You are on page 1of 17

DAFTAR ANALISA

1 M3 GALIAN TANAH BIASA SNI.03-2835-2002.1

Faktor Harga Jumlah Total Harga


Bahan dan Upah Satuan
Koeffisien (Rp) Harga (Rp) (Rp)
PEKERJA 0.400 OH 22,000 8,800.00
TUKANG - OH 27,500
KEPALA TUKANG - 30,750
MANDOR 0.040 OH 29,000 1,160.00
9,960

1 M3 URUGAN TANAH KEMBALI SNI.03-2835-2002.2

Faktor Harga Jumlah Total Harga


Bahan dan Upah Satuan
Koeffisien (Rp) Harga (Rp) (Rp)
PEKERJA 0.192 OH 22,000 4,224
MANDOR 0.019 OH 29,000 551
4,775.00

1 M3 PASANGAN BATU KALI 1 PC : 3 KP : 10 Ps SNI.03-2835-2002

Faktor Harga Jumlah Total Harga


Bahan dan Upah Satuan
Koeffisien (Rp) Harga (Rp) (Rp)
BATU KALI 1.1 M3 166,500 183,150.00
SEMEN PORTLAND 50 Kg 1,040 52,000.00
PASIR PASANG 0.492 M3 76,400 37,588.80
KAPUR PASANG 0.147 M3 156,300 22,976.10
PEKERJA 2 OH 22,000 33,000.00
TUKANG 0.600 OH 27,500 16,500.00
KEPALA TUKANG 0.060 OH 30,750 1,845.00
MANDOR 0.075 OH 29,000 2,175.00
349,235

1 M2 PASANGAN BATU BATA 1/2 BATU 1 PC : 3 KP : 10 Ps SNI-44

Faktor Harga Jumlah Total Harga


Bahan dan Upah Satuan
Koeffisien (Rp) Harga (Rp) (Rp)
BATU BATA 70.000 bh 300 21,000.00
SEMEN PORTLAND 4.5 Kg 1,040 4,680.00
PASIR PASANG 0.050 M3 76,400 3,820.00
KAPUR PASANG 0.015 M3 156,300 2,344.50
PEKERJA 0.320 OH 22,000 7,040.00
TUKANG 0.100 OH 27,500 2,750.00
KEPALA TUKANG 0.010 OH 30,750 307.50
MANDOR 0.015 OH 29,000 435.00
42,377.00
I.03-2835-2002.1

I.03-2835-2002.2
1 M2 PLESTERAN 1PC: 3Kp : 10 PS. 1,5 cm SNI.03-2835-2002.9

Faktor Harga Jumlah


Bahan dan Upah Satuan Total Harga (Rp)
Koeffisien (Rp) Harga (Rp)
PORLAN CEMEN (PC) 1.840 Kg 1,040 1,914
PASIR PASANG 0.010 M3 76,400 764
KAPUR PASANG 0.006 M3 156,300 938
PEKERJA 0.200 OH 22,000 4,400
TUKANG 0.150 OH 27,500 4,125
KEPALA TUKANG 0.015 OH 30,750 461
MANDOR 0.010 OH 29,000 290
12,891.65

1 M3 SLOOF BETON (200Kg + BEGESTING) SNI-35

Faktor Harga Jumlah


Bahan dan Upah Satuan Total Harga (Rp)
Koeffisien (Rp) Harga (Rp)
PAPAN ALBASIAH 0.270 M3 1,200,000 324,000
PAKU 2"-5" 2 Kg 15,000 30,000
BESI BETON 200 M3 9,238 1,847,600
BENDRAD 3.000 Kg 15,000 45,000
SEMEN PORTLAND 323 Kg 1,040 335,920
PASIR 0.520 M3 76,400 39,728
SPLIT/KRIKIL 0.780 M3 206,600 161,148
PEKERJA 4.850 OH 22,000 106,700
TUKANG BATU 0.350 OH 27,500 9,625
TUKANG KAYU 1.560 OH 27,500 42,900
TUKANG BESI 1.400 OH 27,500 38,500
KEPALA TUKANG 0.331 OH 30,750 10,178
MANDOR 0.170 OH 29,000 4,930
2,996,229.25

