.00
L.007 Kepala Tukang 0.1500 OH 35,000.00 5,250.00 35,000.00 5,250.00 31,500.00 4,725.00
L.010 Mandor 0.1000 OH 35,000.00 3,500.00 35,000.00 3,500.00 31,500.00 3,150.00
SNI - J.6.7 Pasang Bak Mandi Fiber Glass Vol. 0,30 m3 BH SNIJ.6.7 365,600.00 SN2J.6.7 344,360.00 SNSJ.6.7 349,375.00
M.015d Bk Fiberglass 1.0000 Bh 175,000.00 175,000.00 157,000.00 157,000.00 175,000.00 175,000.00
- Perlengkapan 18% x hrg Bak Fg 31,500.00 31,500.00 28,260.00 28,260.00 31,500.00 31,500.00
L.008 Pekerja 1.8000 OH 27,000.00 48,600.00 27,000.00 48,600.00 24,500.00 44,100.00
L.001 Tukang Batu 2.7000 OH 32,500.00 87,750.00 32,500.00 87,750.00 29,000.00 78,300.00
L.007 Kepala Tukang 0.5400 OH 35,000.00 18,900.00 35,000.00 18,900.00 31,500.00 17,010.00
L.010 Mandor 0.1100 OH 35,000.00 3,850.00 35,000.00 3,850.00 31,500.00 3,465.00
SNI - J.6.8 Pasang Bak Mandi Batu Bata Vol. 0,30 m3 BH SNIJ.6.8 741,600.00 SN2J.6.8 760,690.00 SNSJ.6.8 714,000.00
M.001m Batu Bata 0.4000 M3 216,000.00 86,400.00 228,000.00 91,200.00 216,000.00 86,400.00
M.002a Portland Cement 120.00 Kg 1,200.00 144,000.00 1,207.00 144,840.00 1,200.00 144,000.00
M.001a Pasir Pasang 0.3000 M3 85,000.00 25,500.00 92,500.00 27,750.00 85,000.00 25,500.00
M.004a Keramik 20/20 cm 109 Bh 1,800.00 196,200.00 1,900.00 207,100.00 1,800.00 196,200.00
M.002b PC Warna / Nat 6.0000 Kg 1,500.00 9,000.00 1,550.00 9,300.00 1,500.00 9,000.00
L.008 Pekerja 6.0000 OH 27,000.00 162,000.00 27,000.00 162,000.00 24,500.00 147,000.00
L.001 Tukang Batu 3.0000 OH 32,500.00 97,500.00 32,500.00 97,500.00 29,000.00 87,000.00
L.007 Kepala Tukang 0.3000 OH 35,000.00 10,500.00 35,000.00 10,500.00 31,500.00 9,450.00
L.010 Mandor 0.3000 OH 35,000.00 10,500.00 35,000.00 10,500.00 31,500.00 9,450.00
SNI - J.6.9 Pasang Bath Tub Porselen BH SNIJ.6.9 4,670,637.50 SN2J.6.9 4,837,437.50 SNSJ.6.9 4,666,875.00
M.015e Bath tubh 1.0000 Bh 3,861,000.00 3,861,000.00 4,000,000.00 4,000,000.00 3,861,000.00 3,861,000.00
- Perlengkapan 20% x hrg B.tubh 772,200.00 772,200.00 800,000.00 800,000.00 772,200.00 772,200.00
L.001 Tukang Batu 0.0750 OH 32,500.00 2,437.50 32,500.00 2,437.50 29,000.00 2,175.00
L.007 Kepala Tukang 0.7500 OH 35,000.00 26,250.00 35,000.00 26,250.00 31,500.00 23,625.00
L.010 Mandor 0.2500 OH 35,000.00 8,750.00 35,000.00 8,750.00 31,500.00 7,875.00
SNI - J.6.11 Pasang Bak Fiber glass vol. 1 m3 air BH SNIJ.6.11 1,181,770.00 SN2J.6.11 908,490.00 SNSJ.6.11 1,152,220.00
M.015d.1 Bak Fiber glass 1.0000 Bh 796,000.00 796,000.00 552,000.00 552,000.00 796,000.00 796,000.00
- Perlengkapan 12% x hrg Bak Fg 95,520.00 95,520.00 66,240.00 66,240.00 95,520.00 95,520.00
L.008 Pekerja 3.0000 OH 27,000.00 81,000.00 27,000.00 81,000.00 24,500.00 73,500.00
L.001 Tukang Batu 4.5000 OH 32,500.00 146,250.00 32,500.00 146,250.00 29,000.00 130,500.00
L.007 Kepala Tukang 0.9000 OH 35,000.00 31,500.00 35,000.00 31,500.00 31,500.00 28,350.00
L.010 Mandor 0.9000 OH 35,000.00 31,500.00 35,000.00 31,500.00 31,500.00 28,350.00
119 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
Pasang Bak Kontrol Pasang Batu Bata Uk. (30x30)
SNI - J.6.16 BH SNIJ.6.16 242,420.00 SN2J.6.16 247,743.00 SNSJ.6.16 230,806.25
cm tinggi 35 cm
M.001m Batu Bata 0.1450 M3 216,000.00 31,320.00 228,000.00 33,060.00 216,000.00 31,320.00
M.002a Portland Cement 44.00 Kg 1,200.00 52,800.00 1,207.00 53,108.00 1,200.00 52,800.00
M.001a Pasir Pasang 0.0700 M3 85,000.00 5,950.00 92,500.00 6,475.00 85,000.00 5,950.00
M.001n Batu Kerikil 0.0700 M3 40,000.00 2,800.00 50,000.00 3,500.00 40,000.00 2,800.00
M.003 Besi Beton 1.6000 Kg 15,000.00 24,000.00 16,000.00 25,600.00 15,000.00 24,000.00
M.001 Pasir Beton 0.0600 M3 92,500.00 5,550.00 100,000.00 6,000.00 92,500.00 5,550.00
L.008 Pekerja 3.2000 OH 27,000.00 86,400.00 27,000.00 86,400.00 24,500.00 78,400.00
L.001 Tukang Batu 1.0150 OH 32,500.00 32,987.50 32,500.00 32,987.50 29,000.00 29,435.00
L.007 Kepala Tukang 0.0015 OH 35,000.00 52.50 35,000.00 52.50 31,500.00 47.25
L.010 Mandor 0.0160 OH 35,000.00 560.00 35,000.00 560.00 31,500.00 504.00
Pasang Bak Kontrol Pasang Batu Bata Uk. (45x45)
SNI - J.6.17 BH SNIJ.6.17 263,417.50 SN2J.6.17 271,406.50 SNSJ.6.17 257,799.00
cm tinggi 50 cm
M.001m Batu Bata 0.2500 M3 216,000.00 54,000.00 228,000.00 57,000.00 216,000.00 54,000.00
M.002a Portland Cement 77.00 Kg 1,200.00 92,400.00 1,207.00 92,939.00 1,200.00 92,400.00
M.001a Pasir Pasang 0.1300 M3 85,000.00 11,050.00 92,500.00 12,025.00 85,000.00 11,050.00
M.001n Batu Kerikil 0.0200 M3 40,000.00 800.00 50,000.00 1,000.00 40,000.00 800.00
M.003 Besi Beton 2.6000 Kg 15,000.00 39,000.00 16,000.00 41,600.00 15,000.00 39,000.00
M.001 Pasir Beton 0.0900 M3 92,500.00 8,325.00 100,000.00 9,000.00 92,500.00 8,325.00
L.008 Pekerja 1.4200 OH 27,000.00 38,340.00 27,000.00 38,340.00 24,500.00 34,790.00
L.001 Tukang Batu 0.4730 OH 32,500.00 15,372.50 32,500.00 15,372.50 29,000.00 13,717.00
