Assumptions:
Cement and Sand (1:3) mix (Inclusive Wastage) = RM 293.42 per m
Labour Gang (2:1) = 1 Plasterer : General Labourer
= 1 Spreader : General Labourer
Wage of Plasterer (skilled - Foreign) = RM 90.00 per day
Wage of Spreader (skilled - Foreign) = RM 90.00 per day
Wage of General Labourer = RM 65.00 per day
Output of spreader = 3.0m per hour
Output of plasterer = 2.5m per hour
Materials waste = 5%
Profit and overhead = 15%
Working Hours = 8 Hours
Material Cost
a) Cost of cement and sand = (RM 293.42 per m x 0.020m) = 5.87
b) Material waste = 5% x RM 5.87 = 0.29
Total Cost of material per m = 6.16
Labour cost
Laying 20mm thick bed (2:1)
Output of 1 spreader : General labourer = 3.0m per hour
a) 1 Spreader = ( 1 x RM 90.00/8 hour )/3.0m per hour = 3.75
b) General Labourer = ( x RM65/8hours)/3.0m per hour = 1.35
Total cost for 20mm Thick Cement and Sand (1:3) Plaster = 17.39
15% OHP = 2.61
Total unit rate (RM) per m = 20.00
WALL FINISHES
Extra over for groove line
Assumption:
15mm x 15mm deep U-Shape PVC Grove Line = RM 1.50 per meter
Profit and overhead = 15%
Material Cost
a) 15mm x 15mm deep U-Shape PVC Grove Line = 1.50
Total cost of material per m 1.50
Assumptions:
Cement and Sand (1:6) mix (Inclusive Wastage) = RM 215.02 per m
Labour Gang (2:1) = 1 Plasterer : General Labourer
= 1 Spreader : General Labourer
Wage of Plasterer (skilled - Foreign) = RM 90.00 per day
Wage of Spreader (skilled - Foreign) = RM 90.00 per day
Wage of General Labourer = RM 65.00 per day
Output of spreader = 3.0m per hour
Output of plasterer = 2.5m per hour
Materials waste = 5%
Profit and overhead = 15%
Working Hours = 8 Hours/day
Material Cost
a) Cost of cement and sand = (RM 215.02 per m x 0.020m) = 4.30
b) Material waste = 5% x RM 4.30 = 0.22
Total Cost of material per m = 4.52
Labour cost
Laying 20mm thick bed (2:1)
Output of 1 spreader : General labourer = 3.0m per hour
a) 1 Spreader = ( 1 x RM 90.00/8 hour )/3.0m per hour = 3.75
b) General Labourer = ( x RM65/8hours)/3.0m per hour = 1.35
Total cost for 20mm Thick Cement and Sand (1:6) Plaster = 15.74
15% OHP = 2.36
Total unit rate (RM) per m = 18.11
WALL FINISHES
13mm Thick Cement and Sand (1:3) Screed
Assumptions:
Cement and Sand (1:3) mix (Inclusive Wastage) = RM 293.42 per m
Labour Gang (2:1) = 1 Spreader : General Labourer
Wage of Spreader (skilled - Foreign) = RM 90.00 per day
Wage of General Labourer = RM 65.00 per day
Output of spreader = 3.0m per hour
Materials waste = 5%
Profit and overhead = 15%
Working Hours = 8 Hours/day
Material Cost
a) Cost of cement and sand = (RM 293.42 per m x 0.013m) = 3.81
b) Material waste = 5% x RM 3.81 = 0.19
Total Cost of material per m = 4.01
Labour cost
Sceeding 13mm thick bed (2:1)
Output of 1 spreader : General labourer = 3.0m per hour
a) 1 Spreader = ( 1 x RM 90.00/8 hour )/3.0m per hour = 3.75
b) 1 General Labourer = ( x RM65/8hours)/3.0m per hour = 1.35
Total Labour Cost per m = 5.10
Total cost for 13mm Thick Cement and Sand (1:3) Screed = 9.11
