You are on page 1of 15

Assignment- constructing a new international airport

ASSIGNMENT - ON

Material & Equipment Management

(GPPM 11)

SUBMITTED TO:

NATIONAL INSTITUTE OF CONTRUCTION


MANAGEMENT

& RESEARCH (NICMAR) PUNE.

SCHOOL OF DISTANCE EDUCATION (SODE)

By
Mr. Vishnu Kumar
(GPPM-11)

Reg.no.-216-09-14-50763-2174

NICMAR- SODE-GPPM 11 -216-09-14-50763-2174 Page 1


Assignment- constructing a new international airport

CONTENTS

SR.NO. DESCRIPTION PAGE NO.


1 ASSIGNMENT. 3
2 PROJECT IDENTIFICATION & 3-4
Project Report
3 PROJECT DEVELOPMENT 4-6
PROCESS
4 PROJECT PLANNING & CONTROL 6-9
5 PROJECT WORK BREAKDOWN & 10-13
CPM/ NETWORK ANALYSIS

6 Development of network: 14-15


7 Analysis Procedure 16-17
8 CONCLUSIONS & 17
RECOMMENDATIONS

1. Introduction

Machine and material are a vital resource to the accomplishment of any construction project.
They enable effective working at any construction site for works that cannot be practically be
executed by manpower.

NICMAR- SODE-GPPM 11 -216-09-14-50763-2174 Page 2


Assignment- constructing a new international airport

1.1 Assignment- constructing a new international airport

Developing and constructing a new international airport 30 KM away from the city. You have
been appointed as a planning engineer (Material and equipment) Project is to be implemented in
a phases. In phase -1. One strip of landing of 100 meter width is to be constructed in 100 days.
The scope of the work in this assignment is only as follows.

A- Cutting and dozing of 100,000- Cum. Of earth. Average height 0.75 meter.
B- Transporting of 20,000- Cum of surplus earth from site to dumping place 3 Km away
from site (Including spreading) and filling 80,000- Cum in landing strip.
C- Bringing of 3,000- Cum of sand from 20 Km (Including spreading and levelling at
site.)
D- Procurement of 150,000- Lit of bitumen. Duration of work is 30 days from 60th day
of starting of the work. Bitumen to be obtained from the refinery at Bongaigaon in
ASHAM. Lead time up to site is 45 days. Storage facility available at site is 50,000-
Lit.
Estimate total cost of work and your plan of
1- Equipment planning Procurement and deployment.
2- Ordering and replenishing of bitumen.

1.1 Description of the Equipments considered for the work

Earthmovers: These machine use for earth cutting, moving or transporting large volume
of earth. A brief description of the equipment used for excavation is reported as follows.

Here we have considered of the following machinery for the task to be executed.

1 nos. crawler mounted hydraulic excavator, TATAEX350 LCH V Super


Bucket Capacity: 1.30-1.90 m3. For excavation and loading to dump truck.
1 Nos. Motor Grader-Articulated TATA Hitachi Motor Grader TG-14 for dozing,
surface dressing, leveling spreading of sand.
5 Nos. Truck Tippers TATA HYHA 2516 for hauling of earth excess earth mass
20000 cum 3 Km away from the site & dumping of earth where filling is required
80000 cum, also to bring sand from 20 Km of volume 3000 cum.

Crawler mounted hydraulic excavator: These are single bucket


excavators names as classified according to running gear as crawler-mounted,
wheeled, walking, rail, floating and combination rubber tyres. These are used for
excavation, moving earth and loading. The benefit of crawler is that it can easily
move in any type of soil. Easily load earth to hauling machine.

