Professional Documents
Culture Documents
This report presents our investigations, the results of our findings, and our foundation
design recommendations for the trail system and associated retaining walls. Although we
presented bridge foundation design recommendations in this report, we understand the
bridge alternative has been eliminated from the project.
It is important that we provide consultation and review during the design phase, and field
observation and testing services during construction, to ensure complete implementation of
the geotechnical design recommendations.
Respectfully submitted,
TETRA TECH
APPENDIX
Important Information About Your Geotechnical Engineering Report (Published by ASFE)
Explanation of Abbreviations and Descriptive Terms
Classification of Soils for Engineering Purposes
As part of the proposed trail system, a bicycle-pedestrian bridge structure was planned to be
constructed over the Bitterroot River adjacent to the existing Highway 93 bridge near Missoula.
The new structure was proposed to have three spans, with each bent consisting of a single column
supported on a drilled shaft foundation. The bridge option has currently been eliminated from the
project, and the proposed plan is to widen the existing Highway 93 bridge sidewalk on the north
spans to accommodate bicycles and pedestrians. We have included the bridge design information
with this report in the event the bridge option is considered in the future.
The purpose of our geotechnical investigations were to, 1) obtain data on subsurface conditions
at the retaining wall locations along the proposed trail alignment, 2) evaluate the RAP source for
potential use in the trail pavement section, either in the base or surfacing course, and 3) design
drilled shaft foundations for the pedestrian bridge.
FIELD EXPLORATION
Tetra Tech conducted an initial field exploration program in January 2014 consisting of five
exploration borings to obtain information on subgrade soil conditions along the proposed trail
site between Lolo and Missoula (see Sheet U.1, Appendix A, prepared by DJ&A). The five
borings were drilled at locations accessible to the drill rig where traffic control was not
necessary. Tetra Tech also visited the RAP storage site in January 2014 to obtain samples for
laboratory testing.
A subsequent field investigation was performed in May 2014, consisting of drilling 19 additional
borings within the footprints of the proposed retaining wall locations. The borings were drilled
The horizontal and vertical coordinates of all borings were surveyed by DJ&A. The elevation,
northing, easting and station of each boring are included on the logs of the borings in Appendix
B. Photos of the initial drilling locations, the RAP stockpile, and the proposed retaining wall
locations are included in Appendix D.
Samples of the subsurface materials were taken with a 2-inch outside diameter (O.D.) split-
spoon sampler driven into the various strata using a 140-pound hammer falling 30 inches. The
number of blows required to advance the sampler each successive 6-inch increment was
recorded; the total number of blows required to advance the sampler the second and third 6-
inch increments is the penetration resistance (N value). The 2-inch O.D. sampler is the standard
penetration test described by ASTM Method D1586. Penetration resistance values indicate the
relative density or consistency of the soils. Disturbed bulk samples were obtained from the
auger cuttings in the upper 10 feet of the borings. Depths at which the samples were taken and
the penetration resistance values are shown on the logs of exploration borings, Figures 1
through 24.
Samples obtained during the field investigations were tested in Tetra Techs laboratory to
determine the physical and engineering characteristics of the on-site soils. This report
summarizes the field data and presents conclusions and recommendations for design and
construction of the trail and bridge foundations based on the proposed construction and
subsurface conditions encountered. The report also includes design parameters and
geotechnical engineering considerations related to retaining wall construction.
LABORATORY TESTING
Samples obtained during the field exploration were taken to Tetra Tech's laboratory, where they
were observed and visually classified in accordance with ASTM Method D2487, which is based
on the Unified Soil Classification System. Representative samples were selected for testing to
determine the physical properties of the soils in general accordance with ASTM or other
approved procedures.
Grain-Size Distribution Size and distribution of soil particles; that is, clay, silt, sand
and gravel.
Moisture-Density Relationship The optimum moisture content for compacting soil and the
maximum dry unit weight (density) for a given compactive
effort.
Laboratory test results are presented graphically on Figures 25 through 55 in the Appendix.
These data, along with the field information, were used to prepare the exploration boring logs,
Figures 1 through 24.
SUBSURFACE CONDITIONS
Access limitations required that all geotechnical borings within the retaining wall footprints be
drilled from the existing highway such that subsurface profiles penetrate through the existing
pavement section. The subsurface profile encountered in the 19 borings drilled within the
station limits of the retaining walls generally consists of an asphalt, base, and subbase section
overlying approximately 5 to 21 feet of predominately sand and gravel road embankment fill
overlying native sand and gravel to the maximum depth explored of 35.5 feet.
The boring logs should be referenced for complete descriptions of the soil types and their
estimated depths. A characterization of the subsurface profile normally includes grouping soils
with similar physical and engineering properties into a number of distinct layers. The
representative subsurface layers at the site are presented below, starting at the ground surface.
The existing asphalt layer ranged in thickness from 0.5 to 1 foot. The granular layer
immediately beneath the pavement surfacing consisted of approximately 1.25 to 5.5 feet of
poorly graded gravel and sand. It was difficult in the field to determine if a separate base and
subbase layer existed, since in most cases the processed granular material beneath the
pavement was relatively homogenous for the depth listed on the logs. The base/subbase layer
was generally; medium to very dense, subrounded to angular, slightly moist based on moisture
contents averaging approximately 5 percent, and brown.
Twelve moisture-density tests were performed following ASTM D698 or ASTM D1557
procedures (Figures 44 through 55, Appendix B). The optimum moisture contents range from 4
to 11 percent and rock corrected maximum dry densities on the order of 123.0 to 148.3 pcf
depending on the methodology used. The May 2014 samples were tested by ASTM D1557
procedures per MDT guidelines requiring D1557 testing for all AASHTO A-1 samples.
PH, resistivity, and sulfate testing was performed on the five samples obtained from the fill layer
in the initial five borings, to be utilized for design of the retaining wall elements, as required.
Since these five samples were taken at locations spread across the project length, further
testing was not performed for the May 2014 drilling program. The following table lists the results
of the pH, resistivity, and sulfate testing.
GROUNDWATER
Subsurface water was encountered in Boring BH-5 at a depth of approximately 12.5 feet below
the ground surface at the time of drilling (January, 2014). Boring BH-5 was drilled during the
initial drilling program, and does not fall within the limits of any of the current retaining wall
station limits. The ground elevation of BH-5 is approximately 30 to 60 feet below the other four
borings drilled, and is closer to the elevation of the Bitterroot River. Groundwater depths will
generally vary depending on the time of year. Numerous factors contribute to groundwater
fluctuations, and evaluation of such factors is beyond the scope of this report.
RETAINING WALLS
Retaining walls are being proposed along approximately 6,800 lineal feet of the trail alignment,
and are predominately located in project Section 3 shown in Appendix A. The majority of the
retaining walls will be constructed on the existing slope east of the Highway 93 guardrail, with
proposed wall heights predominately on the order of 4 to 8 feet. Slopes on the order of
1.5(Horizontal):1(Vertical) are proposed at some locations extending from the back of guardrail
to the top of wall. Several of the wall sections are in fill sections, and are shorter in length and
height.
The following Sheet C.8 from the 95% plan sheets lists the summary of wall station limits and
allowable wall types.
Constructability of the walls, including temporary slope stability, are a significant concerns on
this project. Tetra Tech performed a global slope stability analyses of the proposed walls
sections and slopes, and analyzed several cases, including; 1) temporary construction slopes,
and 2) final constructed slopes. The General Retaining Wall Special Provision includes
estimated station limits where soil nail walls will likely be required to maintain slope stability
during construction.
Following is a discussion the slope stability performed for the walls, site grading, and other
construction and design considerations.
Highway loading is typically modelled as a uniform load equivalent to two feet of soil. For this
project, this is equivalent to 240 pounds per square foot (psf) uniformly applied over the highway
area. The trail will not be subject to highway loading but will be subject to significant loading
during construction. Therefore, the 240 psf uniform load was also applied to the trail area in the
stability models.
The stability modelling was initially calibrated by back-analysis of the existing slopes. For the
purposes of determining shear strength for the existing subsurface materials, a simplified model
of the existing ground surface was analyzed. Station 3097+00 represents the tallest and
steepest portion of the existing highway embankment slopes that will be modified for the trail
construction (approximate 50-foot height at 1.5:1 slopes). The subsurface material was
assumed to be gravel fill with zero cohesion. For a zero cohesion material, the angle of internal
friction must be greater than the existing slope angle (34 degrees) for the slope stability factor of
safety to be greater than 1.0.
As discussed under Subsurface Conditions, penetration resistance values in the fill within the
proposed retaining wall footprints generally ranged from 30 to greater than 50 blows per foot,
with some isolated SPT values in the teens and 20s recorded, indicative of a generally dense to
very dense fill stratum. Lower SPT values between 5 and 10 were recorded in borings B-3 and
A sensitivity analysis was conducted for the proposed worst-case wall/slope configuration at
Station 3097+00 with friction angles varying from 36 to 44 degrees. The results were as
follows;
The sensitivity analyses indicate the existing slopes have a minimum Static Factor of Safety on
the order of 1.2, assuming a minimum friction angle of 36 degrees. A friction angle of 40
degrees is required to achieve a Factor of Safety of 1.3, which is the minimum Factor of Safety
required by MDT for new embankment slopes under static conditions. These analyses
assumed the potential failure surfaces extended a minimum of 10 feet below the ground
surface, limiting the study to those failure modes which would potentially result in significant
damage to the roadway or trail. Figure G-1 includes the slope analyses at Station 3097+00
assuming a friction angle of 40 degrees.
The MDT geotechnical manual indicates a slope stability factor of safety of 1.1 is required under
seismic conditions for highway embankments. The seismic coefficient is typically taken to be
50% of the peak ground acceleration (PGA). For this slope stability analyses, a PGA of 0.142g
was utilized (using 2009 AASHTO Guide Specifications for LRFD Seismic Bridge Design for the
Missoula area). Therefore, for pseudo-static analysis of seismic conditions, a horizontal
acceleration of 0.071g was utilized. For the pseudo-static analyses at Station 3097+00, a
Factor of Safety of 1.159 was achieved assuming a friction angle of 40 degrees (Figure G-2).
Subsequent to the calibration slope analyses, additional slope stability analyses were conducted
at various stations representing potential worst-case scenarios for slope and wall sections to
determine the stability impacts of the new trail. For these analyses, the existing gravel and new
In general, these results indicate an overall slight increase in slope stability with the construction
of the trail. Qualitatively, this is expected since, 1) where new fill is constructed at the toe of
slope, there is increased resistance, and, 2) where the trail is cut into the slopes, the driving
load is reduced.
The global slope analyses conducted indicate that, where the existing slopes are on the order of
1.5:1 or flatter, they have an existing Factor of Safety on the order of 1.2 or greater, assuming a
minimum friction angel of 36. The analyses also indicate that, with stable walls constructed, the
slope Factors of Safety increase slightly.
Appendix F includes three Special Provisions detailing design and construction requirements for
the retaining walls. Based on Tetra Techs slope analyses, the General Retaining Wall Special
Provision, as well as Sheet C.8 included above, outline station limits where soil nail walls will be
required to ensure slope stability during construction. The wall designer will need perform
sufficient design, as outlined in the special provisions, to ensure short-term and long term
stability of the slopes, as well as internal wall stability. A friction angle of 36 degrees is specified
in the special provisions for the fill and backfill material to be used by contractors in their slope
and wall designs.
The minimum required Factor of Safety for global stability of the wall systems for this project will
be 1.5, per the current MDT Geotechnical Manual assuming allowable stress design. The
contractor must design soil nail lengths and spacing, and gravity or MSE wall systems, to
achieve the minimum Factor of Safety of 1.5, assuming an existing friction angle of 36 degrees
for the fill layer. A minimum short-term factor of safety of 1.2 (during construction) must be
achieved by the contractor for slopes excavated during construction, including for soil nail walls.
Note that the minimum required Factor of Safety of 1.5 applies only to the slopes and wall
systems above the proposed trail system. Based on our analyses, the slopes below the
proposed wall system currently have a minimum Factor of Safety of 1.2, and are satisfactory as-
is without further modifications per discussions with the MDT Geotechnical Section.
Data from the borings indicates that groundwater should not be encountered for wall
excavations at Elevation 3,140 or higher; however, groundwater could be encountered in
excavations near BH-5, or at the wall sections where the existing ground elevation is at or below
3,140.00 feet, depending on the time of year of construction. The design and construction
criteria presented below should be observed for site preparation purposes; construction details
should be considered when preparing project documents.
The design and construction criteria presented below should be observed for retaining walls, and
are included in the project Special Provisions.
1. The base of walls should bear on existing sand and gravel fill, native sand and gravel, or
engineered gravel fill, and designed per LRFD specifications.
2. Retaining walls should be designed for internal stability per current LRFD specifications.
3. If silt or clay fill material is encountered at the footing elevation of walls, a minimum of 2
feet of should be subexcavated and replaced with a minimum of 2 feet of engineered
gravel fill.
4. Following excavation for the wall footings and compaction, we recommend proofrolling the
footing subgrade with a heavy wheeled truck to identify soft areas prior to constructing the
wall section. Where soft areas are encountered at subgrade elevation, a minimum of 2
feet should be subexcavated and replaced with a minimum of 2 feet of engineered gravel
fill.
5. Imported granular material used as engineered gravel fill should meet the following
grading limits and be compacted in accordance with Item 6 below.
Sieve or Percent
Screen Size Passing
3-inch 100
No. 40 25 50
No. 200 0-12
6. All fill, backfil and subgrade soils should be approved by the geotechnical engineer,
moisture-conditioned to within 2 percent of optimum moisture content, and placed in uniform
lifts not exceeding 8 inches in thickness. It should then be compacted to the following
minimum dry densities as determined by ASTM D698 or ASTM D1557. Vibratory
compaction equipment is not allowed unless approved by the project manager.
7.
ASTM D698 ASTM D1557
Wall Backfill 95% 90%
Subgrade Preparation 95% 90%
Embankment Fill 95% 90%
9. The contractor is responsible for providing safe working conditions in connection with
excavations for walls adjacent to Highway 93. Temporary construction excavations, which
workers will enter, will be governed by OSHA guideline 1926.6542 Appendix B to subpart P.
For planning purposes, subsoils encountered in the exploration borings classify as Type C.
The wall excavations must be checked for global stability to ensure they have an adequate
Factor of Safety during construction. The global stability analyses must include heavy truck
traffic loads.
10. Temporary and permanent wall sections must be designed for heavy traffic surcharge loads
on Highway 93 adjacent to the guardrail, as well as the 1.5:1 slopes above the wall.
CONSTRUCTION CONSIDERATIONS
Fill slopes up to 15 to 20 feet high are proposed at some locations, with the toe footprint of the
fill extending on the order of 5 to 20 feet horizontally adjacent to the existing toe of slope.
The following items should be considered during design of slopes, and during preparation of the
project plans and documents;
1. The MDT Standard Specifications for Road and Bridge Construction, or the Montana
Public Works Specifications, should be referenced on the plan sheets for slope
construction, including; subgrade preparation prior to beginning fill placement, benching
of existing slopes prior to and during fill placement, compaction of fill, and seeding as
required.
2. Benching the existing slopes is critical to ensure the stability of the fill slope following
construction. We recommend that a note be placed on all plan sheets requiring the
slopes to be benched a minimum of 4-feet wide, with the 4-foot bench required with each
lift of fill placed.
The bridge alternative for this project has currently been eliminated. Following is a
discussion of the bridge foundation analysis and design that was completed prior
to elimination of the bridge alternative from the project.
As part of the proposed Lolo to Missoula trail system, a bicycle-pedestrian bridge structure is
planned to be constructed over the Bitterroot River adjacent to the existing bridge. The
Four geotechnical borings were drilled for the original bridge structure. The locations have been
noted on the attached As-built Drawing No. 6527A (in yellow and green highlight) in Appendix C,
and the logs of the borings are shown on Drawing No. 6528A, Appendix C. The depths of the four
borings were on the order of 70 to 90 feet below the native ground. Two of the borings were drilled
close to the existing median centerline, and two were drilled 133 to 172 feet left of median
centerline. All four borings encompass the footprint of the proposed structure.
The following sections discuss the bridge foundation design and construction considerations.
The specific design manuals utilized for the bridge and foundation design are, 1) AASHTO
LRFD Bridge Design Specifications (2012), 2) 2011 AASHTO Guide Specifications for LRFD
Seismic Bridge Design, 2nd Edition, 3) FHWA Publication No. IF-99-025, Drilled Shafts
Construction Procedures and Design Methods, August 1999.
Ultimate axial drilled shaft capacities have been calculated based on methodologies presented
in FHWA Publication, Drilled Shafts Construction Procedures and Design Methods, August
1999, and computer program SHAFT 6.0, A Program for the Study of Drilled Shafts Under Axial
Loads (2012 with recent 2014 updates).
The following table lists the soil parameters utilized in the axial analyses, and to be used for the
lateral shaft design. We have assumed that HDR will perform the lateral shaft analyses once
the final shaft configuration and diameters have been finalized.
Per LRFD Part II, Table 10.5.5.2.4-1 Resistance Factors for Geotechnical Resistance of
Drilled Shafts, the following factors were utilized to develop the nominal axial capacity charts
presented in Appendix C, Figures 1 and 2, for the abutment and pier drilled shafts. The uplift
and horizontal resistance factors should be used by HDR to determine the uplift capacity of
each shaft. Figures 3 and 4 in Appendix C present the skin friction for the intermediate pier
and abutment drilled shafts to estimate uplift capacity.
The soil parameters utilized for the drilled shaft design are considered conservative. with the
average blow count of 15 extending down to Elevation 3,070 feet for both pier locations, and
very soft or loose soils in the top 25 feet at the abutment locations. Assuming the bottom of
Due to the presence of groundwater in the borings, placement of concrete by tremie or pumping
methods is required. The design and construction criteria presented below should be observed
for a drilled shaft foundation system. A drilled shaft special provision will be included in the project
documents.
1. Structural loads should be supported on drilled shafts penetrating through the native sand
and gravel. The capacity charts included in Appendix C should be utilized by HDR to obtain
shaft depths once loads are finalized.
2. Uplift due to structural loadings on the shafts can be resisted by using the LRFD Factored
skin friction presented in Figures 3 and 4 in Appendix C, plus an allowance for shaft weight.
3. Removal of temporary casing could be difficult. Drilling contractors should anticipate the
need for special drilling and support equipment, including but not limited to; large 4-claw
vibratory hammer, oscillator, or rotary casing advancer.
4. Concrete placed below the water table will require placement by tremie or pumping
methods. All pumping lines should have a minimum diameter of 4 inches and be
constructed with watertight joints. A plug or similar device should be used to separate the
concrete from the fluid in the hole until concreting begins. Concrete placement must not
begin until the discharge orifice is at the shaft base.
