You are on page 1of 242

ROADWAY DESIGN MANUAL Roads and Bridges

Table of Contents Page No.


PART 1: ROADWAY DEVELOPMENT
SECTION 100: GENERAL INFORMATION
101 PURPOSE 100-1
101.01 INTRODUCTION 100-1
102 CONTENTS AND ORGANIZATION 100-1
102.01 PART 1: ROADWAY DEVELOPMENT 100-1
102.02 PART 2: ROADWAY DESIGN 100-2
102.03 PART 3: STRUCTURES AND BRIDGES 100-2
103 TECHNICAL MEMORANDUMS 100-2
103.01 GENERAL 100-2
103.02 TECHNICAL MEMORANDUMS - GENERAL 100-2
103.03 TECHNICAL MEMORANDUMS - SPECIFIC 100-3
104 ROADWAY CLASSIFICATIONS 100-3
104.01 ROADWAY SYSTEM 100-3
104.02 DESIGN 100-3
104.03 CRITERIA FOR DESIGN CLASS DESIGNATION 100-3
105 ROUTE DESIGNATIONS 100-5
105.01 INTRODUCTION 100-5
105.02 ROUTE NUMBERS 100-5
105.03 ADDITIONS, DELETIONS, AND REVISIONS 100-5

SECTION 200: DESIGN CONCEPT DEVELOPMENT


201 TRANSPORTATION PLANNING 200-1
201.01 INTRODUCTION 200-1
201.02 ROAD SECTION 200-1
201.03 TOWN PLANNING 200-1
201.04 MAPPING 200-1
201.04.01 General 200-1
201.04.02 Topographic Mapping 200-2
201.05 PROJECT LIMITS 200-2
201.06 PROJECT IDENTIFICATION AND NUMBERING 200-6
201.07 INTERDEPARTMENTAL COORDINATION 200-6
202 ENVIRONMENTAL FACTORS INFLUENCING DESIGN 200-6
202.01 INTRODUCTION 200-6
202.02 SOCIOECONOMIC/COMMUNITY RESOURCE DATA 200-6
202.02.01 Land Use 200-6
202.02.02 Growth Projections 200-7
202.02.03 Public Services 200-7
202.02.04 Schools 200-7
202.02.05 Mosques 200-8
202.02.06 Utilities 200-8
202.02.07 Security 200-8
202.02.08 Commercial Activities 200-9
202.02.09 Economics 200-9
202.02.10 Local Transportation/Circulation 200-9
202.02.11 Parking Requirements 200-9
202.02.12 Recreation 200-10
202.02.13 Historical Site Identification and Preservation 200-10
202.03 NATURAL/ENVIRONMENTAL RESOURCE DATA 200-10
202.03.01 Landscape Preservation 200-10
202.03.02 Topography 200-11
202.03.03 Water 200-11
202.03.04 Wildlife 200-11
202.03.05 Air Quality 200-11
202.03.06 Noise 200-11

Page -1-
ROADWAY DESIGN MANUAL Roads and Bridges

Table of Contents Page No.


202.03.07 Visual/Aesthetic 200-11
202.03.08 Hazardous Materials 200-11
202.04 ENVIRONMENTAL CHECKLIST 200-12
203 TECHNICAL INVESTIGATIONS 200-12
203.01 INTRODUCTION 200-12
203.02 GEOTECHNICAL ENGINEERING 200-12
203.03 TRAFFIC COUNTS 200-12
203.03.01 Introduction 200-12
203.03.02 Traffic Projections 200-13
203.03.03 Procedures for Traffic Volumes 200-14
203.04 SURVEY CONTROL/FIELD SURVEYS 200-14
203.04.01 Introduction 200-14
203.04.02 Horizontal Control 200-14
203.04.03 Vertical Control 200-14
203.04.04 Coordinate System 200-14
203.04.05 Field Surveys 200-14
203.5 DRAINAGE SURVEYS 200-15

SECTION 300: DESIGN CONCEPT REPORT


301 CONTENTS 300-1
301.01 FORMAT 300-1
302 EXECUTIVE SUMMARY 300-3
303 INTRODUCTION 300-3
304 TRAFFIC ANALYSIS 300-3
305 DESCRIPTION OF ALTERNATIVES 300-3
306 DESIGN DATA 300-4
307 TYPICAL SECTIONS 300-4
308 GEOMETRICS 300-4
309 INTERCHANGE/ INTERSECTION CONFIGURATION 300-5
310 PARKING STUDY 300-5
311 HYDROLOGY AND HYDRAULICS 300-5
311.01 PURPOSE 300-6
311.02 PLANNING & PREPARATION OF THE DRAINAGE DESIGN CONCEPTS 300-6
311.02.01 Problem Categories 300-7
311.02.02 Flood Plain Encroachment and Risk Evaluation 300-9
311.02.03 Data Collection 300-10
311.03 STORM WATER HYDROLOGY 300-14
311.04 OPEN CHANNEL HYDRAULICS 300-15
311.05 BRIDGE HYDRAULICS 300-16
311.05.01 Bridge Location and Hydraulics Report 300-16
311.05.02 Bridge Hydraulics Recommendations Sheet (BHRS) 300-19
311.06 STORMWATER MANAGEMENT USING RETENTION/DETENTION DESIGN 300-20
312 SUBSURFACE INVESTIGATIONS 300-21
313 BRIDGE TYPE SELECTION 300-21
313.01 BRIDGES OVER WATERWAYS 300-22
313.02 WIDENINGS/REHABILITATION 300-22
313.03 BRIDGE SELECTION REPORT 300-22
314 UTILITY IMPACT ANALYSIS 300-23
315 SOCIOECONOMIC ANALYSIS 300-23
316 AGRICULTURE IMPACT 300-23
317 PUBLIC FEEDBACK 300-24
318 SIGNING AND PAVEMENT MARKINGS 300-24
319 LIGHTING CONCEPTS 300-24
320 CONSTRUCTION STAGING 300-24
321 COST ESTIMATE 300-25
322 CONCLUSIONS/RECOMMENDATIONS 300-25
Page -2-
ROADWAY DESIGN MANUAL Roads and Bridges

Table of Contents Page No.


323 APPENDIX 300-25
324 DRAWINGS 300-25

PART 2: ROADWAY DESIGN


SECTION 100: GENERAL DESIGN CRITERIA
101 DESIGN SPEED 100-1
102 DESIGN VEHICLES 100-3
103 DESIGN TRAFFIC 100-3
103.01 DESIGN PERIOD 100-3
103.02 RELATION TO DESIGN 100-3
104 ROADWAY CAPACITY 100-3
104.01 DESIGN CAPACITIES 100-3
104.01.01 Multi-lane Rural Roadway 100-4
104.01.02 Two Lane Roadways 100-4
104.01.03 Expressways 100-5
104.01.04 Expressway Ramps and Weaving Sections 100-5
104.01.05 Intersection Capacity 100-5
105 CONTROL OF ACCESS 100-5
105.01 GENERAL 100-5
105.02 ACCESS CONTROL DESIGN CRITERIA 100-5
105.02.01 Primary Roadways 100-5
105.02.02 Secondary Roadways, ADT > 2500 100-6
105.02.03 Secondary Roadways, ADT < 2500 100-6
105.03 USE OF FRONTAGE ROADS 100-7
105.04 PROTECTION OF ACCESS RIGHTS 100-7
106 DESIGN STANDARD EXCEPTIONS 100-7
107 BICYCLE FACILITIES 100-9
107.01 GENERAL 100-9
107.02 SPECIAL BICYCLE FACILITIES 100-9
107.03 BICYCLE CHARACTERISTICS 100-9
107.04 BICYCLES AT INTERSECTIONS 100-9

SECTION 200: GEOMETRIC DESIGN STANDARDS


201 SIGHT DISTANCE 200-1
201.01 GENERAL 200-1
201.02 PASSING SIGHT DISTANCE 200-1
201.03 STOPPING SIGHT DISTANCE 200-1
201.04 STOPPING SIGHT DISTANCE AT GRADE CRESTS 200-1
201.05 STOPPING SIGHT DISTANCE AT GRADE SAGS 200-3
201.06 STOPPING SIGHT DISTANCE ON HORIZONTAL CURVES 200-3
201.07 DECISION SIGHT DISTANCE 200-3
202 SUPERELEVATION 200-3
202.01 GENERAL 200-3
202.02 SUPERELEVATION STANDARDS 200-4
202.03 CITY ROAD CONDITIONS 200-4
202.04 AXIS OF ROTATION 200-6
202.05 SUPERELEVATION TRANSITION 200-6
202.06 SUPERELEVATION OF COMPOUND CURVES 200-6
203 HORIZONTAL ALIGNMENT 200-9
203.01 GENERAL 200-9
203.02 STANDARDS FOR HORIZONTAL CURVATURE 200-9
204 VERTICAL ALIGNMENT 200-10
204.01 GENERAL 200-10
204.02 VERTICAL ALIGNMENT POSITION WITH RESPECT TO CROSS SECTION 200-10
204.03 STANDARDS FOR GRADES 200-10

Page -3-
ROADWAY DESIGN MANUAL Roads and Bridges

Table of Contents Page No.


204.04 VERTICAL CURVES 200-11
204.05 LONG SUSTAINED GRADES 200-11
204.06 STRUCTURE GRADE LINE 200-11
204.07 SEPARATE PROFILE GRADE LINES 200-16
205 COORDINATION OF HORIZONTAL AND VERTICAL ALIGNMENTS 200-16
206 PAVEMENT TRANSITIONS 200-16
206.01 GENERAL 200-16
206.02 TRANSITIONS FOR MULTILANE ROADWAYS 200-16
207 BRIDGES AND GRADE SEPARATION STRUCTURES 200-18
207.01 CLEAR WIDTH 200-18
207.02 CROSS SLOPE 200-18
207.03 SIDEWALKS 200-18
208 PEDESTRIAN FACILITIES 200-18
208.01 SIDEWALKS 200-18
208.02 PEDESTRIAN GRADE SEPARATIONS 200-18
208.03 PEDESTRIAN UNDERPASSES 200-18
209 CURBS 200-18
209.01 GENERAL 200-18
209.02 TYPES AND USES 200-19
209.03 CURB PARAMETERS 200-19
210 BUS STOPS AND TAXI STOPS 200-19
210.01 BUS STOPS 200-19
210.02 TAXI STOPS 200-19
211 PARKING 200-20
211.01 GENERAL 200-20
211.02 PARKING AREAS 200-20
211.03 ON ROAD PARKING SPACES 200-20
211.04 PARKING LOTS 200-21
211.05 PARKING DEMAND/SUPPLY ANALYSIS 200-21

SECTION 300: GEOMETRIC CROSSECTIONS


301 TRAVELLED WAY STANDARDS 300-1
301.01 TRAVELLED WAY WIDTH 300-1
301.02 TRAVELLED WAY CROSS SLOPES 300-1
302 SHOULDER STANDARDS 300-1
302.01 SHOULDER WIDTH STANDARDS 300-1
302.02 SHOULDER CROSS SLOPES 300-1
303 SIDE SLOPE STANDARDS 300-1
303.01 SIDE SLOPE VALUES 300-2
303.02 SLOPE CLEARANCE FROM RIGHT OF WAY 300-2
304 MEDIAN STANDARDS 300-2
305 CROSS SECTION ELEMENTS 300-2
305.01 RURAL FREEWAY/EXPRESSWAY CROSS SECTION 300-2
305.02 URBAN FREEWAY/EXPRESSWAY CROSS SECTION 300-2
305.03 ARTERIAL (MAIN ROAD) CROSS SECTION 300-4
305.04 SECTOR ROAD CROSS SECTION 300-5
305.05 FRONTAGE ROAD CROSS SECTION 300-5
306 HORIZONTAL AND VERTICAL CLEARANCES 300-5
306.01 HORIZONTAL CLEARANCES 300-5
306.02 VERTICAL CLEARANCES 300-6
306.03 TUNNEL CLEARANCES 300-6
307 CLEAR ZONE CONCEPT 300-6
307.01 APPLICATION OF CLEAR ZONE 300-8
307.01.01 Roadside Terrain: Foreslope 300-8
307.01.02 Roadside Terrain: Backslope 300-9
307.01.03 Roadside Terrain: Cross-slope 300-9
Page -4-
ROADWAY DESIGN MANUAL Roads and Bridges

Table of Contents Page No.


307.01.04 Roadside Terrain: Ditch 300-9
308 BARRIERS 300-11
308.01 BARRIER NEED 300-11
308.02 ROADSIDE BARRIER TYPES AND FEATURES 300-11
308.03 ROADSIDE BARRIER PLACEMENT 300-12
308.03.01 Lateral Placement 300-12
308.03.02 Barrier to Hazard Clearances 300-12
308.03.03 Effects of Roadside Terrain 300-13
308.03.04 Barrier Length Design 300-13
308.04 MEDIAN BARRIERS 300-15
308.04.01 Median Barrier Warrants 300-15
308.04.02 Median Barrier Types and Features 300-15
308.05 MEDIAN BARRIER PLACEMENT 300-15
308.05.01 Median Geometry 300-15
308.05.02 Treatment of Fixed Object Hazards 300-16
308.06 END TREATMENTS AND CRASH CUSHIONS 300-16
308.06.01 End Treatments 300-16
308.06.02 Crash Cushion-Selection Guidelines 300-18
308.06.03 Placement Recommendations 300-18

SECTION 400: AT-GRADE INTERSECTIONS


401 GENERAL 400-1
402 DESIGN CONSIDERATIONS 400-1
403 AT GRADE INTERSECTION TYPES 400-1
404 CHANNELIZATION 400-2
404.01 PREFERENCE TO MAJOR MOVEMENTS 400-2
404.02 AREAS OF CONFLICT 400-2
404.03 INTERSECTION ANGLES 400-2
404.04 POINTS OF CONFLICT 400-2
404.05 SPEED-CHANGE LANES 400-3
404.06 TURNING MOVEMENTS 400-3
404.07 REFUGE AREAS 400-3
404.08 PROHIBITED TURNS 400-3
404.09 EFFECTIVE SIGNAL CONTROL 400-3
404.10 INSTALLATION OF TRAFFIC CONTROL DEVICES 400-3
404.11 GUIDELINES 400-3
405 DESIGN VEHICLES 400-4
405.01 OFF TRACKING 400-4
405.02 DESIGN VEHICLES 400-4
405.03 TURNING TEMPLATES 400-4
406 INTERSECTION DESIGN STANDARDS 400-4
406.01 SIGHT DISTANCE 400-4
406.02 EFFECT OF SKEW 400-10
406.03 EFFECT OF VERTICAL PROFILES 400-13
406.04 LEFT-TURN CHANNELIZATION 400-13
406.05 RIGHT-TURN CHANNELIZATION 400-14
406.06 TRAFFIC ISLANDS 400-14
407 ROUNDABOUT DESIGN 400-15

SECTION 500: INTERCHANGES


501 GENERAL 500-1
502 INTERCHANGE WARRANTS 500-1
503 DESIGN CONSIDERATIONS 500-1
504 INTERCHANGE TYPES 500-1
504.01 THREE-LEG INTERCHANGE 500-1
504.02 FOUR-LEG INTERCHANGES 500-3
Page -5-
ROADWAY DESIGN MANUAL Roads and Bridges

Table of Contents Page No.


505 INTERCHANGE DESIGN PROCEDURES 500-8
506 INTERCHANGE DESIGN STANDARDS 500-8
507 RAMP DESIGN STANDARDS 500-9
508 ENTRANCE/ EXIT RAMP DESIGN STANDARDS 500-11
508.01 RAMP TERMINAL DESIGN 500-16

SECTION 600: GEOTECHNICAL ENGINEERING


601 INTRODUCTION 600-1
602 GENERAL 600-1
603 GEOTECHNICAL REPORT 600-1
604 STRUCTURAL PAVEMENT SECTION DESIGN 600-2
604.01 GENERAL 600-2
604.01.01 Pavement Design Methods 600-2
604.01.02 Comparison of Design Results 600-4
604.02 PAVEMENT DESIGN METHOD 600-5

SECTION 700: DRAINAGE


701 GENERAL 700-1

SECTION 800: UTILITIES


801 GENERAL 800-1
802 UTILITY PLANNING 800-1
803 SERVICE RESERVATIONS 800-2
804 UTILITY DESIGN 800-3
804.01 GENERAL 800-3
804.02 UTILITY PROTECTION 800-3
804.03 UTILITY RELOCATION 800-4
804.04 CONTINGENCY DUCTS 800-4
804.05 UTILITY LOCATIONS 800-4
804.06 NON-DISRUPTIVE ROAD CROSSINGS 800-4

SECTION 900: TRAFFIC ENGINEERING


901 TRAFFIC OPERATIONAL ANALYSIS 900-1
901.01 GENERAL 900-1
901.02 OPERATIONAL ANALYSIS 900-1
902 SIGNALIZATION 900-1
902.01 TRAFFIC SIGNAL DESIGN 900-1
902.02 SIGNALS, POLES, AND CONTROLLERS 900-2
902.03 DUCTS AND PULLBOXES 900-3
902.04 PYLONS 900-3
903 TRAFFIC SURVEILLANCE 900-3
904 SIGNING 900-3
904.01 SIGN STRUCTURE INSTALLATIONS 900-4
904.01.01 Ground Mounted 900-4
904.01.02 Overhead Mounted 900-4
904.02 SIGN SHEETING 900-5
904.03 SIGN TYPES 900-5
904.03.01 Regulatory And Warning Signs 900-5
904.03.02 Guide Signs 900-5
904.04 FINAL SIGNING PLAN REQUIREMENTS 900-5
904.05 ARABIC LETTERING FOR GUIDE SIGNS 900-10
904.05.01 General 900-10
904.05.02 The Arabic Alphabet 900-10
904.05.03 Use of the Standard Arabic Script 900-10
904.06 GUIDE SIGN DIMENSIONS 900-10

Page -6-
ROADWAY DESIGN MANUAL Roads and Bridges

Table of Contents Page No.


904.06.01 Single Message Guide Signs (Example 900-02) 900-10
904.06.02 Multiple Message Guide Signs (Example 900-03) 900-12
904.07 STANDARD ARABIC SCRIPT FOR HIGHWAY SIGNS 1 OF 14 900-15
904.08 SIGN LIGHTING 900-29
904.09 SIGN LUMINARES 900-29
905 PAVEMENT MARKINGS 900-29
905.01 GENERAL 900-29
905.02 TYPES OF PAVEMENT MARKINGS 900-29
905.02.01 Lane Markings 900-29
905.02.02 Stop Line Markings 900-30
905.02.03 Pedestrian Crossing Markings 900-30
905.02.04 Channelization Markings 900-30
905.02.05 Pavement Edge Markings 900-30
905.02.06 Parking Space Markings 900-30
905.02.07 Pavement Symbols 900-30
906 MAINTENANCE OF TRAFFIC 900-30
906.01 CONSTRUCTION STAGING 900-30
906.02 SAFETY MEASURES 900-31
906.03 TEMPORARY TRAFFIC SIGNALS 900-31
906.04 MAINTENANCE OF TRAFFIC PLANS 900-31

SECTION 1000: LIGHTING


1001 ROADWAY LIGHTING 1000-1
1001.01 GENERAL 1000-1
1001.02 LIGHTING DESIGN CONSIDERATIONS 1000-1
1001.03 ILLUMINATION REQUIREMENTS 1000-2
1002 PARKING AREA LIGHTING 1000-3
1002.01 GENERAL 1000-3
1002.02 ILLUMINATION REQUIREMENTS 1000-3
1002.03 LANTERN MOUNTING HEIGHT 1000-4
1002.04 LANTERN SELECTION 1000-4
1003 SIDEWALK LIGHTING 1000-4
1003.01 GENERAL 1000-4
1003.02 ILLUMINATION REQUIREMENTS 1000-4
1003.03 LANTERN MOUNTING HEIGHT 1000-4
1003.04 LANTERN SELECTION 1000-4
1004 LIGHTING CONTROLS 1000-4
1004.01 GENERAL 1000-4
1004.02 LIGHTING CONTROLLER REQUIREMENTS 1000-4
1004.03 DESIGN STANDARDS AND PROCEDURES 1000-4
1005 POWER DISTRIBUTION 1000-4
1006 DESIGN AND SUPERVISION RESPONSIBILITIES 1000-5

SECTION 1100: ROADSIDE DEVELOPMENT


1101 LANDSCAPING 1100-1
1102 IRRIGATION 1100-1
1102.01 IRRIGATION DUCTS 1100-1
1103 FENCING 1100-2
1104 SLOPE PAVING 1100-2
1105 SWEET SAND COVERING 1100-2
1106 STREET FURNITURE 1100-2
1106.01 GENERAL 1100-2
1106.02 DESIGN 1100-2
1106.03 BENCHES 1100-2
1106.03.01 Type A bench 1100-2
1106.03.02 Type B bench 1100-2
Page -7-
ROADWAY DESIGN MANUAL Roads and Bridges

Table of Contents Page No.


1106.03.03 Type C bench 1100-3
1106.04 BUS SHELTERS 1100-3
1106.05 TELEPHONE BOOTHS 1100-3
1107 NOISE ABATEMENT 1100-3

PART 3: STRUCTURE DESIGN


SECTION 100: DESIGN CRITERIA
101 GENERAL 100-1
101.01 PURPOSE 100-1
101.02 DEFINITIONS 100-1
101.03 BRIDGE TYPES 100-1
102 DESIGN FEATURES 100-2
102.01 GENERAL 100-2
102.02 DESIGN METHODS 100-2
102.03 VERTICAL CLEARANCE AT STRUCTURES 100-2
102.03.01 Highway Traffic Structures 100-2
102.03.02 Pedestrian Overpasses 100-2
102.03.03 Railroad Overpasses 100-2
102.03.04 Tunnels 100-3
102.03.05 Sign Structures 100-3
102.03.06 Width 100-3
102.04 RAILINGS 100-3
102.05 CONCRETE BARRIER TRANSITIONS 100-3
102.06 APPROACH SLABS 100-3
102.07 ANCHOR SLABS 100-3
102.08 DECK DRAINAGE 100-3
102.09 WING WALLS 100-4
102.10 LIGHTING 100-4
102.11 BRIDGE DECK ELEVATIONS 100-4
102.12 CONCRETE CRACK CONTROL 100-4
102.13 CORROSION PROTECTION 100-4
103 ARCHITECTURAL CONSIDERATIONS 100-4
103.01 PROCEDURE 100-4
103.02 GENERAL CRITERIA 100-5

SECTION 200: DESIGN LOADS


201 LOAD TYPES 200-1
201.01 GENERAL 200-1
201.02 DEAD LOADS 200-1
201.03 FUTURE WEARING SURFACE 200-1
201.04 WEARING SURFACE 200-1
201.05 HIGHWAY LOADS 200-1
201.06 STRUCTURE LOADINGS 200-1
201.07 FRICTION FORCES 200-1
201.08 THERMAL FORCES 200-1
201.09 STREAM FORCES 200-1
201.10 LATERAL EARTH PRESSURE 200-3
201.11 DIFFERENTIAL SETTLEMENT 200-3
201.12 EARTHQUAKES 200-3
202 DISTRIBUTION OF LOADS 200-4
202.01 SUPERIMPOSED DEADLOAD DISTRIBUTION 200-4
202.02 CONCRETE BOX GIRDERS 200-4
202.03 PRESTRESSED VOIDED SLABS 200-4
202.04 PRESTRESSED BOX BEAMS 200-4
202.05 LATERAL TENSIONING OF MULTI-BEAM UNITS 200-5

Page -8-
ROADWAY DESIGN MANUAL Roads and Bridges

Table of Contents Page No.


202.06 LIVE LOAD DISTRIBUTION 200-5
203 LOAD FACTORS 200-5

SECTION 300: REINFORCED CONCRETE


301 GENERAL 300-1
301.01 CONCRETE 300-1
301.02 DIAPHRAGMS 300-1
301.03 DESIGN METHODS 300-1
301.04 REINFORCEMENT 300-1
302 SLAB DESIGN 300-1
302.01 SPAN LENGTHS 300-2
302.02 SLAB THICKNESS 300-2
302.03 PROTECTION AGAINST CORROSION 300-2
302.04 DISTRIBUTION METHOD 300-2
302.05 RAILING LOADS 300-2

SECTION 400: PRESTRESSED CONCRETE


401 DESIGN CRITERIA 400-1
401.01 GENERAL 400-1
401.02 ALLOWABLE STRESSESCONCRETE 400-1
401.03 SHEAR 400-1
402 POST TENSIONED BOX GIRDER BRIDGES 400-2
402.01 GENERAL 400-2
402.02 CONCRETE 400-2
402.03 BEARING PADS 400-2
402.04 CREEP AND SHRINKAGE 400-2
402.05 FLANGE AND WEB THICKNESS - BOX GIRDERS 400-2
402.06 DIAPHRAGMS 400-2
402.07 DEFLECTIONS 400-2
402.08 ALLOWABLE STRESSES - PRESTRESSING STEEL 400-2
402.09 ALLOWABLE STRESSES-CONCRETE 400-2
402.10 LOSS OF PRESTRESS 400-3
402.11 FLEXURAL STRENGTH 400-3
402.12 SHEAR 400-3
402.13 FLANGE REINFORCEMENT 400-3
402.14 METHOD OF ANALYSIS 400-3
403 PRECAST PRESTRESSED CONCRETE 400-4
403.01 CONCRETE 400-4
403.02 DEFLECTIONS 400-4
403.03 ALLOWABLE STRESSES-PRESTRESSING STEEL 400-4
403.04 ALLOWABLE STRESSES-CONCRETE 400-5
403.05 LOSS OF PRESTRESS 400-5
403.06 SHEAR 400-5
403.07 METHOD OF ANALYSIS 400-5
404 PRESTRESSED I-GIRDERS 400-5
404.01 GENERAL 400-5
404.02 CONCRETE 400-5
404.03 EFFECTIVE FLANGE WIDTH 400-6
404.04 SHEAR 400-6
404.05 INTERMEDIATE DIAPHRAGMS 400-6
404.06 BEARING PADS 400-6
404.07 CREEP FACTOR 400-6
404.08 FRAMES AND CONTINUOUS CONSTRUCTION 400-6
404.09 DIFFERENTIAL SHRINKAGE 400-7
404.10 METHOD OF ANALYSIS 400-7
405 PRESTRESSSED VOIDED SLABS 400-7
Page -9-
ROADWAY DESIGN MANUAL Roads and Bridges

Table of Contents Page No.


405.01 END BLOCKS 400-7
405.02 DIAPHRAGMS 400-7
405.03 LATERAL TIES 400-7
405.04 SHEAR KEYS 400-7
405.05 BARRIERS 400-7
406 PRESTRESSED BOX BEAMS 400-7
406.01 END BLOCKS 400-7
406.02 DIAPHRAGM 400-7
406.03 LATERAL TIES 400-7
406.04 SHEAR KEYS 400-7

SECTION 500: STRUCTURAL STEEL


501 DESIGN CRITERIA 500-1
501.01 GENERAL 500-1
501.02 DESIGN METHODS 500-1
501.03 MATERIALS 500-1
501.04 ALLOWABLE FATIGUE STRESS 500-1
501.05 LOAD CYCLES 500-1
501.06 CHARPY V-NOTCH IMPACT REQUIREMENTS 500-1

SECTION 600: EXPANSION AND CONTRACTION


601 MOVEMENT CRITERIA 600-1
601.01 MOVEMENT RATING 600-1
602 DECK JOINTS 600-1
602.01 GENERAL 600-1
602.02 COMPRESSION SEALS 600-2
602.03 STRIP SEALS 600-2
602.04 MODULAR JOINTS 600-2
603 BEARINGS 600-2
603.01 GENERAL 600-2
603.02 NEOPRENE STRIPS 600-3
603.03 ELASTOMERIC BEARING PADS 600-3
603.04 STEEL BEARINGS 600-4
603.05 SLIDING ELASTOMERIC BEARINGS 600-4
603.06 HIGH-LOAD MULTI-ROTATIONAL BEARINGS 600-4
603.06.01 Description 600-4
603.06.02 Rotational Requirements 600-5
603.06.03 Use 600-5
603.06.04 Design Criteria 600-5
603.07 BEARING SCHEDULE 600-7
604 RESTRAINING DEVICES 600-7
604.01 GENERAL 600-7
604.02 VERTICAL FIXED RESTRAINERS 600-7
604.03 VERTICAL EXPANSION RESTRAINERS 600-8
604.04 EXTERNAL SHEAR KEYS 600-8
604.05 INTERNAL SHEAR KEYS 600-8
604.06 KEYED HINGE 600-8

SECTION 700: GEOTECHNICAL


701 FOUNDATIONS 700-1
701.01 GENERAL 700-1
701.02 SPREAD FOOTINGS 700-1
701.03 PILE FOUNDATIONS 700-1
701.04 DRIVEN PILES 700-2
701.05 BORED PILES 700-2

Page -10-
ROADWAY DESIGN MANUAL Roads and Bridges

Table of Contents Page No.

SECTION 800: RETAINING WALLS


801 DESIGN CRITERIA 800-1
801.01 GENERAL 800-1
801.02 POLICY 800-1
801.03 RESPONSIBILITIES 800-1
801.03.01 Roadway Design Section 800-1
801.03.02 Geotechnical Section 800-2
801.03.03 Bridge Design Section 800-2
801.04 PROPRIETARY RETAINING WALLS 800-2

SECTION 900: MISCELLANEOUS


901 TRAFFIC STRUCTURAL SUPPORTS 900-1
901.01 GENERAL 900-1
901.02 WIND SPEED 900-1
901.03 ALLOWABLE STRESSES 900-1
902 UTILITIES IN STRUCTURES 900-1
902.01 GENERAL 900-1
902.02 POLICY 900-2
902.03 UTILITY AGENCY RESPONSIBILITY 900-2
902.04 BRIDGE GROUP RESPONSIBILITY 900-2
903 FALSEWORK POLICY FOR BRIDGE CONSTRUCTION 900-3
903.01 FALSEWORK REQUIREMENTS 900-3
903.02 FALSEWORK USE 900-3
903.03 FALSEWORK CLEARANCES 900-3
904 CONSTRUCTION JOINT GUIDELINES FOR BRIDGE CONSTRUCTION 900-5
904.01 GENERAL 900-5
904.02 LONGITUDINAL CONSTRUCTION JOINTS 900-5
904.03 PRECAST CONCRETE GIRDER BRIDGES 900-5
904.04 STEEL GIRDER BRIDGES 900-6
904.05 CAST-IN-PLACE BOX GIRDER BRIDGES 900-6

Page -11-
ROADWAY DESIGN MANUAL Roads and Bridges

PART 1 complete. The companion documents to this


manual are:
ROADWAY DEVELOPMENT
! Standard Specifications for Roads and
Bridge Construction - 1996
SECTION 100 ! Consultant Procedures Manual - 1997
GENERAL INFORMATION ! Roadway Standard Drawings - 1996
! Construction Supervision Manual - 1997
101 PURPOSE
Where the Consultant's scope of work and this
101.01 INTRODUCTION manual conflict, the scope of work shall govern.

The Manual is intended to serve as a guide for the Revisions and additions to this manual will be
design of the roads and highways that fall under issued from time to time as required. This section
the jurisdiction of the Road Section, Abu Dhabi contains information regarding technical
Municipality. The Manual provides a range of memorandums used to submit future revisions
acceptable values for critical dimensions and and additions.
outlines parameters that will help designers
conform to the expectations of the Road Section Further contained in this section is an overview of
of the Abu Dhabi Municipality. It is assumed the layout of the manual content, roadway
that the user has the educational and engineering classifications, route designations connecting
experience necessary to properly implement its U.A.E cities and emirates, and streets and place
procedures, guidelines and criteria. names as assigned by Abu Dhabi Municipality.

It is perceived that this manual will promote the 102 CONTENTS AND
following: ORGANIZATION

1. All designs will be based on identical The scope of the Roadway Design Manual is
criteria. comprehensive, and is divided into three parts.
2. Plans will have a consistent, The three parts are further divided into sections,
well-organized format which will not each with appropriate sub-sections. The three
vary greatly from project to project. parts are:
3. Familiarization of criteria and procedures
will be simplified. Part 1 Roadway Development
4. The technical review process will be Part 2 Roadway Design
expedited for both the Road Section and Part 3 Structures and Bridges
the Consultant.
5. Cost efficiencies will be realized during 102.01 PART 1: ROADWAY
design by an early understanding of DEVELOPMENT
procedures and criteria to be employed.
The purpose of the Roadway Development part is
The manual is presented in loose-leaf form to to outline the information and data which must be
facilitate revisions and additions. This manual analyzed to determine a projects scope. This
utilized established analysis techniques and design information and analyses are assembled into a
standards from recognized technical associations Design Concept Report, which becomes the basis
that are listed as references in Appendix A. for the project design.

When the Roadway Design Manual is combined The Roadway Development part is divided into
with the four companion documents listed below, three sections. The first section explains the
the standardization of the planning, design and formal organization of this manual and the other
construction of roadway projects will be two sections, the Design Concept Development

Part 1 100-1
ROADWAY DESIGN MANUAL Roads and Bridges

and the Design Concept Reports, define the Roadway Design part, this document is intended
conceptual design of the project. to be used in conjunction with the Standard
Specifications and the Abu Dhabi Standard
The Design Concept Section includes subsections Drawings for the standardization of details for
in Transportation Planning, Socio-economic structures and bridges.
Data, and Technical Investigations. Conceptual
Design must be based upon site specific Uniform design and construction of structures and
community considerations that reflect military, bridges promotes efficiency of design,
utility, environmental features, physical properties construction, and maintenance. This part focuses
of the site, and circulation that define the project on features incorporating sound design and cost-
design. To support the lands intended use, effective design practices to meet this goal.
procurement of the information from departments
within the Municipality and outside of This part consists of nine sections that cover the
Municipalitys organization is required. general aspects of structures and bridge design.
Subjects covered include, General Design
All the Project-specific data collected forms the Criteria, Design Loads, Reinforced Concrete,
basis for the Design Concept Report, a summary Prestressed Concrete, Structural Steel,
of the technical analyses and schematic design Expansions and Contractions, Geotech and
that are to be used for plan preparation and Retaining Walls. The last section addresses
construction. miscellaneous items such as Traffic Supports,
Utilities and the Falsework Policy and
102.02 PART 2: ROADWAY DESIGN Requirements.

The purpose of the Roadway Design part is to 103 TECHNICAL MEMORANDUMS


identify the design standards that all roadway
projects are required to meet. The project design 103.01 GENERAL
is based on these standards. When used in
conjunction with the Standard Specifications for This manual will be supplemented from time to
Road and Bridge Construction, and Abu Dhabi time with technical memorandums (TM)
Roadway Standard Drawings, the resulting addressed to the Consultants for the purpose of
project plans and specifications for all projects transmitting and formalizing appropriate revisions
are completed to the same requirements and or additions, to the manual. This manual can
format. only be revised by the issuance of a TM
authorized and signed by the Chief of Road
Specifically, the Roadway Design Part provides Section, Abu Dhabi Municipality or his
details in geometric design standards for each designated representative. Technical
component of the roadway project. The memorandums will be developed and issued as
information is divided into eleven sections that two distinct types, general and specific, and are
include General Design Criteria, Geometric further defined below.
Standards, Geometric Cross Sections, At Grade
Intersections, Interchanges, Geotechnical 103.02 TECHNICAL MEMORANDUMS
Engineering, Drainage, Utilities, Traffic - GENERAL
Engineering, Lighting, and Roadside
Development. Technical Memorandums - General, deal with
issues or information that must be distributed on a
102.03 PART 3: STRUCTURES AND system wide basis to all consultants. They are
BRIDGES also used to provide advance directives with
respect to imminent revision or additions to the
The purpose of the Structures and Bridges part is Roadway Design Manual. Examples are
to identify the design details with which all revisions or refinements to policies, guidelines or
structures are required to comply. As with the criteria.

Part 1 100-2
ROADWAY DESIGN MANUAL Roads and Bridges

103.03 TECHNICAL MEMORANDUMS The design classes discussed in this section are
- SPECIFIC applicable to all highway networks in both rural
and urban areas under the jurisdiction of the Road
Technical Memorandums - Specific, deal with Section, Abu Dhabi Municipality.
issues or information that is of specific interest to
a particular section (design contract), and as such Table 100.01 summarizes the major
have no influence or effect on other design characteristics of the first tier classifications, i.e.,
sections. primary, secondary and local roads.

Table 100.02 is a matrix that differentiates the


urban and rural roadway types by their first tier
classifications.

104.02 DESIGN

Roadway design standards are dependent on the


classification of the roadway. The Road Section
will determine the classification. The Design
Concept Report summarizes the design criteria to
be utilized in the design.

The roadway classification system is based on a


hierarchy of roads. Local roads provide access to
adjacent land. Collectors provide a combination
of land access and movement of through traffic.
Arterials and expressways provide for movement
of through traffic. Arterials and Expressways
Examples of such memorandums are: have at-grade or grade-separated intersections.
Freeways shall have only grade-separated
1. Deviations from the Design Procedures crossings and interchanges.
Manual on a project specific basis.
2. Drainage Design Guidelines. 104.03 CRITERIA FOR DESIGN CLASS
3. Lighting Design Guidelines. DESIGNATION
4. Report Transmittals, etc.
Table 100.03 defines the characteristics of the
104 ROADWAY CLASSIFICATIONS second-tier classifications, i.e., freeways,
expressways, arterials, and collectors as they
104.01 ROADWAY SYSTEM relate to design requirements.

Roadways within the jurisdiction of Abu Dhabi


Municipality are classified into one of three
functional categories, consistent with the
Transportation Master plan:

! Primary Roads
Freeways
Expressways
! Secondary Roads
Arterials
Collectors
! Local Roads

Part 1 100-3
ROADWAY DESIGN MANUAL Roads and Bridges

Table 100.01
Summary of Functional Characteristics for Roadway Classifications*

Primary Roads Secondary Roads Local Roads

Function Regional Regional transportation Local circulation


transportation and/or service to major
land developments

Service Points Connects multiple Connects two regions. Residential,


regions. Serves Serves international industrial, and
international connections, military recreational areas
connections and major installations and not served by higher
military installations. seaports not served by class.
Primary Roads. May
connect two Primary
Roads.
Population Density Connections to urban Connections to urban None
areas of 100,000 or areas of 50,000 or
more. more.

Access Access is controlled. May be controlled. Minimal control.

Minimum Level of Service C/D C D

Percent of Total Kilometers 35 35 30

Design Speed 120 kph (urban) 60 kph (urban) 50 kph (urban)


140 kph (rural) 60-100 kph (rural) 60-90 kph (rural)

Weather Related Road


Closures - Allowable Once per 100 years. Once per 50 years. Once per 25 years.
Frequency

Minimum Percent of Truck 25 20 30


Traffic (Other Than Pickups)

* See Part 2.0 for further details.

Part 1 100-4
ROADWAY DESIGN MANUAL Roads and Bridges

105 ROUTE DESIGNATIONS 105.02 ROUTE NUMBERS

105.01 INTRODUCTION Figure 100.01 shows the designated route


numbers between emirates and cities within the
The purpose of route designations is to provide U.A.E.
the highway user with a consistent expectation of
the: Figure 100.02 shows routes designated between
existing primary roads and secondary or local
! relative direction (north, south, east roads in the Abu Dhabi Emirate.
west)
! design standards (design speeds, 105.03 ADDITIONS, DELETIONS, AND
shoulders, etc. resulting from REVISIONS
the highway classification)
! origin/destination of the road. From time to time, it may become necessary to
assign new route numbers, delete route numbers
Route designation and numbering facilitate rapid for obsolete roads or revise route numbers to
and accurate identification of specific locations in reflect changes to road classifications. Users of
the event of emergencies, accident reporting and this manual shall advise the Municipality if they
analysis and in the inventory of roadway perceive the need for changes to the route
appurtenances, i.e., signs, drainage structures, numbering system. Note that all changes of this
guardrails, etc. Route assignments are made by nature are subject to the approval of Abu Dhabi
the Municipality and based on the functional Municipality.
classification of each roadway.

Table 100.02
Roadway Types by Functional Classification

Roadway Roadway Type for Design


Classification Urban Rural
Primary Freeway Freeway
Expressway Expressway

Arterial Collector
Secondary (Main Roads) Major
Frontage Roads Minor

Sector Road Local Access


Local Primary
Local

Part 1 100-5
ROADWAY DESIGN MANUAL Roads and Bridges

Table 100.03
Characteristics of Urban/Rural Design Classes
Freeways/ Arterials Collectors Locals
Expressways
Traffic Service:
Urban and Optimum mobility Traffic movement Traffic movement Traffic movement
Rural primary and land access of secondary
consideration equal importance. consideration
Land Service:
Urban and Full control of access Land access Traffic movement Land access
Rural no direct land access secondary in and land access of primary
consideration equal importance. consideration
Traffic Flow Characteristics:
Urban and Free flow Uninterrupted Interrupted flow Interrupted flow
Rural except at
intersections
Private and Commercial Access:
Urban and Not permitted None or limited Permitted Permitted
Rural
Connection Type for Public Roads:
Urban Grade separations & At-grade At-grade At-grade
interchanges intersections, intersections intersections
interchanges,
orslip-ramps
Rural Grade separations & At-grade At-grade At-grade
interchanges intersections or intersections intersections
interchanges
Connects to:
Urban Arterials Arterials Locals Arterials Locals
Expressways Expressways
Freeways
Rural Expressways Locals Collectors Locals Collectors Locals Collectors
Collectors Expressways
Freeways
Vehicle Type:
Urban All types up to 20 All types up to 20 All types Passenger &
percent heavy trucks percent heavy service vehicles
trucks
Rural All types; heavy trucks All types up to All types, up to Predominantly
average 20%-40% 40% trucks 30% heavy trucks passenger cars &
in the 3 mg to 5 light to medium
mg class trucks: occasional
heavy trucks
ADT (20):
Urban Level of Service is C/D 5,000-30,000 1,000-12,000 100-1,000
Rural Level of Service is C/D 2,000-15,000 200-4,000 0 to 300
Average Running Speed for Off-Peak Conditions:
Urban 80-110 kph 50-80 kph 30-50 kph 30-40 kph
Rural 80-120 kph 60-110 kph 50-90 kph 45-80 kph

Part 1 100-6
ROADWAY DESIGN MANUAL Roads and Bridges

Figure 100.01
Route Designations Between U.A.E. Cities and Emirates
Part 1 100-7
ROADWAY DESIGN MANUAL Roads and Bridges

Figure 100.02
Connections Between Primary and Secondary or Local Roads

Part 1 100-8
ROADWAY DESIGN MANUAL Roads and Bridges

SECTION 200 Utilities Section - The Town Planning Utilities


Section is responsible for the development and
DESIGN CONCEPT
approval of all service reservations.
DEVELOPMENT
201.04 MAPPING
201 TRANSPORTATION
PLANNING 201.04.01 General

201.01 INTRODUCTION Current, accurate base mapping is an essential


tool in transportation planning. The specific
Data collection comprises this phase of the pre- mapping requirements depend on the length and
design process. Existing data is collected from complexity of the project and its location, either
the Abu Dhabi Municipality, other government urban or rural. Aerial mapping is normally the
departments, landowners, and field surveys. This most useful and cost-effective medium for larger
data becomes the foundation for project road and projects. Ground topographical surveys are used
bridge design. The Consultant is responsible for for smaller projects, especially in urban areas and
all data collection. to supplement aerial mapping at specific locations
where more detail and accuracy is needed.
201.02 ROAD SECTION
Three types of aerial maps are used in the
The Road Section is the lead department from planning and design phases of roadway and
which all road and bridge projects are initiated bridge projects:
and approved.
Uncontrolled Aerial Photography - These maps
The Consultant shall work with assigned staff to are produced directly from the aerial photographs
develop the project scope per the Consultant that normally cover large areas at a reduced scale.
Procedures Manual and identify applicable design The maps are generally used in route location
criteria from the Roadway Design Manual. The studies to define transportation corridors and
Consultant is expected to develop the project by alternative alignments. The contact prints from
proper application of Abu Dhabi Municipality the aerial photography are assembled to form a
policies and standards. photomosaic of the area under study to reduce
distortion.
201.03 TOWN PLANNING
Controlled Aerial Photography - Prior to the
The Town Planning Department is comprised of flight, horizontal and vertical ground control
two sections: points are set and marked in the field. These
points are used to control photomosaic products
Planning Section - The Planning Section is that are significantly more accurate and can be
responsible for the development and maintenance prepared at a specific scale. These maps can be
of the Master Plan and planning layouts. The used at larger scales for preliminary engineering
Master Plan is the base document from which the activities including Design Concept Reports.
projects roadway classifications are assigned.
Roadway design standards are identified for each Topographic (Aerial) Mapping - These maps
roadway classification (see Tables 100.01, represent the state-of-the-art in highway design
100.02 and 100.03, in Part 1, Section 100, and consist of topographic maps compiled from
General Information). controlled aerial photography in a digitized
format that can be input directly to CADD. This
The planning layouts are used to identify the mapping can be used for both design concept
existing and proposed land use and development development and final design and is limited to the
intensity. broad roadway corridor.

Part 1 200-1
ROADWAY DESIGN MANUAL Roads and Bridges

The Consultant is responsible for providing base Coordinate Grid - Coordinate grid ticks shall be
mapping for design concept development. shown on the maps at intervals to suit drawing.
Specific requirements will be identified in the
Consultants scope of work. Existing aerial and North Arrow - A north arrow shall be placed on
topographic maps may be available and suitable each map sheet. The north arrow shall be
for use in consultation with the Department. The oriented so that north points to the top or to the
Abu Dhabi Municipality and Town Planning right of the map sheet. Match lines shall also be
Department maintain a limited library of existing labeled so that each sheet may be joined
mapping which the Consultant shall review for accurately to adjacent sheets.
background information.
Map Index - A sheet index diagram shall be
Mapping scales and contour intervals generally prepared for each mapping project. This diagram
suitable for the intended purpose are shown in shall show the position and relationship of each
Table 200.01. sheet to adjacent sheets. A title block is also
required and shall be placed on each sheet.
201.04.02 Topographic Mapping

Topographic maps for a specific project shall be Table 200.01


prepared in accordance with the following: Map Scales and Contour Intervals for
Highway Development
Survey Control/Field Surveys - The
Purpose Scales Interval
requirements for surveys are included in Section (m)
203.04, Survey Control/Field Survey. Route Location Studies:
Mountainous 1:5000 Max. 5
CADD Standards - Mapping features and Rolling to Flat 1:5000 2
symbology will be prepared in accordance with
the latest CADD Standards, supplemented by the Preliminary Design (DCR):
standard symbols shown in Figure 200.01, 200.02 Rural 1:1250 2
and 200.03. Urban 1:1250 2
Primary Control Points - All primary control Rural Design: 1:1250 0.5
points for mapping which were established during
the initial field survey will be shown on the maps Urban Design: 1:500 0.5
in their proper locations and with the appropriate
symbol, identification number and elevation. A Detailed Site Design: 1:100 0.5
tabulation of the primary control points shall also 1:250 0.5
be shown in the original survey notebook. The
tabulation will show the identification number,
coordinates and elevation of the point.
201.05 PROJECT LIMITS
Supplemental Control Points - All supplemental
control points established for controlling aerial The Abu Dhabi Municipality will determine the
photography will be shown on the maps. These limits of the project. Typically, the limits include
include wing points, analytically bridged points, the roadway/bridge, medians, sidewalk,
and aerial photo centers. See Figure 200.01. parkways, and roadside improvements that
enhance the appearance, maintainability and
Planimetric Features - Natural and manmade safety characteristics of the project. The project
limits may also be determined by phased
features, spot elevations, topographic features and
implementation considerations.
relevant political subdivision lines shall be plotted
on the maps as shown in Figure 200.02 and
Figure 200.03.

Part 1 200-2
ROADWAY DESIGN MANUAL Roads and Bridges

Figure 200.01
Standard Mapping Symbols - Boundaries and Monuments

Part 1 200-3
ROADWAY DESIGN MANUAL Roads and Bridges

Figure 200.02
Standard Mapping Symbols - Natural Planimetric Features

Part 1 200-4
ROADWAY DESIGN MANUAL Roads and Bridges

Figure 200.03
Standard Mapping Symbols - Manmade Planimetric Symbols

Part 1 200-5
ROADWAY DESIGN MANUAL Roads and Bridges

201.06 PROJECT IDENTIFICATION This will contribute significantly to public


AND NUMBERING acceptance and the ultimate success of a project.
The following sections describe the various
The Abu Dhabi Municipality Road Section will environmental factors that comprise each of the
assign the Title and Number for each individual two categories. It is the Consultants
roadway and bridge project. The Consultant will responsibility to assess each factor and develop a
include this information on all drawings, reports, functional and compatible design.
correspondence, calculations and other design
documentation associated with the subject project. 202.02 SOCIOECONOMIC/COMMUNITY
RESOURCE DATA
201.07 INTERDEPARTMENTAL
COORDINATION The Consultant shall consider each of the
following factors as part of the development of
Throughout the development of the project, project design. The goal is to develop a
coordination with Municipality Sections as well functional design that accommodates or maintains
as other government departments is essential. the integrity of each socioeconomic and
The Consultant is expected to identify the community resource with minimal disruption. To
requirements of the involved government assist with the planning involved with the
departments, and insure that the project design development of the design, the Consultant should
addresses these requirements. Table 200.02 lists map all resources that are capable of being placed
the agency or authority responsible for onto a map.
transportation related functions.
202.02.01 Land Use

Table 200.02 The project plans must accommodate existing and


Municipal Agencies future land use to the extent possible. The
Function Agency/Authority Consultant is required to provide adequate
Road/Bridge parking and access to adjacent land uses,
Construction ADM-Road Section commensurate with the type of land use and the
Planning ADM-Town Planning Dept. roadway classification (see Tables 100.01,
Utilities ADM-Town Planning Dept. 100.02 and 100.03, Part 1, Section 100, General
Parking ADM-Road Section Information). The roadway volumes used to
Right-of-Way ADM-Town Planning Dept. determine the level of service (existing and 20-
Plantation ADM-Agriculture Section year projection) must include the trip generation
associated with the adjacent land uses.

In the urban areas, the Town Planning Master


202 ENVIRONMENTAL FACTORS Plan is the primary document used to identify the
INFLUENCING DESIGN types and locations of designated land uses. In
rural areas, where the land usage is less defined,
202.01 INTRODUCTION the Consultant must conduct a field survey of the
existing land uses adjacent to the project. The
There are a number of important environmental aforementioned information, combined with the
factors that influence the design of all roadway field survey data, will then be used to identify
and bridge projects. These factors are both potential improvements to be designed as part of
natural and man-made and have been divided into the roadway project.
two major categories; Socioeconomic/
Community Resource Data and Natural/ In rural areas, formal information regarding land
Environmental Resource Data. The identification use may not be available. In these cases, the
of these resources enables the project to be current land use is typically agricultural and will
developed to avoid and/or minimize impact to remain as agricultural unless there is information
these resources to the greatest extent practicable. stating otherwise.

Part 1 200-6
ROADWAY DESIGN MANUAL Roads and Bridges

202.02.02 Growth Projections The development of all road and bridge projects
typically affects many public services. This can
The Abu Dhabi Municipalitys roadways are result from encroachment of the improvement
designed to serve the traffic volume anticipated project beyond the existing roadway, sidewalk,
during the next 20 years. Presently, historical and bridge. As such, pre-design coordination
records of past growth trends do not exist. with public services is required to incorporate
Therefore, it is important that a reasonable design approaches and construction phasing that
growth projection is used to size the project. minimize the project impact.

The growth can be categorized as an increase, The Consultant is responsible for identifying all
decrease or no change. It is anticipated that an public services which may be affected by the
increase will be the most probable scenario in the roadway/bridge project. In addition, the
foreseeable future. The rate of growth can be Consultant is also responsible to compile all
expected to increase linearly each year or relevant design requirements from the affected
exponentially (i.e., an order of growth magnitude public services and incorporate these parameters
each year). into the project design. It is the Consultants
responsibility to assure the Abu Dhabi
The growth projection can dramatically affect Municipality that the design and construction
project sizing. Therefore, the Consultant is phasing meets the approval of the affected public
expected to develop a realistic growth projection service.
which takes into consideration variables such as:
Table 200.03 identifies the various Public
increases in vehicle ownership Services and the responsible agency/authority for
land use each.
population growth rate, i.e. linear or
exponential Table 200.03
Public Services
In urban areas, growth projections are dependent Service Agency/Authority
upon the rate at which the Town Planning Master Road/Bridge
Plan is implemented, as well as the proposed Construction ADM-Road Section
types of land use. The Consultant is expected to Agriculture/Parks ADM-Agriculture
confer with the Town Planning Department to Police Police Directorate/
ascertain the rate at which the Town Planning Traffic Police Dept.
Master Plan is to be implemented. Fire Civil Defense Dept.
Security Defense Dept./CID
In the rural areas, information regarding growth is Schools Town Planning/
less defined. In these cases, it is necessary that Ministry of Education
the Consultant make growth projections. These Sanitation ADM - Health Section
projections should take into account any data Parking ADM - Road Section
concerning growth, including changes in land use Recreational Town Planning/
adjacent to the roadway. As a starting point, it Agriculture
can be assumed that the use of land is primarily Navigable Waters Coast Guard
agricultural, with an average growth of 1% to 2% Mail Service Postal Directorate
per year for a period of 20 years. Public Transportation ADM - Public Transport
Section
The resulting growth projection, along with
supporting data and the rationale used to 202.02.04 Schools
substantiate the project, shall be approved by the
Town Planning Section. Schools are an important national resource. The
design shall accommodate and preserve sufficient
202.02.03 Public Services access to all facilities that are affected by project
design. Therefore, the Consultant is expected to

Part 1 200-7
ROADWAY DESIGN MANUAL Roads and Bridges

adapt the projects design to accommodate each establishment and approval of all Service
schools needs. Reservations.

For each school, there are a number of factors Table 200.04 lists the Responsible
that must be considered in the project design. Agencies/Authorities for Utilities. A survey of
These include: existing utilities is required. The purpose of the
school bus traffic utilities survey is to determine which utilities can:
crosswalks remain in place based on field surveys, as-
school yard fencing built plans and other available information:
parking be protected and/or relocated; and,
landscaping affect the horizontal and vertical alignment of
noise attenuation (i.e., insulated windows, the roadway.
soundwalls)
other safety improvement In the case of future or relocated utilities, it may
relocation of affected structures, as necessary be necessary to preserve adjacent land for utility
affects on potential school expansion installation and relocation. The associated costs
for utility work shall be identified as part of the
In the case of new school site development, the design reflected in the project cost estimate for the
Town Planning Master Plan and Town Planning Design Concept Report. Refer to Part 1, Section
staff shall be consulted to identify these sites 321, Cost Estimate.
within and/or adjacent to the project limits.
Table 200.04
As with all other adjacent property improvements, Responsible Agency/Authority for Utilities
the Consultant is required to provide plans which Service Agency/ Authority
can be used to construct the necessary Water ADM-WED Water (Water and
improvements either in conjunction with the Electricity Dept.)
roadway/bridge project or as a separate project. Sewer ADM-Sanitary Drainage
This is intended so that construction can be Network Section
undertaken on the school sites during scheduled Telephone ETISILAT
school closures. Electricity ADM-WED Electrical (Water
and
202.02.05 Mosques Electricity Department.)
Lighting ADM-WED (Water and
Mosques are extremely important to the Islamic Electricity Department)
faith and cannot be relocated or impacted in any
way. The Consultant shall identify all Mosques 202.02.07 Security
within close proximity to a proposed project. The
project design shall avoid impact to Mosques and Nearly every project is affected by some level of
shall accommodate and preserve sufficient access security issue. All embassies, government
to these sites. installations, palaces, schools, banks and VIP
homes are protected by guards with guardhouses,
202.02.06 Utilities and associated channeling devices. As a result,
many of these facilities interfere with road and
Major road and bridge projects typically include bridge projects.
improvements to all affected utility services. This
also includes preparing plans and specifications The Consultant is required to minimize the
for these improvements. Pre-design activities relocation of affected facilities as part of the road
require coordination with many and bridge project. As with all other adjacent
agencies/departments. Final design approval of property improvements, the Consultant is required
the utility improvements by the utility agencies is to provide plans which can be used to construct
also required. The Utilities Section of the Town the necessary improvements either in conjunction
Planning Department is responsible for

Part 1 200-8
ROADWAY DESIGN MANUAL Roads and Bridges

with the roadway/bridge project or as a separate 202.02.11 Parking Requirements


project. This is intended so that construction can
be undertaken outside of the project right-of-way Roadway and bridge projects typically can affect
at the convenience of the affected property owner. parking. For example, removal of on-street
Since each case will vary, the limits of parking to accommodate road widening may
improvement, access, facility relocation, parking, result in the need for off-site parking.
etc. requires review by the affected party and the
Abu Dhabi Municipality. The Consultant is also Each roadway and bridge project requires the
responsible to assure the Department that the preparation of a parking study. The intent of this
proposed improvements located outside of the analysis is to establish existing and ultimate
project right-of-way are agreeable to the affected parking requirements.
property owner.
The components of the study include, but are not
202.02.08 Commercial Activities limited to:

The effects of commercial activities on the road calculation and survey to establish
and bridge design shall be taken into account. existing parking demand
For example, existing access shall be maintained future growth of parking demand, as a
as well as accommodating special features of the function of land development intensity,
non-project site. As a result, coordination with vehicle ownership/occupancy trends, etc.
the Town Planning Department, adjacent opportunity for mixed parking utilization
landowners and governmental departments is
required to lessen the impact of the road/bridge Both peak and off-peak parking demands should
improvement project on commercial activities. be included in the analysis.

202.02.09 Economics Table 200.05 identifies the minimum parking


generation rates for Central Business Districts
The Consultant shall assess the economic (CBDs). These rates are to be used in the
conditions that exist within the project study area, parking analysis. However, the parking analysis
including income and employment characteristics, should state the rationale used for proposing rates
tax base and property values. The Consultant other than the stated minimum rates. In no case,
shall develop a design that seeks to minimize shall lower parking generation rates be utilized,
adverse impacts on these and other economic unless approved by the Abu Dhabi Municipality.
indicators. This will be done through direct
coordination with representatives of the In rural areas and for areas outside the CBD, an
Municipality. appropriate parking demand shall be established
on the basis of existing development needs, as
202.02.10 Local Transportation/Circulation well as review of the demand for other similar
facilities.
In order to insure that the project fully
incorporates local transportation/circulation
needs, the Consultant shall address the following:

Need for Public Transit Stops or


Turnouts
Staging areas for Regional
Transportation Hubs
Police Enforcement Pads
Pedestrian Walkways and Islands
Special Landscape Areas

Part 1 200-9
ROADWAY DESIGN MANUAL Roads and Bridges

Table 200.05
Existing and Future Parking Generation Rates (CBD)
Use Period Rate Vehicle Occupancy Vehicle Ownership
Factors Factors
Residential Existing 1 space/1000 SF .80 .67
Future 1 space/1000 SF .85 .80
Commercial Existing 1 space/500 SF .85 1.00
Future 1 space/500 SF .90 1.00

202.02.12 Recreation 202.03 NATURAL/ENVIRONMENTAL


RESOURCE DATA
A variety of recreation and leisure activities are
available to residents of Abu Dhabi. These can Natural/Environmental resources within a project
include ball fields, beach access, clubs, golf study area shall be assessed and considered
courses, movie theaters and entertainment during development of the project design. The
complexes. goal is to develop a functional design that avoids
or minimizes impact to the natural environment to
As part of the pre-design activities, the the greatest extent practicable. To facilitate the
Consultant is required to identify the potential planning process involved in the development of
effects on adjacent recreational facilities. The the design, the Consultant should map all
Consultant is required to minimize the relocation resources capable of being placed on a map.
of affected facilities as part of the road and bridge
project. As with all other adjacent property 202.03.01 Landscape Preservation
improvements, the Consultant is required to
provide plans which can be used to construct the Preservation of existing landscaping, agricultural
necessary improvements either in conjunction areas and trees adjacent to proposed roadway
with the roadway/bridge project or as a separate projects is extremely important.
project.
Pre-design activities include a survey of existing
202.02.13 Historical Site Identification and vegetation as part of the design survey stage. The
Preservation results of this survey are to be discussed with the
Abu Dhabi Municipality and the Agriculture
The government recognizes the importance of all Section. Road/bridge improvements including
historical sites and structures that relate to Abu utility locations shall be designed to minimize
Dhabis cultural development. The goal of the removal of vegetation.
government is to identify these sites as they are
discovered, and, where appropriate, preserve the The landscaping survey includes the identification
sites. of the number, size, type, condition, and location
of all trees, shrubs, succulents, flowers, and
During the pre-design process, information grasses. The presence of any vegetation that is
regarding historical sites shall be compiled from specifically protected by decree, or that is
available sources as well as conducting an initial considered rare, threatened, or endangered, shall
site survey. The Consultant shall also meet with also be identified during the survey. The survey
representatives of the Municipality to determine information should then be presented on a scaled
the significance of the site and present plot plan. The scale of each sheet should be
recommendations as to appropriate preservation adequate to clearly convey the information
procedures. contained on it. Each sheet should contain a
legend, which lists the botanical name of the
plant, and its common name. For trees, the size
of the tree shall also be listed.

