VAL

OBRA : MANTENIMIENTO PERIODICO DE LA CARRETERA AIJA - HUAMBA BAJO


RESIDENTE DE OBRA: ING. JERZY ROMULO LEON ANTUNEZ
SUPERVISOR DE OBRA: ING. ALEX HERRERA VILOCHE

METRADO PRESUPUESTO

N DESCRIPCION DE PARTIDAS PRECIO


UND. CANTIDAD
UNITARIO
1.00 OBRAS PROVISIONALES
1.01 CAMPAMENTO PROVISIONAL DE OBRA GBL 1.00 3,443.39
1.02 MOVILIZACION DE MAQUINARIA -HERRAMIENTAS PARA OBRA GBL 1.00 16,096.17
1.03 MOVILIZACION DE PERSONAL EN OBRA MES 3.00 17,708.72
1.04 CARTEL DE IDENTIFICACION DE OBRA UND. 1.00 899.52
1.05 LIMPIEZA DE TERRENO MANUAL DE CAMPAMENTO M2 80.00 25.85
1.06 ELIMINACION DE MALEZA M2 123.50 21.06
2.00 EXPLANACIONES
2.01 RELLENO Y COMPACTADO MANUAL CON MATERIAL DE PRESTAMO M3 181.69 97.99
2.02 ELIMINACION DE MATERIAL EXCEDENTE M3 93.94 172.77
3.00 CALZADAS
3.01 LIMPIEZA GENERAL KM. 53.70 120.23
3.02 ROCE Y DESBROCE M2 12,775.00 15.85
3.03 LIMPIEZA DE DERRUMBES Y HUAYCOS MENORES REND. = 15M3/DIA M3 12,487.50 104.85
4.00 OBRAS DE ARTE
4.01 LIMPIEZA DE CUNETAS M 12,777.63 44.54
COSTO DIRECTO 2,199,638.08
GASTOS GENERALES (8.66%) 190,488.66
TOTAL PRESUPUESTO 2,390,126.74
VALORIZACION DE OBRA MENSUAL
FECHA DE INICIO: 10/10/2014
PLAZO DE EJECUCION: 120 DIAS
PROVINCIA: HUARMEY
AVANCE AL 31 DE OCTUBRE DEL 2010
PRESUPUESTO
AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO
COSTO METRADO COSTO METRADO COSTO METRADO EJEC. COSTO %
PARCIAL
TOTAL EJEC. PARCIAL EJEC. PARCIAL ACUM. ACUM.
78,234.15
3,443.39 0.00 0.00 0.50 1721.70 0.50 1,721.70 50.00
16,096.17 0.00 0.00 0.00 0.00 0.00 0.00 0.00
53,126.16 0.00 0.00 0.00 0.00 0.00 0.00 0.00
899.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2,068.00
2,600.91
34,033.82
17,803.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00
16,230.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00
1,518,254.48
6,456.35 0.00 0.00 0.00 0.00 0.00 0.00 0.00
202,483.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00
1,309,314.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00
569,115.64
569,115.64 0.00 0.00 0.00 0.00 0.00 0.00 0.00
SALDO

METRADO VALORIZADO %

0.50 1,721.70 50.00


1.00 16,096.17 100.00
3.00 53,126.16 100.00
1.00 899.52 100.00

181.69 17,803.80 100.00


93.94 16,230.01 100.00

53.70 6,456.35 100.00


12,775.00 202,483.75 100.00
12,487.50 1,309,314.38 100.00

12,777.63 569,115.64 100.00


OBRA : MANTENIMIENTO PERIODICO DE LA CARRETERA AIJA - HUAMBA BAJO
RESIDENTE DE OBRA: ING. JERZY ROMULO LEON ANTUNEZ
SUPERVISOR DE OBRA: ING. ALEX HERRERA VILOCHE

N DESCRIPCION DE PARTIDAS
METRADO
1 OBRAS PROVISIONALES
1.01 CAMPAMENTO PROVISIONAL DE OBRA GBL 1
1.02 MOVILIZACION DE MAQUINARIA -HERRAMIENTAS PARA OBRA GBL 1
1.03 MOVILIZACION DE PERSONAL EN OBRA MES 3
1.04 CARTEL DE IDENTIFICACION DE OBRA UND. 1
1.05 LIMPIEZA DE TERRENO MANUAL DE CAMPAMENTO M2 80
1.06 ELIMINACION DE MALEZA M2 123.5
2 EXPLANACIONES
2.01 RELLENO Y COMPACTADO MANUAL CON MATERIAL DE PRESTAMO M3 181.69
2.02 ELIMINACION DE MATERIAL EXCEDENTE M3 93.94
3 CALZADAS
3.01 LIMPIEZA GENERAL KM. 53.7
3.02 ROCE Y DESBROCE M2 12775
3.03 LIMPIEZA DE DERRUMBES Y HUAYCOS MENORES REND. = 15M3/DIA M3 12487.5
4 OBRAS DE ARTE
4.01 LIMPIEZA DE CUNETAS M 12777.63
ANTERIOR ACTUAL ACUMULADO
AVANCE (%) SALDO (%)
EJECUTADO EJECUTADO EJECUTADO

0.00 0.50 0.50 50.00 50.00


0.00 0.00 0.00 0.00 100.00
0.00 0.00 0.00 0.00 100.00
0.00 0.00 0.00 0.00 100.00
0.00 0.00 0.00 0.00 100.00
0.00 0.00 0.00 0.00 100.00

0.00 0.00 0.00 0.00 100.00


0.00 0.00 0.00 0.00 100.00

0.00 0.00 0.00 0.00 100.00


0.00 0.00 0.00 0.00 100.00
0.00 0.00 0.00 0.00 100.00

0.00 0.00 0.00 0.00 100.00


CRONOGRAMA DE AVANCE DE OBRA
MA DE AVANCE DE OBRA