5. Before the temporary casing is withdrawn, the level of fresh concrete in the casing must be
a minimum of 5 feet above the hydrostatic water level or the level of the drilling fluid,
whichever is greater. As the casing is withdrawn, care must be exercised to maintain an
adequate level of concrete within the casing so that the fluid trapped behind the casing is
displaced upward and discharged at the ground surface without contaminating or displacing
the shaft concrete.
6. Concrete used in the drilled shafts should have a slump on the order of 6 to 8 inches.
10. The contractor performing the drilled shaft construction should have installed drilled shafts of
both diameter and length in similar subsurface conditions for a minimum of five years prior to
bid date for this project.
11. To ensure proper drilled shaft construction methods, we recommend that a Tetra Tech
geotechnical engineer be present to observe the materials penetrated and document the
drilled shaft installation.
The proposed trail typical sections are included in Appendix E, and include; top paved width on
the order of 10 feet, with mostly unpaved shoulders 1-foot wide on both sides of the trail.
Tetra Tech obtained representative samples from the MDT RAP pile utilizing a large front end
loader to excavate deep into the pile at several locations around the perimeter. The samples
were then tested in Tetra Techs laboratory to determine the suitability of using the material in
either the base or surface course or both. The results of two gradation analyses performed are
Thickness Design:
The majority of traffic the trail section will experience in the future will be bicycles and
occasional maintenance vehicles/trucks. Traffic during construction will include excavators and
haul trucks, as well as trucks to deliver retaining wall materials. The majority of degradation the
pavement section will experience during its life cycle following construction will be due to
environmental effects, including; freeze thaw, oxidation, and moisture infiltration.
Based on conversations with DJ&A, we understand the preferred asphalt pavement surfacing
thickness will be 2 inches. Considering a 2 inch asphalt pavement section, we recommend the
following base layer design.
For the base layer, we recommend constructing a 4-inch thick layer of stabilized RAP. We
recommend utilizing Base One as a stabilizing agent. Base One-treated RAP sections have
proven to be very strong, and allow designs utilizing a thinner section than with conventional
materials.
There are many benefits to treating the 4-inch RAP layer, including;
1) Very firm base on which to support the thin 2-inch asphalt layer,
2) Added support for construction traffic,
3) Added resistance to freeze/thaw-type of cracking. Research has shown that a Base
One-treated base layer has resulted in less thermal/environmental cracking in the
overlying pavements,
4) Bridge over areas of subgrade soil that may be weaker or looser in support strength or
density.
5) Reduced base layer thickness.
6) A 4-inch treated base layer will utilize approximately 6,300 cubic yards of the RAP
source, assuming a 13-foot wide layer.
The Base One product cost delivered to Missoula for 4-inch depth base course will be on the
order of $25,000.00. Given the uniform and consistent RAP grading, we suggest that the base
layer can be rolled smooth to provide a level, firm base on which to pave without the need for a
gravelling leveling course. Research shows that placing a gravel layer on top of 100% RAP will
not provide sufficient bond, and will not perform well.
An asphalt mix design incorporating 20 to 25 percent RAP is recommended for the project. The
performance of lower-percentage RAP mixes has been proven on projects in and around
Missoula, on the Interstate Highways near Missoula, in parking areas, and elsewhere
Using RAP will save project costs by reducing the amount of virgin aggregate and oil required in
the new mix. A MPWS Grade B mix with PG 58-28 oil is recommended, which has proven to
perform well in the Missoula area. Both Knife River and Jenson have current mix designs for a
80/20 RAP mix, both performed by Tetra Tech. A 20% RAP mix will require about 584 cubic
yards of RAP for the trail sections.
This recommended base and asphalt design will require an estiimated 6,900 cubic yards of RAP
material.
The following details should be followed for construction of the stabilized base layer;
Based on Tetra Techs past experience and conversations with reclamation contractors, typical
reclamation equipment can likely cover on the order of two to three miles of a 10-foot wide trail
per day, or 7.4 miles in approximately 2 to 3 days. The estimated cost for reclamation and
mixing would be on the order of $0.50 per square yard, or about $25,000 to complete all 7.4
miles of mixing.
CONTINUING SERVICES
Two additional elements of geotechnical engineering service are important to the successful
completion of this project.
1. Consultation with Tetra Tech during the design phase. This is essential to ensure
that the intent of our recommendations is incorporated in design decisions related to the
project and that changes in the design concept consider geotechnical aspects.
This report has been prepared exclusively for our client for design purposes. We are not
responsible for technical interpretations by others of our exploratory information that has not
been described or documented in this report. As the project evolves, we should provide
continued consultation and field services during construction to review and monitor the
implementation of our recommendations, and verify that our recommendations have been
appropriately interpreted. Significant design changes may require additional analysis or
modifications of the recommendations presented herein. We recommend on-site observation of
excavations and foundation bearing strata and testing of fill by a representative of the
geotechnical engineer.
Prepared by: Marco Fellin, P.E. Reviewed by: Richard Dombrouski, P.E
More construction problems are caused by site subsurface Data derived through sampling and subsequent laboratory
conditions than any other factor. As troublesome as subsurface testing are extrapolated by Geotechnical engineers who then
problems can be, their frequency and extent have been render an opinion about overall subsurface conditions, their
lessened considerably in recent years, due in large measure to likely reaction to proposed conditions, their likely reaction to
programs and publications of ASFE/The Association of proposed construction activity, and appropriate foundation
Engineering Firms Practicing in the Geosciences. design. Even under optimal circumstances actual conditions
may differ from those inferred to exist, because no
The following suggestions and observations are offered to help Geotechnical engineer, no matter how qualified, and not
you reduce the Geotechnical-related delays, cost-overruns and subsurface exploration program, no matter how
other costly headaches that can occur during a construction comprehensive, can reveal what is hidden by earth, rock and
project. time. The actual interface between materials may be fare more
gradual or abrupt than a report indicates. Actual conditions in
A GEOTECHNICAL ENGINEERING areas not sampled may differ from predictions. Nothing can be
done to prevent the unanticipated, but steps can be taken to
REPORT IS BASED ON A UNIQUE SET OF help minimize their impact. For this reason, most experienced
PROJECT-SPECIFIC FACTORS owners retain their Geotechnical consultants through the
construction stage, to identify variances, conduct additional
A Geotechnical engineering report is based on a subsurface tests which may be needed, and to recommend solutions to
exploration plan designed to incorporate a unique set of problems encountered on site.
project-specific factors. These typically include: the general
nature of the structure involved, its size and configuration; the SUBSURFACE CONDITIONS
location of the structure on the site and its orientation; physical
concomitants such as access roads, parking lots, and CAN CHANGE
underground utilities, and the level of additional risk which the
client assumed by virtue of limitations imposed upon the Subsurface conditions may be modified by constantly-
exploratory program. To help avoid costly problems, consult changing natural forces. Because a Geotechnical engineering
the geotechnical engineer to determine how any factors which report is based on conditions which existed at the time of
change subsequent to the date of the report may affect its subsurface exploration, construction decisions should not be
recommendations. based on a Geotechnical engineering report whose adequacy
may have been affected by time. Speak with the Geotechnical
Unless your consulting Geotechnical engineer indicates consultant to learn if additional tests are advisable before
otherwise, your Geotechnical engineer report should not be construction starts.
used:
When the nature of the proposed structure is changed, Construction operations at or adjacent to the site and natural
for example, if an office building will be erected events such as flood, earthquakes or groundwater fluctuations
instead of a parking garage, or if a refrigerated may also affect subsurface conditions and, thus, the continuing
warehouse will be built instead of an unrefrigerated adequacy of a geotechnical report. The geotechnical engineer
one; should be kept apprised of any such events, and should be
when the size or configuration of the proposed consulted to determine if additional tests are necessary.
structure is altered;
when the location or orientation of the proposed GEOTECHNICAL SERVICES ARE
structure is modified: PREFORMED FOR SPECIFIC PURPOSES
when there is a change of ownership, or
for application to an adjacent site.
AND PERSONS
Geotechnical engineers reports are prepared to meet the
Geotechnical engineers cannot accept responsibility for
specific needs of specific individuals. A report prepared for a
problems which may develop if they are not consulted after
consulting civil engineer may not be adequate for a
factors considered in their reports development have changed.
construction contractor, or even some other consulting civil
engineer. Unless indicated otherwise, this report was prepared
MOST GEOTECHNICAL FINDINGS expressly for the client involved and expressly for purposes
ARE PROFESSIONAL ESTIMATES indicated by the client. Use by any other persons for any
purpose, or by the client for a different purpose, may result in
Site exploration identifies actual subsurface conditions only at problems. No individual other than the client should apply this
those points where samples are taken, when they are taken. report for its intended purpose without first conferring with the
geotechnical engineer. No person should apply this report for who do not provide such access may proceed under the
any purpose other than that originally contemplated without mistaken impression that simply disclaiming responsibility for
first conferring with the geotechnical engineer. the accuracy of subsurface information always insulates them
from attendant liability. Providing the best available
A GEOTECHNICAL ENGINEERING information to contractors helps prevent costly construction
problems and the adversarial attitudes which aggravate them to
REPORT IS SUBJECT TO disproportionate scale.
MISINTERPRETATION
READ RESPONSIBILITY
Costly problems can occur when other design professionals
develop their plants based on misinterpretations of a CLAUSES CLOSELY
geotechnical engineering report. To help avoid these
problems, the geotechnical engineer should be retained to work Because geotechnical engineering is based extensively on
with other appropriate design professionals to explain relevant judgment and opinion, it is far less exact than other design
geotechnical findings and to review the adequacy of their plans disciplines. This situation has resulted in wholly unwarranted
and specifications relative to geotechnical issues. claims being lodged against geotechnical consultants. To help
prevent this problem, geotechnical engineers have developed
model clauses for use in written transmittals. These are not
BORING LOGS SHOULD NOT BE exculpatory clauses designed to foist geotechnical engineers
SEPARATED FROM THE liabilities onto someone else. Rather, they are definitive
ENGINEERING REPORT clauses which identify where geotechnical engineers
responsibilities begin and end. Their use helps all parties
Final boring logs are developed by geotechnical engineers involved recognize their individual responsibilities and take
based upon their interpretation of field logs (assembled by site appropriate action. Some of these definitive clauses are likely
personnel) and laboratory evalution of field samples. Only to appear in your geotechnical engineering report, and you are
final boring logs customarily are included in geotechnical encouraged to read them closely. your geotechnical engineer
engineering reports. These logs should not under any will be pleased to give full and frank answers to your
circumstances be redrawn for inclusion in architectural or questions.
other design drawings, because drafters may commit errors or
omissions in the transfer process. Although photographic OTHER STEPS YOU CAN TAKE TO
reproduction eliminates this problem, it does nothing to REDUCE RISK
minimize the possibility of contractors misinterpreting the logs
during bid preparation. When this occurs, delays, disputes and
Your consulting geotechnical engineer will be pleased to
unanticipated costs are the all-too-frequent result.
discuss other techniques which can be employed to mitigate
risk. In addition, ASFE as developed a variety of materials
To minimize the likelihood of boring log misinterpretation,
which may be beneficial. Contact ASFE for a complimentary
give contractors ready access to the complete geotechnical
copy of its publications directory.
engineering report prepared or authorized for their use. Those
Published by
THE ASSOCIATION
OF ENGINEERING FIRMS
PRACTICING IN THE
GEOESCIENCES
SSS (SPT) - Standard penetration resistance test results recorded as the number of blows of a 140-pound hammer falling
30 inches required to drive a 2-inch O.D. split sample spoon the second and third 6-inch increments of an 18-
inch distance.
LSS - Modified penetration test results recorded as the number of blows of a 140-pound hammer falling 30 inches
required to drive a 2.5-inch O.D. split spoon the second and third 6-inch increments of an 18-inch distance.
SRS - Split barrel ring sampler 2-inches I.D. for taking undisturbed samples.
LRS - Split barrel ring sampler 2.5 inches I.D. for taking undisturbed samples.
STS - Shelby tube sampler for taking undisturbed samples (2 to 3-5/16 I.D.).
Sack (SK) - Sample of disturbed soil placed in canvas sack or plastic bag.
or Bag
RQD - Rock quality designation (RQD) for the bedrock samples are determined for each core run by summing the
length of all sound, hard pieces of core over four inches in length, and dividing this number by the total length
of the core run. This value, along with the core recovery percentage, is recorded on the drill logs.
GRAIN SIZES
U.S. Standard Series Sieve Clear Square Sieve Openings
200 40 10 4 3 12
Silts & Clays SAND GRAVEL
Distinguished
Cobbles Boulders
on Basis of Fine Medium Coarse Fine Coarse
Plasticity
GROUP
MAJOR DIVISIONS GROUP NAME
SYMBOL
Clean Gravels Cu 4 and 1 Cc 3E GW Well graded gravel F
Gravels Less than 5%
More than 50% fines Cu < 4 and/or 1 > Cc > 3E GP Poorly graded gravel F
coarse
fraction Gravels with Fines classify as ML or MH GM Silty gravel F G H
retained on Fines
Coarse-Grained Soils No. 4 sieve More than 12%
More than 50% Fines classify as CL or CH GC Clayey gravel F G H
fines
retained on No. 200
sieve Sands Clean Sands Cu 6 and 1 Cc 3E SW Well-graded sand I
50% or more of Less than 5%
coarse fines Cu < 6 and/or 1 > Cc > 3E SP Poorly graded sand I
faction
passes No. 4 Sands with Fines Fines classify as ML or MH SM Silty Sand G H I
sieve More than 12%
fines Fines classify as CL or CH SC Clayey sand G H I
Highly organic soils Primarily organic matter, dark in color, and organic odor PT Peat
E
A
Based on the material passing the 3-in. Cu = D60/D10 Cc=(D30)2 / (D10 x D90) J
If Atterberg limits plot in hatched area, soil
F
(75-mm) sieve. If soil contains 15% sand, add with is a CL-ML, silty clay.
B K
If field sample contained cobbles or sand to group name. . If soil contains 15 to 29% plus No. 200,
G
boulders, or both, add with cobbles or If fines classify as CL-ML, use dual add with sand or with gravel, whichever
boulders, or both to group name. symbol GC-GM, or SC-SM. is predominant.
C H L
Gravels with 5 to 12% require dual If fines are organic, add with organic If solid contains 30% plus No. 200,
symbols: fines to group name. predominantly sand, add sandy to group
GW-GM well-graded gravel with silt I
If soil contains 15% gravel, add with name.
M
GW-GC well-graded gravel with clay gravel to group name. If soil contains 30% plus No. 200,
GP-GM poorly graded gravel with silt If soil contains 15% gravel, add with predominantly gravel, add gravelly to
GP-GC poorly graded gravel with clay gravel to group name. group name.
N
D
Sands with 5 to 12% fines require dual Pl 4 and plots on or above A line.
O
symbols: Pl < 4 or plots below A: line.
P
SW-SM well-graded sand with silt Pl plots on or above A: line.
Q
SW-SC well-graded sand with clay Pl plots below A: line.
SP-SM poorly graded sand with silt
SP-SC poorly graded sand with clay
RESERVE STREET
MISSOULA
T
EE
R
ST
SOUTH AVE.
KS
O
N O
&UHH BR
OFK
*X
D
O L Y 93
H W
BLU 3D
E WWH
H
MTN.
RD. A
AN
O NT INK
M IL L
MILL
RA
ER C
+D\HV
REE
&UHHN 0R
K
RVH
& DQ
*XO
O\
%25(
Q *XOFK
'HDGPD
F:\6078.02 Missoula to Lolo Trail Design\dwg\6078_Sheets_A_Vicinity.dwg.dwg, BORE HOLE, 6/6/2014 3:49:47 PM, DanL
)R
UN
%25(
%25(
0LOOH
: RU G U 6HH6KHHWV88IRUJHRWHFKQLFDOERULQJORJV
HQ
3OX
&UHH
PP
N
HUV
&UHHN
6ORX
JK
&U
HH
N
LOLO
%25(+2/(0$3
8
APPENDIX B
Tetra Tech Figure No. 1
LOG OF BORING
Phone: 406-543-3045
Fax: 406-543-3088
Project Name: Lolo Bike Trail - Missoula County, Montana Project Number: 114-570718
Borehole
Borehole Location: Refer to Site Map Number: BH-1 Sheet 1 of 1
Hammer:
Stationing: Type: Driller: O'Keefe - Butte Logger: Kyle Zanto
Borehole
Drilling Equipment: Mobile B-61 Diameter (in): 6.00 Date Started: 1-09-14 Date Finished: 1-09-14
Elevation
and Datum: Ground: 3138.60 Notes: Northing: 959837.77
DRILL Easting: 816937.02
PLASTICITY INDEX
DESIGNATION (RQD)
LIQUID LIMIT
RECOVERY (%)
ROCK QUALITY
STANDARD
GRAPHIC LOG
OPERATION
RATE (mph)
DEPTH (ft)
DEPTH (ft)
MATERIAL DESCRIPTION REMARKS
TEST
SAMPLE
CORE
SPT LL PI
30 9-14-14 7 FILL, Lean CLAY (CL), tan, moist, low 0.50
plasticity.
FILL, Clayey GRAVEL with sand (GC), fine
40 5-12-14 4 25 10 16 to coarse grained gravel, fine to medium
grained sand, medium dense to dense,
gray, moist, angular gravel, low plasticity.
5
50 18-17-17 5
9.00
10
FILL, lean CLAY with sand (CL), fine to
medium grained sand, gray, moist, low
plasticity.
95 10-19-15 7
13.00
Poorly graded GRAVEL with silt and sand
(GP-GM) to (SP-SM), fine to medium
15 grained gravel, fine to coarse grained sand,
medium dense to dense, tan/brown, moist,
angular gravel, non-plastic.
70 12-9-18 5
20
570718 LOGS.GPJ ` 6-12-14 ` MAT ` MONTANA DOT ENGLISH OUTPUT
70 23-19-16 5
25
70 8-14-12 2
28.50
Bottom of Boring at 28.5 ft
Project Name: Lolo Bike Trail - Missoula County, Montana Project Number: 114-570718
Borehole
Borehole Location: Refer to Site Map Number: BH-2 Sheet 1 of 1
Hammer:
Stationing: Type: Driller: O'Keefe - Butte Logger: Kyle Zanto
Borehole
Drilling Equipment: Mobile B-61 Diameter (in): 6.00 Date Started: 1-09-14 Date Finished: 1-09-14
Elevation
and Datum: Ground: 3203.40 Notes: Northing: 960458.54
DRILL Easting: 817037.62
PLASTICITY INDEX
DESIGNATION (RQD)
LIQUID LIMIT
RECOVERY (%)
ROCK QUALITY
STANDARD
GRAPHIC LOG
OPERATION
RATE (mph)
DEPTH (ft)
DEPTH (ft)
MATERIAL DESCRIPTION REMARKS
TEST
SAMPLE
CORE
SPT LL PI
10 12-9-15 10 FILL, poorly graded SAND with clay and
gravel (SP-SC), fine to coarse grained
sand, fine to medium grained gravel, 2.00
NV NP 10 medium dense, brown, moist, angular
gravel, low plasticity.
