Professional Documents
Culture Documents
Assessing the costs and benefits of rail and pipeline alternatives required first,
the establishment of coal transportation market projections and second, the
development of cost relationships and traffic scenarios for the two modes. Since
the extent and pattern of transportation activity depend on the cost and con-
figuration of the system, these two steps cannot be separated entirely, and the
market projections were later tested for sensitivity to transportation costs. This
chapter contains a brief description of the competing technologies followed by
the results of the two analyses just mentioned.
TECHNOLOGY DESCRIPTION
Pipelines or other beneficiation may take place, and
where the slurry is prepared. Preparation
Slurry pipelines have been proposed as a begins with impact crushing followed by the
method for moving large volumes of coal over addition of water and further grinding to a
great distances. Two such pipelines have been maximum particle size of one-eighth inch.
built in this country, one is in operation, and More water is then added to form a mixture
several are in different stages of planning (see that is about 50 percent dry coal by weight,
figure 1), The economic and environmental and the resulting slurry is stored in a tank with
advantages and limitations are a matter of mechanical agitators to prevent settling.
considerable dispute. In the absence of water-
The optimum size distribution of the coal
ways, however, pipelines are claimed to be
and proportion of water is dependent on
potential competitors for coal traffic in
design tradeoffs that are peculiar to the
volumes of more than approximately 5 million
specific application, and water requirements
tons per year over distances greater than about
are reduced to the extent of the initial
200 miles, particularly where rail facilities are
moisture content of the coal. Water is also not
circuitous or in poor condition.
necessarily the only slurry medium, and oil as
The process involves three major stages: 1) well as methanol derived from the coal itself
grinding the coal and mixing it with a liquid have been proposed.
(generally water) to form the slurry, 2) transmis-
sion through the pipeline, and 3) dewatering Transmission
the coal for use as a boiler fuel, for storage, or
The slurry from the agitated storage tanks is
for transloading to another mode of transpor-
introduced into a buried steel pipe and pro-
tation. These steps are diagramed in figure 2,
pelled by reciprocating positive displacement
and some characteristics of selected coal and
pumps located at intervals of approximately
other mineral slurry pipeline systems are
50 to 150 miles, depending upon terrain, pipe
presented in table 1.
size, a n d o t h e r d e s i g n c o n s i d e r a t i o n s . T h e
slurry travels at a velocity just under 6 feet per
Slurry Preparation
second, but the precise speed also depends on
Coal is assembled from a mine or group of the coal particle size distribution, pipe
mines at a single point where mixing, cleaning, diameter, and economic factors. Ideally, the
27
28 Coal Slurry P i p e l i n e s
GULF INTERSTATE
NORTHWEST PIPELINE
White Bluff
(
\ \
Power Plant
. . . In Progress
flow is maintained at a rate which minimizes scale, and if the pipeline is long enough to
power requirements while maintaining the recover the cost of gathering, preparing, de-
coal in suspension. O n c e s t a r t e d , t h e f l o w watering, and delivering the coal at the ter-
must continue uninterrupted, or the coal will mini, the pipeline can compete with unit
gradually settle and possibly plug the pipe. trains.
Considerable technical controversy surrounds
the likelihood of this event and the possibility Dewatering and Delivery
that the pipeline can be restarted after given
At the downstream end of the pipeline, the
periods of time. To prevent this type of set-
slurry is again introduced into agitated tank
tling, the operating pipeline at Black Mesa has
storage, from which it is fed into a dewatering
ponds into which to empty the pipe in the
facility. Dewatering is accomplished by
event of a break or other interruption.
natural settling, vacuum filtration, or by cen-
The potential economic advantage of this trifuge, and then the finely ground coal still
technology lies in the fact that the volume of suspended in the water can be separated by
coal that can pass through a pipeline increases chemical flocculation. After additional drying
approximately as the square of the pipeline by the application of heat, the coal can then
diameter, while construction, power, and other be stored, transported further by other modes,
operating costs do not rise in as high a propor- or introduced directly into grinding equipment
tion. Therefore, if throughput volumes are high at a powerplant and injected into the boilers.
enough to take advantage of this economy of The reclaimed water can be used in an electric
Ch. IV Coal Slurry Pipeline and Unit Train Systems 29
generating stations cooling system to con- also designed to take advantage of scale
dense steam, or it could theoretically be economies, generally carries a single com-
recycled in a return pipeline. modity in dedicated service between two
points in sufficient volume to achieve cost sav-
Possible variations on this stage, which are
ings. The cars are designed for automated
not covered by this assessment, include in-
loading and unloading, and the train is
troduction of coal slurry as a feedstock for
operated according to procedures which avoid
gasification or liquefaction facilities designed
switching and time-consuming delays in freight
to take into account the fact that the coal is
yards.
already ground and mixed with water, or the
use of a combustible slurry medium Iike oil or A typical coal unit train consists of six 3,000
methanol so that dewatering would not be horsepower locomotives and 100 hopper cars
necessary and the slurry could be used as a with carrying capacitates of 100 tons each.
boiler fuel directly. Roughly two such trains per week are therefore
required to deliver 1 million tons of coal per
year. Speeds vary considerably depending on
Unit Trains
track conditions, but 20 to 50 miles per hour is
The principal economic competitors with a common range. Trains generalIy travel more
coal pipelines are unit trains. This type of train, slowly loaded than empty.
Powerplant
Dewatering
Plant
Source John M Huneke, Teafmcmy Wore the Houaa Commttae on Intemr and Inaular Affaita
on Cud Slurry PIpelIne Laglalatkm, WaalwI@on, D C S@. 12, 1975
30 . Coal Slurry Pipelines
Annual
throughput
System or Length Diameter (million Initial
Slurry material location (miles) (inches) tons/year) operation
Existing
Coal. . . . . . . . . . . . . . . . . . . . Consolidation 108 10 1.3 1957
Black Mesa 273 18 4.8 1970
Limestone . . . . . . . . . . . . . . Calaveras 17 7 1.5 1971
Rugby 57 10 1.7 1964
Trinidad 6 8 0.6 1959
Colombia 17 0.4 1944
Copper Concentrate. . . . . . Bougainvillea 6 1.0 1972
West Irian 69 4 0.3 1972
KBI Turkey 38 5 1.0
Pinto Valley 11 4 0.4 1974
Magnetite Concentrate . . . Tasmania 53 2.3 1967
Waipipi (land) 4 8 1.0 971
Waipipi (offshore) 1.8 12 1.0 971
Pena Colorada 30 8 1.8 974
Gilsonite. ... , . . . . . . . . . . . Am. Gilsonite 72 6 0.4 957
Tails . . . . . . . . . . . . . . . . . . . Japan 44 12 0.6 968
Nickel refinery tailings. . . . West. Mining 4.3 4 0.1 970
In Progress
Coal. . . . . . . . . . . . . . . . . . . . Nevada Power
Utah/Nev. 180 24 10.0
Energy Trans. Systems, Inc.