15% OHP = 1.37
Total unit rate (RM) per m = 10.48
WALL FINISHES
200mm x 250mm "GUOCERA" Classic White Matt PL411AA ceramic tiles
Assumptions:
Tiling
Cost of tile delivered to site = RM 1.50 per piece
Colour cement for pointing (inclusive wastage) = RM 1.00 per m
Tiles adhensive, 25kg = RM 14.50
Tiles adhensive required for 1m (inclusive wastage) = 5kg per m
Labour off-loading and stacking of tiles = 3 minutes per m
Labour gang for Tiling = 2 Tilers : 1 general labourer
Wage of labour for pointing = RM 3.50 per m
Wage of tiler (Skilled - Foreign) = RM 120.00 per day
Wage of General Labour = RM 65.00 per day
Working hour = 8 hours per day
Wastage on tiles = 5%
Profit and overhead = 15%
Material Cost
a) Cost of tiles per m
=(1m/(0.200m x 0.250m)) x RM1.50/piece = 30.00
b) Labour off-loading and stacking per m
=(3 miniutes/60 minutes) x (RM65.00 / 8 hours) = 0.41
Cost of material per m = 30.41
c) Waste on tiles = (5% x RM 30.41) = 1.52
d) Colour cement for pointing per m (inclusive wastage) = 3.00
e) Tiles adhensive = (5kg/25kg) x RM 14.50 = 2.90
Total Cost of Materials per m = 37.83
Labour Cost
Laying tiles (2:1)
Output of 1 tiler : 1/2 labour = 0.75 hour per m
Output of 2 tilers : 1 labour = 0.375 hour per m
WALL FINISHES
200mm x 250mm "GUOCERA" Venner Grey F276CH ceramic tiles
Assumptions:
Tiling
Cost of tile delivered to site = RM 1.80 per piece
Colour cement for pointing (inclusive wastage) = RM 1.00 per m
Tiles adhensive, 25kg = RM 14.50
Tiles adhensive required for 1m (inclusive wastage) = 5kg per m
Labour off-loading and stacking of tiles = 3 minutes per m
Labour gang for Tiling = 2 Tilers : 1 general labourer
Wage of labour for pointing = RM 3.50 per m
Wage of tiler (Skilled - Foreign) = RM 120.00 per day
Wage of General Labour = RM 65.00 per day
Working hour = 8 hours per day
Wastage on tiles = 5%
Profit and overhead = 15%
Material Cost
a) Cost of tiles per m
=(1m/(0.200m x 0.250m)) x RM1.80/piece = 36.00
b) Labour off-loading and stacking per m
=(3 miniutes/60 minutes) x (RM65.00 / 8 hours) = 0.31
Cost of material per m = 36.31
c) Waste on tiles = (5% x RM 36.31) = 1.82
d) Colour cement for pointing per m (inclusive wastage) = 3.00
e) Tiles adhensive = (5kg/25kg) x RM 14.50 = 2.90
Total Cost of Materials per m = 44.03
Labour Cost
Laying tiles (2:1)
Output of 1 tiler : 1/2 labour = 0.75 hour per m
Output of 2 tilers : 1 labour = 0.375 hour per m
WALL FINISHES
200mm x 250mm "GUOCERA" Fusian Magnolia F326D ceramic tiles
Assumptions:
Tiling
Cost of tile delivered to site = RM 1.80 per piece
Colour cement for pointing (inclusive wastage) = RM 1.00 per m
Tiles adhensive, 25kg = RM 14.50
Tiles adhensive required for 1m (inclusive wastage) = 5kg per m
Labour off-loading and stacking of tiles = 3 minutes per m
Labour gang for Tiling = 2 Tilers : 1 general labourer
Wage of labour for pointing = RM 3.50 per m
Wage of tiler (Skilled - Foreign) = RM 120.00 per day
Wage of General Labour = RM 65.00 per day