NICMAR- SODE-GPPM 11 -216-09-14-50763-2174 Page 3


Assignment- constructing a new international airport

Motor Grader: A grader, also commonly referred to as a road grader or a motor


grader, is a construction machine with a long blade used to create a flat surface
during the grading process. Typical models have three axles, with
the engine and cab situated above the rear axles at one end of the vehicle and a
third axle at the front end of the vehicle, with the blade in between. In certain
countries, for example in Finland, almost every grader is equipped with a second
blade that is placed in front of the front axle. Some construction personnel refer to
the entire machine as "the blade". Capacities range from a blade width of 2.50 to
7.30 m and engines from 93373 kW (125500 hp). Certain graders can operate
multiple attachments, or be used for separate tasks.

Truck Tipper - used for transporting loose material (such as sand, gravel, or
demolition waste) for construction. A typical dump truck is equipped with an open-
box bed, which is hinged at the rear and equipped with hydraulic pistons to lift the
front, allowing the material in the bed to be deposited ("dumped") on the ground
behind the truck at the site of delivery.

Asphalt Paver The asphalt paver are capable of laying large quantities of hot
asphalt and leveling it to the required condition.

NICMAR- SODE-GPPM 11 -216-09-14-50763-2174 Page 4


Assignment- constructing a new international airport

Asphalt Sprayer The asphalt sprayer melts the bitumen and sprays it at the
required area. It has burner in it which can the temperature of the bitumen at over
350 degree C.

The calculation of per day work

The total work to be planed for execution per day can be calculated as below.
Total nos. of days = 100.
Working days = 10 Hours/Day

Identification of activities:

The major activities can be listed as below.


1- Earth work in excavation 100000 cum.
2- Hauling of over burden 20000 Cum. Up to lead of 3 Km.
3- Bringing sand 3000 Cum. From 20 Km.
4- Leveling of surface and spreading of sand.
5- Procurement of 150000 Liters of bitumen.

NICMAR- SODE-GPPM 11 -216-09-14-50763-2174 Page 5


Assignment- constructing a new international airport
6- Planning for application of bitumen and procurement keeping in view that total
available storage at a time is 1/3 of total requirement.

Planning of activity
Activity 10 20 30 40 50 60 70 80 90 10
0
Earth work in excavation
Leveling and dressing
Sand filling
Order for bitumen
Delivery of Bitumen
Replenishing of bitumen
Removal of over burden
Spreading of soil

Factors that affect selection of equipment

1- Earth Moving Equipment:

The selection of earth moving equipment mainly depend on:-


Quantity of earth to be moved.
Compaction time.
The decision to choose between crawler-mounted earth moving equipment and a
wheel mounted one depend to a large extent on privileging job condition.
Pay load & cycle time.
The number of associated equipment required to support the main equipment i.e..
Loaders and dumpers.
Cost of owing & operation.
Average age in- service & equipment useful age.

2- Earth Hauling Equipment:

The selection of earth hauling equipment mainly depend on:


Quantum of earth
Space of maneuvering & terrain.
Cost of owing and operation.

NICMAR- SODE-GPPM 11 -216-09-14-50763-2174 Page 6


Assignment- constructing a new international airport
Fleet equipment characteristics.
Expected project duration.
Nature of work.
Distance of hauling.
Average age in-service & equipment useful age.

Mass Diagram

CUMMULATIVE MATRIC VALUME


ALGEBRIC
END AREAS (SQMT) VOLUME (CUM) SUMS
STATION CUT FILL CUTT FILL VALUMES,
CUMULATIV
E
0 186 0 0.000 0 0
1 65 0 17836.594 0 17836.590
2 44 0 7748.370 0 25584.960
3 22 0 4679.708 0 30264.670
3.5 0 0 767.165 0 31031.840
4 0 22 0 -529.276 30502.560
5 0 44 0 -3228.581 27273.980
6 0 65 0 -5345.683 21928.300
7 0 166 0 -12305.657 9622.640
8 0 119 0 -14899.107 -5276.470
9 55 46 2493.287 -8071.452 -10854.600
9.08 0 0 191.791 -185.246 -10848.100
10 0 22 0 -979.160 -11827.200
10.5 0 0 0 -529.276 -12356.500
11 22 0 767.165 0 -11589.400
12 24 0 4679.708 0 -6909.650
13 87 0 9282.700 0 2373.050
14 218 43 21595.704 -2117.102 21851.650
15 64 22 19984.657 -3175.653 38660.660
15.07 0 0 345.224 -238.174 38767.710
16 32 0 2109.705 0 40877.410
16.5 0 0 1150.748 0 42028.160
17 0 32 0 -793.913 41234.250
18 0 61 0 -4551.770 36682.480
19 0 157 0 -10717.83 25964.650
20 90 95 6367.472 -12332.120 20000.000

