Polus Investments (Seychelles) Limited

Shangri-La Resort at Long Island


Seychelles

First Interim Request for


Extension of Time for Completion and
Additional Payment

Island Construction (Pty) Ltd

June 2008
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

Table of Contents
page

1. Introduction..........................................................................................................5
1.1. Background..................................................................................................5
1.2. Purpose of this Document..........................................................................6
1.3. Scope of this Document..............................................................................7
2. The Structure of the Contract............................................................................8
2.1. The Contract Existing..................................................................................8
2.1.1. Lump Sum Contract Price vis-à-vis Scope of Works..............................8
2.1.2. Provisional Sums..................................................................................12
2.1.2.1. Tender Provisions..........................................................................12
2.1.2.2. Contract Provisions.......................................................................13
2.1.2.3. Current Situation............................................................................15
2.1.2.4. Conclusions...................................................................................16
2.2. Relevant Contract Provisions...................................................................17
2.2.1. Sub-clause 1.9 – Delayed Drawings or Instructions.............................17
2.2.2. Sub-clause 3.3 – Instructions of the Project Manager..........................18
2.2.3. Sub-clause 4.7 – Setting Out................................................................19
2.2.4. Sub-clause 4.12 – Unforeseeable Physical Conditions........................19
2.2.5. Sub-clause 8.3 – Programme...............................................................20
2.2.6. Sub-clause 8.4 – Extension of Time for Completion............................22
2.2.7. Sub-clause 8.8 – Suspension of Works................................................22
2.2.8. Sub-clause 8.9 – Consequences of Suspension..................................23
2.2.9. Sub-clause 12.1 – Works to be Measured...........................................23
2.2.10. Sub-clause 12.3 – Evaluation...........................................................24
2.2.11. Sub-clause 13.1 – Right to Vary.......................................................25
2.2.12. Sub-clause 13.3 – Variation Procedure............................................26
2.2.13. Sub-clause 20.1 – Contractor’s Claims.............................................27
2.3. Original Planning and Cash-flow..............................................................29
2.3.1. The Clause 8 Programme.....................................................................29
2.3.2. Planned versus Actual Turnover...........................................................30
2.4. First Revised Programme of Works.........................................................32
2.5. Second Revised Programme of Works....................................................32
2.6. Actual Progress..........................................................................................34
3. Valuation of Variations.....................................................................................35
3.1. Explanation of Heads of Claim.................................................................35
3.2. Specific Heads of Claim............................................................................35
3.3. Methods of Valuation of the Variations...................................................36
3.3.1. Use of Costs as Basis...........................................................................36
3.3.2. Addition for Profit..................................................................................36
3.3.3. Profit as Part of the Value of Variations................................................36
3.3.3.1. Three Types of Variations.............................................................36
3.3.3.2. Changes in Design of the Works...................................................37

page 2
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

3.3.3.2.1. Technical Variations..................................................................37


3.3.3.2.2. Changes to Specified Sequence and Timing............................38
3.3.3.3. Summary.......................................................................................38
3.3.4. The Effects on Unvaried Work..............................................................39
3.3.5. For Uneconomic Working.....................................................................39
3.3.5.1. Loss of Anticipated Income...........................................................40
3.3.5.2. Wasted Monthly Costs...................................................................40
3.3.5.3. Financing Wasted Monthly Costs..................................................41
3.3.6. Profit as Part of ‘Costs’.........................................................................41
3.3.6.1. Authorities on the Basis of ‘Costs’.................................................41
3.3.6.1.1. Powell-Smith’s ‘Some Building Contract Problems’..................42
3.3.6.1.2. Hudson and Minter v. WHTSO..................................................42
3.3.6.1.3. Hudson on the Scope of ‘Costs’................................................43
3.3.6.1.4. The First Part of the Rule in Hadley v. Baxendale....................44
3.3.6.1.5. The Basic Measure of Damages...............................................45
3.3.6.2. Authorities on the Recovery of Profit.............................................46
3.3.6.2.1. General Principle as to Claims..................................................46
3.3.6.2.2. Wraight v. PH&T (Holdings) Ltd................................................46
3.3.6.2.3. Powell-Smith and Sims on Building Contract Claims...............47
3.3.6.3. Summary.......................................................................................48
3.4. The Contractor’s Summary.......................................................................48
4. Circumstances Giving Rise to Claim..............................................................49
4.1. Contractual Basis – Notification of Changes..........................................49
4.2. Late and Inaccurate Survey Data.............................................................65
4.3. Late Receipt of Final Design Information................................................66
4.4. Additional and Varied Work......................................................................66
4.4.1. Excavation in Hard Rock......................................................................66
4.4.1.1. Change in Sequence and Increased Cost.....................................67
4.4.1.2. Increased Quantity........................................................................67
4.4.2. Increased Quantity in Reinforced Concrete..........................................70
4.4.2.1. Villa Type A3 (Example)................................................................70
4.4.2.2. Villa Type B2 (Example)................................................................71
4.4.3. Suspension of Works............................................................................71
4.4.4. Variations to Design..............................................................................72
4.5. Material Procurement Programme...........................................................72
4.6. Conclusion of Effects of Variations.........................................................74
5. Time Analysis....................................................................................................75
5.1. Method of Analysis....................................................................................75
5.1.1. Mitigation by Contractor........................................................................76
5.1.2. Time for Completion..............................................................................76
5.1.3. Impact on Time - Analyses...................................................................77
5.1.4. The Events that Impacted Progress.....................................................77
5.1.4.1. Event No 1 – Setting Out...............................................................79
5.1.4.2. Event No 2 – Unforeseen Ground Conditions...............................82
5.1.4.3. Event No 3 – Later Receipt of Design Information........................91
5.1.4.4. Event No 4 – Increased Scope of Works....................................101
5.1.4.5. Event No 5 – Partial Suspension of Works.................................114
5.1.4.6. Event No 6 – Design Variations (Stainless Steel Items).............119

page 3
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

5.2. Conclusion................................................................................................121
6. Financial Analysis...........................................................................................122
6.1. Consequences..........................................................................................122
6.1.1. Direct Cost..........................................................................................123
6.1.2. Indirect Cost........................................................................................123
6.1.3. Consequential Cost.............................................................................123
6.2. Costs in Extended Contract Period........................................................123
6.2.1. Nature of Loss and Expense..............................................................123
6.2.2. Contractor’s Entitlement to Reimbursement.......................................124
6.3. Finance Cost.............................................................................................124
6.4. Conclusions..............................................................................................125
7. Extension of Time Entitlement.......................................................................126

8. Additional Payment.........................................................................................127
8.1. Introduction..............................................................................................127
8.2. Evaluation of the Financial Consequences...........................................127
8.2.1. Wasted Costs Arising from Delay and Disruption..............................128
8.2.1.1. Staff and Labour..........................................................................128
8.2.1.2. Equipment....................................................................................129
8.2.1.3. Site and Head Office...................................................................130
8.2.1.4. Summary of Wasted Costs..........................................................132
8.2.2. Additional Costs Arising from Acceleration.........................................132
8.2.3. Additional Costs in Extended Contract Period...................................133
8.2.4. Other Costs.........................................................................................134
8.2.4.1. Procurement of Permanent Materials..........................................134
8.2.4.2. Temporary Materials including Equipment..................................135
8.2.5. Finance Costs.....................................................................................135
8.2.6. Grand Summary..................................................................................136
9. Statement of Claim..........................................................................................138

10. Appendices...................................................................................................139
10.1. Wasted Costs........................................................................................139
10.1.1. Record of Resources – Staff and Labour........................................139
10.1.2. Record of Resources – Equipment.................................................139
10.1.3. Direct and Indirect Costs.................................................................139
10.2. RFI and RFA..........................................................................................140
10.3. Correspondence.....................................................................................141

page 4
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

1. Introduction

1.1. Background
A Contract for Building and Engineering Works Designed by the
Employer was entered into on 27 April 2007 between the Polus
Investments (Seychelles) Limited (hereinafter called “the
Employer”) and Island Construction (PTY) Limited (hereinafter
called “the Contractor”).

During the course of both the Employer’s design and the


construction phases of the Contract to date, a number of events
and factors have affected progress of both the design and
construction processes. The Contractor’s view is that the delays
were not his fault. Consequently, the Contractor believes he
should be allowed an Extension of Time and Additional Payment
to complete the work which is the subject of the Contract. He
seeks reimbursement of his additional costs incurred otherwise
not allowed in his tendered rates and prices.

For the Contractor, this is an important matter. He needs the


Project Manager’s agreement to an extension of time requested
and to an interim determination of his additional costs, in order
to allow earliest compensation and to off-set increasing finance
costs.

The Contractor’s further view is that Site conditions are in


variance to that anticipated as the positions of buildings and the
significant increase in hard rock excavation. In addition the
Project Manager suspended progress of the Works and he has
received much of the design phase late. This design when
received shows a significant increase in the quantities of work to
be performed. These facts entitle him to an extension of time. It
would also entitle him to additional payment for the delay and
disruption caused to date.

As will be seen from the sections following this introduction, the


Employer and/or the Project Manager also required the
Contractor to carry out Construction work to a varied timing and
sequence, as opposed to that anticipated by his programme of
works. This was as a result of unforeseen ground conditions.

The issues became clear from the very start of the construction
process. Once the setting out delays was over-come the
Contractor encountered hard rock in excavation at almost all
building locations. This unforeseen circumstance caused a
varied order of construction to that planned together with
numerous late instructions as design evolved.

page 5
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

All of these factors have caused the Contractor to have to carry


out work in a disrupted and disordered manner, and over a
longer period, than he contracted to do. The Employer’s/the
Project Manager’s errors have caused the Contractor to incur
significant higher costs of construction and in addition,
significant costs arising from delay and disruption.

As will be seen from the following sections of this claim, almost


all areas of the site fell behind programme. In addition, it is of
worthy note that the Contract Price awarded was inclusive of
30% allowance for Provisional Sums. That means the Project
Manager must introduce these works as a Variation to the
Contract. The design and construction work are both now a long
way behind programme.

The Contractor has given notice that he will have to make claims
to achieve the relief and payment to which he believes he is
entitled.

1.2. Purpose of this Document


During the course of the work, the Contractor has suffered delay
and disruption through a number of causes. The consequences
of these causes are the contractual responsibility of the
Employer.

The Contractor has made a number of notice submissions to the


Project Manager with regard to these causes. The Contractor
has thereafter, impacted the programme of works to reflect the
effect of these events and changed circumstances.

We acknowledge receipt of the Employer’s letter dated


19 May 2008 and to the Project Managers letters dated
2, 9 and 12 May 2008 referenced E19-02.05.08, E20-
09.05.08 and E21-12.05.08 respectively.

In summary we disagree entirely with all interpretations,


conclusions and what appears to be a determination
made prior to receipt of the Contractor’s detailed
particulars. In such a situation you are making a
prediction on changed events and circumstances and
their consequences without benefit of the position one
Party to the Contract. This is contrary to the duties and
obligations stated at sub-clause 3.1 and 3.5 of the
General Conditions of Contract.

page 6
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

In our letter of 14 April 2008 we indicated a time to


complete the detailed particulars. However, with
consideration to your position now outlined in these
letters, we require more time to complete this exercise.
As such, we will make our full and detailed submission of
claims on Monday 9 June 2008.

The purpose of this document is, therefore, to provide the


Project Manager with an initial analysis so that he may make an
evaluation of the additional payment based on:

 The delays and disruption experienced to May 2008 and


arising additional costs in the form of Wasted Costs, and

 The extensions time for completion requested by the


Contractor in respect of the cause’s notified and
consequent recovery of arising prolongation costs.

for which the Employer is contractually liable.

1.3. Scope of this Document


This document describes the:

1. Causes of delay and disruption to the Works;

2. Impact of these causes on contract completion;

3. Contractual position regarding the Contractor’s


entitlement to extension of time and additional payment,
and

4. Consequences of delay and disruption in terms of the


additional time and additional payment due to the
Contractor.

The scope of this claim submission is limited to known events to


May 2008. As many of the changed events and circumstances
that have given rise to extensions of time and additional cost
continue, the Contractor will be updating this detailed
submission.

page 7
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

2. The Structure of the Contract

2.1. The Contract Existing


2.1.1.Lump Sum Contract Price vis-à-vis Scope of Works
The Letter of Acceptance dated 7 March 2007 referenced
SHAN/zk/ZK/LOA.01 states at paragraph 3.0:

“As per our agreement the lump sum contract price shall
not be amended unless specifically agreed with the
Employer and the Quantity Surveyor. No additional work
(beyond the scope of the lump sum Contract Price) may
be commenced prior to reaching agreement on the price
thereof.”

In practice this is inoperable and this soon became evident at


early stages of the Contract

In a letter dated 24 October 2007 the Contractor gave notice:

Two important matters require your confirmation:

First, we draw your attention to the changes and


variations that are regularly being instructed as works
proceed. Although they are acceptable to the Contractor
we also wish to record that these changes and variations
are made prior to reaching agreement on the price. This
is as you are aware, contrary to the terms and conditions
of the Contract. In the circumstances, because of this
continuing departure from the Contract, it is understood
that the price and consequent additional cost will be
added to the Contract Price.

Secondly, we have reviewed the estimated quantities in


the Bills of Quantity against actual work depicted on the
drawings issued for construction. It is apparent significant
disparity exists between the measure and provision made
in the Contract. As a result, either the scope must be
adjusted in order to retain the Contract Price or, we
require your agreement to perform these works at the
price contained in the contract which additional cost will
be added to the Contract Price. If you require detail of the
variations discussed here, please have your quantity
surveyor consult with ours as quickly as possible.

In conclusion, we require the Employer’s agreement to


payment of these variations as a matter of urgency.

page 8
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

In a further letter dated 23 November 2007 the Contractor


recorded:

This Contract contains specific conditions in regard to


Variations that would increase or decrease the Lump
Sum Contract Price. We wrote on this matter on 24
October 2007 to which a reply has not been received.

In particular it states that “the lump sum contract price


shall not be amended unless specifically agreed with the
Employer and the Quantity Surveyor. No additional work
(beyond the scope of the lump sum Contract Price) may
be commenced prior to reaching agreement on the price
thereof.”

It further states that “Any changes in the design, which


affect the lump sum Contract Price, must be specifically
agreed by the Employer.”

Essentially this means a new or varied price or rate for all


Variations must first receive agreement of the Employer
together with, if relevant, a revised Contract Price prior to
the issue of an instruction because they:

 Introduce a design change;

 Introduce additional works, and

 Introduce an increase in the scope of work beyond


the quantity stated in the Bills of Quantities.

As such, the purpose of this letter is to record several


and significant Variations introduced since
commencement where value and consequent Contract
Price adjustment are not agreed despite the issue of an
instruction. Consequently, we wish to schedule a
“Variation Meeting” to discuss and agree a procedure
that will ensure such increases in value are properly
reported, valued and paid.

At this juncture we have identified the following Claims


and Variations which have caused the Contract Price to
increase:

1. Additional costs associated with delay and


disruption not the responsibility of the
Contractor;

2. Additional costs associated with the Project


Manager’s instruction to accelerate the Works by
working additional hours;

page 9
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

3. Additional costs arising from delays caused by


late design information;

4. Additional costs in excavation of hard rock and


removal to spoil;

5. Additional costs that arise due to the


construction of “mock-up” villas in a sequence
that is in variance to original planning;

6. The increase in size of structural timber to roof


structures where new rates need to be agreed
prior to procurement;

7. Door timber type and finishing specifications


have changed and new rates need to be agreed
prior to procurement;

8. Window timber type and finishing specifications


have changed and new rates need to be agreed
prior to procurement;

9. Ironmongery specifications have changed and


new rates need to be agreed prior to
procurement;

10. Structural galvanised steel plates have changed


to stainless steel and new rates need to be
agreed prior to procurement.

11. Increased costs arising from additional site work


described in Section B of the Principles of
Measurement for Works of Construction.

This meeting must also acknowledge and agree the


additional work being executed is in accordance with
instructions and design details issued and that they are
beyond the scope of the lump sum Contract Price. This
presently includes:

 Excavation in common material;

 Excavation in rock;

 Concrete in foundations to suit varied


ground conditions; and

 Reinforced concrete in columns, ring beams


and suspended slabs.

In addition, all lump sums for works for which detailed


bills of quantities do not exist need to be prepared and

page 10
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

valued using detailed design drawings received in


September 2007.

Please confirm as soon as possible when a meeting can


be convened as these Claims and Variations must be
recorded and valued as a matter of priority.

The last letter with regards Variations and increased scope of


Works was dated 6 December 2007 and recorded:

We acknowledge receipt of your letter dated 4 December


2007 referenced E-09-04-12-07 and wish to confirm our
position by the following extract from the Contract:

The Letter of Acceptance dated 7 March 2007 referenced


SHAN/zk/ZK/LOA.01 states at paragraph 3.0: “the lump
sum contract price shall not be amended unless
specifically agreed with the Employer and the Quantity
Surveyor. No additional work (beyond the scope of the
lump sum Contract Price) may be commenced prior to
reaching agreement on the price thereof.”

It further states that “Any changes in the design, which


affect the lump sum Contract Price, must be specifically
agreed by the Employer.”

The Contract Agreement dated 27 April 2007 lists the


documents forming the Agreement and the Letter of
Acceptance takes priority over the Conditions of
Contract.

Consequently, your reference to sub-clause 12.3 and


13.1 of the Conditions of Contract, although interesting, is
not relevant in the introduction of Variations on this
project, particularly as sub-clause 3.1 has been amended
by the quoted specific conditions above.

We would point out that although the amendment is


impractical it is a significant revision to both Clause 12
and 13 of the Conditions of Contract. In practise it means
that no Variation arising from additional work or by design
change can commence prior to receiving the agreement
of the Employer.

In conclusion, the purpose of our letter dated 23


November 2007 on this subject matter was to bring these
special circumstances to your attention.

A further existing condition of the Contract relates to Provisional


Sums and their inclusion in the Contract as Variations.

page 11
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

2.1.2.Provisional Sums
Clause 13 empowers the Project Manager to issue instructions
to the Contractor directing him how provisional sums are to be
expended. Provisional sums are included in this Contract where
the precise cost or extent of work is not known at time of tender.
The purpose is to have the sum of money to cover the cost.
When the instruction is issued, the sum inserted is omitted and
the variation is then valued in accordance with the principles of
Clause 12 and 13.

The “Building Contract Dictionary” written by Vincent Powell-


Smith and David Chappell, explains the term provisional sum:

A term used to denote a sum of money included in the


contract by the employer, normally as an amount in the
bills of quantities. It is provided to cover the cost of
something which cannot be foreseen or detailed
accurately at the time tenders are invited. (Contractor’s
profit is not added to this sum.) It may be expended as
the architect instructs…

It is important that the Contractor receives proper valuation of


variations measured in accordance with the provisions stated for
Provisional Sums. In particular, all on-costs and overheads
described and allowed in the existing Bill 1 will be equally
relevant to any measured Variations valued under Clause 12
and 13 of the Contract conditions.

It is of worthy note that a very large percentage of the Contract


Works and therefore, the Contract Price, had not been
sufficiently designed at tender stage. The consequences of this
situation will allow the Contractor to measure and value these
works as an addition, within the provisions of Clause 12 and 13.
As such, the value of items listed in Bill no 1 must be increased
to include works falling under Variations. This would then allow
the Contractor to be paid for the work performed.

2.1.2.1. Tender Provisions

At tender stage the value shown for Measured Work was (Bills 1
to 34 inclusive) SCR20,677,661.15, and the value of the
Preliminaries (Bill 1) has been derived from this figure.

However, a value for Preliminary items is clearly not included as


part of the Provisional Sum amount declared by the Employer at
tender stage. The value of Provisional Sums included, amounts
to SCR22,539,454.00, a figure which is greater than the value of
the original Measured Works forming the Contract.

page 12
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

2.1.2.2. Contract Provisions

The contract provides as follows:

Under Clause 13.5, Provisional Sums; Each provisional sum


shall only be used in whole or in part in accordance with the
Project Managers instruction and that the contract sum shall be
adjusted accordingly. It further provides that when the Project
Manager instructs work to be provided by the contractor such
work shall be valued under Clause 13.3 (Variation Procedure).

Under Clause 13.3, Variation Procedure: Each variation will be


valued in accordance with Clause 12. This has been amended
in the Particular Conditions where the measure and value is
made in accordance with the RICS Principles of Measurement
for Works of Construction. Consequently, the full wording of
Clause 12 is:

Under Clause 12.3, Evaluation: a new rate or price shall be


appropriate for an Item of Work if:

(a)

the measured quantity of the item is changed


by more than 10% from the quantity of this
item in the Bill of Quantities or other
Schedule,

this change in quantity multiplied by such


specified rate for this item exceeds 0.01% of
the Accepted Contract Amount,

this change in quantity directly changes the


Cost per unit quantity of this item by more
than 1%, and

this item is not specified in the Contract as a


“fixed rate item";

or (b)

i. the work is instructed under Clause 13


[Variations and Adjustments],

ii. no rate or price is specified in the Contract


for this item, and

iii. no specified rate or price is appropriate


because the item of work is not of similar

page 13
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

character, or is not executed under similar


conditions, as any item in the Contract.

Each new rate or price shall be derived from any relevant


rates or prices in the Contract, with reasonable
adjustments to take account of the matters described in
sub-paragraph (a) and/or (b), as applicable. If no rates or
prices are relevant for the derivation of a new rate or
price, it shall be derived from the reasonable Cost of
executing the work, together with profit, taking account of
any other relevant matters.

With regard to which part of sub-clause 12.3 above is relevant, it


is obvious the measured quantity of the Works originally
included as a value under Provisional Sums complies with those
conditions stated in paragraph (a). As such, all rates and prices
from which the varied works are valued to date, for those Works
not forming part of the original Measured Works, must be
appropriately adjusted.

The procedure in the Contract for the valuation of a variation is


described under sub-clause 13.3 and states:

If the Project Manager requests a proposal, prior to


instructing a Variation, the Contractor shall respond in
writing as soon as practicable, either by giving reasons
why he cannot comply (if this is the case) or by
submitting:

a. a description of the proposed work to be


performed and a programme for its
execution,

b. the Contractor’s proposal for any necessary


modifications to the programme according
to Sub-Clause 8.3 [Programme] and to the
Time for Completion, and

c. the Contractor’s proposal for evaluation of


the Variation.

The Project Manager shall, as soon as practicable after


receiving such proposal (under Sub-Clause 13.2 [Value
Engineering] or otherwise), respond with approval,
disapproval or comments. The Contractor shall not delay
any work whilst awaiting a response.

Each instruction to execute a Variation, with any


requirements for the recording of Costs, shall be issued
by the Project Manager to the Contractor, who shall
acknowledge receipt.

page 14
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

Each Variation shall be evaluated in accordance with


Clause 12 [Measurement and Evaluation], unless the
Project Manager instructs or approves otherwise in
accordance with this Clause.

The procedure adopted by the Project Manager would appear to


be a submission of a “Drawing for Construction”. Therefore, the
three stage process described and allowed above has not been
observed. Nonetheless, it is apparent as a consequence of
these variations, that the value of the Works flowing from the
Provisional Sums has not been determined at time of tender.

2.1.2.3. Current Situation

The Preliminaries had originally been calculated based on the


value of Measured Works identified at tender. A breakdown of
the Preliminaries shown below demonstrates that though certain
items and their related cost therein, is considered fixed, the
majority are of a variable nature. Consequently, the
Preliminaries and their value are directly proportional to the
value of Measured Works to be executed.

Item Nature of Cost Fixed Variable

1 Insurance 250,000.00
2 Foreign Staff, Labour Repatriation 450,000.00
3 Facilities for Staff and Labour 170,000.00
4 Measures against Insect and Pect Nuisance 60,000.00
5 Supply of Foodstuffs 660,000.00
6 Supply of Water 80,318.00
7 Shop Drawings 10,000.00
8 As-Built Documents 5,600.00
9 Temporary Site Office for Employers Consultants 65,250.00
10 Site Signboard 3,275.00
11 Access to Site 35,000.00
12 Site to be Tidy 12,727.00
13 Co-ordination 14,727.00
14 Site Records 3,275.00
15 Site Records 29,913.00
16 Safety Procedures 5,700.00
17 Security at Site 13,426.00
18 Contractors Site Operations 7,485.00
19 Site Radio Communication 11,725.00
20 Environmental Impact Assessment 5,000.00
21 Taking Delivery from NS 50,000.00
22 Contractors Temporary Accommodation 35,000.00
23 Superintendence 15,000.00
24 Transport of People 125,475.00
25 Contractors Equipment 365,000.00
26 Scaffolding 105,000.00

Total 85,250.00 2,503,646.00

page 15
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

It is important to define the difference between a “fixed” and a


“variable” item;

 Fixed items are to cover elements of a cost of work or


their value, which are not to be considered as
proportional to the quantities of the Permanent Works;
whereas

 Variable items are to cover for elements of a cost of work


which are considered proportional to the quantities of
Permanent Work performed.

The distinction is clear and as example, Shop Drawings and Site


Records is a typical Variable item which scope will increase on
introduction of the Variations brought by expenditure of the
provisional sums.

These variable preliminaries items amount to about 12% of the


value of Measured Works. As a result the current situation is:

 The original value of known Measured Works has varied


in quantity and therefore, value, considerably;

 The instructed varied works (which is the value provision


at tender and known as “Provisional Sums”) has or will
considerably increase the value of Measured Works; and

 As a result of a) and b) above, there is a significant


under-recovery of costs on measured works that should
naturally flow from items contained in the Preliminary Bill.

2.1.2.4. Conclusions

The table below shows the various value elements making up


the Contract Price. The known scope of work had been priced
and valued at SR20,677,661.15.

However, the value of Preliminaries is SR2,537,894.00 of which


SR2,503,646.00 is the value of Variable Costs. Therefore,
SR2,503,646.00 as a percentage of the known measured works
at time of tender was 12%. It is this percentage, 12% that must
be added to the value of Variations introduced under Clause 12
and 13.

This means the value adjustment on the original Provisional


Sum amount of SCR22,539,454.00 equates to
SCR2,729,071.00 or such other sum valued in accordance with
the Contract. This sum is to be paid in addition to the Contract
Price.

page 16
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

This signifies that all the Works measured to date are under-
valued. Accordingly, the Conditions of the Contract dictate the
following actions:

Notwithstanding delay and disruption costs caused by events


notified to the Project Manager, further additional costs must be
captured because:

 The Contractor has entitlement to a varied rate for all


unvaried Works,

 The Contractor has entitlement to new rates and prices


for all Works introduced as a Variation in accordance with
sub-clause 12.3, and

 the contractor has entitlement to the addition of 12% to all


his measured work to cover his Preliminary and general
items.

Consequently, the Contractor intends to add 12% to the value of


measured works arising from Instructed Variations. The
Contractor asks the Project Manager to certify payment
applications in accordance with the Contract Conditions and for
the reasons stated in the foregoing.

2.2. Relevant Contract Provisions


2.2.1.Sub-clause 1.9 – Delayed Drawings or Instructions
The Contractor shall give notice to the Project Manager
whenever the works are likely to be delayed or disrupted
if any necessary drawing or instruction is not issued to
the Contractor within a particular time, which shall be
reasonable. The notice shall include details of the
necessary drawing or instruction, details of why and by
when it should be issued, and details of the nature and
amount of the delay or disruption likely to be suffered if it
is late.

If the Contractor suffers delay and/or incurs Cost as a


result of a failure of the Project Manager to issue the
notified drawing or instruction within a time which is
reasonable and is specified in the notice with supporting
details, the Contractor shall give a further notice to the
Project Manager and shall be entitled subject to Sub-
Clause 20.1 [Contractor's Claims] to:

page 17
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

(a) an extension of time for any such delay, if completion


is or will be delayed, under Sub-Clause 8.4 [Extension of
Time for Completion], and

(a) payment of any such Cost plus profit, which shall be


included in the Contract Price.

After receiving this further notice, the Project Manager


shall proceed in accordance with Sub-Clause 3.5
[Determinations] to agree or determine these matters.

However, if and to the extent that the Project Manager's


failure was caused by any error or delay by the
Contractor, including an error in, or delay in the
submission of, any of the Contractor's Documents, the
Contractor shall not be entitled to such extension of time,
Cost or profit.

2.2.2.Sub-clause 3.3 – Instructions of the Project


Manager
The Project Manager may issue to the Contractor (at any
time) instructions and additional or modified Drawings
which may be necessary for the execution of the Works
and the remedying of any defects, all in accordance with
the Contract. The Contractor shall only take instructions
from the Project Manager, or from an assistant to whom
the appropriate authority has been delegated under this
Clause. If an instruction constitutes a Variation, Clause
13 [Variations and Adjustments] shall apply.

The Contractor shall comply with the instructions given


by the Project Manager or delegated assistant, on any
matter related to the Contract. Whenever practicable,
their instructions shall be given in writing. If the Project
Manager or a delegated assistant:

(a) gives an oral instruction,

(b) receives a written confirmation of the instruction,


from (or on behalf of) the Contractor, within two
working days after giving the instruction, and

(c) does not reply by issuing a written rejection and/or


instruction within two working days after receiving
the confirmation,

page 18
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

then the confirmation shall constitute the written


instruction of the Project Manager or delegated assistant
(as the case may be).

2.2.3.Sub-clause 4.7 – Setting Out


The Contractor shall set out the Works in relation to
original points, lines and levels of reference specified in
the Contract or notified by the Project Manager. The
Contractor shall be responsible for the correct positioning
of all parts of the Works, and shall rectify any error in the
positions, levels, dimensions or alignment of the Works.

The Employer shall be responsible for any errors in these


specified or notified items of reference, but the Contractor
shall use reasonable efforts to verify their accuracy
before they are used.

If the Contractor suffers delay and/or incurs Cost from


executing work which was necessitated by an error in
these items of reference, and an experienced contractor
could not reasonably have discovered such error and
avoided this delay and/or Cost, the Contractor shall give
notice to the Project Manager and shall be entitled
subject to Sub-Clause 20.1 [Contractor's Claims] to:

(a) an extension of time for any such delay, if


completion is or will be delayed,
under Sub-Clause 8.4 [Extension of Time for
Completion], and

(b) payment of any such Cost plus profit, which shall


be included in the Contract Price.

After receiving this notice, the Project Manager shall


proceed in accordance with Sub-Clause 3.5
[Determinations] to agree or determine (i) whether and (if
so) to what extent the error could not reasonably have
been discovered, and (ii) the matters described in sub-
paragraphs (a) and (b) above related to this extent.

2.2.4.Sub-clause 4.12 – Unforeseeable Physical


Conditions
In this sub-clause, “physical conditions” means natural
physical conditions and man-made and other physical
obstructions and pollutants, which the Contractor

page 19
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

encounters at the Site when executing the Works,


including sub-surface and hydrological conditions but
excluding climatic conditions.

If the Contractor encounters adverse physical conditions


which he considers to have Unforeseeable, the
Contractor shall give notice to the Project Manager as
soon as practicable.

This notice shall describe the physical conditions, so that


they can be inspected by the Project Manager, and shall
set out the reasons why the Contractor considers them to
be Unforeseeable. The Contractor shall continue
executing the Works, using such proper and reasonable
measures as are appropriate for the physical conditions,
and shall comply with any instructions which the Project
Manager may give. If an instruction constitutes a
Variation, Clause 13 [Variations and Adjustments] shall
apply.

If and to the extent that the Contractor encounters


physical conditions which are Unforeseeable, gives such
a notice, and suffers delay and/or incurs Cost due to
these conditions, the Contractor shall be entitled subject
to Sub-Clause 20.1 [Contractor's Claims] to:

(a) an extension of time for any such delay, if


completion is or will be delayed, under Sub-Clause
8.4 [Extension of Time for Completion], and

(b) payment of any such Cost, which shall be included


in the Contract Price.

After receiving such notice and inspecting and/or


investigating these physical conditions, the Project
Manager shall proceed in accordance with Sub-Clause
3.5 [Determinations] to agree or determine (i) whether
and (if so) to what extent these physical conditions were
Unforeseeable, and (ii) the matters described in sub-
paragraphs (a) and (b) above related to this extent.

2.2.5.Sub-clause 8.3 – Programme


The Contractor shall submit a detailed time programme
to the Project Manager within 28 days after receiving the
notice under Sub-Clause 8.1 [Commencement of Works].
The Contractor shall also submit a revised programme
whenever the previous programme is inconsistent with

page 20
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

actual progress or with the Contractor's obligations. Each


programme shall include:

(a) the order in which the Contractor intends to carry


out the Works, including the anticipated timing of
each stage of design (if any), Contractor's
Documents, procurement, manufacture of Plant,
delivery to Site, construction, erection and testing,

(b) each of these stages for work by each nominated


Subcontractor (as defined in Clause 5 [Nominated
Subcontractors]

(c) the sequence and timing of inspections and tests


specified in the Contract, and

(d) a supporting report which includes:

(i) a general description of the methods which the


Contractor intends to adopt, and of the major
stages, in the execution of the Works, and

(ii) details showing the Contractor's reasonable


estimate of the number of each class of
Contractor's Personnel and of each type of
Contractor's Equipment, required on the Site for
each major stage.

Unless the Project Manager, within 21 days after


receiving a programme, gives notice to the Contractor
stating the extent to which it does not comply with the
Contract, the Contractor shall proceed in accordance with
the programme, subject to his other obligations under the
Contract. The Employer's Personnel shall be entitled to
rely upon the programme when planning their activities.

The Contractor shall promptly give notice to the Project


Manager of specific probable future events or
circumstances which may adversely affect the work,
increase the Contract Price or delay the execution of the
Works. The Project Manager may require the Contractor
to submit an estimate of the anticipated effect of the
future event or circumstances, and/or a proposal under
Sub-Clause 13.3 [Variation Procedure].

If, at any time, the Project Manager gives notice to the


Contractor that a programme fails (to the extent stated) to
comply with the Contract or to be consistent with actual
progress and the Contractor's stated intentions, the
Contractor shall submit a revised programme to the
Project Manager in accordance with this Sub-Clause.

page 21
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

2.2.6.Sub-clause 8.4 – Extension of Time for Completion


The Contractor shall be entitled subject to Sub-clause
20.1 [Contractor’s Claims] to an extension of the Time for
Completion if and to the extent that completion for the
purposes of Sub-Clause 10.1 [Taking-Over of the Works
and Sections] is or will be delayed by any of the following
causes:

(a) a Variation (unless an adjustment to the Time for


Completion has been agreed under Sub-Clause
13.3 [Variation Procedure]) or other substantial
change in the quantity of an item of work included
in the Contract,

(b) a cause of delay giving an entitlement to extension


of time under a Sub-Clause of these Conditions,

(c) exceptionally adverse climatic conditions,

(d) Unforeseeable shortages in the availability of


personnel or Goods caused by epidemic or
governmental actions, or

(e) any delay, impediment or prevention caused by or


attributable to the Employer, the Employer's
Personnel, or the Employer's other contractors.

If the Contractor considers himself to be entitled to an


extension of the Time for Completion, the Contractor
shall give notice to the Project Manager in accordance
with Sub-Clause 20.1 [Contractor's Claims]. When
determining each extension of time under Sub-Clause
20.1, the Project Manager shall review previous
determinations and may increase, but shall not decrease,
the total extension of time.

2.2.7.Sub-clause 8.8 – Suspension of Works


The Engineer may at any time instruct the Contractor to
suspend progress of part or all of the Works. During such
suspension, the Contractor shall protect, store andsecure
such part or the Works against any deterioration, loss or
damage.

The Engineer may also notify the cause for the


suspension. If and to the extent that the cause is notified

page 22
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

and is the responsibility of the Contractor, the following


Sub-Clauses 8.9, 8.10 and 8.11 shall not apply.

2.2.8.Sub-clause 8.9 – Consequences of Suspension


If the Contractor suffers delay and/or incurs Cost from
complying with the Engineer’s instructions under Sub-
Clause 8.8 [Suspension of Work] and/or from resuming the
work, the Contractor shall give notice to the Engineer and
shall be entitled subject to Sub-Clause 20.1 [Contractor’s
Claims] to:

(a) an extension of time for any such delay, if completion


is or will be delayed, under Sub-Clause 8.4 [Extension of
Time for Completion], and

(b) payment of any such Cost, which shall be included in


the Contract Price.

After receiving this notice, the Engineer shall proceed in


accordance with Sub-Clause 3.5 [Determinations] to agree
or determine these matters.

The Contractor shall not be entitled to an extension of


time for, or to payment of the Cost incurred in, making
good the consequences of the Contractor’s faulty design,
workmanship or materials, or of the Contractor’s failure to
protect, store or secure in accordance with Sub-Clause
8.8 [Suspension of Work].

2.2.9.Sub-clause 12.1 – Works to be Measured


The Works shall be measured, and valued for payment,
in accordance with this Clause.

Whenever the Project Manager requires any part of the


Works to be measured, reasonable notice shall be given
to the Contractor's Representative, who shall:

(a) promptly either attend or send another qualified


representative to assist the Project Manager in
making the measurement, and

(b) supply any particulars requested by the Project


Manager.

page 23
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

If the Contractor fails to attend or send a representative,


the measurement made by (or on behalf of) the Project
Manager shall be accepted as accurate.

Except as otherwise stated in the Contract, wherever any


Permanent Works are to be measured from records,
these shall be prepared by the Project Manager. The
Contractor shall, as and when requested, attend to
examine and agree the records with the Project Manager,
and shall sign the same when agreed. If the Contractor
does not attend, the records shall be accepted as
accurate.

If the Contractor examines and disagrees the records,


and/or does not sign them as agreed, then the Contractor
shall give notice to the Project Manager of the respects in
which the records are asserted to be inaccurate. After
receiving this notice, the Project Manager shall review
the records and either confirm or vary them. If the
Contractor does not so give notice to the Project
Manager within 14 days after being requested to examine
the records, they shall be accepted as accurate.

2.2.10. Sub-clause 12.3 – Evaluation


Except as otherwise stated in the Contract, the Project
Manager shall proceed in accordance with Sub-Clause
3.5 [Determinations] to agree or determine the Contract
Price by evaluating each item of work, applying the
measurement agreed or determined in accordance with
the above Sub-Clauses 12.1 and 12.2 and the
appropriate rate or price for the item.

For each item of work, the appropriate rate or price for


the item shall be the rate or price specified for such item
in the Contract or, if there is no such item, specified for
similar work.

For each item of work included in the Bill of Quantities for


which no rate or price was specified shall be considered
as included in other rates and prices in the Bill of
Quantities and will not be paid for separately. However, a
new rate or price shall be appropriate for an item of work
if:

(a) (i) the measured quantity of the item is changed by


more than 25% from the quantity of this item in the Bill of
Quantities or other Schedule,

page 24
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

(ii) this change in quantity multiplied by such specified


rate for this item exceeds 0.25% of the Accepted
Contract Amount,

(iii) this change in quantity directly changes the Cost per


unit quantity of this item by more than 1 %, and

(iv) this item is not specified in the Contract as a "fixed


rate item";

Or

(b)(i) the work is instructed under Clause 13 [Variations


and Adjustments],

(ii) no rate or price is specified in the Contract for this


item, and

(iii) no specified rate or price is appropriate because the


item of work is not of similar character, or is not executed
under similar conditions, as any item in the Contract.

Each new rate or price shall be derived from any relevant


rates or prices in the Contract, with reasonable
adjustments to take account of the matters described in
sub-paragraph (a) and/or (b), as applicable. If no rates or
prices are relevant for the derivation of a new rate or
price, it shall be derived from the reasonable Cost of
executing the work, together with profit, taking account of
any other relevant matters.

Until such time as an appropriate rate or price is agreed


or determined, the Project Manager shall determine a
provisional rate or price for the purposes of Interim
Payment Certificates.

2.2.11. Sub-clause 13.1 – Right to Vary


Variations may be initiated by the Project Manager at any
time prior to the issuing the Taking-Over Certificate for
the Works, either by an instruction or by a request for the
Contractor to submit a proposal.

Contractor shall execute and be bound by each Variation,


unless the Contractor ptly gives notice to the Project
Manager stating (with supporting particulars) that the
Contractor cannot readily obtain the Goods required for
the Variation. Upon receiving notice, the Project Manager
shall cancel, confirm or vary the instruction.

page 25
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

Each Variation may include:

(a) changes to the quantities of any item of work


included in the Contract (however, such changes
do not necessarily constitute a Variation),

(b) changes to the quality and other characteristics of


any item of work,

(c) changes to the levels, positions and/or dimensions


of any part of the Works,

(d) omission of any work unless it is to be carried out


by others,

(e) any additional work, Plant, Materials or services


necessary for the Permanent Works, including any
associated Tests on Completion, boreholes and
other testing and exploratory work, or

(f) changes to the sequence or timing of the


execution of the Works.

The Contractor shall not make any alteration and/or


modification of the Permanent Works, unless and until
the Project Manager instructs or approves a Variation.

2.2.12. Sub-clause 13.3 – Variation Procedure


If the Project Manager requests a proposal, prior to
instructing a Variation, the Contractor shall respond in
writing as soon as practicable, either by giving reasons
why he cannot comply (if this is the case) or by
submitting:

(a) a description of the proposed work to be


performed and a programme for its execution,

(b) he Contractor's proposal for any necessary


modifications to the programme according to Sub-
Clause 8.3 [Programme] and to the Time for
Completion, and

(c) the Contractor's proposal for evaluation of the


Variation.

The Project Manager shall, as soon as practicable after


receiving such proposal (under Sub-Clause 13.2 [Value
Engineering] or otherwise), respond with approval,

page 26
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

disapproval or comments. The Contractor shall not delay


any work whilst awaiting a response.

Each instruction to execute a Variation, with any


requirements for the recording of Costs, shall be issued
by the Project Manager to the Contractor, who shall
acknowledge receipt.

Each Variation shall be evaluated in accordance with


Clause 12 [Measurement and Evaluation], unless the
Project Manager instructs or approves otherwise in
accordance with this Clause.

2.2.13. Sub-clause 20.1 – Contractor’s Claims


If the Contractor considers himself to be entitled to any
extension of time for Completion and/or any additional
payment, under any Clause of these Conditions or
otherwise in connection with the Contract, the Contractor
shall give notice to the Project Manager, describing the
event or circumstance giving rise to the claim. The notice
shall be given as soon as practicable, and not later than
28 days after the Contractor became aware, or should
have become aware, of the event or circumstance.

If the Contractor fails to give notice of a claim within such


period of 28 days, the Time for Completion shall not be
extended, the Contractor shall not be entitled to
additional payment, and the Employer shall be
discharged from all liability in connection with the claim.
Otherwise, the following provisions of this Sub-Clause
shall apply.

The Contractor shall also submit any other notices which


are required by the Contract, and supporting particulars
for the claim, all as relevant to such event or
circumstance.

The Contractor shall keep such contemporary records as


may be necessary to substantiate any claim, either on
the Site or at another location acceptable to the Project
Manager. Without admitting the Employer's liability, the
Project Manager may, after receiving any notice under
this Sub-Clause, monitor the record-keeping and/or
instruct the Contractor to keep further contemporary
records. The Contractor shall permit the Project Manager
to inspect all these records, and shall (if instructed)
submit copies to the Project Manager.

page 27
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

Within 42 days after the Contractor became aware (or


should have become aware) of the event or circumstance
giving rise to the claim, or within such other period as
may be proposed by the Contractor and approved by the
Project Manager, the Contractor shall send to the Project
Manager a fully detailed claim which includes full
supporting particulars of the basis of the claim and of the
extension of time and/or additional payment claimed. If
the event or circumstance giving rise to the claim has a
continuing effect:

(a) this fully detailed claim shall be considered as


interim;

(b) the Contractor shall send further interim claims at


monthly intervals, giving the accumulated delay
and/or amount claimed, and such further
particulars as the Project Manager may
reasonably require; and

(c) the Contractor shall send a final claim within 28


days after the end of the effects resulting from the
event or circumstance, or within such other period
as may be proposed by the Contractor and
approved by the Project Manager.

Within 42 days after receiving a claim or any further


particulars supporting a previous claim, or within such
other period as may be proposed by the Project Manager
and approved by the Contractor, the Project Manager
shall respond with approval, or with disapproval and
detailed comments. He may also request any necessary
further particulars, but shall nevertheless give his
response on the principles of the claim within such time.

Each Payment Certificate shall include such amounts for


any claim as have been reasonably substantiated as due
under the relevant provision of the Contract. Unless and
until the particulars supplied are sufficient to substantiate
the whole of the claim, the Contractor shall only be
entitled to payment for such part of the claim as he has
been able to substantiate.

The Project Manager shall proceed in accordance with


Sub-Clause 3.5 [Determinations] to agree or determine (i)
the extension (if any) of the Time for Completion (before
or after its expiry) in accordance with Sub-Clause 8.4
[Extension of Time for Completion], and/or (ii) the
additional payment (if any) to which the Contractor is
entitled under the Contract.

page 28
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

The requirements of this Sub-Clause are in addition to


those of any other Sub-Clause which may apply to a
claim. If the Contractor fails to comply with this or another
Sub-Clause in relation to any claim, any extension of time
and/or additional payment shall take account of the
extent (if any) to which the failure has prevented or
prejudiced proper investigation of the claim, unless the
claim is excluded under the second paragraph of this
Sub-Clause.