L.007 Kepala Tukang 0.0470 OH 35,000.00 1,645.00 35,000.00 1,645.00 31,500.00 1,480.50
L.010 Mandor 0.0710 OH 35,000.00 2,485.00 35,000.00 2,485.00 31,500.00 2,236.50
Pasang Bak Kontrol Pasang Batu Bata Uk. (60x60)
SNI - J.6.18 BH SNIJ.6.18 408,466.00 SN2J.6.18 421,176.00 SNSJ.6.18 399,666.00
cm tinggi 65 cm
M.001m Batu Bata 0.3710 M3 216,000.00 80,136.00 228,000.00 84,588.00 216,000.00 80,136.00
M.002a Portland Cement 114.00 Kg 1,200.00 136,800.00 1,207.00 137,598.00 1,200.00 136,800.00
M.001a Pasir Pasang 0.1840 M3 85,000.00 15,640.00 92,500.00 17,020.00 85,000.00 15,640.00
M.001n Batu Kerikil 0.0330 M3 40,000.00 1,320.00 50,000.00 1,650.00 40,000.00 1,320.00
M.003 Besi Beton 4.8500 Kg 15,000.00 72,750.00 16,000.00 77,600.00 15,000.00 72,750.00
M.001 Pasir Beton 0.1200 M3 92,500.00 11,100.00 100,000.00 12,000.00 92,500.00 11,100.00
L.009 Tukang Gali 0.1000 OH 27,000.00 2,700.00 27,000.00 2,700.00 24,500.00 2,450.00
L.008 Pekerja 2.1600 OH 27,000.00 58,320.00 27,000.00 58,320.00 24,500.00 52,920.00
L.001 Tukang Batu 0.7200 OH 32,500.00 23,400.00 32,500.00 23,400.00 29,000.00 20,880.00
L.007 Kepala Tukang 0.0720 OH 35,000.00 2,520.00 35,000.00 2,520.00 31,500.00 2,268.00
L.010 Mandor 0.1080 OH 35,000.00 3,780.00 35,000.00 3,780.00 31,500.00 3,402.00
SNI - J.6.19 Pasang Pipa Galvanis dia 1/2" med. B M' SNIJ.6.19 32,768.00 SN2J.6.19 33,543.00 SNSJ.6.19 32,192.00
M.016 Pipa Galvanis 1/2" med. B 1.2000 M' 17,500.00 21,000.00 18,000.00 21,600.00 17,500.00 21,000.00
- Perlengkapan 35% x hrg pipa 6,125.00 6,125.00 6,300.00 6,300.00 6,125.00 6,125.00
L.008 Pekerja 0.0540 OH 27,000.00 1,458.00 27,000.00 1,458.00 24,500.00 1,323.00
L.001 Tukang Batu 0.0900 OH 32,500.00 2,925.00 32,500.00 2,925.00 29,000.00 2,610.00
L.007 Kepala Tukang 0.0090 OH 35,000.00 315.00 35,000.00 315.00 31,500.00 283.50
L.010 Mandor 0.0270 OH 35,000.00 945.00 35,000.00 945.00 31,500.00 850.50
SNI - J.6.20 Pasang Pipa Galvanis dia 3/4" med. B M' SNIJ.6.20 42,068.00 SN2J.6.20 42,843.00 SNSJ.6.20 41,492.00
M.016a Pipa Galvanis 3/4" med. B 1.2000 M' 23,500.00 28,200.00 24,000.00 28,800.00 23,500.00 28,200.00
- Perlengkapan 35% x hrg pipa 8,225.00 8,225.00 8,400.00 8,400.00 8,225.00 8,225.00
L.008 Pekerja 0.0540 OH 27,000.00 1,458.00 27,000.00 1,458.00 24,500.00 1,323.00
L.001 Tukang Batu 0.0900 OH 32,500.00 2,925.00 32,500.00 2,925.00 29,000.00 2,610.00
L.007 Kepala Tukang 0.0090 OH 35,000.00 315.00 35,000.00 315.00 31,500.00 283.50
L.010 Mandor 0.0270 OH 35,000.00 945.00 35,000.00 945.00 31,500.00 850.50
SNI - J.6.21 Pasang Pipa Galvanis dia 1" med. B M' SNIJ.6.21 52,918.00 SN2J.6.21 53,693.00 SNSJ.6.21 52,342.00
M.016b Pipa Galvanis 1" med. B 1.2000 M' 30,500.00 36,600.00 31,000.00 37,200.00 30,500.00 36,600.00
- Perlengkapan 35% x hrg pipa 10,675.00 10,675.00 10,850.00 10,850.00 10,675.00 10,675.00
L.008 Pekerja 0.0540 OH 27,000.00 1,458.00 27,000.00 1,458.00 24,500.00 1,323.00
L.001 Tukang Batu 0.0900 OH 32,500.00 2,925.00 32,500.00 2,925.00 29,000.00 2,610.00
L.007 Kepala Tukang 0.0090 OH 35,000.00 315.00 35,000.00 315.00 31,500.00 283.50
L.010 Mandor 0.0270 OH 35,000.00 945.00 35,000.00 945.00 31,500.00 850.50
SNI - J.6.22 Pasang Pipa Galvanis dia 1 1/2" med. B M' SNIJ.6.22 76,235.00 SN2J.6.22 77,010.00 SNSJ.6.22 75,253.10
M.016c Pipa Galvanis 1 1/2" med. B 1.2000 M' 43,000.00 51,600.00 43,500.00 52,200.00 43,000.00 51,600.00
- Perlengkapan 35% x hrg pipa 15,050.00 15,050.00 15,225.00 15,225.00 15,050.00 15,050.00
L.008 Pekerja 0.1080 OH 27,000.00 2,916.00 27,000.00 2,916.00 24,500.00 2,646.00
L.001 Tukang Batu 0.1800 OH 32,500.00 5,850.00 32,500.00 5,850.00 29,000.00 5,220.00
L.007 Kepala Tukang 0.0180 OH 35,000.00 630.00 35,000.00 630.00 31,500.00 567.00
L.010 Mandor 0.0054 OH 35,000.00 189.00 35,000.00 189.00 31,500.00 170.10
SNI - J.6.22a Pasang Pipa Galvanis dia. 2" med. B M' SNIJ.6.22a 93,285.00 SN2J.6.22a 94,060.00 SNSJ.6.22a 92,303.10
120 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
M.016d Pipa Galvanis 2" med. B 1.2000 M' 54,000.00 64,800.00 54,500.00 65,400.00 54,000.00 64,800.00
- Perlengkapan 35% x hrg pipa 18,900.00 18,900.00 19,075.00 19,075.00 18,900.00 18,900.00
L.008 Pekerja 0.1080 OH 27,000.00 2,916.00 27,000.00 2,916.00 24,500.00 2,646.00
L.001 Tukang Batu 0.1800 OH 32,500.00 5,850.00 32,500.00 5,850.00 29,000.00 5,220.00
L.007 Kepala Tukang 0.0180 OH 35,000.00 630.00 35,000.00 630.00 31,500.00 567.00
L.010 Mandor 0.0054 OH 35,000.00 189.00 35,000.00 189.00 31,500.00 170.10
SNI - J.6.23 Pasang Pipa Galvanis dia. 3" med. B M' SNIJ.6.23 159,160.00 SN2J.6.23 159,935.00 SNSJ.6.23 158,178.10
M.016e Pipa Galvanis 3" med. B 1.2000 M' 96,500.00 115,800.00 97,000.00 116,400.00 96,500.00 115,800.00
- Perlengkapan 35% x hrg pipa 33,775.00 33,775.00 33,950.00 33,950.00 33,775.00 33,775.00