1 M3 TANGGA BETON/ PLAT/ BALOK (200kg BESI +BEGESTING) SNI-44

Faktor Harga Jumlah


Bahan dan Upah Satuan Total Harga (Rp)
Koeffisien (Rp) Harga (Rp)
BALOK TERENTANG 0.250 M3 1,800,000 450,000
PAKU 2"-5" 2 Kg 15,000 30,000
BESI BETON 200 M3 9,238 1,847,600
BENDRAD 3 Kg 15,000 45,000
SEMEN PORTLAND 323 Kg 1,040 335,920
POLY WOOD 2.5 lbr 127,000 317,500
PASIR 0.520 M3 76,400 39,728
KRIKIL 0.720 M3 206,600 148,752
PEKERJA 5.60 OH 22,000 123,200
TUKANG BATU 0.350 OH 27,500 9,625
TUKANG KAYU 2.300 OH 27,500 63,250
TUKANG BESI 1.400 OH 27,500 38,500
KEPALA TUKANG 0.405 OH 30,750 12,454
MANDOR 0.202 OH 29,000 5,858
3,467,386.75
1 M3 PEKERJAAN KUZYN PINTU/ JENDELA (KAYU AKASIA) SNI.03-3434-2002.2

Faktor Harga Jumlah


Bahan dan Upah Satuan Total Harga (Rp)
Koeffisien (Rp) Harga (Rp)
BALOK AKASIA 6/12 1.100 M3 2,400,000 2,640,000
PEKERJA 6.000 OH 22,000 132,000
TUKANG 18.000 OH 27,500 495,000
KEPALA TUKANG 2.000 OH 30,750 61,500
MANDOR 0.300 OH 29,000 8,700
3,337,200.00

1 M3 PEKERJAAN PINTU PANIL (KAYU AKASIA) SNI.03-3434-2002.8

Faktor Harga Jumlah


Bahan dan Upah Satuan Total Harga (Rp)
Koeffisien (Rp) Harga (Rp)
PAPAN AKASIA 0.040 M3 2,400,000 96,000
PEKERJA 1.000 OH 22,000 22,000
TUKANG 2.500 OH 27,500 68,750
KEPALA TUKANG 0.250 OH 30,750 7,688
MANDOR 0.050 OH 29,000 1,450
195,887.50

1 M3 PEKERJAAN PINTU / JENDELA KACA (KAYU AKASIA) SNI.03-3434-2002.10

Faktor Harga Jumlah


Bahan dan Upah Satuan Total Harga (Rp)
Koeffisien (Rp) Harga (Rp)
PAPAN AKASIA 0.035 M3 2,400,000 84,000
KACA 0.750 M3 60,950 45,713
PEKERJA 0.800 OH 22,000 17,600
TUKANG 2.0 OH 27,500 55,000
KEPALA TUKANG 0.200 OH 30,750 6,150
MANDOR 0.040 OH 29,000 1,160
209,622.50

1 M3 PEKERJAAN KONS.KUDA KUDA (KAYU GLUGU TUA) SNI.03-3434-2002.29

Faktor Harga Jumlah


Bahan dan Upah Satuan Total Harga (Rp)
Koeffisien (Rp) Harga (Rp)
BALOK GLUGU 1.100 M3 2,083,000 2,291,300
PLAT STRIP 15.000 Kg 14,600 219,000
PAKU 2"-5" 1 Kg 10,400 10,400
PEKERJA 4.000 OH 22,000 88,000
TUKANG 12.0 OH 27,500 330,000
KEPALA TUKANG 1.200 OH 30,750 36,900
MANDOR 0.200 OH 29,000 5,800
2,981,400.00
1 M3 PEK. PASANG USUK GLUGU, RENG (KAYU KRUING) SNI.03-3434-2002.32

Faktor Harga Jumlah


Bahan dan Upah Satuan Total Harga (Rp)
Koeffisien (Rp) Harga (Rp)
USUK GLUGU 0.014 M3 2,083,000 29,162
RENG KRUING 0.003 M3 3,579,900 10,739.70
PAKU 0.15 Kg 15,000 2,250
PEKERJA 0.100 OH 22,000 2,200
TUKANG 0.1 OH 27,500 2,750
KEPALA TUKANG 0.010 OH 30,750 308
MANDOR 0.005 OH 29,000 145
47,554.20