Wyo./Ark. 1,036 38 25.0
Magnite and Hematite . . . . Sierra Grande 20 8 2.1
Brazil 250 20 12.0
Mexico 17 10 1.5
Planned
Coal. . . . . . . . . . . . . . . . . . . . Houston Nat. Gas
Colo. to Tex. 750 22 9.0
Gulf Interstate N.W.
Pipeline 800 30 16.0
Since these trains are frequently more rive frequently and travel slowly. Also, trains
than 1 mile in length, one of the problems of all kinds produce substantial amounts of
associated with their use is the interruption of noise, and they contribute to community and
traffic at crossings, especially where they ar- Iand-use disruption as well as to a component
Ch. IV Coal Slurry Pipeline and Unit Train Systems 33
of highway traffic accidents. However, com- justify economically a dedicated train and
pared to pipelines, railroads offer advantages often must invest in rapid loading and
in terms of flexibility of operation and absence unloading facilities to m e e t t u r n a r o u n d t i m e
of water requirements at the coal source. requirements. Also, i t i s s o m e t i m e s t o t h e
customers advantage to own the railroad cars
To benefit from this improved service, a
as welI.
customer must ship quantities sufficient to
NORTHWESTERN
(NW)
CENTRAL WESTERN
(CW) NORTHERN
APPALACHIA
(NA)
INTERIOR
EASTERN
CENTRAL
(IE)
INTERIOR APPALACHIA
WESTERN (CA)
(IW)
SOUTHERN
SOUTHWESTERN APPALACHIA
(SW) (SA)
TEXAS
(TX)
First, the sulfur-emission limitation in effect is palachian, bituminous, uncleaned coal. This
d e t e r m i n e d for each unit depending on its assignment procedure, which identifies only
location and the year that it went into service, one coal source for a given State and set of en-
Secondly, costs are compared to determine if vironmental restrictions, represents an impor-
it is more economical to burn the appropriate tant limitation. It causes the model to predict
low sulfur coal without additional cleanup or large concentrated flows of coal from single
to use fIue-gas desulfurization equipment with producing areas to consuming States, so in-
the cheapest coal avaiIable. AlI coal-fired units dividual results at the State level are not as
within a given State that are subject to the reliable as hose corresponding to larger
same suIfur-emission Iimitations burn the same regions,
kind of coal, Neither blending of coals from
Coal Prices
different supply regions nor cleaning of signifi-
cant amounts of coal are considered. Table 3 The prices developed in table 3 are ex-
identifies the assigned coals in each of the four pressed in 1975 dollars and are composed of
categories for each State by class, sulfur con- three major elements. These include an f.o.b.
tent, and delivered price, The class of the mine raw coal price, a transportation cost from
assigned coals are identified by the two letter the region of origin to the State of consump-
code for the region of origin (see table 2 for tion, and an additional component represent-
codes), rank (bituminous (B), sub-bituminous ing l o c a l i z e d s e v e r a n c e t a x e s o r m a r k e t
(S B), or lignite (L)), and whether they are premiums. The f.o.b. mine prices used as a
cleaned (C) or uncleaned (UC). Thus for exam- base are calculated from National Economic
ple, the concatenated designation SA/B/UC Research Associates (N ERA) data and con-
for the nonmetropolitan SIP complying coal National Economic Research A550clate$, Inc , Costs of SOX
for Alabama specifies a Southern Ap- Control for the $t.am F/t=ctr/c Power /ndustry, June 1975
36 Coal Slurry Pipelines
Notes: No entries under Complylng Met SIP means there IS only one is available, Sulfur content as fired. Prices In 1975 dollars,
SIP In that State, arbftrarlly considered to be non.met NONE means Sources: Teknekron, Inc. Pro/ecflorrs of UtI/I?y Coa/ Movement fafterrrs
the Ilmltatlon IS so stringent that no coal which can meet It without FGD 1980-2000.
verted to 1975 dollars. The transportation cost tween the prices of coal and oil and rates at
is based on an assumed straight-line distance which the utilities use these fuels are not in-
and a transportation rate as described below. cluded in the analysis. Regional difference in
A severance tax of 30 percent of f.o.b. mine coal prices, heating value, and sulfur content
price is added to the price of Montana coals are accounted for in all the scenarios but an
(NW/SB class). A premium (economic rent of unlimited supply of coal at current (real) prices
$0.15/106 Btu) is added to the delivered price is assumed.
of Appalachian coals complying with emission
limitations equivalent to, or more stringent Coal Transportation
than, the New Source Performance Standards. The model entails no constraints on the
Time-dependent feedback relationships be- transport of coal. Transport costs were
Ch. IV Coal Slurry Pipeline and Unit Train Systems 37
fossil-fuel fired units are included in the data Schedule for additions to capacity by
base, as are plants of the Tennessee Valley fuel type and State.
Authority (TVA) and municipal systems in Schedule for conversions of gas- and
Nebraska. Excluded utilities owned by public oil-fired plants to coal.
agencies amount to 15 percent of total
The principal elements combined to specify a
generating capacity. N e w u n i t s c u r r e n t l y
given alternative are the effect of Government
planned by the industry for the period 1975-85
demand-management policies on the rate of
are also included, except that they are not
growth in demand for electricity, the additions
b r o u g h t o n l i n e untiI the model determines
to capacity by fuel type to meet demand and
that they are needed. If assumed electricity de-
the oil-to-coal, gas-to-coal, and gas-to-oil con-
mand growth rates are lower than those im-
versions to be carried out. Under the selected
plied by the utilties plans filed with the
scenario, the growth rates of 5.4 and 5.9 per-
Federal Power Commission (FPC), the model
cent for average and peak demand reflect no
defers the startup date for an announced plant
Government policy for demand management. 3
by one or more years beyond that indicated by
Fuel mixes for capacity additions are those
the utility. The model sites new plants beyond
forecast by the nine regional reliability coun-
1985 (or later in the cases where new an-
ciIs.
