Professional Documents
Culture Documents
ASSIGNMENT - ON
(GPPM 11)
SUBMITTED TO:
By
Mr. Vishnu Kumar
(GPPM-11)
Reg.no.-216-09-14-50763-2174
CONTENTS
1. Introduction
Machine and material are a vital resource to the accomplishment of any construction project.
They enable effective working at any construction site for works that cannot be practically be
executed by manpower.
Developing and constructing a new international airport 30 KM away from the city. You have
been appointed as a planning engineer (Material and equipment) Project is to be implemented in
a phases. In phase -1. One strip of landing of 100 meter width is to be constructed in 100 days.
The scope of the work in this assignment is only as follows.
A- Cutting and dozing of 100,000- Cum. Of earth. Average height 0.75 meter.
B- Transporting of 20,000- Cum of surplus earth from site to dumping place 3 Km away
from site (Including spreading) and filling 80,000- Cum in landing strip.
C- Bringing of 3,000- Cum of sand from 20 Km (Including spreading and levelling at
site.)
D- Procurement of 150,000- Lit of bitumen. Duration of work is 30 days from 60th day
of starting of the work. Bitumen to be obtained from the refinery at Bongaigaon in
ASHAM. Lead time up to site is 45 days. Storage facility available at site is 50,000-
Lit.
Estimate total cost of work and your plan of
1- Equipment planning Procurement and deployment.
2- Ordering and replenishing of bitumen.
Earthmovers: These machine use for earth cutting, moving or transporting large volume
of earth. A brief description of the equipment used for excavation is reported as follows.
Here we have considered of the following machinery for the task to be executed.
Truck Tipper - used for transporting loose material (such as sand, gravel, or
demolition waste) for construction. A typical dump truck is equipped with an open-
box bed, which is hinged at the rear and equipped with hydraulic pistons to lift the
front, allowing the material in the bed to be deposited ("dumped") on the ground
behind the truck at the site of delivery.
Asphalt Paver The asphalt paver are capable of laying large quantities of hot
asphalt and leveling it to the required condition.
Asphalt Sprayer The asphalt sprayer melts the bitumen and sprays it at the
required area. It has burner in it which can the temperature of the bitumen at over
350 degree C.
The total work to be planed for execution per day can be calculated as below.
Total nos. of days = 100.
Working days = 10 Hours/Day
Identification of activities:
Planning of activity
Activity 10 20 30 40 50 60 70 80 90 10
0
Earth work in excavation
Leveling and dressing
Sand filling
Order for bitumen
Delivery of Bitumen
Replenishing of bitumen
Removal of over burden
Spreading of soil
Mass Diagram
Cost Analysis:
Cost of equipment operation per hour and cost of each item of work.
Calculation of per day of work
Total quantity of earth = 1, 00,000 cum
NICMAR- SODE-GPPM 11 -216-09-14-50763-2174 Page 7
Assignment- constructing a new international airport
No. of days = 60 Days
Volume of earth to be moved per day per hour= 100000/60/10
Hence hourly production required= 166.66 cum per hour.
3- Calculation of effective cycle per hour divide the 60 minute hour by cycle time and
adjust for availability and efficiencies.
Cycle time 0.48 Minute
Cycle/60 minute hour 60/0.48 = 125
Operator skill/ Efficiency 0.9(90%)
Machine arability 0.95 (95%)
Gen Operational efficiency 0.83 (50Min/hour)
Effective cycle per hour 125 x .9 x .95 x .83 = 89
Hence considering TATA EX350 LCH V Super bucket Capacity: 1.30 1.90 m3
The cost breakdown structure for owning and operating cost of all the fleet equipment has
to be paid larger importance as this is the vital statistic which can make the project in to
profit and if not considered may be lead to financial loss to the project.
Equipment operation cost accounts for the three main categories of cost.
1- Owing cost
2- Operation cost
Fuel expenses are determine by the measurement of the job. This can be determine by
records of the consumption of fuel in liters per hour knowing job condition, viz. if the
soil is loose, machine can do more volume of work in comparison to the work where
the strata of soil is harder. Average hourly consumption of fuel can be calculated
directly knowing the soil properties of the project from previous recorded statistics.
Similarly the cost of lube oil and replacement of tier required can be worked out by
knowing the machine characteristic and abrasion, life of tier.
Operation wages may be include in operation cost, but due to the variance of project,
it is generally practiced to keep the wages of equipment operator is separate category.
The justification behind this is, since every project may have different scheme,
sometimes operators may be in percentage and sometimes may be in the volume or
work done.
