Professional Documents
Culture Documents
# Question
A project team budgeted $3000 for the work performed and has spent $4000, to
1 date. If they budgeted $5000 for the work schedule, what is the cost variance (CV)?
You are tracking your project using earned value management (EVM) and find you
are behind schedule but under budget. Your variances showed schedule variance
(SV) = -$50 million, cost variance CV = $100 million, and your actual cost are $500
2 million. What are the CPI, PV, and SPI?
9 During which project management process group are budget forecast created?
11 In Which parts of the cost management process is earned value (EV) used?
Aggregation, reserve analysis, and expert judgment are OLD tools of which
12 process?
The project budget is proving to be inaccurate. The SPI is 1.1 the team has had
negative deviation from the activity attributes and the sponsor has inserted her
self on the change control board. What is the BEST thing for the project manager to
13 do.?
A project manager has run into cost difficulties. The project scope must be
14 completed, but at lest cost. The project manager should:
After analyzing the status of your project, you determine the earned value (EV) is
lower than the planed value (PV). What should you expect as and outcome if this
15 trend continues?
What would be the BEST explanation for the following: Both the cost variance and
the schedule variance are negative but the cost variance is lower than the schedule
17 variance
18 Which of the following is a KEY way to improve activity cost estimates?
A project manager has completed a detailed WBS and cost estimates for each work
19 package. To create a cost baseline from this data, the project manager will:
Your boss is worried about the project schedule. There is a critical deliverable due
to the federal government in two weeks. If you miss the deliverable, you could lose
the entire contract. To help previous the boss`s stress, you show him the end value
calculations you just completed. They show your cost performance index (CPI) is
1.25. Your actual cost (AC) is $400 million, and your planed value (PV) is $490
20 million. Should your boss be comfortable?
A B C
0.92, $550 million, 1.2 1.20, -$100 million, 0.92 1.20, $650 million, 0.92
Anticipated total cost at project Anticipated expenses at project Estimated average cost and
completion completion project completion
Estimate activity resources Vendor bid analysis Analogous estimating
Creating the cost baseline and Reserve analysis and cost Performance measurement and
the cost control system aggregation variance management planning
The actual cost will be lower The project will finish behind The project will finish below
than planned the schedule the original cost estimate
The WBS level at which earned The budget and how they were
value will be calculated How resources are allocated calculated
Yes, your CPI is 1.05 No, your CPI is too high He needs more data
D Answer
$2,000 C
AC + (BAC-EV) C
Determine budget D
EV-PV D
Executing B
Fixed C
A question like this is the reason you need to understand what each term means in common
terminology. CV = EV - AC. Here, EV is $3,000, AC is $4,000, so cost variance is $3,000 - $4,000 =
($1,000).
First find EV = CV + AC = $600. Calculate CPI = EV/AC = $600/$500 = 1.20. Next, to find PV, you would
use the formula PV = EV - SV = $650. Now you can compute SPI = EV/PV = 600/650 = 0.923.
The value of work completed relates to the cost performance index. A measure of progress achieved
relates to the schedule performance index. AC + (BAC - EV) is a formula for EAC. (BAC - EV)/(BAC -
AC) is the formula for TCPI and is therefore the correct response. This formula divides the work
remaining to be done by the money remaining to do it.
Hiding the reserve is an inappropriate action. Adding cost to each activity will not shorten the
critical path, and thus is an incorrect statement. Management reserves, not contingency reserves,
are maintained by management to cover cost overruns. During the risk management process, you
determine appropriate contingency reserves to cover the cost of identified risks.
Estimate at completion means the total cost of the project at completion, based on current
information.
Earned value (EV) minus planned value (PV) equals schedule variance (SV).
Budget forecasts are an output of Control Costs, which is part of monitoring and controlling.
Fringe benefits are included in overhead and are part of indirect costs.
Creating the cost baseline and the cost control system, reserve analysis, and cost aggregation occur
during project planning. Earned value is not used for reserve analysis or cost aggregation. It is used
in forecasting and project performance reviews.
Aggregation is only used in the Determine Budget process, to roll up work package costs to control
account costs and finally to project costs. The other tools listed are used in Determine Budget as
well as in other processes. This is a case where you must understand the purpose of each tool to
correctly answer the question.
How can changing the depreciation affect the total cost of the project? A benefit cost ratio is too
vague to help eliminate specific project costs. Sunk costs are expended costs and can never be
recovered.The project manager should perform a value analysis, looking for less costly ways to
complete the work.
If earned value is lower than planned value, it indicates less work is occurring than was scheduled,
resulting in schedule slippage.
The exam will ask you what the tools of project management contain in order to test whether you
really understand them. The cost management plan identifies the WBS level at which earned value
will be calculated.
Remember, for variances, negative is bad. In this situation, both the variances are negative. To
answer the question, first look at which of the four choices exhibit negative variances for both cost
and schedule. Since the project underspent because all work was not completed, but overspent for
work that was done, both the cost and schedule variances are negative.
Analogous estimating and gaining expert opinions of project cost should have been completed
before the finalization of the cost baseline. A cost baseline does not include management reserves.
However, it must include a contingency reserve for risks. The project manager must total the work
package estimates and risk contingency reserve estimates to create the cost baseline.
Although the SV is $10 million, this does not indicate all the activities are proceeding on schedule.
You need to find out if the activities leading up to the critical deliverable are on schedule, in order to
comfort your boss. Remember that earned value management (EVM) is a way to discover trends or
indications of the way the project is going. You need to examine the details to be sure. You cannot
determine schedule problems based on the CPI. The SPI is 1.02, not 1.05, but this does not tell you
all the activities are proceeding on schedule. To find SV and SPI you must first find EV. EV = CPI x AC
= 1.25 x $400M = $500M. So SV = EV - PV = $500M - $490M = $10M and SPI = EV / PV = $500M /
$490M = 1.020 (use 3-decimal place accuracy).