You are on page 1of 46

FIDIC CLAUSES COMPARISON

Practical guide for the most significant clauses in Red, Yellow and Silver book.
Composed by Pierluigi Spedicati.
CONSTRUCTION: late 14c., from Old French construction or directly from Latin constructionem (nominative constructio),
from construct-, past participle stem of construere "pile up together, accumulate; build, make, erect," from com- "together +
struere "to pile up".

1
ISSUE RED (2005) YELLOW (1999) SILVER (1999)



REGULATION Recommended for building Recommended for the Suitable for the provision on
AND and engineering works provision of electrical a turnkey basis of a process
WORKS designed by the Employer and/or mechanical plant or power plant, of a factory
or his representative, the and for the design and or similar facility, or of an
Engineer. Under the usual execution of building or infrastructure project or
arrangements for this type of engineering works. Under other type of development,
contract, the Contractor the usual arrangements for this where
constructs the works in type of contract, the 1. A higher degree of
accordance with a design Contractor designs and certainty of final price
provided by the Employer. provides, in accordance with and time is required,
However, the works may the Employers requirements, and
include some elements of plant and/or other works; 2. The Contractor takes
Contractor designed which may include any total responsibility for
civil, mechanical, electrical combination of civil, the design and
and/or construction works. mechanical, electrical and/or execution of the
construction works. project, with little
involvement of the
Employer.
Under the usual arrangements
for turnkey projects, the
Contractor carries out all the
Engineering, Procurement and
Construction (EPC): providing
a fully equipped facility, ready
for operation (at the turn of
the key).

2
CONTRACT The Contract is administered The Contract is administered There is Not Engineer. The
ADMINISTRATION? by the Engineer (appointed by by the Engineer (appointed by Contract is administered
the Employer) who shall the Employer) who shall directly by the Employer or its
determine any claim for determine any claim for representative who endeavours
extension of time and extension of time and to reach agreement with the
additional payment, certify additional payment, certify Contractor on each claim. The
payments and issue taking- payments and issue taking- Introductory Note to the
over and performance over and performance Silver Book emphasises that if
certificates. certificates. the Contractor is to achieve
the certainly of time and price
stipulated, then the
involvement of the Employer
must be limited to a minimum
during construction.
HO W A R E T H E R ISK S Risks are allocated on a fair Risks are allocated on a fair A majority of risks is allocated
ALLOCATED? and equitable basis taking and equitable basis taking to the Contractor under the
account of such matters as account of such matters as Contract, including any errors
insurability, and each party's insurability, and each party's in:
ability to foresee, and mitigateability to foresee, and mitigate
the effect of, the circumstancesthe effect of, the circumstances 1. Setting Out Data (Sub-
relevant to each risk.
relevant to each risk. Clause 4.7);
There are a number of key There are a number of key 2. Site data (Sub- Clause
risks that the Employer retains,risks that the Employer retains, 4.10);
for example: for example: 3. Unforeseeable difficulties
or costs (Sub-Clause 4.12).
1. Errors in the Setting Out 1. Errors in the Setting Out
data (Sub-Clause 4.7); data (Sub-Clause 4.7); The Contractor is expected to:
2. Site data (Sub-Clause 4.10); 2. Site data (Sub-Clause 4.10);
Price these risks; and/or
3. "Unforeseeable" Site risks 3. "Unforeseeable" Site risks
Carry out extensive due
3
ISSUE RED (2005) YELLOW (1999) SILVER (1999)

(Sub-Clause 4.12). (Sub-Clause 4.12). diligence to mitigate
risks.
As a result, the tender time can As a result, the tender time can A longer period for
be relatively short. be relatively short. preparation of a tender is
therefore usually required, in
particular to inspect the Site
and examine data hydrological
and subsurface data and also
to scrutinise the Employer's
Requirements.
THE DESIGN 4. 1 The Contractor shall 5. 1 The Contractor shall 5. 1 The Contractor shall be
- design (to the extent specified carry out, and be deemed to have scrutinised,
ER R O R S I N T H E in the Contract), execute and responsible for, the design prior to the Base Date, the
E M P L O Y E R S complete the Works in of the Works . Employer's Requirements
RE Q U I R E M E N T S accordance with the Design shall be prepared by (including design criteria and
Contract and with the qualified designers who are calculations, if any). The
Engineers instructions, and engineers who comply with the Contractor shall be responsible
shall remedy any defects in the criteria (if any) stated in the for the design of the Works
Works. Employer's Requirements. and for the accuracy of such
Except to the extent specified Unless otherwise stated in the Employer's Requirements
in the Contract, the Contractor Contract, the Contractor (including design criteria and
(i) Shall be responsible for all shall submit to the Engineer calculations), except as stated
Contractors Documents, for consent the name and below.
Temporary Works, and such particulars of each proposed The Employer shall not be
design of each item of Plant designer and design responsible for any error,
and Materials as is required for Subcontractor. inaccuracy or omission of
the item to be in accordance The Contractor warrants any kind in the Employer's
with the Contract, and that he, his designers and Requirements as originally
(ii) Shall not otherwise be design Subcontractor s have included in the Contract and