FILL, poorly graded GRAVEL with silt and
50 5-11-15 3 sand (GP-GM), fine to medium grained
5
gravel, fine to coarse grained sand,
medium dense to dense, brown/tan, moist,
angular gravel, non-plastic.
55 9-15-17 3
10
11.00
FILL, sandy lean CLAY (CL), fine to
medium grained sand, tan to gray, moist,
low plasticity. 13.00
Clayey SAND (SC) to Poorly graded SAND
70 12-15-15 6 with clay (SP-SC), fine to medium grained
15 sand, medium dense to dense, black/gray,
moist, low plasticity.
70 11-14-11 6
20
570718 LOGS.GPJ ` 6-12-14 ` MAT ` MONTANA DOT ENGLISH OUTPUT
80 13-13-20 7
25
25.50
Bottom of Boring at 25.5 ft
Project Name: Lolo Bike Trail - Missoula County, Montana Project Number: 114-570718
Borehole
Borehole Location: Refer to Site Map Number: BH-3 Sheet 1 of 1
Hammer:
Stationing: Type: Driller: O'Keefe - Butte Logger: Kyle Zanto
Borehole
Drilling Equipment: Mobile B-61 Diameter (in): 6.00 Date Started: 1-09-14 Date Finished: 1-09-14
Elevation
and Datum: Ground: 3170.40 Notes: Norhting: 965154.66
DRILL Easting: 818454.49
PLASTICITY INDEX
DESIGNATION (RQD)
LIQUID LIMIT
RECOVERY (%)
ROCK QUALITY
STANDARD
GRAPHIC LOG
OPERATION
RATE (mph)
DEPTH (ft)
DEPTH (ft)
MATERIAL DESCRIPTION REMARKS
TEST
SAMPLE
CORE
SPT LL PI
75 10-5-4 19 FILL, Clayey SAND with gravel, fine to
34 14 36
coarse grained sand and gravel, very loose
to medium dense, brown to tan, moist to
wet, low to medium plasticity.
5 2-2-1 19
5
7-6-4
10
10-10-11 18
15
16.00
Poorly graded SAND with clay and gravel
(SP-SC), fine to coarse grained sand, fine
grained gravel, medium dense, brown to
gray, moist, low plasticity.
50 6-12-12 6
20
570718 LOGS.GPJ ` 6-12-14 ` MAT ` MONTANA DOT ENGLISH OUTPUT
50 11-15-12 5
25
25.50
Bottom of Boring at 25.5 ft
Project Name: Lolo Bike Trail - Missoula County, Montana Project Number: 114-570718
Borehole
Borehole Location: Refer to Site Map Number: BH-4 Sheet 1 of 1
Hammer:
Stationing: Type: Driller: O'Keefe - Butte Logger: Kyle Zanto
Borehole
Drilling Equipment: Mobile B-61 Diameter (in): 6.00 Date Started: 1-10-14 Date Finished: 1-10-14
Elevation
and Datum: Ground: 3198.60 Notes: Northing: 967685.35
DRILL Easting: 819048.18
PLASTICITY INDEX
DESIGNATION (RQD)
LIQUID LIMIT
RECOVERY (%)
ROCK QUALITY
STANDARD
GRAPHIC LOG
OPERATION
RATE (mph)
DEPTH (ft)
DEPTH (ft)
MATERIAL DESCRIPTION REMARKS
TEST
SAMPLE
CORE
SPT LL PI
50 10-8-13 11 FILL, clayey SAND with gravel (SC), fine to
24 9 29
coarse grained sand and gravel, loose to
medium dense, brown, moist, some
cobbles, angular gravel, low to medium
plasticity.
20 3-6-3 13
5
10 9-4-4 2
10
25 15-14-11 8
15
16.00
Poorly graded GRAVEL with sand (GP),
fine to coarse grained sand and gravel,
dense, tan, moist, subrounded gravel.
60 19-20-26 4
20
20.50
Bottom of Boring at 20.5 ft
570718 LOGS.GPJ ` 6-12-14 ` MAT ` MONTANA DOT ENGLISH OUTPUT
Project Name: Lolo Bike Trail - Missoula County, Montana Project Number: 114-570718
Borehole
Borehole Location: Refer to Site Map Number: BH-5 Sheet 1 of 1
Hammer:
Stationing: Type: Driller: O'Keefe - Butte Logger: Kyle Zanto
Borehole
Drilling Equipment: Mobile B-61 Diameter (in): 6.00 Date Started: 1-10-14 Date Finished: 1-10-14
Elevation
and Datum: Ground: 3137.00 Notes: Northing: 970666.40
DRILL Easting: 822999.89
PLASTICITY INDEX
DESIGNATION (RQD)
LIQUID LIMIT
RECOVERY (%)
ROCK QUALITY
STANDARD
GRAPHIC LOG
OPERATION
RATE (mph)
DEPTH (ft)
DEPTH (ft)
MATERIAL DESCRIPTION REMARKS
TEST
SAMPLE
CORE
SPT LL PI
85 6-6-9 19 FILL, Clayey SAND with gravel (SP-SC),
23 9 33
fine to coarse grained sand, fine grained
gravel, medium dense, tan/gray, moist,
subrounded gravel, non-plastic.
5 17-11-4 3
5
6.00
Clayey GRAVEL with sand (GC), fine to
coarse grained sane and gravel, medium
dense, brown, moist, subrounded gravel,
low plasticity.
15 9-13-7 12 9.50
10 Poorly graded SAND with gravel (SP), fine
to coarse grained sand, fine grained gravel,
medium dense, brown, moist to wet, trace
silt, non-plastic.
55 9-10-13 9
15
16.00
Poorly graded to clayey SAND with gravel,
fine grained sand, very loose to loose, gray,
wet, trace silt, non-plastic to low plasticity.
100 2-2-2 33
20
570718 LOGS.GPJ ` 6-12-14 ` MAT ` MONTANA DOT ENGLISH OUTPUT
100 0-2-3 37
25
25.50
Bottom of Boring at 25.5 ft
PLASTICITY INDEX
DESIGNATION (RQD)
LIQUID LIMIT
RECOVERY (%)
ROCK QUALITY
STANDARD
GRAPHIC LOG
OPERATION
RATE (mph)
DEPTH (ft)
DEPTH (ft)
MATERIAL DESCRIPTION REMARKS
TEST
SAMPLE
CORE
SPT LL PI
Asphalt 0.75
14-11-13 5
Granular Base Course, Poorly Graded 2.00
Gravel and Sand.
22 7 17 FILL. Silty Clayey Gravel with Sand,
14-42-27 3
medium to very dense, subrounded to
5 subangular, slightly moist, brown,
occasional cobbles.
10 9-7-10-13 4
15 12-19-12 5
18.00
Silty Clayey Gravel with Sand (GC-GM),
20 20-33-31 4 very dense, subrounded, slightly moist,
brown, occasional cobbles.
25 12-22-34 4
LOLO LOG_DATA.GPJ ` 6-12-14 ` AJK ` MONTANA DOT ENGLISH OUTPUT
25.50
Bottom of Boring 25.5'
PLASTICITY INDEX
DESIGNATION (RQD)
LIQUID LIMIT
RECOVERY (%)
ROCK QUALITY
STANDARD
GRAPHIC LOG
OPERATION
RATE (mph)
DEPTH (ft)
DEPTH (ft)
MATERIAL DESCRIPTION REMARKS
TEST
SAMPLE
CORE
SPT LL PI
8-10-11-14 5
ASPHALT 0.50
Granular Base Course
2.60
FILL. Silty Clayey Gravel with Sand, dense
to very dense, subrounded to sub angular,
5 slightly moist, brown, occasional seams of
15-20-14-17 4 poorly graded sand with gravel and
occasional cobbles.
10
16-18-23-25 4
15
10-15-19-20 5
18.00
Silty Clayey Gravel with Sand (GC-GM),
20
very dense, subrounded, slightly moist,
16-22-25-28 4
brown, occasional cobbles.
23.00
Moderately Weathered Gray Bedrock
25
LOLO LOG_DATA.GPJ ` 6-12-14 ` AJK ` MONTANA DOT ENGLISH OUTPUT
21-24-50/(0.4) 5
26.40
Bottom of Boring 26.4'
PLASTICITY INDEX
DESIGNATION (RQD)
LIQUID LIMIT
RECOVERY (%)
ROCK QUALITY
STANDARD
GRAPHIC LOG
OPERATION
RATE (mph)
DEPTH (ft)
DEPTH (ft)
MATERIAL DESCRIPTION REMARKS
TEST
SAMPLE
CORE
SPT LL PI
ASPHALT 0.75
12-16-13 3
Granular Base Course and Subbase,
Poorly Graded Gravel and Sand
4.00
5 10-10-16 5 FILL. Silty Clayey Gravel with Sand,
21 6 18 medium dense to dense, subrounded to
subangular, slightly moist, brown,
occasional cobbles.
8.00
Silty Clayey Gravel with Sand (GC-GM),
10 10-19-22 5 dense, subrounded, slightly moist, brown,
occasional cobbles.
15 15-23-20 5
15.50
Bottom of Boring 15.5'
LOLO LOG_DATA.GPJ ` 6-12-14 ` AJK ` MONTANA DOT ENGLISH OUTPUT
PLASTICITY INDEX
DESIGNATION (RQD)
LIQUID LIMIT
RECOVERY (%)
ROCK QUALITY
STANDARD
GRAPHIC LOG
OPERATION
RATE (mph)
DEPTH (ft)
DEPTH (ft)
MATERIAL DESCRIPTION REMARKS
TEST
SAMPLE
CORE
SPT LL PI
14-4-10 3 Topsoil 0.75
FILL. Poorly Graded Gravel with Silt and
Sand, medium dense to dense, subrounded
to subangular, slightly moist, brown,
occasional cobbles.
5
10-13-17-15 4 NV NP 6
10 10-10-9-11
2-3-4-5 15 11.00
Sandy Silt (ML), loose, fine-grained sand,
slighty moist to moist, tan to red.
15
2-3-3-6 20
17.00
Bottom of Boring 17'
LOLO LOG_DATA.GPJ ` 6-12-14 ` AJK ` MONTANA DOT ENGLISH OUTPUT
PLASTICITY INDEX
DESIGNATION (RQD)
LIQUID LIMIT
RECOVERY (%)
ROCK QUALITY
STANDARD
GRAPHIC LOG
OPERATION
RATE (mph)
DEPTH (ft)
DEPTH (ft)
MATERIAL DESCRIPTION REMARKS
TEST
SAMPLE
CORE
SPT LL PI
ASPHALT 0.75
14-17-12 4
Granular Base Course and Subbase,
Poorly Graded Gravel and Sand.
5 13-35-38 4 5.00
23 8 23 FILL. Clayey Sand with Gravel, medium
dense, subangular, slightly moist, brown,
occasional cobbles.
10 12-16-10 6 10.00
Silty Clayey Gravel with Sand (GC-GM),
dense to very dense, subrounded to
rounded, slightly moist to moist, tan, dark
bown, gray, occasional cobbles.
15 6-18-38 7
20 10-16-23 12
20.50
Bottom of Boring 20.5'
LOLO LOG_DATA.GPJ ` 6-12-14 ` AJK ` MONTANA DOT ENGLISH OUTPUT
PLASTICITY INDEX
DESIGNATION (RQD)
LIQUID LIMIT
RECOVERY (%)
ROCK QUALITY
STANDARD
GRAPHIC LOG
OPERATION
RATE (mph)
DEPTH (ft)
DEPTH (ft)
MATERIAL DESCRIPTION REMARKS
TEST
SAMPLE
CORE
SPT LL PI
13-15-15-22 5 Asphalt 0.75
Granular Base Course and Subbase,
Poorly Graded Gravel and Sand.
5
9-12-16-16 6 5.50
FILL. Clayey Gravel with Sand, dense to
very dense, subrounded to subangular,
slightly moist, brown to reddish-brown,
occasional cobbles.
10
45-50/(0.5) 5
12.00
Clayey Gravel with Sand (GC), medium
dense to dense, subrounded, slightly moist,
brown to reddish-brown, occasional
15 cobbles.
23-27-17-15 7
15-14-12-11 7
20 20.00
Bottom of Boring 20.0'
LOLO LOG_DATA.GPJ ` 6-12-14 ` AJK ` MONTANA DOT ENGLISH OUTPUT
PLASTICITY INDEX
DESIGNATION (RQD)
LIQUID LIMIT
RECOVERY (%)
ROCK QUALITY
STANDARD
GRAPHIC LOG
OPERATION
RATE (mph)
DEPTH (ft)
DEPTH (ft)
MATERIAL DESCRIPTION REMARKS
TEST
SAMPLE
CORE
SPT LL PI
ASPHALT 0.75
16-15-14 4
Granular Base Course and Subbase,
Poorly Graded Gravel and Sand. 2.50
FILL. Clayey Gravel with Sand, dense,
22-19-15 4 24 10 16
subangular to angular, slightly moist,
5 reddish-brown, occasional cobbles.
9.00
10 11-35-30 6 24 10 Clayey Gravel with Sand (GC), dense to
very dense, subrounded to angular, slightly
moist, reddish-brown, occasional cobbles.
15 16-20-24 6
20 10-27-42 6
20.50
Bottom of Boring 20.5'
LOLO LOG_DATA.GPJ ` 6-12-14 ` AJK ` MONTANA DOT ENGLISH OUTPUT
PLASTICITY INDEX
DESIGNATION (RQD)
LIQUID LIMIT
RECOVERY (%)
ROCK QUALITY
STANDARD
GRAPHIC LOG
OPERATION
RATE (mph)
DEPTH (ft)
DEPTH (ft)
MATERIAL DESCRIPTION REMARKS
TEST
SAMPLE
CORE
SPT LL PI
Asphalt 1.00
12-30-27-19 5 Granular Base Course and Subbase,
Poorly Graded Gravel and Sand 3.00
FILL. Clayey Sand with Gravel, very
5
dense, angular to subangular, slightly moist
to moist, reddish to orange-brown,
occasional cobbles.
14-22-30-26 6
10
22 9 41
20-32-29-31 7
14.00
15 Clayey Gravel with Sand (GC), dense to
very dense, sub angular to angular, slightly
17-21-26-36 7
moist, brown, occasional cobbles. Auger
Refusal at 18'.
13-17-18-19 9
20 20.00
Bottom of Boring 20.0'
LOLO LOG_DATA.GPJ ` 6-12-14 ` AJK ` MONTANA DOT ENGLISH OUTPUT
PLASTICITY INDEX
DESIGNATION (RQD)
LIQUID LIMIT
RECOVERY (%)
ROCK QUALITY
STANDARD
GRAPHIC LOG
OPERATION
RATE (mph)
DEPTH (ft)
DEPTH (ft)
MATERIAL DESCRIPTION REMARKS
TEST
SAMPLE
CORE
SPT LL PI
ASPHALT 0.67
22-23-26 4
Granular Base Course and Subbase,
Poorly Graded Gravel and Sand
3.00
FILL. Clayey Sand with Gravel, medium
5 13-23-28 6 dense to very dense, subrounded to
subangular, slightly moist, brown to
reddish-brown, occasional cobbles.
10 13-15-21 8
15 26-31-21 6
20 11-15-18 7
21.00
Clayey Sand with Gravel (SC), medium
dense to very dense, subrounded to
subangular, slightly moist, brown to
reddish-brown, occasional cobbles. Very
25 11-16-12 8 hard drilling 21-24'
LOLO LOG_DATA.GPJ ` 6-12-14 ` AJK ` MONTANA DOT ENGLISH OUTPUT
25.50
Bottom of Boring 25.5'
PLASTICITY INDEX
DESIGNATION (RQD)
LIQUID LIMIT
RECOVERY (%)
ROCK QUALITY
STANDARD
GRAPHIC LOG
OPERATION
RATE (mph)
DEPTH (ft)
DEPTH (ft)
MATERIAL DESCRIPTION REMARKS
TEST
SAMPLE
CORE
SPT LL PI
ASPHALT 0.67
28-29-38 4
Granular Base Course and Subbase,
Poorly Graded Gravel and Sand
3.00
FILL. Clayey Sand with Gravel, medium
5 9-15-18 5 dense to dense, subrounded to subangular,
24 10 25
slightly moist, brown to reddish-brown,
occasional cobbles.
10 9-15-16 7
15 7-12-9 10
20 11-15-29 8
21.00
Clayey Sand with Gravel (SC), dense,
subrounded to subangular, moist, dark
brown to orange-brown, occasional
cobbles.
25 10-21-29 8
LOLO LOG_DATA.GPJ ` 6-12-14 ` AJK ` MONTANA DOT ENGLISH OUTPUT
25.50
Bottom of Boring 25.5'
PLASTICITY INDEX
DESIGNATION (RQD)
LIQUID LIMIT
RECOVERY (%)
ROCK QUALITY
STANDARD
GRAPHIC LOG
OPERATION
RATE (mph)
DEPTH (ft)
DEPTH (ft)
MATERIAL DESCRIPTION REMARKS
TEST
SAMPLE
CORE
SPT LL PI
ASPHALT 0.75
21-27-29 4
Granular Base Course and Subbase,
Poorly Graded Gravel and Sand.
3.00
FILL. Clayey Gravel with Sand, dense to
5 13-25-19 3 26 10 14 very dense, subangular to angular, slightly
moist to moist, brown to reddish brown,
occasional cobbles.
10 17-30-43 3
15 50/5" 1
18.00
Clayey Gravel with Sand (GC), very dense,
20 16-27-33 3 subangular to angular, slightly moist to
moist, brown to reddish-brown, occasional
cobbles.
24.30
50/4" 1
Bottom of Boring 24.3'
LOLO LOG_DATA.GPJ ` 6-12-14 ` AJK ` MONTANA DOT ENGLISH OUTPUT
PLASTICITY INDEX
DESIGNATION (RQD)
LIQUID LIMIT
RECOVERY (%)
ROCK QUALITY
STANDARD
GRAPHIC LOG
OPERATION
RATE (mph)
DEPTH (ft)
DEPTH (ft)
MATERIAL DESCRIPTION REMARKS
TEST
SAMPLE
CORE
SPT LL PI
19-20-16-12 5
ASPHALT 0.50
Granular Base Course and Subbase,
Poorly Graded Gravel and Sand.