1 M' PEKERJAAN LISPLANG (KAYU AKASIA) SNI.03-3434-2002.8

Faktor Harga Jumlah


Bahan dan Upah Satuan Total Harga (Rp)
Koeffisien (Rp) Harga (Rp)
PAPAN AKASIA 3/20 0.0072 M3 2,400,000 17,280
PAKU 2"-5" 0.05 Kg 15,000 750
PEKERJA 0.100 OH 22,000 2,200
TUKANG 0.200 OH 27,500 5,500
KEPALA TUKANG 0.020 OH 30,750 615
MANDOR 0.005 OH 29,000 145.0
26,490.00

1 M2 PEKERJAAN LANGIT LANGIT TERNIT POLOS SNI.03-3434-2002.21

Faktor Harga Jumlah


Bahan dan Upah Satuan Total Harga (Rp)
Koeffisien (Rp) Harga (Rp)
TERNIT POLOS 1.0 lbr 7,500 7,500
PAKU 2"-5" 0.06 Kg 15,000 900
PEKERJA 0.270 OH 22,000 5,940
TUKANG 0.400 OH 27,500 11,000
KEPALA TUKANG 0.040 OH 30,750 1,230
MANDOR 0.0135 OH 29,000 391.5
26,961.50

1 M2 PASANGAN KERAMIK LANTAI (MULIA) SNI.47

Faktor Harga Jumlah


Bahan dan Upah Satuan Total Harga (Rp)
Koeffisien (Rp) Harga (Rp)
KERAMIK 30x30 POLOS 1.1 M3 30,000 33,000
SEMEN PORTLAN 11.38 lbr 1,040 11,835
PASIR PASANG 0.042 M3 76,400 3,208.80
SEMEN WARNA 1.5 Kg 1,910 2,865.00
PEKERJA 0.620 OH 22,000 13,640
TUKANG 0.350 OH 27,500 9,625
KEPALA TUKANG 0.035 OH 30,750 1,076.25
MANDOR 0.0300 OH 29,000 870.0
76,120.25
3-3434-2002.10

3-3434-2002.29
3-3434-2002.32

3-3434-2002.21
1 M2 PEKERJAAN PASANG GENTENG PLENTONG (SOKA) SNI.03-3436-1998.1

Faktor Harga Jumlah


Bahan dan Upah Satuan Total Harga (Rp)
Koeffisien (Rp) Harga (Rp)
GENTENG PLENTONG 25 Bh 850 21,250
PEKERJA 0.150 OH 22,000 3,300
TUKANG 0.075 OH 27,500 2,063
KEPALA TUKANG 0.008 OH 30,750 246
MANDOR 0.008 OH 29,000 232
27,090.50

1 M2 PEKERJAAN PASANG GENTENG KARPUS (SOKA) SNI.03-3436-1998.1

Faktor Harga Jumlah


Bahan dan Upah Satuan Total Harga (Rp)
Koeffisien (Rp) Harga (Rp)
GENTENG KARPUS 3.5 Bh 3,000 10,500
SEMEN PORTLAN 8.00 Kg 1,040 8,320
PASIR 0.03 M3 76,400 2,445
PEKERJA 0.400 OH 22,000 8,800
TUKANG 0.200 OH 27,500 5,500
KEPALA TUKANG 0.020 OH 30,750 615
MANDOR 0.002 OH 29,000 58
36,237.80

1 M2 PEKERJAAN PENGECATAN BARU (PLAMIR,3 LAP.CAT) SNI-14

Faktor Harga Jumlah


Bahan dan Upah Satuan Total Harga (Rp)
Koeffisien (Rp) Harga (Rp)
PLAMIR 0.1 Kg 3,000 300
CAT DASAR 1 X 0.10 Kg 12,925 1,293
CAT 2X 0.20 Kg 12,925 2,585
PEKERJA 0.020 OH 22,000 440
TUKANG 0.060 OH 27,500 1,969
KEPALA TUKANG 0.0063 OH 30,750 194
MANDOR 0.0025 OH 29,000 73
6,852.48

1 M2 PEKERJAAN PENGECATAN KAYU BARU SNI-9

Faktor Harga Jumlah


Bahan dan Upah Satuan Total Harga (Rp)
Koeffisien (Rp) Harga (Rp)
CAT MENI 0.2 Kg 27,000 5,400
PLAMIR 0.15 Kg 15,900 2,385
CAT PENUTUP AVIAN 3 X 0.350 Kg 35,000 12,250
MINYAK CAT 0.40 ltr 7,475 2,990
PEKERJA 0.070 OH 22,000 1,540
TUKANG 0.110 OH 27,500 3,025.00
KEPALA TUKANG 0.0040 OH 30,750 123.00
MANDOR 0.0025 OH 29,000 72.50
27,785.50
1 BUAH KUNCI SLOT SNI.11

