DAILY REPORT FORMAT

Project:- majestic tower Location:-nahur Date:-6/07/2017

MATERIAL INSPECTION
Qty
Sr Date Material Total Qty Status Third party/In- Challan/Chec
Unit Rejected Supplier Remark
no checked received Pass/Fail house lab klist ID
/Debited
1 6/07/2017 Steel MT PASS NIL
2 AAC blocks
Sand 3{truck} BRASS Pass NIL Arihant 576 , 4% ,
Trading , 486 , 6 %,
Arihant 504 5%
3
trading ,
Arihant
Trading
4
Bricks 2{truck} No Pass Nil Arihant 62 , 6 ,
Trading, 201 6
5
Gururani
Traders
6 Concrete CU.M
7 Tiles
8 Paints
9 Admixtures
10 Door frames
Aluminum
11
windows
12 Glass
Gypsum 1 No Pass Nil Natural 3850 1120 {no}
13 falase
ceiling
Whether ok as
Mock up test per
Sr New material Approval Consumption/unit
taken Unit manufacturers Accepted/Rejected Reason Remark
NO application Yes/No (cum/sq m/litre)
Yes/No specification or
not
1
2
3

CUBE REPORTS
Cubes Status
Sr
Date Location tested(no Supplier Grade (pass/ Corrective action Remark
No
of sets) fail)
1 23/6/17 D wing 21th floor column 1 Sky way M40 Pass 32.75
to
30/6/17

INSPECTION
Communication
Sr
Date Location Activity checked Status(NC/OK) (photo/mail/ph Remark
No
one)