Part 1 200-10
ROADWAY DESIGN MANUAL Roads and Bridges

All urban area projects include landscaping in the 202.03.04 Wildlife


medians and other designated areas within the
project limits. The landscaping design is The Consultant shall describe any existing
normally undertaken by the Agriculture Section. wildlife habitat within the project study area. The
However, the Consultants design, shall ensure Consultant is responsible for identifying the types
the following are provided as part of the project, of wildlife species, if any, that are likely to utilize
if so required: the habitat. The Consultants design shall avoid,
where possible, those habitat areas that support
Irrigation Service rare, threatened or endangered wildlife species.
Sidewalks
Walls 202.03.05 Air Quality
Fences
The Consultant shall assess a projects affect on
Water for irrigation is reclaimed water from the existing air quality to determine whether or not it
sewage treatment plant, therefore all large will result in significant deterioration due to
distribution lines require design input from, as increased air emissions.
well as approval by, the Sanitary Drainage
Network Section. 202.03.06 Noise

The Agriculture Section will assume The Consultant shall assess a proposed projects
responsibility for plantings and other special affect on ambient noise levels to determine
features. whether or not it will result in a significant
deterioration from the existing condition. Noise
Maintenance and operation of the irrigation sensitive receptors, such as Mosques, schools and
systems are the responsibility of the Agricultural residential dwellings, shall be identified within the
Section. project limits. The Consultant shall strive to
develop a design that will have the least increase
202.03.02 Topography in noise levels to these receptors.

Topographic data is important to the development 202.03.07 Visual/Aesthetic


of the Design Concept. Roadway profiles,
horizontal alignment, and drainage, are directly The Consultant shall assess the existing visual
affected by topography, which, in turn, affect the and aesthetic appearance of the project study
project cost. As discussed in Section 201.04, area. In developing the design, the Consultant
Mapping, the Consultant is expected to review should consider the effect that the project will
existing maps. In addition, new surveys shall be have on the visual and aesthetic environment upon
required to establish the topography for the build-out. Views from the project of the
project. surrounding environment as well as views of the
project from adjacent vantage points shall be
202.03.03 Water considered. The objective of the design is to
develop a project that compliments rather than
The Consultant shall identify and determine the contrasts the existing visual and aesthetic
importance of all freshwater and saltwater character of the area.
features within the study area. Aquifers and
wells, especially those that supply drinking water, 202.03.08 Hazardous Materials
shall also be identified within project limits. In
developing the design, the Consultant shall avoid The Consultant shall conduct a survey to identify
impacts to water resources to the greatest extent the actual presence of or likelihood of hazardous
possible. If avoidance is not an option, the material sites within the project study area.
Consultant shall develop a design that minimizes Ideally, the project design should be developed to
impact to water resources. avoid impacting such hazardous sites. This will
reduce the health and safety risk and overall

Part 1 200-11
ROADWAY DESIGN MANUAL Roads and Bridges

project cost. If a hazardous materials site cannot Geotechnical


be avoided, the Consultant shall take appropriate Traffic Data Collection
steps to remediate the hazardous site prior to Survey Control/Field Surveys
construction in order to reduce the potential Drainage Surveys
health/safety risk.
203.02 GEOTECHNICAL
202.04 ENVIRONMENTAL ENGINEERING
CHECKLIST
The objective of highway geotechnical work
All of the environmental factors described in should be to seek, interpret, and evaluate
Sections 202.02 and 202.03 are included in the subsurface and surface data in order to predict the
Environmental Checklist located at the end of this behavior of the soils and materials along, and
section. Where appropriate to this project, the adjacent to, the alignment. The resulting
Consultant shall use the Environmental Checklist information is to be presented in a technical report
as an initial tool to identify those environmental to be used in the project design.
factors that may influence the design of
alternatives Data collection includes research of existing
geotechnical reports which were prepared for
The checklist is designed as a question and other projects in the geographic area as well as
answer exercise that will aid in the comparison of field reviews and preliminary testing. For review
project alternatives. A response of No to a of existing geotechnical reports, the Abu Dhabi
specific question means the environmental factor Municipality Road Section as well as other
in question is not applicable to the project. A Municipality and Government agencies should be
response of Yes or Maybe indicates to the contacted. The existing data will be used to
Consultant that the environmental resource exists define the number of additional soil borings and
and may be affected by the proposed project. In the testing requirements for the boring program as
this case, the resource should be assessed further described in Part 1, Section 300, Design Concept
during the development of alternative designs to Report and Part 2, Section 600, Geotechnical
determine the exact nature and extent of impact Engineering. The Consultant shall obtain
that will be incurred on that resource. The approval from the Road Section, Traffic Police
objective is to design a project alternative that has and any other concerned agencies prior to
the least amount of adverse impact to the commencing geotechnical investigation.
environmental factors on the checklist. An
alternative design that yields all No answers on 203.03 TRAFFIC COUNTS
the Environmental Checklist is considered to be
the ideal design. However, this ideal situation is 203.03.01 Introduction
seldom achieved as there is always some level of
impact to the listed environmental considerations. Traffic counts are basic to all phases of highway
development and operation. An important
203 TECHNICAL INVESTIGATIONS component of traffic counts is existing and future
traffic volumes. Traffic volumes are needed for
203.01 INTRODUCTION highway planning, project cost-benefit
comparisons, priority determinations, analyzing,
All roadway and bridge projects require technical monitoring and controlling traffic movement on
investigations, to establish the basic building the highways, traffic accident surveillance,
blocks of the design. These technical research purposes, highway maintenance, public
investigations are initiated in the data collection information, highway legislation and for many
phase and continue through the development of other purposes. However, it should be noted that
the Design Concept Report. This subsection the traffic data collection and projection
identifies the initial activities associated with techniques described herein are specifically
these investigations. The basic technical intended for providing traffic volume data
investigations include: required for roadway and bridge design. It is the

Part 1 200-12
ROADWAY DESIGN MANUAL Roads and Bridges

goal of the Abu Dhabi Municipality to establish a next 20 years will increase exponentially.
permanent automated traffic data collection Formula B shall be used when the Engineer
system for the Municipality. However, until this judges that the traffic volume will increase
system is fully developed and implemented, the linearly.
specific procedures outlined in this section shall
be followed in the collection of traffic data for Formula A:
roadway and bridge projects. ADT (20) = ADT Present Growth Factor (GF)
20
The procedures which follow establish the Where GF = 1 + Annual % Traffic Growth
minimum requirements; however, this does not 100
preclude the Engineer from using more
sophisticated procedures if available. Formula B:
ADT (20) = ADT present +
203.03.02 Traffic Projections Annual % Traffic Growth ADT Present 20
100
The Abu Dhabi Municipalitys roadways are
designed to serve the traffic volume anticipated Examples:
during the next 20 years. Therefore, the existing The following is an example of the use of the two
Average Daily Traffic (ADT) must be projected formulas when the annual percent of traffic
over a 20-year time frame. For the 20-year travel growth is anticipated to be 10 percent and the
forecast, variables such as an increase in auto ADT at present is 4,000.
ownership and vehicle registration, population,
employment, and residential/ commercial/ Formula A:
industrial land uses which strongly influence the ADT (20) = 4,000 1 + 10 20

future traffic volume shall be taken into 100


consideration. Presently, a long historical record = (4,000) (6.73)
of past growth trends does not exist. The Abu = 26,920
Dhabi Municipality will use the transportation
modeling software for the City of Abu Dhabi. Formula B:
This model shall be the primary source for ADT (20) = 4,000 + 10 4,000 20
projected traffic volumes over different time 100
frames. The projected traffic volumes of this = 4,000 + 8,000
transportation modeling software will be based on = 12,000
changes in socioeconomic data for the concerned
time period. The following is an example of the use of the two
formulas when the annual percent of traffic
In case the transportation modeling software is growth is anticipated to be 15 percent over the
unavailable, then the following formulas shall be first 5-year period and 10 percent over the last
used to determine the ADT for a 20-year time 15-year period. The ADT present equals 4,000.
frame ADT (20). The Engineer is required to the
collect data to determine the current ADT. In Formula A:
addition, the Engineer must provide his rationale ADT (20) = 4,000 1 + 15 5
+ 1 + 10 15

for the estimated traffic growth anticipated for the 100 100
next 20 years by considering all previously
acquired data regarding all activity growth in the = 4,000 [(1.15) 5 + (1.10)15]
proximity of the highway improvement. = 4,000 [(2.01) + (4.18)]
= 24,760
The following formulas may be applied under
assumptions of increasing, decreasing, or equal
percentages of traffic growth over the 20-year
projection. Formula A shall be used when the
Engineer judges that the traffic volume over the

Part 1 200-13
ROADWAY DESIGN MANUAL Roads and Bridges

Formula B: 203.04.02 Horizontal Control


ADT(20) = 4,000+ 154,000 5 + 104000 15
100 100 The current inventory of horizontal control points
established in the vicinity of the project will need
= 4,000 +3,000 + 6,000 to be investigated. The Abu Dhabi Municipality
= 13,000 and Town Planning Department should be
consulted on the order of accuracy and status of
203.03.03 Procedures for Traffic Volumes existing primary and secondary control points.

Table 200.06 specifies the minimum procedures The need for setting new horizontal control points
that shall be met when traffic studies are will be ascertained from the existing data. A
conducted to identify the present ADT. discussion of surveying methods and procedures
Collection of traffic volumes for three functional used to establish new horizontal control points is
classes of highways (Primary, Secondary, and beyond the scope of this manual and will be
Local) and five types of improvements (up- covered in a companion Technical Manual on the
grading existing Primary or Secondary Roads; subject of surveying and mapping.
new Primary or Secondary Road on new
alignment/location; upgrading existing 203.04.03 Vertical Control
intersection/interchange on Primary or Secondary
Roads; new intersection/interchange on existing There are several vertical datum currently being
Primary or Secondary Roads; and new Local used for construction in Abu Dhabi. Table
Streets are considered. 200.07 summarizes the most common vertical
datum and the relationship between them. In
203.04 SURVEY CONTROL/FIELD addition, some Sewerage Projects Committee
SURVEYS projects use their own datum, in which + 100.00
meters equals 0.00 meters, New Abu Dhabi
203.04.01 Introduction Datum. All design work will be referred to the
New Abu Dhabi Datum.
Each project requires initial field surveys to
establish baseline topographic information for 203.04.04 Coordinate System
project scoping and design. Setting horizontal
and vertical control is of great importance in A Coordinate System has been established by
mapping. Relative position in the horizontal Abu Dhabi Municipality Town Planning
plane is maintained by horizontal control. Department. This Coordinate System shall be
Horizontal control consists of a series of points used for all surveys.
accurately fixed in position by distance and
direction in the horizontal plane. 203.04.05 Field Surveys

For most topographic surveying, traverses furnish Field Surveys will be required on nearly every
satisfactory control. For strip maps, the open project to supplement the aerial topography,
traverse is used. The open traverse can be tied to record underground utility or drainage features,
fixed points at each end. For area maps, the reflect new existing features, provide cross-
closed traverse is used. The closed traverse can sections and existing pavement elevations at the
be closed to form a net which is accurate to the limits of improvement, obtain building floor
degree required. elevations and other related information needed
for preliminary and final design.
Relative position in the vertical plane can be
maintained by a series of benchmarks in the map Once the horizontal alignment, including
area. These benchmarks are referred to a known applicable alternative alignments, has been
datum, usually mean sea level. established, the roadway centerline will be staked

Part 1 200-14
ROADWAY DESIGN MANUAL Roads and Bridges

in the field to enable close examination of the In absence of drainage master plans or other
roadway location by Department representatives pertinent studies to establish area hydrology, the
and Consultants staff. The staking interval and Consultant is responsible to develop/collect
definition of the project geometrics required will hydrologic data. This data is to include:
be determined on a project specific basis in
consultation with the Municipality rainfall measurement (volume and time) at a
Representative. suitable collection site, such as the airport
measurement of area run-off
A detailed survey of the existing greenery miscellaneous basic data such as soil type,
impacted by the project will be required. The land use, aerial photographs, infiltration,
survey will record the location, size and limits of evaporation, solar radiation and
all trees shrubs and flower beds within the limits oceanography
of improvement. Photographs should be taken to
supplement the data. This information will be Note that sources for miscellaneous data are
recorded on drawings and used to investigate scattered. The Consultant must rely upon the
alignment adjustments or alternatives that will collective experience of design in other similar
minimize the removal of greenery. areas to compile this information.

203.05 DRAINAGE SURVEYS

The Consultant is responsible for a


comprehensive survey of drainage facilities and
conditions and data collection during the pre-
design activities. The data collection consists of
three activities:

field review of existing drainage facilities and


identification of flood plains within the
projects zone of influence
field testing including particle size analysis,
scour, etc.
review of existing drainage master plans
(urban areas), hydrologic studies/data
collection (urban and rural areas), and other
pertinent studies

The review of the existing drainage facilities


should include:

pump stations
outfalls
reinforced concrete box structures
channels
ditches
large diameter pipes
pumps, etc.

Part 1 200-15
ROADWAY DESIGN MANUAL Roads and Bridges

Table 200.06
Procedures for Traffic Studies
EXISTING ROADS
Primary or 24-hour counts for 7 continuous days for each of four yearly periods:
Secondary Roads March, April, May
June, July, August
September, October, November
December, January, February
24-hour manual traffic counts for trucks classified by axle for any three days from the following four days:
Sunday
Monday
Tuesday
Wednesday
Intersections Afternoon (or morning) and evening intersection peak hour counts summarized in 15-minute increments by direction (left turn, right turn
and through movements). Counts taken on Sunday or Wednesday, Monday and Tuesday. Hourly summary of same includes separate totals
for:
Passenger vehicles, vans, pick-up trucks
Buses
Trucks by axle count
Local Streets 12-hour manual counts taken from 6 a.m. to 6 p.m. on Sunday, (or Wednesday), Monday and Tuesday. Total hourly volumes shall be
recorded.
Convert to 24-hour ADT by multiplying the 12-hour volume by 2. This will provide a conservative estimate of the 24-hour ADT. If more
accurate volumes are required a 24-hour count should be made.
NEW ROAD
Primary and Determine/analyze the design ADT for new road using area demographics and travel patterns, determine the redistribution of existing traffic
Secondary Roads volumes and traffic volumes generated by new development that will use the new road(s).
Conduct Roadside Interview Origin Destination Surveys to estimate the directional distribution of traffic.
Local Streets 12-hour manual counts taken from 6 a.m. to 6 p.m. on Sunday or Wednesday, Monday and Tuesday. Total hourly volumes shall be recorded.
Convert to 24-hour ADT by multiplying the 12-hour volume by 2. This will provide a conservative estimate of the 24-hour ADT. If more
accurate volumes are required a 24-hour count should be made.
FOR ALL TRAFFIC COUNTS
1. Counts shall not be taken on special holidays or during events which occur once per year.
2. Counters shall be placed at points of obvious traffic volume changes
3. Manual counts shall be taken at the same place(s) as machine counts. Manual counts shall be used to verify machine counts.
4. Manual and machine counts shall be performed for each direction.

Part 1 200-16
ROADWAY DESIGN MANUAL Roads and Bridges

Table 200.07
Summary of Datums Used In Abu Dhabi
Reference Level Admiralty Chart Admiralty Chart Abu Dhabi Datums Abu Dhabi Datums Sauti Datums
Datums Datums Old New
Existing Corrected
Meters Feet Meters Feet Meters Feet Meters Feet Meters Feet
Bench Mark on Plinth of ADPC 3.20 10.50 3.50 11.48 2.15 7.05 2.20 7.22 1.90 6.23
Building
Mean Higher High Water at 1.89 6.20 2.19 7.18 0.84 2.76 0.89 2.92 0.59 1.94
Springs near Solstices
Mean Higher High Water 1.56 5.12 1.86 6.10 0.51 1.67 0.56 1.84 0.26 0.85
Sauti Datums 1.30 4.27 1.60 5.25 0.25 0.82 0.30 0.98 0.00 0.00
Mean Lower High Water 1.19 3.90 1.49 4.89 0.14 0.46 0.19 0.62 -0.11 -0.36
Mean Sea Level 0.95 3.12 1.25 4.10 -0.10 -0.33 -0.05 -0.16 -0.35 -1.15
Abu Dhabi Old Datums 1.05 3.44 1.35 4.43 0.00 0.00 0.05 0.16 -0.25 -0.82
Abu Dhabi New Datums 1.00 3.28 1.30 4.26 -0.05 -0.16 0.00 0.00 -0.30 -0.98
Mean Higher Low Water 0.80 2.62 1.10 3.61 -0.25 -0.82 -0.20 -0.66 -0.50 -1.64
Mean Lower Low Water 0.25 0.82 0.55 1.80 -0.80 -2.62 -0.75 -2.46 -1.05 -3.44
Admiralty Chart Datums Existing 0.00 0.00 0.30 0.98 -1.05 -3.44 -1.00 -3.28 -1.30 -4.27
Mean Lower Low Water at -0.18 -0.59 0.12 0.39 -1.23 -4.04 -1.18 -3.87 -1.48 -4.86
Spring Near Solstices
Admiralty Chart Datums -0.30 -0.98 0.00 0.00 -1.35 -4.43 -1.30 -4.27 -1.60 -5.25
Corrected

Part 1 200-17
ROADWAY DESIGN MANUAL Roads and Bridges

ENVIRONMENTAL CHECKLIST
Project: Date:

Page 1 of 4 Yes No Maybe


1 Water: Will the proposal result in:
Changes in currents, or the course of direction of water movements,
in either marine or fresh waters?
Changes in absorption rates, drainage patterns, or the rate and
amount of surface water runoff?
Alterations to the course or flow of flood waters?
Change in the amount of surface water in any water body?
Discharge into surface waters, or any alteration of surface water
quality, including but not limited to temperature, dissolved oxygen
or turbidity?
Alteration of the direction or rate of flow of ground waters?
Change in the quantity of ground waters, either through direct
additions or withdrawals, or through interception of an aquifer by
cuts or excavations?
Deterioration in ground water quality, either through direct injection,
or through the seepage of leachate, phosphates, detergents,
waterborne viruses or bacteria, or other substances into the ground
waters?
Reduction in the amount of water otherwise available for public
water supplies?
2 Landform: Will the proposal result in:
Unstable earth conditions or changes in geologic substructures?
Disruptions, displacement, compaction or overcovering of the soil?
Change in topography or ground surface relief features?
The destruction, covering or modification of any unique geologic or
physical features?
Any increase in wind or water erosion of soils, either on or off the
site?
Changes in deposition or erosion of beach sands, or changes in
siltation, deposition or erosion that may modify the bed of the
ocean, bay, or inlet?
Changes in deposition or erosion or changes in siltation, deposition
or erosion that may modify the channel of a wadi or stream, or the
bed of a lake?
Placing fill below the ordinary high water mark of wadis and
streams?
Cut or fill placement through swamps, marshes, bogs, and other
similar areas that are frequently inundated or saturated by ground
water?

Part 1 200-18
ROADWAY DESIGN MANUAL Roads and Bridges

Page 2 of 4 Yes No Maybe


3 Vegetation: Will the proposal result in:
Change in the diversity of species, or numbers of any species of
flora (including trees, shrubs, grasses, crops, microflora, and
aquatic plants)?
Reduction of the numbers of any unique, rare, or endangered
species of flora?
Introduction of new species of flora into an area, or a barrier to the
normal replenishment of existing species?
4 Wildlife: Will the proposal result in:
Changes in the diversity of species, or numbers of any species of
fauna (birds, land animals including reptiles, fish and shellfish,
benthic organisms, insects, or microfauna)?
Reduction of the numbers of any unique, rare, or endangered
species of fauna?
Introduction of new species of fauna into an area, or result in a
barrier to the migration or movement of fauna?
Deterioration of existing fish or wildlife habitat?
5 Agricultural Lands: Will the proposal result in:
Reduction in the quality or quantity of usable farm land?
Reduction in the quality or quantity of usable grazing land?
6 Natural Resources: Will the proposal result in:
Increase in the rate of use of any natural resources?
Depletion of any nonrenewable natural resource?
7 Economics: Will the proposal affect local employment,
taxes, property values, etc.?
8 Public Services: Will the proposal have an effect upon, or
result in a need for new or altered services
in any of the following areas?
Mosques?
Cemeteries?
Fire protection?
Police protection?
Schools?
Parks or other recreational facilities?
Maintenance of public facilities, including roads?
Health Services?
Other Services?

Part 1 200-19
ROADWAY DESIGN MANUAL Roads and Bridges

Page 3 of 4 Yes No Maybe


9 Antiquities/Historical: Will the proposal result in an
alteration of a significant archaeological or
historical site, structure, object, or building?
10 Air Quality: Will the proposal result in:
Increased air emissions or deterioration of ambient air quality?
The creation of objectionable odors?
11 Noise: Will the proposal increase existing noise levels?
12 Light & Glare: Will the proposal produce new light or
glare?
13 Land Use:Will the proposal result in the alteration of the
present or planned land use of an area?
14 Hazardous Conditions: Does the proposal involve a risk of
an explosion or the release of hazardous
substances (including, but not limited to, oil,
pesticides, chemicals or radiation) in the event
of an accident or hazardous condition?
15 Population: Will the proposal:
Alter the location, distribution, density, or growth of an area?
Affect racial or ethnic groups including minority, elderly, or low
income?
Split neighborhoods, or separate residences from commercial
facilities?
16 Housing: Will the proposal:
Affect existing housing (including, but not limited to, rural or urban
residences and business or commercial buildings)?
Create a demand for additional housing?
17 Transportation/Circulation: Will the proposal result in:
Generation of additional vehicular movement?
Generation of additional movement of bicyclists or pedestrians?
Impact on existing parking facilities, or demand for new parking?
Impact upon existing transportation systems?
Alterations to present patterns of circulation or migration of people
and domestic animals?
Alterations to waterborne, rail, or air traffic?
Increase in traffic hazards to motor vehicles, bicyclists, or
pedestrians?

Part 1 200-20
ROADWAY DESIGN MANUAL Roads and Bridges

Page 4 of 4 Yes No Maybe


18 Energy: Will the proposal result in:
Use of substantial amounts of fuel or energy?
Require the development of new sources of energy?
19 Utilities: Will the proposal result in a need for new systems,
or alterations to the following utilities:
Power or natural gas?
Communications systems?
Water?
Sewer or septic tanks?
Storm water drainage?
Solid waste collection and disposal?
20 Human Health: Will the proposal result in the creation of
any health hazard or potential health
hazard?
21 Aesthetics: Will the proposal result in:
The obstruction of any scenic vista or view open to the public?
The creation of aesthetically offensive site open to the public view?
22 Recreation: Will the proposal impact upon the quality or
quantity of existing recreational
opportunities?
23 Severance: Will the proposal disrupt the cohesive nature
of the community it resides in?
Will public services be severed from a particular physiographic
segment of the community or a particular population?
Will emergency service routes be disrupted by the proposal? Will a
particular segment of the community be without service or suffer
from longer response times due to rerouting of emergency
assistance?

Part 1 200-21
ROADWAY DESIGN MANUAL Roads and Bridges

SECTION 300 The preliminary engineering activities associated


with the DCR involve preparation of numerous
DESIGN CONCEPT REPORT
technical studies and reports, many of which are
301 CONTENTS initiated in the data collection phase as described
in Part 1, Section 200, Design Concept
The Abu Dhabi Municipality Road Section Development. These are prepared as stand alone
requires the preparation and approval of a Design documents and are included as an Appendices to
Concept Report (DCR) prior to commencing final the DCR. The DCR will summarize the results of
project design. The report is to be prepared under these individual reports under the respective topic
the direction of an experienced engineer included in the DCR Table of Contents (See text
designated by the Municipality. Part 1, Section box). Furthermore, the discussion under each
200, Design Concept Development, includes a topic will address interdisciplinary relationships
discussion of the background information and necessary to coordinate all technical aspects of
data collection activities necessary to develop the the design concept. The sections that follow
design concept. Part 1, Section 300, Design provide guidance for the development of the
Concept Report, contains a discussion of the technical studies and requirements for
specific requirements and content of a DCR. presentation of the material in the DCR.

The role of a DCR is to summarize the needs, 301.01 FORMAT


alternatives, costs, and overall impacts of the
proposed roadway or bridge project. The scope The DCR will prepare and packaged as follows:
of the project is defined and the design criteria
identified. The DCR is the project scoping DCR (Volume I) - Written portion of the
document and the basis for selecting the project report bound separately in A4 size.
design. The basic roadway configurations shown DCR (Volume II) - Drawings that accompany
in the DCR will be carried forward to the final the report bound separately in A3 size.
design phase.
DCR (Appendices) -
Technical Memorandums, Studies and
DCR Reports bound in A4 size. For smaller
Table of Contents projects the documents should be bound
Executive Summary together. Larger projects may require
Introduction separate packaging of the reports, titled as
Traffic Analysis Appendix A, Appendix B, etc.
Description of Alternatives
Design Data Each document will include the following
Typical Sections information on the cover:
Geometrics
Interchange/Intersection Configurations Municipality of Abu Dhabi, Road Section
Parking Study
Design Concept Report
Hydrology and Hydraulics
Subsurface Investigations
Volume No. or Appendix No.
Bridge Type Selection Project Name and Route No.
Utility Impact Analysis Project Number
Socioeconomic Analysis Vicinity Map Schematic with Project Termini
Agriculture Impact noted
Public Feedback Consultant Identification
Signing and Pavement Markings
Lighting See Figure 300.01 to be used as the standard
Construction Staging cover sheet for the DCR.
Cost Estimate
Conclusion/Recommendations
Drawings, Plans, Profiles, Typical Sections and
Architectural Features

Part 1 300-1
ROADWAY DESIGN MANUAL Roads and Bridges

Location / Design Concept Study

Project Location

Final Report
Project No.

15 May 1997

Prepared by
De Leuw Cather & Co. Client Prepared for
Preparers th
3875 N. 44 Street, Suite 250 Logo
Logo
Phoenix, AZ 85018 Abu Dhabi Municipality
Figure 300.01
Standard Design Concept Report
Cover Sheet

Part 1 300-2
ROADWAY DESIGN MANUAL Roads and Bridges

302 EXECUTIVE SUMMARY lanes, auxiliary lanes, turning lane requirements


including storage lengths, signal warrants, level of
The Executive Summary is a short (2-4 pages) service and capacity. Schematic diagrams of the
recapitulation of the DCR document. The roadway segments and intersections should be
Summary should address the following key used to display the data. This information will be
topics: presented in the DCR along with a summary of
the project traffic data including current and
Purpose and Need of the Project forecasted ADT values, peak hour and peak hour
Alternatives Evaluated directional splits and percent of trucks.
Recommended Design Concept
Major or Controversial Issues Traffic signal recommendations will be included
Estimated Cost in the report. For each signal location, the
following information should be provided:
Conclusion

It is not necessary to address every aspect or Phasing Diagram


technical consideration that is discussed in the Controller Equipment
main body of the report. The summary should Detection requirements
focus on items presented in the report that are of CCTV
critical interest to the Municipality such as an Interconnection
accurate concise description of the recommended Power Source
design concept and the estimated cost. It should
be clearly stated how the recommended design On all projects where the primary justification, or
responds to the purpose and need of the project. an important justification, of the project is to
Both the major benefits (i.e. improve traffic improve safety, the DCR should include accident
circulation, improve intersection safety) and the history data and an analysis of the causes of the
adverse impacts (i.e. displacement of coastal accidents as well as a collision diagram.
vegetation) should be summarized. Estimates should be made of the accident
reductions expected if the improvement proposal
303 INTRODUCTION (or alternatives) is built. The monetary value of
the accident savings should be calculated over the
The introduction is to prepare the reader for the design period of the project (normally 20 years
subject matter that will follow in the body of the where geometric improvements are proposed).
report. It should only be a few paragraphs in
length and should provide a brief description of A summary of the traffic analysis shall be
the project as well as the reason for preparing the included in the body of the DCR. The complete
Design Concept Report. The project description report is also included as a separate Appendix.
should be very general and should identify the
projects location, the agency/municipality in 305 DESCRIPTION OF
charge of its implementation, and the source of ALTERNATIVES
funding that will be used for its design and
construction. A statement can also be included In consultation with the Municipality, the
that identifies how the project fits into the overall engineer shall develop alternatives to be evaluated
transportation infrastructure of the area. that respond to the project purpose and need to
varying degrees. The alternatives identified may
304 TRAFFIC ANALYSIS include separate horizontal alignments, profile
variations, typical section concepts etc., that can
The collection of traffic data and the traffic be evaluated in a matrix form to qualitatively and
projection procedures are discussed in Part 1, quantitatively review the alternatives to identify
Section 203.03, Traffic Counts. The data will be major differences. The engineering, social,
used to analyze and shape the various alternatives economic and natural environmental impacts for
and geometrics. This is an iterative process that each alternative under consideration must be
results in identification of the number of through addressed.
Part 1 300-3
ROADWAY DESIGN MANUAL Roads and Bridges

The horizontal alternative alignments will be the minimum design speed(s), min.
displayed on aerial photographs for evaluation of horizontal/vertical curve radii, sight min.
associated impacts. The sheets will show the distance (passing and stopping), max.
proposed centerline, stationing, proposed superelevation and other design requirements
structures, edge of pavement lines and affected associated with the classification of the road;
properties, at a scale that is appropriate to the the actual design speed(s), horizontal/vertical
project length and character. curve radii, sight distance (passing and
stopping), superelevation, etc. used for the
A cost estimate will be prepared for each project;
alternative and include: lane width, shoulder width, and bridge width;
on the project
Construction costs cross slope;
Utility relocation works costs grade;
Land acquisition costs horizontal and vertical alignment (actual);
horizontal and vertical clearance; and,
At this point, meetings will be held with various bridge structural capacity.
Municipality and Government Departments that
have a vested interest in the project. The engineer The design exceptions identified shall be prepared
will present the alternatives, review the evaluation in a Fact Sheet format as described in Part 2,
criteria and matrix form and discuss merits and Section 100, General Design Criteria.
adversities of the different alternatives.
Comments and direction received at the 307 TYPICAL SECTIONS
meeting(s) will be factored into the alternatives
evaluation matrix. The typical roadway cross sections and the
dimensions of the lanes, shoulders, median(s) for
Finally, the analysis will conclude with a both the mainline and all ramps are to be
discussion of the evaluation criteria for each identified. The number of typical sections will
matrix parameter, input/direction received depend on the number of significantly different
concerning the project and a summary discussion roadway/pavement structure conditions. At a
of the advantages and disadvantages of each minimum, at least one section should be provided
alternative studied. This will be followed by the which depicts all facilities within the limits of the
engineers recommended alternative with right-of-way (i.e., ramps, frontage roads, drainage
supporting justification for the selection. channels, etc.).

306 DESIGN DATA The type of roadway section, i.e., cut or fill,
number of lanes, shoulders, pavement structural
This section will document the design criteria section, cross slopes, and any retaining walls are
associated with the recommended design concept also to be included. Drawings that illustrate this
and specifically identify any exceptions from the information are to be included in the Appendix to
minimum criteria established for the roadway the DCR.
classification.
308 GEOMETRICS
It is very important that sufficient detail is
included in the DCR so that future revisions to The alignment, profile, and number of traffic
basic design features and project scope are held to lanes, including through lanes, auxiliary lanes,
a minimum. turning lanes and ramp lanes are to be plotted on
an appropriately scaled plan. A scale of 1:500
The following basic design criteria established in should be used for urban projects and 1:2500 for
Part 2, Roadway Design, shall be included: rural projects. The alignment should be displayed
on an aerial base and the corresponding roadway
the functional classification of the road per profile shown below in a split sheet format.
Part 1, Section 100, General Information.

Part 1 300-4
ROADWAY DESIGN MANUAL Roads and Bridges

The text in this section should include a narrative The results of the study shall be summarized in
description of the geometrics, constraints, the body of the DCR, with the entire study
controlling factors, drainage considerations and included in the Appendix.
reference to the design exceptions. The plans are
to be attached as an appendix to the DCR. The summary of the results shall include:

309 INTERCHANGE/ the existing parking demand


INTERSECTION the anticipated parking demand
CONFIGURATION the resulting parking shortfall (or excess)
the alternatives as to how the project can
The various types of traffic interchanges are provide adequate parking
described in Part 2, Section 500, Interchanges. cost comparison of parking alternatives
The discussion in this section should identify the economic impact of inadequate parking
site and project considerations which led to the if required by the roadway classification, the
selection of the interchange and intersection type. need for off-street parking facilities
the costs and right-of-way requirements
The site considerations include: associated with each of the above alternatives
the recommended alternative to meet the
the constraints imposed by the existing and anticipated parking demand,
nearby transportation facilities the conceptual design of the recommended
proximity of adjacent interchanges alternative (see Part 2, Section 211, Parking).
the standards and arrangement of the local
street system including traffic control devices 311 HYDROLOGY AND
right of way controls HYDRAULICS
local planning
community impact, and cost topography. The Design Concept Report shall include a
separate section (study) for drainage design
The project considerations include: concepts, which shall also include, when required,
separate reports for flood plain encroachment and
the speed, volume, and composition of traffic major waterway crossing studies.
to be served
the number of intersecting legs The drainage design concepts section shall
crossing and turning conflicts address the following items:
safety considerations
cost Planning consideration for the overall
watershed considering the project and other
The interchange/intersection alternatives should existing and future development
be evaluated as a part of the alternatives analysis
described in Part 1, Section 305, Description of Assessment of existing and future conditions
Alternative, when viable options are identified for affecting drainage areas, flow patterns, and
the particular project. This is especially true for flood levels
freeway and expressway projects where the
Interchange/Intersection type has a significant Estimate of future development and its effect
impact on the project character, capacity and on flows and flood levels
cost.
Drainage map showing topographic features,
310 PARKING STUDY watershed boundary, slope contours, drainage
areas, existing drainage systems, proposed
In accordance with Part 1, Section 202.09, cross-drain locations (including peak flow
Parking Requirements, a parking study shall be volume, design high water elevation and
prepared and included as part of the DCR. culvert size) and proposed conveyance

Part 1 300-5
ROADWAY DESIGN MANUAL Roads and Bridges

systems (pipes and channels including flow 311.02 PLANNING & PREPARATION OF
direction, sizes and peak flow volume) THE DRAINAGE DESIGN
CONCEPTS
Hydrology calculations for drainage area
intercepted by the project to include peak The Municipality often is and should be perceived
runoff volume flow rates from each drainage as a developer of transportation facilities that
area have the potential to stimulate secondary activity
along the transportation corridor just as a major
Proposed concepts for disposal of storm residential development can stimulate commercial
water. activity. Accordingly, there is a requirement to
address overall stormwater management needs in
Design criteria, procedures, methodology, and conjunction with existing and future developments
assumptions for analysis and design. planned for the foreseeable future. Because the
transportation corridor often traverses several
Proposed concepts for handling and disposing watersheds, the development of an adequate
of storm water during construction. stormwater management plan can be severely
fragmented and significant problems created if
Recommended size and location of cross there is a lack of coordinated planning among
drainage structures and channels, including concerned parties.
design high water elevation that might affect
the road profile grades or the roadway To be truly effective, a stormwater management
location. plan should consider the total scope of
development (i.e. transportation, residential,
Proposed concepts for on-site roadway commercial, industrial and agricultural).
drainage collection, detention, and outfall Department coordination with responsible
locations. Agencies and other Departments is essential to
ensure that proposed facilities match existing
ones, and that they are consistent with the long-
Separate Flood Plain Study Report where the
term needs of the area. Significant savings can
roadway encroaches on flood plains either
often be realised by planning overall combined
longitudinally or transversely.
stormwater management facilities, even though
the roadway development is only a small part of
Bridge Location and Hydraulics Report for
the total system. In addition, the Municipality can
bridge or large box culvert waterway
provide important information to other Agencies
crossings.
and private developers wishing to develop a
comprehensive stormwater management plan
311.01 PURPOSE
without assuming responsibility for the planning
and decision making process for the entire
The purpose of the drainage design concept study
watershed.
is to document the methodology and results of the
hydrologic analysis and the rationale used in
Accordingly, prior to design, a level of planning
developing the roadway drainage system. It shall
and coordination shall be undertaken by the
define the type, size, and location of cross
designers that will properly locate facilities and
drainage structures and channels, and determine
adequately address the overall drainage needs of
flood level elevations.
the overall watershed(s) in regards to existing and
future (foreseeable planning) development. This
The drainage design concept study shall determine
section provides general guidelines and major
the initial type, size and location of the onsite
considerations for evaluating these factors during
roadway drainage system and determine outfall
the planning process.
location(s). It shall also address any floodplain
encroachments and the overall watershed
planning.

Part 1 300-6
ROADWAY DESIGN MANUAL Roads and Bridges

311.02.01 Problem Categories aesthetically objectionable, and disrupt flow


and navigation.
Planning for drainage and stormwater
management facilities should include a Nutrients: Accelerated eutrophication that
consideration of the potential problems associated stimulates growth of aquatic vegetation can
with stormwater quality and quantity. Several cause a water body to become aesthetically
categories of data should be obtained and objectionable, deplete dissolved oxygen, and
evaluated including: decrease recreational value by creating odor
and overgrowth. Advanced eutrophication can
Runoff quality provisions lead to sediment build-up, which reduces
Runoff quantity determination storage capabilities.
Flood plain delineation
Inventory of problem and future Toxicity: The two types of toxics generally
developments found in stormwater (metals and
Development of alternative plan concepts pesticides/persistent organics) may build up
Consideration of multipurpose opportunities in sensitive areas over the long term. At high
and constraints levels, they can have serious shock effects on
Hydrologic and hydraulic analysis of aquatic life. Low levels can become
alternative concepts significant by accumulation up the food
Benefits analysis and evaluation chain.

These are further defined as follows: Quantification of the levels of contaminants that
are being washed off a roadway is complicated by
A. Quality: Several broad categories of the variable effects of and the periods between
degradation have been developed to delineate or storm events. The contributory factors are rainfall
describe levels of stormwater impacts: intensity, street surface characteristics, and
particle size. The varying interaction of these
Aesthetic deterioration: Undesirable general factors makes it difficult to precisely estimate the
appearance features (dirty, turbid, or cloudy) impact that discharge will have on water quality.
and actual physical features (odors, floating
debris, oil films, scum, or slime) are present. However, where it is suspected that periodic
runoff may have a serious quality effect upon the
receiving area, further investigation, analysis and
Dissolved oxygen depletion: When the oxygen
methods for solving the problem should be
demand of bacteria is stimulated by the
presented for review and approval.
organics, the subsequent reduction in oxygen
levels can disturb the balance between lower
The quality control management procedure
forms and the food chain. Unoxidized
particularly applicable to this region would
nitrogen compounds (ammonia) can also
consist of diverting the first 8 to 10 millimeters of
cause problems. This is of concern when
runoff into retention (often combined with
discharging into reservoirs, small, limited
detention for peak quantity control) basins where
flush, tidewater areas, and freshwater
the more concentrated contaminates and
streams.
sediments can be contained. The volume of
stormwater is then allowed to dissipate slowly by
Pathogen concentrations: High concentrations
seepage and evaporation, effectively trapping the
of several pathogens can reduce the
contaminates in the basin for periodic cleanout
acceptable users of the receiving waters. A
and disposal in a sanitary land-fill as needed.
concern where discharge may be accessed for
domestic use and discharge near public use
An exception is erosion and sediment control,
areas (bathing beach).
which is often a significant component of
stormwater quality. In general, erosion and
Suspended solids: The physical build-up of
sediment transport should be limited by
solids can cover productive bottoms, be
Part 1 300-7
ROADWAY DESIGN MANUAL Roads and Bridges

developing and implementing an erosion and 3. Will the project require retention or detention
sediment control plan which addresses both storage areas to mitigate the impacts of
temporary and permanent control practices. increased runoff, or can the increase be
handled by other project features?
B. Quantity: Determinations of stormwater
quantity are primarily useful for evaluating and 4. Is there sufficient area to construct a retention
mitigating the impact of a project. Without or detention storage within the project limits?
detention, land development increases peak runoff Are alternative sites available for storage of
rates and volumes from storm events, which can stormwater?
lead to higher flood elevations. Appropriate
hydrologic and hydraulic calculations presented in 5. What are the groundwater and soil
various chapters of this manual should be made to conditions? Is there a high groundwater
determine the required conveyance through the table, or are there impermeable soil layers?
Municipalitys project limits, and to aid in
mitigating impacts to downstream structures and C. Flood Plain Encroachment: The primary
development. drainage consideration for facility location in
highway planning is the evaluation of the impact
Procedures contained in Part 2, Section 700, of flood plain encroachment for a steam or wadi
Roadway Drainage Design, should be used to crossing or where the road embankment
evaluate the ability of a facility to accomplish the longitudinally encroaches into the flood plain
following controls for a particular area: area.

Provide positive drainage and runoff The following factors for locating a stream
collection to the minimum criteria for safe crossing that involves encroachment within a
passage of traffic on the project roads and flood plain area:
parkings.
Waterway characteristics (stable or
Reduce runoff rates when applicable by unstable)
increasing infiltration, and by storing Geometry
precipitation and runoff where it falls and Hydrology
releasing it slowly. Hydraulics
Alignment
Protect areas subject to flood damages by Flood plain flow
keeping runoff confined to drainage facilities Needs of the area
such as pipes or channels and by building Economic and environmental concerns
appropriate flood control facilities.
A detailed evaluation of these factors is part of
Maintain offsite flows, through the project the bridge location and hydraulics study. When a
area. suitable crossing location has been selected,
specific crossing components can then be
Limit flood plain enroachment to acceptable determined. When necessary, these include the
upstream/downstream flooding impacts. geometry and length of the approaches to the
crossing, the probable type and approximate
The following questions should be considered location of the abutments, the probable number
when selecting the plan for disposal of stormwater and approximate location of the piers, the
runoff: estimated depth to the footing supporting the piers
1. Are existing drainage systems large enough to (to protect against local scour), the location of the
handle runoff? longitudinal encroachment in the flood plain, the
amount of allowable longitudinal encroachment
2. Are runoff estimates consistent with adopted into the main channel, and the required river
drainage plans and Municipality criteria? training works, to ensure that river flows
approach the crossing or the encroachment in a
Part 1 300-8
ROADWAY DESIGN MANUAL Roads and Bridges

complementary way. Exact information on these before and after the proposed project in both the
components is usually not developed until the upstream and downstream directions for a
final design stage. distance to where it can be shown that no further
impact over pre-project conditions is influenced
Where the roadway embankment encroaches by the project for: (i) the design event storm, (ii)
significantly in a longitudinal direction into the for the 100 year storm, and (iii) the maximum
flood plain, a separate floodplain encroachment probable storm (usually the 500 year event).
study must be made to evaluate the increased Besides the peak water surface profile, the
flood depths and velocities that may impact, analysis shall include the flow volumes, velocity
upstream and down stream properties. profiles (velocity at various points in the cross-
section), and hydraulic structural alternatives that
Further details defining flood plain encroachment were evaluated to mitigate significant
are provided in Section 311.02.02. encroachment.

D. Other Departments Coordination: The frequency with which the highway or


Coordination between concerned agencies during watershed divide is likely to be overtopped should
the project planning phase will help produce a be stated. If the overtopping flood is a 500-year
design that is more satisfactory to all. Substantial flood or greater, it should be stated. The location
cost savings and other benefits frequently can be of the overtopping should be indicated.
realized for both the roadway and other
development projects through coordinated B. Economic Analysis: An economic analysis
planning between the various Government should include a comparison of design
Departments and private developers. alternatives, using expected total costs
(construction costs plus risk and damage costs) to
311.02.02 Flood Plain Encroachment and determine the alternative with the Least Total
Risk Evaluation Expected Cost (LTEC). The comparison will
include probable flood-related costs during the
When a highway project will encroach on a flood service life of the facility for: highway operation,
plain, careful consideration must be given to the maintenance, and repair; highway-aggravated
potential risks from the encroachment. Any flood damage to other property; and additional or
proposed project that encroaches on a flood plain interrupted highway travel. Other costs include
either transversely or longitudinally, and is crop damage, structure damage and public
predicted to result in a significant adverse impact inconvenience.
on natural flood plain values, a significant
increase in flood risk, or a significant change in C. Study of Flooding Encroachments: The
the potential for interruption of main access flood plain study should include an inspection of
roadways, emergency service or major services, the flood plain to determine the increase in the
must be evaluated with a complete hydraulic number of flood receptors and the increase in the
analysis and a risk analysis, to be included in a damage to present flood receptors that will result
separate flood-plain study or a bridge location from the expected increase in flood heights.
and hydraulics study for transverse crossings. Consultation with local citizens and other
These separate reports must document Departments should be initiated where necessary
considerations of alternatives which do not to adequately assess encroachments.
include such encroachments. Significant
encroachments will not be approved unless there D. Risk Assessment: All designs with flood
is no practical alternative. plain encroachments should include an evaluation
of the inherent flood-related risks to the highway
The flood plain study (and/or bridge location and facility and to the surrounding property. In the
hydraulics study) shall include the following: traditional design process, the level of risk is
seldom quantified, but is instead implied through
A. Hydraulic Analysis: The hydraulic analysis the application of predetermined design standards.
must provide the water surface profile elevations For example, the design frequency, backwater

Part 1 300-9
ROADWAY DESIGN MANUAL Roads and Bridges

limitations, and limiting velocity are parameters constraints would be the preferred design. This
for which design standards can be set. design should then be investigated for the 100-
year flood.
Two other approaches, however, are available
that quantify risk on projects that involve 311.02.03 Data Collection
highway facilities designed to encroach within the
limits of a flood plain. These are risk assessment Identification of drainage data needs should be a
and economic analysis. Risk assessment is a part of the early planning phase of a project,
subjective analysis of the risks engendered by when appropriate procedures for performing
various design alternatives, without detailed hydrologic and hydraulic calculations are
quantification of flood risks and losses. It may selected. Several categories of data may be
consist of developing the construction costs for relevant to a particular drainage project, including
each alternative and subjectively comparing the published data such as precipitation, soils, land
risks associated with each alternative. Economic use, topography, streamflow and flood history.
analysis (sometimes called risk analysis) Published mapping is usually inadequate, so field
encompasses a complete evaluation of all investigations and surveys are necessary to
quantifiable flood losses and the costs associated determine drainage areas, identify pertinent
with them for each structure alternative. This can features, obtain high water information, survey
include damage to structures, embankments, lateral ditch alignments and survey bridge and
surrounding property, traffic-related losses and culvert crossings. In addition, hydrology
scour or stream channel change. The level of calculations for a watershed or larger drainage
expense and effort required for an economic area will usually require some sort of topographic
analysis is considerably higher than for a risk mapping. The preferred mapping is using aerial
assessment, and selection of the process to be photography showing contour elevations using
used should be based on the size of the project digital techniques is preferred. Manual ground
and the potential risk involved. A risk assessment surveys are usually adequate for smaller areas.
is usually more appropriate for small structures The requirements in more detail are as follows:
or for structures whose size is highly influenced
by non-hydraulic constraints. A. Data Collection Procedure: Drainage data
should be collected before calculations are
Policy dictates that hydraulic facilities be initiated, under the following general guidelines:
designed so that highway facilities will perform
without significant damage or hazard to people or 1. Identify data needs, sources, and uses. Much
property during the appropriate standard design of this information will have to be provided in
frequency flood. Risks associated with floods of the concept report and kept in the supporting
magnitudes greater than the standard design files.
frequency flood should be evaluated in
accordance with the risk evaluation levels 2. Collect published data, based on sources
presented in this section. If warranted, a design identified in Step 1.
based on a lower or higher frequency flood may
be used. The minimum design frequency for 3. Compile and document the results of Step 2,
bridges on main highways, however, is 50 years. and compare data needs and uses with
published data availability. Identify any
A typical example would be a major cross drain additional field data needs.
box culvert for a primary highway. The standard
design frequency would be a 50-year frequency 4. Collect field data based on needs identified in
flood. A design based on this frequency should Steps 1 and 3.
be produced in the "traditional" manner, including
development of feasible alternatives. The 5. Compile and document the results of Step 4.
alternatives would be compared for cost and for
risks associated with the 50-year frequency flood. B. Published Data: At present, there is limited
The lowest total cost structure that met the design published data with regards to soils, land use,

Part 1 300-10
ROADWAY DESIGN MANUAL Roads and Bridges

streamflow, flow histories, etc; however, a For urban type construction surveys, appropriate
thorough search for soils investigation records city maps or specially prepared maps should be
and existing utility/drainage systems should be marked to show the boundaries of total areas
made from as-builts of other projects in the contributing to the project. Streets or other
vicinity. Old newspaper records may also be a drainage facilities in these areas should be marked
source of timing and pictures of past flooding with flow arrows. In many instances, elevations
events. may have to be determined to accurately delineate
direction of flow in gutters or side of road
C. Drainage Areas: If there is sufficient channels.
topographic information for a project site from
readily available sources (aerial mapping), a field All areas contributing to existing storm drains
determination of drainage area may not be which drain to or across the project should be
necessary, but spot-checking selected control shown. In very flat terrain, it is often necessary
elevations is always advised. For those project to develop profiles for cross streets and parallel
sites for which detailed information is not streets to make a definite determination of
available, field survey work or aerial photo drainage areas.
mapping should be performed. In all cases, a site
visit by the designer is mandatory to confirm Specially flown aerial photography should be
drainage area conditions. obtained for most construction projects.
Elevation contours and ridge lines usually can be
Drainage areas shall be outlined on the drainage indicated on the photographs utilizing digitized
map (preferably on a contoured photo base map). cartography combined with ground based control
Drainage area boundaries should connect with the surveys. When photographs are used, the field
job centerline, typically at high points in grade or survey party should verify questionable points
at other locations where there is a definite division and supplement the information with structure
in the direction of storm runoff flow. After the sizes, elevations, and elevations as required.
overall areas are plotted, the drainage area should Drainage areas can also be determined by stereo
be sub-divided to show how the various sections interpretation of stereo paired photographs with
contribute to the structures in the proposed spot field survey work as appropriate (usually
drainage or storm drain system. sufficient for smaller areas).

All drainage area boundaries should be followed D. Drainage Maps: For roadway projects, the
from project centerline around the area being drainage maps should be prepared on pre-
covered and closed again to the roadway formatted sheets that use a cross section grid
centerline. Ridges that do not establish an area printed across the lower portion for plotting the
draining to the project should not be shown unless project profile. The profile is plotted to some
pertinent to determination of runoff concentration convenient scale according to need. For projects
points or flow path segments. Exceptions to the involving interchanges, rest areas, urban streets
rule for closing all drainage area boundaries to and the like, a supplemental drainage map that
centerline are to be indicated clearly on the map shows only the plan portion on a sheet without a
by notation. These notations should show profile grid is required. The supplemental map is
location and elevation of breakover or diversion to provided to show the small areas needed to
or from the drainage area. calculate pipe sizes for the tabulation of drainage
structures within these special areas.
Typically, a drainage area should close to each
existing culvert along the project, for each The following data should be provided on the plan
probable cross drain location to each inlet for portion of the map:
piped system, and protected overland flow
entrances to channels. As an exception, where 1. Physical land features affecting drainage,
two or more structures operate conjunctively to such as elevation contours, land use,
drain a single area, flow distribution information vegetation cover, streams, wadis, reservoirs
should be noted. and tidal areas, together with past high water

Part 1 300-11
ROADWAY DESIGN MANUAL Roads and Bridges

and date of occurrence, if available, and 6. In the report, the various cross-drain
present water elevations with the dates of the culverts should be summarized by station,
readings, as appropriate. size, invert elevation and minimum culvert
backfill values for pH, resistivity, sulphates,
2. Existing drainage structures, showing type, and chlorides for the various alternate
size, flow line, flow direction, and any other culvert materials.
pertinent data.
The profile portion of the map should include the
3. Drainage divides and information, where following data:
applicable, to indicate the overland flow of
water. Drainage areas on maps of urban and 1. Plot of the existing ground, done in a light
rural sections should be shown to the solid line to the same horizontal scale as was
accuracy necessary, depending on the system used for the plan portion.
involved. A guide to the appropriate
accuracy for a non-critical system is 2. Drainage map sheets with the profile blocks
provided. Critical systems usually require a deep enough to sufficiently show the
drainage area determination within 2 to 3 necessary profiles and cross-drain profiles.
percent.
3. Plot of the proposed profile grade line.

Size Accuracy 4. Plots of all proposed special ditches, except


median, when horizontal and vertical scales
Drainage Mainly Mainly permit.
Area Impervious Pervious
(Hectares) (Hectares) (Hectares) 5. Plots of proposed cross drains, except
0.0 - 0.2 0.02 0.04 median drains. Skew and pipe slope are not
0.2 - 2 0.04 0.08 shown.
2-4 0.08 0.2
4-8 0.2 0.4 6. For urban projects, plot only the storm drain
8 - 20 0.4 0.8 and mainline structures. Laterals are not
20 - 40 0.8 2 plotted. Flow line elevations are posted
40 - 80 2 4 along the main.
>80 4 10
E. Existing Features Survey: In areas draining
Inserts are used to show areas of such to a project site, all streams, wadis, ditches,
magnitude that the boundaries cannot be reservoirs, drainage structures, and other possible
plotted at the regular scale. Proposed conflicting utilities should be shown. Flow lines,
drainage structures are plotted by symbol controlling grade elevations, and high water
only in the plan portion and noted by stages should be documented for existing
structure number. structures. The concept report should note record
the estimated reliability of flow and high water
4. Aerial photography is desirable because it observations.
will document the development and often the
drainage pattern which existed at the time of 1. Survey Notes: The drainage survey notes
design. should show all pipe lines, culverts, and bridges
in place on the existing roadway. Pipe length,
5. Design, base, and overtopping (or maximum size, type, and conditions should be given. The
probable flood) discharge and stage values design for alternate culvert materials requires
are required on all expressway and mainroad accurate information on the condition and length
projects for all cross structures that would of service for existing culverts. Data on
back floodwater outside the project limits, corrugated pipe should include material (steel or
regardless of structure size. aluminium), coatings, size, and type (annular or

Part 1 300-12
ROADWAY DESIGN MANUAL Roads and Bridges

spiral) and size of corrugation. Flow line any location where water comes to and/or leaves a
elevations of pipes should be shown at both inlet proposed project. They should clearly show the
and outlet. For box culverts to be extended, an path and approximate elevations of flow for
accurate sketch should be made showing the size existing ditches and natural streams. Inflow data
and length of the culvert, thickness of all walls, should be provided for a distance sufficient to
wings, and slabs, and the angle of the barrel with indicate the degree of channelization and the
the survey centreline. Elevations should be given direction of flow, usually a distance of 30 to 100
on the top of the bottom slab, top and bottom of meters.
top slab, parapet walls, wings, etc., on each end
of the culvert. Data on the outfall portion should extend far
enough to determine the direction and degree of
The type, length and width of roadway, location channelization and the rate of fall in water
of bents, number of piles per bent and type of surface, and to reach a point of positive and safe
footings should be shown for bridges in place. disposal. If ditch or channel work appears
Profiles should be shown as centerline of necessary, collection of topographic data should
roadway, from the edge of pavement left and right continue downstream to a point at which damage
of centerline of survey, and under the bridge on to adjacent property appears to be insignificant.
centerline of survey. The profiles should
accurately define the top and bottom of channel If the length of an outfall raises serious doubts
banks and the channel bottom. about its usefulness, the field party should
terminate the survey at 150 meters and note the
2. High Water Information: Reliable high approximate distance to a suitable disposal point.
water information is necessary to evaluate flood This note should give the distance, the water
elevations and establish roadway grades. High elevation at the approximate end, and a brief
water elevations should be shown upstream of the description of the topography (i.e., tidal bay,
proposed project, upstream of significant existing reservoir, wadi, etc.) into which the outfall will
structures, and at some point along or at the end drain if extended. The designers can then
of outfall ditch surveys. The location at which a determine if a further detailed outfall survey is
high water elevation is taken should be clearly required.
recorded in the field notes, along with the date and
time if available. The field survey for a lateral ditch should always
include property boundaries or plot walls/fences,
At many locations, it is not possible to obtain which are often the determining factors in the
documents information on high water. In such ultimate location of outfalls. With property
cases, elevation may be estimated by observation boundaries marked, the design engineer is in a
of natural growth, evasion marks or by other much better position to determine the extent of
means. The survey crew should provide complete cross-sectioning needed to cover possible
information on the methods used. The crew chief alterations in alignment, and the design engineer
should attempt to obtain information from local is aware of the limitations in changes he may
residents or maintenance personnel. consider.

