You are on page 1of 4

Development of a heuristic algorithm to design stand-alone microgrids for rural

electrification projects considering distributed generation


Fredy Caizares Oriol Gomis
(fredy.canizares@microenergy-international.com) (oriol.gomis@upc.edu)
Research Group MicroEnergy Systems Universitat Politcnica de Catalunya
Technische Universitt Berlin, Berlin, Germany Barcelona, Spain
Hannes Kirchhoff Matteo Ranaboldo
(hannes.kirchhoff@microenergy-international.com) (matteo.ranaboldo@upc.edu)
Research Group MicroEnergy Systems Universitat Politcnica de Catalunya
Technische Universitt Berlin, Berlin, Germany Barcelona, Spain

Abstract Nevertheless, big efforts have been made separately on


Electricity supply in rural areas by means of renewable the optimal design of urban distribution networks
energy based microgrids has been advocated as a (Gilvanejad et al., 2007).
sustainable solution to increase the access to electricity in In (Ranaboldo et al., 2014), a design model is
developing countries. Due to the challenges linked to their presented, where the electrical network and generation
design, several tools are available to facilitate their system are designed, but based on a single generation
planning stage. Even though widely used tools have been
successfully utilized in multiple electrification projects, they point for each microgrid. To our knowledge, there are no
do not design the electrical network of the microgrid and tools capable of designing both the generation system and
do not consider multiple generation points. A proper design the electrical network of the microgrid, considering
of these aspects could greatly contribute to the distributed generators (multiple generation points within a
sustainability of the project and to keep an adequate single microgrid), leaving aside the multiple potential
electrical behavior of the microgrid. For this reason, this benefits of such scheme.
study presents a heuristic algorithm to design solar energy-
based microgrids, considering distributed generation. The
algorithm is capable of designing both the electrical Research Objectives
network and multiple generation points. Moreover, the Taking into consideration the high level of complexity
algorithm is validated by comparing its results to different of planning and designing RE-based microgrids, which
scenarios, based on standard design approaches.
involve distributed generators (DGs), and the evident gap
Keywords: microgrid, distributed generation. on the research of models that facilitates the design
process, this study aims at making a contribution by
Introduction proposing a heuristic algorithm capable of designing
Worldwide, 1.3 billion people lack access to electricity, microgrids based on solar energy, considering DG for
out of which 84% are located in rural areas (IEA, 2011a). rural areas while minimizing the investment set by the
To achieve the objectives of Sustainable Energy for All required equipment. The algorithm was designed based on
(SE4ALL) by 2030, efforts must be made towards the a combination between Reduction and Monte Carlo
universal access to modern energy, improvements in Methods, where the space of solutions is firstly restricted
energy efficiency and increase of the share of renewable in order to simplify the problem, so that in a later stage,
energies. Having such targets, it is clear that small off- the search can be better performed.
grid applications play an essential role. Specifically, it is As the goal is to ease the design process, the algorithm
estimated that mini- and microgrids will have to provide is able to solve the number and location of DGs, as well
around 40% of the new power capacity required to as the topology of the microgrid. Additionally, to properly
achieve universal modern energy access by 2030 (IEA, size the DGs considering the local conditions in order to
2010). cover the power demand, the optimal number and type of
In general, the design of off-grid systems based on each device can be found. .
renewable energy technologies (RETs) is characterized by
a high complexity (IEA, 2011b). Furthermore, when the Methods
design of the electrical network is considered, finding the
cost effective solution becomes a problem difficult to Architecture of the algorithm
overcome. Consequently, several tools have been Unlike the design process of islanded microgrids based
developed to support to design process. Some of the most on centralized generation, when planning microgrids
widely used tools in off-grid projects are HOMER, based on distributed generation, the process becomes
RETScreen and Hybrid 2. These tools have been validated more demanding and complex due to the inclusion of
in multiple rural electrification projects worldwide (Longe additional variables such as size, number and locations of
et al., 2014), greatly simplifying the design process. multiple DGs, each one affecting the electrical behavior of
However, they do not generally consider the design of the the microgrid. In consequence, the planning becomes a
electrical network, but rather just focus on the challenging optimization problem with additional
optimization of the generation system of the microgrid.
variables where several criteria must be satisfied to each microgrid. This step allows the algorithm to
achieve stability, losses and costs reduction. substantially reduce the solution space of the problem
The solution hereby proposed consists of a heuristic composed by the possible number of DGs and their
algorithm designed to define the location of the DGs locations and focus the next phases to the reduced search
within a microgrid, as well as the sizing of the required zone.
components for the generation points (i.e. PV arrays, Each possible number of DGs contains a local optimum
charge controllers, bank of batteries, inverters) and the that differs from the other alternatives, as illustrated in
configuration of the radial AC electrical network to Figure 2. Its value is given by the optimal mix of devices
minimize the up-front cost of the microgrid. Such up-front that bring the lowest investment and, to a lesser extent, by
cost is given by the investment required for the the location of the DGs, as long as it is ensured that they
components of the generation points. Hence, the are properly distributed. Therefore, by selecting the
algorithm builds the different microgrids considering their amount of DGs that can produce the lowest overall
geographical locations and electric demand, the local solar investment, it is possible to greatly reduce the solution
resource and a pre-defined set of commercial components. space. For example, the reduction of the search space to
The proposed algorithm is structured in three main the scenarios produced by installing two and n-1 DGs
phases, as shown in Figure 1. (See Figure 2) focuses the search on areas with more
probabilities of having the lowest investment costs.
It is important to point out that the modularity of the
components of the generation system has big effects on
the up-front costs of each alternative, highly depending on
the available capacities of the commercial components
and their associated costs. Hence, higher costs can emerge
from using many smaller DGs than a few bigger ones to
supply the same demand, or vice versa. Following this
idea, the algorithm chooses the best alternatives based on
the assumptions of the estimation, by calculating the
required cost of using each potential amount of DGs.