4
responsible for the design or the experience and shall not be deemed to have
specification of the Permanent capability necessary for the given any representation of
THE DESIGN Works. design. accuracy or completeness of
- The Contractor shall, The Contractor undertakes any data or information,
ER R O R S I N T H E whenever required by the that the designers shall be except as stated below. Any
E M P L O Y E R S Engineer, submit details of available to attend discussions data or information received
RE Q U I R E M E N T S the arrangements and with the Engineer at all by the Contractor, from the
methods, which the reasonable times, until the Employer or otherwise, shall
Contractor proposes to expiry date of the relevant not relieve the Contractor
adopt for the execution of Defects Notification Period. from his responsibility for
the Works. No significant Upon receiving notice under the design and execution of
alteration to these Sub-Clause8.1 [Commencement of the Works.
arrangements and methods Works], the Contractor shall However, the Employer
shall be made without this scrutinise the Employer's shall be responsible for the
having previously been Requirements (including correctness of the following
notified to the Engineer. design criteria and portions of the Employer's
If the Contract specifies that calculations) and the items of Requirements and of the
the Contractor shall design any reference mentioned in Sub- following data and information
part of the Permanent Clause 4.7 [Setting Out]. provided by (or on behalf of)
Works, Within the period stated in the the Employer:
then unless otherwise stated in the Appendix to Tender, (a) Portions, data and
Particular Conditions: calculated from the information which are stated
(a) The Contractor shall Commencement Date, the in the Contract as being
submit to the Engineer the Contractor shall give notice immutable or the responsibility
Contractors Documents for to the Engineer of any error, of the Employer,
this part in accordance with fault or other defect found in (b) Definitions of intended
the procedures specified in the the Employer's Requirements purposes of the Works or any
Contract; or these items of reference. parts thereof,
(b) These Contractors After receiving this notice, the (c) Criteria for the testing and

5
ISSUE RED (2005) YELLOW (1999) SILVER (1999)

Documents shall be in Engineer shall determine performance of the completed
THE DESIGN accordance with the whether Clause 13 [Variations Works, and
- Specification and Drawings, and Adjustments] shall be (d) Portions, data and
ER R O R S I N T H E shall be written in the language applied, >>> so, give notice information which cannot
E M P L O Y E R S for communications defined in to the Contractor accordingly.
RE Q U I R E M E N T S 1.4 [Law and Language], and If and to the extent that
shall include additional (taking account of cost and
information required by the time) an experienced
Engineer to add to the contractor exercising due
Drawings for co-ordination of care would have discovered
each the error, fault or other
Partys designs; defect when examining the
(c) The Contractor shall be Site and the Employer's
responsible for this part and it Requirements before
shall, when the Works are submitting the Tender , the
completed, be fit for such Time for Completion shall
purposes for which the part is not be extended and the
intended as are specified in the Contract Price shall not be
Contract; and adjusted.
(d) Prior to the
commencement of the Tests
on Completion, the Contractor
shall submit to the Engineer
the as-built documents and
operation and maintenance
manuals in accordance with
the Specification and in
sufficient detail for the
Employer to operate, maintain,

6
dismantle, reassemble, adjust
and repair this part of the
Works. Such part shall not be
THE DESIGN considered to be completed
- for the purposes of taking-
ER R O R S I N T H E over under Sub-Clause 10.1
E M P L O Y E R S [Taking Over of the Works
RE Q U I R E M E N T S and Sections] until these
documents and manuals have
been submitted to the
Engineer
ISSUE RED (2005) YELLOW (1999) SILVER (1999)
CONTRACT PRICE Unless otherwise stated in the Unless otherwise stated in the Unless otherwise stated in the
Particular Conditions: Particular Conditions: Particular Conditions:
(a) The Contract Price shall (a) The Contract Price shall be (a) Payment for the Works
be agreed or determined the lump sum accepted shall be made on the basis
under Sub-Clause 12.3 contract amount and be of the lump sum Contract
(below) and be subject to subject to adjustments in Price, subject to adjustments
adjustments in accordance accordance with the Contract; in accordance with the
with the Contract, (Sub-clause (b) The Contractor shall pay Contract;
12.3, For each item of work, the all taxes, duties and fees (b) The Contractor shall pay
appropriate rate or price for the item required to be paid by him all taxes, duties and fees
shall be the rate or price specified for under the Contract, and the required to be paid by him
such item in the Contract or, if there Contract Price shall not be under the Contract, and the
is no such item, specified for similar adjusted for any of these costs, Contract Price shall not be
work Any item of work included in except as stated in Sub-Clause adjusted for any of these costs,
the Bill of Quantities for which no 13.7 [Adjustments for Changes except as stated in Sub-
rate or price was specified shall be in Legislation]; Clause 13.7 [The Contract Price
considered as included in other rates (c) Any quantities which shall be adjusted to take account of
7
ISSUE RED (2005) YELLOW (1999) SILVER (1999)

