You are on page 1of 66

Quantity Takeoff

Dr. Ahmed Elyamany

1
Outline
 Importance of Quantity Takeoff
 Preparation of Quantity Takeoff
 Measurement Units
 Measuring excavation, P.C footings, Beams, Columns,
slabs, and stairs.
 Solved Example

2
Quantity Takeoff
 Quantity takeoff is an activity performed by General
Contractors, Subcontractors, Cost Consultants, and
Quantity Surveyors as part of the construction process.

 It involves counting the number of items associated with


a particular construction project

3
Quantity Takeoff
 Quantity Takeoff is performed by:
 General Contractors,
 Subcontractors,
 Cost Consultants,
 Quantity Surveyors

 Counting the number of items associated with a


particular construction project

 Determining the associated materials and labor costs

 Preparing an estimate as part of the bidding process.

 Applied to the pricing process.


4
Quantity take-off: Why?
 Owner perspective:
 Initial estimate of the project costs at the different stages of the
project.
 Preparing the BOQ as a requirement of the contract documents.
 Estimating the work done for issuing the contractor payments.

 Contractor perspective:
 Pricing different work items.
 Identifying the needed resources (Labor, Equipment, etc.).
 Project schedule.
 Preparing invoices for work done.
 Subcontractors payments.
 Review and control of crews production rates.

5
Quantity Takeoff
 The quantity takeoff process is typically done manually
using a printout, a pen, and a calculator.

6
Quantity Takeoff
 New Trend is Building Information Modeling (BIM)

 Provide a solution that generates a set of takeoff


elements (counts, measurements, conditions that affect
cost) enables estimators to more quickly and more
accurately perform takeoff for bidding or pricing.

7
Quantity Takeoff
 Important to specify the type of ;
 Imported materials
 Suppliers
 Equipment
 Labors
 Work in project

 Important to know project budget

 Important to know activities logic

8
Quantity Takeoff Criteria
 It must be as accurate as possible

 Should be based on all available engineering and design


data.

 Use of appropriate automation tools is highly


recommended.

 The Quantity Takeoff is an important part of the cost


estimate.

9
Quantity Takeoff Input Documents
 Input from the client (task description).
 Conditions (general, special, supplementary).
 Drawing and specifications.
 Addenda.
 Agreement form.
 Modifications.

10
Quantity Development Guidelines
 Coordinate the quantity takeoff process and plan with the
estimator.

 Include a list of materials in quantity takeoffs.

 Utilize a process that easily records the quantity

 Check scales and dimensions on each drawing sheet.

 Highlight drawing areas where quantities have been


determined to ensure all elements is captured but not
double counted.
11
Quantity Development Guidelines
 Consider items that have no material but still require
cost, e.g., job office overhead, task setup, training and
certifications.

 Add a certain amount of waste, loss, drop off, or length


related to the material purchases for a bulk order.

 Coordinate with designers if the design appears in error..

12
Takeoff Sheet & Bill Of Quantities
 Quantity Takeoff Sheet

 Estimated Quantities

 Actual Quantities

 Bill Of Quantities (BOQ)


13
Quantity Takeoff Sheet

Dimension Part
Item Item Unit Quantity Total
Length Width Height Subtraction Addition

14
Bill Of Quantities

Price Notes
Item Item Unit Quantity
Unit Total

1
2
3

15
Bill of Quantities classification
 The Bill of Quantities is classified into the following work
groups:
 Civil works
 Sanitary works
 Electrical works
 Mechanical works

16
Bill of Quantities classification
 Civil works:
 Earth works:
 leveling,
 excavation,
 backfilling,
 transportation of excavated soil)
 Foundation works:
 plain concrete
 reinforced concrete
 piling foundations

17
Bill of Quantities classification
 Civil works:
 Brick works:
 Internal brick work
 External brick work
 Skelton reinforce concrete:
 Columns,
 Beans,
 Slabs
 Stairs

18
Bill of Quantities classification
 Civil works:
 Finishing:
 Water proofing
 Staircases
 Plastering
 Flooring
 Painting
 Metal works:
 Windows
 Doors
 Accessories

19
Bill of Quantities classification
 Sanitary works:
 Water feeding systems
 Internal and external plumbing works
 Finishes of plumbing works

 Electrical works:
 Electrical cables
 Wiring; Accessories
 Internal connections

 Mechanical works:
 Air conditioning systems
 Elevators
20
Work order
 Items in takeoff sheets are organized in the same
construction sequence.

