You are on page 1of 29

MANUFACTURING DESIGN ENGINEERING

QUALITY TOOL

Lean Manufacturing Principle and

Case Study
QUALITY TOOLS MISSION
and LEAN OBJECTIVES

PROVIDE ON-TIME DELIVERY


REDUCE LEADTIME
MINIMIZE INVENTORY
REDUCE CUSTOMER PRICES
Quality Tool Production Philosophy

KANBAN/CONWIP
(Minimizes Inventory / Minimizes Lead Time)

KANBAN/CONWIP Batch Build


Increasing Cost

Small lot size, Large lot size,


low inventory high inventory

Total Costs
Optimal Range

Inventory
Set up costs
costs

Increasing Lot Size


Batch Build with No Inventory

Typical demand: 1000 units per month


Typical order: 1000 units with a 4 week lead time

1000
unit
order
placed
Process time
Work Center A Work Center C

Work Center B

Week 1 Week 2 Week 3 Week 4

1000
units
ship
Batch Build with No Inventory

1000
unit
order
placed

Work Center A Work Center C


Work Center B

Week 1 Week 2 Week 3 Week 4 1000


units
ship

Problem:

The present demand is met but the


lead time is too long. I want shorter
lead times for 1000 units.
Batch Build with Simple Stocking

Solution: Add Inventory / Kanban

1000
unit 1000 Units
order Inventory
placed Replenished

Inventory Work Center A Work Center C


Level
Work Center B
=1000

Week 1 Week 2 Week 3 Week 4

1000
units
inventory Near zero lead time
ship 1000 unit inventory
Batch Build with Simple Stocking

Inventory costs money


Interest
Warehouse
Insurance
Obsolescence
Damage
Opportunity Cost

It is widely accepted that inventory costs


for one year are approximately 25% of the
total cost of the product.

Problem:
I want to reduce the amount of
inventory in the system.
Batch Build with Simple Stocking

Solution: Step 1. Reduce cycle time by


reducing lot sizes.
Order
Placed
Work Center A Work Center C
for 1000
units Work Center B

Week 1 Week 2 Week 3 Week 4 1000


units
ship
Less time spent in
Order each work center
Placed
for 500
units
A C The smaller the order size,
B the less time a job spends at
each work center and the
Week 1 Week 2 500 less time it takes to move
units through the plant.
ship
Batch Build with Simple Stocking

Step 2. Deliver smaller quantities, more frequently.


500 500
unit unit 500 Units
order order Inventory
placed placed Replenished

A C A C
B B
Inv. = 500

Week 1 Week 2 Week 3 Week 4

500 500
units units
inventory ship
ship
Near zero lead time
Inventory cut to 500 units
Twice as many orders placed
Batch Build with Simple Stocking

Problem:

There is still too much

inventory. I want even less.


Batch Build with Simple Stocking
Solution:
Step 1. Reduce cycle time by reducing lot sizes
Step 2. Reduce inventory
250 250 250 250
unit unit unit unit 250 Units
order order order order Inventory
placed placed placed placed Replenished

A C A C A C A C
B B B B
Inv. = 250
Week 1 Week 2 Week 3 Week 4

250 250 250 250


units units units units
inventory ship ship ship
ship
Inventory cut to 250 units
Near zero lead time
Four times as many orders placed
Batch Build with Simple Stocking
Theoretically, we can infinitely increase the
number of orders, reduce cycle times and
push all of the inventory out of the system.

Lower
Shorter Turns = Inventory

order
order

order

order

order

order

order

order
order

order

order

order

Week 1 Week 2 Week 3 Week 4


ship

ship

ship

ship

ship

ship

ship
ship

ship

ship

ship

ship
With no stock in the system our stocking program
turns into a CONTINUOUS FLOW system.
OBSTACLES TO DOING THIS
ON A PART BY PART BASIS, CUSTOMERS
ACTUAL DEMAND IS VERY SPORADIC - HOW
CAN WE CONTINUOUSLY MAKE THAT PART
WHEN DEMAND ISNT CONTINUOUS?

FOR MAJORITY OF PARTS WE RUN, SETUPS


CAN CONSUME AS MUCH TIME (OR MORE)
THAN ACTUAL RUN-TIME - HOW CAN WE MAKE
SMALL QUANTITIES ECONOMICALLY?

WE MANUFACTURE OVER 5000 PART NUMBERS


FOR OVER 175 CUSTOMERS - I.E. HIGH MIX,
AND A RANGE OF VOLUMES...
A Case Study at QUALITY TOOL of a

CONTINUOUS IMPROVEMENT /
LEAN

program that overcomes these


obstacles.
Case Study: The Situation
QUALITY TOOL has a customer that:
Has over 800 part numbers in production at QT.
Part volumes range from 1/year to 1000s/year.
Lead times are less than our cycle time.
FG inventory at QT is approximately $500k.
Packaging is number one cause of rejects.
Forecast is available.