5 5.00
10-9-7-8 7 FILL. Poorly Graded Gravel with Clay and
Sand, dense, angular to subangular,
slightly moist, reddish-brown, occasional
cobbles.
10
13-14-15-21 3
12.00
Poorly Graded Gravel with Sand (GP),
dense, angualr, slightly mosit,
reddish-brown, occasional cobbles. Very
15 hard drilling.
39-18-19-22 4
20
14-15-21-20 14
22.00
Poorly Graded Sand with Gravel (SP),
dense, angular gravel, slightly moist, brown.
25
LOLO LOG_DATA.GPJ ` 6-12-14 ` AJK ` MONTANA DOT ENGLISH OUTPUT
15-18-18-20 2
27.00
Bottom of Boring 27.0'
PLASTICITY INDEX
DESIGNATION (RQD)
LIQUID LIMIT
RECOVERY (%)
ROCK QUALITY
STANDARD
GRAPHIC LOG
OPERATION
RATE (mph)
DEPTH (ft)
DEPTH (ft)
MATERIAL DESCRIPTION REMARKS
TEST
SAMPLE
CORE
SPT LL PI
ASPHALT 0.58
20-29-30 4
Granual Base Course and Subbase, Poorly
Graded Gravel and Sand.
3.00
FILL. Poorly Graded Gravel with Clay and
5 18-12-14 4 Sand, medium dense to very dense,
subangular to subrounded, slightly moist to
moist, reddish-brown to dark brown. Large
cobbles and small boulders 10-14'.
10 20-44-29 3
15 15-20-18 5
24 12 11
20 23-24-12 12
21.00
Poorly Graded Gravel with Sand (GP),
dense to very dense, subangular to
angular, slightly moist to moist,
reddish-brown, occasional cobbles and
25 21-31-49 5 boulders, hard drilling.
LOLO LOG_DATA.GPJ ` 6-12-14 ` AJK ` MONTANA DOT ENGLISH OUTPUT
30 35-28-34 4
35 26-26-21 3
35.50
Bottom of Boring 35.5'
Operation Sampler Split
Types: Auger Types: Spoon
Penetrometer WATER LEVEL OBSERVATIONS
Mud While Drilling NE ft Upon Completion of Drilling ft
Air Rotary Shelby Vane Shear
Rotary
Time After Drilling
Continuous Diamond Bulk
California Ring Depth To Water (ft)
Flight Auger Core Sample
Wash Drive Grab
Testpit Remarks:
Rotary Casing Sample
Revised 5-17-11 (MAT)
Tetra Tech Figure No. 19
2525 Palmer Street, Suite 2
Missoula, MT 59808 LOG OF BORING
Phone: 406-543-3045
Fax: 406-543-3088
PLASTICITY INDEX
DESIGNATION (RQD)
LIQUID LIMIT
RECOVERY (%)
ROCK QUALITY
STANDARD
GRAPHIC LOG
OPERATION
RATE (mph)
DEPTH (ft)
DEPTH (ft)
MATERIAL DESCRIPTION REMARKS
TEST
SAMPLE
CORE
SPT LL PI
ASPHALT 0.58
26-34-35 5
Granular Base Course and Subbase,
Poorly Graded Gravel and Sand.
4.00
5 11-25-21 4 FILL. Poorly Graded Gravel with Clay and
Sand, dense to very dense, subangular to
subrounded, slightly moist to moist,
reddish-brown to brown, occasional
cobbles.
10 50/(0.3) 3
15 26-50/(0.3) 5
20 13-50/(0.4) 5
24.00
25 13-12-13 8 Silty Sand with Gravel (SM), medium 25.00
LOLO LOG_DATA.GPJ ` 6-12-14 ` AJK ` MONTANA DOT ENGLISH OUTPUT
30 22-35-31 6
30.50
Bottom of Boring 30.5'
PLASTICITY INDEX
DESIGNATION (RQD)
LIQUID LIMIT
RECOVERY (%)
ROCK QUALITY
STANDARD
GRAPHIC LOG
OPERATION
RATE (mph)
DEPTH (ft)
DEPTH (ft)
MATERIAL DESCRIPTION REMARKS
TEST
SAMPLE
CORE
SPT LL PI
ASPHALT 0.58
21-22-12 6
Granular Base Course and Subbase,
Poorly Graded Gravel and Sand.
5 8-11-18 7
6.00
FILL. Silty Clayey Sand, medium dense to
18 4 35 very dense, slightly moist to damp,
reddish-tan, occcasional cobbles.
10 22-32-50 3
11.00
Poorly Graded Gravel with Sand (GP), very
dense, angular, slightly moist, pinkish-tan.
15 36-50/(0.4) 5
38-50/(0.4) 7 19.90
Bottom of Boring 19.9'
LOLO LOG_DATA.GPJ ` 6-12-14 ` AJK ` MONTANA DOT ENGLISH OUTPUT
PLASTICITY INDEX
DESIGNATION (RQD)
LIQUID LIMIT
RECOVERY (%)
ROCK QUALITY
STANDARD
GRAPHIC LOG
OPERATION
RATE (mph)
DEPTH (ft)
DEPTH (ft)
MATERIAL DESCRIPTION REMARKS
TEST
SAMPLE
CORE
SPT LL PI
ASPHALT 0.75
11-16-30-50 5
Granular Base Course and Subbase,
2.25
Poorly Graded Gravel and Sand.
FILL. Silty Gravel with Sand, medium
dense to very dense, subangular to
5 angular, slighty moist to damp, brown.
8-11-43-27 4
10
11-22-50/(0.4) 6
15
7-12-7-13 5
17.00
Poorly Graded Gravel with Sand (GP), very
dense, angular, slightly moist, brown to
pinkish-brown, occasional cobbles.
20
43-50/(0.3) 3
25
LOLO LOG_DATA.GPJ ` 6-12-14 ` AJK ` MONTANA DOT ENGLISH OUTPUT
39-43-49-50 9
27.00
Bottom of Boring 27.0'
PLASTICITY INDEX
DESIGNATION (RQD)
LIQUID LIMIT
RECOVERY (%)
ROCK QUALITY
STANDARD
GRAPHIC LOG
OPERATION
RATE (mph)
DEPTH (ft)
DEPTH (ft)
MATERIAL DESCRIPTION REMARKS
TEST
SAMPLE
CORE
SPT LL PI
ASPHALT 0.68
12-21-18 5
Granular Base Course and Subbase,
Poorly Graded Gravel and Sand.
4.00
5 8-11-10 4 FILL. Silty Gravel with Sand, medium
dense, angular to subangular, slightly moist
to damp, reddish-brown, occasional
cobbles.
10 41-50/(0.25) 3 10.00
Poorly Graded Gravel with Sand (GP), very
dense, subrounded to subangular, slightly
moist to damp, reddish-brown, occasional
cobbles.
15 50/(0.4) 5
20 50/(0.4) 2
24.20
50/(0.2)
Bottom of Boring 24.2'
LOLO LOG_DATA.GPJ ` 6-12-14 ` AJK ` MONTANA DOT ENGLISH OUTPUT
PLASTICITY INDEX
DESIGNATION (RQD)
LIQUID LIMIT
RECOVERY (%)
ROCK QUALITY
STANDARD
GRAPHIC LOG
OPERATION
RATE (mph)
DEPTH (ft)
DEPTH (ft)
MATERIAL DESCRIPTION REMARKS
TEST
SAMPLE
CORE
SPT LL PI
ASPHALT 0.75
14-24-25-38 5
Granular Base Course and Subbase,
Poorly Graded Gravel and Sand
5
12-50/(0.46) 5 6.00
FILL. Silty Gravel with Sand, very dense,
subangular to angular, slightly moist,
brown, occasional cobbles.
10
30-50/(0.25) 3
15
50/(0.5) 2
20
10-23-30-49 4 NV NP 19
22.00
Poorly Graded Gravel with Sand (GP),
dense to very dense, angular to
subrounded, slightly moist to damp,
25 reddish-brown.
LOLO LOG_DATA.GPJ ` 6-12-14 ` AJK ` MONTANA DOT ENGLISH OUTPUT
13-20-15-33 3
30
13-9-17-36 4
32.00
Bottom of Boring 32.0'
PLASTICITY INDEX
DESIGNATION (RQD)
LIQUID LIMIT
RECOVERY (%)
ROCK QUALITY
STANDARD
GRAPHIC LOG
OPERATION
RATE (mph)
DEPTH (ft)
DEPTH (ft)
MATERIAL DESCRIPTION REMARKS
TEST
SAMPLE
CORE
SPT LL PI
ASPHALT 0.67
31-46-36 4
Granular Base Course and Subbase,
Gravel and Sand.
3.00
FILL. Silty Clayer Gravel with Sand, dense
5 19-22-28 4 19 6 16 to very dense, subangular to angular,
slightly moist to moist, brown to
reddish-brown, occasional cobbles.
10 27-50/(0.25) 6 10.00
Silty Gravel with Sand (GC-GM), very
dense, subrounded to angular, slightly
moist, brown. Occasional cobbles and
boulders, increasing with depth. Auger
refusal at 21'.
15 40-50/(0.4) 1
20 50/(0.25) 1
21.00
Bottom of Boring 21.0'
LOLO LOG_DATA.GPJ ` 6-12-14 ` AJK ` MONTANA DOT ENGLISH OUTPUT
90
80
70
PERCENT FINER BY WEIGHT
60
50
40
30
20
10
0
100 10 1 0.1 0.01 0.001
GRAIN SIZE IN MILLIMETERS
GRAVEL SAND
COBBLES SILT OR CLAY
coarse fine coarse medium fine
Specimen Identification D100 D60 D30 D10 %Gravel %Sand %Silt %Clay
570718 LOGS.GPJ ` 6-12-14 ` MAT ` TT_US GRAIN SIZE
90
80
70
PERCENT FINER BY WEIGHT
60
50
40
30
20
10
0
100 10 1 0.1 0.01 0.001
GRAIN SIZE IN MILLIMETERS
GRAVEL SAND
COBBLES SILT OR CLAY
coarse fine coarse medium fine
Specimen Identification D100 D60 D30 D10 %Gravel %Sand %Silt %Clay
570718 LOGS.GPJ ` 6-12-14 ` MAT ` TT_US GRAIN SIZE
90
80
70
PERCENT FINER BY WEIGHT
60
50
40
30
20
10
0
100 10 1 0.1 0.01 0.001
GRAIN SIZE IN MILLIMETERS
GRAVEL SAND
COBBLES SILT OR CLAY
coarse fine coarse medium fine
Specimen Identification D100 D60 D30 D10 %Gravel %Sand %Silt %Clay
570718 LOGS.GPJ ` 6-12-14 ` MAT ` TT_US GRAIN SIZE
90
80
70
PERCENT FINER BY WEIGHT
60
50
40
30
20
10
0
100 10 1 0.1 0.01 0.001
GRAIN SIZE IN MILLIMETERS
GRAVEL SAND
COBBLES SILT OR CLAY
coarse fine coarse medium fine
Specimen Identification D100 D60 D30 D10 %Gravel %Sand %Silt %Clay
570718 LOGS.GPJ ` 6-12-14 ` MAT ` TT_US GRAIN SIZE
90
80
70
PERCENT FINER BY WEIGHT
60
50
40
30
20
10
0
100 10 1 0.1 0.01 0.001
GRAIN SIZE IN MILLIMETERS
GRAVEL SAND
COBBLES SILT OR CLAY
coarse fine coarse medium fine
Specimen Identification D100 D60 D30 D10 %Gravel %Sand %Silt %Clay
570718 LOGS.GPJ ` 6-12-14 ` MAT ` TT_US GRAIN SIZE
90
80
70
PERCENT FINER BY WEIGHT
60
50
40
30
20
10
0
100 10 1 0.1 0.01 0.001
GRAIN SIZE IN MILLIMETERS
GRAVEL SAND
COBBLES SILT OR CLAY
coarse fine coarse medium fine
Specimen Identification D100 D60 D30 D10 %Gravel %Sand %Silt %Clay
R-2 - (3 - 10 ft) 37.5 5.929 1.001 47 36 17
90
80
70
PERCENT FINER BY WEIGHT
60
50
40
30
20
10
0
100 10 1 0.1 0.01 0.001
GRAIN SIZE IN MILLIMETERS
GRAVEL SAND
COBBLES SILT OR CLAY
coarse fine coarse medium fine
Specimen Identification D100 D60 D30 D10 %Gravel %Sand %Silt %Clay
R-6 - (5 - 9 ft) 25 5.587 0.683 45 37 18
90
80
70
PERCENT FINER BY WEIGHT
60
50
40
30
20
10
0
100 10 1 0.1 0.01 0.001
GRAIN SIZE IN MILLIMETERS
GRAVEL SAND
COBBLES SILT OR CLAY
coarse fine coarse medium fine
Specimen Identification D100 D60 D30 D10 %Gravel %Sand %Silt %Clay
R-9 - (5 - 6.5 ft) 75 13.009 6.006 0.228 75 19 6
90
80
70
PERCENT FINER BY WEIGHT
60
50
40
30
20
10
0
100 10 1 0.1 0.01 0.001
GRAIN SIZE IN MILLIMETERS
GRAVEL SAND
COBBLES SILT OR CLAY
coarse fine coarse medium fine
Specimen Identification D100 D60 D30 D10 %Gravel %Sand %Silt %Clay
R-10 - (5 - 9 ft) 25 4.31 0.188 38 39 23
90
80
70
PERCENT FINER BY WEIGHT
60
50
40
30
20
10
0
100 10 1 0.1 0.01 0.001
GRAIN SIZE IN MILLIMETERS
GRAVEL SAND
COBBLES SILT OR CLAY
coarse fine coarse medium fine
Specimen Identification D100 D60 D30 D10 %Gravel %Sand %Silt %Clay
R-14 - (4 - 10.5 ft) 25 5.483 0.75 43 41 16
90
80
70
PERCENT FINER BY WEIGHT
60
50
40
30
20
10
0
100 10 1 0.1 0.01 0.001
GRAIN SIZE IN MILLIMETERS
GRAVEL SAND
COBBLES SILT OR CLAY
coarse fine coarse medium fine
Specimen Identification D100 D60 D30 D10 %Gravel %Sand %Silt %Clay
R-16 - (10 - 18 ft) 25 0.841 15 44 41
90
80
70
PERCENT FINER BY WEIGHT
60
50
40
30
20
10
0
100 10 1 0.1 0.01 0.001
GRAIN SIZE IN MILLIMETERS
GRAVEL SAND
COBBLES SILT OR CLAY
coarse fine coarse medium fine
Specimen Identification D100 D60 D30 D10 %Gravel %Sand %Silt %Clay
R-20 - (5 - 10 ft) 25 3.094 0.133 30 45 25
90
80
70
PERCENT FINER BY WEIGHT
60
50
40
30
20
10
0
100 10 1 0.1 0.01 0.001
GRAIN SIZE IN MILLIMETERS
GRAVEL SAND
COBBLES SILT OR CLAY
coarse fine coarse medium fine
Specimen Identification D100 D60 D30 D10 %Gravel %Sand %Silt %Clay
R-22 - (4 - 10.5 ft) 37.5 16.525 3.046 65 21 14
90
80
70
PERCENT FINER BY WEIGHT
60
50
40
30
20
10
0
100 10 1 0.1 0.01 0.001
GRAIN SIZE IN MILLIMETERS
GRAVEL SAND
COBBLES SILT OR CLAY
coarse fine coarse medium fine
Specimen Identification D100 D60 D30 D10 %Gravel %Sand %Silt %Clay
R-26 - (15 - 20 ft) 25 7.673 4.218 67 22 11
90
80
70
PERCENT FINER BY WEIGHT
60
50
40
30
20
10
0
100 10 1 0.1 0.01 0.001
GRAIN SIZE IN MILLIMETERS
GRAVEL SAND
COBBLES SILT OR CLAY
coarse fine coarse medium fine
Specimen Identification D100 D60 D30 D10 %Gravel %Sand %Silt %Clay
R-30 - (7 - 11 ft) 19 0.668 13 52 35
90
80
70
PERCENT FINER BY WEIGHT
60
50
40
30
20
10
0
100 10 1 0.1 0.01 0.001
GRAIN SIZE IN MILLIMETERS
GRAVEL SAND
COBBLES SILT OR CLAY
coarse fine coarse medium fine
Specimen Identification D100 D60 D30 D10 %Gravel %Sand %Silt %Clay
S-2 - (20 - 22 ft) 37.5 5.89 0.193 43 38 19
90
80
70
PERCENT FINER BY WEIGHT
60
50
40
30
20
10
0
100 10 1 0.1 0.01 0.001
GRAIN SIZE IN MILLIMETERS
GRAVEL SAND
COBBLES SILT OR CLAY
coarse fine coarse medium fine
Specimen Identification D100 D60 D30 D10 %Gravel %Sand %Silt %Clay
S-4 - (4 - 5.5 ft) 37.5 5.369 0.333 42 42 16
90
80
70
PERCENT FINER BY WEIGHT
60
50
40
30
20
10
0
100 10 1 0.1 0.01 0.001
GRAIN SIZE IN MILLIMETERS
GRAVEL SAND
COBBLES SILT OR CLAY
coarse fine coarse medium fine
Specimen Identification D100 D60 D30 D10 %Gravel %Sand %Silt %Clay
570718 LOGS.GPJ ` 6-12-14 ` MAT ` TT_US GRAIN SIZE
90
80
70
PERCENT FINER BY WEIGHT
60
50
40
30
20
10
0
100 10 1 0.1 0.01 0.001
GRAIN SIZE IN MILLIMETERS
GRAVEL SAND
COBBLES SILT OR CLAY
coarse fine coarse medium fine
Specimen Identification D100 D60 D30 D10 %Gravel %Sand %Silt %Clay
570718 LOGS.GPJ ` 6-12-14 ` MAT ` TT_US GRAIN SIZE
130 GRADATION
% Gravel % Sand % Fines
56 28 16
125
ATTERBERG LIMITS
LL PL PI
DRY DENSITY, pcf
120 25 14 11
2.70
110 2.60
105
100
95
570718 LOGS.GPJ ` 6-12-14 ` MAT ` TT_COMPACTION W/CURVE
90
85
0 5 10 15 20 25 30
WATER CONTENT, %
MOISTURE-DENSITY RELATIONSHIP
Project: Lolo Bike Trail - Missoula County, Montana
Location: Refer to Site Map
Number: 114-570718 Figure No. 44
Revised 1-23-08 (MAT)
150
130 GRADATION
% Gravel % Sand % Fines
62 28 10
125
ATTERBERG LIMITS
LL PL PI
DRY DENSITY, pcf
120 NV NV NP
2.70
110 2.60
105
100
95
570718 LOGS.GPJ ` 6-12-14 ` MAT ` TT_COMPACTION W/CURVE
90
85
0 5 10 15 20 25 30
WATER CONTENT, %
MOISTURE-DENSITY RELATIONSHIP
Project: Lolo Bike Trail - Missoula County, Montana
Location: Refer to Site Map
Number: 114-570718 Figure No. 45
Revised 1-23-08 (MAT)
150
130 GRADATION
% Gravel % Sand % Fines
23 40 36
125
ATTERBERG LIMITS
LL PL PI
DRY DENSITY, pcf
120 34 20 14
2.70
110 2.60
105
100
95
570718 LOGS.GPJ ` 6-12-14 ` MAT ` TT_COMPACTION W/CURVE
90
85
0 5 10 15 20 25 30
WATER CONTENT, %
MOISTURE-DENSITY RELATIONSHIP
Project: Lolo Bike Trail - Missoula County, Montana
Location: Refer to Site Map
Number: 114-570718 Figure No. 46
Revised 1-23-08 (MAT)
150
130 GRADATION
% Gravel % Sand % Fines
33 38 29
125
ATTERBERG LIMITS
LL PL PI
DRY DENSITY, pcf
120 24 15 9
2.70
110 2.60
105
100
95
570718 LOGS.GPJ ` 6-12-14 ` MAT ` TT_COMPACTION W/CURVE
90
85
0 5 10 15 20 25 30
WATER CONTENT, %
MOISTURE-DENSITY RELATIONSHIP
Project: Lolo Bike Trail - Missoula County, Montana
Location: Refer to Site Map
Number: 114-570718 Figure No. 47
Revised 1-23-08 (MAT)
150
130 GRADATION
% Gravel % Sand % Fines
18 49 33
125
ATTERBERG LIMITS
LL PL PI
DRY DENSITY, pcf
120 23 13 10
2.70
110 2.60
105
100
95
570718 LOGS.GPJ ` 6-12-14 ` MAT ` TT_COMPACTION W/CURVE
90
85
0 5 10 15 20 25 30
WATER CONTENT, %
MOISTURE-DENSITY RELATIONSHIP
Project: Lolo Bike Trail - Missoula County, Montana
Location: Refer to Site Map
Number: 114-570718 Figure No. 48
Revised 1-23-08 (MAT)
150
130 GRADATION
% Gravel % Sand % Fines
47 36 17
125
ATTERBERG LIMITS
LL PL PI
DRY DENSITY, pcf
120 22 15 7
2.70
110 2.60
105
100
95
LOLO LOG_DATA.GPJ ` 6-12-14 ` AJK ` TT_COMPACTION W/CURVE
90
85
0 5 10 15 20 25 30
WATER CONTENT, %
MOISTURE-DENSITY RELATIONSHIP
Project: MISSOULA TO LOLO TRAIL
Location: 2011+00
Number: 114-570781 Figure No. 49
Revised 1-23-08 (MAT)
150
130 GRADATION
% Gravel % Sand % Fines
45 37 18
125
ATTERBERG LIMITS
LL PL PI
DRY DENSITY, pcf
120 21 15 6
2.70
110 2.60
105
100
95
LOLO LOG_DATA.GPJ ` 6-12-14 ` AJK ` TT_COMPACTION W/CURVE
90
85
0 5 10 15 20 25 30
WATER CONTENT, %
MOISTURE-DENSITY RELATIONSHIP
Project: MISSOULA TO LOLO TRAIL
Location: 2021+00
Number: 114-570781 Figure No. 50
Revised 1-23-08 (MAT)
150
130 GRADATION
% Gravel % Sand % Fines
38 39 23
125
ATTERBERG LIMITS
LL PL PI
DRY DENSITY, pcf
120 23 15 8
2.70
110 2.60
105
100
95
LOLO LOG_DATA.GPJ ` 6-12-14 ` AJK ` TT_COMPACTION W/CURVE
90
85
0 5 10 15 20 25 30
WATER CONTENT, %
MOISTURE-DENSITY RELATIONSHIP
Project: MISSOULA TO LOLO TRAIL
Location: 3011+50
Number: 114-570781 Figure No. 51
Revised 1-23-08 (MAT)
150
130 GRADATION