L.008 Pekerja 0.1080 OH 27,000.00 2,916.00 27,000.00 2,916.00 24,500.00 2,646.00
L.001 Tukang Batu 0.1800 OH 32,500.00 5,850.00 32,500.00 5,850.00 29,000.00 5,220.00
L.007 Kepala Tukang 0.0180 OH 35,000.00 630.00 35,000.00 630.00 31,500.00 567.00
L.010 Mandor 0.0054 OH 35,000.00 189.00 35,000.00 189.00 31,500.00 170.10
SNI - J.6.24 Pasang Pipa Galvanis dia 4" med. B M' SNIJ.6.24 214,258.00 SN2J.6.24 215,033.00 SNSJ.6.24 213,030.45
M.016f Pipa Galvanis 4" med. B 1.2000 M' 130,500.00 156,600.00 131,000.00 157,200.00 130,500.00 156,600.00
- Perlengkapan 35% x hrg pipa 45,675.00 45,675.00 45,850.00 45,850.00 45,675.00 45,675.00
L.008 Pekerja 0.1350 OH 27,000.00 3,645.00 27,000.00 3,645.00 24,500.00 3,307.50
L.001 Tukang Batu 0.2250 OH 32,500.00 7,312.50 32,500.00 7,312.50 29,000.00 6,525.00
L.007 Kepala Tukang 0.0225 OH 35,000.00 787.50 35,000.00 787.50 31,500.00 708.75
L.010 Mandor 0.0068 OH 35,000.00 238.00 35,000.00 238.00 31,500.00 214.20
SNI - J.6.25 Pasang Pipa PVC diameter 1/2" type AW M' SNIJ.6.25 9,395.00 SN2J.6.25 10,170.00 SNSJ.6.25 9,067.70
M.016g Pipa PVC 1/2" 1.2000 M' 4,000.00 4,800.00 4,500.00 5,400.00 4,000.00 4,800.00
- Perlengkapan 35% x hrg pipa 1,400.00 1,400.00 1,575.00 1,575.00 1,400.00 1,400.00
L.008 Pekerja 0.0360 OH 27,000.00 972.00 27,000.00 972.00 24,500.00 882.00
L.001 Tukang Batu 0.0600 OH 32,500.00 1,950.00 32,500.00 1,950.00 29,000.00 1,740.00
L.007 Kepala Tukang 0.0060 OH 35,000.00 210.00 35,000.00 210.00 31,500.00 189.00
L.010 Mandor 0.0018 OH 35,000.00 63.00 35,000.00 63.00 31,500.00 56.70
121 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
SNI - J.6.26 Pasang Pipa PVC diameter 3/4" type AW M' SNIJ.6.26 11,642.50 SN2J.6.26 12,417.50 SNSJ.6.26 11,315.20
M.016h Pipa PVC diam. 3/4" 1.2000 M' 5,450.00 6,540.00 5,950.00 7,140.00 5,450.00 6,540.00
- Perlengkapan 35% x hrg pipa 1,907.50 1,907.50 2,082.50 2,082.50 1,907.50 1,907.50
L.008 Pekerja 0.0360 OH 27,000.00 972.00 27,000.00 972.00 24,500.00 882.00
L.001 Tukang Batu 0.0600 OH 32,500.00 1,950.00 32,500.00 1,950.00 29,000.00 1,740.00
L.007 Kepala Tukang 0.0060 OH 35,000.00 210.00 35,000.00 210.00 31,500.00 189.00
L.010 Mandor 0.0018 OH 35,000.00 63.00 35,000.00 63.00 31,500.00 56.70
SNI - J.6.27 Pasang Pipa PVC diameter 1" type AW M' SNIJ.6.27 14,045.00 SN2J.6.27 14,820.00 SNSJ.6.27 13,717.70
M.016i Pipa PVC diam. 1" 1.2000 M' 7,000.00 8,400.00 7,500.00 9,000.00 7,000.00 8,400.00
- Perlengkapan 35% x hrg pipa 2,450.00 2,450.00 2,625.00 2,625.00 2,450.00 2,450.00
L.008 Pekerja 0.0360 OH 27,000.00 972.00 27,000.00 972.00 24,500.00 882.00
L.001 Tukang Batu 0.0600 OH 32,500.00 1,950.00 32,500.00 1,950.00 29,000.00 1,740.00
L.007 Kepala Tukang 0.0060 OH 35,000.00 210.00 35,000.00 210.00 31,500.00 189.00
L.010 Mandor 0.0018 OH 35,000.00 63.00 35,000.00 63.00 31,500.00 56.70
SNI - J.6.28 Pasang Pipa PVC diameter 1 1/2" type AW M' SNIJ.6.28 19,935.00 SN2J.6.28 21,020.00 SNSJ.6.28 19,607.70
M.016j Pipa PVC diam. 1 1/2" 1.2000 M' 10,800.00 12,960.00 11,500.00 13,800.00 10,800.00 12,960.00
- Perlengkapan 35% x hrg pipa 3,780.00 3,780.00 4,025.00 4,025.00 3,780.00 3,780.00
L.008 Pekerja 0.0360 OH 27,000.00 972.00 27,000.00 972.00 24,500.00 882.00
L.001 Tukang Batu 0.0600 OH 32,500.00 1,950.00 32,500.00 1,950.00 29,000.00 1,740.00
L.007 Kepala Tukang 0.0060 OH 35,000.00 210.00 35,000.00 210.00 31,500.00 189.00
L.010 Mandor 0.0018 OH 35,000.00 63.00 35,000.00 63.00 31,500.00 56.70
SNI - J.6.29 Pasang Pipa PVC diameter 2" type AW M' SNIJ.6.29 26,260.00 SN2J.6.29 26,492.50 SNSJ.6.29 25,769.05
M.016k Pipa PVC diam. 2" 1.2000 M' 13,850.00 16,620.00 14,000.00 16,800.00 13,850.00 16,620.00
- Perlengkapan 35% x hrg pipa 4,847.50 4,847.50 4,900.00 4,900.00 4,847.50 4,847.50
L.008 Pekerja 0.0540 OH 27,000.00 1,458.00 27,000.00 1,458.00 24,500.00 1,323.00
L.001 Tukang Batu 0.0900 OH 32,500.00 2,925.00 32,500.00 2,925.00 29,000.00 2,610.00
L.007 Kepala Tukang 0.0090 OH 35,000.00 315.00 35,000.00 315.00 31,500.00 283.50
L.010 Mandor 0.0027 OH 35,000.00 94.50 35,000.00 94.50 31,500.00 85.05
SNI - J.6.31 Pasang Pipa PVC diameter 3" type AW M' SNIJ.6.31 47,030.00 SN2J.6.31 48,192.50 SNSJ.6.31 46,539.05
M.016l Pipa PVC diam. 3" 1.2000 M' 27,250.00 32,700.00 28,000.00 33,600.00 27,250.00 32,700.00
- Perlengkapan 35% x hrg pipa 9,537.50 9,537.50 9,800.00 9,800.00 9,537.50 9,537.50
L.008 Pekerja 0.0540 OH 27,000.00 1,458.00 27,000.00 1,458.00 24,500.00 1,323.00
L.001 Tukang Batu 0.0900 OH 32,500.00 2,925.00 32,500.00 2,925.00 29,000.00 2,610.00
L.007 Kepala Tukang 0.0090 OH 35,000.00 315.00 35,000.00 315.00 31,500.00 283.50
L.010 Mandor 0.0027 OH 35,000.00 94.50 35,000.00 94.50 31,500.00 85.05
SNI - J.6.32 Memasang 1 m' Pipa PVC diameter 4" type AW M' SNIJ.6.32 76,940.50 SN2J.6.32 78,490.50 SNSJ.6.32 76,203.90
M.016m Pipa PVC diam. 4" 1.2000 M' 45,000.00 54,000.00 46,000.00 55,200.00 45,000.00 54,000.00
