You are on page 1of 43

NEPAL ELECTRICITY AUTHORITY

(An Undertaking of Government of Nepal)

TRANSMISSION DIRECTORATE

(A component of Power Transmission and Distribution Efficiency


Enhancement Project

BIDDING DOCUMENT
FOR
Procurement of Plant for Gas Insulated 220 kV Barhabise Substation (Design, Supply,
Install and Commission)

Single-Stage, Two-Envelope
Bidding Procedure

Issued on: .
Invitation for Bids No.: ICB-TD-TKTLP073/74 - 02
ICB No.: ICB-TD-TKTLP073/74 - 02
Employer: Nepal Electricity Authority
Country: Nepal

VOLUME III OF III

May 2017

Tamakoshi-Kathmandu 220/400 kV Transmission Line Project


Transmission Directorate, NEA Training Center Complex
Kharipati, Bhaktapur, Nepal

Telephone: +977-1-6620016
Contract.
Fax: +977-1-6620016
SCHEDULE - 1 PAGE 1 OF 12
NEPAL ELECTRICITY AUTHORITY
TRANSMISSION DIRECTORATE
Tamakoshi-Kathmandu 220/400 kV Transmission Line Project
IFB No. : ICB-TD-TKTLP-073/74-02: Design, Supply, Installation and Commissioning of Gas Insulated 220 kV Barhabise Substation

Schedule No.1: Plant and Equipment including Mandatory Spares to be supplied from abroad
FC: Foreign Currency LC: Local Currency

CIP (site) including insurance, clearing,


Total Amount
forwarding and transportation to site Custom, VAT and
Estimated (Excluding Taxes
Item Country of (Excluding Taxes and Duties applicable other taxes
Item description and Duties)
No. origin in Nepal)
FC FC LC
Quantity Unit
Currency# Unit Rate Amount
1 2 3 4 5 6 7 8 = (7) x (4) 9=8 10
I 220/132/11 kV GIS Barhabise Substation
PART - A: OWNER ASSESSED QUANTITIES
A POWER TRANSFORMER
53.33MVA, 220/3 / 132//3 kV Single Phase Power Transformer
a) 4 Nos.
(without transformer Oil)
b) Insulating oil for the above Power Transformer 4 Lot
c) 33kV Current transformer (NCT) for autotrasnformer 1 No
d) Oil Storage tank of 20KL 2 Nos.

B POWER TRANSFORMER
5 MVA, 132 /11 kV Three Phase Power Transformer (without
a) 1 Nos.
transformer Oil)
b) Insulating oil for the above Power Transformer 1 Lot

C) LT Transformer
a) 630KVA 11/0.400 Kv 2 Nos.

D 245 KV EQUIPMENTS
D1 245KV GIS Equipment
1.1 245kV, SF6 GIS Bus Bars Module as per section project 2 Sets
1.2 245kV, SF6 GIS Bus Coupler feeder bay Module as per section project
1 Sets
1.3 245kV, SF6 GIS Line feeder bay Module as per section project 4 Sets
1.4 245kV, SF6 GIS spare Line feeder bay Module as per section project
2 Sets
1.5 245kV, SF6 GIS ICT feeder bay Module as per section project 1 Sets
1.6 SF6 Gas Insulated Bus Duct (GIB) outside GIS Hall alongwith
associated support structure and accessories
a) OPTION-I
SCHEDULE - 1 PAGE 2 OF 12
CIP (site) including insurance, clearing,
Total Amount
forwarding and transportation to site Custom, VAT and
Estimated (Excluding Taxes
Item Country of (Excluding Taxes and Duties applicable other taxes
Item description and Duties)
No. origin in Nepal)
FC FC LC
Quantity Unit
Currency# Unit Rate Amount
1600A, 40kA for 1 sec. Single Phase 240 Mtr.
OPTION-II
1600A, 40kA, 1sec three phase 80 Mtr.
Note : Bidder is required to quote for either option-I or Option-II
b) 1600A, 40kA for 1 sec. Single Phase ( for 4X53.33 MVA 1 ph
60 mtr
Transformer)
1.7 220kV, SF6 to Air Bushing alongwith associated support structure

a) 1600A, 40kA for 1 sec. Single Phase 16 Nos.


1.8 245kV, SF6 GIS Auxiliary Bus Module as per section project to
1 set
connect spare unit of Transformer
D.2 245KV Outdoor Equipment
1.1 216 KV Surge Arrester (1-phase) 16 Nos.
1.2 4400pF, 245 kV Capacitive Voltage Transformer (1-Phase) 12 Nos.
1.3 245kV Bus Post Insulator (1-Phase) (Except for wave trap) 12 Nos.

E 145kV Equipment
E.1 145KV GIS Equipment
1.1 145kV, SF6 GIS Bus Bars Module as per section project 2 Sets
1.2 145kV, SF6 GIS Bus Coupler feeder bay Module as per section project
1 Set
1.3 145kV, SF6 GIS Line feeder bay Module as per section project 2 Sets
1.4 145kV, SF6 GIS Spare Line feeder bay Module as per section project
1 Sets
1.5 145kV, SF6 GIS ICT feeder bay Module as per section project for
1 Sets
220/132 kV Transformer
1.6 145kV, SF6 GIS ICT feeder bay Module as per section project for
1 Sets
132/11 kV Transformer
1.7 SF6 Gas Insulated Bus Duct (GIB) outside GIS hall including Bus Duct
support structure and associated accessories
a) 1250A, 31.5kA, 1sec three phase 50 Mtr
b 1250A, 31.5 kA 1sec single phase (for 4x53.33MVA 1-Phase
30 Mtr
Transformer bays)
1.8 145kV, SF6 to Air Bushing alongwith associated support structure

a) 1250A, 31.5kA, 1sec single phase 13 Set


1.9 145kV, SF6 GIS Auxiliary Bus Module as per section project to
1 set
connect spare unit of Transformer
SCHEDULE - 1 PAGE 3 OF 12
CIP (site) including insurance, clearing,
Total Amount
forwarding and transportation to site Custom, VAT and
Estimated (Excluding Taxes
Item Country of (Excluding Taxes and Duties applicable other taxes
Item description and Duties)
No. origin in Nepal)
FC FC LC
Quantity Unit
Currency# Unit Rate Amount
E.2 145kV EQUIPMENT(AIS)
1.0 120 kV Surge Arrestors (1-Phase) 13 Nos.
2.0 8800pF, 145 kV Capacitive Voltage Transformer (1-Phase) 6 Nos.
3.0 145KV Bus Post Insulator 6 Nos.

F 11 KV EQUIPMENT
1.0 11 kV Isolator (3-phase)-HDB
i 400A, 25kA for 3 sec, Isolator without E/s (Beam Mounted) 2 Set
2.0 9 kV Surge Arrester (1 ph.) 6 Nos
3.0 11 kV Horn Gap fuse (1 ph.) 6 Nos
4.0 11kV BPI 6 Nos

G 11kV, 25 kA (3 Phase) Indoor switch gear panel


i) 11kV Transformer Module 1 Nos
ii) 11kV LT Transformer Module 1 Nos
iii) Bus PT Module 1 Nos
H Testing & Maintenance Equipment for GIS
1.1 SF6 Gas processing Unit 1 Set
1.2 Partial Discharge Monitoring System 1 Set
1.3 Dew Point Meter 1 Set
1.4 SF6 Gas Leak Detector 1 Set
1.5 Portable Ladder with adustable height as per TS 1 Nos.
1.6 EOT crane for 220kV GIS Hall 1 Set
1.7 EOT crane for 132kV GIS Hall 1 Set

I RELAY PANELS (WITH AUTOMATION)


1 245kV
1.1 Circuit Breaker Relay Panel
a) CB Relay Panel With Auto Reclose 6 Nos.
b) CB Relay Panel Without Auto Reclose 2 Nos.
1.2 Line Protection Panel 6 Nos.
1.3 Transformer Protection Panel (For both HV & MV side) 1 Nos.
1.4 Bus Bar Protection Panel 1 set
2 145kV
1.1 Circuit Breaker Relay Panel
a) CB Relay Panel With Auto Reclose 3 Nos.
b) CB Relay Panel Without Auto Reclose 3 Nos.
1.2 Line Protection Panel 3 Nos.
SCHEDULE - 1 PAGE 4 OF 12
CIP (site) including insurance, clearing,
Total Amount
forwarding and transportation to site Custom, VAT and
Estimated (Excluding Taxes
Item Country of (Excluding Taxes and Duties applicable other taxes
Item description and Duties)
No. origin in Nepal)
FC FC LC
Quantity Unit
Currency# Unit Rate Amount
1.3 Transformer Protection Panel (For both HV & MV side) 1 Nos.
1.4 Bus Bar Protection Panel 1 set
3 Other/Common equipments Pertaining to C & R System
a) Time Synchronisation Equipment 1 No.
a) Relay Test kit 1 No.

J SUBSTATION AUTOMATION
1 Substation Automation System as per Technical Specification:
a) 220kV System 8 Nos.
b) 132 kV System 6 Nos.
c) BCU for auxilary system 1 set
d) 11 kV HT Indoor Switchgear 1 set

K Digital Protection Coupler , PBAX & Wave Trap


a Digital Protection Coupler 16 Nos
b PBAX with following configuration as per TS 1 Set
i 2 wire subscriber interface card with capacity 32 local subscribers
(along with 32 nos. Instruments)
ii 4 wire E & M interface card with capacity 8 nos. trunks (For PLCC)

iii) E-1 interface with 2 trunks G-703


iv) 2 wire interface with 1 trunk (For PSTN)
c) Line Trap
i) 1250A,0.5mH,31.5kA(132 kV) 2 nos
ii) Bus Post Insulator for above 132 kv Wave Trap 6 no.

