Professional Documents
Culture Documents
1- introduction
In common practice, electric distribution systems are using radial feeders due to their economical
aspects and simplicity of protection schemes. the protection scheme uses simple protection devices
such as auto-recloser, fuses and, in some cases, over-current relays for main feeder. The coordination
between these protection devices is well-established. It causes many problems in the protection
system, such as false tripping of protective devices, protection blinding, undesirable network
islanding and out of- synchronism auto-reclosers. When a fault occurs, it is important to locate the
fault quickly to minimize the damage and improve system reliability. Proper selectivity between
relays, auto-reclosers, fuses and other protective equipment is necessary. The study is implemented
on a 33-node radial distribution network using ETAP software. The proposed in these chapter firstly
study and analyses setting and load flow. Secondly design how to protect the system; select placement
protection devices; and adopt the coordination between these devices. The proposed fuses large size
saving so it using auto-recloser. Because a lot of faults at transmission line it transient faults. When
save the fuse against transient faults we save a lot of time to change fuse; save the cost and ensures
continued service and increased reliability.
System data
There are same load models used in this test feeder. The loads are different value. The Total active
and reactive loads in system respectively are 3715 KW and 2300 KVAR. Information about the 33-
bus system is Presented in Table A
Table (1) System data for 33-bus radial distribution network
3- Setting of Model Using ETAP
Figure (2); Single line diagram of the original system IEEE 33-Bus under Study in ETAP
Overhead lines have same configurations based on the number of phases and same parameter of each
phase is following; And impedance of each T.L it following at table (A)
Frequency 50
Conductor type AAAC
Source name Pirelli
Temperature
Base T1 Base T2 Ta Tc
20 75 35 75
code size strands
Chlorine 34.4 mm^2 7
Note :
Positive resistane = negative resistance
zero sequance resistance = 3 * positive resistance in the system
3-2 Power grid
The system have one source U1. it connection 3 phase, 12.66 KV Swing balanced, operated at 100%
of voltage,3.567MW, 2.179Mvar.
The short circuit rating at 3 phase 500MVAsc, X/R=10.
At 1 phase 333.435MVAsc, X/R=20 following at the figure (4)
Buses 33
Branches 32
Generators 0
Power Grids 1
Loads 32
Load-MW 3.567
Load-Mvar 2.179
Generation-MW 3.567
Generation-Mvar 2.179
Loss-MW 0.162
Loss-Mvar 0.092
Mismatch-MW 0
Mismatch-Mvar 0
Mvar Amp
Bus ID Nominal kV Voltage MW Loading
Loading Loading
1 12.66 100 3.567 2.179 190.6
2 12.66 99.73 3.557 2.174 190.6
3 12.66 98.72 3.059 1.951 167.6
4 12.66 98.06 2.06 1.469 117.7
5 12.66 97.42 1.931 1.385 111.2
6 12.66 95.82 1.845 1.331 108.3
7 12.66 95.52 0.959 0.46 50.76
8 12.66 94.36 0.767 0.362 41.01
9 12.66 93.82 0.586 0.271 31.37
10 12.66 93.33 0.53 0.252 28.68
11 12.66 93.25 0.478 0.234 26.01
12 12.66 93.13 0.438 0.208 23.74
13 12.66 92.61 0.384 0.176 20.8
14 12.66 92.42 0.332 0.145 17.88
15 12.66 92.3 0.229 0.077 11.95
16 12.66 92.18 0.178 0.068 9.432
17 12.66 92.01 0.127 0.051 6.777
18 12.66 91.96 0.076 0.034 4.131
19 12.66 99.68 0.356 0.159 17.85
20 12.66 99.33 0.266 0.118 13.37
21 12.66 99.26 0.177 0.079 8.913
22 12.66 99.19 0.089 0.039 4.455
23 12.66 98.38 0.893 0.434 46
24 12.66 97.75 0.801 0.382 41.39
25 12.66 97.43 0.399 0.19 20.66
26 12.66 95.66 0.828 0.847 56.48
27 12.66 95.44 0.771 0.823 53.88
28 12.66 94.45 0.708 0.793 51.31
29 12.66 93.75 0.648 0.77 48.97
30 12.66 93.44 0.54 0.707 43.42
31 12.66 93.09 0.364 0.182 19.96
32 12.66 93.01 0.234 0.121 12.92
33 12.66 92.98 0.052 0.035 3.058
4-4 load flow Branch results using ETAP
%
From To kW kvar Amp kW kvar
ID % PF Voltage
Bus Bus Flow Flow Flow Losses Losses
Drop
Line1 1 2 3567 2179 190.6 85.34 0.27 10.049 5.122
Line2 2 3 3100 1955 167.6 84.59 1.01 41.543 3.96
Rated %
ID Rating kW kvar Amp % PF Vtermal
kV Loading
Load2 117 kVA 12.66 99.788 59.871 5.321 85.75 100 99.73
Load3 98.5 kVA 12.66 87.708 38.984 4.434 91.38 98.8 98.72
Load4 144 kVA 12.66 115 76.805 6.44 83.21 97.9 98.06
Load5 67.1 kVA 12.66 56.944 28.476 2.98 89.44 97.4 97.42
Load6 63.2 kVA 12.66 55.095 18.362 2.764 94.87 96 95.82
Load7 224 kVA 12.66 183 91.413 9.758 89.44 95.7 95.52
Load8 224 kVA 12.66 178 89.198 9.639 89.44 94.5 94.36
