You are on page 1of 6

ANALISA HARGA SATUAN

Jenis Pekerjaan : Lapisan ATB


Satuan Pembayaran : Ton
No.
URAIAN KEGIATAN SAT. KOEFFISIEN HARGA SATUAN JUMLAH
( Rp. ) ( Rp. )
1 2 3 4 5 6=45

1 Mandor Jam 0.0613 8,571.43 525.43


2 Pekerja Jam 0.4293 4,571.43 1,962.51
3 Agregat Kasar m3 0.7028 175,200.00 123,130.56
4 Agregat Halus m3 0.5341 173,880.00 92,869.31
5 Filter Kg 139.2000 1,350.00 187,920.00
6 Aspal Curah Kg 157.0000 7,300.00 1,146,100.00
7 Sewa Asphatt Mixing Plant Jam 0.0613 3,800,000.00 232,940.00
8 Sewa Wheel Leader 10-15 HP Jam 0.0421 482,502.02 20,313.34
9 Sewa Dump Truck 8-10 m3 Jam 0.5429 65,000.00 35,288.50
10 Sewa Asphatt Finisher Jam 0.0767 856,725.00 65,710.81
11 Sewa Todem Roller Jam 0.0476 223,436.00 10,635.55
12 Sewa Tire Roller Jam 0.0356 226,360.00 8,058.42
13 Sewa Alat Bantu set 1.0000 1,000.00 1,000.00

HARGA SATUAN PEKERJAAN / M3 1,926,454.42


HARGA SATUAN PEKERJAAN / TON 844,936.15
DIBULATKAN 844,930.00

Jenis Pekerjaan : Lapisan AC


Satuan Pembayaran : m2
No.
URAIAN KEGIATAN SAT. KOEFFISIEN HARGA SATUAN JUMLAH
( Rp. ) ( Rp. )
1 2 3 4 5 6=45

1 Mandor Jam 0.0024 8,571.43 20.66


2 Pekerja Jam 0.0241 4,571.43 110.17
3 Agregat Kasar m3 0.0336 175,200.00 5,886.72
4 Agregat Halus m3 0.0149 173,880.00 2,590.81
5 Filter Kg 4.8015 1,350.00 6,482.03
6 Aspal Curah Kg 6.6150 7,300.00 48,289.50
7 Sewa Asphatt Mixing Plant Jam 0.0024 3,800,000.00 9,158.00
8 Sewa Wheel Leader 10-15 HP Jam 0.0016 482,502.02 772.00
9 Sewa Dump Truck 8-10 m3 Jam 0.0385 65,000.00 2,502.50
10 Sewa Asphatt Finisher Jam 0.0030 856,725.00 2,570.18
11 Sewa Todem Roller Jam 0.0018 223,436.00 402.18
12 Sewa Tire Roller Jam 0.0025 226,360.00 565.90
13 Sewa Alat Bantu set 1.0000 1,000.00 1,000.00

HARGA SATUAN PEKERJAAN 80,350.65


DIBULATKAN 80,350.00
Jenis Pekerjaan : Pengecatan Marka Jalan dengan Thermoplastic ( teb. 2mm)
Satuan Pembayaran : M2
No.
URAIAN KEGIATAN SAT. KOEFFISIEN HARGA SATUAN JUMLAH
( Rp. ) ( Rp. )
1 2 3 4 5 6=45

1 Mandor Jam 0.0140 8,571.43 120.00


2 Operator Jam 0.0140 5,000.00 70.00
3 Pengemudi / sopir Jam 0.0140 5,000.00 70.00
4 Pekerja / buruh tak terampil Jam 0.0275 4,571.43 125.71
5 Thermoplastic kg 2.8000 27,000.00 75,600.00
6 Glass beed kg 0.5000 40,000.00 20,000.00
7 Cargo truck 5,0 ton jam 0.0500 109,814.52 5,490.73
8 Road marking machine jam 0.0500 41,600.00 2,080.00

HARGA SATUAN PEKERJAAN 103,556.44


DIBULATKAN 103,555.00

Jenis Pekerjaan : Lapisan Aspal Pengikat ( Tack Coat)


Satuan Pembayaran : Lt
No.
URAIAN KEGIATAN SAT. KOEFFISIEN HARGA SATUAN JUMLAH
( Rp. ) ( Rp. )
1 2 3 4 5 6=45

1 Mandor Jam 0.0030 8,571.43 25.71


2 Pekerja Terampil Jam 0.0201 4,571.43 91.89
3 Aspal Curah Kg 0.8894 7,300.00 6,492.62
4 Minyak Tanah Ltr 0.2530 7,000.00 1,771.00
5 Sewa Aspal Spatyer Jam 0.0030 23,000.00 69.00
6 Sewa Compresor Jam 0.0063 75,000.00 472.50
7 Sewa Dump Truck 8-10 m3 Jam 0.0030 65,000.00 195.00

HARGA SATUAN PEKERJAAN 9,117.72


DIBULATKAN 9,115.00
DAFTAR HARGA SATUAN ALAT & BAHAN

Nama Kegiatan : #REF!


Nama Pekerjaan : #REF!
Lokasi : #REF!