2.3. Original Planning and Cash-flow


2.3.1.The Clause 8 Programme
The programme of works that appears below is summary task
format was issued and approved for construction in XX 2007.

This programme of works considers the original scope of works


depicted in the bills of quantities, including time provision for
provisional sums. The provisional sum value included in the
Contract allowed for inclusion by Variation all works not defined
at time of tender. The Contractor’s original cash-flow was
produced using this data.

page 29
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2007 2008
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct
1 SHANGRI-LA , Long Island Resort Seychelles 0%
2 General Conditions and Preliminaries 0%
17 Site establishment 0%
41 Material/equipment procurement 0%
182 Lot 1 0%
183 A3 Villas ( 6 nos) 0%
453 C311 Executive Villas ( 1 nos) 0%
497 GM Villa ( subject to receipt of GFW drawings) 0%
537 Employees Facilities ( subject to receipt of GFW drawings) 0%
581 Laundry F& B service office ( subject to receipt of GFW drawings) 0%
625 Health Club/ Medical Centre( subject to receipt of GFW drawings) 0%
666 Administration Block ( subject to receipt of GFW drawings) 0%
707 1 bedroom Villa ( Excom, 6 units)( subject to receipt of GFW drawings) 0%
750 Main Lobby ( subject to receipt of GFW drawings) 0%
791 Tennis Courts ( subject to receipt of GFW drawings) 0%
807 External works ( subject to receipt of GFW drawings) 0%
816 Drainage works ( subject to receipt of EME details) 0%
819 Fuel Farm ( subject to receipt of EME details) 0%
823 Sea water Storage Tank & Water Tanks( subject to receipt of EME details) 0%
827 Desalination plant( subject to receipt of EME details) 0%
831 MLV Panel( subject to receipt of EME details) 0%
835 Step Up Transformer( subject to receipt of EME details) 0%
839 Incinerator/ Garbage room( subject to receipt of EME details) 0%
843 Sewer treatement plant( subject to receipt of EME details) 0%
847 Lot 2 0%
848 A3 Villas (17 nos) 0%
1614 B223 Villas ( 7 nos) 0%
1965 B4 Villa (2 nos.) 0%
2056 Retail 1( subject to receipt of GFW drawings) 0%
2094 Retail 2( subject to receipt of GFW drawings) 0%
2132 Retail 3( subject to receipt of GFW drawings) 0%
2170 Seafood resort( subject to receipt of GFW drawings) 0%
2211 Greeting Pavillion( subject to receipt of GFW drawings) 0%
2250 External works ( subject to receipt of GFW drawings) 0%
2259 Drainage works ( subject to receipt of EME details) 0%
2262 Lot 3 0%
2263 A3 Villas ( 9 nos) 0%
2664 B223 Villas ( 3 nos) 0%
2808 B4 Standard Villas ( 2 nos) 0%
2899 BC311 Executive Villa 0%
3115 P3 Presidential suites ( 3 nos) 0%
3245 Hilltop sunset deck( subject to receipt of GFW drawings) 0%
3280 External works ( subject to receipt of GFW drawings) 0%
3289 Drainage works ( subject to receipt of EME details) 0%
3292 Lot 4 0%
3293 Couple treatment room( subject to receipt of GFW drawings) 0%
3334 Single treatment room( subject to receipt of GFW drawings) 0%
3375 Dive Centre( subject to receipt of GFW drawings) 0%
3413 Kid's club( subject to receipt of GFW drawings) 0%
3452 Recreation House( subject to receipt of GFW drawings) 0%
3491 Watersports rental( subject to receipt of GFW drawings) 0%
3529 3 Meals restaurant( subject to receipt of GFW drawings) 0%
3570 Beach Pool Bar( subject to receipt of GFW drawings) 0%
3611 Signature Pool area( subject to receipt of GFW drawings) 0%
3650 Wedding Chapel( subject to receipt of GFW drawings) 0%
3685 BOH/Admin Building( subject to receipt of GFW drawings) 0%
3726 Chi Sanctum( subject to receipt of GFW drawings) 0%
3767 Yoga Pavillion( subject to receipt of GFW drawings) 0%
3805 External works ( subject to receipt of GFW drawings) 0%
3814 Drainage works ( subject to receipt of EME details) 0%
3817 M&E Installations- External 0%
3828 Sundries 0%
3829 Site cleaning & demobilisation 0%
3830 Project Commissioning 0%

2.3.2.Planned versus Actual Turnover


The chart below provides a comparison between planned cash-
flow, based on the programme of works, and actual income.

It can be seen the period through to XX, the first X-months of the
construction programme, both planned and actual cash-flow
remain reasonably constant. This is to be expected.

However, thereafter the gap widens because:

 Excavations took longer because of hard rock;

 Sub-structure work took longer due to greater scope of


work;

 Work slowed down waiting information and detailed


design, and

 Works were suspended

page 30
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

PlanCumm ActualCumm

30,000,000.00

25,000,000.00

20,000,000.00

15,000,000.00

10,000,000.00

5,000,000.00

0.00
Feb-07

Mar-07

Apr-07

May-07

Jun-07

Jul-07

Aug-07

Sep-07

Oct-07

Nov-07

Dec-07

Jan-08

Feb-08

Mar-08

Apr-08

May-08
-5,000,000.00

The following table provides the value of payment applications


certified to end of May 2008.

Month Planned PlanCumm Actual ActualCumm


Feb-07 3,100,000.00 3,100,000.00 0.00 0.00
Mar-07 601,658.62 3,701,658.62 0.00 0.00
Apr-07 1,352,295.74 5,053,954.37 0.00 0.00
May-07 1,852,720.48 6,906,674.85 3,100,000.00 3,100,000.00
Jun-07 2,236,090.71 9,142,765.56 0.00 3,100,000.00
Jul-07 2,684,335.78 11,827,101.34 682,032.85 3,782,032.85
Aug-07 2,189,910.64 14,017,011.97 351,989.15 4,134,022.00
Sep-07 2,236,090.71 16,253,102.68 145,803.63 4,279,825.63
Oct-07 2,258,038.74 18,511,141.42 357,556.62 4,637,382.25
Nov-07 2,258,038.74 20,769,180.15 478,924.03 5,116,306.28
Dec-07 1,754,288.50 22,523,468.65 0.00 5,116,306.28
Jan-08 1,289,372.84 23,812,841.49 0.00 5,116,306.28
Feb-08 1,040,280.70 24,853,122.19 274,355.16 5,390,661.44
Mar-08 500,424.74 25,353,546.93 1,086,667.96 6,477,329.40
Apr-08 2,575,212.46 27,928,759.39 0.00 6,477,329.40
May-08 0.00 27,928,759.39 0.00 6,477,329.40

It can be seen in the cumulative column how the gap widens as


of almost the outset of the contract and has increased
progressively in the period to date, May 2008. It is also of worthy
note the “flatness” of the line showing cumulative income which
results from:

 A reduced income caused by the delays notified;

 The fixed nature of the Advance repayment;

page 31
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

 The value retained in retention.

The Contractor notified the financial imbalance being caused by


the Advance repayment in his letters dated 19 November 2007:

Please refer to the Cash Flow Forecast dated 10


February 2007 included in the Contract Document
Volume 1. As you are aware, this cash flow was
preliminary and assumed payment of the Advance would
occur in February 2007.

However, as payment of the Advance is the trigger to


commencement of repayment, it is now necessary to
amend this preliminary cash flow to reflect the actual date
of receipt, which we record, was in May 2007.

Accordingly, please find attached the amended Cash


Flow forecast adjusted to reflect the month the Advance
was received and consequent 10-month repayment
drawn-down against Interim Payments.

A further notice was issued on 21 November 2007:

Please refer to the amended Cash Flow Forecast


submitted under cover of letter dated 19 November 2007.
As you are aware, this cash flow was preliminary and
assumed repayment of the Advance against projected
income derived from the original programme of works.

However, the progress of works has been delayed and


disrupted for reasons provided in separate notifications
and as a result, income is significantly lower in the period
to date.

Accordingly, please find attached an amended Cash


Flow forecast adjusted to reflect a 15-month repayment
drawn-down against Interim Payments consequent to the
extended contract period shown on the revised
programme of works.

2.4. First Revised Programme of Works


The Programme of Works above was issued under cover of
letter dated 19 November 2007 in accordance with Clause 8 of
the Contract Conditions.

In accordance with your request please find attached our


revised programme reflecting actual progress achieved at
6 November 2007. This programme of works takes

page 32
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

consideration of events and changed circumstances


since commencement that caused original planned timing
and sequence to vary.

Unless notice is received stating the extent to which it


does not comply with the Contract, we shall proceed in
accordance with this programme and will rely upon this
programme when planning our activities.

Therefore, the Contractor’s timing, sequence are clearly


explained in support of this programme. This programme of
works indicated a revised completion date.

2.5. Second Revised Programme of Works


At the request of the Project Manager a second revised
programme of works was issued on 14 March 2008.

In accordance with your recent request in the weekly


progress meetings, please find attached revised
programme of works for your consent.

The revised programme takes into consideration the


various events and changed circumstances since
commencement up to 29 February 2008.

These events and changed circumstances, as separately


notified to you and further illustrated in our situation
report dated 29 February 2009, have caused the original
planned timing and sequence of works to vary. They
include the following;

 Unforeseen hard rock excavation including


spoiling;

 Suspension of works, except for the mock up


villas, for two months and associated acceleration
measures;

 Instructed design variations, e.g. exchange of


galvanised steel with stainless steel components
for installation in the roof resulting into delays in
procurement;

 Late Instructions, e.g. several changes to the


location, position and orientation of buildings by
revision in the setting out details have delayed and
disrupted the works;

page 33
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

 Late Design Information resulting into delays in


procurement thus preventing timely arrival of
materials at site;

 Increased scope of works occasioned by


unforeseen site conditions and instructed
additional works;

 Inclement weather condition; unexpected high


amounts of rainfall currently being experienced at
site is slowing down progress of works.

The overall effect of all the above has been to delay the
completion date for the works up to 24 March 2009 as
indicated in the attached revised programme.

We therefore request extension of time to completion of


the works.

As stated in the last paragraph of this notice, an extension of


time had been requested.

2.6. Actual Progress


Since the outset of the Contract the Contractor suffered delay
due to four major reasons;

 Late and inaccurate survey data;

 Unforeseen ground conditions;

 Project Manager’s instruction to suspend Works (partial);

 Late receipt of final design information, and

 Additional and varied works.

As a result of Works did not commence as planned.

page 34
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

3. Valuation of Variations

3.1. Explanation of Heads of Claim


In his various notifications the Contractor has made reference to
at least three types of variations. One type is the changes to the
scope of work, a second is the late receipt of design and the
third is the changes to the sequence and timing of work. All of
these have been sufficiently described and defined in these
notifications.

During the currency of work, the first two types of change


occurred simultaneously, as well as following consecutively. For
example, design drawings which have been issued late, to allow
the commencement of certain works, showed changes to the
Contract drawings. Further these changes occurred when the
Contractor encountered unforeseen ground conditions at most
of the respective sites. That is simultaneous occurrence.

There were many instances of consecutive occurrence. For


example, where drawings were revised a number of times over
a period of several months and even over more than a year,
those were consecutive.

3.2. Specific Heads of Claim


Where variations are the cause of delay, the costs associated
with the delay have to be taken into account in the valuation of
the variations. There are two types of cost to be taken into
account. One is the cost of prolongation of work on site. This is
the cost of (1) maintaining the site establishment and (2) off-site
overheads.

The second type of cost is that of the uneconomic way of


working, which results from incorporating the varied work into
the Works. This includes the direct cost of the disrupted nature
of work on site, and the loss of anticipated income at the times
envisaged in the original cash-flow predictions.

page 35
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

3.3. Methods of Valuation of the Variations


3.3.1.Use of Costs as Basis
In submitting these particulars of prolongation costs and
particulars of slowdown Costs, the Contractor is providing what
he is obliged to do by the Contract, which is to make use of
contemporary records of costs. The costs were to be used as
basis for valuing the variations.

3.3.2.Addition for Profit


It is evident that there are two generic types of claim. One is for
‘costs’ and the other is for value. Therefore, it is necessary to
look at profit as a part of both value and cost. The Contractor’s
entitlement to have profit added to his cost, to the extent that the
costs claimed are included in variation valuations, profit must be
added to those costs for inclusion in such valuations. It is noted
that Clause 13 clearly indicates that all variations referred to
shall be valued in accordance with Clause 12.

In compliance with this requirement of the Contract, the


proposition that where the time related costs are indicative of
loss of efficiency due to the variation in the timing and sequence
of events and are used to formulate a new rate for a particular
bill item, then they should include all expenditure, whether on or
off the Site. Clause 12 states that the

a new rate or price shall be derived from the reasonable


Cost of executing the work, together with reasonable
profit

This clarifies that a valuation under Clause 12 must include


profit on time related costs. Profit addition on this contract is
15%.

3.3.3.Profit as Part of the Value of Variations


3.3.3.1. Three Types of Variations

The three types of variation included in this submission:

1. Changes in design of parts of the Works,

2. Additional and Varied works, and

3. Changes in the timing and sequence

page 36
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

As noted above, all such variations fall to be valued under


Clause 13, with the possibility that Clause 12 can be invoked in
respect of the effects of variations on unvaried work.

The Contractor confirms that costs claimed are the indirect costs
of the delays to the Works, whilst the direct costs include the
direct costs of performing the works. In other words, the
Contractor’s claim is for the time-related costs to be rolled into
the Clause 12 variation valuations.

It is helpful now to give some consideration to each type of


variation in turn, so that the Employer can see how profit is
included in the valuation of each.

3.3.3.2. Changes in Design of the Works

The first of those two speaks for itself. The claim is for the time-
related costs of the variations to be included in the variation
valuations. It is unnecessary to argue the point that any such
valuation must include profit, under the valuation rules. All
valuation rules, in Clauses 12, are founded in rates and prices. It
is implicit that they already include profit. It follows that any new
rate or price will also include profit.

Of the complaints notified, the first variation event relates to


delayed setting out, the second to unforeseen ground
conditions, the third to delayed and incomplete design drawings
and the fourth to additional and varied Works. Those variations
comprised:

1. The changes in the position of buildings, foundation design


(partly arising from excavation in rock), unforeseen ground
conditions, suspension of Works, late design information,
and

2. The change to the specified sequence and timing of the


Works

Again, it is helpful to consider each type separately.

3.3.3.2.1. Technical Variations

As example, the changes in design of the Works referred to


immediately above; there can be no doubt that a valuation of
this type of variation to the foundation works will have to include
profit in any event. Similarly, changes in ground conditions must
equally include profit.

page 37
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

3.3.3.2.2. Changes to Specified Sequence and


Timing

Clause 13.1 (f), Conditions of Contract Part I, confirms any


change to the specified sequence or timing of construction of
any part of the Works instructed by the Project Manager,
constitutes a Variation.

In order to establish a Variation to sequence and time, it is


therefore necessary to establish the specified sequence and
timing of the Works. Clause 8.3, Conditions of Contract Part I,
requires the Contractor to submit to the Project Manager for his
approval, a program which illustrates the sequence and timing
the Contractor intends on performing his Works.

Project Manager’s approval of the Contractor’s Clause 8.3


Program was received in XX 2007. Consequently, the Clause
8.3 Program approved by the Project Manager represents the
specified sequence and timing of the Works and any change to
this sequence and timing instructed by the Project Manager in
writing represents a Variation in accordance with Clause 12.3
(b) (iii).

The Employer will agree that the late receipt of design


information is a specified sequence or timing of work as
envisaged by Clause 13.1(f) of the General Conditions of
Contract. Similarly, the suspension of the works must be treated
in the same manner.

Consequently, the Employer will agree that the Project Manager


has changed those sequences or timings, and that the
Contractor is entitled to have the change treated as variation
within the meaning of the said Clause.

The Contractor’s claim to have the changes of sequence and


timing brought within Clause 13.1(f) means that those changes
also fall to be valued under Clause 12.3. As with the previous
types of variation valuation, it must include profit.

3.3.3.3. Summary

When considering profit as part of the valuation of variations, the


matters affected are:

1. Changes in the Design of the Works

page 38
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

2. Variations to foundations, which splits into two further sub-


divisions, namely (1) technical variations and (2) changes to
the sequence and timing of work.

It is evident from the foregoing that all of the valuations of the


variations referred to must include profit. Therefore, to the extent
that the costs claimed are included in variation valuations, profit
must be added to those costs.

Clearly, as the foundation work was one of the earliest site


operations, the amount of costs, to which profit must be added,
is considerable.

3.3.4.The Effects on Unvaried Work


As can be seen from the claims referred in this submission,
numerous variations have either been issued or arisen as a
consequence of unforeseen ground conditions. In addition,
design drawings have generally been received much later than
required as depicted on the programme of works. The extent of
the variations is such that the original scope of the work included
in the Contract has been changed considerably.

So profound have the effects of the changes to both the scope


of work and to the sequence and timing of work been, that the
relatively few areas of work, which were not varied, have been
affected by those variations. The effects fall into the basic
categories of (1) prolongation and (2) disruption of the unvaried
work.

Clause 12.3 provides the mechanism for including the effects of


prolongation and disruption of the unvaried work:

No rate or price is appropriate because the item of work


is not of similar character, or is not executed under
similar conditions, as any item in the Contract.

This term of the Contract provides an indemnity to the


Contractor for all costs reasonably incurred in carrying out
variations.

3.3.5.For Uneconomic Working


From the foregoing discussion and analysis, it is evident that a
claim for uneconomic working comes within the ambit of Sub-
clause 12.3, when the costs are caused directly by performing
variations under Clause 13.1, when costs arise from carrying out

page 39
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

the work described in the Contract. In practice, it is not possible


to separate uneconomic working from the effects on unvaried
working, due to the close proximity of site operations, and the
continual interchange of resources between varied and unvaried
work.

The types of costs of uneconomic working are:

1. The loss of anticipated income, by way of financing.

2. Wasted monthly costs.

3. Financing wasted monthly costs.

Each of those heads of claim is dealt with in turn.

3.3.5.1. Loss of Anticipated Income

This is the cost to the Contractor of financing the shortfall


between the income he reasonably expected to receive, and
what he actually received, in Interim Payment Certificates.

As to the suspension or slowdown costs, the Contractor claims


in respect of lost income for the period from commencement in
March 2007 to May 2008. That is because the Particulars
included in this submission also relate to the delays in that
period.

3.3.5.2. Wasted Monthly Costs

This is a measure of the waste of resources, caused by the


disruption, dislocation and re-sequencing of work.

In this document the Contractor describes the cause which


resulted in suspension or slowdown of the works. At this section
he describes the effect of the cause that is what he means by
wasted monthly costs:

One of the types of damage incurred by the Contractor would be


the idle time, and/or reduced output, of resources. It is not
possible to sever the damage incurred by reason of the delayed
setting out of sites, unforeseen ground conditions, changes in
scope of works, from that incurred by reason of the delayed
design drawings.

The schedules showing the monthly labour and plant levels are
evidence that the Contractor not only mobilised, but also
maintained, levels of each, which should have ensured outputs

page 40
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

at the level of anticipated monthly income referred to above. The


schedules showing the amounts certified for each month are
evidence that, notwithstanding the level of resources on site, the
Contractor’s turnover was far less than he reasonably
anticipated.

In order to arrive at a measure of the cost of idle time, and the


reduced output, the Contractor has calculated the percentage,
which the loss of income represents for each month, of the
anticipated income. The Contractor has then applied the same
percentage to the monthly cost of labour, equipment, both site
and head office overheads, to arrive at the cost on which he has
had no return.

The Contractor believes this is the most sensible way of


approaching this head of claim. It uses evidence, as opposed to
estimates, or supposition.

3.3.5.3. Financing Wasted Monthly Costs

This should be self-explanatory. However, a few words of


explanation will help. The Contractor’s entitlement relies on the
following:

The Employer should agree that the Contractor is entitled to


either the financing charges for the wasted monthly costs if
either these are agreed, in the form of interest on late payment
in accordance with Clause 14.8 of the conditions of contract or
finance charges incurred, whichever is the greater.

The application of finance charges as compensation for the


Contractor being kept out of his money replaces interest on late
payments. Accordingly, the Contractor claims to be entitled to
financing charges on the wasted costs included in the valuation
of the Variations.

3.3.6.Profit as Part of ‘Costs’


To the extent that profit on costs could become an issue, the
Contractor’s contentions are as follows.

3.3.6.1. Authorities on the Basis of ‘Costs’

In order to appreciate what should be included in a


determination of costs, it is necessary to grasp the concept of

page 41
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

the expression as used in the contract claims machinery. There


are a number of helpful authorities, which explain this.

3.3.6.1.1. Powell-Smith’s ‘Some Building Contract


Problems’

The following passage from ‘Some Building Contract Problems’


(page 141), by the late Dr Vincent Powell-Smith, who was a
well-known international lecturer, commentator and author,
illustrates the purpose of what some construction contracts call
‘direct loss and/or expense’. The parallel in the Contract is
‘costs’:

The purpose of the contract claims machinery is to put


the contractor back into the position he would have been
but for the delay or disruption, and various cases
establish that the term ‘direct loss and/or expense’
means in effect that what is recoverable is substantially
the same as the damages recoverable at common law
under the first rule in the old case of Hadley v. Baxendale
(1854)

This fits directly with the criterion used in the Robinson v.


Harman case (see below).

3.3.6.1.2. Hudson and Minter v. WHTSO

In the extract from Hudson’s Building and Project Managering


Contracts, Eleventh Edition, Volume 1, on page 1020, there is a
summary of the ruling in the case of F G Minter v. Welsh Health
Technical Services Organisation (1980) 13BLR1:

By Clauses 11(6) and 24(1) respectively of the 1963


RIBA/JCT forms of contract, the contractor was entitled to
be paid ‘direct loss and expense’ not reimbursable under
the preceding variation valuation rules, in the one case,
or as a result of disturbance of progress due to late
receipt of drawings and information from the architect on
the other. The contractor claimed financing charges on
the additional expenditure in each case as sums due and
to be certified by the architect under the two clauses.

Held, by the Court of Appeal, on preceding judicial


authority the words ‘direct loss and expense’ meant such
damages as would be recoverable as naturally flowing
from a breach of contract under the first branch of the
rule in Hadley v. Baxendale.

page 42
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

Again, although the extract refers to the expression ‘loss and/or


expense’, it is the equivalent of the ‘costs’ suffered by the
Contractor under the Contract.

The discussion of the judgment following the passage quoted


from it in Hudson is at the heart of this issue in this Claim. In
paragraph 8-096, the learned author says:

The wider importance of the Minter and Rees and Kirby


cases in the Construction field cannot be ignored. The
reasoning of the Court of Appeal in the Minter case was
that previous authority showed that the contractual “direct
loss and expense” expression meant the same as the
measure of damage “arising naturally in the usual course
of things” under the first branch of the Hadley v.
Baxendale rule. The contract therefore expressly applied
that test to both the Clause 11(6) basis of claim
(variations and not, therefore, a breach of contract) and
to the Clause 24(1)(a) basis (late information and,
therefore, a breach of contract). [Author’s emphasis.]

The author’s discussion draws attention to the importance of the


comparison of direct loss and expense, or, as in the Contract,
‘cost’, with damages envisaged by Hadley v. Baxendale. The
costs referred to have been incurred as a result of denial of
possession of parts of the site, and of late and varied
information.

3.3.6.1.3. Hudson on the Scope of ‘Costs’

From the two foregoing authorities, it is evident that the more


widely used expression ‘loss and expense’ is a direct parallel to
the word ‘costs’ as used in the instant Contract. Underpinning
this is the breadth of coverage given to the expression ‘loss and
expense’. This is illustrated by the following extract from page
1096 of Hudson, paragraphs 8.213 to 8.216. In paragraph
8.213, the author draws attention to the coverage of ‘loss and
expense’:

a. ‘Direct’ or ‘consequential’ damage provisions

… In this context, ‘consequential’ damage will sometimes


be contrasted with ‘direct’ damage as the subject of
exclusion, or sometimes used on its own to indicate an
intended class of compensation. Thus, since 1963 the
English standard forms, and in particular the RIBA/JCT
forms, have employed the expression ‘direct loss and
expense’ in the context of positive provisions for

page 43
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

additional payment expressly permitted by these


contracts. …

He then draws the parallel with Hadley v. Baxendale for the type
of damage to be included in loss and expense, and what he
calls ‘wording of this kind’, in paragraph 8.215:

These strict interpretations in the case of exclusions


clauses have been paralleled by a correspondingly
generous interpretation of ‘direct loss and expense’.
Wording when used positively in compensation
provisions. It has already been seen that interest in the
form of financing charges has been held to be
recoverable by contractors under this wording under
Clauses 11(6) and 24 of the 1963 RIBA/JCT forms.
Wording of this kind will include any damage recoverable
under the first branch of the Hadley v. Baxendale rule,
which it has been seen will include a wide range of heads
of damage which might otherwise in a loose sense be
described as ‘consequential’ or ‘indirect’.

It should be noted that, on page 1098 of the extract, in the


reference to the second case, Wraight v. PH&T (Holdings) Ltd
(1968), it says that it was held that a contractor was entitled to
his loss of profit. This case is referred to specifically below.

This extract is included as Appendix 4.

3.3.6.1.4. The First Part of the Rule in Hadley v.


Baxendale

The case of Hadley v. Baxendale is at the very heart of


damages for breach of contract, and need not be quoted at
length. Having established that a contractor’s claim for loss and
expense, or cost, or indeed for anything covered by ‘wording of
this kind’, it is helpful to refer to the judgment in Hadley v.
Baxendale, to see exactly what the first part of the rule allows.

The Contractor reproduces here an extract from ‘Contract Cases


and Materials’ by Hugh Beale, William Bishop and the very well-
known and respected Prof Michael Furmston, who is also the
author of the classic work on contract law, ‘Furmston, Cheshire
and Fifoot’. The extract is in fact part of the judgment in the
case, at page 395:

We think that there ought to be a new trial in this case;


but, in so doing, we deem it to be expedient and
necessary to state explicitly the rule which the Judge, at

page 44
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

the next trial, ought, in our opinion, to direct the jury to be


governed by when they estimate the damages. …

Now we think the proper rule in such a case as the


present is this: - Where two parties have made a
contract, which one of them has broken, the damages
which the other party ought to receive in respect of such
breach of contract should be such as may fairly and
reasonably be considered either arising naturally, i.e.
according to the usual course of things, from such breach
of contract itself, or such as may reasonably be
supposed to have been in the contemplation of both
parties, at the time they made the contract, as the
probable result of the breach of it.

Thus, the first part of the rule is that:

… the damages which the other party ought to receive …


should be such as may fairly and reasonably be
considered … arising naturally, i.e. according to the usual
course of things, from such breach of contract itself …

In the case of the matters claimed, the Contractor is therefore


entitled to reimbursement of costs, which include costs, which
arose naturally from the breach.

3.3.6.1.5. The Basic Measure of Damages

Having established that the Contractor is entitled to have his


costs determined on the basis of what flowed naturally from the
breach, it is necessary to alight upon the correct measure of
damage. There is precise authority for this in the case of
Robinson v. Harman (1848) 1Exch850, 855. The relevant
passage is as follows:

The rule of the common law is, that where a party


sustains loss by reason of a breach of contract, he is, so
far as money can do it, to be placed in the same
situation, with respect to damages, as if the contract had
been performed.

The quoted passage is taken from page 11 of Beale, Bishop and


Furmston’s book.

This the truly prescriptive rule for what should be in the


determination of costs. It has been shown by logical steps that
‘costs’ in their generic sense equate to common law damages.
From that, it is the common law rule that damages must put the

page 45
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

offended party back in the same position he would have been in,
but for the events complained of.

It follows from this that a contractor, who suffers as a result of an


act or omission of the employer or his agents, is entitled to
recover his profit.

3.3.6.2. Authorities on the Recovery of Profit

Now that the basic premise for using the criterion applicable to
common law damages for breach of contract has been
presented, the Contractor will show that the recovery of profit
comes within that criterion.

3.3.6.2.1. General Principle as to Claims

The general rule that claims for loss and expense or costs are to
be treated as claims for damages at common law is expounded
by Dr Powell-Smith on page 143 of ‘Some building Contract
Problems’:

Claims under clause 26 can be equated with claims for


damages at common law, and are governed by the same
principles. On that basis, the consequences of the late
instruction must have been within the reasonable
contemplation of the contracting parties at the time the
contract was made. The additional cost arises as a direct
and natural result of the architect’s default and is thus
claimable under the contract terms: see Hadley v.
Baxendale (1854)

3.3.6.2.2. Wraight v. PH&T (Holdings) Ltd

In the case of Wraight v. PH&T (Holdings) Ltd (1968), a


contractor pursued a claim for loss of profit, as a result of his
own determination of his employment under a building contract.

The contractor in the case put his argument as summarised in


the judgment on page 284, near the bottom:

It is said here on behalf of the [contractors] that quite


plainly the loss of profit to the [contractors] was, in any
ordinary sense of the word, a direct consequence of the
determination of the contract. If the contract had not been
determined, they would have gone on and done the work,
continued their legal obligations thereunder and would

page 46
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

have had their legal right to obtain their full contractual


remuneration at the end of it, and therefore they have, by
this determination, lost the right to receive that sum of
money which they would have received if the contract
had not been determined: what can be more direct than
that?

Obviously, the event complained of in the case is determination


of the contractor’s employment. However, that is not of
importance. It is a type of event, which entitles the offended
contractor to reclaim his losses, just as the denial of possession
and late information in the Contract do.

The important thing is that the contractor in the case was looking
to recover the sum of money he would have recovered, but for
the event complained of. It is natural that such sum of money
included profit.

The judge concluded, on page 285:

In my judgment, there are no grounds for giving to the


words ‘direct loss and/or damage caused to the
contractor by the determination’ any other meaning than
that which they have, for example, in a case of breach of
contract or other question of the relationship of a fault to
damage in a legal context. Therefore it follows … that the
[contractors] are, as a matter of law entitled to recover
that which they would have obtained if this contract had
been fulfilled in terms of the picture visualised in advance
but which they have not obtained.

It was held (page 284) that:

The words direct loss and/or damage in clause 26 must


be given the same meaning as they would have in the
case of a breach of contract. The loss of profit was the
direct and natural consequence of the determination of
the contract, and the contractors were entitled to
succeed.

3.3.6.2.3. Powell-Smith and Sims on Building


Contract Claims

The authors of ‘Building Contract Claims’, Vincent Powell-Smith


and John Sims, state unequivocally on page 110 of their book
that:

Loss of profit, which the contractor would otherwise have


earned but for the delay or disruption, is an allowable

page 47
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

head of claim. It is recoverable under the rule in Hadley


v. Baxendale (1854).

Pages 110 to 113 of the book are included in Appendix 9.

It is worth noting that the authors refer to the Wraight case on


page 111, and that they make a distinction between the profit
normally to be expected, and exceptionally high profit. The
Contractor is only claiming here the level of profit allowed for in
his tender.

The extract also mentions the possibility of claiming for profit lost
on other contracts. The Contractor is not claiming for that. He is
only claiming for his profit on the Contract, which is much more
direct than that lost on other projects.

3.3.6.3. Summary

There are plenty of authorities to show that:

1. A claim for payment of ‘costs’ is to be treated as a claim for


common law damages.

2. Such damages should put the complaining party back into


the position he would have been in, but for the event
complained of.

3. Profit is an allowable head of claim under common law


damages.

The Contractor’s claim is only for profit on the Contract work, not
for other work, so it is within the first rule in Hadley v.
Baxendale, and should be allowed.

3.4. The Contractor’s Summary


For all of the foregoing reasons, the Contractor contends that
the profit claimed by him is allowable. It should be treated in the
same way as damage within the meaning of the first rule in
Hadley v. Baxendale, and fulfil the criterion in Robinson v.
Harman.

There is no prohibition of it as a head of claim. If the Project


Manager were to have the power to deprive the Contractor of
profit on any claim he chose to treat as one for ‘costs’, then all
contractors could be placed in the unacceptable position of
doing a large proportion of work at cost. This is clearly not what

page 48
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

the Contract stipulates, nor could it have been the intention of


the parties.

page 49
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

4. Circumstances Giving Rise to Claim


Performance of the construction activities required the
availability of final setting out details and foundation design
information (arising from unforeseen ground conditions) to
permit execution of the Works. Records show that setting out
was delayed and information with respect to rock excavation
was neither evident from records available. These two initial
events seriously impacted progress and caused significant
delays. It was further and seriously compounded by the Project
Manager’s instructions to suspend the Works which lasted 2
months.

Furthermore, it is a fundamental requirement of the Contract that


detailed design information is made available in the times
consistent with the Contractor’s programme of works. In the
event, such information was late, and aggravated by incomplete
and inconsistent design details that naturally caused a change in
the planned methods of working. This is particularly evident at
the two “Mock-up” villas that underwent numerous changes as
works proceeded.

In addition to the above, payment for varied work performed was


not fully received by the Contractor in accordance with the
procedures and time stated in the contract.

4.1. Contractual Basis – Notification of Changes


The Contractual basis of the heads of claim is described in
subsequent sections of this document. That is, the Contractor
gave notice of the difficulties existing at the Site arising from
delays and disruptions.

The Contractor issued notice of the following issues on

We acknowledge receipt of your letter dated 4 December


2007 referenced E-09-04-12-07 and wish to confirm our
position by the following extract from the Contract:

The Letter of Acceptance dated 7 March 2007 referenced


SHAN/zk/ZK/LOA.01 states at paragraph 3.0: “the lump
sum contract price shall not be amended unless
specifically agreed with the Employer and the Quantity
Surveyor. No additional work (beyond the scope of the
lump sum Contract Price) may be commenced prior to
reaching agreement on the price thereof.”

page 50
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

It further states that “Any changes in the design, which


affect the lump sum Contract Price, must be specifically
agreed by the Employer.”

The Contract Agreement dated 27 April 2007 lists the


documents forming the Agreement and the Letter of
Acceptance takes priority over the Conditions of
Contract.

Consequently, your reference to sub-clause 12.3 and


13.1 of the Conditions of Contract, although interesting, is
not relevant in the introduction of Variations on this
project, particularly as sub-clause 3.1 has been amended
by the quoted specific conditions above.

We would point out that although the amendment is


impractical it is a significant revision to both Clause 12
and 13 of the Conditions of Contract. In practise it means
that no Variation arising from additional work or by design
change can commence prior to receiving the agreement
of the Employer.

In conclusion, the purpose of our letter dated 23


November 2007 on this subject matter was to bring these
special circumstances to your attention.

A further notice was issued on XX relating to the instruction to


suspend the works:

Please refer to your letter dated 23 November 2007


referenced E-01-23.11.07 to which we wish to clarify this
situation with regards to the cause for suspension of
works.

First, the suspension of the Works, other than the two


Mock-up villas occurred between 29 August 2007 and 29
November 2007. The reason for your suspension relies
on work covered prior to inspection, but not with our site
organisation. We have covered this aspect in our
previous letter and pointed out remedies in the Contract
available to the Engineer in these situations.

Secondly, although it was suggested in our email dated


28 August 2007 that concrete work would stop, in reality
it did not and work continued until your instruction to
suspend Works on 29 August 2007. This is all a matter of
record and should be common ground.

Consequently, we disagree with contentions raised in


your letter and reiterate our entitlement to extensions of

page 51
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

time and additional payment arising from your


instructions.

A notice was issued in regards to several of the delaying events


on XX

We acknowledge receipt of your letter dated 23


November 2007 referenced E-07-23.11.07 regarding
records of meeting No. 27 held on 9 November 2007. We
disagree with your position on the 3 points for the
following reasons:

Point 3 – minute 6.2: It is impossible for the Project


Manager to have knowledge of the Contractor’s
management and manpower with respect to their ability
to handle the complete site. This is complete conjecture
and only the Contractor can have that knowledge. In any
event, it is not a contractual provision to suspend work
based upon the Project Manager’s perceived knowledge
of the Contractor’s planning and operations. Even if this
is your reason for suspension the provisions of sub-
clause 8.9 remain relevant.

The facts are recorded in our letter dated 29 October


2007 where reasons for suspension were indeed
because work was covered up prior to inspection and
approval. Once again, if this is your remedy in these
circumstances, then the same provisions at sub-clause
8.9 are relevant.

Point 4 – minute 6.2: We have recorded severally


delays caused by setting-out, increased scope of work for
normal excavation, rock excavation and fixing steel
reinforcement, shuttering and volume of concrete. The
combination of these issues had caused a delay to
progress at the time of this meeting (which is in the same
period the works were suspended) by at least 3 weeks.

Normally, the Project Manager would give notice to the


Contractor in accordance with sub-clause 8.3 which last
paragraph, states:

If, at any time, the Engineer gives notice to the Contractor that
a programme fails (to the extent stated) to comply with the
Contract or to be consistent with actual progress and the
Contractor’s stated intentions, the Contractor shall submit a
revised programme to the Engineer in accordance with this
Sub-Clause.

This revised programme is issued in accordance with the


provisions of sub-clause 8.6, which states:

page 52
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

If, at any time:

(a) actual progress is too slow to complete within the Time for
Completion, and/or

(b) progress has fallen (or will fall) behind the current
programme under Sub-Clause8.3 [Programme],other than as
a result of a cause listed in Sub-Clause 8.4 [Extension of Time
for Completion], then the Engineer may instruct the Contractor
to submit, under Sub-Clause 8.3 [Programme], a revised
programme and supporting report describing the revised
methods which the Contractor proposes to adopt in order to
expedite progress and complete within the Time for
Completion. (Emphasis added)

Unless the Engineer notifies otherwise, the Contractor shall


adopt these revised methods, which may require increases in
the working hours and/or in the numbers of Contractor’s
Personnel and/or Goods, at the risk and cost of the Contractor.
If these revised methods cause the Employer to incur
additional costs, the Contractor shall subject to Sub-Clause 2.5
[Employer’s Claims] pay these costs to the Employer, in
addition to delay damages (if any) under Sub-Clause 8.7
below.

Please confirm if you intend to give a notice in


accordance with this sub-clause? If that does remain
your intention, then we must draw your attention to sub-
clause 8.4, to paragraphs (a) and (b).

In the alternative, we confirm having issued a compliant


notice in accordance with sub-clause 8.4 and provision of
claims under sub-clause 20.1.

In conclusion, as we are not responsible for the delay


and disruption to date, and the extended time to
completion at 8 December 2007, we will not adopt any
acceleration measures to recover earlier delays unless
and until instructed.

At the request of the Project Manager a second revised


programme of works was issued on 14 March 2008. In this
notice the Contractor clearly indicated the various delays
effecting impacting progress:

In accordance with your recent request in the weekly


progress meetings, please find attached revised
programme of works for your consent.

page 53
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

The revised programme takes into consideration the


various events and changed circumstances since
commencement up to 29 February 2008.

These events and changed circumstances, as separately


notified to you and further illustrated in our situation
report dated 29 February 2009, have caused the original
planned timing and sequence of works to vary. They
include the following;

 Unforeseen hard rock excavation including


spoiling;

 Suspension of works, except for the mock up


villas, for two months and associated acceleration
measures;

 Instructed design variations, e.g. exchange of


galvanised steel with stainless steel components
for installation in the roof resulting into delays in
procurement;

 Late Instructions, e.g. several changes to the


location, position and orientation of buildings by
revision in the setting out details have delayed and
disrupted the works;

 Late Design Information resulting into delays in


procurement thus preventing timely arrival of
materials at site;

 Increased scope of works occasioned by


unforeseen site conditions and instructed
additional works;

 Inclement weather condition; unexpected high


amounts of rainfall currently being experienced at
site is slowing down progress of works.

The overall effect of all the above has been to delay the
completion date for the works up to 24 March 2009 as
indicated in the attached revised programme.

We therefore request extension of time to completion of the


works.

The Contractor wrote again on 21 April 2008 with a notice


stating the events that delayed progress:

page 54
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

Reference is made to your letter dated 7 April 2008, E17-


07.04.2008 to which this letter relates.

The purpose of this letter is to seek approval to


accelerate progress to Completion in solution to recovery
of earlier delays experienced which is made without
prejudice to our current contractual position.

Progress To Date and Causes of Delay

We have written on several occasions about various


events that caused delay and disruption to the regular
progress of the work since the outset of this Contract.
Some of these events and changed circumstances are
described below and are significant by either their impact
on time to completion or cost or both:

Late Design Information

Both survey data and final construction design are being


issued late and this has naturally caused delay. As
example, drawings for construction are required at
commencement in order to allow procurement; however,
drawings are still being issued or remain outstanding 12
months after commencement. The lateness of such
information prevents rapid conclusion and timely arrival
of materials at Site.

The Contractor also records he has not received any


structural drawings that must in the first instant, be
approved by the Ministry of National Development.

A further complication arises from having two structural


engineers engaged to design different parts of the
Contract. This has led to disruption in the design process.

Provisional Sums

Almost 30% of the Contract Price is derived from lump


sum provisions for works not sufficiently detailed or
identified at time of tender. The subsequent introduction
of these works requires an instruction in accordance with
the conditions stated in the Contract. As such, they are
not works necessarily envisaged as forming part of the
Works until and unless the Project Manager issues an
instruction.

A further complication is that for these particular works


neither detailed bill of quantities exists nor design
drawings, although almost 12-months of the Contract
period have elapse. In practise the Quantity Surveyor

page 55
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

should have prepared these Bills for submission to the


Contractor to enable pricing and material procurement.
As a result, their value is not defined and detailed
programming is not possible and that indicates the
Contract Price and the time of Completion must change.

Material Procurement

In the absence of complete design information


procurement has not proceeded as planned. Delays in
procurement will undoubtedly cause delay to completion.
In addition, prices quoted at tender stage cannot be
secured because orders are confirmed much later than
planned.

Suspension of work

The Works were suspended in the period from 29 August


2007 through to 29 October 2007 as recorded in minutes
of monthly meeting No 27 held 9 November 2007. The
reason for this suspension by the Project Manager relies
on work covered-up before inspection (at one villa
column base).

The Conditions of Contract contain provisions for


breaking out and exposing work and this would have
been the sensible solution, not suspension. As to
progress, it is evident from the photographs taken of the
site at that date excellent progress was being made at
several locations. The impact of 2 months suspension
has had on progress was significant.

Re-measurement Contract vis-à-vis Fixed Lump Sum

The Conditions of Contract adopted on this project is a


standard form and allows re-measurement however, all
Clauses that allow Variations have not been revised or
amended as one would expect in order to suit a Fixed
Lump Sum Contract.

In addition, the Letter of Acceptance states that:

“the lump sum contract price shall not be amended


unless specifically agreed with the Employer and the
Quantity Surveyor. No additional work (beyond the
scope of the lump sum Contract Price) may be
commenced prior to reaching agreement on the price
thereof.” [Emphasis added]

It further states that:

page 56
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

“Any changes in the design, which affect the lump sum


Contract Price, must be specifically agreed by the
Employer.”

Clearly, any alteration to the scope of work, introduction


of additional work or design change, is very likely to
influence a change in the Contract Price and the time to
Completion. On this contract three areas of change will
cause the Contract Price to vary and the time to
Completion to extend, namely:

Variations to Scope of Works

Changes in the scope of work do arise by virtue of


drawings issued for construction that automatically
increase quantities shown in the Bills of Quantities. This
is for two reasons; a) the correlation between
substructure design and actual ground conditions are at
variance, and b) a general enhancement of the reinforced
concrete structure designed.

Flowing from variations generally introduced by final


design drawings or drawings issued for construction, the
scope of work has increased considerably, as example:

 A significant increase in excavation of hard rock


for which a small provision was made in the
Contract;

 A significant increase in the quantity of normal


excavation to that indicated in the Contract, which
is dictated by the topographic site conditions;

 A significant increase in volume of reinforced


concrete placed to that indicated in the Contract;

 A significant increase in associated temporary


works such as shuttering to that indicated in the
Contract; and

 A significant increase in steel reinforcement to that


indicated in the Contract.

All these changes are not within the control of the


Contractor, they are instructed Variations and naturally
have time and cost considerations.

Instructed Design Variations

Mainly changes brought by a) interior design


requirements, and b) because of superstructure
variations. Once again, these variations are not within the

page 57
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

control of the Contractor, they are instructed Variations.


One example of a design change relates to the exchange
of galvanised steel with stainless steel components for
installation in the roof. Notwithstanding the delay in
making procurement of this specialist item, the additional
cost is significant.

Lump Sums

The values of many of the structures included in the


Contract Price are based on a square-metre rate in the
absence of a detailed bill of quantity. As design drawings
are now issued (September 2007) these works need to
be measured and valued. The outcome of this evaluation
will undoubtedly cause the Contract Price to vary. In
addition, the time required to complete these structures
can only be evaluated once detailed design drawings are
made available. At that juncture, the details of these
structures can be introduced in the programme of works.

