Before raising the counter claim, the Respondents wish to present the
necessary background of the dispute as also the scope of work as per the RFP,
the LOA and the clarification sought and tendered in the pre-bid conference
and the guidelines under IPDS Scheme of MOP with respect to Single
Software license for the entire State.
It is submitted that some delay in presentation of the counter claim in the
Arbitration proceeding is occasioned by Petition submitted to the
Respondents on behalf of the claimant seeking amendment in the prayer
portion vide Petitions submitted on 22.05.2017 which required deliberation at
the end of Respondents. Subsequently, the claimant held meeting on
26.05.2017 and 04.07.2017 and submitted letter dated 06.07.2017 regarding
withdrawal of the prayer clause on payment from the Arbitration.
The initial claim couples with the two Petitions were examined before
submitting the counter claim.
Before submitting the stand of the Power Company strictly based on RFP and
the allied documents being separately filed as Volume II, the background of
the project and dispute may be permitted to be placed as follows:
2. The Programme
Programme consists of Part-A covering Information Technology
application in theelectricity distribution system and Part B covering the
System strengthening, improvementand augmentation of distribution system
capacity. The focus of the programmeis on actual, demonstrable
performance in terms of loss reduction. Establishmentof reliable and
automated systems for sustained collection of accurate base linedata, and the
adoption of Information Technology in the areas of energy accountingwill
be essential for the success of the R-APDRP.
The Programmewas proposed to be implemented on all India basis
covering Towns andCities with a population of more than 30,000 (10,000 in
case of Special CategoryStates) as per population data of 2001 Census.
The GIS licensing should cover viewing rights to all users and
edit/deletion/addition rights to one identified authorized user at
Electric Supply Division level in both the Distribution companies of
BSPHCL.
All the licenses shall be owned by BSPHCL even after the end of
period of 5 years from the date of GO- LIVE.
The GIS licensing should cover viewing rights to all users and
edit/deletion/addition rights to one identified authorized user at
Electric Supply Division level in both the Distribution companies of
BSPHCL.
All the licenses shall be owned by BSPHCL even after the end of
period of 5 years from the date of GO- LIVE.
The stand of the Power Company that enterprise wide license under
the RFP is to apply for non RAPDRP towns as well stands confirmed by the
PFC which has issued guidelines for the IPDS scheme. It clearly says that
license procured under RAPDRP Project would be good for other areas of
the State hence there is no requirement for further software licenses. The
said guidelines may be reproduced as hereunder:
i. That license cost for entire Bihar has been considered in the
floated tender document for RAPDRP Part-A project. Hence
M/s Reliance Infrastructure has to provide all the software
licenses (Central Software) for entire Bihar without any
additional cost to the utility for central software licenses.
ii. Utility has estimated the cost of central software licenses based
on the cost quoted by the M/s Reliance Infrastructure, the
estimated cost of central software for Non-RAPDRP part is
Rs.102,50,74,660/- (Rupees One hundred two Crore fifty lacs
seventy four thousand six Hundred and sixty only).
iii. Present consumer count in R-APDRP towns is 15,00,000. The
software cost per consumer has been derived to Rs. 123/- on the
basis of total cost of software given by M/s Reliance
Infrastructure in price bid and total number of consumers, this
unit cost of software has been derived by dividing the total cost
of software by total no. of consumers. Presently, total no. of
consumers in Non- RAPDRP area is 83,24,930. The total
software cost required for Non-RAPDRP consumers is Rs (123
x 83,24,930) i.e. Rs102,50,74,660. In this cost it is assumed that
the AMC cost is included in the quoted by M/s Reliance-
Infrastructure. The detailed is given below:-