- Perlengkapan 35% x hrg pipa 15,750.00 15,750.00 16,100.00 16,100.00 15,750.00 15,750.00
L.008 Pekerja 0.0810 OH 27,000.00 2,187.00 27,000.00 2,187.00 24,500.00 1,984.50
L.001 Tukang Batu 0.1350 OH 32,500.00 4,387.50 32,500.00 4,387.50 29,000.00 3,915.00
L.007 Kepala Tukang 0.0135 OH 35,000.00 472.50 35,000.00 472.50 31,500.00 425.25
L.010 Mandor 0.0041 OH 35,000.00 143.50 35,000.00 143.50 31,500.00 129.15
SNI - J.6.33 Memasang 1 Buah Bak Cuci Piring Stainless Steel BH SNIJ.6.33 264,662.50 SN2J.6.33 255,662.50 SNSJ.6.33 263,427.25
M.015f Bak Cuci piring Stainless stell 1.0000 Bh 224,000.00 224,000.00 215,000.00 215,000.00 224,000.00 224,000.00
M.015g Water drain + Asesories 1.0000 Set 29,000.00 29,000.00 29,000.00 29,000.00 29,000.00 29,000.00
L.008 Pekerja 0.0300 OH 27,000.00 810.00 27,000.00 810.00 24,500.00 735.00
L.001 Tukang Batu 0.3000 OH 32,500.00 9,750.00 32,500.00 9,750.00 29,000.00 8,700.00
L.007 Kepala Tukang 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
L.010 Mandor 0.0015 OH 35,000.00 52.50 35,000.00 52.50 31,500.00 47.25
SNI - J.6.35 Memasang 1 Buah Kran diameter 3/4" BH SNIJ.6.35 39,107.50 SN2J.6.35 39,107.50 SNSJ.6.35 38,680.00
M.015h Kran air 3/4" 1.0000 Bh 35,000.00 35,000.00 35,000.00 35,000.00 35,000.00 35,000.00
M.015i Seal tape 0.0250 Bh 2,500.00 62.50 2,500.00 62.50 2,500.00 62.50
L.008 Pekerja 0.0100 OH 27,000.00 270.00 27,000.00 270.00 24,500.00 245.00
L.001 Tukang Batu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
SNI - J.6.35a Memasang 1 Buah Kran diameter 1/2" BH SNIJ.6.35a 19,107.50 SN2J.6.35a 19,107.50 SNSJ.6.35a 18,680.00
M.015h.1 Kran air 1/2" 1.0000 Bh 15,000.00 15,000.00 15,000.00 15,000.00 15,000.00 15,000.00
M.015i Seal tape 0.0250 Bh 2,500.00 62.50 2,500.00 62.50 2,500.00 62.50
L.008 Pekerja 0.0100 OH 27,000.00 270.00 27,000.00 270.00 24,500.00 245.00
L.001 Tukang Batu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
122 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
123 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
SNI - J.6.36 Memasang 1 Buah Floor Drain BH SNIJ.6.36 24,045.00 SN2J.6.36 24,045.00 SNSJ.6.36 23,617.50
M.015j Floor Drain 1.0000 Bh 20,000.00 20,000.00 20,000.00 20,000.00 20,000.00 20,000.00
L.008 Pekerja 0.0100 OH 27,000.00 270.00 27,000.00 270.00 24,500.00 245.00
L.001 Tukang Batu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
K. PEKERJAAN KUNCI DAN KACA

SNI - K.6.1 Pasang Kunci Tanam Antik BH SNIK.6.1 323,325.00 SN2K.6.1 323,325.00 SNSK.6.1 320,854.50
M.014 Kunci Tanam Antik 1.0000 Bh 300,000.00 300,000.00 300,000.00 300,000.00 300,000.00 300,000.00
L.008 Pekerja 0.0600 OH 27,000.00 1,620.00 27,000.00 1,620.00 24,500.00 1,470.00
L.002 Tukang Kayu 0.6000 OH 32,500.00 19,500.00 32,500.00 19,500.00 29,000.00 17,400.00
L.007 Kepala Tukang 0.0600 OH 35,000.00 2,100.00 35,000.00 2,100.00 31,500.00 1,890.00
L.010 Mandor 0.0030 OH 35,000.00 105.00 35,000.00 105.00 31,500.00 94.50
SNI - K.6.2 Pasang Kunci Tanam Biasa BH SNIK.6.2 107,045.00 SN2K.6.2 102,045.00 SNSK.6.2 105,217.50
M.014a Kunci Tanam Biasa 1.0000 Bh 90,000.00 90,000.00 85,000.00 85,000.00 90,000.00 90,000.00
L.008 Pekerja 0.0100 OH 27,000.00 270.00 27,000.00 270.00 24,500.00 245.00
L.002 Tukang Kayu 0.5000 OH 32,500.00 16,250.00 32,500.00 16,250.00 29,000.00 14,500.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
SNI - K.6.3 Pasang Kunci Tanam Kamar Mandi BH SNIK.6.3 52,045.00 SN2K.6.3 49,045.00 SNSK.6.3 50,217.50
M.014b Kunci Tanam Kamar Mandi 1.0000 Bh 35,000.00 35,000.00 32,000.00 32,000.00 35,000.00 35,000.00
L.008 Pekerja 0.0100 OH 27,000.00 270.00 27,000.00 270.00 24,500.00 245.00
L.002 Tukang Kayu 0.5000 OH 32,500.00 16,250.00 32,500.00 16,250.00 29,000.00 14,500.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.0050 OH 35,000.00 175.00 35,000.00 175.00 31,500.00 157.50
SNI - K.6.5 Pasang Engsel Pintu BH SNIK.6.5 13,331.25 SN2K.6.5 13,331.25 SNSK.6.5 12,713.63
M.014c Engsel pintu 1.0000 Bh 7,500.00 7,500.00 7,500.00 7,500.00 7,500.00 7,500.00
L.008 Pekerja 0.0150 OH 27,000.00 405.00 27,000.00 405.00 24,500.00 367.50
L.002 Tukang Kayu 0.1500 OH 32,500.00 4,875.00 32,500.00 4,875.00 29,000.00 4,350.00
L.007 Kepala Tukang 0.0150 OH 35,000.00 525.00 35,000.00 525.00 31,500.00 472.50
L.010 Mandor 0.00075 OH 35,000.00 26.25 35,000.00 26.25 31,500.00 23.63
SNI - K.6.6 Pasang Engsel Jendela Kupu-kupu BH SNIK.6.6 10,831.25 SN2K.6.6 10,831.25 SNSK.6.6 10,213.63
M.014d Engsel Jendela kupu-kupu 1.0000 Bh 5,000.00 5,000.00 5,000.00 5,000.00 5,000.00 5,000.00
L.008 Pekerja 0.0150 OH 27,000.00 405.00 27,000.00 405.00 24,500.00 367.50
L.002 Tukang Kayu 0.1500 OH 32,500.00 4,875.00 32,500.00 4,875.00 29,000.00 4,350.00
L.007 Kepala Tukang 0.0150 OH 35,000.00 525.00 35,000.00 525.00 31,500.00 472.50
L.010 Mandor 0.00075 OH 35,000.00 26.25 35,000.00 26.25 31,500.00 23.63