Other Factors Impacting Progress

Although the following issues were known and


considered at time of tender and therefore, allowed in our
programme of works, they clearly have an influence on
progress. They are mentioned here because with the
prevailing delays described in Points 1 and 2 above, their
very existence compounds a situation that is already
impacting progress.

Tidal Movement

Each and every day/month typical low-tide conditions


exist that prevent movement of vessels delivering
material to Long Island. This is not a situation that can
change and such time considerations are incorporated in
the programme of works. The situation is compounded as
the immediate area to Long Island is a protected Marine
Park.

Transport of Materials to Long Island

All materials are brought by sea via one large barge in


deep water which off-loads to two small barges at
shallower water. At times it is not uncommon for a barge
to suffer mechanical failure and there is possibility of
disruption in the material supply. There are no other
methods available that allows bulk supply of materials to
the island, so although these difficulties are present all
efforts are made to ensure these operations are limited.

page 58
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

Procurement of Local Raw Materials

The level of construction in the Seychelles is quite


substantial and demands for natural quarry materials
places a considerable strain on the local supplier. The
supply of quarry materials in the Seychelles are a
monopoly and alternate sources are not available.
Occasionally, a quarry product is in short supply, usually
because of demand, and this will cause disruption in
placement of concrete at site.

Wet Weather Conditions

The weather patterns are fairly regular and wet seasons


can cause considerable difficulty at site, particularly prior
to establishment of all-weather access roads. Once
again, this is not a situation that can change and such
time considerations are incorporated in the programme of
works.

Suspension of Quarry Operations

In parallel with wet weather seasons all quarry operations


do not function, particularly when rainfall is persistent
over several days. As a consequence quarry products
such as dust and aggregates and composite items as
concrete blocks are not produced which interrupts the
regular supply to Site.

Financial Considerations

The events and changed circumstances described in the


foregoing have directly impacted the Contractor’s income
which, together with Advance repayments has caused a
negative cash flow.

Reduced Income

Regular progress of the works has been reduced


significantly because of the delays occasioned by
Variations, additional works and suspension of the whole
Site (except the two mock-up villas). As a consequence,
the value of work performed is significantly lower than
anticipated and as indicated on the original cash flow
chart. Therefore, costs are constantly greater than
income derived for work performed.

Also, during these periods of delay and disruption direct


and indirect costs are not fully recovered because
planned progress has not been achieved. In addition, and
as a result of a continuous shortfall in income, the value

page 59
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

of the Advance to the Contractor has diminished at a rate


greater than anticipated as it’s been consumed in loss
and expense.

Repayment of Advance Loan

The repayment of the Advance is directly linked to


projected income which is derived from the programme of
works. However, because progress has not been
achieved income is considerably lower and the time for
completion has extended. As a result, the monthly value
of repayment has to be adjusted in light of the change in
income flowing from an extended time to completion.

Proposed Remedy

The revised programme of works issued under cover of


our letter dated 14 March 2008 shows a revised
completion date of 24 March 2009. This is the date
substantial completion can be achieved and is based on
two important criteria; a) an adjustment to the value and
period of the initial Advance repayment and, b) the
payment of a second Advance.

The programme considers delays experienced to date,


which principally is the setting out, excavation in hard
rock, delays in receipt of detailed design drawings and
delayed arrival of major material components to site.

It is anticipated that with the measures to recover earlier


delays explained below, this continuing delays will be
halted and in some respects, time will be recovered.

For reasons provided in the foregoing, this situation with


respect to cash flow is not sustainable. In order to rapidly
and affectively halt escalation of this situation the
Contractor proposes the following solutions:

Adjusting Repayment of Advance

The cash flow estimate has been adjusted once to date


to meet changed circumstances on site and this must be
done again. The monthly value and period of repayment
will need to be aligned with the revised durations shown
on the programme of works. A proposed revised recovery
on this Advance is shown in the table below:

page 60
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

Cert. No. Month AdvancePayment Certified AdvanceRepayment

Advance May-07 3,100,000.00


1 Jun-07 682,032.85
2 Jul-07 351,989.15 200,000.00
3 Aug-07 145,803.63 200,000.00
4 Sep-07 357,556.62 200,000.00
Oct-07 0.00 357,142.86
5 Nov-07 478,926.03 214,285.71
6 Dec-07 0.00 214,285.71
Jan-08 0.00 214,285.71
7 Feb-08 1,276,534.91 100,000.00
8 Mar-08 1,276,534.91 100,000.00
9 Apr-08 1,276,534.91 100,000.00
10 May-08 1,276,534.91 100,000.00
11 Jun-08 1,276,534.91 100,000.00
12 Jul-08 1,276,534.91 100,000.00
13 Aug-08 1,276,534.91 100,000.00
14 Sep-08 1,276,534.91 100,000.00
15 Oct-08 1,276,534.91 100,000.00
16 Nov-08 1,276,534.91 100,000.00
17 Dec-08 1,276,534.91 100,000.00
18 Jan-09 1,276,534.91 100,000.00
13 Feb-09 1,276,534.91 100,000.00
14 Mar-09 1,276,534.91 100,000.00
15 Apr-09 1,276,534.91 100,000.01
16 May-09 1,276,534.91
17 Jun-09 1,276,534.91
18 Jul-09 1,276,534.91
17 Aug-09 1,276,534.91
18 Sep-09 1,276,534.91
13 Oct-09 1,276,534.91
14 Nov-09 1,276,534.91

Total 3,100,000.00 30,100,076.26 3,100,000.00

Measures to Recover Earlier Delays

To facilitate measures to accelerate progress the


Contractor will enhance existing resources. This will
involve bringing to site additional equipment and staff and
labour resource over and above that planned at tender.

The table below lists planned additional staff and labour


and equipment that will be deployed at Site. It also
includes the delay and disruption costs arising during the
2-month period of suspension.

page 61
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

ID Designation Value UD$ Amount

Staff and Labour

1 Senior Project Manager 168,630.00


2 Quality Assurance Manager 168,630.00
3 Senior Quantity Surveyor 107,250.00
4 Assistant Quantity Surveyor 99,000.00
5 Expatriate Workers 880,000.00 1,423,510.00

Equipment

1 Potain tower crane (2Nr) 131,400.00


2 Scaffolding 105,791.00
3 Merlo Car-Mix 62,500.00
4 JCB 70,000.00
5 Concrete Paver 45,000.00
6 Rock Breaker 32,000.00
7 Mini Excavator (15 Tonne) 88,500.00 535,191.00

Delay and Disruption Costs 565,714.29

Total additonal resources 2,524,415.29

In recognition of the additional cost flowing from


deploying additional resources and loss and expense
suffered during periods of delay and disruption, the
Contractor requests reimbursement of a portion of these
direct costs. These have been established in the above
table and amounts to US$2,524,415.29. The Contractor
asks payment in nine (9) equal interim Certificates
starting from April 200 with the last in December 2008.

Second Secured Advance Payment

The major and immediate expense typically flows from


material and equipment procurement. A subsidiary of that
is increased staff and labour over and above that
originally planned.

The first component, materials, is the critical element to


achieving sustained progress and once 80% has been
secured and delivered at Site, a major obstacle is
overcome. This is particularly significant with respect to
the geographic location of the Seychelles and the
difficulties this presents for material procurement.

Material not ordered is either because design details


have not been availed or that Bills of Quantities and
respective designs flowing from Provisional Sums is still
in abeyance.

page 62
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

The second component, equipment, dictates the methods


and pace at which the works proceed. In other words, by
increasing the number of certain pieces of equipment and
by changing methods, progress can be improved
significantly.

The last element considered is staff and labour, the major


change will be deployment of two European Site Agents
well experienced in this type of work. In addition, we will
deploy further expatriates of all trades in order to meet
the demands of a revised programme of works, which we
will submit shortly.

As shown in the impacted programme issued 14 March


2008, because of earlier delays many operations have
been delayed, therefore, commencement of most
buildings have been compressed on the original
programme of works. This means that site operations are
not working sequentially but simultaneously and this is a
major planning problem existing today. Consequently, all
these resources will allow expansion of operations to
many areas of site allowing work to proceed
simultaneously and therefore achieve earliest completion.

To meet additional and immediate costs in this recovery


program and to meet the changed circumstances, the
Contractor requires a minimum Advance payment
amounting to US$3,500,000.00. The proposed recovery
on this Advance is shown in the table below:

Month Value Repaid

May-08 250,000.00
Jun-08 250,000.00
Jul-08 250,000.00
Aug-08 300,000.00
Sep-08 300,000.00
Oct-08 350,000.00
Nov-08 400,000.00
Dec-08 550,000.00
Jan-09 400,000.00
Feb-09 450,000.00

Total 3,500,000.00

The next table is the projected combined recovery on


both Advance payments:

page 63
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

Month FirstAdvance SecondAdvance Combined

May-07 0.00 0.00


Jun-07 0.00 0.00
Jul-07 200,000.00 0.00 200,000.00
Aug-07 200,000.00 0.00 200,000.00
Sep-07 200,000.00 0.00 200,000.00
Oct-07 357,142.86 0.00 357,142.86
Nov-07 214,285.71 0.00 214,285.71
Dec-07 214,285.71 0.00 214,285.71
Jan-08 214,285.71 0.00 214,285.71
Feb-08 100,000.00 0.00 100,000.00
Mar-08 100,000.00 0.00 100,000.00
Apr-08 100,000.00 0.00 100,000.00
May-08 100,000.00 250,000.00 350,000.00
Jun-08 100,000.00 250,000.00 350,000.00
Jul-08 100,000.00 250,000.00 350,000.00
Aug-08 100,000.00 300,000.00 400,000.00
Sep-08 100,000.00 300,000.00 400,000.00
Oct-08 100,000.00 350,000.00 450,000.00
Nov-08 100,000.00 400,000.00 500,000.00
Dec-08 100,000.00 550,000.00 650,000.00
Jan-09 100,000.00 400,000.00 500,000.00
Feb-09 100,000.00 450,000.00 550,000.00
Mar-09 100,000.00 100,000.00
Apr-09 100,000.01 100,000.01

Total 3,100,000.00 3,500,000.00 6,600,000.00

The revised Organisation Chart is attached to which has


been added the additional management staff. Evidence
of projected expenditure for staff, labour and materials is
provided in the table below and is likely to exceed US$5
million.

page 64
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

ID Designation Value UD$ Amount

Staff and Labour (one month)

1 Senior Project Manager 15,330.00


2 Quality Assurance Manager 15,330.00
3 Senior Quantity Surveyor 9,750.00
4 Assistant Quantity Surveyor 9,000.00
5 Expatriate Workers 80,000.00 129,410.00

Equipment

1 Potain tower crane (2Nr) 131,400.00


2 Scaffolding 105,791.00
3 Merlo Car-Mix 62,500.00
4 JCB 70,000.00
5 Concrete Paver 45,000.00
6 Rock Breaker 32,000.00
7 Mini Excavator (15 Tonne) 88,500.00 535,191.00

Materials

1 Balau timber (special size) 1,764,705.88


2 Stainless steel roof components 2,559,900.00
3 Shingles 333,600.00 4,658,205.88

Total Second Advance 5,322,806.88

Conclusion

It is evident from the foregoing the considerable


difficulties encountered on this project since the outset
are not the responsibility of the Contractor.

The majority of changes and consequent difficulties exist


because a significant portion of design was not
developed at tender. Of worthy note, after expiry of
almost 12 months of the Contract period close to 30% of
the scope of works has not been identified through
detailed Bills of Quantities; an essential requirement
outwith prevents material procurement and disrupts
planning.

Recent suggestions to engage other contractors to


perform portions of the scope of works will have little
effect because constraints imposed by operational
logistics and design development are unlikely to diminish.

Consequently, with the valuable knowledge and


experience gained it is our considered opinion drastic
measures must be implemented by both the Contractor
and Employer’s design teams. The respective
responsibility of each party is important and the

page 65
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

Contractor has in this letter, set-out under paragraph 5


above, what he feels is required to bring this project to
earliest completion.

First, the Contractor looks forward to receiving proposals


from the Employer’s design team indicating what
measures will be taken to address outstanding design
issues. Secondly, the scope of works must be defined in
order to establish the revised Contract Price outwith the
Contract Completion date will remain at large.

Finally, payment of the Contractor’s acceleration costs


and the Second Secured Advance is of paramount
importance in the measures required to conclude this
Contract thus allowing a reduction of the Contractor’s
extended costs and indeed, the Employer’s losses.

We look forward to receiving approval in principle of the


foregoing and subsequent instructions.

Accordingly, the Contractor is entitled to receive, under Sub-


Clause 20.1, extensions of time and additional payment as
described under Sub-Clause 8.4, 1.9 and 2.1 of the Contract
Conditions.

4.2. Late and Inaccurate Survey Data


The completeness, accuracy and timely issue of survey
information remain the responsibility of the Project Manager.
Sub-clause 4.7 of the Contract Conditions is clear on this
subject and it should be common ground as to the
consequences of the Contractor being provided information
inconsistent with design and site conditions.

The table below provides dates when setting-out was performed


and reasons why for many the exercise was repeated. In most
instances it was because the position and orientation were
varied to suit site conditions.
Baseline Programme Setting Delays due to Changes in Setting Out Details &
Villa Out Finish date Initial Setting Out Revised Setting Out Orientation (days)

A3/30 29-Mar-07 25-Apr-07 26-Jun-07 62.00


A3/20 13-Apr-07 25-Apr-07 20-Jul-07 86.00
A3/11 10-Apr-07 25-Apr-07 03-Jun-07 39.00
A3/07 03-Apr-07 25-Apr-07 04-Jun-07 40.00

It can be seen in the table above critical delays occurred at four


villas of between 40 and 86 calendar days. These delays are
considered and included in the extension of time request.

page 66
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

4.3. Late Receipt of Final Design Information


In addition to receiving design information late, the Contractor
has had the inconvenience and time-consuming problem of
dealing with design drawings issued that are either late or are
revised.
Structure/Villa Baseline Programme Drawing Receipt Schedule
Drwgs Required 120 days
Commencement Completion prior POW Start Date Structural Architectural Delay (Days)

A3 Pool Villa 02-Apr-07 15-Mar-08 28-Feb-07 14-Mar-07 09-Mar-07 14.00


B223 Standard Villa 28-May-07 15-Mar-08 28-Feb-07 14-Mar-07 09-Mar-07 14.00
B4 Standard Villa with Pool 16-Apr-07 15-Mar-08 28-Feb-07 14-Mar-07 09-Mar-07 14.00
C311 Executive Villas 12-Apr-07 15-Mar-08 28-Feb-07 14-Mar-07 09-Mar-07 14.00
P3 Presidential Villas 20-Jun-07 20-Mar-08 28-Feb-07 19-Oct-07 09-Mar-07 233.00
Sunset Deck 23-Jul-07 14-Mar-08 25-Mar-07 09-Apr-08 22-Aug-07 381.00
Employees Facilities Complex 14-Jun-07 19-Mar-08 28-Feb-07 31-Aug-07 22-Aug-07 92.00
Excom Villa 14-Jun-07 17-Mar-08 28-Feb-07 19-Oct-07 22-Aug-07 233.00
GM Villa 14-Jun-07 15-Mar-08 28-Feb-07 19-Oct-07 22-Aug-07 233.00
Health club 14-Jun-07 15-Mar-08 28-Feb-07 11-Jun-07 28-May-07 103.00
Single Treatment room 02-Jul-07 17-Mar-08 04-Mar-07 10-Jun-07 28-May-07 98.00
Couple treatment room 02-Jul-07 19-Mar-08 04-Mar-07 25-Jun-07 28-May-07 113.00
Sanctum 02-Jul-07 15-Mar-08 04-Mar-07 19-Oct-07 28-May-07 229.00
Yoga Pavilion 02-Jul-07 14-Mar-08 04-Mar-07 19-Oct-07 28-May-07 229.00
BOH Building 02-Jul-07 17-Mar-08 04-Mar-07 19-Oct-07 28-May-07 229.00
Wedding chapel 02-Jul-07 14-Mar-08 04-Mar-07 09-Apr-08 28-May-07 402.00
Seafood Resort 18-Jun-07 19-Mar-08 28-Feb-07 11-Jun-07 28-May-07 103.00
Retail Pavilion 18-Jun-07 14-Mar-08 28-Feb-07 11/06/2007 28-May-07 103.00
Kid's club 02-Jul-07 14-Mar-08 04-Mar-07 20-Dec-07 08-Jan-08 291.00
Recreation House 02-Jul-07 14-Mar-08 04-Mar-07 20-Dec-07 08-Jan-08 291.00
Water sport Rental 02-Jul-07 14-Mar-08 04-Mar-07 20-Dec-07 08-Jan-08 291.00
Dive Center 02-Jul-07 14-Mar-08 04-Mar-07 20-Dec-07 08-Jan-08 291.00
Mechanical Area 22-Oct-07 09-Apr-08 24-Jun-07 Not Received Yet 08-Jan-08 326.00
3 Meal Restaurant 02-Jul-07 26-Mar-08 04-Mar-07 Not Received Yet 08-Jan-08 438.00
Signature Pool 02-Jul-07 15-Mar-08 04-Mar-07 Not Received Yet 08-Jan-08 438.00
Beach Pool Bar 02-Jul-07 17-Mar-08 04-Mar-07 Not Received Yet 08-Jan-08 438.00

The table above shows the timing of receipt of design drawings


and is evidence of continuing delays. In some instances
structural drawings are still outstanding where in others they
have been issued late by between 14 and 438 calendar days.

Due to the lateness in receipt of design drawings, not only


construction delayed but also procurement. Delays in
procurement cause the Contractor to incur greater costs
because prices secured at tender either expired or prices in the
period increased.

4.4. Additional and Varied Work


4.4.1.Excavation in Hard Rock
Due to the nature of the ground and the topography of the Site,
it was important to adhere to the Contractor’s original planning in
terms of construction sequence.

Furthermore, the scope of this work was restricted to a) the


numbers of buildings identified at tender stage and, b) the
position of the buildings. Obviously, with a major part of the

page 67
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

Contract Price falling under Provisional Sums, both these factors


had to change and, with that change (Variation), brought a
number of unforeseen difficulties.

One such consequent change involved significant increase in


excavation in hard rock. Furthermore, the change in timing and
sequence exacerbated the difficulty in extraction and the method
in which the work could be performed.

4.4.1.1. Change in Sequence and Increased Cost

Although the sequence change was caused by survey work,


rock excavation and more specifically the suspension of Works,
work at each site then became in variance to the contractor’s
original planning, the conversion and expenditure of Provisional
sums exacerbated its impact.

4.4.1.2. Increased Quantity

In addition to the complications of performing controlled blasting,


the quantity of rock excavated to date has increased between
20% and over 300% to that anticipated. In these conditions the
Contractor has entitlement to the additional time to perform
these varied works.

The following tables are recorded evidence of the significant


increased volume of rock excavation found at almost every villa
site. The tender provision was clearly too low and that has been
reflected in the Contractor’s planning.

As example, the first table below illustrates the quantities of rock


excavated using blasting methods otherwise not foreseen. At
villa B2/01 the volume of hard rock excavated has already
reached close to 240m3 whereas the allowance in the Contract
was zero. The time taken to remove this rock to date, as it is not
finished, is already close to 200 calendar days. Consequently,
the duration taken for this activity at this villa is already 200
calendar days and delay is considered critical.

The following table lists volume of rock excavated at each villa


which, as stated above, is all unforeseen. As such at each villa
the delay caused in performing this activity is critical and
prevents commenced of subsequent dependant activities.

page 68
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

Villa Rock Blasting (m3) Increase

A3/02 95.00 100%


A3/03 97.85 100%
A3/04 23.00 100%
A3/05 1.14 100%
A3/06 12.69 100%
A3/08 11.41 100%
A3/09 54.50 100%
A3/10 171.68 100%
A3/11 139.00 100%
A3/19 47.97 100%
A3/20 65.10 100%
A3/21 42.13 100%
A3/28 4.17 100%
A3/29 4.18 100%
A3/31 2.31 100%
B2/01 239.14 100%
B2/04 147.55 100%
B2/05 13.87 100%
B2/06 48.40 100%
B2/07 7.73 100%
B2/08 5.04 100%
B2/09 28.50 100%
B2/10 52.50 100%

The next table provides a summary of volumes of hard rock


excavated at the various sites. Once again it is apparent that the
tender provision represents only between 8% and 55% of the
actual quantity excavated. Once again with such a significant
change it is obvious removing over 60m3 of rock takes
significantly longer than 5m3.

Villa Rock Exc without blasting BOQ quantity Change

A3/01 9.05 5.00 81%


A3/03 8.75 5.00 75%
A3/04 18.75 5.00 275%
A3/05 22.50 5.00 350%
A3/06 19.50 5.00 290%
A3/08 25.88 5.00 418%
B2/01 60.62 5.00 1112%
B2/02 64.28 5.00 1186%
B2/04 60.45 5.00 1109%
B2/07 4.74 5.00 -5%

The next table summarises excavated material volumes in


common material. It can be seen volumes have increased
significantly

page 69
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

Villa Exc other than rock BOQ quantity Change

A3/04 124.54 38.00 228%


A3/05 141.12 38.00 271%
A3/09 37.81 38.00 0%
A3/30 112.02 38.00 195%
A3/31 122.80 38.00 223%
A3/32 75.82 38.00 100%
B2/01 191.68 70.00 174%
B2/02 345.02 70.00 393%
B2/03 383.36 70.00 448%
B2/04 230.02 70.00 229%
B2/05 191.68 70.00 174%
B2/06 191.68 70.00 174%
B2/07 345.02 70.00 393%
B2/08 191.68 70.00 174%

The next table consolidates all the changed quantities of all


materials excavated at each villa. Comparing anticipated
durations based on bills of quantities and actual, it can be seen
in the extreme right hand column the significant variance in time.

The durations shown which range from 26 to 354 calendar days


are considered critical, as all subsequent activities that follow
excavation are equally delayed.
Rock Excavation without Excavation, other than Duration Taken To Baseline Duration based on
Villa Rock Blasting (m3) Blasting (m3) rock (m3) Actual excavation schedule Date (Days) BQ quantities (Days) Critical Delay
Commencement Completion
A3/01 9.05 15 October 2007 25 December 2007 71.00 3.00 68.00
A3/02 95.00 20 December 2007 on progress 90% 147.00 3.00 144.00
A3/03 97.85 8.75 11 September 2007 on progress 95% 247.00 3.58 243.42
A3/04 23.00 18.75 124.54 04 June 2007 22 July 2007 48.00 2.00 46.00
A3/05 1.14 22.50 141.12 07 June 2007 25 July 2007 48.00 2.63 45.38
A3/06 12.69 19.50 09 June 2007 18 December 2007 192.00 2.08 189.92
A3/08 11.41 25.88 05 May 2007 16 January 2008 256.00 1.04 254.96
A3/09 54.50 37.81 01 January 2008 on progress 90% 135.00 1.04 133.96
A3/10 171.68 16 April 2007 15 August 2007 121.00 1.04 119.96
A3/11 139.00 14 June 2007 on progress 40% 336.00 1.04 334.96
A3/19 47.97 15 June 2007 on progress 20% 335.00 1.04 333.96
A3/20 65.10 19 November 2007 on progress 45% 178.00 1.04 176.96
A3/21 42.13 14 June 2007 on progress 45% 336.00 1.04 334.96
A3/26 120.00 18 April 2007 05 March 2008 322.00 322.00
A3/27 125.00 27 August 2007 28 November 2007 93.00 93.00
A3/28 4.17 25 June 2007 22 November 2007 150.00 2.08 147.92
A3/29 4.18 23 June 2007 10 August 2007 48.00 2.08 45.92
A3/30 112.02 04 June 2007 23 July 2007 49.00 2.00 47.00
A3/31 2.31 122.80 09 June 2007 24 July 2007 45.00 2.08 42.92
A3/32 75.82 04 June 2007 02 July 2007 28.00 2.00 26.00
B2/01 239.14 60.62 191.68 20 October 2007 on progress 50% 208.00 1.04 206.96
B2/02 64.28 345.02 09 July 2007 18 November 2007 132.00 1.04 130.96
B2/03 383.36 11 June 2007 24 July 2007 43.00 1.00 42.00
B2/04 147.55 60.45 230.02 11 May 2007 06 March 2008 300.00 1.04 298.96
B2/05 13.87 191.68 25 May 2007 on progress 95% 356.00 1.04 354.96
B2/06 48.40 191.68 03 December 2007 on progress 65% 164.00 1.04 162.96
B2/07 7.73 4.74 345.02 27 May 2007 20 November 2007 177.00 1.04 175.96
B2/08 5.04 191.68 24 December 2007 on progress 65% 143.00 1.04 141.96
B2/09 28.50 21 November 2007 on progress 75% 176.00 1.04 174.96
B2/10 52.50 15 November 2007 on progress 75% 182.00 1.04 180.96

Note: it has not been possible to separate the delays resulting


from blasting and those arising out of increased quantities of
other excavated materials. The works are executed at the same
time. The table above therefore shows the combined delays
arising from the above 3 changed events.

page 70
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

4.4.2.Increased Quantity in Reinforced Concrete


The two examples below show changes in scope to standard
villa, A3 and B2. The increase in quantities indicated relate to
these two villas only. However, the Contract includes a further
32 number of type A and 10 number of Type B and the same
change in scope is applicable to all villas. As a consequence, an
equal or similar additional time will be required to perform the
changed scope of work.

4.4.2.1. Villa Type A3 (Example)

Steel reinforcement, shuttering and the concrete volume has


increased considerably and the example below is for one villa
only. As detailed in the table, the duration to perform these
works has extended from 12 calendar days as planned to 45
calendar days. Once again, the additional time is critical and has
delayed dependant and subsequent activities shown on the
programme of works.

Villa Type Item Unit Tender Quantity Design Quantities


A3 Frame
Reinforcement kg 3,040.00 5,130.00
Concrete m3 32.00 43.00
Formwork m2 305.85 351.00

Baseline duration for Tender Quantity 12 Days


Actual Duration due to increased quantity 45 Days

The following table compares the planned and actual durations


for completing various other concrete components of the
building structure.
A3 Type Frame Baseline Duration Revised Duration

set kickers 1.00 2.00


Conc. Columns & shear walls 2.00 11.00
Conc. G. F Beams 2.00 6.00
Conc. Plantroom 2.00 5.00
Conc. Floor slab & swimming pool base 2.00 10.00
Blockwork 2.00 9.00
Conc. Swimming pool sides & overflow channels 3.00 7.00
Conc. Ring & tie beams 2.00 7.00

page 71
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

4.4.2.2. Villa Type B2 (Example)

Villa Type Item Unit Tender Quantity Design Quantities


B2 Frame
Reinforcement kg 5,826.00 9,645.00
Concrete m3 84.00 102.00
Formwork m2 727.00 730.00

Baseline duration based on Tender Quantity 70 Days


Actual Duration due to increased quantity 80 Days

B2 Type Frame Baseline Duration Revised Duration

set kickers 1.00 2.00


Conc. Columns & shear walls to GF 8.00 6.00
Conc. Plantrooms 6.00 8.00
Conc. GF slab and beams 4.00 10.00
Blockwork up to FF slab 7.00 6.00
set kickers on GF 1.00 2.00
Conc. Columns & shear walls to FF 8.00 8.00
Conc. FF slab & beams 8.00 10.00
Blockwork up to roof 7.00 6.00
set kickers on FF 1.00 2.00
Conc. Columns & shear walls to roof 8.00 8.00
Conc. Ring & tie beams 7.00 7.00

In the circumstances, these variations dictate significant


divergence from original designs. Therefore, in order to comply
with these variations the Contractor’s construction duration for
this activity has increased significantly, from an estimated 17
days (substructure) to 37 days for column construction, an
increase of 22 working days for each villa.

4.4.3.Suspension of Works
The Contractor was instructed to suspend the works, which
suspension lasted 61 days and directly effected progress of the
villas listed. This period of suspension is considered a critical
delay.

The following table summarises the delay at each villa in


progress at the time of the instruction to suspend. However, it
should be noted that the effect of this instruction is to delay all
the Works on the whole project (except mock-up villas for this
particular event).

page 72
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

Villa Works Suspended From To Delay (Days)


A3/03 Excavation 29-Aug-07 29-Oct-07 61.00
A3/04 Concrete foundation 29-Aug-07 29-Oct-07 61.00
A3/05 Concrete foundation 29-Aug-07 29-Oct-07 61.00
A3/06 Excavation 29-Aug-07 29-Oct-07 61.00
A3/08 Excavation 29-Aug-07 29-Oct-07 61.00
A3/10 Concrete casting for foundation 29-Aug-07 29-Oct-07 61.00
A3/27 Excavation 29-Aug-07 29-Oct-07 61.00
A3/28 Excavation 29-Aug-07 29-Oct-07 61.00
A3/29 Concrete works 29-Aug-07 29-Oct-07 61.00
A3/30 Blinding 29-Aug-07 29-Oct-07 61.00
A3/31 Blinding 29-Aug-07 29-Oct-07 61.00
B2/02 Excavation 29-Aug-07 29-Oct-07 61.00

4.4.4.Variations to Design
The design drawings issued for construction show all steel roof
members as stainless steel although the bill of quantities, as
priced at tender, show galvanised steel. As a result the sourcing
and procurement time consumed an additional 81 calendar
days. This delayed roof construction at the 2 Mock-up Villas and
is considered a critical delay.

Description Commenced Completion Delay (Days)


Procurement, Fabrication & Installation of Stainless
Steel Plates to complete roof structure 26-Nov-07 15-Feb-08 81

4.5. Material Procurement Programme


A critical feature of this project is timely supply of materials to
site as most are being sourced off-shore. The timely arrival of
materials is an integral part of his planning and any delay in the
design and procurement process will automatically have a
detrimental impact on his programme of works.

The current situation relative major material procurement is


shown in the table below:

page 73
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
Q uantity
Des c ription of Materials Ordered Date O rdered Amount rec eived B alanc e C omments

F OR AL L 55 VIL L AS

50K G bags P ortland C ement 2,800.00 04/04/07 300.00 2,500.00 B alance on order s ubject to payment to s upplier
P lywood for S huttering/R oofing 6,000.00 14/11/07 1,800.00 4,200.00 B alance on order s ubject to payment to s upplier
C rus her D us t 6,000.00 23/06/07 1,565.13 4,434.87 B alance on order s ubject to payment to s upplier
Aggregate 8,000.00 25/06/07 1,222.64 6,777.36 B alance on order s ubject to payment to s upplier
P las tering S and 1,000.00 16/07/07 80.00 920.00 B alance on order s ubject to payment to s upplier
150mm S oild concrete B locks 125,000.00 05/07/07 31,975.00 93,025.00 B alance on order s ubject to payment to s upplier
100mm Hollow concrete B locks 15,000.00 15/07/07 2,340.00 12,660.00 B alance on order s ubject to payment to s upplier
A252 W eld Mes h (R oadworks ) 912.00 14/05/07 162.00 750.00 B alance on order s ubject to payment to s upplier
High tens ile s teel-8,10,12,16,25mm (tons ) 500.00 14/01/07 158.00 342.00 B alance on order s ubject to payment to s upplier
C edar S hingles (s qm) 12,757.64 03/05/07 3,712.00 9,045.64 B alance on order s ubject to payment to s upplier
Iroko timber (external cladding) L M 54,198.00 07/05/07 1,548.00 52,650.00 B alance on order s ubject to payment to s upplier
12mm G yps um boards (S H E E T S ) 5,600.00 03/02/07 5,600.00 0.00 Awaiting for other building from I.D
S tainles s s teel threaded rods 12,16mm 16,300.00 09/11/07 8,110.00 8,190.00 B alance on order s ubject to payment to s upplier (Not B .O .Q item)
S tainles s s teel gus s et plates (variation) 450.00 09/11/07 50.00 400.00 B alance on order s ubject to payment to s upplier (Not B .O .Q item)
B alau T imber (L M) 169,074.50 08/06/07 6,148.16 162,926.34 B alance on order s ubject to payment to s upplier
T reated P ine T imber (L M) 94,148.50 20/04/07 43,225.50 50,923.00 B alance on order s ubject to payment to s upplier

The following table summarises the dates drawings have been


received. It is clear many drawings were not issued at
commencement and therefore, complete procurement of all
major materials was not possible.

It is also clear that drawings have been issued progressively


throughout the Contract period; again this is contrary to planning
expectations. Finally, it is also clear the majority of Interior
Design drawings have yet to be issued.

Item Structure/Villa Drawing Receipt Register


Structural Architectural Interior Design

1 A3 Pool Villa 14-Mar-07 09-Mar-07 09-Apr-07


2 B223 Standard Villa 14-Mar-07 09-Mar-07 09-Apr-07
3 B4 Standard Villa with Pool 14-Mar-07 09-Mar-07 09-Apr-07
4 C311 Executive Villas 14-Mar-07 09-Mar-07 09-Apr-07
5 P3 Presidential Villas 19-Oct-07 09-Mar-07 09-Apr-07
6 Sunset Deck 09-Apr-08 22-Aug-07 Not received
7 Employees Facilities Complex 31-Aug-07 22-Aug-07 "
8 Excom Villa 19-Oct-07 22-Aug-07 "
9 GM Villa 19-Oct-07 22-Aug-07 "
10 Health club 11-Jun-07 28-May-07 "
11 Single Treatment room 10-Jun-07 28-May-07 "
12 Couple treatment room 25-Jun-07 28-May-07 "
13 Sanctum 19-Oct-07 28-May-07 "
14 Yoga Pavilion 19-Oct-07 28-May-07 "
15 BOH Building 19-Oct-07 28-May-07 "
16 Wedding chapel 09-Apr-08 28-May-07 "
17 Seafood Resort 11-Jun-07 28-May-07 "
18 Retail Pavilion 11-Jun-07 28-May-07 "
19 Kid's club 20-Dec-07 08-Jan-08 "
20 Recreation House 20-Dec-07 08-Jan-08 "
21 Water sport Rental 20-Dec-07 08-Jan-08 "
22 Dive Center 20-Dec-07 08-Jan-08 "
23 Mechanical Area Not Received Yet 08-Jan-08 "
24 3 Meal Restaurant Not Received Yet 08-Jan-08 "
25 Signature Pool Not Received Yet 08-Jan-08 "
26 Beach Pool Bar Not Received Yet 08-Jan-08 "

page 74
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

For all the foregoing reasons stated above, the Contractor could
not have progressed major material procurement because he
was constrained by two issues:

1. Cash flow prevented completion of


orders to allow shipment, and

2. Design drawings were not available


at the times consistent with his
programme of works.

4.6. Conclusion of Effects of Variations


Additional work is, under the Contract provisions, is also caused
by Provisional Sums converted to Variations under Clause 13,
by comparison with the value of work envisaged at tender.
Nevertheless, additional work executed to date is certain to
affect progress because the scope of such variations has only
been defined post tender.

The degree of change reflects the changed requirements of the


Employer after the award of the project. Although the Contractor
received instructions throughout the project to include work
anticipated under the Provisional Sums, this has been
compounded by the delaying events described even for known
works defined at award.

With so many variations, it is not possible to make an attribution


of the overall delay to each item. It is true to say that the earlier
variations were critical to the Contractor’s progress, and that any
delays caused by them are subsumed into the latter period.

However, the delays caused by the changes to the setting out


and rock excavation together with suspension of Works, and to
other areas of the Works as all the design information, as listed
in the tables above, are evident and the primary cause for
remaining on site longer.

All the issues described above generally run consecutively,


despite late information relative design is continuing
simultaneously together with rock excavation. The factual matrix
of variation instructions and late information is one of interwoven
facts and events. It is not possible to disconnect them. However,
the latest programme of works is evidence that work to most of
the buildings and villas is in progress at the time of compiling
this claim.

page 75
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

5. Time Analysis

5.1. Method of Analysis


As some of the effects of unforeseen events are concurrent, not
all of them will carry an automatic extension of time entitlement.
The purpose of the form of analysis described below is to
demonstrate which events have contributed to the project over-
run and the precise amount of time attributable to each event. At
time of preparing this document a Second Request for an
Extension of Time has been submitted.

Furthermore, additional costs have arisen as a result of various


notified delay and disruption events. The loss and expense are
recoverable as:

 direct costs in the period when resources suffered delay


and disruption, and

 indirect costs that will arise in the extended period of the


Contract.

The time analysis has been carried out in three stages for each
claimable event:

1. At the date immediately prior to the event, the progress


status of the project has been established from the
progress records. The Programme of Works has been
updated with this information, to give a project completion
date that was likely to have been achieved if the delay
had not occurred. This element of the analysis takes into
account and eliminates any delays that might have
occurred before the point in time in question, for which
the Contractor might be responsible.

2. Next, the effect of the claimable event on the scheduled


activities has been calculated. These effects have been
inserted into the time scheduled and the network re-
analysed. This gives a revised project completion date,
assuming that the work proceeds in the same sequence
and with the same resources as were originally planned.
The difference between this completion date and the
progress completion date is the extension of time for the
event if it is not reasonably possible to achieve any
mitigation of its delaying impact.

3. Finally, there is an obligation on a contractor to attempt to


mitigate the effects of any delaying event, if it is
reasonably feasible. Accordingly, such opportunities for

page 76
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

mitigation have been considered in the evaluation of


extension of time entitlement.

Any mitigation measures that the Contractor took, such


as additional resources, re-sequencing of work etc., has
been detailed and inserted into the schedule. The re-
analysis of this programme gives the final assessment of
additional time that the Contractor is entitled to claim for
the cause under consideration.

These three stages have been repeated for each of the events
in turn and the results are reflected in the Contractor’s two
requests made to date for an extension of time.

5.1.1.Mitigation by Contractor
The Contractor mitigated the effects of the late supply of design
information by starting work on a particular activity without
waiting for the whole of the design needed for a particular piece
of work. This was particularly noticeable at the Mock-up villas
where architectural details were constantly revised as works
progressed. The success in taking this phase-advanced
approach to work has not produced the results anticipated.

These mitigation measures will be shown in the Programme of


Works analysis by changing the logic links between design
activities and construction activities.

5.1.2.Time for Completion


It is shown in the subsequent sections of this submission the
impact of the changed events and circumstances of the various
parts of the Site has caused to the planned progress. In
addition, the failure by the Project Manager to provide the
necessary design details in due time and the subsequent
alterations in mode and manner of execution has also caused
the Contractor, because of these events, to be delayed to such
an extent that completion of the Contract Works has been
unavoidably prolonged and will extend the date set for its
completion.

Accordingly, the Contractor is entitled to treat the date for


completion as no longer being fixed. That is to say, he is entitled
to be allowed such additional time for completion as is
reasonably necessary for him to accommodate and deal with the

page 77
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

Project Manager’s and Employer’s fault to discharge the


remainder of his obligations.

5.1.3.Impact on Time - Analyses


The purpose of this exercise is to determine the overall delay to
the contractual completion date as indicated in the approved
base programme of works. The impacted programme of works
will establish the contractor’s entitlement to a delayed
completion date for the project. This can then be used to
evaluate the financial loss incurred by the contractor and the
amount of acceleration required in the event that the client
requires the project to be completed earlier.

Events are impacted on the programme according to


chronological order to determine the effect in the sequence that
the delays took place. When the Event is impacted correctly only
the activity is affected and those which are dependent on its
completion are delayed. If this activity falls in the critical path of
the project then the completion date of the project is also
delayed. The critical path of a project may change due to delay
in a particular set of activities.

5.1.4.The Events that Impacted Progress


There has been initial delay in receipt of final setting out details
for various parts of the project without which it was not possible
for the contractor to start construction of that relevant section of
the works. Additionally it will be seen that unforeseen ground
conditions, the partial suspension of Works caused severe
disruption to the contractors planned sequence of execution of
the works. Initial events impacted will show the effect that these
delays had on the execution of the works.

Furthermore there has been a substantial change to the scope


of works as originally anticipated as shown on drawings and
what the Contractor encountered on site. A significant variance
is attributed to unknown site conditions, as for example, quantity
of rock excavated required achieving foundation depth.

The rest of the changes will be attributed to changes in original


design other than depicted on tender drawings such as the
increased quantities of reinforced concrete. Needless to say the
extra volume requires more time to secure placement of steel
reinforcement, timber shuttering and concrete placement to
columns and slabs, hence more time being required to

page 78
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

completion of activity and an overall delay experienced on this


section.

The overall effect of these delays and disruptions can be


evidenced by a reduced cash flow, and by his current position
on site with regards completion of the works. It can be clearly
evidenced that not only has the contractor taken steps to
mitigate the delays experienced he has also in his eagerness to
recover lost time already taken acceleration measures into
account and deployed extra resources over and above his
planned and contractually required resources.

This exercise serves to establish the contractor’s entitlement to


additional time for completion of the project and the cause and
effect on his progress to date.