Faktor Jumlah
Bahan dan Upah Satuan Harga (Rp) Total Harga (Rp)
Koeffisien Harga (Rp)
SLOT PINTU YALF 1 Bh 60,900 60,900
PEKERJA 0.020 OH 22,000 440
TUKANG 0.200 OH 27,500 5,500
KEPALA TUKANG 0.020 OH 30,750 615
MANDOR 0.001 OH 29,000 29
67,484.00

1 BUAH PASANG ENGSEL PINTU SNI.5

Faktor Jumlah
Bahan dan Upah Satuan Harga (Rp) Total Harga (Rp)
Koeffisien Harga (Rp)
ENGSEL PINTU NILON 1 Bh 10,200 10,200
PEKERJA 0.015 OH 22,000 330
TUKANG 0.150 OH 27,500 4,125
KEPALA TUKANG 0.015 OH 30,750 461
MANDOR 0.00075 OH 29,000 21.75
15,138.00

1 BUAH PASANG ENGSEL JENDELA SNI.6


Faktor Jumlah
Bahan dan Upah Satuan Harga (Rp) Total Harga (Rp)
Koeffisien Harga (Rp)
ENGSEL JENDELA 1 Bh 6,900 6,900
PEKERJA 0.010 OH 22,000 220
TUKANG 0.100 OH 27,500 2,750
KEPALA TUKANG 0.010 OH 30,750 308
MANDOR 0.005 OH 29,000 145.00
10,322.50

1 BUAH PASANG KAIT ANGIN SNI.9

Faktor Jumlah
Bahan dan Upah Satuan Harga (Rp) Total Harga (Rp)
Koeffisien Harga (Rp)
KAIT ANGIN 1 Bh 9,400 9,400
PEKERJA 0.015 OH 22,000 330
TUKANG 0.150 OH 27,500 4,125.00
KEPALA TUKANG 0.020 OH 30,750 513.75
MANDOR 0.00075 OH 29,000 21.75
14,390.50

1 M2 PEK. PASANG RANGKA LANGIT LANGIT (KAYU TAHUN) SNI.03-3434-2002.40

Faktor Jumlah
Bahan dan Upah Satuan Harga (Rp) Total Harga (Rp)
Koeffisien Harga (Rp)

BALOK KAYU TAHUN 0.0125 M3 1,800,000 22,500


PAKU 2"-5" 0.1 Kg 15,000 1,500
PEKERJA 0.150 OH 22,000 3,300
TUKANG 0.3 OH 27,500 6,875
KEPALA TUKANG 0.025 OH 30,750 769
MANDOR 0.075 OH 29,000 2,175
37,118.75
3-3434-2002.40
1 M2 PLESTERAN 1PC: 3 Ps TEBAL 15 mm F.6.3

Faktor Harga Jumlah


Bahan dan Upah Satuan Total Harga (Rp)
Koeffisien (Rp) Harga (Rp)
PORLAN CEMEN (PC) 6.480 Kg 1,040 6,739
PASIR PASANG 0.019 M 3
76,400 1,452
PEKERJA 0.200 OH 22,000 4,400
TUKANG 0.150 OH 27,500 4,125
KEPALA TUKANG 0.015 OH 30,750 461
MANDOR 0.010 OH 29,000 290
17,467.05

1 bh CLOSET JONGKOK BIASA SNI.2

Faktor Harga Jumlah


Bahan dan Upah Satuan Total Harga (Rp)
Koeffisien (Rp) Harga (Rp)
CLOSED JONGKOK BIASA 1.0 bh 152,958 152,958
PORLAN CEMEN (PC) 6.0 Kg 1,040 6,240
PASIR PASANG 0.010 M3 76,400 764
PEKERJA 1.0 OH 22,000 22,000
TUKANG 1.0 OH 27,500 27,500
KEPALA TUKANG 1.0 OH 30,750 30,750
MANDOR 0.160 OH 29,000 4,640
244,852.00