L LT Switchgear (As per Technical specification)


a 400V Main switchboard 1 Set
b 400V ACDB 1 Set
c 400V MLDB 1 Set
d 400V Emergency LDB 1 Set
e 220V DCDB 2 Sets
g 48V DCDB 2 Set

M Batteries
a 220V
i 600 AH 2 Nos
b 48V
SCHEDULE - 1 PAGE 5 OF 12
CIP (site) including insurance, clearing,
Total Amount
forwarding and transportation to site Custom, VAT and
Estimated (Excluding Taxes
Item Country of (Excluding Taxes and Duties applicable other taxes
Item description and Duties)
No. origin in Nepal)
FC FC LC
Quantity Unit
Currency# Unit Rate Amount
i 600AH 2 Nos

N Float Cum Boost Battery Charger


a 220V Float Cum Boost Battery Charger
i 90A/90A 2 Nos
b 48V Float Cum Boost Battery Charger
i 90A/90A 2 Nos

O Diesel Generator with control Panel


a 250 kVA 1 Set

P Fire Protection System


a Portable /Trolley/Wheel mounted extinguishers
i 9 litre water type 2 Nos
ii 50 litre foam type 2 Nos
iii 4.5 kg CO2 type 6 Nos
iv 4.5 kg Dry Chemical Power (DCP) type 2 Nos
b Smoke detection system 1 Set
c Fire detection and Alarm System 1 Set

Q Cables along with clamps, glands, lugs and straight joints etc.

a 11kV HT Cable alongwith accessories and termination equipments


2.5 KM
b Power Cables - (1.1kV grade)
i 3.5Cx300 sqmm (XLPE) cable for filter Machine along with 2 nos
1 KM
outdoor receptacles -250A

R Air conditioning
High wall type split AC unit of 2 TR capacities for control room, relay
1 25 Nos.
room and battery room

S STEEL STRUCTURES (Tower,Gantry structures& Equipment


support structures)
a Lattice/pipe Structure for towers,beams and equipments including peak
plates/pack washers and guest paltes including foundation
bolts(nuts,washers,MS plate welded at the bottom)
i) Lattice stucture & foundation bolts 100 MT
SCHEDULE - 1 PAGE 6 OF 12
CIP (site) including insurance, clearing,
Total Amount
forwarding and transportation to site Custom, VAT and
Estimated (Excluding Taxes
Item Country of (Excluding Taxes and Duties applicable other taxes
Item description and Duties)
No. origin in Nepal)
FC FC LC
Quantity Unit
Currency# Unit Rate Amount
ii Pipe structure & foundation bolts 22 MT
b Fastners for towers,beams and equipment support strcutures 5 MT

T Communication Equipment
1 Transmission Equipment
SDH Equipment ( STM- 4 MADM, upto 3 MSP protected
A
directions)
Base Equipment (Common cards, Cross-connect/control cards, Optical
base cards, Power supply cards, power cabling, other hardware &
(I) 2 No.
accessories including sub-racks, patch cords, DDF etc. fully equipped
excluding (II) and (III) below)
(II) Optical Interface/SFP# for
a) S4.1 4 Nos.
(a) L4.2 6 Nos.
(III) Tributary Cards
(a) E1 Interface card (Minimum 16 interfaces per card ) 2 Nos.
Ethernet interfaces 10/100 Mbps with Layer-2 switching (Minimum
(b) 4 No.
4 interfaces per card.)
2 Termination Equipment
Drop/Insert Multiplexer
Base Equipment (Common cards, Power supply cards, power cabling,
A1
other hardware & accessories including sub-racks, etc. fully equipped 2 Nos.
excluding subscriber line interface cards)
A2 Subscriber Line Interface Cards
a) 2 wire (sub/sub) voice channel cards (min 8 channels per card) 2 Nos.
b) 4 wire (E&M) voice channel cards (min 8 channels per card) 2 Nos.
c) Asynchronous Sub Channels data cards (minimum 4 channels per card) 2 No.
d) Synchronous data card (NX64kbps) 2 Nos.
3 Equipment Cabinets
a) For Drop/Insert Multiplexer 2 No.
b) For SDH Equipment 2 No.
4 TMN Craft Terminal for SDH & PDH Equipments
(a) Hardware 1 set
(b) Software 1 set
5 Synchronization Equipment
GPS clock including all hardware & accessories 1 set
Main Distribution Frame
6
SCHEDULE - 1 PAGE 7 OF 12
CIP (site) including insurance, clearing,
Total Amount
forwarding and transportation to site Custom, VAT and
Estimated (Excluding Taxes
Item Country of (Excluding Taxes and Duties applicable other taxes
Item description and Duties)
No. origin in Nepal)
FC FC LC
Quantity Unit
Currency# Unit Rate Amount
6
(100 pairs) 2 no
7.0 Test Equipment as per TS 1 set
SUB TOTAL PART-A

PART-B: VENDOR ASSESSED QUANTITIES


Erection Hardware :-Insulator strings, Disc Insulators, Hardware,
conductor, bus-bar materials, cable trays, clamps, spacers, connectors
A including conectors for Auto Transformer , Junction box, earthwire,
earthing material risers, buried cable trenches/pipe of equipment &
lighting, all accessories etc. for the following:
1 220 kV DM-type layout for GIS termination arrangement
1.1 Line Bay 4 Set
1.2 Transformer Bay 1 Sets

2 132 kV DM-type layout for GIS termination arrangement


1.1 Line Bay 2 Sets
1.2 Transformer Bay 2 Sets

3 11 KV 2 SET
Bus post insulators, Spacers, equipment support structures,
conductor(s), Al tube, clamp, connectors required for arrangement of
B Neutral formation for one transformer bank for making connection 1 Sets
arrangement to connect spare unit in place of any other unit without
physical shifting complete in all respect

C Ventilation & heating System


2 Ventilation & heating system (as per technical specification)
(i) 220kV GIS Hall 1 LS
(ii) 132 kV GIS Hall 1 LS

D Illumination System
1.1 Substation Lighting
(i) Control Room cum administrative building illumination 1 LS
(ii) 220kV GIS Building 1 LS
(iii) 132kV GIS Building 1 LS
IV. Indoor Switchyrad Panel Room 1 LS
v Fire Fighting Room 1 LS
vi Outdoor Switchyard Lighting 1 LS
SCHEDULE - 1 PAGE 8 OF 12
CIP (site) including insurance, clearing,
Total Amount
forwarding and transportation to site Custom, VAT and
Estimated (Excluding Taxes
Item Country of (Excluding Taxes and Duties applicable other taxes
Item description and Duties)
No. origin in Nepal)
FC FC LC
Quantity Unit
Currency# Unit Rate Amount
vii Street Lighting 1 LS
viii Occupancy sensor 1 LS
1.2 Township Area Lighting 1 LS

E Fire Protection System per technical Specification)


1 Pumping arrangement inside pump house 1 set
2 Hydrant system outside the Pump House. 1 set
3 HVW spray system & Hydrant system for Transformer :
a 53.33 MVA, 220/132 kV Single Phase Auto Transformer 4 nos
b 5 MVA,132/11 kV Three phase transformer 1 nos

F POWER & CONTROL CABLES


1 1.1 kV LV Cables
1.1 Power Cable(PVC insulated) 1 LS
1.2 Power Cable(XLPE insulated) 1 LS
1.3 Control Cable (PVC insulated) 1 LS
Cable glands, lugs & straight through joints for Power & Control cables
1.4 1 LS

Visual Monitoring System for watch & ward as per technical


G 1 LS
specification

H Earthing and lightning protection including necesaary


connectors/connections, risers etc. complete in all respect
i Earth Conductor (copper) 1 LS
ii Earth Rod (copper clad steel) 1 LS
iii Equipment for lightning protection 1 LS

I SUBSTATION AUTOMATION
a Integration of all 220/132kV Bays under present scope with the 1 LS
SCADA of SIEMENS (SINAUT Spectrum) at Load Dispatch Centre,
Kathmandu including supply of Hardware, Software, accessories etc. as
per TS Section Project.
SUB TOTAL PART-B

PART-C: MANDATORY SPARES (Break up of Lumpsum


quantity shall be as per Annexure-I, Section Project of Technical
Specification).
SCHEDULE - 1 PAGE 9 OF 12
CIP (site) including insurance, clearing,
Total Amount
forwarding and transportation to site Custom, VAT and
Estimated (Excluding Taxes
Item Country of (Excluding Taxes and Duties applicable other taxes
Item description and Duties)
No. origin in Nepal)
FC FC LC
Quantity Unit
Currency# Unit Rate Amount
I. Transformer(220/132 kV) 1 LS
II Transformer(132//11 kV) 1 LS
III. GIS(22O KV & 132 KV) 1 LS
IV 220kV CVT 1 no
V 132kV CVT 1 no
VI 216kV LA 1 no
VII 120kV LA 1 no
VIII DG Set 1 LS
IX Battery Charger 1 LS
X Relay & Protection 1 LS
XI Digital Protection Copler 1 LS
XII Sub-Station Automation System 1 LS
XIII LT Transformer 1 LS
XIV Illumination System 1 LS
XV Erection Hardware 1 LS
XVI Telecommunication Equipments 1 LS
XVII LT Indoor Switchgear 1 LS
XVIII Fire Fighting 1 LS
SUB-TOTAL PART-C
Total for 220/132/11kV BARHABISE Substation (I) (Part-A+ Part-
B+ Part C)

II EXTENSION OF 220 KV KHIMTI S/S


PART -A: OWNER ASSESSED QUANTITIES
A 245 KV EQUIPMENTS
A1 245KV GIS Equipment
1.1 245kV, SF6 GIS Bus Bars Module as per section
2 Sets
project(EXTENSION)
1.2 245kV, SF6 GIS Line feeder bay Module as per section project 2 Sets
1.3 220kV, SF6 to Cable Bushing alongwith associated support structure

a) 2000A, 40kA for 1 sec. Single Phase 6 Nos.


A2 245KV Outdoor Equipment
1.1 216 KV Surge Arrester (1-phase) 6 Nos.
1.2 4400pF, 245 kV Capacitive Voltage Transformer (1-Phase) 6 Nos.
1.3 245kV Bus Post Insulator (1-Phase) (Except for wave trap) 12 Nos.

B Testing & Maintenance Equipment for GIS


SCHEDULE - 1 PAGE 10 OF 12
CIP (site) including insurance, clearing,
Total Amount
forwarding and transportation to site Custom, VAT and
Estimated (Excluding Taxes
Item Country of (Excluding Taxes and Duties applicable other taxes
Item description and Duties)
No. origin in Nepal)
FC FC LC
Quantity Unit
Currency# Unit Rate Amount
1.1 SF6 Gas processing Unit 1 Set
1.2 Partial Discharge Monitoring System 1 Set
1.3 Dew Point Meter 1 Set
1.4 SF6 Gas Leak Detector 1 Set

C RELAY PANELS (WITH AUTOMATION)


1 245kV
1.1 Circuit Breaker Relay Panel
a) CB Relay Panel With Auto Reclose 2 Nos.
1.2 Line Protection Panel 2 Nos.
1.3 Integration of existing Bus Bar Protection 1 set
3 Other/Common equipments Pertaining to C & R System
a) Relay Test kit 1 No.

