System component ISO 8943 Jiskoot Benefits

Sample probe Device inserted into the line to extract an The same
LNG sample from the line

LNG sample vaporiser Apparatus to completely gasify the sample The same
extracted from the LNG line

Accumulator Vessel to absorb pressure pulsation and The same


homogenise the gasified LNG

Gasified LNG Compressor used for boosting pressure of Not required As the design of the Jiskoot system does not use the line pressure of
compressor gasified LNG to the gas sample holder the gasified LNG to 'fill' a gas sample holder this component of the
(if required) (if required) system is not required as the pressure differential between line and
gas outlet only needs to ensure a continuous flow through the
system.The system uses a positive displacement sampler to fill the gas
sample container (constant pressure sample receiver) rather than
relying on line pressure to provide a pressure equilibrium in the gas
sample holder.

Pressure regulator Maintains gas pressure constant at gas The same


sample holder inlet

Gas sample holder Holder used for collecting a continuous Not required The Jiskoot system has an automated sampler that allows significantly
stream of LNG more volume of gas through the system and extracts a significant
number (typically 5000) of 'grabs' which are immediately discharged
Compressor for Used to charge the sample collected in Not required into a piston type sample receiver where they are stored at
charging gas sample the gas sample holder into the gas sample approximately 20-40 bar. This avoids the need for the process of
container container bubbling to saturate the seal water, removes the need for a large gas
Gas sample container Used for the retention of the gas The same and also a pressurised sample holder to take a whole batch sample and as each grab is
sample for transportation to sample container discharged into a pressurised receiver avoids the need for a
lab/analysis equipment multistage sampling process with a compressor to evacuate the gas
sample holder. As three samples are taken concurrently a
repeatability check exists in the system design. Manual samples can
also be taken as a check

Repeatability Not stated Better than 0.15% for density and


calorific value

System operation Manual set-up of system flow System flow does not need
when unloading rate is stable to setting for every batch
ensure sample fills gas sample holder System takes samples of the
Must be stopped in the event of whole batch and not susceptible to
any rate/pressure changes changes in pressure or flow
Gas sample holder seal water Samples (1,2 or 3) are
must be saturated by 'bubbling' automatically taken and directly
Samples must be rapidly pressurised into the sample
transferred to sample container to receivers
avoid contamination
Gas sample receivers are manually
filled (risk of error)
Samples are stored at the
pressure of the evacuating
compressor

Maintenance Complicated and complex system Simple sample pumps and sample
with compressors and water-filled receivers are the only items
sample holders that needs regular requiring maintenance
maintenance Gas sample receivers

Cost and installation Expensive and complex (typically Simple and lower cost (typically
4m x 4m x 2.5m) 0.5m x 1.5 x 1.5m)

Jiskoot Limited - UK Jiskoot Incorporated - USA These are standard design specifications.
Goods Station Road, 14503 Bammel N, Houston #110, We operate a policy of continuous
Tunbridge Wells, Kent TN1 2DJ Houston,Texas, 77014. development and the information on this
Tel: +44 (0)1892 518000 Tel: +1 281 583 0583 sheet may be updated without notice.
Fax: +44 (0)1892 518100 Fax: +1 281 583 0587
Email: sales@jiskoot.com E-mail: sales@usa.jiskoot.com www.jiskoot.com

You might also like