% Gravel % Sand % Fines
15 44 41
125
ATTERBERG LIMITS
LL PL PI
DRY DENSITY, pcf
120 22 13 9
2.70
110 2.60
105
100
95
LOLO LOG_DATA.GPJ ` 6-12-14 ` AJK ` TT_COMPACTION W/CURVE
90
85
0 5 10 15 20 25 30
WATER CONTENT, %
MOISTURE-DENSITY RELATIONSHIP
Project: MISSOULA TO LOLO TRAIL
Location: 3023+50
Number: 114-570781 Figure No. 52
Revised 1-23-08 (MAT)
150
130 GRADATION
% Gravel % Sand % Fines
30 45 25
125
ATTERBERG LIMITS
LL PL PI
DRY DENSITY, pcf
120 24 14 10
2.70
110 2.60
105
100
95
LOLO LOG_DATA.GPJ ` 6-12-14 ` AJK ` TT_COMPACTION W/CURVE
90
85
0 5 10 15 20 25 30
WATER CONTENT, %
MOISTURE-DENSITY RELATIONSHIP
Project: MISSOULA TO LOLO TRAIL
Location: 3040+50
Number: 114-570781 Figure No. 53
Revised 1-23-08 (MAT)
150
130 GRADATION
% Gravel % Sand % Fines
67 22 11
125
ATTERBERG LIMITS
LL PL PI
DRY DENSITY, pcf
120 24 12 12
2.70
110 2.60
105
100
95
LOLO LOG_DATA.GPJ ` 6-12-14 ` AJK ` TT_COMPACTION W/CURVE
90
85
0 5 10 15 20 25 30
WATER CONTENT, %
MOISTURE-DENSITY RELATIONSHIP
Project: MISSOULA TO LOLO TRAIL
Location: 3055+00
Number: 114-570781 Figure No. 54
Revised 1-23-08 (MAT)
150
130 GRADATION
% Gravel % Sand % Fines
13 52 35
125
ATTERBERG LIMITS
LL PL PI
DRY DENSITY, pcf
120 18 14 4
2.70
110 2.60
105
100
95
LOLO LOG_DATA.GPJ ` 6-12-14 ` AJK ` TT_COMPACTION W/CURVE
90
85
0 5 10 15 20 25 30
WATER CONTENT, %
MOISTURE-DENSITY RELATIONSHIP
Project: MISSOULA TO LOLO TRAIL
Location: 3063+00
Number: 114-570781 Figure No. 55
Revised 1-23-08 (MAT)
APPENDIX C
APPENDIX D
Project Photographs
Lolo Bike Trail Missoula County, MT
Geotechnical Drilling and RAP Pile, January 2014
Project No. 114-570781
PHOTOGRAPH 1 Looking north at drill rig at BH-1. PHOTOGRAPH 2 Looking north at drill rig at BH-2.
PHOTOGRAPH 3 Looking north at drill rig at BH-3. PHOTOGRAPH 4 Looking north at drill rig at BH-5.
PHOTOGRAPH 5 Making RAP sampling Pile. PHOTOGRAPH 6 Excavating RAP from Pile.
Project Photographs
Lolo Bike Trail Missoula County, MT
Retaining Wall Locations, May 2014
Project No. 114-570781
PHOTOGRAPH 7 Looking north STA 2009. PHOTOGRAPH 8 Looking north STA 2021.
PHOTOGRAPH 9 Looking south at STA 3011. PHOTOGRAPH 10 Looking north STA 3036.
PHOTOGRAPH 11 Looking north STA 3050. PHOTOGRAPH 12 Looking north STA 3089.
Project Photographs
Lolo Bike Trail Missoula County, MT
Retaining Wall Locations, May 2014
Project No. 114-570781
1
1
1
TYPICAL SECTION
C.1
1
2
1
TYPICAL SECTION
C.2
1
1
1
TYPICAL SECTION
C.3
APPENDIX F
Montana Public Works Standard Specifications,
Sixth Edition, April, 2010
(DJ&A, P.C. revisions included)
SECTION 02401
RETAINING WALLS
PART 1: GENERAL
1.1 DESCRIPTION
A. Approximately 6,831 feet of retaining walls will be constructed. Tetra Tech has
conducted a geotechnical investigation (report dated June XXX, 2014) along the
retaining wall alignment, and the report includes; soil borings, laboratory testing,
and slope stability analyses at the proposed retaining wall locations. Prior to
bidding on the work for this project, the contractor is strongly advised to, 1)
perform a site walk of the entire retaining wall alignment, 2) thoroughly review
the project geotechnical report, and 3) thoroughly review the project
specifications. The retaining wall contractor will construct the retaining walls to
meet the requirements in the Section 02403 Gravity or MSE Retaining Walls or
Section 02402 Soil Nail Retaining Walls.
1.2 REFERENCES
PART 2: PRODUCTS
2.1 GENERAL
A. See Section 02403 Gravity or MSE Retaining Walls, and Section 02402 Soil Nail
Walls.
PART 3: EXECUTION
3.1 The retaining walls must be constructed at the precise locations shown on the plans.
3.2 Temporary slopes cut to allow construction of the retaining walls must be constructed per
OSHA requirements.
3.3 As outlined in the project special provisions, prior to constructing the walls, the
contractor must submit design details, and global stability analyses, to ensure adequate
factors for short and long-term stability of the wall systems, as well as for the slopes
above and below the proposed retaining walls.
3.4 The retaining walls and associated cuts must be constructed without removing or
affecting the stability of the existing guardrail, or the stability of Highway 93.
Section 02401
RETAINING WALLS
Page 1 of 2
Montana Public Works Standard Specifications,
Sixth Edition, April, 2010
(DJ&A, P.C. revisions included)
3.5 The contractor may choose to utilize Highway 93 for staging purposes, provided that
traffic control is secured, and that a traffic control plan is submitted to MDT for approval
prior to commencing construction.
3.6 The retaining wall contractor must select equipment, and payloads of delivery and
material trucks, to ensure stability of the embankment slopes during construction. The
Project Manager may elect to limit the size of delivery trucks and loads delivered to the
site based on an evaluation by the Tetra Tech geotechnical engineer during construction.
3.7 The contractor may choose to construct the wall system of their choice at all locations,
provided the walls meet the requirements of the project special provisions, and contains
the facing requirements detailed in the special provisions.
4.1 Measurement and Payment for Retaining walls will be as outlined in Section 02402 and
Section 02403 as applicable.
END OF SECTION
Section 02401
RETAINING WALLS
Page 2 of 2
Montana Public Works Standard Specifications,
Sixth Edition, April, 2010
(DJ&A, P.C. revisions included)
SECTION 02402
PART 1: GENERAL
1.1 DESCRIPTION
A. This work consists of furnishing all materials, labor, and equipment necessary to
design, construct, and test drilled and grouted soil nail retaining walls with
shotcrete facing in accordance with these specifications and the lines, grades, and
dimensions shown on the plans or otherwise established by the Project Manager.
Soil nails must be drilled and grouted. Soil nail construction techniques consisting
of driven soil nails or jet-grouted nails are not acceptable. Have a Professional
Engineer registered in the State of Montana oversee the soil nail retaining wall
design and sign and seal the design calculations and drawings
1.2 REFERENCES
A. Division I, Section 5, Retaining Walls and other appropriate articles of the 17th
Edition of the AASHTO Standard Specification for Highway Bridges (2002)
including current interim specifications.
B. FHWA publication No. FHWA-SA-96-069R, Manual for Design and
Construction Monitoring of Soil Nail Walls, revised Oct. 1998.
C. FWHA publication No. FHWA-IF-03-017, Geotechnical Engineering Circular
No. 7, 2003.
PART 2: PRODUCTS
2.1 GENERAL
A. All materials and products utilized in the construction of the soil nail walls shall
be in conformance with the references listed above, and as further detailed below.
A. Nail Solid Bar. AAHSTO M31/ASTM A615, Grade 420 or 520, ASTM A 722
for Grade 1035. Deformed bar, continuous without splices or welds, new,
straight, undamaged, bare, or epoxy-coated, or encapsulated as shown on the
Plans. Threaded, a minimum of 6 inches on the wall anchorage end, to allow
proper attachment of bearing plate and nut. Threading may be continuous spiral
deformed ribbing provided by the bar deformations (continuous thread bards) or
may be cut into a reinforcing bar. If threads are cut into a reinforcing bar, provide
the next-larger bar number designation from that is shown on the Plans, at no
additional cost.
Section 02402
SOIL NAIL RETAINING WALLS
Page 1 of 14
Montana Public Works Standard Specifications,
Sixth Edition, April, 2010
(DJ&A, P.C. revisions included)
B. Bar Coupler. Bar couplers shall develop the full ultimate tensile strength of the
bar as certified by the manufacturer.
C. Fusion Bonded Epoxy Coating. ASTM A 775. Minimum 0.016 inch thickness
electrostatically applied. Bend test requirements are waived. Coating at the wall
anchorage end of epoxy-coated bars may be omitted over the length provided for
threading the nut against the bearing plate.
Section 02402
SOIL NAIL RETAINING WALLS
Page 2 of 14
Montana Public Works Standard Specifications,
Sixth Edition, April, 2010
(DJ&A, P.C. revisions included)
2.5 WELDED WIRE FABRIC
A. Pipe. ASTM 1785 Schedule 40 PVC solid and perforated wall, cell classification
12454-B or 12354-C, wall thickness SDR 35, with solvent weld or elastomeric
joints.
B. Fittings. ASTM D3034, cell classification 12454-B or C, wall thickness SDR 35,
with solvent or elastomeric joints.
A. Submit for approval, all materials, methods, and control procedures for this work.
PART 3: EXECUTION
A. The wall Contractor and the wall Designer/Engineer must attend, or send a duly
appointed representative, to the Pre-Construction Conference.
3.4 DESIGN
A. Meet the following requirements for the design of the soil nail wall(s).
Preliminary wall dimensions given on the plans are for estimating purposes only.
The contractor, through its chosen system, is responsible for producing a design,
which will establish:
a. Roadway plans. The Roadway plans include the final plans, profile, and
cross-sections for the Contract, including the proposed soil nail wall
locations.
b. Geotechnical Report, prepared by Tetra Tech, dated June xxx, 2014. This
report contains logs of all soil borings performed along the length of the
proposed soil nail wall. It is the responsibility of the contractor to obtain
any additional soil information required to complete the wall design.
c. The design peak ground acceleration is: 0.10g
d. The final design wall batter is 1H:10V
e. Ensure that the soil nail wall design meets the following minimum internal
factors of safety:
Soil Nail Pullout Resistance 2.0
Section 02402
SOIL NAIL RETAINING WALLS
Page 4 of 14
Montana Public Works Standard Specifications,
Sixth Edition, April, 2010
(DJ&A, P.C. revisions included)
Nail Bar Tensile Strength 1.8
f. Ensure that the facing strength of the wall design meets the following
minimum factors of safety:
Facing Flexure 1.5
Facing Punching Shear 1.5
g. MDTs Project Geotechnical Consultant evaluated the proposed wall
layout and determined that adequate external factors of safety exist for
global stability and bearing capacity. Verify that the final nail wall design
meets the following minimum external factors of safety (FS):
Global Stability 1.5
Compound Stability 1.5
Sliding 1.5
Seismic Stability FS 75% of static FS
(all failure modes)
h. Design the wall with a maximum 5-foot vertical and horizontal spacing
between soil nails. The soil nails must be spaced horizontally to penetrate
between the vertical guardrail posts along Interstate 90.
i. All steel components in the wall design must meet FHWA Buy America
requirements.
Design a drainage system to drain water and prevent hydrostatic pressure
buildup behind the facing. Include details in the drainage system for a
permanent interception ditch to control surface runoff and direct runoff
away from the top of the wall as shown in the Plans. The permanent ditch
must be constructed of reinforced concrete, a minimum of 2 feet in width,
4 inches in thickness, and graded to drain horizontally away from the top
of the wall. The permanent ditch must have outlets spaced at a maximum
of 250 feet to drain surface runoff to the drainage system and away from
the wall area.
j. Aesthetic Treatment. Apply an Aesthetic Treatment to the wall facing
consisting of a permanent stain applied by the Contractor.
1. Obtain prior approval from the Project Manager for the aesthetic
treatment. The method(s) for demonstrating the quality and color
of the aesthetic treatment are the sole responsibility of the
Contractor. Do not begin the aesthetic treatment without written
approval from the Project Manager.
2. Stain the facing to approximate and blend with the color(s) of
adjacent cut sections.
3. Apply the permanent stain in accordance with the manufacturers
recommendations.
4. If the unstained color of the shotcrete facing generally matches the
color of the new adjacent cuts prior to staining, the Project
Manager may waive the staining requirement at their discretion.
k. The shotcrete mixture must contain provisions for fiber reinforcement to
increase the durability of the mix and resistance to crack propagation. If
steel fibers are used, the design must incorporate measures to prevent
rusting of the fibers and discoloration of the final wall face.
Section 02402
SOIL NAIL RETAINING WALLS
Page 5 of 14
Montana Public Works Standard Specifications,
Sixth Edition, April, 2010
(DJ&A, P.C. revisions included)
3.6 SOIL NAIL WALL DESIGN REQUIREMENTS.
A. Ensure that the wall has an adequate factor of safety with respect to both the
internal stability of the reinforced soil mass (including nail pullout and nail bar
tensile strength), and the external stability (including global stability, bearing
capacity, and sliding) in the wall design. The design life of the structure is 75
years unless otherwise specified. Design the wall in accordance with Division I,
Section 5, Retaining Walls and other appropriate articles of the 17th Edition of the
AASHTO Standard Specification for Highway Bridges (2002) including current
interim specifications. Design the wall using the Load Resistance Factor Design
(LRFD) approach in accordance with FHWA publication No. FHWA-SA-96-
069R, Manual for Design and Construction Monitoring of Soil Nail Walls,
revised Oct. 1998 and general guidance from the FWHA publication No. FHWA-
IF-03-017, Geotechnical Engineering Circular No. 7, 2003.
A. At least 30 calendar days before the planned start of wall excavation, submit
complete design calculations and working drawings to DJ and A for review and
comment. Include all details, dimensions, quantities, ground profiles, and cross-
sections necessary to construct the wall. Verify the limits of the wall and ground
survey data before preparing drawings.
A. Design calculations must include, but not be limited to, the following items:
a. A written summary report that describes the overall soil nail wall design.
b. Applicable code requirements and design references.
c. Soil nail wall critical design cross-sections geometry including soil strata
and location, magnitude, and direction of design slope or external
surcharge loads and piezometric levels.
d. Design criteria including, soil/rock shear strengths (friction angle and
cohesion), unit weights, bond strength between the in situ soils and grout,
and any other assumptions for each soil strata.
e. Factors of safety used for internal stability checks, surcharges, soil unit
weights, reinforcing material properties, and wall panel unit materials.