The order of the impacted charts that follow are in the sequence
each event occurred at Site.

page 79
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

5.1.4.1. Event No 1 – Setting Out


ID Task Name
2007 2008
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1 SHANGRI-LA , Long Island Resort Seychelles 0%
2 General Conditions and Preliminaries 0%
17 Site establishment 0%
41 Material/equipment procurement 0%
182 Lot 1 0%
183 A3 Villas ( 6 nos) 0%
184 Villa A3/01 0%
228 Villa A3/02 0%
273 Villa A3/03 0%
318 Villa A3/04 0%
363 Villa A3/05 0%
408 Villa A3/06 0%
453 C311 Executive Villas ( 1 nos) 0%
454 Villa C3/01 0%
497 GM Villa ( subject to receipt of GFW drawings) 0%
537 Employees Facilities ( subject to receipt of GFW drawings) 0%
581 Laundry F& B service office ( subject to receipt of GFW drawings) 0%
625 Health Club/ Medical Centre( subject to receipt of GFW drawings) 0%
666 Administration Block ( subject to receipt of GFW drawings) 0%
707 1 bedroom Villa ( Excom, 6 units)( subject to receipt of GFW drawings) 0%
750 Main Lobby ( subject to receipt of GFW drawings) 0%
791 Tennis Courts ( subject to receipt of GFW drawings) 0%
807 External works ( subject to receipt of GFW drawings) 0%
816 Drainage works ( subject to receipt of EME details) 0%
819 Fuel Farm ( subject to receipt of EME details) 0%
823 Sea water Storage Tank & Water Tanks( subject to receipt of EME details) 0%
827 Desalination plant( subject to receipt of EME details) 0%
831 MLV Panel( subject to receipt of EME details) 0%
835 Step Up Transformer( subject to receipt of EME details) 0%
839 Incinerator/ Garbage room( subject to receipt of EME details) 0%
843 Sewer treatement plant( subject to receipt of EME details) 0%
847 Lot 2 0%
848 A3 Villas (17 nos) 0%
849 Villa A3/07 0%
850 substructure 0%
851 set out 0%
852 Excavate 0%
853 Conc. Foundation 0%
854 Backfill 0%
855 termite treatment 0%
856 DPC (where applicable) 0%
857 M&E inlet/outlet works - first fix 0%
858 frame 0%
859 set kickers 0%
860 Conc. Columns & shear walls 0%
861 Conc. G. F Beams 0%
862 M&E first fix 0%
863 Conc. Plantroom 0%
864 Conc. Floor slab & swimming pool base 0%
865 Blockwork 0%
866 Conc. Swimming pool sides & overflow channels 0%
867 Conc. Ring & tie beams 0%
868 Roof & Ceiling 0%
869 Fix wall plate & truss 0%
870 Fix purlins and rafters 0%
871 Fix shingles ( subject to receipt of timber) 0%
872 Fix ceiing battens & joists 0%
873 Fix ceiling boards 0%
874 M&E first fix 0%
875 Finishes 0%
876 Wall plaster (internal & External) 0%
877 M&E 1st fix 0%
878 Floor finishes 0%
879 Fix windows & doors 0%
880 Swimming pool finishes 0%
881 M&E final fix 0%
882 Fix fittings and Fixtures 0%
883 M&E Installations 0%
884 Cable Tray, Conduit and Wiring 0%
885 Electrical boards and connections 0%
886 Electrical accessories 0%
887 Light fittings and ceiling fans 0%
888 Hot and cold water 0%
889 Waste and sewage incl. biobox 0%
890 Electric water heater 0%
891 Swimming pool 0%
892 Split unit installation 0%
893 Toilet ventilation, grilles 0%
894 Villa A3/08 0%
939 Villa A3/09 0%
984 Villa A3/10( mock up) 0%
1029 Villa A3/11 0%
1030 substructure 0%
1031 set out 0%
1032 Excavate 0%
1033 Conc. Foundation 0%
1034 Backfill 0%
1035 termite treatment 0%
1036 DPC (where applicable) 0%
1037 M&E inlet/outlet works - first fix 0%
1038 frame 0%
1039 set kickers 0%
1040 Conc. Columns & shear walls 0%
1041 Conc. G. F Beams 0%
1042 M&E first fix 0%
1043 Conc. Plantroom 0%
1044 Conc. Floor slab & swimming pool base 0%
1045 Blockwork 0%
1046 Conc. Swimming pool sides & overflow channels 0%
1047 Conc. Ring & tie beams 0%
1048 Roof & Ceiling 0%
1049 Fix wall plate & truss 0%
1050 Fix purlins and rafters 0%
1051 Fix shingles ( subject to receipt of timber) 0%
1052 Fix ceiing battens & joists 0%
1053 Fix ceiling boards 0%
1054 M&E first fix 0%

page 80
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2007 2008 20
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
1055 Finishes 0%
1056 Wall plaster (internal & External) 0%
1057 M&E 1st fix 0%
1058 Floor finishes 0%
1059 Fix windows & doors 0%
1060 Swimming pool finishes 0%
1061 M&E final fix 0%
1062 Fix fittings and Fixtures 0%
1063 M&E Installations 0%
1064 Cable Tray, Conduit and Wiring 0%
1065 Electrical boards and connections 0%
1066 Electrical accessories 0%
1067 Light fittings and ceiling fans 0%
1068 Hot and cold water 0%
1069 Waste and sewage incl. biobox 0%
1070 Electric water heater 0%
1071 Swimming pool 0%
1072 Split unit installation 0%
1073 Toilet ventilation, grilles 0%
1074 Villa A3/12 0%
1119 Villa A3/13 0%
1164 Villa A3/18 0%
1209 Villa A3/19 0%
1254 Villa A3/20 0%
1255 substructure 0%
1256 set out 0%
1257 Excavate 0%
1258 Conc. Foundation 0%
1259 Backfill 0%
1260 termite treatment 0%
1261 DPC (where applicable) 0%
1262 M&E inlet/outlet works - first fix 0%
1263 frame 0%
1264 set kickers 0%
1265 Conc. Columns & shear walls 0%
1266 Conc. G. F Beams 0%
1267 M&E first fix 0%
1268 Conc. Plantroom 0%
1269 Conc. Floor slab & swimming pool base 0%
1270 Blockwork 0%
1271 Conc. Swimming pool sides & overflow channels 0%
1272 Conc. Ring & tie beams 0%
1273 Roof & Ceiling 0%
1274 Fix wall plate & truss 0%
1275 Fix purlins and rafters 0%
1276 Fix shingles ( subject to receipt of timber) 0%
1277 Fix ceiing battens & joists 0%
1278 Fix ceiling boards 0%
1279 M&E first fix 0%
1280 Finishes 0%
1281 Wall plaster (internal & External) 0%
1282 M&E 1st fix 0%
1283 Floor finishes 0%
1284 Fix windows & doors 0%
1285 Swimming pool finishes 0%
1286 M&E final fix 0%
1287 Fix fittings and Fixtures 0%
1288 M&E Installations 0%
1289 Cable Tray, Conduit and Wiring 0%
1290 Electrical boards and connections 0%
1291 Electrical accessories 0%
1292 Light fittings and ceiling fans 0%
1293 Hot and cold water 0%
1294 Waste and sewage incl. biobox 0%
1295 Electric water heater 0%
1296 Swimming pool 0%
1297 Split unit installation 0%
1298 Toilet ventilation, grilles 0%
1299 Villa A3/21 0%
1344 Villa A3/22 0%
1389 Villa A3/23 0%
1434 Villa A3/24 0%
1479 Villa A3/25 0%
1524 Villa A3/26 0%
1569 Villa A3/27 0%
1614 B223 Villas ( 7 nos) 0%
1615 Villa B2/01 0%
1665 Villa B2/02 0%
1715 Villa B2/04 (mock up villa) 0%
1765 Villa B2/05 0%
1815 Villa B2/06 0%
1865 Villa B2/07 0%
1915 Villa B2/08 0%
1965 B4 Villa (2 nos.) 0%
1966 Villa B4/01 0%
2011 Villa B4/02 0%
2056 Retail 1( subject to receipt of GFW drawings) 0%
2094 Retail 2( subject to receipt of GFW drawings) 0%
2132 Retail 3( subject to receipt of GFW drawings) 0%
2170 Seafood resort( subject to receipt of GFW drawings) 0%
2211 Greeting Pavillion( subject to receipt of GFW drawings) 0%
2250 External works ( subject to receipt of GFW drawings) 0%
2259 Drainage works ( subject to receipt of EME details) 0%
2262 Lot 3 0%
2263 A3 Villas ( 9 nos) 0%
2264 Villa A3/14 0%
2309 Villa A3/15 0%
2354 Villa A3/16 0%
2399 Villa A3/17 0%
2444 Villa A3/28 0%
2489 Villa A3/29 0%
2534 Villa A3/30 0%
2535 substructure 0%
2536 set out 0%
2537 Excavate 0%
2538 Conc. Foundation 0%
2539 Backfill 0%
2540 termite treatment 0%
2541 DPC (where applicable) 0%
2542 M&E inlet/outlet works - first fix 0%

page 81
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2007 2008 2009
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
2543 frame 0%
2544 set kickers 0%
2545 Conc. Columns & shear walls 0%
2546 Conc. G. F Beams 0%
2547 M&E first fix 0%
2548 Conc. Plantroom 0%
2549 Conc. Floor slab & swimming pool base 0%
2550 Blockwork 0%
2551 Conc. Swimming pool sides & overflow channels 0%
2552 Conc. Ring & tie beams 0%
2553 Roof & Ceiling 0%
2554 Fix wall plate & truss 0%
2555 Fix purlins and rafters 0%
2556 Fix shingles ( subject to receipt of timber) 0%
2557 Fix ceiing battens & joists 0%
2558 Fix ceiling boards 0%
2559 M&E first fix 0%
2560 Finishes 0%
2561 Wall plaster (internal & External) 0%
2562 M&E 1st fix 0%
2563 Floor finishes 0%
2564 Fix windows & doors 0%
2565 Swimming pool finishes 0%
2566 M&E final fix 0%
2567 Fix fittings and Fixtures 0%
2568 M&E Installations 0%
2569 Cable Tray, Conduit and Wiring 0%
2570 Electrical boards and connections 0%
2571 Electrical accessories 0%
2572 Light fittings and ceiling fans 0%
2573 Hot and cold water 0%
2574 Waste and sewage incl. biobox 0%
2575 Electric water heater 0%
2576 Swimming pool 0%
2577 Split unit installation 0%
2578 Toilet ventilation, grilles 0%
2579 Villa A3/31 0%
2624 Villa A3/32 0%
2664 B223 Villas ( 3 nos) 0%
2665 Villa B2/03 0%
2708 Villa B2/09 0%
2758 Villa B2/10 0%
2808 B4 Standard Villas ( 2 nos) 0%
2809 Villa B4/03 0%
2854 Villa B4/04 0%
2899 BC311 Executive Villa 0%
2900 Villa C3/02 0%
2943 Villa C3/03 0%
2986 Villa C3/04 0%
3029 Villa C3/05 0%
3072 Villa C3/06 0%
3115 P3 Presidential suites ( 3 nos) 0%
3116 Villa P3/01 0%
3159 Villa P3/02 0%
3202 Villa P3/03 0%
3245 Hilltop sunset deck( subject to receipt of GFW drawings) 0%
3280 External works ( subject to receipt of GFW drawings) 0%
3289 Drainage works ( subject to receipt of EME details) 0%
3292 Lot 4 0%
3293 Couple treatment room( subject to receipt of GFW drawings) 0%
3334 Single treatment room( subject to receipt of GFW drawings) 0%
3375 Dive Centre( subject to receipt of GFW drawings) 0%
3413 Kid's club( subject to receipt of GFW drawings) 0%
3452 Recreation House( subject to receipt of GFW drawings) 0%
3491 Watersports rental( subject to receipt of GFW drawings) 0%
3529 3 Meals restaurant( subject to receipt of GFW drawings) 0%
3570 Beach Pool Bar( subject to receipt of GFW drawings) 0%
3611 Signature Pool area( subject to receipt of GFW drawings) 0%
3650 Wedding Chapel( subject to receipt of GFW drawings) 0%
3685 BOH/Admin Building( subject to receipt of GFW drawings) 0%
3726 Chi Sanctum( subject to receipt of GFW drawings) 0%
3767 Yoga Pavillion( subject to receipt of GFW drawings) 0%
3805 External works ( subject to receipt of GFW drawings) 0%
3814 Drainage works ( subject to receipt of EME details) 0%
3817 M&E Installations- External 0%
3828 Sundries 0%
3829 Site cleaning & demobilisation 0%
3830 Project Commissioning 0%

The following table provides a summary of the delay caused by


late setting out at each of the buildings.
Impacted Programme Baseline Programme
Villa commencement completion commencement completion Baseline duration Revised Duration
A3/07 25-Apr-07 07-Jan-08 02-Apr-07 12-Nov-07 224.08 257.08
A3/11 09-Apr-07 02-Jun-08 09-Apr-07 15-Mar-08 341.13 420.08
A3/20 25-Apr-07 23-Jun-08 12-Apr-07 15-Mar-08 338.13 425.08
A3/30 25-Apr-07 29-Mar-08 28-May-07 15-Mar-08 292.13 339.13

As a result of this delaying event the time for completion has


been extended from 16 May 2008 to 9 August 2008, a period of
85 calendar days.

page 82
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

5.1.4.2. Event No 2 – Unforeseen Ground Conditions


ID Task Name
2007 2008 2009
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1 SHANGRI-LA , Long Island Resort Seychelles 0%
2 General Conditions and Preliminaries 0%
17 Site establishment 0%
41 Material/equipment procurement 0%
182 Lot 1 0%
183 A3 Villas ( 6 nos) 0%
184 Villa A3/01 0%
185 Substructure 0%
186 set out 0%
187 Excavate 0%
188 Conc. Foundation 0%
189 Backfill 0%
190 termite treatment 0%
191 DPC (where applicable) 0%
192 M&E inlet/outlet works - first fix 0%
193 Frame 0%
203 Roof & Ceiling 0%
210 Finishes 0%
217 M&E Installations 0%
228 Villa A3/02 0%
229 substructure 0%
230 set out 0%
231 Excavate 0%
232 Conc. Foundation 0%
233 Backfill 0%
234 termite treatment 0%
235 DPC (where applicable) 0%
236 M&E inlet/outlet works - first fix 0%
237 frame 0%
247 Roof & Ceiling 0%
254 Finishes 0%
262 M&E Installations 0%
273 Villa A3/03 0%
274 substructure 0%
275 set out 0%
276 Excavate 0%
277 Conc. Foundation 0%
278 Backfill 0%
279 termite treatment 0%
280 DPC (where applicable) 0%
281 M&E inlet/outlet works - first fix 0%
282 frame 0%
292 Roof & Ceiling 0%
299 Finishes 0%
307 M&E Installations 0%
318 Villa A3/04 0%
363 Villa A3/05 0%
408 Villa A3/06 0%
409 substructure 0%
410 set out 0%
411 Excavate 0%
412 Conc. Foundation 0%
413 Backfill 0%
414 termite treatment 0%
415 DPC (where applicable) 0%
416 M&E inlet/outlet works - first fix 0%
417 frame 0%
427 Roof & Ceiling 0%
434 Finishes 0%
442 M&E Installations 0%
453 C311 Executive Villas ( 1 nos) 0%
497 GM Villa ( subject to receipt of GFW drawings) 0%
537 Employees Facilities ( subject to receipt of GFW drawings) 0%
581 Laundry F& B service office ( subject to receipt of GFW drawings) 0%
625 Health Club/ Medical Centre( subject to receipt of GFW drawings) 0%
666 Administration Block ( subject to receipt of GFW drawings) 0%
707 1 bedroom Villa ( Excom, 6 units)( subject to receipt of GFW drawings) 0%
750 Main Lobby ( subject to receipt of GFW drawings) 0%
791 Tennis Courts ( subject to receipt of GFW drawings) 0%
807 External works ( subject to receipt of GFW drawings) 0%
816 Drainage works ( subject to receipt of EME details) 0%
819 Fuel Farm ( subject to receipt of EME details) 0%
823 Sea water Storage Tank & Water Tanks( subject to receipt of EME details) 0%
827 Desalination plant( subject to receipt of EME details) 0%
831 MLV Panel( subject to receipt of EME details) 0%
835 Step Up Transformer( subject to receipt of EME details) 0%
839 Incinerator/ Garbage room( subject to receipt of EME details) 0%
843 Sewer treatement plant( subject to receipt of EME details) 0%
847 Lot 2 0%
848 A3 Villas (17 nos) 0%
849 Villa A3/07 0%
894 Villa A3/08 0%
895 substructure 0%
896 set out 0%
897 Excavate 0%
898 Conc. Foundation 0%
899 Backfill 0%
900 termite treatment 0%
901 DPC (where applicable) 0%
902 M&E inlet/outlet works - first fix 0%
903 frame 0%
913 Roof & Ceiling 0%
920 Finishes 0%
928 M&E Installations 0%
939 Villa A3/09 0%
940 substructure 0%
941 set out 0%
942 Excavate 0%
943 Conc. Foundation 0%
944 Backfill 0%
945 termite treatment 0%
946 DPC (where applicable) 0%
947 M&E inlet/outlet works - first fix 0%
948 frame 0%
958 Roof & Ceiling 0%
965 Finishes 0%
973 M&E Installations 0%

page 83
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2007 2008 2009 2010
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
984 Villa A3/10 0%
985 substructure 0%
986 set out 0%
987 Excavate 0%
988 Conc. Foundation 0%
989 Backfill 0%
990 termite treatment 0%
991 DPC (where applicable) 0%
992 M&E inlet/outlet works - first fix 0%
993 frame 0%
1003 Roof & Ceiling 0%
1010 Finishes 0%
1018 M&E Installations 0%
1029 Villa A3/11 0%
1030 substructure 0%
1031 set out 0%
1032 Excavate 0%
1033 Conc. Foundation 0%
1034 Backfill 0%
1035 termite treatment 0%
1036 DPC (where applicable) 0%
1037 M&E inlet/outlet works - first fix 0%
1038 frame 0%
1048 Roof & Ceiling 0%
1055 Finishes 0%
1063 M&E Installations 0%
1074 Villa A3/12 0%
1119 Villa A3/13 0%
1164 Villa A3/18 0%
1209 Villa A3/19 0%
1210 substructure 0%
1211 set out 0%
1212 Excavate 0%
1213 Conc. Foundation 0%
1214 Backfill 0%
1215 termite treatment 0%
1216 DPC (where applicable) 0%
1217 M&E inlet/outlet works - first fix 0%
1218 frame 0%
1228 Roof & Ceiling 0%
1235 Finishes 0%
1243 M&E Installations 0%
1254 Villa A3/20 0%
1255 substructure 0%
1256 set out 0%
1257 Excavate 0%
1258 Conc. Foundation 0%
1259 Backfill 0%
1260 termite treatment 0%
1261 DPC (where applicable) 0%
1262 M&E inlet/outlet works - first fix 0%
1263 frame 0%
1273 Roof & Ceiling 0%
1280 Finishes 0%
1288 M&E Installations 0%
1299 Villa A3/21 0%
1300 substructure 0%
1301 set out 0%
1302 Excavate 0%
1303 Conc. Foundation 0%
1304 Backfill 0%
1305 termite treatment 0%
1306 DPC (where applicable) 0%
1307 M&E inlet/outlet works - first fix 0%
1308 frame 0%
1318 Roof & Ceiling 0%
1325 Finishes 0%
1333 M&E Installations 0%
1344 Villa A3/22 0%
1389 Villa A3/23 0%
1434 Villa A3/24 0%
1479 Villa A3/25 0%
1524 Villa A3/26 0%
1525 substructure 0%
1526 set out 0%
1527 Excavate 0%
1528 Conc. Foundation 0%
1529 Backfill 0%
1530 termite treatment 0%
1531 DPC (where applicable) 0%
1532 M&E inlet/outlet works - first fix 0%
1533 frame 0%
1543 Roof & Ceiling 0%
1550 Finishes 0%
1558 M&E Installations 0%
1569 Villa A3/27 0%
1570 substructure 0%
1571 set out 0%
1572 Excavate 0%
1573 Conc. Foundation 0%
1574 Backfill 0%
1575 termite treatment 0%
1576 DPC (where applicable) 0%
1577 M&E inlet/outlet works - first fix 0%
1578 frame 0%
1588 Roof & Ceiling 0%
1595 Finishes 0%
1603 M&E Installations 0%
1614 B223 Villas ( 7 nos) 0%
1615 Villa B2/01 0%
1616 substructure 0%
1617 set out 0%
1618 Excavate 0%
1619 Conc. Foundation 0%
1620 Backfill 0%
1621 termite treatment 0%
1622 DPC (where applicable) 0%
1623 M&E inlet/outlet works - first fix 0%
1624 frame 0%
1640 Roof & Ceiling 0%
1647 Finishes 0%
1654 M&E Installations 0%

page 84
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2007 2008 2009 2010
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
1665 Villa B2/02 0%
1666 substructure 0%
1667 set out 0%
1668 Excavate 0%
1669 Conc. Foundation 0%
1670 Backfill 0%
1671 termite treatment 0%
1672 DPC (where applicable) 0%
1673 M&E inlet/outlet works - first fix 0%
1674 frame 0%
1690 Roof & Ceiling 0%
1697 Finishes 0%
1704 M&E Installations 0%
1715 Villa B2/04 0%
1716 substructure 0%
1717 set out 0%
1718 Excavate 0%
1719 Conc. Foundation 0%
1720 Backfill 0%
1721 termite treatment 0%
1722 DPC (where applicable) 0%
1723 M&E inlet/outlet works - first fix 0%
1724 frame 0%
1740 Roof & Ceiling 0%
1747 Finishes 0%
1754 M&E Installations 0%
1765 Villa B2/05 0%
1766 substructure 0%
1767 set out 0%
1768 Excavate 0%
1769 Conc. Foundation 0%
1770 Backfill 0%
1771 termite treatment 0%
1772 DPC (where applicable) 0%
1773 M&E inlet/outlet works - first fix 0%
1774 frame 0%
1790 Roof & Ceiling 0%
1797 Finishes 0%
1804 M&E Installations 0%
1815 Villa B2/06 0%
1816 substructure 0%
1817 set out 0%
1818 Excavate 0%
1819 Conc. Foundation 0%
1820 Backfill 0%
1821 termite treatment 0%
1822 DPC (where applicable) 0%
1823 M&E inlet/outlet works - first fix 0%
1824 frame 0%
1840 Roof & Ceiling 0%
1847 Finishes 0%
1854 M&E Installations 0%
1865 Villa B2/07 0%
1866 substructure 0%
1867 set out 0%
1868 Excavate 0%
1869 Conc. Foundation 0%
1870 Backfill 0%
1871 termite treatment 0%
1872 DPC (where applicable) 0%
1873 M&E inlet/outlet works - first fix 0%
1874 frame 0%
1890 Roof & Ceiling 0%
1897 Finishes 0%
1904 M&E Installations 0%
1915 Villa B2/08 0%
1916 substructure 0%
1917 set out 0%
1918 Excavate 0%
1919 Conc. Foundation 0%
1920 Backfill 0%
1921 termite treatment 0%
1922 DPC (where applicable) 0%
1923 M&E inlet/outlet works - first fix 0%
1924 frame 0%
1940 Roof & Ceiling 0%
1947 Finishes 0%
1954 M&E Installations 0%
1965 B4 Villa (2 nos.) 0%
1966 Villa B4/01 0%
1967 substructure 0%
1968 set out 0%
1969 Excavate 0%
1970 Conc. Foundation 0%
1971 Backfill 0%
1972 termite treatment 0%
1973 DPC (where applicable) 0%
1974 M&E inlet/outlet works - first fix 0%
1975 frame 0%
1976 set kickers 0%
1977 Conc. Columns & shear walls 0%
1978 Conc. G. F Beams 0%
1979 M&E first fix 0%
1980 Conc. Plantroom 0%
1981 Conc. Floor slab & swimming pool base 0%
1982 Blockwork 0%
1983 Conc. Swimming pool sides & overflow channels 0%
1984 Conc. Ring & tie beams 0%
1985 Roof & Ceiling 0%
1986 Fix wall plate & truss 0%
1987 Fix purlins and rafters 0%
1988 Fix shingles ( subject to receipt of timber) 0%
1989 Fix ceiing battens & joists 0%
1990 Fix ceiling boards 0%
1991 M&E first fix 0%
1992 Finishes 0%
1993 Wall plaster (internal & External) 0%
1994 M&E 1st fix 0%
1995 Floor finishes 0%
1996 Fix windows & doors 0%
1997 Swimming pool finishes 0%
1998 M&E final fix 0%
1999 Fix fittings and Fixtures 0%

page 85
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2007 2008 2009 2010
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
2000 M&E Installations 0%
2001 Cable Tray, Conduit and Wiring 0%
2002 Electrical boards and connections 0%
2003 Electrical accessories 0%
2004 Light fittings and ceiling fans 0%
2005 Hot and cold water 0%
2006 Waste and sewage incl. biobox 0%
2007 Electric water heater 0%
2008 Swimming pool 0%
2009 Split unit installation 0%
2010 Toilet ventilation, grilles 0%
2011 Villa B4/02 0%
2012 substructure 0%
2013 set out 0%
2014 Excavate 0%
2015 Conc. Foundation 0%
2016 Backfill 0%
2017 termite treatment 0%
2018 DPC (where applicable) 0%
2019 M&E inlet/outlet works - first fix 0%
2020 frame 0%
2021 set kickers 0%
2022 Conc. Columns & shear walls 0%
2023 Conc. G. F Beams 0%
2024 M&E first fix 0%
2025 Conc. Plantroom 0%
2026 Conc. Floor slab & swimming pool base 0%
2027 Blockwork 0%
2028 Conc. Swimming pool sides & overflow channels 0%
2029 Conc. Ring & tie beams 0%
2030 Roof & Ceiling 0%
2031 Fix wall plate & truss 0%
2032 Fix purlins and rafters 0%
2033 Fix shingles ( subject to receipt of timber) 0%
2034 Fix ceiing battens & joists 0%
2035 Fix ceiling boards 0%
2036 M&E first fix 0%
2037 Finishes 0%
2038 Wall plaster (internal & External) 0%
2039 M&E 1st fix 0%
2040 Floor finishes 0%
2041 Fix windows & doors 0%
2042 Swimming pool finishes 0%
2043 M&E final fix 0%
2044 Fix fittings and Fixtures 0%
2045 M&E Installations 0%
2046 Cable Tray, Conduit and Wiring 0%
2047 Electrical boards and connections 0%
2048 Electrical accessories 0%
2049 Light fittings and ceiling fans 0%
2050 Hot and cold water 0%
2051 Waste and sewage incl. biobox 0%
2052 Electric water heater 0%
2053 Swimming pool 0%
2054 Split unit installation 0%
2055 Toilet ventilation, grilles 0%
2056 Retail 1( subject to receipt of GFW drawings) 0%
2057 substructure 0%
2058 set out 0%
2059 Excavate (Drill in rock to anchor steel rods) 0%
2060 Conc. Foundation 0%
2061 Backfill ( where applicable ) 0%
2062 termite treatment 0%
2063 DPC (where applicable) 0%
2064 M&E inlet/outlet works 0%
2065 frame 0%
2066 set kickers 0%
2067 Conc. Columns & shear walls 0%
2068 Conc. G. F Beams 0%
2069 Conc. Plantroom 0%
2070 Conc. Floor slab 0%
2071 Blockwork 0%
2072 Conc. Ring & tie beams 0%
2073 Roof & Ceiling 0%
2074 Fix wall plate & truss 0%
2075 Fix purlins and rafters 0%
2076 Fix shingles ( subject to receipt of timber) 0%
2077 Fix ceiing battens & joists 0%
2078 Fix ceiling boards 0%
2079 Finishes 0%
2080 Wall plaster (internal & External) 0%
2081 M&E 1st fix 0%
2082 Floor finishes 0%
2083 Fix windows & doors 0%
2084 M&E final fix 0%
2085 Fix fittings and Fixtures 0%
2086 M&E Installations 0%
2087 Cable Tray, Conduit and Wiring 0%
2088 Electrical boards and connections 0%
2089 Electrical accessories 0%
2090 Light fittings and ceiling fans 0%
2091 Hot and cold water 0%
2092 Waste and sewage incl. biobox 0%
2093 Fan coil unit 0%
2094 Retail 2( subject to receipt of GFW drawings) 0%
2095 substructure 0%
2096 set out 0%
2097 Excavate (Drill in rock to anchor steel rods) 0%
2098 Conc. Foundation 0%
2099 Backfill ( where applicable ) 0%
2100 termite treatment 0%
2101 DPC (where applicable) 0%
2102 M&E inlet/outlet works 0%
2103 frame 0%
2104 set kickers 0%
2105 Conc. Columns & shear walls 0%
2106 Conc. G. F Beams 0%
2107 Conc. Plantroom 0%
2108 Conc. Floor slab 0%
2109 Blockwork 0%
2110 Conc. Ring & tie beams 0%

page 86
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2008 2009 2010 2011
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
2111 Roof & Ceiling 0%
2112 Fix wall plate & truss 0%
2113 Fix purlins and rafters 0%
2114 Fix shingles ( subject to receipt of timber) 0%
2115 Fix ceiing battens & joists 0%
2116 Fix ceiling boards 0%
2117 Finishes 0%
2118 Wall plaster (internal & External) 0%
2119 M&E 1st fix 0%
2120 Floor finishes 0%
2121 Fix windows & doors 0%
2122 M&E final fix 0%
2123 Fix fittings and Fixtures 0%
2124 M&E Installations 0%
2125 Cable Tray, Conduit and Wiring 0%
2126 Electrical boards and connections 0%
2127 Electrical accessories 0%
2128 Light fittings and ceiling fans 0%
2129 Hot and cold water 0%
2130 Waste and sewage incl. biobox 0%
2131 Fan coil unit 0%
2132 Retail 3( subject to receipt of GFW drawings) 0%
2133 substructure 0%
2134 set out 0%
2135 Excavate (Drill in rock to anchor steel rods) 0%
2136 Conc. Foundation 0%
2137 Backfill ( where applicable ) 0%
2138 termite treatment 0%
2139 DPC (where applicable) 0%
2140 M&E inlet/outlet works 0%
2141 frame 0%
2142 set kickers 0%
2143 Conc. Columns & shear walls 0%
2144 Conc. G. F Beams 0%
2145 Conc. Plantroom 0%
2146 Conc. Floor slab 0%
2147 Blockwork 0%
2148 Conc. Ring & tie beams 0%
2149 Roof & Ceiling 0%
2150 Fix wall plate & truss 0%
2151 Fix purlins and rafters 0%
2152 Fix shingles ( subject to receipt of timber) 0%
2153 Fix ceiing battens & joists 0%
2154 Fix ceiling boards 0%
2155 Finishes 0%
2156 Wall plaster (internal & External) 0%
2157 M&E 1st fix 0%
2158 Floor finishes 0%
2159 Fix windows & doors 0%
2160 M&E final fix 0%
2161 Fix fittings and Fixtures 0%
2162 M&E Installations 0%
2163 Cable Tray, Conduit and Wiring 0%
2164 Electrical boards and connections 0%
2165 Electrical accessories 0%
2166 Light fittings and ceiling fans 0%
2167 Hot and cold water 0%
2168 Waste and sewage incl. biobox 0%
2169 Fan coil unit 0%
2170 Seafood resort( subject to receipt of GFW drawings) 0%
2171 substructure 0%
2172 set out 0%
2173 Excavate (Drill in rock to anchor steel rods) 0%
2174 Conc. Foundation 0%
2175 Backfill ( where applicable ) 0%
2176 termite treatment 0%
2177 DPC (where applicable) 0%
2178 M&E inlet/outlet works 0%
2179 frame 0%
2180 set kickers 0%
2181 Conc. Columns & shear walls 0%
2182 Conc. G. F Beams 0%
2183 Conc. Plantroom 0%
2184 Conc. Floor slab 0%
2185 Blockwork 0%
2186 Conc. Ring & tie beams 0%
2187 Roof & Ceiling 0%
2188 Fix wall plate & truss 0%
2189 Fix purlins and rafters 0%
2190 Fix shingles ( subject to receipt of timber) 0%
2191 Fix ceiing battens & joists 0%
2192 Fix ceiling boards 0%
2193 Finishes 0%
2194 Wall plaster (internal & External) 0%
2195 M&E 1st fix 0%
2196 Floor finishes 0%
2197 Fix windows & doors 0%
2198 M&E final fix 0%
2199 Fix fittings and Fixtures 0%
2200 M&E Installations 0%
2201 Cable Tray, Conduit and Wiring 0%
2202 Electrical boards and connections 0%
2203 Electrical accessories 0%
2204 Light fittings and ceiling fans 0%
2205 Hot and cold water 0%
2206 Waste and sewage incl. biobox 0%
2207 Kitchen extraction duct 0%
2208 Chilled water piping 0%
2209 Fan coil unit 0%
2210 Toilet ventilation, grilles 0%
2211 Greeting Pavillion( subject to receipt of GFW drawings) 0%
2212 substructure 0%
2213 set out 0%
2214 Excavate (Drill in rock to anchor steel rods) 0%
2215 Conc. Foundation 0%
2216 Backfill ( where applicable ) 0%
2217 termite treatment 0%
2218 DPC (where applicable) 0%
2219 M&E inlet/outlet works 0%
2220 frame 0%
2221 set kickers 0%
2222 Conc. Columns & shear walls 0%
2223 Conc. G. F Beams 0%
2224 Conc. Plantroom 0%
2225 Conc. Floor slab 0%
2226 Blockwork 0%
2227 Conc. Ring & tie beams 0%

page 87
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2007 2008 2009 2010
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
2228 Roof & Ceiling 0%
2229 Fix wall plate & truss 0%
2230 Fix purlins and rafters 0%
2231 Fix shingles ( subject to receipt of timber) 0%
2232 Fix ceiing battens & joists 0%
2233 Fix ceiling boards 0%
2234 Finishes 0%
2235 Wall plaster (internal & External) 0%
2236 M&E 1st fix 0%
2237 Floor finishes 0%
2238 Fix windows & doors 0%
2239 M&E final fix 0%
2240 Fix fittings and Fixtures 0%
2241 M&E Installations 0%
2242 Cable Tray, Conduit and Wiring 0%
2243 Electrical boards and connections 0%
2244 Electrical accessories 0%
2245 Light fittings and ceiling fans 0%
2246 Hot and cold water 0%
2247 Waste and sewage incl. biobox 0%
2248 Fan coil unit 0%
2249 Toilet ventilation, grilles 0%
2250 External works ( subject to receipt of GFW drawings) 0%
2251 Infrastructures 0%
2252 Set out road (cabbies), vehicular 0%
2253 Set out Pedestrian walkways 0%
2254 Set out main water pipe alignment 0%
2255 Set out main electricity network 0%
2256 landscaping 0%
2257 Villas milieu 0%
2258 Main access road milieu 0%
2259 Drainage works ( subject to receipt of EME details) 0%
2260 Set out/implement main sewerage network 0%
2261 Set out/implement main rain water drainage alignment 0%
2262 Lot 3 0%
2263 A3 Villas ( 9 nos) 0%
2264 Villa A3/14 0%
2309 Villa A3/15 0%
2354 Villa A3/16 0%
2399 Villa A3/17 0%
2444 Villa A3/28 0%
2445 substructure 0%
2446 set out 0%
2447 Excavate 0%
2448 Conc. Foundation 0%
2449 Backfill 0%
2450 termite treatment 0%
2451 DPC (where applicable) 0%
2452 M&E inlet/outlet works - first fix 0%
2453 frame 0%
2463 Roof & Ceiling 0%
2470 Finishes 0%
2478 M&E Installations 0%
2489 Villa A3/29 0%
2490 substructure 0%
2491 set out 0%
2492 Excavate 0%
2493 Conc. Foundation 0%
2494 Backfill 0%
2495 termite treatment 0%
2496 DPC (where applicable) 0%
2497 M&E inlet/outlet works - first fix 0%
2498 frame 0%
2508 Roof & Ceiling 0%
2515 Finishes 0%
2523 M&E Installations 0%
2534 Villa A3/30 0%
2535 substructure 0%
2536 set out 0%
2537 Excavate 0%
2538 Conc. Foundation 0%
2539 Backfill 0%
2540 termite treatment 0%
2541 DPC (where applicable) 0%
2542 M&E inlet/outlet works - first fix 0%
2543 frame 0%
2553 Roof & Ceiling 0%
2560 Finishes 0%
2568 M&E Installations 0%
2579 Villa A3/31 0%
2624 Villa A3/32 0%
2625 substructure 0%
2626 set out 0%
2627 Excavate 0%
2628 Conc. Foundation 0%
2629 Backfill 0%
2630 termite treatment 0%
2631 DPC (where applicable) 0%
2632 frame 0%
2641 Roof & Ceiling 0%
2647 Finishes 0%
2653 M&E Installations 0%
2664 B223 Villas ( 3 nos) 0%
2665 Villa B2/03 0%
2666 substructure 0%
2667 set out 0%
2668 Excavate 0%
2669 Conc. Foundation 0%
2670 Backfill 0%
2671 termite treatment 0%
2672 DPC (where applicable) 0%
2673 frame 0%
2686 Roof & Ceiling 0%
2692 Finishes 0%
2697 M&E Installations 0%
2708 Villa B2/09 0%
2709 substructure 0%
2710 set out 0%
2711 Excavate 0%
2712 Conc. Foundation 0%
2713 Backfill 0%
2714 termite treatment 0%
2715 DPC (where applicable) 0%
2716 M&E inlet/outlet works - first fix 0%
2717 frame 0%
2733 Roof & Ceiling 0%

page 88
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2007 2008 2009 2010
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
2740 Finishes 0%
2747 M&E Installations 0%
2758 Villa B2/10 0%
2759 substructure 0%
2760 set out 0%
2761 Excavate 0%
2762 Conc. Foundation 0%
2763 Backfill 0%
2764 termite treatment 0%
2765 DPC (where applicable) 0%
2766 M&E inlet/outlet works - first fix 0%
2767 frame 0%
2783 Roof & Ceiling 0%
2790 Finishes 0%
2797 M&E Installations 0%
2808 B4 Standard Villas ( 2 nos) 0%
2809 Villa B4/03 0%
2810 substructure 0%
2811 set out 0%
2812 Excavate 0%
2813 Conc. Foundation 0%
2814 Backfill 0%
2815 termite treatment 0%
2816 DPC (where applicable) 0%
2817 M&E inlet/outlet works - first fix 0%
2818 frame 0%
2819 set kickers 0%
2820 Conc. Columns & shear walls 0%
2821 Conc. G. F Beams 0%
2822 M&E first fix 0%
2823 Conc. Plantroom 0%
2824 Conc. Floor slab & swimming pool base 0%
2825 Blockwork 0%
2826 Conc. Swimming pool sides & overflow channels 0%
2827 Conc. Ring & tie beams 0%
2828 Roof & Ceiling 0%
2829 Fix wall plate & truss 0%
2830 Fix purlins and rafters 0%
2831 Fix shingles ( subject to receipt of timber) 0%
2832 Fix ceiing battens & joists 0%
2833 Fix ceiling boards 0%
2834 M&E first fix 0%
2835 Finishes 0%
2836 Wall plaster (internal & External) 0%
2837 M&E 1st fix 0%
2838 Floor finishes 0%
2839 Fix windows & doors 0%
2840 Swimming pool finishes 0%
2841 M&E final fix 0%
2842 Fix fittings and Fixtures 0%
2843 M&E Installations 0%
2844 Cable Tray, Conduit and Wiring 0%
2845 Electrical boards and connections 0%
2846 Electrical accessories 0%
2847 Light fittings and ceiling fans 0%
2848 Hot and cold water 0%
2849 Waste and sewage incl. biobox 0%
2850 Electric water heater 0%
2851 Swimming pool 0%
2852 Split unit installation 0%
2853 Toilet ventilation, grilles 0%
2854 Villa B4/04 0%
2855 substructure 0%
2856 set out 0%
2857 Excavate 0%
2858 Conc. Foundation 0%
2859 Backfill 0%
2860 termite treatment 0%
2861 DPC (where applicable) 0%
2862 M&E inlet/outlet works - first fix 0%
2863 frame 0%
2864 set kickers 0%
2865 Conc. Columns & shear walls 0%
2866 Conc. G. F Beams 0%
2867 M&E first fix 0%
2868 Conc. Plantroom 0%
2869 Conc. Floor slab & swimming pool base 0%
2870 Blockwork 0%
2871 Conc. Swimming pool sides & overflow channels 0%
2872 Conc. Ring & tie beams 0%
2873 Roof & Ceiling 0%
2874 Fix wall plate & truss 0%
2875 Fix purlins and rafters 0%
2876 Fix shingles ( subject to receipt of timber) 0%
2877 Fix ceiing battens & joists 0%
2878 Fix ceiling boards 0%
2879 M&E first fix 0%
2880 Finishes 0%
2881 Wall plaster (internal & External) 0%
2882 M&E 1st fix 0%
2883 Floor finishes 0%
2884 Fix windows & doors 0%
2885 Swimming pool finishes 0%
2886 M&E final fix 0%
2887 Fix fittings and Fixtures 0%
2888 M&E Installations 0%
2889 Cable Tray, Conduit and Wiring 0%
2890 Electrical boards and connections 0%
2891 Electrical accessories 0%
2892 Light fittings and ceiling fans 0%
2893 Hot and cold water 0%
2894 Waste and sewage incl. biobox 0%
2895 Electric water heater 0%
2896 Swimming pool 0%
2897 Split unit installation 0%
2898 Toilet ventilation, grilles 0%
2899 BC311 Executive Villa 0%
2900 Villa C3/02 0%
2943 Villa C3/03 0%
2986 Villa C3/04 0%
3029 Villa C3/05 0%
3072 Villa C3/06 0%

page 89
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2008 2009 2010 2011
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
3115 P3 Presidential suites ( 3 nos) 0%
3116 Villa P3/01 0%
3159 Villa P3/02 0%
3202 Villa P3/03 0%
3245 Hilltop sunset deck( subject to receipt of GFW drawings) 0%
3280 External works ( subject to receipt of GFW drawings) 0%
3289 Drainage works ( subject to receipt of EME details) 0%
3290 Set out/implement main sewerage network 0%
3291 Set out/implement main rain water drainage alignment 0%
3292 Lot 4 0%
3293 Couple treatment room( subject to receipt of GFW drawings) 0%
3334 Single treatment room( subject to receipt of GFW drawings) 0%
3375 Dive Centre( subject to receipt of GFW drawings) 0%
3413 Kid's club( subject to receipt of GFW drawings) 0%
3452 Recreation House( subject to receipt of GFW drawings) 0%
3491 Watersports rental( subject to receipt of GFW drawings) 0%
3529 3 Meals restaurant( subject to receipt of GFW drawings) 0%
3570 Beach Pool Bar( subject to receipt of GFW drawings) 0%
3611 Signature Pool area( subject to receipt of GFW drawings) 0%
3650 Wedding Chapel( subject to receipt of GFW drawings) 0%
3685 BOH/Admin Building( subject to receipt of GFW drawings) 0%
3726 Chi Sanctum( subject to receipt of GFW drawings) 0%
3767 Yoga Pavillion( subject to receipt of GFW drawings) 0%
3805 External works ( subject to receipt of GFW drawings) 0%
3814 Drainage works ( subject to receipt of EME details) 0%
3817 M&E Installations- External 0%
3828 Sundries 0%
3829 Site cleaning & demobilisation 0%
3830 Project Commissioning 0%

The following table provides summary of the current delay


caused by unforeseen ground conditions at each of the
buildings. This change involved significant delay and difficulty
excavating hard rock.
Impacted Programme Baseline Programme
Villa commencement completion commencement completion Baseline duration Revised Duration
A3/01 28-Feb-07 09-Jul-08 23-Jul-07 15-Mar-08 236.13 497.13
A3/02 12-Apr-07 09-Dec-08 23-Jul-07 15-Mar-08 236.13 607.08
A3/03 12-Apr-07 30-Dec-08 23-Jul-07 15-Mar-08 236.13 628.08
A3/06 09-Apr-07 02-Jul-08 23-Jul-07 15-Mar-08 236.13 450.13
A3/08 02-Apr-07 22-Dec-08 02-Apr-07 15-Mar-08 348.13 630.08
A3/09 02-Apr-07 06-May-09 02-Apr-07 15-Mar-08 348.13 765.08
A3/10 09-Apr-07 02-Jul-08 09-Apr-07 15-Mar-08 341.13 450.13
A3/11 09-Apr-07 18-May-09 09-Apr-07 15-Mar-08 341.13 770.08
A3/19 12-Apr-07 13-Jun-09 12-Apr-07 15-Mar-08 338.13 793.13
A3/20 25-Apr-07 29-May-09 12-Apr-07 15-Mar-08 338.13 765.13
A3/21 12-Apr-07 29-May-09 12-Apr-07 15-Mar-08 338.13 778.13
A3/26 16-Apr-07 06-Jan-09 16-Apr-07 15-Mar-08 334.13 631.08
A3/27 16-Apr-07 29-Sep-08 16-Apr-07 15-Mar-08 334.13 532.08
A3/28 28-May-07 06-Aug-08 28-May-07 15-Mar-08 292.13 436.08
A3/29 28-May-07 23-Apr-08 28-May-07 15-Mar-08 292.13 331.13
A3/30 25-Apr-07 15-May-08 28-May-07 15-Mar-08 292.13 386.13
A3/32 28-May-07 16-Nov-07 28-May-07 16-Nov-07 172.04 172.04
B2/01 16-Apr-07 04-Feb-09 03-Jul-07 15-Mar-08 256.13 660.08
B2/02 16-Apr-07 24-Jun-08 03-Jul-07 15-Mar-08 256.13 435.08
B2/03 28-May-07 25-Dec-07 28-May-07 04-Dec-07 190.17 211.13
B2/04 16-Apr-07 10-Oct-08 03-Jul-07 15-Mar-08 256.13 543.13
B2/05 16-Apr-07 08-Jan-09 03-Jul-07 15-Mar-08 256.13 633.13
B2/06 23-Apr-07 16-Jan-09 03-Jul-07 15-Mar-08 256.13 634.13
B2/07 23-Apr-07 07-Jun-08 03-Jul-07 15-Mar-08 256.13 411.13
B2/08 23-Apr-07 16-Jan-09 03-Jul-07 15-Mar-08 256.13 634.13
B2/09 28-May-07 12-Mar-09 28-May-07 15-Mar-08 292.13 654.13
B2/10 28-May-07 18-Mar-09 28-May-07 15-Mar-08 292.13 660.13

The next table records the delays to other buildings as a


consequence of the delays to the current to preceding tasks. In
retaining the original planned sequence depicted on the original
programme of works, the completion date is extended to 9
September 2009.

page 90
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

Impacted Programme Baseline Programme


Villa commencement completion commencement completion Delay
P3 Presidential Villas 21-Jun-08 23-Mar-09 20-Jun-07 20-Mar-08 367.00
Sunset Deck 24-Jul-08 17-Mar-09 23-Jul-07 14-Mar-08 367.00
Employees Facilities Complex 30-Mar-08 03-Jan-09 14-Jun-07 19-Mar-08 290.00
Excom Villa 30-Mar-08 01-Jan-09 14-Jun-07 17-Mar-08 290.00
GM Villa 30-Mar-08 31-Dec-08 14-Jun-07 15-Mar-08 290.00
Health club 30-Mar-08 31-Dec-08 14-Jun-07 15-Mar-08 290.00
Single Treatment room 03-Jul-08 19-Mar-09 02-Jul-07 17-Mar-08 367.00
Couple treatment room 03-Jul-08 21-Mar-09 02-Jul-07 19-Mar-08 367.00
Sanctum 03-Jul-08 18-Mar-09 02-Jul-07 15-Mar-08 367.00
Yoga Pavilion 03-Jul-08 17-Mar-09 02-Jul-07 14-Mar-08 367.00
BOH Building 03-Jul-08 19-Mar-09 02-Jul-07 17-Mar-08 367.00
Wedding chapel 08-Jul-08 17-Mar-09 02-Jul-07 14-Mar-08 372.00
Seafood Resort 31-Aug-08 02-Jun-09 18-Jun-07 19-Mar-08 440.00
Retail Pavilion 31-Aug-08 28-May-09 18-Jun-07 14-Mar-08 440.00
Kid's club 03-Jul-08 17-Mar-09 02-Jul-07 14-Mar-08 367.00
Recreation House 03-Jul-08 17-Mar-09 02-Jul-07 14-Mar-08 367.00
Water sport Rental 03-Jul-08 17-Mar-09 02-Jul-07 14-Mar-08 367.00
Dive Center 03-Jul-08 17-Mar-09 02-Jul-07 14-Mar-08 367.00

It should be noted that rock excavation is continuing at various


sites where excavation activities is yet to start. Consequently,
the delay attributed to this event is continuing.

As a result of the current delay caused by this event the time for
completion has been further extended from 9 August 2008 to 9
September 2009, a period of 396 calendar days.

However, in recognition of more rock excavation at other areas


of the Site it is anticipated further delays will be experienced.
Accordingly, the Contractor gives notice of further delays likely
at the remaining areas of the site where buildings will be
positioned.