nounced plants have been deferred), with the
mix between coal and nuclear specified ex- Coal prices have been discussed earlier, but
ogenously. the model includes other fuels as well. Oil
prices are assumed to remain constant in real
Demand for Electricity
terms, while natural gas prices rise from cur-
Starting with actual electricity sales in 1973, rent values to the Btu-equivalent price of oil in
a national average growth in peak and average 1981, as reflected by current trends. Uranium
power demand is specified exogenously to the prices are formed from a complex projection
model. This average rate is made to vary by of utilities current contracts and the estimates
region of the country to reflect normalized of future uranium prices, resulting in a signifi-
variations in population growth rates. Average cant rise in (real) price into the 1990s.
power-demand growth is 5.4 percent per year
The curtailment of natural gas, in both the
in the selected scenario, while growth in peak
interstate and intrastate markets, significantly
demand is 5.9 percent per year.
affects the future of the electric utility indus-
try in the primary gas-burning States. The in-
Scenario Description dustry must replace the curtailed capacity by
Energy Alternatives
Fed era I E nergy Adm I n lstratlon, Nat Iona I E nergy Outlook,
Each energy alternative specifies both February 1976
Government energy policy and the utilities 4Texas, Ok Iahoma, Lou IS Iana, K a nsas, F Iorlda, and C a I Iforn la
(Texas alone burned 45 percent of all 1975 gas deliveries to
2 steam-e lectrtc plants Louls}ana was second with 11 percent )
Ibid
38 Coal Slurry Pipelines
The last category includes 32 percent of the Considering only the steam capacity
Nations gas plants and 40 percent of the planned after 1985, the division between coal,
Texas, Louisiana, Oklahoma, and California oil, and nuclear in capacity additions is ap-
gas capacity. This degree of curtailment agrees proximately as follows:
closely with utility plans filed with the FPC. Coal . . . 33 percent
Fossil = 41 percent
Additions to generating capacity in the Oil . . . . . 8 percent
selected scenario are an extension of currently
scheduled additions to generating capacity as Nuclear. . 59 percent
Table 4. Scheduled Additions to Capacity, for the Decade 1976-85, as of April 1,1976,
as Reported by Nine Regional Reliability Councils
I
I
SPP
SERC
ERCOT
Table 5. Planned Additions to Capacity for the Decade 1986-95, as of April 1,1976,
as Reported by Nine Regional Reliability Councils
Total Nuclear Fossil Hydro, other
Council additions MW 0/0 MW % MW 0/0
(MW)
All post-1985 steam capacity is assigned in the All new oil-fired fossil steam units com-
above proportion and the mix of capacity ing online after 1980 burn oil.
planned to 1985 remains unaltered. Gas plants that can burn either coal or
oiI switch to these fuels in proportion to
A coal conversion pIan for existing and an-
the consumption of coal and oil by
nounced fossil steam units embodied in the
powerplants in the affected State.
selected scenario is as follows:
Environmental Alternatives
Federal Energy Administration (FEA) con-
version orders under the Energy Supply When incorporated into a scenario, each of
and Environmental Coordination Act several environmental policy alternatives will
(ESECA), for the conversion of oil and gas elicit a different response from the utilities,
plants to coal plants, are not approved by because of the intimate relationship between
E PA, and no such conversions take place. regulation and the behavior of the industry.
The alternatives considered emphasize limita-
Gas plants that can convert only to coal
do SO. tions on emissions from coal-fired plants as
well as plant-siting restrictions. UtiIity
All new oil-fired fossil steam units coming response concerns the type of coal used, the
online after 1980 burn oil. pollution-control strategy employed, and the
Gas plants that can burn either coal or oil location of the post-1985 plants.
switch to these fuels in proportion to the The chosen scenario illustrates the impact
consumption of coaI and oil by o f a N o n - S i g n i f i c a n t Deterioration (NSD)
powerplants in the affected State. policy reflecting recent amendments to the
In summary, the energy alternative Clean Air Act. This alternative is characterized
represented by the selected scenario is a rela- by a restrictive siting policy and by one inter-
tively high demand, high nuclear one, par- pretation of what constitutes Best Available
ticularly in the years beyond 1985. The high Control Technology (BACT). Siting is pro-
rate of demand growth and the low proportion hibited in areas where deterioration of air
of coal to nuclear plants tend to balance each quality cannot be tolerated (for example, na-
other to produce an intermediate projection of tional parks and other Federal lands) and in
coal use. A recapitulation of the main energy nonattainment areas. Flue gas desulfurization
features of the scenario follows. (FGD) is required for all new coal units online
after 1981. Assumed policy instruments in-
Growth in demand for electric energy clude:
5.4 percent per year
Current State implementation plans.
Growth in peak power demand Current New Source Performance Stand-
5.9 percent per year ards.
Additions of new steam capacity after Siting prohibited in Class I and nonattain-
1985 ment areas. Since siting is not allowed in
33 percent coal any county that contains any part of a
8 percent oil Class I area, a significant land area is pro-
59 percent nuclear scribed for development.
For new sources online after 1981, BACT
Conversion policy is required for S0 2 . This is interpreted to
FEA conversion orders under ESECA, mean mandatory FGD with 90-percent
for the conversion of oil and gas plants removal efficiency.
to coal plants, are not approved by EPA
and no such conversions take place. The policy of nonsignificant deterioration is
Gas plants that can convert only to coal designed to prevent the deterioration of air
do SO. quality in those regions now cleaner than re-
Ch. IV Coal Slurry Pipeline and Unit Train Systems 41
quired by the National Ambient Air Quality tions of future costs of transport indicate an in-
Standards. The recent Clean Air Act amend- creased tendency toward remote siting. On the
ments have the same goal. Area descriptions other hand, nonsignificant deterioration pro-
relating to NSD requirements considered in posals would constrain both the number of
this analysis are as follows: available sites and the maximum size of a
Mandatory Class I if area exceeds 5,000 fossil-fueled plant. Taking all considerations
acres into account leads to two different siting con-
national and international parks straints:
national wilderness areas and wildlife Siting of new (post-1985) fossil-fueled
refuges plants conforms to NSD regulations.