 Order of items in the same chapter:


 Items estimated in (m3)
 Items estimated in (m2)
 Items estimated in (m)
 Items estimated in (unit)
 Items estimated in (ton)
 Items estimated in (L.S.)

21
Measuring
Units
 The units of measurements for civil engineering
works are mainly categorized for their:
 Nature
 Shape
 Size and
 Payments to the contractor.

 There are a number of standard codes and methods of


measurement that are available.

22
Measuring
Units
Cubic meter (m3)
 Used for items such as:
 Excavation
 Backfilling
 Concrete
 Brick walls (25 cm thick)

Square meter (m2)


 Used for items such as:
 Brick walls (<25 cm thick)
 Plastering
 Flooring
 Painting

23
Measuring
Units
Linear meter (m)
 Used for items such as:
 Pipe lines
 Canals
 Stair steps
 Windows sills

Number (unit)
 Used for items such as:
 Electric outlets
 Doors and windows
 Sanitary fixtures
 Precast concrete

24
Measuring
Units
Lump sum(L.S.)
 Item is subcontracted when the contractor does not
have enough experience to construct it or there is an
item which has a small quantities of many work items
such as:
 Manholes
 Lifts
 Some electrical and plumbing works

 Weight (Ton):
 Metallic works
 Reinforcement steel

25
Preparation of Quantity Takeoff
 Check the availability of drawings

 Check the axis and dimensions

 Check building levels and link it to structural drawings.

 Check doors and windows model numbers

 Check ground water levels

26
Preparation of Quantity Takeoff
 Check architectural against structural drawings

 Check foundation design and foundation levels

 Check construction members dimension and


reinforcement.

 Review the contract conditions and specifications

27
Formulas
Square

Rectangle

Parallelogram

Trapezoid

Trapezium
28
Formulas
Triangles

Regular Polygons

Circle

Parabola

Ellipse

29
Formulas

30
Formulas

31
Formulas

32
Formulas

33
Formulas

34
Formulas

35
Earth works
Excavation
 Quantities are calculated based on the dimensions of the
foundation in plans from the owner perspective.

 Contractors should consider the excess of material excavated


to all for safe operations.

 Prices differ based on the soil type, deep of excavation, ground


water level, site location, shoring system, Equipment used, etc.

 Unit of measurement is cubic meter (volume).

 Consider the example in the following slide:

36
Earth works
Excavation
 The length of excavation = 5.4 2 + (4.4 2) 2 = 15.6 m
 Depth of excavation = 1.8 m
 Width of excavation = width of plain concrete footing = 1.0 m
 Volume = 15.6 1.8 1.0 = 18.8 m3

37
Earth works
Backfilling
 Unit of measurement is cubic meter (volume)

 Consider the example shown in previous slide, the


volume of backfilling could be calculated as follow:
 Volume of backfilling = excavation concrete brick

 Volume of concrete = 15.6 1 0.4 = 6.24 m3

 Volume of brick = 15.6 0.4 1.4 = 8.736 m3

 Volume of backfilling = 18.8 (6.24 + 8.736) = 3.824 m3

38
Earth works
Site leveling & Soil transportation
 Site leveling:
 Measured in m2 (area) if thickness < 30cm.
 Measured in m3 (volume) if thickness > 30cm.