Cost Analysis:

Cost of equipment operation per hour and cost of each item of work.
Calculation of per day of work
Total quantity of earth = 1, 00,000 cum
NICMAR- SODE-GPPM 11 -216-09-14-50763-2174 Page 7
Assignment- constructing a new international airport
No. of days = 60 Days
Volume of earth to be moved per day per hour= 100000/60/10
Hence hourly production required= 166.66 cum per hour.

1- Determine of material type and bucket fill factor.


Average soil = 85 to 90%

2- Estimate of the cycle time


Referring to the suppliers equipment cycle time estimating chart
Average = 0.43 to 0.52 Minute.

3- Calculation of effective cycle per hour divide the 60 minute hour by cycle time and
adjust for availability and efficiencies.
Cycle time 0.48 Minute
Cycle/60 minute hour 60/0.48 = 125
Operator skill/ Efficiency 0.9(90%)
Machine arability 0.95 (95%)
Gen Operational efficiency 0.83 (50Min/hour)
Effective cycle per hour 125 x .9 x .95 x .83 = 89

4- Calculate the bucket capacity divide hourly production requirement by effective


cycles per hour, adjust for material density and fill factor.
Hourly production required 166 cum/hour
Effective cycle/hour 89
=Required pay load 166/89 = 1.87 cum
Material density / loose 1.6 Ton/ m3
=Bucket payload volume 1.87/1.6 = 1.17 m3
Fill factor 0.85(85%)
Nominal bucket size 1.17/.85 = 1.38m3

Hence considering TATA EX350 LCH V Super bucket Capacity: 1.30 1.90 m3

The cost breakdown structure for owning and operating cost of all the fleet equipment has
to be paid larger importance as this is the vital statistic which can make the project in to
profit and if not considered may be lead to financial loss to the project.

Equipment operation cost accounts for the three main categories of cost.
1- Owing cost

2- Operation cost

NICMAR- SODE-GPPM 11 -216-09-14-50763-2174 Page 8


Assignment- constructing a new international airport
It is cumulative some of expenses an owner experience by working a machine on the
project. It is some of expenses like fuel, lube oil expenses, grease, repair &
maintenance of machinery.

Fuel expenses are determine by the measurement of the job. This can be determine by
records of the consumption of fuel in liters per hour knowing job condition, viz. if the
soil is loose, machine can do more volume of work in comparison to the work where
the strata of soil is harder. Average hourly consumption of fuel can be calculated
directly knowing the soil properties of the project from previous recorded statistics.

Similarly the cost of lube oil and replacement of tier required can be worked out by
knowing the machine characteristic and abrasion, life of tier.

3- Wages of Equipment Operation:

Operation wages may be include in operation cost, but due to the variance of project,
it is generally practiced to keep the wages of equipment operator is separate category.
The justification behind this is, since every project may have different scheme,
sometimes operators may be in percentage and sometimes may be in the volume or
work done.

The cost should include all benefits paid by the company as per its policy.

Cost of owing can be determined by knowing

1- Estimated ownership period in years.


2- Estimated usages (Hours/year)
3- Ownership usage (Total hours)

Operating cost:
1- Fuel cost and consumption rate (Unit/hour)
2- Lube oils, Filters, Grease.
3- Tyres.
4- Repair reserve (Extended use & Basic repair)

Fuel cost can be calculated on the theoretical basis .

The resulting theoretical values must be adjusted by the time and load factore that account for
working conditions. Time factor- Actual working time of machine. Load factor percentage of
rated horsepower.