Minimum required global factors of safety for stability and sliding for
both construction, and long-term conditions.
f. Design calculation sheets with:
Project Name
Wall Designer/Engineers project number
Wall location
Designation
Date of preparation
Initials of designer and checker
Page number at the top of each page.
Section 02402
SOIL NAIL RETAINING WALLS
Page 6 of 14
Montana Public Works Standard Specifications,
Sixth Edition, April, 2010
(DJ&A, P.C. revisions included)
An index page with the design calculations.
g. Design notes including an explanation of any symbols and computer
programs used in the design.
h. Soil nail wall final design cross-sections geometry including soil/rock
strata and location, magnitude, and direction of slope or external surcharge
loads and piezometric levels with critical slip surface shown along with
minimum calculated global stability and sliding factors of safety for both
construction, and long term conditions.
i. Structural design calculations for the shotcrete wall facing, connections,
soil nails, and connections between the soil nails and the facing.
j. Grout mix compressive strength test results, from a qualified independent
testing laboratory, verifying that the proposed nail grout mix will achieve
the specified 3-day (72 hour) compressive strength.
k. Other design calculations.
A. Working drawings must include, but are not limited to, the following items:
a. A plan view of the wall(s) identifying:
b. A reference baseline and elevation datum.
c. The offset from the construction centerline or baseline to the face of the
wall at its base at all changes in horizontal alignment.
d. Beginning and end of wall stations.
e. Right-of-way and permanent or temporary construction easement limits,
location of all known active and abandoned existing utilities, adjacent
structures or other potential interferences, the centerline of any drainage
structure or drainage pipe behind, passing through, adjacent to, or passing
under the wall.
f. Limits of longest nails.
g. Location of subsurface exploration borings performed by Tetra Tech.
h. An elevation view of the wall(s) identifying:
a. The elevation at the top of the wall, at all horizontal and vertical break
points, and at least every 15 feet along the wall.
j. Elevations at the wall base.
k. Beginning and end of wall stations.
l. The distance along the face of the wall to all steps in the wall base.
m. Wall elevation view showing the location of wall drainage elements along
the wall length.
n. Existing and finish grade profiles both behind and in front of the wall.
o. Design parameters and applicable codes.
p. Specifications for soil nails and connection pins.
q. General notes for constructing the wall including construction sequencing,
wall excavation, foundation preparation, wall erection, grouting
procedures and other special construction requirements.
r. Horizontal and vertical curve data affecting the wall and wall control
points.
Section 02402
SOIL NAIL RETAINING WALLS
Page 7 of 14
Montana Public Works Standard Specifications,
Sixth Edition, April, 2010
(DJ&A, P.C. revisions included)
s. Match lines or other details to relate wall stationing to centerline
stationing.
t. A listing of the summary of quantities on the elevation drawing of each
wall showing estimated square feet of wall face areas.
u. Soil nail wall typical sections including excavation elevations, nail
inclination, and wall face batter.
v. Details and dimensions for wall appurtenances such as barriers, coping,
drainage gutters, guardrail installations, sign posts, fences, etc.
w. Details for constructing walls around drainage facilities (if applicable).
x. Details for terminating walls and adjacent slope construction.
y. Details for performing verification and proof testing of the nails.
B. Have a Registered Professional Engineer sign and seal the drawings and
calculations. If the soil nail wall Contractor uses a Consultant designer
subcontractor or manufacturers representative to prepare the design, the soil nail
wall Contractor still retains overall contractual responsibility for both the design
and the construction.
C. Submit 3 sets of the wall drawings with the initial submission. One set will be
returned with any indicated corrections. DJ and A will review and provide
comments on the Contractor's submittals within 15 calendar days after receipt of a
complete submission. If revisions are necessary, make the necessary corrections
and resubmit 3 revised sets. When the drawings are approved, furnish 5 sets of
the drawings and a digital copy of the drawings in PDF format to the Project
Manager. The Contractor will not be allowed to begin wall construction or
incorporate materials into the work until the submittal requirements are satisfied
and found acceptable to the Owner. Changes or deviations from the approved
submittals must be re-submitted for approval. No adjustments in contract time
will be allowed due to incomplete submittals.
D. Revise the drawings when plan dimensions are revised due to field conditions or
for other reasons. Within 30 days after completion of the work, submit as-built
drawings to the Project Manager. Provide revised design calculations signed by a
Registered Professional Engineer for all design changes made during the
construction of the wall.
E. Provide 5 sets of the drawings and a digital copy of the drawings showing the
final as-built wall, design revisions, and revised calculations in PDF format to
the Project Manager.
A. Construct the wall and perform verification and proof testing according to the
approved set of working drawings and in accordance with the wall designers and
wall manufacturers recommendations, the Special Provisions, and the appropriate
sections of the Specifications.
Section 02402
SOIL NAIL RETAINING WALLS
Page 8 of 14
Montana Public Works Standard Specifications,
Sixth Edition, April, 2010
(DJ&A, P.C. revisions included)
3.11 NAIL TESTING CRITERIA
Where:
LBV = As-built bonded test length (ft or m)
Qd = Allowable pullout resistance (kips/ft or kN/m, of
grouted nail length, specified in the approved
submittals)
And:
Maximum Test Load (MTL) = 2.0 x DTL (kips or kN)
Section 02402
SOIL NAIL RETAINING WALLS
Page 10 of 14
Montana Public Works Standard Specifications,
Sixth Edition, April, 2010
(DJ&A, P.C. revisions included)
o. Incrementally load the verification test nails to a Maximum Test Load of
200% of the Design Test Load (DTL) in accordance with the following
Loading Schedule. Record the soil nail movements at each load
increment. Develop a form to record test nail location, inclination,
azimuth, bond length, test start-finish time, incremental loading dial
records and measurements of creep during the Creep Test.
Where:
LBP = As-built bonded test length (feet or meters)
Section 02402
SOIL NAIL RETAINING WALLS
Page 11 of 14
Montana Public Works Standard Specifications,
Sixth Edition, April, 2010
(DJ&A, P.C. revisions included)
Qd = Allowable pullout resistance (kips/ft or kN/m, of
grouted nail length, specified in the approved
submittals)
And:
Maximum Test Load (MTL) = 2.0 x DTL (kips or kN)
s. Perform proof tests by incrementally loading to a Maximum Test Load of
150% of the Design Test Load (DTL) in accordance with the following
Loading Schedule. Measure and record the nail movement at each load
with the Project Manager observing and verifying the data in the same
manner as the verification tests. Monitor the proof test load using a jack
pressure gauge with a sensitivity and range meeting the requirements of
pressure gauges used for verification test nails. At load increments other
than the Maximum Test Load, hold the load long enough to obtain a stable
reading.
The Alignment Load (AL) should be the minimum load required to align
the testing apparatus and should not exceed 5% of the Design Test Load
(DTL). Set dial gauges to "zero" after the Alignment Load has been
applied. Maintain load increments within 5% of the intended load.
Depending on performance, perform either 10 minute or 60 minute creep
tests at the Maximum Test Load (1.50 DTL). Start the creep period as
soon as the Maximum Test Load is applied and measure and record the
nail movement at 1, 2, 3, 5, 6, and 10 minutes. Where the nail movement
between 1 minute and 10 minutes exceeds 0.04 inches (1mm), maintain
the Maximum Test Load an additional 50 minutes and record movements
at 20, 30, 50, and 60 minutes.
A. If a test nail does not satisfy the acceptance criterion, determine the cause.
B. For verification test nails, the Project Manager will evaluate the results of each
verification test. Installation methods which do not satisfy the nail testing
requirements will be rejected. The Contractor must propose alternative
installation methods and install replacement verification test nails. Install and test
replacement test nails at no additional cost to the Department.
C. For proof test nails, the Project Manager may require the Contractor to replace
some or all of the installed production nails between a failed proof test nail and
the adjacent passing proof test tail.
D. Alternatively, the Project Manager may require the installation and testing of
additional proof test nails to verify that adjacent previously installed production
nails have sufficient load carrying capacity. Contractor modifications may
include, but are not limited to: the installation of additional proof test nails;
increasing the drillhole diameter to provide increased capacity; modifying the
installation or grouting methods; reducing the production nail spacing from that
specified in the approved submittals; and installing more production nails at a
reduced capacity.
Section 02402
SOIL NAIL RETAINING WALLS
Page 13 of 14
Montana Public Works Standard Specifications,
Sixth Edition, April, 2010
(DJ&A, P.C. revisions included)
E. Installation and testing of additional proof test nails or installation of additional or
modified nails as a result of proof test nail failure(s) will be at no additional cost
to the Department.
3.14 RECORDS
A. Submit records of each soil nail installation on a daily basis and submit a
summary form of all installations performed on a weekly basis to the project
manager.
4.1 MEASUREMENT
1. Soil Nail Retaining Walls will be measured by the finished area of wall
face per square foot. The finished area is calculated based on the height of
wall from the finished grade at the toe of the wall to the top of the wall as
measured in the field, installed, and accepted.
4.2 PAYMENT
A. The accepted quantities will be paid for at the contract unit price per unit of
measurement as reflected in the bid schedule. Payment will be full compensation
for all labor, equipment, materials, tests, investigations, and incidentals necessary
to acceptably design, construct, and test the soil nail retaining walls.
END OF SECTION
Section 02402
SOIL NAIL RETAINING WALLS
Page 14 of 14
Montana Public Works Standard Specifications,
Sixth Edition, April, 2010
(DJ&A, P.C. revisions included)
SECTION 02403
PART 1: GENERAL
1.1 DESCRIPTION
A. Description. Furnish all materials, labor, and equipment necessary to design and
construct Gravity or Mechanically Stabilized Earth (MSE) retaining wall(s) in
accordance with these specifications and the lines, grades, and dimensions shown
on the plans or otherwise established by the Engineer. Have a professional
engineer licensed in Montana oversee the retaining wall design and sign and seal
the design calculations and drawings.
B. Preliminary dimensions given on the plans are for estimating purposes only.
Produce a design for a Gravity or MSE wall system that will establish:
1.2 REFERENCES
PART 2: PRODUCTS
2.1 Use materials meeting the following requirements to construct Gravity or MSE walls.
Section 02403
GRAVITY OR MSE RETAINING WALLS
Page 1 of 8
Montana Public Works Standard Specifications,
Sixth Edition, April, 2010
(DJ&A, P.C. revisions included)
1. Concrete for Leveling Pads. Provide MDT Class DD or equivalent Concrete for
leveling pads. The bottom of the concrete leveling pad shall be provided with a
minimum soil cover of 42 inches for frost protection.
c. Soundness. Use materials that are substantially free of shale or other soft,
poor durability particles. Use material having a magnesium sulfate
soundness loss of less than 30 percent after four cycles, measured in
accordance with AASHTO T-104, or a sodium sulfate less of less than 15
percent after five cycles determined in accordance with AASHTO T-104.
Section 02403
GRAVITY OR MSE RETAINING WALLS
Page 2 of 8
Montana Public Works Standard Specifications,
Sixth Edition, April, 2010
(DJ&A, P.C. revisions included)
3. Reinforcement Material. Use reinforcement material that will not degrade over
the design life of the structure. When specifying the reinforcement material, use
the criteria given in the FHWA Publication Corrosion/Degradation of Soil
Reinforcements for Mechanically Stabilized Earth Walls and Reinforced Soil
Slopes, Publication No. FHWA-NHI-00-044.
4. Facing. Use modular block, welded wire grid, or precast concrete panel facing.
Use modular concrete blocks in conformance with ASTM C 1372, Standard
Specification for Segmental Retaining Wall Units. Use precast concrete panels
meeting the requirements set forth for precast members in AASHTO Section 5,
Concrete Structures.
PART 3: EXECUTION
1. Project Geotechnical Report By Tetra Tech, Inc. dated June XXX, 2014.
2. Boring Logs included in geotechnical report and the construction
drawings.
3. Contract Drawings including detailed drawings, plan and profile
drawings, and cross-section drawings for the proposed retaining wall
locations. These drawings will show right of way and construction limits,
and utilities.
B. All retaining walls shall be designed to tolerate a seismic event characterized with
a coefficient of acceleration of 0.18g.
C. Internal wall stability shall be the responsibility of the contractor including design
for slopes immediately above and below retaining walls. The following design
properties may be assumed for on-site materials for gravity wall, MSE wall, and
slope design:
At least 30 calendar days before the planned start of wall excavation, submit complete
design calculations and working drawings to DJ and A for review. Include all details, di-
mensions, quantities, ground profiles, and cross-sections necessary to construct the wall.
Verify the limits of the wall and ground survey data before preparing drawings.
Section 02403
GRAVITY OR MSE RETAINING WALLS
Page 3 of 8
Montana Public Works Standard Specifications,
Sixth Edition, April, 2010
(DJ&A, P.C. revisions included)
A. Design Calculations. Submit design calculations to include, but not be limited to,
the following items:
1. Applicable code requirements and design references.
2. Retaining wall critical design cross-section geometry including soil/rock
strata and location, magnitude, and direction of design slope or external
surcharge loads and piezometric levels along with the Capacity Demand
Ratios for, long-term conditions.
3. Design parameters including drained and undrained soil/rock shear
strengths (friction angle and cohesion), unit weights, and any other
assumptions for each soil/rock strata along with reinforcing material
properties, and facing materials.
4. Capacity Demand Ratios calculated from LRFD.
5. Design calculation sheets with the project number, wall location,
stationing, date of preparation, initials of designer and checker, and page
number at the top of each page. Provide an index page with the design
calculations.
6. Design notes including an explanation of any symbols and computer
programs used in the design.
7. Design calculations for wall facing units, connection pins, and reinforcing
material, and connections between the reinforcing material and the facing.
8. Other design calculations.
Submit 3 sets of the wall drawings to DJ and A with the initial submission. DJ
and A will review the Contractor's submittals within 20 calendar days after receipt
of a complete submission. If revisions are necessary, make the necessary
corrections and resubmit 3 revised sets. After the drawings have been reviewed
and found acceptable, furnish 5 sets of the drawings. Do not begin wall
construction or incorporate materials into the work until the submittal
requirements are satisfied and found acceptable to DJ and A. Changes or
deviations from the accepted submittals must be re-submitted and reviewed. No
adjustments in contract time will be allowed due to incomplete submittals.
Revise the drawings when plan dimensions are revised due to field conditions or
for other reasons. Within 30 days after completion of the work, submit as-built
drawings to the Engineer. Provide revised design calculations signed by a
Registered Professional Engineer for all design changes made during the
construction of the wall.
3.3 CONSTRUCTION
A. Construct the wall according to the approved set of working drawings, the special
provisions, and the appropriate sections of the Standard Specifications.
Section 02403
GRAVITY OR MSE RETAINING WALLS
Page 5 of 8
Montana Public Works Standard Specifications,
Sixth Edition, April, 2010
(DJ&A, P.C. revisions included)
1. Reinforced Backfill Source Approval. At least 30 calendar days before
beginning wall construction, submit a sample from the proposed borrow
source for backfill material.
2. Reinforcement Source Approval. Submit a manufacturers certificate of
compliance signed by an authorized manufacturers official stating that the
reinforcement material meets the requirements specified in the working
drawings. Submit a sample at least 5 feet in length by the full
reinforcement width for testing. After the sample and the required
information have been submitted to the Project Manager, allow 30
calendar days for evaluation. Remove and replace any material not
meeting the specified requirements at the Contractors expense.
3. Have a technical representative of the wall manufacturer on site during the
beginning of wall construction to ensure that the wall is installed properly.
4. Excavation. Complete the excavation in reasonably close conformity to
the limits shown on the approved design plans. The contractor is
responsible for temporary excavation support (as required).
5. Foundation Preparation. Prior to wall construction, compact the
foundation soils to a minimum of 95 percent of ASTM D698. The surface
should be smooth and level such that any shallow depressions or humps do
not exceed 6 inches in depth or height. Proofroll the subgrade and remove
and replace any unsuitable foundation soils with backfill material as per
Materials of these specifications. Do not use vibratory compaction
equipment unless approved by the Project Manager.
6. After placement of the leveling pad concrete, allow it to cure a minimum
of 12 hours before placing wall panels or modular block units.
7. Backfill Placement. Place backfill following each course of facing. Place
and compact backfill in such a manner to avoid any disturbance of the
wall materials or misalignment of the facing or reinforcing element.
Remove and replace any wall materials that become damaged during
construction at Contractors expense. Place, spread, and compact backfill
in such a manner that minimizes development of wrinkles in or movement
of reinforcement. Place backfill near the facing to assure that no voids
exist directly beneath the reinforcing elements. Place backfill in
maximum 8 inch loose lifts. Compact backfill to a minimum of 95 percent
of the maximum density determined by ASTM D698 within +/- 2 percent
of the optimum moisture content. Compact the backfill within 4 feet of
the wall face using a lightweight mechanical tamper or roller. Do not use
vibratory compaction equipment unless approved by the Project Manager..
At the end of each days operation, slope the level of the backfill away
from the wall facing to rapidly direct runoff away from the face. Do not
allow surface water from adjacent areas to enter the wall construction site.
8. Reinforcement Placement. At each reinforcement level, place and
compact the backfill to the level of the reinforcement. Place
reinforcement on a smooth horizontal surface. Pull the reinforcement
material tight before covering it with backfill. If using a geosynthetic
reinforcement, orientation of geosynthetic reinforcement is critical since
the strength of geosynthetic reinforcement varies with direction. Use soil
Section 02403
GRAVITY OR MSE RETAINING WALLS
Page 6 of 8
Montana Public Works Standard Specifications,
Sixth Edition, April, 2010
(DJ&A, P.C. revisions included)
piles, pins, or the manufacturers approved method to hold the
reinforcement material tight during backfill placement. Do not operate
equipment directly on the reinforcement material. Do not splice or
overlap geosynthetic reinforcement in the principal strength direction.
9. Modular Block Fill. Fill the voids in all modular blocks with aggregate
satisfying the following gradation:
10. Wall Batter. The completed wall has a vertical tolerance not exceeding
1/2 inch per 10 feet of wall height from the batter shown on the approved
set of working drawings.
11. Corrective Action. If any defects are found in the wall, begin repairing the
wall by a method approved by DJ and A. Within seven calendar days of
determining the need for wall repairs, submit four copies of calculations
and working drawings, stamped by a Professional Engineer licensed in
Montana, to the Project Manager for modifications to the wall caused by
the remedial action. Furnish all material and labor necessary to correct the
wall at no cost to the Department.
12. Contractor shall submit a construction plan to the Project Manager
approval prior to mobilization of materials or equipment. The
construction plan shall include schedules, excavation plans, excavation
safety, staging areas, surface water management plan.
13. Contractor shall submit an emergency response plan for Project Manager
approval prior to mobilization of materials. The plan shall include
provisions for traffic management in the event of construction excavation
slope failure.