D SUBSTATION AUTOMATION
Augmentation of Substation Automation System as per Technical
1
Specification:
a) 220kV System 2 Nos.

E Cables along with clamps, glands, lugs and straight joints etc.

a 220 kV grade 1 core, 1200sq.mm.XLPE insulated copper cable as per


1.5 KM
technical specification
b Cable end termination(s) on Gantry as per technical specification 6 nos

F STEEL STRUCTURES (Tower,Gantry structures& Equipment


support structures)
a Lattice Structure for towers,beams and equipments including peak
plates/pack washers and guest paltes including foundation 32 MT
bolts(nuts,washers,MS plate welded at the bottom)
b Fastners for towers,beams and equipment support strcutures 1 MT
SUB TOTAL -PART-A

PART-B: VENDOR ASSESSED QUANTITIES


SCHEDULE - 1 PAGE 11 OF 12
CIP (site) including insurance, clearing,
Total Amount
forwarding and transportation to site Custom, VAT and
Estimated (Excluding Taxes
Item Country of (Excluding Taxes and Duties applicable other taxes
Item description and Duties)
No. origin in Nepal)
FC FC LC
Quantity Unit
Currency# Unit Rate Amount
Erection Hardware :-Insulator strings, Disc Insulators, Hardware,
conductor, bus-bar materials, cable trays, clamps, spacers, connectors
A including conectors for Auto Transformer , Junction box, earthwire,
earthing material risers, buried cable trenches/pipe of equipment &
lighting, all accessories etc. for the following:
1 220 kV DM-type layout for GIS termination arrangement
1.1 Line Bay 2 Set

B POWER & CONTROL CABLES


1 1.1 kV LV Cables
1.1 Power Cable(PVC insulated) 1 LS
1.2 Control Cable (PVC insulated) 1 LS
Cable glands, lugs & straight through joints for Power & Control cables
1.3 1 LS

C Earthing and lightning protection including necesaary


1 LS
connectors/connections, risers etc. complete in all respect
SUB TOTAL PART-B

PART-C: MANDATORY SPARES (Break up of Lumpsum


quantity shall be as per Annexure-I, Section Project of Technical
Specification).
I GIS 1 LS
II 220kV CVT 1 no
III 216kV LA 1 no
IV Digital protecion Coupler 1 LS
V Sub-Station Automation System 1 LS
VI Illumination System 1 LS
VII Erection Hardware 1 LS
VIII Relay & Protection 1 LS
TOTAL PART-C
Total for 220kV KHIMTI Substation (II) (Part-A+ Part-B+ Part
C)
TOTAL (Total of (I) & (II) to be carried forward to Schedule No.
5: Grand Summary)
Note : 1) Bidder is required to quote prices in this Schedule for all the individual items/sub-items.
2.) The Prices of equipments are inclusive of type test charges except for those mentioned in Schedule 4( e)
SCHEDULE - 1 PAGE 12 OF 12
CIP (site) including insurance, clearing,
Total Amount
forwarding and transportation to site Custom, VAT and
Estimated (Excluding Taxes
Item Country of (Excluding Taxes and Duties applicable other taxes
Item description and Duties)
No. origin in Nepal)
FC FC LC
Quantity Unit
Currency# Unit Rate Amount
3.) BOQ given above is indicative only based on the scope of work as given in Project Specific Requirements. The quantities mentioned above may undergo change during detailed engineering
to meet the functional requirement and scope of work defined in Employer's Requirements.
Name of Bidder: Date:
Signature of Bidder:
(Printed Name)
(Designation)
(Common Seal)
SCHEDULE - 2 PAGE 1 OF 11

NEPAL ELECTRICITY AUTHORITY


TRANSMISSION DIRECTORATE
Tamakoshi-Kathmandu 220/400 kV Transmission Line Project
IFB No. : ICB-TD-TKTLP-073/74-02: Design, Supply, Installation and Commissioning of Gas Insulated 220 kV Barhabise Substation

Schedule No. 2: Plant and Equipment including Mandatory Spares Parts to be supplied from within Nepal including Type Test Charges
All prices in local currency, NRs
Ex Faxtory Price (Excluding Total Amount VAT and other
Inland Transportation up to Site Total Amount
Item No. Item Description Quantity Unit VAT) (Excluding Taxes) taxes
Unit Rate Amount Unit Rate Amount
1 2 3 4 5 6 7 8 9 10 11
I 220/132/11 kV GIS Barhabise Substation
PART - A: OWNER ASSESSED QUANTITIES
A POWER TRANSFORMER
53.33MVA, 220/3 / 132//3 kV Single Phase Power
a) 4 Nos.
Transformer (without transformer Oil)
b) Insulating oil for the above Power Transformer 4 Lot
c) 33kV Current transformer (NCT) for autotrasnformer 1 No
d) Oil Storage tank of 20KL 2 Nos.

B POWER TRANSFORMER
5 MVA, 132 /11 kV Three Phase Power Transformer (without
a) 1 Nos.
transformer Oil)
b) Insulating oil for the above Power Transformer 1 Lot

C) LT Transformer
a) 630KVA 11/0.400 Kv 2 Nos.

D 245 KV EQUIPMENTS
D1 245KV GIS Equipment
1.1 245kV, SF6 GIS Bus Bars Module as per section project 2 Sets
1.2 245kV, SF6 GIS Bus Coupler feeder bay Module as per section
1 Sets
project
1.3 245kV, SF6 GIS Line feeder bay Module as per section project
4 Sets
1.4 245kV, SF6 GIS spare Line feeder bay Module as per section
2 Sets
project
1.5 245kV, SF6 GIS ICT feeder bay Module as per section project
1 Sets
1.6 SF6 Gas Insulated Bus Duct (GIB) outside GIS Hall alongwith
associated support structure and accessories
a) OPTION-I
1600A, 40kA for 1 sec. Single Phase 240 Mtr.
SCHEDULE - 2 PAGE 2 OF 11

Ex Faxtory Price (Excluding Total Amount VAT and other


Inland Transportation up to Site Total Amount
Item No. Item Description Quantity Unit VAT) (Excluding Taxes) taxes
Unit Rate Amount Unit Rate Amount
OPTION-II
1600A, 40kA, 1sec three phase 80 Mtr.
Note : Bidder is required to quote for either option-I or Option-II

b) 1600A, 40kA for 1 sec. Single Phase ( for 4X53.33 MVA 1 ph


60 mtr
Transformer)
1.7 220kV, SF6 to Air Bushing alongwith associated support
structure
a) 1600A, 40kA for 1 sec. Single Phase 16 Nos.
1.8 245kV, SF6 GIS Auxiliary Bus Module as per section project to
1 set
connect spare unit of Transformer
D.2 245KV Outdoor Equipment
1.1 216 KV Surge Arrester (1-phase) 16 Nos.
1.2 4400pF, 245 kV Capacitive Voltage Transformer (1-Phase)
12 Nos.
1.3 245kV Bus Post Insulator (1-Phase) (Except for wave trap)
12 Nos.

E 145kV Equipment
E.1 145KV GIS Equipment
1.1 145kV, SF6 GIS Bus Bars Module as per section project 2 Sets
1.2 145kV, SF6 GIS Bus Coupler feeder bay Module as per section
1 Set
project
1.3 145kV, SF6 GIS Line feeder bay Module as per section project
2 Sets
1.4 145kV, SF6 GIS Spare Line feeder bay Module as per section
1 Sets
project
1.5 145kV, SF6 GIS ICT feeder bay Module as per section project
1 Sets
for 220/132 kV Transformer
1.6 145kV, SF6 GIS ICT feeder bay Module as per section project
1 Sets
for 132/11 kV Transformer
1.7 SF6 Gas Insulated Bus Duct (GIB) outside GIS hall including
Bus Duct support structure and associated accessories

a) 1250A, 31.5kA, 1sec three phase 50 Mtr


b 1250A, 31.5 kA 1sec single phase (for 4x53.33MVA 1-Phase
30 Mtr
Transformer bays)
1.8 145kV, SF6 to Air Bushing alongwith associated support
structure
a) 1250A, 31.5kA, 1sec single phase 13 Set
1.9 145kV, SF6 GIS Auxiliary Bus Module as per section project to
1 set
connect spare unit of Transformer
SCHEDULE - 2 PAGE 3 OF 11

Ex Faxtory Price (Excluding Total Amount VAT and other


Inland Transportation up to Site Total Amount
Item No. Item Description Quantity Unit VAT) (Excluding Taxes) taxes
Unit Rate Amount Unit Rate Amount
E.2 145kV EQUIPMENT(AIS)
1.0 120 kV Surge Arrestors (1-Phase) 13 Nos.
2.0 8800pF, 145 kV Capacitive Voltage Transformer (1-Phase)
6 Nos.
3.0 145KV Bus Post Insulator 6 Nos.

F 11 KV EQUIPMENT
1.0 11 kV Isolator (3-phase)-HDB
i 400A, 25kA for 3 sec, Isolator without E/s (Beam Mounted)
2 Set

2.0 9 kV Surge Arrester (1 ph.) 6 Nos


3.0 11 kV Horn Gap fuse (1 ph.) 6 Nos
4.0 11kV BPI 6 Nos

G 11kV, 25 kA (3 Phase) Indoor switch gear panel


i) 11kV Transformer Module 1 Nos
ii) 11kV LT Transformer Module 1 Nos
iii) Bus PT Module 1 Nos
H Testing & Maintenance Equipment for GIS
1.1 SF6 Gas processing Unit 1 Set
1.2 Partial Discharge Monitoring System 1 Set
1.3 Dew Point Meter 1 Set
1.4 SF6 Gas Leak Detector 1 Set
1.5 Portable Ladder with adustable height as per TS 1 Nos.
1.6 EOT crane for 220kV GIS Hall 1 Set
1.7 EOT crane for 132kV GIS Hall 1 Set

I RELAY PANELS (WITH AUTOMATION)


1 245kV
1.1 Circuit Breaker Relay Panel
a) CB Relay Panel With Auto Reclose 6 Nos.
b) CB Relay Panel Without Auto Reclose 2 Nos.
1.2 Line Protection Panel 6 Nos.
1.3 Transformer Protection Panel (For both HV & MV side) 1 Nos.
1.4 Bus Bar Protection Panel 1 set
2 145kV
1.1 Circuit Breaker Relay Panel
a) CB Relay Panel With Auto Reclose 3 Nos.
b) CB Relay Panel Without Auto Reclose 3 Nos.
1.2 Line Protection Panel 3 Nos.
1.3 Transformer Protection Panel (For both HV & MV side) 1 Nos.
1.4 Bus Bar Protection Panel 1 set
SCHEDULE - 2 PAGE 4 OF 11

Ex Faxtory Price (Excluding Total Amount VAT and other


Inland Transportation up to Site Total Amount
Item No. Item Description Quantity Unit VAT) (Excluding Taxes) taxes
Unit Rate Amount Unit Rate Amount
3 Other/Common equipments Pertaining to C & R System
a) Time Synchronisation Equipment 1 No.
a) Relay Test kit 1 No.

