You are on page 1of 7

OBRA : CONSTRUCCION DEL CANAL PRINCIPAL DE CONDUCCION, TRAMO NEPEA CASMA

CONCLUSION KM 71+810 AL KM 87+920


CONTRATISTA : CONSORCIO VETA COLORADA
SUPERVISION : SISA CONSULTORES SA
JJM MINERIA & CONSTRUCCION
SUBCONTRATISTA : JJM Mineria y Construccin SAC

2.02 2.03 2.04 2.05 2.06


PROGRESIVA DISTANCIA AREA CORTE A. CORTE CERRADO AREA RELLENO MS RD RF EPCMS EPCRD EPCRF ECCMS ECCRD
74+300 29.02 13.76 27.54 100%
74+320 20.00 59.27 10.18 100% 882.90
74+340 20.00 120.36 10.18 100% 1,796.30
74+360 20.00 105.42 10.18 100% 2,257.80
74+380 20.00 10.93 10.18 100% 1,163.50
74+400 20.00 - 7.03 76.32 100% 109.30
74+420 20.00 7.07 2.85 53.23 100% 70.70
74+440 20.00 68.88 10.18 100% 759.50
74+460 20.00 32.86 10.18 1,017.40
74+480 20.00 19.68 10.18 525.40

75+360 73.13 19.53 100%


75+380 20.00 60.46 16.05 100% 1,335.90
75+400 20.00 40.59 18.42 100% 1,010.50
75+420 20.00 27.85 19.44 100% 684.40
75+440 20.00 16.27 18.78 100% 441.20
75+460 20.00 13.37 19.61 100% 296.40
75+480 20.00 13.40 17.55 100% 267.70
75+500 20.00 9.94 17.56 100% 233.40

82+400 71.09 100% -


82+420 20.00 82.68 100% 1,537.70
OBRA : CONSTRUCCION DEL CANAL PRINCIPAL DE CONDUCCION, TRAMO NEPEA CASMA
CONCLUSION KM 71+810 AL KM 87+920
CONTRATISTA : CONSORCIO VETA COLORADA
SUPERVISION : SISA CONSULTORES SA
JJM MINERIA & CONSTRUCCION
SUBCONTRATISTA : JJM Mineria y Construccin SAC

2.02 2.03 2.04 2.05 2.06


PROGRESIVA DISTANCIA AREA CORTE A. CORTE CERRADO AREA RELLENO MS RD RF EPCMS EPCRD EPCRF ECCMS ECCRD
82+440 20.00 14.58 100% 972.60
82+460 20.00 1.43 100% 160.10
82+480 20.00 37.19 100% 386.20
82+500 20.00 83.31 100% 1,205.00

82+880 - 48.42 100% -


82+900 20.00 54.72 100% 547.20
82+910 10.00 58.37 100% 565.45
82+920 10.00 13.42 9.78 100% 358.95
82+940 20.00 40.16 6.79 100% 535.80
82+960 20.00 47.73 0.83 100% 878.90
82+980 20.00 52.38 100% 1,001.10

83+100 13.46 21.02 21.79 100% -


83+120 20.00 20.81 22.10 19.51 100% 342.70 431.20
83+140 20.00 37.03 22.48 15.54 100% 578.40 445.80
83+160 20.00 61.28 22.48 15.84 100% 983.10 449.60
83+180 20.00 43.98 12.12 6.72 100% 1,052.60 346.00
83+190 10.00 - 100% 219.90 60.60

83+270 - 100% -
83+280 10.00 38.70 30% 70% 58.05 135.45 -
83+290 10.00 - 100% 193.50 -
OBRA : CONSTRUCCION DEL CANAL PRINCIPAL DE CONDUCCION, TRAMO NEPEA CASMA
CONCLUSION KM 71+810 AL KM 87+920
CONTRATISTA : CONSORCIO VETA COLORADA
SUPERVISION : SISA CONSULTORES SA
JJM MINERIA & CONSTRUCCION
SUBCONTRATISTA : JJM Mineria y Construccin SAC

2.02 2.03 2.04 2.05 2.06


PROGRESIVA DISTANCIA AREA CORTE A. CORTE CERRADO AREA RELLENO MS RD RF EPCMS EPCRD EPCRF ECCMS ECCRD

83+460 9.40 3.72 100%


83+480 20.00 13.65 21.51 20.60 100% 230.50 252.30
83+500 20.00 2.87 19.59 20.94 100% 165.20 411.00
83+520 20.00 5.35 100% 82.20 195.90
83+540 20.00 8.00 100% 133.50 -
83+560 20.00 13.62 21.12 21.83 100% 216.20 211.20
83+580 20.00 5.87 18.39 27.29 100% 194.90 395.10
83+600 20.00 7.64 20.22 21.71 100% 135.10 386.10
83+620 20.00 20.71 22.48 16.46 100% 283.50 427.00
83+640 20.00 1.81 14.90 29.33 100% 225.20 373.80
9,112.50 7,853.35 9,265.45 4,385.60 -

2.02 2.03 2.04 2.05 2.06


METRADO ACUMULADO ACTUAL 9,112.50 7,853.35 9,265.45 4,385.60 -
METRADO ACUMULADO ANTERIOR - - - - -
PRESENTE METRADO A VALORIZAR 9,112.50 7,853.35 9,265.45 4,385.60 -
ERIA & CONSTRUCCION S.A.C.

2.07 2.14 2.15


ECCRF RCMPC RCMA

239.40
203.60
203.60
203.60
172.10
98.80
130.30
203.60
203.60

-
355.80
344.70
378.60
382.20
383.90
371.60
351.10
ERIA & CONSTRUCCION S.A.C.

2.07 2.14 2.15


ECCRF RCMPC RCMA

-
484.20
-
48.90
165.70
76.20
8.30
ERIA & CONSTRUCCION S.A.C.

2.07 2.14 2.15


ECCRF RCMPC RCMA

206.00
415.40
209.40
-
218.30
491.20
490.00
381.70
457.90
1,658.60 6,221.10 -

2.07 2.14 2.15


1,658.60 6,221.10 -
- - -
1,658.60 6,221.10 -
OBRA : CONSTRUCCION DEL CANAL PRINCIPAL DE CONDUCCION, TRAMO NEPEA CASMA

CONCLUSION KM 71+810 AL KM 87+920

CONTRATISTA : CONSORCIO VETA COLORADA

SUPERVISION : SISA CONSULTORES SA JJM MINERIA & CONSTRUCCION S.A.C.


SUBCONTRATISTA : JJM Mineria y Construccin SAC

Partida 01.01 Movilizacin y Desmovilizacion de Equipos (Glb)

Item Movilizacin Desmovilizacion Unidad Avance Metrado


1 50% 0% Glb 50% 0.5

METRADO ACUMULADO ACTUAL 0.50


METRADO ACUMULADO ANTERIOR -
PRESENTE METRADO A VALORIZAR 0.50