CONTRACT PRICE and prices in the Bill of Quantities may be set out in a Schedule any increase or decrease in Cost
and will not be paid for separately. are estimated quantities and resulting from a change in the Laws
However, a new rate or price shall are not to be taken as the of the Country (including the
be appropriate for an item of work if actual and correct quantities introduction of new Laws and the
the price increase by more than 25% of the Works which the repeal or modification of existing
from the quantity of this item in the Contractor is required to Laws) or in the judicial or official
Bill of Quantities or other Schedule execute; governmental interpretation of such
but this item must not be specified (d) Any quantities or price Laws, made after the Base Date,
in the Contract as a fixed rate data, which may be set out in a which affect the Contractor in the
item"; Schedule, shall be used for the performance of obligations under the
CONTRACT PRICE (b) The Contractor shall pay purposes stated in the Contract.].
all taxes, duties and fees Schedule and may be
required to be paid by him inapplicable for other
under the Contract, and the purposes.
Contract Price shall not be However, if any part of the
adjusted for any of these costs Works is to be paid according
except as stated in Sub-Clause to quantity supplied or work
13.7 [Adjustments for Changes done, the provisions for
in Legislation]; measurement and evaluation
(c) Any quantities which shall be as stated in the
may be set out in the Bill of Particular Conditions. The
Quantities or other Schedule Contract Price shall be
are estimated quantities and determined accordingly,
are not to be taken as the subject to adjustments in
actual and correct quantities: accordance with the Contract.
1. Of the Works which the
Contractor is required to
execute, or
2. For the purposes of Clause

8
12 [Measurement and
Evaluation ];
(d) The Contractor shall
submit to the Engineer,
within 28 days after the
Commencement Date, a
proposed breakdown of
each lump sum price in the
Schedules. The Engineer may
take account of the breakdown
when preparing Payment
Certificates, but shall not be
bound by it.
(e) Notwithstanding the
provisions of subparagraph
(b), Contractors Equipment,
including essential spare parts
therefore, imported by the
Contractor for the sole
purpose of executing the
Contract shall be exempt from
the payment of import duties
and taxes upon importation.

9
ISSUE RED (2005) YELLOW (1999) SILVER (1999)

PAYMENT 14. 2 The Employer shall 14. 2 The Employer shall 14. 2 The Employer shall
make an advance payment, as make an advance payment, as make an advance payment,
an interest-free loan for an interest-free loan for as an interest-free loan for
mobilisation, when the mobilisation, when the mobilization and design,
Contractor submits a Contractor submits a when the Contractor
guarantee. Unless and until the guarantee. Unless and until the submits a guarantee.
Employer receives this Employer receives this Employer shall pay the first
PAYMENT guarantee, or if the total guarantee, or if the total instalment after receiving
advance payment is not stated advance payment is not stated (i) A Statement;
in the Contract Data (or in the Contract Data (or (ii) The Performance
Appendix to Tender), this Sub- Appendix to Tender), this Sub- Security(This guarantee shall be
Clause shall not apply. Clause shall not apply. issued by an entity and from within
The Engineer shall issue an The Engineer shall issue an a country (or other jurisdiction)
Interim Payment Certificate Interim Payment Certificate approved by the Employer, and shall
for the first instalment after: for the first instalment after: be in the form annexed to the
1. Receiving a Statement and 1. Receiving a Statement and Particular Conditions or in another
after the Employer after the Employer form approved by the Employer).
2. Receives: 2. Receives: 14. 3 The Contractor shall
(i) The Performance Security (i) The Performance Security submit a Statement in six
(ii) a guarantee in amounts (ii) a guarantee in amounts copies to the Employer after
and currencies equal to the and currencies equal to the the end of the period of
advance payment (This advance payment (This payment stated in the
guarantee shall be issued by an guarantee shall be issued by an Contract (if not stated, after
entity and from within a country (or entity and from within a country (or the end of each month), in a
other jurisdiction) approved by the other jurisdiction) approved by the form approved by the
Employer, and shall be in the form Employer, and shall be in the form Employer, showing in detail
annexed to the Particular annexed to the Particular the amounts to which the
Conditions or in another form Conditions or in another form Contractor considers himself
approved by the Employer.) approved by the Employer.) to be entitled, together with

10
14. 3 The Contractor shall 14. 3 The Contractor shall supporting documents.
submit a Statement in six submit a Statement in six If the Contract includes a
copies to the Engineer after copies to the Engineer after Schedule of Payments
the end of each month, in a the end of each month, in a specifying the instalments in
PAYMENT form approved by the form approved by the which the Contract Price will
Engineer, showing in detail the Engineer, showing in detail the be paid, then unless otherwise
amounts to which the amounts to which the stated in this Schedule.
Contractor considers himself Contractor considers himself 14. 4 If the Contract
to be entitled, together with to be entitled, together with includes a Schedule of
supporting documents which supporting documents which Payments specifying the
shall include the report on the shall include the report on the instalments in which the
progress during this month. progress during this month. Contract Price will be paid,
14. 4 If the Contract includes 14. 4 If the Contract includes then unless otherwise stated in
a schedule of payments a schedule of payments this Schedule:
specifying the instalments in specifying the instalments in (a) The instalments quoted in
which the Contract Price will which the Contract Price will the Schedule of Payments shall
be paid, then unless otherwise be paid, then unless otherwise be the estimated contract
stated in this schedule: stated in this schedule: (b) If these instalments are not
(a) The instalments quoted in (a) The instalments quoted in defined by reference to the
this schedule of payments shall this schedule of payments shall actual progress achieved in
be the estimated contract be the estimated contract executing the Works, and if
values. values. actual progress is found to be
(b) If these instalments are not (b) If these instalments are not less than that on which the
defined by reference to the defined by reference to the Schedule of Payments was
actual progress achieved in actual progress achieved in based, then the Employer may
executing the Works, and if executing the Works, and if proceed as follows:
actual progress is found to be actual progress is found to be - To agree or determine
less than that on which the less than that on which the revised instalments, which
Schedule of Payments was Schedule of Payments was shall take account of the extent