J SUBSTATION AUTOMATION
1 Substation Automation System as per Technical Specification:
a) 220kV System 8 Nos.
b) 132 kV System 6 Nos.
c) BCU for auxilary system 1 set
d) 11 kV HT Indoor Switchgear 1 set

K Digital Protection Coupler , PBAX & Wave Trap


a Digital Protection Coupler 16 Nos
b PBAX with following configuration as per TS 1 Set
i 2 wire subscriber interface card with capacity 32 local
subscribers (along with 32 nos. Instruments)
ii 4 wire E & M interface card with capacity 8 nos. trunks (For
PLCC)
iii) E-1 interface with 2 trunks G-703
iv) 2 wire interface with 1 trunk (For PSTN)
c) Line Trap
i) 1250A,0.5mH,31.5kA(132 kV) 2 nos
ii) Bus Post Insulator for above 132 kv Wave Trap 6 no.

L LT Switchgear (As per Technical specification)


a 400V Main switchboard 1 Set
b 400V ACDB 1 Set
c 400V MLDB 1 Set
d 400V Emergency LDB 1 Set
e 220V DCDB 2 Sets
g 48V DCDB 2 Set

M Batteries
a 220V
i 600 AH 2 Nos
b 48V
i 600AH 2 Nos

N Float Cum Boost Battery Charger


a 220V Float Cum Boost Battery Charger
i 90A/90A 2 Nos
SCHEDULE - 2 PAGE 5 OF 11

Ex Faxtory Price (Excluding Total Amount VAT and other


Inland Transportation up to Site Total Amount
Item No. Item Description Quantity Unit VAT) (Excluding Taxes) taxes
Unit Rate Amount Unit Rate Amount
b 48V Float Cum Boost Battery Charger
i 90A/90A 2 Nos

O Diesel Generator with control Panel


a 250 kVA 1 Set

P Fire Protection System


a Portable /Trolley/Wheel mounted extinguishers
i 9 litre water type 2 Nos
ii 50 litre foam type 2 Nos
iii 4.5 kg CO2 type 6 Nos
iv 4.5 kg Dry Chemical Power (DCP) type 2 Nos
b Smoke detection system 1 Set
c Fire detection and Alarm System 1 Set

Q Cables along with clamps, glands, lugs and straight joints


etc.
a 11kV HT Cable alongwith accessories and termination
2.5 KM
equipments
b Power Cables - (1.1kV grade)
i 3.5Cx300 sqmm (XLPE) cable for filter Machine along with 2
1 KM
nos outdoor receptacles -250A

R Air conditioning
High wall type split AC unit of 2 TR capacities for control room,
1 25 Nos.
relay room and battery room

S STEEL STRUCTURES (Tower,Gantry structures&


Equipment support structures)
a Lattice/pipe Structure for towers,beams and equipments
including peak plates/pack washers and guest paltes including
foundation bolts(nuts,washers,MS plate welded at the bottom)

i) Lattice stucture & foundation bolts 100 MT


ii Pipe structure & foundation bolts 22 MT
b Fastners for towers,beams and equipment support strcutures
5 MT

T Communication Equipment
1 Transmission Equipment
SDH Equipment ( STM- 4 MADM, upto 3 MSP protected
A
directions)
SCHEDULE - 2 PAGE 6 OF 11

Ex Faxtory Price (Excluding Total Amount VAT and other


Inland Transportation up to Site Total Amount
Item No. Item Description Quantity Unit VAT) (Excluding Taxes) taxes
Unit Rate Amount Unit Rate Amount

Base Equipment (Common cards, Cross-connect/control cards,


Optical base cards, Power supply cards, power cabling, other
(I) 2 No.
hardware & accessories including sub-racks, patch cords, DDF
etc. fully equipped excluding (II) and (III) below)

(II) Optical Interface/SFP# for


a) S4.1 4 Nos.
(a) L4.2 6 Nos.
(III) Tributary Cards
(a) E1 Interface card (Minimum 16 interfaces per card ) 2 Nos.
Ethernet interfaces 10/100 Mbps with Layer-2 switching
(b) 4 No.
(Minimum 4 interfaces per card.)
2 Termination Equipment
Drop/Insert Multiplexer

Base Equipment (Common cards, Power supply cards, power


A1
cabling, other hardware & accessories including sub-racks, etc. 2 Nos.
fully equipped excluding subscriber line interface cards)

A2 Subscriber Line Interface Cards


a) 2 wire (sub/sub) voice channel cards (min 8 channels per card) 2 Nos.

b) 4 wire (E&M) voice channel cards (min 8 channels per card) 2 Nos.

Asynchronous Sub Channels data cards (minimum 4 channels


c) 2 No.
per card)
d) Synchronous data card (NX64kbps) 2 Nos.
3 Equipment Cabinets
a) For Drop/Insert Multiplexer 2 No.
b) For SDH Equipment 2 No.
4 TMN Craft Terminal for SDH & PDH Equipments
(a) Hardware 1 set
(b) Software 1 set
5 Synchronization Equipment
GPS clock including all hardware & accessories 1 set
Main Distribution Frame
6
(100 pairs) 2 no
7.0 Test Equipment as per TS 1 set
SUB TOTAL PART-A

PART-B: VENDOR ASSESSED QUANTITIES


SCHEDULE - 2 PAGE 7 OF 11

Ex Faxtory Price (Excluding Total Amount VAT and other


Inland Transportation up to Site Total Amount
Item No. Item Description Quantity Unit VAT) (Excluding Taxes) taxes
Unit Rate Amount Unit Rate Amount
Erection Hardware :-Insulator strings, Disc Insulators,
Hardware, conductor, bus-bar materials, cable trays, clamps,
spacers, connectors including conectors for Auto Transformer ,
A
Junction box, earthwire, earthing material risers, buried cable
trenches/pipe of equipment & lighting, all accessories etc. for
the following:

1 220 kV DM-type layout for GIS termination arrangement


1.1 Line Bay 4 Set
1.2 Transformer Bay 1 Sets

2 132 kV DM-type layout for GIS termination arrangement


1.1 Line Bay 2 Sets
1.2 Transformer Bay 2 Sets

3 11 KV 2 SET
Bus post insulators, Spacers, equipment support structures,
conductor(s), Al tube, clamp, connectors required for
arrangement of Neutral formation for one transformer bank for
B making connection arrangement to connect spare unit in place of 1 Sets
any other unit without physical shifting complete in all respect

C Ventilation & heating System


2 Ventilation & heating system (as per technical specification)
(i) 220kV GIS Hall 1 LS
(ii) 132 kV GIS Hall 1 LS

D Illumination System
1.1 Substation Lighting
(i) Control Room cum administrative building illumination 1 LS
(ii) 220kV GIS Building 1 LS
(iii) 132kV GIS Building 1 LS
IV. Indoor Switchyrad Panel Room 1 LS
v Fire Fighting Room 1 LS
vi Outdoor Switchyard Lighting 1 LS
vii Street Lighting 1 LS
viii Occupancy sensor 1 LS
1.2 Township Area Lighting 1 LS
SCHEDULE - 2 PAGE 8 OF 11

Ex Faxtory Price (Excluding Total Amount VAT and other


Inland Transportation up to Site Total Amount
Item No. Item Description Quantity Unit VAT) (Excluding Taxes) taxes
Unit Rate Amount Unit Rate Amount
E Fire Protection System per technical Specification)
1 Pumping arrangement inside pump house 1 set
2 Hydrant system outside the Pump House. 1 set
3 HVW spray system & Hydrant system for Transformer :
a 53.33 MVA, 220/132 kV Single Phase Auto Transformer 4 nos
b 5 MVA,132/11 kV Three phase transformer 1 nos

F POWER & CONTROL CABLES


1 1.1 kV LV Cables
1.1 Power Cable(PVC insulated) 1 LS
1.2 Power Cable(XLPE insulated) 1 LS
1.3 Control Cable (PVC insulated) 1 LS
Cable glands, lugs & straight through joints for Power &
1.4 1 LS
Control cables

Visual Monitoring System for watch & ward as per technical


G 1 LS
specification

H Earthing and lightning protection including necesaary


connectors/connections, risers etc. complete in all respect
i Earth Conductor (copper) 1 LS
ii Earth Rod (copper clad steel) 1 LS
iii Equipment for lightning protection 1 LS

I SUBSTATION AUTOMATION
a Integration of all 220/132kV Bays under present scope with the 1 LS
SCADA of SIEMENS (SINAUT Spectrum) at Load Dispatch
Centre, Kathmandu including supply of Hardware, Software,
accessories etc. as per TS Section Project.