The cost should include all benefits paid by the company as per its policy.
Operating cost:
1- Fuel cost and consumption rate (Unit/hour)
2- Lube oils, Filters, Grease.
3- Tyres.
4- Repair reserve (Extended use & Basic repair)
The resulting theoretical values must be adjusted by the time and load factore that account for
working conditions. Time factor- Actual working time of machine. Load factor percentage of
rated horsepower.
Name of equipments:
Excavator - crawler excavator is the ultimate digging tool, designed to deliver long lasting
performance, strength, power and leading fuel efficiency. Reach new levels of efficiency, as you
can depend on the machine for quarrying, mining, road building, civil engineering, general
construction and more.
Per day (08 Hr.) capacity of the crawler excavator is 240 cum. The hiring charges for per
cum of soil excavating is as per DSR 2016 is Rs. 130/cum in normal soil condition.
Tipper - used for transporting loose material (such as sand, gravel, or demolition waste)
for construction. A typical dump truck is equipped with an open-box bed, which is hinged
at the rear and equipped with hydraulic pistons to lift the front, allowing the material in
the bed to be deposited ("dumped") on the ground behind the truck at the site of delivery.
Capacity of 12 to 20 cum/trip and hiring charges is Rs. 4200/ trip, lead up to 20 Km as per DSR 2016.
Grader -
Capacity of 3000 Sqmt/per day (8 Hr.) of loose soil in normal condition. The hiring
charges for the grader is Rs. 269/cum.
Water load capacity of 10000 liter and hiring charges with water is Rs. 1800/ trip, with lead of
water is not more than 3Km.
Plane wheel compactor - A road roller (sometimes called a roller-compactor, or just roller) is a
compactor type engineering vehicle used to compact soil, gravel, concrete, or asphalt in the
construction of roads and foundations. Similar rollers are used also at landfills or in agriculture.
Per day capacity to compact soil of 1500 Sqmt with layer of 15 cm thick in OMC. The hiring
charges fof one day is Rs. 2200/ day (8 Hr.)
Vibrator roller A vibratory roller is a compactor having a drum* (roll or horizontal cylinder)
used to densify (compact) soil, asphalt or other materials through the application of combined
static and dynamic forces (weight and vibrations) to increase the load-bearing capacity of the
surface.
Per day capacity to compact soil of 3000 Sqmt with layer of 15 cm thick in OMC. The hiring
charges for one day is Rs. 5200/ day (8 Hr.)
2.
3. Compliance
Outline the means to determine that you and other party are doing jobs properly throughout the project.
What standards will you apply to this project? What will be your criteria for acceptance of a vendor,
what type of procurement method do you propose?
4. Project Deliverables
Describe how you will deliver the end results of the project. State the number of each deliverable you
will provide, the person or persons you will provide the deliverables to and how you will provide the
deliverables to and how you will deliver these to the intended audience.
5. Project Timeline
6. Project Budget
DESIGN SPECIFICATION - The Designer of Record shall direct and provide site or
subsurface investigation judged necessary in accordance with the Agreement for professional
services. This will include contacting Central Utilities and the Engineering Design and
Construction departments for any university records of site hazards, investigative work and
surveyor reports, testing laboratories (including test borings), soil analysis (including load
bearing capabilities) and related site analysis. Submit two copies of any site investigative reports
to the Designated University Project Manager.
The Architect/Engineer shall define the types of earthwork being specified including earth
excavation, rock excavation, mass excavation, confined excavation, and shall specify the format
for the Contractor's payment schedule associated with these different scopes. The
Architect/Engineer must specify the required soil dry density and moisture content tests. The
Contractor shall provide the Owner's Testing Agency with a continuously updated and accurate
schedule of the construction activities that require sampling, observation, or verification by the
Testing Agency. The Contractor shall also establish benchmarks for reference on the site.
Show all boring locations, cross sections and soil conditions. Also show all: existing conduits,
drains, utility lines, sewers, tunnels, cables, trees, paving, walks, foundations and other objects
or obstructions, whether in use or abandoned. State that information is for contractors use and
that in no way shall the University be held responsible for accuracy of the information.
QUALITY ASSURANCE The University will contract for the services of an independent
Testing Agency to perform required field and laboratory testing. The Testing Agency will submit
the following reports to the University Project Manager and copy the Contractor:
1. Analysis of all soil materials tested, including fill, backfill, and borrow.
2. Verification of each footing subgrade.
3. In-place density test reports.
4. Moisture-density relationship test reports.
5. Compressive strength or bearing test reports.
6. All other reports requested by the Architect/Engineer or the University.