The soils investigation usually supplies water 4. Bridge and Large Culvert Surveys:
table information within the project limits; Locations of larger culverts and bridges often
however, the survey crew should note information must be detailed. The meander of both banks of a
pertaining to standing water, areas of heavy stream for a sufficient distance upstream and
seepage, or springs within the basin area. downstream to determine the approximate extent
of any probable channel relocation should be
3. Lateral Ditch Surveys: Most highway section obtained. This ordinarily can be shown within
projects should routinely include lateral ditch 150 meters upstream and downstream from the
surveys at the locations of existing ditches, project. Any major overflow channels also should
streams, wadis, swales, etc. The surveys should be indicated within approximately the same limits
provide a clear picture of existing conditions at or within the limits that these channels leave and

Part 1 300-13
ROADWAY DESIGN MANUAL Roads and Bridges

return to the main channel. Meandering channels Field surveys at existing bridges should include
close to and approximately parallel to the project three profiles: the first on the survey centerline,
centerline should be located carefully and cross- the second approximately 10 meters right of the
sectioned. survey centerline, and the third approximately 10
meters left of the survey centerline. The purpose
Across flood plains where the proposed project of the second and third profiles is to provide data
follows an existing fill, cross-sections should at the edge of the bridge. The centerline profile
extend far enough to provide a record of natural should show the roadway grades and the ground
ground profiles right and left of the project. Any line under the bridge. Cross-sections should be
washouts or significant swales, side wadiis, taken across the bridge area to furnish elevations
sloughs or ditch outlets should be noted clearly in for plotting the face of the slopes and for accurate
the topography. plotting of low water channels. All profiles
should include points indicating the top of the low
Recommendations for significant realignment or water banks (the edges of the low water channel),
improvement of an existing channel often will water level at the date of the survey, and the
come as part of the structure design, making it profile of the stream bed along the survey lines.
necessary to survey a designated location. For Where new lanes for the roadway are to be
this reason, specific channel location surveys located at bridges from a survey along the old
should not be made during the initial location roadway using cross-sections for approximate
survey unless the need for and logical location of elevations, it is necessary that the three profiles be
such changes are apparent. run along each side of the new roadway,
furnishing complete channel limits and elevations
Required data on existing roadway and railroad on each profile. These surveys should include
structures upstream and downstream should be corrected stationing referenced to the road survey,
identified by the drainage engineer so it can be showing station and elevation equalities if
included in the survey. For fills and structures in necessary. At expressways, where a single profile
reasonable proximity to the project, a profile of is run along the centerline of the median for the
the existing roadway showing structure openings roadway survey, the three profiles and cross-
should be established relative to the project data. sections should be performed for each lane at all
For structures farther removed, it is often bridges.
adequate to include only a profile and high water
information. The information should include 5. Documentation: Documentation involves the
observations on scour, washouts, or other compilation and presentation of all pertinent
pertinent hydraulic factors. Where scour is watershed data collected for the project. It should
significant, cross-sections should be taken to include (but is not limited to) basic items such as
determine the depth and extent. drainage area and other maps, field survey
information, published data references,
Appropriate flood elevation data should be photographs, and narratives from witnesses of
obtained for bridges. If reliable data is not historic floods. This data should be maintained in
available, that fact should be noted by the field the permanent records. The orderly compilation
party. The extreme high water, its location, and and presentation of watershed data will expedite
the approximate date of its occurrence should be the design, review, and evaluation phases of a
recorded, if available. Other elevation high water drainage project
that can be dated should also be recorded when
practical. If possible, a "normal" high water 311.03 STORM WATER HYDROLOGY
elevation, or one which can be expected to recur
about every 2 to 3 years, should be determined. To convert precipitation to stormwater runoff,
A normal elevation that would be expected to hydrologic calculations are generally used to
prevail through seasons of average rainfall should quantify the abstractions (precipitation losses)
be recorded. which occur as part of the hydrologic cycle.
Virtually all drainage and flood plain calculations
only consider infiltration, interception, and

Part 1 300-14
ROADWAY DESIGN MANUAL Roads and Bridges

surface storage losses, since short time scales will 7. Perform downstream channel and reservoir
usually render losses from evaporation and routings, as appropriate.
transpiration insignificant. A possible exception
to this usage is for land-locked watersheds. 8. Record the necessary calculation process
and the results on the appropriate drainage
Since the governing relationships of hydrology are maps, and in the drainage section of the
complex and, unlike problems in engineering Design Concept Report, as appropriate.
mechanics, are not easily solved through direct
use of the fundamental laws of physics, a wide 311.04 OPEN CHANNEL HYDRAULICS
variety of hydrologic procedures have been
developed. Procedures for making time of The consideration of open channel hydraulics is
concentration and rainfall excess calculations, an integral part of roadway projects in which
procedures for estimating peak runoff rates at artificial channels and improvements to natural
gaged and ungaged sites, procedures for channels are a primary concern. Procedures for
developing design storm hyetographs, and flood performing uniform flow calculations that aid in
hydrograph and hydrologic channel routing the selection or evaluation of appropriate channel
procedures are contained in the drainage volume linings, depths, and grades are included in the
of the design manual. drainage volume of the design manual. For most
artificial channels, the most desirable lining is
Drainage studies often follow a similar sequence natural, emerging vegetation, with grass used to
of calculations for all procedures, because provide initial and long-term erosion resistance.
precipitation must be routed through watersheds, If natural vegetation, usually grass, is unfeasible,
channels, and reservoirs. In most cases, concrete lining is used. Also, flexible linings
stormwater runoff will be estimated using the comprised of rock riprap asphalt or articulating
following general procedure: concrete grids can be used for preventing erosion.
Allowable velocities and permissible depths of
1. Divide the watershed into appropriate flow are provided in the drainage volume of the
subareas to correspond with homogeneous design manual, along with various adaptations of
land use conditions and the placement of Manning's Equation suitable for evaluating
drainage facilities such as inlets, reservoirs, channel capacity.
and open channels.
Open channels can be generally classified as those
2. Collect and analyze watershed data. which occur naturally and those which are man-
made or improved natural channels. The later,
3. Establish design storm conditions as called artificial channels, include the following
appropriate for the procedure selected. types in use on most roadway project:

4. Calculate the peak runoff rate or determine 1. Right-of-way ditches which usually acts as
the time distribution of rainfall excess. No an overland flow interceptor ditch collecting
further calculations are generally required if water before it reaches the roadway.
only the peak runoff rate is desired. 2. Roadside or roadway ditch and (sometime
called the borrow ditch)
5. Develop a unit hydrograph for the 3. Median ditches on divided highway.
watershed, if a runoff hydrograph is desired 4. Outfall ditches for connecting and carrying
and the procedure selected uses a unit flows from ditch types 1, 2 and 3, a short
hydrograph. distance to a natural outlet or to another,
larger conveyance channel.
6. Develop the direct runoff hydrograph, using 5. Lateral ditches are a larger size channel,
the unit hydrograph and rainfall excess usually used for continuing upstream flows
determined above, as appropriate. past the project area.
6. Canals are large size conveyance channels.

Part 1 300-15
ROADWAY DESIGN MANUAL Roads and Bridges

Each of these channel types are artificial systems 311.05.01 Bridge Location and Hydraulics
designed to provide specific drainage capacities. Report
The right-of-way ditch functions as a type of
relief ditch, handling drainage needs other than A. Documentation: Documentation shall be
those for the roadway and thus freeing roadside provided in detail commensurate with the
ditches from carrying anything except roadway complexity of the project. Documentation shall
runoff. Right-of-way ditches can also act as be sufficient enough so that an independent
interceptor ditches to provide a method for engineer with expertise in bridge hydraulics, but
intercepting offsite flows or subsurface not involved with the design, can fully interpret,
groundwater flows above cut slopes, thereby follow and understand the logic, methods,
controlling slope erosion. computations, analysis and considerations used to
develop the final design.
In general, roadside or median ditches are
relatively shallow trapezoidal channels or swales Documentation for bridge and large culvert
(which are shallow triangular channels). Both designs shall include as a minimum the following:
types are designed to handle local surface runoff
from roadway surfaces, or to lower water table 1. Hydrologic analysis including sources of data
elevations by intercepting groundwater. In some and methodology.
cases, they may also handle other than project
drainage. Outfall ditches or canals are designed 2. Alternative analysis or evaluation of structure
in most cases as receptors of runoff from sizes (length and vertical height/clearance).
numerous secondary drainage facilities, such as This evaluation shall be done consistent with
side ditches or storm drains. The use of a Department criteria for bridge hydraulic
roadside ditch as an outfall ditch is not design and shall include consideration of:
recommended, since its probable depth and size
could create a potential hazard. a. cost
b. design standards
311.05 BRIDGE HYDRAULICS c. structure hydraulic performance,
including backwater, velocity and scour
Bridge hydraulic designs shall be documented in d. Impacts of the structure on adjacent
the Bridge Location and Hydraulics Report property
(BLHR). Design information shall be e. environmental impacts
summarised on the Bridge Hydraulics
Recommendations Sheet (BHRS). The format for 3. The alternative analysis shall include the
the BHRS is provided in Section 3.11. reasons for selecting the recommended
structure and a clear explanation as to why it
BLHR and the BHRS shall be prepared for the is the most economical structure for the site in
projects listed below: question. As a minimum, the following
structure sizes shall be evaluated:
1. Bridges and large culverts (culverts larger
than 1800 mm dia pipes or 1200 mm x a. The minimum structure size required to
1200m box culverts) on new alignments meet hydraulic standards for vertical and
2. Bridge and large culvert replacements on horizontal clearance, scour and
existing alignments backwater.
3. For other bridge and large culvert projects b. Existing structure size if applicable.
involving actions within the Base Flood c. The recommended structure size if
Plain (work within the 100 yr. Flood different from (a) or (b).
elevation) e.g., bridge widening and large
culvert extensions. 4. Design recommendations for bridges
recommendations shall include:

Part 1 300-16
ROADWAY DESIGN MANUAL Roads and Bridges

a. Bridge length, and justification for the the subsections identified below. Rather than a
length, including locations (stations) of formal item by item approach, a narrative
abutments description of the site and the hydraulics
b. Channel excavation requirements recommendations is suggested.
c. Minimum vertical clearance
d. Minimum horizontal clearance Preliminary Information
e. Abutment type and orientation
f. Pier orientation A. General Site Location
g. Scour depths for the design flood, 100-
year flood and maximum probable flood 1. Highway Description
(usually the 500-year flood).
h. Scour protection requirements for a. Type (expressway, main, secondary,
abutments, piers and channel rural, urban, etc.)
i. Deck drainage b. Lanes (two, four, divided, limited across,
etc.)
5. Documentation of large culvert hydraulic c. Importance (main access between towns
designs shall include hydraulic calculations and borders, military route, alternate
and recommendations for the following: routes available, etc.)

a. Culvert Size, and justification for the 2. Topography of site and basin
size, barrel length and location 3. Location: small scale map with site located
b. Peak water surface profiles and cross-
section velocity profiles for the design B. Potential Site Problems
flood, the 100 yr flood and the maximum
probable flood for a distance 150 meters 1. Land Use (obtain from responsible
upstream, through the culvert to a Department)
distance 150 metres downstream.
c. Upstream and downstream invert a. Encroachment on the flood plain
elevations. b. Recreational use
d. Endwall type for entrance and outlet, c. Domestic water supply
including the need for an improved inlet. d. Security area
e. Skew
f. Inlet end and outlet end scour protection 2. Channel Stability
requirements
a. Bank stability
6. Final project plans shall show the peak b. Bends and meanders
stages, peak discharges, peak velocities, and c. Potential for natural change of channel
peak scour predictions for the design flood, d. Aggradation or degradation of bottom
the 100 year flood and the maximum e. Scour history
probable flood that can be expected to flow
through the structure. 3. Potential Water Stages

B. Report Outline: An outline of items that a. Flood history (dates; stages; source of
should typically be considered in the preparation information; extent of flooding;
of a BLHR is given below. Non-applicable items approximate frequency; damage to
should be so indicated rather than omitted without structure, embankment or highway)
comment. Additional information may be b. Potential backwater from other streams
appropriate at unusual sites. or rivers
c. Reservoirs of flood control projects
The BLHLR should be divided into two basic (Department and status)
sections: Preliminary Information and Design d. Tidally affected (mean high and low
Data. These sections are then broken down into water)

Part 1 300-17
ROADWAY DESIGN MANUAL Roads and Bridges

e. Other controls, if any 7. Determination of design discharge and


f. Normal high and mean high water stages development of discharge-frequency curve
8. Determination of design flood stage and
4. Clearances (horizontal and vertical) development of stage-storage-frequency curve

a. Drift at flood stage (not necessarily at D. Hydraulic Analysis


peak backwater stage)
b. Navigation at mean high water or normal 1. Bridges
high water stage
a. Determination of permissible upstream
Final Design Data water surface
b. With bridge length set to minimum
A. Inventory of Existing Crossing(s) criteria or environmental controls,
determination of backwater
1. Location in relation to crossing(s) c. Adjustment of (b) if required to satisfy
2. Determination of drainage area (when (a)
significantly different) d. Check of conveyance for 100-year flood
3. Physical data on structure(s) (size, type, and maximumbable flood; adjustment of
spans, foundation type, low member, bridge length if required
available waterway area) e. Evaluation of scour potential
4. Flood history f. Evaluation of need for channel changes
5. Evaluation of hydraulic adequacy of g. Evaluation of need for bank protection
structure(s) (Note: This data should be including limits of protection, type,
obtained not only for the site under materials, and specifications
consideration, but upstream and downstream h. Evaluation of need for spur dikes and
crossings as well) other training devices
i. Evaluation of effects of construction and
B. Selection of Design Flood temporary activities
j. Evaluation of effect on downstream
1. Importance to highway system structures and properties
2. Importance to life and property
3. Conveyance of design, 100-year and 2. Large Culverts (any cross-drain culvert larger
maximum probable flood (under or than 1800 mm dia pipe, or 1200mm x 1200
over/under the highway) mm box culverts)

C. Hydrologic Analysis a. Determination of allowable headwater


(AHW) and design storm tailwater
1. Site review (extremely important) elevations
2. Interview with persons providing flood b. Selection of trial culvert size
history data c. Evaluation of culvert for abrasion,
3. Review of available flood records corrosion, debris, scour, suitability for
(Department, newspapers) improved entrance, etc.
4. Review of available stream gages in vicinity d. Design of inlet and outlet scour
5. Definition of drainage area above site protection, if necessary
6. Evaluation of potential watershed basin e. Check of conveyance of 100-year flood
changes (20-year minimum) and max. probable flood
f. Evaluation of effect on stream stability.
a. Urbanization g. Evaluation of effect on fish and wildlife,
b. Channelization if applicable
c. Water management practices h. Evaluation of effect of channel change
i. Evaluation of effect on downstream
properties and structures

Part 1 300-18
ROADWAY DESIGN MANUAL Roads and Bridges

E. Additional Survey Data of Proposed Site design flood, the base (or 100-year) flood, and
either the overtopping or maximum probable
1. Data sufficient to prepare a contour map flood, whichever occurs first. The overtopping
(intervals at 30 cm or 60 cm depending on flood is the one in which flow crosses the
scale); required distance upstream and highway, or spills into another watershed or
downstream will vary with site through a relief structure. The max. probable
2. In lieu of (1), a minimum of three cross flood is normally a 500-year event. Flood data
sections will suffice for some cases includes stage elevation, discharge, average
(upstream, at, and downstream of site) velocity (on larger crossings a velocity profile
3. Vegetation, estimated bed load, bottom soil across key cross-section is usually needed) and
material and soil properties, and other general exceedance probability.
site parameters
Water surface elevations are classified as normal
F. Departmental Coordination high water for non-tidal areas and as mean low
and mean high water for tide-influenced areas.
1. Contact Departments involved and identify Normal high water is defined as the 2-year event;
what other projects may be affected by the mean low water and mean high water data can be
culvert/bridge obtained from the admiralty charts.
2. Investigate possibility or necessity for a
cooperative project Hydraulic recommendations should include the
beginning and ending bridge stations, data on the
It is also suggested that a checklist of required channel section (including any excavation),
items for each site be prepared and given to the navigation and drift clearances, scour prediction,
survey crew to ensure complete data will be slope protection, and deck drainage.
obtained with a minimum of supplemental or
unnecessary effort. Space should be provided for a small scale
location map outlining the drainage area. A plan
311.05.02 Bridge Hydraulics view of the existing and proposed bridge area
Recommendations Sheet (BHRS) must also be included. The scale should
adequately depict the area adjacent to the
The BLHR is a full size drawing, to be included structure, including existing and proposed
with the BLHR. It is divided into several contours. Drainage areas for very flat sites
information blocks, which must be as completely warrant careful delineation since only one or two
filled out as is appropriate for the design and contours may occur. For a bridge, a profile of the
location. The BHRS must always include the channel section should be shown; for a large
Project Number and the Bridge Number as per culvert, the culvert centreline should be profiled.
the drainage map in the title box. The profile should show channel work and bridge
end treatment. If necessary for clarity, bridge
The information requested for existing bridge or ends should be drawn at a larger scale.
large culverts near the site includes foundations, The assumed configuration, deck drainage, and
overall length, span length, type of construction, scour recommendations need to be approved by
area of opening at high water, roadway width, the Municipality before plans are completed.
and the low member elevation. The area of This review provides an opportunity to evaluate
opening at high water generally refers to the flow the impact of substantial changes on the hydraulic
area available through the existing structure design conditions.
below the water surface determined for a design
storm frequency.

The BHRS hydraulic design data section should


include water surface elevations and several
categories of flood data for various events,
including the maximum event of record, the

Part 1 300-19
ROADWAY DESIGN MANUAL Roads and Bridges

311.06 STORMWATER Conveyance of drainage to the site


MANAGEMENT USING Availability of land
RETENTION/DETENTION Suitability of site for water storage
DESIGN Availability of suitable outlet point
Adjacent land use
In general, retention refers to stormwater storage Roadway control elevations
without access to a positive outlet, while detention Soil infiltration capability
facilities offer temporary storage accompanied by
Water table fluctuations
controlled release of the stored water. Wet
Outfall high water elevations
detention typically has a pool of water below the
Type of facilities proposed
outlet elevation; dry detention is typically placed
with the basin bottom above the seasonal high Safety and maintenance requirements
water table. Retention and detention can be used
separately or together in storage basins as site Planning for retention/detention facilities should
conditions and management objectives require. be co-ordinated with the evaluation of borrow
requirements for the project. To the maximum
Historically, "detention" basins are used only extent possible, excavation from construction of
when such use reduced the outfall size (by the retention/detention basins should be used as
reducing the peak discharge) enough to justify the fill material. If borrow material is required for
cost. An additional benefit is that they can also basin embankments, it should be obtained within
be effective in improving stormwater quality. the project limits, if possible.

The drainage volume of the design manual The objective of drainage design is to provide the
provides general design criteria for necessary roadway drainage facilities which
retention/detention basins as well as procedures allows the public to use the roadway during times
for performing preliminary sizing and final of significant runoff and in a manner that
reservoir routing calculations. The Storage minimizes the potential for adverse effects on
Indication Method is presented as an acceptable adjacent property and existing patterns.
method for detention calculations. Exfiltration
calculations may be required for certain retention The effect of the roadway on the existing drainage
systems for estimations of percolated discharge pattern, the potential flood hazards, as well as the
rates. effect of floods on the roadway are to be assessed
in the design process.
Land-locked drainage areas will require retention
storage areas designed to meet special The engineer shall perform a drainage study in
considerations. accordance with current design methodology,
requirements and criteria in the drainage volume
The collection of field and published data for the
of the design manual. The criteria should identify
planning and location of retention/detention
such items as the hydrology method to be used,
facilities should be coordinated so that it can be
the design storm frequency to be accommodated,
accomplished concurrently with other aspects of a
the allowable spread of water on the pavement to
particular project. A general discussion of data
be tolerated at the specified storm frequency and
collection procedures is presented in Section
any other pertinent hydraulic criteria which is a
311.02.03.
design control for the project. Applicability of
existing Master Drainage Plans will be discussed.
A key element to proper planning of
retention/detention facilities is the selection of
The purpose of the drainage study is to identify
potential sites that will provide control of both
potential drainage problems for the proposed
flooding and stormwater quality. Other important
improvement, to recommend solutions, and to
considerations include:
establish initial pipe and channel sizings and
alignments consistent with the improvement
Runoff quality requirements
concept. The major drainage features shall be
Stormwater management master plan

Part 1 300-20
ROADWAY DESIGN MANUAL Roads and Bridges

displayed on the roadway geometric plans in both The Geotechnical Report will assemble the results
plan and profile. of the subsurface exploration program, analyze,
and make geotechnical engineering
Basic hydrologic conditions should be fully recommendations using the field boring and lab
quantified and discussed. Analysis of test data. This will be presented in an engineering
preconstruction hydrologic conditions should be report, prepared by the engineer for the project
performed in order to evaluate hydraulics and included in the Appendix. The results will be
(capacity, velocity, flood over-topping elevations summarized in the DCR.
etc.) of any existing structures and the impacts of
alternatives considered. The Report is to contain the following
information:
The engineer shall research and evaluate potential
Summary of previous geotechnical
future development (20 year planning horizon)
investigations
within the watershed which may have an impact
description of the program undertaken to
on future drainage flows and ultimately the
identify geotechnical and subsurface elements
performance of existing or proposed hydraulic
which affect project design
structures.
results of surface visual observations
The engineer shall carefully document and groundwater data
photograph all existing drainage problems, a summary of the information obtained from
carefully evaluate recommended solutions and and the location diagram of the soil borings
assure existing conditions are not impacted by the general description of the subsurface
roadway improvements. geologic strata obtained from the soil borings,
including any areas of unacceptable soil
The engineer shall document drainage problems, conditions
design approaches, solutions, and initial hydraulic particle size analysis and potential for scour
structures requirements in a separate Initial results of any material testing
Drainage Study which will be included in the analysis and recommendations for
Appendix. A summary will be presented in the embankment construction including
DCR. settlement and surcharging
an analysis and preliminary recommendations
312 SUBSURFACE for pavement structural section and
INVESTIGATIONS foundations.

Once the project location, horizontal and vertical 313 BRIDGE TYPE SELECTION
alignment and structure requirements have been
generally defined, the engineer will formulate Selection of the most suitable type of structure
subsurface exploration and testing program. The involves investigating alternate superstructure and
objective of the exploration program, is to foundation types including variation of span
provide, specific subsurface information along length, structure depth and number of girders to
successive design sections or reaches of the determine the best bridge type and arrangement
project. The data will allow some basic for a particular site. This is an iterative phase
judgments to be made, i.e., the most suitable where assumptions must be made and later
type(s) of foundations for structures and verified or modified during the process. Detailed
recommended pavement designs to be developed design should not be performed unless it is
during the design phase. necessary to confirm the adequacy of a concept.

In the case of either the structure borings or When performing the concept studies the
roadway borings, the geotechnical program will following shall be considered as a minimum:
serve to reveal the type, severity and extent of
Cost
geotechnical design problems.
Constructability
Maintenance
Part 1 300-21
ROADWAY DESIGN MANUAL Roads and Bridges

Aesthetics The existing waterway opening, vertical and


horizontal clearances.
Sketches should be made of the various The need for adding approach slabs.
alternatives investigated and included in the
The adequacy of existing bridge rail.
report.
When the above items have been investigated,
Both the vertical and horizontal clearances should
preliminary design can proceed by studying
be checked to ensure that adequate clearances are
alternatives. Possible alternatives include:
provided. Inadequate vertical clearance will
widening to one side, widening symmetrically on
necessitate a change in either profile grade or
both sides or replacing the bridge with a new
superstructure depth while inadequate horizontal
structure. Approximate costs based on
clearance may necessitate a change in span
preliminary quantities and unit costs associated
length.
with each solution will be required.
The geotechnical aspects of the site should be
considered since the foundation type and 313.03 BRIDGE SELECTION REPORT
associated cost may influence the type of bridge
selected. An initial (stage one) subsurface The preparation of the Bridge Selection Report is
exploration and testing program will be the final activity in the preliminary design phase.
performed in parallel as described in Part 1, This activity involves incorporating the contents
Section 312, Subsurface Investigations, and will of the Initial Drainage Study, and the
be used to determine foundation type and costs. Geotechnical Report to produce a final Bridge
Selection Report and develop the preliminary
Traffic requirements must be investigated plans for the selected alternative. The preliminary
including any detours or phasing requirements. plans consist of the General Plan and General
These requirements will be addressed in the Notes and Quantities Sheets. The preliminary
discussion detailed in Part 1, Section 320, plans are not considered complete until the
Construction Staging. drainage report and geotechnical foundation
recommendation is received and incorporated in
313.01 BRIDGES OVER WATERWAYS the plans.

For waterway crossings, coordination with the After fully considering the above factors to
project drainage requirements will be necessary. determine the proper structure type, the engineer
The designer should obtain the Initial Drainage will discuss the architectural features with the
Report and thoroughly review the contents before appropriate Municipality Departments. For large
starting the analysis of alternatives. For or controversial projects, approval by the
navigable crossings, the channel width, vertical Executive Council or higher authority will be
clearance, pier protection and navigational aids required. These may be individual or joint
should be investigated and discussed. discussions as dictated by the size, location,
complexity, and sociological, economical,
313.02 WIDENINGS/REHABILITATION ecological and environmental demands of the
project.
On projects involving widenings, in addition to
the requirements for new bridges, the following Through these discussions a structure with
items should be investigated: architectural features that are compatible with
structural, safety and site requirements can be
The existing structure should be checked for developed.
structural adequacy.
The condition of the existing deck joints. The completed Bridge Selection Report shall
The condition of the existing bearings. include a general plan of the bridge. This reduced
The condition of existing diaphragms on steel plan reflects the bridge geometrics, architectural
girder bridges. theme, the bridge substructure and the type of
The existing foundations. foundations. A complete discussion of the cost

Part 1 300-22
ROADWAY DESIGN MANUAL Roads and Bridges

and feasibility of alternative designs must be Location


included. This is especially important for unusual Status
and major structures. The Bridge Selection Remarks
Report will be included as an Appendix to the
DCR. The DCR will summarize the impacts for each
major utility (water, sewer, telephone, irrigation,
The results of bridge type selection process will electrical). The responsibility for design and
be summarized in the DCR. The factors that led construction of the facilities will be addressed.
to the selection of the preferred alternative will be Schematic plans showing the major existing and
thoroughly discussed. The proposed structures proposed utilities should be prepared and included
should be described and address: in the drawings section. Recommendations will
be given for general utility relocation schemes and
Foundation Type for resolution of specific utility conflicts.
Substructure Associated utility costs will be included in the
Superstructure preliminary cost estimate.
Architectural Features
Vertical and Horizontal Clearance For larger projects a separate Utility Report
Other Key Factors should be prepared and included as an Appendix
to the DCR.
The General Plan shall be included in the
Drawings (A3 size) that will accompany the 315 SOCIOECONOMIC ANALYSIS
DCR.
An analysis and discussion of the socioeconomic-
314 UTILITY IMPACT ANALYSIS data per the requirements described in Part 1,
Section 202, Environmental Factors Influencing
Utility impacts are a key project issue, especially Design, shall be included in the DCR. Each of
within existing transportation corridors. Data the topics covered in Part 1, Section 202,
collection and coordination with the various Environmental Factors Influencing Design shall
agencies/departments is discussed in Part 1, be included or, if not relevant, it should be so
Section 200, Design Concept Development. The stated including the reason why it is not relevant.
second phase of work includes analysis of the
existing and proposed utilities with respect to For any of the topics which are not relevant, prior
each alternative in order to permit estimation of approval from the Municipality is required to
costs and evaluation within the alternatives exclude the issue from the DCR. The required
matrix. information as to the reasons why the topics are
not relevant shall be summarized in a concise
Utility corridors including proposed Service Technical Memorandum accompanied by
Reservations should be identified and indicated on supporting documentation as necessary. The
the typical sections and roadway plans included in Municipality shall make a determination as to the
the DCR. For urban projects, the location of relevance of the topic based on this information.
service reservations will affect the roadway The Technical Memorandum and supporting
geometrics including parking areas, green areas documentation is to be included as a separate
and the proposed pavement surfacing. appendix in the DCR.

The DCR will include a through discussion of the 316 AGRICULTURE IMPACT
utility impacts and a tabulation of the existing
utility inventory as follows: Agricultural resources are important to mans
survival and therefore must be preserved to the
Item Number greatest extent possible. The Consultant shall
Owner identify the potential impact that the proposed
Description project alternatives may have on these resources
Station within the study area. Primarily, this involves
Part 1 300-23
ROADWAY DESIGN MANUAL Roads and Bridges

determining whether or not the project will 318 SIGNING AND PAVEMENT
directly impact (i.e. irreversibly commit ) land MARKINGS
that is presently used for agricultural purposes.
In the description of impact, the Consultant shall Signing Concept plans will be developed to show
identify whether the land is actively farmed or the major guide signs required for the proposed
fallow as well as the types if crops that would be facility in accordance with the MUTCD and
affected. Impacts will be quantified in hectares. criteria included in Part 2, Section 900, Traffic
Indirect impacts will also be identified and Engineering. It may be necessary to include
described. These may include, but are not limited signing outside of the project limits. New signs or
to, the potential description of the existing modifications required to existing signs shall be
irrigation system or pollution of nearby clearly identified. The signing requirements shall
agricultural lands from untreated stormwater be displayed on a reduced scale version of the
runoff. Impacts associated with each project project geometrics sufficient to show the required
alternative will be compared and the alternative detail. Proposed guide signs should be illustrated
with least agricultural impact shall be identified if graphically with leaders pointing to the sign
such an alternative exists. location. Signing requirements associated with
the construction staging/detour scheme should
317 PUBLIC FEEDBACK also be discussed.

Public involvement is an important aspect in the The signing and lighting concept plans will be
overall success of a project. At the onset of the included in the drawings section of the DCR.
project, the consultant shall develop a Public
Involvement Plan that will establish the approach 319 LIGHTING CONCEPTS
to be used to coordinate project planning and
details with the public. In addition to keeping the This section should begin with a discussion of the
public informed of the project, the plan will also design criteria that governs the location of
provide the public with the opportunity to lighting, the type of lighting relevant to the
comment at various stages of project roadway classification or route and the method of
development. By soliciting and actively illumination analysis. Applicability or
considering public input, the Consultant is more conformance to existing Master Lighting Plans
likely to produce a design that is economically must be considered. Alternative types of lighting
feasible and acceptable to the public. such as high mast at major interchanges should
also be addressed. The typical spacing between
This section of the DCR should briefly describe light sources, and the compatibility with adjacent
the elements of the Public Information Plan, or intersecting lighting system will be shown and
including the location and scheduling of public illustrated on schematic plans.
information meetings, workshops, consensus
building sessions or any other forums aimed at 320 CONSTRUCTION STAGING
soliciting public input. A summary of the
primary issues raised by the public should be
Maintenance of traffic during construction can
presented along with a discussion of how these
have a significant affect on the surrounding traffic
issues have been addressed during the
system, in terms of public convenience, design,
development of the project, and whether or not
cost and the duration of construction. The DCR
consensus has been reached. A file should be
shall include a discussion as to how construction
maintained as backup for each public meeting
of the project will be staged including:
that contains a list of participants and the issues
raised.

Part 1 300-24
ROADWAY DESIGN MANUAL Roads and Bridges

Number of Stages Initial Drainage Study


Erection of Falsework Geotechnical Report
Anticipated Detours Bridge Selection Report
Duration of each Stage Utilities Report
Traffic Analysis Report
The final design plans will generally be prepared
in conformance with staging described in the 324 DRAWINGS
DCR.
The drawings prepared to illustrate and define the
321 COST ESTIMATE design concept should be presented in A3 format
as Volume II of the written report which is bound
The DCR preliminary cost estimate must be as separately in A4 format. The drawings should
realistic and accurate as possible. The degree of include the following:
effort and detail for each project is expected to
vary depending upon the complexity and Typical Sections
sensitivity of the project-related issues. Alternatives
Bridge General Plans
The preliminary cost estimate should be prepared Roadway Plan/Profile
using the Preliminary Project Cost Estimate Signing and Lighting Concept Plans
form (Figure 300.02) to summarize the individual Architectural Renderings
bills. This is intended to standardize the format
Construction Staging Schematics
and type of items that need to be considered in the
Other project specific plans as required
project consistent with the General Specifications.
Similar forms must be developed for each bill
section to back-up the summary, including the
estimated quantities and unit prices. It is
important that all known items of work be
identified and estimated. In some instances, not all
of the items can be identified at this stage and an
appropriate contingency factor should be applied
to reflect possible increases such as modification
of the project limits or adding decorative features.

322 CONCLUSIONS/
RECOMMENDATIONS

This section will include conclusions,


recommendations, and their associated costs. The
name and title of the Project Engineer responsible
for the preparation of the DCR as well as the Abu
Dhabi Municipalitys Engineer who served as the
Municipality Representative shall also be
indicated.

323 APPENDIX

This section will be used for appending Technical


Memorandums and the complete detailed studies
or reports including:

Fact Sheet-Design Exceptions


Parking Study
Part 1 300-25
ROADWAY DESIGN MANUAL Roads and Bridges

MUNICIPALITY OF ABU DHABI


PROJECT NAME AND ROUTE NO.___________________
PROJECT NUMBER_________________

PRELIMINARY PROJECT COST ESTIMATE


SUMMARY OF BILLS OF QUANTITIES

BILL
BILL DESCRIPTION AMOUNT IN FIGURES
NO.
DH Fs
I GENERAL
II EARTHWORKS
III SUBBASE AND BASE COURSES
IV ASPHALT WORKS
V CONCRETE WORKS
VI SURFACE DRAINAGE SYSTEM
VII WATER WORKS
VIII PRESTRESSED CONCRETE WORKS
IX TRAFFIC MARKINGS AND SIGNS
X SITE LABORATORY
XI CONCRETE PILE FOUNDATIONS
XII METAL WORKS
XIII POST-TENSIONED CONCRETE WORKS
XIV EXPANSION AND FIXED JOINTS
XV IRRIGATION WORKS
XVI LIGHTING AND ELECTRICAL DISTRIBUTION WORKS
XVII TRAFFIC CONTROL SYSTEM
XVIII DAILY WORKS SCHEDULE
XIX TELEPHONE WORKS
XX SEWERAGE WORKS
XXI STREET FURNITURE
XXII PARKING STRUCTURE
XXV LANDSCAPING

TOTAL ESTIMATED COST

Figure 300.02
Cost Estimate Worksheet

Part 1 300-26
ROADWAY DESIGN MANUAL Roads and Bridges

PART 2 rails, bridge columns, retaining walls, sound


walls, cut slopes, and median barriers.
ROADWAY DESIGN
The cost to correct such restrictions may not be
justified. Technically, this will result in a
SECTION 100 reduction in the effective design speed at the
GENERAL DESIGN CRITERIA location in question. Such technical reductions
should be discussed and carefully considered
101 DESIGN SPEED before accepted.

Design speed establishes specific minimum Design speed may be lowered, especially in
roadway design elements. These design elements densely developed urban areas. The design speed
include vertical and horizontal alignment, and for special projects will be established by the
sight distance. Design speed relates indirectly to Road Section. Maximum design speeds, as related
other elements such as pavement and shoulder to roadway classifications, are shown in Table
width, and horizontal clearance. 100.01.

Design speed is influenced by terrain, economic Table 100.01


considerations, environmental factors, type and Design Speed
volume of traffic, roadway functional Roadway Terrain Desirable Min.
classification, and adjacent land use (rural or Classification Type (kph) (kph)
RURAL
urban).
Freeway
Drivers expect consistent design speeds for Flat 140 120
Rolling 120 100
adjacent roadways or roadways with similar
Mountainous 100 80
characteristics. A driver in a mountainous area Expressway
would expect to travel more slowly than a driver Flat 140 120
crossing the open desert. Further, the driver Rolling 120 100
crossing the open desert expects the travel speed Mountainous 100 80
to be similar for a divided road or a two-lane Major Collector
roadway. Normally, the design speed difference Flat 100 80
between adjacent segments should not exceed 10 Mountainous 80 60
kph. Minor Collector
Flat 90 80
A roadway carrying a large traffic volume may Rolling 80 60
justify a higher design speed than a less important Mountainous 60 40
facility in similar topography, particularly where Local Access
Flat 90 80
the savings in vehicle operation and other costs
Rolling 80 60
are sufficient to offset the increased cost of right Mountainous 60 40
of way and construction.. However, a lower URBAN
design speed should not be assumed for a Freeway 120 100
secondary road where the topography is such that Expressway 120 100
drivers are likely to travel at high speeds. Arterial (Main Rd)
Outlying 100 80
Subject to the above considerations, as high a Low Interruption 90 60
design speed as practical should be used. The High Interruption 60 40
design speed for any section of roadway should be Frontage Road 60 50
a constant value. However, during design, Sector Road 50 40
situations may arise in which engineering, DIRECTIONAL RAMPS 80 60
economic, environmental, or other considerations The maximum design speed varies by area on Abu
make it impractical to provide the minimum Dhabi Island therefore, refer to Figure 100.01 for the
posted speeds on the Island. Posted speeds are
elements established by the design speed.
considered to be approximately 85% of design speed.
Examples include partial or brief horizontal sight
distance restrictions, like those imposed by bridge
Part 2 100-1
ROADWAY DESIGN MANUAL Roads and Bridges

Figure 100.01
Posted Speeds On Abu Dhabi Island

Part 2 100-2
ROADWAY DESIGN MANUAL Roads and Bridges

102 DESIGN VEHICLES Within a project, one design designation should


be used except when:
For primary roadway projects, the design vehicle
will be a WB-12 intermediate semi trailer (a) The design hourly traffic warrants a
combination. For secondary and local roads, the change in the number of lanes, or
design vehicle will be a single unit bus. The (b) A decided change in topography dictates
design vehicles are as defined in a A Policy on a change in design speed.
Geometric Design of Highways and Streets,
AASHTO, 1994. Refer to Section 405 for The design designation should appear on the
additional information on design vehicles. typical cross section for all new roadway
construction projects.
103 DESIGN TRAFFIC
104 ROADWAY CAPACITY
103.01 DESIGN PERIOD
104.01 DESIGN CAPACITIES
Geometric design of new facilities should be
based on estimated traffic 20 years after Design capacity is the maximum volume of traffic
completion of construction unless otherwise for which a projected roadway can provide a
directed by the Road Section. selected level of service. Design capacity varies
with a number of factors, including:
Safety, resurfacing, restoration, rehabilitation,
and operational improvement projects should be (a) Level of service selected.
designed using current traffic volumes with (b) Width and number of lanes.
consideration for future growth. (c) Weaving sections.
(d) Presence or absence of, and width of,
103.02 RELATION TO DESIGN shoulders.
(e) Grades.
The design designation is a simple, concise (f) Horizontal alignment.
expression of the basic factors controlling the (g) Operating speed.
design of a given roadway. Following is an (h) Lateral clearance.
example of this expression: (i) Side friction generated by parking, drive
ways, intersections, and interchanges.
ADT (2000) = 9800 D = 60% Volumes of trucks, buses, recreational
ADT (2020) = 20,000 T = 12% vehicles, bicycles and pedestrians.
DHV = 3000 V = 110 kph, (j) Percentage of trucks, buses, and
recreational vehicles.
where: (k) Spacing and timing of traffic signals.
ADT (2000) = The average daily traffic, in
number of vehicles, for the construction Design capacity is based on the factors above,
year. design year traffic and operation at a specified
ADT (2020) = The average daily traffic for level of service (LOS).
the future year used as a target in design.
DHV = The two-way design hourly volume, Broadly defined, in terms of traffic flow, LOS A
vehicles. is associated with free flow traffic; LOS B
D = The percentage of the DHV in the indicates reasonable free flow; LOS C is stable
direction of heavier flow. operation; LOS D is lower range of stable flow;
T = The character of the traffic. This is LOS E is unstable flow; and LOS F indicates
expressed by the truck increment (T) as forced flow.
a percent of the DHV (excluding
recreational vehicles). Design levels of service for various conditions are
V = Design speed in kph. shown in Table 100.02. The highest feasible LOS
should be selected and used for design, except

Part 2 100-3
ROADWAY DESIGN MANUAL Roads and Bridges

where unreasonable costs or environmental For an approximation of the number of lanes


constraints would dictate a lower LOS. required on a multi-lane freeway or expressway,
use the following design year peak hour traffic
Level terrain is defined as a roadway on which volumes at the specified level of service:
trucks can maintain speeds that approach or are
equal to those of passenger cars. Level of Traffic Volume
Service (Average Vehicles)
Rolling terrain is defined as a roadway on which Per Lane Per Hour
trucks substantially reduce their speed below Urban C-E 1400-2000
passenger cars on some sections. Rural C-D 1000-1200

Mountainous terrain is defined as a roadway The following sections deal with the general
where trucks operate at crawls speeds for long capacity calculations for various roadways. Since
distances or frequent intervals. these calculation methods are lengthy and beyond
the scope of this document, the reader is referred
Table 100.02 to the Highway Capacity Manual (HCM), 1994.
Relation of Conditions to Design Levels of
Service 104.01.01 Multi-lane Rural Roadway
Conditions Design Levels
of Service The general equation for service volume of all
RURAL multi-lane roadways is given by:
Freeway Flat B SV = 2000 N (v/c) T W
Rolling B where:
Mountainous C SV = Service volume (one direction) for a
Expressway Flat B given level of service
Rolling B N = Number of lanes in each direction
Mountainous C v/c = Service volume to capacity ratio
Major Collector T = Adjustment factor for trucks on grades
Flat B W = Adjustment for width and lateral
Rolling B clearance
Mountainous C
Minor Collector (See HCM Section 100.04.02)
Flat C
Rolling C 104.01.02 Two Lane Roadways
Mountainous D
Local Access Flat D Service volumes and capacities for two lane
Rolling D roadways are always both directions without
Mountainous D regard to the distribution of volume by direction.
URBAN
Freeway C The general equation is given by:
Expressway C SV = 2000 (v/c) T W
Arterial (Main Rd) C-D where:
Frontage Road D SV = Service volume in vehicles per hour
Sector Road D (total both directions)
DIRECTIONAL RAMPS B-C v/c = Service volume to capacity ratio
T = Adjustment factor for trucks on grades
W = Adjustment for width and lateral
As an alternative to level of service D,
clearance
consideration should be given to pairs of one-way
roads or alternative bypass routes to improve the
(See HCM Section 100.04.02)
LOS.

Part 2 100-4
ROADWAY DESIGN MANUAL Roads and Bridges

104.01.03 Expressways Table 100.03


Control of Access by Road Type
Expressways are analyzed using a series of
nomographs covering a range of average roadway Roadway Type Degree of Access Control
speeds. The charts are based on 3.65 m lanes, full Freeway Full Access Control
width shoulders, and adequate clearances. (See Expressway Full or Partial Access Control
HCM Section 100.04.02) Major Collector
Main Road Partial Access Control
104.01.04 Expressway Ramps and Weaving Minor Arterial Approach Road
Sections Sector Road and Driveway
Local Road Regulations
Capacities of urban expressways are influenced
by entrance and exit volumes, weave distance, All Roadways will have some degree of access
and the geometric layout. All of these factors control. The appropriate degree of access control
should be considered in the capacity analysis. by roadway type is given in Table 100.03. More
(See HCM Section 100.04.02) detailed guidelines for establishing the control of
access lines by roadway classification are
104.01.05 Intersection Capacity
presented in the following section.
Intersections capacity generally governs the
capacity of the associated roadway. Signal 105.02 ACCESS CONTROL DESIGN
timing, intersection spacing, turning movement all CRITERIA
play a critical role in determining the overall
capacity. (See HCM Section 100.04.02) 105.02.01 Primary Roadways

105 CONTROL OF ACCESS The number of access openings on expressways


with access control should be held to a minimum.
105.01 GENERAL Parcels which have access to another frontage or
sector road as well as expressway frontage are
Control of access is achieved by limiting the not allowed expressway access. In some
number and location of roadway access points so instances, parcels fronting only on the
that the through traffic capacity or safety of the expressway may be given access to another
facility will not be significantly impaired. There sector road by constructing suitable connections
are three degrees of access control: if such access can be reasonably provided.

Full Access Control - Gives preference to With the exception of extensive expressway
through traffic by providing access only through frontages, access openings are limited to one
selected frontage/sector roads and by prohibiting opening per parcel. Wherever possible, one
at-grade crossings or direct access from abutting opening should serve two or more parcels. In the
property. case of a large expressway frontage under one
ownership, the feasibility of limiting access to
Partial Access Control - Still gives preference to one opening may be prohibitive, or the property
through traffic but permits some at-grade may be divided by a natural physical barrier such
crossings and some private driveway as a wadi or ridge, making it necessary to
connections. provide an additional opening. However, in the
latter case, it may be preferable to connect the
Approach Road and Driveway Regulations - physically separated portions with a low-cost
Without access control, abutting properties are structure or road rather than permit two
permitted access to the roadway, but the number, openings.
location and geometrics are regulated.
Access rights shall be acquired along interchange
ramps to their junction with the nearest public
road, and shall extend to the end of the ramp taper

Part 2 100-5
ROADWAY DESIGN MANUAL Roads and Bridges

(or at least 50 m beyond the end of the curb provided. See Section 105.03, Use of
return or ramp radius). Frontage Roads, for further discussions.
(8) Access openings on divided roadways shall
In remote areas, infrequent access should be not be permitted within 100 m of a median
accommodated by providing locked gates. This opening unless the access opening is directly
will only be considered for areas that are remote, opposite the median opening.
infrequently used, and have no other access (9) Access approaches shall be limited to right
means. Direct access will not be provided if it turns only unless (1) the approach has no
creates an unsafe condition. Turning movements signalization potential and allowing left turns
will be limited to right turns only. Written would significantly reduce congestion and
approval must be granted by the Abu Dhabi safety problems at a nearby intersection; or
Road Section. (2) there are no intersections, existing or
planned, that allow a U-turn; and (3) left
turns can be safety designed without
105.02.02 Secondary Roadways, signalization.
ADT > 2500 (10)Access approaches with signalization
potential and that require left turn movements
In general, the number of access openings shall be must (1) meet the signalization requirements
held to a minimum for any facility. Additional as specified in Part 2, Section 902,
access may be necessary to satisfy a range of Signalization, and (2) shall not interfere with
design issues/access requirements. The following the location, planning, or operation of the
is a list of issues to consider when providing general road system and nearby property
access points. access.

(1) Emergency vehicles shall have a right to 105.02.03 Secondary Roadways,


direct roadway access. ADT < 2500
(2) Private direct roadway access shall be
permitted only when the property in question The primary function of these roadways is to
has no other reasonable access to the local provide reasonable and safe access to abutting
road system. property. Access needs generally take priority
(3) If feasible, parcels fronting only on the over through traffic as long as roadway safety is
roadway shall be given access to another not compromised. Control of access is not
public road by constructing suitable obtained, but the location, number, and
connections. geometrys of access points must meet the
(4) Roadway access openings are limited to one following criteria:
per parcel. Exceptions may be considered if
they do not affect roadway safety or (a) The number of access approaches to a parcel
operation and they are necessary for safe and shall be controlled by safety and design
efficient property use. considerations and shall be separated by at
(5) In certain cases, a natural physical barrier least the stopping sight distance.
such as a wadi or ridge may divide the parcel.
In this case additional access openings may (b) For safety reasons, frontage roads or parallel
be warranted. However, it may be preferable service roads are not permitted along two-
to connect the physically separated portions lane roadways because this results in the
of the parcel with a low cost structure or road appearance of a divided roadway.
rather than permit multiple access openings.
(6) Wherever possible, one access opening should (c) Left turns if safety and design standards are
serve two parcels. met.
(7) When the number of required access openings
on one side of a divided roadway exceeds (d) In rural areas, approach roads shall be
three in 400 m, a frontage/sector road shall be provided as necessary for local access or
emergency/rest stops. The maximum spacing

Part 2 100-6
ROADWAY DESIGN MANUAL Roads and Bridges

between approach roads shall be 5 km for (2) New Alignment. Sector roads generally
these purposes. are not provided on new expressway
alignments since the abutting property
(e) In urban areas with signalized intersections, owners never had legal right of access to
the minimum spacing between access points the new facility. They may be provided,
shall be that which is necessary for the safe however, on the basis of considerations
operation and proper design of intersections mentioned above.
as specified in Section 400.
(3) Existing Alignment. Where an expressway
105.03 USE OF FRONTAGE ROADS is developed parallel to an existing
roadway or local road, all or part of the
(1) General Policy existing roadway is often retained as a
frontage or sector road. Frontage roads
(a) Frontage roads are provided: must be constructed to serve landlocked
To control access to the urban remainders or the remainders must be
expressway and main road purchased outright if other means of
through lanes, thus increasing access cannot be provided. The decision
safety. whether to provide access or purchase
should be based on considerations of cost,
To provide access to sectors. right of way impacts, road system
Maintain continuity of the local continuity and similar factors discussed
road systems. above.
Provide for non-motorized
traffic that might otherwise 105.04 PROTECTION OF ACCESS
desire to use the expressway. RIGHTS

(b) Typically a frontage road is Access Control lines/limits shall be shown on the
justified if their construction costs project right-of-way plans. Where possible, the
are less than the costs of providing right-of-way line and control of access line
other direct access. Right of way should be coincident.
considerations are often the
determining factor. Thus, a For proper control of access, fencing or other
frontage road would be justified if approved barriers shall be installed on all
the investment in construction and controlled access roadways, located on the
extra right of way is less than control or access line where appropriate.
either the severance damages or
the costs of acquiring the affected 106 DESIGN STANDARD
property. Frontage roads may be EXCEPTIONS
required to connect parts of a
severed property or to serve a A design standard exception is a design feature
landlocked parcel resulting from which does not meet the design standards
right of way acquisition. presented in the Roadway Design Manual.
Occasionally these design exceptions are justified
(c) Direct access to the through lanes but it is important that each design exception be
is allowable on expressways. documented and approved in writing prior to plan
However, when the number of acceptance.
access openings on one side of the
expressway exceeds three in 500 The request for approval of design exceptions
m, a frontage road should be shall be in the form of a Design Exception
provided. Request. This request sheet shall be presented to
the Municipality for written approval. The
request sheet shall include the following topics:

Part 2 100-7
ROADWAY DESIGN MANUAL Roads and Bridges

Proposed Project Roadway Design Manual Part and


Existing Roadway Section number(s).
Proposed Design Exception
Additional Cost To Comply With B. Describe the proposed design exception
Standards or the existing design exception which is
Incremental Improvements proposed to be maintained. If proposed,
Supportive Data state whether the design exception is an
improvement over the existing condition.
A detailed description of the items required in the Describe proposed improvements that
Design Exception Request sheet is included on the would qualify as safety enhancements
following pages. over the existing condition, such as:
median barrier, guardrail upgrade,
DESIGN EXCEPTION REQUEST SHEET flattening slopes, correcting
superelevation, eliminating roadside
1. PROPOSED PROJECT obstructions, etc.

A. Project Description: Briefly describe the C. Provide a thorough brief justification for
project. Note the type of project and/or the design exception. Reasons for
major elements of work to be done, such granting design exceptions include a
as safety or operational improvement, combination of excessive cost, right of
roadway widening, rehabilitation, way impacts and/or environmental
reconstruction, etc. Provide the impacts. Supportive factors have
geographic project limits and length. included low accident frequency, local
opposition, and consistency with adjacent
B. Proposed Project Total Cost: Include a roadway segments.
estimate of the proposed project cost
segregated by major elements, including: 4. ADDITIONAL COST TO COMPLY
roadway, structures, right of way, utility WITH STANDARDS
relocation, environmental mitigation, etc.,
as needed. Provide a realistic estimate of the additional
cost required to meet the design standard for
2. EXISTING ROADWAY which the proposed exception is requested.

A. Existing Roadway Description: 5. INCREMENTAL IMPROVEMENTS


Describe the existing roadway features
relevant to the proposed design exception. Discuss other practical alternatives that are
This may include such things as the intermediate in scope and cost between the
widths of lanes, shoulders, median, clear proposed project (requiring this design
zones, roadbed, and structures; exception) and the full, standard solution.
horizontal and vertical alignment and Provide enough information on costs versus
clearances; design speed, sight distance, benefits, right of way and environmental
grades, cross slope, superelevation, etc. impacts, etc., to explain why none of the
incremental alternatives are recommended.
If relevant, provide a similar brief These alternatives should normally be
description of adjacent existing roadway investigated prior to requesting an exception.
segments, noting existing nonstandard
features. 6. SUPPORTIVE DATA

3. PROPOSED DESIGN EXCEPTION A. Traffic Data: Provide both ADTs and


DHV (design hourly volumes). Use
A. State the specific design standard(s) design year traffic.
which are not being met and refer to their

Part 2 100-8
ROADWAY DESIGN MANUAL Roads and Bridges

B. Accident Analysis: Safety is of primary For further information and guidelines on


importance when considering design bicycles, refer to the latest edition of AASHTO,
exception approval. If relevant, include Guide for Development of Bicycle Facilities.
an accident data analysis to identify
prevalent accident types and causes, plus 107.02 SPECIAL BICYCLE FACILITIES
an evaluation of the effect of the
requested design exception on accident At certain locations or in certain corridors, it is
types and frequencies. appropriate to supplement further the existing
highway system by providing specifically
C. Attachments: designated bikeways (for either exclusive or non-
exclusive bicycle use). Rural arterials often are
1. Provide a location or vicinity map the only direct connection between areas of
for the project. population and locations to which the public
2. Provide plan sheets, cross sections, wishes to travel, Schools, parks, and rural
profiles and/or special details to housing developments are usually located to be
clearly illustrate the proposed readily accessible by automobile. However,
design exception. pedestrians and bicycle riders may also wish to
travel to the same destination points. When such
3. Attach pertinent letters, a situation exists, the designer should consider the
resolutions, meeting minutes, effects on the safety and operation of the arterial.
studies, etc., which further develop A special effort should be made to provide the
or clarify the proposed design greatest degree of safety within the economic
exception. constraints that must always be considered.

107 BICYCLE FACILITIES 107.03 BICYCLE CHARACTERISTICS

107.01 GENERAL To provide for bicycle traffic, it is necessary to


become familiar with bicycle dimensions,
The bicycle has become an important element for operating characteristics, and requirements.
consideration in the highway design process. These factors determine acceptable turning radii,
Fortunately, most of the mileage needed for grades, and sight distance. In many instances
bicycle travel is comprised of the street and design features of separate bike facilities are
highway system. While many highway agencies controlled by the adjoining roadway, so that even
allow bicycles on partially access controlled then consideration of bicycles is an essential
facilities, most highway agencies do not allow element the design of the highway itself.
bicycles on fully access controlled facilities.
107.04 BICYCLES AT
Measures such as the following, which are INTERSECTIONS
generally of low capital intensity, can
considerably enhance a routes safety and When on-street bicycle lanes and/or off-street
capacity for bicycle traffic: bicycle paths enter an intersection, the design of
the intersection should be modified accordingly.
Paved shoulders. This may mean special sight distance
considerations, wider roadways to accommodate
Wide outside traffic lane (4.2 m minimum) if
on-street lanes, special lane markings to
no shoulder.
channelize and separate bicycles from right
Bicycle-safe drainage grates.
turning vehicles, provisions for left turn bicycle
Adjusting manhole covers to the grade.
movements, or special traffic signal designs (such
Maintaining a smooth, clean riding surface. as conveniently located push buttons at actuated
signals or even separate signal indication for
bicyclists).

Part 2 100-9
ROADWAY DESIGN MANUAL Roads and Bridges

SECTION 200
If providing passing sight distance is not
GEOMETRIC DESIGN
economically feasible, stopping sight distance is
STANDARDS the minimum sight distance provided on multilane
and 2-lane roads. Stopping sight distance is the
201 SIGHT DISTANCE minimum provided for interchanges, at-grade
intersections and private road connections.
201.01 GENERAL
Table 200.01 shows the standards for sight
Sight distance is the continuous length of roadway distance related to design speed.
ahead visible to the driver. There are three distinct
types - passing, stopping, and decision. Passing Table 200.01
sight distance is the minimum sight distance Sight Distance Standards
required by a driver to safely pass another
vehicle. Stopping sight distance is the distance Design Minimum Desired Minimum
required by a driver, traveling at a given speed, to Speed Stopping Stopping Passing
stop after seeing an object on the road. At certain Sight (1) Sight (1) Sight
locations decision sight distance is required to Distance Distance Distance
allow drivers extra time for making decisions. (kph) (m) (m) (m)

30 30 30 220
201.02 PASSING SIGHT DISTANCE
40 45 45 285
50 60 65 345
Passing sight distance is the minimum sight
60 75 85 410
distance required by a driver to safely pass
70 95 115 485
another vehicle. The sight distance available for
80 115 140 545
passing is the longest distance at which a driver
90 135 170 605
whose eyes are 1070 mm above the pavement can
100 160 205 670
see the top of a 1300 mm high object on the road.
110 180 250 730
Passing must be accomplished without reducing
120 205 290 795
the speed of an oncoming vehicle traveling at the
130 235 330 855
design speed. Table 200.01 lists sight distance
standards.
Minimum values shall be avoided in design,
Passing sight distance is only considered on 2- higher values are desirable.
lane roads and should be provided at frequent (1) Increase by 20% on downgrades >3% & >2
intervals. In general, minimum passing sight km. Values shown are for wet pavements.
distance should be provided for 60% of the route
length in level terrain, 40-60% in rolling terrain Chapter III of A Policy on Geometric Design of
and 20-60% in mountainous terrain. Economics Highways and Streets, AASHTO, 1994,
should be weighed against providing passing sight contains a thorough discussion of the derivation
distance or auxiliary passing lanes. of stopping sight distance.

201.03 STOPPING SIGHT DISTANCE 201.04 STOPPING SIGHT DISTANCE


AT GRADE CRESTS
Stopping sight distance is the distance required by
a driver, traveling at a given speed, to stop after Figure 200.02 shows the relationship between
sighting an object on the road. Stopping sight vertical curve length, design speed, and algebraic
distance is measured from the drivers eyes, 1070 difference in grades. Any one factor can be
mm above the road, to an object 150 mm high on determined when the other two are known.
the road.

Part 2 200-1
ROADWAY DESIGN MANUAL Roads and Bridges

Figure 200.01
Stopping Sight Distance on Crest Vertical Curves

Figure 200.02
Stopping Sight Distance on Sag Vertical Curves

Part 2 200-2
ROADWAY DESIGN MANUAL Roads and Bridges

201.05 STOPPING SIGHT DISTANCE


AT GRADE SAGS Table 200.02
Decision Sight Distance
Stopping sight distance for grade sags is
Design Decision Sight Distance
important at night when headlights need to
Speed for Avoidance Maneuver (m)
illuminate the road ahead. Figure 200.02,
kph A B C D E
provides the minimum sag vertical curve length
which provides headlight sight for a given design
speed. Lighting may be considered as an 50 75 160 145 160 200
economic option to lengthening the sag curve. 60 95 205 175 205 235
70 125 250 200 240 275
201.06 STOPPING SIGHT DISTANCE 80 155 300 230 275 315
ON HORIZONTAL CURVES 90 185 360 275 320 360
100 225 415 315 365 405
Figure 200.03 is used to determine the required 110 265 455 335 390 435
clear distance (at a given design speed) from the 120 305 505 375 415 470
inside lane centerline to a roadside obstruction.
The drivers eye is assumed 1070 mm above the A Stop on rural road.
inside lane centerline (inside with respect to B Stop on urban road.
curve) and the object is 150 mm high. With little C Speed/path/direction change on rural road.
or no vertical curvature, the sight line is assumed D Speed/path/direction change on suburban
to intercept the obstruction at the midpoint of the road.
sight line, 610 mm above the inside lane E Speed/path/direction change on urban road.
centerline. The clear distance (m) is measured
from the inside lane center to the obstruction. From AASHTO, 1994, A Policy on Geometric
Design of Highways and Streets
201.07 DECISION SIGHT DISTANCE
202 SUPERELEVATION
Decision sight distance is the distance required for
a driver to detect an unexpected or difficult to 202.01 GENERAL
perceive information source or hazard in a
roadway environment that may be visually As a vehicle travels a curved section of road it is
cluttered, select an appropriate speed and path, subjected to centrifugal force which tends to push
and initiate and complete the required maneuver it towards the outside of the curve. If the surface
safely and efficiently. Decision sight distance is is flat, the vehicle is held in its curved path by
used at major decision points such as lane drops, side friction between the tires and pavement.
changes in cross section, off-ramp noses to Roadways are superelevated to further counter
interchanges, branch connections, roadside rests, centrifugal force. Superelevation is the sloping of
vista points, and inspection stations. At these the roadway surface upward toward the outside of
locations, sight distance greater than stopping the curve. On a superelevated roadway,
sight distance is desirable to allow drivers time centrifugal force is resisted by the vehicle weight
for making decisions component parallel to the superelevated surface
and the tire side friction. However, it is
The decision sight distances in Table 200.02 impractical to balance centrifugal force by
provide appropriate decision sight distance superelevation alone, because for a given curve
rounded for design. Decision sight distance is radius a certain superelevation rate is exactly
based on a 1070 mm eye height and a 150 mm correct at only one speed. At all other speeds side
object height. thrust will either be toward or away from the
curve center. This thrust must be offset by side
friction.