1 M3 URUGAN PASIR BAWAH PONDASI B.6.15

Faktor Harga Jumlah


Bahan dan Upah Satuan Total Harga (Rp)
Koeffisien (Rp) Harga (Rp)

PASIR URUG 1.2 M3 76,400 91,680


PEKERJA 0.192 OH 22,000 4,224
MANDOR 0.019 OH 29,000 551
96,455.00
RAB PEMBANGUNAN RUANG KELAS BARU
SMK BINA KARYA 1 KARANGANYAR
Jl. KARTINI NO. 6 KARANGANYAR - KEBUMEN
TAHUN 2009
Harga Satuan Jumlah Harga Jumlah Total
No Jenis Pekerjaan Analisis Volume
(Rp) (Rp) (Rp)
I Pek. Persiapan
1 Pekerjaan Bongkaran Ls 2,700,000.00
2 Administrasi dan dokumen Ls 1,500,000.00
3 Pek. Pengukuran Ls 500,000.00
Sub total pekerjaan persiapan 4,700,000.00
II Pek. Tanah/ Galian
1 Galian Pondasi SNI.03-2835-2002.1 49.20 m² 9,960.00 490,032.00
2 Urugan Tanah SNI.03-2835-2002.2 16.40 m³ 4,775.00 78,310.00
3 Urugan Pasir B.6.15 3.85 m² 96,455.00 371,351.75
Sub total pekerjaan tanah 939,693.75
III Pek. Pasangan
1 Pasangan Batu Kali SNI.03-2835-2002 49.20 m² 349,234.90 17,182,357.08
2 Pasangan Dinding 1/2 batu SNI-44 390.29 m² 42,377.00 16,539,319.33
3 Plesteran Dinding 15 cm SNI.03-2835-2002.9 780.59 m² 12,891.65 10,063,093.07
4 Plesteran beton 1.5 cm F.6.3 95.85 m² 17,467.05 1,674,216.74
Sub total pekerjaan pasangan 45,458,986.23
IV Pek. Beton bertulang
1 Foot plat Beton 1Pc:2Ps:3Kr SNI-35 4.416 m³ 2,996,229.25 13,231,348.37
2 Sloof beton 15/20 SNI-35 1.080 m³ 2,996,229.25 3,235,927.59
3 Kolom praktis 15/20 SNI-35 6.2425 m³ 2,996,229.25 18,703,961.09
4 Tiang Beton 15/25 SNI-35 1.05 m³ 2,996,229.25 3,146,040.71
5 Balok latai 15/20 SNI-35 1.1700 m³ 2,996,229.25 3,505,588.22
6 Ring balok 1Pc:2Ps:3Kr SNI-35 2.8500 m³ 2,996,229.25 8,539,253.36
7 Balok Beton induk 20/55 SNI-44 4.53 m³ 3,467,386.75 15,707,261.98
8 Plat lantai 1Pc:2Ps:3Kr SNI-44 28.35 m³ 3,467,386.75 98,300,414.36
9 Tangga Beton 1Pc:2Ps:3Kr SNI-44 2.100 m³ 3,467,386.75 7,281,512.18
10 Balok Sunduk 7/30 SNI-44 0.651 m³ 3,467,386.75 2,257,268.77
Sub total pekerjaan beton 173,908,576.64
V Pek. Kusen pintu dan jendela (Kamper)
1 Kusen pintu/jendela Kamper SNI.03-3434-2002.2 1.9343 m³ 6,857,200.00 13,263,881.96
2 Daun pintu panil 3 cm Kamper SNI.03-3434-2002.8 11.52 m³ 323,887.50 3,731,184.00
3 Jendela kaca 5 mm Kamper SNI.03-3434-2002.10 14.40 m³ 321,623.00 4,631,371.20
4 Jendela kaca mati 5 mm Ls 9.60 m³ 125,623.00 1,205,980.80
5 Jalusi 2/10 Papan Kamper Ls 208.00 m² 16,500.00 3,432,000.00
Sub total pekerjaan kusen pintu/jendela 26,264,417.96
VI Pek. Rangka dan penutup atap
1 Rangka atap kayu Glugu SNI.03-3434-2002.29 4.3488 m³ 2,981,400.00 12,965,512.32
2 Pas.usuk glugu/reng ky.tahun SNI.03-3434-2002.32 574.50 m² 47,554.20 27,319,887.90
3 Pas genteng plentong press SNI.03-3436-1998.1 574.50 m² 27,090.50 15,563,492.25
4 Pasang kerpus SNI.03-3436-1998.1 51.50 m¹ 36,237.80 1,866,246.70
5 Pasang lisplang akasia 2/20 SNI.03-3434-2002.8 107.00 m¹ 26,490.00 2,834,430.00
6 Pas.rangka langit-langit SNI.03-3434-2002.40 456.00 m¹ 37,118.75 16,926,150.00
7 Pas.langit-langit softboard SNI.03-3434-2002.21 456.00 m² 37,118.75 16,926,150.00
Sub total pekerjaan kusen pintu/jendela 94,401,869.17
VII Pek. lantai
1 Keramik lantai 30x30putih SNI.47 501.75 m² 76,120.25 38,193,335.44
2 Pas Keramik KM/WC 20x20 SNI.47 7.50 m² 76,120.25 570,901.88
3 Pas. Keramik Dinding 20x25 SNI.47 21.75 m² 76,120.250 1,655,615.44
Sub total pekerjaan lantai 40,419,852.75
VIII Pek. Cat
1 Cat tembok SNI-14 876.43 6,852.48 6,005,714.66
2 Cat Minyak SNI-9 211.19 27,785.50 5,868,075.32
3 Cat Ternit SNI-14 21.75 6,852.48 149,041.33
Harga Satuan Jumlah Harga Jumlah Total
No Jenis Pekerjaan Analisis Volume
(Rp) (Rp) (Rp)
Sub total pekerjaan Cat 12,022,831.31
IX Pek. Utilitas
1 Pas.closet Jongkok Biasa SNI.2 2 bh 244,844.00 489,688.00
2 Pas bak mandi fiber Ls 2 bh 200,000.00 400,000.00
3 pas pipa pvc 3/4 Ls 8 m 10,000.00 75,000.00
4 pas lampu TL 20 watt komplit Ls 30 bh 150,000.00 4,500,000.00
5 pas stop kontak Ls 15 bh 150,000.00 2,250,000.00
6 pas kran 3/4 Ls 2 bh 30,000.00 60,000.00
Sub total pekerjaan utilitas 7,774,688.00
X Pek. Penggantung
1 Slot pintu SNI.11 17 bh 67,484.00 1,147,228.00
2 Engsel pintu SNI.5 21 bh 15,138.00 317,898.00
3 Grendel jendela ls 30 bh 4,500.00 135,000.00
4 Engsel jendela SNI.6 12 bh 10,322.50 123,870.00
5 Pas.kait angin SNI.9 30 bh 14,390.50 431,715.00
Sub total pekerjaan penggantung 2,155,711.00

