You are on page 1of 2

GROUND & SLOPE STABILISATION 29

On contaminated land
A recent foundation
project in So Paulo,
Brazil, encountered
heavily contaminated
soils. Ground
Engineering
Operations (GEOs) G3
system helped contain
the contamination
during drilling using
stabilisation slurry,
writes Jorge Frade
new residential building between 3m and 9m depth from immediate impact on the cost of

A
D-wall excavation
is being developed in So street level was contaminated the project. The excavated soil and casting
Paulo by Gafisa, one of with benzene, a known carcino- would require specific disposal
Brazils largest real-estate and genic compound, as well as other procedures that included special
construction companies. The pro- toxic hydrocarbons. The contami- transportation and using specific
jects foundation design included nated soil from that layer, after sites willing to accept contami-
a total of 1,332m3 of diaphragm the excavation to install the nated soils. These sites not only
walls (D-walls) and barrettes; the D-walls and barrettes, could not accept these soils but apply
thickness of the D-walls and bar- be disposed of as it was, and specific treatments to them.
rettes ranged from 400mm to had to be separated for special Considering that the cost of
1,000mm, with an average depth treatment. physical or chemical treatment
of 23m for the D-walls and 33m An effort had to be made for this kind of contaminated soil
for the barrettes. to assure that uncontaminated in Brazil can range from US$40
The company that installed the layers were kept intact, due to to US$200 per tonne of soil, in Identifying
foundation elements was Drilling the high cost of treating benzene- addition to the regular disposal benzene
do Brasil. The main challenge contaminated soil. This is where costs, the direct costs of soil and other
faced by the foundation contrac- GEOs main stabilisation polymer, disposal for the project could
tor was that the building is being Polymud, came into play. have increased at least sevenfold. contamin-
erected on the previous site of The D-walls and barrettes had ants in
a gas station. SOIL CHARACTERISATION to be installed using stabilisation the layer
Due to leakage from the fuel Soil-contamination studies of the fluid, which could cause the
between
storage tanks, the soil layer site were conducted by CGA, a contaminated water in the soil to
lab that specialises in environmen- interact with the free water in the 3m and
tal and geological issues, stabilisation fluid. This contamina- 9m had an
in order to identify the types of tion would then be transmitted to immediate
elements present in the soil, if any. the slurry, and as a consequence,
The following substances were to the rest of the excavated soil,
impact on
identified: benzene, ethylben- increasing the already high costs the cost of
zene, xylene and toluene (BTEX), of soil disposal. the project
the most relevant being the Accordingly, the stabilisation
benzene. slurry solution had to prevent this
According to Brazilian law, for from happening.
soil to be considered contami- Basically, the stabilisation slurry
nated with benzene, its isocon- properties should not be affected
centration in underground water by the contaminating elements
circulating in the soil should be found in the soil and jeopardise
higher than 5g/L. Here, values the excavation stabilisation. On
of >1,000g/L were registered. top of all of this, the average
concrete overbreak could not
CHALLENGES AND GOALS surpass 15% without affecting
Identifying benzene and other the structural integrity of the BETEX and PAH
contaminants in the layer concrete poured into the dia- sampling and
between 3m and 9m had an phragm walls and barrettes. testing

April 2017
30 GROUND & SLOPE STABILISATION

The exposed above the maximum allowed for


D-walls normal soil disposal, the exam-
ined soil layers would be classi-
fied as a Class II contaminated
soil, and be transported to a
special treatment plant.
Samples for testing were made
on all the excavations in the
following soil intervals: 1-3m,
3-6m, 6-9m and 9-20m.
As for GEO, quality control is
always performed on the execu-
tion of each foundation element,
with particular focus on D-wall/
barrette integrity and excavation
POLYMUD The properties of the slurry stabilisation.
Polymud is a highly concentrated were adjusted to neutralise Besides verifying and guaran-
polymer and has been specifically and isolate the contaminating teeing that the slurry parameters
designed to interact chemically, elements from having a negative were kept according to GEOs
GEO after being properly hydrated/ effect on the performance of the specifications, a viscosity check
mixed with water, with different Polymud stabilisation slurry. on a sample of the used slurry
estimates types of soil. The slurry was adjusted on site was made when reaching 50% of
that by During this project, adjust- to follow even stricter specifica- the project depth of the excava-
preventing ments were made to the concen- tions than the project require- tion, to guarantee that the
the conta- tration of Polymud in a given ments and local laws demanded. contaminant elements werent
volume of slurry, to prevent free affecting the slurry stabilisation
mination of water in the slurry, which in turn CONTROL AND TESTING characteristics.
all the other decreased the risk of passing the The CGA lab was responsible for A variation of )5s between the
existing contaminating elements into the monitoring the contaminating fresh slurry sent to the excavation
slurry. This strategy helps isolate elements throughout the project, and a sample of the slurry from
layers of the contamination and prevents and verifying that the soil contami- the bottom of the excavation,
soil, the it from spreading. nation was kept isolated and after reaching 50% of design
project Another big consideration within boundaries. The work depth, was considered regular.
achieved relied on slurry membrane focused on measuring and If the variation was >5s, it would
development over the excavation detecting 6 BTEX and 16 PAH be necessary to check for the
savings of sidewall, yielding a water- (polycyclic aromatic hydrocarbons) presence of contaminant ele-
at least repellent effect that prevents in all soil and surroundings. All ments in the slurry.
US$44,500 the infiltration of groundwater areas with contaminated soil were In addition, because GEOs
into the slurry column, once kept isolated until collection. slurry is reusable through the
again preventing the spread If the presence of any of these entire project, an analysis of the
of the contaminating elements. elements was in concentrations presence of contaminants in the
slurry is required before the
Project results disposal of the slurry at the end
of the project. If any of the
For the entire project, in every layer ranging from 3m to 9m depth. contaminating elements were
excavation, the contaminating Average concrete overbreak of present in the slurry, a special
elements were contained in the the foundation elements for this treatment of the slurry would also
project was 8.37%. be necessary.
Slurry viscosity monitoring
proved that the slurry didnt lose CONCLUSION
its properties while in the presence Considering the average specific
of the contaminating elements. weight of the soil in wet condi-
Analysis of the contaminating tions on this site, GEO estimates
elements in the slurry at the end that by preventing the contami-
Slurry samples of the project proved that the slurry nation of all the other existing
to test for was within specifications for disposal layers of soil, the project
contaminants in local water-collection points. achieved savings of at least
US$44,500.

Jorge Frade is technical team leader at Ground Engineering Operations

April 2017

You might also like