REQUEST FOR INSPECTION NOTICES

Cut off : 07-Jul-17


Date Time Inspection Status Result (Date)
Ready for Inspectio
Package inspection Postpone to n done
No RFI no. Description Location Contractor Package No. Inspector OUI JV From Until From Until (Y/N) new date (Y/N) Accepted Rejected Witnessed Reviewed Remarks

0014-0301-4110-
166 Concrete pouring for DCT Slab cover 1.7x1 #120 to 143 4110 0014 23-May-17 10:00
203

0014-0301-4110-
167 Pre concrete and concrete pouring for wall sump #28 4110 0014 23-May-17 10:00
204

0014-0301-4110-
168 Pre concrete and concrete pouring for precast sump wall #27 4110 0014 23-May-17 10:10
205

0014-0301-4110-
169 Post concrete for precast IDB 213 4110 0014 23-May-17 15:00
206

0014-0301-4110-
170 concrete pouring precast IDB 213 4110 0014 23-May-17 15:00
207

0014-0301-4110-
171 Pre concrete and concrete pouring for precast sump base 1A & 1B 4110 0014 23-May-17 10:45
208

0014-0301-08A-
172 Demolish of road RO7 6900-08A 0014 23-May-17 10:00
168

0014-0301-08A-
173 Pre concrete and concrete pouring for EDB 810 & 809 6900-08A 0014 23-May-17 10:00
169

0014-0301-08A-
174 Concrete pouring for pipe support 1st lift K708, K709 & K710 6900-08A 0014 23-May-17 10:30
170

0014-0301-4800- Pre concrete and concrete pouring for wall pipe sleeper K040
175 4800 0014 23-May-17 10:15
181 gridline 049

Pre concrete and concrete pouring for precast footing


0014-0301-4800-
176 miscellaneous pipe support PLT K056 (2 nos), K055 (3 nos), K027 (2 4800 0014 23-May-17 10:15
182
nos), K056

Pre concrete and concrete pouring for precast footing


0014-0301-4800-
177 miscellaneous pipe support PS K704, K622, K622A, K701, K702, 4800 0014 23-May-17 10:15
183
K706, K700, K708, K705, K707

0014-0301-4800-
178 Post installation for precast AOC manhole 4800 0014 23-May-17 15:00
184

0014-0301-6210- Concrete pouring for 1st lift pedestal pipe rack K0004 gridline A &
179 6210 0014 23-May-17 10:35
019 B

0014-0301-4850- Concrete pouring for 1st lift pedestal pipe rack K012 gridline B 1 &
180 4850 0014 23-May-17 10:40
017 2

Cube crushing test for concreting of shear key culvert no 11,


0014-0301-TEST- concreting of sump #19,20,21,22,23 & 24, 1st lift pedestals
181 holcim 0014 23-May-17 10:00
CUBE-4157 K652,K627,K639 & K651, sump wall 37, slab cover #95,to 119 (4110
area), IDB 210 & IDB 211 #345723 - 7 days

Cube crushing test for Concreting of wall of anchor sleeper K144


line 225-226, 2nd lift pedestal of rack K009 line J,K,L,M,N (01D
0014-0301-TEST-
182 area), Footing of meter station pipe sleeper K185 no 1&2 & K186 holcim 0014 23-May-17 10:00
CUBE-4158
no 1-3, wall of sump no DWG 170 (TCF area), wall of anchor sleeper
K154 line 183-184 (01C area) # - 7 days
Date Time Inspection Status Result (Date)
Ready for Inspectio
Package inspection Postpone to n done
No RFI no. Description Location Contractor Package No. Inspector OUI JV From Until From Until (Y/N) new date (Y/N) Accepted Rejected Witnessed Reviewed Remarks

0014-0301-TEST- Cube crushing test for Slab of MSTW U3600 gridline 133-138 (01B
183 holcim 0014 23-May-17 10:30
CUBE-4162 area) #334329 & #234939 - 28 days

0014-0301-01D- Pre concrete and concrete pouring for wall of pipe sleeper K161
190 01D 0014 23-May-17 14:00
042 line 222

0014-0301-01D- Pre concrete and concrete pouring for footing of pipe sleeper K167 line
191 01D 0014 23-May-17 14:00
043 224

0014-0301-01D- Pre concrete and concrete pouring for footing and tie beam of
192 01D 0014 23-May-17 14:00
044 anchor sleeper K151 line 240-241

0014-0301-01D- Pre concrete and concrete pouring for footing and tie beam of pipe
193 01D 0014 23-May-17 14:00
045 rack RCK K009 line A

0014-0301-01D-
194 Pre installation for steam trap pit No 18 & 19 01D 0014 23-May-17 14:00
046

0014-0301-01A-
195 Pre installation for RC pipe culvert No 201 1A 0014 23-May-17 14:30
504

0014-0301-01C- Pre concrete and concrete pouring for slab of MSTW U3300
196 01C 0014 23-May-17 14:30
273 (connection to MSTW RC Box No 5)