JUMLAH TOTAL = 408,046,626.81


BERITA ACARA PENETAPAN
RENCANA ANGGARAN PEMBANGUNAN RUANG KELAS BARU (RKB)

Pada hari ini , Sabtu 28 Pebruari 2009 , kami yang bertanda tangan di bawah ini

Nama : SIMIN
Jabatan : Ketua Komite Sekolah
Instansi : SMK Bina Karya 1
Alamat : Jl. Kartini No 6 Karanganyar Kab. Kebumen

Telah melaksanakan dan menyelesaikan Rencana Anggaran Biaya (RAB) Pembangunan


Ruang Kelas Baru di SMK Bina Karya 1 Karanganyar Kab. Kebumen dengan nilai nominal
dan jenis pekerjaan:

I Pek. Persiapan 4,700,000


II Pek. Tanah/ Galian 939,694
III Pek. Pasangan 45,458,986
IV Pek. Beton bertulang 173,908,577
V Pek. Kusen pintu dan jendela (Kamper) 26,264,418
VI Pek. Rangka dan penutup atap 94,401,869
VII Pek. lantai 40,419,853
VIII Pek. Cat 12,022,831
IX Pek. Utilitas 7,774,688
X Pek. Penggantung 2,155,711
Jumlah 408,046,627

Biaya tak terduga (10%) = 40,804,663


Jumlah total = 448,851,289
Dibulatkan = 448,800,000

Total Biaya Pembangunan RKB = 448,800,000


Bantuan Pemerintah = 359,040,000
Dana Pendamping Sekolah (20%) = 89,760,000

KETUA KOMITE SEKOLAH KEPALA SEKOLAH

SIMIN MULYANTO,S.E.
DAFTAR HARGA SATUAN BAHAN DAN UPAH
PEMBANGUNAN RUANG KELAS BARU SMK BINA KARYA 1
JL. KARTINI 6 KARANGANYAR KEBUMEN
TAHUN 2009

