You are on page 1of 19

NORTH COAST RAILWAY

LINE BEAMS ROAD


OVERPASS
(INDIVIDUAL ASSIGNMENT)

CIVIL DESIGN PROJECT


ENB476
Prepared for: Associate Prof Johnathan Bunker
Prepared by: Mohamad Jovi Prasetyo
(N9558403)
EXECUTIVE SUMMARY

As you reading this briefing report the feasibility study of this project has been done.
This report consist of the summary of the project brief it tells you of what is this project
about. It tells you the summary of the current condition of the nearby location and
whose interest need to be taken for consideration in this project

Besides all of those information this report also consist of how we manage to do the
feasibility study of this project and also the project package that we propose to
undertake this project. Mostly for the project package we try to use the simplest method
in terms of construction method to reduce the output of this project.

And at the end it tells you the team assignment and time table of things need to be done
in this semester. And we hope that we could execute this project properly and get a
good result which satisfies the clients and road users needs
Table of Contents & Figures

Contents
A.0 PROJECT BRIEF INFORMATION SUMMARY .................. ERROR! BOOKMARK NOT
DEFINED.
B.0 PROJECT TASK (STRUCTURAL) ..................................................................................... 1
C.0 PROJECT FEASIBILITY STUDY ........................................................................................ 4
C.1 TRAFFIC ANALYSIS .................................................................................................................................... 5
C.2 PROJECT LOCATION ANALYSIS................................................................................................................. 6
C.3 GEOTECHNICAL ENGINEERING ANALYSIS .............................................................................................. 8
C.4 OVERPASS STRUCTURE DESIGN............................................................................................................... 8
C.5 PEDESTRIAN RAMP DESIGN ..................................................................................................................... 8
D.0 THE MAIN COMPONENTS OF THE STUDY AREA ....................................................10
D.1 QUANTITATIVE ANALYSIS ....................................................................................................................... 8
D.2 QUALITATIVE ANALYSIS .......................................................................................................................... 8
D.3 THE ANALYSISNG TOOLS .......................................................................................................................... 8
D.4 WHOSE INTEREST NEED TO BETAKEN INTO CONSIDERATION .......................................................... 8
D.5 HOWLONG THE TIME PERIODS AND HORRIZONS ARE IMPORTANT FOR ANALYSIS ........................ 8
E.0 PROJECT PACKAGE..........................................................................................................11
E.1 FOUNDATION DESIGN .............................................................................................................................. 8
E.2 STRUCTURAL DESIGN ............................................................................................................................... 8
E.3 PEDISTRIAN RAMP DESIGN ..................................................................................................................... 8
F.0 GANTT CHART OF ACTIVITY NEED TO BE UNDERTAKE ...................................11
E.0 PROJECT PACKAGE..........................................................................................................11
E.0 PROJECT PACKAGE..........................................................................................................11

List of Figure
Figure 1: Carbon Dioxide Equivalent Emissions, Queensland .................................................... 3
Figure 2: Annual Global Temperature Anomalies ........................................................................ 3
Figure 3: Industrial Land Consumption .......................................................................................... 5
Figure 4: Annual Mean Temperature Anomaly ............................................................................. 6
Figure 5: Model of Industrial Building ....................................................................................... 7
Figure 6: Model of Industrial Building ....................................................................................... 7
Figure 7: Energy Produced ........................................................................................................... 8
Figure 8: Energy Consumption in Queensland .............................................................................. 9
Figure 9: Energy Consumption By Top 5 Industry Sectors in Queensland ............................... 9

I
A. Project Brief Information Summary

Beam road that located in the northern suburb of Brisbane city is predominately
classified as an arterial road that connecting urban area and suburban area in the
regional network. Therefore, beam road has an important function in east-west
arterial routes as it also provide access to suburbs along its axis.
Although Beam road categorizes as an arterial road, beam road does not provide
a primary freight route access. However, since it connects the Sandgate road and
Stanworth road where it linking to the access of gateway motorway. Now beam
road allow a limited freight vehicle (19m semi-trailer,not oversize) to access the
road.
Nevertheless Beam road also can be categorized as an environment-friendly road
for the cycling and also have 2 lanes dual carriageway. The only problem is that
there are three train tracks which is the North Coast Railway Line (NCRL) with
40m width that cutting the Beam not perpendicularly also still in the form of open
level crossing (OLC). With the facts that all the community services located near
the Carseldine train station shows that lots of people crossing the OLC every.
Nonetheless if we it look from a safety point of view, open level crossing is not
suitable for current traffic flow. Also based on Queensland Level Safety Strategy
Annual Report, in 2012 2021 the strategy aims to:
o Eliminate Level Crossing Collision
o Reduce the number of near miss incidents at level crossings
o Minimize the impact of any incidents that occur