Part 2 200-3
ROADWAY DESIGN MANUAL Roads and Bridges

Figure 200.03
Stopping Sight Distance on Horizontal Curves

If the vehicle is not skidding, all forces are in elements related to speed and horizontal
equilibrium and are governed by the following curvature.
equation:
Table 200.03
Centrifugal Factor = e + f = 0.0079V2 = V2 Maximum Superelevation Rates
R 127R
Roadway emax
Where:
Classification
e = Superelevation rate in m per m
Freeways 0.06
emax = Maximum superelevation rate for
Expressways 0.06
a given condition
Ramps 0.06
f = Side friction factor
Main Roads and Collectors 0.04
R = Curve radius in m
Sector Roads Normal Crown
V = Velocity in kph

This equation is used to design superelevated 202.03 CITY ROAD CONDITIONS


curves for comfortable operation. Standard
Lower superelevation rates may be necessary in
superelevation rates are designed to keep the
urban areas where restricted speed zones or
portion of centrifugal force countered by tire
intersections are controlling factors. In addition,
friction within allowable limits.
existing road grades, curbs, or drainage may
prove difficult to alter. Such conditions may
202.02 SUPERELEVATION
warrant, for example, a reduction in the
STANDARDS
superelevation rate, different rates for each half of
the roadbed, or both. In warping road areas for
Maximum superelevation rates for various
drainage, adverse superelevation should be
roadway classifications are shown on Table
avoided.
200.03. Table 200.04 shows values for design

Part 2 200-4
ROADWAY DESIGN MANUAL Roads and Bridges

Table 200.04
Values for Design Elements Related to Speed and Horizontal Curvature
From AASHTO, 1994, A Policy on Geometric Design of Highways and Streets
Part 2 200-5
ROADWAY DESIGN MANUAL Roads and Bridges

202.04 AXIS OF ROTATION An example of expressway superelevation


development is shown on Figure 200.04.
Aesthetics, grade distortion, superelevation
transitions, drainage, and driver perception should For roadways on the inside of the curve, the
be considered when selecting the axis of rotation. outside shoulder will begin rotating when the
inside roadway pavement has reached a
Undivided Roadways - The axis of rotation shall superelevation of -3.0 percent (normal shoulder
be at the roadway centerline. However, in special slope). When superelevation becomes greater than
cases changing the axis of rotation to the inside -3.0 percent, the pavement and shoulder will
travelled way edge can avoid drainage problems rotate in unison.
caused by superelevation, or, improve curve
perception for curves preceded by long relatively The location of a superelevation transition, with
level tangents. respect to the point of curvature, will be
determined using the inside roadway transition.
Expressway Connections and Ramps - The axis Approximately one-third of the transition length
of rotation may be about either edge of travelled will be placed on the curve. The remaining
way or centerline if multinale. Appearance and transition length will be on the tangent. The
drainage considerations shall be considered when transition location will be adjusted to begin/end at
selecting the axis of rotation. a 10 meter station.

Divided Roadways - The axis of rotation shall be For roadways on the outside of the curve, the
at the median edge of each travelled way. transition will begin/end at the adjust the curve
However, for bridges with decked medians the determined by the inside roadway transition. An
axis of rotation shall be at the centerline. additional transition length is required to rotate
the outside shoulder from -3.0 percent (normal
202.05 SUPERELEVATION shoulder slope) to -1.5 percent (normal pavement
TRANSITION slope). This shoulder transition length must be
added to the pavement transition length to get the
General - Superelevation transition should be total transition length.
designed in accordance with Figure 200.04. The
length of superelevation transition should be Restrictive Areas - In restrictive areas, where
based upon the combination of superelevation rate full superelevation cannot be achieved, the highest
and width of rotation plane. possible superelevation rate and transition length
shall be used. But, in no case shall the cross slope
Edge of travelled way and shoulder profiles rate of change exceed 4% per 20 m.
should be plotted and irregularities and drainage
problems should be eliminated. Superelevation Transitions on Bridges -
Superelevation transitions on bridges should be
Superelevation Transitions - Roadways avoided.
separated by barrier or median will be
superelevated at independent rates. The transition 202.06 SUPERELEVATION OF
length will be based on pavement width and COMPOUND CURVES
superelevation change. The profile of the outside
edge of through pavement cannot differ from the Compound curve superelevation shall be per
profile gradeline by more than the percentage Figure 200.05. Where feasible, the criteria in
shown on Table 200.04 and will be an unbroken Section 202.05 shall apply.
line throughout the transition. The minimum
transition length for a two lane roadway is shown
on Table 200.04. For multiple lane roadways the
minimum length shall increase proportionately.

Part 2 200-6
ROADWAY DESIGN MANUAL Roads and Bridges

Figure 200.04
Freeway/Expressway Superelevation Transitions

Part 2 200-7
ROADWAY DESIGN MANUAL Roads and Bridges

Figure 200.05
Superelevation Transitions for Compound Curves

Part 2 200-8
ROADWAY DESIGN MANUAL Roads and Bridges

203 HORIZONTAL ALIGNMENT If a glare screen or median barrier is used,


adjustments may be necessary to maintain the
203.01 GENERAL required sight distance on divided roadway
curves.
Horizontal alignment consists of a series of
circular curves and tangent sections. The Alignment Consistency - Sudden reductions in
horizontal alignment should provide safe alignment standards shall be avoided.
continuous uniform operation for substantial Introduction of curves with lower design speeds
roadway lengths. The major factors influencing shall be avoided at the end of long tangents, steep
horizontal alignment design are safety, profile, downgrades, or at other locations where high
type of facility, design speed, cost, geotechnical approach speeds may be anticipated. In no case
constraints, topography, aesthetics, and shall the design speed between successive curves
functionality. All of these factors must be change more than 15 kph.
balanced to produce the safest, most economical
alignment, which is in harmony with the natural On roadways in mountainous or rolling terrain
contour of the land, and at the same time adequate where horizontal and vertical curves are
for the design classification of the roadway. superimposed at grade summit or sag, the design
speed of the horizontal curve should be at least
In design, safety is always a major factor. The equal to that of the crest or sag, and not more
horizontal alignment shall provide at least the than 15 kph less than the measured or estimated
minimum stopping sight distance for the chosen running (85th percentile) speed of vehicles on the
design speed at all points along the roadway. The approach roadway.
following standards apply to horizontal curvature
on both 2-lane and multilane roadways except as Curve Length and Central Angle - For central
noted. angles less than 10 degrees, the minimum curve
length should be 240 m to avoid a kinked
203.02 STANDARDS FOR
appearance. For central angles smaller than 30
HORIZONTAL CURVATURE
minutes, no curve is required. Above a 6000 m
Minimum Curvature - Table 200.05 gives the radius, parabolic curves may be used. In no case
minimum curve radius based on design speed. shall sight distance or other safety considerations
be sacrificed to meet the above requirements.
Table 200.05
Standards For Curve Radius Lane curve lengths in excess of 800m on 2-lane
roadways should be avoided in consideration of
Roadway Minimum the safety aspects associated with driver
Classification Curve Radius (m) attentiveness and oncoming headlight glare.
RURAL
Freeway 2000 On 2-lane roads a curve should not exceed a
Expressway 2000 length of 800 m.
Collector 600
Local Access 100 Compound Curves - Compound curves shall be
URBAN
avoided, except where use of a simple curve
Freeway 600
results in excessive cost.
Expressway 600
Arterial (Main Rd) 600
If compound curves are used, the shorter radius
Frontage Road 600
should be at least two-thirds the longer radius
Sector Road 100
when the shorter radius is 300 m or less. The total
LOOP RAMPS 45
arc length of a compound curve should not be less
This table assumes unlimited sight distance. than 150 m.
Minimum radius should also be checked against
Figure 200.03. Every effort should be made to
exceed the minimum.

Part 2 200-9
ROADWAY DESIGN MANUAL Roads and Bridges

Reverse Curves - When horizontal curves 204.02 VERTICAL ALIGNMENT


reverse direction the connecting tangents shall be POSITION WITH RESPECT TO
long enough to accommodate the standard CROSS SECTION
superelevation runoffs given on Figure 200.04. In
no case shall the cross slope rate of change The grade line should generally coincide with the
exceed 4% per 20 m. axis of rotation for superelevation. Its relation to
the cross section should be as follows:
Broken Back Curves - A broken back curve
consists of two curves in the same direction joined Undivided Roadways - The grade line should
by a short tangent section. Broken back curves coincide with the roadway centerline.
are unsightly, undesirable and should be avoided.
Expressway Connections and Ramps - The
Alignment at Bridges - If possible, a bridge grade line may be positioned at either edge of
should be located entirely on a tangent or curve travelled way or centerline if multilane.
because superelevation transitions on bridges
almost always result in unsightly bridge and Divided Roadways - The grade line may be
bridge railing appearance. However, alignment positioned at either the median centerline or at the
and safety considerations shall govern. ultimate median edge of travelled way. The
former case is appropriate for paved medians 9 m
Intersections and Interchanges - If possible, wide or less. The latter case is appropriate when:
intersections should be on tangent sections or flat
horizontal curves with very little superelevation. a) The median edges of travelled way of the
two roadways are at equal elevation.
Interchanges, such as a typical diamond b) The roadways are at different elevations.
interchange, include two closely spaced at-grade c) The median width is ununiform.
intersections that function inter-dependently. A
tangent alignment should be maintained between 204.03 STANDARDS FOR GRADES
intersections for signal visibility and lane
assignment determinations required by the Maximum Grades - Table 200.06 lists the
motorist. maximum grades for design for rural roadways
based on design speed and urban roadways based
204 VERTICAL ALIGNMENT on roadway type.

204.01 GENERAL Minimum Grades - The desirable minimum


grades should be not less than 0.3 percent for
Vertical alignment consists of a series of grades curbed pavement sections and 0.2 percent in very
connected by parabolic vertical curves. It is used flat terrain. Minimum grades can be maintained
to establish elevations for all roadway features. It in very flat terrain by use of a rolling profile.
is controlled mainly by topography, roadway
class, horizontal alignment, safety, sight distance, In developed urban areas with extremely flat
costs, cultural development, drainage, and terrain, flatter minimum grades may be warranted
aesthetics. Steep grades affect truck speeds and in consideration of adjacent building elevations
overall capacity. and offsite drainage problems associated with
rolling profiles. The use of minimum grades
All portions of the vertical alignment shall meet flatter than those specified above will require case
minimum sight distance requirements. by case approval by the Road Section.

Part 2 200-10
ROADWAY DESIGN MANUAL Roads and Bridges

Table 200.06 grade length must be considered because it has a


Grade Standards major effect on operational speed, capacity, level
of service, and contributes to heavy truck delays.
Rural
Figure 200.09 shows the speed reduction in kph
Design Level Rolling Mountainous
for an assumed typical heavy truck of 180 kg/kW
Speed
as a function of grade length and upgrade percent.
(kph) % % %
Generally, a truck speed reduction of up to 15
kph does not significantly impact roadway
60 5 6 8
capacity.
70 5 6 7
80 4 5 7
Consideration should be given to adding lanes
90 4 5 6
where the truck speed reduction is greater than 15
100 3 4 6
kph and there is a significant reduction in level-
110 3 4 5
of-service when moving from the approach
120 3 4 5
segment to the grade. On two lane roadways, a
130 3 4 4
climbing lane should be considered when, in
Urban Desirable Absolute
addition to the above criteria, the upgrade traffic
Roadway Maximum Maximum
flow is in excess of 200 vehicles per hour and the
Type % %
truck factor is in excess of ten percent. Decision
Freeway 3 4 sight distance should be provided at climbing lane
Expressway 3 4 drops on expressways.
Ramps 4 6
Arterial (Main Rd) 2 3 204.06 STRUCTURE GRADE LINE
Frontage Road 2 3 Structure Depth - The depth to span ratio for a
Sector Roads 2 3 structure is dependent on many factors. Use a
structure depth to span ratio of 0.04 to 0.045 for
204.04 VERTICAL CURVES preliminary design purposes.
Parabolic vertical curves are used in roadway Falsework Allowance - To establish the grade of
design per Figure 200.06. a structure constructed with a falsework opening,
Figures 200.07 and 200.08 will be used to obtain allowance must be made for the falsework depth.
vertical curves lengths. For design speeds greater The minimum vertical falsework clearance over
than 65 kph, the minimum vertical curve length primary and secondary roadways shall be 4.8 m.
should be 120 m. For 50 kph design speed, it The minimum vertical falsework clearance over
should be 60 m. local roadways shall be 4.5 m.

Flat vertical curves may develop poor drainage in Bridge Deck Drainage - Vertical alignment
the level section. Adjusting the edge grade or design requires special consideration of structure
shortening the vertical curve may be required. drainage. Zero gradients and sag vertical curves
should be avoided on bridges. Parapets collect
Design of these long vertical curves should be large amounts of debris and smaller bridge deck
avoided because many drivers will not pass on drains or scuppers have a higher potential for
curves over 1 km long, despite adequate sight clogging. The minimum desirable longitudinal
distance. It may be more economical to construct slope for bridge deck drainage is 0.2 percent.
passing lanes than to obtain passing sight distance Where vertical curves on bridges cannot be
by using a long vertical curve. avoided, the elevations should be checked to
provide a minimum effective longitudinal grade of
204.05 LONG SUSTAINED GRADES 0.5 percent, and not extend more than 15 m either
side of the sag or crest point.
The maximum grade guideline is not sufficient to
insure uniform roadway operation. The uphill

Part 2 200-11
ROADWAY DESIGN MANUAL Roads and Bridges

Figure 200.06
Symmetric Parabolic Vertical Curves

Part 2 200-12
ROADWAY DESIGN MANUAL Roads and Bridges

Figure 200.07
Design Controls for Crest Vertical Curves, for Stopping Sight Distance- Upper Range.
From AASHTO, 1994, A Policy on Geometric Design of Highways and Streets
.

Part 2 200-13
ROADWAY DESIGN MANUAL Roads and Bridges

Figure 200.08
Design Controls for Sag Vertical Curves - Upper Range.
From AASHTO, 1994, A Policy on Geometric Design of Highways and Streets.

Part 2 200-14
ROADWAY DESIGN MANUAL Roads and Bridges

Figure 200.09
Critical Lengths of Grade for Design, Assumed Typical Heavy Truck of 180 kg/kW,
Entering Speed 90 kph.
From AASHTO, 1994, A Policy on Geometric Design of Highways and Streets.

Part 2 200-15
ROADWAY DESIGN MANUAL Roads and Bridges

204.07 SEPARATE PROFILE GRADE high approach speeds may result in erratic
LINES operation, especially at night.
For moderate changes in horizontal alignment
Separate grade lines should be considered for all at grade summits, the horizontal curve should
divided roadways. The use of separate grade lines overlap the vertical curve.
provides the opportunity to optimize the vertical Avoid successive changes in profile which are
alignment, drainage features, and provide a safer not associated with horizontal curves. The
more economical design. succession of humps is unattractive.
Horizontal and vertical curvature at
They are not normally considered appropriate intersections should be as flat as physical
where medians are less than 18 m wide. conditions permit.
Exceptions to this may be minor differences Avoid excessive curvature to obtain flat
between opposing grade lines in special grades and tangent alignment or flat curves at
situations. the expense of steep or long grades. It is
better to balance horizontal and vertical
In addition, for either interim or ultimate alignments.
expressways, any appreciable grade differential In general, alignments should be designed to
between roadbeds should be avoided in the take full advantage of scenic opportunities.
vicinity of at-grade intersections. For traffic
entering from the crossroad, confusion and
206 PAVEMENT TRANSITIONS
wrong-way movements could result if the
pavement of the far roadway is obscured because
206.01 GENERAL
of excessive differential.

205 COORDINATION OF A pavement transition occurs when changing


HORIZONTAL AND VERTICAL from one roadway cross section to another. If
feasible, the transition should occur on a tangent
ALIGNMENTS
section. And be entirely visible to the driver.
The coordination, of horizontal and vertical Avoid locations with sight distance restrictions.
alignments is based on experience and engineering Transitions should not occur within at-grade
judgment. Successful coordination is essential for intersections. Decision sight distance shall be
a safe well balanced design. The following are provided at all lane drops.
guidelines to be used, where possible.
206.02 TRANSITIONS FOR
Vertical curves should be superimposed on MULTILANE ROADWAYS
horizontal curves. This reduces the number of
sight restrictions, makes profile changes less Four Lanes to Two Lanes - A typical transition
apparent, and results in a pleasing between 4 lanes and 2 lanes is shown in Figure
appearance. However, when superimposed, 200.10. The alignment and the unspecified radius
the superelevation and profile grade of curvature varies depending on median width
combination may distort the outer pavement and other site considerations.
edges, confusing drivers at night. In such
Lane Drop - The minimum taper length for a
situations edge of pavement profiles should
lane drop should be equal to 0.6WV, where W =
be plotted and smooth curves introduced to
Dropped Lane Width (m), and V = Design Speed
eliminate distortion.
(kph). The transition should be on the right so
Avoid sharp horizontal curvature at or near that traffic merges left.
the top of a crest vertical curve. This
condition makes it difficult for the driver to Lane Addition - The minimum taper rate to add
perceive the curve, especially at night when
a lane should be 25:1 but in no case shall the
headlights do not illuminate the curve.
taper length be less than 50 m.
Avoid sharp horizontal curvature at or near
the low point of a sag vertical curve.
Foreshortening of the horizontal curve and
Part 2 200-16
ROADWAY DESIGN MANUAL Roads and Bridges

Figure 200.10
Typical Two-Lane to Four Lane Transitions
Part 2 200-17
ROADWAY DESIGN MANUAL Roads and Bridges

207 BRIDGES AND GRADE 208.02 PEDESTRIAN GRADE


SEPARATION STRUCTURES SEPARATIONS

207.01 CLEAR WIDTH Pedestrian grade separations are not normally


provided on roadways. However, if pedestrian use
The clear curb to curb width of all bridges or is extensive, an overcrossing or undercrossing
grade separation structures shall equal the sum of may be considered. Justification for pedestrian
the full travelled way approach width, paved grade separation structures comes from the
shoulders and barrier offset (if any). detailed study of present and future community
needs. Each situation should be studied separately
207.02 CROSS SLOPE and the study should include pedestrian
generating sources, travel patterns, crossing
The cross slope shall be the same as the approach volumes, roadway classification,
pavement. The crown is normally centered on the location/circuitry of adjacent crossings, land uses,
bridge except for one-way roadways where a sociological and cultural factors, and the
straight crosslope in one direction should be used. predominant type and age of users.
207.03 SIDEWALKS Established pedestrian patterns should be
maintained across expressway routes. Separate
Sidewalks should be provided where justified by pedestrian structures should be provided if
pedestrian traffic or if the approach roadway has vehicular crossings are inadequate for
sidewalk. The sidewalk width should match the pedestrians. If a circuitous route is involved, a
approach sidewalk width and crosslope. pedestrian separation may be justified. Special
consideration should be given to school crossings.
208 PEDESTRIAN FACILITIES
The choice between an undercrossing or an
208.01 SIDEWALKS overcrossing should be based on relative costs,
groundwater influence, drainage, existing utilities,
Sidewalk widths and locations vary but they shall current and future land use, visibility, topography
have a minimum width of 2.0 m and be located to and the surrounding architecture.
provide continuity in pedestrian movement.
208.03 PEDESTRIAN UNDERPASSES
Pedestrian crosswalk ramps shall be located at all
intersections and all other locations where main Undercrossings require special consideration,
pedestrian traffic crosses curblines. visibility issues and the potential for criminal
incidents and vandalism. If an undercrossing is
Cross Slope - The minimum sidewalk cross slope used, unobstructed visibility shall be provided
should be 1.5% toward the roadway. through the structure and approaches. The desired
vertical clearance is 3.0 m, but in no case shall
Sidewalk Widths - The guidelines in Table the clearance be less than 2.0 m. The minimum
200.07 should be used to determine sidewalk width shall be 2.5 m.
width.
209 CURBS
Table 200.07
Sidewalk Width Guidelines 209.01 GENERAL
Area/ vicinity Width (m)
Multi Family Units/Schools/ Curbs will be provided along all edges of
Office/Industrial 2.0 pavement in urban areas. Reasons for providing
Shopping/Recreation/Bus/Taxi 4.0 Curbs include:

The minimum sidewalk width shall be 2.0 m.

Part 2 200-18
ROADWAY DESIGN MANUAL Roads and Bridges

Required for proper drainage. Transitions - A transition from one curb type to
Needed for channelization, delineation, another shall be done in 3.0 m. At curb termini,
control of access, or improving traffic flow the curb should transition from normal curb
and safety. height to zero in 5.0 m.
To protect pedestrians and provide continuity
at ramp connections with local roads. 210 BUS STOPS AND TAXI STOPS
To replace existing curbs.
In urban areas, bus stops and taxi stops will be
To protect the expressway fence on frontage
provided on all main roads.
roads where required.
To prevent ponding in bus and taxi stops on flat
209.02 TYPES AND USES
grades use either a reverse cross slope toward the
main road pavement with slotted trench drains or
Curb types and uses are shown in the current
continue the slope of the roadway and install an
Standard Drawings and are discussed below.
inlet along the loading/unloading curb line.
Precast Curb Type A, B, C - These curbs are
210.01 BUS STOPS
used to deter vehicles from using areas outside the
travelled way, control drainage, and regulate and Bus stops will be located at the far side of
control parking. Type A curbs are typically used intersections and as necessary at midblock
on the outside of the travelled way, adjacent to locations. Near side bus stops should be avoided.
sidewalks and parking lanes. Typical B and C
curbs are used at the median edge adjacent to the Normally, bus stops shall be constructed as
green area. shown on the current Standard Drawings. Under
restrictive conditions these standards may be
The above curb types are classified as barrier reduced to 15.0 m length, 10.0 m tapers and 3.25
curbs and are not generally used on high-speed m width.
roadways as they present a safety hazard for
errant vehicles. A continuous concrete barrier At all bus stops a 4.0 m wide sidewalk shall be
(safety shape) should be used where it is provided along the loading/unloading area. This
necessary to control drainage or access on high- shall be connected to the nearest sidewalk with a
speed roadways. 4.0 m wide perpendicular sidewalk.

Cast-In-Situ Concrete Curb Type D - This curb 210.02 TAXI STOPS


is flush with the pavement and used to separate
Taxi stops will be located at the far side of
the travelled way from interlocking vehicular
intersections, no closer than 30.0 m to the radius
pavement.
return or end of right turn taper. Taxi stops
should be located as necessary within the block
Precast Concrete Curb Type E - This curb is
but no closer than 30.0 m to a sector road.
used between interlocking pedestrian pavers and
green or service reservation areas. Taxi stops shall be constructed as shown on the
current Standard Drawings. At all taxi stops a 4.0
Cast-In-Situ Concrete Curb Type F - This curb m wide sidewalk shall be provided along the
is flush with the pavement and used to separate loading/unloading area. This shall be connected to
interlocking pedestrian pavers from quarry tile. the nearest sidewalk with a 4.0 m wide
perpendicular sidewalk.
209.03 CURB PARAMETERS

Placement - Curbs should be positioned to


provide the same unobstructed roadway width
that is normally provided. All curb dimensions are
to the inside face of curb.

Part 2 200-19
ROADWAY DESIGN MANUAL Roads and Bridges

211 PARKING Generally it is desirable to locate parking exits


onto main roads about 50 meters prior to the start
To maximize the effective capacity of expressway of the left turn storage lane, and parking entrances
and main road improvements, sufficient off- off of main roads about 60 meters prior to the
system parking facilities should be provided to intersection, and/or prior to the start of the free
avoid the need for curb lane parking along right turn taper.
primary expressways and main roads.
In the typical case, a parking area is physically
211.01 GENERAL separated from the main road lanes by a
curb/sidewalk/curb combination which has been
Parking facilities are of four general types: designated as a wide curb. See Lot P2 in Figure
200.11. The minimum distance between the faces
1. Parking areas located parallel to, but of the two curbs is 1.0 m.
physically separated from, main road
moving traffic lanes, The parking area edge nearest the buildings
2. On-road parking spaces developed should be set parallel to the building line and at a
adjacent to the travelled lanes of sector sufficient offset distance to allow a sidewalk
roads, and along the building line.
3. Independent parking lots developed off
sector roads. The current Standard Drawings illustrate typical
4. Parking Structures. parking area and show stall dimensions and
pavement markings for both perpendicular and
Each facility consists of an aisle area and a 45-degree parking arrangements. Aisle widths and
standing area (parking stalls). In the case of on- stall depths should be as per Table 200.08.
road parking, the moving lanes of the sector road
also serve as the aisle. Table 200.08
Parking Isles and Stall Depths
Figure 200.11 illustrates different forms of the
Parking Aisle Width Stall Depth
basic types of parking facilities. Angle (m) (m)
Absolute Desirable Absolute Desirable
211.02 PARKING AREAS Min Min Min Min
Lots P1 and P2 on Figure 200.11 are typical 90o 7.0 7.3 5.5 5.8
parking areas, characterized by one entrance 60o 5.0 5.5 5.7 6.0
off the main road, then an aisle area with adjacent 45o 4.5 5.0 5.3 5.6
perpendicular and/or 45 degree parking, and
finally an exit leading back onto the main road
travel lanes. Desirably, the entrances and exits
should be independent of any sector road or main 211.03 ON ROAD PARKING SPACES
road intersections (i.e., Lot P2). When physical
conditions prevent this, a common entrance (or Parking spaces along sector roads are developed
exit) may be an acceptable arrangement (i.e., Lot by constructing added pavements immediately
P1). adjacent to the sector road moving lanes (usually
two lanes with one lane for travel in each
The minimum safe distance from a main road direction). Such parking spaces should be either
intersection to a parking entrance or exit will be parallel or perpendicular. The use of 45-degree
dependent on many factors, such as, volume and parking should be limited to one-way sector
speed of the traffic, type of intersection, width roads.
and number of lanes in the main road, the volume
of traffic using the parking area, and any sight Figure 200.11 shows examples of on-road
distance restrictions. parking space developments along sector roads.
Dimensions for perpendicular and 45-degree

Part 2 200-20
ROADWAY DESIGN MANUAL Roads and Bridges

parking stalls are similar to those given on the 3. determine the need for added parking facilities
Standard Drawings. and establish an approximate location for
such parking.
Parallel parking stalls should have a length of 7.0
m and a desirable minimum width of 2.5 m as The required analysis regarding parking will thus
shown on the Standard Drawings. vary from project to project since parking demand
is sensitive to site-specific factors, such as land
Where sector roads are widened to provide use and proposed community developments.
parking stalls, the widened sector road
arrangement should not be carried through sector In the absence of site specific parking criteria,
road/sector road intersections. The fillets at such Table 200.09 should be used. Also refer to Part 1,
intersections (usually 5.0 m radii) should be Section 202.02.11 for further parking
positioned to line up with the edge of the travelled requirements.
lanes.
Table 200.09
211.04 PARKING LOTS Parking Requirements

Figure 200.11 also shows samples of independent


Type of Development Parking
parking lots developed off sector roads. Such lots
Requirements
are of two general varieties:
Commercial/Office 1 space / 50 m2 floor
1. Single entrance/exit (see lots P3, P4 and P5)
space
and
Retail 1 space / 30-50 m2 floor
2. Double entrance/exit (see Lots P6 and P7).
space
Governmental 1 space / 50 m2 floor
Wherever practical, these layout rules should be
space
followed:
School 1 space / 3 employees
plus
1. Aisles and entrance/exit widths should be
1 space / 5 students
typically designed for two-way operation in
Hospital 1 space / 2 employees
conjunction with perpendicular parking.
plus
2. A median (curb/sidewalk/curb combination)
1 space / 4 beds
at least 1.0 m wide should be provided
Low Density
between adjacent parking bays served off
Residential Villas 2 spaces / dwelling unit
different aisles (i.e., on Figure 200.11, a
Medium Density
barrier is provided between Lots P6 and P7).
Apartments 1 space / (100
3. Forty-five degree parking should only be used
m2*.85*.80)
in conjunction with one-way aisles/sector
High Density
roads.
Apartments 1 space / (100
m2*.85*.80)
211.05 PARKING DEMAND/SUPPLY
ANALYSIS
These requirements should be considered as
minimums.
During the early portion of the Concept Design
Phase, the designer will:
It is possible that the number of spaces required
1. determine the location of existing parking by these guidelines cannot be provided due to
facilities, space limitations. In that case, efforts should be
2. identify any facilities to be displaced by road directed toward providing the maximum amount
improvements that should thus be replaced, of parking in a reasonable configuration.
and

Part 2 200-21
ROADWAY DESIGN MANUAL Roads and Bridges

Figure 200.11
Typical Parking Facilities

Part 2 200-22
ROADWAY DESIGN MANUAL Roads and Bridges

SECTION 300 most urban roads because curbs provide


pavement structural support, and disabled
GEOMETRIC CROSS SECTION
vehicles can park in parking lanes, side streets, or
driveways.
301 TRAVELLED WAY STANDARDS
302.01 SHOULDER WIDTH
301.01 TRAVELLED WAY WIDTH STANDARDS

Travelled way width is one of the most important Table 300.01 summarizes the minimum
safety factors in design. A wide two-lane two-way continuous usable width of paved shoulder for
pavements provides higher capacity, higher driver various roadway classifications.
comfort levels, consistent operation and lower
accident rates. Table 300.01
Paved Shoulder Width Standards
Minimum travelled way widths of 7.30 m shall be
provided on all design classes of roadways. Roadway Inside Outside
Class Shoulder Shoulder
Traffic lane widths shall be 3.65 m, and the
/ verge / verge
number of lanes required shall be based on the
(m) (m)
projected traffic volume and roadway
RURAL
classifications. Loop ramp lanes shall be 5.0 m.
Freeway 3.0 4.0/2.0
Expressway 3.0 4.0/2.0
See Section 302 for general shoulder widths and
Collector - 2.4
see Section 305 for specific roadway cross
Local Access 2.0
section widths.
URBAN
Freeway 3.0 4.0/2.0
301.02 TRAVELLED WAY CROSS
Expressway 3.0 4.0/2.0
SLOPES
Arterial (Main Rd) - 4.0/2.0
Frontage Road 1.2 1.2
Tangent cross slope is balanced between steep
Sector Road - -
cross slopes, desirable for drainage and the fact
2-LANE RAMP 2.4/2.0 3.0/2.0
that vehicles drift toward the lower pavement
LOOP RAMP 2.0/1.0 3.0/1.0
edge on steep cross slopes. Generally, cross
slopes below 1.5 percent have little effect on The verge is the area outside the paved shoulder,
vehicle steering. Cross slope values for the usually rounded, at the top of embankment
various roadway classifications are provided in slopes.
the following sections.
302.02 SHOULDER CROSS SLOPES
Unpaved travelled ways shall have a cross slope
of 3.0 percent.
In normal tangent sections, inside shoulder slope
shall match the travel lanes and outside shoulders
See Section 305 for specific roadway cross slope
shall slope on a 3% grade away from the travelled
rates.
way.
Pavement superelevation on curves shall be as
determined in Section 202.
303 SIDE SLOPE STANDARDS

Properly designed side slopes insure roadway


302 SHOULDER STANDARDS
stability and provide a safe recovery area for
errant vehicles.
Shoulders provide pavement structural support,
improve sight distance, provide emergency
Where feasible, slopes should be flattened to be
stopping areas, and help provide required side
consistent with the roadway classification and
clearance. However, shoulders are unnecessary on
topography. The tops and ends of all slopes
Part 2 300-1
ROADWAY DESIGN MANUAL Roads and Bridges

should be rounded 3.0 m where the material is Shoulders - Shoulder widths for various roadway
other than solid rock. classifications are summarized in Table 300.01.

303.01 SIDE SLOPE VALUES 305.01 RURAL FREEWAY/


EXPRESSWAY CROSS
Side slopes should be 1:6 or flatter depending on SECTION
soil type. If slopes are steeper than 1:3, barrier
may be required. Earth cut slopes should be at General - The typical section for rural
least 1:3 but in no case steeper than 1:2. expressways shall be comprised of two roadways
with shoulders, divided by a median.
303.02 SLOPE CLEARANCE FROM
RIGHT OF WAY Travelled Roadways - Each roadway will
consist of a minimum of three 3.65 m through
The minimum clearance from the right of way line lanes. Ramps shall be 5.0 m for one lane and,
to the catch point should be 3.0 m with 4.5 m where volumes demand, two 3.65 m lanes.
desired. For cut slopes this is measured from the
outer edge of the rounding or crown drainage Median - Median treatment may be either
system. Slopes over 15.0 m high may require standard concrete barriers placed along the inside
additional clearance for maintenance. shoulder edge or an unpaved depressed median.
Median width may vary to match existing median
304 MEDIAN STANDARDS widths. The width of the depressed median
measured between edges of travelled pavement
A median is the portion of a divided roadway shall be 20.0 m minimum.
between the opposing travelled pavements.
Cross Slope - Except superelevated sections, a
Raised medians shall be used on urban roads to uniform cross slope of 1.5 percent shall be
regulate left-turn movements. Paved medians, applied across the inside shoulder and driving
including those bordered by curbs, should be lanes. The outside shoulder will have a cross-
crowned at the center, sloping towards the sides at slope of 3.0 percent. The pavement will slope
the slope of the adjacent pavement. toward the outside of the section.

Unpaved, landscaped medians between curbs On structures, the cross-slope shall be 1.5 percent
shall be graded flat. Other unpaved medians uniformly across the inside shoulder, driving
should slope downward from the shoulders to lanes, and outside shoulder.
form a shallow valley. Cross slopes should be
1:10 or flatter 1:20 being preferred. Slopes as Profile Grade Line - The profile grade line shall
steep as 1:6 are acceptable if necessary for be at the median edge of the travelled roadway.
drainage.
305.02 URBAN FREEWAY/
See Section 305 for specific roadway median EXPRESSWAY CROSS
requirements. SECTION

305 CROSS SECTION ELEMENTS General - The typical section for urban
expressways shall be comprised of two roadways,
See Figure 300.01 for typical cross sections of with shoulders, divided by a median. Due to space
various roadway classifications. limitations, the cross section may vary. The final
configuration shall be determined during the
Pavement Structure - For the Standard concept phase of design.
Pavement Structures, see current Standard
Drawings. Also, refer to Section 604 Structural
Pavement Section Design.

Part 2 300-2
ROADWAY DESIGN MANUAL Roads and Bridges

Figure 300.01
Typical Cross Sections

Part 2 300-3
ROADWAY DESIGN MANUAL Roads and Bridges

Travelled Roadways - Each roadway will Parking, Loading/Unloading Lanes - Except for
consist of a minimum of three 3.65 m wide taxi stops and bus stops, no parking or
through lanes. Ramps shall be one 5.0 m lane, loading/unloading spaces shall be provided on
and where volumes demand, two 3.65 m lanes. main roads without being separated from the
traffic lanes by a wide curb.
Median - A minimum 7.0 m wide median shall be
used. However, a 10.0 m median width is Median - A median with 22 cm high curbs shall
desirable. The median may be either unpaved and be provided. The median width should be at least
depressed (if 20.0 m wide or more), or it may 5.0 m. Where an existing street with a median of
have concrete barriers. less than 5.0 m is being upgraded, the median
should be increased to 5.0 m if possible. Where
Cross Slope - Except in superelevated sections, a an existing street with a median width of greater
uniform cross slope of 1.5 percent shall be than 5.0 m is being upgraded, the existing median
applied across the inside shoulder and driving width should be maintained for planting. Median
lanes. The outside shoulder will have a cross width shall be reduced to permit exclusive left-
slope of 3.0 percent. The pavement will slope turn lanes at intersections where required.
toward the outside of the section.
No provision shall be made for U-turns except at
On structures, the cross slope shall be 1.5 percent intersections.
uniformly across the inside shoulder, driving
lanes, and outside shoulder. Curbs - Curbs shall be provided along all edges
of pavement in urban areas. Curb types and uses
Profile Grade Line - The profile grade line shall are shown in the current Standard Drawings.
be the median edge of the travelled roadway.
Sidewalks - Sidewalk widths and locations will
305.03 ARTERIAL (MAIN ROAD) vary but the minimum width shall be 2.0 m and
CROSS SECTION they shall be located to provide pedestrian
movement continuity. In addition, whenever
The standard cross section of roadways is possible a 2.0 m wide sidewalk adjacent to the
comprised of two unidirectional pavements, pavement and green areas should be provided
median, sidewalks, service reservations and green primarily for aesthetic purposes.
areas.
Pedestrian crosswalk ramps shall be used at all
Pavement and Lane Widths - The pavement will intersections and all other locations where the
consist of a minimum of three traffic lanes in each main pedestrian sidewalk crosses curb lines.
direction divided by a raised median. Wherever
necessary, auxiliary lanes shall be provided for Cross Slope - All pavement will have a broken
turning movements. Auxiliary lanes, whether cross-slope of 1.25 percent sloping away from the
allocated to through traffic or to turning median across the two inside lanes and 2.0
movements, shall be 3.65 m wide. percent for the outside lanes. A 1.5 percent cross-
slope shall be provided toward the pavement on
Free Right Turn Islands and Lanes - Exclusive sidewalks. Cross-slope will vary at intersections
right-turn lanes and islands shall be used in accordance with current Standard Drawings.
wherever possible. No more than one exclusive
right-turn lane shall be provided in any direction. Profile Grade Line - The profile grade line shall
be the median edge of pavement.
Left Turn Lanes - Unless otherwise approved by
the Municipality Road Section under special
conditions, no more than one left-turn lane shall
be provided from the median.

Part 2 300-4
ROADWAY DESIGN MANUAL Roads and Bridges

305.04 SECTOR ROAD CROSS 305.05 FRONTAGE ROAD CROSS


SECTION SECTION

The cross section for sector roads will consist of Pavement and Lane Widths - The minimum
an undivided two-directional roadway. Curbs paved cross section for urban frontage roads shall
shall be provided along both edges of pavement. be two 3.65 m lanes with curbing. The minimum
paved cross section for rural frontage roads shall
Pavement and Lane Widths - Lane width shall be 3.65 m lanes with 1.2 m paved shoulders.
be 3.65 m for two lanes in each direction and 4.0
to 5.0 m for one lane in each direction. Cross Slope - All pavement will have a 1.5
percent uniform cross slope either at a straight
Free Right Turn Islands and Lanes - No free cross slope from one edge of pavement to the
right turn islands or lanes shall be used in the other or by utilizing a crowned roadway design.
design of sector roads.
Outer Separation - Outer separation is the
Left Turn Lanes - Left turn lanes shall not be distance from the main road travelled way to the
used in the design of sector roads. frontage road travelled way. In urban and
mountainous areas, the outer separation should be
Parking Loading/Unloading Lanes - Generally, 8.0 m minimum. In rural areas, other than
no loading or unloading lanes shall be provided on mountainous terrain, the outer separation should
Sector Roads. It is up to the designer and Design 12.0 m minimum.
Project Manager to determine the need and type
of on-street sector road parking. If required, see Headlight Glare - Frontage road design shall
Section 211, Parking. account for potential headlight glare interfering
with the vision of oncoming motorists. The
Median - Sector roads shall not have medians. preferred measures to prevent headlight glare
interference on new construction are wider outer
Curbs - Curbs shall be provided along the outside separations, revised alignment and raised or
edge of sector roads. Types and uses are shown in lowered profiles.
the current Standard Drawings.
306 HORIZONTAL AND VERTICAL
Sidewalks - Sidewalk widths and locations will CLEARANCES
vary but minimum width shall be 2.0 m.
Whenever possible a 2.0 m wide sidewalk 306.01 HORIZONTAL CLEARANCES
dividing the pavement and green areas should be
provided. The sidewalk surface will slope toward Unshielded Horizontal Clearance - The
the roadway at a uniform cross slope of 1.0 minimum desired horizontal clearance between the
percent. travelled way edge and fixed objects shall be the
clear zone width. Fixed objects within the clear
Pedestrian crosswalk ramps shall be used at all zone shall be eliminated, moved, redesigned
intersections and all other locations where main (breakaway design), or shielded (see barrier
pedestrian traffic crosses curb lines. design below ) where practical.

Cross Slope - All pavement will have a 1.5 Shielded Horizontal Clearance - If fixed objects
percent uniform cross slope either at a straight cannot be eliminated, moved or redesigned then
cross slope from one edge of pavement to the lesser clearance is allowable if barriers or
other or by utilizing a crowned roadway design. guardrail is used to shield the object.
Sector roads shall not have superelevation.
The clearance to fixed objects such as bridge
Profile Grade Line - The profile grade line for rails, concrete barriers, abutments, retaining
sector roads shall be the centerline or as walls or noise barriers on all roadway facilities,
determined by the Consultant. shall be equal to the standard roadway shoulder

Part 2 300-5
ROADWAY DESIGN MANUAL Roads and Bridges

width stated in Table 300.01, except that a 306.03 TUNNEL CLEARANCES


minimum clearance of 1.2 m shall be provided
where the standard shoulder width is less than Horizontal Clearances - The minimum
1.2 m. Approach rail connections to bridge rail expressway tunnel width should equal the full
may require special treatment to maintain approach travelled way width plus paved
standard shoulder width. Safety shaped barrier shoulders.
face shall be constructed integrally at the base of
any retaining wall, pier, or abutment which faces In one-way tunnels on conventional roadways the
traffic and is less than 4.6 m from the edge of minimum side clearance from the edge of the
travelled way. travelled way (unless sight distance dicatates
otherwise) shall be 1.5 m on the left and 2.0 m on
Curbed Roadway Sections - A minimum the right. For two-way tunnels, this clearance
horizontal clearance of 1.0 m should be provided shall be 2.0 m on each side.
along intersection curb returns and near driveway
edges to allow for design vehicle off tracking. Vertical Clearances - The desirable vertical
Where sidewalks are located immediately clearance shall be 6.0 m measured at any point
adjacent to curbs, fixed objects should be located over the travelled way. Lesser clearance may be
behind the sidewalk, providing an unobstructed approved by the Municipality Road Section.
pedestrian area.
307 CLEAR ZONE CONCEPT
306.02 VERTICAL CLEARANCES
Clear Zone - A clear zone is an unobstructed, flat
General - Efforts should be made to avoid or gently sloping area beyond the travelled way
decreasing the existing vertical clearance edge. It gives drivers the opportunity to regain
whenever possible and consideration should be control of errant vehicles. The clear zone is
given to increasing vertical clearance on projects measured horizontally from the travelled way
involving structural section removal and edge to the nearest point on an obstruction. Where
replacement. feasible, fixed objects should not be located
within the clear zone.
Structure Type Vertical Clearance
(m) In an area where the roadside is relatively clear,
Pavement Surface to nearest flat and straight, application of the clear zone
underside of superstructure. 6.0 concept is straightforward. However, factors
such as roadside embankments, space restrictions
Sign Structures 5.5
and roadway curvature and superelevation
Overhead Communication Lines 7.0 complicate the application of the clear zone.
Power Lines (Volts)
Clear Zone Standard - The clear zone width
0 - 750 7.0
required is based on geometry, traffic volumes,
750 - 15,000 9.0
and operating speeds as shown on Figure 300.02.
15,000 and greater 10.0
Pedestrian Overpass 6.0 Curvature Correction Factors - Figure 300.03
Pedestrian Overpass with shows correction factors used to adjust the clear
Overhead Guide Sign 6.0 zone distances, taking into account roadway
curvatures. These modifications should be used
only in locations with high accident rates and
where increasing the clear zone distance is cost
effective.

Part 2 300-6
ROADWAY DESIGN MANUAL Roads and Bridges

Figure 300.02
Clear Zone Distance Curves
Part 2 300-7
ROADWAY DESIGN MANUAL Roads and Bridges

Figure 300.03
Horizontal Curve Adjustments Factors

307.01 APPLICATION OF CLEAR reaching the base. Embankments with slopes


ZONE between 1:3 and 1:4 generally fall under this
category. A smooth clear run-out area with a
307.01.01 Roadside Terrain: Foreslope slope of 1:6 or flatter, in addition to the
recommended clear zone distance is recommended
When a roadway is on an embankment, the side at the base of the slope. The width of the runout
slope is called a foreslope (negative slope) which area is determined according to the available
can be recoverable, non-recoverable, or critical: width between the edge of traveled way and the
breakpoint between the flatter (1:4 and flatter)
Recoverable - A recoverable slope is one that an and steeper (1:4 and 1:3) slope of the
errant vehicle can drive across, slow down, stop, embankment. This available width is then
and return to the roadway. Recoverable slopes subtracted from the clear zone distance obtained
are 1:4 or flatter, relatively smooth, and clear of from Figure 300.02, based on the steeper slope of
all fixed object hazards. The top of the slope shall the embankment. The difference is the width of
be rounded so a vehicles wheels remain in the clear runout area. See Figure 300.04 for
contact with the roadway when encountering the example.
embankment. The toe of slope shall also be
rounded so the driver is able to negotiate and Critical - A critical slope is one where a vehicle
drive across if the vehicle reaches the base of the has a high probability of overturning, slopes
embankment. steeper than 1:3 fall in this category. If the
available clear zone is narrower than the
Non-recoverable - A non-recoverable slope is recommended width or it is not practical to adjust
one which an errant vehicle can be driven across the roadside geometry, installing a barrier system
but may not be able to slow down or stop before may be necessary.

Part 2 300-8
ROADWAY DESIGN MANUAL Roads and Bridges

307.01.04 Roadside Terrain: Ditch


307.01.02 Roadside Terrain: Backslope
The primary function of ditches is to prevent
When a roadway is located in a cut section, the roadways from flooding by directing and carrying
cut slope is called a backslope. A traversable water away from the roadway. They are
backslope is 1:3 or flatter, relatively smooth, especially hazardous because of fixed hazards
clear of fixed object hazards, and where a vehicle such as, exposed pipes, headwalls and culverts.
can be driven across without becoming stranded. The ditch cross section itself can also represent a
This type of backslope can be included as part of serious hazard. Preferred ditch cross sections are
the clear zone. However if the backslope is traversable and free of hazards. See Figures
steeper than 1:3, rock cut or rough sided, the base 300.05 and 300.06. Cross sections that fall
of the backslope shall be outside the clear zone. within the shaded area are considered traversable.
If the recommended clear zone can not be Cross sections that fall outside the shaded regions
practically accommodated, a barrier system may are considered less desirable and should be used
be required to protect motorists. only under conditions of:
restricted ROW
307.01.03 Roadside Terrain: Cross-slope
rugged terrain
Cross-slopes can be located along medians, resurfacing, restoration or rehabilitation
intersecting driveways and roadways. Cross low volume or low speed roads
slopes can be more hazardous to motorists than Conditions where a ditch has a cross section that
foreslopes or backslopes because of the falls outside the shaded region, and is located in a
possibility of colliding with opposing traffic. vulnerable location shall consider closed drainage
Cross-slopes of 1:10 or flatter, traversable, systems or shielding with barrier systems.
relatively smooth, and clear of fixed object
hazards are recommended particularly in medians
immediately adjacent to opposing traffic. In
roadside sections where 1:10 can not be
accommodated, such as urban areas, a maximum
slope of 1:6 should be used.

Figure 300.04
Clear Runout Area

Part 2 300-9
ROADWAY DESIGN MANUAL Roads and Bridges

Figure 300.05
Preferred Vee-Ditch Cross Sections

Figure 300.06
Preferred Trapezoidal ditch Cross Sections
Part 2 300-10
ROADWAY DESIGN MANUAL Roads and Bridges

308 BARRIERS Install drop inlets for roadside drainage


systems rather than exposed pipes and
308.01 BARRIER NEED culverts.
Remove or relocate all manmade or natural
The roadside barriers primary function is to fixed obstacles such as utility poles, signs,
prevent errant vehicles from leaving the roadway. luminare supports, trees, and boulders.
Barrier need is based on the premise that Install breakaway bases for signs and
installing a barrier will reduce the number of luminare supports if removal or relocation is
accidents and/or reduce the magnitude of an not practical.
accident at that location. The engineer must also
evaluate the barrier installation itself to be less 308.02 ROADSIDE BARRIER TYPES
hazardous than the hazard. Efforts shall be made AND FEATURES
to eliminate hazards within the clear zone prior to
considering any barrier installations. There are two types of roadside barriers
commonly used. See Figure 300.08.
When determining barrier requirements, the
following factors must be considered: Blocked-Out W-Beam Barrier
Risks involved with encroaching on a hazard Roadside Concrete Barriers
versus colliding with a barrier.
Evaluating roadway design speed and traffic Block-Out W-Beam Barrier - This barrier
volumes to barrier need. system is the mainly used as a guardrail system.
Evaluating costs of installing and maintaining It shall be installed in most locations that
a barrier system versus not installing a barrier warrants a guardrail system, except for urban
system. areas and locations that require a concrete barrier.
Costs of accidents involving barriers versus This system has been tested to successfully
not involving a barriers. redirect 800-2000 kg vehicles. It has also
successfully redirected a 2100 kg van at impact
Figure 300.07 for example, compares the risks conditions of 21 at 95 kph.
involved with encroaching on an embankment
versus colliding with a barrier. Embankments Concrete Safety Shape Barrier - The concrete
that fall outside the shaded region do not warrant safety shape roadside barrier is a rigid system
shielding. Figure 300.07 however does not not designed to redirect vehicles without any
take into account other factors such as, object deflection. Because of its rigidity, vehicles would
hazards on the embankments within the clear have a higher probability of overturning or
zone, installation and maintenance costs of a vaulting over the barrier. Therefore, shape of the
barrier system, and accident costs involving a front face of the barrier is critical to its
barrier system. All these factors must be performance. The distance from the top of the
considered together when evaluating barrier roadway surface to the break between the upper
needs. and lower slopes shall not exceed 330 mm.

As previously stated, if hazards exist within the Roadside barriers are also designed with varying
borders of the clear zone, efforts shall be made to heights to counteract overturning moments of
eliminate the hazard first, prior to considering trucks with high centers of gravity. The basic
barrier installation. These considerations can roadside barrier is designed at 810 mm high. At
include any of the following: this height, the roadside barrier can successfully
Regrading of roadside topography in the clear redirect 820-2000 kg vehicles, and occasionally
zone to a smooth and safe cross section. redirect 18,000 kg buses at moderate impact. A
Extend exposed pipes, culverts and install roadside barrier designed at 1070 mm high, have
headwalls outside the clear zone. successfully redirected a 36,300 kg tractor-trailer
with impact conditions of 15 at 84 kph.

Part 2 300-11
ROADWAY DESIGN MANUAL Roads and Bridges

Figure 300.07
Risk Warrants for Embankments

308.03 ROADSIDE BARRIER 308.03.02 Barrier to Hazard Clearances


PLACEMENT
In cases when a roadside barrier is required to
308.03.01 Lateral Placement shield an isolated hazard, clearance must be
provided between the barrier and the hazard.
Placement of a barrier system shall be determined Upon impact, some barriers will deflect, making
in a manner that increases motorist safety, the clearance between the barrier and the hazard
decreases accidents and minimizes injuries. A important. Furthermore, if a barrier is struck by
barrier system shall shield the motorist from a vehicle with a high center of gravity, the vehicle
roadway hazards and not contribute to the hazard. may roll or vault over the barrier. If sufficient
It is therefore a standard rule that the barrier distance is not provided, the vehicle may collide
system shall be placed as far from the edge of with the hazard. Sufficient distance must be
travelled way as possible. This allows drivers provided between the barrier and the hazard being
room to regain control of their vehicle and shielded.
possibly avoid an accident. It is important to note
however; as the distance between the edge of
travelled way and the barrier increases, the
potential angle of impact of the vehicle also
increases. Barriers at high angle of impacts are
significant hazards themselves.

Part 2 300-12
ROADWAY DESIGN MANUAL Roads and Bridges

308.03.03 Effects of Roadside Terrain Runout Lengths (LR) and Hazard Lateral
Distance (LH) - When designing the length of a
The profile between the edge of traveled way and barrier, the two primary factors that must be
the barrier can have significant effects on the final considered are:
placement of the barrier. The vehicles wheels
should remain in contact with the ground and its LR - Runout Length
suspension system neither compressed or LH - Hazard Lateral Distance
suspended at the moment of impact with the
barrier. This holds true for all barrier systems. The runout length (LR) is the distance a vehicle
Locations of roadside curbs and slopes require needs to stop prior to colliding with a hazard once
particular attention when determining barrier it has left the roadway. Its distance is measured
design and placement. from the point the vehicle is assumed to leave the
roadway to the hazard ahead. Runout length
Curbs - Guardrail/Curb combinations are highly requirements vary according to the roadway
discouraged in locations where high-speed and design speed. See Figure 300.04.
high angle impacts are likely to occur. Areas
with no alternative but to use this combination The lateral distance (LH) is the distance between
shall use a curb less than 100 mm or, stiffen the the edge of the travelled way to the far side of the
guardrail to reduce deflection by bolting a w- hazard, if the hazard is a fixed object. If the
beam to the back of the posts or by adding a rub hazard is an embankment, the lateral distance
rail. would be extended to the edge of the clear zone.
If the hazard extends beyond the clear zone, the
Slopes - As previously mentioned, guardrail minimum lateral distance would be only to the
performance is affected by the vehicles position edge of the clear zone.
at moment of impact. Crash tests show, roadside
barriers perform most effectively when installed After determining the runout length and lateral
on slopes 1:10 or flatter. distance, the length of the barrier depends on the
barrier tangent length, barrier lateral offset, and
308.03.04 Barrier Length Design flare rate.

Figure 300.08
Roadside Barrier Types and Features

Part 2 300-13
ROADWAY DESIGN MANUAL Roads and Bridges

Figure 300.09
Barrier Layout Diagram

Part 2 300-14
ROADWAY DESIGN MANUAL Roads and Bridges

Barrier Tangent Length (LT) and Barrier Median barriers are warranted in locations that
Lateral Offset (L1) - The barrier tangent length have a history of cross-median accidents. On
(LT) is the portion immediately ahead from the roadways that have wide medians, (greater than
hazard and parallel to the roadway. It is of nine meters) median barriers generally are not
variable length, selected by the designer, and warranted unless there is a history of cross-
shall be at least as long as the flared section of the median accidents or there are fixed object hazards
barrier. within the median.

The barriers lateral offset (L1) is the distance 308.04.02 Median Barrier Types and
between the edge of travelled way to the barrier. Features
This offset is also selected by the designer and
shall be as far away from the edge of travelled There are three types of commonly used median
way as possible. This provides an unobstructed barriers. See Figure 300.10.
recovery area to allow an out of control vehicle to
gain control without colliding with the barrier. Concrete Safety Shape Median Barrier
Single Face Concrete Barrier
Flare Rate (b:a) - The flared portion of the Metal-Beam Guardrail
barrier is not parallel to the roadway. Flared
sections are used mainly to introduce the barrier The concrete safety shape barrier is the most
toward the barrier line or a narrower segment of commonly used median barrier, and shall be
the roadway. The flared transition decreases the installed in most locations requiring a barrier. In
likelihood that the barrier is perceived as a hazard areas where the adjoining sections of roadway
by motorists. have previously installed a Metal Beam Guardrail
consideration may be given to continue using it
Flared barrier sections have their disadvantages. for that segment. Single face Concrete Barriers
The greater the flare rate, the greater the angle of are used mainly to shield hazards or for earth
impact from an approaching vehicle. This may berm support.
increase the magnitude of injuries particularly
with rigid barriers. Barrier flares can also 308.05 MEDIAN BARRIER
increase the probability that an impacting vehicle PLACEMENT
will be redirected across the roadway and into
incoming traffic. This is particularly dangerous if The two primary factors to consider when placing
the roadway has two-way traffic not separated by median barriers are:
a median or a median barrier. Therefore, flatter
flare rates shall be used particularly in locations Median Geometry
with two-way traffic or steep embankments. Treatment of Fixed Object Hazards in the
Median
See Figure 300.09 for barrier layout diagram.
308.05.01 Median Geometry
308.04 MEDIAN BARRIERS
As previously mentioned, a median that is flat
308.04.01 Median Barrier Warrants (1:10 or flatter), relatively smooth and clear of
fixed obstacles is desirable. If a median barrier is
A Median barriers primary function is to warranted under these conditions, it shall be
separate opposing traffic on a divided roadway installed at the center of the median.
and/or shield fixed object hazards within the
median. Like all types of barriers, median If the median is a v-shaped foreslope embankment
barriers shall only be installed if it is less or a ditch and warrants a barrier, it shall be
hazardous colliding with the barrier than not installed near the shoulder on both sides of the
having a barrier installed at all. Barrier median.
installation shall be considered only if the fixed
object hazards can not be removed.

Part 2 300-15
ROADWAY DESIGN MANUAL Roads and Bridges

If the full width of the median is a foreslope 308.05.02 Treatment of Fixed Object
embankment steeper than 1:10, and warrants a Hazards
barrier, the barrier shall be installed on the higher
edge of the median. If the slope is 1:10 or flatter In some situations, the entire median does not
and requires a barrier, the barrier shall be require a barrier system. However, there may be
installed at the center of the median. However, if hazards in the median that require shielding.
the median is rough cut, obstructed with hazards, Treatment of hazards can include but not limited
and non-traversable, barriers shall be installed, at to those illustrated in Figure 300.11.
the edge of both shoulders.
308.06 END TREATMENTS AND
If the median is a backslope that is rough cut, CRASH CUSHIONS
non-traversable or is inside the clear zone area,
barriers shall be installed on both sides of the 308.06.01 End Treatments
median to avoid vehicle snagging. If the
backslope is traversable but sufficiently steep to All roadside and median barriers terminating
redirect vehicles, a semi rigid barrier can be within the clear zone and/or are located where
installed on the high point of the slope. they have a high probability of being hit head-on,
shall terminate with a crashworthy terminal on the
approach end of the barrier. Refer to the most
recent edition of the AASHTO Roadside Design
Guide.

Figure 300.10
Median Barrier Types and Features

Part 2 300-16
ROADWAY DESIGN MANUAL Roads and Bridges

Figure 300.11
Treatment of Fixed Hazards

Part 2 300-17
ROADWAY DESIGN MANUAL Roads and Bridges

308.06.02 Crash Cushion The minimum requirement for a crash cushion


system shall have the following characteristics:
A Crash Cushions main function is to decrease
the magnitude of an accident by absorbing some The system shall be able to stop or redirect a
of the force from an impact. They are effective in colliding vehicle without any debris
gradually slowing down and stopping or safely penetrating the passenger compartment of the
redirecting errant vehicles in head-on and side vehicle.
impact collisions.
The colliding vehicle shall remain in the
Crash Cushions shall be used to shield hazardous upright position and not violently redirected
conditions and fixed object hazards that can not to other traffic.
be removed, relocated or designed to breakaway.
These include ends of bridge barriers, rails and
bridge piers in gore areas. Crash Cushions are 308.06.03 Placement Recommendations
also commonly used at ends of roadside and
median barriers . Crash Cushion systems perform best on relatively
flat surfaces. Therefore they shall be installed on
Selection Guidelines hard level surfaces such as portland cement
concrete or hot bituminous concrete pads. This
The selection criteria for crash cushions differ in allows the crash cushion system to compress
each individual case. Engineers must evaluate uniformly throughout the impact. The path
each hazard and select the most effective and between the roadway and the crash cushions shall
appropriate crash cushion system for that case. be relatively smooth and clear of obstructions.
Refer to the most recent edition of the AASHTO Ideally the vehicles suspension systems should
Roadside Design Guide. not be collapsed or extended when it collides with
the crash cushions.