QUALITY TOOL has the following challenges:


Meeting & reducing lead times.
Reducing inventory.
Packaging the product - preventing damage.
Cutting costs.
The Solution - Step 1

OBJECTIVE: IMPLEMENT QUICK FIX TO MEET LEAD TIMES

METHOD: USE FORECAST TO ANTICIPATE DEMAND

Forecast in paper form - too tough to manage


Develop software to receive forecast
electronically
Merge forecast with our own MRP data
Generate reports that show us what to build -
eliminate process of manual discovery
The Solution - Step 1

RESULT: DATABASE CREATED LINKING FORECAST TO MRP


The Solution - Step 2

OBJECTIVE: DETERMINE IF A CONTINUOUS FLOW


MODEL CAN BE ADAPTED TO THIS CUSTOMER

METHOD: ANALYZE ACTUAL PART DEMAND

RESULT:
TYPICAL PART DEMAND OVER TIME PROCESS DEMAND OVER TIME

Process Demand
Part Demand

Time Time
The Solution - Step 3

OBJECTIVE: REDUCE TIME IN THE PROCESS


METHOD: ANALYZE AVERAGE CYCLE TIME FOR ALL PARTS

RESULT:
2 Days 8 Days 4 Days 4 Days 6 Days 2 Days

SHEAR PUNCHING FORMING PAINT


Engineering Review Queue 3+days Queue 3+days Queue at
Order material/pre-sheared Turret = 1.5hr Brake = 3.7hr painter,
blanks (3 to 7 days) 4+days
Queued at shear Return to
Shear < 1hr warehouse,
1day
Non Value Add Time
DATA ENTRY SHIP
Queue order Re-pack parts
Value Add Time
Put order in system Load truck
Stuff shop router packet
The Solution - Step 4

OBJECTIVE: REDUCE THE NON-VALUE ADD TIME

METHOD: USE LEAN MANUFACTURING TECHNIQUES,


KAIZEN PRINCIPLES (5S, ETC.).
START AT THE END OF THE PROCESS
The Solution - Step 4

RESULT: STANDARD PACKAGING DEVELOPED


The Solution - Step 4

RESULT: COMMON TURRET TOOL LOAD CREATED

Percentage of Set-Ups vs. Tool


Inventory

120%
% of Set-Ups

100%
80%
60%
40%
20%
0%
1

52

103

154

205

256

307

358

409

460

511

562
# of Tools
The Solution - Step 4

ADDITIONAL RESULTS:

Developed press brake tooling identification scheme.


Tools documented by their I.D. on setup sheets.

Standardized blank sizes from >100 unique blanks to


20. Our supplier agreed to maintain these sizes for us
on their floor - reducing raw material lead time down
to 1 day.

Cross trained (2) additional people to perform order


entry function.
The Score
CYCLE TIME:
1 Day 2 Days 2 Days 2 Days 4 Days 1 Day

DATA ENTRY SHEAR PUNCHING FORMING PAINT SHIP


-1 day - 6 days -2 days - 2 days - 2 days - 1 day
CYCLE TIME REDUCED 54% FROM 26 DAYS TO 12 DAYS (so far)

DELIVERY: DELIVERY PERFORMANCE INCREASED FROM 74%


TO 92% (AT SAME TIME CUSTOMER HAS CUT LEAD TIME
REQUIREMENTS FROM 20 DAYS TO 10 DAYS.)

QUALITY: REJECTS DUE TO PACKAGING REDUCED 100%


(11,200 DPPM TO 100 DPPM)

INVENTORY: REDUCED 78% FROM $500K TO $110K


PRICE: REDUCED 21% TO CUSTOMER
Continuous Improvement...
REDUCE CYCLE TIME FURTHER:
1 1 1 2

DATA ENTRY & SHEAR


PUNCH
FORM
GOAL: 5 DAY CYCLE TIME
PAINT
& SHIP
DELIVERY: 100%
QUALITY: 0 REJECTS
INVENTORY: REDUCE TO $0. ELIMINATE BUILDING TO
FORECAST - BUILD TO ORDER.
PRICE: ONGOING REVIEW AND PRICE REDUCTIONS
AS JOINT LEAN INITIATIVES PROGRESS.
QUALITY TOOL IS THE
LOWEST COST MANUFACTURER TO OUR
CUSTOMERS, because
WE UNDERSTAND THE THEORETICAL
RELATIONSHIP BETWEEN LEAD-TIME, CYCLE TIME,
INVENTORY, AND COST.

WE RECOGNIZE THE PRACTICAL OBSTACLES TO


OPTIMIZING ALL 4 FACTORS IN A MFG.
ENVIRONMENT.

OUR SYSTEM AND METHODS ARE PROVEN WITH


REAL-WORLD EXAMPLES. WE HAVE MINIMIZED THE
OBSTACLES TO BECOME THE LOWEST COST
MANUFACTURER.
With our success in Lean, we commit to do
the following for our customers:

PROVIDE ON-TIME DELIVERY


REDUCE YOUR LEADTIME
REDUCE YOUR INVENTORY
REDUCE YOUR COST

We will distinguish ourselves as your premier


supplier of metal products.
MANUFACTURING DESIGN ENGINEERING

You might also like