Since the current OLC giving high workload zone which inherently risky.
Therefore, in this project we are assign to replace the Beam road OLC with Grade
Separated Overpass of the NCRL

1
B. Project Task
o Design the structural design of a four lane, dual carriageway bridge overpass
of the North Coast Railway line and preserved northern busway
corridor(including barriers and gantry signage structure), with a left side
shoulder bicycle lane of 2.0m width on each carriageway, along with a
separate 2.0m pedestrian path on each of the north and south sides of the
overpass
o Design the structural design of a pedestrian ramp from the pedestrian on the
northern side of the overpass, to land indicatively adjacent to the present bus
interchange at the Carseldine railway station

C. Project Feasibility Study


Here are the mind maps of how this project feasibility study will be done, We
divide it into 6 consecutive steps.

2
C.1. Traffic analysis

In this part of the study we will gather the information of :


o The road characteristic like the vehicle volume etc that will be used to
determine the work load of the overpass.
o Nearby public transportation: since we know that theres a Carseldine
train station which also have bus interchange. That indicate public
transport mode share would be high. Therefore, we need to know that,
does this project will be affecting the public transport timetable.
o City council plan for Beam road : we need to check whether this project
is oppose the Kedron city council plan.

C.2. Project location analysis

in this part we need to take account for all of the property nearby and do the risk
management like whether we need to do the property acquisition or not, here
are the list of nearby property:
o South-west quadrant: public open space and sporting field
o South-east quadrant: car-wrecker yard
o North-east quadrant: 25m unformed preserved corridor for the proposed
future extension of the Northern Busway (north-south) with residential
estate immediately to its east
o North-west quadrant: Carseldine railway station park & ride lot, passenger
set-down facility and bus interchange facility

Moreover, we need to analysis the suitable height and width of the overpass
since we need to design it based on the corresponding train tracks width and the
height of the electricity pole plus the suitable degree of incline for the disability
people.

3
C.3. Geotechnical Engineering Analysis

o Preliminary maps analysis : to determine the road chainage for the overpass
construction.
o Contour maps analysis : is done to check whether the project location is
located above some geological anomalies or not.
o Soil analysis : is done to determine the soil property like the soil strength
and layer, that will be used for designing the suitable foundation.
o Overview the underground service maps : to make sure that the project will
not accidently destroy the underground services

C.4. Overpass structure design


As you can see from the mind map it tells you step by step what we need to do in
this part of the study like we can determine the maximum load by the information
that we gather in traffic analysis etc. but the main thing from this part that we should
came up with one preliminary design that have higher allowable design load than
the maximum working load.

C.5. Pedestrian ramp design


After we finish with the dual carriage overpass we could just adjust the pedestrian
ramps design so that I can suit perfectly with overpass design aesthetic and also the
needs of the pedestrian. Besides those two reason, the overall calculation for this is
only take little amount of time compare to the overpass and also customizable

Each steps are done consecutively so that if one of the pervious steps doesnt pass the
feasibility study the rest of the steps would not be done. For example if this project
conflict with the city council plan why we need to bother by building an overpass and
also if the project location is located above type of soil that only could support limited
amount of load and you need load of earth work then why you need to continue with
the design study if its already cost so much until this stage.

4
D. The Main Components of the Structural Study Area
D.1 Quantitative Analysis
o Overpass Measurements
In this part we going to analyze the appropriate length and width of the
overpass so that we not design it to close to the electrical pole or to high
o Load Analysis
In this part we going to analyze the maximum load which is the working
load that we could determine from the vehicle volume and traffic flow
and also the design load which the load that can be supported by our
structural design
o Soil properties
In this part we analyze the soil properties that affecting the calculation
of foundation design such as bearing capacity, coefficient, and water
table
o Forces
In this part we analyze and calculate all the forces that working in the
structure such as bending moment, shear forces, and axial forces
(compression and tension)
o Money resource or budget
Last but not least we need to balancing between our design and the
budget itself

D.2. Qualitative Analysis


o Structural efficiency (to make sure that we not overly design our
structure)
o Materials grade and quality (to make sure that we not over spec the
structure material)
o Geological location (to make sure there no problem with the soil layer
below the structure)
o Where to put temporary crossing (to make sure we provide alternative
route)

5
o Weather impacts (to make sure the design is suitable with the usual
weather)
o Service installation along the overpass (ex/ storm water management,
cable installation, etc)

D.3. Analysis tools and measures of effectiveness


o Software
Google earth To get clearer view of the location
without going to the site
and can get preliminary
measurement

AutoCad To draw the blue print of the


design

Space Gass To do calculate structural forces

Microsoft Office To do the paper works

ETABS To determine the steel section for


the structure

Microsoft Project To tracking the design progress

o Guide code
Concrete design code in Australia and Steel design Code in Australia,
all of these code is used so that the structure is safe and adequate.
o Ratio between the maximum load and allowable design load (ratio of
effectiveness)

6
D.4. Whose interests need to be taken into consideration (stakeholders)
o Nearby property owner
o Train commuter
o Bus commuter
o Nearby society
o KCC
o Road user
o Public transportation department
o Consultant
o Owner
o Environment

D.5. How long the time periods (e.g. times of day, week, year) and horizons (e.g.
opening, 10 years, 25 years, 50 years) are important for analysis?