SNI - K.6.7 Pasang Engsel Angin BH SNIK.6.7 28,090.00 SN2K.6.7 28,090.00 SNSK.6.7 27,235.00
M.014e Engsel angin 1.0000 Bh 20,000.00 20,000.00 20,000.00 20,000.00 20,000.00 20,000.00
L.008 Pekerja 0.0200 OH 27,000.00 540.00 27,000.00 540.00 24,500.00 490.00
L.002 Tukang Kayu 0.2000 OH 32,500.00 6,500.00 32,500.00 6,500.00 29,000.00 5,800.00
L.007 Kepala Tukang 0.0200 OH 35,000.00 700.00 35,000.00 700.00 31,500.00 630.00
L.010 Mandor 0.01000 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
SNI - K.6.9 Pasang Kait Angin model lipat BH SNIK.6.9 10,831.25 SN2K.6.9 10,831.25 SNSK.6.9 10,213.63
M.014f Kait Angin model lipat 1.0000 Bh 5,000.00 5,000.00 5,000.00 5,000.00 5,000.00 5,000.00
L.008 Pekerja 0.0150 OH 27,000.00 405.00 27,000.00 405.00 24,500.00 367.50
L.002 Tukang Kayu 0.1500 OH 32,500.00 4,875.00 32,500.00 4,875.00 29,000.00 4,350.00
L.007 Kepala Tukang 0.0150 OH 35,000.00 525.00 35,000.00 525.00 31,500.00 472.50
L.010 Mandor 0.00075 OH 35,000.00 26.25 35,000.00 26.25 31,500.00 23.63
SNI - K.6.9a Pasang Kait Angin model antik BH SNIK.6.9a 22,331.25 SN2K.6.9a 22,331.25 SNSK.6.9a 21,713.63
M.014f.1 Kait Angin model antik 1.0000 Bh 16,500.00 16,500.00 16,500.00 16,500.00 16,500.00 16,500.00
L.008 Pekerja 0.0150 OH 27,000.00 405.00 27,000.00 405.00 24,500.00 367.50
L.002 Tukang Kayu 0.1500 OH 32,500.00 4,875.00 32,500.00 4,875.00 29,000.00 4,350.00
L.007 Kepala Tukang 0.0150 OH 35,000.00 525.00 35,000.00 525.00 31,500.00 472.50
L.010 Mandor 0.00075 OH 35,000.00 26.25 35,000.00 26.25 31,500.00 23.63
SNI - K.6.10 Pasang Door Closer BH SNIK.6.10 219,437.50 SN2K.6.10 219,437.50 SNSK.6.10 217,378.75
M.014g Door Closer 1.0000 Bh 200,000.00 200,000.00 200,000.00 200,000.00 200,000.00 200,000.00
L.008 Pekerja 0.0500 OH 27,000.00 1,350.00 27,000.00 1,350.00 24,500.00 1,225.00
L.002 Tukang Kayu 0.5000 OH 32,500.00 16,250.00 32,500.00 16,250.00 29,000.00 14,500.00
L.007 Kepala Tukang 0.0500 OH 35,000.00 1,750.00 35,000.00 1,750.00 31,500.00 1,575.00
124 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
L.010 Mandor 0.00250 OH 35,000.00 87.50 35,000.00 87.50 31,500.00 78.75
SNI - K.6.11 Pasang Kunci Slot BH SNIK.6.11 92,775.00 SN2K.6.11 92,775.00 SNSK.6.11 91,951.50
M.014h Kunci Slot 1.0000 Bh 85,000.00 85,000.00 85,000.00 85,000.00 85,000.00 85,000.00
L.008 Pekerja 0.0200 OH 27,000.00 540.00 27,000.00 540.00 24,500.00 490.00
L.002 Tukang Kayu 0.2000 OH 32,500.00 6,500.00 32,500.00 6,500.00 29,000.00 5,800.00
L.007 Kepala Tukang 0.0200 OH 35,000.00 700.00 35,000.00 700.00 31,500.00 630.00
L.010 Mandor 0.00100 OH 35,000.00 35.00 35,000.00 35.00 31,500.00 31.50
125 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
SNI - K.6.12 Pasang Pegangan Pintu / Door Holder BH SNIK.6.12 194,937.50 SN2K.6.12 194,937.50 SNSK.6.12 192,878.75
M.014i Pegangan Pintu / Door Holder 1.0000 Bh 175,500.00 175,500.00 175,500.00 175,500.00 175,500.00 175,500.00
L.008 Pekerja 0.0500 OH 27,000.00 1,350.00 27,000.00 1,350.00 24,500.00 1,225.00
L.002 Tukang Kayu 0.5000 OH 32,500.00 16,250.00 32,500.00 16,250.00 29,000.00 14,500.00
L.007 Kepala Tukang 0.0500 OH 35,000.00 1,750.00 35,000.00 1,750.00 31,500.00 1,575.00
L.010 Mandor 0.00250 OH 35,000.00 87.50 35,000.00 87.50 31,500.00 78.75
SNI - K.6.13 Pasang Door Stop BH SNIK.6.13 40,887.50 SN2K.6.13 40,887.50 SNSK.6.13 40,475.75
M.014j Door Stop 1.0000 Bh 37,000.00 37,000.00 37,000.00 37,000.00 37,000.00 37,000.00
L.008 Pekerja 0.0100 OH 27,000.00 270.00 27,000.00 270.00 24,500.00 245.00
L.002 Tukang Kayu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0100 OH 35,000.00 350.00 35,000.00 350.00 31,500.00 315.00
L.010 Mandor 0.00050 OH 35,000.00 17.50 35,000.00 17.50 31,500.00 15.75
SNI - K.6.14 Pasang Rel Pintu Dorong BH SNIK.6.14 323,325.00 SN2K.6.14 323,325.00 SNSK.6.14 320,854.50
M.014k Rel Pintu Dorong 1.0000 Bh 300,000.00 300,000.00 300,000.00 300,000.00 300,000.00 300,000.00
L.008 Pekerja 0.0600 OH 27,000.00 1,620.00 27,000.00 1,620.00 24,500.00 1,470.00
L.002 Tukang Kayu 0.6000 OH 32,500.00 19,500.00 32,500.00 19,500.00 29,000.00 17,400.00
L.007 Kepala Tukang 0.0600 OH 35,000.00 2,100.00 35,000.00 2,100.00 31,500.00 1,890.00
L.010 Mandor 0.00300 OH 35,000.00 105.00 35,000.00 105.00 31,500.00 94.50
SNI - K.6.16 Pasang Kaca tb. 3 mm M2 SNIK.6.16 61,931.25 SN2K.6.16 66,331.25 SNSK.6.16 61,313.63
M.008 Kaca bening tb. 3 mm 1.1000 M2 51,000.00 56,100.00 55,000.00 60,500.00 51,000.00 56,100.00
L.008 Pekerja 0.0150 OH 27,000.00 405.00 27,000.00 405.00 24,500.00 367.50
L.002 Tukang Kayu 0.1500 OH 32,500.00 4,875.00 32,500.00 4,875.00 29,000.00 4,350.00
L.007 Kepala Tukang 0.0150 OH 35,000.00 525.00 35,000.00 525.00 31,500.00 472.50
L.010 Mandor 0.00075 OH 35,000.00 26.25 35,000.00 26.25 31,500.00 23.63
SNI - K.6.17 Pasang Kaca tb. 5 mm M2 SNIK.6.17 88,331.25 SN2K.6.17 89,981.25 SNSK.6.17 87,713.63