Figure 1: Main phases of the proposed algorithm.


The description of each phase is shown next.
Phase 1: Initial solution construction
The initial solution construction begins with the
selection of a first generation point from the overall set of Figure 2: Representation of the solution space.
consumption points. Such selection is done based on the
demand indicator proposed in (Ranaboldo et al., 2013), This is achieved considering that a certain number of
aimed at evaluating the demand concentration around a DGs can equally contribute to cover the demand and, thus
single point. have similar power capacities. Therefore, their power
Once the initial point is selected, the algorithm tries to capacities can be calculated by splitting the demand into
extend the microgrid to its closest consumption points, the total number of DGs plus the contribution on losses,
considering the maximum voltage drop allowed in the which at this stage are assumed as a certain percentage of
network, estimated from the initial point. When the next the overall demand. Using these capacities, the required
possible connection produces a voltage drop beyond the investment is calculated according to the costs of the
acceptable limits, the microgrid is finished and a new available commercial components.
initial point is selected. The procedure is repeated until all Once the cost per DG is calculated, the overall
the points belong to a microgrid or until all points are investment necessary for a certain amount of DGs can be
analyzed. Consequently, the output of this stage is the set derived, allowing for the selection of the best alternatives
of different microgrids that can be formed from a given by the assumptions. At this point, the algorithm
centralized perspective, while keeping their maximum assumes a low sensitivity of the investment cost to the
voltage drops within the limits. location of the DGs, which is ensured in the next phases
by focusing on the scenarios close to the optimal among
Phase 2: Distributed generation incorporation the ones considered.
Starting with the microgrids formed in the previous After the selection of the potential number of DGs,
phase, the next step consists of the optimal location for different scenarios can be simulated, where multiple
the DGs within the microgrids. However, it is important locations are assessed for each microgrid built in Phase 1.
to firstly determine how many DGs should be installed in This is achieved by integrating into the algorithm a power
flow, giving robustness and reliability to the solutions algorithm was applied to a case study. The case study
considered in later stages. Therefore, the assessment of selected is an electrification project in Sonzapote, a rural
the DGs locations permits the accurate selection of community located in Nicaragua. This is a pilot project
candidate solutions that comply with the voltage drop aimed at boosting the governmental investment on RE
limit, low power losses, feasibility of implementation and solutions, to increase the rural electrification rates in the
reactive power constraints. Furthermore, it calculates the country.
total power that each DG must supply on the scenarios The project includes 33 non-electrified households and
considered on each microgrid. one church. For this reason, the energy and power demand
The power flow method selected is an improved version had to be estimated based on similar projects implemented
of the Backward/Forward Sweep due to its simplicity, in the region. The estimation showed a base energy and
flexibility, robustness and computational efficiency when power demand per house of 240Wh/day, and 195W
solving radial networks (Zhang et al., 2009). This method respectively, considering one inhabitant per house and an
was improved from its original version to handle PV increment of 45 Wh and 15W per person for multiple
nodes, which corresponds to the appropriate model of the inhabitants. For the case of the church, the energy and
solar energy-based DGs on this study. Hence, the power demand are 1500 Wh/day and 900 W respectively.
generation points were considered as PQ nodes, while an The minimum solar irradiance reaching the community
injection/absorption of reactive power is performed in occurs in November, corresponding to 4.7kWh/m2. As
each iteration, so that the voltage levels at the generation mentioned before, the proposed algorithm requires a set of
nodes are controlled and kept close to the nominal. potential commercial devices to be used in the generation
Finally, the sizing of the DGs is carried out for each system and electrical network to carry out the necessary
scenario, where the components of the generation system calculations and decision-making. In Table 1, the
are sized according to the results of the power flow equipment considered is presented, taking into account
described above. Therefore, the algorithm solves the local prices. Additional electrical parameters such as
optimal number and type of components based on a set of efficiencies, temperature constants and security margins
commercial components, minimizing the overall were also considered. Additionally, a maximum voltage
investment. Such calculation links each scenario with its drop of 7% was set as a constraint.
respective investment, so that the cheapest solution within
Table 1: Equipment alternatives for the Case Study.