Class I with provision for redesignation as Transmission costs, transportation costs,
Class I I avaiIabiIity of water, and suitabiIity of ter-
national monuments, recreationaI rain are taken into account only in Class II
areas, wiId and scenic rivers areas. No siting is allowed in Class I c o u n -
ties, because the allowed air quality in-
Class I I with provision for redesignation to crements are too smalI to support an eco-
Class I nomically sized generation faciIity. A
national preserves, forests, reserva- Class I county is a county having any-
tions, and other Federal lands where within its boundaries a Class I area
as specified by the proposed amend-
All mandatory or discretionary Class I areas ments,
are considered Class I in the Utility Simulation Siting of new (post-1 985) plants is pro-
Model. The models smallest resolution is at
hibited in areas where primary NAAQS for
the county level; hence, any county containing sulfur oxides, nitrogen oxides, or total
any Class I area is designated a Class I county. suspended particulate are currently ex-
In this scenario, the siting of fossil-fuel
ceeded.
powerplants in Class I counties is prohibited,
even though a small plant might be permitted
by the increment of deterioration allowed.
Results
In selecting a site for a new plant a utility
The projections generated by the model
makes a difficult decision, taking into account
under the selected scenario approximate an
the distance to load center, costs of fuel and
average annual compound growth rate for
electricity transmission, availability of water
utility steam coal consumption of 4.2 percent.
and labor, and siting restrictions for en-
The total volume is projected to be 942 million
vironmental reasons, There are conflicting
tons in the year 2000 compared with actual
criteria for siting. Remote siting may be re-
deliveries to electric utilities of 429 million
quired to remove the source from a polluted
tons in 1975. Before 1985, the projection is
area with a high population density, while
consistently lower than those of several other
reguIations to prevent the significant
studies, due to three major causes. One is the
deterioration of air quality exert pressure for
exclusion of some noninvestor-owned utilities,
siting away from clean areas toward areas hav-
which accounted for 27 million tons of coal in
ing greater popuIation density.
1974. Another is the use in this study of electric
Remote siting has been an important alter- power demand growth instead of announced
native for coal. Typically, transportation ac- additions to generating capacity as a realistic
counts for a very significant fraction of the determinant of future fuel use. The last causes
cost of coal delivered to the utility. Location a reduced rate of assumed growth based on re-
near the mine, with long transmission lines, has cent experience a s o p p o s e d t o h i s t o r i c a l
proved cost effective in some cases. Projec- averages.
42 . Coal Slurry Pipelines
a 1975 figures are actual. Differences in the distribution of production between 1975 and 1980 are due Primarily to the
assumption underlying the model that specified environmental regulations will be complied with by 1980.
Source: Derived from data in Teknekron, Inc.
Ch. IV Coal Slurry Pipeline and Unit Train Systems 43
Table 7. Projected Utility Coal Distribution From Region of Origin to State of End Use
(Millions of tons per year)
Year
State 1980 1985 1990 1995 2000
Alabama (total). . . . . . . . . . . . . . . . . . . . . . . 12 12 15 18 21
S. Appalachian. . . . . . . . . . . . . . . . . . . . . 12 12 15 18 21
C. Western . . . . . . . . . . . . . . . . . . . . . . . . 0.20 0.10 0.03
Arizona (total). . . . . . . . . . . . . . . . . . . . . . . . 2.7 0.44 0.34 0 0
S. Western . . . . . . . . . . . . . . . . . . . . . . . . 2.7 0.44 0.34
Arkansas (total) . . . . . . . . . . . . . . . . . . . . . . 0 1.6 3.4 7.0 8.4
I. Eastern . . . . . . . . . . . . . . . . . . . . . . . . . . 1.6 1.8 7.0 8.4
C. Western . . . . . . . . . . . . . . . . . . . . . . . . 1.6
California (total). . . . . . . . . . . . . . . . . . . . . . 0.91 9.2 14 31 39
C. Western . . . . . . . . . . . . . . . . . . . . . . . . 0.64 8.9 14 31 38
S. Western . . . . . . . . . . . . . . . . . . . . . . . . 0.27 0.27 0.95
Colorado (total) . . . . . . . . . . . . . . . . . . . . . 4.4 6.3 8.8 12 16
C. Western . . . . . . . . . . . . . . . . . . . . . . . . 4.4 6.3 8.8 12 16
Connecticut (total) . . . . . . . . . . . . . . . . . . . 0 1.1 0 0 0
C. Appalachian . . . . . . . . . . . . . . . . . . . . 1.1
Delaware (total). . . . . . . . . . . . . . . . . . . . . . 1.2 1.0 1.2 1.1 0.96
C. Appalachian . . . . . . . . . . . . . . . . . . . . 1.2 1.0 1.2 1.1 0.96
C. Western . . . . . . . . . . . . . . . . . . . . . . . . 0.03
Florida (total) . . . . . . . . . . . . . . . . . . . . . . . . 8.8 16 21 22 32
S. Appalachian. . . . . . . . . . . . . . . . . . . . . 8.8 16 21 22 32
Georgia (total) . . . . . . . . . . . . . . . . . . . . . . . 1.6 19 23 28 39
I. Eastern . . . . . . . . . . . . . . . . . . . . . . . . . 1.6 19 23 28 39
Idaho (total) . . . . . . . . . . . . . . . . . . . . . . . . . 1.5 3.0 3,0 2.9 3.0
C. Western . . . . . . . . . . . . . . . . . . . . . . . . 1.5 3.0 3.0 2.9 3.0
Illinois (total) . . . . . . . . . . . . . . . . . . . . . . . . 30 35 38 47 74
I. Eastern . . . . . . . . . . . . . . . . . . . . . . . . . 10 16 22 31 58
C. Western . . . . . . . . . . . . . . . . . . . . . . . . 20 19 16 16 16
Indiana (total). . . . . . . . . . . . . . . . . . . . . . . . 30 30 43 47 59
I. Eastern . . . . . . . . . . . . . . . . . . . . . . . . . 5.3 18 28 42
C. Western . . . . . . . . . . . . . . . . . . . . . . . . 30 25 25 19 17
Iowa (total) . . . . . . . . . . . . . . . . . . . . . . . . . . 5.9 8.7 9.0 7.4 10
I. Eastern . . . . . . . . . . . . . . . . . . . . . . . . . 5.9 4.7 4.1 3.3 2.7