The revised completion date is now 9 September 2009.

page 91
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

5.1.4.3. Event No 3 – Later Receipt of Design


Information
ID Task Name
2007 2008 2009
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1 SHANGRI-LA , Long Island Resort Seychelles 0%
2 General Conditions and Preliminaries 0%
17 Site establishment 0%
41 Material/equipment procurement 0%
182 Lot 1 0%
183 A3 Villas ( 6 nos) 0%
453 C311 Executive Villas ( 1 nos) 0%
497 GM Villa ( subject to receipt of GFW drawings) 0%
498 substructure 0%
499 set out ( subject to receipt of GFW dwg by Mid June 07) 0%
500 Excavate (Drill in rock to anchor steel rods as required) 0%
501 Conc. Foundation 0%
502 Backfill ( where applicable ) 0%
503 termite treatment 0%
504 DPC (where applicable) 0%
505 M&E inlet/outlet works 0%
506 frame 0%
507 set kickers 0%
508 Conc. Columns & shear walls upto roof 0%
509 Conc. G. F Beams 0%
510 Conc. Floor slab GF 0%
511 Blockwork upto roof 0%
512 Conc. Ring & tie beams 0%
513 Roof & Ceiling 0%
514 Fix wall plate & truss 0%
515 Fix purlins and rafters 0%
516 Fix shingles ( subject to receipt of timber) 0%
517 Fix ceiing battens & joists 0%
518 Fix ceiling boards 0%
519 Finishes 0%
520 Wall plaster (internal & External) 0%
521 M&E 1st fix 0%
522 Floor finishes 0%
523 Fix windows & doors 0%
524 M&E final fix 0%
525 Fix fittings and Fixtures 0%
526 M&E Installations 0%
527 Cable Tray, Conduit and Wiring 0%
528 Electrical boards and connections 0%
529 Electrical accessories 0%
530 Light fittings and ceiling fans 0%
531 Hot and cold water 0%
532 Waste and sewage incl. biobox 0%
533 Electric water heater 0%
534 Swimming pool 0%
535 Split unit installation 0%
536 Toilet ventilation, grilles 0%
537 Employees Facilities ( subject to receipt of GFW drawings) 0%
538 substructure 0%
539 set out 0%
540 Excavate 0%
541 Conc. Foundation 0%
542 Backfill ( where applicable ) 0%
543 termite treatment 0%
544 DPC (where applicable) 0%
545 M&E inlet/outlet works 0%
546 frame 0%
547 set kickers 0%
548 Conc. Columns & shear walls upto GF floor level 0%
549 Conc. G. F Beams 0%
550 Conc. G.F Floor slab 0%
551 Conc. Columns & shear walls upto FF level 0%
552 Blockwork upto FF level 0%
553 Conc. F. Floor slab 0%
554 Conc. Columns & shear walls upto roof level 0%
555 Blockwork upto roof 0%
556 Conc. Ring & tie beams 0%
557 Roof & Ceiling 0%
558 Fix wall plate & truss 0%
559 Fix purlins and rafters 0%
560 Fix shingles ( subject to receipt of timber) 0%
561 Fix ceiing battens & joists 0%
562 Fix ceiling boards 0%
563 Finishes 0%
564 Wall plaster (internal & External) 0%
565 M&E 1st fix 0%
566 Floor finishes 0%
567 Fix windows & doors 0%
568 M&E final fix 0%
569 Fix fittings and Fixtures 0%
570 M&E Installations 0%
571 Cable Tray, Conduit and Wiring 0%
572 Electrical boards and connections 0%
573 Electrical accessories 0%
574 Light fittings and ceiling fans 0%
575 Hot and cold water 0%
576 Waste and sewage incl. biobox 0%
577 Boiler 0%
578 Chiller 0%
579 Fan coil unit 0%
580 Toilet ventilation, grilles 0%
581 Laundry F& B service office ( subject to receipt of GFW drawings) 0%
625 Health Club/ Medical Centre( subject to receipt of GFW drawings) 0%
626 substructure 0%
627 set out 0%
628 Excavate (Drill in rock to anchor steel rods) 0%
629 Conc. Foundation 0%
630 Backfill ( where applicable ) 0%
631 termite treatment 0%
632 DPC (where applicable) 0%
633 M&E inlet/outlet works 0%
634 frame 0%
635 set kickers 0%
636 Conc. Columns & shear walls 0%
637 Conc. G. F Beams 0%
638 Conc. substructure 0%
639 Conc. Floor slab 0%
640 Blockwork 0%
641 Conc. Ring & tie beams 0%

page 92
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2007 2008 2009 2010
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
642 Roof & Ceiling 0%
643 Fix wall plate & truss 0%
644 Fix purlins and rafters 0%
645 Fix shingles ( subject to receipt of timber) 0%
646 Fix ceiing battens & joists 0%
647 Fix ceiling boards 0%
648 Finishes 0%
649 Wall plaster (internal & External) 0%
650 M&E 1st fix 0%
651 Floor finishes 0%
652 Fix windows & doors 0%
653 M&E final fix 0%
654 Fix fittings and Fixtures 0%
655 M&E Installations 0%
656 Cable Tray, Conduit and Wiring 0%
657 Electrical boards and connections 0%
658 Electrical accessories 0%
659 Light fittings and ceiling fans 0%
660 Hot and cold water 0%
661 Waste and sewage incl. biobox 0%
662 Boiler 0%
663 Chiller 0%
664 Fan coil unit 0%
665 Toilet ventilation, grilles 0%
666 Administration Block ( subject to receipt of GFW drawings) 0%
707 1 bedroom Villa ( Excom, 6 units)( subject to receipt of GFW drawings) 0%
708 substructure 0%
709 set out 0%
710 Excavate 0%
711 Conc. Foundation 0%
712 Backfill ( where applicable ) 0%
713 termite treatment 0%
714 DPC (where applicable) 0%
715 M&E inlet/outlet works 0%
716 frame 0%
717 set kickers 0%
718 Conc. Columns & shear walls upto GF floor level 0%
719 Conc. G. F Beams 0%
720 Conc. G.F Floor slab 0%
721 Conc. Columns & shear walls upto FF level 0%
722 Blockwork upto FF level 0%
723 Conc. F. Floor slab 0%
724 Conc. Columns & shear walls upto roof level 0%
725 Blockwork upto roof 0%
726 Conc. Ring & tie beams 0%
727 Roof & Ceiling 0%
728 Fix wall plate & truss 0%
729 Fix purlins and rafters 0%
730 Fix shingles ( subject to receipt of timber) 0%
731 Fix ceiing battens & joists 0%
732 Fix ceiling boards 0%
733 Finishes 0%
734 Wall plaster (internal & External) 0%
735 M&E 1st fix 0%
736 Floor finishes 0%
737 Fix windows & doors 0%
738 M&E final fix 0%
739 Fix fittings and Fixtures 0%
740 M&E Installations 0%
741 Cable Tray, Conduit and Wiring 0%
742 Electrical boards and connections 0%
743 Electrical accessories 0%
744 Light fittings and ceiling fans 0%
745 Hot and cold water 0%
746 Waste and sewage incl. biobox 0%
747 Electric water heater 0%
748 Split unit installation 0%
749 Toilet ventilation, grilles 0%
750 Main Lobby ( subject to receipt of GFW drawings) 0%
791 Tennis Courts ( subject to receipt of GFW drawings) 0%
807 External works ( subject to receipt of GFW drawings) 0%
816 Drainage works ( subject to receipt of EME details) 0%
819 Fuel Farm ( subject to receipt of EME details) 0%
823 Sea water Storage Tank & Water Tanks( subject to receipt of EME details) 0%
827 Desalination plant( subject to receipt of EME details) 0%
831 MLV Panel( subject to receipt of EME details) 0%
835 Step Up Transformer( subject to receipt of EME details) 0%
839 Incinerator/ Garbage room( subject to receipt of EME details) 0%
843 Sewer treatement plant( subject to receipt of EME details) 0%
847 Lot 2 0%
848 A3 Villas (17 nos) 0%
1614 B223 Villas ( 7 nos) 0%
1965 B4 Villa (2 nos.) 0%
2056 Retail 1( subject to receipt of GFW drawings) 0%
2057 substructure 0%
2058 set out 0%
2059 Excavate (Drill in rock to anchor steel rods) 0%
2060 Conc. Foundation 0%
2061 Backfill ( where applicable ) 0%
2062 termite treatment 0%
2063 DPC (where applicable) 0%
2064 M&E inlet/outlet works 0%
2065 frame 0%
2066 set kickers 0%
2067 Conc. Columns & shear walls 0%
2068 Conc. G. F Beams 0%
2069 Conc. Plantroom 0%
2070 Conc. Floor slab 0%
2071 Blockwork 0%
2072 Conc. Ring & tie beams 0%
2073 Roof & Ceiling 0%
2074 Fix wall plate & truss 0%
2075 Fix purlins and rafters 0%
2076 Fix shingles ( subject to receipt of timber) 0%
2077 Fix ceiing battens & joists 0%
2078 Fix ceiling boards 0%
2079 Finishes 0%
2080 Wall plaster (internal & External) 0%
2081 M&E 1st fix 0%
2082 Floor finishes 0%
2083 Fix windows & doors 0%
2084 M&E final fix 0%
2085 Fix fittings and Fixtures 0%

page 93
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2008 2009 2010 2011
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
2086 M&E Installations 0%
2087 Cable Tray, Conduit and Wiring 0%
2088 Electrical boards and connections 0%
2089 Electrical accessories 0%
2090 Light fittings and ceiling fans 0%
2091 Hot and cold water 0%
2092 Waste and sewage incl. biobox 0%
2093 Fan coil unit 0%
2094 Retail 2( subject to receipt of GFW drawings) 0%
2095 substructure 0%
2096 set out 0%
2097 Excavate (Drill in rock to anchor steel rods) 0%
2098 Conc. Foundation 0%
2099 Backfill ( where applicable ) 0%
2100 termite treatment 0%
2101 DPC (where applicable) 0%
2102 M&E inlet/outlet works 0%
2103 frame 0%
2104 set kickers 0%
2105 Conc. Columns & shear walls 0%
2106 Conc. G. F Beams 0%
2107 Conc. Plantroom 0%
2108 Conc. Floor slab 0%
2109 Blockwork 0%
2110 Conc. Ring & tie beams 0%
2111 Roof & Ceiling 0%
2112 Fix wall plate & truss 0%
2113 Fix purlins and rafters 0%
2114 Fix shingles ( subject to receipt of timber) 0%
2115 Fix ceiing battens & joists 0%
2116 Fix ceiling boards 0%
2117 Finishes 0%
2118 Wall plaster (internal & External) 0%
2119 M&E 1st fix 0%
2120 Floor finishes 0%
2121 Fix windows & doors 0%
2122 M&E final fix 0%
2123 Fix fittings and Fixtures 0%
2124 M&E Installations 0%
2125 Cable Tray, Conduit and Wiring 0%
2126 Electrical boards and connections 0%
2127 Electrical accessories 0%
2128 Light fittings and ceiling fans 0%
2129 Hot and cold water 0%
2130 Waste and sewage incl. biobox 0%
2131 Fan coil unit 0%
2132 Retail 3( subject to receipt of GFW drawings) 0%
2133 substructure 0%
2134 set out 0%
2135 Excavate (Drill in rock to anchor steel rods) 0%
2136 Conc. Foundation 0%
2137 Backfill ( where applicable ) 0%
2138 termite treatment 0%
2139 DPC (where applicable) 0%
2140 M&E inlet/outlet works 0%
2141 frame 0%
2142 set kickers 0%
2143 Conc. Columns & shear walls 0%
2144 Conc. G. F Beams 0%
2145 Conc. Plantroom 0%
2146 Conc. Floor slab 0%
2147 Blockwork 0%
2148 Conc. Ring & tie beams 0%
2149 Roof & Ceiling 0%
2150 Fix wall plate & truss 0%
2151 Fix purlins and rafters 0%
2152 Fix shingles ( subject to receipt of timber) 0%
2153 Fix ceiing battens & joists 0%
2154 Fix ceiling boards 0%
2155 Finishes 0%
2156 Wall plaster (internal & External) 0%
2157 M&E 1st fix 0%
2158 Floor finishes 0%
2159 Fix windows & doors 0%
2160 M&E final fix 0%
2161 Fix fittings and Fixtures 0%
2162 M&E Installations 0%
2163 Cable Tray, Conduit and Wiring 0%
2164 Electrical boards and connections 0%
2165 Electrical accessories 0%
2166 Light fittings and ceiling fans 0%
2167 Hot and cold water 0%
2168 Waste and sewage incl. biobox 0%
2169 Fan coil unit 0%
2170 Seafood resort( subject to receipt of GFW drawings) 0%
2171 substructure 0%
2172 set out 0%
2173 Excavate (Drill in rock to anchor steel rods) 0%
2174 Conc. Foundation 0%
2175 Backfill ( where applicable ) 0%
2176 termite treatment 0%
2177 DPC (where applicable) 0%
2178 M&E inlet/outlet works 0%
2179 frame 0%
2180 set kickers 0%
2181 Conc. Columns & shear walls 0%
2182 Conc. G. F Beams 0%
2183 Conc. Plantroom 0%
2184 Conc. Floor slab 0%
2185 Blockwork 0%
2186 Conc. Ring & tie beams 0%
2187 Roof & Ceiling 0%
2188 Fix wall plate & truss 0%
2189 Fix purlins and rafters 0%
2190 Fix shingles ( subject to receipt of timber) 0%
2191 Fix ceiing battens & joists 0%
2192 Fix ceiling boards 0%
2193 Finishes 0%
2194 Wall plaster (internal & External) 0%
2195 M&E 1st fix 0%
2196 Floor finishes 0%
2197 Fix windows & doors 0%
2198 M&E final fix 0%
2199 Fix fittings and Fixtures 0%

page 94
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2007 2008 2009 2010
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
2200 M&E Installations 0%
2201 Cable Tray, Conduit and Wiring 0%
2202 Electrical boards and connections 0%
2203 Electrical accessories 0%
2204 Light fittings and ceiling fans 0%
2205 Hot and cold water 0%
2206 Waste and sewage incl. biobox 0%
2207 Kitchen extraction duct 0%
2208 Chilled water piping 0%
2209 Fan coil unit 0%
2210 Toilet ventilation, grilles 0%
2211 Greeting Pavillion( subject to receipt of GFW drawings) 0%
2250 External works ( subject to receipt of GFW drawings) 0%
2259 Drainage works ( subject to receipt of EME details) 0%
2262 Lot 3 0%
2263 A3 Villas ( 9 nos) 0%
2664 B223 Villas ( 3 nos) 0%
2808 B4 Standard Villas ( 2 nos) 0%
2899 BC311 Executive Villa 0%
3115 P3 Presidential suites ( 3 nos) 0%
3116 Villa P3/01 0%
3117 substructure 0%
3118 set out 0%
3119 Excavate 0%
3120 Conc. Foundation 0%
3121 Backfill ( where applicable ) 0%
3122 termite treatment 0%
3123 DPC (where applicable) 0%
3124 M&E inlet/outlet works 0%
3125 frame 0%
3126 set kickers 0%
3127 Conc. Columns & shear walls 0%
3128 Conc. G. F Beams 0%
3129 Conc. Plantroom 0%
3130 Conc. Floor slab & swimming pool base 0%
3131 Blockwork 0%
3132 Conc. Swimming pool sides & overflow channels 0%
3133 Conc. Ring & tie beams 0%
3134 Roof & Ceiling 0%
3135 Fix wall plate & truss 0%
3136 Fix purlins and rafters 0%
3137 Fix shingles ( subject to receipt of timber) 0%
3138 Fix ceiing battens & joists 0%
3139 Fix ceiling boards 0%
3140 Finishes 0%
3141 Wall plaster (internal & External) 0%
3142 M&E 1st fix 0%
3143 Floor finishes 0%
3144 Fix windows & doors 0%
3145 Swimming pool finishes 0%
3146 M&E final fix 0%
3147 Fix fittings and Fixtures 0%
3148 M&E Installations 0%
3149 Cable Tray, Conduit and Wiring 0%
3150 Electrical boards and connections 0%
3151 Electrical accessories 0%
3152 Light fittings and ceiling fans 0%
3153 Hot and cold water 0%
3154 Waste and sewage incl. biobox 0%
3155 Electric water heater 0%
3156 Swimming pool 0%
3157 Split unit installation 0%
3158 Toilet ventilation, grilles 0%
3159 Villa P3/02 0%
3160 substructure 0%
3161 set out 0%
3162 Excavate 0%
3163 Conc. Foundation 0%
3164 Backfill ( where applicable ) 0%
3165 termite treatment 0%
3166 DPC (where applicable) 0%
3167 M&E inlet/outlet works 0%
3168 frame 0%
3169 set kickers 0%
3170 Conc. Columns & shear walls 0%
3171 Conc. G. F Beams 0%
3172 Conc. Plantroom 0%
3173 Conc. Floor slab & swimming pool base 0%
3174 Blockwork 0%
3175 Conc. Swimming pool sides & overflow channels 0%
3176 Conc. Ring & tie beams 0%
3177 Roof & Ceiling 0%
3178 Fix wall plate & truss 0%
3179 Fix purlins and rafters 0%
3180 Fix shingles ( subject to receipt of timber) 0%
3181 Fix ceiing battens & joists 0%
3182 Fix ceiling boards 0%
3183 Finishes 0%
3184 Wall plaster (internal & External) 0%
3185 M&E 1st fix 0%
3186 Floor finishes 0%
3187 Fix windows & doors 0%
3188 Swimming pool finishes 0%
3189 M&E final fix 0%
3190 Fix fittings and Fixtures 0%
3191 M&E Installations 0%
3192 Cable Tray, Conduit and Wiring 0%
3193 Electrical boards and connections 0%
3194 Electrical accessories 0%
3195 Light fittings and ceiling fans 0%
3196 Hot and cold water 0%
3197 Waste and sewage incl. biobox 0%
3198 Electric water heater 0%
3199 Swimming pool 0%
3200 Split unit installation 0%
3201 Toilet ventilation, grilles 0%
3202 Villa P3/03 0%
3203 substructure 0%
3204 set out 0%
3205 Excavate 0%
3206 Conc. Foundation 0%
3207 Backfill ( where applicable ) 0%
3208 termite treatment 0%
3209 DPC (where applicable) 0%
3210 M&E inlet/outlet works 0%

page 95
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2008 2009 2010 2011
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
3211 frame 0%
3220 Roof & Ceiling 0%
3226 Finishes 0%
3234 M&E Installations 0%
3235 Cable Tray, Conduit and Wiring 0%
3236 Electrical boards and connections 0%
3237 Electrical accessories 0%
3238 Light fittings and ceiling fans 0%
3239 Hot and cold water 0%
3240 Waste and sewage incl. biobox 0%
3241 Electric water heater 0%
3242 Swimming pool 0%
3243 Split unit installation 0%
3244 Toilet ventilation, grilles 0%
3245 Hilltop sunset deck( subject to receipt of GFW drawings) 0%
3246 substructure 0%
3247 set out 0%
3248 Excavate 0%
3249 Conc. Foundation 0%
3250 Backfill ( where applicable ) 0%
3251 termite treatment 0%
3252 DPC (where applicable) 0%
3253 M&E inlet/outlet works 0%
3254 frame 0%
3255 set kickers 0%
3256 Conc. Columns & shear walls 0%
3257 Conc. G. F Beams 0%
3258 Conc. Plantroom 0%
3259 Conc. Floor slab 0%
3260 Blockwork 0%
3261 Conc. Ring & tie beams 0%
3262 Roof & Ceiling 0%
3263 Fix wall plate & truss 0%
3264 Fix purlins and rafters 0%
3265 Fix shingles ( subject to receipt of timber) 0%
3266 Fix ceiing battens & joists 0%
3267 Fix ceiling boards 0%
3268 Finishes 0%
3269 Wall plaster (internal & External) 0%
3270 M&E 1st fix 0%
3271 Floor finishes 0%
3272 Fix windows & doors 0%
3273 M&E final fix 0%
3274 Fix fittings and Fixtures 0%
3275 M&E Installations 0%
3276 Cable Tray, Conduit and Wiring 0%
3277 Electrical boards and connections 0%
3278 Electrical accessories 0%
3279 Light fittings and ceiling fans 0%
3280 External works ( subject to receipt of GFW drawings) 0%
3289 Drainage works ( subject to receipt of EME details) 0%
3292 Lot 4 0%
3293 Couple treatment room( subject to receipt of GFW drawings) 0%
3294 substructure 0%
3295 set out 0%
3296 Excavate 0%
3297 Conc. Foundation 0%
3298 Backfill ( where applicable ) 0%
3299 termite treatment 0%
3300 DPC (where applicable) 0%
3301 M&E inlet/outlet works 0%
3302 frame 0%
3303 set kickers 0%
3304 Conc. Columns & shear walls 0%
3305 Conc. G. F Beams 0%
3306 Conc. Plantroom 0%
3307 Conc. Floor slab 0%
3308 Blockwork 0%
3309 Conc. Ring & tie beams 0%
3310 Roof & Ceiling 0%
3311 Fix wall plate & truss 0%
3312 Fix purlins and rafters 0%
3313 Fix shingles ( subject to receipt of timber) 0%
3314 Fix ceiing battens & joists 0%
3315 Fix ceiling boards 0%
3316 Finishes 0%
3317 Wall plaster (internal & External) 0%
3318 M&E 1st fix 0%
3319 Floor finishes 0%
3320 Fix windows & doors 0%
3321 M&E final fix 0%
3322 Fix fittings and Fixtures 0%
3323 M&E Installations 0%
3324 Cable Tray, Conduit and Wiring 0%
3325 Electrical boards and connections 0%
3326 Electrical accessories 0%
3327 Light fittings and ceiling fans 0%
3328 Hot and cold water 0%
3329 Waste and sewage incl. biobox 0%
3330 Electric water heater 0%
3331 Water feature 0%
3332 Split unit installation 0%
3333 Toilet ventilation, grilles 0%
3334 Single treatment room( subject to receipt of GFW drawings) 0%
3335 substructure 0%
3336 set out 0%
3337 Excavate 0%
3338 Conc. Foundation 0%
3339 Backfill ( where applicable ) 0%
3340 termite treatment 0%
3341 DPC (where applicable) 0%
3342 M&E inlet/outlet works 0%
3343 frame 0%
3344 set kickers 0%
3345 Conc. Columns & shear walls 0%
3346 Conc. G. F Beams 0%
3347 Conc. Plantroom 0%
3348 Conc. Floor slab 0%
3349 Blockwork 0%
3350 Conc. Ring & tie beams 0%
3351 Roof & Ceiling 0%
3352 Fix wall plate & truss 0%
3353 Fix purlins and rafters 0%
3354 Fix shingles ( subject to receipt of timber) 0%
3355 Fix ceiing battens & joists 0%
3356 Fix ceiling boards 0%

page 96
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2008 2009 2010 2011
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
3357 Finishes 0%
3358 Wall plaster (internal & External) 0%
3359 M&E 1st fix 0%
3360 Floor finishes 0%
3361 Fix windows & doors 0%
3362 M&E final fix 0%
3363 Fix fittings and Fixtures 0%
3364 M&E Installations 0%
3365 Cable Tray, Conduit and Wiring 0%
3366 Electrical boards and connections 0%
3367 Electrical accessories 0%
3368 Light fittings and ceiling fans 0%
3369 Hot and cold water 0%
3370 Waste and sewage incl. biobox 0%
3371 Electric water heater 0%
3372 Water feature 0%
3373 Split unit installation 0%
3374 Toilet ventilation, grilles 0%
3375 Dive Centre( subject to receipt of GFW drawings) 0%
3376 substructure 0%
3377 set out 0%
3378 Excavate 0%
3379 Conc. Foundation 0%
3380 Backfill ( where applicable ) 0%
3381 termite treatment 0%
3382 DPC (where applicable) 0%
3383 M&E inlet/outlet works 0%
3384 frame 0%
3385 set kickers 0%
3386 Conc. Columns & shear walls 0%
3387 Conc. G. F Beams 0%
3388 Conc. Plantroom 0%
3389 Conc. Floor slab 0%
3390 Blockwork 0%
3391 Conc. Ring & tie beams 0%
3392 Roof & Ceiling 0%
3393 Fix wall plate & truss 0%
3394 Fix purlins and rafters 0%
3395 Fix shingles ( subject to receipt of timber) 0%
3396 Fix ceiing battens & joists 0%
3397 Fix ceiling boards 0%
3398 Finishes 0%
3399 Wall plaster (internal & External) 0%
3400 M&E 1st fix 0%
3401 Floor finishes 0%
3402 Fix windows & doors 0%
3403 M&E final fix 0%
3404 Fix fittings and Fixtures 0%
3405 M&E Installations 0%
3406 Cable Tray, Conduit and Wiring 0%
3407 Electrical boards and connections 0%
3408 Electrical accessories 0%
3409 Light fittings and ceiling fans 0%
3410 Hot and cold water 0%
3411 Waste and sewage incl. biobox 0%
3412 Toilet ventilation, grilles 0%
3413 Kid's club( subject to receipt of GFW drawings) 0%
3414 substructure 0%
3415 set out 0%
3416 Excavate 0%
3417 Conc. Foundation 0%
3418 Backfill ( where applicable ) 0%
3419 termite treatment 0%
3420 DPC (where applicable) 0%
3421 M&E inlet/outlet works 0%
3422 frame 0%
3423 set kickers 0%
3424 Conc. Columns & shear walls 0%
3425 Conc. G. F Beams 0%
3426 Conc. Plantroom 0%
3427 Conc. Floor slab 0%
3428 Blockwork 0%
3429 Conc. Ring & tie beams 0%
3430 Roof & Ceiling 0%
3431 Fix wall plate & truss 0%
3432 Fix purlins and rafters 0%
3433 Fix shingles ( subject to receipt of timber) 0%
3434 Fix ceiing battens & joists 0%
3435 Fix ceiling boards 0%
3436 Finishes 0%
3437 Wall plaster (internal & External) 0%
3438 M&E 1st fix 0%
3439 Floor finishes 0%
3440 Fix windows & doors 0%
3441 M&E final fix 0%
3442 Fix fittings and Fixtures 0%
3443 M&E Installations 0%
3444 Cable Tray, Conduit and Wiring 0%
3445 Electrical boards and connections 0%
3446 Electrical accessories 0%
3447 Light fittings and ceiling fans 0%
3448 Hot and cold water 0%
3449 Waste and sewage incl. biobox 0%
3450 Electric water heater 0%
3451 Toilet ventilation, grilles 0%
3452 Recreation House( subject to receipt of GFW drawings) 0%
3453 substructure 0%
3454 set out 0%
3455 Excavate 0%
3456 Conc. Foundation 0%
3457 Backfill ( where applicable ) 0%
3458 termite treatment 0%
3459 DPC (where applicable) 0%
3460 M&E inlet/outlet works 0%
3461 frame 0%
3462 set kickers 0%
3463 Conc. Columns & shear walls 0%
3464 Conc. G. F Beams 0%
3465 Conc. Plantroom 0%
3466 Conc. Floor slab 0%
3467 Blockwork 0%
3468 Conc. Ring & tie beams 0%
3469 Roof & Ceiling 0%
3470 Fix wall plate & truss 0%
3471 Fix purlins and rafters 0%
3472 Fix shingles ( subject to receipt of timber) 0%

page 97
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2008 2009 2010 2011
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
3473 Fix ceiing battens & joists 0%
3474 Fix ceiling boards 0%
3475 Finishes 0%
3476 Wall plaster (internal & External) 0%
3477 M&E 1st fix 0%
3478 Floor finishes 0%
3479 Fix windows & doors 0%
3480 M&E final fix 0%
3481 Fix fittings and Fixtures 0%
3482 M&E Installations 0%
3483 Cable Tray, Conduit and Wiring 0%
3484 Electrical boards and connections 0%
3485 Electrical accessories 0%
3486 Light fittings and ceiling fans 0%
3487 Hot and cold water 0%
3488 Waste and sewage incl. biobox 0%
3489 Electric water heater 0%
3490 Toilet ventilation, grilles 0%
3491 Watersports rental( subject to receipt of GFW drawings) 0%
3492 substructure 0%
3493 set out 0%
3494 Excavate 0%
3495 Conc. Foundation 0%
3496 Backfill ( where applicable ) 0%
3497 termite treatment 0%
3498 DPC (where applicable) 0%
3499 M&E inlet/outlet works 0%
3500 frame 0%
3501 set kickers 0%
3502 Conc. Columns & shear walls 0%
3503 Conc. G. F Beams 0%
3504 Conc. Plantroom 0%
3505 Conc. Floor slab 0%
3506 Blockwork 0%
3507 Conc. Ring & tie beams 0%
3508 Roof & Ceiling 0%
3509 Fix wall plate & truss 0%
3510 Fix purlins and rafters 0%
3511 Fix shingles ( subject to receipt of timber) 0%
3512 Fix ceiing battens & joists 0%
3513 Fix ceiling boards 0%
3514 Finishes 0%
3515 Wall plaster (internal & External) 0%
3516 M&E 1st fix 0%
3517 Floor finishes 0%
3518 Fix windows & doors 0%
3519 M&E final fix 0%
3520 Fix fittings and Fixtures 0%
3521 M&E Installations 0%
3522 Cable Tray, Conduit and Wiring 0%
3523 Electrical boards and connections 0%
3524 Electrical accessories 0%
3525 Light fittings and ceiling fans 0%
3526 Hot and cold water 0%
3527 Waste and sewage incl. biobox 0%
3528 Toilet ventilation, grilles 0%
3529 3 Meals restaurant( subject to receipt of GFW drawings) 0%
3530 substructure 0%
3531 set out 0%
3532 Excavate 0%
3533 Conc. Foundation 0%
3534 Backfill ( where applicable ) 0%
3535 termite treatment 0%
3536 DPC (where applicable) 0%
3537 M&E inlet/outlet works 0%
3538 frame 0%
3539 set kickers 0%
3540 Conc. Columns & shear walls 0%
3541 Conc. G. F Beams 0%
3542 Conc. Plantroom 0%
3543 Conc. Floor slab 0%
3544 Blockwork 0%
3545 Conc. Ring & tie beams 0%
3546 Roof & Ceiling 0%
3547 Fix wall plate & truss 0%
3548 Fix purlins and rafters 0%
3549 Fix shingles ( subject to receipt of timber) 0%
3550 Fix ceiing battens & joists 0%
3551 Fix ceiling boards 0%
3552 Finishes 0%
3553 Wall plaster (internal & External) 0%
3554 M&E 1st fix 0%
3555 Floor finishes 0%
3556 Fix windows & doors 0%
3557 M&E final fix 0%
3558 Fix fittings and Fixtures 0%
3559 M&E Installations 0%
3560 Cable Tray, Conduit and Wiring 0%
3561 Electrical boards and connections 0%
3562 Electrical accessories 0%
3563 Light fittings and ceiling fans 0%
3564 Hot and cold water 0%
3565 Waste and sewage incl. biobox 0%
3566 Boiler 0%
3567 Chiller 0%
3568 Fan coil unit 0%
3569 Ducting and fans 0%
3570 Beach Pool Bar( subject to receipt of GFW drawings) 0%
3571 substructure 0%
3572 set out 0%
3573 Excavate 0%
3574 Conc. Foundation 0%
3575 Backfill ( where applicable ) 0%
3576 termite treatment 0%
3577 DPC (where applicable) 0%
3578 M&E inlet/outlet works 0%
3579 frame 0%
3580 set kickers 0%
3581 Conc. Columns & shear walls 0%
3582 Conc. G. F Beams 0%
3583 Conc. Plantroom 0%
3584 Conc. Floor slab 0%
3585 Blockwork 0%
3586 Conc. Ring & tie beams 0%

page 98
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2008 2009 2010 2011
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
3587 Roof & Ceiling 0%
3588 Fix wall plate & truss 0%
3589 Fix purlins and rafters 0%
3590 Fix shingles ( subject to receipt of timber) 0%
3591 Fix ceiing battens & joists 0%
3592 Fix ceiling boards 0%
3593 Finishes 0%
3594 Wall plaster (internal & External) 0%
3595 M&E 1st fix 0%
3596 Floor finishes 0%
3597 Fix windows & doors 0%
3598 M&E final fix 0%
3599 Fix fittings and Fixtures 0%
3600 M&E Installations 0%
3601 Cable Tray, Conduit and Wiring 0%
3602 Electrical boards and connections 0%
3603 Electrical accessories 0%
3604 Light fittings and ceiling fans 0%
3605 Hot and cold water 0%
3606 Waste and sewage incl. biobox 0%
3607 Electric water heater 0%
3608 Beach Pool 0%
3609 Split unit installation 0%
3610 Toilet ventilation, grilles 0%
3611 Signature Pool area( subject to receipt of GFW drawings) 0%
3612 substructure 0%
3613 set out 0%
3614 Excavate 0%
3615 Conc. Foundation 0%
3616 Backfill ( where applicable ) 0%
3617 termite treatment 0%
3618 DPC (where applicable) 0%
3619 M&E inlet/outlet works 0%
3620 frame 0%
3621 set kickers 0%
3622 Conc. Columns & shear walls 0%
3623 Conc. G. F Beams 0%
3624 Conc. Plantroom 0%
3625 Conc. Floor slab 0%
3626 Blockwork 0%
3627 Conc. Ring & tie beams 0%
3628 Roof & Ceiling 0%
3629 Fix wall plate & truss 0%
3630 Fix purlins and rafters 0%
3631 Fix shingles ( subject to receipt of timber) 0%
3632 Fix ceiing battens & joists 0%
3633 Fix ceiling boards 0%
3634 Finishes 0%
3635 Wall plaster (internal & External) 0%
3636 M&E 1st fix 0%
3637 Floor finishes 0%
3638 Fix windows & doors 0%
3639 M&E final fix 0%
3640 Fix fittings and Fixtures 0%
3641 M&E Installations 0%
3642 Cable Tray, Conduit and Wiring 0%
3643 Electrical boards and connections 0%
3644 Electrical accessories 0%
3645 Light fittings and ceiling fans 0%
3646 Hot and cold water 0%
3647 Waste and sewage incl. biobox 0%
3648 Electric water heater 0%
3649 Signature Pool 0%
3650 Wedding Chapel( subject to receipt of GFW drawings) 0%
3651 substructure 0%
3652 set out 0%
3653 Excavate 0%
3654 Conc. Foundation 0%
3655 Backfill ( where applicable ) 0%
3656 termite treatment 0%
3657 DPC (where applicable) 0%
3658 M&E inlet/outlet works 0%
3659 frame 0%
3660 set kickers 0%
3661 Conc. Columns & shear walls 0%
3662 Conc. G. F Beams 0%
3663 Conc. Plantroom 0%
3664 Conc. Floor slab 0%
3665 Blockwork 0%
3666 Conc. Ring & tie beams 0%
3667 Roof & Ceiling 0%
3668 Fix wall plate & truss 0%
3669 Fix purlins and rafters 0%
3670 Fix shingles ( subject to receipt of timber) 0%
3671 Fix ceiing battens & joists 0%
3672 Fix ceiling boards 0%
3673 Finishes 0%
3674 Wall plaster (internal & External) 0%
3675 M&E 1st fix 0%
3676 Floor finishes 0%
3677 Fix windows & doors 0%
3678 M&E final fix 0%
3679 Fix fittings and Fixtures 0%
3680 M&E Installations 0%
3681 Cable Tray, Conduit and Wiring 0%
3682 Electrical boards and connections 0%
3683 Electrical accessories 0%
3684 Light fittings and ceiling fans 0%
3685 BOH/Admin Building( subject to receipt of GFW drawings) 0%
3686 substructure 0%
3687 set out 0%
3688 Excavate 0%
3689 Conc. Foundation 0%
3690 Backfill ( where applicable ) 0%
3691 termite treatment 0%
3692 DPC (where applicable) 0%
3693 M&E inlet/outlet works 0%
3694 frame 0%
3695 set kickers 0%
3696 Conc. Columns & shear walls 0%
3697 Conc. G. F Beams 0%
3698 Conc. Plantroom 0%
3699 Conc. Floor slab 0%
3700 Blockwork 0%
3701 Conc. Ring & tie beams 0%

page 99
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2008 2009 2010 2011
Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr
3702 Roof & Ceiling 0%
3703 Fix wall plate & truss 0%
3704 Fix purlins and rafters 0%
3705 Fix shingles ( subject to receipt of timber) 0%
3706 Fix ceiing battens & joists 0%
3707 Fix ceiling boards 0%
3708 Finishes 0%
3709 Wall plaster (internal & External) 0%
3710 M&E 1st fix 0%
3711 Floor finishes 0%
3712 Fix windows & doors 0%
3713 M&E final fix 0%
3714 Fix fittings and Fixtures 0%
3715 M&E Installations 0%
3716 Cable Tray, Conduit and Wiring 0%
3717 Electrical boards and connections 0%
3718 Electrical accessories 0%
3719 Light fittings and ceiling fans 0%
3720 Hot and cold water 0%
3721 Waste and sewage incl. biobox 0%
3722 Electric water heater 0%
3723 Pond 0%
3724 Split unit installation 0%
3725 Toilet ventilation, grilles 0%
3726 Chi Sanctum( subject to receipt of GFW drawings) 0%
3727 substructure 0%
3728 set out 0%
3729 Excavate 0%
3730 Conc. Foundation 0%
3731 Backfill ( where applicable ) 0%
3732 termite treatment 0%
3733 DPC (where applicable) 0%
3734 M&E inlet/outlet works 0%
3735 frame 0%
3736 set kickers 0%
3737 Conc. Columns & shear walls 0%
3738 Conc. G. F Beams 0%
3739 Conc. Plantroom 0%
3740 Conc. Floor slab 0%
3741 Blockwork 0%
3742 Conc. Ring & tie beams 0%
3743 Roof & Ceiling 0%
3744 Fix wall plate & truss 0%
3745 Fix purlins and rafters 0%
3746 Fix shingles ( subject to receipt of timber) 0%
3747 Fix ceiing battens & joists 0%
3748 Fix ceiling boards 0%
3749 Finishes 0%
3750 Wall plaster (internal & External) 0%
3751 M&E 1st fix 0%
3752 Floor finishes 0%
3753 Fix windows & doors 0%
3754 M&E final fix 0%
3755 Fix fittings and Fixtures 0%
3756 M&E Installations 0%
3757 Cable Tray, Conduit and Wiring 0%
3758 Electrical boards and connections 0%
3759 Electrical accessories 0%
3760 Light fittings and ceiling fans 0%
3761 Hot and cold water 0%
3762 Waste and sewage incl. biobox 0%
3763 Electric water heater 0%
3764 Pond 0%
3765 Split unit installation 0%
3766 Toilet ventilation, grilles 0%
3767 Yoga Pavillion( subject to receipt of GFW drawings) 0%
3768 substructure 0%
3769 set out 0%
3770 Excavate 0%
3771 Conc. Foundation 0%
3772 Backfill ( where applicable ) 0%
3773 termite treatment 0%
3774 DPC (where applicable) 0%
3775 M&E inlet/outlet works 0%
3776 frame 0%
3777 set kickers 0%
3778 Conc. Columns & shear walls 0%
3779 Conc. G. F Beams 0%
3780 Conc. Plantroom 0%
3781 Conc. Floor slab 0%
3782 Blockwork 0%
3783 Conc. Ring & tie beams 0%
3784 Roof & Ceiling 0%
3785 Fix wall plate & truss 0%
3786 Fix purlins and rafters 0%
3787 Fix shingles ( subject to receipt of timber) 0%
3788 Fix ceiing battens & joists 0%
3789 Fix ceiling boards 0%
3790 Finishes 0%
3791 Wall plaster (internal & External) 0%
3792 M&E 1st fix 0%
3793 Floor finishes 0%
3794 Fix windows & doors 0%
3795 M&E final fix 0%
3796 Fix fittings and Fixtures 0%
3797 M&E Installations 0%
3798 Cable Tray, Conduit and Wiring 0%
3799 Electrical boards and connections 0%
3800 Electrical accessories 0%
3801 Light fittings and ceiling fans 0%
3802 Hot and cold water 0%
3803 Waste and sewage incl. biobox 0%
3804 Electric water heater 0%
3805 External works ( subject to receipt of GFW drawings) 0%
3814 Drainage works ( subject to receipt of EME details) 0%
3817 M&E Installations- External 0%
3828 Sundries 0%
3829 Site cleaning & demobilisation 0%
3830 Project Commissioning 0%

page 100
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

The following table summarises the timing of receipt of design


drawings and information. It has been shown that although
these drawings are significantly late, it has not affected progress
at site.

The reason for this is the earlier delays caused by setting out
and unforeseen ground conditions extended and revised the
original start dates of many activities. Consequently, as the
buildings revised schedule start date is much later than originally
planned drawings issued for construction had no impact.

However, as a consequence of the lateness in receipt of


detailed drawings, procurement of materials could not proceed
as originally planned.
Impacted Programme Baseline Programme
Item Building commencement completion commencement completion
1 P3 Presidential Villas 21-Jun-08 23-Mar-09 20-Jun-07 20-Mar-08
2 Sunset Deck 24-Jul-08 17-Mar-09 23-Jul-07 14-Mar-08
3 Employees Facilities Complex 30-Mar-08 03-Jan-09 14-Jun-07 19-Mar-08
4 Excom Villa 30-Mar-08 01-Jan-09 14-Jun-07 17-Mar-08
5 GM Villa 30-Mar-08 31-Dec-08 14-Jun-07 15-Mar-08
6 Health club 30-Mar-08 31-Dec-08 14-Jun-07 15-Mar-08
7 Single Treatment room 03-Jul-08 19-Mar-09 02-Jul-07 17-Mar-08
8 Couple treatment room 03-Jul-08 21-Mar-09 02-Jul-07 19-Mar-08
9 Sanctum 03-Jul-08 18-Mar-09 02-Jul-07 15-Mar-08
10 Yoga Pavilion 03-Jul-08 17-Mar-09 02-Jul-07 14-Mar-08
11 BOH Building 03-Jul-08 19-Mar-09 02-Jul-07 17-Mar-08
12 Wedding chapel 08-Jul-08 17-Mar-09 02-Jul-07 14-Mar-08
13 Seafood Resort 31-Aug-08 02-Jun-09 18-Jun-07 19-Mar-08
14 Retail Pavilion 31-Aug-08 28-May-09 18-Jun-07 14-Mar-08
15 Kid's club 03-Jul-08 17-Mar-09 02-Jul-07 14-Mar-08
16 Recreation House 03-Jul-08 17-Mar-09 02-Jul-07 14-Mar-08
17 Water sport Rental 03-Jul-08 17-Mar-09 02-Jul-07 14-Mar-08
18 Dive Center 03-Jul-08 17-Mar-09 02-Jul-07 14-Mar-08
19 Mechanical Area 24-Oct-08 09-Jan-09 22-Oct-07 19-Feb-08
20 3 Meal Restaurant 04-Sep-08 28-Mar-09 02-Jul-07 26-Mar-08
21 Signature Pool 04-Sep-08 18-Mar-09 02-Jul-07 15-Mar-08
22 Beach Pool Bar 04-Sep-08 19-Mar-09 02-Jul-07 17-Mar-08

Delays’ resulting from hard rock excavation is a parallel delay to


design drawings.

Items 1 - 18 relates to critical delays caused by hard rock


excavation for preceding structures. Items 19 – 22 relates to
delay arising from late design drawings, which is critical. More
delays will be encountered once excavation works proceed at
remaining locations.

As a result of the current delay caused by this event the time for
completion has not extended the current revised date of 9
September 2009.