Working hour = 8 hours per day
Wastage on tiles = 5%
Profit and overhead = 15%
Material Cost
a) Cost of tiles per m
=(1m/(0.200m x 0.250m)) x RM1.80/piece = 36.00
b) Labour off-loading and stacking per m
=(3 miniutes/60 minutes) x (RM65.00 / 8 hours) = 0.41
Cost of material per m = 36.41
c) Waste on tiles = (5% x RM 36.41) = 1.82
d) Colour cement for pointing per m (inclusive wastage) = 3.00
e) Tiles adhensive = (5kg/25kg) x RM 14.50 = 2.90
Total Cost of Materials per m = 44.13
Labour Cost
Laying tiles (2:1)
Output of 1 tiler : 1/2 labour = 0.75 hour per m
Output of 2 tilers : 1 labour = 0.375 hour per m
WALL FINISHES
200mm x 330mm "GUOCERA" Loft Mink H265D ceramic tiles
Assumptions:
Tiling
Cost of tile delivered to site = RM 2.20 per piece
Colour cement for pointing (inclusive wastage) = RM 1.00 per m
Tiles adhensive, 25kg = RM 14.50
Tiles adhensive required for 1m (inclusive wastage) = 5kg per m
Labour off-loading and stacking of tiles = 3 minutes per m
Labour gang for Tiling = 2 Tilers : 1 general labourer
Wage of labour for pointing = RM 3.50 per m
Wage of tiler (Skilled - Foreign) = RM 120.00 per day
Wage of General Labour = RM 65.00 per day
Working hour = 8 hours per day
Wastage on tiles = 5%
Profit and overhead = 15%
Material Cost
a) Cost of tiles per m
=(1m/(0.200m x 0.330m)) x RM2.20/piece = 33.33
b) Labour off-loading and stacking per m
=(3 miniutes/60 minutes) x (RM65.00 / 8 hours) = 0.41
Cost of material per m = 33.74
c) Waste on tiles = (5% x RM 33.74) = 1.69
d) Colour cement for pointing per m (inclusive wastage) = 3.00
e) Tiles adhensive = (5kg/25kg) x RM 14.50 = 2.90
Total Cost of Materials per m = 41.33
Labour Cost
Laying tiles (2:1)
Output of 1 tiler : 1/2 labour = 0.75 hour per m
Output of 2 tilers : 1 labour = 0.375 hour per m
WALL FINISHES
200mm x 250mm "GUOCERA" Fusian Charcoal F326E ceramic tiles
Assumptions:
Tiling
Cost of tile delivered to site = RM 1.80 per piece
Colour cement for pointing (inclusive wastage) = RM 1.00 per m
Tiles adhensive, 25kg = RM 14.50
Tiles adhensive required for 1m (inclusive wastage) = 5kg per m
Labour off-loading and stacking of tiles = 3 minutes per m
Labour gang for Tiling = 2 Tilers : 1 general labourer
Wage of labour for pointing = RM 3.50 per m
Wage of tiler (Skilled - Foreign) = RM 120.00 per day
Wage of General Labour = RM 65.00 per day
Working hour = 8 hours per day
Wastage on tiles = 5%
Profit and overhead = 15%
Material Cost
a) Cost of tiles per m
=(1m/(0.200m x 0.250m)) x RM1.80/piece = 36.00
b) Labour off-loading and stacking per m
=(3 miniutes/60 minutes) x (RM65.00 / 8 hours) = 0.41
Cost of material per m = 36.41
c) Waste on tiles = (5% x RM 36.41) = 1.82
d) Colour cement for pointing per m (inclusive wastage) = 3.00
e) Tiles adhensive = (5kg/25kg) x RM 14.50 = 2.90
Total Cost of Materials per m = 44.13
Labour Cost
Laying tiles (2:1)
Output of 1 tiler : 1/2 labour = 0.75 hour per m
Output of 2 tilers : 1 labour = 0.375 hour per m