I. Western . . . . . . . . . . . . . . . . . . . . . . . . . 3.8 4.9 4.1 7.3
Kansas (total). . . . . . . . . . . . . . . . . . . . . . . . 5.7 4.8 8.1 23 19
l. Eastern . . . . . . . . . . . . . . . . . . . . . . . . . 5.7 1.8
l. Western.. . . . . . . . . . . . . . . . . . . . . . . . 3.0 3.6
C. Western . . . . . . . . . . . . . . . . . . . . . . . . 4.5 23 19
Kentucky (total). . . . . . . . . . . . . . . . . . . . . . 23 23 25 29 34
C. Appalachian . . . . . . . . . . . . . . . . . . . . 23 19 5 13
I. Eastern . . . . . . . . . . . . . . . . . . . . . . . . . 3.6 9.8 16 23
Louisiana (total). . . . . . . . . . . . . . . . . . . . . . 0 8.5 9.4 14 16
S. Appalachian.. . . . . . . . . . . . . . . . . . . . 1.5 8.3 11 16
I. Eastern . . . . . . . . . . . . . . . . . . . . . . . . . 1.5 1.1
C. Western . . . . . . . . . . . . . . . . . . . . . . . . 5.5 3.5
44 Coal Slurry Pipelines
Table 7. Projected Utility Coal Distribution From Region of Origin to State of End UseContinued
(Millions of tons per year)
Year
State 1980 1985 1990 1995 2000
Maine (total). . . . . . . . . . . . . . . . . . . . . . . . . 0 0 0 0 0
Maryland and D.C. (total) . . . . . . . . . . . . . . 3.6 6.2 5.6 12 14
N. Appalachian . . . . . . . . . . . . . . . . . . . . 3.4 5.8 5.1 12 14
C. Appalachian . . . . . . . . . . . . . . . . . . . . 0.13 0.30 0.40
S. Appalachian. . . . . . . . . . . . . . . . . . . . . 0.10 0.10
C. Western . . . . . . . . . . . . . . . . . . . . . . . . 0.10 0.10 0.10 0.03 0.03
Massachusetts (total). . . . . . . . . . . . . . . . . 0 0 0 0 0
Michigan (total) . . . . . . . . . . . . . . . . . . . . . . 25 29 26 26 30
l. Eastern . . . . . . . . . . . . . . . . . . . . . . . . . 5.8 8.2 7.6 13
N. Western . . . . . . . . . . . . . . . . . . . . . . . . 25 23 18 17 17
C. Western . . . . . . . . . . . . . . . . . . . . . . . . 0.06 1.8
Minnesota (total) . . . . . . . . . . . . . . . . . . . . . 5.4 11 14 16 17
N. Western . . . . . . . . . . . . . . . . . . . . . . . . 5.4 9.7 13 15 16
C. Western . . . . . . . . . . . . . . . . . . . . . . . . 1.2 1.1 1.1 1.0
Mississippi (total . . . . . . . . . . . . . . . . . . . . 3.8 4.9 6.1 10 13
S. Appalachian . . . . . . . . . . . . . . . . . . . . 3.8 4.9 6.1 10 13
Missouri (total).. .................... 25 27 29 35 41
I. Western. . . . .................... 1.6 6,0 17 27
C. Western . . . .................... 25 25 23 18 14
Montana (total) . . . . . . . . . . . . . . . . . . . . . . 7.4 7.4 7.3 7.3 7.3
N. Western . . . . . . . . . . . . . . . . . . . . . . . . 7.4 7.4 7.3 7.3 7.3
Nebraska (total) . . . . . . . . . . . . . . . . . . . . . . 5.2 5.2 5.2 5.2 5.2
C. Western . . . . . . . . . . . . . . . . . . . . . . . . 5.2 5.2 5.2 5.2 5.2
Nevada (total). . . . . . . . . . . . . . . . . . . . . . . . 6.5 7.4 9.8 7.5 3.9
C. Western . . . . . . . . . . . . . . . . . . . . . . . . 6.5 7.4 9.8 7.5 3.9
New Hampshire (total) . . . . . . . . . . . . . . . . 0.10 0.60 0.04 0.50 0.30
N. Appalachian . . . . . . . . . . . . . . . . . . . . 0.10 0.60 0.04 0.50 0.30
New Jersey (total). . . . . . . . . . . . . . . . . . . . 1.5 1.3 1.0 1.0 2.5
N. Appalachian . . . . . . . . . . . . . . . . . . . . 0.52 0.32 1.5
C. Appalachian . . . . . . . . . . . . . . . . . . . . 1.0 1.0 1.0 1.0 1.0
New Mexico (total) . . . . . . . . . . . . . . . . . . . 7.3 8.1 9.3 12 10
C. Western . . . . . . . . . . . . . . . . . . . . . . . . 2.4
S. Western . . . . . . . . . . . . . . . . . . . . . . . . 7.3 8.1 9.3 12 7.9
New York (total). . . . . . . . . . . . . . . . . . . . . . 3.8 3.5 8.8 8.8 11
N. Appalachian . . . . . . . . . . . . . . . . . . . . 1.9 1.8 7.2 7.6 8.3
C. Appalachian . . . . . . . . . . . . . . . . . . . . 1.9 1.7 1.6 1.2 2.6
North Carolina (total) . . . . . . . . . . . . . . . . . 18 18 15 15 16
C. Appalachian . . . . . . . . . . . . . . . . . . . . 18 18 15 15 16
S. Appalachian. . . . . . . . . . . . . . . . . . . . . 0.31 0.10 0.01 0.07
North Dakota (total). . . . . . . . . . . . . . . . . . . 0.29 0.77 3.9 6.6 12
N. Western . . . . . . . . . . . . . . . . . . . . . . . . 0.26 0.76 3.9 6.6 12
C. Western . . . . . . . . . . . . . . . . . . . . . . . . 0.03 0.01 0.01 0.01 0.02
Ch. IV Coal Slurry Pipeline and Unit Train Systems 45
Table 7. Projected Utility Coal Distribution From Region of Origin to State of End UseContinued
(Millions of tons per year)
Year
State 1980 1985 1990 1995 2000
Ohio (total). . . . . . . . . . . . . . . . . . . . . . . . . . 45 48 43 48 48
N. Appalachian . . . . . . . . . . . . . . . . . . . . 43 47 42 47 47
C. Western . . . . . . . . . . . . . . . . . . . . . . . . 1.6 1.3 1.1 1.1 0.92
Oklahoma (total) . . . . . . . . . . . . . . . . . . . . . 0.02 9.2 14 17 25
I. Western . . . . . . . . . . . . . . . . . . . . . . . . . 9.2 14 17 25
C. Western . . . . . . . . . . . . . . . . . . . . . . . . 0.02
Oregon (total). ...... . . . . . . . . . . . . . . . . 1.5 3.1 0.06 5.1 1.0
N. Western . . . . . . . . . . . . . . . . . . . . . . . . 0.9 1.0
C. Western . . . . . . . . . . . . . . . . . . . . . . . . 1.5 3.1 0.06 4.2
Pennsylvania (total). . . . . . . . . . . . . . . . . . . 37 36 55 59 67
N. Appalachian . . . . . . . . . . . . . . . . . . . . 33 32 50 57 67
C. Appalachian . . . . . . . . . . . . . . . . . . . . 4.0 3.6 4.9 1.9
Rhode island (total). .., . . . . . . . . . . . . . . . 0 0 0 0 0
South Carolina (total) . . . . . . . . . . . . . . . . . 1.9 2.0 1.7 1.2 1.2
S. Appalachian. . . . . . . . . . . . . . . . . . . . . 1.9 2.0 1.7 1.2 1.2
South Dakota (total) . . . . . . . . . . . . . . . . . . 1.4 2.1 2.2 2.4 2.7
N. Western . . . . . . . . . . . . . . . . . . . . . . . . 1.4 1.4 1.4
C. Western . . . . . . . . . . . . . . . . . . . . . . . . 0.70 0.80 1.0 2.7
Tennessee (total). . . . . . . . . . . . . . . . . . . . . 19 8.8 7.0 2.8 0.96
S. Appalachian . . . . . . . . . . . . . . . . . . . . . 19 8.8 7.0 2.8 0.96