14. Construction shall proceed in accordance with the approved construction
plan based on the type of walls selected.
4.1 MEASUREMENT
4.2 PAYMENT
Section 02403
GRAVITY OR MSE RETAINING WALLS
Page 7 of 8
Montana Public Works Standard Specifications,
Sixth Edition, April, 2010
(DJ&A, P.C. revisions included)
A. The accepted quantities will be paid for at the contract unit price per unit of
measurement as reflected in the bid schedule. Payment will be full compensation
for all labor, equipment, materials, tests, investigations, and incidentals necessary
to acceptably design, construct, and test the retaining walls.
END OF SECTION
Section 02403
GRAVITY OR MSE RETAINING WALLS
Page 8 of 8
Montana Public Works Standard Specifications,
Sixth Edition, April, 2010
(DJ&A, P.C. revisions included)
SECTION 02510
PART 1: GENERAL
1.1 DESCRIPTION
A. This work is the production and placement of plant mix asphalt concrete
pavement.
B. Hot plant mix asphalt concrete is a mineral aggregate and asphalt material mixed
at a central hot plant meeting these specifications and placed in one or more
courses on a newly prepared or existing street roadway in accordance with the
contract documents.
1.2 REFERENCES
AASHTO T11 Amount of Material Finer than No. 200 (0.075 mm) Sieve
(ASTM D1140) in Aggregate
ASTM D5361 Standard Practice for Sampling Compacted Bituminous
Mixtures for Laboratory Testing
AASHTO T27 Sieve Analysis of Fine and Coarse Aggregate
(ASTM C136)
AASHTO T89 Determining Liquid Limit of Soils
(ASTM D4318)
AASHTO T90 Determining the Plastic Limit and Plasticity Index of Soils
(ASTM D4318)
AASHTO T283 Resistance of Compacted Asphalt Mixtures to Moisture-
(ASTM D4867) Induced Damage
AASHTO T176 Sand Equivalent Value of Soils and Fine Aggregate
(ASTM D2419)
AASHTO T245 Resistance to Plastic Flow of Bituminous Mixtures Using
(ASTM D6926, D6927) Marshall Apparatus
AASHTO T96 Resistance to Degradation of Small-Size Coarse Aggregate
(ASTM C131) by Abrasion and Impact in the Los Angeles Machine
ASTM D2041 Theoretical Maximum Specific Gravity and Density of
Bituminous Mixtures
ASTM C1097 Hydrated Lime for Use in Asphaltic Concrete Mixtures
ASTM D3666 Evaluating and Qualifying Agencies Testing and
Inspecting
ASTM D5821 Determining the Percentage of Fractured Particles in
Coarse Aggregate
ASTM C123 Lightweight Particles in Aggregate
ASTM D6307 Asphalt Content of Hot Mix Asphalt by Ignition Method
ASTMC142 Clay Lumps and Friable Particles in Aggregates
MS-2 Asphalt Institute - Mix Design Methods
Section 02510
ASPHALT CONCRETE PAVEMENT
Page 1 of 21
Montana Public Works Standard Specifications,
Fifth Edition, March 2003
(DJ&A, P.C. revisions included)
PART 2: PRODUCTS
2.1 GENERAL
A. The specific type and grading of aggregate shall be consistent with those used on
other local, state, or federal projects with similar type construction as is outlined
for this project. Submit proposed aggregate gradation to the Engineer for
approval. Aggregate types and grades are described in this specification.
B. The furnishing of asphalt materials for use in asphaltic concrete mixes shall meet
the requirements for the particular grade specified in the contract documents. The
types and grades are described in this specification.
C. Prepare pavement course to conform to the lines, grades, thickness and typical
cross sections shown in project documents and plans, and shall be rolled, finished,
and approved by the Engineer before the placement of the next course.
B. Furnish test data as outlined in this section on each source to be used for
acceptance by the Engineer.
C. Designation of the sources of supply and the acceptability of the material there
from, does not extend to the grading of the material as it may naturally come from
the pit or crusher. Adjust the crusher and screens to remove certain portions of
the material as may be necessary to furnish gravel that will comply with the
specifications in the contract. No additional compensation will be allowed for
such adjustment of the equipment or the rejection of waste. It is understood that
the Engineer may order procurement of material from any portion of any area
designated as a pit site and may reject portions of the deposit as unacceptable.
D. Aggregate materials shall not contain more than 1.5% by weight of clay lumps,
shale, or coal, nor lightweight particles shall exceed 3.5% by weight. No
combination of clay, shale, coal, or lightweight particles shall exceed 3.5% by
weight. Do not use Scoria (fired clay). Aggregate materials shall conform to the
grading stipulated in the contract documents. Use reasonable care in the selection
of material in a pit so that uniform product will be produced at all times. No
compensation will be allowed for such stripping of the pit as may be required in
order that satisfactory material may be secured.
Section 02510
ASPHALT CONCRETE PAVEMENT
Page 2 of 21
Montana Public Works Standard Specifications,
Sixth Edition, April, 2010
(DJ&A, P.C. revisions included)
E. Aggregate used shall consist of gravel, crushed to the specified size, crushed
stone, composed of hard durable pebbles or stone fragments, reclaimed asphalt
pavement, and finely crushed stone filler, sand or natural clean material, or other
fine mineral material. The portion of the material retained on the No. 4 sieve
(4.74 mm) will be called coarse aggregate and that passing the No. 4 sieve (4.74
mm) and retained on the #200 sieve (0.075) will be called fine aggregate. The
material passing the #200 (0.075 mm) will be called mineral filler. The reclaimed
asphalt pavement shall be removed from its original location and reduced by
suitable means to such particle size as may be required for use in hot plant mix
asphalt concrete.
F. For all gradings of fine aggregate, including any blended fine aggregate and
mineral filler, passing a No. 40 sieve (0.425 mm), shall have a liquid limit not
exceeding 25 and a plasticity index of not more than 6.
G. Produce coarse aggregate retained on the No. 4 sieve (4.74 mm) having a
minimum of 50% by weight of particles with at least one mechanically fractured
face. The coarse aggregate shall not exceed 40% wear at 500 revolutions.
H. Preliminary acceptance of aggregates proposed for use may be made at the point of
production. Final acceptance will be made only after tests of the aggregates are
complete and in place.
TABLE 1
1. The above gradation bands represent the job mix target limits, which
determine the suitability of aggregate for use. The final job mix target
gradation must be within the specified bands and uniformly graded from
Section 02510
ASPHALT CONCRETE PAVEMENT
Page 3 of 21
Montana Public Works Standard Specifications,
Fifth Edition, March 2003
(DJ&A, P.C. revisions included)
coarse to fine and not vary from the low limits on one screen to the high
limits on the adjacent screen, or vice versa. The final job mix gradation
limits are established by applying the job mix tolerances to the job mix
targets.
2. The job mix formula establishes target values. During production of the
mix, the target gradation shall lie within the job mix grading limits
specified in Table 1. For example, Type A, No. 200 band is 4-7. ZA
job mix target of 5 has been selected for the final mix. The job mix
gradation limits is 5, plus and minus 2. Therefore, the job mix gradation
limits for production is 3-7.
1. Grade:
a. (PGAB) PG 58-28
C. Obtain Engineer approval of the asphalt material source before shipments are
made to any project. The source of supply cannot change after work is started
unless approved in writing by the Engineer. The Engineer is not liable for the
quantity shipped.
D. Samples of asphalt binder material may be taken, as directed by the Engineer, and
placed in uncontaminated one-quart containers. When sampled, these shall be
taken from the tanker car or truck at the point of delivery on the project and
submitted to the Engineer.
E. All transport vehicles must be equipped with a spigot or gate valve installed in
either: (1) the unloading line, (2) in the tanker at the centerline on the tank, (3) in
the pressure line from the unloading pump, or other locations approved by the
Engineer. Assure the spigot or gate valve has a diameter of between 3/8 inch (1
cm) and 3/4 inch (2.5 cm). The spigot valve must be located to prevent
contamination from plant dust or other contaminants.
Section 02510
ASPHALT CONCRETE PAVEMENT
Page 4 of 21
Montana Public Works Standard Specifications,
Fifth Edition, March 2003
(DJ&A, P.C. revisions included)
F. The supplier furnishing the asphalt binder material shall inspect each tanker car or
truck before it is loaded and ship only in clean, uncontaminated, fully insulated
cars or trucks, sealed after loading by the supplier.
H. The certificate of compliance is the basis for tentative acceptance and use of the
material. Samples taken according to applicable sampling methods and retained
by the Engineer may be tested at the Engineers discretion. Failure of the asphalt
material to meet these specifications may result in rejection of the entire,
associated work. If rejected, remove and replace rejected work.
J. Upon request by the Engineer, furnish the Engineer and/or laboratory (responsible
for completing the mix design) with data or a report showing the temperature-
viscosity relationship of each asphalt binder used on the project. Assure this data
covers the range of temperatures used for mixing and compaction. In addition,
the Engineer may request a complete set of test results from Table 3 for each
grade used on the project.
Section 02510
ASPHALT CONCRETE PAVEMENT
Page 5 of 21
Montana Public Works Standard Specifications,
Fifth Edition, March 2003
(DJ&A, P.C. revisions included)
TABLE 3
a. If creep stiffness is below 300 MPa, the direct tension test is not required. If the creep
stiffness is between 300 and 600 MPa, the direct tension failure strain requirement can be
used in lieu of the creep stiffness requirement. The m-value requirement must be
satisfied in both cases.
Section 02510
ASPHALT CONCRETE PAVEMENT
Page 6 of 21
Montana Public Works Standard Specifications,
Fifth Edition, March 2003
(DJ&A, P.C. revisions included)
A. General
1. Submit to the engineer for approval a mix design for each mix required on
the project. Assure the job-mix formula is within the gradation limits in
Part 2 Products in this Section.
3. Keep the job mix formula current and contain the following minimum
information:
4. In addition to the job mix formula, all asphalt concrete surfacing mix
submittals will have laboratory tests indicating that the Tensile Strength
Ratio (TSR) as determined by AASHTO T-283, is at least 70%. Test shall
be performed at 7.0 +/- 1% air voids and shall include the freeze cycle.
1. The maximum permissible variation from the job-mix formula within the
specification limits is as follows:
Section 02510
ASPHALT CONCRETE PAVEMENT
Page 7 of 21
Montana Public Works Standard Specifications,
Fifth Edition, March 2003
(DJ&A, P.C. revisions included)
* This tolerance will be permitted only if the job mix parameter
curves indicate that the corresponding Marshall design limits are
not exceeded.
2. Produce Hot Plant Mix Asphalt Concrete Base Courses having the
following characteristics as measured by AASHTO T245, ASTM D6726
& D6927 Resistance to Plastic Flow of Bituminous Mixtures by means of
the Marshall Apparatus:
TABLE 4
Section 02510
ASPHALT CONCRETE PAVEMENT
Page 8 of 21
Montana Public Works Standard Specifications,
Fifth Edition, March 2003
(DJ&A, P.C. revisions included)
PART 3: EXECUTION
3.1 CRUSHING:
A. Crushing Equipment
B. Screening Plants
C. Scales
2. House the recording devices of the scales in a suitable manner. Place the
scales in a location suitable to facilitate accurate weighing of loads. The
scales shall be accurate to one-half of one percent at any weight. Alternate
methods or devices for weighing may be acceptable, provided that these
methods or devices produce the same degree of accuracy as required of
platform scales.
A. All work involved in clearing and stripping pits and quarries, including handling
unsuitable material encountered, are performed with no additional compensation
being allowed for this work. The pits as utilized shall immediately be opened so
as to expose the vertical faces of the various strata of acceptable material and,
unless otherwise directed, the material shall be secured in successive vertical cuts
extending through all the exposed strata.
D. Provide a storage bin of ample capacity to insure uniform quality and delivery of
material. Loading of trucks directly from the conveyor belt, from the crusher or
screening plant will not be permitted.
3.3 STOCKPILES:
A. Grub and clean sites for aggregate stockpiles prior to storing aggregates. Assure
the site is firm, smooth and well drained. Maintain a bed of aggregate suitable to
avoid the inclusion of soil or foreign material.
B. Build up coarse aggregate stockpiles in tiers of not more than 4 feet (1.2 m) in
thickness. Assure each tier is completely in place before the next tier is placed.
Do not allow material to cone down over the next lower tier.
F. Transfer the aggregate from the stockpiles in such a manner that uniform grading
of the material is preserved.
Section 02510
ASPHALT CONCRETE PAVEMENT
Page 10 of 21
Montana Public Works Standard Specifications,
Fifth Edition, March 2003
(DJ&A, P.C. revisions included)
3.6 ASPHALT MIXING PLANTS
A. Use mixing plants of either the weight batching type, the continuous flow mixing
type, or drum dryer type. Use drum dryer mixers specifically designed and
constructed for producing hot mix.
B. Equip all plants with approved conveyors, power units, aggregate handling
equipment, aggregate screens and bins that are coordinated and operated to
produce a uniform mixture within the specified job mix tolerances.
D. Stop production and remove from the project mixing plants that fail to
continuously produce a mixture meeting requirements as specified.
A. The Contractors independent testing agency shall provide the engineer with a
gradation analysis of the completed mix to assure that the materials being
produced and used are within the tolerances of the mix design and the
specifications of the mix being used.
B. Samples will be used to verify compliance with the requirements set forth in this
Section. If there is a dispute, a third party testing firm may be retained by the
Section 02510
ASPHALT CONCRETE PAVEMENT
Page 11 of 21
Montana Public Works Standard Specifications,
Fifth Edition, March 2003
(DJ&A, P.C. revisions included)
Contractor for additional testing.
A. When the moisture in the stockpiled aggregate or the dryer adversely effects the
quality of mix production, normal plant operations, or when pools of water are
observed on the base, mixing and placing of hot-mix asphalt is prohibited.
B. Do not place asphalt hot-mix surface course mixture when the air temperature is
less than 40F (4C) and rising. Do not place asphalt hot-mix base course
mixtures of compacted lifts 4 inches (10 cm) or more when the air temperature is
less than 30F (-1C) and rising. Do not place asphalt upon a surface which is
frozen or that has a temperature of less than 32F (0C). Do not place paving
during rainfall or in standing water.
A. Assure the area to be paved is true to line and grade and has a dry and properly
prepared surface before starting paving operations. Assure the surface is free
from all loose screenings and other loose or foreign material.
A. For new work, meet the surface preparation requirements in Sections 02230,
02234 or 02235 of these specifications. Prime stabilized layer if indicated as a
bid item in the Contract Documents.
3.14 PATCHING:
A. Weather Limitations
B. Surface Preparations
1. Assure the area to be paved is true to line and grade, is dry and properly
prepared surface before starting paving operations. Clean the surface of
all loose screenings and other loose or foreign material.
2. Before paving, proof roll the base. Areas that yield excessively or crack
under such wheel loads will be excavated and replaced, to correct yielding
and cracking problems. This does not replace the base or subgrade
compaction requirements. Cut the edge of existing pavements against
which additional pavement is to be placed straight and vertical.
c. Cut asphalt edges at least 30 cm (12 inches) wider than the trench
width on each side of trench excavations; and, in general, be cut
parallel to the street centerline for mainline construction and
perpendicular to the street centerline for service lateral
construction.
4. Remove and replace asphalt surface widths of less than 3 feet (90 cm).
C. Compaction
A. Transport the mix in vehicles cleaned of all foreign material which may affect the
mix. The truck beds must be painted, or sprayed with a lime-water, soap or
detergent solution at least once a day or as often as required. After this operation,
elevate the truck bed and thoroughly drain it, with no excess solution being
permitted. Dispatch the vehicles so that all material delivered is placed in
daylight, unless the Engineer approves artificial light. Deliver material to the
paver at a uniform rate and in amount well within the capacity of the paving and
compacting equipment.
A. Spread and strike off the base and surface courses with a mechanical paving
machine. Operate the paving machine so that material does not accumulate and
remain along the sides of the receiving hopper.
Section 02510
ASPHALT CONCRETE PAVEMENT
Page 13 of 21
Montana Public Works Standard Specifications,
Fifth Edition, March 2003
(DJ&A, P.C. revisions included)
B. Do not use equipment, which leaves tracks or indented areas, which cannot be
corrected in normal operation, produces flushing or other permanent blemishes, or
fails to produce a satisfactory surface.
C. Construct longitudinal joints and edges to true line markings. Establish lines for
the paver to follow in placing individual lanes parallel to the centerline of the
proposed roadway. Position and operate the paver to follow closely the
established lines.
D. When using pavers in echelon, assure the first paver follows the marks or lines
with the second paver following the edge of the material placed by the first paver.
To assure a hot joint and obtain proper compaction, assure the pavers work as
close together as possible, not exceeding 100 feet (30 m) apart. In backing trucks
against the paver, take care not to jar the paver out of its proper alignment.
E. As soon as the first load of material has been spread, check the texture of the
unrolled surface to determine its uniformity. Segregation of materials is not
permitted. If segregation occurs, suspend spreading operation until the cause is
determined and corrected.
F. Offset transverse joints in succeeding courses at least 2 feet (0.6 m). Offset
longitudinal joints at least 6 inches (15 cm).
A. In small areas where the use of mechanical finishing equipment is not practical,
the mix may be spread and finished by hand, if so directed by the Engineer. Wood
or steel forms, approved by the Engineer, rigidly supported to assure correct grade
and cross section, may be used. In such instances, measuring blocks and
intermediate strips must be used to obtain the required cross-section. Perform
hand placing carefully. Uniformly distribute the material to avoid segregation of
the coarse and fine aggregate. Broadcasting of material is not permitted. During
Section 02510
ASPHALT CONCRETE PAVEMENT
Page 14 of 21
Montana Public Works Standard Specifications,
Fifth Edition, March 2003
(DJ&A, P.C. revisions included)
the spreading operation, loosen and uniformly distribute all material using lutes or
covered rakes. Reject material that has formed into lumps and does not break
down readily. Following placing and before rolling, check the surface with
templates and straightedges and correct all irregularities.
B. Maintain on the project heating equipment for keeping hand tools free from
asphalt. Exercise caution to prevent heating that may burn the material. Assure
the temperature of the tools when used is not greater than the temperature of the
mix being placed. Use heat only to clean hand tools; petroleum oils or solvents
are not permitted.
3.19 COMPACTION:
A. Due to the location of the trail on the existing fill embankment, vibratory
rolling methods to compact the pavement layer are not allowed unless
otherwise specified by the Engineer. If the contractor is experiencing
difficulty achieving compaction utilizing non-vibratory methods, the
Engineer will contact Tetra Tech to discuss alternative compaction methods.
C. After the longitudinal joints and edges have been compacted, start rolling
longitudinally at the sides and progress toward the center of the pavement.