11
ISSUE RED (2005) YELLOW (1999) SILVER (1999)

based, then the Engineer may based, then the Engineer may to which progress is less than
proceed as follows: proceed as follows: that on which the instalments
PAYMENT - To agree or determine - To agree or determine were previously based.
revised instalments, which revised instalments, which If the Contract does not
shall take account of the extent shall take account of the extent include a Schedule of
to which progress is less than to which progress is less than Payments, the Contractor
that on which the instalments that on which the instalments shall submit non-binding
were previously based. were previously based. estimates of the payments,
If the Contract does not If the Contract does not which he expects to become
include a schedule of include a schedule of due during each quarterly
payments: payments: period.
The Contractor shall submit The Contractor shall submit The first estimate shall be
non-binding estimates of non-binding estimates of submitted within 42 days after
the payments, which he the payments, which he the Commencement Date.
expects to become due expects to become due Revised estimates shall be
during each quarterly during each quarterly submitted at quarterly
period. period. intervals, until the Taking-
The first estimate shall be The first estimate shall be Over Certificate has been
submitted within 42 days after submitted within 42 days after issued for the Works.
the Commencement Date. the Commencement Date.
Revised estimates shall be Revised estimates shall be
submitted at quarterly submitted at quarterly
intervals, until the Taking- intervals, until the Taking-
Over Certificate has been Over Certificate has been
issued for the Works. issued for the Works.

12
ISSUE RED (2005) YELLOW (1999) SILVER (1999)
ADDITIONAL TIME Various rights for the Various rights for the 8. 4 The Contractor shall be
OR Contractor to claim additional Contractor to claim additional entitled to an EOT if (and to
ADDITIONAL MONEY time OR money under the time OR money under the the extent that) completion for
- Contract for errors: Contract for errors: the purposes of Taking Over
UNFORESEEABLE PHYSICAL - In the Setting Out data - In the Setting Out data of the Works and Sections
CONDITIONS (Sub-Clause 4.7) (Sub-Clause 4.7) is or will be delayed by any of
Preamble: The Employer shall be Preamble: The Employer shall be the following causes:
responsible for any errors in these responsible for any errors in these (a) A Variation (unless an
specified or notified items of specified or notified items of adjustment to the Time for
reference, but the Contractor shall reference, but the Contractor shall Completion has been agreed
use reasonable efforts to verify their use reasonable efforts to verify their under Variation Procedure;
accuracy before they are used. accuracy before they are used. (b) A cause of delay giving an
However: if the Contractor However: if the Contractor entitlement to extension of
suffers delay and/or incurs suffers delay and/or incurs time under a Sub- Clause of
Cost from executing work Cost from executing work these Conditions;
which was necessitated by an which was necessitated by an (c) Any delay, impediment or
ADDITIONAL TIME error in these items of error in these items of prevention caused by (or
OR reference, and an reference, and an attributable to) the Employer,
ADDITIONAL MONEY experienced contractor experienced contractor the Employers Personnel, or
- could not reasonably have could not reasonably have the Employers other
UNFORESEEABLE PHYSICAL discovered such error and discovered such error and contractors on the Site.
CONDITIONS avoided this delay and/or avoided this delay and/or If the Contractor considers
Cost, Cost, himself to be entitled to an
The Contractor shall give The Contractor shall give EOT for Completion, the
notice to the Engineer and notice to the Engineer and Contractor shall give notice to
shall be entitled to: shall be entitled to: the Employer in accordance to
(a) An extension of time for (a) An extension of time for 20.1 When determining each
any such delay, if completion is any such delay, if completion is EOT under 20.1, the
13
ISSUE RED (2005) YELLOW (1999) SILVER (1999)

or will be delayed [8.4 EOT] or will be delayed [8.4 EOT] Employer shall review
OR OR previous determinations and
(b) Payment of any such (b) Payment of any such may increase, but shall not
Cost plus profit, which shall Cost plus profit, which shall decrease, the total extension of
be included in the Contract be included in the Contract time.
Price. Price. 20. [Contractors Claims].
- In the Site data - In the Site data If the Contractor considers
(Sub-Clause 4.10) (Sub-Clause 4.10) himself to be entitled to any
Preamble: The Employer shall Preamble: The Employer shall EOT for Completion and/or
have made available to the have made available to the any additional payment, under
Contractor for his information, prior Contractor for his information, prior any Clause of these Conditions
to the Base Date, all relevant data to the Base Date, all relevant data or otherwise in connection
in the Employers possession on sub- in the Employers possession on sub- with the Contract, the
surface and hydrological conditions surface and hydrological conditions Contractor shall give notice to
at the Site, including environmental at the Site, including environmental the Employer, describing the
aspects. The Employer shall aspects. The Employer shall event or circumstance giving
similarly make available to the similarly make available to the rise to the claim.
Contractor all such data, which Contractor all such data, which The notice shall be given as
ADDITIONAL TIME come into the Employers possession come into the Employers possession soon as practicable, and not
OR after the Base Date. The Contractor after the Base Date. The Contractor later than 28 days after the
ADDITIONAL MONEY shall be responsible for interpreting shall be responsible for interpreting Contractor became aware,
- all such data. all such data. or should have become
UNFORESEEABLE PHYSICAL In this clause, there are not In this clause, there are not aware, of the event or
CONDITIONS provision, it can be used the provision, it can be used the circumstance.
remedy for the clause n. 4.7. remedy for the clause n. 4.7. If the Contractor fails to give
- Unforeseen Site risks - Unforeseen Site risks notice of a claim within such
(Sub-Clause 4.12) (Sub-Clause 4.12) period of 28 days, the Time for
If the Contractor encounters If the Contractor encounters Completion shall not be
adverse physical conditions, adverse physical conditions, extended, the Contractor shall