Texas (total) . . . . . . . . . . . . . . . . . . . . . . . . . 15 48 84 112 141
S. Appalachian. . . . . . . . . . . . . . . . . . . . . 1.5 1.1 1.0
C. Western . . . . . . . . . . . . . . . . . . . . . . . . 1.3 35 72 93 125
S. Western . . . . . . . . . . . . . . . . . . . . . . . . 0.20 0.20
Texas . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14 12 12 18 16
Utah (total) . . . . . . . . . . . . . . . . . . . . . . . . . . 3.2 4.0 2.0 8.0 18
C. Western. . . . . . . . . . . . . . . . . . . . . . . . 3.2 4.0 2.0 8.0 18
Vermont (total). . . . . . . . . . . . . . . . . . . . . . . o 0 0 0 0
Virginia (total) . . . . . . . . . . . . . . . . . . . . . . . 6.2 3.4 5.2 5.3 9.2
C. Applalachian . . . . . . . . . . . . . . . . . . . . 3.4 1.5 4.4 4.5 8.9
S. Applachian. . . . . . . . . . . . . . . . . . . . . . 2.8 1.90 0.80 0.80 0.30
Washington (total). . . . . . . . . . . . . . . . . . . . 2.9 2.9 2.9 2.9 2.9
N. Western . . . . . . . . . . . . . . . . . . . . . . . . 2.9 2.9 2.9 2.9 2.9
West Virginia (total) . . . . . . . . . . . . . . . . . . 24 23 30 44 52
N. Appalachian . . . . . . . . . . . . . . . . . . . . 1.2 1.1 0.97 0.54
C. Appalachian . . . . . . . . . . . . . . . . . . . . 23 22 29 43 52
Wisconsin (total). . . . . . . . . . . . . . . . . . . . . 12 13 9.2 10 6.5
I. Eastern . . . . . . . . . . . . . . . . . . . . . . . . . 7.5 9.3 5.9 6.9 3.5
N. Western. . . . . . . . . . . . . . . . . . . . . . . . 4,4 3.9 3.3 3.3 3.0
Wyoming (total). . . . . . . . . . . . . . . . . . . . . . 4.4 10 12 9.8 12
C .Western . . . . . . . . . . . . . . . . . . . . . . . . 4.4 10 12 9.8 12
40 NORTHERN
...,
ESTERN
TEXAS
CENTRAL WESTERN .
NOR N
(NW)
CENTRAL WESTERN
. (cw)
SOUTHWESTERN \ SOUTHERN
(SW)
NORTHWESTERN
(NW)
CENTRAL WESTERN 17
(CW)
SOUTHWESTERN \ . / SOUTHERN
(SW)
NORT
Comparison of the economic and environ- simplified projections of the coal transporta-
mental features of a world with slurry pipelines tion market, but also on crude cost estimates
to another without them requires the establish- and uncertain predictions of the behavior of
ment of plausible scenarios describing the transportation firms, their customers, and
nature of the transportation system in each government regulatory bodies. However, the
case. The critical characteristics to be purpose of this section is to derive a plausible
specified for each mode are cost and extent of if arbitrary set of market share and cost
operations. The world without pipelines in- assumptions that are sufficiently favorable to
volves a rail system which, with other present pipelines to provide a basis for comparison
modes, would meet the hypothetical demand with a no pipeline alternative.
for utility coal transportation outlined in the
last section. Under the other scenario, one en-
visions a hybrid rail and pipeline system which costs
would carry projected traffic by the cheaper
Four hypothetical case studies, described in
mode from the shippers standpoint.
Volume 11, provide the focus for both the cost
The second scenario is necessarily highly and environmental analyses of the assessment.
conjectural, depending not only on the Four coal flows from among those identified in
Ch. IV Coal Slurry Pipeline and Unit Train Systems 49
the last section were chosen and arbitrarily the application can be expressed in terms of
assigned specific States of origin as follows: the following factors:
1. C e n t r a l W e s t e r n c o a l f r o m W y o m i n g t o 1. Distance the coal must be carried.
Texas, 2. Volume of coal to be carried,
2. N o r t h w e s t e r n c o a l f r o m M o n t a n a t o 3. Moisture content of the coal.
Minnesota and Wisconsin, 4. Difference between elevations of termini.
3. C e n t r a l W e s t e r n c o a l f r o m U t a h t o 5. Terrain characteristics.
California. 6. Distance to and elevation of the water
4. S o u t h e r n AppaIachian coal from Supply.
Tennessee to Florida 7. Size and spacing of mines.
8. Size and spacing of powerplants.
These four origin and destination pairs exhibit
differences in a) region of the country, b) con- engineering design considerations, industrial
dition and circuity of the rail system, c) type of experience, and data from equipment
terrain, d) access to water, e) type and c o n c e n - manufacturers form the basis for identifying
t r a t i o n of mining activity, and f) volumes of and quantifying individual resource re-
coal to be transported. quirements as follows:
square inch. Fewer stations are therefore re- 6. Track maintenance per mile per year
quired as the diameter of the pipe increases. $5,300 plus $342 per million tons of traffic
These costs have been adjusted in the case 7. Administration
studies to account for acquisition of water and $0.30 per thousand ton-miles
for nonideal construction conditions based on Acquisition and operating costs of loading
the particular characteristics of a pipeline ap- and unloading faciIities depend on site-
plication. Areas of particular uncertainty in- specific conditions as do the amount of fuel
clude future construction costs and the ap- and track upgrading required. The amount of
propriate price for water. track investment required for a particular traf-
Rail Estimating Procedure fic element is particularly uncertain, as is the
degree to which other traffic should properly
Although operating experience for railroads be charged for some of the cost of a given im-
is more extensive than for pipelines due to the provement. Also, railroad ownership of rolling
longer history of the industry and its more stock has been assumed. If customers owned
e s t a b l i s h e d t e c h n o l o g i e s , establishing the the hopper cars, they would pay a reduced
marginal, or out-of-pocket costs for a given transportation rate and would have to finance
element of hypothetical traffic is no more the acquisition and maintenance of the cars.
