No of orders 13
No of replenishment cycles out of stock 1.022444846
Mean Weekly Demand, D 2,500
Standard Deviation of Weekly Demand 500
Order Quantity, Q 10,000
Replenishment Lead Time, L 2
ROP 6,000
Lead time Demand, DL 5000
SD of Lead Time Demand 707.1067812
Safety Stock 1000
Expected Shortage Quantity, ESQ 25.13
Fill Rate 99.75%
Mean Weekly Demand, D 2,500
Standard Deviation of Weekly Demand 500
Order Quantity, Q 10,000
Replenishment Lead Time, L 2
Lead time Demand, DL 5000
SD of Lead Time Demand 707.1067812
Cycle Service Level 90.00%
200.00 194.79
161.59
150.00
129.14 126.23
111.56
100.00 97.50 96.76
81.80
66.70
50.00
0.00
0% 5% 10% 15% 20%
Mean Weekly Demand, D 250
Standard Deviation of Weekly Demand 150
Order Quantity, Q 1,000
Replenishment Lead Time, L 2
Reorder Level, R 600
Lead time Demand, DL 500
Safety Stock, ss 100
SD of Lead Time Demand 212.132
Cycle Service Level 68.13%
Price 30
Holding cost 25%
Aggregation
Aggregated Weekly Demand 720000
SD of aggregated weekly demand 3000
Replenishment Lead Time, L 4
Lead time Demand, DL 2880000
SD of Lead Time Demand 6000
Cycle Service Level 95.00%
Price 100
Holding cost 25%
Aggregation
Aggregated Weekly Demand 45000
SD of aggregated weekly demand 1500
Replenishment Lead Time, L 4
Lead time Demand, DL 180000
SD of Lead Time Demand 3000
Cycle Service Level 95.00%