A. BAHAN

HARGA SATUAN
NO SATUAN JENIS BAHAN
(Rp)

1 M3 TANAH URUG Rp 25,000


2 M3 PASIR BETON Rp 76,400
3 M3 PASIR PASANG Rp 76,400
4 M3 PASIR URUG Rp 30,000
5 M3 KAPUR PASANG Rp 156,300
6 M3 BATU KALI Rp 166,500
7 M3 SPLIT/ KRIKIL 2/3 CM Rp 206,600
8 Bj BATU BATA Rp 300
9 Kg SEMEN PORTLAN Rp 1,040
10 Kg PC WARNA Rp 3,000
11 Kg BESI BETON Rp 9,238
12 Kg BENDRAD Rp 15,000
13 Kg PLAT BEGEL Rp 10,000
14 Bj KERAMIK 20 x 20 Rp 3,000
15 Bj KERAMIK 20 X 25 Rp 3,000
16 Bj KERAMIK 30 x 30 Rp 3,000
17 M3 KAYU AKASIA Rp 2,400,000
18 M3 KAYU KRUING Rp 3,100,000
19 Kg PAKU USUK Rp 9,500
20 Kg PAKU KAIT Rp 7,500
21 Lbr SENG PLAT BJLS 30 Rp 65,000
22 Bj GENTENG PRES KODOK Rp 750
23 Bj GENTENG KARPUS Rp 4,000
24 Lbr ASBES GELOMBANG Rp 50,000
25 Kg CAT TEMBOK DECOLITH Rp 12,925
26 Kg CAT MINYAK Rp 35,000
27 Kg MENY BESI Rp 27,000
28 Kg PLAMIR TEMBOK Rp 3,000
29 Kg PLAMIR KAYU Rp 10,000
30 Lbr SOFT BOARD Rp 22,500
31 M1 LIS KAYU 1/4 Rp 5,000
32 M3 KUNCI TAHAN BIASA Rp 52,000
33 M3 ENGSEL PINTU Rp 11,000
34 M3 ENGSEL JENDELA Rp 9,000
35 M3 KUNCI SLOT Rp 64,500
36 M3 KLOSET JONGKOK Rp 525,000
37 M3 KAIT ANGIN Rp 8,000
38 M2 KACA BENING 3 MM Rp 65,000
B. UPAH
HARGA SATUAN
NO SATUAN JENIS UPAH (RP)
1 HARI TUKANG BATU 27,500
2 HARI TUKANG KAYU 27,500
3 HARI TUKANG BESI 27,500
4 HARI TUKANG CAT 27,500
5 HARI KEPALA TUKANG 30,750
6 HARI PEKERJA 22,000
7 HARI MANDOR 29,000
REKAPITULASI RENCANA ANGGARAN BIAYA
PEMBANGUNAN RUANG KELAS BARU
SMK BINA KARYA 1 KARANGANYAR KEBUMEN
TAHUN 2009

NO JENIS PEKERJAAN JUMLAH HARGA


I Pek. Persiapan 4,700,000.00
II Pek. Tanah/ Galian 939,693.75
III Pek. Pasangan 45,458,986.23
IV Pek. Beton bertulang 173,908,576.64
V Pek. Kusen pintu dan jendela (Kamper) 26,264,417.96
VI Pek. Rangka dan penutup atap 94,401,869.17
VII Pek. lantai 40,419,852.75
VIII Pek. Cat 12,022,831.31
IX Pek. Utilitas 7,774,688.00
X Pek. Penggantung 2,155,711.00
Jumlah 408,046,626.81

Biaya tak terduga (10%) = 40,804,662.68


Jumlah total = 448,851,289.49
Dibulatkan = 448,800,000.00

Total Biaya Pembangunan RKB = 448,800,000.00


Bantuan Pemerintah = 359,040,000.00
Dana Pendamping Sekolah (20%) = 89,760,000.00

KETUA KOMITE SEKOLAH PERENCANA

SIMIN KARMAN

Mengetahui
Kepala Sekolah

Mulyanto,S.E

You might also like