.straightforward. The factors determining rail Utilities often find this arrangement advan-
costs for coal unit trains include the following: tageous. Initial investment financing, inflation,
1. Distance the coal must be carried. and taxes are all treated in the same fashion as
2. Volume of the coal to be carried. for pipelines, and the details of the
3. Unused capacity and condition of tracks methodology are also described more fulIy in
along the route. Volume II.
4. Length and speed of trains. Figure 10Slurry Facility First Costs
5. Terrain and circuity of the route. (Including an 18 percent provision for
engineering, inspection, and contingencies)
6. A d m i n i s t r a t i o n .
110
The cost elements that do not depend on Dewatering Facility
100
site-specific conditions appear below:
1. Acquisition of rolling stock
$550,000 per locomotive
$30,000 per 100 net-ton hopper car
$43,000 per caboose
2. Track improvement
Slurry Preparation
$500,000 per mile of new track
$200,000 per mile of upgraded track 50 -
4. Diesel fuel
$0.35 per gallon 20
5. O p e r a t i o n a n d m a i n t e n a n c e o f r o l l i n g 10
5
stock
$0.44 per mile per year per locomotive -o 5 10 15 20 25 30 35
$0.03 per mile per year per hopper car Million Tons Per Year, Dry Coal
$002 per mile per year per caboose Source General Research Corp
Ch. IV Coal Slurry Pipeline and Unit Train Systems 51
4
Excavation, Welding,
Installation, and Backfill
(Ideal Terrain) 3
2
Maintenance Materials
1 and Supplies
I I I I I I I
o 5 10 15 20 25 30 35
Million Tons Per Year, Dry Coal Figure 14Annual Operation and Maintenance
Source General Research Corp
Costs per Pumping Station
5 2
3
1
2
Maintenance Materials
General Administration
1
General
o I I I I I I 0
o 5 10 15 20 25 30 35
0 5 10 15 20 25 30 35
Million Tons Per Year, Dry Coal
Million Tons Per Year, Dry Coal
Source General Research Corp Source General Research Corp
52 . Coal Slurry Pipelines
Selected Case Results and Discussion producing areas, 35 percent of the track would
have to be replaced or upgraded, and trains
Table 8 illustrates the comparative
would be substantially shorter and slower than
characteristics and costs of four specific coal
i n the other cases.
flows by rail and pipeline. Pipeline transporta-
tion appears more economical in the Wyoming Other factors not mentioned above which
to Texas and Tennessee to Florida cases, and influence the relative costs of unit trains and
rail is less costly for both Montana to Min- slurry pipeIines include the expected rate of in-
nesota and Wisconsin, and for Utah to Califor- flation in labor and operating costs of electric-
nia. ity and diesel fuel, and the cost of water de-
livered at the pipeline source. To oversimplify
The Wyoming to Texas case illustrates the
somewhat, the cost of unit train transportation
advantages of carrying a large volume of coal
of coal is roughly one-third amortization of in-
in a single pipeline over a great distance. The
vestment in faciIities and equipment and two-
pipeline would be over 1,000 miles long and
thirds operating expense, including labor. Pipe-
carry 35 milIion tons per year over most of its
line costs, on the other hand represent nearly
length. To achieve this scale requires that eight
two-thirds initial investment and just over one-
powerplants in two regions of Texas be served
third continuing operation. Therefore, high
by the same pipeline, and the fact that only
rates of anticipated inflation favor pipelines
four mines near Gillette, Wyo., could produce
over rail, while high real interest rates and
the required volume contributes to the
labor productivity improvements have the op-
economy of operation.
posite effect. The cost figures derived here are
Between Montana and the destinations in based on a 6-percent annual rate of inflation
Minnesota and Wisconsin, the rail route is and a 61A-percent real interest rate, which add-
direct and in good physical condition. Train ed together, amount to a nominal discount
lengths of 105 cars and average speeds of 22 rate of 1 21/2 percent.
miles per hour, including stops for loading and
Energy resource costs also influence the
unloading, also play a role in the rail cost ad-
relative advantages of each mode. If one con-
vantage in this case, as does the railroads flex-
siders the fuel required to generate electricity,
ibility to serve economicalIy a relatively larger
raiIroads and pipelines use roughly com-
number of mines and powerplants for a given
parable amounts of energy directly to provide
volume of coal.
power for equipment. However at $0.35 per
The Utah to California case represents the gal Ion, diesel fuel represents typically about
least annual volume, the shortest distance, and one-eighth of the cost of operating a coal unit
the smallest mines served. It also represents train, while electricity at $0.026 per kilowatt
the most difficult terrain for both pipeline con- hour amounts to approximately one-fifth of
struction and rail operation, and the ad- the cost of carrying the same coal by an
vantage of trains is offset partially by their equivalent-sized pipeline. Since the energy
roughly 30-percent greater route circuity and portion of the cost is substantial, increases in
the need to replace 25 percent of the present the cost of diesel fuel relative to that of elec-
raiI. tricity will improve the competitive position of
pipelines, at least untiI electrification becomes
The only case east of the Mississippi, from
advantageous to the raiIroads.