14
which he considers to have which he considers to have not be entitled to additional
been Unforeseeable, the been Unforeseeable, the payment, and the Employer
Contractor shall give notice Contractor shall give notice shall be discharged from all
to the Engineer as soon as to the Engineer as soon as liability in connection with the
practicable. practicable. claim.
If and to the extent that the If and to the extent that the
Contractor encounters Contractor encounters
physical conditions which are physical conditions which are
Unforeseeable, gives such a Unforeseeable, gives such a
notice, and suffers delay notice, and suffers delay
and/or incurs Cost due to and/or incurs Cost due to
these conditions, the these conditions, the
Contractor shall be entitled Contractor shall be entitled
to: to:
(a) An extension of time for (a) An extension of time for
any such delay, if completion is any such delay, if completion is
or will be delayed [8.4 - EOT] or will be delayed [8.4 - EOT]
OR OR
(b) Payment of any such (b) Payment of any such
ADDITIONAL TIME Cost, which shall be included Cost, which shall be included
OR in the Contract Price. in the Contract Price.
ADDITIONAL MONEY BE CAREFULT TO THIS BE CAREFULT TO THIS
- PROVISION > However, PROVISION > However,
UNFORESEEABLE PHYSICAL before additional Cost is finally before additional Cost is finally
CONDITIONS agreed or determined agreed or determined
The Engineer may also The Engineer may also
review whether other review whether other
physical conditions in physical conditions in
similar parts of the Works similar parts of the Works

15
ISSUE RED (2005) YELLOW (1999) SILVER (1999)

and > (if any) were more and > (if any) were more
favourable than could favourable than could
reasonably have been reasonably have been
foreseen foreseen
when the Contractor when the Contractor
submitted the Tender and if submitted the Tender and if
the extent that these more the extent that these more
favourable conditions were favourable conditions were
encountered, the Engineer encountered, the Engineer
may to agree or determine the may to agree or determine the
reductions in Cost which were reductions in Cost which were
due to these conditions, which due to these conditions, which
may be included (as may be included (as
deductions) in the Contract deductions) in the Contract
Price and Payment Certificates Price and Payment Certificates
PO S S E S S I O N
AND The Employer shall give the The Employer shall give the The Employer shall give the
ACCESS TO THE SITE Contractor right of access to, Contractor right of access to, Contractor right of access
and possession of, all parts and possession of, all parts to, and possession of, all the
of the Site within the time of the Site within the time Site parts of the Site within
(or times) stated in the (or times) stated in the the time (or times) stated in
Contract Data. The right and Contract Data. The right and the Particular Conditions.
possession may not be possession may not be The right and possession may
exclusive to the Contractor. If, exclusive to the Contractor. If, not be exclusive to the
under the Contract, the under the Contract, the Contractor. If, under the
Employer is required to give Employer is required to give Contract, the Employer is
(to the Contractor) possession (to the Contractor) possession required to give (to the
of any foundation, structure, of any foundation, structure, Contractor) possession of any
plant or means of access, the plant or means of access, the foundation, structure, plant or
Employer shall do so in the Employer shall do so in the means of access, the Employer

16
time and manner stated in the time and manner stated in the shall do so in the time and
Specification. However, the Specification. However, the manner stated in the
Employer may withhold any Employer may withhold any Employers Requirements.
such right or possession until such right or possession until However, the Employer may
the Performance Security the Performance Security withhold any such right or
has been received. has been received. possession until the
If no such time is stated in the If no such time is stated in the Performance Security has
Contract Data, the Employer Contract Data, the Employer been received.
shall give the Contractor shall give the Contractor If no such time is stated in the
right of access to, and right of access to, and Particular Conditions, the
possession of, the Site possession of, the Site Employer shall give the
within such times as may be within such times as may be Contractor right of access to,
require o enable the require o enable the and possession of, the Site
Contractor to proceed in Contractor to proceed in with effect from the
accordance with the accordance with the Commencement Date.
PO S S E S S I O N
AND programme submitted under programme submitted under If the Contractor suffers delay
ACCESS TO THE SITE 8.3 [Programme]. 8.3 [Programme]. and/or incurs Cost as a result
If the Contractor suffers delay If the Contractor suffers delay of a failure by the Employer to
and/or incurs Cost as a result and/or incurs Cost as a result give any such right or
of a failure by the Employer to of a failure by the Employer to possession within such time,
give any such right or give any such right or the Contractor shall give
possession within such time, possession within such time, notice to the Employer and
the Contractor shall give the Contractor shall give shall be entitled subject to:
notice to the Engineer and notice to the Engineer and (a) An extension of time for
shall be entitled to: shall be entitled to: any such delay, if completion is
(a) An extension of time for (a) An extension of time for or will be delayed, [EOT]
any such delay, if completion is any such delay, if completion is OR
or will be delayed, [EOT] or will be delayed, [EOT] (b) Payment of any such
OR OR Cost plus profit, which shall