Part 2 300-18
ROADWAY DESIGN MANUAL Roads and Bridges

SECTION 400 There are three categories of roadway


intersections. This section deals with at-grade
AT-GRADE INTERSECTIONS
intersections. Grade separations (i.e., without
ramps), and interchanges are discussed in Section
401 GENERAL 500.
An intersection is the area where two or more
402 DESIGN CONSIDERATIONS
roadways connect. It includes the roadway and
roadside facilities available for traffic movement.
Intersection design affects roadway efficiency,
Each roadway radiating from an intersection is
safety, capacity, operating cost and operating
called an intersection leg.
speed. Well designed intersections reduce the
severity of user conflicts while accommodating
Intersection design is very important to the overall
their varied interests. Intersection design is a
roadway safety and level of service. Many
cooperative effort between roadway and traffic
accidents and safety problems occur at
engineers, based on human factors, traffic
intersections. Intersection type and spacing
considerations, physical elements and economic
control roadway capacity and travel time.
factors.
Intersections handle a variety of conflicts among
vehicles and pedestrians. Vehicles arriving,
departing, merging, turning, and crossing traffic
403 AT GRADE INTERSECTION
have to be accommodated within a relatively TYPES
small area. These movements may be handled by
various means, depending on the intersection type. There are three basic types of at-grade
intersections, the three-leg intersection, the four-
leg intersection, and the multileg intersection. See
Figure 400.01. Factors in determining the type of
intersection include, the number of

Figure 400.01
Basic Intersection Types

Part 2 400-1
ROADWAY DESIGN MANUAL Roads and Bridges

intersecting legs, topography, traffic patterns, and Give preference to major traffic movements.
desired operation. Intersections within a basic Reduce areas of conflict.
type vary greatly however, the general application Cross traffic at right angles (75-90o desirable
of at-grade intersection design is common to all. - skew no more than 60o.)
Traffic volume, design speed, and the roadway Separate points of conflict.
classification are the principal factors used to Provide speed-change lanes and separate
determine intersection type. turning lanes where appropriate.
Restrict undesirable movements.
Three-Leg Intersection - The three-leg Provide adequate width to shadow turning
intersection has three intersecting legs which form traffic.
a T or a Y. Operationally three-leg and four- Enhance signal control.
leg intersections are preferred and multidirectional
"Y" intersections and intersections with more than
404.01 PREFERENCE TO MAJOR
four legs should be avoided.
MOVEMENTS
Four Leg Intersections - Four-leg intersections Whenever possible, preference should be given to
may be right angled, oblique, or offset. The right- the major traffic movements. This usually requires
angled crossing is easily signed and signalized, stopping, funneling, or eliminating minor
provides good visibility, and is the safest to movements. Controlling measures should conform
negotiate. The oblique crossing creates problems to natural movement paths and be introduced
with visibility, pedestrian safety, and vehicle- gradually to promote smooth and efficient
turning angles. The offset intersection has low operation.
capacity, is difficult to comprehend and negotiate,
and is difficult to sign and signalize. 404.02 AREAS OF CONFLICT
Multileg Intersections - These intersections have Large multilane undivided intersection areas are
more than four legs and can have several undesirable because drivers cannot predict the
configurations. Multileg intersections are other vehicles movements. By separating traffic
confusing, have poor visibility, poor turning movements into definite travel paths
angles, and are difficult to sign, mark, and channelization reduces these conflicts.
signalize. This type of intersection should be Channelization also separates points of conflict
avoided if possible. within the intersection and clearly defines vehicle
pathways.
Roundabout Intersections - Roundabout designs
generally have three or four legs joining a circular 404.03 INTERSECTION ANGLES
roadway. All traffic turns right to merge with
traffic in the roundabout. Traffic continues to A 90o intersection provides the shortest crossing
turn right through the circle to eliminate through for intersecting traffic and provides the most
and left turn movements. Roundabout designs are favorable condition for drivers to judge the
characterized by light traffic volumes and slow relative position and speed of approaching
speeds through the intersection. The roundabout vehicles. The minimum desirable intersection
intersection is a design that can be used in lieu of angle is 75 degrees. Intersection angles less than
the traditional three or four leg intersections. For 60 degrees should be realigned.
further descriptions and types see Part 2, Section
407, Roundabout Design. 404.04 POINTS OF CONFLICT

404 CHANNELIZATION Points of conflict occur when drivers paths cross.


The highest number of conflicts occur at
Channelization is the separation of traffic into intersections. For example, a driver making a
definite travel paths using pavement markings or left turn on to a roadway must cross right-bound
raised islands. Channelization should be used to: traffic and merge into the left-bound traffic

Part 2 400-2
ROADWAY DESIGN MANUAL Roads and Bridges

stream. That single maneuver causes conflict 404.08 PROHIBITED TURNS


with both directions of travel. Where ever
possible, points of conflict should be reduced so Traffic islands may be used to divert traffic
drivers are only exposed to one conflict or streams in desired directions and prevent specific
decision at a time. This can be done by using undesirable movements.
stop signs, traffic signals, grade separations, and
channelization. Channelization separates and 404.09 EFFECTIVE SIGNAL CONTROL
clearly defines points of conflict within the
intersection. At intersections with complex turning
movements, channelization is required for
Channelization separates and clearly defines effective signal control. Channelization enables
points of conflict within the intersection. Drivers sorting and storing of approach traffic for orderly
should be exposed to only one conflict or movement through the intersection during
confronted with one decision at a time. separate signal phases. Channelization is
particularly effective when used with traffic-
404.05 SPEED-CHANGE LANES actuated signal controls.

Speed-change lanes improve intersection safety 404.10 INSTALLATION OF TRAFFIC


and efficiency. Entering traffic merges most CONTROL DEVICES
efficiently with through traffic when the merging
angle is less than 15o and speed differentials are Traffic islands enhance the effectiveness of, and
at a minimum. provide space for, traffic control devices such as
signals and signs. Dimensions and clearances for
Speed change lanes for diverging traffic should traffic control devices should be considered when
permit vehicles to decelerate after leaving the sizing traffic islands.
through lanes.
404.11 GUIDELINES
404.06 TURNING MOVEMENTS
Striping is preferable to curbed islands,
A separate right turning lane removes turning especially adjacent to high-speed traffic
movements from the intersection area, increasing where curbing can be an obstruction to out-
safety and capacity. Also adding dedicated left of-control vehicles.
turn lanes removes left turn traffic from the thru
lanes which also increases safety and capacity. Where curbing must be used, first
Abrupt changes in alignment or sight distance consideration should be given to mountable
should be avoided. curbs. Barrier curbs should only be used
where pedestrian protection is a primary
404.07 REFUGE AREAS concern.

Properly sized traffic islands can provide refuge Avoid complex intersections that present
for vehicles and pedestrians. The shadowing multiple movement options or decisions.
effect of islands provides refuge for vehicles
waiting to cross or enter an uncontrolled traffic Accident records provide a valuable guide to
stream. the type of channelization needed.

Channelization can also provide a safer crossing The Standard Drawings include details for a
of two or more traffic streams by permitting channelized free right turn and typical
drivers to select adequate gaps in one traffic pavement markings at intersections.
stream at a time. Channelization should also
provide ample storage for vehicles to make the
turning or crossing movements.

Part 2 400-3
ROADWAY DESIGN MANUAL Roads and Bridges

405 DESIGN VEHICLES

405.01 OFF TRACKING Approach Sight Triangle - The area bounded


by the required sight distances along the
A vehicle traveling around a circular curve intersection legs and the sight line connecting
sweeps a wider path than the width of the their ends is known as the "sight triangle". See
vehicle. The difference between the swept width Figure 400.04.
and the vehicle width is called off tracking. On
large trucks and buses offtracking can be Unobstructed sight distance along all intersection
significant and must be considered in design. approaches and across the included corners must
be sufficient to permit operators of approaching
405.02 DESIGN VEHICLES vehicles to perceive each other, react and
complete an appropriate accelerating, slowing or
Intersection geometric design depends on the stopping maneuver. If all corners of the
dimensional and operational characteristics of the intersection cannot be cleared and maintained to
vehicles involved. The American Association of provide unobstructed views in the approach sight
State Highway and Transportation Officials have triangle, the intersection shall have stop control
adopted "design vehicles" representing the various imposed.
classes of commonly used vehicles.
Departure Sight Triangle - The departure sight
For freeways and expressways, the design vehicle triangle is bounded by the location of the stopped
shall be a WB-12 medium tractor semi-trailer driver, the appropriate sight distance along the
combination. For arterials, collectors and sector intersecting road, and the connecting sight line.
roads, the design vehicle will be a single unit bus. See Figure 400.04. The driver must have
Design vehicles are as defined in A Policy on sufficient sight distance along the intersecting
Geometric Design of Highways and Streets, legs to make a safe departure movement. All
AASHTO, 1994. Dimensions for various design corners of the intersection shall be constructed to
vehicles are shown in Figure 400.02. provide a clear line of sight throughout the
departing sight triangle.
405.03 TURNING TEMPLATES
Intersection Controls - The following controls
Turning templates are used to locate the turning apply to at-grade intersections.
paths of large vehicles. The template is used to
determine corner radii, position island noses, No Control - vehicles need sufficient sight
establish clearances and the width of channeled distance to adjust their speed.
separate turning lanes. Turning templates for the Yield Control - Vehicles on minor roadway
various design vehicles are shown in Figure yield to vehicles on major roadway.
400.03. It should be noted that state-of-the-art Stop Control - Vehicles on minor roadway
turning template computer software exists which stop at major roadway.
can be used in-lieu of Figure 400.03. Signal Control - All legs are controlled by
either stop signs or traffic signals.
406 INTERSECTION DESIGN Left-turn Control - Stopped left-turning
STANDARDS vehicles on minor roadway must yield to
opposing vehicles on major roadway.
406.01 SIGHT DISTANCE
No Control - For a given speed, the approach
General - The Driver of a vehicle should have an sight triangle is determined from Figure 400.04
unobstructed view of the entire intersection. and Table 400.01. Departure sight triangles
Stopping sight distance shall be the minimum should be commensurate with those provided at
provided throughout all parts of intersections. stop controlled intersections.

Part 2 400-4
ROADWAY DESIGN MANUAL Roads and Bridges

Table 400.01 Stop Control - Adequate sight distance must be


Sight Triangle Distances provided so a driver traveling at the design speed
No Intersection Control can perceive and safely stop at the stop sign.
Vehicle Speed (kph) Distance (m) Once stopped, the driver must have adequate sight
20 20 distance on the major road to permit safe
30 25 departure movements.
40 35
50 40 The three basic departure movements are:
60 50
70 60 To travel across the intersecting roadway,
80 65
clearing oncoming traffic in both directions;
90 75
100 85 To turn left onto the intersecting roadway,
110 90 clearing oncoming traffic from the left and
120 100 entering the traffic stream coming from the
The sight triangle dimensions are determined using right;
these distances per Figure 400.04 for No Control. To turn right onto the intersecting roadway
These distances are based on level roadways. by entering the traffic stream coming from the
left.

Yield Control - Approach sight triangles should


be provided at all intersection corners. Minimum
sight distances provided along the legs should be
at least stopping sight distance. For departure
sight triangles see Stop Control.

Part 2 400-5
ROADWAY DESIGN MANUAL Roads and Bridges

Figure 400.02
Design Vehicle Dimensions

Part 2 400-6
ROADWAY DESIGN MANUAL Roads and Bridges

This turning template shows the turning paths of the specified AASHTO design vehicle. The paths shown
are for the left front overhang and the outside rear wheel. The left front wheel follows the circular curve,
however, its path is not shown.

Figure 400.03
Minimum Turning Path for P Design Vehicles
From AASHTO, 1994, A Policy on Geometric Design of Highways and Streets

Part 2 400-7
ROADWAY DESIGN MANUAL Roads and Bridges

FOR APPROACHING VEHICLE

FOR DEPARTING VEHICLE

Figure 400.04
Intersection Sight Triangles
Part 2 400-8
ROADWAY DESIGN MANUAL Roads and Bridges

Stop Control with Crossing Maneuver -


Crossing maneuver sight distance is based on the
time it takes for the stopped vehicle to clear the
intersection and the distance travelled in that time
by an oncoming vehicle on the cross road. The
distance may be calculated from

d = 0.28V(2.0+ta)

where: d = sight distance required along


the major roadway from the
intersection (m).
V = design speed on the major
roadway (kph)
ta = time required to accelerate and
traverse the distance to clear
the major roadway travelled
way (s)

The solid line curves in Figure 400.05 labeled


P, SU and WB-15 are the recommended
vehicle time-distance relationships to compute ta.
If significant grades are present, ta should be
adjusted per Table 400.02.

The distance that a crossing vehicle travels to


clear a major roadway is:

S = D+W+L
Figure 400.05
where: D = distance from near edge-of- Sight Distance at Intersections Acceleration
travelled way to the front of a from Stop.
stopped vehicle (typically 3.0 From AASHTO, 1004, A Policy on Geometric
m). Design of Highways and Streets
W = travelled way width along path
of crossing vehicle (m)
L = overall length of vehicle (m)

Calculated sight distance shall be checked against


stopping sight distance. The larger of the
distances shall be used.

Part 2 400-9
ROADWAY DESIGN MANUAL Roads and Bridges

Turning Left Onto a Major Roadway - requirement for the right-turn maneuver is
Because it takes longer to turn and accelerate to approximately one meter less than that required
operating speed than to go straight across an for the left-turn maneuver in Turning Left Onto
intersecting roadway, the critical sight distances a Major Roadway. See Figure 400.07 curve Cb
are those required for turning movements. The for the required sight distance for a vehicle
driver must have sufficient sight distance to the turning right and accelerating to 85 percent of the
left to cross the near lanes(s) without interfering design speed before being overtaken by vehicles
with oncoming traffic. The driver must also have slowing to 85 percent of design speed. Trucks
sufficient sight distance to the right to turn left will take considerably longer than passenger
and accelerate to a speed where oncoming traffic vehicles.
is not significantly impaired.
Signal Control - Because of unanticipated
The sight distance required to the left are vehicle conflicts at signalized intersections, (such
calculated from: as, signal violations, right-turns on red, signal
malfunction, or use of flashing red/yellow mode)
dL = 0.28V(2.0+ta) the requirements for Stop Controlled
intersections should be met. At intersections
where: dL = sight distance required to the where right-turns on red are permitted, the
left along the major roadway departure sight line for right-turning vehicles
from the intersection (m). should be determined by the methods for
V = design speed on the major Turning Right into a Major Roadway."
roadway (kph)
ta = time required to accelerate and Stopped Vehicle Turning Left from a Major
traverse the distance to clear Roadway - The driver will need sufficient sight
the traffic in the lane distance ahead to turn left and clear the opposing
approaching from the left. travel lane(s) before an approaching vehicle
reaches the intersection. The sight distance
The required sight distance to the right is based required is calculated from:
on the assumption that the mainline vehicle will
slow to 85 percent of the design speed and d = 0.28V(2.0+ta)
maintain a 2.0 second gap from the turning
vehicle. To calculate the necessary sight distance where: d = sight distance required along
first determine from Figure 400.06 the distance P the major roadway from the
required for the turning vehicle to reach a speed intersection (m).
of 85 percent of the mainline design speed. The V = design speed on the major
sight distance required to the right is calculated roadway (kph)
from: ta = time required to accelerate and
traverse the distance to clear
dR = (t+2)(.28)(.95V) - (P-5- the traffic in the approaching
(.56)(.85V) - Lv) lane.
where: dR = Sight distance required to 406.02 EFFECT OF SKEW
the right along the major
roadway from the Intersection skew has no effect on sight distance
intersection (m). requirements since they are measured along the
T = time required to travel intersecting legs. However, the sight triangle
distance P (Table 400.01). configuration is affected by skew. Care should be
V = mainline design speed taken to verify that the area within the sight
(kph) triangles can be constructed and maintained to
Lv = Vehicle Length (m) provide a unobstructed view throughout the sight
triangle with a 1070 mm eye height on the minor
Turning Right Onto a Major Roadway - The road to a 1300 mm object height on the major
right-turning-vehicle must have sufficient sight road.
distance to the left to complete its turn and
accelerate to a predetermined speed before being Skew also affects the distance a vehicle travels to
overtaken by approaching traffic travelling at the cross the intersection. Heavily skewed
same predetermined speed. The sight distance intersections should be controlled.
Part 2 400-10
ROADWAY DESIGN MANUAL Roads and Bridges

Figure 400.06
Acceleration Curves
From AASHTO, 1994, A Policy on Geometric Design of Highways and Streets

Part 2 400-11
ROADWAY DESIGN MANUAL Roads and Bridges

Figure 400.07
Intersection Sight Distances
For turning onto a major roadway AASHTO, 1994,
A Policy on Geometric Design of Highways and Streets

Part 2 400-12
ROADWAY DESIGN MANUAL Roads and Bridges

406.03 EFFECT OF VERTICAL be 3.65 m. Three meter wide left-turn lanes may
PROFILES be used on low speed urban roadways. The width
is measured from the adjacent edge of travelled
A vehicle descending a grade requires greater way, excluding shy distance.
stopping distance than one on level ground.
Conversely, a vehicle ascending a grade requires Medians - To improve left-turn visibility, the left-
less distance to stop. Grades up to 3 percent have turn-lane should be placed as far to the left as
little effect on stopping sight distances. In no case possible in the median leaving only the painted or
should the grades exceed 6 percent. curbed nose. Excess width between the left-turn
lane and the adjacent same-direction through lane
For Stop Controlled intersections, the time should be treated as painted island. When left-
required to cross a roadway is affected by the turn lanes are placed in raised (curbed) medians,
crossing grade. If the grade is significant, the a minimum nose width of 1.0 m should remain for
sight distance should be increased. pedestrian refuge and traffic control devices.

Where the intersection leg grades are other than Approach Tapers - On roadways with narrow or
flat, corrections should be made to the sight no medians, room for the left-turn lane is made by
distances using the approximate ratios given in shifting traffic laterally to the right. The taper
Table 400.02. length used to effect this shift should be 0.6WV,
where W = lateral shift (m) and V = design speed
Table 400.02 (kph).
ta Adjustment For Grade
Sight Triangle Distances Bay Tapers - The bay taper length should be
Ratio, ta on grade / ta level (Figure 400.05) short to clearly identify the additional lane.
Generally the taper length should be 15:1.
Crossroad Grade %
Deceleration Length - Whenever feasible, the
Design Vehicle -4 -2 0 2 4 left-turn lane should provide deceleration clear of
P 0.7 0.9 1.0 1.1 1.3 the through lanes. The minimum deceleration
SU 0.8 0.9 1.0 1.1 1.3 lengths, exclusive of bay taper and vehicle
WB-15 0.8 0.9 1.0 1.2 1.7 storage, for 50, 60 and 80 kph are 70, 100 and
130 m, respectively.
Use this table to adjust ta values for effect of
grade. Based on the likely range of crossing In urban areas, it may not be possible to provide
distances. the deceleration lengths and maintain the storage
and approach taper lengths required. In these
situations, these lengths should be used as a
406.04 LEFT-TURN
desirable goal.
CHANNELIZATION

General - A left-turn lane expedites through Storage Length - The storage length should be
sufficient:
traffic flow, controls turning traffic movement,
and improves the intersection safety and capacity.
To store the number of vehicles during
The left-turn lane should be laid out such that the critical periods.
turning vehicle must make a definite move to To avoid left-turning vehicles stopping in the
enter the lane. The desirable length of the left-turn through lanes.
lane is the sum of the required storage length and So the lane entrance is not blocked by
deceleration length, including the bay taper standing through traffic.
length.
Refer to the Highway Capacity Manual, Special
Width - The desirable left-turn lane width should Report No. 209, Transportation Research
Board, 1986 for further discussion.
Part 2 400-13
ROADWAY DESIGN MANUAL Roads and Bridges

406.05 RIGHT-TURN Storage Length - Storage requirements and goals


CHANNELIZATION are the same as for left-turns.

General - Right-turn lanes improve intersection Free Right-Turns - Uncontrolled free right-
capacity and safety. As for left-turn lanes, right- turns improve capacity of an intersection with a
turn lanes should be laid out such that a right- heavy right-turn demand. The right-turn is made
turning vehicle must make a definite move to "free" by channelizing the turning movement
enter the lane. outside of the intersection controls. Free right-
turns shall only be provided where the turning
The desirable length of the right-turn lane is the movement can be made into an auxiliary or
sum of storage requirements and deceleration acceleration lane.
length, including bay taper.
406.06 TRAFFIC ISLANDS
Width - The desirable right-turn lane width
should be 3.65 m. Three meter wide right-turn General - Traffic islands are located between
lanes may be used on low speed urban roadways. traffic lanes and are commonly designated using
The width is measured from the adjacent edge of paint, raised pavement markers, or curbs. They
travelled way, excluding shy distance. serve to:

The normal shoulder should be provided at the confine specific traffic movements into
right-turn lane although, if right of way is definite channels;
severely constrained, a minimum 1.2 m wide separate traffic moving in the same or
shoulder may be used. The normal curb should be opposite direction;
carried through the right-turn section. aid and protect pedestrians crossing the
intersection; and,
Approach Tapers - Generally right-turn lane discourage or prohibit undesirable
approach tapers are not required because the lane movements.
is added to the outside of the travelled way and
the travel lanes are not shifted. However, if the Design - Traffic islands must be large enough to
travel lanes must be shifted to accommodate a be seen and to command the attention of the
right-turn lane, the taper should be the same as driver. Islands for channelizing should preferably
for left-turn lanes. be at least 9.0 m2. Curbed islands for separating
traffic streams should not be less than 1.0 m wide
Bay Tapers - The bay taper which guides the and 8.0 m long.
motorist into the right-turn lane is a straight line
along the right edge of the travelled way. Curbed islands should be offset from the through
Generally the taper length should be 15:1. traffic lanes by a minimum shy distance of 0.6 m
and 0.9 m is preferable for approach speeds
Deceleration Length - Whenever feasible, the greater than 25 kph.
right-turn lane should provide deceleration clear
of the through lanes. The minimum deceleration The approach end of a curbed island should be
lengths, exclusive of bay taper and vehicle rounded at 0.5 to 1.0 m radius and tapered at 15:1
storage, for 50, 60 and 80 kph are 70, 100 and to guide the driver into the channelization.
130 m, respectively.
Where there is an approach shoulder (1.2 m or
In urban areas, it may not be possible to provide wider), the curbed island should be offset from
the deceleration lengths and maintain the storage the through lane by the width of the shoulder.
and approach taper lengths required. In these With an approach shoulder the flared approach is
situations, these lengths should be used as a not necessary, except where a deceleration or
desirable goal. turning lane has been provided.

Part 2 400-14
ROADWAY DESIGN MANUAL Roads and Bridges

Avoid curbed traffic islands where the approach roundabout. For these reasons roundabouts
operating speeds are 80 kph or greater. tend to be removed and replaced with
Mountable curbs should be used at curbed islands conventional signalized intersections instead
except where barrier curbs are provided for of being modified.
greater pedestrian protection. Roundabouts require more land than
conventional intersections.
407 ROUNDABOUT DESIGN Roundabouts are not well suited for
pedestrian traffic, because pedestrians are not
There are three main types of roundabouts, able to walk in a clear path through the
Normal, Mini and Double. There are other forms intersection. In areas of high pedestrian
of roundabouts but they variations of these basic traffic, pedestrians can cause major problems
types. They are Ring Junctions, Grade Separated with illegal crossings.
and Signalized Roundabouts. More information
about the use and design of these and other Normal Roundabouts: The normal
roundabouts can be found in the Geometric configuration of a roundabout is made up of a
Design of Roundabouts. When reading this one-way road around a circular curbed island 4m
design manual the designer should be aware that or more in diameter. The approaches are usually
the manual was written for left-hand running flared to allow multiple vehicle entries. The
traffic and appropriate modifications should be number of entries should be limited to three or
made for when adapting these standards to right- four arms. The efficiency and driver
hand running traffic patterns. comprehension decreases as the number of arms
is increased. The minimum radius of curvature
The roundabout is used at intersecting streets with also increases with additional arms which can
low capacity and low design speed. Roundabouts raise circulatory speeds. Double roundabouts can
should be considered when they are cost effective be an alternative under these conditions. See
or increase safety over standard intersection Figure 400.08.
designs.

Advantages: There are several advantages to


roundabout design versus conventional three and
four leg intersections.
Roundabouts are more efficient than signals
on balanced traffic demand intersections.
Roundabouts allow for continuous traffic
flow.
Roundabouts can reduce traffic speeds in
existing intersections.

Disadvantages: There are several disadvantages


to roundabouts that make them less favorable
than conventional designs. Figure 400.08
Driver comprehension to right-of-way with Normal Roundabout
respect to yielding to traffic flow.
Mini Roundabouts: The mini-roundabout is
Roundabouts are prone to large congestion
similar to the normal roundabout except the
problems when traffic exceeds design
diameter of the island is less than 4m. Instead of
capacity.
a curbed island a raised, reflectorized dome is
It is difficult to redesign an existing
used for driver recognition of the high spot. The
roundabout to increase its capacity. Redesign
mini-roundabout is a good alternative for existing
requires adding more lanes which greatly
roads with extremely low traffic volumes that
increases the land required for the
have high safety and delay problems. Where
intersection. This increase in diameter also
physical deflection of approaching traffic is not
increases the design speed through the
Part 2 400-15
ROADWAY DESIGN MANUAL Roads and Bridges

possible, roadway stripping and traffic islands


may be used. See Figure 400.09.

Figure 400.09 Figure 400.10


Mini Roundabout Double Roundabout

Double Roundabouts: Double roundabouts are


generally used in areas with unique traffic
requirements such as:
Where intersection improvements are done
and the roundabout eliminates the need to
realign an approach road.
In areas where more than four arms are
entering the intersection.
At intersections with unusual or asymmetrical
configurations.
Where single island configurations do not
have enough capacity.
The joining of parallel roads separated by an
existing feature.

These unique circumstances should be evaluated


by an experienced traffic engineer and the
Municipality must be informed on the decision to
consider a double roundabout. The double
roundabout should only be used after proper
consideration and is contingent only with the
approval of experienced personnel and the
Municipality. See Figure 400.10.

Part 2 400-16
ROADWAY DESIGN MANUAL Roads and Bridges

SECTION 500
INTERCHANGES 503 DESIGN CONSIDERATIONS

Due to the complex nature of interchange design


501 GENERAL
it is important to establish a set of consistent
design parameters. Listed below are features
The ability to accommodate high traffic volumes
which should be considered during the
safely and efficiently through intersections
interchange design process.
depends on how intersecting traffic is handled.
The greatest efficiency, safety, and capacity are
Provide consistent design features.
attained when intersecting through traffic lanes
are physically separated. An interchange does Ramp exits shall be from the right.
this with a combination of ramps and grade Ramp entrances shall be on the right.
separations at the junction of two or more One exit per direction from main roadway.
roadways. This reduces or eliminates traffic Ramp design speed beyond exit should
conflicts, improves safety, and increases traffic preferably be one-half to two-thirds that of
capacity. Crossing conflicts are eliminated by the roadway.
grade separations and turning conflicts are Provide ramps for return or complementary
eliminated or minimized depending on the traffic movements at same interchange.
interchange configuration. Use grades and slopes as flat as possible.
Consider signing during geometric design.
The selection and design of grade separations
and interchanges is influenced by roadway 504 INTERCHANGE TYPES
classification, traffic volume, traffic composition,
design speed, access control, signing This section includes examples of commonly
requirements, economics, terrain, right-of-way, used interchange configurations. See Chapter X
capacity and safety. Interchange types vary of "A Policy on Geometric Design of Highways
widely so each site should be studied and and Streets," AASHTO, 1994, for additional
alternate concepts made to determine the examples.
appropriate layout.
504.01 THREE-LEG INTERCHANGE
502 INTERCHANGE WARRANTS
Three-leg interchanges have three intersecting
Interchanges are very costly and should be used legs. They usually consist of one or more
only where necessary. Interchanges should be roadway grade separations and one-way
considered based on the following warrants: roadways for all traffic movements. Because
future expansion is difficult, three-leg
Where intersecting traffic volumes are interchanges should only be used when one of
heavy. the three legs is permanently terminated. Heavy
Where topography does not lend itself to the traffic volume should be favored with more
construction of an intersection. direct alignments, and lesser volumes can be
When making a connection to a freeway. looped. Skewed crossings are desirable because
For a roadway with access control between travel distance is less, the turning radius is flatter
selected terminals. for the heavier left-turning volume and there is
To eliminate a traffic bottleneck. less angle of turn for both left turns.
To eliminate a hazardous at-grade
intersection. Figure 500.01 illustrates several types of three
leg interchanges.
When road-user benefits are substantial.

Part 2 500-1
ROADWAY DESIGN MANUAL Roads and Bridges

Figure -500.01
Three-Leg Interchanges
From AASHTO, 1994," A Policy on Geometric Design of Highways and Streets".

Part 2 500-2
ROADWAY DESIGN MANUAL Roads and Bridges

504.02 FOUR-LEG INTERCHANGES Comparatively low construction cost.


Direct cross road turning maneuvers.
Four-leg interchanges include diamond Single exit feature simplifies expressway
interchanges, full cloverleaves, partial signing.
cloverleaves (parclo), and interchanges with No need for speed change lanes on or under
direct and semidirect connections. Each basic the structure.
interchange type is described and discussed in No weaving on the expressway.
the following sections.
Disadvantages -
Diamond Interchange Overall capacity is limited by ramp
intersection capacity.
Diamond interchanges are the most commonly Capacity is lowered on the minor road due
used interchange (Figure 500.02). They consist to left turning movements.
of four ramps which parallel the main roadway, Increased accident potential unless
providing all eight turning movements. signalized.
Possibility of wrong-way movements.
Turning traffic from the expressway is
obliged to stop at the minor road. Storage
lane treatment may be required.
Little possibility for future expansion.

Single Point Diamond Interchange


The Single Point Interchange (SPI) is also known
as an urban interchange or a single point
diamond interchange (Figure 500.03). All four
turning movements are controlled by a single
traffic signal and opposing left turns cross to the
left of each other.

Figure 500.02
Simple Diamond

Application - The diamond is used at


major/minor roadway crossings with direct high
speed exit/entrance ramps on the major roadway
and at-grade intersections on the minor roadway.

It is adaptable to a wide range of traffic volumes


and capacity may be increased by widening the
ramps and cross road in the intersection area by
providing storage lanes, two-lane left turns,
channelization, and traffic signals at the ramp
cross road intersections.

Advantages -
High design standard single exits in advance
Figure 500.03
of the structure.
Single Point Diamond Interchange
High design standard single entrances
beyond the structure.
Requires relatively little right-of-way.
Part 2 500-3
ROADWAY DESIGN MANUAL Roads and Bridges

Application - Best suited for areas where right-


of-way is restricted.

Advantages
Relatively narrow right-of-way.
Opposing left turns pass to the left of each
other.
Traffic signal is three-phase rather than four.
Operates with a single traffic signal reducing
delay through the ramp intersection.
Handles high volume left-turns on the cross
road more efficiently than a diamond.
Curve radii for left-turn movements through
the intersection are significantly flatter than
at conventional intersections, and therefore
the left turns move at higher speeds.
Higher capacity than a conventional tight
diamond interchange.
Figure 500.04
Disadvantages - Cloverleaf
Higher construction cost than a conventional
tight diamond interchange.
Extensive retaining walls required where Advantages -
right-of-way is restricted. Left-turn conflicts eliminated
Vehicle path through the intersection Single structure design.
requires, at a minimum, a painted guidance Traffic signals are unnecessary.
stripe. Lends itself to stage construction.
Not suitable for skewed interchanges.
Adding pedestrian movement to the Disadvantages -
interchange adds a signal phase and reduces Large right-of-way requirements.
efficiency. Weaving may severely limit capacity.
Adding weaving lanes on and under structure
Cloverleaf
increase cost.
High weave volumes require collector
The cloverleaf is a four-leg interchange that uses
distributor roads.
loop ramps to eliminate the four left-turn
movements and uses outer ramps for the four Double exit on the expressway complicates
right-turn movements (Figure 500.04). An signing.
interchange with loops in all quadrants is referred Insufficient deceleration length from
to as "full cloverleaf" and all others as a "partial expressway speed to control speed of inner
cloverleaf (parclo)". loop.
Poor safety features.
Application - Where there is a need to avoid Extra travel distance/time required for left
restrictive at-grade left turns and adequate right turns.
of way is available. Large trucks may experience problems with
tight curves.

Part 2 500-4
ROADWAY DESIGN MANUAL Roads and Bridges

Cloverleaf with Collector Distributor Road Disadvantages -


May require more right of way than basic
A collector distributor road in conjunction with a cloverleaf.
cloverleaf removes the weaving ramp traffic Higher structure costs than basic cloverleaf
from the main roadway (Figure 500.05). due to greater span.
Signing is more complicated than basic
clover leaf

Partial Cloverleaf (Parclo)

A partial clover leaf is a portion of the full clover


leaf design. Ramps should be arranged so that the
entrance and exit turning movements create the
least impediment to major roadway traffic flows.
The general parclo interchange applications,
advantages and disadvantages are given below.
Figures 500.06 through 500.10 show several
parclo arrangements and lists their relative
advantages and disadvantages.

Application - This interchange is suitable for


locations where by removing two left-turn
movements from the intersections the remaining
left-turn conflicts can be tolerated.

General Advantages -
Suitable for stage construction.
Figure 500.05
Cloverleaf with Collector Distributor Road Exit terminals in advance of structure.
Weaving eliminated.
Single exit simplifies signing.
Application - Same as for basic cloverleaf except Expandable if structure opening wide
is more suitable for areas with high weaving enough.
volumes. Can be configured to optimize traffic
volume/capacity.
Advantages - Future expansion if structure opening wide
Minimizes weaving conflicts by placing enough.
weave on collector distributor road.
Minimizes signing difficulties. General Disadvantages -
Provides a single exit and entrance from Minor road has stop condition for left-turn.
main roadway. Minor road may require left-turn storage.
Reduce merging and diverging points on Points of conflict on the minor roadway at
main roadway. the ramp terminals limit capacity and safety.
Higher volume than basic cloverleaf design. Right-turn expressway traffic stops at minor
roadway.

Part 2 500-5
ROADWAY DESIGN MANUAL Roads and Bridges

Figure 500.06 Figure 500.09

Advantages - Disadvantages -
Entrance ramp loops. Stop condition on minor road and ramps for
Disadvantages - left turns.
Stop condition on minor road and ramps for Expressway traffic exits onto small radius
left turns. loop.

Figure 500.07 Figure 500.10

Advantages - Advantages -
Stop for left-turns confined to movements Stop condition for left turns confined to
from ramps only. movements from minor roadway only.
Entrance ramp loops. Not conducive to wrong-way movements.

Disadvantages -
Expressway traffic exits onto small radius
loop.

Directional Interchanges
A direct connection is defined as a one-way
roadway that does not deviate greatly from -the
intended direction of travel. Interchanges that
use direct connections for the major left-turn
movements are termed directional interchanges
(Figure 500.11). Direct connections for one or
Figure 500.08 all left-turn movements would qualify an
interchange to be termed directional even if the
Disadvantages - minor left turn movements are accommodated on
Stop condition on minor road and ramps for loops.
left turns.
Expressway traffic exits onto small radius
loop.
Entrance/exit loops

Part 2 500-6
ROADWAY DESIGN MANUAL Roads and Bridges

Directional interchanges have one or more grade


separations with direct or semidirect ramp
connections for one or more left turning
movements. Free flow is provided for high
turning traffic volumes in one or two quadrants
comparable in volume to through traffic.
When one or more interchange connections are
indirect in alignment yet more direct than loops,
the interchange is described as semi-directional.
All left-turn connections or only those that
accommodate major left-turn movements may be
semi-direct in alignment.
The most widely used type of directional
interchange is the four-level layout system
shown in Figure 500.11A. A variation of this
type is the four-level interchange with two exits
from both major roadways, as shown in Figure
500.11B.
Chapter X of "A Policy on Geometric Design of
Highways and Streets," AASHTO, 1994, has
additional examples of directional interchanges.
Application - Semi-direct or direct connections
for one or more left-turning movements are often
required at major interchanges in urban areas.
Interchanges involving two freeways nearly
always call for directional layouts. In such cases
turning movements in one or two quadrants often
are comparable in volume to through
movements.
Advantages -
Reduced travel distance.
Increased speed and capacity.
Weaving eliminated.
Avoids the indirection in driving on a loop.
Higher levels of service . Figure 500.11
Require little right of way. Directional Interchanges

Disadvantages -
High construction costs.
Require detailed, time-consuming study.

Part 2 500-7
ROADWAY DESIGN MANUAL Roads and Bridges

consistent with the design speed for the roadways


505 INTERCHANGE DESIGN and driving conditions expected.
PROCEDURES
Spacing - Minimum interchange spacing is
General - Since interchanges are so costly, and a determined by weaving volumes, ability to sign,
vital element of freeway capacity it is important signal progression, and required lengths of speed
that a well functioning, economic design be change lanes. Interchange spacing has a
conceived. In general, alternative interchange pronounced effect on freeway operation. In
schemes should be analyzed and several general, minimum spacing shall be:
preferred alternatives should be selected based
on geometry, capacity, signing, aesthetics, Rural Urban
environmental compatibility, overall adaptability, 3.0 km 1.5 km
route continuity, route uniformity, maintaining
traffic during construction, suitability to stage
construction, right-of-way requirements and the Uniformity - To the extent practicable all
effect on the local road and roadway network. interchanges along a freeway should be uniform
in geometric layout and general appearance. All
From these preferred alternatives, preliminary entrance and exit ramps shall be on the right.
plans, profiles and cost estimates should be
prepared. Include costs for right-of way, Signing and Marking - Signs, pavement
construction, maintenance, and other appropriate striping, delineators and other markings should
items. Once this data has been prepared, the best conform to the Manual on Uniform Traffic
interchange design concept can be selected. Control Devices (MUTCD).

506 INTERCHANGE DESIGN Basic Number of Lanes - Design traffic


STANDARDS volumes and a capacity analysis should be used
to determine the basic number of roadway lanes
An interchange consists of the through freeway, and the minimum number of ramp lanes. The
the ramps and the cross road. This section deals basic number of lanes should be established for a
primarily with the interchange as a whole. substantial length of freeway and should not be
Specific designs for ramps are discussed in the changed through pairs of interchanges.
sections that follow.
Auxiliary Lanes - An auxiliary lane is defined
Sight Distance - Stopping sight distance shall be as the portion of the roadway adjoining the
the minimum sight distance provided on the travelled way for emergency stopping, speed
respective roadways through an interchange and change, turning, turning storage, weaving, truck
preferably longer. Decision sight distance shall climbing, and other purposes supplementary to
be provided at exits. Sight distance requirements through-traffic movement.
are discussed in Part 2, Section 300, Geometric
Cross Section. An auxiliary lane may be needed when:
interchanges are closely spaced.
For minimum radius curves, the normal lateral the distance between the end of the taper on
clearance may not provide minimum stopping the entrance terminal and the beginning of
sight distance because piers, abutments and the taper on the exit terminal is short.
bridge rail limit horizontal sight distance. If a local frontage roads do not exist.
flatter curve cannot be used, the clearances necessary for lane balance.
should be increased to obtain the proper sight necessary for capacity requirements.
distance even though it is necessary to increase necessary for weaving.
structure spans or widths.
An auxiliary lane may be introduced as a single
Design Speed Considerations - In the design of exclusive lane or in conjunction with a two-lane
interchanges it is important to provide vertical entrance. Auxiliary lanes may be dropped in a
and horizontal alignment standards which are single or two-lane exit or carried to the physical
gore nose before tapering into the through

Part 2 500-8
ROADWAY DESIGN MANUAL Roads and Bridges

roadway. Auxiliary lanes may be tapered or Table 500.01


parallel and shall be a minimum of 3.65 m wide. Ramp Entrance/Exit Design Speed
Lane Reduction - The basic number of freeway Freeway Design Speed Ramp Design Speed
lanes may be reduced if the exit volume is large kph kph
enough to change the basic number of lanes 140 100
required beyond the reduction point for the 120 85
freeway as a whole. 100 70

The reduction may be made at a two-lane exit These speeds do not apply to ramp terminals,
ramp or between interchanges. The lane-drop which should be designed using the intersecting
taper should be on a horizontal tangent on the roadway speed.
approach side of a crest vertical curve, or on a
sag vertical curve. The lane reduction shall be Profile - A typical ramp profile consists of the
made on the right using a desirable taper rate of ramp body on an appreciable grade, between
70:1 (minimum taper rate of 50:1). vertical curves that connect to the intersection
legs. The profile at the ramp terminal is
Weaving Sections - Weaving sections are generally determined by the cross road.
roadway segments where vehicles entering and
leaving at adjacent access points cross each Ramp grades should be as flat as feasible. Down
others paths. Weaving sections reduce grades should be limited to 3 or 4 percent on
interchange capacity and should be eliminated ramps with sharp horizontal curvature and
from the main facility where feasible. Refer to significant heavy truck or bus traffic. However,
the Highway Capacity Manual for further sight distance is more important than a specific
discussion on weaving sections. gradient control and should be favored in design.
As general criteria, it is desirable that ascending
507 RAMP DESIGN STANDARDS gradients on ramps be limited to:

General - A ramp is typically a one-way Table 500.02


roadway connecting interchange legs. Ramps Ramp Grades
consist of three main parts. The ramp freeway Ramp Ramp
entrance or exit, the ramp body and the ramp Design Speed Gradient
intersection with the cross road. The intersection kph %
with the freeway is called the ramp entrance or 70-80 3-5
exit and the intersection with the cross roads is 60 4-6
typically defined as the ramp terminal. 40-50 5-7
30-40 6-8
This section deals mainly with general ramp
design criteria. Specific ramp entrance/exit and
terminal designs are discussed separately in the Curvature - The factors and assumptions of
following sections. minimum-turning roadway curves for various
speeds apply to ramps and are discussed in
Design Speed - Ramp design speed varies based Section 200.
on location along the ramp. The freeway
entrance or exit design speed approximates the Sight Distance - The minimum sight distance
freeway design speed. The ramp terminal design provided anywhere along the ramp shall be
speed usually approximates that of the cross road stopping sight distance. See the sections on
if there is no stop condition. The design speed freeway entrance/exit ramp and ramp terminals
for the ramp body transitions from the freeway for specific requirements at those areas.
design speed to the terminal design speed. See
typical examples in Table 500.01. Shoulder Width - Shoulder widths for ramps
shall be as indicated in Part 2, Section 300,
Geometric Cross Section.

Part 2 500-9
ROADWAY DESIGN MANUAL Roads and Bridges

Gores - The term "gore" indicates an area Lane Drops - Typically the ramp lane reduction
downstream from the shoulder intersection points shall be made using a desirable taper rate of 70:1,
as illustrated in Figure 500.12. The gore nose is 50:1 maximum.
defined as that point where the distance
measured between the main line and ramp Lane drop tapers should not extend beyond the 2
travelled ways is 7.0 m. If feasible, the unpaved meter point (the beginning of the weaving
area beyond the nose should be graded level with length) without the provision of an auxiliary
the roadways. Heavy sign supports, street lights, lane.
and roadway structure supports shall be kept out
of the graded gore area. Lane Additions - Lane additions to ramps shall
use a taper rate of 10:1.
Profile grade considerations are of particular
concern through entrance and exit gore areas. In Superelevation And Cross Slope - The factors
some instances the ramp profile, or the controlling superelevation rates discussed in Part
combination of profile and cross slope, is 2, Section 200, Geometric Design Standards,
sufficiently different from the freeway through apply to ramps. Ramp superelevation rates shall
lanes that grade breaks across the gore become be per Table 200.04.
necessary. Where adjacent lanes or lanes and
gore areas at freeway entrances and exits are not Where feasible, the curve radius should be
in the same plane, the algebraic difference in increased to reduce the required standard
pavement cross slope shall not exceed 5%. superelevation rate. Both the edge of travelled
way and the edge of shoulder should be
examined at ramp junctions to assure a smooth
transition.

Figure 500.12
Typical Gore Area
From AASHTO, 1994, A Policy on Geometric Design of Highways and Streets

Part 2 500-10
ROADWAY DESIGN MANUAL Roads and Bridges

Widening - Where ramps have curve radii of 90 facilitate acceleration and merging. Where the
m or less with a central angle greater than 60 loop ramp has a small radius on a steep descent
degrees the lane furthest to the right of the ramp, (over 6%), it is important to develop the standard
shall be widened in accordance with Table 2/3 full superelevation rate by the beginning of
500.03 in order to accommodate large truck the curve. On loop entrance ramps this can often
wheel paths. More than one lane may be be facilitated by beginning the ramp with a short
widened if warranted by truck and bus usage. tangent (20 m to 30 m) that diverges from the
cross street at an angle of 4 to 9 degrees. Longer
Table 500.03 tangents are desirable.
Ramp Widening For Trucks
Distance Between Successive On-Ramps - The
Ramp Radius Widening Lane Width minimum distance between two successive
(m) (m) (m) freeway on-ramps should be the distance needed
<40 2.0 5.6 to provide the standard on-ramp acceleration
40 - 44 1.6 5.2 taper shown on Figure 500.13. This distance
45 - 54 1.3 4.9 should be about 300 m. If the upstream ramp
55 - 64 0.9 4.5 adds an auxiliary lane, the downstream ramp
65 - 74 0.6 4.2 should merge with the auxiliary lane. The
75 - 90 0.3 3.9 distance between on-ramp noses will then be
>90 0 3.6 controlled by interchange geometry.
For ramps having curve radii of 90 m or less
with a central angle greater than 60 degrees. Distance Between Successive Exits - The
minimum distance between successive exit
ramps for guide signing should be 300 m on the
Normally, loop ramps are one lane unless
freeway and 180 m on collector-distributor roads.
capacity warrants additional lanes.
Consideration should be given to providing a
directional ramp when loop volumes exceed 508 ENTRANCE/ EXIT RAMP
1500 vehicles per hour. If multiple lanes are DESIGN STANDARDS
provided, normally only the right lane needs to
be widened. General - The ramp entrance/exit is that ramp
portion adjacent to the through travelled way,
Loop Ramps - Radii for loop ramps should including speed-change lanes, tapers, and
normally range from 45 m to 60 m. Increasing islands. All freeway entrances and exits shall
the radii beyond 60 m is typically not cost connect to the right of through traffic. The
effective as the slight increase in design speed is following paragraphs discuss various design
usually outweighed by the increased right of way elements of ramp entrances/exits.
requirements and the increased travel distance.
For roadway design speeds greater than 80 kph Entrance/Exit Sight Distance - Decision sight
the loop design speed should not be less than 40 distance is desirable along the freeway prior to
kph (45 m radius). Extremely tight curves (less an exit nose and the entire exit terminal should
than 35 m radii) should be avoided because they be visible.
lead to increased off-tracking and increase the
potential for vehicles to enter the curve with When an exit must be located where visibility is
excessive speed. See Table 200.05 for further limited by physical restrictions which cannot be
guidelines on radius versus design speed. corrected by cut widening or object removal, an
auxiliary lane in advance of the exit should be
Research indicates that trucks often enter loops provided. The minimum length of auxiliary lane
with excessive speed, either due to inadequate shall be 300 m desirable, 180 m minimum.
deceleration on exit ramps or due to driver
efforts to maintain speed on entrance ramps to

Part 2 500-11
ROADWAY DESIGN MANUAL Roads and Bridges

Figure 500.13
Single Lane Freeway Entrances and Exits
From Caltrans, 1995, Highway Design Manual

Part 2 500-12
ROADWAY DESIGN MANUAL Roads and Bridges

Exit Design Speed - The minimum design speed Two-Lane Exit Ramps - Where design year
at the exit nose should be 80 kph or greater for estimated volumes exceed 1500 equivalent
both ramps and branch connections. Decision passenger cars per hour, a 2-lane exit per Figure
sight distance should be provided at freeway 500.14 should be used. A minimum 400 m
exits and branch connectors. auxiliary lane should be provided in advance of a
two-lane exit. Provisions should also be made
Entrance Design Speed - The design speed at for widening to three or more lanes at the cross
the nose should be consistent with approach road intersection.
alignment standards. If the approach is a branch
connection or diamond ramp with high alignment For volumes less than 1500 but more than 900, a
standards, the minimum design speed should be one-lane width exit ramp should be provided
80 kph. with provision for adding an auxiliary lane and
an additional lane on the ramp.
Entrance/Exit Designs - Design of freeway
entrances and exits should conform to the Branch Connections - A branch connection
standard designs in Figures 500.13, 500.14, and should be provided when the design year volume
500.15 for single lane, two lane entrances and exceeds 1500 equivalent passenger cars per hour.
exits, and diverging branch connections,
respectively. A branch connection is defined as a Merging branch connections should be designed
multilane connection between two freeways. as shown in Figure 500.14. Diverging branch
connections should be designed as shown in
The minimum deceleration length shown on Figure 500.15. The standard ramp exit connects
Figure 500.13 shall be provided prior to the first to a local street. The diverging branch
curve beyond the exit nose. This provides for connection connects to another freeway and has a
adequate deceleration before entering the curve. flatter angle that allows a higher departure speed.
When the subsequent curve is a descending loop
or hook ramp, or if the upstream condition is a At a branch merge, an 800 m length of auxiliary
sustained downgrade, deceleration length should lane should be provided beyond the merge of one
be increased. (see AASHTO, A Policy on lane of the inlet, except where it does not appear
Geometric Design of Highways and Streets, that capacity on the freeway will be reached until
1994, Chap. X for additional information). five or more years after the 20 year design
period. In this case the length of auxiliary lane
Single-lane Freeway to Freeway Connections should be a minimum of 300 m. For diverging
Freeway-to-freeway connectors may be single connections where less than capacity conditions
lane or multilane. Where design year volume is beyond the design year are anticipated, the length
between 900 and 1500 equivalent passenger cars of auxiliary lane in advance of the exit should be
per hour, initial construction should provide a 400 m.
single lane connection with the capability of
adding an additional lane. Single lane directional Branch Lane Drops - The lane drop taper on a
connectors should be designed using the general freeway-to-freeway connector shall not be less
configurations shown on Figure 500.13, but than 70:1.
utilizing the flatter diverge angle shown in Figure
500.15. Single lane loop connectors may use a
diverge angle of as much as that shown on Figure
500.13 for ramps, if necessary. The choice will
depend upon interchange configuration and
driver expectancy. Single-lane connectors in
excess of 300 m in length should be widened to
two lanes to provide for passing maneuvers.

Part 2 500-13
ROADWAY DESIGN MANUAL Roads and Bridges

Figure 500.14
Two-Lane Entrance and Exit Ramps
From Caltrans, 1995, Highway Design Manual
Part 2 500-14
ROADWAY DESIGN MANUAL Roads and Bridges

Figure 500.15
Diverging Branch Connections
From Caltrans, 1995, Highway Design Manual

Part 2 500-15
ROADWAY DESIGN MANUAL Roads and Bridges

Two-Lane Entrance Ramps - A standard two On curved entrance ramps the distance from the
lane entrance ramp is illustrated in Figure inlet nose (4.25 m point) to the end of the
500.14. This design may be utilized in situations acceleration lane taper should equal the sum of
where the estimated design year volume exceeds the distances shown on Figure 500.13 The 50:1
1500 equivalent passenger cars per hour. Figure taper may be curved to fit the conditions, and the
500.14 includes a minimum 300 m auxiliary lane 1000 m radius curve may be adjusted.
parallel to the freeway, which is only used where
adequate design year capacity exists on the Entrance/ Exit Grades - Grades for freeway
through facility. If capacity is inadequate, entrances and exits are controlled primarily by
consideration should be given to extending the sight distance requirements. Ramp profile grades
auxiliary lane to the next interchange or adding should not exceed 6%.
additional freeway through lanes. For most
Exit Profiles - Vertical curves located just
urban situations, it is recommended that multiple
beyond the exit nose should be designed with a
ramp lanes taper to a single lane prior to the 2-
minimum 80 kph stopping sight distance.
meter separation point (where merging is
Beyond this point, progressively lower design
considered to begin).
speeds may be used to accommodate loop ramps
Entrance/Exit Locations - Freeway entrances and other geometric features.
and exits should be located on tangent sections
Entrance Profiles - Entrance profiles should
wherever possible. This provides maximum
approximately parallel the freeway profile for at
sight distance and optimum traffic operation.
least 30 m prior to the inlet nose to provide
Where it is necessary to locate entrances/exits on intervisibility in merging situations. The vertical
a curve, the ramp entrances and exit tapers curve at the inlet nose should be consistent with
should also be curved. The exit taper radius approach alignment standards.
should approximate the freeway edge of travelled
Where large-truck volumes exceed 20 vehicles
way in order to develop the standard degree of
per hour on ascending entrance ramps with
divergence (Figure 500.16).
sustained upgrades exceeding 2%, a minimum
450 m long auxiliary lane should be provided to
insure satisfactory separating conditions.
Exit Ramp Transitions - Exit ramps in urban
areas may require additional lanes at the cross
road intersection to provide storage and increase
capacity.
If the length of a single lane ramp exceeds 300
m, an additional lane should be provided on the
ramp to permit passing maneuvers.
508.01 RAMP TERMINAL DESIGN
The ramp terminal is defined as the area where
the ramp meets the cross road.
Terminals - Ramp terminals should be treated as
at-grade intersections. The terminal design shall
be per Part 2, Section 400, At-Grade
Intersections, based on near-minimum turning
conditions.

Figure 500.16 Terminal Grades - Ascending off-ramps should


Curved Entrance/Exit Locations join the cross roads on a reasonably flat grade to
From Caltrans, 1995, Highway Design Manual expedite truck starts from a stopped condition.
Ramp terminals should connect where the grade

Part 2 500-16
ROADWAY DESIGN MANUAL Roads and Bridges

of the over crossing is 4% or less to avoid movements are allowed within 125 m of the
potential overturning of trucks. ramp intersection.
Terminal Locations - Factors which influence Terminal Sight Distances Horizontal sight
the location of ramp terminals include sight restrictions may be caused by bridge railings,
distance, construction costs, right of way costs, bridge piers, or slopes. Sight distance is
circuitry of travel for left-turn movements, measured between the center of the outside lane
crossroads gradient at ramp intersections, storage approaching the ramp and the eye of the driver of
requirements for left-turn movements off the the ramp vehicle assumed 3.0 m back from the
crossroads, and the proximity of other local road edge of shoulder at the crossroads. Figure
intersections. 500.17 illustrates ramp setback from an over
crossing structure. This figure is based on sight
Where a separate right turn lane is provided at distance being controlled by the bridge rail, but
ramp terminals the turn lane should not continue the same relationship exists for sight distance
as a "free" right unless pedestrian volumes are controlled by bridge piers or slopes.
low, the right turn lane continues as a separate
full width lane for at least 60 m prior to merging, Where ramp set back is unobtainable, sight
and access control is maintained for at least 60 m distance shall be provided by flaring the end of
past the ramp intersection. Provision of the the overcrossing structures or setting back the
"free" right should also be precluded if left turn piers or end slopes of an undercrossing structure.

Figure 500.17
Ramp Setback
From Caltrans, 1995, Highway Design Manual

Part 2 500-17
ROADWAY DESIGN MANUAL Roads and Bridges

SECTION 600 may be obtained through the Abu Dhabi


Municipality Road Section as well as other
GEOTECHNICAL ENGINEERING
Municipality and Government Agencies.

601 INTRODUCTION The geotechnical report is to contain the


information shown in Table 600.01 as a
The first part of this section is intended to give an minimum.
overview of what is required in a geotechnical
report used for roadway and structural design. It Table 600.01
does not cover the specific methods of testing, GEOTECHNICAL REPORT
sampling or analysis required. Standard SI Table of Contents
practices and the Municipality Roads Section
Guidelines for Subsurface Investigations for Civil Introduction
Engineering Purposes current revision should be Location Map
used for guidance in this area. Proposed Construction
Previous Information and/or Investigations
The second part of this section outlines the Field Investigation And Laboratory Testing
pavement design procedure. Include Boring Location Plan
Site and Subsurface Conditions
602 GENERAL Climate
Significant Geotechnical Features
The Consultant shall obtain approval from the Regional Geology and Seismicity
Road Section, Traffic Police and any other Analysis and Recommendations
concerned Agencies prior to commencing a Retaining Wall Recommendations
geotechnical investigation. Excavation and Ground Compaction
Factors
Generally a geotechnical investigation is carried Expected Settlements
out in two phases. The initial phase consists of Groundwater Observations
preliminary drilling and testing to gather enough Allowable Foundation Loads
project specific information to advance the Foundation Recommendations
roadway and structure design. The final stage, if
Borrow/Material Source
required, is performed for design features
Slope Stability
requiring specific geotechnical recommendations.
Soil Corrosivity to Buried Structures
Subgrade Support for Pavement Design
603 GEOTECHNICAL REPORT
Topsoil Plating Recommendations
Once the preliminary horizontal and vertical Treatment for Problem Soils
alignment and structure locations have been Any Relevant Geotechnical Aspects
defined, the engineer will prepare a preliminary a Affecting Future Performance of the
subsurface exploration and testing program. Works
Providing information such as foundation types, Appendices
safe slope angles and preliminary pavement Boring Logs
thickness allows the initial design to be advanced Summary of Test Results
and refined. The initial program also identifies Other Pertinent Information
the type, severity and extent of any geotechnical
design problems. Pertinent information should be included in the
appendices. In certain circumstances, such as a
The geotechnical report should consist of results major bridge design or other major structure, an
and recommendations from the initial drilling and additional report may be required to define special
testing program as well as any information from geotechnical aspects of foundation design.
prior investigations. Prior investigations and data

Part 2 600-1
ROADWAY DESIGN MANUAL Roads and Bridges

604 STRUCTURAL PAVEMENT The advantage of the phenomenological approach


SECTION DESIGN is that one does not need to spend resources on
measurement of input variables. The advantage
of the analytical approach, however, is that
604.01 GENERAL
conditions outside the experience of the designer
can be designed for by selecting the appropriate
604.01.01 Pavement Design Methods
input variables.
Pavement design is a challenging process because
Actual pavement design methods fall somewhere
the analytical framework for design is so
between these two extremes. Field and laboratory
complex. Complexity is introduced both by the
investigation of pavement properties and
number of materials involved and the number of
performance over the last 20 to 30 years have led
variables required for design. The pavement
to semi-analytical methods based on observations.
section itself consists of a surfacing material and
The many input variables are introduced either
several supporting layers. The strengths and
through equations developed by regression or
moduli of these layers vary through several orders
equations developed from first principles.
of magnitude, and at least the lowest layer (native
subgrade) is best described by non-linear
The TRIP pavement design method was based on
constitutive models. These factors by themselves
the interim AASHTO method developed in the
make development of equations which control
late 1970s. The approach to pavement design has
even simple material behaviors such as deflection
advanced considerably since that time. In order
under load extremely non-trivial.
to take advantage of these advances several state-
of-the art pavement design methods were
The problem is exacerbated by the sheer number
evaluated against the TRIP method for use in the
of variables which ought to be considered. The
Municipality.
pavement is influenced by the soil upon which the
pavement is supported, the number of vehicles
The interim AASHTO method, upon which TRIP
expected to pass over the pavement, the weight of
was based, was developed from the results of
the vehicles which pass over, the spatial
observations of roadway performance on test beds
arrangement of the tires which support that
in the midwestern United States. This method
weight, the tire pressure, the material properties
was widely regarded as the best compromise
of the pavement section materials, the temperature
between observation and analysis available in the
and temperature range, the moisture condition of
late 1970's. However, because of its origins
the subgrade, the likelihood of freeze-and-thaw
primarily in the Midwestern United States, the
cycles, and probably several more. Many of these
applicability of the method to other climates was
variables are extremely difficult to evaluate. The
questioned. Further, the characterization of the
soil conditions under the pavement is evaluated at
soil support was relatively unsophisticated, and
only a few points, and the weakest points are
there was no way to directly treat the desired level
statistically likely to be missed. Traffic
of confidence in the design. Economic analysis
predictions are notoriously complicated and
based on life-cycle was not explicitly
inaccurate. Furthermore, pavement failure is very
incorporated. The method included no means for
difficult to define, as there are many possible
representing the statistical validity of the soil
failure modes. The analytical process underlying
sampling or the traffic design. AASHTO
each failure mode is different.
continued researching the performance of
pavements in the road test site to correct these
Generally speaking, there is a spectrum of design
problems after 1972. This research primarily
approaches which could be taken, ranging from
consisted of more detailed monitoring of the test
polar extremes of purely analytical methods to
road beds, to allow better correlations to be
purely phenomenological methods.
drawn amongst more parameters than were
included in the original method.