the analyzed scenarios can be selected for each microgrid.
Inverters Capacity [W] Cost [USD]
Phase 3: Microgrid expansion Type 1 200 46
During the Phase 3, the algorithm tries to expand each Type 2 300 70
microgrid, by interconnecting it with the neighboring Type 3 400 92.5
ones. This stage builds bigger networks and avoids Type 4 1500 444
sudden separation of consumers in densely populated Batteries Capacity [Wh] Cost [USD]
areas, separations that might otherwise be caused by the Type 1 1290 325.47
voltage drop limitations considered in Phase 1. This phase Type 2 2520 693.21
takes advantage of the improvements of the voltage PV Modules Capacity [Wp] Cost [USD]
profile produced by the incorporation of the DGs, Type 1 55 359
allowing the microgrids to be further expanded. For this Type 2 150 800
reason, each potential connection among microgrids is Type 3 250 1002
ensured to comply with the electrical constraints of Charge Controllers Capacity [W] Cost [USD]
voltage drop, feasibility and reactive power limits. Type 1 72 92.5
Moreover, new location scenarios are assessed in order to Type 2 300 400
find alternatives that bring to a lower investment when Type 3 540 721
connecting both microgrids, rather than keeping them
The solution proposed by the algorithm is presented in
disconnected.
Figure 3. As it can be seen, for the rural community in
If the connection between two microgrids under the
Sonzapote, two independent microgrids were built.
cheapest feasible scenario produces a lower investment
Microgrids 1 and 2 supply energy to a demand of 6.1kW
cost than having both microgrids isolated, the connection
and 2.8kW respectively (PF=0.9). Furthermore, two DGs
is confirmed, repeating the procedure with the remaining
supply the required energy by each microgrid, and are
connections. Consequently, at the end of this stage, the
located as indicated in Figure 2. It can be noted that the
different microgrids are ensured to have the lowest costs
DGs in Microgrid 2 are located close to each other, while
among the considered scenarios. Furthermore, the optimal
in Microgrid 1 the opposite occurs. Such results are linked
number and types of the commercial components of each
to the fact that Microgrid 1 has a higher power demand
DG that cover the demand are also calculated, including
and length, which would require more dispersed DGs to
the cables of the electrical network.
avoid higher voltage drops and losses. This effect is not as
relevant in Microgrid 2 due to its lower overall power
Results demand. As well, since the algorithm tries to set similar
In the previous sections, the proposed heuristic sizes to the DGs and bigger microgrids that tend to have
algorithm to design stand-alone microgrids based on solar higher load distribution variations on their different
energy, considering distributed generators, was presented. branches, the algorithm is forced to distribute the DGs so
To test it, properly analyze and compare it, the heuristic that they can similarly contribute to cover the demand.
It is important to point out that the algorithm selects a contributing to the sustainability of the project. As it was
low number of DGs due to the cheaper USD/Watt presented, a proper design of the electrical network and
normally involved when selecting bigger equipment. location of the DGs can also achieve additional cost
However, limitations in the maximum number of devices savings, as well as further benefits of this configuration.
can change the decision towards more expensive ones.
The construction of two microgrids instead of one is Discussion
related to the cost of the cable required to connect them, This study presented a heuristic algorithm to design
as well as to the voltage drop constraints, and the low stand-alone microgrids based on solar energy and
savings linked to the new configuration possibilities when considering distributed generation. It is capable of
having a bigger microgrid in this case. designing the electrical network of the microgrid as well
The initial investment of the electrification project as the multiple generation systems, given the geographical
proposed by the algorithm, considering PV modules, location of the consumers and a set of commercial
inverters, charge controllers, bank of batteries, and cables, components to use in the project. The results showed that
was calculated to be USD 61,510. In order to properly the solution proposed by the algorithm for the Case Study
compare this result, but also due to the lack of similar is cheaper than the solution given by standard design
models, the same electrification project was designed for approaches. Moreover, it includes the advantages of
two common approaches widely used in rural changing the paradigm to a decentralized generation
electrification projects. within the microgrids improving their electrical behavior
and reliability, highly contributing to the sustainability of
the project.
The algorithm hereby presented is part of an ongoing
research that aims at filling the existing gap presented in
the design models of RE based microgrids using DG.
Aspects related to the integration of SHS in the solutions
or DC-based microgrids that can be more suitable under
certain conditions, as well as new approaches such as
swarm electrification (Groh, S. et al., 2014) are within
the scope of the research.