7
E. Project Package Design

White Hat Information

(what are the information need)

Red Hat Feeling Looking forward to came up with an


suitable and efficient structural design
(what are my feelings about this)
Worrying about unexpected risk that I
have to dealt with in the design process

Black Hat Weaknesses There are several private property around


the project location, this project will
(what is might wrong with this)
affecting nearby public transport, and
route diversion

Yellow Hat Strengths This project could reducing road users


workload, improve the traffic flow in
(what are the good Points?)
beams road, and reducing risk on OLC

Green Hat New Ideas Use precast material to speed up


construction, use the suitable material but
(what are the possibilities)
not expensive for pedestrian ramp such
as timber deck. Use the simplest structure
to speed up the design

8
Blue Hat Thinking Careful thinking , logic thinking, and
down to earth thinking
(what thinking is needed)

Based on all of the design thinking process above here are the proposed project package
design for this project.

E.1 Foundation Design

Where we begin to choosing or designing the appropriate structure we always


start by designing the suitable foundation type first. When we start designing a
foundation there are a certain check-list we should do

9
10
11
12
Table. E.1.1 Foundation selection (Shaw, 2008)

After we know what types of foundation that appropriate for this project we
could start designing it by calculation all the forces. And then we could choose
how the construction of the foundation will be done. But from my point of view
everything that precast is much more efficient in time and man power. For the
materials its depending on the type of foundation it self

E.2. Overpass structure design

In this part of design first thing to do is we determine what will be the working
load of the overpass. And then we choose which type of structure that suitable
for the overpass. In our opinion we would go with the precast segmental double-
T concrete that will be design in a little bit of an arch shape. The reason why we
propose precast concrete structure is the fact that precast concrete is generally
more durable than cast-in-place/in-situ concrete because of the controlled
environment when the manufacturer producing the precast concrete. Besides ,
the precast also reducing the rate of cracking in the deck slab that making it less
penetrable (smith, 2012).

The other reason why this structure is much better than the conventional one is
that based in Li (Li, 2010) is that
o Double-T design are valid for a range of span length used in highway
overpass (which almost the same like Railway overpass)
o Double-T design can reduce the systems sensitivity to post-
tensioning losses
o Compare to the conventional one the system is competitive by
comparing material use, cost, scheduling and aesthetic criteria.

But the main reason why choose precast and shaped a little bit like arch is that
we can reduce the length of the overpass while maintaining the required height
so that the overpass did not hit the electrical pole of the rail ways. Moreover,
this shape also can help reducing the materials, time, money and all other
resources that will be used.

13
E.3 Pedestrian Ramp design

In this part of the design we would to propose a pedestrian ramp design that still
follow the guideline that affecting level of service. There are three main factors
which are physical characteristic factors, location factors, and user factors. And
in our design we try to keep maintaining some of the important point of factors
from each factors such as for physical characteristic the main point is support
facilities, location factors main point is connectivity, and for the user factor
main points are personal security and mix path user (Gallin, 2001). These are
the main guideline for us to designing the pedestrian ramp.

For the detailed design of pedestrian ramp itself we want to propose of using
steel structure and timber deck. The reason of why we choosing this design is
that to minimize the material cost and also reducing time of the construction
since steel structure is way much more simple to build than a concrete structure
for a small scale structure.

14
F. Gantt Chart of Activity That Need To Be Undertake

1
G. Professional Attributes
The following findings of experiences and attributes of the team was found out from
the discussion process in this team
Member Experiences Job Suitable
Mohamad Jovi Prasetyo
Siu Chung Leung
John William Horasia
Nathan

H. Team Working Plan


H.1 Strategy
H.2 Behaviour and Professionalism
H.3 Communication
Nowadays communication isnt an issue anymore. There are lots of ways of how we
communicate. We can use Facebook Group for discussion, Phone call for urgent
matters, Dropbox for file sharing, and Microsoft online for writing the report. But
besides that we always have a physical meeting each week so that each person can
presenting their progress besides we can review our design as well.

H.4 Time management


H.5 Conflict Management

1.0 CONCLUSION

5.0 Reference List


References

You might also like