Consequently, the revised completion date remains at 9


September 2009.

page 101
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

5.1.4.4. Event No 4 – Increased Scope of Works


ID Task Name
2007 2008 2009
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1 SHANGRI-LA , Long Island Resort Seychelles 0%
2 General Conditions and Preliminaries 0%
17 Site establishment 0%
41 Material/equipment procurement 0%
182 Lot 1 0%
183 A3 Villas ( 6 nos) 0%
184 Villa A3/01 0%
185 Substructure 0%
193 Frame 0%
194 set kickers 0%
195 Conc. Columns & shear walls 0%
196 Conc. G. F Beams 0%
197 M&E first fix 0%
198 Conc. Plantroom 0%
199 Conc. Floor slab & swimming pool base 0%
200 Blockwork 0%
201 Conc. Swimming pool sides & overflow channels 0%
202 Conc. Ring & tie beams 0%
203 Roof & Ceiling 0%
210 Finishes 0%
217 M&E Installations 0%
228 Villa A3/02 0%
229 substructure 0%
237 frame 0%
238 set kickers 0%
239 Conc. Columns & shear walls 0%
240 Conc. G. F Beams 0%
241 M&E first fix 0%
242 Conc. Plantroom 0%
243 Conc. Floor slab & swimming pool base 0%
244 Blockwork 0%
245 Conc. Swimming pool sides & overflow channels 0%
246 Conc. Ring & tie beams 0%
247 Roof & Ceiling 0%
254 Finishes 0%
262 M&E Installations 0%
273 Villa A3/03 0%
274 substructure 0%
282 frame 0%
283 set kickers 0%
284 Conc. Columns & shear walls 0%
285 Conc. G. F Beams 0%
286 M&E first fix 0%
287 Conc. Plantroom 0%
288 Conc. Floor slab & swimming pool base 0%
289 Blockwork 0%
290 Conc. Swimming pool sides & overflow channels 0%
291 Conc. Ring & tie beams 0%
292 Roof & Ceiling 0%
299 Finishes 0%
307 M&E Installations 0%
318 Villa A3/04 0%
319 substructure 0%
320 set out 0%
321 Excavate 0%
322 Conc. Foundation 0%
323 Backfill 0%
324 termite treatment 0%
325 DPC (where applicable) 0%
326 M&E inlet/outlet works - first fix 0%
327 frame 0%
328 set kickers 0%
329 Conc. Columns & shear walls 0%
330 Conc. G. F Beams 0%
331 M&E first fix 0%
332 Conc. Plantroom 0%
333 Conc. Floor slab & swimming pool base 0%
334 Blockwork 0%
335 Conc. Swimming pool sides & overflow channels 0%
336 Conc. Ring & tie beams 0%
337 Roof & Ceiling 0%
338 Fix wall plate & truss 0%
339 Fix purlins and rafters 0%
340 Fix shingles ( subject to receipt of timber) 0%
341 Fix ceiing battens & joists 0%
342 Fix ceiling boards 0%
343 M&E first fix 0%
344 Finishes 0%
345 Wall plaster (internal & External) 0%
346 M&E 1st fix 0%
347 Floor finishes 0%
348 Fix windows & doors 0%
349 Swimming pool finishes 0%
350 M&E final fix 0%
351 Fix fittings and Fixtures 0%
352 M&E Installations 0%
353 Cable Tray, Conduit and Wiring 0%
354 Electrical boards and connections 0%
355 Electrical accessories 0%
356 Light fittings and ceiling fans 0%
357 Hot and cold water 0%
358 Waste and sewage incl. biobox 0%
359 Electric water heater 0%
360 Swimming pool 0%
361 Split unit installation 0%
362 Toilet ventilation, grilles 0%
363 Villa A3/05 0%
364 substructure 0%
365 set out 0%
366 Excavate 0%
367 Conc. Foundation 0%
368 Backfill 0%
369 termite treatment 0%
370 DPC (where applicable) 0%
371 M&E inlet/outlet works - first fix 0%
372 frame 0%
373 set kickers 0%
374 Conc. Columns & shear walls 0%
375 Conc. G. F Beams 0%
376 M&E first fix 0%
377 Conc. Plantroom 0%

page 102
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2007 2008 2009 2010
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
378 Conc. Floor slab & swimming pool base 0%
379 Blockwork 0%
380 Conc. Swimming pool sides & overflow channels 0%
381 Conc. Ring & tie beams 0%
382 Roof & Ceiling 0%
383 Fix wall plate & truss 0%
384 Fix purlins and rafters 0%
385 Fix shingles ( subject to receipt of timber) 0%
386 Fix ceiing battens & joists 0%
387 Fix ceiling boards 0%
388 M&E first fix 0%
389 Finishes 0%
390 Wall plaster (internal & External) 0%
391 M&E 1st fix 0%
392 Floor finishes 0%
393 Fix windows & doors 0%
394 Swimming pool finishes 0%
395 M&E final fix 0%
396 Fix fittings and Fixtures 0%
397 M&E Installations 0%
398 Cable Tray, Conduit and Wiring 0%
399 Electrical boards and connections 0%
400 Electrical accessories 0%
401 Light fittings and ceiling fans 0%
402 Hot and cold water 0%
403 Waste and sewage incl. biobox 0%
404 Electric water heater 0%
405 Swimming pool 0%
406 Split unit installation 0%
407 Toilet ventilation, grilles 0%
408 Villa A3/06 0%
409 substructure 0%
410 set out 0%
411 Excavate 0%
412 Conc. Foundation 0%
413 Backfill 0%
414 termite treatment 0%
415 DPC (where applicable) 0%
416 M&E inlet/outlet works - first fix 0%
417 frame 0%
418 set kickers 0%
419 Conc. Columns & shear walls 0%
420 Conc. G. F Beams 0%
421 M&E first fix 0%
422 Conc. Plantroom 0%
423 Conc. Floor slab & swimming pool base 0%
424 Blockwork 0%
425 Conc. Swimming pool sides & overflow channels 0%
426 Conc. Ring & tie beams 0%
427 Roof & Ceiling 0%
434 Finishes 0%
442 M&E Installations 0%
453 C311 Executive Villas ( 1 nos) 0%
497 GM Villa ( subject to receipt of GFW drawings) 0%
537 Employees Facilities ( subject to receipt of GFW drawings) 0%
581 Laundry F& B service office ( subject to receipt of GFW drawings) 0%
625 Health Club/ Medical Centre( subject to receipt of GFW drawings) 0%
666 Administration Block ( subject to receipt of GFW drawings) 0%
707 1 bedroom Villa ( Excom, 6 units)( subject to receipt of GFW drawings) 0%
750 Main Lobby ( subject to receipt of GFW drawings) 0%
791 Tennis Courts ( subject to receipt of GFW drawings) 0%
807 External works ( subject to receipt of GFW drawings) 0%
816 Drainage works ( subject to receipt of EME details) 0%
819 Fuel Farm ( subject to receipt of EME details) 0%
823 Sea water Storage Tank & Water Tanks( subject to receipt of EME details) 0%
827 Desalination plant( subject to receipt of EME details) 0%
831 MLV Panel( subject to receipt of EME details) 0%
835 Step Up Transformer( subject to receipt of EME details) 0%
839 Incinerator/ Garbage room( subject to receipt of EME details) 0%
843 Sewer treatement plant( subject to receipt of EME details) 0%
847 Lot 2 0%
848 A3 Villas (17 nos) 0%
849 Villa A3/07 0%
850 substructure 0%
851 set out 0%
852 Excavate 0%
853 Conc. Foundation 0%
854 Backfill 0%
855 termite treatment 0%
856 DPC (where applicable) 0%
857 M&E inlet/outlet works - first fix 0%
858 frame 0%
859 set kickers 0%
860 Conc. Columns & shear walls 0%
861 Conc. G. F Beams 0%
862 M&E first fix 0%
863 Conc. Plantroom 0%
864 Conc. Floor slab & swimming pool base 0%
865 Blockwork 0%
866 Conc. Swimming pool sides & overflow channels 0%
867 Conc. Ring & tie beams 0%
868 Roof & Ceiling 0%
869 Fix wall plate & truss 0%
870 Fix purlins and rafters 0%
871 Fix shingles ( subject to receipt of timber) 0%
872 Fix ceiing battens & joists 0%
873 Fix ceiling boards 0%
874 M&E first fix 0%
875 Finishes 0%
876 Wall plaster (internal & External) 0%
877 M&E 1st fix 0%
878 Floor finishes 0%
879 Fix windows & doors 0%
880 Swimming pool finishes 0%
881 M&E final fix 0%
882 Fix fittings and Fixtures 0%
883 M&E Installations 0%
884 Cable Tray, Conduit and Wiring 0%
885 Electrical boards and connections 0%
886 Electrical accessories 0%
887 Light fittings and ceiling fans 0%
888 Hot and cold water 0%
889 Waste and sewage incl. biobox 0%
890 Electric water heater 0%
891 Swimming pool 0%
892 Split unit installation 0%
893 Toilet ventilation, grilles 0%

page 103
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2007 2008 2009 2010
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
894 Villa A3/08 0%
895 substructure 0%
896 set out 0%
897 Excavate 0%
898 Conc. Foundation 0%
899 Backfill 0%
900 termite treatment 0%
901 DPC (where applicable) 0%
902 M&E inlet/outlet works - first fix 0%
903 frame 0%
904 set kickers 0%
905 Conc. Columns & shear walls 0%
906 Conc. G. F Beams 0%
907 M&E first fix 0%
908 Conc. Plantroom 0%
909 Conc. Floor slab & swimming pool base 0%
910 Blockwork 0%
911 Conc. Swimming pool sides & overflow channels 0%
912 Conc. Ring & tie beams 0%
913 Roof & Ceiling 0%
920 Finishes 0%
928 M&E Installations 0%
939 Villa A3/09 0%
940 substructure 0%
941 set out 0%
942 Excavate 0%
943 Conc. Foundation 0%
944 Backfill 0%
945 termite treatment 0%
946 DPC (where applicable) 0%
947 M&E inlet/outlet works - first fix 0%
948 frame 0%
949 set kickers 0%
950 Conc. Columns & shear walls 0%
951 Conc. G. F Beams 0%
952 M&E first fix 0%
953 Conc. Plantroom 0%
954 Conc. Floor slab & swimming pool base 0%
955 Blockwork 0%
956 Conc. Swimming pool sides & overflow channels 0%
957 Conc. Ring & tie beams 0%
958 Roof & Ceiling 0%
965 Finishes 0%
973 M&E Installations 0%
984 Villa A3/10 0%
985 substructure 0%
986 set out 0%
987 Excavate 0%
988 Conc. Foundation 0%
989 Backfill 0%
990 termite treatment 0%
991 DPC (where applicable) 0%
992 M&E inlet/outlet works - first fix 0%
993 frame 0%
994 set kickers 0%
995 Conc. Columns & shear walls 0%
996 Conc. G. F Beams 0%
997 M&E first fix 0%
998 Conc. Plantroom 0%
999 Conc. Floor slab & swimming pool base 0%
1000 Blockwork 0%
1001 Conc. Swimming pool sides & overflow channels 0%
1002 Conc. Ring & tie beams 0%
1003 Roof & Ceiling 0%
1010 Finishes 0%
1018 M&E Installations 0%
1029 Villa A3/11 0%
1030 substructure 0%
1031 set out 0%
1032 Excavate 0%
1033 Conc. Foundation 0%
1034 Backfill 0%
1035 termite treatment 0%
1036 DPC (where applicable) 0%
1037 M&E inlet/outlet works - first fix 0%
1038 frame 0%
1039 set kickers 0%
1040 Conc. Columns & shear walls 0%
1041 Conc. G. F Beams 0%
1042 M&E first fix 0%
1043 Conc. Plantroom 0%
1044 Conc. Floor slab & swimming pool base 0%
1045 Blockwork 0%
1046 Conc. Swimming pool sides & overflow channels 0%
1047 Conc. Ring & tie beams 0%
1048 Roof & Ceiling 0%
1055 Finishes 0%
1063 M&E Installations 0%
1074 Villa A3/12 0%
1075 substructure 0%
1076 set out 0%
1077 Excavate 0%
1078 Conc. Foundation 0%
1079 Backfill 0%
1080 termite treatment 0%
1081 DPC (where applicable) 0%
1082 M&E inlet/outlet works - first fix 0%
1083 frame 0%
1084 set kickers 0%
1085 Conc. Columns & shear walls 0%
1086 Conc. G. F Beams 0%
1087 M&E first fix 0%
1088 Conc. Plantroom 0%
1089 Conc. Floor slab & swimming pool base 0%
1090 Blockwork 0%
1091 Conc. Swimming pool sides & overflow channels 0%
1092 Conc. Ring & tie beams 0%
1093 Roof & Ceiling 0%
1094 Fix wall plate & truss 0%
1095 Fix purlins and rafters 0%
1096 Fix shingles ( subject to receipt of timber) 0%
1097 Fix ceiing battens & joists 0%
1098 Fix ceiling boards 0%
1099 M&E first fix 0%

page 104
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2007 2008 2009 2010
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
1100 Finishes 0%
1101 Wall plaster (internal & External) 0%
1102 M&E 1st fix 0%
1103 Floor finishes 0%
1104 Fix windows & doors 0%
1105 Swimming pool finishes 0%
1106 M&E final fix 0%
1107 Fix fittings and Fixtures 0%
1108 M&E Installations 0%
1109 Cable Tray, Conduit and Wiring 0%
1110 Electrical boards and connections 0%
1111 Electrical accessories 0%
1112 Light fittings and ceiling fans 0%
1113 Hot and cold water 0%
1114 Waste and sewage incl. biobox 0%
1115 Electric water heater 0%
1116 Swimming pool 0%
1117 Split unit installation 0%
1118 Toilet ventilation, grilles 0%
1119 Villa A3/13 0%
1120 substructure 0%
1121 set out 0%
1122 Excavate 0%
1123 Conc. Foundation 0%
1124 Backfill 0%
1125 termite treatment 0%
1126 DPC (where applicable) 0%
1127 M&E inlet/outlet works - first fix 0%
1128 frame 0%
1129 set kickers 0%
1130 Conc. Columns & shear walls 0%
1131 Conc. G. F Beams 0%
1132 M&E first fix 0%
1133 Conc. Plantroom 0%
1134 Conc. Floor slab & swimming pool base 0%
1135 Blockwork 0%
1136 Conc. Swimming pool sides & overflow channels 0%
1137 Conc. Ring & tie beams 0%
1138 Roof & Ceiling 0%
1139 Fix wall plate & truss 0%
1140 Fix purlins and rafters 0%
1141 Fix shingles ( subject to receipt of timber) 0%
1142 Fix ceiing battens & joists 0%
1143 Fix ceiling boards 0%
1144 M&E first fix 0%
1145 Finishes 0%
1146 Wall plaster (internal & External) 0%
1147 M&E 1st fix 0%
1148 Floor finishes 0%
1149 Fix windows & doors 0%
1150 Swimming pool finishes 0%
1151 M&E final fix 0%
1152 Fix fittings and Fixtures 0%
1153 M&E Installations 0%
1154 Cable Tray, Conduit and Wiring 0%
1155 Electrical boards and connections 0%
1156 Electrical accessories 0%
1157 Light fittings and ceiling fans 0%
1158 Hot and cold water 0%
1159 Waste and sewage incl. biobox 0%
1160 Electric water heater 0%
1161 Swimming pool 0%
1162 Split unit installation 0%
1163 Toilet ventilation, grilles 0%
1164 Villa A3/18 0%
1165 substructure 0%
1166 set out 0%
1167 Excavate 0%
1168 Conc. Foundation 0%
1169 Backfill 0%
1170 termite treatment 0%
1171 DPC (where applicable) 0%
1172 M&E inlet/outlet works - first fix 0%
1173 frame 0%
1174 set kickers 0%
1175 Conc. Columns & shear walls 0%
1176 Conc. G. F Beams 0%
1177 M&E first fix 0%
1178 Conc. Plantroom 0%
1179 Conc. Floor slab & swimming pool base 0%
1180 Blockwork 0%
1181 Conc. Swimming pool sides & overflow channels 0%
1182 Conc. Ring & tie beams 0%
1183 Roof & Ceiling 0%
1184 Fix wall plate & truss 0%
1185 Fix purlins and rafters 0%
1186 Fix shingles ( subject to receipt of timber) 0%
1187 Fix ceiing battens & joists 0%
1188 Fix ceiling boards 0%
1189 M&E first fix 0%
1190 Finishes 0%
1191 Wall plaster (internal & External) 0%
1192 M&E 1st fix 0%
1193 Floor finishes 0%
1194 Fix windows & doors 0%
1195 Swimming pool finishes 0%
1196 M&E final fix 0%
1197 Fix fittings and Fixtures 0%
1198 M&E Installations 0%
1199 Cable Tray, Conduit and Wiring 0%
1200 Electrical boards and connections 0%
1201 Electrical accessories 0%
1202 Light fittings and ceiling fans 0%
1203 Hot and cold water 0%
1204 Waste and sewage incl. biobox 0%
1205 Electric water heater 0%
1206 Swimming pool 0%
1207 Split unit installation 0%
1208 Toilet ventilation, grilles 0%
1209 Villa A3/19 0%
1210 substructure 0%
1211 set out 0%

page 105
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2007 2008 2009 2010
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
1212 Excavate 0%
1213 Conc. Foundation 0%
1214 Backfill 0%
1215 termite treatment 0%
1216 DPC (where applicable) 0%
1217 M&E inlet/outlet works - first fix 0%
1218 frame 0%
1219 set kickers 0%
1220 Conc. Columns & shear walls 0%
1221 Conc. G. F Beams 0%
1222 M&E first fix 0%
1223 Conc. Plantroom 0%
1224 Conc. Floor slab & swimming pool base 0%
1225 Blockwork 0%
1226 Conc. Swimming pool sides & overflow channels 0%
1227 Conc. Ring & tie beams 0%
1228 Roof & Ceiling 0%
1235 Finishes 0%
1243 M&E Installations 0%
1254 Villa A3/20 0%
1255 substructure 0%
1256 set out 0%
1257 Excavate 0%
1258 Conc. Foundation 0%
1259 Backfill 0%
1260 termite treatment 0%
1261 DPC (where applicable) 0%
1262 M&E inlet/outlet works - first fix 0%
1263 frame 0%
1264 set kickers 0%
1265 Conc. Columns & shear walls 0%
1266 Conc. G. F Beams 0%
1267 M&E first fix 0%
1268 Conc. Plantroom 0%
1269 Conc. Floor slab & swimming pool base 0%
1270 Blockwork 0%
1271 Conc. Swimming pool sides & overflow channels 0%
1272 Conc. Ring & tie beams 0%
1273 Roof & Ceiling 0%
1280 Finishes 0%
1288 M&E Installations 0%
1299 Villa A3/21 0%
1300 substructure 0%
1301 set out 0%
1302 Excavate 0%
1303 Conc. Foundation 0%
1304 Backfill 0%
1305 termite treatment 0%
1306 DPC (where applicable) 0%
1307 M&E inlet/outlet works - first fix 0%
1308 frame 0%
1309 set kickers 0%
1310 Conc. Columns & shear walls 0%
1311 Conc. G. F Beams 0%
1312 M&E first fix 0%
1313 Conc. Plantroom 0%
1314 Conc. Floor slab & swimming pool base 0%
1315 Blockwork 0%
1316 Conc. Swimming pool sides & overflow channels 0%
1317 Conc. Ring & tie beams 0%
1318 Roof & Ceiling 0%
1325 Finishes 0%
1333 M&E Installations 0%
1344 Villa A3/22 0%
1345 substructure 0%
1346 set out 0%
1347 Excavate 0%
1348 Conc. Foundation 0%
1349 Backfill 0%
1350 termite treatment 0%
1351 DPC (where applicable) 0%
1352 M&E inlet/outlet works - first fix 0%
1353 frame 0%
1354 set kickers 0%
1355 Conc. Columns & shear walls 0%
1356 Conc. G. F Beams 0%
1357 M&E first fix 0%
1358 Conc. Plantroom 0%
1359 Conc. Floor slab & swimming pool base 0%
1360 Blockwork 0%
1361 Conc. Swimming pool sides & overflow channels 0%
1362 Conc. Ring & tie beams 0%
1363 Roof & Ceiling 0%
1364 Fix wall plate & truss 0%
1365 Fix purlins and rafters 0%
1366 Fix shingles ( subject to receipt of timber) 0%
1367 Fix ceiing battens & joists 0%
1368 Fix ceiling boards 0%
1369 M&E first fix 0%
1370 Finishes 0%
1371 Wall plaster (internal & External) 0%
1372 M&E 1st fix 0%
1373 Floor finishes 0%
1374 Fix windows & doors 0%
1375 Swimming pool finishes 0%
1376 M&E final fix 0%
1377 Fix fittings and Fixtures 0%
1378 M&E Installations 0%
1379 Cable Tray, Conduit and Wiring 0%
1380 Electrical boards and connections 0%
1381 Electrical accessories 0%
1382 Light fittings and ceiling fans 0%
1383 Hot and cold water 0%
1384 Waste and sewage incl. biobox 0%
1385 Electric water heater 0%
1386 Swimming pool 0%
1387 Split unit installation 0%
1388 Toilet ventilation, grilles 0%
1389 Villa A3/23 0%
1390 substructure 0%
1391 set out 0%
1392 Excavate 0%
1393 Conc. Foundation 0%
1394 Backfill 0%
1395 termite treatment 0%
1396 DPC (where applicable) 0%
1397 M&E inlet/outlet works - first fix 0%

page 106
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2007 2008 2009 2010
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
1398 frame 0%
1399 set kickers 0%
1400 Conc. Columns & shear walls 0%
1401 Conc. G. F Beams 0%
1402 M&E first fix 0%
1403 Conc. Plantroom 0%
1404 Conc. Floor slab & swimming pool base 0%
1405 Blockwork 0%
1406 Conc. Swimming pool sides & overflow channels 0%
1407 Conc. Ring & tie beams 0%
1408 Roof & Ceiling 0%
1409 Fix wall plate & truss 0%
1410 Fix purlins and rafters 0%
1411 Fix shingles ( subject to receipt of timber) 0%
1412 Fix ceiing battens & joists 0%
1413 Fix ceiling boards 0%
1414 M&E first fix 0%
1415 Finishes 0%
1416 Wall plaster (internal & External) 0%
1417 M&E 1st fix 0%
1418 Floor finishes 0%
1419 Fix windows & doors 0%
1420 Swimming pool finishes 0%
1421 M&E final fix 0%
1422 Fix fittings and Fixtures 0%
1423 M&E Installations 0%
1424 Cable Tray, Conduit and Wiring 0%
1425 Electrical boards and connections 0%
1426 Electrical accessories 0%
1427 Light fittings and ceiling fans 0%
1428 Hot and cold water 0%
1429 Waste and sewage incl. biobox 0%
1430 Electric water heater 0%
1431 Swimming pool 0%
1432 Split unit installation 0%
1433 Toilet ventilation, grilles 0%
1434 Villa A3/24 0%
1435 substructure 0%
1436 set out 0%
1437 Excavate 0%
1438 Conc. Foundation 0%
1439 Backfill 0%
1440 termite treatment 0%
1441 DPC (where applicable) 0%
1442 M&E inlet/outlet works - first fix 0%
1443 frame 0%
1444 set kickers 0%
1445 Conc. Columns & shear walls 0%
1446 Conc. G. F Beams 0%
1447 M&E first fix 0%
1448 Conc. Plantroom 0%
1449 Conc. Floor slab & swimming pool base 0%
1450 Blockwork 0%
1451 Conc. Swimming pool sides & overflow channels 0%
1452 Conc. Ring & tie beams 0%
1453 Roof & Ceiling 0%
1454 Fix wall plate & truss 0%
1455 Fix purlins and rafters 0%
1456 Fix shingles ( subject to receipt of timber) 0%
1457 Fix ceiing battens & joists 0%
1458 Fix ceiling boards 0%
1459 M&E first fix 0%
1460 Finishes 0%
1461 Wall plaster (internal & External) 0%
1462 M&E 1st fix 0%
1463 Floor finishes 0%
1464 Fix windows & doors 0%
1465 Swimming pool finishes 0%
1466 M&E final fix 0%
1467 Fix fittings and Fixtures 0%
1468 M&E Installations 0%
1469 Cable Tray, Conduit and Wiring 0%
1470 Electrical boards and connections 0%
1471 Electrical accessories 0%
1472 Light fittings and ceiling fans 0%
1473 Hot and cold water 0%
1474 Waste and sewage incl. biobox 0%
1475 Electric water heater 0%
1476 Swimming pool 0%
1477 Split unit installation 0%
1478 Toilet ventilation, grilles 0%
1479 Villa A3/25 0%
1480 substructure 0%
1481 set out 0%
1482 Excavate 0%
1483 Conc. Foundation 0%
1484 Backfill 0%
1485 termite treatment 0%
1486 DPC (where applicable) 0%
1487 M&E inlet/outlet works - first fix 0%
1488 frame 0%
1489 set kickers 0%
1490 Conc. Columns & shear walls 0%
1491 Conc. G. F Beams 0%
1492 M&E first fix 0%
1493 Conc. Plantroom 0%
1494 Conc. Floor slab & swimming pool base 0%
1495 Blockwork 0%
1496 Conc. Swimming pool sides & overflow channels 0%
1497 Conc. Ring & tie beams 0%
1498 Roof & Ceiling 0%
1499 Fix wall plate & truss 0%
1500 Fix purlins and rafters 0%
1501 Fix shingles ( subject to receipt of timber) 0%
1502 Fix ceiing battens & joists 0%
1503 Fix ceiling boards 0%
1504 M&E first fix 0%
1505 Finishes 0%
1506 Wall plaster (internal & External) 0%
1507 M&E 1st fix 0%
1508 Floor finishes 0%
1509 Fix windows & doors 0%
1510 Swimming pool finishes 0%
1511 M&E final fix 0%
1512 Fix fittings and Fixtures 0%

page 107
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2007 2008 2009 2010
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
1513 M&E Installations 0%
1514 Cable Tray, Conduit and Wiring 0%
1515 Electrical boards and connections 0%
1516 Electrical accessories 0%
1517 Light fittings and ceiling fans 0%
1518 Hot and cold water 0%
1519 Waste and sewage incl. biobox 0%
1520 Electric water heater 0%
1521 Swimming pool 0%
1522 Split unit installation 0%
1523 Toilet ventilation, grilles 0%
1524 Villa A3/26 0%
1525 substructure 0%
1526 set out 0%
1527 Excavate 0%
1528 Conc. Foundation 0%
1529 Backfill 0%
1530 termite treatment 0%
1531 DPC (where applicable) 0%
1532 M&E inlet/outlet works - first fix 0%
1533 frame 0%
1534 set kickers 0%
1535 Conc. Columns & shear walls 0%
1536 Conc. G. F Beams 0%
1537 M&E first fix 0%
1538 Conc. Plantroom 0%
1539 Conc. Floor slab & swimming pool base 0%
1540 Blockwork 0%
1541 Conc. Swimming pool sides & overflow channels 0%
1542 Conc. Ring & tie beams 0%
1543 Roof & Ceiling 0%
1550 Finishes 0%
1558 M&E Installations 0%
1569 Villa A3/27 0%
1570 substructure 0%
1571 set out 0%
1572 Excavate 0%
1573 Conc. Foundation 0%
1574 Backfill 0%
1575 termite treatment 0%
1576 DPC (where applicable) 0%
1577 M&E inlet/outlet works - first fix 0%
1578 frame 0%
1579 set kickers 0%
1580 Conc. Columns & shear walls 0%
1581 Conc. G. F Beams 0%
1582 M&E first fix 0%
1583 Conc. Plantroom 0%
1584 Conc. Floor slab & swimming pool base 0%
1585 Blockwork 0%
1586 Conc. Swimming pool sides & overflow channels 0%
1587 Conc. Ring & tie beams 0%
1588 Roof & Ceiling 0%
1595 Finishes 0%
1603 M&E Installations 0%
1614 B223 Villas ( 7 nos) 0%
1615 Villa B2/01 0%
1616 substructure 0%
1617 set out 0%
1618 Excavate 0%
1619 Conc. Foundation 0%
1620 Backfill 0%
1621 termite treatment 0%
1622 DPC (where applicable) 0%
1623 M&E inlet/outlet works - first fix 0%
1624 frame 0%
1625 set kickers 0%
1626 Conc. Columns & shear walls to GF 0%
1627 Conc. Plantrooms 0%
1628 M&E first fix GF 0%
1629 Conc. GF slab and beams 0%
1630 Blockwork up to FF slab 0%
1631 set kickers on GF 0%
1632 Conc. Columns & shear walls to FF 0%
1633 M&E first fix FF 0%
1634 Conc. FF slab & beams 0%
1635 Blockwork up to roof 0%
1636 set kickers on FF 0%
1637 Conc. Columns & shear walls to roof 0%
1638 M&E first fix roof 0%
1639 Conc. Ring & tie beams 0%
1640 Roof & Ceiling 0%
1647 Finishes 0%
1654 M&E Installations 0%
1665 Villa B2/02 0%
1666 substructure 0%
1667 set out 0%
1668 Excavate 0%
1669 Conc. Foundation 0%
1670 Backfill 0%
1671 termite treatment 0%
1672 DPC (where applicable) 0%
1673 M&E inlet/outlet works - first fix 0%
1674 frame 0%
1675 set kickers 0%
1676 Conc. Columns & shear walls to GF 0%
1677 Conc. Plantrooms 0%
1678 M&E first fix GF 0%
1679 Conc. GF slab and beams 0%
1680 Blockwork up to FF slab 0%
1681 set kickers on GF 0%
1682 Conc. Columns & shear walls to FF 0%
1683 M&E first fix FF 0%
1684 Conc. FF slab & beams 0%
1685 Blockwork up to roof 0%
1686 set kickers on FF 0%
1687 Conc. Columns & shear walls to roof 0%
1688 M&E first fix roof 0%
1689 Conc. Ring & tie beams 0%
1690 Roof & Ceiling 0%
1697 Finishes 0%
1704 M&E Installations 0%
1715 Villa B2/04 0%
1716 substructure 0%
1717 set out 0%
1718 Excavate 0%

page 108
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2007 2008 2009 2010
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
1719 Conc. Foundation 0%
1720 Backfill 0%
1721 termite treatment 0%
1722 DPC (where applicable) 0%
1723 M&E inlet/outlet works - first fix 0%
1724 frame 0%
1725 set kickers 0%
1726 Conc. Columns & shear walls to GF 0%
1727 Conc. Plantrooms 0%
1728 M&E first fix GF 0%
1729 Conc. GF slab and beams 0%
1730 Blockwork up to FF slab 0%
1731 set kickers on GF 0%
1732 Conc. Columns & shear walls to FF 0%
1733 M&E first fix FF 0%
1734 Conc. FF slab & beams 0%
1735 Blockwork up to roof 0%
1736 set kickers on FF 0%
1737 Conc. Columns & shear walls to roof 0%
1738 M&E first fix roof 0%
1739 Conc. Ring & tie beams 0%
1740 Roof & Ceiling 0%
1747 Finishes 0%
1754 M&E Installations 0%
1765 Villa B2/05 0%
1766 substructure 0%
1767 set out 0%
1768 Excavate 0%
1769 Conc. Foundation 0%
1770 Backfill 0%
1771 termite treatment 0%
1772 DPC (where applicable) 0%
1773 M&E inlet/outlet works - first fix 0%
1774 frame 0%
1775 set kickers 0%
1776 Conc. Columns & shear walls to GF 0%
1777 Conc. Plantrooms 0%
1778 M&E first fix GF 0%
1779 Conc. GF slab and beams 0%
1780 Blockwork up to FF slab 0%
1781 set kickers on GF 0%
1782 Conc. Columns & shear walls to FF 0%
1783 M&E first fix FF 0%
1784 Conc. FF slab & beams 0%
1785 Blockwork up to roof 0%
1786 set kickers on FF 0%
1787 Conc. Columns & shear walls to roof 0%
1788 M&E first fix roof 0%
1789 Conc. Ring & tie beams 0%
1790 Roof & Ceiling 0%
1797 Finishes 0%
1804 M&E Installations 0%
1815 Villa B2/06 0%
1816 substructure 0%
1817 set out 0%
1818 Excavate 0%
1819 Conc. Foundation 0%
1820 Backfill 0%
1821 termite treatment 0%
1822 DPC (where applicable) 0%
1823 M&E inlet/outlet works - first fix 0%
1824 frame 0%
1825 set kickers 0%
1826 Conc. Columns & shear walls to GF 0%
1827 Conc. Plantrooms 0%
1828 M&E first fix GF 0%
1829 Conc. GF slab and beams 0%
1830 Blockwork up to FF slab 0%
1831 set kickers on GF 0%
1832 Conc. Columns & shear walls to FF 0%
1833 M&E first fix FF 0%
1834 Conc. FF slab & beams 0%
1835 Blockwork up to roof 0%
1836 set kickers on FF 0%
1837 Conc. Columns & shear walls to roof 0%
1838 M&E first fix roof 0%
1839 Conc. Ring & tie beams 0%
1840 Roof & Ceiling 0%
1847 Finishes 0%
1854 M&E Installations 0%
1865 Villa B2/07 0%
1866 substructure 0%
1867 set out 0%
1868 Excavate 0%
1869 Conc. Foundation 0%
1870 Backfill 0%
1871 termite treatment 0%
1872 DPC (where applicable) 0%
1873 M&E inlet/outlet works - first fix 0%
1874 frame 0%
1875 set kickers 0%
1876 Conc. Columns & shear walls to GF 0%
1877 Conc. Plantrooms 0%
1878 M&E first fix GF 0%
1879 Conc. GF slab and beams 0%
1880 Blockwork up to FF slab 0%
1881 set kickers on GF 0%
1882 Conc. Columns & shear walls to FF 0%
1883 M&E first fix FF 0%
1884 Conc. FF slab & beams 0%
1885 Blockwork up to roof 0%
1886 set kickers on FF 0%
1887 Conc. Columns & shear walls to roof 0%
1888 M&E first fix roof 0%
1889 Conc. Ring & tie beams 0%
1890 Roof & Ceiling 0%
1897 Finishes 0%
1904 M&E Installations 0%
1915 Villa B2/08 0%
1916 substructure 0%
1917 set out 0%
1918 Excavate 0%
1919 Conc. Foundation 0%

page 109
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2007 2008 2009 2010
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
1920 Backfill 0%
1921 termite treatment 0%
1922 DPC (where applicable) 0%
1923 M&E inlet/outlet works - first fix 0%
1924 frame 0%
1925 set kickers 0%
1926 Conc. Columns & shear walls to GF 0%
1927 Conc. Plantrooms 0%
1928 M&E first fix GF 0%
1929 Conc. GF slab and beams 0%
1930 Blockwork up to FF slab 0%
1931 set kickers on GF 0%
1932 Conc. Columns & shear walls to FF 0%
1933 M&E first fix FF 0%
1934 Conc. FF slab & beams 0%
1935 Blockwork up to roof 0%
1936 set kickers on FF 0%
1937 Conc. Columns & shear walls to roof 0%
1938 M&E first fix roof 0%
1939 Conc. Ring & tie beams 0%
1940 Roof & Ceiling 0%
1947 Finishes 0%
1954 M&E Installations 0%
1965 B4 Villa (2 nos.) 0%
2056 Retail 1( subject to receipt of GFW drawings) 0%
2094 Retail 2( subject to receipt of GFW drawings) 0%
2132 Retail 3( subject to receipt of GFW drawings) 0%
2170 Seafood resort( subject to receipt of GFW drawings) 0%
2211 Greeting Pavillion( subject to receipt of GFW drawings) 0%
2250 External works ( subject to receipt of GFW drawings) 0%
2259 Drainage works ( subject to receipt of EME details) 0%
2262 Lot 3 0%
2263 A3 Villas ( 9 nos) 0%
2264 Villa A3/14 0%
2265 Substructure 0%
2266 set out 0%
2267 Excavate 0%
2268 Conc. Foundation 0%
2269 Backfill 0%
2270 termite treatment 0%
2271 DPC (where applicable) 0%
2272 M&E inlet/outlet works - first fix 0%
2273 Frame 0%
2274 set kickers 0%
2275 Conc. Columns & shear walls 0%
2276 Conc. G. F Beams 0%
2277 M&E first fix 0%
2278 Conc. Plantroom 0%
2279 Conc. Floor slab & swimming pool base 0%
2280 Blockwork 0%
2281 Conc. Swimming pool sides & overflow channels 0%
2282 Conc. Ring & tie beams 0%
2283 Roof & Ceiling 0%
2284 Fix wall plate & truss 0%
2285 Fix purlins and rafters 0%
2286 Fix shingles ( subject to receipt of timber) 0%
2287 Fix ceiing battens & joists 0%
2288 Fix ceiling boards 0%
2289 M&E first fix 0%
2290 Finishes 0%
2291 Wall plaster (internal & External) 0%
2292 M&E 1st fix 0%
2293 Floor finishes 0%
2294 Fix windows & doors 0%
2295 Swimming pool finishes 0%
2296 M&E final fix 0%
2297 Fix fittings and Fixtures 0%
2298 M&E Installations 0%
2299 Cable Tray, Conduit and Wiring 0%
2300 Electrical boards and connections 0%
2301 Electrical accessories 0%
2302 Light fittings and ceiling fans 0%
2303 Hot and cold water 0%
2304 Waste and sewage incl. biobox 0%
2305 Electric water heater 0%
2306 Swimming pool 0%
2307 Split unit installation 0%
2308 Toilet ventilation, grilles 0%
2309 Villa A3/15 0%
2310 substructure 0%
2311 set out 0%
2312 Excavate 0%
2313 Conc. Foundation 0%
2314 Backfill 0%
2315 termite treatment 0%
2316 DPC (where applicable) 0%
2317 M&E inlet/outlet works - first fix 0%
2318 frame 0%
2319 set kickers 0%
2320 Conc. Columns & shear walls 0%
2321 Conc. G. F Beams 0%
2322 M&E first fix 0%
2323 Conc. Plantroom 0%
2324 Conc. Floor slab & swimming pool base 0%
2325 Blockwork 0%
2326 Conc. Swimming pool sides & overflow channels 0%
2327 Conc. Ring & tie beams 0%
2328 Roof & Ceiling 0%
2329 Fix wall plate & truss 0%
2330 Fix purlins and rafters 0%
2331 Fix shingles ( subject to receipt of timber) 0%
2332 Fix ceiing battens & joists 0%
2333 Fix ceiling boards 0%
2334 M&E first fix 0%
2335 Finishes 0%
2336 Wall plaster (internal & External) 0%
2337 M&E 1st fix 0%
2338 Floor finishes 0%
2339 Fix windows & doors 0%
2340 Swimming pool finishes 0%
2341 M&E final fix 0%
2342 Fix fittings and Fixtures 0%
2343 M&E Installations 0%
2344 Cable Tray, Conduit and Wiring 0%
2345 Electrical boards and connections 0%

page 110
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2007 2008 2009 2010
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
2346 Electrical accessories 0%
2347 Light fittings and ceiling fans 0%
2348 Hot and cold water 0%
2349 Waste and sewage incl. biobox 0%
2350 Electric water heater 0%
2351 Swimming pool 0%
2352 Split unit installation 0%
2353 Toilet ventilation, grilles 0%
2354 Villa A3/16 0%
2355 substructure 0%
2356 set out 0%
2357 Excavate 0%
2358 Conc. Foundation 0%
2359 Backfill 0%
2360 termite treatment 0%
2361 DPC (where applicable) 0%
2362 M&E inlet/outlet works - first fix 0%
2363 frame 0%
2364 set kickers 0%
2365 Conc. Columns & shear walls 0%
2366 Conc. G. F Beams 0%
2367 M&E first fix 0%
2368 Conc. Plantroom 0%
2369 Conc. Floor slab & swimming pool base 0%
2370 Blockwork 0%
2371 Conc. Swimming pool sides & overflow channels 0%
2372 Conc. Ring & tie beams 0%
2373 Roof & Ceiling 0%
2374 Fix wall plate & truss 0%
2375 Fix purlins and rafters 0%
2376 Fix shingles ( subject to receipt of timber) 0%
2377 Fix ceiing battens & joists 0%
2378 Fix ceiling boards 0%
2379 M&E first fix 0%
2380 Finishes 0%
2381 Wall plaster (internal & External) 0%
2382 M&E 1st fix 0%
2383 Floor finishes 0%
2384 Fix windows & doors 0%
2385 Swimming pool finishes 0%
2386 M&E final fix 0%
2387 Fix fittings and Fixtures 0%
2388 M&E Installations 0%
2389 Cable Tray, Conduit and Wiring 0%
2390 Electrical boards and connections 0%
2391 Electrical accessories 0%
2392 Light fittings and ceiling fans 0%
2393 Hot and cold water 0%
2394 Waste and sewage incl. biobox 0%
2395 Electric water heater 0%
2396 Swimming pool 0%
2397 Split unit installation 0%
2398 Toilet ventilation, grilles 0%
2399 Villa A3/17 0%
2400 substructure 0%
2401 set out 0%
2402 Excavate 0%
2403 Conc. Foundation 0%
2404 Backfill 0%
2405 termite treatment 0%
2406 DPC (where applicable) 0%
2407 M&E inlet/outlet works - first fix 0%
2408 frame 0%
2409 set kickers 0%
2410 Conc. Columns & shear walls 0%
2411 Conc. G. F Beams 0%
2412 M&E first fix 0%
2413 Conc. Plantroom 0%
2414 Conc. Floor slab & swimming pool base 0%
2415 Blockwork 0%
2416 Conc. Swimming pool sides & overflow channels 0%
2417 Conc. Ring & tie beams 0%
2418 Roof & Ceiling 0%
2419 Fix wall plate & truss 0%
2420 Fix purlins and rafters 0%
2421 Fix shingles ( subject to receipt of timber) 0%
2422 Fix ceiing battens & joists 0%
2423 Fix ceiling boards 0%
2424 M&E first fix 0%
2425 Finishes 0%
2426 Wall plaster (internal & External) 0%
2427 M&E 1st fix 0%
2428 Floor finishes 0%
2429 Fix windows & doors 0%
2430 Swimming pool finishes 0%
2431 M&E final fix 0%
2432 Fix fittings and Fixtures 0%
2433 M&E Installations 0%
2434 Cable Tray, Conduit and Wiring 0%
2435 Electrical boards and connections 0%
2436 Electrical accessories 0%
2437 Light fittings and ceiling fans 0%
2438 Hot and cold water 0%
2439 Waste and sewage incl. biobox 0%
2440 Electric water heater 0%
2441 Swimming pool 0%
2442 Split unit installation 0%
2443 Toilet ventilation, grilles 0%
2444 Villa A3/28 0%
2445 substructure 0%
2446 set out 0%
2447 Excavate 0%
2448 Conc. Foundation 0%
2449 Backfill 0%
2450 termite treatment 0%
2451 DPC (where applicable) 0%
2452 M&E inlet/outlet works - first fix 0%
2453 frame 0%
2454 set kickers 0%
2455 Conc. Columns & shear walls 0%
2456 Conc. G. F Beams 0%
2457 M&E first fix 0%

page 111
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2007 2008 2009 2010
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
2458 Conc. Plantroom 0%
2459 Conc. Floor slab & swimming pool base 0%
2460 Blockwork 0%
2461 Conc. Swimming pool sides & overflow channels 0%
2462 Conc. Ring & tie beams 0%
2463 Roof & Ceiling 0%
2470 Finishes 0%
2478 M&E Installations 0%
2489 Villa A3/29 0%
2490 substructure 0%
2491 set out 0%
2492 Excavate 0%
2493 Conc. Foundation 0%
2494 Backfill 0%
2495 termite treatment 0%
2496 DPC (where applicable) 0%
2497 M&E inlet/outlet works - first fix 0%
2498 frame 0%
2499 set kickers 0%
2500 Conc. Columns & shear walls 0%
2501 Conc. G. F Beams 0%
2502 M&E first fix 0%
2503 Conc. Plantroom 0%
2504 Conc. Floor slab & swimming pool base 0%
2505 Blockwork 0%
2506 Conc. Swimming pool sides & overflow channels 0%
2507 Conc. Ring & tie beams 0%
2508 Roof & Ceiling 0%
2515 Finishes 0%
2523 M&E Installations 0%
2534 Villa A3/30 0%
2535 substructure 0%
2536 set out 0%
2537 Excavate 0%
2538 Conc. Foundation 0%
2539 Backfill 0%
2540 termite treatment 0%
2541 DPC (where applicable) 0%
2542 M&E inlet/outlet works - first fix 0%
2543 frame 0%
2544 set kickers 0%
2545 Conc. Columns & shear walls 0%
2546 Conc. G. F Beams 0%
2547 M&E first fix 0%
2548 Conc. Plantroom 0%
2549 Conc. Floor slab & swimming pool base 0%
2550 Blockwork 0%
2551 Conc. Swimming pool sides & overflow channels 0%
2552 Conc. Ring & tie beams 0%
2553 Roof & Ceiling 0%
2560 Finishes 0%
2568 M&E Installations 0%
2579 Villa A3/31 0%
2624 Villa A3/32 0%
2625 substructure 0%
2626 set out 0%
2627 Excavate 0%
2628 Conc. Foundation 0%
2629 Backfill 0%
2630 termite treatment 0%
2631 DPC (where applicable) 0%
2632 frame 0%
2633 set kickers 0%
2634 Conc. Columns & shear walls 0%
2635 Conc. Ground Beams 0%
2636 Conc. Plantroom 0%
2637 Conc. Floor slab & swimming pool base 0%
2638 Blockwork 0%
2639 Conc. Swimming pool sides & overflow channels 0%
2640 Conc. Ring & tie beams 0%
2641 Roof & Ceiling 0%
2647 Finishes 0%
2653 M&E Installations 0%
2664 B223 Villas ( 3 nos) 0%
2665 Villa B2/03 0%
2666 substructure 0%
2667 set out 0%
2668 Excavate 0%
2669 Conc. Foundation 0%
2670 Backfill 0%
2671 termite treatment 0%
2672 DPC (where applicable) 0%
2673 frame 0%
2674 set kickers 0%
2675 Conc. Columns & shear walls to GF 0%
2676 Conc. Plantrooms 0%
2677 Conc. GF slab and beams 0%
2678 Blockwork up to FF slab 0%
2679 set kickers on GF 0%
2680 Conc. Columns & shear walls to FF 0%
2681 Conc. FF slab & beams 0%
2682 Blockwork up to roof 0%
2683 set kickers on FF 0%
2684 Conc. Columns & shear walls to roof 0%
2685 Conc. Ring & tie beams 0%
2686 Roof & Ceiling 0%
2692 Finishes 0%
2697 M&E Installations 0%
2708 Villa B2/09 0%
2709 substructure 0%
2710 set out 0%
2711 Excavate 0%
2712 Conc. Foundation 0%
2713 Backfill 0%
2714 termite treatment 0%
2715 DPC (where applicable) 0%
2716 M&E inlet/outlet works - first fix 0%
2717 frame 0%
2718 set kickers 0%
2719 Conc. Columns & shear walls to GF 0%
2720 Conc. Plantrooms 0%
2721 M&E first fix GF 0%
2722 Conc. GF slab and beams 0%
2723 Blockwork up to FF slab 0%

page 112
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2007 2008 2009 2010
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb
2724 set kickers on GF 0%
2725 Conc. Columns & shear walls to FF 0%
2726 M&E first fix FF 0%
2727 Conc. FF slab & beams 0%
2728 Blockwork up to roof 0%
2729 set kickers on FF 0%
2730 Conc. Columns & shear walls to roof 0%
2731 M&E first fix roof 0%
2732 Conc. Ring & tie beams 0%
2733 Roof & Ceiling 0%
2740 Finishes 0%
2747 M&E Installations 0%
2758 Villa B2/10 0%
2759 substructure 0%
2760 set out 0%
2761 Excavate 0%
2762 Conc. Foundation 0%
2763 Backfill 0%
2764 termite treatment 0%
2765 DPC (where applicable) 0%
2766 M&E inlet/outlet works - first fix 0%
2767 frame 0%
2768 set kickers 0%
2769 Conc. Columns & shear walls to GF 0%
2770 Conc. Plantrooms 0%
2771 M&E first fix GF 0%
2772 Conc. GF slab and beams 0%
2773 Blockwork up to FF slab 0%
2774 set kickers on GF 0%
2775 Conc. Columns & shear walls to FF 0%
2776 M&E first fix FF 0%
2777 Conc. FF slab & beams 0%
2778 Blockwork up to roof 0%
2779 set kickers on FF 0%
2780 Conc. Columns & shear walls to roof 0%
2781 M&E first fix roof 0%
2782 Conc. Ring & tie beams 0%
2783 Roof & Ceiling 0%
2790 Finishes 0%
2797 M&E Installations 0%
2808 B4 Standard Villas ( 2 nos) 0%
2899 BC311 Executive Villa 0%
3115 P3 Presidential suites ( 3 nos) 0%
3245 Hilltop sunset deck( subject to receipt of GFW drawings) 0%
3280 External works ( subject to receipt of GFW drawings) 0%
3289 Drainage works ( subject to receipt of EME details) 0%
3292 Lot 4 0%
3293 Couple treatment room( subject to receipt of GFW drawings) 0%
3334 Single treatment room( subject to receipt of GFW drawings) 0%
3375 Dive Centre( subject to receipt of GFW drawings) 0%
3413 Kid's club( subject to receipt of GFW drawings) 0%
3452 Recreation House( subject to receipt of GFW drawings) 0%
3491 Watersports rental( subject to receipt of GFW drawings) 0%
3529 3 Meals restaurant( subject to receipt of GFW drawings) 0%
3570 Beach Pool Bar( subject to receipt of GFW drawings) 0%
3611 Signature Pool area( subject to receipt of GFW drawings) 0%
3650 Wedding Chapel( subject to receipt of GFW drawings) 0%
3685 BOH/Admin Building( subject to receipt of GFW drawings) 0%
3726 Chi Sanctum( subject to receipt of GFW drawings) 0%
3767 Yoga Pavillion( subject to receipt of GFW drawings) 0%
3805 External works ( subject to receipt of GFW drawings) 0%
3814 Drainage works ( subject to receipt of EME details) 0%
3817 M&E Installations- External 0%
3828 Sundries 0%
3829 Site cleaning & demobilisation 0%
3830 Project Commissioning 0%

The following table summarises the revised durations to perform


a significantly revised scope of work depicted on the design
drawings issued for construction. It should be noted the delay
indicated on the extreme right column also includes the earlier
delays caused by the setting out, unforeseen ground conditions
and design drawings.