 Soil transportation:
 Transported soil = Vol. of exc. Vol. of backfilling + additional
soil at site
 Add swelling factor based on the soil type:
 5% sandy soil.
 15% clayey soil and
 25% for demolition material. (owner or contractor)

39
Concrete works
Plain concrete & Reinforced concrete
 Plain concrete (PC):
 Measured in m2 (area) if thickness < 20 cm.
 Measured in m3 (volume) if thickness 20 cm.
 Average thickness should be mentioned when measurement is
done by area.

 Reinforced concrete (RC):


 All RC elements measured by volume (m3) except hollow
block slabs measured by area (m2).
 Domes, cylindrical roofs and shells measured by area in the
horizontal projection.

40
Concrete works
Plain Concrete Footing
 Quantity of P.C footing = No. of footings for a specific
model * length * width * depth

 Total quantity of P.C footings = summation of P.C footing


models

RC Footing

PC Footing

41
Concrete works
Ground Beams
 Quantity of ground beam = No. of ground beams for a
specific model * length * width * depth

 Total quantity of ground beams = summation of ground


beam models

Ground Beam

RC Footing

PC Footing

42
Concrete works
Columns
 Quantity of columns = No. of columns for a specific
model * length * width * height

 Total quantity of columns = summation of columns


models

Columns

RC Footing

PC Footing

43
Concrete works
Slabs
 Solid slabs:
 Quantity of slab = length * width * thickness

 Flat slab:
 Quantity of slab = length * width * thickness

 Beams:
 Quantity of beam = length * width * height

44
Brick works
 Measured in m2 (by area) if thickness <25 cm.

 Measured in m3 (by volume) if thickness 25cm.

 Deduct all openings.

 Deduct half the area (volume) of arches.

 Deduct all Concrete elements.

 Separate item for each brick type

45
Stairs
 Quantity of stairs = inclined length * width * height +
stair section area * stair width * No. of stairs

stair section area

46
Plastering
 Internal Plaster:
 Engineering measurement by area (m2).
 All openings are deducted.
 All openings sides are added.
 Inclined slabs are calculated based on their horizontal
projection.

47
Plastering
 External plaster:
 Measured by area (m2).
 Openings with areas < 4 m2 are kept with deduction.
 Deduct half the area of the openings 4 m2.
 Openings with areas < 4 m2 are kept with deduction.
 Cantilever slabs < 1 m projection not added.
 Add half the area of cantilever slabs 1 m.

48
EXAMPLE 1
Substructure Taking-off List
 Site preparation
 Removing trees and shrubs
 Lifting turf
 Top soil/removing/preserving
 Excavation
 Reduce levels/disposal of excavated material
 Excavating trenches/disposal of excavated
 Material/Filling/Surface treatments
 Concrete Foundations
 Beds/formwork/damp-proof membrane
 Masonry Brick walls
 Forming cavities
 Filling to cavities

49
EXAMPLE 1
Substructure Site levels
 Top soil cannot be used for backfilling as it would, over time,
cause damage to the substructure.

 The usual default depth for topsoil is 150 mm

 Next figure is a 5 m grid of a survey of levels taken on a site.

 The site is required to be reduced to a level of 35.62 and in


order to calculate the volume of excavation required the
average level of the site must be determined.

 This can be easily done by weighting the levels as follows


starting at the top left-hand corner of the site (35.90) and
working from left to right.

50
EXAMPLE 1
Substructure Site levels

Level Total Level


35.90 35.90
35.86 2 71.72
35.89 2 71.78
35.92 2 71.84
35.90 2 71.80
35.89 35.89
35 86 2 71.72
35.84 4 143.36
35.88 4 143.52
35.90 4 143.60
35.90 4 143.60
35.86 2 71.72
35.84 35.84
35.85 2 71.70 Number of Points = 40
35.87 2 71.74 Average site level = 1435.07 / 40 = 35.87
35.90 2 71.80 Reduced level = 35.62
35.88 2 71.76
35.78 35.78 Average Excavation depth = 35.87 - 35.62 = 0.25
Total 1435.07