SUB TOTAL PART-B

PART-C: MANDATORY SPARES (Break up of Lumpsum


quantity shall be as per Annexure-I, Section Project of
Technical Specification).
I. Transformer(220/132 kV) 1 LS
II Transformer(132//11 kV) 1 LS
III. GIS(22O KV & 132 KV) 1 LS
IV 220kV CVT 1 no
V 132kV CVT 1 no
VI 216kV LA 1 no
VII 120kV LA 1 no
SCHEDULE - 2 PAGE 9 OF 11

Ex Faxtory Price (Excluding Total Amount VAT and other


Inland Transportation up to Site Total Amount
Item No. Item Description Quantity Unit VAT) (Excluding Taxes) taxes
Unit Rate Amount Unit Rate Amount
VIII DG Set 1 LS
IX Battery Charger 1 LS
X Relay & Protection 1 LS
XI Digital Protection Copler 1 LS
XII Sub-Station Automation System 1 LS
XIII LT Transformer 1 LS
XIV Illumination System 1 LS
XV Erection Hardware 1 LS
XVI Telecommunication Equipments 1 LS
XVII LT Indoor Switchgear 1 LS
XVIII Fire Fighting 1 LS
SUB-TOTAL-C
Total for 220/132/11kV BARHABISE Substation (I) (Part-
A+ Part-B+ Part C)

II EXTENSION OF 220 KV KHIMTI S/S


PART -A: OWNER ASSESSED QUANTITIES
A 245 KV EQUIPMENTS
A1 245KV GIS Equipment
1.1 245kV, SF6 GIS Bus Bars Module as per section
2 Sets
project(EXTENSION)
1.2 245kV, SF6 GIS Line feeder bay Module as per section project
2 Sets
1.3 220kV, SF6 to Cable Bushing alongwith associated support
structure
a) 2000A, 40kA for 1 sec. Single Phase 6 Nos.
A2 245KV Outdoor Equipment
1.1 216 KV Surge Arrester (1-phase) 6 Nos.
1.2 4400pF, 245 kV Capacitive Voltage Transformer (1-Phase)
6 Nos.
1.3 245kV Bus Post Insulator (1-Phase) (Except for wave trap)
12 Nos.

B Testing & Maintenance Equipment for GIS


1.1 SF6 Gas processing Unit 1 Set
1.2 Partial Discharge Monitoring System 1 Set
1.3 Dew Point Meter 1 Set
1.4 SF6 Gas Leak Detector 1 Set

C RELAY PANELS (WITH AUTOMATION)


1 245kV
1.1 Circuit Breaker Relay Panel
SCHEDULE - 2 PAGE 10 OF 11

Ex Faxtory Price (Excluding Total Amount VAT and other


Inland Transportation up to Site Total Amount
Item No. Item Description Quantity Unit VAT) (Excluding Taxes) taxes
Unit Rate Amount Unit Rate Amount
a) CB Relay Panel With Auto Reclose 2 Nos.
1.2 Line Protection Panel 2 Nos.
1.3 Integration of existing Bus Bar Protection 1 set
3 Other/Common equipments Pertaining to C & R System
a) Relay Test kit 1 No.

D SUBSTATION AUTOMATION
Augmentation of Substation Automation System as per
1
Technical Specification:
a) 220kV System 2 Nos.

E Cables along with clamps, glands, lugs and straight joints


etc.
a 220 kV grade 1 core, 1200sq.mm.XLPE insulated copper cable
1.5 KM
as per technical specification
b Cable end termination(s) on Gantry as per technical
6 nos
specification

F STEEL STRUCTURES (Tower,Gantry structures&


Equipment support structures)
a Lattice Structure for towers,beams and equipments including
peak plates/pack washers and guest paltes including foundation
32 MT
bolts(nuts,washers,MS plate welded at the bottom)

b Fastners for towers,beams and equipment support strcutures


1 MT

SUB TOTAL -PART-A

PART-B: VENDOR ASSESSED QUANTITIES


Erection Hardware :-Insulator strings, Disc Insulators,
Hardware, conductor, bus-bar materials, cable trays, clamps,
spacers, connectors including conectors for Auto Transformer ,
A
Junction box, earthwire, earthing material risers, buried cable
trenches/pipe of equipment & lighting, all accessories etc. for
the following:

1 220 kV DM-type layout for GIS termination arrangement


1.1 Line Bay 2 Set

B POWER & CONTROL CABLES


1 1.1 kV LV Cables
1.1 Power Cable(PVC insulated) 1 LS
SCHEDULE - 2 PAGE 11 OF 11

Ex Faxtory Price (Excluding Total Amount VAT and other


Inland Transportation up to Site Total Amount
Item No. Item Description Quantity Unit VAT) (Excluding Taxes) taxes
Unit Rate Amount Unit Rate Amount
1.2 Control Cable (PVC insulated) 1 LS
Cable glands, lugs & straight through joints for Power &
1.3 1 LS
Control cables

C Earthing and lightning protection including necesaary


1 LS
connectors/connections, risers etc. complete in all respect
SUB TOTAL PART-B

PART-C: MANDATORY SPARES (Break up of Lumpsum


quantity shall be as per Annexure-I, Section Project of
Technical Specification).
I GIS 1 LS
II 220kV CVT 1 no
III 216kV LA 1 no
IV Digital protecion Coupler 1 LS
V Sub-Station Automation System 1 LS
VI Illumination System 1 LS
VII Erection Hardware 1 LS
VIII Relay & Protection 1 LS
TOTAL PART-C
Total for 220kV KHIMTI Substation (II) (Part-A+ Part-B+
Part C)

Total Ex-works Price ( Total of (I) and (II) to be carried


forward to Schedule No. 5A: Grand Summary)

Note : 1) Bidder is required to quote prices in this Schedule for all the individual items/sub-items.
2.) The Prices of equipments are inclusive of type test charges except for those mentioned in Schedule 4( e)
3.) BOQ given above is indicative only based on the scope of work as given in Project Specific Requirements. The quantities mentioned above may undergo change during detailed
engineering to meet the functional requirement and scope of work defined in Employer's Requirements.

Name of Bidder: Date:


Signature of Bidder:
(Printed Name)
(Designation)
(Common Seal)
SCHEDULE - 3 PAGE 1 OF 1

NEPAL ELECTRICITY AUTHORITY


TRANSMISSION DIRECTORATE
Tamakoshi-Kathmandu 220/400 kV Transmission Line Project
IFB No. : ICB-TD-TKTLP-073/74-02: Design, Supply, Installation and Commissioning of Gas Insulated 220 kV Barhabise Substation

Schedule A-3: Design Services : NOT APPLICABLE

Unit Prices Total Prices


Item Estimated
Item Description Local Currency portion Foreign Currency Portion
No.
Quantity Unit NRs Currency LC FC
1 2 3 4 5 6 7=3x5 8=3x6

1 NOT APPLICABLE

Name of Bidder: Date:


Signature of Bidder:
(Printed Name)
(Designation)
(Common Seal)
SCHEDULE - 4 (a) PAGE 1 OF 12

NEPAL ELECTRICITY AUTHORITY


TRANSMISSION DIRECTORATE
Tamakoshi-Kathmandu 220/400 kV Transmission Line Project
IFB No. : ICB-TD-TKTLP-073/74-02: Design, Supply, Installation and Commissioning of Gas Insulated 220 kV Barhabise Substation

Schedule No. 4: Installation Services


(a): Installation and Construction Charges

Installation Charges
Portion in Nepaln Currency
Portion in Foreign Currency
Sl. No. Item Description Unit Qty. (in NRs)
Currency* Unit Rate Total Charges Unit Rate Total Charges

(1) (2) (3) (4) (5) (6) (7)=(4)X6) (8) (9)=(4)X(8)


I 220/132/11kV GIS BARHABISE Substation
PART - A: OWNER ASSESSED QUANTITIES
A POWER TRANSFORMER
53.33MVA, 220/3 / 132//3 kV Single Phase Power Transformer (without
a) Nos. 4
transformer Oil)
b) Insulating oil for the above Power Transformer Lot 4
c) 33kV Current transformer (NCT) for autotrasnformer No 1
d) Oil Storage tank of 20KL Nos. 2

B POWER TRANSFORMER
a) 5 MVA, 132 /11 kV Three Phase Power Transformer (without transformer Oil) Nos. 1

b) Insulating oil for the above Power Transformer Lot 1

C) LT Transformer
a) 630KVA 11/0.400 Kv Nos. 2

D 245 KV EQUIPMENTS
D1 245KV GIS Equipment
1.1 245kV, SF6 GIS Bus Bars Module as per section project Sets 2
1.2 245kV, SF6 GIS Bus Coupler feeder bay Module as per section project Sets 1
1.3 245kV, SF6 GIS Line feeder bay Module as per section project Sets 4
1.4 245kV, SF6 GIS spare Line feeder bay Module as per section project Sets 2
1.5 245kV, SF6 GIS ICT feeder bay Module as per section project Sets 1
1.6 SF6 Gas Insulated Bus Duct (GIB) outside GIS Hall alongwith associated support
structure and accessories
a) SF6 Gas Insulated Bus Duct (GIB) outside GIS Hall alongwith associated support
structure and accessories
OPTION-I Mtr. 240
1600A, 40kA for 1 sec. Single Phase
OPTION-II Mtr. 80
1600A, 40kA, 1sec three phase
Note : Bidder is required to quote for either option-I or Option-II
b 1600A, 40kA for 1 sec. Single Phase ( for 4X53.33 MVA 1 ph Transformer) mtr 60
SCHEDULE - 4 (a) PAGE 2 OF 12

Installation Charges
Portion in Nepaln Currency
Portion in Foreign Currency
Sl. No. Item Description Unit Qty. (in NRs)
Currency* Unit Rate Total Charges Unit Rate Total Charges

1.7 220kV, SF6 to Air Bushing alongwith associated support structure Nos. 16
1.8 245kV, SF6 GIS Auxiliary Bus Module as per section project to connect spare unit of
set 1
Transformer
D.2 1600A, 40kA for 1 sec. Single Phase
1.1 216 KV Surge Arrester (1-phase) Nos. 16
1.2 4400pF, 245 kV Capacitive Voltage Transformer (1-Phase) Nos. 12
1.3 245kV Bus Post Insulator (1-Phase) (Except for wave trap) Nos. 12

E 145kV Equipment
E.1 145KV GIS Equipment
1.1 145kV, SF6 GIS Bus Bars Module as per section project Sets 2
1.2 145kV, SF6 GIS Bus Coupler feeder bay Module as per section project Set 1
1.3 145kV, SF6 GIS Line feeder bay Module as per section project Sets 2
1.4 145kV, SF6 GIS Spare Line feeder bay Module as per section project Sets 1
1.5 145kV, SF6 GIS ICT feeder bay Module as per section project for 220/132 kV
Sets 1
Transformer
1.6 145kV, SF6 GIS ICT feeder bay Module as per section project for 132/11 kV
Sets 1
Transformer
1.7 SF6 Gas Insulated Bus Duct (GIB) outside GIS hall including Bus Duct support
structure and associated accessories
a) 1250A, 31.5kA, 1sec three phase Mtr 50
b 1250A, 31.5 kA 1sec single phase (for 4x53.33MVA 1-Phase Transformer bays)
mtr 30
1.8 145kV, SF6 to Air Bushing alongwith associated support structure
a) 1250A, 31.5kA, 1sec single phase Set 13
1.9 145kV, SF6 GIS Auxiliary Bus Module as per section project to connect spare unit of
set 1
Transformer
E.2 145kV EQUIPMENT(AIS)
1.0 120 kV Surge Arrestors (1-Phase) Nos. 13
2.0 8800pF, 145 kV Capacitive Voltage Transformer (1-Phase) Nos. 6
3.0 145KV Bus Post Insulator Nos. 6