Load9 63.2 kVA 12.66 52.816 17.602 2.706 94.87 94 93.82
Load10 63.2 kVA 12.66 52.261 17.417 2.692 94.87 93.5 93.33
Load11 54.1 kVA 12.66 39.135 26.085 2.3 83.21 93.1 93.25
Load12 69.5 kVA 12.66 52.036 30.351 2.95 86.38 93.1 93.13
Load13 69.5 kVA 12.66 51.46 30.015 2.934 86.38 92.5 92.61
Load14 144 kVA 12.66 102 68.214 6.069 83.21 92.2 92.42
Load15 60.8 kVA 12.66 51.115 8.517 2.56 98.64 92.4 92.3
Load16 63.2 kVA 12.66 50.989 16.993 2.659 94.87 92.3 92.18
Load17 63.2 kVA 12.66 50.8 16.93 2.654 94.87 92.2 92.01
Load18 98.5 kVA 12.66 76.114 33.831 4.131 91.38 92 91.96
Load19 98.5 kVA 12.66 89.422 39.746 4.477 91.38 99.7 99.68
Load20 98.5 kVA 12.66 88.791 39.466 4.461 91.38 99.4 99.33
Load21 98.5 kVA 12.66 88.667 39.411 4.458 91.38 99.3 99.26
Load22 98.5 kVA 12.66 88.555 39.361 4.455 91.38 99.2 99.19
Load23 103 kVA 12.66 87.146 48.404 4.621 87.42 98.3 98.38
Load24 465 kVA 12.66 401 191 20.73 90.29 97.7 97.75
Load25 465 kVA 12.66 399 190 20.66 90.29 97.4 97.43
Load26 65 kVA 12.66 54.904 22.873 2.836 92.31 95.8 95.66
Load27 65 kVA 12.66 54.65 22.767 2.829 92.31 95.6 95.44
Load28 63.2 kVA 12.66 53.529 17.84 2.724 94.87 94.6 94.45
Load29 139 kVA 12.66 106 61.547 5.943 86.38 93.7 93.75
Load30 632 kVA 12.66 174 524 26.93 31.62 93.4 93.44
Load31 166 kVA 12.66 130 60.821 7.047 90.62 93.3 93.09
Load32 233 kVA 12.66 182 86.638 9.883 90.29 93.1 93.01
Load33 72.1 kVA 12.66 51.878 34.579 3.058 83.21 92.9 92.98
5- Protection devices at case (1)
5-1 Introduction to protection of the system
In common practice, electric distribution systems are using radial feeders due to their economical
aspects and simplicity of protection schemes. the protection schemes use sample protection devices
such as auto-recloser, fuse and in some cases over-current relays for main feeder. The coordination
between these protection devices is well-established. It causes many problems in the protection
system, such as false tripping of protective devices, protection blinding, undesirable network
islanding and out of synchronism auto-reclosers. When fault occurs, it is important to locate the fault
quickly to minimize the damage and improve system reliability. Proper selectivity between relays,
auto-recloser, fuses and other protective is necessary.
we used five Fuses; one reclosers and one over current relay to protect the system. The pickup currents
of the over-current relay and recloser are taken 1.25 of full load current. And the rated size of fuse is
taken as 1.5 to 2.0 times of the maximum full load current.
1- Fuses
Current full load it 117.7(AMP). Taken pickup current 1.25*117.7 = 147.125 selected 150 A
At high current Ip =1.35 * I sc max at remote end
Ip = 1.35 * 3011 = 4064.85. selected 4050 A
ID Recloser Rec1
Manufacturer G&W Electric
Model Viper-G (15.5kV)
Max kV 15.5
Max Cont. Amp 630 A
Interrupting kA 12.5 KA
Interrupting Time Cycles 4.5
Manufacturer Schweitzer
Controller
Model 351R
fast slow
Trip Element phase phase
U4 - U.S. Extremely
Curve Curve D (116)
Inverse
range 0.1 - 19200 primary 0.1 - 19200 primary
Tap (pickup) setting 150 150
Primary(A) 150 150
The current transformer (CT). ID: CT1. 10P20. ALF*In > I max sc current in secondary
ALF * In = 20* 5 =100 & I max sc = 19250/200 =96.25A; Then we select CT Ratio of 1000:5
The pickup currents of the over-current relay it taken 1.25 of full load current
Ipickup = 1.25 * 190.6 = 238.25 Selected the pickup current 250 (Amp) and time dial 10. The
instantaneous relay; The max short circuit current at remote end of primary zone at bus 3 it
10530(AMP). Ip = 1.35 * I max sc at remote end. Ip = 1.35 * 10530 =14215.5 A. selected 14200A.
Relay ID Relay1
Manufacturer GE Multilin
Model 750/760
CT Ratio 1000:5
Level OC1
Primary zone
Element
From node To node
Relay 1 3
3 time operates 3 6
Recloser 2 time operates 7 14
2 time operates 26 33
Fuse1 15 18
Fuse2 7 14
Fuse3 26 33
Fuse4 23 25
Fuse5 19 22
Applying the coordination star sequence-of-operation (SSO) to the original network without inserting
DG, the primary and backup tripping zones with its tripping time and Short Circuit Current (SCC)
are given in Table (2). Its time-current characteristic (TCC) is shown in Figure (12). The coordination
is simply achieved without any violation. One may note that TCC of R1, Rec1, Fuse2 and fuse3 have
intersection points but outside the minimum and maximum fault levels, which does not affect the
validity of PDC.
Table (2); Tripping elements, time and SCC at different locations