51
Example
5.6m

710/m
15cm

4.8m 712/m

A A

52
Example
216 416+ 68/m
.

0.3m x 0.5m

0.3m x 0.3m
3.0m


0.3m x 0.5m
1.2 m
1m x 1m x 0.4m

1.6m x 1.6m x 0.3m


Section A-A
53
Example
 It is required to estimate the quantities of the
following jobs:
 Excavation ()
 Plain Concrete Footings ()
 Reinforced Concrete Footings ()
 Ground Beams concrete ()
 Filling ()
 Columns concrete ()
 Slab and beams Concrete ()
 Slab and beams Reinforcement (
)

54
Excavation

1.6 m

4.8 m 1.2 m

1.6 m

.15 m 5.6 m .15 m

5.3
1.6 m
0.8 m 3.7 m
55
Excavation
No. Item Unit Number Length Width Depth Total
1 Excavation m3 4 1.6 1.6 1.2 12.288
2 3.7 0.3 0.5 1.11
2 2.9 0.3 0.5 0.87

56
PC Concrete Footings
No. Item Unit Number Length Width Depth Total
2 PC Concrete m3 4 1.6 1.6 0.3 3.072

1.6 m

0.3 m

1.6 m

57
RC Concrete Footings
No. Item Unit Number Length Width Depth Total
3 RC Concrete m3 4 1 1 0.4 1.6

1.0 m

0.4 m

1.0 m

58
Ground Beams
No. Item Unit Number Length Width Depth Total
4 Ground Beams m3 2 5.3 0.3 0.5 1.59
2 4.5 0.3 0.5 1.35

0.5 m

4.5 m
4.8 m
0.3 m 0.3 m
5.6 m
0.15 m
0.15 m

5.3

59
Filling
No. Item Unit Number Length Width Depth Subtotal Total
1 Excavation m3 14.27

2 PC Concrete m3 3.07
3 RC Concrete m3 1.60
4 Ground Beams m3 2.94
Total Concrete m3 7.61
5 Filling m3 6.66

60
Columns
No. Item Unit Number Length Width Depth Total
6 Columns Concrete m3 4 0.3 0.3 3 1.08

3.0 m
3.0 m

3.0 m

61
Slab & Beams
No. Item Unit Number Length Width Depth Total
7 Slab & Beams m3 2 5.3 0.3 0.5 1.59
2 4.5 0.3 0.5 1.35
1 5 4.2 0.15 3.15

0.15 m

5.0 m
0.5 m

4.5 m
4.8 m
4.2 m 15
cm

0.3 m

5.6 m 0.15 m
0.15 m

62 5.3
Take-off Summary Table
No. Item Unit Number Length Width Depth Total
1 Excavation m3 14.27
2 PC Concrete m3 3.07
3 RC Concrete m3 1.60
4 Ground Beams m3 2.94
5 Filling m3 6.66
6 Columns Concrete m3 1.08
7 Slab & Beams m3 6.09
Total Concrete 14.78

63
Reinforcement Takeoff
216 416+ 68/m .
30cm 0.3m x 0.5m

2.5cm 2.5cm

25cm 710/m

712/m

50cm 45cm

64
Reinforcement Takeoff
Unit No. of Length Total Unit Total
(kg) bars length Weight Weight
16 upper (beams) 4 4.8 19.2 1.63 31.296
4 5.6 22.4 1.63 36.512
16 lower (beams) 8 4.8 38.4 1.63 62.592
8 5.6 44.8 1.63 73.024
10 long (Slab) 34 5.6 190.4 0.63 119.952
12 short (Slab) 40 4.8 192 0.92 176.640
8 stirrup (beams) 60 1.55 93 0.41 38.130
51 1.55 79.05 0.41 32.411
Total Steel 570.557

65
Questions?

66

You might also like