F 11 KV EQUIPMENT
1.0 11 kV Isolator (3-phase)-HDB
i 400A, 25kA for 3 sec, Isolator without E/s (Beam Mounted) Set 2
2.0 9 kV Surge Arrester (1 ph.) Nos 6
3.0 11 kV Horn Gap fuse (1 ph.) Nos 6
4.0 11kV BPI Nos 6

G 11kV, 25 kA (3 Phase) Indoor switch gear panel


i) 11kV Transformer Module Nos 1
ii) 11kV LT Transformer Module Nos 1
iii) Bus PT Module No 1
H Testing & Maintenance Equipment for GIS
SCHEDULE - 4 (a) PAGE 3 OF 12

Installation Charges
Portion in Nepaln Currency
Portion in Foreign Currency
Sl. No. Item Description Unit Qty. (in NRs)
Currency* Unit Rate Total Charges Unit Rate Total Charges

1.6 EOT crane for 220kV GIS Hall Set 1


1.7 EOT crane for 132kV GIS Hall Set 1

I RELAY PANELS (WITH AUTOMATION)


1 245kV
1.1 Circuit Breaker Relay Panel
a) CB Relay Panel With Auto Reclose Nos. 6
1.2 Line Protection Panel Nos. 6
1.3 Transformer Protection Panel (For both HV & MV side) Nos. 1
1.4 Bus Bar Protection Panel set 1
2 145kV
1.1 Circuit Breaker Relay Panel
a) CB Relay Panel With Auto Reclose Nos. 3
b) CB Relay Panel Without Auto Reclose Nos. 3
1.2 Line Protection Panel Nos. 3
1.3 Transformer Protection Panel (For both HV & MV side) Nos. 1
1.4 Bus Bar Protection Panel set 1
3 Other/Common equipments Pertaining to C & R System
a) Time Synchronisation Equipment No. 1

J SUBSTATION AUTOMATION
1 Substation Automation System as per Technical Specification:
a) 220kV System Nos. 8
b) 132 kV System Nos. 6
c) BCU for auxilary system set 1
d) 11 kV HT Indoor Switchgear set 1

K Digital Protection Coupler , PBAX & Wave Trap


a) Digital Protection Coupler Nos 16
b) PBAX with following configuration as per TS Set 1
i 2 wire subscriber interface card with capacity 32 local subscribers (along with 32 nos.
Instruments)
ii 4 wire E & M interface card with capacity 8 nos. trunks (For PLCC)
iii) E-1 interface with 2 trunks G-703
iv) 2 wire interface with 1 trunk (For PSTN)
c) Line Trap
i) 1250A,0.5mH,31.5kA(132 kV) nos 2
ii) Bus Post Insulator for above 132 kv Wave Trap no. 6

L LT Switchgear (As per Technical specification)


a 400V Main switchboard Set 1
b 400V ACDB Set 1
c 400V MLDB Set 1
d 400V Emergency LDB Set 1
SCHEDULE - 4 (a) PAGE 4 OF 12

Installation Charges
Portion in Nepaln Currency
Portion in Foreign Currency
Sl. No. Item Description Unit Qty. (in NRs)
Currency* Unit Rate Total Charges Unit Rate Total Charges

e 220V DCDB Sets 2


g 48V DCDB Set 2

M Batteries
a 220V
i 600 AH Nos 2
b 48V
i 600AH Nos 2

N Float Cum Boost Battery Charger


a 220V Float Cum Boost Battery Charger
i 90A/90A Nos 2
b 48V Float Cum Boost Battery Charger
i 90A/90A Nos 2

O Diesel Generator with control Panel


a 250 kVA Set 1

P Fire Protection System


a Portable /Trolley/Wheel mounted extinguishers
i 9 litre water type Nos 2
ii 50 litre foam type Nos 2
iv 4.5 kg Dry Chemical Power (DCP) type Nos 2
b Smoke detection system Set 1
c Fire detection and Alarm System Set 1

Q Cables along with clamps, glands, lugs and straight joints etc.
i 3.5Cx300 sqmm (XLPE) cable for filter Machine along with 2 nos outdoor
KM 1
receptacles -250A

R Air conditioning
High wall type split AC unit of 2 TR capacities for control room, relay room and
1 Nos. 25
battery room

S STEEL STRUCTURES (Tower,Gantry structures& Equipment support


structures)
a Lattice/pipe Structure for towers,beams and equipments including peak plates/pack
washers and guest paltes including foundation bolts(nuts,washers,MS plate welded at
the bottom)
i) Lattice stucture & foundation bolts MT 100
ii Pipe structure & foundation bolts MT 22
b Fastners for towers,beams and equipment support strcutures MT 5

T Communication Equipment
SCHEDULE - 4 (a) PAGE 5 OF 12

Installation Charges
Portion in Nepaln Currency
Portion in Foreign Currency
Sl. No. Item Description Unit Qty. (in NRs)
Currency* Unit Rate Total Charges Unit Rate Total Charges

1 Transmission Equipment
A SDH Equipment ( STM- 4 MADM, upto 3 MSP protected directions)

Base Equipment (Common cards, Cross-connect/control cards, Optical base cards,


(I) Power supply cards, power cabling, other hardware & accessories including sub- No. 2
racks, patch cords, DDF etc. fully equipped excluding (II) and (III) below)

(II) Optical Interface/SFP# for


a) S4.1 Nos. 4
(a) L4.2 Nos. 6
(III) Tributary Cards
(a) E1 Interface card (Minimum 16 interfaces per card ) Nos. 2
Ethernet interfaces 10/100 Mbps with Layer-2 switching (Minimum 4 interfaces
(b) No. 4
per card.)
2 Termination Equipment
Drop/Insert Multiplexer
A1 Base Equipment (Common cards, Power supply cards, power cabling, other hardware
Nos. 2
& accessories including sub-racks, etc. fully equipped excluding subscriber line
A2 Subscriber Line Interface Cards
b) 4 wire (E&M) voice channel cards (min 8 channels per card) Nos. 2
c) Asynchronous Sub Channels data cards (minimum 4 channels per card) No. 2
d) Synchronous data card (NX64kbps) Nos. 2
3 Equipment Cabinets
a) For Drop/Insert Multiplexer No. 2
b) For SDH Equipment No. 2
(a) Hardware set 1
(b) Software set 1
5 Synchronization Equipment
GPS clock including all hardware & accessories set 1
Main Distribution Frame
6
(100 pairs) no 2
7.0 Test Equipment as per TS set 1
SUB TOTAL PART-A

PART-B: VENDOR ASSESSED QUANTITIES

Erection Hardware :-Insulator strings, Disc Insulators, Hardware, conductor, bus-bar


materials, cable trays, clamps, spacers, connectors including conectors for Auto
A
Transformer , Junction box, earthwire, earthing material risers, buried cable
trenches/pipe of equipment & lighting, all accessories etc. for the following:

1 220 kV DM-type layout for GIS termination arrangement


1.1 Line Bay Set 4
1.2 Transformer Bay Sets 1

2 132 kV DM-type layout for GIS termination arrangement


1.1 Line Bay Sets 2
SCHEDULE - 4 (a) PAGE 6 OF 12

Installation Charges
Portion in Nepaln Currency
Portion in Foreign Currency
Sl. No. Item Description Unit Qty. (in NRs)
Currency* Unit Rate Total Charges Unit Rate Total Charges

3 11 KV SET 2
Bus post insulators, Spacers, equipment support structures, conductor(s), Al tube,
clamp, connectors required for arrangement of Neutral formation for one transformer
B Sets 1
bank for making connection arrangement to connect spare unit in place of any other
unit without physical shifting complete in all respect

C Ventilation & heating System


(ii) 132 kV GIS Hall LS 1

D Illumination System
1.1 Substation Lighting
(iii) 132kV GIS Building LS 1
IV. Indoor Switchyrad Panel Room LS 1
v Fire Fighting Room LS 1
vi Outdoor Switchyard Lighting LS 1
vii Street Lighting LS 1

E Fire Protection System per technical Specification) set 1


1 Pumping arrangement inside pump house set 1
2 Hydrant system outside the Pump House. set 1
3 HVW spray system & Hydrant system for Transformer :
b 5 MVA,132/11 kV Three phase transformer nos 1

F POWER & CONTROL CABLES


1 1.1 kV LV Cables
1.1 Power Cable(PVC insulated) LS 1
1.2 Power Cable(XLPE insulated) LS 1
1.3 Control Cable (PVC insulated) LS 1
1.4 Cable glands, lugs & straight through joints for Power & Control cables LS 1

G Visual Monitoring System for watch & ward as per technical specification LS 1

H Earthing and lightning protection including necesaary connectors/connections, risers


etc. complete in all respect
i Earth Conductor (copper) LS 1
ii Earth Rod (copper clad steel) LS 1
iii Equipment for lightning protection LS 1
I SUBSTATION AUTOMATION
a Integration of all 220/132kV Bays under present scope with the SCADA of LS 1
SIEMENS (SINAUT Spectrum) at Load Dispatch Centre, Kathmandu including
supply of Hardware, Software, accessories etc. as per TS Section Project.