Once again, the revised durations are not critical to completion


but activities typically take longer than planned.

page 113
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

Impacted Programme Baseline Programme


Villa commencement completion commencement completion Baseline duration Revised Duration Delay
A3/01 28-Feb-07 09-Jul-08 23-Jul-07 15-Mar-08 236.13 497.13 261.00
A3/02 12-Apr-07 09-Dec-08 23-Jul-07 15-Mar-08 236.13 607.08 370.96
A3/03 12-Apr-07 30-Dec-08 23-Jul-07 15-Mar-08 236.13 628.08 391.96
A3/04 09-Apr-07 15-Mar-08 23-Jul-07 15-Mar-08 236.13 341.13 105.00
A3/05 09-Apr-07 15-Mar-08 23-Jul-07 15-Mar-08 236.13 341.13 105.00
A3/06 09-Apr-07 02-Jul-08 23-Jul-07 15-Mar-08 236.13 450.13 214.00
A3/07 25-Apr-07 07-Jan-08 02-Apr-07 12-Nov-07 224.08 257.08 33.00
A3/08 02-Apr-07 22-Dec-08 02-Apr-07 15-Mar-08 348.13 630.08 281.96
A3/09 02-Apr-07 06-May-09 02-Apr-07 15-Mar-08 348.13 765.08 416.96
A3/10 09-Apr-07 02-Jul-08 09-Apr-07 15-Mar-08 341.13 450.13 109.00
A3/11 09-Apr-07 18-May-09 09-Apr-07 15-Mar-08 341.13 770.08 428.96
A3/12 09-Apr-07 15-Mar-08 09-Apr-07 15-Mar-08 341.13 341.13 0.00
A3/13 09-Apr-07 15-Mar-08 09-Apr-07 15-Mar-08 341.13 341.13 0.00
A3/14 28-May-07 15-Mar-08 28-May-07 15-Mar-08 292.13 292.13 0.00
A3/15 28-May-07 15-Mar-08 28-May-07 15-Mar-08 292.13 292.13 0.00
A3/16 28-May-07 15-Mar-08 28-May-07 15-Mar-08 292.13 292.13 0.00
A3/17 28-May-07 15-Mar-08 28-May-07 15-Mar-08 292.13 292.13 0.00
A3/18 12-Apr-07 15-Mar-08 12-Apr-07 15-Mar-08 338.13 338.13 0.00
A3/19 12-Apr-07 13-Jun-09 12-Apr-07 15-Mar-08 338.13 793.13 455.00
A3/20 25-Apr-07 29-May-09 12-Apr-07 15-Mar-08 338.13 765.13 427.00
A3/21 12-Apr-07 29-May-09 12-Apr-07 15-Mar-08 338.13 778.13 440.00
A3/22 12-Apr-07 13-Sep-08 12-Apr-07 15-Mar-08 338.13 520.33 182.21
A3/23 16-Apr-07 16-Sep-08 16-Apr-07 15-Mar-08 334.13 519.38 185.25
A3/24 16-Apr-07 16-Sep-08 16-Apr-07 15-Mar-08 334.13 519.38 185.25
A3/25 16-Apr-07 16-Sep-08 16-Apr-07 15-Mar-08 334.13 519.38 185.25
A3/26 16-Apr-07 06-Jan-09 16-Apr-07 15-Mar-08 334.13 631.08 296.96
A3/27 16-Apr-07 29-Sep-08 16-Apr-07 15-Mar-08 334.13 532.08 197.96
A3/28 28-May-07 06-Aug-08 28-May-07 15-Mar-08 292.13 436.08 143.96
A3/29 28-May-07 23-Apr-08 28-May-07 15-Mar-08 292.13 331.13 39.00
A3/30 25-Apr-07 15-May-08 28-May-07 15-Mar-08 292.13 386.13 94.00
A3/31 28-May-07 15-Mar-08 28-May-07 15-Mar-08 292.13 292.13 0.00
A3/32 28-May-07 10-Dec-07 28-May-07 16-Nov-07 172.04 196.38 24.33
B2/01 16-Apr-07 04-Feb-09 03-Jul-07 15-Mar-08 256.13 660.08 403.96
B2/02 16-Apr-07 24-Jun-08 03-Jul-07 15-Mar-08 256.13 435.08 178.96
B2/03 28-May-07 17-Jan-08 28-May-07 04-Dec-07 190.17 234.17 44.00
B2/04 16-Apr-07 10-Oct-08 03-Jul-07 15-Mar-08 256.13 543.13 287.00
B2/05 16-Apr-07 08-Jan-09 03-Jul-07 15-Mar-08 256.13 633.13 377.00
B2/06 23-Apr-07 16-Jan-09 03-Jul-07 15-Mar-08 256.13 634.13 378.00
B2/07 23-Apr-07 07-Jun-08 03-Jul-07 15-Mar-08 256.13 411.13 155.00
B2/08 23-Apr-07 16-Jan-09 03-Jul-07 15-Mar-08 256.13 634.13 378.00
B2/09 28-May-07 12-Mar-09 28-May-07 15-Mar-08 292.13 654.13 362.00
B2/10 28-May-07 18-Mar-09 28-May-07 15-Mar-08 292.13 660.13 368.00

As a result of the extended durations caused by this event the


time for completion has not been extended and the revised
completion date remains at 9 September 2009.

The revised completion date remains at 9 September 2009.

page 114
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

5.1.4.5. Event No 5 – Partial Suspension of Works


ID Task Name
2007 2008 2009
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
1 SHANGRI-LA , Long Island Resort Seychelles 0%
2 General Conditions and Preliminaries 0%
17 Site establishment 0%
41 Material/equipment procurement 0%
182 Lot 1 0%
183 A3 Villas ( 6 nos) 0%
184 Villa A3/01 0%
228 Villa A3/02 0%
273 Villa A3/03 0%
274 substructure 0%
275 set out 0%
276 Excavate 0%
277 Conc. Foundation 0%
278 Backfill 0%
279 termite treatment 0%
280 DPC (where applicable) 0%
281 M&E inlet/outlet works - first fix 0%
282 frame 0%
283 set kickers 0%
284 Conc. Columns & shear walls 0%
285 Conc. G. F Beams 0%
286 M&E first fix 0%
287 Conc. Plantroom 0%
288 Conc. Floor slab & swimming pool base 0%
289 Blockwork 0%
290 Conc. Swimming pool sides & overflow channels 0%
291 Conc. Ring & tie beams 0%
292 Roof & Ceiling 0%
299 Finishes 0%
307 M&E Installations 0%
318 Villa A3/04 0%
319 substructure 0%
320 set out 0%
321 Excavate 0%
322 Conc. Foundation 0%
323 Backfill 0%
324 termite treatment 0%
325 DPC (where applicable) 0%
326 M&E inlet/outlet works - first fix 0%
327 frame 0%
328 set kickers 0%
329 Conc. Columns & shear walls 0%
330 Conc. G. F Beams 0%
331 M&E first fix 0%
332 Conc. Plantroom 0%
333 Conc. Floor slab & swimming pool base 0%
334 Blockwork 0%
335 Conc. Swimming pool sides & overflow channels 0%
336 Conc. Ring & tie beams 0%
337 Roof & Ceiling 0%
338 Fix wall plate & truss 0%
339 Fix purlins and rafters 0%
340 Fix shingles ( subject to receipt of timber) 0%
341 Fix ceiing battens & joists 0%
342 Fix ceiling boards 0%
343 M&E first fix 0%
344 Finishes 0%
345 Wall plaster (internal & External) 0%
346 M&E 1st fix 0%
347 Floor finishes 0%
348 Fix windows & doors 0%
349 Swimming pool finishes 0%
350 M&E final fix 0%
351 Fix fittings and Fixtures 0%
352 M&E Installations 0%
353 Cable Tray, Conduit and Wiring 0%
354 Electrical boards and connections 0%
355 Electrical accessories 0%
356 Light fittings and ceiling fans 0%
357 Hot and cold water 0%
358 Waste and sewage incl. biobox 0%
359 Electric water heater 0%
360 Swimming pool 0%
361 Split unit installation 0%
362 Toilet ventilation, grilles 0%
363 Villa A3/05 0%
364 substructure 0%
365 set out 0%
366 Excavate 0%
367 Conc. Foundation 0%
368 Backfill 0%
369 termite treatment 0%
370 DPC (where applicable) 0%
371 M&E inlet/outlet works - first fix 0%
372 frame 0%
373 set kickers 0%
374 Conc. Columns & shear walls 0%
375 Conc. G. F Beams 0%
376 M&E first fix 0%
377 Conc. Plantroom 0%
378 Conc. Floor slab & swimming pool base 0%
379 Blockwork 0%
380 Conc. Swimming pool sides & overflow channels 0%
381 Conc. Ring & tie beams 0%
382 Roof & Ceiling 0%
383 Fix wall plate & truss 0%
384 Fix purlins and rafters 0%
385 Fix shingles ( subject to receipt of timber) 0%
386 Fix ceiing battens & joists 0%
387 Fix ceiling boards 0%
388 M&E first fix 0%
389 Finishes 0%
390 Wall plaster (internal & External) 0%
391 M&E 1st fix 0%
392 Floor finishes 0%
393 Fix windows & doors 0%
394 Swimming pool finishes 0%
395 M&E final fix 0%
396 Fix fittings and Fixtures 0%
397 M&E Installations 0%
398 Cable Tray, Conduit and Wiring 0%
399 Electrical boards and connections 0%
400 Electrical accessories 0%
401 Light fittings and ceiling fans 0%
402 Hot and cold water 0%

page 115
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2007 2008 2009
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
403 Waste and sewage incl. biobox 0%
404 Electric water heater 0%
405 Swimming pool 0%
406 Split unit installation 0%
407 Toilet ventilation, grilles 0%
408 Villa A3/06 0%
409 substructure 0%
410 set out 0%
411 Excavate 0%
412 Conc. Foundation 0%
413 Backfill 0%
414 termite treatment 0%
415 DPC (where applicable) 0%
416 M&E inlet/outlet works - first fix 0%
417 frame 0%
418 set kickers 0%
419 Conc. Columns & shear walls 0%
420 Conc. G. F Beams 0%
421 M&E first fix 0%
422 Conc. Plantroom 0%
423 Conc. Floor slab & swimming pool base 0%
424 Blockwork 0%
425 Conc. Swimming pool sides & overflow channels 0%
426 Conc. Ring & tie beams 0%
427 Roof & Ceiling 0%
434 Finishes 0%
442 M&E Installations 0%
453 C311 Executive Villas ( 1 nos) 0%
497 GM Villa ( subject to receipt of GFW drawings) 0%
537 Employees Facilities ( subject to receipt of GFW drawings) 0%
581 Laundry F& B service office ( subject to receipt of GFW drawings) 0%
625 Health Club/ Medical Centre( subject to receipt of GFW drawings) 0%
666 Administration Block ( subject to receipt of GFW drawings) 0%
707 1 bedroom Villa ( Excom, 6 units)( subject to receipt of GFW drawings) 0%
750 Main Lobby ( subject to receipt of GFW drawings) 0%
791 Tennis Courts ( subject to receipt of GFW drawings) 0%
807 External works ( subject to receipt of GFW drawings) 0%
816 Drainage works ( subject to receipt of EME details) 0%
819 Fuel Farm ( subject to receipt of EME details) 0%
823 Sea water Storage Tank & Water Tanks( subject to receipt of EME details) 0%
827 Desalination plant( subject to receipt of EME details) 0%
831 MLV Panel( subject to receipt of EME details) 0%
835 Step Up Transformer( subject to receipt of EME details) 0%
839 Incinerator/ Garbage room( subject to receipt of EME details) 0%
843 Sewer treatement plant( subject to receipt of EME details) 0%
847 Lot 2 0%
848 A3 Villas (17 nos) 0%
849 Villa A3/07 0%
894 Villa A3/08 0%
895 substructure 0%
896 set out 0%
897 Excavate 0%
898 Conc. Foundation 0%
899 Backfill 0%
900 termite treatment 0%
901 DPC (where applicable) 0%
902 M&E inlet/outlet works - first fix 0%
903 frame 0%
904 set kickers 0%
905 Conc. Columns & shear walls 0%
906 Conc. G. F Beams 0%
907 M&E first fix 0%
908 Conc. Plantroom 0%
909 Conc. Floor slab & swimming pool base 0%
910 Blockwork 0%
911 Conc. Swimming pool sides & overflow channels 0%
912 Conc. Ring & tie beams 0%
913 Roof & Ceiling 0%
920 Finishes 0%
928 M&E Installations 0%
939 Villa A3/09 0%
984 Villa A3/10 0%
985 substructure 0%
986 set out 0%
987 Excavate 0%
988 Conc. Foundation 0%
989 Backfill 0%
990 termite treatment 0%
991 DPC (where applicable) 0%
992 M&E inlet/outlet works - first fix 0%
993 frame 0%
994 set kickers 0%
995 Conc. Columns & shear walls 0%
996 Conc. G. F Beams 0%
997 M&E first fix 0%
998 Conc. Plantroom 0%
999 Conc. Floor slab & swimming pool base 0%
1000 Blockwork 0%
1001 Conc. Swimming pool sides & overflow channels 0%
1002 Conc. Ring & tie beams 0%
1003 Roof & Ceiling 0%
1010 Finishes 0%
1018 M&E Installations 0%
1029 Villa A3/11 0%
1074 Villa A3/12 0%
1119 Villa A3/13 0%
1164 Villa A3/18 0%
1209 Villa A3/19 0%
1254 Villa A3/20 0%
1299 Villa A3/21 0%
1344 Villa A3/22 0%
1389 Villa A3/23 0%
1434 Villa A3/24 0%
1479 Villa A3/25 0%
1524 Villa A3/26 0%
1569 Villa A3/27 0%
1570 substructure 0%
1571 set out 0%
1572 Excavate 0%
1573 Conc. Foundation 0%

page 116
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2007 2008 2009
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
1574 Backfill 0%
1575 termite treatment 0%
1576 DPC (where applicable) 0%
1577 M&E inlet/outlet works - first fix 0%
1578 frame 0%
1579 set kickers 0%
1580 Conc. Columns & shear walls 0%
1581 Conc. G. F Beams 0%
1582 M&E first fix 0%
1583 Conc. Plantroom 0%
1584 Conc. Floor slab & swimming pool base 0%
1585 Blockwork 0%
1586 Conc. Swimming pool sides & overflow channels 0%
1587 Conc. Ring & tie beams 0%
1588 Roof & Ceiling 0%
1595 Finishes 0%
1603 M&E Installations 0%
1614 B223 Villas ( 7 nos) 0%
1615 Villa B2/01 0%
1665 Villa B2/02 0%
1666 substructure 0%
1667 set out 0%
1668 Excavate 0%
1669 Conc. Foundation 0%
1670 Backfill 0%
1671 termite treatment 0%
1672 DPC (where applicable) 0%
1673 M&E inlet/outlet works - first fix 0%
1674 frame 0%
1675 set kickers 0%
1676 Conc. Columns & shear walls to GF 0%
1677 Conc. Plantrooms 0%
1678 M&E first fix GF 0%
1679 Conc. GF slab and beams 0%
1680 Blockwork up to FF slab 0%
1681 set kickers on GF 0%
1682 Conc. Columns & shear walls to FF 0%
1683 M&E first fix FF 0%
1684 Conc. FF slab & beams 0%
1685 Blockwork up to roof 0%
1686 set kickers on FF 0%
1687 Conc. Columns & shear walls to roof 0%
1688 M&E first fix roof 0%
1689 Conc. Ring & tie beams 0%
1690 Roof & Ceiling 0%
1697 Finishes 0%
1704 M&E Installations 0%
1715 Villa B2/04 0%
1765 Villa B2/05 0%
1815 Villa B2/06 0%
1865 Villa B2/07 0%
1915 Villa B2/08 0%
1965 B4 Villa (2 nos.) 0%
2056 Retail 1( subject to receipt of GFW drawings) 0%
2094 Retail 2( subject to receipt of GFW drawings) 0%
2132 Retail 3( subject to receipt of GFW drawings) 0%
2170 Seafood resort( subject to receipt of GFW drawings) 0%
2211 Greeting Pavillion( subject to receipt of GFW drawings) 0%
2250 External works ( subject to receipt of GFW drawings) 0%
2259 Drainage works ( subject to receipt of EME details) 0%
2262 Lot 3 0%
2263 A3 Villas ( 9 nos) 0%
2264 Villa A3/14 0%
2309 Villa A3/15 0%
2354 Villa A3/16 0%
2399 Villa A3/17 0%
2444 Villa A3/28 0%
2445 substructure 0%
2446 set out 0%
2447 Excavate 0%
2448 Conc. Foundation 0%
2449 Backfill 0%
2450 termite treatment 0%
2451 DPC (where applicable) 0%
2452 M&E inlet/outlet works - first fix 0%
2453 frame 0%
2454 set kickers 0%
2455 Conc. Columns & shear walls 0%
2456 Conc. G. F Beams 0%
2457 M&E first fix 0%
2458 Conc. Plantroom 0%
2459 Conc. Floor slab & swimming pool base 0%
2460 Blockwork 0%
2461 Conc. Swimming pool sides & overflow channels 0%
2462 Conc. Ring & tie beams 0%
2463 Roof & Ceiling 0%
2470 Finishes 0%
2478 M&E Installations 0%
2489 Villa A3/29 0%
2490 substructure 0%
2491 set out 0%
2492 Excavate 0%
2493 Conc. Foundation 0%
2494 Backfill 0%
2495 termite treatment 0%
2496 DPC (where applicable) 0%
2497 M&E inlet/outlet works - first fix 0%
2498 frame 0%
2499 set kickers 0%
2500 Conc. Columns & shear walls 0%
2501 Conc. G. F Beams 0%
2502 M&E first fix 0%
2503 Conc. Plantroom 0%
2504 Conc. Floor slab & swimming pool base 0%
2505 Blockwork 0%
2506 Conc. Swimming pool sides & overflow channels 0%
2507 Conc. Ring & tie beams 0%
2508 Roof & Ceiling 0%
2515 Finishes 0%
2523 M&E Installations 0%

page 117
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2007 2008 2009
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov
2534 Villa A3/30 0%
2535 substructure 0%
2536 set out 0%
2537 Excavate 0%
2538 Conc. Foundation 0%
2539 Backfill 0%
2540 termite treatment 0%
2541 DPC (where applicable) 0%
2542 M&E inlet/outlet works - first fix 0%
2543 frame 0%
2544 set kickers 0%
2545 Conc. Columns & shear walls 0%
2546 Conc. G. F Beams 0%
2547 M&E first fix 0%
2548 Conc. Plantroom 0%
2549 Conc. Floor slab & swimming pool base 0%
2550 Blockwork 0%
2551 Conc. Swimming pool sides & overflow channels 0%
2552 Conc. Ring & tie beams 0%
2553 Roof & Ceiling 0%
2560 Finishes 0%
2568 M&E Installations 0%
2579 Villa A3/31 0%
2580 substructure 0%
2581 set out 0%
2582 Excavate 0%
2583 Conc. Foundation 0%
2584 Backfill 0%
2585 termite treatment 0%
2586 DPC (where applicable) 0%
2587 M&E inlet/outlet works - first fix 0%
2588 frame 0%
2589 set kickers 0%
2590 Conc. Columns & shear walls 0%
2591 Conc. G. F Beams 0%
2592 M&E first fix 0%
2593 Conc. Plantroom 0%
2594 Conc. Floor slab & swimming pool base 0%
2595 Blockwork 0%
2596 Conc. Swimming pool sides & overflow channels 0%
2597 Conc. Ring & tie beams 0%
2598 Roof & Ceiling 0%
2599 Fix wall plate & truss 0%
2600 Fix purlins and rafters 0%
2601 Fix shingles ( subject to receipt of timber) 0%
2602 Fix ceiing battens & joists 0%
2603 Fix ceiling boards 0%
2604 M&E first fix 0%
2605 Finishes 0%
2606 Wall plaster (internal & External) 0%
2607 M&E 1st fix 0%
2608 Floor finishes 0%
2609 Fix windows & doors 0%
2610 Swimming pool finishes 0%
2611 M&E final fix 0%
2612 Fix fittings and Fixtures 0%
2613 M&E Installations 0%
2614 Cable Tray, Conduit and Wiring 0%
2615 Electrical boards and connections 0%
2616 Electrical accessories 0%
2617 Light fittings and ceiling fans 0%
2618 Hot and cold water 0%
2619 Waste and sewage incl. biobox 0%
2620 Electric water heater 0%
2621 Swimming pool 0%
2622 Split unit installation 0%
2623 Toilet ventilation, grilles 0%
2624 Villa A3/32 0%
2664 B223 Villas ( 3 nos) 0%
2665 Villa B2/03 0%
2708 Villa B2/09 0%
2758 Villa B2/10 0%
2808 B4 Standard Villas ( 2 nos) 0%
2899 BC311 Executive Villa 0%
3115 P3 Presidential suites ( 3 nos) 0%
3245 Hilltop sunset deck( subject to receipt of GFW drawings) 0%
3280 External works ( subject to receipt of GFW drawings) 0%
3289 Drainage works ( subject to receipt of EME details) 0%
3292 Lot 4 0%
3293 Couple treatment room( subject to receipt of GFW drawings) 0%
3334 Single treatment room( subject to receipt of GFW drawings) 0%
3375 Dive Centre( subject to receipt of GFW drawings) 0%
3413 Kid's club( subject to receipt of GFW drawings) 0%
3452 Recreation House( subject to receipt of GFW drawings) 0%
3491 Watersports rental( subject to receipt of GFW drawings) 0%
3529 3 Meals restaurant( subject to receipt of GFW drawings) 0%
3570 Beach Pool Bar( subject to receipt of GFW drawings) 0%
3611 Signature Pool area( subject to receipt of GFW drawings) 0%
3650 Wedding Chapel( subject to receipt of GFW drawings) 0%
3685 BOH/Admin Building( subject to receipt of GFW drawings) 0%
3726 Chi Sanctum( subject to receipt of GFW drawings) 0%
3767 Yoga Pavillion( subject to receipt of GFW drawings) 0%
3805 External works ( subject to receipt of GFW drawings) 0%
3814 Drainage works ( subject to receipt of EME details) 0%
3817 M&E Installations- External 0%
3828 Sundries 0%
3829 Site cleaning & demobilisation 0%
3830 Project Commissioning 0%

The following table shows the individual delays arising at each


villa suspended which also incorporates the delays described in
Event 1 through to 4.

page 118
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

Impacted Programme Baseline Programme


Villa commencement completion commencement completion Baseline duration Revised Duration Delay
A3/03 12-Apr-07 30-Dec-08 23-Jul-07 15-Mar-08 236.13 628.08 391.96
A3/04 09-Apr-07 15-Mar-08 23-Jul-07 15-Mar-08 236.13 341.13 105.00
A3/05 09-Apr-07 15-Mar-08 23-Jul-07 15-Mar-08 236.13 341.13 105.00
A3/06 09-Apr-07 05-Aug-08 23-Jul-07 15-Mar-08 236.13 484.38 248.25
A3/08 02-Apr-07 22-Dec-08 02-Apr-07 15-Mar-08 348.13 630.08 281.96
A3/10 09-Apr-07 02-Jul-08 09-Apr-07 15-Mar-08 341.13 450.13 109.00
A3/27 16-Apr-07 29-Sep-08 16-Apr-07 15-Mar-08 334.13 532.08 197.96
A3/28 28-May-07 06-Aug-08 28-May-07 15-Mar-08 292.13 436.08 143.96
A3/29 28-May-07 23-Apr-08 28-May-07 15-Mar-08 292.13 331.13 39.00
A3/30 25-Apr-07 15-May-08 28-May-07 15-Mar-08 292.13 386.13 94.00
A3/31 28-May-07 15-Mar-08 28-May-07 15-Mar-08 292.13 292.13 0.00
B2/02 16-Apr-07 13-Sep-08 03-Jul-07 15-Mar-08 256.13 516.33 260.21

As a result the delay caused by this event is not critical and the
time for completion has not extended the revised date of 9
September 2009.

Consequently, the revised completion date remains at 9


September 2009.

page 119
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

5.1.4.6. Event No 6 – Design Variations (Stainless Steel


Items)
ID Task Name
2007 2008 2009
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
1 SHANGRI-LA , Long Island Resort Seychelles 0%
2 General Conditions and Preliminaries 0%
17 Site establishment 0%
41 Material/equipment procurement 0%
182 Lot 1 0%
183 A3 Villas ( 6 nos) 0%
184 Villa A3/01 0%
228 Villa A3/02 0%
273 Villa A3/03 0%
318 Villa A3/04 0%
363 Villa A3/05 0%
408 Villa A3/06 0%
453 C311 Executive Villas ( 1 nos) 0%
497 GM Villa ( subject to receipt of GFW drawings) 0%
537 Employees Facilities ( subject to receipt of GFW drawings) 0%
581 Laundry F& B service office ( subject to receipt of GFW drawings) 0%
625 Health Club/ Medical Centre( subject to receipt of GFW drawings) 0%
666 Administration Block ( subject to receipt of GFW drawings) 0%
707 1 bedroom Villa ( Excom, 6 units)( subject to receipt of GFW drawings) 0%
750 Main Lobby ( subject to receipt of GFW drawings) 0%
791 Tennis Courts ( subject to receipt of GFW drawings) 0%
807 External works ( subject to receipt of GFW drawings) 0%
816 Drainage works ( subject to receipt of EME details) 0%
819 Fuel Farm ( subject to receipt of EME details) 0%
823 Sea water Storage Tank & Water Tanks( subject to receipt of EME details) 0%
827 Desalination plant( subject to receipt of EME details) 0%
831 MLV Panel( subject to receipt of EME details) 0%
835 Step Up Transformer( subject to receipt of EME details) 0%
839 Incinerator/ Garbage room( subject to receipt of EME details) 0%
843 Sewer treatement plant( subject to receipt of EME details) 0%
847 Lot 2 0%
848 A3 Villas (17 nos) 0%
849 Villa A3/07 0%
894 Villa A3/08 0%
939 Villa A3/09 0%
984 Villa A3/10 0%
1029 Villa A3/11 0%
1074 Villa A3/12 0%
1119 Villa A3/13 0%
1164 Villa A3/18 0%
1209 Villa A3/19 0%
1254 Villa A3/20 0%
1299 Villa A3/21 0%
1344 Villa A3/22 0%
1389 Villa A3/23 0%
1434 Villa A3/24 0%
1479 Villa A3/25 0%
1524 Villa A3/26 0%
1569 Villa A3/27 0%
1614 B223 Villas ( 7 nos) 0%
1615 Villa B2/01 0%
1665 Villa B2/02 0%
1715 Villa B2/04 0%
1765 Villa B2/05 0%
1815 Villa B2/06 0%
1865 Villa B2/07 0%
1915 Villa B2/08 0%
1965 B4 Villa (2 nos.) 0%
2056 Retail 1( subject to receipt of GFW drawings) 0%
2094 Retail 2( subject to receipt of GFW drawings) 0%
2132 Retail 3( subject to receipt of GFW drawings) 0%
2170 Seafood resort( subject to receipt of GFW drawings) 0%
2211 Greeting Pavillion( subject to receipt of GFW drawings) 0%
2250 External works ( subject to receipt of GFW drawings) 0%
2259 Drainage works ( subject to receipt of EME details) 0%
2262 Lot 3 0%
2263 A3 Villas ( 9 nos) 0%
2264 Villa A3/14 0%
2309 Villa A3/15 0%
2354 Villa A3/16 0%
2399 Villa A3/17 0%
2444 Villa A3/28 0%
2489 Villa A3/29 0%
2534 Villa A3/30 0%
2579 Villa A3/31 0%
2624 Villa A3/32 0%
2625 substructure 0%
2626 set out 0%
2627 Excavate 0%
2628 Conc. Foundation 0%
2629 Backfill 0%
2630 termite treatment 0%
2631 DPC (where applicable) 0%
2632 frame 0%
2633 set kickers 0%
2634 Conc. Columns & shear walls 0%
2635 Conc. Ground Beams 0%
2636 Conc. Plantroom 0%
2637 Conc. Floor slab & swimming pool base 0%
2638 Blockwork 0%
2639 Conc. Swimming pool sides & overflow channels 0%
2640 Conc. Ring & tie beams 0%
2641 Roof & Ceiling 0%
2642 Fix wall plate & truss 0%
2643 Fix purlins and rafters 0%
2644 Fix shingles ( subject to receipt of timber) 0%
2645 Fix ceiing battens & joists 0%
2646 Fix ceiling boards 0%
2647 Finishes 0%
2648 Wall plaster (internal & External) 0%
2649 Floor finishes 0%
2650 Fix windows & doors 0%
2651 Swimming pool finishes 0%
2652 Fix fittings and Fixtures 0%
2653 M&E Installations 0%
2654 Cable Tray, Conduit and Wiring 0%
2655 Electrical boards and connections 0%
2656 Electrical accessories 0%
2657 Light fittings and ceiling fans 0%

page 120
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
ID Task Name
2007 2008 2009
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
2658 Hot and cold water 0%
2659 Waste and sewage incl. biobox 0%
2660 Electric water heater 0%
2661 Swimming pool 0%
2662 Split unit installation 0%
2663 Toilet ventilation, grilles 0%
2664 B223 Villas ( 3 nos) 0%
2665 Villa B2/03 0%
2666 substructure 0%
2667 set out 0%
2668 Excavate 0%
2669 Conc. Foundation 0%
2670 Backfill 0%
2671 termite treatment 0%
2672 DPC (where applicable) 0%
2673 frame 0%
2674 set kickers 0%
2675 Conc. Columns & shear walls to GF 0%
2676 Conc. Plantrooms 0%
2677 Conc. GF slab and beams 0%
2678 Blockwork up to FF slab 0%
2679 set kickers on GF 0%
2680 Conc. Columns & shear walls to FF 0%
2681 Conc. FF slab & beams 0%
2682 Blockwork up to roof 0%
2683 set kickers on FF 0%
2684 Conc. Columns & shear walls to roof 0%
2685 Conc. Ring & tie beams 0%
2686 Roof & Ceiling 0%
2687 Fix wall plate & truss 0%
2688 Fix purlins and rafters 0%
2689 Fix shingles ( subject to receipt of timber) 0%
2690 Fix ceiing battens & joists 0%
2691 Fix ceiling boards 0%
2692 Finishes 0%
2693 Wall plaster (internal & External) 0%
2694 Floor finishes 0%
2695 Fix windows & doors 0%
2696 Fix fittings and Fixtures 0%
2697 M&E Installations 0%
2698 Cable Tray, Conduit and Wiring 0%
2699 Electrical boards and connections 0%
2700 Electrical accessories 0%
2701 Light fittings and ceiling fans 0%
2702 Hot and cold water 0%
2703 Waste and sewage incl. biobox 0%
2704 Electric water heater 0%
2705 Swimming pool ( not applicable) 0%
2706 Split unit installation 0%
2707 Toilet ventilation, grilles 0%
2708 Villa B2/09 0%
2758 Villa B2/10 0%
2808 B4 Standard Villas ( 2 nos) 0%
2899 BC311 Executive Villa 0%
3115 P3 Presidential suites ( 3 nos) 0%
3245 Hilltop sunset deck( subject to receipt of GFW drawings) 0%
3280 External works ( subject to receipt of GFW drawings) 0%
3289 Drainage works ( subject to receipt of EME details) 0%
3292 Lot 4 0%
3293 Couple treatment room( subject to receipt of GFW drawings) 0%
3334 Single treatment room( subject to receipt of GFW drawings) 0%
3375 Dive Centre( subject to receipt of GFW drawings) 0%
3413 Kid's club( subject to receipt of GFW drawings) 0%
3452 Recreation House( subject to receipt of GFW drawings) 0%
3491 Watersports rental( subject to receipt of GFW drawings) 0%
3529 3 Meals restaurant( subject to receipt of GFW drawings) 0%
3570 Beach Pool Bar( subject to receipt of GFW drawings) 0%
3611 Signature Pool area( subject to receipt of GFW drawings) 0%
3650 Wedding Chapel( subject to receipt of GFW drawings) 0%
3685 BOH/Admin Building( subject to receipt of GFW drawings) 0%
3726 Chi Sanctum( subject to receipt of GFW drawings) 0%
3767 Yoga Pavillion( subject to receipt of GFW drawings) 0%
3805 External works ( subject to receipt of GFW drawings) 0%
3814 Drainage works ( subject to receipt of EME details) 0%
3817 M&E Installations- External 0%
3828 Sundries 0%
3829 Site cleaning & demobilisation 0%
3830 Project Commissioning 0%

Similarly, the following table shows the delay which occurred at


the Mock-up Villas. Again, this delay is not critical to completion
because of the earlier delays.

Impacted Programme Baseline Programme


Villa commencement completion commencement completion Baseline duration Revised Duration Delay
A3/32 28-May-07 19-Mar-08 28-May-07 16-Nov-07 172.04 296.17 124.13
B2/03 28-May-07 12-May-08 28-May-07 04-Dec-07 190.17 350.38 160.21

page 121
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

5.2. Conclusion
At the outset of the Contract the Contractor suffered delays in
setting out the works. This was followed by significant disruption
caused by excavation in hard rock and partial suspension of
Works. With respect to the Contract and the Contractor’s
Programme of Works to which consent has been given, such
departure from his original planning has caused significant
increased cost. In addition, significant increases in quantities of
work caused the Contractor to fall further behind his programme.

The Project Manager also required the Contractor to perform his


work in accordance with the Programme of Works. In addition,
he has the duty to provide correct design details, in
conformance with site conditions, to the Contractor in good time
for him to be able to perform his material procurement and
construction work in accordance with that programme.

By altering the sequence, timing and quality of the design details


supplied to the Contractor, the Project Manager has acted
outside the boundaries of the existing Contract provisions.

In failing to provide final survey data, unnecessarily suspending


Works, failing to have identified and have taken account site
conditions, and not providing design information to the
Contractor in accordance with the Programme of Works, the
Employer is in breach of his obligations (through the Project
Manager in respect of design information) under the terms of the
Contract.

Furthermore, by altering the sequence, timing and quality of the


design information, when it was eventually provided to the
Contractor, the Project Manager has required the Contractor to
operate in a manner different from, slower and more expensive
than had been shown on the Programme of Works than he had
reasonably anticipated at the time of tender.

The consequences of this breach and variance of the Contract,


in terms of time for completion and financial compensation, are
explained in previous and subsequent sections of this
submission.

page 122
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

6. Financial Analysis

6.1. Consequences
During the periods of delay and disruption which results directly
from the varied site circumstances, varied scope of work, piece-
meal work or an adverse condition, the Contractor has incurred
costs of reduced and non-productive work necessitated by
retaining levels of resources, which otherwise would have been
decreased or deployed elsewhere. The Contractor would
maintain that it was not reasonable to discharge Staff and
Labour and remove equipment off Site for those periods. These
costs include idle equipment and labour and other direct costs,
and are recoverable under the terms and conditions of contract.

Furthermore, in response to the change in timing and sequence


of the Works, the Contractor has reorganised his resources to
meet the varied circumstances. As a consequence of such
measures to improve his production, loss of efficiency costs
caused by overtime, extra crews, larger crews, crowding or
stacking of trades, are recoverable costs under the terms and
conditions of contract. These additional costs are Wasted Costs
(in order to use one title to capture all delaying events) and are
recoverable as a Variation under the terms of the Contract.

Finally, because of the delays, which are not the fault of the
Contractor, substantial completion of the whole Works can only
be achieved beyond the original date. Consequently, the
Contractor will incur additional costs in the extended period that
is not recovered through the rates and prices of the contract.

An aspect of delay-induced expense is the cost of continuing


work on a project over a longer time than first anticipated.
Additional costs of labour, equipment and overhead has been
incurred due to the fact that performance had to be spread out,
sometimes leaving the Contractor’s resources idle or forced
personnel and equipment to remain thus postponing other work
sites.

Therefore, the amount of recovery is based on the total amount


of cost expended during the period the contract was delayed. At
the time of preparing this claim submission, delays and
disruption continue and consequently, additional costs.

The Contractor is entitled to recover the cost of his resources,


overheads and profit for this period. The additional costs will fall
under three categories:

page 123
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

6.1.1.Direct Cost
The direct cost of this event, delay and disruption, is the cost of
labour, staff and equipment directly employed at the Site
including profit.

6.1.2.Indirect Cost
Indirect cost flows from on-site establishments such as the
Contractor’s head and site offices and yard, which overheads
are only partially recovered during the periods of planned
construction operations when extended.

6.1.3.Consequential Cost
The consequential cost is the effect on the work in terms of
disruption to the various activities and prolongation of the
Contractor’s time related resources arising from re-sequencing
the planned work.

This cause occurred at the outset of the project and disruption


has been assessed as significant. The change, impacts planned
logic and links of many tasks shown on his Programme of Works
on which, the Contractor is heavily dependant if he is to retain
his original tender cost provisions.

6.2. Costs in Extended Contract Period


6.2.1.Nature of Loss and Expense
The loss and expense flowing from the causes described in this
Document are time-related. The loss and expense attributable to
these causes has been incurred over all of the Periods identified
in this claim. However, the major period in which variations have
caused loss and expense is:

 In the period of construction to date, May 2008, and

 In the extended construction period.

page 124
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

6.2.2.Contractor’s Entitlement to Reimbursement


Instructions issued are covered by the first paragraph of Clause
13.1 of the Conditions. This refers to Instructions in regard to:

 Revised setting out details;

 Suspension of Work;

 Design drawings issued for construction; and

 Additional and varied works.

The criteria for allowing the Contractor reimbursement are given


in the penultimate paragraph of Clause 12.3:

Each new rate or price shall be derived from any relevant


rates or prices in the Contract, with reasonable
adjustments to take account of the matters described in
sub-paragraph (a) and/or (b), as applicable. If no rates or
prices are relevant for the derivation of a new rate or
price, it shall be derived from the reasonable Cost of
executing the work, together with profit, taking account of
any other relevant matters.

The loss and expense were not provided for, nor reasonably
contemplated by, the Contract. The Instructions did not result
from a breach by the Contractor. Accordingly, the loss and
expense must be added to the Contract Price.

6.3. Finance Cost


As this is a claim for breach of contract, the Contractor’s
approach to the quantum, or the measure of damage, is to
follow the common law rule. This is that the damages should put
the complaining party in the position he would have been, had
the breach not taken place, insofar as damages can do that.

In order to attain this, the Contractor has approached the


calculation of the quantum of the damages by asking what
would have happened, had the breach not taken place, and
comparing that with what did actually happen. The measure of
the damage is the financial consequences flowing from the
difference between the two positions.

There is one generic type of potential direct damage suffered


while the other is the financing of the work. Those two aspects
are summarised in the two points below:

page 125
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

1. Loss of anticipated income by way of financing. This is


the cost to the Contractor of financing the shortfall
between the income he reasonably expected to receive,
and what he actually received.

2. The idle time, and/or reduced output, of resources from


the outset of the contract to the present date.

In addition, for the purpose of satisfying the Employer’s


requirements for identifying additional costs, the Contractor has
also included additional costs anticipated to January 2010. This
date is the latest the Contractor anticipates reaching substantial
completion given all the varying circumstances existing at site.

6.4. Conclusions
In failing to provide final survey data and all the various design
details, the unforeseen ground conditions, instructing
suspension of the Works and subsequently altering the
sequence, timing and logic of his original planning, the Employer
has caused the Contractor to unavoidably incur greater costs,
loss and expense than would have been the case had the failure
not occurred. These costs are evaluated in subsequent sections
of this submission.

Since these costs, losses and expense have flowed directly from
the Employer’s failure and subsequent deviation from the terms
of the Contract, the Contractor is entitled to be compensated for
them by the Employer paying a fair value for the different type of
work that has been performed.

page 126
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

7. Extension of Time Entitlement


The Project Manager is requested to refer to the Contractor’s
two separate submissions for extensions of time and the
detailed analysis included in those submissions.

The Contractor had planned that all his resources would be


deployed at Site from 7 March 2007 through to 31 May 2008. In
the event, because of circumstances beyond his control and not
his responsibility, it is anticipated resources of the Contractor will
be delayed at Site until 31 January 2010.

Therefore, in order to complete the whole Works, the Contractor


requires a further 20 months to reach substantial completion.
This includes the first and second requests for an interim
extension of the period to Completion, whereas:

1. Requested on 21 November 2007 for an


extension of time amounting to 191-calendar days
from 31 May 2008 to 8 December 2008. The
Project Manager’s determination has not been
issued at time of compiling this submission;

2. Requested on 14 March 2008 for an extension of


time amounting to 106-calendar days from 8
December 2008 to 24 March 2009. The Project
Manager’s determination has not been issued at
time of compiling this submission.

The Contractor on 19 November 2007 had also updated his


programme of works showing progress achieved at 6 November
2007. In the final paragraph he stated:

Unless notice is received stating the extent to which it


does not comply with the Contract, we shall proceed in
accordance with this programme and will rely upon this
programme when planning our activities.

The Project Manager has not responded to this notice at time of


compiling this submission or to making an interim determination
for an extension of time requested in neither the Contractor’s
First request nor his Second Request.