NICMAR- SODE-GPPM 11 -216-09-14-50763-2174 Page 9


Assignment- constructing a new international airport

Name of equipments:

1- For Equipment used departmentally

(I) Ownership Charges:


(a) Total investment at site of work (This include A/T Cost, Sales tax, excise, custom and
other transport expenses consisting of fright (by ocean and rail) insurance loading
/unloading charges and erection and commissioning on receipt ....Rs. 50,00,000/-
(b) Deduct salvage value @15% of A
.Rs. 7, 50, 000/-
(c) Total investment to be depreciated = A-B
Rs. 42, 50,000/-
(d) Economics life of machine in hours as per appendix 7.11
(As per ministry norms, it is 9000 Hrs)
(e) Depreciation per hours (C/D)
.Rs. 472.22/-
(f) Storage charges per hour (1 percentage of c spread over the economics life)
= 0.01x (c)/(d)..Rs. 472.22/-

Total owner ship charges = (e) + (f)

..Rs. 476.94 (I)

(II) Operational charges:


Repair charges per hour including maintenance and replacement of tyres (150 percent
of c spread over

Economic life = 1.5 x c/d..Rs. 708.33 (II)

(III) Overhead charges:

@5% of ownership and operational charges


= 5 (I + II)/100
Overhead charges per hours ....Rs. 59..23 (III)

(IV) Running Charges:

Operating staff/labour & wages: No. Wages/Month


Designation
(i) Operator @ 584.21 per day
(ii) Helper @ 428.00 per day

NICMAR- SODE-GPPM 11 -216-09-14-50763-2174 Page 10


Assignment- constructing a new international airport
(iii) Cleaners @ 89.36 per day
(iv) Mics. Expenses (Welder) @ 5%
(v) TA. Etc. @ 15%

(g) Wages per hour

Total operating cost per hour ..Rs. 165.23 (IV)

(h) Service charges for fuel and lube, etc.


Consumption/hr. Rate/lit cost/hr.

a- Fuel @7lit/hr.cost per hour = 14 liters x Rs. 41.29 = Rs. 578.06


b- Lubricants, grease Hyd. Oil, gear oil, cotton waste, etc. @Rs 52.73 per hour.

Total service charge per hour ...Rs. 630.79 (V)

(i) Cost of lub. Uil, fuel etc. Hr.


Total running charges per hour (g + h) ....Rs. 796.02 (VI)

(V) Overhead charges @ 5% of the total charges.


Per hour = 5 x

1- Hydraulic excavator with 1 cum capacity bucket 9 nos.


2- Tipper with capacity of 20 cum. 18 nos.
3- Hydraulic Grader 1 nos.
4- Road roller (smooth wheel) 2 nos.
5- Vibrator Roller 1 nos.
6- Tanker for bitumen transport (12000 lit) -2 no.
7- Water tanker 10000/- lit - 2 Nos.

NICMAR- SODE-GPPM 11 -216-09-14-50763-2174 Page 11


Assignment- constructing a new international airport

Excavator - crawler excavator is the ultimate digging tool, designed to deliver long lasting
performance, strength, power and leading fuel efficiency. Reach new levels of efficiency, as you
can depend on the machine for quarrying, mining, road building, civil engineering, general
construction and more.

Per day (08 Hr.) capacity of the crawler excavator is 240 cum. The hiring charges for per
cum of soil excavating is as per DSR 2016 is Rs. 130/cum in normal soil condition.

Tipper - used for transporting loose material (such as sand, gravel, or demolition waste)
for construction. A typical dump truck is equipped with an open-box bed, which is hinged
at the rear and equipped with hydraulic pistons to lift the front, allowing the material in
the bed to be deposited ("dumped") on the ground behind the truck at the site of delivery.

Capacity of 12 to 20 cum/trip and hiring charges is Rs. 4200/ trip, lead up to 20 Km as per DSR 2016.