SUB TOTAL PART-B


SCHEDULE - 4 (a) PAGE 7 OF 12

Installation Charges
Portion in Nepaln Currency
Portion in Foreign Currency
Sl. No. Item Description Unit Qty. (in NRs)
Currency* Unit Rate Total Charges Unit Rate Total Charges

PART-C: Civil Works


Excavation in all types of soil and rock including backfilling disposal etc. for all leads
1.0 Cu.M 16,550
and lifts
2.0 Providing and laying of Plain Cement Concrete (PCC) (1:4:8) Cu.M 1950
3.0 Providing and laying of Plain Cement Concrete (PCC) (1:2:4) Cu.M 910
Providing and laying of Reinforced Cement Concrete Design Mix M25 including pre
4.0 cast, shuttering, Grouting of pockets & underpinning but excluding steel Cu.M 4710
reinforcement
Providing and laying Plain Cement Concrete 1:5:10 (1 cement : 5 sand : 10 Stone
5.0 Cu.M 600
aggregate)
6.0 Steel Reinforcement ( Fe 500) MT 380
7.0 Stone filling (40 mm size) over grating of transformer/ reactor foundation Cu.M 20
8.0 Misc. Structural steel including rails, embedments, edge protection angles, gratings MT 37
9.0 Stone spreading including antiweed treatment in switchyard excluding PCC Sq. M. 8000
10.0 All civil works for following buildings as per technical specification and approved
i) Auxilliary building (11kV indoor panel) Sq. M. 125
ii) Fire fighting pump house building (excluding external finish)
Sq. M. 98
iii) Water Tank (excluding external finish) LS 1
v) Township (Quarters)
(a) B Type Sq. M. 500
(b) C Type Sq. M. 600
(c) D Type Sq. M. 210
vi) Transit Camp Sq. M. 420
vii) Parking Shed (for 10 Cars) LS 3
11.0 External finish as per specification for following buildings:
i) Auxilliary building (11kV indoor panel) Sq. M. 125
ii) Fire fighting pump house building (excluding external finish) Sq. M. 98
iii) Water Tank (excluding external finish) LS 1
v) Township (Quarters)
(a) B Type Sq. M. 500
(b) C Type Sq. M. 600
(c) D Type Sq. M. 210
vi) Transit Camp Sq. M. 420
vii) Parking Shed (for 10 Cars) LS 3
12.0 PRE ENGINEERED BUILDINGS
i) CONTROL ROOM BULIDING
All Civil works including finishing, internal cable trench, etc. complete as per Sq. M. 750
ii) technical
220 KV GISspecification
HALL and approved drawings, excluding excavation, PCC, RCC and
All Civil works including finishing, internal cable trench, etc. complete as per Sq. M. 600
iii) technical
132 KV GISspecification
HALL and approved drawings, excluding excavation, PCC, RCC and
All Civil works including finishing, internal cable trench, etc. complete as per Sq. M. 500
technical specification and approved drawings, excluding excavation, PCC, RCC and
13.0 Concrete road as per drawing except reinforcement & concrete
SCHEDULE - 4 (a) PAGE 8 OF 12

Installation Charges
Portion in Nepaln Currency
Portion in Foreign Currency
Sl. No. Item Description Unit Qty. (in NRs)
Currency* Unit Rate Total Charges Unit Rate Total Charges

(a) Road 3.75m wide Sq.M. 2850


Construction of rail cum road as per drawing including all items such as excavation,
14.0 compaction, rolling, watering, WBM etc but excluding concrete, reinforcement and
structural steel.
a) Section having four rails Sq.M. 230
Chain link fencing as per technical sepcification and approved drawing excluding
15.0 RM 300
concrete
16.0 Switchyard Gate excluding Concrete Nos. 2
Septic tank and soak pit (for 50 users) complete as per technical specification and
17.0 approved drawing excluding concrete & reinforcment which shall be measured and LS 3
paid seperately under respective items of BPS .

18.0 Supplying & laying hume pipe of grade (NP-3) excluding concrete and reinforcement

a) 250mm dia RM 150


b) 300mm dia RM 120
c) 450mm dia RM 80
d) 600mm dia RM 40
e) 900mm dia RM 10
19.0 Supplying and erecting dewatering pumps
a) 5 HP Nos. 2
b) 0.5 HP Nos. 2
20.0 Drains Excluding Concrete
a) Section A-A (300 mm wide X depth up to 600mm) RM 200
b) Section B-B ( 450 mm wideX depth from 600 mm to 900 mm) RM 100
c) Section C-C (600 mm wide X depth from 900 mm to 1200 mm) RM 80
d) Section D-D (750 mm wide X depth from 1200 mm to 1500mm ) RM 20
21.0 External water supply from borewell/main water supply point to Fire water Tank,
(control roomDia
i ) 80 mm building,
GI pipetownship buildings RM 100
( ii ) 50 mm Dia GI pipe RM 80
(iii) 40mm Dia GI pipe RM 60
(iii) 25mm Dia GI pipe RM 40
22.0 External sewerage system including all item such as excavation, piping, pipe fittings,
manholes,
(i) 250 mmgali
Dia.trap, gali chamber etc. RM 50
(i) 150 mm Dia. RM 50
All civil works for Boundary wall including excavation, concrete, reinforcement steel
,structural steel, plaster, painting, barbed wire and concertina coil etc all complete as
23.0 RM 1200
per technical specification (2.5 m high brick masonary wall and 0.5 m high angle
support on top).
Main boundary wall Gate (Steel ) including all works complete as per technical
24.0 LS 1
specification
25.0 Site levelling
SCHEDULE - 4 (a) PAGE 9 OF 12

Installation Charges
Portion in Nepaln Currency
Portion in Foreign Currency
Sl. No. Item Description Unit Qty. (in NRs)
Currency* Unit Rate Total Charges Unit Rate Total Charges

Earth work in excavation and filling in all types of soils including soft/disintegrated
i Cu. M 50000
rock with all leads and lifts within sub station boundary
Earth work in filling with borrowed earth with all leads and lifts including
ii Cu. M 10000
royalty,taxes etc
All civil works for security room as per TS including septic tank and soak pit. Internal
26.0 and external finish, sanitary and plumbing works, plinth protection etc. to complete Sq. m. 9
the building are included in the item.

Construction of retaining wall with random rubble masonary in cement sand mortar
(1:6) including levelling up with cement concrete (1:6:12), providing weep holes of
PVC pipes (150 mm dia) with necessary filter material at the mouth of weep holes, 50
27.0 mm thick cement concrete (1:2:4) copping on the top of wall, 100 mm thick PCC Cu. M 9900
(1:4:8) below RR masonary work, excavation of foundation for all lifts up to 3m
above lower level. Item of excavation, PCC (1:2:4 & 1:4:8) shall be measured and
paid seperately under respective items of BPS

28 Soil Investigation as per TS LS 1


29 Aproach Road-Strenghthening of existing approach road as per TS (2.5 cm thick pre- Sq. m. 24000
SUB-TOTAL-C
Total for 220/132/11kV BARHABISE Substation (I) (Part-A+ Part-B+ Part C)

II EXTENSION OF 220 KV KHIMTI S/S


PART -A: OWNER ASSESSED QUANTITIES
A 245 KV EQUIPMENTS
A1 245KV GIS Equipment
1.1 245kV, SF6 GIS Bus Bars Module as per section project(EXTENSION) Sets 2
1.2 245kV, SF6 GIS Line feeder bay Module as per section project Sets 2
1.3 220kV, SF6 to Cable Bushing alongwith associated support structure
a) 2000A, 40kA for 1 sec. Single Phase Nos. 6
A2 245KV Outdoor Equipment
1.1 216 KV Surge Arrester (1-phase) Nos. 6
1.2 4400pF, 245 kV Capacitive Voltage Transformer (1-Phase) Nos. 6
1.3 245kV Bus Post Insulator (1-Phase) (Except for wave trap) Nos. 12

B Testing & Maintenance Equipment for GIS


1.1 SF6 Gas processing Unit Set 1
1.2 Partial Discharge Monitoring System Set 1
1.3 Dew Point Meter Set 1
1.4 SF6 Gas Leak Detector Set 1

C RELAY PANELS (WITH AUTOMATION)


1 245kV
1.1 Circuit Breaker Relay Panel
a) CB Relay Panel With Auto Reclose Nos. 2
SCHEDULE - 4 (a) PAGE 10 OF 12

Installation Charges
Portion in Nepaln Currency
Portion in Foreign Currency
Sl. No. Item Description Unit Qty. (in NRs)
Currency* Unit Rate Total Charges Unit Rate Total Charges

1.2 Line Protection Panel Nos. 2


1.3 Integration of existing Bus Bar Protection set 1
3 Other/Common equipments Pertaining to C & R System
a) Relay Test kit No. 1

D SUBSTATION AUTOMATION
1 Augmentation of Substation Automation System as per Technical Specification:
a) 220kV System Nos. 2

E Cables along with clamps, glands, lugs and straight joints etc.
a 220 kV grade 1 core, 1200sq.mm.XLPE insulated copper cable as per technical
KM 1.5
specification
b Cable end termination(s) on Gantry as per technical specification nos 6

F STEEL STRUCTURES (Tower,Gantry structures& Equipment support


structures)
a Lattice Structure for towers,beams and equipments including peak plates/pack
washers and guest paltes including foundation bolts(nuts,washers,MS plate welded at MT 32
the bottom)
b Fastners for towers,beams and equipment support strcutures MT 1
SUB TOTAL -PART-A

PART-B: VENDOR ASSESSED QUANTITIES

Erection Hardware :-Insulator strings, Disc Insulators, Hardware, conductor, bus-bar


materials, cable trays, clamps, spacers, connectors including conectors for Auto
A
Transformer , Junction box, earthwire, earthing material risers, buried cable
trenches/pipe of equipment & lighting, all accessories etc. for the following:

1 220 kV DM-type layout for GIS termination arrangement


1.1 Line Bay Set 2

B POWER & CONTROL CABLES


1 1.1 kV LV Cables
1.1 Power Cable(PVC insulated) LS 1
1.2 Control Cable (PVC insulated) LS 1
1.3 Cable glands, lugs & straight through joints for Power & Control cables LS 1

C Earthing and lightning protection including necesaary connectors/connections, risers


LS 1
etc. complete in all respect
SUB TOTAL PART-B

PART-C-Civil Works
SCHEDULE - 4 (a) PAGE 11 OF 12

Installation Charges
Portion in Nepaln Currency
Portion in Foreign Currency
Sl. No. Item Description Unit Qty. (in NRs)
Currency* Unit Rate Total Charges Unit Rate Total Charges

Excavation in all types of soil and rock including backfilling disposal etc. for all leads
1.0 Cu.M 950
and lifts
2.0 Providing and laying of Plain Cement Concrete (PCC) (1:4:8) Cu.M 125
3.0 Providing and laying of Plain Cement Concrete (PCC) (1:2:4) Cu.M 60
Providing and laying of Reinforced Cement Concrete Design Mix M25 including pre
4.0 cast, shuttering, Grouting of pockets & underpinning but excluding steel Cu.M 230
reinforcement
Providing and laying Plain Cement Concrete 1:5:10 (1 cement : 5 sand : 10 Stone
5.0 Cu.M 75
aggregate)
6.0 Steel Reinforcement ( Fe 500) MT 11

Misc. Structural steel including rails, embedments, edge protection angles, gratings
7.0 MT 5
etc. but excluding the reinforcement steel and steel for lattice and pipe structures.