Consequently, the Extension of Time to which the Contractor is


now fairly entitled to receive amounts to 20 months from 31
May 2008 to 31 January 2010 as substantiated in this
submission. This is the date on which it is anticipated substantial
Completion will be achieved.

page 127
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

8. Additional Payment

8.1. Introduction
Each of the sections in this document briefly describes the
events that have occurred that are contrary to those envisaged
at time of tender. Therefore, allowance for the event so
described has not been made in the tender rates and prices.
This Chapter of the document contains the financial details,
demonstrating the reimbursable additional value or cost of these
disruptive events.

This unforeseen difficulty has impacted all the Contractor's


resources that were on site during the periods of delay and
disruption. In addition, the same resources are, as a
consequence of the varied circumstances, to be retained on Site
for a further 20 months. That is from the original Completion
date to 31 January 2010.

8.2. Evaluation of the Financial Consequences


The delay and disruption has been caused by late survey data,
unforeseen ground conditions, suspension of works, varied
scope of work and to incomplete and late design information.

Although the Contractor continued to perform as much work as


possible in these periods, the unforeseen conditions and
changed circumstances will cause the original time to
completion to extend from 31 May 2008 to 31 January 2010.

The extension of time and associated loss and expense the


Contractor has suffered falls into five categorises:

 In the original construction period when equipment and


labour resources were under-utilised and recovery of
overheads were not secured because of a reduced
income;

 In an extended period when again the equipment and


labour resources will be retained on Site for longer than
planned and overheads are not recovered;

 In measures taken to recover earlier delays by the


addition of resources and working longer hours; and

 Other Direct and Indirect Costs

page 128
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

 In the original and extended period of construction where


the cost of financing construction increased due to the
longer period to completion.

8.2.1.Wasted Costs Arising from Delay and Disruption


These costs arise in the period from commencement to May
2008.

8.2.1.1. Staff and Labour

The following table provides a summary of planned revenue


against actual. The fourth column records the shortfall value
which is expressed as a percentage on planned.

Forecast Actual Shortfall as a


Month Monthly Monthly Shortfall % of Forecast

Feb-07 3,100,000.00 0.00 3,100,000.00 100%


Mar-07 601,658.62 0.00 601,658.62 100%
Apr-07 1,352,295.74 0.00 1,352,295.74 100%
May-07 1,852,720.48 3,100,000.00 -1,247,279.52 -67%
Jun-07 2,236,090.71 0.00 2,236,090.71 100%
Jul-07 2,684,335.78 682,032.85 2,002,302.93 75%
Aug-07 2,189,910.64 351,989.15 1,837,921.49 84%
Sep-07 2,236,090.71 145,803.63 2,090,287.08 93%
Oct-07 2,258,038.74 357,556.62 1,900,482.12 84%
Nov-07 2,258,038.74 478,924.03 1,779,114.71 79%
Dec-07 1,754,288.50 0.00 1,754,288.50 100%
Jan-08 1,289,372.84 0.00 1,289,372.84 100%
Feb-08 1,040,280.70 274,355.16 765,925.54 74%
Mar-08 500,424.74 1,086,667.96 -586,243.22 -117%
Apr-08 2,575,212.46 0.00 2,575,212.46 100%
May-08 0.00 0.00 0.00 0%

The next table provides a summary of the actual cost of labour


from commencement to end of May 2008. Against these values
the percentage calculated representing the shortfall on revenue
has been applied to arrive at the value of wasted costs. To this
figure 15% profit has been added in order to properly value the
Variation.

page 129
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

Month LabourCost % Wasted AmountWasted 15%Profit Total

Mar-07 26,831.00 100% 26,831.00 4,024.65 30,855.65


Apr-07 47,046.00 100% 47,046.00 7,056.90 54,102.90
May-07 52,890.00 -67% -35,606.35 -5,340.95 -40,947.30
Jun-07 60,384.00 100% 60,384.00 9,057.60 69,441.60
Jul-07 60,984.00 75% 45,489.26 6,823.39 52,312.65
Aug-07 61,812.00 84% 51,876.82 7,781.52 59,658.34
Sep-07 61,812.00 93% 57,781.57 8,667.24 66,448.80
Oct-07 67,056.00 84% 56,437.80 8,465.67 64,903.47
Nov-07 80,944.00 79% 63,775.99 9,566.40 73,342.39
Dec-07 86,068.00 100% 86,068.00 12,910.20 98,978.20
Jan-08 86,709.00 100% 86,709.00 13,006.35 99,715.35
Feb-08 85,629.00 74% 63,045.90 9,456.89 72,502.79
Mar-08 90,629.00 -117% -106,171.08 -15,925.66 -122,096.75
Apr-08 90,629.00 100% 90,629.00 13,594.35 104,223.35
May-08 115,007.00 0% 0.00 0.00 0.00

Total 683,441.44

8.2.1.2. Equipment

The following table provides a summary of planned revenue


against actual. The fourth column records the shortfall value
which is expressed as a percentage on planned.

Forecast Actual Shortfall as a


Month Monthly Monthly Shortfall % of Forecast

Feb-07 3,100,000.00 0.00 3,100,000.00 100%


Mar-07 601,658.62 0.00 601,658.62 100%
Apr-07 1,352,295.74 0.00 1,352,295.74 100%
May-07 1,852,720.48 3,100,000.00 -1,247,279.52 -67%
Jun-07 2,236,090.71 0.00 2,236,090.71 100%
Jul-07 2,684,335.78 682,032.85 2,002,302.93 75%
Aug-07 2,189,910.64 351,989.15 1,837,921.49 84%
Sep-07 2,236,090.71 145,803.63 2,090,287.08 93%
Oct-07 2,258,038.74 357,556.62 1,900,482.12 84%
Nov-07 2,258,038.74 478,924.03 1,779,114.71 79%
Dec-07 1,754,288.50 0.00 1,754,288.50 100%
Jan-08 1,289,372.84 0.00 1,289,372.84 100%
Feb-08 1,040,280.70 274,355.16 765,925.54 74%
Mar-08 500,424.74 1,086,667.96 -586,243.22 -117%
Apr-08 2,575,212.46 0.00 2,575,212.46 100%
May-08 0.00 0.00 0.00 0%

The next table provides a summary of the actual cost of


equipment from commencement to end of May 2008. Against
these values the percentage calculated representing the
shortfall on revenue has been applied to arrive at the value of
wasted costs. To this figure 15% profit has been added in order
to properly value the Variation

page 130
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

Month EquipCost % Wasted AmountWasted 15%Profit Total

Mar-07 262,545.19 100% 262,545.19 39,381.78 301,926.96


Apr-07 262,545.19 100% 262,545.19 39,381.78 301,926.96
May-07 262,545.19 -67% -176,749.40 -26,512.41 -203,261.81
Jun-07 262,545.19 100% 262,545.19 39,381.78 301,926.96
Jul-07 262,545.19 75% 195,838.02 29,375.70 225,213.72
Aug-07 262,545.19 84% 220,345.72 33,051.86 253,397.58
Sep-07 262,545.19 93% 245,426.01 36,813.90 282,239.91
Oct-07 262,545.19 84% 220,971.60 33,145.74 254,117.34
Nov-07 262,545.19 79% 206,860.05 31,029.01 237,889.06
Dec-07 262,545.19 100% 262,545.19 39,381.78 301,926.96
Jan-08 262,545.19 100% 262,545.19 39,381.78 301,926.96
Feb-08 269,952.60 74% 198,757.50 29,813.62 228,571.12
Mar-08 293,656.30 -117% -344,015.79 -51,602.37 -395,618.16
Apr-08 293,656.30 100% 293,656.30 44,048.44 337,704.74
May-08 293,656.30 0% 0.00 0.00 0.00

Total 2,729,888.31

8.2.1.3. Site and Head Office

The following table provides the wasted costs associated with


the indirect staff and labour costs arising from the Site Office
overheads. The value of overheads is estimated to be at 3%.

Month LabourCost % Wasted AmountWasted 15%Profit Total

Mar-07 26,831.00 3% 804.93 120.74 925.67


Apr-07 47,046.00 3% 1,411.38 211.71 1,623.09
May-07 52,890.00 3% 1,586.70 238.01 1,824.71
Jun-07 60,384.00 3% 1,811.52 271.73 2,083.25
Jul-07 60,984.00 3% 1,829.52 274.43 2,103.95
Aug-07 61,812.00 3% 1,854.36 278.15 2,132.51
Sep-07 61,812.00 3% 1,854.36 278.15 2,132.51
Oct-07 67,056.00 3% 2,011.68 301.75 2,313.43
Nov-07 80,944.00 3% 2,428.32 364.25 2,792.57
Dec-07 86,068.00 3% 2,582.04 387.31 2,969.35
Jan-08 86,709.00 3% 2,601.27 390.19 2,991.46
Feb-08 85,629.00 3% 2,568.87 385.33 2,954.20
Mar-08 90,629.00 3% 2,718.87 407.83 3,126.70
Apr-08 90,629.00 3% 2,718.87 407.83 3,126.70
May-08 115,007.00 3% 3,450.21 517.53 3,967.74

Total 37,067.84

Similarly, the table below provides the wasted costs associated


with indirect staff and labour costs arising from the Head Office
overheads. The value of overheads is estimated to be 9%.

page 131
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

Month LabourCost % Wasted AmountWasted 15%Profit Total

Mar-07 26,831.00 9% 2,414.79 362.22 2,777.01


Apr-07 47,046.00 9% 4,234.14 635.12 4,869.26
May-07 52,890.00 9% 4,760.10 714.02 5,474.12
Jun-07 60,384.00 9% 5,434.56 815.18 6,249.74
Jul-07 60,984.00 9% 5,488.56 823.28 6,311.84
Aug-07 61,812.00 9% 5,563.08 834.46 6,397.54
Sep-07 61,812.00 9% 5,563.08 834.46 6,397.54
Oct-07 67,056.00 9% 6,035.04 905.26 6,940.30
Nov-07 80,944.00 9% 7,284.96 1,092.74 8,377.70
Dec-07 86,068.00 9% 7,746.12 1,161.92 8,908.04
Jan-08 86,709.00 9% 7,803.81 1,170.57 8,974.38
Feb-08 85,629.00 9% 7,706.61 1,155.99 8,862.60
Mar-08 90,629.00 9% 8,156.61 1,223.49 9,380.10
Apr-08 90,629.00 9% 8,156.61 1,223.49 9,380.10
May-08 115,007.00 9% 10,350.63 1,552.59 11,903.22

Total 111,203.51

The following table provides the wasted costs associated with


the indirect Equipment costs arising from the Site Office
overheads. The value of overheads is estimated to be at 3%.

Month EquipCost % Wasted AmountWasted 15%Profit Total

Mar-07 262,545.19 3% 7,876.36 1,181.45 9,057.81


Apr-07 262,545.19 3% 7,876.36 1,181.45 9,057.81
May-07 262,545.19 3% 7,876.36 1,181.45 9,057.81
Jun-07 262,545.19 3% 7,876.36 1,181.45 9,057.81
Jul-07 262,545.19 3% 7,876.36 1,181.45 9,057.81
Aug-07 262,545.19 3% 7,876.36 1,181.45 9,057.81
Sep-07 262,545.19 3% 7,876.36 1,181.45 9,057.81
Oct-07 262,545.19 3% 7,876.36 1,181.45 9,057.81
Nov-07 262,545.19 3% 7,876.36 1,181.45 9,057.81
Dec-07 262,545.19 3% 7,876.36 1,181.45 9,057.81
Jan-08 262,545.19 3% 7,876.36 1,181.45 9,057.81
Feb-08 269,952.60 3% 8,098.58 1,214.79 9,313.36
Mar-08 293,656.30 3% 8,809.69 1,321.45 10,131.14
Apr-08 293,656.30 3% 8,809.69 1,321.45 10,131.14
May-08 293,656.30 3% 8,809.69 1,321.45 10,131.14

Total 139,342.69

Similarly, the table below provides the wasted costs associated


with indirect staff and labour costs arising from the Head Office
overheads. The value of overheads is estimated to be 9%.

page 132
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

Month EquipCost % Wasted AmountWasted 15%Profit Total

Mar-07 262,545.19 9% 23,629.07 3,544.36 27,173.43


Apr-07 262,545.19 9% 23,629.07 3,544.36 27,173.43
May-07 262,545.19 9% 23,629.07 3,544.36 27,173.43
Jun-07 262,545.19 9% 23,629.07 3,544.36 27,173.43
Jul-07 262,545.19 9% 23,629.07 3,544.36 27,173.43
Aug-07 262,545.19 9% 23,629.07 3,544.36 27,173.43
Sep-07 262,545.19 9% 23,629.07 3,544.36 27,173.43
Oct-07 262,545.19 9% 23,629.07 3,544.36 27,173.43
Nov-07 262,545.19 9% 23,629.07 3,544.36 27,173.43
Dec-07 262,545.19 9% 23,629.07 3,544.36 27,173.43
Jan-08 262,545.19 9% 23,629.07 3,544.36 27,173.43
Feb-08 269,952.60 9% 24,295.73 3,644.36 27,940.09
Mar-08 293,656.30 9% 26,429.07 3,964.36 30,393.43
Apr-08 293,656.30 9% 26,429.07 3,964.36 30,393.43
May-08 293,656.30 9% 26,429.07 3,964.36 30,393.43

Total 418,028.07

8.2.1.4. Summary of Wasted Costs

Item Category Amount

Staff and Labour 683,441.44


Equipment 2,729,888.31
Site Overheads Staff and Labour 37,067.84
Equipment 139,342.69
Head Office Overheads Staff and Labour 111,203.51
Equipment 418,028.07

Total 4,118,971.85

8.2.2.Additional Costs Arising from Acceleration


In order to recover part of the earlier delays the Contractor has
already implemented steps to improve and increase his staff,
labour and equipment.

At this juncture the Contractor has ordered and organised the


following additional resources shown in the table below.

page 133
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

ID Designation Value UD$ Amount

Staff and Labour

1 Senior Project Manager 168,630.00


2 Quality Assurance Manager 168,630.00
3 Senior Quantity Surveyor 107,250.00
4 Assistant Quantity Surveyor 99,000.00
5 Expatriate Workers 880,000.00 1,423,510.00

Equipment

1 Potain tower crane (2Nr) 131,400.00


2 Scaffolding 105,791.00
3 Merlo Car-Mix 62,500.00
4 JCB 70,000.00
5 Concrete Paver 45,000.00
6 Rock Breaker 32,000.00
7 Mini Excavator (15 Tonne) 88,500.00 535,191.00

Total additonal resources 1,958,701.00

8.2.3.Additional Costs in Extended Contract Period


The Contractor has entitlement to recovery of his indirect costs
arising in the extended contract period. These costs arise in the
period the Contract is extended as a result of critical delays.

Consequently, this allowance has no relation to additional


expenditure arising in the original contract period as a result of
non-critical delays. That is to say, those costs that are attributed
to delay and disruption, the first period, are separate to costs
flowing in an extended period, the second period.

The Contractor has entitlement to payment of additional indirect


costs in the period they arise. However, this recovery would
exclude his indirect costs not paid through his rates and prices
for doing the work which remain recoverable in the extended
period. These costs are detailed below:

page 134
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

Item Nature of Cost Fixed Variable PlannedCost ExtendedPeriod

1 Insurance 250,000.00 17,857.14 321,428.57


2 Foreign Staff, Labour Repatriation 450,000.00 32,142.86 578,571.43
3 Facilities for Staff and Labour 170,000.00 12,142.86 218,571.43
4 Measures against Insect and Pect Nuisance 60,000.00 4,285.71 77,142.86
5 Supply of Foodstuffs 660,000.00 47,142.86 848,571.43
6 Supply of Water 80,318.00 5,737.00 103,266.00
7 Shop Drawings 10,000.00 714.29 12,857.14
8 As-Built Documents 5,600.00 400.00 7,200.00
9 Temporary Site Office for Employers Consultants 65,250.00 0.00 0.00
10 Site Signboard 3,275.00 0.00 0.00
11 Access to Site 35,000.00 2,500.00 45,000.00
12 Site to be Tidy 12,727.00 909.07 16,363.29
13 Co-ordination 14,727.00 1,051.93 18,934.71
14 Site Records 3,275.00 233.93 4,210.71
15 Site Records 29,913.00 2,136.64 38,459.57
16 Safety Procedures 5,700.00 407.14 7,328.57
17 Security at Site 13,426.00 959.00 17,262.00
18 Contractors Site Operations 7,485.00 534.64 9,623.57
19 Site Radio Communication 11,725.00 0.00 0.00
20 Environmental Impact Assessment 5,000.00 0.00 0.00
21 Taking Delivery from NS 50,000.00 3,571.43 64,285.71
22 Contractors Temporary Accommodation 35,000.00 2,500.00 45,000.00
23 Superintendence 15,000.00 1,071.43 19,285.71
24 Transport of People 125,475.00 8,962.50 161,325.00
25 Contractors Equipment 365,000.00 26,071.43 469,285.71
26 Scaffolding 105,000.00 7,500.00 135,000.00

Total 3,218,973.43

8.2.4.Other Costs
The following activities caused the Contractor to incur additional
costs because of the changed events described in this
document. At time of preparing this submission these costs have
yet to be ascertained and will therefore, be part of future claim
submissions.

8.2.4.1. Procurement of Permanent Materials

The following table provides a summary of all major materials


ordered on the project to date. It will be noted that all major
materials required for 55 number villas are ordered although the
constraint to receiving the complete order is payment.

The inability to complete full payment to the supplier has been


explained in various notifications, particularly the Advance
recovery which is disconnected from progress payments. This
compounded an existing reduced income generated each month
because progress could not be achieved as planned due to as
example, unforeseen ground conditions.

page 135
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment
Q uantity
Des c ription of Materials Ordered Date O rdered Amount rec eived B alanc e C omments

F OR AL L 55 VIL L AS

50K G bags P ortland C ement 2,800.00 04/04/07 300.00 2,500.00 B alance on order s ubject to payment to s upplier
P lywood for S huttering/R oofing 6,000.00 14/11/07 1,800.00 4,200.00 B alance on order s ubject to payment to s upplier
C rus her D us t 6,000.00 23/06/07 1,565.13 4,434.87 B alance on order s ubject to payment to s upplier
Aggregate 8,000.00 25/06/07 1,222.64 6,777.36 B alance on order s ubject to payment to s upplier
P las tering S and 1,000.00 16/07/07 80.00 920.00 B alance on order s ubject to payment to s upplier
150mm S oild concrete B locks 125,000.00 05/07/07 31,975.00 93,025.00 B alance on order s ubject to payment to s upplier
100mm Hollow concrete B locks 15,000.00 15/07/07 2,340.00 12,660.00 B alance on order s ubject to payment to s upplier
A252 W eld Mes h (R oadworks ) 912.00 14/05/07 162.00 750.00 B alance on order s ubject to payment to s upplier
High tens ile s teel-8,10,12,16,25mm (tons ) 500.00 14/01/07 158.00 342.00 B alance on order s ubject to payment to s upplier
C edar S hingles (s qm) 12,757.64 03/05/07 3,712.00 9,045.64 B alance on order s ubject to payment to s upplier
Iroko timber (external cladding) L M 54,198.00 07/05/07 1,548.00 52,650.00 B alance on order s ubject to payment to s upplier
12mm G yps um boards (S H E E T S ) 5,600.00 03/02/07 5,600.00 0.00 Awaiting for other building from I.D
S tainles s s teel threaded rods 12,16mm 16,300.00 09/11/07 8,110.00 8,190.00 B alance on order s ubject to payment to s upplier (Not B .O .Q item)
S tainles s s teel gus s et plates (variation) 450.00 09/11/07 50.00 400.00 B alance on order s ubject to payment to s upplier (Not B .O .Q item)
B alau T imber (L M) 169,074.50 08/06/07 6,148.16 162,926.34 B alance on order s ubject to payment to s upplier
T reated P ine T imber (L M) 94,148.50 20/04/07 43,225.50 50,923.00 B alance on order s ubject to payment to s upplier

Consequently, it is likely initial materials ordered and not


secured by full payment will attract a different cost at a later
date. The additional cost arising is not the responsibility of the
Contractor. These costs will be identified and evidenced at a
later date as they arise.

8.2.4.2. Temporary Materials including Equipment

A similar situation exists with temporary materials whereby


orders could not be made to enhance productivity at Site.

8.2.5.Finance Costs
The additional costs defined within the preceding sections of this
chapter on claim for additional payment have been borne and
financed by the Contractor. The Contractor has paid the costs
by obtaining bank loans or overdrafts, or by the use of working
capital that would have been employed in profitable work. These
financing costs are an additional cost incurred as a
consequence of the circumstances herein and, become part of
the reimbursable sum.

The Contractor has carried this additional cost since the outset
of the Contract to the present date, end of May 2008, a period of
about 14 months.

Compound interest over this period is against the heads of cost


amount to:

page 136
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

Month Labour Equipment Sub-total SiteO/H H/Q Total Sub-total Total

Mar-07 26,831.00 262,545.19 289,376.19 3.00% 9.00% 12.00% 34,725.14 324,101.33


Apr-07 47,046.00 262,545.19 309,591.19 3.00% 9.00% 12.00% 37,150.94 346,742.13
May-07 52,890.00 262,545.19 315,435.19 3.00% 9.00% 12.00% 37,852.22 353,287.41
Jun-07 60,384.00 262,545.19 322,929.19 3.00% 9.00% 12.00% 38,751.50 361,680.69
Jul-07 60,984.00 262,545.19 323,529.19 3.00% 9.00% 12.00% 38,823.50 362,352.69
Aug-07 61,812.00 262,545.19 324,357.19 3.00% 9.00% 12.00% 38,922.86 363,280.05
Sep-07 61,812.00 262,545.19 324,357.19 3.00% 9.00% 12.00% 38,922.86 363,280.05
Oct-07 67,056.00 262,545.19 329,601.19 3.00% 9.00% 12.00% 39,552.14 369,153.33
Nov-07 80,944.00 262,545.19 343,489.19 3.00% 9.00% 12.00% 41,218.70 384,707.89
Dec-07 86,068.00 262,545.19 348,613.19 3.00% 9.00% 12.00% 41,833.58 390,446.77
Jan-08 86,709.00 269,952.60 356,661.60 3.00% 9.00% 12.00% 42,799.39 399,460.99
Feb-08 85,629.00 293,656.30 379,285.30 3.00% 9.00% 12.00% 45,514.24 424,799.53
Mar-08 90,629.00 293,656.30 384,285.30 3.00% 9.00% 12.00% 46,114.24 430,399.53
Apr-08 90,629.00 293,656.30 384,285.30 3.00% 9.00% 12.00% 46,114.24 430,399.53
May-08 115,007.00 0.00 115,007.00 3.00% 9.00% 12.00% 13,800.84 128,807.84

Period Principle Amount Interest Finance Total


Month/Year Days Monthly Cummulative Gross Rate Value Amount

Mar-07 31.00 324,101.33 324,101.33 324,101.33 11.00% 3,027.91 327,129.23


Apr-07 30.00 346,742.13 327,129.23 673,871.36 11.00% 6,092.54 679,963.90
May-07 31.00 353,287.41 679,963.90 1,033,251.31 11.00% 9,653.11 1,042,904.42
Jun-07 30.00 361,680.69 1,042,904.42 1,404,585.11 11.00% 12,698.99 1,417,284.10
Jul-07 31.00 362,352.69 1,417,284.10 1,779,636.79 11.00% 16,626.20 1,796,262.98
Aug-07 31.00 363,280.05 1,796,262.98 2,159,543.03 11.00% 20,175.46 2,179,718.49
Sep-07 30.00 363,280.05 2,179,718.49 2,542,998.54 11.00% 22,991.49 2,565,990.03
Oct-07 31.00 369,153.33 2,565,990.03 2,935,143.36 11.00% 27,421.48 2,962,564.84
Nov-07 30.00 384,707.89 2,962,564.84 3,347,272.73 11.00% 30,263.01 3,377,535.74
Dec-07 31.00 390,446.77 3,377,535.74 3,767,982.51 11.00% 35,202.25 3,803,184.76
Jan-08 31.00 399,460.99 3,803,184.76 4,202,645.74 11.00% 39,263.07 4,241,908.82
Feb-08 28.00 424,799.53 4,241,908.82 4,666,708.35 11.00% 39,379.35 4,706,087.70
Mar-08 31.00 430,399.53 4,706,087.70 5,136,487.23 11.00% 47,987.46 5,184,474.69
Apr-08 30.00 430,399.53 5,184,474.69 5,614,874.22 11.00% 50,764.62 5,665,638.84
May-08 31.00 128,807.84 5,665,638.84 5,794,446.68 11.00% 54,134.42 5,848,581.10

Total Amount 415,681.34

Finance Costs will continue on this amount and in the remaining


contract period unless these additional costs are paid.

8.2.6.Grand Summary
The additional costs defined within the preceding sections of this
chapter are summarised below:

page 137
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

Gategory of Additional Cost Amount

Wasted Monthly Costs in Original Contract Period 4,118,971.85


Acceleration Costs 1,958,701.00
Finance Costs in Period 415,681.34
Extended Costs 3,218,973.43

Total Additional Costs to May 2008 9,712,327.62

page 138
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

9. Statement of Claim
During the course of performing the Contract Works to May
2008, the Contractor has drawn the Project Manager’s attention
to the fact that the Employer has deviated from certain of the
contractual requirements established in the Contract. He has
required the Contractor to perform the Contract Works in a
manner significantly different from that laid down in the Contract
Conditions and Specifications. These deviations are:

1. The Project Manager failed to provide setting out data in


variance to the Contract or the timing depicted on the
Programme of Works;

2. The Project Manager unnecessarily instructed a partial


suspension of the Works;

3. The Project Manager did not issue construction design


details in accordance with the Contract or the Contract
Programme of Works;

4. The discovery of significant had rock at many of the Villa


locations, which occurrence is an unforeseen condition as
allowed and described in the Contract;

5. The Project Manager did not issue construction design


details free from significant errors in accordance with the
Contract; and

6. The Project Manager has not properly measured, valued,


or paid for changes to the scope of work in respect of
additional time and cost.

The Contractor is entitled to payment, in respect of the


above matters for the reasons stated. In addition he is also
entitled to an extension of time all as summarised below:

Head of Claim EOT Months Value


Extension of time (31 May 08 – 31Jan 09) 20 3,218,973.43
Wasted Costs to May 2008 In period 4,118,971.85
Acceleration Costs In extended period 1,958,701.00
Finance Costs To May 2008 415,681.34
Total Entitlement USD 9,712,327.62

page 139
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

10.Appendices

10.1. Wasted Costs


10.1.1. Record of Resources – Staff and Labour

10.1.2. Record of Resources – Equipment

10.1.3. Direct and Indirect Costs


The following table provides figures from the Contractor’s
audited accounts.

The next table shows the average indirect costs for the head
office (Victoria, Mahe) and site office expressed as a
percentage. The Contractor expects to recover as a return on
turnover, approximately 9% on the head office costs and 3% for
the site office costs.

page 140
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

10.2. RFI and RFA


ID Date Reference From To Subject EventType Location EventDescription Notes
Roof trusses - Stainless steel Contractor requested for detailed PM stated the designs shall follow
plates - Detailed drawings Request for designs for stainless steel plates forthose of the mock up villas already
001 10-Mar-08 RFI-001 Island Construction Polus Investments required Information Villas & Buildings all the remaining buildings constructed
Contractor requested the detailed PM provided the required information
Thermal Roof Insulation - Request for Mock up villas and design and insulation details for on 16 Mar '08. Information was
002 10-Mar-08 RFI-002 Island Construction Polus Investments Design details required Information other buildings thermal roof insulation required by 15 March 2008
PM provided clarification on 13 March
A3 Villas - Decking Span - Request for Contractor requested clarification on 2008. Information was required by 15
003 12-Mar-08 RFI-003 Island Construction Polus Investments Clarification Required Information A3 Villas the span of the timber decking March 2008
Request for clarification on Request for Contractor requested clarification on
004 10-Mar-08 RFI-004 Island Construction Polus Investments socket position at B2/03 Information B2/03 the socket position at B2/03 Clarification provided

A3 Villas - Lanai screens - Request for Contractor requested design for Clarification provided on 13 Mar '08.
005 12-Mar-08 RFI-005 Island Construction Polus Investments designs required Information A3 Villas lanai screens Information was required by 15 Mar '08
All Villas – Bathroom Entrance
Door Type DO.02 – Infill Clarification required on the
Bamboo Resin Panel – Request for descrepancy in sizes of the bamboo
006 12-Mar-08 RFI-006 Island Construction Polus Investments Discrepancy in Size Information Villas resing panel Clarification provided
Clarification required on the
Mock Up Villas – Window Sill & desrepancy in sizes of window sill
Lining Details – Cut Stone Request for Mock up villas A3/32 shown in the desgn and the one Clarification provided on 16 Mar '08.
007 13-Mar-08 RFI-007 Island Construction Polus Investments Cladding – Discrepancy in Size Information and B2/03 supplied Information was required by 16 Mar 08

Ironmongery – Supplier – Other Request for Further contact details of


008 14-Mar-08 RFI-008 Island Construction Polus Investments Contact Details Required Information Villas ironmongery supplier required Not yet provided

page 141
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

10.3. Correspondence
ID Date Reference From To Subject EventType Location EventDescription Notes
PS, Ministry of Concessions Granted for the Shangri-La Resort Concessions granted during the
001 05-Jul-07 FIN/PS/POLUS/83 Finance Polus Investments Project Information Project construction phase of the project
Environment Visit Report - 10 Shangri-La Resort Contractor's response to
002 11-Jul-07 LIHRD/env/05 Island Construction Polus Investments July 2007 Environmental Project Environmental visit report
Quotation for Retaining Wall
along CHI-SPA Shangri-La Resort Quotation for Retaining wall along
003 30-Aug-07 LIHRD/VO/01 Island Construction Polus Investments area/Restaurant Area Quotation Project CHI-SPA area/Restaurant area
Shangri-La Resort PM requested to approve the list of
004 30-Aug-07 LIHRD/VO/02 Island Construction Polus Investments List of Variations Variations Project variations
Shangri-La Resort New rates for boat transport as a
005 03-Sep-07 Angel Fish Island Construction New Rates for Boat Transport Information Project result of increased fuel prices
Shangri-La Resort Schedules for boat transport from
006 12-Sep-07 Island Construction Angel Fish Transfer Boat to Long Island Information Project Mahe to Long Island and back
Inquiry from Independent Shangri-La Resort Submission of the company's
007 19-Sep-07 Island Construction Polus Investments Engineer Information Project technical profile
Instructed variations and changes are
being made prior to reaching
agreement on the price contrary to
terms and conditions of the contract.
Lump Sum Contract Price - There exists disparities between BQ
Variations to Scope of Works - Shangri-La Resort Request for Employer's agreement to quantities and quantities measured
008 24-Oct-07 Island Construction Polus Investments Instructions Variations Project payment of changes and variations from construction drawings.

Timing and sequence for the mock up


villas is not allowed in the POW,
material procurement and labour
The requirement to complete Mock requirements are in variance to original
up villas is a variation. Detailed planning, advance construction of the
particulars of associated delays and mock-up villas continues to be an
Mock-up Villas - Variation Variation & Shangri-La Resort additional costs shall be submitted impediment on the rate of progress for
009 24-Oct-07 Island Construction Polus Investments Instruction - Additional Costs Notification Project once ready other parts of works.
Disagreement to Minutes of meeting
No. 23 and all previous minutes.
Minutes of Meeting No.23 - Proposal by the Contractor to verify The minutes are in Contractor's view
Recorded Minutes - Not Shangri-La Resort and comment on the minutes before inaccurate and have not received
010 24-Oct-07 Island Construction Polus Investments Approved Information Project circulation Contractor's concurrence.
Notification of Contractor's
Suspension of Works- entitlement to time extension and In addition, the Contractor awaits PM's
Extension of Time & Additional Shangri-La Resort additional costs occassioned by instruction to proceed with all the works
011 26-Oct-07 Island Construction Polus Investments Payment-Notice Notification Project suspension of works. affected by the suspension notice
Notification of delay and disruption The changes constiture variation.
Setting Out - Late Instructions & Notification & Shangri-La Resort occassioned by varied location, Associated delays and costs to be
012 26-Oct-07 Island Construction Polus Investments Variations - Additional Costs Variation Project position and orientation of buildings submitted once ready
Request for PM's concurrence with
Advance Payment - Unfixed Contractor's intention to raise a
Materials & Goods - Payment Shangri-La Resort separate statement for payment of
013 26-Oct-07 Island Construction Polus Investments Application Payment Project Unfixed Materials and Goods
Shangri-La Resort Quotation for earth filling to CHI-SPA
014 26-Oct-07 Island Construction Polus Investments Earth Filling to CHI-SPA area Quotation Project area

page 142
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

Shangri-La Resort
015 26-Oct-07 Island Construction Polus Investments Quotation for Rock Excavation Quotation Project Quotation for rock excavation

Contractor maintains changes in the


location, position and orientation of
buildings constitute variation, hence
delays and additional costs, detailed
Setting Out - Late Instructions & Shangri-La Resort particulars of which will be submitted
016 29-Oct-07 Island Construction Polus Investments Variations - Additional Costs Variation Project once available

Contractor maintains he has


Suspension of Works- entitlement to extensions of time and
Extension of Time & Additional Shangri-La Resort recovery of costs due to suspension.
017 29-Oct-07 Island Construction Polus Investments Payment-Entitlement Determination Project Awaiting PM's determination
Programme - Revision 1 Dated
6th Nov 2007 - Progress of Programme of Shangri-La Resort Submission of Revised Programme
018 19-Nov-07 Island Construction Polus Investments Works Works Project of Works

Interim Statement No. 3 - Issue


of Interim Payment Certificate - Shangri-La Resort Undercertification shall subsequently
019 19-Nov-07 Island Construction Polus Investments Contract Procedure Payment Project attract finance costst

Cash Flow Forecast - Advance Shangri-La Resort


020 19-Nov-07 Island Construction Polus Investments Repayment - Ammendment Cash Flow Project Ammended cash flow forecast
Shangri-La Resort
021 20-Nov-07 LIHRD/PC/05 Island Construction Polus Investments Interim Statement No. 3 Statement Project Application for Payment for works
The Contractor claims extension of
Extension of Time for time for completion up to 8 Dec 08
Completion-First Interim Shangri-La Resort and additional costs amounting to
022 21-Nov-07 Island Construction Polus Investments Entitlement-Claim Claim Project US$ 857,145.00
Ammeded cash flow forecast
Cash Flow Forecast - Advance consequent to the extended contract
Repayment - Proposed Shangri-La Resort period as per the revised programme
023 21-Nov-07 Island Construction Polus Investments Revisions Cash Flow Project of works
Clarification on time and money
issues contained in the minutes and
notification of intention to submit
Minutes of Meeting Nr. 27 - Clarification & Shangri-La Resort additional costs for acceleration of
024 21-Nov-07 Island Construction Polus Investments Clarification - Notice Notice Project works
Contractor requests a Variation
Variations & Adjustments - Meeting to discuss and agree on all
Instructed Changes & Additions Claims & Shangri-La Resort the variations and claims on the The Variations and claims identified so
025 23-Nov-07 Island Construction Polus Investments - Measurement & Evaluation Variations Project project to date far are listed
PM states it is the Contractor who
suspended the works hence refuse to The PM encloses previous email
Shangri-La Resort approved any Extension of time and correspondences with the Contractor
026 23-Nov-07 E-01-23.11.07 Polus Investments Island Construction Suspension of works Claim Project Additional Costs over the issue

Shangri-La Resort PM will endeavour to issue meeting


027 23-Nov-07 E-01-23.11.07 Polus Investments Island Construction Minutes of Meeting Information Project minutes by every Wednesday

page 143
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

Instruction to vary any part of the


works whether for the specification or PM agrees to have mutual
Measurement and Payment for Shangri-La Resort quantities is additional work entitled measurement of variation and payment
028 23-Nov-07 E-03-23.11.07 Polus Investments Island Construction Variations Variations Project to additional payment thereof
Shangri-La Resort The PM states mock up villas do not
029 23-Nov-07 E-04-23.11.07 Polus Investments Island Construction Mock-up Villas Variations Project comprise variation
Shangri-La Resort All communications must be
030 23-Nov-07 E-05-23.11.07 Polus Investments Island Construction Clients Address Address Project addressed to the Project Manager
Setting out at Site - Changes in Variation & Shangri-La Resort PM requires detailed particulars for
031 23-Nov-07 E-06-23.11.07 Polus Investments Island Construction Positions, Orientation Claim Project associated delays and costs
PM awaits detailed document
Clarification & Shangri-La Resort regarding Variations and claims so
032 23-Nov-07 E-07-23.11.07 Polus Investments Island Construction Minutes of Meeting Notice Project far identified

Variations & Adjustments -


Instructed Changes & Additions Shangri-La Resort PM agrees to value changes in
033 04-Dec-07 E-09-04.12.07 Polus Investments Island Construction - Measurement & Evaluation Variations Project design and quantities as Variations

Interim Statement No.3 - Issue The Invoice required is not


of Interim Payment Certificate - Shangri-La Resort contractual but solely for accounting
034 04-Dec-07 E-08-04.12.07 Polus Investments Island Construction Contract Procedure Payment Project purposes

Contractor proposes the amount in


General Contractor's the Performance Security is reduced
Obligations-Performance Performance Shangri-La Resort equal to the amount of cover included
035 07-Dec-07 Island Construction Polus Investments Security-Reduction of Amount Security Project in the EME's performance security

The Letter of Acceptance takes


priority over the conditions of
contract. As such, in practice it
means that no variation arising from
Variations & Adjustments - aditional work or design change can
Instructed Changes & Additions Shangri-La Resort commence prior to receiving the
036 08-Dec-07 Island Construction Polus Investments - Measurement & Evaluation Variations Project agreement of the Employer
Shangri-La Resort
037 19-Dec-07 E-13-19.12.07 Polus Investments Island Construction List of Plants for A3/32 - B2/03 Landscaping Project Enclosed list of plants
The PM can still issue a payment
Interim Statements for Payment certificate even when the amount falls
- Issue of Interim Payment Shangri-La Resort below the minimum payable by the
038 24-Dec-07 Island Construction Polus Investments Certificate-Payment Payment Project Employer

Contractor maintains Mock-up villas


is a variation because the
Mock-up Villas - Variation Shangri-La Resort procurement process is in complete
039 24-Dec-07 Island Construction Polus Investments Instruction - Additional Costs Variation Project variance to original planning
Shangri-La Resort
040 15-Jan-08 Polus Investments Island Construction Specification for Door panelling Specification Project Specification for door panelling

Environment Visit Report - 13 Shangri-La Resort Contractor required to take necessary


041 17-Jan-08 E-14-17.01.08 Polus Investments Island Construction Dec 2007 Environmental Project measures to improve the situation

page 144
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

Environmental - Monitoring visit


for Class 1 Project and SPA at Shangri-La Resort Steps being taken to address the
042 21-Jan-08 Island Construction Polus Investments Long Island Environmental Project environmental issues
Roof structure gusset plate Shangri-La Resort The proposed 4.5mm thick gusset
043 22-Jan-08 Island Construction Polus Investments design Design Project plate is appropriate for use
Shangri-La Resort
044 29-Jan-08 Polus Investments Island Construction Revised cash flow Cash Flow Project PM forwards a revised cashflow

Shangri-La Resort PM requires the mock-up villas


045 29-Jan-08 E-14-29.01.08 Polus Investments Island Construction Mock-up Villas - Variation Variation Project completed as per original programme
Shangri-La Resort Payment has been made to the Main
046 30-Jan-08 E-15-30.01.08 Polus Investments Island Construction Certification and Payment Payment Project Contractor
Shangri-La Resort
047 30-Jan-08 Polus Investments Island Construction Approved Balustrade Design Project Pictures of approved balustrade
Shangri-La Resort 2 Hard copies of the statement
048 04-Feb-08 E-16-04.02.08 Polus Investments Island Construction Statement Statement Project required
Minutes of meeting between Zsolt
Shangri-La Resort and Wilson. Action by Contractor
049 06-Feb-08 Polus Investments Island Construction Site Issues General Project required
Shangri-La Resort
050 07-Feb-08 Island Construction Polus Investments Site Issues General Project Response to issues raised above
Programme of Shangri-La Resort Contractor required to submit revised
051 13-Feb-08 E-18-13.02.08 Polus Investments Island Construction Revised Programme of works Works Project programme of works

The negative amount reflects very


slow progress at site. Submit revised
Payment Certificate & Rate of Shangri-La Resort POW and supporting report outlining
052 13-Feb-08 E-19-13.02.08 Polus Investments Island Construction Progress Certificate Project methods to expedite progress

Nominated Subcontractor EME Existing contractual matters that


Overseas Ltd - Design and prevent execution of agreement
Build Subcontract Conditions - Shangri-La Resort between Island Construction Pty ltd
053 26-Feb-08 Island Construction Polus Investments Objection to Nomination Subcontract Project and EME overseas
Suspension of Works -
Extension of time and Entitlement to Extensions of time and
Additional Payment - Suspension of Shangri-La Resort additional payment arising from
054 27-Feb-08 Island Construction Polus Investments Entitlement Works Project instruction to suspend works
Delaying Events Shangri-La Resort Delaying Events and Proposed
055 01-Mar-08 Island Construction Polus Investments Situation Report Details Project Financial Arrangements
Delaying Events & Changed
Circumstances - Revised
Programme of works - Request for
Extension of time for Extension of Shangri-La Resort Request for extension of time for
057 14-Mar-08 Island Construction Polus Investments completion Time Project completion to 24 March 2009
Cash Flow Forecast - Advance Revision of
Repayment - Proposed Advance Shangri-La Resort Proposed amendment of cashflow
058 19-Mar-08 Island Construction Polus Investments Revision Recovery Project with revised advance recovery
Shangri-La Resort
059 07-Apr-08 Island Construction Polus Investments Extension of time Time Extension Project Detailed particulars required

page 145
Island Construction (Pty) Ltd Shangri-La Resort Development
Interim Request for Extension of Time and Additional Payment

Interim Report on Programme Programme & Shangri-La Resort Report on Programme of Works and
056 08-Apr-08 Island Construction Polus Investments of Works, Progress & Valuation Valuation Report Project Request for Time Extension
PM responds to ICCL's objection to
Shangri-La Resort enter into nominated subcontract with
060 09-Apr-08 E-18-09.04.08 Polus Investments Island Construction Nominated Subcontractor Subcontract Project EME
Nominated Subcontract -
Subcontract Agreement - Shangri-La Resort Reason for Objection of nominated
061 14-Apr-08 E-17-07.04.2008 Polus Investments Island Construction Reason for Objection Subcontract Project subcontract agreement
Extension of Time for
Completion - First Interim Detailed Request for approval to submit
Entitlement - Detailed particulars for Shangri-La Resort detailed particulars within 45 days
062 15-Apr-08 Island Construction Polus Investments Particulars Extension of time Project from 15 April 2008
Shangri-La Resort Statement for works done up to End
063 15-Apr-08 Island Construction Polus Investments Interim Statement Nr. 08 Statement Project of March 2008
Interim Statement Nr. 08 -
Materials On & Off site - Shangri-La Resort Amended statement incorporating off
064 17-Apr-08 Island Construction Polus Investments Amendment Statement Project site Balau timber

Landscaping - Additional Work - Shangri-La Resort Confirmation of oral instruction to


065 17-Apr-08 Island Construction Polus Investments Confirmation of Oral Instruction Additional Works Project execute landscaping works
Delay to Completion - Recovery
Programme - Approval to Shangri-La Resort Request for approval to accelerate
066 21-Apr-08 Island Construction Polus Investments Accelerate Programme Project works
PM states ICCL has not
Extension of Shangri-La Resort demonstrated entitlement to time
067 02-May-08 E19-02.05.08 Polus Investments Island Construction Delays Time Project extension
Shangri-La Resort
068 05-May-08 E-21-05.05.08 Polus Investments Island Construction Valuation Certificate Payment Project Valuation certificate No. 08
Shangri-La Resort
069 06-May-08 Island Construction Polus Investments Interim Payment - Invoice No. 7 Payment Project Invoice for Interim Payment
Valuation No. 8 - Cession of
Right for Material On and Off Shangri-La Resort Cession of right for materials on and
070 07-May-08 Island Construction Polus Investments Site Materials On Site Project off site
The Employer is contemplating
Programme of Shangri-La Resort engaging others to expedite progress
071 09-May-08 E20-09.05.08 Polus Investments Island Construction Accelerative measures Works Project of works
Programme of Shangri-La Resort PM outlines ways of putting the
072 12-May-08 E21-12.05.08 Polus Investments Island Construction Recovery Measures Works Project recovery measures into effect

Employer proposes the contractor


engages in discussions with PM on
Delays and Completion of Shangri-La Resort the ammendment of the contract and
073 19-May-08 Polus Investments Island Construction works Delays Project the remedial measures
Claim for Time and Additional
Payment - Entitlement - Shangri-La Resort ICCL informs PM detailed particulars
074 28-May-08 Island Construction Polus Investments Determination Claim Project will be submitted on 09 June 2008

page 146