17
ISSUE RED (2005) YELLOW (1999) SILVER (1999)

(b) Payment of any such (b) Payment of any such be included in the Contract
Cost plus profit, which shall Cost plus profit, which shall Price.
be included in the Contract be included in the Contract After receiving this notice, the
Price. Price. Employer shall proceed in
After receiving this notice, the After receiving this notice, the accordance with Sub-Clause
Engineer shall proceed in Engineer shall proceed in 3.5 [Determinations] to agree
accordance with se 3.5 accordance with se 3.5 or determine these matters.
[Determinations] to agree or [Determinations] to agree or However, if and to the extent
determine these matters. determine these matters. that the Employers failure was
However, if and to the extent However, if and to the extent caused by any error or delay by
that the Employers failure was that the Employers failure was the Contractor, including an
caused by any error or delay by caused by any error or delay by error in, or delay in the
the Contractor, including an the Contractor, including an submission of, any of the
error in, or delay in the error in, or delay in the Contractors Documents, the
submission of, any of the submission of, any of the Contractor shall not be entitled
Contractors Documents, the Contractors Documents, the to such extension of time, Cost
Contractor shall not be entitled Contractor shall not be entitled or profit.
to such extension of time, Cost to such extension of time, Cost
or profit. or profit.

18
ISSUE RED (2005) YELLOW (1999) SILVER (1999)
TE S T S
ON 9. 1 The Contractor shall 9. 1 The Contractor shall 9. 1 The Contractor shall
COMPLETION carry out the Tests on carry out the Tests on carry out the Tests on
Completion. Completion. Completion.
The Contractor shall give to The Contractor shall give to The Contractor shall give to
the Engineer not less than 21 the Engineer not less than 21 the Employer not less than 21
days notice of the date after days notice of the date after days notice of the date after
which the Contractor will be which the Contractor will be which the Contractor will be
ready to carry out each of ready to carry out each of ready to carry out each of
the Tests on Completion. the Tests on Completion. the Tests on Completion.
Unless otherwise agreed, Unless otherwise agreed, Unless otherwise agreed,
Tests on Completion shall Tests on Completion shall Tests on Completion shall
be carried out within 14 days be carried out within 14 days be carried out within 14 days
after this date, on such day after this date, on such day after this date, on such day
or days as the Engineer or days as the Engineer or days as the Employer
shall instruct. shall instruct. shall instruct.
In considering the results of Unless otherwise stated in the Unless otherwise stated in the
the Tests on Completion, the Particular Conditions, the Particular Conditions, the
Engineer shall make Tests on Completion shall be Tests on Completion shall be
allowances for the effect of carried out in the following carried out in the following
any use of the Works by the sequence: sequence:
Employer on the performance (A) (A)
or other characteristics of the PRE-COMMISSIONING TESTS PRE-COMMISSIONING TESTS,
Works. As soon as the Works, which shall include the which shall include the
or a Section, have passed any appropriate inspections and appropriate inspections and
Tests on Completion, the ("dry" or "cold") functional (dry or cold) functional
Contractor shall submit a tests to demonstrate that tests to demonstrate that
certified report of the results each item of Plant can safely each item of Plant can safely
of these Tests to the undertake the next stage, under-take the next stage,
19
ISSUE RED (2005) YELLOW (1999) SILVER (1999)

Engineer. (b); (b);
9. 2 If the Tests on (B) (B)
Completion are being unduly COMMISSIONING TESTS, COMMISSIONING TESTS,
delayed by the Contractor, the which shall include the which shall include the
Engineer may by notice specified operational tests to specified operational tests to
require the Contractor to demonstrate that the Works demonstrate that the Works
carry out the Tests within 21 or Section can be operated or Section can be operated
days after receiving the safely and as specified, safely and as specified,
notice. The Contractor shall under all available operating under all available operating
carry out the Tests on such day conditions; and conditions; and
or days within that period as (c) (c)
the Contractor may fix and of TRIAL OPERATION, TRIAL OPERATION,
which he shall give notice to which shall demonstrate that which shall demonstrate that
the Engineer. the Works or Section the Works or Section
If the Contractor fails to carry perform reliably and in perform reliably and in
out the Tests on Completion accordance with the accordance with the
within the period of 21 days, Contract. Contract.
the Employers Personnel During trial operation, when During trial operation, when
may proceed with the Tests the Works are operating under the Works are operating under
at the risk and cost of the stable conditions, the stable conditions, the
Contractor. The Tests on Contractor shall give notice Contractor shall give notice
Completion shall then be to the Engineer that the to the Employer that the
deemed to have been carried Works are ready for any Works are ready for any
out in the presence of the other Tests on Completion, other Tests on Completion,
Contractor and the results of including performance tests to including performance tests to
the Tests shall be accepted as demonstrate whether the demonstrate whether the
accurate. Works conform with criteria Works conform with criteria
9.4 Failure to pass tests specified in the Employer's specified in the Employers
If the Works, or a Section, fail Requirements and with the Requirements and with the