Part 2 600-2
ROADWAY DESIGN MANUAL Roads and Bridges

In 1986, a major modification was released which The last significant change was in the input
provided a significantly more sophisticated design parameter to use for describing the supporting
and analysis tool. The improvements primarily soil strength. In the 1986 edition, the soil is
were in the areas of failure definition, statistical characterized by the resilient modulus instead of
treatment, and soil characterization. the more nebulous soil support number used in
the 1972 interim method. The resilient modulus
Performance and failure concerns were is a measure of the soil behavior after thousands
incorporated in the 1986 edition by virtue of then of load repetitions, and has come to be widely
longer term monitoring of the pavement sections regarded as the most accurate characterization
in the original test. Pavement condition was variable for pavement design. Climate is directly
added through the Pavement Serviceability Index included in the resilient modulus determination
(PSI), a qualitative evaluation of ride condition through the boundary values used for the test.
using a Likert-type scale. Using this approach, it
is possible to select the amount of condition AASHTO released the final method in 1993. The
change which constitutes failure. A model was most significant changes in the intervening years
developed which linked the change in the (1986-1993) concerned the design method for
pavement condition over time to the usage and overlays and rehabilitation. A major evaluation
environment of the roadway. In addition to of the performance of the design method and its
providing more performance-based design, this underlying assumptions is currently underway in
improvement also allowed life cycle cost analysis. the United States, as part of the Strategic
Highway Research Program (SHRP). This
The underlying concept of life-cycle analysis is to analysis includes detailed observation of nearly
select a pavement solution for the transportation 800 test sections scattered across all parts of the
corridor, rather than for the pavement itself. United States, and an assessment of the ability of
Simply put, the idea is to consider pavement the AASHTO method to predict serviceability and
systems with a lower initial cost (perhaps due to performance. Preliminary results (SHRP, 1994)
thinner pavement) and a higher maintenance cost indicate that while traffic loadings are notoriously
(including overlays) alongside methods with under-predicted (a non-conservative error), the
higher initial costs and lower maintenance costs. results are to some extent offset by severe under-
Because of the serviceability index concept, one prediction of field moduli in the laboratory
can keep track of the changing pavement resilient modulus test (a conservative error). The
performance with time, and thereby determine the major change that is expected in the future will be
timing of major maintenance for economic direct analysis of each potential failure mode,
analyses. Most modern pavement design methods rather than the serviceability approach currently
utilize some form of life cycle analysis. in use, which lumps together many different
failure modes.
Also new in the 1986 interim AASHTO method
was treatment of statistical variability. The The AASHTO method has been modified by
statistical variability of the input parameters and many individual state departments of
pavement performance are incorporated through transportation in the United States. The Arizona
two factors- reliability and standard deviation. Department of Transportation method (ADOT,
The reliability factor accounts for chance 1992) is optimized for the hot climate of the
variation in traffic prediction and performance by southwestern United States. The method is very
allowing the selection of a degree of confidence similar to the AASHTO method, but deals more
that the design will last the design period. The explicitly with the statistical variability of the
higher the desired degree of confidence in the underlying soils. The resilient modulus is the
design, the thicker the pavement. The standard operative soil characterization variable, although
deviation factor accounts for statistical variability due to difficulty in measurement of the resilient
in the input parameters, particularly the traffic modulus ADOT uses a correlation with the
predictions. Hveem Resistance Value (R-value).

Part 2 600-3
ROADWAY DESIGN MANUAL Roads and Bridges

Another method of potential interest is that used same input variables, then one method can be said
by the Ministry of Communications of the to yield a substantially more conservative design
Kingdom of Saudi Arabia (MOC). This is a than the other. In the current case, we will
relatively simple method to apply, in which the compare the SN value for the original TRIP
soil is characterized by the CBR, and the traffic method with the newer design methods using a
by a 16-kip equivalent single axle loading. consistent set of material coefficients.
Design charts are then entered to perform the
actual design. roads are placed into two A SN was developed for each roadway
categories ("Expressways" and "Roads Other classification pavement section described in the
Than Expressways"), allowing some treatment of DCIL TRIP report. The TRIP SN are compared
the desired level of reliability. to the SN resulting from each pavement design
method used in this study in Table 600.02.
Each of these methods incorporates all of the
variables described in the beginning of this Table 600.02
section, with the primary difference being the Comparison of Structural Numbers for
degree to which these variables are explicitly Multiple Design Methods
incorporated in the analytical portion of the
Design Truck Freeway Main Sector
analysis. In general, one can characterize the
Method Route Expressway Road Road
AASHTO method as closest to the analytical end
TRIP 8.40 7.28 5.69 3.31
of the spectrum, and the MOC method as closest
AASHTO 7.9-9.5 7.3-8.9 5.6-6.8 2.8-3.7
to the phenomenological end of the spectrum.
ADOT 7.27 6.90 4.91 2.50
There are methods which are even more heavily
MOC * * * 4.69
weighted towards analysis, but these are most
commonly used for research rather than practice.
The methods described herein are considered *Traffic values too far beyond the range of design
representative of many methods in common use charts to allow extrapolation.
today, and are illustrative of the important factors
in pavement design. The AASHTO results show a range because of
the correlation from CBR to resilient modulus
604.01.02 Comparison of Design Results required for the AASHTO method. A design
CBR of 10 was used for the TRIP design. In
Calculations were performed using the newest order to correlate CBR to resilient modulus,
AASHTO method, the ADOT method, and the AASHTO recommends the equation:
MOC method and compared with the TRIP
method. In order to simplify direct comparison of Mr = 1500(CBR) (Eqn. 1)
results, the comparison was based on Structural
Numbers (SN) which result from each analysis, where-
rather than on a comparison of the pavement Mr = Resilient Modulus (psi)
sections themselves. This approach was used
because the SN is the most useful design CBR = California Bearing Ratio
descriptor which results from the procedures, and
because it is independent of the individual Equation 1 was used to develop the lower SN's
pavement layer components chosen by a given shown in Table 600.02. However, there was
agency. considerable scatter in the correlation between the
CBR and the resilient modulus, with the
High traffic, weak soil, or high degrees of conversion factor ranging to as low a value as
conservatism will all yield higher SN values, and 750. In the absence of actual measured resilient
this number thereby allows direct comparison of moduli with which to evaluate the applicability of
the results of an analysis for similar input the AASHTO conversion, a conservative
variables. For example, if two methods are used approach was adopted in which the design would
that generate vastly different SN values for the be checked with a lower resilient modulus

Part 2 600-4
ROADWAY DESIGN MANUAL Roads and Bridges

corresponding to the lower end of the AASHTO The 1993 AASHTO pavement design method has
correlation range: been used extensively in a variety of climates
across the United States and many other parts of
the world, and has been found to work effectively
Mr = 750(CBR) (Eqn. 2) in a wide range of conditions. The pavement
design method outlined below is based on the
The highest SN shown in each classification for 1993 AASHTO method with modifications
the AASHTO method results from a correlation tailored to local conditions.
to resilient modulus using Equation 2. This range
should capture the range of results likely to result The use of the AASHTO method will allow site
from actual resilient modulus testing. The ADOT specific treatment of individual roads within the
method, which is also based on resilient modulus, Municipality of special importance or roads
was completed using the correlation recommended outside the Municipality on less familiar or less
by AASHTO and presented here as Equation 1. uniform soils. The following method should be
used in conjunction with the 1993 AASHTO
The MOC method was only applicable for the method for all Municipality pavement designs.
lightest roadway classification, the Sector Road.
In every other case, the design equivalent axle 604.02 PAVEMENT DESIGN METHOD
loading for the TRIP roadways was well beyond
the inference space depicted on the MOC design Step 1: Develop Equivalent Single Axle Load,
thickness charts. This result comes about due to W18
the degree of overloading common on TRIP
roadways, rather than to an excessive number of Traffic is represented in the 1993 AASHTO
vehicles. The MOC method is based on a 16-kip method by the equivalent single axle load
axle load, requiring a large destructive effect (ESAL), or the number of 18-kip equivalent
factor when considering that up to 27-kip loads single axle loads that will pass over the pavement
were used in the TRIP report. during its initial service lifetime (typically 20
years). To calculate this value, three components
As can be seen from Table 600.02, there is some are required:
variation in the results based on the method used.
It is readily apparent that the TRIP thickness (1) the number of vehicles which will pass over
results are well within the range of modern the pavement during its lifetime, and
pavement design methods. The TRIP results are (2) the breakdown of those vehicles by weight
well above the ADOT methods and firmly within classification, and
the range of new AASHTO SN's. The method is (3) a means of converting the number of vehicles
non-conservative compared to the MOC method; in each class to an 18-kip equivalent single
however, this comparison is believed to result axle load.
largely from the large truck overloads leading to
huge traffic loadings compared to the 16-kip To estimate the total number of vehicles utilizing
single axle loadings used for design in the MOC. a pavement during its design life, existing and
projected traffic volumes are needed. To
The conclusion is that the major modifications to determine the total number of vehicles, use a
the AASHTO methods which have occurred since straight line interpolation between the existing
the original TRIP method was devised have not traffic volumes and traffic volumes of the design
significantly altered the designs which would be year. For existing pavement studies, calculate the
recommended if the same input variables were average rate between the existing traffic volume
used to start the design process today. The and the traffic volume of the design year. That
suitability of the input variables, both standard average rate is then multiplied by the projected
and road specific, is therefore the most design life of the pavement. For new pavements
appropriate question for the development of a new the number of vehicles would be estimated using
method. Of the methods examined, the 1993 the design period.
AASHTO method is the most appropriate choice.
Part 2 600-5
ROADWAY DESIGN MANUAL Roads and Bridges

The second component, the number of vehicles in Step 2: Develop soil resilient modulus, MR
certain weight classifications comes from detailed
counts of vehicle types in the traffic mix at a The resilient modulus of the soil subgrade is
variety of times and places within each roadway required for design and must be measured or
class. estimated. The AASHTO correlation below gives
reasonable agreement between the California
Finally, a means of converting the rough traffic Bearing Ratio (CBR) and the soil resilient
numbers, broken down by vehicle class, to the 18- modulus. Unless site specific investigations
kip equivalent single axle load is needed. The determine different resilient modulus-CBR
axle load equivalency factors used in the design correlation factors, the AASHTO correlation
method vary with the load on the axle, the type of should be used.
vehicle, and the pavement thickness. See the
AASHTO guidelines for a complete set of tables. Mr = 1500(CBR)
It should be noted that these tables do not reflect where:
the higher tire pressures that are often used in the Mr = Resilient Modulus (psi)
Municipality. However, the tabulated values still CBR = California Bearing Ratio
form a good starting place for equivalency
factors. For a simplified approach, the values in Step 3: Determine the overall standard
Table 600.03 form an acceptable interim deviation, So
approach:
The overall standard deviation is a dimensionless
Table 600.03 parameter that accounts for random variation in
Generic Equivalency Factors the traffic projections and normal variation in the
pavement parameters. Simply put, it provides a
Vehicle Type Equivalency Factor
means of accounting for areas of weaker than
Heavy Truck 6.5
average pavement receiving higher than expected
Medium Truck 1
traffic. A value of 0.45 for So is commonly used
Light Truck .25
for flexible pavement materials.
Automobile .0008
Step 4: Select the level of reliability, R
Using these values and counts or estimations of
traffic loading within the classifications, the The level of reliability describes the degree of
overall 18-kip equivalent single axle loading can certainty that the pavement will last as long as the
be estimated. The advantages of the AASHTO design service period. Statistically, the thicker the
equivalency factor approach outlined above are pavement section the higher the likelihood that the
that (a) the method can be used with very little pavement will last throughout its intended service
data about the traffic composition, or with very life, other factors being equal. The level of
detailed traffic counts; (b) most other methods reliability is represented in the AASHTO equation
require very detailed information about tire by the standard normal deviate, ZR, and in the
pressures, wheel configurations, and load layouts, design nomograph by R. Table 600.04 contains
information which would be even harder to come recommended values for the roadway
by than the traffic counts, and (c) the equivalency classifications. The table contains very
factors can be easily and directly incorporated conservative values to reflect the need for high
within the method. Ideally, detailed weight and performing pavements in a high-growth, low
composition data can be obtained to allow the maintenance management mode.
development of system-specific equivalency
factors, but the AASHTO factors can be used in
the meantime.

Part 2 600-6
ROADWAY DESIGN MANUAL Roads and Bridges

Step 6: Solve for the structural number, SN


Table 600.04
Reliability Parameters The preceding steps 1-5 were independent.
However, a value must be obtained for each one
Roadway Level of Standard
in order to complete step 6, solving for the
Classification Reliability, R Normal
structural number. The structural number can be
R Deviate, ZR
solved for using the equation below, using a trial-
Truck Route 99.9 -3.090
and-error procedure.
Rural/Urban 99.9 -3.090
Expressway 99.9 -3.090
log10W18 = (ZR )(So) + 9.36log10(SN + 1) - 0.20
Main Road 99.0 -2.327
Sector Road 95.0 -1.645 log10 PSI
4.2-1.5
+ + 2.32log10MR - 8.07
Step 5: Select design serviceability loss, PSI 1094
0.40 +
The pavement serviceability is a general measure (SN+1)5.19
of the pavements ability to service the traffic
which must pass over it. Serviceability ranges
from 0 (impassable) to 5 (ideal), and represents a Where:
quantification of subjective impressions about the W18 = Equivalent Single Axle load, Step 1
roadway quality. Note that a low serviceability MR = Soil Resilient modulus, Step 2
implies only that the road has become difficult to SO = Overall Standard Deviation , Step 3
travel over, and provides no information about the ZR = Standard Normal Deviate, Step 4
failure mode (e.g. rutting, stripping, cracking) PSI = Design Serviceability loss, Step 5
that has created the low serviceability. The
design serviceability loss (PSI) is the allowable Or the solution may be obtained by using the
change from the initial serviceability (po) to the nomograph in Figure 600.01 on page 600.10.
terminal serviceability at the end of the design
period (pt). The design serviceability loss is Step 7: Determine pavement and base
obtained by simply subtracting the final value thickness
from the initial value, and so describes the
amount of degradation of service which is Once determined from step 6, the structural
acceptable during the design lifetime. number is used to determine the thickness of each
Recommended values for the different roadway pavement material layer using the appropriate
classifications are shown in Table 600.05. material coefficients from Table 600.06.

Table 600.05 Table 600.06


Serviceability Parameters Pavement Material Coefficients
Roadway Initial Terminal Design Pavement Coefficient
Classification po pt Serviceability Material (per cm)
Loss, PSI ai
Truck Route 4.2 3.0 1.2 Asphaltic Concrete 0.17
Freeway 4.2 3.0 1.2 Aggregate Base 0.05
Expressway 4.2 3.0 1.2 Sand-Asphalt Base 0.08
Main Road 4.1 2.6 1.5 Soil Subbase 0.04
Sector Road 4.0 2.4 1.6

Part 2 600-7
ROADWAY DESIGN MANUAL Roads and Bridges

The structural number is related to the Anticipated Construction Problems -


coefficients as follows: Consideration should also be given to the
feasibility of the proposed design in regard to
SN = a1t1+a2t2+a3t3+...+antn standard construction methods.

where: Costs - Comparative costs provided in the


ai = material coefficient for each material pavement design procedure should be given
in the pavement section (Table consideration in the selection of the pavement
600.06). design. Consideration should also be given to
ti = thickness of each material in the maintenance cost.
pavement section (cm).
SN = Structural number desired for the Minimum Structural Number - AASHTO
pavement section (Step 6). design is based on traffic-induced fatigue failure.
Establishing a minimum design takes into account
Various combinations of pavement materials of such factors as ease of construction, maintenance,
various thickness are possible to meet or exceed a current practice or failure under the action of a
given structural number. Once the structural few heavy design loads. Table 600.07 should be
requirements are met the combination and used as a guide for minimum pavement design.
thickness of the individual pavement material
sections is based on such factors as aggregate Table 600.07
availability , aggregate size, cost of various Minimum Pavement Design
pavement materials, minimum recommended
Roadway Minimum Minimum
thickness, restrictions on overall thickness,
Classification Structural AC
number of lifts required. These factors are
Number Thickness (cm)
discussed in more detail below.
Truck Route 7.9 30
Freeway 6.9 28
Material Availability - Conservation of natural
Expressway 6.9 28
resources should be given considered in the
Main Road 4.9 21
evaluation of the pavement design, and in areas
Sector Road 2.5 11
where materials are scarce, availability should be
Low Volume 2.0 6
given considerable weight.
Additionally on layered sections using aggregate
Continuity of Pavement Type - To maintain
base, a minimum thickness of 20 cm shall be used
uniform driving conditions, consideration should
for the base material.
be given to continuing the same type of exiting
pavements, especially if a new project is relatively
short. This is assuming that the existing Normally, the pavement section which satisfies
pavements are satisfactory. the structural requirements and represents the
least cost would be selected. However, as
Location and Local Conditions - Although there previously discussed, there may be times when the
are many pavement designs that will meet the least cost design would not necessarily be the
requirements of the design equation, there are most appropriate design. The following page
situations when local conditions, such as contains an example of a typical flexible
underground utilities close to the surface, poor pavement design.
drainage, flooding, etc. where one design might
function more efficiently than another. Past
experience and judgement should be used in the
final selection of the pavement design.

Part 2 600-8
ROADWAY DESIGN MANUAL Roads and Bridges

EXAMPLE FLEXIBLE PAVEMENT DESIGN


Given the bold faced information, determine the pavement
materials and thickness required for a truck route.

Step 1 - Develop Equivalent Single Axle Load, W18


Vehicles
Breakdown Table 600.03
per W18
of Vehicles Vehicle Equivalency Factors
Lifetime
338502756 5% Heavy Truck 6.5 110013396
5% Medium Truck 1 16925138
5% Light Truck 0.25 4231284
85% Automobile 0.0008 230182
W18 = 131400000

Step 2 Develop soil resilient Modulus, Mr


Mr = 1500CBR
= 1500(10)
= 15000 psi

Step 3 Determine the overall standard deviation, So


So = 0.45 Typical

Step 4 Select the level of reliability, R


Truck Route, Table 600.04 R = 99.9 ZR = -3.090

Step 5 Select design serviceability loss, PSI


Table 600.05
po = 4.2
pt = 3.0
PSI = 1.2

Step 6 Solve for structural number, SN


SN =8.0

Step 7 - Determine Material Thickness


Table 600.06
Trial
Pavement Coefficient SN
Thickness
Material (per cm) Contribution
(per cm)
Asphaltic Concrete 0.17 30 5.1
Aggregate Base 0.05 22 1.1
Sand-Asphalt Base 0.08 0 0.0
Soil Subbase 0.04 45 1.8
Actual SN = 8.0

Note: Various material combinations can be compared economically to


determine the optimum design. Make certain thickness meet Table 600.07.

Part 2 600-9
ROADWAY DESIGN MANUAL Roads and Bridges

Figure 600.01

Part 2 600-10
ROADWAY DESIGN MANUAL Roads and Bridges

SECTION 700
DRAINAGE

701 GENERAL

Drainage is an important element of roadway


design. The objective of roadway drainage design
is to provide the necessary facilities which allow
the public the appropriate use of the roadway
during times of significant runoff and which
minimize the potential for adverse effects on
adjacent property and existing drainage patterns.
Toward this goal, roadway drainage design is to
minimize off-project impacts while maintaining
use of the roadway at an acceptable frequency of
protection.

There has been so much data and so many


guidelines written on the hydrologic and hydraulic
aspects in roadway design that it is impractical to
contain all the references within this manual. A
separate manual, ROADWAY DESIGN
MANUAL Drainage, has been prepared to
provide guidance and direction on the design of
the drainage components of roadway facilities.
Strict use of that manual does not replace sound
engineering judgment. The drainage design must
be undertaken by experienced drainage engineers
who are in responsible charge.

Part 2 700-1
ROADWAY DESIGN MANUAL Roads and Bridges

SECTION 800 The Departments objective is that Roadway and


Bridge projects are developed to include all
UTILITIES
required construction of utility protection,
relocation and installation by the Contractor.
801 GENERAL This provides for single source responsibility for
the procurement of materials, and the scheduling
Utilities are an important element of roadway of the proposed improvements; while minimizing
design, especially in an urban environment. disruption of services to the public. This concept
There are three categories of utility reduces Contractor delay claims and the time
improvements: required for advance utility works. The actual
timing and responsibility for construction of
Utility Protection- Existing utilities within the individual services will be determined on a project
project limits that have been determined to be by project basis.
geometrically compatible with the proposed
improvements; and are in good condition with an Although contained in a single set of construction
acceptable remaining service life; may remain in documents, there are normally several
place and must be protected from traffic loads Consultants involved in the preparation of
and maintenance operations. The traffic loads individual utility plans, specifications and BOQ.
consist of both construction loading and post- Several Municipality Departments use designated
construction vehicular loading. Consultants for the planning and design of their
respective services, as further described in
Utility Relocation- Existing utilities that are Section 804.01. The Roadway/Bridge Consultant
incompatible with the roadway geometrics will is responsible for overall coordination and
require relocation, which may extend beyond the packaging of the documents into a complete and
limits of the proposed improvement depending on comprehensive set of tender documents. The
connection requirements. Relocated utilities will parallel development of plans and specifications
be replaced in-kind with the same size or capacity by multiple Consultants must be continuously
as the existing utility. The existing capacity may monitored to avoid conflict and contradiction.
be undersized and require an increase in capacity
or other utility expansions or improvements may 802 UTILITY PLANNING
be require. Such an up grade or development
work must be requested by the responsible utility
The Utilities Section of the Town Planning
agency and approved by the Road Section before
Department is responsible for master planning
the design of the upgraded utility can be included
and coordination of utility services. Service
in the roadway project.
corridors will be reserved within each project for
utilities in accordance with the planning data
New Utilities- New service facilities that may be
obtained from the Utilities Section. The corridors
required to support growth within the typical 20-
are established based on the approved design
year design life of the proposed roadway
concept and reflect the anticipated growth and
improvements; may replace redundant or outdated
overall needs of the individual utility agencies.
facilities or are major trunk lines routed through
The agencies or Municipality department
the project corridor that serve a broader purpose.
responsible for the individual services are as
follows:
Utility planning begins in the preliminary design
phase and is a factor in the project scoping
Water - Water and Electricity Department
process that leads to identification of the final
(WED)
roadway geometrics. A thorough investigation of
Telephone and Telecommunications -
existing utility location and condition is
ETISILAT
undertaken as an early final design activity.
Drainage - Abu Dhabi Municipality Sanitary
Drainage Network Division

Part 2 800-1
ROADWAY DESIGN MANUAL Roads and Bridges

Electricity - Water and Electricity review and give final approval of the project
Department (WED) utility scope of works. The utility planning
Irrigation - Abu Dhabi Municipality process is depicted on Figure 800.01.
Agriculture Section
Sewer - Abu Dhabi Municipality Sewerage 803 SERVICE RESERVATIONS
Projects Committee.
Gas Line - Abu Dhabi National Oil The Departments objective is to locate all utility
Company. services in designated utility corridors or Service
Reservations. This policy applies to all projects
The Utilities Section will provide details on the including new construction and roadway
agency or department responsible for special widening. Service reserves are located for ease of
services such as oil and gas pipelines, 132 KV construction and maintenance and to minimize
and national defense systems. disruption or damage to permanent works caused
by future utility installations or maintenance
Information on existing utilities shall be obtained operations. The reserves are generally located
from the Town Planning Utilities Section, the outside the roadway pavement in parking or
individual Service (Utility) Departments and/or pedestrian areas that are surfaced with removable
the designated Consultant at the beginning of materials including interlocking tiles and precast
design work. This data will include: tile blocks, and asphalt pavements of reduced
thickness. Roadway crossings are perpendicular
Current Service Reservation Locations to the centerline and primarily concentrated at
Distribution of Services intersection locations. The design standards
As-built Drawings require construction of ducts for all existing,
Proposed Facility Plans proposed and future services that cross roadway
pavement. The utility corridors are defined in
This information shall be compiled and analyzed close coordination with the project geometrics and
to ascertain the status of each individual utility. the Town Planning Department. The reserves are
Utility data should be supplemented by field established within geometric criteria that is suited
investigation of the existing facilities including to the installation of pipelines and conduits.
surveys to record structure locations and pipe Alignments are as straight as possible and angle
invert elevations. Manual(by hand) excavation to points limited in severity with the degree of
locate services that are critical to the design deflection ideally corresponding to pipeline
should be performed as necessary. The fittings (22-1/2, 45 degrees).
Consultant will arrange coordination meetings
with the Service Departments to identify utilities The Standard Drawings show several different
to be protected, relocated to the service distributions of standard service reservations.
reservations and new service requirements. The Special reserves for any utilities other than those
service authority may also have plans or projects shown on the standard drawings (CCTV, 132
for utility improvements in progress within the KV, gas, oil.) shall be provided in each project
project limits. with specific approval from the Town Planning
Department. Project design drawings should show
Once the scope of the utility works has been a section view of these special service reserves
defined, the Consultant will prepare separate cost similar to that shown on standard drawings.
estimates of the utility works that are required Deviations from the standard distribution may be
due to conflict with proposed works and new warranted to:
facilities that are proposed for inclusion in the
project by the utility agencies. It is important to Accommodate existing utilities that would not
make a clear distinction between required works otherwise require relocation.
and facility upgrades, since this information will Suit the project geometrics.
be used to determine the extent of the utility Allow for constructability and/or maintenance
works to be included in the project and cost of service facilities with excessive width,
sharing responsibilities. The Department will diameter or depth.

Part 2 800-2
ROADWAY DESIGN MANUAL Roads and Bridges

The final Service Reservation distribution and Separate Plans and Specifications Prepared by
geometry requires the approval of the Town Utility Authority- WED(Electric) and
Planning Department. ETISILAT normally prepare design plans and
specifications for their facilities in-house. WED
804 UTILITY DESIGN develops schematic drawings and estimated
quantities for relocation, protection, salvage and
804.01 GENERAL supply of new cables for inclusion in the tender
documents. The drawings and Bill of Quantities
Utility design requirements will be defined on
are modified as necessary by the authority based
final determination of the scope of utility works
on the results of the manual excavation and issued
by the Department. The final design of each
to Construction. The Contractor will then
utility will proceed based on the existing utility
prepare fully detailed shop drawings for final
information and proposed facility requirements.
approval by the WED.
Refer to the Utilities Procedures Flow Chart,
Figure 800.01.
ETISILAT normally prepares detailed plans and
In general, rapid development, incomplete as-built specifications for the work based on their record
information and the harsh soil conditions make it drawings of the existing telephone system and the
difficult to determine the exact requirements for need for relocation or protection of plant impacted
each service line, especially minor branches and by the improvement project. These drawings are
connections, without the benefit of an extensive normally included with the tender documents.
manual excavation program to locate the utilities. Any necessary adjustments based on manual
As a result, this effort should be accomplished excavation will be done through the shop drawing
during the construction phase to enable process in construction.
preparation of detailed shop drawings that will
fully define the requirements for each utility. The Consultant Prepared Plans and Specifications-
procedure and specifications for this work are The prime Consultant for the improvement
oulined in the Standard Specifications. The project is required to prepare final design plans
tender documents are prepared based on the best and specifications for Surface Drainage, Lighting,
available information and may be limited to the Traffic Control and Drainage/Irrigation. The
major components of a particular service. This designs are prepared in consultation with the
procedure varies with the different utilities and agency or department and the drawings are
generally can be described under three categories: normally prepared as separate documents and
included with the project tender document
Separate Plans and Specifications Prepared by package. Any necessary adjustments based on
Agency Designated Consultant- WED(Water) manual excavation will be done through the shop
and Sanitary Drainage Network Section use a drawing process in construction.
designated Consultant for the design of facilities.
Final design plans, specifications and BOQ are 804.02 UTILITY PROTECTION
prepared as separate documents and included in
the project tender document package. The All utilities under the roadway must be protected.
drawings will indicate the existing facilities This protection will continue under all pavements
anticipated to be protected, relocated or and extend beyond the back of curb, edge of
abandoned as well as new pipeline requirements. shoulder or at the duct end wall constructed at the
Based on the results of the manual excavation, the end of the duct by 0.50 meters. The Standard
Contractor will prepare detailed shop drawings Drawings and General Specifications outline the
that include refinements and adjustments to the type of protection to be used for the various
tender drawings to reflect the conditions utilities consisting of three types:
encountered in the field. The shop drawings
require the approval of the designated Consultant Concrete Slab (Precast or Cast-in-Situ)
and the WED. Concrete Encasement
Split Sleeve Concrete Encased

Part 2 800-3
ROADWAY DESIGN MANUAL Roads and Bridges

These methods are designed to protect the utility conduits may be placed in split ducts and concrete
from induced traffic loading including encased.
construction equipment loads. The Consultant
should check that the depth of existing utilities is Duct bank ends are terminated outside the
sufficiently below the subgrade level to permanent pavement in a reinforced concrete end
accommodate the protection device. wall structure that allows access to the duct ends
without damaging the integrity of the structural
804.03 UTILITY RELOCATION pavement section. These are required at all
multiple duct service reserve crossings. The end
Utility relocation will generally be determined by wall design and details are included in the
the individual utility agency and is subject to Standard Drawings.
approval by the Municipality. Each agency will
supply their relocation design drawings for All duct crossing locations are to be marked in the
inclusion in the Project documents. These field with permanent markers as shown in the
drawings will then be reviewed by the Standard Drawings. These markers are placed at
Municipality to obtain their approval prior to the end of the duct or set in the top of the duct end
inclusion in the Tender Documents. No utilities wall concrete.
other than lighting, underground cables, and
irrigation pipes shall be installed along the central 804.05 UTILITY LOCATIONS
median parallel to the roadway. These lighting
cables and irrigation lines in the median shall be With the exception of lighting cable and irrigation
as close as possible to the curb to avoid distribution lines, there shall be no construction of
disturbance to the greenery. Quantities, except utility lines such as power distribution lines,
for relocation work designed by a designated water lines, sewer lines, storm waterlines or any
utility consultant, shall be calculated by the other lines in the central median of primary roads.
primary Consultant. WED(E) and ETISILAT Utilities of all kinds shall not be constructed
will supply respective relocation quantities. under main roadway asphalt pavement. Utility
lines can be installed in service reserves under
Supply of all the materials required for the sector roads or parking areas where asphalt
relocation works for electrical shall be included in pavement is reduced in thickness.
each contract. Removed and salvaged LV, 11
KV and 33 KV cables excluding joints from site 804.06 NON-DISRUPTIVE ROAD
can be reused for the relocation works if approved CROSSINGS
by the WED. Quantities for the supply and
salvage items shall be as estimated by the WED Utility crossings of completed permanent works,
for each project. All 132 KV cables required for especially Main Roads, Expressways and
the relocation work shall be new and shall be Freeways are to be avoided. Contingency ducts
supplied under each contract. or alternate routes should be used to
accommodate the service requirements whenever
804.04 CONTINGENCY DUCTS possible. When the crossing of primary roadways
is unavoidable, Department policy requires the
Contingency ducts are required at roadway design to specify non-disruptive methods(pipe
crossings for future services to be located in jacking) or tunneling to cross the facility. This
service reserves and at other specific locations should be a performance based specification to
established by the utility authority. Ducts are offer the Contractor flexibility in selecting the
installed where pavements with asphalt or non- equipment and methods.
removable pavers cross over the service reserve.

These ducts may be designed to accommodate


existing or proposed service facilities with spare
or reserve capacity for future (contingency)
installations. Existing facilities such as cables or

Part 2 800-4
ROADWAY DESIGN MANUAL Roads and Bridges

Existing Utility Data


Town Planning Utility Agency
Utilities Section As-Built Drawings
P Design Concept
L New Utility
A Determine Conflicts Geometric Adjustment
Requirements
N
N Define Utility Scope of Work
I Utility Agency
N Service Reserve Dwgs.
Approval
G Prepare Cost Estimates
Town Planning
Approval
Department Approval

D Utility Design Agency Design


E
Consultant Design
S
Coordination
I
G
N Tender Documents Designated Consultant

Notice of Intent

C Manual Excavation
O As-Built Drawings Tender Drawings
N
Existing Utility Shop Drawings
S
Agency Review
T Consultant Review
R
U Revised Design Drawings - RFC Designated Consultant
C Service Reservations
T
I Utility Works Shop Drawings
O Town Planning Approval Agency Approval
N
Resident Engineer Approval
Designated Consultant
Construction

Record Drawings

Figure 800.01
Utility Procedures Flow Chart

Part 2 800-5
ROADWAY DESIGN MANUAL Roads and Bridges

SECTION 900 3. Freeway weaving analysis.


4. Basic segments capacity and operational
TRAFFIC ENGINEERING
analysis.
5. Intersection capacity and operational
901 TRAFFIC OPERATIONAL analysis.
ANALYSIS
Signal warrant analysis shall be performed to
901.01 GENERAL determine the need for signals at an intersection.
Part 1, Section 200, Design Concept The Manual on Uniform Traffic Control Devices
Development, of this manual discusses traffic (MUTCD) signal warrants shall be used for this
counts and traffic projection methods suitable for purpose. All necessary traffic engineering studies
the design concept phase of a project. Part 2, required for signal warrants shall be conducted.
Section 200, Geometric Design Standards,
outlines the data required to develop a preliminary Where necessary, intersection simulation analysis
parking demand analysis for inclusion in the shall be performed using a microscopic
Design Concept Report. simulation program that models individual vehicle
flow. Optimal phasing/timing and coordination
Final design may require refinement of concept parameters shall be used in the above mentioned
data before a final traffic report can be operational and capacity analyses.
completed. Specific model updating may be
necessary to incorporate roadway network For interchanges, conceptual designs will be
changes and revised roadway classifications. assessed and recommendations provided for
modification. Interchange operational analyses
Model output shall be calibrated to reflect current shall be performed to assess alternative concepts
traffic trends by comparing the present actual once the general plans of the alternatives have
traffic volume to a current model run and been developed.
applying corrective adjustments to depict the
actual conditions. Lane configurations and the required turn-lane
storage shall be designated at all intersections,
Model output shall be refined, particularly ramp
furthermore, lane requirements of the freeway,
volume and intersection turning volumes, to
mainline, ramps, cross-streets and frontage roads.
balance the daily traffic volumes from network
The designations shall be a direct result of the
link to network link. Directional design hourly
analyses performed and shall be incorporated into
volumes shall be derived in a manner similar to
roadway and bridge design drawings.
the daily volume adjustments.

Sub-modeling computer programs should be used 902 SIGNALIZATION


to determine the roadway volumes associated with
the proposed frontage roads and other roadway 902.01 TRAFFIC SIGNAL DESIGN
characteristics not incorporated in the original
model. Traffic signal phase and phase interval sequence
diagrams shall be provided for intersections and
901.02 OPERATIONAL ANALYSIS interchange ramp terminals. The signal system
design shall include the following:
The final traffic report should include an
operational analyses utilizing the balanced traffic Signal pole locations
volumes determined from the traffic forecasts. Mast arm orientation and lengths
The analysis will follow procedures and methods Signal head locations on mast arms and poles
of the Highway Capacity Manual, By the
Signal face types
Transportation Research Board and will include:
Conduits (ducts) location, including spares
Local Signal Controller and Changeover
1. Ramp intersection capacity analysis.
Switch foundations locations
2. Ramp merge/diverge analysis.

Part 2 900-1
ROADWAY DESIGN MANUAL Roads and Bridges

Red Violation Camera Loops and foundations A signal head shall be comprised of one signal
locations face only. Typical signal locations shall be as
Closed Circuit Television (CCTV) Poles and follows:
CCTV Controller foundations locations
Pedestrian signals locations and placement 1. A minimum of one signal face shall be
Free Right Turn signal foundation locations provided for each separate vehicular
Pullboxes types and locations movement and a minimum of two signal faces
Cabling requirements and terminations shall be provided for each through or major
Grades for system conduits (ducts) and movement.
location of system detectors 2. Vehicular signals shall be placed in such a
way so as to provide clear visibility to
Local intersection inductive detector loops
approaching traffic. They shall be located no
requirement, design and locations
less than 12 m or no greater than 35 m
Master Controller foundation requirement and
beyond the stopline.
location
Supplemental signal heads shall be used only
Phasing information should be used as a guide in
when warranted, and after a detailed study of the
determining which phases and interval sequences
location is conducted.
shall be provided at a specific location. New
signals should be synchronized with the existing
There shall be one eight-phase, dual ring, single
Arterial Progression System and/or the Central
entry, fully actuated microprocessor based
Computer Control System at the Traffic
controller per intersection interconnected with
Computer Center.
existing systems as required. The controller shall
be equivalent to a menu-driven NEMA type
All traffic signals and associated equipment shall
controller with LCD display capable of operating
be in accordance with the Standard
in a closed loop coordination system.
Specifications. Any variance relating to
equipment type or performance shall be approved
Signal control details including signal plans and
in writing by the Abu Dhabi Municipality.
all traffic signal parameters for signal controller
operation at an intersection/interchange shall be
902.02 SIGNALS, POLES, AND
provided. A note shall be included on the plans
CONTROLLERS
and specifications stating that the control cabinet
is to be wired with the same phase number
Only mast arm signal poles as per the standard
designations as shown on the plans.
drawings shall be utilized. Combination mast arm
signal and lighting poles or poles with multiple
Traffic signal systems shall include inductive loop
mast arms will not be used. All signal lenses shall
detectors with adequate size, shape and number of
be 30 cm including arrow lenses. All signal heads
turns to provide proper actuation. Loop detectors
shall be pole or mast-arm mounted. Span-wire
in bridge decks will normally utilize preformed
mounted signals will not be used.
loop detector material. Saw cutting of detector
loops in newly poured bridge decks will not be
Pedestrian signals will normally be installed in
permitted. Detector loops so located shall be cast
pedestrian pylons. Where appropriate, pedestrian
integral with the bridge deck.
signals shall be installed on the traffic signal pole,
on a street light pole, or on a separate 3.2 m pole.
Separate loop wires for each loop shall be
Pedestrian signals will have two signal sections
provided. There shall be a splice to connect the
with 30 cm lenses. The graphic symbols for
loop wires to the lead-in cable in the curbside
WALK and DONT WALK shall be used.
pullbox. This lead-in cable shall be terminated at
When illuminated, the DONT WALK indication
the detector amplifier in the local intersection
(hand palm) shall be red, and the WALK
controller. There shall be no splices in the lead-in
indication (man walking) shall be green.
cable.

Part 2 900-2
ROADWAY DESIGN MANUAL Roads and Bridges

Where feasible, power feeds for traffic signals If the width of the roadway median at the
should come from two separate substations and intersection is more than 5, but less than 10
be controlled by a changeover switch. This will meters, an additional pylon is placed at the
enable signals to remain functional in the event midpoint of the median with two pedestrian
one of the substations loses power. Separate feed signals back to back. If the median width is more
plans should be developed in cooperation with the than 10 meters, one pylon is placed at each edge
WED. of the median, each with one pedestrian signal.

The signalization design for each intersection Each pedestrian signal is comprised of two signal
shall include as a minimum: units with WALK and DON'T WALK
indications. The DON'T WALK unit, mounted
1. Plan symbols as shown on the standard on top of the WALK unit, has a polycarbonate
drawings. lens with black background and an illuminated
2. A drawing of the overall layout depicting red human hand symbol placed vertically. The
signal pole, detector, signal head and conduit WALK unit, mounted below the DON'T WALK
placements. All vehicular and pedestrian unit, has a polycarbonate lens with black
signal indications shall be labeled by background and an illuminated green walking
movement (signal group) number. man symbol.
3. A drawing including the pole schedule,
detector schedule, clearance times matrix, 903 TRAFFIC SURVEILLANCE
phase movements, and if necessary, notes
specifically corresponding to the design and Communication system facilities shall be installed
installation. on main roads, expressways and freeways. The
4. A drawing showing the conductor schedule. system will communicate traffic conditions to a
5. Additional drawings as necessary for central computer, which will then communicate
installation and materials details. back with the ramp signals, changeable message
signs and TV cameras. Interconnections between
902.03 DUCTS AND PULLBOXES signalized intersections surveillance facilities and
the central computer will be through concrete
All ducts shall be encased in concrete. Based on encased, 4-way or 8-way 10 cm PVC ducts.
the requirement, either 8-way, 4-way, 2-way or 1-
way 10 cm diameter ducts shall be utilized. CCTV cameras are to be located at intervals of
Raceways shall be 2-way 5 cm diameter except approximately one mile. Typical camera locations
for the traffic signal pole foundations raceways will be at interchanges and at midpoint locations
which shall be 3-way 5 cm diameter raceways. between interchanges. To provide for future
Standard pullboxes types (Type I, II and IV) shall implementation, 2 stub-outs of 10 cm diameter
be used as appropriate. schedule 40 PVC conduit, 1 m long, will be
extended from a pull box nearest the midpoint
902.04 PYLONS between interchanges. All conduit shall be
securely capped and locations precisely recorded
Pylons are used to house the pedestrian signals. on as-built plans. The locations, numbers of
Their appearance and materials are meant to add ducts and foundations will be determined from the
color to the streetscape. They are comprised of CCTV Master Plan drawings.
an aluminum tube column base and an aluminum
crown. External color is dark bronze. 904 SIGNING
Pylons with Type B crown are used at all General - Discussion in this section is
signalized intersections where pedestrian signals complimentary to the MUTCD and shall be used
are required unless pedestrian signals can be in conjunction with that document. However,
mounted on nearby light poles. Pylons with Type policies presented in the MUTCD reflect general
B crown are placed within green areas at both practices which may not always be applicable to
ends and at the outer edge of pedestrian crossings. Abu Dhabi. Where there are conflicts between

Part 2 900-3
ROADWAY DESIGN MANUAL Roads and Bridges

this section, the Standard Drawings and the 1. Designating the lane use at forks of major
MUTCD, the guidelines in this section and the inter-city expressway routes.
Standard Drawings should be followed, consistent
with sound engineering practices and judgement. 2. Where roadway and ramp configurations
may be misleading without lane
Traffic signs are installed to regulate, warn, and designations, such as: locations where the
guide road users. Installation, reflectivity, legend through expressway lanes end beyond the
size, legend color, placement, and support type interchange in a terminal, or locations
should all be considered to provide a consistent, where two or more ramps depart from the
safe and informative signing plan. through lanes and require lane use
demarcation for clarity.
904.01 SIGN STRUCTURE
INSTALLATIONS 3. Where lateral space is unavailable for a
ground mounted sign.
904.01.01 Ground Mounted
At interchanges between rural expressways, it is
Ground mounted signs are unobtrusive and can desirable to sign the through expressway lanes in
provide drivers with the essential information in addition to the ramp lanes. This can be
most instances. They are appropriate for marking accomplished with a ground mounted guide sign
all intersections and most interchanges. Typical in the median, if the median is wide enough. If the
guide sign treatments at expressway interchanges median width is inadequate, the through lanes
with main roads are diagrammed in Figure 900.01 guide sign may be cantilevered overhead in the
and Figure 900.02. median. The ramp sign may also be cantilever-
mounted for uniform appearance.
Sign post lengths are to be calculated based upon
the Standard Drawings and the roadway cross Similarly, space for other ground mounted guide
section at the sign locations. Foundations for signs may be restricted, thereby indicating the use
stubs shall be flush with the ground and stub of an overhead cantilever mounting.
protrusions of the concrete foundation shall also
conform to the Standard Drawings. Signs Typical overhead guide sign treatments at major
installed in the median are to be designed for the rural expressway junctions are portrayed in
ultimate roadway section. Figure 900.02.

904.01.02 Overhead Mounted Tubular Structure - Advanced guide and exit


direction signing on the mainline shall use tubular
Overhead signs may detract from the aesthetic cantilever and tubular sign bridge structures.
appearance of the roadway and architectural
treatment of bridge structures. They also limit the The Standard Drawings have tubular sign
clearances for large trucks and their loads. As a structures which have been developed to
rule, overhead signs should be used sparingly at accommodate sign panels up to 4 m in height
locations where ground mounted signs cannot including the exit panel. Therefore, all efforts
provide the essential directions to the motorist. should be made to limit sign panel heights to 4
meters. This may require some minor reductions
Overhead guide signs are principally applicable in legend size or spacing. The use of sign panels
for marking free flow traffic movements at in excess of 4 m in height will require a complete
interchanges between rural expressways where sign structure design. Tubular sign structure
lane orientation is necessary for directing the standards shall be incorporated in the final plan
motorist, or at locations where lateral space for submittal.
ground mounted signs is not available. Overhead
guide sign use should be limited to: Interchange sequential signs shall be located in
the center of the median back to back on a single
structure approximately halfway between

Part 2 900-4
ROADWAY DESIGN MANUAL Roads and Bridges

interchanges. Existing structures shall be utilized Route markers shall be placed as separate signs
for sign mounting wherever possible. and in conjunction with guide signs as shown in
Figures 900.01 and 900.02. The background used
Bridge Mounted - Sign mounting brackets, for for route markers shall be the falcon symbol
bridge mounted signs, are to be designed based shown below. The sign panel shall have a yellow
upon the criteria set forth in this manual for sizing legend and border on a blue background.
sign panels. Cast-in-place anchor bolts shall be
provided with the bridge structure, together with Guide post types and lengths shall be as per
all the necessary hardware for sign lighting. Figure 900.04 and the Standard Drawings.

904.02 SIGN SHEETING

Sign panel materials, reflectivity and color shall


be per the Standard Drawings and the Standard
Specifications. Any changes to the standards shall
be approved in writing.

904.03 SIGN TYPES

904.03.01 Regulatory And Warning


Signs

Regulatory and warning signs inform drivers of


traffic regulations and warn of potentially
hazardous conditions. Messages are portrayed
using standard international symbols. These signs
are generally less than one square meter in area.
904.04 FINAL SIGNING PLAN
Post types and lengths shall be as per Figure REQUIREMENTS
900.03 and the Standard Drawings. Locations
shall be per the Standard Drawings and the The final signing drawings should include
MUTCD. information and details not covered by the
Standard Plans or Specifications such as:
904.03.02 Guide Signs Site specific sign details
Sign Layout Sheets with sign dimensions,
Guide signs direct drivers to their destinations by character dimensions, sign message, support
informing them of intersecting streets or type and reflective sheeting requirements.
prominent places along the route. Messages shall Plan sheets showing sign placement.
be shown in both Arabic and English and vary in Signing sheets may be combined with striping
length and height. Space for these messages sheets as long as the plans are legible. Scale shall
require large sign faces as well as structural be such that all signs and markings are clearly
supports. The guide signs may be ground depicted.
mounted on the side of the roadway or mounted
overhead above the roadway or shoulder. Guide
signs shall be placed and designed per the
Standard Drawings, the Standard Specifications
and the MUTCD.

Part 2 900-5
ROADWAY DESIGN MANUAL Roads and Bridges

Figure 900.01
Guide Sign Treatment
Interchanges With Main Roads

Part 2 900-6
ROADWAY DESIGN MANUAL Roads and Bridges

Figure 900.02
Guide Sign Treatment
Major Junctions Between Rural Expressways

Part 2 900-7
ROADWAY DESIGN MANUAL Roads and Bridges

Figure 900.03
Sign Installation And Post Selection

Part 2 900-8
ROADWAY DESIGN MANUAL Roads and Bridges

AISC DESIGNATIONS
DIMENSIONS IN CENTIMETERS
TWO POSTS

POST TYPE A = W6x15


POST TYPE B = W10x22
POST TYPE C = W14x26

SIGN DEPTH SIGN WIDTH POST TYPE


(cm) (cm)
91,107 Up to 600 A
122,137 Up to 500 A
122,137 501 to 600 B

153,168 Up to 400 A
153,168 401 to 600 B
183,198 Up to 350 A

183,198 351 to 600 B


213,229 Up to 250 A
213,229 251 to 600 B

244,259 Up to 200 A
244,259 201 to 500 B
244,259 501 to 600 C

274,290 Up to 200 A
274,290 201 to 400 B
274,290 401 to 600 C

305,320 Up to 350 B
305,320 351 to 600 C
335,351 Up to 350 B

335,351 351 to 600 C


366,381 Up to 300 B
366,381 301 to 600 C

Note: For signs wider than 600 cm, use 3 posts.

Figure 900.04
Sign Post Types

Part 2 900-9
ROADWAY DESIGN MANUAL Roads and Bridges

904.05 ARABIC LETTERING FOR GUIDE quite a distance below this baseline; therefore, the
SIGNS vertical spacing on the sign face should be
checked and adjusted, if necessary.
904.05.01 General

Guide signs shall be designed in Arabic and The width of the message Corniche Road is
English, with the Arabic message above the calculated in Example 900-01 on the following
English translation. To size the signs, the actual page. The page numbers refer to the fourteen
width of the Arabic and English messages must pages in the Standard Arabic Script for Highway
be determined. Signs, Section 904.07. Aleph height was assumed
to be 24 cm, slightly larger than the English 20
904.05.02 The Arabic Alphabet cm lettering. Calculations proceed right to left.

The first letter in the Arabic alphabet is aleph Looking at the last letter in the first word, the
which is a simple downstroke. For the purposes of shape extends 43 mm below the baseline. Using
the Standard Script, aleph is used to proportion the proportion of 4.8, at least 20.64 cm will be
the height of the letters. In developing the required between the Arabic and English message
Standard Script, it has been determined that an to avoid conflict.
aleph height of 30 cm generally corresponds to
signing on freeways, while an aleph height of 24 904.06 GUIDE SIGN DIMENSIONS
cm corresponds to signing on arterial roads.
904.06.01 Single Message Guide Signs
Figure 900.05 provides spacing criteria for Guide (Example 900-02)
Sign design. Figures 900.06 through 900.17 are
template guides for Arabic letters and numerals. After computing the preliminary sign width
(message width, arrow width, and offsets) it shall
When designing guide signs for all Abu Dhabi be rounded to the nearest 5 cm to get the final
roadway projects, signs to be read from freeways sign width. Changes to the adjustable base
and expressways will have 30 cm (aleph height) dimensions most likely will have to be made to
Arabic lettering and 27 cm English lettering. achieve this.
Signs to be read from ramps and main roads will
have 24 cm (aleph height) Arabic lettering and 20 Sign faces shall be detailed as per the theoretical
cm English lettering. height dimensions for a particular sign. Small
variations in the spacing between the legend and
904.05.03 Use of the Standard Arabic Script the border can be used to increase or decrease the
overall sign height to an even 50mm increment.
The shape of each letter and number in the However, any reduction shall be limited to 90%
Standard Script is shown on a five-millimeter grid of the original spacing.
in Figures 900.06 through 900.17.
Changes made to achieve the recommended height
To get the actual width of a word on the guide and width shall be spread as evenly as possible
sign, find the width of each letter shape in the over the appropriate adjustable dimensions. If the
Standard Script. Then multiply that width by the preliminary sign height or width is a halfway
proportion of the aleph height in the final guide between two recommended sign heights or widths,
sign to the aleph height shown in the Script. always round to the higher size.
Finally, add the width of each letter shape, taking
into account the spacing rules for unconnected Center the smaller lettering with the center of the
letters to obtain the total message width. wider lettering.

Arabic lettering is aligned on a baseline, just as in


English. The location of the baseline for each
letter is indicated by an arrow (V) adjacent to that
letter in the Standard Script. Some letters extend

Part 2 900-10
ROADWAY DESIGN MANUAL Roads and Bridges

Proportion: 24 cm = 4.8
5 cm

First letter: page 6; connected on left: 55 mm x 4.8 = 26.40 cm


Second letter: Page 3; connected on right 10 mm x 4.8 = 4.80 cm
Space: from Table A, 1-1/2 squares: 7.5 mm x 4.8 = 3.60 cm
Third letter: page 5; unconnected: 30 mm x 4.8 = 14.40 cm
Space: from Table A, overlap by 1-1/2 squares: 7.5 mm x 4.8 = -3.60 cm
Fourth letter: page 9; end of word: 53 mm x 4.8 = 25.44 cm
Space between words: 6 squares: 30mm x 4.8 = 14.40 cm
First letter: page 3; unconnected: 8 mm x 4.8 = 3.84 cm
Space: from Table A, 1-1/2 squares: 7.5 mm x 4.8 = 3.60 cm
Second letter: page 11; connected on left: 22 mm x 4.8 = 10.56 cm
Third letter: page 10; connected both sides: 50mm x 4.8 = 24.00 cm
Fourth letter: page 12; connected on right: 45mm x 4.8 = 21.60 cm
Space: from Table A, no space: = 0.00 cm
Fifth letter: page 5, unconnected: 30mm x 4.8 = 14.40 cm
Space: from Table A, overlap by 2 squares: -10 mm x 4.8 = -4.80 cm
sixth letter: page 11, connected on left: 22 mm x 4.8 = 10.56 cm
Seventh letter: page 12, connected both sides: 27 mm x 4.8 = 12.96 cm
Eighth letter: page 6, end of word: 80 mm x 4.8 = 38.40 cm

Total Length of Message = 220.56 cm

Example 900-01
Sample Calculation Of Arabic Message Width

Part 2 900-11
ROADWAY DESIGN MANUAL Roads and Bridges

904.06.02 Multiple Message Guide Signs These multiple messages shall be centered
(Example 900-03) with the center of the largest message.
The dimension between two messages shall be
For multiple message guide signs, the rules and
the same as between the Arabic lettering and
base dimensions for a single message guide shall
the upper border stripe on a single message
apply, with a few additions and exceptions.
guide sign.
Guide sign width shall be determined by the The guide arrow shall be vertically centered.
widest message (message width, arrow width and It will also be horizontally offset from the
offsets), measured as if it was a single message largest message as in a single message sign.
guide sign.
Separate guide arrows for each message (multiple
To achieve a recommended height, changes in he messages):
adjustable dimensions should be spread as evenly
as possible throughout all messages. The smaller messages shall not be centered
with largest message, but placed with the
The multiple sign should be shown with a similar same offsets from the guide arrow side of the
dimensional breakdown as the single message sign sign as if they were a single message sign.
(Example 900-02). A single white stripe of 3 or 5 cm shall be
placed between all messages that use separate
The following paragraphs provide guides for use
guide arrows. English and Arabic lettering
with messages containing arrows. Separate guide
shall be offset from this line as from the
arrows for each message:
border stripes in a single message guide sign.
It is preferable to place the guide arrows on
The smaller message shall not be centered
opposite sides of the guide sign.
with the larger message, but placed with the
same offsets from the guide arrow side of the Same guide arrow for multiple messages:
sign as if they were a single message sign.
A single white stripe of 3 cm or 5 cm shall be These multiple messages shall be centered
placed between all messages that use separate with the center of the largest message.
guide arrows. English and Arabic lettering The dimension between two messages shall be
shall be offset from this line as from the the same as between the Arabic lettering and
border stripes in a single message guide sign. the upper border stripe on a single message
It is preferable to place the guide arrows on guide sign.
opposite sides of the guide sign. The guide arrow shall be vertically centered.
It will also be horizontally offset from the
Separate guide arrows for each message:
largest message as in a single message sign.

Part 2 900-12
ROADWAY DESIGN MANUAL Roads and Bridges

Dimensions For Guide Signs


Aleph Height

24 cm 30 cm

A 3 5
B* 20 27
C 20 27
D (See Note A)
E 24 30
F* 24 30
G* 35 (See Note B) 40
H* 30 (See Note B) 40
J (See Note C)
K (See Note D)

(A) 10 cm + largest distance an Arabic letter in the message goes below the baseline.

(B) From the edge of the wider message, Arabic or English.

(C) See Standard Drawings for arrow dimensions.

(D) (Height of sign - arrow height) 2, use whole numbers.

* These dimensions may be adjusted to comply with recommended heights and widths.

Example 900-02
Dimensions For Guide Signs

Part 2 900-13
ROADWAY DESIGN MANUAL Roads and Bridges

Example 900-03
Multiple Message Guide Signs

Part 2 900-14
ROADWAY DESIGN MANUAL Roads and Bridges

1 of 14
904.07 STANDARD ARABIC SCRIPT
FOR HIGHWAY SIGNS

This section consists of pages numbered 1


through 14 of 14. The design of each letter and
number is shown on a 5 mm grid in Figures
900.06 through 900.17. Letter shapes are shown
when the letter occurs at the end of a word (or is
unconnected), at the beginning of a word, and in
the middle of a word (generally shown left to right
respectively). The length of the connections to
proceeding and following letters are included in
the design. However, they may be increased
slightly to maintain proper proportion with the
English legend if it is larger than the Arabic
legend.

Letter height and spacing between words shall be


detailed in the project drawings.

Certain Arabic letters are not connected with


letters which follow in the same word. The space
between the letters and the letters which follow
them are given in Figure 900.05.

Part 2 900-15
ROADWAY DESIGN MANUAL Roads and Bridges

2 of 14

Figure 900.05
Guide Sign Letter Spacing

Part 2 900-16
ROADWAY DESIGN MANUAL Roads and Bridges

3 of 14

Figure 900.06
Guide Sign Lettering

Part 2 900-17
ROADWAY DESIGN MANUAL Roads and Bridges

4 of 14

Figure 900.07
Guide Sign Lettering

Part 2 900-18
ROADWAY DESIGN MANUAL Roads and Bridges

5 of 14

Figure 900.08
Guide Sign Lettering
Part 2 900-19
ROADWAY DESIGN MANUAL Roads and Bridges

6 of 14

Figure 900.09
Guide Sign Lettering
Part 2 900-20
ROADWAY DESIGN MANUAL Roads and Bridges

7 of 14

Figure 900.10
Guide Sign Lettering

Part 2 900-21
ROADWAY DESIGN MANUAL Roads and Bridges

8 of 14

Figure 900.11
Guide Sign Lettering
Part 2 900-22
ROADWAY DESIGN MANUAL Roads and Bridges

9 of 14

Figure 900.12
Guide Sign Lettering

Part 2 900-23
ROADWAY DESIGN MANUAL Roads and Bridges

10 of 14

Figure 900.13
Guide Sign Lettering
Part 2 900-24
ROADWAY DESIGN MANUAL Roads and Bridges

11 of 14

Figure 900.14
Guide Sign Lettering

Part 2 900-25
ROADWAY DESIGN MANUAL Roads and Bridges

12 of 14

Figure 900.15
Guide Sign Lettering
Part 2 900-26
ROADWAY DESIGN MANUAL Roads and Bridges

13 of 14

Figure 900.16
Guide Sign Lettering
Part 2 900-27
ROADWAY DESIGN MANUAL Roads and Bridges

14 of 14

Figure 900.17
Guide Sign Lettering

Part 2 900-28
ROADWAY DESIGN MANUAL Roads and Bridges

904.08 SIGN LIGHTING reflect general practices which may not always be
applicable to Abu Dhabi. Where there are
Roadway sign lighting shall be as recommended conflicts between this section, the Standard
in AASHTOs An Informational Guide for Drawings and the MUTCD, the guidelines in this
Roadway Lighting, 1984, pages 30-32. section and the Standard Drawings should be
followed, consistent with sound engineering
Sign Lighting shall be designed using medium practices and judgment.
ambient illuminance in accordance with the
following table: All pavement markings and symbols shall be
thermoplastic per the Standard Drawings and the
Table 900.01 Standard Specifications.
Sign Lighting
Lighting Medium Ambient Typical urban layouts for pavement markings and
Levels Illuminance raised pavement markers are shown in the
Illuminance 20-40 Fc Standard Plans. Raised pavement markers are
Luminance 48-96 cd/m2 generally not used in rural areas.

The uniformity (maximum) for the illuminance 905.02 TYPES OF PAVEMENT


shall not exceed a ratio of 6:1, 4:1 is desirable. MARKINGS

904.09 SIGN LUMINARES The following types of pavement markings shall


be used, as required:
High-pressure sodium fixtures shall be used, 150
watt size. Each sign lighting shall be designed for 1. Lane Markings
mounting horizontally at the top of the sign 2. Stop Line Markings
panels, number and spacing of the fixtures shall 3. Pedestrian Crossing Markings
be determined during design. Maximum spacing 4. Channelization Markings
of the fixtures should not exceed 6 m. 5. Pavement Edge Markings
6. Parking Space Markings
Sign lighting shall follow AASHTO 7. Pavement Symbols (Arrows and Letters)
recommendations. Independent design
calculations are recommended using the design 905.02.01 Lane Markings
program Micro-Site-Lite, CALA or equivalent.
The effect of adjacent roadway lighting on the In urban areas, markings separating traffic lanes
sign should be considered in these calculations. in the same direction shall be comprised of type
CR and type NR pavement markers spaced as
Each fixture shall be individually fused in a shown on the Standard Drawings. Markings
NEMA 32 box at each sign structure. If a sign separating exclusive turning lanes from through
structure has four or more sign lights, two traffic lanes shall be type NR pavement markers
independent circuits shall be provided for that spaced as shown on the Standard Drawings from
structure. the stop bar to the end of the taper.