8.0 Stone spreading including antiweed treatment in switchyard excluding PCC Sq. M. 1000

9.0 Concrete road as per drawing except reinforcement & concrete


(a) Road 3.75m wide Sq.M. 375
Chain link fencing as per technical sepcification and approved drawing excluding
10.0 RM 50
concrete
11.0 Dismantling & reerection of chain link fencing excluding concrete RM 50

12.0 Supplying & laying hume pipe of grade (NP-3) excluding concrete and reinforcement
a) 250mm dia RM 50
b) 300mm dia RM 30
c) 450mm dia RM 25
d) 600mm dia RM 25
13.0 Drains Excluding Concrete
a) Section A-A (300 mm wide X depth up to 600mm) RM 60
b) Section B-B ( 450 mm wideX depth from 600 mm to 900 mm) RM 20
c) Section C-C (600 mm wide X depth from 900 mm to 1200 mm) RM 20
d) Section D-D (750 mm wide X depth from 1200 mm to 1500mm ) RM 20
14.0 Site levelling
Earth work in excavation and filling in all types of soils including soft/disintegrated
i Cu. M 10000
rock with all leads and lifts within sub station boundary
Earth work in filling with borrowed earth with all leads and lifts including
ii Cu. M 2000
royalty,taxes etc

Construction of retaining wall with random rubble masonary in cement sand mortar
(1:6) including levelling up with cement concrete (1:6:12), providing weep holes of
PVC pipes (150 mm dia) with necessary filter material at the mouth of weep holes, 50
15.0 mm thick cement concrete (1:2:4) copping on the top of wall, 100 mm thick PCC Cu. M 1000
(1:4:8) below RR masonary work, excavation of foundation for all lifts up to 3m
above lower level. Item of excavation, PCC (1:2:4 & 1:4:8) shall be measured and
paid seperately under respective items of BPS
SCHEDULE - 4 (a) PAGE 12 OF 12

Installation Charges
Portion in Nepaln Currency
Portion in Foreign Currency
Sl. No. Item Description Unit Qty. (in NRs)
Currency* Unit Rate Total Charges Unit Rate Total Charges

Total PART-C
Total for 220kV KHIMTI Substation (II) (Part-A+ Part-B+ Part C)
TOTAL INSTALLATION SERVICES (Total of (I) and (II) to be carried
forward to Schedule No. 5: Grand Summary)
Note : 1) Bidder is required to quote prices in this Schedule for all the individual items/sub-items.
2.) BOQ given above is indicative only based on the scope of work as given in Employer's Requirements. The quantities mentioned above may undergo change during detailed engineering to meet the functional requirement and scope
of work defined in Employer's Requirements.
* Specify currency in accordance with BDS ITB Clause 19.1, Part-I of the Bidding Documents.
Strike out if not applicable

Name of Bidder: Date:


Signature of Bidder:
(Printed Name)
(Designation)
(Common Seal)
Schedule-4 (b) Page 1 of 1

NEPAL ELECTRICITY AUTHORITY


TRANSMISSION DIRECTORATE
Tamakoshi-Kathmandu 220/400 kV Transmission Line Project
IFB No. : ICB-TD-TKTLP-073/74-02: Design, Supply, Installation and Commissioning of Gas Insulated 220 kV Barhabise Substation

Schedule No. 4 : Installation and Other Services


(b):Training Charges for training to be imparted abroad

Country Nos. of Training Total Training Charges


Sl. where training Trainee duration in
Description Item for which training is to be imparted.
No. is to be days Currency Total
imparted Training Charges
1 2 3 4 5 6 7 = 4x5 x 6
i) Control & Protection and Substation 3 5 days
Automation System
Training to Owners personnel on Design , testing and
ii) GIS 3 5 days
A Maintenance aspect as per Section Project, Technical
iii) Telecommunication Equipment (SDH ,MUX 3 5 days
Specification at manufacturer's works
& NMS (Craft Terminal))
iv)Transformer 3 5 days
Total for Training Charges (Total of column 7 to be
carried forward to Schedule No. 5: Grand Summary)

Name of Bidder: Date:


Signature of Bidder:
(Printed Name)
(Designation)
(Common Seal)
Schedule 4 (c) Page 1 of 1

NEPAL ELECTRICITY AUTHORITY


TRANSMISSION DIRECTORATE
Tamakoshi-Kathmandu 220/400 kV Transmission Line Project
IFB No. : ICB-TD-TKTLP-073/74-02: Design, Supply, Installation and Commissioning of Gas Insulated 220 kV Barhabise Substation

Schedule No. 4 : Installation and Other Services


(c):Training Charges for training to be imparted to Employer's Personnel by Bidder's Instructor in Nepal

Training Training Charges for Contractors


Sl. No. Description of the Test duration in Total
Item for which training is to be imparted. Currency
days Training Charges
1 2 3 4 5 6 = 4x 5
i) Control & Protection 5

ii) Substation Automation System including


integration aspect of existing SCADA (of Siemens
5
suppliedSINAUT Spectrum Software) at Load
On Job training on operation, maintenance and Dispatch Center
a) testing & commissioning aspectat at one Location in
Nepal as per section Project, Technical Specification GIS 5
iv) Telecommunication Equipment (SDH ,MUX &
5
NMS (Craft Terminal))

TRANSFORMERS 5
Total for Training Charges ( total of column 6 To
be carried forward to Schedule 5: Grand
Summary)

Date: Signature:

Printed Name:

Designation:

Common Seal:
Schedule 4 (d) Page 1 of 1

NEPAL ELECTRICITY AUTHORITY


TRANSMISSION DIRECTORATE
Tamakoshi-Kathmandu 220/400 kV Transmission Line Project
IFB No. : ICB-TD-TKTLP-073/74-02: Design, Supply, Installation and Commissioning of Gas Insulated 220 kV Barhabise Substation

Schedule No. 4 : Installation and Other Services


(d): Maintenance Charges
Total Maintenance Charges
Sl No Description Unit Qty.
Currency Total Maintenance Charges

Maintenance Charges for Communication


1 Equipments including SDH & MUX. for One Year 1
(1) year during Warranty period
Maintenance Charges for Communication
2 Equipments including SDH & MUX. for Six Year 6
(6) years after Warranty period
Total Maintenance Charges (To be
carried forward to Schedule 5: Grand
Summary)

Date: Signature:

Printed Name:

Designation:

Common Seal:
SCHEDULE - 4 (e) PAGE 1 OF 1

TRANSMISSION DIRECTORATE
Tamakoshi-Kathmandu 220/400 kV Transmission Line Project

IFB No. : ICB-TD-TKTLP-073/74-02: Design, Supply, Installation and Commissioning of Gas Insulated 220 kV Barhabise Substation

Schedule No. 4 : Installation and Other Services


(e): Type Test charges for Type Tests to be conducted abroad

Sl. No. Description of Tests Country of Testing Unit Qty. Currency # Amount
(1) (2) (3) (4) (5) (6) (7)=(5) x ( 6)
I 220/132kV, 53.33MVA Single Phase Power Transformer
a) Temperate rise test 1
b) Measurement of zero sequence reactance 1
c) Measurement of Accoustic Noise Level 1
d) Measurement of Harmonic Level at No-load current 1
e) Measurement of power taken by fans and pumps 1
II 132/11, 5 MVA Three Phase Power Transformer
a) Temperate rise test 1
b) Measurement of zero sequence reactance 1
c) Measurement of Accoustic Noise Level 1
d) Measurement of Harmonic Level at No-load current 1
e) Measurement of power taken by fans and pumps 1

TOTAL (Total of column 7 to be carried forward to Schedule No. 5:


Grand Summary)
# Specify currency in accordance with BDS ITB Clause 19.1, Part-I of the Bidding Documents.

Name of Bidder: Date:


Signature of Bidder:
(Printed Name)
(Designation)
(Common Seal)
Schedule 5 Page 1 of 1

NEPAL ELECTRICITY AUTHORITY


TRANSMISSION DIRECTORATE
Tamakoshi-Kathmandu 220/400 kV Transmission Line Project
IFB No. : ICB-TD-TKTLP-073/74-02: Design, Supply, Installation and Commissioning
of Gas Insulated 220 kV Barhabise Substation

Schedule No. 5: Grand Summary

Total Price Foreign Total Price Local


Sl. No. Description
( ) ( )

1 TOTAL SCHEDULE NO. 1

Plant and Equipment including Mandatory Spares to be


supplied from abroad.

2 TOTAL SCHEDULE NO. 2

Plant and Equipment including Mandatory Spares Parts to


be supplied from within Nepal

3 TOTAL SCHEDULE NO. 3


Design Services
4 TOTAL SCHEDULE NO. 4

(a) Installation and construction charges

(b) Training charges for training to be imparted abroad

( c) Training charges for training to be imparted in Nepal

(d) Maintenance charges

(e) Type Tests charges for type Tests to be conducted


abroad

GRAND TOTAL FOR PART A [1+2+3+4]

Date: Signature:

Printed Name:

Designation:

Common Seal:
SCHEDULE - 6 PAGE 1 OF 1

NEPAL ELECTRICITY AUTHORITY


TRANSMISSION DIRECTORATE
Tamakoshi-Kathmandu 220/400 kV Transmission Line Project
IFB No. : ICB-TD-TKTLP-073/74-02: Design, Supply, Installation and Commissioning of Gas Insulated 220 kV Barhabise
Substation

Schedule No. 6: Recommended Availability/Optional Spares parts and Recommended Test Equipment (in line with Technical Specifications)

Item No. Name & Description of Name of Original Part No. Number of Units in Total No. of Sets to Unit Price Total Price Remarks
Parts Manufacturer each set be provided

Name of Bidder: Date:


Signature of Bidder:
(Printed Name)
(Designation)
(Common Seal)

You might also like