NO. URAIAN SATUAN

1 Batu pecah mesin 0,5/1 cm m3


2 Batu pecah mesin 1/2 cm m3
3 Batu pecah mesin 2/3 cm m3
4 Batu pecah mesin (3/5 cm) dan (4/6 cm) m3
5 Batu kali pecah 15/20 cm m3
6 Batu Pecah 2/3 Cm m3
7 Aspal panas AC 60/70 ( termasuk angkutan ) kg
8 Aspal Curah kg
9 Agregat Kasar m3
10 Agregat Halus m3
11 Filler kg
12 Kawat Ikat Beton kg
13 Besi Beton Polos kg
14 Kayu Menganti ( Bekesting ) m3
15 Paku kg
16 Batu Krikil Beton m3
17 Pasir Pasang m3
18 Minyak Tanah lt
19 Sewa alat bantu ( 1 set @ 3 alat ) Set
20 Sewa aspal finisher ( min. 3 jam ) jam
21 Sewa aspal sprayer ( min. 4 jam ) jam
22 Sewa pneumatic tire roller ( min. 5 jam ) jam
23 Sewa tandem roller ( min. 5 jam ) jam
24 Sewa compresor ( min. 5 jam ) jam
25 Sewa dump truck 5 T ( min. 5 jam ) jam
26 Sewa dump truck 8-10 jam
27 Sewa motor grader 125-140 pk ( min. 5 jam ) jam
28 Sewa truck tanki air ( min. 5 jam ) jam
29 Sewa walles ( min. 5 jam ) jam
30 Sewa Aspal Mixing Plant jam
31 Sewa Vibarator Roller ( min. 5 Jam) jam
32 Sewa Generator Set jam
33 Sewa Wheel Loader 10-15 HP jam
34 Sewa Concrete Mixer 0,5 m3 jam
35 Biaya gilas perkerasan dengan tebal 15-20 cm m
36 Thermoplastic Kg
37 Glass beed Kg
38 Road marking machine Jam
39 Gedeg Guling m2
40 Cargo truck 5,0 ton Jam
41 Got Talang R.15 ( segmen ) Bh
42 Got talang R.25 ( segmen ) Bh
43 Paving Abu-abu Tb. 6 cm ( 4 persegi Pj. ) Bh
DAFTAR HARGA SATUAN ALAT & BAHAN

Nama Kegiatan : #REF!


Nama Pekerjaan : #REF!
Lokasi : #REF!

NO. URAIAN SATUAN

44 Paving Abu-abu Tb. 8 cm ( 4 persegi Pj. ) Bh


45 Stoper / Topi Uskup Merah tb. 6 cm Bh
46 Stoper / Topi Uskup Merah tb. 8 cm Bh
47 Batu Bata Bh
48 Bambu Bongkotan dia. 8-12 cm ; Pj. 2,5 m Btg
49 Bambu Ori dia. 10-12 cm ; Pj. 3 m Btg
50 Kastin Trap uk.15.25.40 m1
51 Pasir Cor m3
52 Sement PC ( Portland Cement ) 50 Kg Zak
53 Pasir Urug m3
54 Tasirtu m3
55 Sewa Crane 30 T - min 8 jam Jam

DAFTAR HARGA SATUAN UPAH

Nama Kegiatan : #REF!


Nama Pekerjaan : #REF!
Lokasi : #REF!

NO. URAIAN SATUAN

1 Mandor Orang Hari


2 Pekerja Terampil Orang Hari
3 Pekerja / Buruh Tak Terampil Orang Hari
4 Operator Orang Hari
5 Pembantu Operator Orang Hari
6 Tenaga Pemasak Aspal Orang Hari
7 Sopir Orang Hari
8 Pembantu Sopir Orang Hari
9 Kepala Tukang batu Orang Hari
10 Tukang batu Orang Hari
11 Kepala Tukang Besi Orang Hari
12 Tukang Besi Orang Hari
13 Kepala Tukang Kayu Orang Hari
14 Tukang kayu Orang Hari
15 Masinis Orang Hari
16 Pembantu masinis Orang Hari
HARGA SATUAN

Rp 173,880.00
Rp 175,200.00
Rp 171,240.00
Rp 164,400.00
Rp 131,894.00
Rp 171,240.00
Rp 2,832.00
Rp 7,300.00
Rp 175,200.00
Rp 173,880.00
Rp 1,350.00
Rp 15,350.00
Rp 12,500.00
Rp 1,636,000.00
Rp 11,040.00
Rp 114,000.00
Rp 110,000.00
Rp 7,000.00
Rp 1,000.00
Rp 856,725.00
Rp 23,000.00
Rp 226,360.00
Rp 223,436.00
Rp 75,000.00
Rp 65,000.00
Rp 65,000.00
Rp 270,000.00
Rp 70,000.00
Rp 80,000.00
Rp 3,800,000.00
Rp 135,000.00
Rp 235,950.00
Rp 482,502.02
Rp 50,000.00
Rp 9,200.00
Rp 27,000.00
Rp 40,000.00
Rp 41,600.00
Rp 29,500.00
Rp 109,814.52
Rp 19,250.00
Rp 24,050.00
Rp 950.00
HARGA SATUAN

Rp 1,200.00
Rp 4,000.00
Rp 5,000.00
Rp 300.00
Rp 15,500.00
Rp 21,600.00
Rp 40,600.00
Rp 115,000.00
Rp 56,000.00
Rp 94,400.00
Rp 87,850.00
Rp 150,000.00

HARGA SATUAN

Rp 60,000.00
Rp 35,000.00
Rp 32,000.00
Rp 35,000.00
Rp 32,000.00
Rp 35,000.00
Rp 35,000.00
Rp 32,000.00
Rp 50,000.00
Rp 40,000.00
Rp 50,000.00
Rp 35,000.00
Rp 50,000.00
Rp 40,000.00
Rp 40,000.00
Rp 30,000.00

You might also like