Operate the rollers at a slow, uniform speed with the drive roll or wheel nearest
the paver. Do not exceed 3 miles per hour (4.8 km per hour).
D. Do not quickly change the line of rolling reversing direction suddenly. If rolling
displaces the material, re-work the area using lutes or shovels and restore it the
original grade of the loose material before re-rolling. Do not permit heavy
equipment or rollers to stand on the finished surface before it has been compacted
and has thoroughly cooled.
E. When paving in single width, roll the first lane placed as follows:
1. Transverse joints
2. Outside edge
3. Initial or breakdown rolling, beginning on the low side and progressing
toward the high side.
4. Second rolling, same procedures as 3
5. Finish rolling
G. When paving in echelon, leave 2 or 3 inches (5 to 7.5 cm) of the edge unrolled,
Section 02510
ASPHALT CONCRETE PAVEMENT
Page 15 of 21
Montana Public Works Standard Specifications,
Sixth Edition, April, 2010
(DJ&A, P.C. revisions included)
which the second paver can match unrolled. Then the joint between the lanes can
be rolled together. Do not leave edges exposed more than 15 minutes without
being rolled.
H. In laying a surface mix adjacent to any finished area, place it high enough so that,
when compacted, the finished surface is true and uniform.
I. On slight grades, check gutters with a straightedge and test with running water to
assure drainage to the planned outlet.
J. The average density shall be equal to or greater than 93 percent of the maximum
density as determined by ASTM D2041 and no individual sample shall be less
than 92 percent of maximum density.
A. Construct and compact transverse joints to provide a smooth riding surface. Joints
will be straight edged and string lined to assure smoothness and true alignment.
B. Joint formed with bulkheads to provide a straight line and vertical face will be
checked with a straightedge before fresh material is placed against it to complete
the joint. If bulkheads are not used to form the joint and the roller is permitted to
roll over the edge of the new material, locate the joint line in back of the rounded
edge the distance required to provide a true surface and cross-section. If a joint
has been distorted by traffic or by other causes, trim it to line. Paint the joint face
with a thin coating of asphalt before the fresh material is placed against it.
C. Place the material against the joints vertical face with the paving machine
positioned so that the material overlaps the edge of the joint 1 to 2 inches (2.5 to 5
cm). Maintain a uniform depth of the overlapped material. Remove and dispose
of the coarse aggregate in the overlapped material that dislodged during raking.
E. Keep the number of transverse joints to a minimum. When paving single width
and maintaining traffic, pave one lane no farther than one block. Complete all
lanes to the same station at the end of each paving day. When paving in echelon,
bring the lanes up even as is practical.
A. Roll longitudinal joints directly behind the paving operation. Assure the first lane
Section 02510
ASPHALT CONCRETE PAVEMENT
Page 16 of 21
Montana Public Works Standard Specifications,
Sixth Edition, April, 2010
(DJ&A, P.C. revisions included)
placed is true to line and grade and has a vertical face. Place the material in the
lane being paved up firmly against the face of the previously placed lane. Position
the paver during spreading to assure the material overlaps the edge of the lane
previously placed by 1 inch to 2 inches (25 to 50 mm). Uniformly maintain the
width and depth of the overlapped material at all times. Keep the paver aligned
with the line or markings placed along the joint for alignment purposes. Before
rolling, remove and dispose of the coarse aggregate in the material overlapping
the joint.
B. Shift rollers onto the previously placed lane so that not more than 6 inches (15
cm) of the roller wheel rides on the edge of the fine material left by brooming.
Operate the rollers to compact the fines gradually across the joint. Continue
rolling until a compacted, neat joint is obtained. When the abutting lane is not
placed in the same day, paint the joint with a very think coating of asphalt before
placing the abutting lane. If the joint is distorted during the days work by traffic
or by other causes, carefully trim the edge of the lane to a neat line.
3.23 EDGES:
A. Roll the pavement edges concurrently with or immediately after rolling the
longitudinal joint.
B. Exercise care in consolidating the course along the entire length of the edges. In
rolling pavement edges, extend the roller wheels 2 to 4 inches (5 to 10 cm)
beyond the pavement edge.
A. Assure the second rolling follows the breakdown rolling as close as possible while
the paving mix is still at a temperature that will provide the specified density.
A. Perform the finish rolling while the material is still warm enough to remove roller
marks. If necessary, the Engineer may require using pneumatic-tired rollers.
Section 02510
ASPHALT CONCRETE PAVEMENT
Page 17 of 21
Montana Public Works Standard Specifications,
Sixth Edition, April, 2010
(DJ&A, P.C. revisions included)
Complete finish rolling the same day the mixture is placed.
3.27 SHOULDERS:
A. Where paved shoulders or curbs are not specified, do not place the shoulder
material against the pavement edges until the surface course rolling completed.
Take care to prevent distortion of the pavement edge from specified line and
grade. When shoulders are paved (except in conjunction with the traveled way
paving), cold joint construction procedure is required to assure a tight bond at the
joint.
B. When the rolling of the surface has been completed and the edges have been
thoroughly compacted, immediately place shoulder material against the edges and
roll it.
A. The average mat density shall be equal to or greater than 93 percent of the
maximum density as determined by ASTM D2041 and no individual sample shall
be less than 92 percent of maximum (Rices) density, prepared as specified in Part
2-Products in this section and made from plant mix meeting the job-mix formula.
Verification of maximum density as determined by ASTM D2041 from plant
produced material during production is recommended.
B. Produce a final surface that is uniform in texture and meets the line and grade
specified. Before final acceptance of the Project or during the progress of the
work, the Engineer will determine the thickness of all courses. Repair or replace
all unsatisfactory work.
C. Assure density and thickness meets the plans and specifications. During
compaction, preliminary tests to aid in controlling the thickness, may be
performed by inserting a flat blade, correctly graduated, through the material to
the top of the previously placed base, or by other approved methods.
D. In checking compacted depth, the cutting of the test holes, refilling with
acceptable materials and proper compaction may be performed by the Owners
testing agency.
E. For testing the surface on all courses, a 10-foot (3 m) straightedge will be used
with the centerline of the straightedge placed parallel to the roadway centerline.
Section 02510
ASPHALT CONCRETE PAVEMENT
Page 18 of 21
Montana Public Works Standard Specifications,
Sixth Edition, April, 2010
(DJ&A, P.C. revisions included)
F. Any variations that exceed 5/16-inch (0.8 cm) in 10 feet (3 m) for base course and
1/4-inch (0.64 cm) in 10 feet (3 m) for surface course must be corrected. Correct
irregularities that may develop before the completion of rolling by loosening the
surface mix and removing or adding materials as is required. If any irregularities
or defects remain after the final compaction, remove the surface course and place
and compact new material to a true and even surface. All minor surface
projections, joints and minor honeycombed surfaces must be rolled smooth to
grade, as directed.
B. Materials failing to meet the tests specified may be retested if approved and as
directed by the Engineer. The Contractor shall pay the costs of any required re-
testing for acceptance purposes. Re-testing will be performed by the Owners
testing agency unless otherwise approved by the owner. If there is a dispute, a
third party testing firm may be retained by the contractor for additional retesting
for the Engineers review and consideration.
E. The field density and thickness of the pavement is determined by measuring the
cores tested. The actual thickness must be no less than 1/4-inch (6.5 mm) from
the specified thickness.
F. When the measurement of any core is less than the plan thickness by more than
the allowable deviation, the actual thickness of the pavement in this area may be
determined by taking additional cores at intervals of parallel to the centerline in
Section 02510
ASPHALT CONCRETE PAVEMENT
Page 19 of 21
Montana Public Works Standard Specifications,
Sixth Edition, April, 2010
(DJ&A, P.C. revisions included)
each direction from the affected location. Continue in each direction until a core
is found which is not deficient by more than the allowable deviation. The
Engineer will evaluate areas found deficient in thickness and determine which
areas warrant removal. Remove and replace the areas with asphaltic concrete of
the thickness shown on the plans. Additional coring is considered as re-testing of
failing areas.
4.1 MEASUREMENT
1. Measure asphalt paving mixture by the ton (2000 pounds) including the
asphalt. The quantities measured for payment are the amount of asphalt
paving materials actually used in the completed and accepted work in
accordance with the plans and specifications. To measure asphalt concrete
pavement, provide a commercial or project weighing system meeting
requirements as outlined in Section 02231 Trail Excavation 4.1.
4.2 PAYMENT
A. The accepted quantities will be paid for at the contract unit price per unit of
measurement as reflected in the bid schedule.
END OF SECTION
Section 02510
ASPHALT CONCRETE PAVEMENT
Page 20 of 21
Montana Public Works Standard Specifications,
Sixth Edition, April, 2010
(DJ&A, P.C. revisions included)
SECTION 02236
PART 1: GENERAL
1.1 DESCRIPTION
1.2 REFERENCES
AASHTO T11 Amount Finer than No. 200 (0.075 mm) Sieve in Aggregate
AASHTO T90 Determining the Plastic Limit and Plasticity Index of Soils
Section 02236
STABILIZED RECYCLED ASPHALT PAVEMENT (RAP) BASE COURSE
Page 1 of 8
Montana Public Works Standard Specifications,
Sixth Edition, April, 2010
(DJ&A, P.C. revisions included)
2. In-place field density tests for quality assurance are at Owner expense
meeting AASHTO T191 (ASTM D1556) Sand Cone method or
AASHTOT310 (ASTM ( D6938) Nuclear Densometer method. Quality
assurance field density testing frequency is at the discretion of the
Engineer.
1. Moisture density curves will be provided by the Contractor for each base
material provided. These will be provided at the expense of the
Contractor.
1. Submit to the Engineer gradations, moisture density curves and other test results
for sources to be used for base materials prior to delivery to the site for approval
by the Engineer.
2.1 GENERAL
A. Consists of both fine and coarse fragments of RAP (milled pavement), and/or
natural gravel if required due to shortage of milled pavement.
B. Use 100 percent RAP as provided by the owner. The primary stockpile of
recycled asphalt pavement material available to the contractor is located at
[ADDRESS OF STOCKPILE]. This stockpile was created in [DATE].
2.3 GRADATION
A. As determined by AASHTO Methods T11 and T27, furnish material meeting the
requirement below:
Section 02236
STABILIZED RECYCLED ASPHALT PAVEMENT (RAP) BASE COURSE
Page 2 of 8
Montana Public Works Standard Specifications,
Sixth Edition, April, 2010
(DJ&A, P.C. revisions included)
TABLE OF GRADATIONS
PERCENTAGES BY WEIGHT PASSING SQUARE MESH SIEVE
Passing
D. That portion of the fine aggregate passing the No. 200 sieve must be less than 60
percent of that portion passing the No. 40 sieve.
E. The liquid limit for that portion of the fine aggregate passing a No. 40 sieve
cannot exceed 25, nor the plasticity index exceed 6, as determined by AASHTO
T89 and T90.
2.5 WATERING:
2.6 EQUIPMENT
Section 02236
STABILIZED RECYCLED ASPHALT PAVEMENT (RAP) BASE COURSE
Page 3 of 8
Montana Public Works Standard Specifications,
Sixth Edition, April, 2010
(DJ&A, P.C. revisions included)
in the Plans or as directed by the Engineer. This machine shall have automatic
depth and cross-slope controls and maintain a constant cutting depth. The
automatic depth controls shall maintain the cutting depth to within plus or minus
inch of the depth shown on the Plans. The Road Reclaimer shall be fitted with
equipment capable of adequately mixing the RAP material while injecting the
base stabilizing agent water mixture as detailed in the Mixing/Injecting portion of
this specification. The equipment shall provide a positive means for accurately
controlling the rate of flow and total delivery of the base stabilizing agent water
mixture in relation to the speed of the reclaiming machine and quantity of
material being blended. The injection system shall accurately and uniformly add
the specified percent of water to the binder. The equipment shall be fitted with a
sampling nozzle to provide field samples of the base stabilizing agent water
mixture.
C. Water Additive Systems- The Reclaimer shall be equipped with a system capable
of adding stabilizer/water mixture for material compaction, from bulk tankers,
directly into the mixing chamber.
D. Controls for Liquid Additive Systems- All pumps shall be separately controlled
by the automatic system in the operators cabin. During automatic operation, the
system will allow liquids to be added only when the machine is in motion.
G. There shall be a system allowing the operator to verify that the nozzles on the
spray bars are open and working from the operators cabin.
H. There shall be provided a gallon per minute gauge to indicate instantaneous flow.
PART 3: EXECUTION
Section 02236
STABILIZED RECYCLED ASPHALT PAVEMENT (RAP) BASE COURSE
Page 4 of 8
Montana Public Works Standard Specifications,
Sixth Edition, April, 2010
(DJ&A, P.C. revisions included)
3.1 GENERAL
A. Before placing the RAP base course layer, smooth, shape, and compact the
surface of the underlying subgrade to the cross section shown on the plans before
placing the base course. The subgrade shall be compacted to a minimum of 90
percent of ASTM D1557, or 95 percent of ASTM D698. In areas where the
trail is to be constructed on existing highway embankment, the contractor
will not use vibratory rolling methods to compact the subgrade. If the
contractor is experiencing difficulty achieving compaction of the subgrade
utilizing non-vibratory methods, the contractor will notify the Engineer who
will determine alternative compaction methods.
B. Do not place base course on a wet or muddy subgrade. Complete at least one area
of finished and accepted subgrade before the placing of any base course layer.
A. Deposit and spread each load of material on the prepared subgrade continuously
without interruption. Discontinue operating haul units over subgrade if the haul
units damage the subgrade.
B. Deposit and spread the material in a uniform layer, without segregation, to a loose
depth so that when compacted, and making allowance for the stabilizer to be
blended on the road, the layer has the specified 4-inch thickness.
D. Construct each layer meeting these requirements. Blade smooth and thoroughly
compact each layer as specified before placing the succeeding layer.
F. Uniformly add water, when required, on site and place in amounts required to
compact the material as necessary to aid in densification and to limit segregation.
Maintain an adequate water supply during the work. Assure the equipment used
for watering is of the capacity and design to provide uniform water application.
G. Apply water during the work to control dust and to maintain the base course in a
damp condition in accordance with Section 01500 under Dust Control.
Section 02236
STABILIZED RECYCLED ASPHALT PAVEMENT (RAP) BASE COURSE
Page 5 of 8
Montana Public Works Standard Specifications,
Sixth Edition, April, 2010
(DJ&A, P.C. revisions included)
H. Water required for compacting base gravel may be obtained from the municipal
system if approved by the owner, or from other sources.
A. The RAP base material shall be blended to in one operation so that the entire mass
of material is uniformly blended/mixed. Depending on the width of the reclaimer,
it may take more than one pass horizontally to cover the entire width of the trail.
B. The blended RAP material shall meet the previous gradation requirements listed
under Materials. In the event that the reclamation process extends slightly into the
existing sand and gravel fill layer, up to approximately 5 percent oversize
particles (greater than 2 inches in size) will be allowed in the final base layer
product.
C. During the stabilization operation the Contractor shall physically dig down,
approximately every 1000 feet to check the blending depth and visually verify
that a 4-inch stabilized depth is being achieved. Additional depth verifications
will be performed by the owner representative at intervals determined by the
engineer.
D. The reclaimer shall have the capacity to uniformly inject the stabilizing agent and
water mixture through the reclamation machine into the stabilized layer in one
pass. Spraying the product onto the surface or on windrows is not allowed.
G. The contractor shall utilize a vibratory steel drum roller capable of producing 250
lbs/in of drum width or a pneumatic tired roller (self propelled or towed) having a
compacting width of 5 feet or more and sufficient mass to provide 100-250 lbs./in
of rolling width. In areas where the trail is to be constructed on existing
highway embankment, the contractor will not use vibratory rolling methods
to compact the subgrade. If the contractor is experiencing difficulty
achieving compaction of the subgrade utilizing non-vibratory methods, the
contractor will notify the Engineer who will determine alternative
compaction methods..
H. During the compaction process, the contractor shall provide sufficient water so
the stabilized mixture will be at +/- 2 percent of the optimum moisture content per
ASTM D698. If a nuclear density gauge is used to determine the in-situ density
and moisture content, care should be taken to correct for the asphalt content of the
Section 02236
STABILIZED RECYCLED ASPHALT PAVEMENT (RAP) BASE COURSE
Page 6 of 8
Montana Public Works Standard Specifications,
Sixth Edition, April, 2010
(DJ&A, P.C. revisions included)
stabilized material. All stabilized material shall be blended, spread, watered,
compacted, and shaped, by the end of each workday.
I. Following stabilization and prior to paving, the contractor shall maintain the
reclaimed surface so it is free of ruts, washboards, and potholes. This may require
application of water and using a scarifying blade on a road grader. Stabilized
material with a wash board surface condition shall be scarified to a depth below
that lowest surface of the wash boarded area and recompacted immediately prior
to paving. This work shall be performed at no additional cost to the Owner. Any
costs associated with maintaining this surface is incidental to Stabilized Recycled
Asphalt Pavement (RAP) Base Course.
J. The contractor shall allow the stabilized layer to cure for a minimum of 10
calendar days prior to paving. Depending on the product used, traffic might be
allowed to travel on the surface upon completion of compaction. Should the
treated surface be exposed to significant rainfall (more than 4 hours of continuous
rainfall per day) during the recommended 10-day cure period, the reclaimed
material should be allowed a minimum of one additional dry day (no rainfall) to
cure for each day where rain fell for more than 4 hours.
K. Prior to paving, water shall be applied when directed by the engineer for dust
control.
A. The base course surface when finished and tested with a 10-foot straight edge
placed on the surface with its center line parallel to the center line of the street,
will not have a surface deviation more than 0.02 feet (0.6 centimeters) at any
point from the staked elevations, and the sum of the deviations from two points
not more than 30 feet (9.0 meters) apart cannot exceed 0.02 feet (0.6 centimeters).
4.1 MEASUREMENT
1. Measure recycled asphalt pavement base course in its final compacted and
treated position. Compute the quantity using the average end areas
multiplied by the horizontal distance along a centerline or reference line
between the end areas. Deduct any quantity outside the designed or staked
limits. Do not measure the treatment of the base course or haul separately.
Section 02236
STABILIZED RECYCLED ASPHALT PAVEMENT (RAP) BASE COURSE
Page 7 of 8
Montana Public Works Standard Specifications,
Sixth Edition, April, 2010
(DJ&A, P.C. revisions included)
Treatment and haul are considered incidental to the construction of the
base course layer.
4.2 PAYMENT
A. The accepted quantities will be paid for at the contract unit price per unit of
measurement as reflected in the bid schedule.
END OF SECTION
Section 02236
STABILIZED RECYCLED ASPHALT PAVEMENT (RAP) BASE COURSE
Page 8 of 8
APPENDIX G