Grader -

Capacity of 3000 Sqmt/per day (8 Hr.) of loose soil in normal condition. The hiring
charges for the grader is Rs. 269/cum.

NICMAR- SODE-GPPM 11 -216-09-14-50763-2174 Page 12


Assignment- constructing a new international airport
Water tanker - A water tank is used to store water to tide over the daily requirements. In road,
highway or any field construction, used for the water supply of different uses or sprinkler as per
requirement.

Water load capacity of 10000 liter and hiring charges with water is Rs. 1800/ trip, with lead of
water is not more than 3Km.

Plane wheel compactor - A road roller (sometimes called a roller-compactor, or just roller) is a
compactor type engineering vehicle used to compact soil, gravel, concrete, or asphalt in the
construction of roads and foundations. Similar rollers are used also at landfills or in agriculture.

Per day capacity to compact soil of 1500 Sqmt with layer of 15 cm thick in OMC. The hiring
charges fof one day is Rs. 2200/ day (8 Hr.)

Vibrator roller A vibratory roller is a compactor having a drum* (roll or horizontal cylinder)
used to densify (compact) soil, asphalt or other materials through the application of combined
static and dynamic forces (weight and vibrations) to increase the load-bearing capacity of the
surface.

NICMAR- SODE-GPPM 11 -216-09-14-50763-2174 Page 13


Assignment- constructing a new international airport

Per day capacity to compact soil of 3000 Sqmt with layer of 15 cm thick in OMC. The hiring
charges for one day is Rs. 5200/ day (8 Hr.)

2.
3. Compliance
Outline the means to determine that you and other party are doing jobs properly throughout the project.
What standards will you apply to this project? What will be your criteria for acceptance of a vendor,
what type of procurement method do you propose?

4. Project Deliverables
Describe how you will deliver the end results of the project. State the number of each deliverable you
will provide, the person or persons you will provide the deliverables to and how you will provide the
deliverables to and how you will deliver these to the intended audience.

5. Project Timeline

6. Project Budget

7. Attachments: (number and identify)

NICMAR- SODE-GPPM 11 -216-09-14-50763-2174 Page 14


Assignment- constructing a new international airport

DESIGN SPECIFICATION - The Designer of Record shall direct and provide site or
subsurface investigation judged necessary in accordance with the Agreement for professional
services. This will include contacting Central Utilities and the Engineering Design and
Construction departments for any university records of site hazards, investigative work and
surveyor reports, testing laboratories (including test borings), soil analysis (including load
bearing capabilities) and related site analysis. Submit two copies of any site investigative reports
to the Designated University Project Manager.
The Architect/Engineer shall define the types of earthwork being specified including earth
excavation, rock excavation, mass excavation, confined excavation, and shall specify the format
for the Contractor's payment schedule associated with these different scopes. The
Architect/Engineer must specify the required soil dry density and moisture content tests. The
Contractor shall provide the Owner's Testing Agency with a continuously updated and accurate
schedule of the construction activities that require sampling, observation, or verification by the
Testing Agency. The Contractor shall also establish benchmarks for reference on the site.
Show all boring locations, cross sections and soil conditions. Also show all: existing conduits,
drains, utility lines, sewers, tunnels, cables, trees, paving, walks, foundations and other objects
or obstructions, whether in use or abandoned. State that information is for contractors use and
that in no way shall the University be held responsible for accuracy of the information.

QUALITY ASSURANCE The University will contract for the services of an independent
Testing Agency to perform required field and laboratory testing. The Testing Agency will submit
the following reports to the University Project Manager and copy the Contractor:
1. Analysis of all soil materials tested, including fill, backfill, and borrow.
2. Verification of each footing subgrade.
3. In-place density test reports.
4. Moisture-density relationship test reports.
5. Compressive strength or bearing test reports.
6. All other reports requested by the Architect/Engineer or the University.

NICMAR- SODE-GPPM 11 -216-09-14-50763-2174 Page 15

You might also like