M.008a Kaca bening tb. 5 mm 1.1000 M2 75,000.00 82,500.00 76,500.00 84,150.00 75,000.00 82,500.00
L.008 Pekerja 0.0150 OH 27,000.00 405.00 27,000.00 405.00 24,500.00 367.50
L.002 Tukang Kayu 0.1500 OH 32,500.00 4,875.00 32,500.00 4,875.00 29,000.00 4,350.00
L.007 Kepala Tukang 0.0150 OH 35,000.00 525.00 35,000.00 525.00 31,500.00 472.50
L.010 Mandor 0.00075 OH 35,000.00 26.25 35,000.00 26.25 31,500.00 23.63
SNI - K.6.18 Pasang Kaca tb. 8 mm M2 SNIK.6.18 204,413.50 SN2K.6.18 206,613.50 SNSK.6.18 203,734.20
M.008b Kaca bening tb. 8 mm 1.1000 M2 180,000.00 198,000.00 182,000.00 200,200.00 180,000.00 198,000.00
L.008 Pekerja 0.0165 OH 27,000.00 445.50 27,000.00 445.50 24,500.00 404.25
L.002 Tukang Kayu 0.1650 OH 32,500.00 5,362.50 32,500.00 5,362.50 29,000.00 4,785.00
L.007 Kepala Tukang 0.0165 OH 35,000.00 577.50 35,000.00 577.50 31,500.00 519.75
L.010 Mandor 0.00080 OH 35,000.00 28.00 35,000.00 28.00 31,500.00 25.20
SNI - K.6.20 Pasang Kaca Cermin tb. 5 mm M2 SNIK.6.20 192,831.25 SN2K.6.20 195,031.25 SNSK.6.20 192,213.63
M.008c Kaca Cermin tb. 5 mm 1.1000 M2 170,000.00 187,000.00 172,000.00 189,200.00 170,000.00 187,000.00
L.008 Pekerja 0.0150 OH 27,000.00 405.00 27,000.00 405.00 24,500.00 367.50
L.002 Tukang Kayu 0.1500 OH 32,500.00 4,875.00 32,500.00 4,875.00 29,000.00 4,350.00
L.007 Kepala Tukang 0.0150 OH 35,000.00 525.00 35,000.00 525.00 31,500.00 472.50
L.010 Mandor 0.00075 OH 35,000.00 26.25 35,000.00 26.25 31,500.00 23.63
L. PEKERJAAN LANTAI

SNI - L.6.2 Pas. Lantai Ubin PC abu-abu uk. ( 30 x 30 ) cm M2 SNIL.6.2 49,542.50 SN2L.6.2 52,580.00 SNSL.6.2 48,365.75
M.004q Ubin Abu-abu 30 x 30 cm 11.8700 Bh 2,000.00 23,740.00 2,250.00 26,707.50 2,000.00 23,740.00
M.002a Portland Cement 10.0000 Kg 1,200.00 12,000.00 1,207.00 12,070.00 1,200.00 12,000.00
M.001a Pasir Pasang 0.0215 M3 85,000.00 1,827.50 85,000.00 1,827.50 85,000.00 1,827.50
L.008 Pekerja 0.2600 OH 27,000.00 7,020.00 27,000.00 7,020.00 24,500.00 6,370.00
L.001 Tukang Batu 0.1250 OH 32,500.00 4,062.50 32,500.00 4,062.50 29,000.00 3,625.00
L.007 Kepala Tukang 0.0125 OH 35,000.00 437.50 35,000.00 437.50 31,500.00 393.75
L.010 Mandor 0.0130 OH 35,000.00 455.00 35,000.00 455.00 31,500.00 409.50
SNI - L.6.3 Pas. Lantai Ubin PC abu-abu uk. ( 20 x 20 ) cm M2 SNIL.6.3 44,620.00 SN2L.6.3 47,444.05 SNSL.6.3 43,397.25
M.004p Ubin Abu-abu 20 x 20 cm 26.5000 Bh 700.00 18,550.00 800.00 21,200.00 700.00 18,550.00
M.002a Portland Cement 10.4000 Kg 1,200.00 12,480.00 1,207.00 12,552.80 1,200.00 12,480.00
M.001a Pasir Pasang 0.0135 M3 85,000.00 1,147.50 92,500.00 1,248.75 85,000.00 1,147.50
L.008 Pekerja 0.2700 OH 27,000.00 7,290.00 27,000.00 7,290.00 24,500.00 6,615.00
L.001 Tukang Batu 0.1300 OH 32,500.00 4,225.00 32,500.00 4,225.00 29,000.00 3,770.00
L.007 Kepala Tukang 0.0130 OH 35,000.00 455.00 35,000.00 455.00 31,500.00 409.50
L.010 Mandor 0.0135 OH 35,000.00 472.50 35,000.00 472.50 31,500.00 425.25
SNI - L.6.44 Pas. Lantai Keramik uk. ( 20 x 20 ) cm (Klas A) M2 SNIL.6.44 93,061.00 SN2L.6.44 96,180.66 SNSL.6.44 90,058.50
126 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
M.004 Ubin Keramik 20 x 20 cm (Klas A) 26.5000 Bh 1,630.00 43,195.00 1,730.00 45,845.00 1,630.00 43,195.00
M.002a Portland Cement 11.3800 Kg 1,200.00 13,656.00 1,207.00 13,735.66 1,200.00 13,656.00
M.001a Pasir Pasang 0.0420 M3 85,000.00 3,570.00 92,500.00 3,885.00 85,000.00 3,570.00
M.002b Semen Warna 1.5000 Kg 1,500.00 2,250.00 1,550.00 2,325.00 1,500.00 2,250.00
L.008 Pekerja 0.6200 OH 27,000.00 16,740.00 27,000.00 16,740.00 24,500.00 15,190.00
L.001 Tukang Batu 0.3500 OH 32,500.00 11,375.00 32,500.00 11,375.00 29,000.00 10,150.00
L.007 Kepala Tukang 0.0350 OH 35,000.00 1,225.00 35,000.00 1,225.00 31,500.00 1,102.50
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
127 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
SNI - L.6.44a Pas. Lantai Keramik uk. ( 20 x 20 ) cm (Klas B) M2 SNIL.6.44a 97,566.00 SN2L.6.44a 100,685.66 SNSL.6.44a 94,563.50
M.004a Ubin Keramik 20 x 20 cm (Klas B) 26.5000 Bh 1,800.00 47,700.00 1,900.00 50,350.00 1,800.00 47,700.00
M.002a Portland Cement 11.3800 Kg 1,200.00 13,656.00 1,207.00 13,735.66 1,200.00 13,656.00
M.001a Pasir Pasang 0.0420 M3 85,000.00 3,570.00 92,500.00 3,885.00 85,000.00 3,570.00
M.002b Semen Warna 1.5000 Kg 1,500.00 2,250.00 1,550.00 2,325.00 1,500.00 2,250.00
L.008 Pekerja 0.6200 OH 27,000.00 16,740.00 27,000.00 16,740.00 24,500.00 15,190.00
L.001 Tukang Batu 0.3500 OH 32,500.00 11,375.00 32,500.00 11,375.00 29,000.00 10,150.00
L.007 Kepala Tukang 0.0350 OH 35,000.00 1,225.00 35,000.00 1,225.00 31,500.00 1,102.50
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
SNI - L.6.44b Pas. Lantai Keramik uk. ( 20 x 20 ) cm (Klas C) M2 SNIL.6.44a 113,466.00 SN2L.6.44a 113,935.66 SNSL.6.44a 110,463.50