Tennessee to Florida, illustrates that even
though several mines and powerplants would High water costs, on the other hand, can
have to be served and the rail route is not par- substantially weaken the competitive position
ticularly circuitous, pipelines may be ad- of pipelines. Carrying 18 million tons of coal
vantageous if raiI operating conditions are from Gillette, Wyo., to Dallas, Tex., for exam-
significantly less than ideal. On this route, ple, would require 8,554 acre-feet of water per
which is not necessarily typical of coal- year. If this amount were purchased for $20
Ch. IV Coal Slurry Pipeline and Unit Train Systems 53
Montana to
Characteristics Wyoming to Minnesota & Utah to Tennessee
Texas Wisconsin California to Florida
General
Number of mines ., ., . 4 3 7 8
Pipeline
W a t e r s o u r c e . Big Horn River Big Horn River Green River Lake Nickajack
Montana to
Characteristics Wyoming to Minnesota & Utah to Tennessee
Texas Wisconsin California to Florida
Rail
Percentage of track to
be upgraded . . . . . Gillette-Dallas 5 percent 10 percent 30 percent
30 percent
Gillette-Houston
20 percent
per acre-foot at Big Horn River and trans- Figure 15 Form of Typical Rail and Pipeline
ported by pipe to Gillette, the total cost would Cost Ranges for a Given Annual Tonnage
be $922 per acre-foot, or $0.47 per ton of coal
shipped. Of the totaI amount of water used,
about 4,905 acre-feet couId be extracted and
recycled by return pipeline, raising the total
water cost to $1 75 per ton of coal, Increases
of this magnitude, whether due to economic
competition for Iimited supplies of western cost
water or to institutional requirements that
water be recycled or obtained from distant or
costly sources, w i l l d i m i n i s h t h e a m o u n t o f
coaI traffic for which pipelines can compete
effectively
The following list IS a recapitulation of the
principal factors infIuencing the relative costs
of unit trains and slurry pipelines for coal
A Distance B
transportation
Source Office of Technology Assessment
1. Annual volume of coal
2 Distance to be traversed Some generalization is required to compare
Expec-ted rate of infIation
.3 the case resuIts with previous studies Figure
4 Real interest rate 16 iIIustrates the resuIts of an assortment of
5 Size and spacing of mines, other coal SIurry pipeline cost calcuIations,
6 Presence of generaI large customers to and figure 17 shows the resuIts of two other
receive coaI coaI unit train studies for comparison. In inter-
7 Terra in and excavation difficulty preting the latter, one Should note that
8 Water availability and cost reguIated tariffs are not aIways the same as
9 Relative costs of diesel fuel and costs, and that individual tariffs vary
electricity. significantly from the vaIues represented by
10 RaiIroad track circuity and condition the ICF regression Iines
11. Length and speed of trains.
The results of the case analyses developed
The principal lessons from the foregoing here appear in figure 18 Although the dif-
analysis are that a) Slurry pipelines are more ferences between any two sets of cost
economical than unit trains some specific estimates are due in part to dissimilar underly-
types of individual movements, and b) the ing assumptions and procedures, the results of
comparative costs of the two modes do not the studies taken together serve as additlonal
lend themselves to easy generalization based evidence of the wide range of unncertainty
on simple criteria The latter observation is il- associated with global generalizations about
lustrated by figure 15, which shows ranges of the relative costs of slurry pipelines and unit
rail and pipeline costs for a given v o l u m e o f trains in specific applications.
coal as they vary typicalIy with distance. The
precise cost within the range is determined by
the several factors other than volume and Traffic Assumptions
distance discussed above Note that the cost
ranges overlap between distances A and B, and Painting a plausible scenario for the purpose
that one can onIy concude with confidence of evaluating the global economic effects, as
that rail will be least costly at distances less opposed to the locaIized costs, of the develop-
than A, and that a pipeline will be more ment of a coaI sIurry pipeline industry required
economical at distances greater than B. Ignoring one of the Iessons of the cost analysis
56 . Coal Slurry Pipelines
0 I I I 1 I I 1
0 200 400 600 800 1000 1200 1400 1600 1800
Distance (Miles)
and attempting to deduce, by some general and distances above and to the right of the
criteria, which of the coal flows identified curve would be carried more economically by
earlier in table 7 might be carried by pipeline. pipeline, w h i l e r a i l w o u l d b e m o r e a d -
To accomplish this purpose, with as little vantageous otherwise. The conditions most ad-
violence to the conclusions of the cost analysis vantageous to rail are therefore represented by
as possible, a s s u m e d d i s t a n c e s a n d c o a l the characteristics of the Montana to Becker,
volumes were varied artificially and calcula- Minn., c o r r i d o r , w h i l e t h o s e f e a t u r e s m o s t
tions repeated to determine those combina- favorable to pipelines exist between Tennessee
tions of values for which rail and pipeline costs and Tampa, Fla., provided that one does not
are equal under the conditions governing each consider volume and distance.
of the four cases. For simplicity, the computa-
The flows of coal from producing regions to
tion included only a single destination region
consuming States in the transportation de-
for each movement, and the resulting indif-
mand scenario could be compared to the indif-
ference curves appear in figure 19.
ference curves and assigned to pipelines
For each set of conditions, traffic volumes whenever the combinations of distance and
C h . IV Coal Slurry Pipeline and Unit Train Systems 5 7
sustained volume felI in the region favorable served by raiI because of the simiIarity of con-
to pipelines under all four sets of case condi- ditions to the Montana to M i n n e s o t a and
tion, and barge transportation was not an ob- Wisconsin case, and finally, the Georgia coal
vious competitor. Only Central Western coal was considered unlikely to justify pipeline con-
destined for Indiana and Texas falls in this struction because of the terrain along the
category. Five other flows fall in a region of route,
uncertainty between the two extreme indif-
ference curves: Central Western to Missouri, A highly speculative but plausible traffic
Kansas, and IIlinois; I n t e r i o r E a s t e r n t o scenario derived in this necessarily somewhat
Georgia; and Southern Appalachian to Florida. arbitrary manner is illustrated in table 9. All
Of these, the Florida traffic was assigned to other coal is assumed to travel by another
pipeline because of the results of examining mode, probably rail or barge, These postulated
that specific case, Missouri and Kansas traffic volumes are in no way intended as a projection
was assigned to pipeline because of similarity of pipeline market penetration. They only pro-
to the Texas case and the possibility of sharing vide a starting point for an analysis of what
a common pipeline, IIlinois was assumed to be might happen if the equivalent of approx-
58 . Coal Slurry P i p e l i n e s
Figure 18 Results of Case Studies Comparing Coal Slurry Pipeline and Unit Train Costs
3.5
RR17
RC35
10
o I I I I I I I I
o 200 400 600 800 1000 1200 1400 1600 1800
Distance (Miles) (No Clrcuity)
Origin Year
Destination 1985 1990 1995 2000
Central Western
Indiana. . . . . . . . 17 17 17 17
Kansas. . . . . . . . 19 19
Missouri. . . . . . . 14 14 14 14
Texas . . . . . . . . . 35 72 93 125
Southern Appalachian
Florida . . . . . . . . 16 16 16 32
Total . . . . . . 82 119 159 207