20
to pass the Tests on Schedule of Guarantees. Performance Guarantees.
Completion repeated under Trial operation shall not Trial operation shall not
Sub- Clause 9.3 [Retesting], the constitute a taking-over constitute a taking-over
Engineer shall be entitled to: under Clause 10 under Clause 10
(a) Order further repetition of [Employers Taking Over]. [Employers Taking Over].
Tests on Completion under Unless otherwise stated in the Unless otherwise stated in the
Sub-Clause 9.3; Particular Conditions, any Particular Conditions, any
(b) If the failure deprives the product produced by the product produced by the
Employer of substantially the Works during trial operation Works during trial operation
whole benefit of the Works or shall be the property of the shall be the property of the
Section, reject the Works or Employer. Employer.
Section (as the case may be), in In considering the results of In considering the results of
which event the Employer the Tests on Completion, the the Tests on Completion,
shall have the same remedies Engineer shall make appropriate allowances shall be
as are provided in allowances for the effect of made for the effect of any use
subparagraph (c) of Sub- any use of the Works by the of the Works by the Employer
Clause 11.4 [Failure to Remedy Employer on the performance on the performance or other
Defects]; or or other characteristics of the characteristics of the Works.
(c) Issue a Taking-Over Works. As soon as the Works, As soon as the Works, or a
Certificate, if the Employer so or a Section, have passed each Section, have passed each of
requests. of the Tests on Completion the Tests on Completion
But in this case >> the described in sub-paragraph (a), described in sub-paragraph (a),
Contractor shall proceed in (b) or (c), the Contractor (b) or (c), the Contractor
accordance with all other shall submit a certified shall submit a certified
obligations under the Contract, report of the results of these report of the results of these
and the Contract Price shall be Tests to the Engineer. Tests to the Employer.
reduced by such amount as 9. 2 If the Tests on 9.2 If the Tests on Completion
shall be appropriate to cover Completion are being unduly are being unduly delayed by
the reduced value to the delayed by the Contractor, the the Contractor, the Employer

21
ISSUE RED (2005) YELLOW (1999) SILVER (1999)

Employer as a result of this Engineer may by notice may by notice require the
failure. Unless the relevant require the Contractor to carry Contractor to carry out the
reduction for this failure is out the Tests within 21 days Tests within 21 days after
stated (or its method of after receiving the notice. receiving the notice. The
calculation is defined) in the The Contractor shall carry out Contractor shall carry out the
Contract, the Employer may the Tests on such day or days Tests on such day or days
require the reduction to be within that period as the within that period as the
(i) Agreed by both Parties (in Contractor may fix and of Contractor may fix and of
full satisfaction of this failure which he shall give notice to which he shall give notice to
only) and paid before this the Engineer. the Employer.
Taking-Over Certificate is If the Contractor fails to If the Contractor fails to
issued; carry out the Tests on carry out the Tests on
(ii) Determined and paid Completion within the Completion; within the
under Sub-Clause 2.5 period of 21 days, the period of 21 days, the
[Employers Claims] and Sub- Employer's Personnel may Employers Personnel may
Clause 3.5 [Determinations]. proceed with the Tests at proceed with the Tests et
the risk and cost of the the risk and cost of the
Contractor. The Tests on Contractor. These Tests on
Completion shall then be Completion shall then be
deemed to have been carried deemed to have been carried
out in the presence of the out in the presence of the
Contractor and the results of Contractor and the results of
the Tests shall be accepted as the Tests shall be accepted as
accurate. accurate.
9.4 Failure to pass tests 9.4 Failure to pass tests
If the Works, or a Section, fail If the Works, or a Section, fail
to pass the Tests on to pass the Tests on
Completion repeated under Completion repeated under
Sub-Clause 9.3 [Retesting], the Sub- Clause 9.3 [Retesting], the

22
Engineer shall be entitled Employer shall be entitled
to: to:
(a) Order further repetition of (a) Order further repetition of
Tests on Completion under Tests on Completion under
Sub-Clause 9.3; Sub-Clause 9.3;
(b) If the failure deprives the (b) If the failure deprives the
Employer of substantially the Employer of substantially the
whole benefit of the Works or whole benefit of the Works or
Section, reject the Works or Section, reject the Works or
Section (as the case may be), in Section (as the case may be), in
which event the Employer which event the Employer
shall have the same remedies shall have the same remedies
as are provided in sub- as are provided in sub-
paragraph (c) of Sub-Clause paragraph (c) of Sub-Clause
11.4 [Failure to Remedy 11.4 [Failure to Remedy Defects];
Defects]; (c) Issue a Taking-Over
(c) Issue a Taking-Over Certificate.
Certificate. But in this case >> the
But in this case >> the Contractor shall proceed in
Contractor shall then proceed accordance with all other
in accordance with all other obligations under the Contract,
obligations under the Contract, and the Contract Price shall be
and the Contract Price shall be reduced by such amount as
reduced by such amount as shall be appropriate to cover
shall be appropriate to cover the reduced value to the
the reduced value to the Employer as a result of this
Employer as a result of this failure. Unless the relevant
failure. Unless the relevant reduction for this failure is
reduction for this failure is stated (or its method of