References
Gilvanejad, M., Ghadiri, H., Shariati, M. R., Farzalizadeh, S.,
& Arefi, A. (2007). A novel algorithm for distribution network
Figure 3: Solution proposed for the Case Study. planning using loss reduction approach. In Power Engineering
Conference, 2007. AUPEC 2007. (pp. 16).
The first one considers all the consumers being supplied International Energy Agency. (2010). World Energy Outlook.
by SHS, which means that there is no interconnection www.worldenergyoutlook.org/media/weo2010.pdf
between them. The second scenario is based on an International Energy Agency. (2011a). Energy for All:
islanded microgrid supplied by a single generation point Financing Energy Access for the Poor. Retrieved from
(centralized scheme) supplied a PV system. These http://www.iea.org/papers/2011/weo2011_energy_for_all.pdf
International Energy Agency.(2011b).Worldwide overview of
scenarios were designed based on the same design criteria
design and simulation tools for hybrid PVsystems(PVPS T11).
and commercial components presented above to make Longe, O. M., Ouahada, K., Ferreira, H. C., & Chinnappen, S.
them comparable. The results of the total required initial (2014).Renewable Energy Sources microgrid design for rural
investment of each scenario is presented in Table 2. area in South Africa.Innovative Smart Grid Technologies
Table 2: Comparison between the solution costs of Conference,2014IEEEPES(pp.15).
Lotveit, M., Suul, J. A., Tedeschi, E., & Molinas, M. (2014).
different scenarios.
A study of biomass in a hybrid stand-alone Micro-Grid for the
Scenarios Cost [USD] Difference rural village of Wawashang, Nicaragua. In 2014 Ninth
Proposed Algorithm 61,510 -- International Conference on Ecological Vehicles and Renewable
Solar Home Systems 73,221 -19% Energies (EVER) (pp. 17).
Centralized generation 63,364 -3% Orhan,T.,Shafiullah,G.M., Stojcevski, A., & Oo, A. (2014). A
feasibility study on microgrid for various Islands in Australia.
As it can be seen, the algorithm produced a solution PowerEngineering Conference,2014AustralasianUniversities,pp.18
19% cheaper than using SHS for all the consumers in Ranaboldo, M., Ferrer-Mart, L., Garca-Villoria, A., & Pastor
Sonzapote, reflecting important savings for the project. Moreno, R. (2013). Heuristic indicators for the design of
On the other hand, when compared to the solution community off-grid electrification systems based on multiple
following a centralized configuration, the required renewable energies. Energy 50, 501512
investment is 3% cheaper. It is important to point out that Ranaboldo, M., Garca-Villoria, A., Ferrer-Mart, L.,Pastor
these three solutions represent different topologies. Moreno, R.(2014).A heuristic method to design autonomous
Therefore, the advantages and disadvantages of using village electrification projects with renewable energies.Energy
73, 96-109.
each one differ. On this sense, by using a decentralized Zhang, L., Tang, W., & Guan, H. (2009). The back/forward
scheme within the microgrid the reliability of supply as sweep-based power flow method for distribution networks with
well as the voltage profile of the microgrid can be greatly DGs.In2009 2nd International Conference on Power Electronics
enhanced, improving the service given to the consumers and Intelligent Transportation System(Vol.1,pp. 145149).

You might also like