M.004b Ubin Keramik 20 x 20 cm (Klas C) 26.5000 Bh 2,400.00 63,600.00 2,400.00 63,600.00 2,400.00 63,600.00
M.002a Portland Cement 11.3800 Kg 1,200.00 13,656.00 1,207.00 13,735.66 1,200.00 13,656.00
M.001a Pasir Pasang 0.0420 M3 85,000.00 3,570.00 92,500.00 3,885.00 85,000.00 3,570.00
M.002b Semen Warna 1.5000 Kg 1,500.00 2,250.00 1,550.00 2,325.00 1,500.00 2,250.00
L.008 Pekerja 0.6200 OH 27,000.00 16,740.00 27,000.00 16,740.00 24,500.00 15,190.00
L.001 Tukang Batu 0.3500 OH 32,500.00 11,375.00 32,500.00 11,375.00 29,000.00 10,150.00
L.007 Kepala Tukang 0.0350 OH 35,000.00 1,225.00 35,000.00 1,225.00 31,500.00 1,102.50
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
SNI - L.6.47 Pas. Lantai Keramik uk. ( 33 x 33 ) cm (Klas C) M2 SNIL.6.47 119,866.00 SN2L.6.47 122,335.66 SNSL.6.47 116,863.50
M.004c Ubin Keramik 33 x 33 cm (Klas C) 10.0000 Bh 7,000.00 70,000.00 7,200.00 72,000.00 7,000.00 70,000.00
M.002a Portland Cement 11.3800 Kg 1,200.00 13,656.00 1,207.00 13,735.66 1,200.00 13,656.00
M.001a Pasir Pasang 0.0420 M3 85,000.00 3,570.00 92,500.00 3,885.00 85,000.00 3,570.00
M.002b Semen Warna 1.5000 Kg 1,500.00 2,250.00 1,550.00 2,325.00 1,500.00 2,250.00
L.008 Pekerja 0.6200 OH 27,000.00 16,740.00 27,000.00 16,740.00 24,500.00 15,190.00
L.001 Tukang Batu 0.3500 OH 32,500.00 11,375.00 32,500.00 11,375.00 29,000.00 10,150.00
L.007 Kepala Tukang 0.0350 OH 35,000.00 1,225.00 35,000.00 1,225.00 31,500.00 1,102.50
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
SNI - L.6.47a Pas. Lantai Keramik uk. ( 40 x 40 ) cm (Klas A) M2 SNIL.6.47a 96,556.00 SN2L.6.47a 98,425.66 SNSL.6.47a 93,553.50
M.004d Ubin Keramik 40 x 40 cm (Klas A) 7.0000 Bh 6,670.00 46,690.00 6,870.00 48,090.00 6,670.00 46,690.00
M.002a Portland Cement 11.3800 Kg 1,200.00 13,656.00 1,207.00 13,735.66 1,200.00 13,656.00
M.001a Pasir Pasang 0.0420 M3 85,000.00 3,570.00 92,500.00 3,885.00 85,000.00 3,570.00
M.002b Semen Warna 1.5000 Kg 1,500.00 2,250.00 1,550.00 2,325.00 1,500.00 2,250.00
L.008 Pekerja 0.6200 OH 27,000.00 16,740.00 27,000.00 16,740.00 24,500.00 15,190.00
L.001 Tukang Batu 0.3500 OH 32,500.00 11,375.00 32,500.00 11,375.00 29,000.00 10,150.00
L.007 Kepala Tukang 0.0350 OH 35,000.00 1,225.00 35,000.00 1,225.00 31,500.00 1,102.50
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
SNI - L.6.47b Pas. Lantai Keramik uk. ( 40 x 40 ) cm (Klas B) M2 SNIL.6.47b 101,806.00 SN2L.6.47b 103,675.66 SNSL.6.47b 98,803.50
M.004e Ubin Keramik 40 x 40 cm (Klas B) 7.0000 Bh 7,420.00 51,940.00 7,620.00 53,340.00 7,420.00 51,940.00
M.002a Portland Cement 11.3800 Kg 1,200.00 13,656.00 1,207.00 13,735.66 1,200.00 13,656.00
M.001a Pasir Pasang 0.0420 M3 85,000.00 3,570.00 92,500.00 3,885.00 85,000.00 3,570.00
M.002b Semen Warna 1.5000 Kg 1,500.00 2,250.00 1,550.00 2,325.00 1,500.00 2,250.00
L.008 Pekerja 0.6200 OH 27,000.00 16,740.00 27,000.00 16,740.00 24,500.00 15,190.00
L.001 Tukang Batu 0.3500 OH 32,500.00 11,375.00 32,500.00 11,375.00 29,000.00 10,150.00
L.007 Kepala Tukang 0.0350 OH 35,000.00 1,225.00 35,000.00 1,225.00 31,500.00 1,102.50
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
SNI - L.6.47c Pas. Lantai Keramik uk. ( 40 x 40 ) cm (Klas C) M2 SNIL.6.47c 115,666.00 SN2L.6.47c 116,835.66 SNSL.6.47c 112,663.50
M.004e.1 Ubin Keramik 40 x 40 cm (Klas C) 7.0000 Bh 9,400.00 65,800.00 9,500.00 66,500.00 9,400.00 65,800.00
M.002a Portland Cement 11.3800 Kg 1,200.00 13,656.00 1,207.00 13,735.66 1,200.00 13,656.00
M.001a Pasir Pasang 0.0420 M3 85,000.00 3,570.00 92,500.00 3,885.00 85,000.00 3,570.00
M.002b Semen Warna 1.5000 Kg 1,500.00 2,250.00 1,550.00 2,325.00 1,500.00 2,250.00
L.008 Pekerja 0.6200 OH 27,000.00 16,740.00 27,000.00 16,740.00 24,500.00 15,190.00
L.001 Tukang Batu 0.3500 OH 32,500.00 11,375.00 32,500.00 11,375.00 29,000.00 10,150.00
L.007 Kepala Tukang 0.0350 OH 35,000.00 1,225.00 35,000.00 1,225.00 31,500.00 1,102.50
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
SNI - L.6.47d Pas. Lantai Keramik uk. ( 40 x 40 ) cm (Klas D) M2 SNIL.6.47d 138,066.00 SN2L.6.47d 139,550.66 SNSL.6.47d 135,063.50
M.004e.2 Ubin Keramik 40 x 40 cm (Klas D) 7.0000 Bh 12,600.00 88,200.00 12,745.00 89,215.00 12,600.00 88,200.00
M.002a Portland Cement 11.3800 Kg 1,200.00 13,656.00 1,207.00 13,735.66 1,200.00 13,656.00
M.001a Pasir Pasang 0.0420 M3 85,000.00 3,570.00 92,500.00 3,885.00 85,000.00 3,570.00
M.002b Semen Warna 1.5000 Kg 1,500.00 2,250.00 1,550.00 2,325.00 1,500.00 2,250.00
L.008 Pekerja 0.6200 OH 27,000.00 16,740.00 27,000.00 16,740.00 24,500.00 15,190.00
L.001 Tukang Batu 0.3500 OH 32,500.00 11,375.00 32,500.00 11,375.00 29,000.00 10,150.00
L.007 Kepala Tukang 0.0350 OH 35,000.00 1,225.00 35,000.00 1,225.00 31,500.00 1,102.50
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
128 / 128
KODE KATAGORI K-I (Mudah) KATAGORI K-II (Sulit) SWAKELOLA
JENIS & URAIAN PEKERJAN KOEFISIEN SAT.
