@ seawater
MOOGERAH DAM
EMERGENCY ACTION
PLANMoogerah Dam
Emergeney Acton Plan
@seqwater
DISTRIBUTION CONTROL SHEET (Controlled Hard Copies)
‘Agency
Seqwater
Seqwater
Seqvater
Department of Eneray
‘and Water Supply
Queensiand Fire and
Emergency Services
Ipswich Cty Counc
‘Scenic Rim Regional
Counc
Police
Police
Position
‘Storage Supervisor
Principal Engineer Dam Safety
Principal Enginser Dam Safety
Director of Dam Safety
Duty Offcer
Local Disaster Coordinator
Local Disaster Coordinator
District Disaster Management
(Coordinator
District Disaster Management
Coordinator
Location
‘Moogerat Dam
Flood Operations
Centre, Brisbane
Flood Operations
Cente, Ipswich
Brisbane
Brisbane
tsa
Scanie Rim
Ipswich’Somerset
Logan‘Scenic
RimMoogerah Dam
Emergency Acton Plan
Revision Status
RevNo, | Date
° (October 2008
1 ‘August 2008
2 September 2010
21 dune 2011
3 September 2011
4 ‘August 2012
5 November 2013
a (Cdtober 2044
@sequater
Revision Description
Original
Revision 1
Revsion 2
Contact register updated
Revision 3
Revision 4
FRovised and updated in accordance with new
guidelines from the Department of Energy and Water
Supply
Revised following dlscussions with the Department of
Energy and Water Supply and other stakeholders