905 PAVEMENT MARKINGS In instances where two parallel and adjacent


longitudinal lines are placed, they shall be 10 cm
905.01 GENERAL apart.

Pavement markings shall be used for regulating, For lane marking standards not shown in the
warning, and guiding road users. Discussion in Standard Drawings see Figure 900.18.
this section is complimentary to the Manual on
Uniform Traffic Control Devices (MUTCD) and
shall be used in conjunction with that document.
However, policies presenting in the MUTCD
Part 2 900-29
ROADWAY DESIGN MANUAL Roads and Bridges

905.02.05 Pavement Edge Markings

Pavement edges shall be marked only when there


is no curb. The marking shall be a 10 cm wide
continuous white line on the outside edge and a
yellow line on the inside edge with corresponding
type CR or YR pavement markings at 16.0 m
intervals as shown on the Standard Drawings.

905.02.06 Parking Space Markings

Parking space markings shall be used wherever


parking is allowed. They shall be 10 cm wide
solid lines showing the borders of each parking
space.

905.02.07 Pavement Symbols


(Arrows and Letters)

Arrows shall be used, as necessary, to indicate the


types of movements, that can be made from the
lanes where arrows are placed. They shall be
solid, elongated, and 5.0 m long. The shape shall
Figure 900.18 be as specified by international standards.
Lane Markings
Letters, whenever used, shall be solid, elongated,
905.02.02 Stop Line Markings and 3.0 m long. The shape shall be as specified
by international standards. Letter messages shall
Stop line markings shall be continuous from curb be both in Arabic and English.
to curb and shall be 30 cm wide as shown on the
standard drawings. 906 MAINTENANCE OF TRAFFIC

905.02.03 Pedestrian Crossing Markings During Construction, existing traffic flow will be
maintained on paved, lighted detour roads. In
Pedestrian crossings shall be marked by general, detours will have two through lanes in
longitudinal stripes through the width of the each direction.
pedestrian crossing which shall be 4.0 m. Stripes
shall be 50 cm wide, with a 50 cm gap between 906.01 CONSTRUCTION STAGING
adjacent stripes.
Construction will be staged so as to avoid
The distance between the upstream edge of the disruption of traffic flow as much as possible.
pedestrian crossing and the beginning of the When required and possible, pedestrian
adjacent stop line shall be 1.0 m. movements will be maintained by temporary
sidewalks.
905.02.04 Channelization Markings
Temporary pavement shall be used for all
All channelization markings, except those detours. Temporary lighting shall be provided
mentioned above, shall be 20 cm wide solid lines. during all stages of construction, including
Dead areas created by channelization will have temporary detours.
chevrons which shall be comprised of 20 cm
continuous line.

Part 2 900-30
ROADWAY DESIGN MANUAL Roads and Bridges

906.02 SAFETY MEASURES

Standard barriers, barricades, signs, flashers and


other protective measures will be provided for
guiding, warning, and protecting vehicular and
pedestrian traffic during construction.

All road closures and construction traffic shall be


coordinated with local police and fire services.

906.03 TEMPORARY TRAFFIC SIGNALS

At locations of complex traffic movements,


temporary and portable traffic signals will be
used for the safe, orderly movement of traffic
during construction.

906.04 MAINTENANCE OF TRAFFIC


PLANS

A work phase plan shall be established by


construction phases or sequence, indicating the
duration of each phase or sequence. The plan
shall include but not be limited to:
maintenance of traffic circulation during
construction,
traffic control methods that need to be
implemented,
construction detours,
Work areas per stage,
temporary barrier locations and details,
temporary signing and striping locations and
details,
temporary construction quantities.

Part 2 900-31
ROADWAY DESIGN MANUAL Roads and Bridges

SECTION 1000 lighting enhances traffic safety through high


visibility, the need for fewer poles, and greater
LIGHTING
flexibility in their location.
1001 ROADWAY LIGHTING Arterials and Frontage Roads
Arterials serve moderately high volumes of traffic
1001.01 GENERAL at lower speeds than freeways and expressways.
Although their primary function is to move and
The main function of roadway lighting is to maintain uninterrupted traffic flow, they
improve driver visibility. A well illuminated frequently have busy at-grade intersections
roadway increases safety by allowing drivers to requiring traffic control devices. These at-grade
identify potential hazards or conflicts. Well intersections require greater visibility for traffic
designed lighting allows the driver to quickly signals, signs and the resulting crossing and
recognize roadway features such as alignment, turning conflicts.
delineation, intersections, ramps, traffic signs,
traffic signals, and pedestrian crossings. The Also, increased commercial development along
improved driving environment in turn improves arterials means increased pedestrian movements
traffic operations, capacity and safety. and possibly the need to accommodate public
transportation (taxicabs and buses). Adequate
Lighting continuity is recommended for esthetic lighting for pedestrian movements and public
and functional reasons. Lighting continuity helps transportations frequent stopping, loading and
drivers identify roadway facilities and acts as a unloading of passengers is vital to safety along
unifying design element. arterials. Arterial lighting must also blend with
commercial development lighting to avoid
Lighting design responsibility generally combinations which detract from the overall
encompasses entire roadways within the project lighting or result in poor visibility.
limits. However, at the time of concept planning,
the design responsibility may be reduced or Sector Roads
expanded by the Municipality. The designer A sector roads primary function is to provide
should consult the Road Section as to any direct access to adjacent properties. Although
variation in the design requirements. traffic speed is low, traffic volume can be heavy
and frequently interrupted especially in residential
1001.02 LIGHTING DESIGN and commercially developed areas. Because of
CONSIDERATIONS increased access to commercial and private
property, sector roads, compared to arterials,
Freeways and Expressways must accommodate an even heavier volume of
Because freeways and expressways are wide and pedestrian movement. Lighting considerations are
have higher traffic speeds, general street lighting much the same as for arterials.
requirements are inadequate for freeway and
expressway lighting. High lumen lamps in Intersections and Pedestrian Crossings
conjunction with high mast poles are used to Lighting intersection and pedestrian crossings is
illuminate large roadway areas and reduce glare. of particular concern and must be adequate for
traffic and pedestrian security, as well as meeting
Interchanges environmental objectives. If necessary for traffic
High mast lighting is ideal for illuminating safety, pedestrian security, or to enhance
interchanges and other large areas, because the appearance, the lighting color should be varied to
illumination pattern is not confined to the basic define the various elements more clearly.
driving lanes. High mast lights illuminate the Generally, the illumination level at an intersection
entire interchange, creating the same overall view of two at-grade roadways is the sum of the
of the area as that perceived in daylight. High illumination of the two roadways.
mast poles can be installed in suitably wide
medians on multiple-lane roadways. This type of
Part 2 1000-1
ROADWAY DESIGN MANUAL Roads and Bridges

Table 1000.01
Illumination Requirements
Roadway Minimum Uniformity Light Lantern Pole
Illumination Ratio Source Height
(Lux) (m)
Freeways & 22 2:1 HPS Cut-off Type III 30.5
Expressways
Interchanges 22 2:1 HPS Cut-off Type V 30.5 ***

Main Roads/ 22 2:1 HPS or Rectilinear, Sharp Cut-off 14


Arterials MH
Sector Roads 15* 3:1 HPS or Rectilinear, Sharp Cut-off 10 ***
/Ramps MH
Crosswalks 33 2:1 HPS or Rectilinear, Sharp Cut-off 10-14
MH
Ramp Terminals 40** 2:1 Match Cut-off Type 30.5 ***
&Traffic Conflict Road or 14
Areas
Parking Areas 15 3:1 HPS, or Rectilinear, Sharp Cut-off 10
MH
Sidewalks Away 10* 3:1 HPS Decorative 4.6
From Road
HPS - High Pressure Sodium
MH - Metal Halide

Notes:
1. Lamps for sign lighting should be a different color from roadway. Mercury vapor lamps for sign
lights will provide good contrast and easy differentiation from high pressure sodium roadway
lighting.
2. Recommended illumination level indictates the minimum allowable. Individual designs shall specify
lighting levels as advised by the Municipality/WED at the design phase.

* On high volume roads, lighting will be upgraded to suit conditions.


** Areas of traffic conflict would have high levels of illumination equal to the sum of values
recommended for each of the intersecting roads.
*** Use high mast with HPS on ramps wherever possible.

Rural Lighting 1001.03 ILLUMINATION


Rural roadway lighting is generally warranted REQUIREMENTS
only at decision points such as interchanges or
intersections. However, accident records should Table 1000.01 summarizes the illumination
be examined to determine if poor visibility was a requirements for various roadways.
recurring factor. Continuous lighting on rural
roadways may be considered early in the design Illumination
process. Illumination levels stated in Table 1000.01
represent the lowest average maintained levels
considered appropriate for each kind of roadway
or walkway in the various areas. Illumination

Part 2 1000-2
ROADWAY DESIGN MANUAL Roads and Bridges

criteria and calculations are based on the Lanterns mounted on 10 m poles shall be 400
Illuminating Engineering Societys (I.E.S.) watt high pressure sodium or metal halide
standards modified to meet the higher uniformity lanterns.
and illumination levels required by the WED and
the Municipality of Abu Dhabi. Lanterns shall have optical systems sealed against
moisture, dirt and insects, and be mechanically
Uniformity Ratio strong and easy to maintain.
A Uniformity Ratio (UR) is defined as the
average maintained illumination of the roadway Glare control for the mounting height specified,
design area, divided by the lowest value at any and cut-off characteristics shall be designed based
point in the area. See Table 1000.01 for roadway on I.E.S. standards.
criteria.
Lantern Mounting Height
Light Source High mast lighting (30.5 m) is proposed for
Light sources shall be as identified in Table applicable interchanges and between closely
1000.01 and as modified during the design phase spaced interchanges when conditions permit. On
if advised by the Municipality. It is important major thoroughfares not suitable for high mast
that the lighting design be compatible with the lighting, but where substantial lighting
surrounding area. requirements remain, pole heights would be 14m.

The roadways not identified in this manual will High-mast lighting (30.5 m poles) shall be used
use a light source as directed by the Municipality. on rural and urban freeways and expressways
Side roads and ramps shall have the same light with wide medians where one row of 14 m poles
source as the adjacent main roads. Metal halide is not suitable. The 30.5 m poles shall also be
or high pressure sodium shall be selected to blend used at all interchanges. Wherever possible high
with the surroundings on sector roads. mast lighting shall be used for ramps.

Lantern and Lamp Selection High mast lighting will be used on main roads
Sharp cutoff lanterns are proposed for roadway only when light height will not substantially
lighting per Table 1000.01. These lanterns are interfere with nearby buildings. On other major
designed to illuminate a relatively large area thoroughfares, poles would be 14 m high and
without spilling light into adjacent areas. They would be placed at the side or in the median of the
produce uniform illumination and minimum glare. roadway, as applicable. Single or multiple
lanterns would be used to provide uniform
High pressure sodium lamps provide excellent illumination of the roadway.
golden white color and enhance the esthetic
qualities of concrete, stone and brick. Metal 1002 PARKING AREA LIGHTING
halide gives a whiter light, providing a color
contrast to sodium lamps, and enhance the 1002.01 GENERAL
appearance of green and pastel colored materials.
The function of light sources in parking areas is
The lanterns shall be mechanically strong and to give an overall view of the parking area and
easy to maintain. They shall be of adequate provide a measure of security. Lighting is also
design to operate at mounting heights of 30.5 critical for vehicle maneuvers such as backing.
meters and able to withstand sustained wind
speeds of 160 kph with 208 kph gusts. 1002.02 ILLUMINATION
REQUIREMENTS
Lanterns mounted on 14 meter poles shall be
1000 Watt high pressure sodium, metal halide Light source shall be high pressure sodium or
and mercury vapor lanterns cut-off, and provide metal halide selected to blend with the
efficient even illumination. surroundings per Table 1000.01.

Part 2 1000-3
ROADWAY DESIGN MANUAL Roads and Bridges

1002.03 LANTERN MOUNTING HEIGHT 1004 LIGHTING CONTROLS

Ten meter high poles shall be used for all parking 1004.01 GENERAL
lot areas. Lantern configuration and light
distribution shall be selected to suit the parking These items provide required electrical
area geometry. connections and controls to all roadway lighting,
decorative lighting and street furniture lighting
1002.04 LANTERN SELECTION items (i.e. bus shelters, telephone booths and
sidewalk lights).
Lanterns shall be as detailed in the General
Specifications and Table 1000.01. 1004.02 LIGHTING CONTROLLER
REQUIREMENTS
1003 SIDEWALK LIGHTING
Lighting shall be controlled by a 24 hour timing
1003.01 GENERAL switch. Control cabinet requirements shall be as
specified in the Standard Specifications.
Sidewalk lighting provides visually pleasant and
decorative illumination to sidewalks adjacent to 1004.03 DESIGN STANDARDS AND
buildings, to buildings themselves and to the other PROCEDURES
pedestrian walkways.
Control cabinets should be located in the median
1003.02 ILLUMINATION where feasible. The maximum voltage drop in the
REQUIREMENTS outgoing circuits beginning at the control cabinet
shall be four percent. Branching of underground
Light source will be high pressure sodium per cable circuits from all lighting units except 4.6 m
Table 1000.01 unless otherwise directed by the poles will be allowed. There shall not be any
Municipality. Sidewalk lights will be provided intermediate joints in the lighting cable circuitry
only for the areas specifically advised by the except the terminations in the lighting units or in
Municipality. the junction boxes.

1003.03 LANTERN MOUNTING HEIGHT 1005 POWER DISTRIBUTION

Sidewalk light poles shall generally be 4.6 meters Electric service is 415/240 volts, three-phase,
high with 2-100 watt high pressure sodium four-wire, 50 Hz system furnished by the Water
lanterns. However, special pole heights and and Electricity Department (WED). This service
lantern types may be required to meet special shall be provided at the lighting control cabinets.
situations. The Project Design Manager should Underground distribution to the lighting units
consult the Municipality as to the exact nature of utilizes four conductor and steel wire armored
the requirements at the time of concept planning. XPLE insulated cables. Conductor size will be
25 mm2 for all 30.5 and 14 m light poles and 16
1003.04 LANTERN SELECTION mm2 for all 10 and 4.6 m poles, street furniture
and decorative lighting units. The lanterns will be
Ornamental lighting of proper height for the connected in phase sequence to provide a
pedestrian is proposed for sidewalks along balanced three-phase load.
buildings and in parks and landscaped areas.
Low-level ground lights would be used to
illuminate vegetation.

Part 2 1000-4
ROADWAY DESIGN MANUAL Roads and Bridges

Type IV pull boxes shall be used adjacent to light 1006 DESIGN AND SUPERVISION
pole foundations in paved areas except where RESPONSIBILITIES
interlocking pavers are used. They should be
installed between the foundation race way conduit The Municipality is responsible for the lighting
and the electrical conduit. Cables shall be direct criteria standards to light the roads. This
buried under sidewalks and interlocking pavers criterion covers illumination levels, uniformity
used in parking areas except at the entry or exit of ratios and distribution and differences in
sector roads or parking areas where PVC ducts brightness of the roadways.
shall be provided. Cables under interlocking tiles
at the entry or exit of sector roads and parking WED may suggest/advise of criteria or
areas, shall be through concrete encased PVC improvements in lighting for the Municipality and
ducts. its Consultant to consider in design and
construction. However, WED responsibility is
All PVC conduits and ducts for underground limited to advising of its requirements for
cable lighting circuitry, shall be a minimum of 10 maintenance and access to the lighting poles and
cm diameter. There should be a minimum of one lanterns for inclusion in the Specifications. The
spare duct at each crossing. Where lighting Municipality and its Consultant are responsible
cables are proposed along the service reserves at for adherence to the lighting specifications.
road crossings, the available electrical ducts shall
be used. Separate lighting road crossing ducts are WED is responsible for the technical
not required at these locations. specifications and sizing for the electrical power
supply for the lighting system including
The underground lighting cables shall be installed underground cable circuits, fuses, control
along electrical service reserves in all possible cabinets, pull boxes and conduit. Accordingly,
cases. Wherever the lighting cables are proposed WED will be responsible for review of contractor
outside the service reserve, the cable route shall submittals covering these items during the
be immediately adjacent to the curb line. construction period. WED shall have the right to
inspect such construction in the field and approval
Separate earthing is required only at the terminal by WED shall be required prior to burial of the
pole of each circuitry. All light poles and fixtures underground cable circuitry by the Contractor.
shall be earthed through the cable armoring.

Part 2 1000-5
ROADWAY DESIGN MANUAL Roads and Bridges

SECTION 1100 The Agricultural Section will determine if a


reservoir is required on a project. They will, also
ROADSIDE DEVELOPMENT
determine its location and size. However, final
approval for including this work in a project must
1101 LANDSCAPING come from the Road Section.
Landscaping and the associated irrigation system 1102.01 IRRIGATION DUCTS
for the roadside areas and medians will be
designed by the Agricultural Section of the Abu All irrigation facility crossings of all roadways
Dhabi Municipality. The Design Project shall be accommodated within a duct. Duct
Manager is responsible for coordinating with the details are included on the Miscellaneous Utility
Agricultural Section to ensure that they are aware Detail Standard Drawings. Duct crossings should
of the Project and its design schedule. be located within allocated service reservation
corridors.
Special permission from the Municipality is
required for the removal of any green (planted) Guidelines for providing the irrigation ducts and
area. Newly created areas suitable for planting appurtenances are:
along with remaining green areas must be
identified and presented on the General Plans. 1. Ducts for irrigation lines may be Glass
The Design Project Manager must provide these Reinforced Plastic (GRP) or
plans to the Agricultural Section so that they can Polyvinylchloride (PVC) pipe conforming to
design the new landscaping and irrigation system. the Standard Specifications.
Close coordination with the Agricultural Section
is essential to ensure that the irrigation design is 2. Generally, ducts will be provided under the
completed early enough to be incorporated into roadway at intersection crossings. Additional
the Tender Documents of the roadway project. contingency ducts shall be located at spacing
of approximately 250 to 300 meters between
Agricultural planting areas should be shown on interchanges. Specific contingency duct
the general plans designated as green areas. requirements for each project must be
Green areas within the residential sectors, (sectors coordinated with the Agriculture Department.
predominantly villas or low rise structures), Ducts under the roadway pavement must be
should be maximized while reducing paved areas. aligned with each other in the median, both
In general the green areas should be limited to the horizontally and vertically.
front portion of building plots. The areas
between and behind the existing buildings should 3. Ducts should normally have one meter of
be paved with pedestrian or vehicular pavers as cover, however, one-half meter of cover is
applicable. However, each sector must be acceptable where positioning is due to
considered individually. Local residents, conflicts with existing or proposed utilities.
Mosques, Embassies and/or some other In superelevated sections, the ducts should
significant feature within the sector, often require have approximately the same degree of cross
special (non-standard) treatment. slope as the highway. All ducts should have
a nominal (1%) slope for drainage.
1102 IRRIGATION
4. The end of ducts must extend 0.5 meters
It may be required to design an irrigation (minimum) past back face of curbs or
reservoir with electrical and water services. In sidewalks when in curbed situations.
general, it will include the reservoir, pump-house
structure and the incoming services, but will not 5. The end of the ducts should extend into the
include the interior piping, wiring or pumping verge area in an un-curbed condition. The
systems. intent is to maintain the cover from the

Part 2 1100-1
ROADWAY DESIGN MANUAL Roads and Bridges

sideslope at one meter (minimum) where the uniform and visually pleasing design and
irrigation line comes out of sleeve. appearance.

6. Ducts should be considered where In general, street furniture will only be provided
maintenance roads and driveways cross in roadway projects at the direction of the Road
irrigation lines. Section. For urban interchange projects,
installation of street furniture will be included as
1103 FENCING part of the proposed improvements. On rural
interchange contracts, the extent of street
The Designer and Abu Dhabi Road Section shall furniture required could range from pedestrian
review fence requirements on a project specific signals to a full compliment of street furniture
basis. elements. On all types of projects, during the
close of the Concept Phase, the Designer should
1104 SLOPE PAVING consult with the Abu Dhabi Road Section to
determine the types of street furniture that should
Slope paving at bridge abutments shall conform be provided.
to the Abu Dhabi Road Section Standard slope
paving details. Descriptions of the basic function, elements,
design standards and procedure for each street
Where the mainline is depressed below the local furniture item are included in following sections.
crossroad, the slope paving shall approximate the
typical cross section contours. A 6 meter grading 1106.02 DESIGN
transition at each edge of the slope paving should
be indicated on the plans. Details of street furniture have been designed and
shown on the Standard Street Furniture Detail
Special treatment of slope paving may be drawings and in the Standard Specifications.
applicable at specific locations. The Designer These details do not have to be revised from one
should coordinate slope paving treatments with contract to the other unless there is a project-
the Abu Dhabi Road Section. specific requirement.

1105 SWEET SAND COVERING 1106.03 BENCHES

In general, all proposed green areas shall be Benches provide resting facilities for pedestrians,
covered with a 30 cm minimum depth of sweet much needed in Abu Dhabi in view of the warm
sand at the finish grade. climate. There are three types of benches
designed for the Abu Dhabi Roadway Section
The Designer shall calculate the quantity of sweet projects, Type A, Type B and Type C.
sand required for the project. The General Plan
drawings will show the green areas included in the 1106.03.01 Type A bench
project.
This type of bench is comprised of two precast
1106 STREET FURNITURE concrete ends and wood slats (over aluminum
tubes), and does not have a backrest. The Type A
bench is always used in combination with the
1106.01 GENERAL
Type B bench, except when it is used at taxi
stops.
Street furniture to be provided as part of the Abu
Dhabi Roadway Section projects includes
1106.03.02 Type B bench
benches, bus shelters, telephone booths and
sidewalk lighting. The purpose is to provide
This type of bench includes a back rest, a planter
pedestrian amenities and to enhance the urban
and a waste receptacle. Basic elements of the
environment with street furniture that has a
bench itself are the same as the Type A bench,

Part 2 1100-2
ROADWAY DESIGN MANUAL Roads and Bridges

except for the back rest and higher ends. The Bus shelters are to be placed at every bus stop
Type B bench is also used in combination with a except where space limitations prohibit their use.
Type A bench to create a small gathering place They are to be located at the far (downstream,
for a group of people. according to the direction of traffic) end of the
bus stop with one meter from the edge of the
1106.03.03 Type C bench curb.

This type of bench is comprised of the same 1106.05 TELEPHONE BOOTHS


elements as a Type A bench except it is used only
in bus shelters. Foundations for telephone booths will be provided
in road projects, the telephone booth and
Subject to space availability, basic criteria for operating equipment are the responsibility of
placement of benches are as follows: Etisalat.

1. Two combination Type A/Type B benches Etisalat determines locations and quantity of
are placed at every intersection, with each in telephone booths to be included in each Contract
different quadrant (preferably diagonal as approved by the Road Section.
quadrants).
2. If space does not permit the above 1107 NOISE ABATEMENT
arrangement, a Type B bench is placed in the
same fashion. The Designer and the Abu Dhabi Road Section
3. At least two Type B benches are placed at shall review any noise abatement requirements on
each side of the main road between two a project specific basis. In general, the Designer
intersections. is to mitigate, as much as possible, any increase
4. Two Type C benches are placed within each in the traffic noise, especially in residential
bus shelter (considered as part of and paid neighborhoods.
under bus shelters).
5. One Type A bench is placed at each taxi stop. In special circumstances involving sensitive areas,
depressed roadways or noise abatement walls may
1106.04 BUS SHELTERS be required.

Bus shelters are placed on bus stop sidewalks to


provide shade and seating for bus passengers.

Part 2 1100-3
ROADWAY DESIGN MANUAL Roads and Bridges

PART 3 AASHTOAmerican Association of State


Highway and Transportation Officials Standard
STRUCTURE DESIGN Specifications for Highway Bridges, 15th Edition
-1992, including all Interim Specifications to
date.
SECTION 100
DESIGN CRITERIA ApprovalApproval as obtained from the Abu
Dhabi Roads Section Project Manager.
101 GENERAL
Drainage ReportThe Drainage Report as
101.01 PURPOSE produced by the Bridge Drainage Section or,
when applicable, by a consultant.
The purpose of this section is to provide Bridge
Design Criteria in order to establish a uniform Geotechnical ReportThe Geotechnical Report
project design and construction policy that will including the Foundation Design Report as
aid the Consultant in the preparation of final produced by the Geotechnical Section or by a
design, plans and specifications, and insure safe consultant.
and uniform structural capacity throughout the
project. Special ProvisionsThe Special Provisions to
the Standard Project Specifications as specifically
Structures shall be designed in accordance with written for each individual project.
the latest edition, including revisions, of the
Standard Specifications for Highway Bridges - Standard SpecificationsThe Standard Project
published by the American Association of State Specifications
Highway and Transportation Officials
(AASHTO) and the Structural Design Standards AASHTO Specifications for Structural
included herewith in Part 3 of this Roadway SupportsThe AASHTO Standard
Design Manual. The design shall be based on the Specifications for Structural Supports for
latest edition of the AASHTO specifications as Highway Signs, Luminaries and Traffic Signals,
existing on the date of the design contract. The latest Edition.
Structural Design Standards presented hereunder
shall govern over the AASHTO Specifications 101.03 BRIDGE TYPES
wherever the are At Variance With or In
Addition To the AASHTO Specifications. Bridge DefinitionA Bridge is defined as a
structure including supports erected over a
These criteria set forth minimum standards. The depression or an obstruction, as water, highway
Consultant may propose more conservative or railway and having a track or passageway for
criteria if, in his judgment, such criteria are carrying traffic or other moving loads and having
required. However, all deviations from the an opening measured along the center of the
criteria must be justified and receive prior roadway of more than 6.00 meters between
approval from the Abu Dhabi Roads Section undercopings of abutments or springlines of
Project Manager. arches or extreme ends of openings for multiple
boxes; it may include multiple pipes, where the
101.02 DEFINITIONS clear distance between openings is less than half
of the smaller contiguous opening.
The following definitions and abbreviations are
provided to clarify usage of terms and to avoid BridgeThe term bridge is usually reserved
the need for excessive verbiage. for structures over water courses or canyons.

OverpassA structure carrying the principal


route over a highway street or railroad.

Part 3 100-1
ROADWAY DESIGN MANUAL Roads and Bridges

UnderpassA structure which provided for 102.03.01 Highway Traffic Structures


passage of the principal route under a highway,
street, railroad or other feature. The design vertical clearance to structures
passing over Freeways, Highways and all Rural
Traffic InterchangeAn overpass or underpass and Urban Arterials shall be at least 6.00 meters
is also called a T.I. if on and off ramps are over the entire roadway width, including auxiliary
provided to the intersecting roadway. lanes and shoulders. An allowance of 150
millimeters is included to accommodate future
ViaductA structure of some length carrying a resurfacing. This allowance may be waived if the
roadway over various features such as streets, roadway under the structure is surfaced with
waterways or railroads. portland cement concrete.

TunnelA structure carrying a roadway through The design vertical clearance to structures
a hill or mountain. passing over all other highways and streets shall
be at least 5.50 meters over the entire roadway
Pedestrian OverpassA structure carrying a width, including auxiliary lanes and shoulders.
pedestrian walkway over a roadway. An allowance of 150 millimeters is included to
accommodate future resurfacing. This allowance
Pedestrian UnderpassA structure which may be waived if the roadway under the structure
provides for passage of a pedestrian walkway is surfaced with portland cement concrete.
under a roadway.
Certain routes have been designated as truck
102 DESIGN FEATURES routes. On these routes, larger vertical clearance
must be maintained. For future projects, these
102.01 GENERAL routes will be identified by the Abu Dhabi Roads
Section Project Manager during the concept
The general features of design shall be as stage.
specified in Section 2 of AASHTO except as
clarified or modified in this manual. 102.03.02 Pedestrian Overpasses

102.02 DESIGN METHODS Because of their lesser resistance to impacts, the


minimum design vertical clearance to pedestrian
ALL BRIDGE MEMBERS ARE TO BE overpasses shall be 6.00 meters regardless of the
DESIGNED IN ACCORDANCE WITH highway system classification. An allowance of
AASHTO AND THE REQUIREMENTS OF 150 millimeters is included to accommodate
THIS MANUAL. (Other standards may be future resurfacing.
allowed with Department approval.)
102.03.03 Railroad Overpasses
102.03 VERTICAL CLEARANCE AT
STRUCTURES Structures over railways shall provide a minimum
(AASHTO 2.2.3) clearance of 7.00 meters above top of rail, except
that overhead clearance greater than 7.00 meters
The following are minimum vertical clearance may be approved when justified on the basis of
standards for highway traffic structures, railroad electrification. No additional allowance
pedestrian overpasses, railroad overpasses, shall be provided for future track adjustments.
tunnels and sign structures. Lesser clearances
may be used only under very restrictive
conditions, upon individual analysis and with the
approval of the Abu Dhabi Roads Section Project
Manager.

Part 3 100-2
ROADWAY DESIGN MANUAL Roads and Bridges

102.03.04 Tunnels 102.06 APPROACH SLABS

The minimum design vertical clearance for Concrete approach slabs shall be used on all
tunnels shall be at least 6.00 meters for freeways structures. Approach slabs serve a dual purpose
and arterials and at least 5.50 meters for all other of providing a transition structure from the bridge
highways and streets. to the approach roadway should the roadway
embankment settle and of eliminating the live load
102.03.05 Sign Structures surcharge of the abutment backwall when the
conditions specified in AASHTO 3.20.4 are
Because of their lesser resistance to impacts, the satisfied. Approach slabs are to be designed
minimum design vertical clearance to sign using the Service Load Design Method and shall
structures shall be 6.00 meters regardless of the cover the entire roadway width including the
highway system classification. An allowance of shoulders, from wingwall to wingwall.
150 millimeters is included to accommodate
future resurfacing. 102.07 ANCHOR SLABS

102.03.06 Width (AASHTO 2.3.1) When approach roadways are paved with
portland cement concrete pavement (PCCP),
The horizontal clear width for rural bridges where adequate means shall be provided to prevent
approach guardrail is used shall provide an pavement growth from causing damage to the
additional width on each side of the approach bridge. Use of a properly designed anchor slab is
roadway width to allow the bridge rail to line up one means of providing such protection
with the approach guardrail. The horizontal clear
width for urban bridges, in which curb and gutter 102.08 DECK DRAINAGE
and/or sidewalks are used, shall equal the
approach roadway width. On grade separation structures, roadway drains
shall not discharge water onto unprotected
102.04 RAILINGS (AASHTO 2.7) embankment slopes or within five meters of the
traveled roadway below, nor shall drains be
In general, concrete barrier should be used as a located less than 1.5 meters from the centerlines
vehicular railing. For situations requiring a of abutments or piers. In urban areas collection
different barrier type, only FHWA crash test of deck drainage in a pipe system may be
approved bridge rails are allowable alternatives. required, with down drains in or on pier columns
discharging into storm drainage collector systems.
Bridge rails shall be constructed vertical. Consideration should always be given to provide
Concrete barriers shall not be slipformed. For collector drains and discharge systems on the
cast-in-place, post-tensioned concrete bridges, approach roadway gutter rather than on the
barriers shall be cast after post-tensioning and bridge.
may be cast before falsework removal.
For bridges with sidewalks, expansion joints shall
102.05 CONCRETE BARRIER be turned up at the curb line to prevent roadway
TRANSITIONS water from entering sidewalk areas. Appropriate
means shall be taken to ensure that sidewalk
Transitions from bridge concrete barrier to drainage does not pond and that the water does
approach guardrail should, when practical, be not escape around the wing walls and erode the
located on the bridge, approach slab or embankment.
wingwalls.
For deck drainage design criteria, refer to the
ROADWAY DESIGN MANUAL - Drainage.

Part 3 100-3
ROADWAY DESIGN MANUAL Roads and Bridges

102.09 WING WALLS 102.12 CONCRETE CRACK CONTROL

Wing walls shall extend 1.50 meters beyond the Maximum flexural crack width at the tensile face
catch point, where catch point is defined as the of a reinforced concrete section shall not exceed
intersection of the fill slope in front of the 0.25mm for normal conditions of exposure and
abutment with the finished approach grade at the 0.20mm for marine and unfavorable conditions of
outside face of the wing wall. The bottom of the exposure (such as alternate wetting and drying,
wing walls shall be embedded a minimum of 1 humid atmosphere, direct contact with soil, etc.).
meter into the approach fill at the end of the wing The allowable crack width can be increased by
walls. 25% under earthquake/wind/temporary
construction conditions.
102.10 LIGHTING
102.13 CORROSION PROTECTION
Consideration shall be given to special lighting (AASHTO 8.22)
above and below the structure. This lighting shall
serve as ornamental lighting to enhance the Due to the adverse corrosive environment, all
aesthetics and also to enhance safety. This reinforced concrete structures shall use epoxy
lighting is in additional to the normal roadway coated rebar unless otherwise directed by the
lighting. Refer to the lighting section of this Project Manager.
manual for roadway lighting criteria.
Coordination of all structure lighting with existing 103 ARCHITECTURAL
and/or planned lighting of connecting and CONSIDERATIONS
adjacent roads must be considered.
103.01 PROCEDURE
102.11 BRIDGE DECK ELEVATIONS
Following the approval of the civil and basic
The project design group shall prepare either structural concepts for an interchange, including
computer plotted contours at 0.1 meter intervals configuration, alignment, profile and pier
at a 1:50 scale or tabulate elevations at 3.0 meter locations, the Project Design Manager will meet
intervals along the profile grade line, with with the Structural, Architectural, and Graphics
additional elevation points on each perpendicular Design Managers to develop basic alternatives
(radial) such that the bridge can be completely and set architectural design parameters.
covered with 0.1 meter contours. The number of Environmental constraints and influences will be
elevation points on each perpendicular must be established. The Concept Design Team will
such that the lowest, or the highest, point is determine the number of structural concepts and
outside the bridge for use by the construction architectural options to be studied. The purpose
supervision staff to help check the contractors of these studies will be do develop applicable
geometric layout. concepts and options in the form of presentation
displays, to be used as a basis for the Abu Dhabi
Roads Section review and decision making. The
approved displays are submitted to the Abu
Dhabi Roads Section for review and selection of
the desired alternative. The approved scheme the
will progress to the preliminary and final design
phases.

Part 3 100-4
ROADWAY DESIGN MANUAL Roads and Bridges

103.02 GENERAL CRITERIA

Every effort should be made in the treatment of


structures to respect the Islamic design and
culture.

Design concepts should be easily implemented.


Construction considerations are also taken into
account in the architectural treatment concepts.
Architectural elements should be functional,
durable and easily maintained.

Each structure should have individuality;


however, a totally different design is not required
for each structure. It is desirable to maintain a
sense of continuity throughout the whole
program.

Architectural treatment should be continuous


through an interchange.

In the downtown area, underpasses spanning a


given roadway should have similar treatment to
establish continuity. Decorative and median
lighting should be similar on overpasses along a
given route.

Part 3 100-5
ROADWAY DESIGN MANUAL Roads and Bridges

SECTION 200 201.06 STRUCTURE LOADINGS


DESIGN LOADS
1. Highway Bridge Live Load: AASHTO 20-44
increased by 25 percent.
201 LOAD TYPES
2. Wind Velocity: 160 kilometers per hour.
3. Humidity Range: 25 percent to 100 percent.
201.01 GENERAL
4. Earth Pressure: For specific project
Loads shall be as specified in Section 3 of recommendations, refer to Soils Report
AASHTO except as clarified or modified in this 5. Future Utilities: 75 kg/m of Bridge Deck.
manual. 6. Earth Weight: 1920 kg/m3
7. Earthquake Loading: Only to be considered
201.02 DEAD LOADS (AASHTO 3.3.1) if directed by the Road Section Project
Manager.
Utility loads shall be included as applicable.
201.07 FRICTION FORCES
201.03 FUTURE WEARING SURFACE (AASHTO 3.9.2)
(AASHTO 3.3.3)
Friction forces due to elastomeric bearing pads or
All new structures shall be designed to carry an TFE surfaces shall be based on the
additional dead load of 120 kg/m2 from curb to Manufacturers data for the bearing used.
curb of roadway to allow for a future wearing
surface. This load is in addition to any wearing 201.08 THERMAL FORCES
surface which may be applied at the time of (AASHTO 3.16)
construction. The weight of the future wearing
surface shall be excluded from the dead load for 1. Temperature Range: 70C.
deflection calculations. 2. Temperature Fall: 30C to 0C = 30C.
3. Temperature Rise: 30C to 70C = 40C.
201.04 WEARING SURFACE 4. The temperature gradient between the top
(AASHTO 3.3.5) slab and bottom slab of concrete box girder
bridges is 20C.
The top 15 millimeters of the deck shall be
considered as a wearing surface. The weight of 201.09 STREAM FORCES
the wearing surface shall be included in the dead (AASHTO 3.18.1)
load but the 15 millimeter shall not be included in
the depth of the structural section for all strength A Drainage Report shall be produced by Bridge
calculations including the deck, superstructure Drainage Section or a consultant, when
and the pier cap, where appropriate. appropriate, for all stream and/or channel
crossings. The designer should review the
201.05 HIGHWAY LOADS Drainage Report for a full understanding of
(AASHTO 3.7.1.1) waterway considerations. The report should
contain as a minimum, the following information
P Loads (permit design live loads) are special for both the critical flow and superflood
vehicular loads that will be applied only to conditions:
specific structures, such as interchange ramps,
and at the direction of the Abu Dhabi Roads High water elevation
Section. Mean Velocity
Scour Elevations (General and Local)
Angle of attack
Required bank protection
Special drainage considerations
Horizontal and Vertical Clearances

Part 3 200-1
ROADWAY DESIGN MANUAL Roads and Bridges

Direction of Flow the bridge in the stream width. Local pier and
abutment scour occurs locally at substructure
For design for the most critical flow and the units due to the turbulence caused by the presence
superflood condition, the following criteria shall of the substructure unit.
be used unless more severe criteria is
recommended in the Drainage Report. Bridges over natural water courses shall be
investigated for four different streambed ground
Design calculations of stream forces on piers over lines. Refer to Figure 200.01 for an illustration
natural water courses shall assume a 0.6 meter of these cases.
increase in pier width per side due to blockage by
debris with a shape factor k = 1.40 for the first Case 1 represents the as-constructed stream
3.5 meters of depth. For flows with depths cross section. For this case, the bridge shall be
greater than 3.5 meters, only the top 3.5 meters designed to withstand the forces from the
shall be assumed blocked by debris with lower AASHTO Groups I to VII load combinations.
sections using the actual pier width and a shape
factor in accordance with AASHTO. For Case 2 represents the long term dry streambed
uncased drilled shafts, a 20% increase in diameter cross section, i.e. the as-constructed stream
should be assumed to account for possible cross section minus the depth of the general
oversizing of the hole and any irregular shape. scour. For this case, the bridge shall be designed
The force distribution on the pier shall be to withstand the same forces as for Case 1. The
assumed to vary linearly from the value at the requirements contained in AASHTO 4.4.5.2 need
water surface to zero at the bottom of the scour not be met.
hole as described in AASHTO.
Case 3 represents the streambed cross section
When the clear distance between columns or condition for the most critical design flow.
shafts is 5.00 meters or greater, each column or Abutment protection is designed to withstand this
shaft shall be treated as an independent unit for event and abutments may be assumed to be
stream forces and debris. When the clear distance protected from scour for this condition. Piers will
is less than 5.00 meters the greater of the two experience the full general and critical flow local
following criteria shall be used: 1) Each column scour. For this case, the bridge shall be designed
or shaft acting as an independent unit or 2) All to withstand the forces from the AASHTO
columns or shafts acting as one totally clogged Groups I to VI load combinations.
unit with 0.6 meters of debris normal to the flow
added on each end. Case 4 represents the streambed cross section
conditions for the superflood condition. For this
The average main channel velocity for the case, all bank protection and approach
appropriate flow condition shall be used in embankments are assumed to have failed.
calculating the stream forces. The water surface Abutments and piers should be designed for the
elevation shall be the high water elevation for the superflood scour assuming all substructure units
appropriate flow condition. A minimum angle of have experienced the maximum scour
attack of 15 degrees shall be assumed. simultaneously. For this case, the bridge shall be
designed to withstand the following forces: DL +
Scour may be categorized into two main types: SF + B + 0.5W. For members designed using the
general and local. General scour is the permanent WSD Method an allowable overstress of 140%
loss of soil due to degradation or mining while shall be used. For members designed using the
local scour is the temporary loss of soil during a LFD Method a gamma factor of 1.25 shall be
peak flow. Local scour may consist of two types: used.
contraction scour and local pier or abutment
scour. Contraction scour occurs uniformly across

Part 3 200-2
ROADWAY DESIGN MANUAL Roads and Bridges

Figure 200.01
Groundline Variations Due to Scour

201.10 LATERAL EARTH PRESSURE Roads Section Project Manager, a minimum


(AASHTO 3.20.1) differential settlement of 25mm may be used in
the design.
For backfills compacted in conformance with the
Standard Specifications, active pressure for Differential settlement, if required, shall be
unrestrained walls should be calculated using an considered the same as temperature and shrinkage
internal angle of friction of 33 degrees unless forces and included in Group IV, V and VI load
recommended otherwise in the Geotechnical combinations.
Report.
201.12 EARTHQUAKES
201.11 DIFFERENTIAL SETTLEMENT (AASHTO 3.21)
(AASHTO 3.3.2.1)
Earthquake criteria will only be considered in the
Differential settlement shall be considered in the design process at the direction of the Road
design when indicated in the Geotechnical Report. Section Project Manager. If so directed, reference
The Geotechnical Report should provide the is made to AASHTO Division 1-A.
magnitude of differential settlement to be used in
the design. If not addressed in the Geotechnical
Report, and at the direction of the

Part 3 200-3
ROADWAY DESIGN MANUAL Roads and Bridges

202 DISTRIBUTION OF LOADS In calculating bending moments in multi-beam


precast concrete bridges, conventional or
Loads shall be distributed as specified in Section prestressed, no longitudinal distribution of wheel
3 of AASHTO except as clarified or modified in load shall be assumed.
this manual.
The live load bending moment for each section
202.01 SUPERIMPOSED DEADLOAD shall be determined by applying to the beam the
DISTRIBUTION fraction of a wheel load (both front and rear)
(AASHTO 3.23.2.3.1.1) determined by the following relations:

The weight of curbs, barriers and sidewalks for Load Fraction = S


an I-Girder bridge with composite concrete deck D
shall be distributed as follows:
Where
i) Equally over all girders
ii) Equally over all girders under the sidewalk S = 12 NL + 9
iii) If there is no sidewalk, curb and barrier shall Ng
be distributed 60% to the exterior girders and
40% to the interior girders. D = 5 + NL + ( 3- 2NL ) ( 1-C ) 2 when C<3
10 7 3
Each girder shall be designed for the condition
that causes highest stresses. Girders shall in no D = 5 + NL when C>3
way be designed for loads less than that specified 10
in AASHTO Section 3.
NL = total number of traffic lanes from
202.02 CONCRETE BOX GIRDERS AASHTO Article 3.6
(AASHTO 3.23.2.3.2.2)
Ng = number of longitudinal beams
In calculating the number of lanes of live load on C = K(W/L), a stiffness parameter
the superstructure, the entire cross section of the
superstructure shall be considered as one unit W = overall width of bridge in meters
with the number of lanes of live load equal to the
out-to-out width of the deck in meters divided by L = span length in meters
4.27. Do not reduce this number for multiple
lanes as specified in AASHTO 3.12.1 nor round Values of K To Be Used in C = K(W/L)
to a whole number as specified in AASHTO Bridge Type Beam Type K
3.6.3. Multi-Beam Non-Voided Rect 0.7
Rect. w/ Circular Voids 0.8
202.03 PRESTRESSED VOIDED SLABS Box Section 1.0
(AASHTO 3.23.4.3) Channel 2.2

The equations for distribution of live load


202.04 PRESTRESSED BOX BEAMS
contained in the Fifteenth Edition (1992)
(AASHTO 3.23.4.3)
including the 1993 and 1994 Interims shall not be
used. The new distribution factors in the latest
The equations for distribution of live load
edition, initially changed in the Fourteenth Edition
contained in the Fifteenth Edition (1992)
(1989), are based on tests on T-beams and are not
including the 1993 and 1994 Interims, shall not
deemed appropriate for voided slabs or box
be used. Refer to Distribution of Loads in
beams. Instead, the equations in the Thirteenth
Section 202.02 of this manual for criteria on
Edition (1983) as repeated below shall be used to
distribution of loads.
distribute live loads:

Part 3 200-4
ROADWAY DESIGN MANUAL Roads and Bridges

202.05 LATERAL TENSIONING OF 1. (Gamma) Factor


MULTI-BEAM UNITS
(AASHTO 3.23.4.1) The (gamma) factor is the most basic of the
three. It varies in magnitude from one load
Each lateral tensioning tie shall consist of a 38 combination to another, but it always applies to
millimeter diameter mild steel bar tensioned to all the loads in a combination. Its main effect is
13,560 kg. Tension in the 38 millimeter diameter stress control that says we do not want to use
mild steel should be applied by the turn of nut more than about 0.8 of the ultimate capacity. Its
method. The designer should determine the most common magnitude, 1.3 lets us use 77%.
number of turns of the nut required to achieve the Earthquake loads are not factored above 1.0
13,560 kg force. This value should be shown on because we recognize that stresses in the plastic
the plans. range are allowed, as long as collapse does not
occur.
A36M steel bars for the tie normally come in 6
meter lengths. the final total length of the tie An example may be given to justify the use of
should be made using threaded couplers; not gamma of 1.3 for dead load. Assuming the live
welded splices. When couplers are used, the hole load being absent, the probable upper value of the
through the diagram should be increased from the dead load could be a minimum of 30% greater
normal 64 millimeter to 102 millimeter diameter than calculated. For a simple structure this
to accommodate the couplers. percentage may be as follows:

Adequate means shall be used to ensure that the 10% due to excess weight.
ties are adequately protected from corrosion. the 5% due to misplaced rebar
rod, nut and bearing plate shall be galvanized in 5% structure behavior approximation
accordance with ASTM A153 (AASHTO M- 10% stress increase (actual vs. calcs.)
232). 30% Total variation assumed to occur
concurrently at the section most
202.06 LIVE LOAD DISTRIBUTION heavily stressed.
(AASHTO 3.6.3 AND 3.12.1)
2. (Beta) Factor
In designing the superstructure, the live load
distribution factors shall not be reduced for The second factor, (beta), is a measure of the
multiple lanes as specified in AASHTO 3.12.1 or accuracy with which we can predict various kinds
rounded to a whole number as specified in of loads. It also reflects the probability of one
AASHTO 3.6.3. These two reductions apply to loads simultaneous application with others in a
substructure design only. combination. It applies separately, with different
magnitudes, to different loads in a combination.
203 LOAD FACTORS For example, it is usually 1.0 for dead load. It
varies from 1.0 to 1.67 for live loads and impact.
An essential feature of Load Factor Design (LFD)
requires raw design loads or related internal Due regard has been given to sign in assigning
moments and forces to be modified by specified values to beta factors, as one type of loading may
load factors (, gamma and , beta), and produce effects of opposite sense to that produced
computed material strengths to be reduced by by another type. The load combinations with
specified reduction factor (, phi). D=0.75 are specifically included for the case
where a higher dead load reduces the effects of
These are safety factors which ensure certain other loads.
margins for variation. The three different kinds
of factors are each set up for a distinct purpose,
each independent of the other two. In this way,
any one of them may be refined in the future
without disturbing the other two.

Part 3 200-5
ROADWAY DESIGN MANUAL Roads and Bridges

The beta factors for prestressing force effects are


set so that when multiplied by the respective
gamma factor, the product is unity. Beta of 1.67
for live load plus impact from H loads reflects
AASHTOs way of handling permit loads.

3. (Phi) Factor

(phi), the third factor, relates to materials and is


called either a capacity reduction factor or a
strength reduction factor. Its purpose is to
account for small adverse variations in material
strength, workmanship, and dimensions. It
applies separately to different magnitudes for
various load effects in reinforced concrete, and
various manufacturing processes in prestressed
concrete. Since relates to materials rather than
loads, its values are given in the various material
specifications. For structural steel it is almost
always 1.0. For concrete it varies from 0.7 to
1.0.

Part 3 200-6
ROADWAY DESIGN MANUAL Roads and Bridges

SECTION 300 301.03 DESIGN METHODS


(AASHTO 8.14.1)
REINFORCED CONCRETE
In accordance with the applicable provisions of
301 GENERAL AASHTO, the Strength Design Method (LFD)
shall be used for the design of all reinforced
Reinforced concrete design criteria shall be as concrete members except where such members
specified in Section 8 of AASHTO except as are to be below grade or intended for water
clarified or modified in this manual. retention, then the Service Load Design Method
shall be used.
301.01 CONCRETE (AASHTO 8.2)
301.04 REINFORCEMENT
Concrete for highway structures shall have the (AASHTO 8.15.2.2)
following minimum cylinder strengths, unless
otherwise directed by the Project Manager: Concrete shall be reinforced only with fusion
bonded epoxy coated reinforcement steel
Decks except barriers f c = 280 kg/cm2 conforming to AASHTO M 31M (ASTM
Abutments f c = 210 kg/cm2 A615M) Grade 400 as follows:
Piers except footings f c = 280 kg/cm2
Drilled Shafts f c = 280 kg/cm2 Deformed Round Steel Bar Reinforcement,
All other f c = 210 kg/cm2 AASHTO M 31M Grade 400

For Design Load use Concrete Weight = 2500 fy = 4 080 kg/cm2


kg/m3 fu = 6 120 kg/cm2
fs = 1 680 kg/cm2 T or C in beams
Class K 250 Concrete Design Parameters Es = 2 039 470 kg/cm2

f c = 210 kg/cm2 Spiral Reinforcement and Welded Wire


fc = 80 kg/cm2 Fabric
Ec = 220 000 kg/cm2
Steel Bars used as Spirals, AASHTO M
Class K 335 Concrete Design Parameters 31M Grade 400

f c = 280 kg/cm2 Steel Wire used as Spirals, AASHTO M


fc = 110 kg/cm2 32
Ec = 255 000 kg/cm2
Welded Wire Fabric used as reinforcement
Class K 415 Concrete Design Parameters in concrete and mortar, AASHTO M 55

f c = 350 kg/cm2 302 SLAB DESIGN


fc = 140 kg/cm2
Ec = 283 000 kg/cm2 Slabs shall be designed in accordance with the
criteria specified in Section 3 of AASHTO except
301.02 DIAPHRAGMS (AASHTO 8.12.3) as clarified or modified below.

Reinforced concrete box girder diaphragm criteria All reinforcing bars are to be epoxy coated bars.
shall be the same as for post-tensioned box All reinforcing bars shall be straight bars top and
girders as specified under Diaphragms in Section bottom. The use of truss bars will not be
402.06 of this manual. permitted.

Part 3 300-1
ROADWAY DESIGN MANUAL Roads and Bridges

For skews less than or equal to 20 degrees the 302.03 PROTECTION AGAINST
transverse bars shall be placed parallel to the CORROSION
skew. For skews greater than 20 degrees the (AASHTO 8.22.1)
transverse bars shall be placed normal to the
girders. The minimum clearance for top reinforcing in
new decks shall be 50 millimeters with 50
Use of steel stay-in-place forms should be millimeter Asphaltic wearing surface and the
considered during design for steel girder or minimum specified concrete strength (f c) shall
precast girder bridges for special conditions only. be 280 kg/cm2.
Some circumstances which warrant such
investigation include: bridges over heavily 302.04 DISTRIBUTION METHOD
traveled roads, bridges over live streams and (AASHTO 3.24.3)
bridges over deep canyons. A discussion on their
use shall be made in the Design Concept Report. Use the AASHTO method for load distribution
If use of steel stay-in-place forms is not on slabs except for unusual loads or unusual
recommended during design, they will not be structures such as single cell boxes.
allowed during construction due to the extra dead
load. Contractor requests for usage during 302.05 RAILING LOADS
construction will not be approved. (AASHTO 3.24.5.2)

302.01 SPAN LENGTHS When barriers are located at the deck edge, the
(AASHTO 3.24.1.2) deck shall be designed to resist both the axial
force and the bending moments due to all dead
The deck slab span length for AASHTO loads and horizontal rail load or due to all dead
girders shall be the clear distance between the loads plus vertical wheel loads, whichever is
top flanges plus one-half the flange width. critical.

302.02 SLAB THICKNESS


(AASHTO 8.11.1)

The thickness of new deck slabs shall be


designed in 10 millimeter increments with the
minimum thickness as shown below, unless
otherwise directed by the Project Manager.

Slab Thickness
S(m) t(mm)

Up to 1.800 190
1.801 to 2.100 200
2.101 to 2.400 210
2.401 to 2.700 220
2.701 to 3.000 230
3.001 to 3.300 240
3.301 to 3.600 250
3.601 to 3.900 260

Where S = Design span as defined in AASHTO


3.24.1 and above.
t = Minimum thickness of deck slab.

Part 3 300-2
ROADWAY DESIGN MANUAL Roads and Bridges

SECTION 400 401.02 ALLOWABLE STRESSES


CONCRETE (AASHTO 9.15.2.2)
PRESTRESSED CONCRETE
The maximum allowable tensile stresses in a
401 DESIGN CRITERIA precompressed tensile zone at service load after
losses have occurred shall be in accordance with
401.01 GENERAL AASHTO except as modified below:
Prestressed design criteria shall be as specified
in Section 9 of AASHTO except as clarified or Tension
modified in this manual. Load Condition Allowable
Stress
Members shall be designed to meet both Service Girder DL + Prestress 0
Load Design and Strength Design (Load Factor Total Service Load 0.8 'c
Design) criteria as specified in AASHTO.

Prestressing steel for precast prestressed 401.03 SHEAR (AASHTO 9.20)


members and cast-in-place post-tensioned
members shall be 12.50 millimeter diameter Shear design shall be in accordance with
"Uncoated Seven-wire High Tensile Cold Ultimate Strength Design Method contained in
Drawn Low Relaxation Strand for Prestressed the latest AASHTO Specifications.
Concrete" as specified in ASTM A416, Grade
270 with f c = 18 360 kg/cm2 and Eps = 2 Prestressed concrete members shall be
039 470 kg/cm2. Use of 15.20 millimeter reinforced for diagonal tension stresses. Shear
diameter strand is allowed for cast-in-place reinforcement shall be placed perpendicular to
post-tensioned members only. the axis of the member with spacing not-to-
exceed three-fourths the depth of the member.
The yield point stress of prestressing steel, f*y,
may be assumed equal to 0.90 f c for low The critical sections for shear in simply
relaxation strand. supported beams will usually not be near the
ends of the span where the shear is a maximum,
Prestress losses shall be calculated in accordance but at some point away from the ends in a
with AASHTO Article 9.16.2.1. The estimated region of high moment.
losses contained in Table 9.16.2.2 and Article
9.16.2.2 shall not be used. For the design of web reinforcement in simply
supported members carrying moving loads, it is
Section properties shall be based on gross area of recommended that shear be investigated only in
members. Use of the transformed area of bonded the middle half of the span length. The web
reinforcement shall only be used for unusual reinforcement required at the quarter points
structures and only when approved. should be used throughout the outer quarters of
the span if the critical shear section is included
Web reinforcement for shear shall consist of within the design section.
rebars; not welded wire fabric.
For continuous bridges whose individual spans
The minimum top cover for slab reinforcement consist of precast prestressed girders, web
specified in AASHTO Article 9.25.1.2.1 shall be reinforcement shall be designed for the full
50 millimeters with 50 millimeter Asphaltic length of interior spans and for the interior
wearing surface. three-quarters of the exterior span and based on
the critical shear design section.
Expansion and contraction design criteria shall be
as specified in Part 3, Section 600 of this manual.

Part 3 400-1
ROADWAY DESIGN MANUAL Roads and Bridges

402 POST TENSIONED BOX normal to girder for sloping exterior webs).
GIRDER BRIDGES Interior webs shall be constructed vertical.

402.01 GENERAL 402.06 DIAPHRAGMS (AASHTO 9.10)

Post-Tensioned Box Girder Bridges shall be A single 250 millimeter thick intermediate
designed in accordance with AASHTO diaphragm shall be placed at the midspan for all
specifications. Girders shall be designed by bridges. Special consideration for additional
Working Stress Method and checked by the diaphragms should be given to box girders with
Ultimate Strength Method (Load Factor Design). large skews, curved boxes and boxes over 2
The deck slab is to be designed by the Working meters in depth. Diaphragms shall be placed
Stress Method. parallel to abutments and piers for skews less
than or equal to 20 degrees and normal to girders
402.02 CONCRETE and staggered for skews over 20 degrees.
(AASHTO 9.2 AND 9.22) Diaphragms shall be cast integral with girder
The following concrete strengths are the desired webs.
strengths to be used. Higher strengths may be
used if approved by the Abu Dhabi Roads Section 402.07 DEFLECTIONS (AASHTO 9.11)
Project Manager.
The deflection shall be calculated using dead load
Initial 2
f c = 290 kg/cm minimum. including barriers, but not the future wearing
surface, gross section properties and calculated
Final f c = 350 kg/cm2 minimum final losses. The additional long term deflection
f c = 420 kg/cm2 maximum shall be calculated by multiplying the deflection
by two. An additional parabolic shaped
402.03 BEARING PADS deflection with a peak equal to 30 millimeters per
100 meters should be added to the total deflection
Allow an extra 80mm movement per 100 meters for simple spans. The final long term deflection
of girder length for long-term creep and shall be the sum of the deflection, the additional
shortening due to post-tensioning. long term deflection and the additional deflection
for simple spans. The camber shown on the plans
402.04 CREEP AND SHRINKAGE shall be the final long term deflection.
(AASHTO 9.4)

For restrained members in continuous bridges 402.08 ALLOWABLE STRESSES -


where shortening due to post-tensioning induces PRESTRESSING STEEL
moments and shears, a shrinkage and creep (AASHTO 9.15.1)
coefficient of 1.5 shall be used for design of
substructure elements with the total movement In calculating the stress in the prestressing steel
equal to 1.5 times the initial shortening. For after seating, the friction and anchor set losses
superstructure elements, no creep factor should be only should be included. For post-tensioned
applied except for long term deflection members, overstressing for short periods of time
considerations. to offset seating and friction losses is permitted
but the maximum allowable jacking stress for low
402.05 FLANGE AND WEB relaxation strand shall be limited to 0.78 f s.
THICKNESS - BOX GIRDERS
(AASHTO 9.9) 402.09 ALLOWABLE STRESSES-
CONCRETE (AASHTO 9.15.2)
Minimum top slab thickness shall be 200
millimeters. Minimum bottom slab thickness In calculating the temporary stress in the concrete
shall be 150 millimeters. Minimum web before losses due to creep and shrinkage, the
thickness shall be 300 millimeters (measured friction, anchor set and elastic shortening losses
should be included.