ANALISA HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp) HRG SAT(Rp) HARGA (Rp)
1 2 3 4 6 7=3X6 8 9=3X8 10 11 = 3 X 10
Pas. Lantai Homogenous Tile sek. Niro Granito
M2 SNIL.6.47d 207,606.00 SN2L.6.47d 134,452.66 SNSL.6.47d 130,023.50
uk. ( 40 x 40 ) cm (warna muda)
Homogenous Tile Niro Granito 40 x 40 6.6000 Bh 23,900.00 157,740.00 12,745.00 84,117.00 12,600.00 83,160.00
M.002a Portland Cement 11.3800 Kg 1,200.00 13,656.00 1,207.00 13,735.66 1,200.00 13,656.00
M.001a Pasir Pasang 0.0420 M3 85,000.00 3,570.00 92,500.00 3,885.00 85,000.00 3,570.00
M.002b Semen Warna 1.5000 Kg 1,500.00 2,250.00 1,550.00 2,325.00 1,500.00 2,250.00
L.008 Pekerja 0.6200 OH 27,000.00 16,740.00 27,000.00 16,740.00 24,500.00 15,190.00
L.001 Tukang Batu 0.3500 OH 32,500.00 11,375.00 32,500.00 11,375.00 29,000.00 10,150.00
L.007 Kepala Tukang 0.0350 OH 35,000.00 1,225.00 35,000.00 1,225.00 31,500.00 1,102.50
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
Pas. Lantai Homogenous Tile sek. Niro Granito
M2 SNIL.6.47d 237,966.00 SN2L.6.47d 134,452.66 SNSL.6.47d 130,023.50
uk. ( 40 x 40 ) cm (warna tua)
Homogenous Tile Niro Granito 40 x 40 6.6000 Bh 28,500.00 188,100.00 12,745.00 84,117.00 12,600.00 83,160.00
M.002a Portland Cement 11.3800 Kg 1,200.00 13,656.00 1,207.00 13,735.66 1,200.00 13,656.00
M.001a Pasir Pasang 0.0420 M3 85,000.00 3,570.00 92,500.00 3,885.00 85,000.00 3,570.00
M.002b Semen Warna 1.5000 Kg 1,500.00 2,250.00 1,550.00 2,325.00 1,500.00 2,250.00
L.008 Pekerja 0.6200 OH 27,000.00 16,740.00 27,000.00 16,740.00 24,500.00 15,190.00
L.001 Tukang Batu 0.3500 OH 32,500.00 11,375.00 32,500.00 11,375.00 29,000.00 10,150.00
L.007 Kepala Tukang 0.0350 OH 35,000.00 1,225.00 35,000.00 1,225.00 31,500.00 1,102.50
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00
Pas. Homogenous Tile Dinding Ext.Uk. 60 x 60 cm
M2 SNIL.6.47d 188,052.00 SN2L.6.47d 100,932.98 SNSL.6.47d 95,735.00
sek. Indo Gress (warna hitam)
Homogenous Tile uk 60 x 60 cm (hitam) 2.9200 Bh 42,700.00 124,684.00 12,745.00 37,215.40 12,600.00 36,792.00
M.002a Portland Cement 12.4400 Kg 1,200.00 14,928.00 1,207.00 15,015.08 1,200.00 14,928.00
M.001a Pasir Pasang 0.0250 M3 85,000.00 2,125.00 92,500.00 2,312.50 85,000.00 2,125.00
M.002b Semen Warna 1.5000 Kg 1,500.00 2,250.00 1,550.00 2,325.00 1,500.00 2,250.00
L.008 Pekerja 0.7200 OH 27,000.00 19,440.00 27,000.00 19,440.00 24,500.00 17,640.00
L.001 Tukang Batu 0.6500 OH 32,500.00 21,125.00 32,500.00 21,125.00 29,000.00 18,850.00
L.007 Kepala Tukang 0.0650 OH 35,000.00 2,275.00 35,000.00 2,275.00 31,500.00 2,047.50
L.010 Mandor 0.0350 OH 35,000.00 1,225.00 35,000.00 1,225.00 31,500.00 1,102.50
Pas. Homogenous Tile Dinding Int.Uk. 40 x 40 cm
M2 SNIL.6.68a 194,755.00 SN2L.6.68a 57,387.10 SNSL.6.68a 54,339.50
sek. Indo Gress (warna muda)
Homogenous Tile Niro Granito 40 x 40 6.6000 Bh 23,900.00 157,740.00 3,045.00 20,097.00 2,945.00 19,437.00
M.002a Portland Cement 9.3000 Kg 1,200.00 11,160.00 1,207.00 11,225.10 1,200.00 11,160.00
M.001a Pasir Pasang 0.0180 M3 85,000.00 1,530.00 92,500.00 1,665.00 85,000.00 1,530.00
M.002b Semen Warna 1.5000 Kg 1,500.00 2,250.00 1,550.00 2,325.00 1,500.00 2,250.00
L.008 Pekerja 0.6000 OH 27,000.00 16,200.00 27,000.00 16,200.00 24,500.00 14,700.00
L.001 Tukang Batu 0.1000 OH 32,500.00 3,250.00 32,500.00 3,250.00 29,000.00 2,900.00
L.007 Kepala Tukang 0.0450 OH 35,000.00 1,575.00 35,000.00 1,575.00 31,500.00 1,417.50
L.010 Mandor 0.0300 OH 35,000.00 1,050.00 35,000.00 1,050.00 31,500.00 945.00

M. PEKERJAAN PENGECATAN

SNI - M.6.1 Mengikis/Mengerok Permukaan Cat Tembok Lama M2 SNIM.6.1 5,087.50 SN2M.6.1 5,087.50 SNSM.6.1 4,703.75
M.012l Soda Api 0.0500 Kg 19,000.00 950.00 19,000.00 950.00 19,000.00 950.00
L.008 Pekerja 0.1500 OH 27,000.00 4,050.00 27,000.00 4,050.00 24,500.00 3,675.00
L.010 Mandor 0.0025 OH 35,000.00 87.50 35,000.00 87.50 31,500.00 78.75
SNI - M.6.6 Mendempul dan Menggosok Kayu M2 SNIM.6.6 4,050.25 SN2M.6.6 4,112.50 SNSM.6.6 3,787.50
M.012e Dempul Jadi 0.0800 Kg 16,000.00 1,280.00 16,500.00 1,320.00 16,000.00 1,280.00
M.011g Minyak Cat 0.0200 Kg 5,000.00 100.00 6,000.00 120.00 5,000.00 100.00
M.012 Batu Kambang / Apung 0.0100 Kg 6,275.00 62.75 6,500.00 65.00 6,275.00 62.75
L.008 Pekerja 0.0400 OH 27,000.00 1,080.00 27,000.00 1,080.00 24,500.00 980.00
L.004 Tukang Cat 0.0400 OH 32,500.00 1,300.00 32,500.00 1,300.00 29,000.00 1,160.00
L.007 Kepala Tukang 0.0040 OH 35,000.00 140.00 35,000.00 140.00 31,500.00 126.00
L.010 Mandor 0.0025 OH 35,000.00 87.50 35,000.00 87.50 31,500.00 78.75
SNI - M.6.7 Pengecatan Bidang Kayu Lama ( Sek. Avian ) M2 SNIM.6.7 19,895.50 SN2M.6.7 20,242.50 SNSM.6.7 19,423.00
M.012b Plamir Kayu 0.1500 Kg 16,000.00 2,400.00 16,500.00 2,475.00 16,000.00 2,400.00
M.011 Cat dasar ( sek. Avian ) 0.1700 Kg 37,700.00 6,409.00 38,500.00 6,545.00 37,700.00 6,409.00
M.011 Cat Penutup ( sek. Avian ) 0.1700 Kg 37,700.00 6,409.00 38,500.00 6,545.00 37,700.00 6,409.00
L.008 Pekerja 0.0700 OH 27,000.00 1,890.00 27,000.00 1,890.00 24,500.00 1,715.00
L.004 Tukang Cat 0.0750 OH 32,500.00 2,437.50 32,500.00 2,437.50 29,000.00 2,175.00
L.007 Kepala Tukang 0.0075 OH 35,000.00 262.50 35,000.00 262.50 31,500.00 236.25
L.010 Mandor 0.0025 OH 35,000.00 87.50 35,000.00 87.50 31,500.00 78.75
Pengecatan Bidang Kayu Baru( 1 lps plamir, 1 lps
SNI - M.6.8 M2 SNIM.6.8 23,291.00 SN2M.6.8 23,910.00 SNSM.6.8 23,054.75
cat dasar, 2 lps cat penutup ) Sek. Avian
M.011f Cat meni 0.2000 Kg 11,000.00 2,200.00 12,000.00 2,400.00 11,000.00 2,200.00
M.012b Plamir Kayu 0.1500 Kg 16,000.00 2,400.00 16,500.00 2,475.00 16,000.00 2,400.00
M.011 Cat dasar ( sek. Avian ) 0.1700 Kg 37,700.00 6,409.00 38,500.00 6,545.00 37,700.00 6,409.00
M.011 Cat Penutup ( sek. Avian ) 0.2600 Kg 37,700.00 9,802.00 38,500.00 10,010.00 37,700.00 9,802.00