Part 3 400-2
ROADWAY DESIGN MANUAL Roads and Bridges

Special consideration shall be given to bridges Calculations shall include the shear due to
supported on falsework with large openings where secondary moment and cable shear. For curved
deflections could be harmful to the structure. box girder bridges, the shear due to torsion shall
Unless falsework requirements are strengthened be included.
or other means taken to ensure the bridge does not
form tension cracks prior to tensioning, the 402.13 FLANGE REINFORCEMENT
maximum allowable tension in a precompressed (AASHTO 9.24)
tensile zone shall be limited to zero.
Reinforcing in the bottom slab of box girders
402.10 LOSS OF PRESTRESS shall conform to the provisions of AASHTO
(AASHTO 9.16) 8.17.2.3 except that the minimum distributed
reinforcing in the bottom flanges parallel to the
For multi-span bridges, the cable path should girders as specified in AASHTO 8.17.2.3.1 shall
have its low point at the midspan. Design should be modified to be 0.30 percent of the flange area.
be based on usage of galvanized rigid ducts with
K = 0.00000066 and = 0.25. Anchor set losses 402.14 METHOD OF ANALYSIS
should be based on 16 millimeter set.
The superstructure may be designed using the
For creep of concrete, the variable fcds should be system as described below:
calculated using the total dead load applied after 1) The bottom slab, in the vicinity of the
prestressing, including the 120 kg/m2 future intermediate support, may be flared to
wearing surface. increase its thickness at the face of the
support when the required concrete strength
402.11 FLEXURAL STRENGTH exceeds 320 kg/cm2. When thickened, the
(AASHTO 9.17) bottom slab thickness should be increased by
In determining the negative ultimate moment a minimum of 50 percent. The length of the
capacity, the top layer of temperature and flare should be at least one-tenth of the span
shrinkage and bottom layer of distribution length (measured from the center of the
reinforcing may be used. In determining the support) unless design computations indicate
positive ultimate moment capacity, the that a longer flare is required.
longitudinal flange reinforcing (AASHTO 9.24) 2) Section properties at the face of the support
may be used. should be used throughout the support; i.e.
the solid cap properties should not be
402.12 SHEAR (AASHTO 9.20) included in the model.
Girder webs will be designed for shear using the 3) Negative moments should be reduced to
Ultimate Strength Method according to the 1979 reflect the effect of the width of the integral
Interim AASHTO Standard Specifications. The support.
maximum girder web stirrup spacing will be 300
mm within 6 meters from the front face of the 4) Dead load forces should not produce any
abutment diaphragms. This will eliminate the tension in the extreme fibers of the
need for re-spacing the web stirrups at the point superstructure.
of web flare if the post-tensioning system requires
flaring. 5) The superstructure should be designed as a
unit with the number of live loads applied in
The value of "d" to be used in shear calculations accordance with Section 202.02 of this
shall be the larger of the calculated "d" value or manual.
0.8 times the overall effective depth.
For box girders with severe sloping webs or
Horizontal shear shall be investigated in boxes over 2 meter deep, transverse flange
accordance with the provisions of AASHTO forces induced by laterally inclined longitudinal
9.20.4. post-tensioning shall be considered in the design.

Part 3 400-3
ROADWAY DESIGN MANUAL Roads and Bridges

Single span structures should be jacked from one The Release Deflection equals the deflection the
end only. Symmetrical two span structures may prestress girder undergoes at the time of strand
be jacked from one end only or jacked from both release. The Release Deflection includes the dead
ends. Unsymmetrical bridges should be jacked load of the girder and the release prestressing
from one end or both ends as required by the force (including the effects of elastic shortening).
design. Three span or longer structures should
be jacked from both ends. The Initial Deflection equals the deflection the
prestress girder undergoes at the time of erection
Several prestressing systems should be checked prior to the diaphragm or deck pours. The Initial
to verify that the eccentricity and anchorage Deflection includes the deflection due to the dead
details will work. In determining the center of load of the girder, the initial prestressing and the
gravity of the strands, the Z factor, the difference effects of creep and shrinkage up to the time of
between the center of gravity of the strands and erection. The time of erection should be assumed
the center of the ducts, shall be considered. For to be 60 days after release.
structures over 120 meters in length, in
determining the c.g. of the strands, the diameter The Final Deflection equals the deflection due to
of the ducts should be oversized by 13 the dead load of the deck slab, diaphragms and
millimeters to allow for ease of pulling the barriers and the effects of long term creep on the
strands. composite girders. The effects of the 120 kg/m2
future wearing surface shall be excluded from
For horizontally curved bridges, special care deflection calculations.
shall be taken in detailing stirrups and duct ties.
Friction losses should be based on both vertical Minimum build-up at the edge of Type III girders
and horizontal curvatures. In designing for and smaller shall be 15 millimeters. For Type IV,
horizontal curvature, the exterior web with the V and VI girders the minimum build-up shall be
smallest radius shall be used. Consideration to 25 millimeters. This minimum build-up at the
the 5% variation allowed per web shall be critical section will ensure that the flange of the
included. girder will not encroach into the gross depth of
the slab.
403 PRECAST PRESTRESSED
CONCRETE The tops of the erected girders shall be surveyed
in the field prior to placement of the deck
403.01 CONCRETE (AASHTO 9.2) forming. If the tops of the erected girder
elevations are higher than the finish grade plus
Concrete for highway structures shall have a camber elevations minus deck slab and buildup
minimum specified initial and final concrete thickness, adjustments will have to be made in the
strengths as shown below. Higher strength roadway profile or in the girder seat elevations.
concrete may only be used when required by Encroachment into the slab of up to 15
design and when approved. millimeters will be allowed for random
occurrences.
Initial f ci = 290 kg/cm2 Min
f ci = 320 kg/cm2 Max 403.03 ALLOWABLE STRESSES-
PRESTRESSING STEEL
Final f c = 360 kg/cm2 Min (AASHTO 9.15.1)
f c = 420 kg/cm2 Max
For pretensioned members, overstressing the
prestressing steel above the initial stressing limit
403.02 DEFLECTIONS (AASHTO 9.11)
for short periods of time to offset seating losses is
not permitted.
The Release, Initial and Final Deflections shall be
shown on the plans. Deflections shall be shown
in centimeters at the tenth points.

Part 3 400-4
ROADWAY DESIGN MANUAL Roads and Bridges

403.04 ALLOWABLE STRESSES- The location of the harped point of the strand
CONCRETE (AASHTO 9.15.2) should be located as required by design with the
preferable locations being near the 1/10 of the
In calculating the temporary stress in concrete span as measured from the midspan of the girder.
before losses due to creep and shrinkage, the steel
relaxation prior to release and the elastic 404 PRESTRESSED I-GIRDERS
shortening should be included.
404.01 GENERAL
403.05 LOSS OF PRESTRESS
(AASHTO 9.16) Precast Prestressed I-Girder Bridges shall be
designed in accordance with AASHTO
For creep of concrete, the variable fcds, should be specifications. Girders shall be designed by
calculated using the total dead load applied after Working Stress Method and checked by the
prestressing including the 120 kg/m2 future Ultimate Strength Method (Load Factor Design).
wearing surface. The deck slab is to be designed by the Working
Stress Method using a maximum allowable stress
For girders with required concrete release of Fc = 110 kg/cm, Class K 335.
strengths of 320 kg/cm2 or less, the time of
release may be assumed to be 18 hours. For The slab and diaphragm dead load is to be
specified strengths over 320 kg/cm2 the time of supported by the girders only.
release should be increased accordingly. For
precast girders, the final losses shall include The Girders are to be designed as a composite-
release losses. section, simply-supported beams for Live Load
and Impact and all superimposed dead loads.
The value of relative humidity to be used in Negative moment reinforcement is to be designed
calculating shrinkage losses, shall be the value of over the intermediate supports considering span
relative humidity at the bridge site. continuity and all loads.

403.06 SHEAR (AASHTO 9.20) Continuity designs will include shrinkage and
creep moments as required by AASHTO Article
The value of "d" to be used in shear calculations 9.7.2.1.
shall equal the depth of the beam plus the
effective depth of the slab with a minimum d = 404.02 CONCRETE
0.80 times the overall depth. The shear shall be
calculated assuming full continuity for composite The following concrete strengths are the desired
dead load and live load plus impact. strengths to be used. Higher strengths may be
used if approved by the Abu Dhabi Roads Section
For single span structures, use the shear design Project Manager.
spacing at the 1/4 point for sections from the end
of the beam to the 1/4 point. For continuous Initial f ci = 280 kg/cm minimum.
multi-span structures, use the shear design f ci = 350 kg/cm maximum.
spacing required from the 1/4 point to the pier for
the section from the 1/4 point to the abutment end Note: 350 kg/cm release strengths can be
to obtain a symmetrical reinforcing pattern for all usually obtained within 18 hours, but require 4 to
girders. 6 additional hours for each additional 7 kg/cm
required above 350 kg/cm. Permission is
403.07 METHOD OF ANALYSIS required from the Abu Dhabi Roads Section
Project Manager for release strengths above 350
The dead load shall be assumed to be unsupported kg/cm and final strengths above 420 kg/cm.
and carried by the girders only. Use of masked
strands for debonding shall not be allowed. Final f c = 350 kg/cm minimum
f c = 420 kg/cm maximum

Part 3 400-5
ROADWAY DESIGN MANUAL Roads and Bridges

The maximum allowable stresses are to be in Allow an extra 40 mm movement per 100 meters
accordance with AASHTO except as modified of girder length for long-term creep and
below: shortening due to prestressing.

Elastomeric bearing pads will be a maximum


Tension width of 50 mm less than the normal width of the
Load Condition Allowable bottom flange to accommodate the 20 mm side
Stress chamfer and should be set back 50 mm from the
Girder DL + Prestress 0 end of the girder to avoid spalling of the girder
Total Service Load 0.8 'c ends.

404.07 CREEP FACTOR


404.03 EFFECTIVE FLANGE WIDTH
(AASHTO 9.8 AND 8.10.1) Use a creep factor of 3 when calculating long
term deflections.
The effective flange width will be as specified by
AASHTO except for Type V and standard and
404.08 FRAMES AND CONTINUOUS
modified type VI girders where the requirement of
CONSTRUCTION (AASHTO
12 times the slab thickness plus web thickness
9.7.2)
will be increased by 430 mm.
Girders shall be designed as composite section,
404.04 SHEAR simple supported beams for live load plus impact
and composite dead load. The superstructure
Girders will be designed for shear using the latest
shall be constructed continuous with the negative
AASHTO Standard Specifications. The depth to
moment reinforcing designed considering
be used in the calculation of shear will be the
continuity over intermediate supports for live load
depth of the beam plus the depth of the of the
plus impact and composite dead loads. The
slab. If composite action is fully developed, the
positive moment connection may be designed
shear will be calculated assuming full continuity
using the method described in the PCA
for composite dead load and live load plus
publication "Design of Continuous Highway
impact.
Bridges with Precast, Prestressed Concrete
Girders". In determining the positive restraint
404.05 INTERMEDIATE DIAPHRAGMS
moment, use 30 days as the length, of time
(AASHTO 9.10)
between casting the girders and deck closure. The
development length of the strands may be based
A single 300 millimeter thick intermediate
on the criteria contained in Report No. FHWA-
diaphragm shall be placed at the midspan for all
RD-77-14, "End Connections of Pretensioned I-
spans over 12 meters. For skews less than or
Beam Bridges" November 1974. In determining
equal to 10, place the diaphragms parallel to the
the number and pattern of strands extended,
skew. For skews greater than 10, the
preference shall be given to limiting the number of
diaphragms shall be staggered and placed normal
strands by increasing the extension length and
to the girders.
alternating the pattern to increase constructability.
404.06 BEARING PADS

Laminated neoprene bearing pads should be used


for relatively light reactions and moderate
superstructure movements.

Pot type bearings should be used for heavy


reactions, large superstructure movements and
superstructure on horizontal curve alignment.
Part 3 400-6
ROADWAY DESIGN MANUAL Roads and Bridges

404.09 DIFFERENTIAL SHRINKAGE 406 PRESTRESSED BOX BEAMS


(AASHTO 9.13.3.3)
406.01 END BLOCKS
Differential shrinkage should be considered in the
design when the effects become significant and END BLOCKS 450 MILLIMETERS LONG
when approved by the Project Manager. SHALL BE PROVIDED AT EACH END
AND SUFFICIENT STEEL SHALL BE
404.10 METHOD OF ANALYSIS PROVIDED IN THE END BLOCKS TO
RESIST THE TENSILE FORCES DUE TO
AASHTO Type V and Type VI modified girders THE PRESTRESSING LOADS.
should be used in place of Type V and Type VI
regular girders whenever possible. 406.02 DIAPHRAGM

The theoretical build-up depth shall be ignored for Diaphragms, cast within the beam, shall be
calculation of composite section properties. provided at the midspan for spans up to 15
meters, at the third points for spans from 15 to 22
405 PRESTRESSSED VOIDED SLABS meters and at quarter points for spans over 22
meters.
405.01 END BLOCKS
406.03 LATERAL TIES
End Blocks should be 380 millimeters long with
sufficient steel provided to resist the tensile forces One lateral tie shall be provided through each
due to concentrated prestressing loads. diaphragm located at the mid-depth of the section.
However, for the 990 millimeter and 1065
405.02 DIAPHRAGMS millimeter deep sections, when adjacent units are
tied in pairs for skewed bridges, in lieu of
Diaphragms shall be cast within the slab at continuous ties, two ties shall be provided, located
midspan for spans up to 12 meters and at third at the third points of the section depth.
points for spans over 12 meters.
406.04 SHEAR KEYS
405.03 LATERAL TIES
After shear keys have been filled with an
One lateral tie shall be provided through each approved non-shrink, low slump mortar, lateral
diaphragm located at the mid-depth of the section. ties shall be placed and tightened.

405.04 SHEAR KEYS

After shear keys have been filled with an


approved non-shrink mortar, lateral ties shall be
placed and tightened.

405.05 BARRIERS

Barriers shall have a 6 millimeter open joint at the


midspan to prevent the barrier from acting as an
edge beam and causing long term differential
deflection of the exterior beam.

Part 3 400-7
ROADWAY DESIGN MANUAL Roads and Bridges

SECTION 500 501.05 LOAD CYCLES (AASHTO 10.3.2)


STRUCTURAL STEEL
The stress cycle case to be used in AASHTO
Table 10.3.2A shall be Case I.
501 DESIGN CRITERIA
501.06 CHARPY V-NOTCH IMPACT
501.01 GENERAL REQUIREMENTS
(AASHTO 10.3.3)
Structural steel design criteria shall be as
specified in Section 10 of AASHTO except as Where applicable, the Charpy V-Notch impact
clarified or modified in this manual. requirements for structural steel shall be for
Temperature Zone 1 at elevations less than 1800
501.02 DESIGN METHODS meters and Temperature Zone 2 at elevations
1800 meters and higher, unless otherwise directed
The Service Load Design Method (Allowable by the Project Manager.
Stress Design) shall be used except that the
Strength Design Method (Load Factor Design) Intermediate stiffeners shall be placed only on the
may be used for major or unusual structures when inside face of exterior girders.
approved.
The number and location of girder shop and field
501.03 MATERIALS (AASHTO 10.2) splices shall be determined so as to minimize
fabricated and erected cost of the girders.
Materials shall conform with the requirements of
AASHTO Article 10.2 with the selection based All connections except field connections shall be
on stress requirements and overall economy. welded. ASTM A325M high strength bolts shall
be used for field connections.
The preferred maximum thickness of tension
flanges is 50 millimeters. Tension flanges thicker
than 50 millimeters shall be normalized.

501.04 ALLOWABLE FATIGUE


STRESS (AASHTO 10.3.1)

Splices, stiffeners, shear connectors and bracing


details shall be designed using categories A
through C details in order to limit the fatigue
stress.

Category E details shall not be used.

Part 3 500-1
ROADWAY DESIGN MANUAL Roads and Bridges

SECTION 600
To allow for the effects of long term creep and
EXPANSION AND
shrinkage in post-tensioned box girder bridges,
CONTRACTION the following additional shortening shall be
included:
601 MOVEMENT CRITERIA
Joints: 40 mm per 100 meters.
601.01 MOVEMENT RATING Bearings: 80 mm per 100 meters.

Provisions shall be made in the design of 602 DECK JOINTS


structures to resist induced stresses or to provide
for movements resulting from variations in 602.01 GENERAL
temperature and anticipated shortening due to The movement rating for joints for steel structures
creep, shrinkage or prestressing. Accommodation shall be based primarily on the thermal expansion
of thermal and shortening movements will entail and contraction characteristics of the
consideration of deck expansion joints, bearing superstructure, while for concrete structures the
systems, restraining devices and the interaction of effects of shortening due to creep and shrinkage
these three items. and where applicable, prestressing shall also be
added. Movement ratings shall be based on
The main purpose of the deck joint is to seal the temperature variations as measured from the
joint opening to obtain a watertight joint while assumed mean temperature.
allowing for vertical, horizontal and/or rotational
movement. The bearings are required to transmit Published movement ratings are usually based on
the vertical and lateral loads from the the difference between the maximum and
superstructure to the substructure units and to minimum openings without consideration to the
allow for movement in the unrestrained directions. required minimum installation width. In
Restraining devices are required to limit the determining the movement rating, consideration
displacement in the restrained directions. must be given to the installation width required to
Improper design or construction of any of these install the seal element.
devices could adversely affect the operation of the
other devices. Other factors which should be considered in
determining the required movement rating include
The required movement rating is equal to the total consideration of the effects of any skew,
anticipated movement (i.e. the difference between anticipated settlement and rotations due to live
the widest and the narrowest opening of a joint). loads and dead loads, where appropriate.
The calculated movements used in determining Items requiring attention include:
the required movement rating shall be as specified
in AASHTO except as modified below: 1) The type of anchorage system to be used.
2) The method of joint termination at the
Mean temperature and temperature ranges shall ends.
be as specified in Section 201.08 of this manual. 3) The method of running joints through
barriers, sidewalks and/or medians.
To allow for the effects of long term creep and 4) Physical limitation on size of joints.
shrinkage in precast prestressed concrete 5) Susceptibility of joint to leakage.
members, the following additional shortening 6) Possible interference with post-tensioning
shall be considered: anchorages.
7) Selection of appropriate modular
Joints: 20 mm per 100 meters. proprietary systems that meet design
Bearings: 40 mm per 100 meters. requirements.
8) Forces applied to the surrounding
concrete by the joint.

Part 3 600-1
ROADWAY DESIGN MANUAL Roads and Bridges

Available types of joints include compression list of approved joint types which can be obtained
seals, strip seals, and modular joints. from the Project Manager.
Compression seal joints and strip seal joints are
generic and should be detailed on the plans, by 602.02 COMPRESSION SEALS
standards and/or covered in the special
provisions. Modular joints are proprietary and The compression seal element should have a
require that the designer specify allowable joint shape factor of 1:1 (width to height) to minimize
types and styles in the special provisions. side wall pressure. The size of the compression
Information concerning specific design seal shall be specified on the plans.
parameters and installation details of modular
joints should be obtained from literature supplied Effective movement ratings for this type of joint
by the manufacturer of the system. It is the range up to 50 millimeters. Advantages for this
responsibility of the designer to review the type of joint include its low cost, proven
proprietary joint literature and related performance and acceptance for use on pedestrian
manufacturer's specifications to ensure that the walkways. However, this type of joint can not be
selected joint types are properly specified and unbolted and easily raised, generates pressure and
compatible with the design requirements. is not good for high skews or horizontal
directional changes.
The following features of joints should be shown
on the plans: 602.03 STRIP SEALS

1) Blockout details showing a second pour, Strip seals should generally conform to the details
including blockout dimensions and shown in the structure detail drawing titled "Strip
additional reinforcing required. Seal Joint". Proprietary alternates to this detail
2) Required end treatment in barriers or other than those shown on the detail drawing will
curbs, including enough detail or not be allowed.
explanation to accommodate each of the
proprietary systems selected (i.e. cover Effective movement ratings for this type of joint
plates, etc.). range up to 100 millimeters. This type of joint is
3) Consideration to traffic control in best used when the movement rating is beyond the
determining section pattern lengths. capacity of compression seals and for large
4) Movement rating. skews. Strip seal joints will require cover plates
5) Assumed temperature and opening at time for pedestrian walkways.
of installation with temperature correction
factors. 602.04 MODULAR JOINTS
6) Actual horizontal length of joint measured
from inside of barrier face to inside of Modular joints are very complex joint systems.
barrier face corrected for skew. Effective movement ratings range from 100
millimeters up to 750 millimeters. Modular joints
The following features of joints should be are the best choice for movement ratings over 100
specified in the specifications: millimeters.

1) For modular joints, the joint style, gland 603 BEARINGS


type, steel edge beam material, and the
name of a representative manufacturer. 603.01 GENERAL
2) Method of measurement (by linear meter
from face to face of barrier). Unlike joints, where the opening can be adjusted
if the ambient temperature at the time of
A general discussion of joint types follows. construction is different than the assumed mean
However, for modular joints the actual selection temperature, bearings must be designed to be
of the specific alternates should be made from the installed at temperatures other than the mean
temperature. For this reason, the movement

Part 3 600-2
ROADWAY DESIGN MANUAL Roads and Bridges

rating should be based on the full temperature due to prestressing is greater than 25 millimeters
range and not the rise or fall from a mean and where the movement rating including elastic
temperature. shortening, long term creep and shrinkage and
temperature is greater than 40 millimeters.

Calculation of the movement rating shall include 603.03 ELASTOMERIC BEARING


thermal movement and anticipated shortening due PADS
to creep, shrinkage and prestressed shortening.
For cast-in-place post-tensioned concrete box Elastomeric bearing pads shall conform to the
girder bridges both the elastic and long term requirements of Section 14 of AASHTO. Bearing
prestress shortening effects shall be considered. pads shall be designed to be constructed using
either steel or fiberglass laminates, with the
An initial offset of the top sliding surface from the controlling case determining the size. The
centerline of bearing should be calculated and following data should be shown on the plans:
shown on the plans so that the top sliding surface
will be centered over the bottom sliding surface Length, width and thickness of pad
and the centerline of bearing after all shrinkage, Durometer Hardness
creep and post-tensioning shortening has taken Design Method (A or B)
place in the sperstructure. Design Load
Low Temperature Zone (A, B or C)
Permissible bearing types include neoprene strips, Elastomer Grade (0, 2 or 3)
elastomeric bearing pads, steel bearings, sliding Shear Modulus
elastomeric bearings and high-load multi-
rotational bearings (pot, disc or spherical). Generally, bearing pads shall be Durometer 60 -
Elastormer with steel reinforcement.
Neoprene strips, elastomeric bearing pads and
steel bearings are generic and shall be detailed on Normally Design Method A will be used in
the plans and/or covered in the standard design, however, where only steel reinforced pads
specifications and special provisions. High-load will work Design Method B may be used provided
multi-rotational bearings are proprietary bearing the special testing is performed.
types and require that the designer include a
Bearing Schedule in the plans. It is the The following should be used as a guide for
responsibility of the designer to review the Stored determining low temperature zones:
Specification to ensure that the bearings are
properly specified and compatible with the design Elevation (meters) Zone
requirements. Sliding elastomeric bearings are Below 900 A
both generic and proprietary in that a generic 900-1800 B
bearing should be designed and detailed on the 1800 and above C
plans with proprietary alternates allowed.

All bearings types except elastomeric bearing Pads shall have a minimum thickness of 25
pads shall be designed for impact. millimeters and be designated in 10 millimeter
increments. The use of elastomeric bearing pads
603.02 NEOPRENE STRIPS should generally be limited to a thickness not
greater than 100 millimeters. Holes will not be
Neoprene strips consist of a sliding plate on a allowed in the pads.
continuous neoprene pad. Where appropriate,
neoprene strips are the preferred bearing type for Width and length dimensions shall be detailed in
post-tensioned box girder bridges. However, even 50 millimeter increments. When used with
neoprene strips are not appropriate for the prestressed I-girders, pads shall be sized a
following applications: curved bridges, skews minimum width of 50 millimeters less than the
greater than 20 degrees, contributing spans nominal width of the girder base to accommodate
greater than 50 meters, where initial shortening the 20 millimeter side chamfer and shall be set
Part 3 600-3
ROADWAY DESIGN MANUAL Roads and Bridges

back 50 millimeters from the end of the girder to appropriate. The pad dimensions and all details
avoid spalling of the girder ends. of the anchorage and restraint systems shall be
shown on the plans. The special provisions
Elastomeric pads should not be used in cases should allow for proprietary alternates.
where deck joints or bearings limit vertical
movements, such as in older style sliding steel Sliding elastomeric bearings should be considered
plate joints or widenings where existing steel for applications where regular elastomeric bearing
bearings are to remain. pads would exceed 100 millimeters in height or
where special access details would be required for
Where elastomeric bearing pads with greased other proprietary bearings in such places as
sliding plates are used on post-tensioned box hinges.
girder bridges to limit the required thickness of
the pad, the pad thickness should be determined 603.06 HIGH-LOAD MULTI-
based on temperature movements only, with the ROTATIONAL BEARINGS
initial and long term shortening assumed to be
taken by the sliding surface. 603.06.01 Description

Elastomeric bearing pads are the preferred High-load multi-rotational fixed bearings consist
bearing type for new steel girders, precast of a rotational element of the Pot-type, Disc-type
prestressed girders and post-tensioned box girder or Spherical-type. High-load multi-rotational
bridges where neoprene strips are not appropriate. expansion bearings consist of a rotational element
of the Pot-type, Disc-type or Spherical-type,
603.04 STEEL BEARINGS sliding surfaces to accommodate translation and
guide bars to limit movement in specified
Steel bearings may consist of rockers or fixed or directions when required.
expansion assemblies which conform to the
requirements specified in Section 10 of Pot bearings consist of a rotational element
AASHTO. comprised of an elastomeric disc totally confined
within a steel cylinder. Disc bearings consist of a
Steel bearings are not a preferred bearing type rotational element comprised of a polyether
and their use should normally be limited to urethane disc confined by upper and lower steel
situations where new bearings are to match the bearing plates and restricted from horizontal
existing bearing type on bridge widening projects. movement by limiting rings and a shear restriction
mechanism. Spherical bearings consist of a
603.05 SLIDING ELASTOMERIC rotational element comprised of a spherical
BEARINGS bottom convex plate and mating spherical top
concave plate.
Sliding elastomeric bearings consist of an upper
steel bearing plate anchored to the superstructure, These design criteria were prepared for the broad
a stainless steel undersurface and an elastomeric range of normal applications and the specified
pad with a teflon coated upper surface. The limits of loads, forces and movements. The
teflon surface shall be attached to a 10 millimeter design and manufacture of multi-rotational
minimum thick plate which is vulcanized to the bearings relies heavily on the principles of
elastomeric pad. The bearing accommodates engineering mechanics and extensive practical
horizontal movement through the teflon sliding experience in bearing design and manufacture.
surface and rotation through the elastomeric Therefore, in special cases where structural
bearing with the thickness of the elastomeric requirements fall outside the normal limits, a
bearing determined by the rotational and friction bearing manufacturer should be consulted.
force requirements. Keepers may be used for
horizontal restraint of the pads. Vertical restraint
may be provided by anchor bolts with slotted
keeper plates or individual vertical restrainers as

Part 3 600-4
ROADWAY DESIGN MANUAL Roads and Bridges

603.06.02 Rotational Requirements 9. It is desirable to reduce the moment


applied to truss or space frame panels.
The rotational requirements of these bearings is
treated in a new way. Rotational requirements of 10. Large movements are anticipated.
the bearings, Rb, are determined by:
11. Economical, long life, or low
Rb = Rs + Rc maintenance bearings are desirable.

where 12. Regular elastomeric bearing pads


would exceed 100 millimeters in height.
Rb = Rotation capacity designed into
the bearing. 603.06.04 Design Criteria
Rs = Anticipated rotation of the
structure in service. (includes live Since special details are required to allow for
loads and rotations induced by access for inspection, repair or replacement of the
construction/erection sequences). bearings, the respacing of joints to eliminate the
Rc = Rotation induced in the bearing need for use of these bearing types should be
by construction tolerances, 0.02 considered.
radians maximum (see Design
Criteria 14). Some structural considerations in use of multi-
rotational bearings are listed below. Reference to
603.06.03 Use "this specification" refers to the design criteria
below.
Use of multi-rotational bearings is especially
indicated where: 1. Vertical and horizontal loads shall be
assumed to occur simultaneously. All
1. Low profile, high load bearings are loads are service loads. Minimum
required. vertical loads are for dead loads and
superimposed dead loads excluding the
2. Long span, curved, or skewed bridges future wearing surface. Maximum
and other similar structures of complex vertical loads are for dead loads,
design are required. superimposed dead loads including the
future wearing surface, and live loads
3. Long slender columns or light frames and impact.
and members exhibit minimum stiffness
or rigidity. 2. The total recommended clearance
between all guiding and guided sliding
4. The direction of rotation varies. surfaces is 1.5 millimeters in order to
limit edge stress on guiding interfaces.
5. The direction of rotation cannot be
precisely determined. 3. Avoid specifying total spacing of more
than 1.5 millimeters between guides
6. Settlement of the substructure is and guided components where possible.
anticipated.
4. In specifying the horizontal force
7. Self aligning capabilities are required. capacity of bearings, it is recommended
only one fixed or guided expansion
8. Load and rotation eccentricity does not bearing shall be assumed to resist the
significantly alter the net distribution of sum of all the horizontal forces at each
stress through the bearing and into the abutment, bent, column, hinge or pier.
substructure and superstructure.

Part 3 600-5
ROADWAY DESIGN MANUAL Roads and Bridges

5. Where feasible provide at least two


fixed or guided expansion bearings 13. The minimum Structure Rotational, Rs,
each able to resist all horizontal forces of bearings covered in the specification
at each abutment, column, hinge or pier is 0.01 radians. Rs comprises live
for design redundancy. loads and rotations induced by
construction/erection sequences.
6. Some press-fit guide bar details in
common use have proven 14. The maximum Construction Rotation,
unsatisfactory in resisting horizontal Rc (rotation induced by construction
loads. When analyzing these designs, tolerances), is 0.02 radians. The
consideration should be given to the designer may elect to specify a smaller
possibility of rolling of the bar in the Rc than 0.02 radians but is cautioned
recess. to investigate the cost and practicality
of the changes contemplated.
7. Multi-rotational bearings should not be
used at vertical loads less than 20% of 15. Recommended coefficients of friction
their vertical capacity. Bearings for for structure design follows:
less than 20% vertical capacity require
special design. Unfilled sheet or woven fiber
PTFE/stainless steel 0.04
8. Special consideration in bearing design
shall be given where high horizontal to Filled PTFE sheet/stainless 0.08
vertical load (above 0.30) is
anticipated. The above coefficients of friction are
based on the average stress and limits
9. Frictional resistance of bearing slide of edge stress of PTFE in this
surfaces should be neglected when specification. Out of level installations
calculating horizontal load capacity. within the limits of this specification
and normal in service oxidation of the
10. The installed alignment of bearing stainless steel mating surface. Service
guiding systems relative to the conditions, where exceptional corrosion
anticipated movement direction of the of the stainless steel mating surface
structure should be carefully considered may occur, will require special
to avoid bearing guide system failure. assessment of the long term coefficient
Special studies or designs may be of friction.
required on curved or skewed
structures to ensure correct installation. 16. Pot, disc and spherical multi-rotational
bearings should not be mixed at the
11. The substructure and superstructure same expansion joint or bent. The
should be designed so as to remain differing deflection characteristics and
rigid under all service conditions in differing rotation characteristics may
areas around and in contact with the result in damage to the bearings and/or
bearings, paying particular attention to structure.
the use of stiffeners at extreme points
of movements. 17. Contract drawings and documents
should contain a Bearing Schedule (See
12. The substructure and superstructure Section 603.07, Bearing Schedule).
design should permit bearings to be
removed for inspection or rehabilitation 18. Some bearing tests are very costly to
by minimum jacking of the structure. perform. Other bearing tests cannot be
Jacking points shall be provided in the performed because of the unavailability
structural design. of test equipment. The following test

Part 3 600-6
ROADWAY DESIGN MANUAL Roads and Bridges

requirements should be carefully 9. Allowable coefficient of friction of


considered before specifying them: slide surfaces.

A) Vertical loads exceeding 10. Surface coating requirements and the


2,250,000 kg. appropriate specifications.

B) Horizontal loads exceeding 11. Seismic requirements, if any.


225,000 kg.
12. Uplift details, temporary attachments
C) The simultaneous application or other requirements.
of horizontal and vertical loads
where the horizontal loads 13. Installation scheme.
exceeds 75% of the vertical
loads. 14. Bearing preset details, if required.

D) Triaxial test loading. Design rotation, movement and other


requirements in the Bearing Schedule should only
E) The requirement for dynamic refer to the requirements of the structure where
rotation of the test bearing the bearings are to be used.
while under vertical load.
604 RESTRAINING DEVICES
603.07 BEARING SCHEDULE
604.01 GENERAL
A bearing schedule shall be included in the
contract drawings and documents and shall Restraining devices are meant to prohibit
contain the following as a minimum: movement in a specified direction. Restraining
devices shall be designed to resist the imposed
1. A schedule of all minimum and loads including earthquake as specified in
maximum vertical and horizontal AASHTO and as modified in Section 200 of this
service loads. manual.

2. Minimum Structure and Construction Restraining devices could include concrete shear
Rotation requirements. keys or end blocks, horizontal or vertical cable
restrainers or mechanical restraining devices
3. Magnitude and direction of movements which could be an integral part of a bearing or a
at all bearing support points. separate system. Restraining devices to prohibit
vertical displacement at expansion ends, shall be
4. Quantity, type (fixed, expansion or designed to allow for inspection and future
guided expansion). replacement of bearings.

5. Plan view, alignment and location of all Allowable restraining devices include, but are not
bearing units. limited to the following: Vertical Fixed
Restrainers, Vertical Expansion Restrainers,
6. Allowable upper and lower bearing External Shear Keys, Internal Shear Keys and
contact pressure. Keyed Hinges.

7. Fixing or anchorage details and/or 604.02 VERTICAL FIXED


requirements. RESTRAINERS

8. Grades, bevels and slopes of all Vertical fixed restrainers consist of cable and
bearings. appropriate hardware and are designed to allow

Part 3 600-7
ROADWAY DESIGN MANUAL Roads and Bridges

rotation but no translation in either horizontal or 604.06 KEYED HINGE


vertical directions.
A keyed hinge is a restraining device which limits
604.03 VERTICAL EXPANSION displacements in both horizontal directions while
RESTRAINERS allowing rotation.

Vertical expansion restrainers consist of cable For a typical expansion seat abutment where
and appropriate hardware and are designed to restraining devices are required, the restraining
allow rotation and longitudinal translation but no devices will consist of vertical expansion
transverse translation. Some limited vertical restrainers and external shear keys.
displacement is allowed to permit replacement of
bearings if required. For a typical pinned seat abutment for a post-
tensioned box girder bridge, restraining devices
604.04 EXTERNAL SHEAR KEYS will consist of vertical fixed restrainers and
external shear keys. For a typical pinned seat
External shear keys are reinforced concrete blocks abutment for a prestressed girder bridge,
designed to limit transverse displacement while restraining devices will consist of vertical fixed
allowing longitudinal and rotational movements. restrainers and external or internal shear keys.
External shear keys are preferred to internal shear
keys since they are more accessible for repairs For a typical expansion pier, restraining devices
and easier to construct. will consist of vertical expansion restrainers and
internal shear keys.
604.05 INTERNAL SHEAR KEYS
For a typical pinned pier, restraining devices will
Internal shear keys are reinforced concrete blocks consist of vertical fixed restrainers and internal
designed to limit transverse displacement while shear keys or a keyed hinge.
allowing longitudinal and rotational movements.

Part 3 600-8
ROADWAY DESIGN MANUAL Roads and Bridges

SECTION 700 701.02 SPREAD FOOTINGS


GEOTECHNICAL
Where good soil materials exist near the surface,
shallow foundations in the form of spread
701 FOUNDATIONS footings will normally be the recommended
foundation type. For foundation units situated in
701.01 GENERAL a stream, spread footings shall only be used when
they can be placed on non-erodible rock. Spread
The main purpose of this section is to document footings are normally not placed on embankment
bridge design criteria as related to bridge material.
foundation geotechnical issues.
When spread footings are the recommended
Since problems requiring geotechnical and foundation type, the Geotechnical Report shall
structural expertise often result in confusion contain the allowable bearing pressure, the
concerning the responsibilities of each, another elevation of the bottom of the footing and the
purpose of this section is to define the role of the estimated total settlement, differential settlement
geotechnical engineer and the bridge engineer in and time rate of settlement, if applicable.
design problems involving both fields.
The bridge design group shall size the footing to
The usual procedure for designing bridge ensure that the allowable bearing pressure is not
foundation substructure units is as follows: exceeded for any AASHTO Group Loading and
that the footing is properly sized and reinforced to
The bridge design group will develop a resist the maximum applied moments and shears.
preliminary location plan. The bottom elevations of spread footings shall be
set at the recommended depth. The minimum top
The Geotechnical Engineer will conduct a site cover over the top of footings shall be 500
investigation, identify borehole locations, drill and millimeters. If the possibility for differential
log borings, perform soil testing as appropriate, settlement is identified, the bridge designer shall
plot the boring logs and summarize the results in ensure that the entire structure is capable of
a Geotechnical Report. The Geotechnical Report structurally resisting the forces induced by the
will include a Foundation Design Report which differential settlement.
identifies the type of foundation recommended for
each substructure unit including the allowable 701.03 PILE FOUNDATIONS
loads and required depths.
When good foundation material is not located
The Geotechnical Engineer is responsible for near the surface, when settlement is a problem, or
preparing the boring logs on construction plans. for foundation units located in streams where
They also prepare necessary special provisions scour is a problem, deep foundations will usually
for construction of the foundation elements. be recommended. One type of deep foundation is
During construction of the bridge foundations, the a driven pile. Driven piles may be either steel H
Geotechnical Engineer oversees geotechnical piles, steel pipe piles or prestressed concrete piles.
testing, spread footing excavations and piling and The other type of deep foundation is a bored pile.
drilled shaft construction. They work closely
with bridge design group to jointly resolve
problems requiring redesign because of changed
site conditions. The bridge design group is
responsible for producing the structural design
and construction documents for the substructure
units as part of the bridge plans.

Part 3 700-1
ROADWAY DESIGN MANUAL Roads and Bridges

701.04 DRIVEN PILES For the most part, bored piles will include a
temporary casing or liner intended to preclude the
The Geotechnical Engineer is responsible for intrusion of earth into the hole during the boring
recommending when driven piles are to be used, operation and a permanent casing or liner that
The type of driven pile to be used, the allowable will remain in place and not be withdrawn during
capacity of the pile, the estimated pile tip the concreting process. The temporary casing
elevation and any special requirements necessary will be advanced a sufficient depth into rock to
to drive the piles. When steel piles are used, the provide a seal against water inflow. The
corrosive life of the pile will be reported in the temporary casing shall be clean and free of water
Geotechnical Report. The Geotechnical Engineer before the permanent casings or liners, reinforcing
is also responsible for running the WEAP87 wave steel and concrete are placed.
equation computer program to determine the
driveability of the specified piles and to develop The bridge design group is responsible for
charts or other guidelines to be used by ensuring that the allowable axial capacity is not
construction personnel to control the pile driving exceeded for any AASHTO Group Loading and
process. that the shaft can withstand the applied lateral
loads.
The bridge design group is responsible for
ensuring that the allowable axial capacity is not Unless specified otherwise in the Geotechnical
exceeded for any AASHTO Group Loading and Report, the following minimum criteria should be
that the pile can withstand the applied lateral used in designing bored pile foundations:
loads.
1. Bored Piles shall be spaced a minimum of
701.05 BORED PILES two diameters measured center to center of
the holes plus 100mm.
A bored pile foundation consists of excavating a
round hole by machine, installing a metal casing 2. Temporary and permanent casings or liners
or liner, placing a reinforcing cage in the casing shall be designed to withstand handling
or liner and then filling the casing or liner with stresses, applicable concrete and surrounding
concrete. soil pressures, and shall be watertight.

The Geotechnical Engineer is responsible for 3. Vertical reinforcing should be detailed to


recommending the minimum diameter of bored provide the minimum recommended clearance
pile to be used and providing the necessary in AASHTO Article 4.6.6.2.1. In no case
information for determining the minimum shall the clearance between vertical
required embedment below a specified elevation reinforcing be less than 115 millimeters.
to develop the required axial load. The
Geotechnical Engineer is also responsible for 4. Reinforcement shall have a clear distance of
determining the soil properties in each layer to be not less than 50 millimeters from the inside
used in analyzing lateral loads and whether slurry face of the permanent casing or lining.
methods of construction may be utilized. If
necessary, methods of testing the pile after 5. Horizontal ties should be spaced at 150
concreting will be specified in the Geotechnical millimeters minimum.
Report.
6. The footing, if applicable, shall be sized to
extend a minimum of 200 millimeters from
the edge of a bored pile.

Part 3 700-2
ROADWAY DESIGN MANUAL Roads and Bridges

SECTION 800 801.02 POLICY


RETAINING WALLS
The following policy shall apply to retaining wall
design:
801 DESIGN CRITERIA
1. Walls up to 6 meters high:
801.01 GENERAL
The Consultant shall prepare
Retaining walls are used when normal fill or cut drawings for cast-in-place concrete
slopes extend beyond acceptable limits. Walls retaining walls utilizing the Abu
may be classified in the following classes: Dhabi Roads Section Standards and
Specifications.
Gravity Walls
Bin 2. Walls over 6 meters high:
Crib
Wire basket The Consultant shall evaluate the
Mass concrete applicability of mechanically
Cantilever Walls stabilized wall systems and confirm
Concrete their site-specific suitability. If the
Braced Walls Consultant determines that a
Anchored Walls mechanically stabilized wall system
Soldier pile and lagging is not appropriate due to soils
Tangent cylinder piles conditions or other site specific
Mechanically Stabilized Walls conditions, a complete cast-in-place
Reinforced Earth concrete retaining wall design must
VSL Retained Earth be prepared for inclusion into the bid
Hilfiker-Reinforced Soil embankment documents.

Walls shall be designed for a minimum factor of 801.03 RESPONSIBILITIES


safety of 1.5 against sliding and 2.0 against
overturning. The design of a retaining wall will usually involve
the efforts of three sections: Roadway Design
The wall selection process includes identification Section, Geotechnical Section, and the Bridge
of types of walls appropriate for the site, Design Section.
evaluation of geotechnical behavior and
properties affecting wall behavior and selection of 801.03.01 Roadway Design Section
wall systems which fit all site constraints.
Identification of alternate designs may be Roadway Design Section is responsible for
appropriate. identifying the need for and limits of the retaining
walls. They will be responsible for providing a
In determining the types of retaining walls profile adjacent to the top of the wall and the soil
capable of fitting a particular site the following profile line along the front face of the wall.
should be considered: Roadway Design is also responsible for
Availability of materials identifying the acceptable limit of excavation
required to maintain traffic and to design any
Service life, maintenance, future use
detours when required.
Deflection tolerance
Ease of construction
Environmental/visual considerations
Special loading requirements
Settlement tolerance
Availability of space

Part 3 800-1
ROADWAY DESIGN MANUAL Roads and Bridges

801.03.02 Geotechnical Section details for drainage on plans. Appurtenant traffic


and/or pedestrian rails will also be designed and
The Geotechnical Section is responsible for detailed by the Bridge Design Section. This
investigating the site, drilling exploratory holes as Section works with the Geotechnical Section on
required, determining the external stability of the required structural design changes during
site and determining the material properties of the construction because of changed site conditions.
existing soil and backfill. The Geotechnical
Section will also recommend soil strength 801.04 PROPRIETARY RETAINING
parameters and groundwater elevations for WALLS
computing design lateral earth pressure. They are
also responsible for determining the maximum When a proprietary retaining wall is chosen as an
safe slopes allowed during excavation. acceptable alternate, the special provisions will
specify the pre-approved wall systems which are
The Geotechnical Section also is responsible for acceptable for the particular application and site.
determining the type of foundation required to The proprietary wall type is to be chosen from a
support the wall loads, the allowable bearing pre-approved list of wall types. The contractor
pressure of the soil and the minimum required will be required to identify the alternate in his bid,
depths of the foundation units. This Section with bid shopping after the award of the contract
determines the soil properties to be used in not allowed.
determining the lateral loads to be applied to the
wall and determines the amount of settlement, The Roadway Design Section will prepare plans
differential settlement and the time rate of showing the location and extent of the walls and
settlement for walls on compressible foundation the profile along the top of the wall and the soil
soils. profile along the front face of the wall. The plans
should also show any restrictions regarding
The Geotechnical Section prepares appropriate excavation which may exist and requirements for
Special Provisions for construction of the appurtenant features such as traffic barrier,
retaining walls and monitors construction of the handrail or other attachments. Blockouts for
foundation elements, assisting the resident lighting, signing, utilities and drainage structures
engineer as requested concerning geotechnical will also be detailed on the plans or identified to
issues. The Section works closely with the Bridge be included with the proprietary plan submittals.
Design Section on any structural design changes
needed during construction because of changed The Geotechnical Section will prepare special
site conditions. provisions containing the design criteria to be
used in evaluating the proprietary wall. As a
801.03.03 Bridge Design Section minimum the following should be included:

The Bridge Design Section is responsible for the 1. The minimum factor of safety against
design of the structural elements of the wall, the overturning
length of the wall and for producing the required 2. The minimum factor of safety against sliding
construction plans, when requested by others, for 3. Maximum coefficient of friction against
any non-proprietary wall requiring structural sliding
analysis. The Bridge Design Section is also 4. Phi angle of the backfill
responsible for determining whether shoring will 5. Allowable bearing pressure
be required during construction based on the 6. Minimum design life
acceptable limits of excavation provided by 7. Water table level
Roadway Design and the safe excavation slopes 8. Elevation of footing bottom
provided by Geotechnical. The Bridge Design 9. Maximum tolerable deflection
Section also selects walls which will handle
differential settlement, when present, and provides

Part 3 800-2
ROADWAY DESIGN MANUAL Roads and Bridges

SECTION 900 structures will not be permitted. Trenching in the


vicinity of existing piers or abutments shall be
MISCELLANEOUS
kept a sufficient distance from footings to
prevent undercutting of existing footings or to
901 TRAFFIC STRUCTURAL prevent disturbing foundation soils for future
SUPPORTS foundations.

901.01 GENERAL Where other locations prove to be extremely


difficult and very costly, utility lines except
Luminaires, traffic signals and sign supports natural gas may be allowed in the structures.
shall be designed using the AASHTO
Specifications for Structural Supports except as Natural gas encroachments will be evaluated
clarified or modified in this manual. under the following policy:

901.02 WIND SPEED A. Cases where gas line attachments to


structures will not be considered under any
Major structural supports shall be designed for condition:
the wind frequency of 160 kph.
1. Grade separation structures carrying
901.03 ALLOWABLE STRESSES vehicular traffic on or over freeways.
2. Inside closed cell-type box girder
The, L /45.7 limitation on dead load deflection bridges.
contained in Article 1.9.1(A) need not be 3. High pressure transmission lines over 4
satisfied since there is no scientific basis to kg/cm2 and/or distribution lines of over
support this limitation. 150 millimeters in diameter.
4. Gas lines over minor waterway crossings
For high mast light poles, the maximum where burial is feasible.
deflection shall be limited to 15% of the pole
height under wind load. The maximum allowable B. Gas line attachments on structures will be
yield strength for design purposes shall be 4590 considered under the following cases or
kg/cm2. conditions:

For all other applications, for steel with a yield 1. Each case will be judged on its own
strength greater than 3360 kg/cm2, the allowable merit with the utilities providing
stresses for design shall be limited to a yield complete justification as to why
strength of 3360 kg/cm2. This limitation alternative locations are not feasible.
indirectly places a limit on allowable deflections 2. Economics will not be a significant
in an attempt to satisfy the criteria of Article factor considered in the feasibility issue.
1.9.1. This limitation also reduces the stresses in 3. Open girder type structures across major
any high strength welds which are more brittle rivers.
and subject to cracking due to fatigue from 4. Pedestrian or utility bridges where
vibrations. proper vented casings and other safety
systems are used.
902 UTILITIES IN STRUCTURES 5. All lines are protected by casements.

902.01 GENERAL Provision for accommodation of relocated and


future utilities on structures should follow the
Where utility conflicts exist; water, power, following General Policy.
telephone, cable TV and gas lines will be
relocated as required for construction of the
project. Where it is feasible and reasonable to
locate utility lines elsewhere, attachment to

Part 3 900-1
ROADWAY DESIGN MANUAL Roads and Bridges

902.02 POLICY 3. Size and schedule of sleeved casings.


4. Spacing and details of support brackets.
Support bracket details and attachments for all 5. Expansion device details.
utilities will require Bridge Group approval. 6. Total combined weight of carrier pipe
and transmitted fluids, conduits, casings,
All approved utilities shall have individual support brackets, expansion joints and
sleeved casings, conduits or ducts as appropriate. other related items.
7. Design calculations.
All utilities carrying liquids shall be placed inside
casings through the entire length of the structure. 902.04 BRIDGE GROUP
The casing shall be designed to carry full service RESPONSIBILITY
pressure so as to provide a satisfactory
containment in case the utility is damaged or The Bridge Group shall be responsible for and
leaks. have final approval authority for the following
aspects of the design:
Water lines, telephone conduits, power lines,
cable TV lines, supports or other related items 1. Determination of how many lines, if any,
will not be permitted to be suspended below or the structure can accommodate.
attached to the exterior of any new or existing 2. Determination of where such lines should
structure. be located within a structure.
3. Determination of the size of the access
Product lines for transmitting volatile fluids will openings and design of the required
not be permitted to be attached to or suspended reinforcing.
from or placed within any new or existing 4. Determination of construction problems
structure. related to required sequencing of project.
5. Tracking man-hours associated with
902.03 UTILITY AGENCY utility relocations for cost recovery.
RESPONSIBILITY
Usually utilities will be accommodated by
The utility agency is responsible for obtaining providing individual access openings for casings
necessary information regarding the proposed and sleeves to pass through. Access openings
construction schedule for the project. The should be 50 millimeters larger than the diameter
agency shall submit a request including of the casings or sleeves and spaced as required
justification for attaching to the structure and by structural considerations.
preliminary relocation plans including line mass
and support spacing as early as possible but no For box girder bridges, access openings should
later than the completion of preliminary be located as low as possible but no lower than
structural plans. 250 millimeters above the top of the bottom slab
to allow for support brackets to be supported
The utility agency shall be responsible for the from the bottom slab. Where possible all utilities
design of all conduits, pipes, sleeves, casings, shall be supported from the bottom slab for box
expansion devices, supports and other related girder bridges.
items including the following information:
For girder bridges, the utilities shall not be
1. Number and size of conduits for power, placed in the exterior girder bay and shall be
telephone and cable TV lines. supported from the deck slab.
2. Size and schedule of carrier pipe for
water lines.

Part 3 900-2
ROADWAY DESIGN MANUAL Roads and Bridges

903 FALSEWORK POLICY FOR 903.03 FALSEWORK CLEARANCES


BRIDGE CONSTRUCTION
For cast-in-place structures, the preferred method
903.01 FALSEWORK REQUIREMENTS of construction is to route traffic around the
construction site and to use earth fills for
To ensure that traffic handling is given proper falsework. This provides an economical solution,
consideration in the early design stages, it is a safe working area and eliminates possible
necessary to identify traffic handling and problems associated with the design, approval,
falsework assumptions in the Bridge Selection construction and performance of falsework
Report. If falsework is to be used, the horizontal including the possible effect of excessive
and vertical clearances shall be shown on the deflections of falsework on the structure.
General Plan. Usually, one of the following
listed conditions will prevail: When the street or highway must be kept open
and detours are not feasible, falsework shall be
1. Traffic will be routed around construction used with openings through which traffic may
site. pass. Because the width of traffic openings
through falsework can significantly affect costs,
2. Traffic will pass through construction site. special care should be given to minimizing
opening widths consistent with traffic and safety
A. No falsework allowed over traffic. This considerations. The following should be
restriction would require precast considered:
concrete or steel superstructure with field
splices located clear of traffic. 1. Staging and traffic handling
requirements.
B. Stage construction required. Stage 2. The width of approach roadway that will
construction must be detailed on the exist at the time the bridge is
plans. Construction joints or hinges constructed.
would be required. 3. Traffic volumes and percentage of
trucks.
C. Falsework openings required. The size 4. Vehicular design speed.
and number of openings must be shown. 5. Desires of local agencies.
6. Controls in the form of existing facilities.
General discussions and a table of falsework 7. The practical problems of falsework
openings are covered under "Falsework construction.
Clearances". 8. Consideration of pedestrian
requirements.
903.02 FALSEWORK USE
The minimum width of traffic openings through
When traffic must pass through the construction falsework for various lane and shoulder
site, three possible conditions exist. Condition requirements shall be as shown in Table 900.01.
2.A. is limited to sites which can be spanned by The resulting falsework span shown in Table
precast members or where steel is competitive in 900.01 is the minimum span. When temporary
cost. The staged construction option of concrete barrier is used, 0.6 meters of safety
Condition 2.B. is not always feasible while the margin per side is allowed for deflection. When
presence of a hinge is a permanent disadvantage. blocked-out "W" beam is used, 1.2 meters of
Condition 2.C. is used for all other cases when it safety margin per side is allowed for deflection.
is necessary to route traffic through the The normal spans may be reduced or increased if
construction site. The elimination of permanent other forms of protection are used depending on
obstructions by using longer spans and the required space for installation and deflection.
eliminating shoulder piers will usually outweigh The actual width of traffic openings through
objections to the temporary inconvenience of falsework and the resulting falsework span to be
falsework during construction. used in design shall be determined by the Abu

Part 3 900-3
ROADWAY DESIGN MANUAL Roads and Bridges

Dhabi Roads Section Project Manager and shall Where the vertical falsework clearance is less
be stated in the Bridge Selection Report. than 4.50 meters, advance warning devices shall
be specified or shown on the plans. Such devices
To establish the grade line of a structure may consist of flashing lights, overhead signs,
spanning an existing street or highway, over-height detectors or a combination of these or
allowance must be made for depth of falsework, other devices. A standard insert sheet has been
where used, to provide the clearance needed to developed for the details of the over-height
permit traffic through the work area during detectors or safety beams. Providing for these
construction. The minimum allowances to be devices in the specifications or on the plans shall
made for depth of falsework shall be as shown in be the responsibility of the Abu Dhabi Roads
Table 900.02 and shall be based on the actual Section Project Manager.
falsework openings determined by the Abu Dhabi
Roads Section Project Manager. Note to bridge designer: Special consideration
shall be given to limit the maximum allowable
The minimum vertical clearance for falsework tension in a precompressed tensile zone of post-
over freeways shall be 4.50 meters. tensioned box girder bridges supported on
falsework with large openings.

Table 900.01
FALSEWORK SPAN REQUIREMENTS

Detour Roadway Minimum Width Resulting Falsework Span (1)


Facility to No. Shoulder of Traffic Temporary Blocked-out
be spanned Lanes Widths Opening (1) Conc. Barrier "W" beam
(meters) (meters) (meters) (meters)
Freeway & 1 0.6 & 0.6 4.8 7.2 8.4
Non-Freeway 2 0.6 & 0.6 8.4 10.8 12.0
3 0.6 & 0.6 12.0 14.4 15.6
4 0.6 & 0.6 15.6 18.0 19.2
NOTES: (1) Traffic Opening and Falsework Span are measured normal to detour centerline.

Table 900.02
FALSEWORK DEPTH REQUIREMENTS
Falsework Opening 7.2 8.4 10.8 12.0 14.4 15.6 18.0 19.2
(meters)
Minimum Required
Falsework Depth(mm)
Max 3365 kg/m 485 510 585 815 915 1070 1095 1145
per girder line
3365 - 4580 kg/m 510 560 815 890 1070 1120 1145 1170
per girder line
NOTES:
1. DL based on 2550 kg/m3 concrete.
2. Table 900.02 is based on the superstructure concrete being designed for zero tensile stress at the
falsework openings. Superstructures designed with concrete tensile stresses can significantly
increase the required falsework depths shown in the table and amount of falsework required.
3. Structures with greater than 4580 kg/m Dead Load per girder line will require special
considerations for required falsework depths.

Part 3 900-4
ROADWAY DESIGN MANUAL Roads and Bridges

904 CONSTRUCTION JOINT 5. The Contractor shall submit drawings


GUIDELINES FOR BRIDGE showing the placement sequence,
CONSTRUCTION construction joint locations, directions
of the concrete placement and any other
904.01 GENERAL pertinent data to the Engineer for his
review. The drawing shall be submitted
The type of structure and method of construction, at least four weeks prior to the date of
combined with sound engineering judgment, deck placement.
should be used in determining the number and 6. Construction joints shall be placed in
location of superstructure construction joints. the locations shown on the project plans
The use of construction joints should be or as approved by the Engineer.
minimized for ease of construction and 7. All construction joints shall be
subsequent cost savings. Some items which perpendicular to the principal lines of
should be considered are: stress and in general located at points of
minimum shear and moment.
1. Method of construction - earthen fill
falsework, conventional falsework or 904.02 LONGITUDINAL
girder bridge without falsework. CONSTRUCTION JOINTS
2. Phase construction because of physical
constraints such as traffic handling. Longitudinal construction joints in bridge decks
3. Span length and estimated rotation and and/or superstructures should be identified as
deflection. optional unless required by construction phasing.
4. Degree of fixity at abutments and piers. The optional deck joints should be placed on lane
5. Effects of locating a construction joint in lines or at center of structure. All longitudinal
a region of negative moment. construction joints should be keyed.
6. Volume of concrete to be poured without
a joint. 904.03 PRECAST CONCRETE GIRDER
7. Consequences of continuous pour, BRIDGES
including adverse effects caused by a
breakdown during the pour. Precast concrete girder bridges made continuous
over supports shall have transverse construction
Some important requirements regarding joints placed so that the girders undergo their
construction joints contained in the Standard positive moment deflections prior to the final
Specifications are as follows: pour over the negative moment areas of the fixed
piers or abutments. There shall be no horizontal
1. The sequence of concrete placement construction joint between fixed pier diaphragm
shall be as shown on the project plans or abutment diaphragm and the deck.
or as approved by the Engineer when
not shown on the project plans. Girder bridges will usually require details on the
2. The rate of concrete placement and plans showing a plan view with joint locations,
consolidation shall be such that the deck pour sequence and direction of pour, if
formation of cold joints within required. There should be a minimum of 12
monolithic sections of any structure will hours between adjacent pours. A continuous
not occur. pour from abutment to abutment will not be
3. The rate of concrete placement for allowed. Construction joints where required
major structures shall not be less than should be parallel to the centerline of the pier.
27 cubic meters per hour unless Their location will be near the point of minimum
otherwise specified or approved in dead load plus live load moment and shear. This
writing by the Engineer. distance is generally one-quarter of the span
4. Placement of the deck concrete shall be length from the pier if the adjacent spans are
in accordance with the placing sequence approximately equal length.
shown on the project plans.

Part 3 900-5
ROADWAY DESIGN MANUAL Roads and Bridges

904.04 STEEL GIRDER BRIDGES the pier. Their location should be near the point
of dead load counterflexure.
The effects of uplift and allowing a continuous
pour should be considered when developing deck 904.05 CAST-IN-PLACE BOX GIRDER
pour schedules for multi-span continuous steel BRIDGES
girder bridges. The required rate of pour should
be compared to the quantity of concrete to be Box girder bridges made continuous over
placed and the potential for poured sections to set supports shall have transverse construction joints
up and develop tensile stresses from pours in placed so that the webs undergo their positive
adjacent spans shall be considered when moment falsework deflections prior to the final
determining the need for construction joints. pour over the negative moment areas of the fixed
Consideration must be given to the potential for piers or abutments if the superstructure
negative moment stresses in the deck due to formwork is supported on conventional
placement of positive moment pours in adjacent falsework. The transverse construction joints
spans. may be omitted if the superstructure formwork is
supported on earthen fill. The webs and all
Girder bridges will usually require details on the diaphragms should be poured concurrently with
plans showing a plan view with joint locations, the bottom slab. Transverse construction joints
deck pour sequence and direction of pour, if where required should be parallel to the
required. Except where otherwise required, there centerline of the pier. Their location near the
should be a minimum of 12 hours between inflection point is generally one-quarter of the
adjacent pours. Construction joints, where span length from the pier if the adjacent spans
required, should be parallel to the centerline of are approximately equal length.

Part 3 900-6

You might also like