23
ISSUE RED (2005) YELLOW (1999) SILVER (1999)

stated (or its method of calculation is defined) in the
calculation is defined) in the Contract: the Employer may
Contract: the Employer may require the reduction to be
require the reduction to be (i) Agreed by both Parties (in
(i) Agreed by both Parties (in full satisfaction of this failure
full satisfaction of this failure only) and paid before this
only) and paid before this Taking-Over Certificate is
Taking-Over Certificate is issued;
issued; (ii) Determined and paid
(ii) Determined and paid under Sub-Clause 2.5
under Sub-Clause 2.5 [Employers Claims] and Sub-
[Employers Claims] and Sub- Clause 3.5 [Determinations].
Clause 3.5 [Determinations].
TAKING OVER 10. 1 Except as stated in Sub-Clause 10. 1 Except as stated in Sub-Clause 10. 1 Except as stated in Sub-Clause
9.4 [Failure to Pass Tests on 9.4 [Failure to Pass Tests on 9.4 [Failure to Pass Tests on
Completion], the Works shall be Completion], the Works shall be Completion], the Works shall be
taken over by the Employer taken over by the Employer taken over by the Employer
when when when
(i) The Works have been (i) The Works have been (i) The Works have been
completed in accordance completed in accordance completed in accordance with
with the Contract, including with the Contract, including the Contract, including the
the matters described in Sub- the matters described in Sub- matters described in 8.2 [Time
Clause 8.2 [Time for Completion] Clause 8.2 [Time for Completion] for Completion] and except as
and except as allowed in sub- and except as allowed in sub- allowed in sub-paragraph (a)
paragraph (a) below, and paragraph (a) below, and below;
(ii) A Taking-Over (ii) A Taking-Over (ii) A Taking-Over Certificate
Certificate for the Works has Certificate for the Works has for the Works has been issued,
been issued, or is deemed to been issued, or is deemed to or is deemed to have been
have been issued in accordance have been issued in accordance issued in accordance with this

24
with this Sub-Clause. with this Sub-Clause. Sub-Clause.
The Contractor may apply by The Contractor may apply by The Contractor may apply
notice to the Engineer for a notice to the Engineer for a by notice to the Employer
TAKING OVER Taking-Over Certificate not Taking-Over Certificate not for a Taking-Over
earlier than 14 days before the earlier than 14 days before the Certificate not earlier than
Works will, in the Contractors Works will, in the Contractors 14 days before the Works
opinion, be complete and opinion, be complete and will, in the Contractors
ready for taking over. If the ready for taking over. If the opinion, be complete and
Works are divided into Works are divided into ready for taking over.
Sections, the Contractor may Sections, the Contractor may If the Works are divided into
similarly apply for a Taking- similarly apply for a Taking- Sections, the Contractor may
Over Certificate for each Over Certificate for each similarly apply for a Taking-
Section. Section. Over Certificate for each
The Engineer shall, within The Engineer shall, within Section.
28 days after receiving the 28 days after receiving the The Employer shall, within 28
Contractors application: Contractors application: days after receiving the
(a) Issue the Taking-Over (a) Issue the Taking-Over Contractors application:
Certificate to the Contractor, Certificate to the Contractor, (a) Issue the Taking-Over
stating the date on which stating the date on which Certificate to the Contractor,
the Works or Section were the Works or Section were stating the date on which
completed in accordance completed in accordance the Works or Section were
with the Contract, except for with the Contract, except for completed in accordance
any minor outstanding work any minor outstanding work with the Contract, except for
and defects which will not and defects which will not any minor outstanding work
substantially affect the use of substantially affect the use of and defects which will not
the Works or Section for their the Works or Section for their substantially affect the use of
intended purpose (either until intended purpose (either until the Works or Section for their
or whilst this work is or whilst this work is intended purpose (either until
completed and these defects completed and these defects or whilst this work is

25
ISSUE RED (2005) YELLOW (1999) SILVER (1999)

are remedied) are remedied) completed and these defects
or or are remedied)
or
(b) Reject the application, (b) Reject the application, (b) Reject the application,
TAKING OVER giving reasons and giving reasons and giving reasons and
specifying the work required specifying the work required specifying the work required
to be done by the Contractor to be done by the Contractor to be done by the Contractor
to enable the Taking-Over to enable the Taking-Over to enable the Taking-Over
Certificate to be issued. The Certificate to be issued. The Certificate to be issued. The
Contractor shall then complete Contractor shall then complete Contractor shall then complete
this work before issuing a this work before issuing a this work before issuing a
further notice under this Sub- further notice under this Sub- further notice under this Sub-
Clause. Clause. Clause.
If the Engineer fails either to If the Engineer fails either to If the Employer fails either to
issue the Taking-Over issue the Taking-Over issue the Taking-Over
Certificate or to reject the Certificate or to reject the Certificate or to reject the
Contractors application within Contractors application within Contractors application within
the period of 28 days, and if the period of 28 days, and if the period of 28 days, and if
the Works or Section (as the the Works or Section (as the the Works or Section (as the
case may be) are substantially case may be) are substantially case may be) are substantially
in accordance with the in accordance with the in accordance with the
Contract, the Taking-Over Contract, the Taking-Over Contract, the Taking-Over
Certificate shall be deemed Certificate shall be deemed Certificate shall be deemed
to have been issued on the to have been issued on the to have been issued on the
last day of that period. last day of that period. last day of that period.
10. 2 The Engineer may, at the 10. 2 The Engineer may, at the 10. 2 Parts of the Works
sole discretion of the sole discretion of the (other than Sections) shall not
Employer, issue a Taking-Over Employer, issue a Taking-Over be taken over or used by the
Certificate for any part of the Certificate for any part of the Employer, except as may be

26
Permanent Works. Permanent Works. stated in the Contract or as
The Employer shall not use The Employer shall not use may be agreed by both Parties.
any part of the Works (other any part of the Works (other
than as a temporary measure than as a temporary measure
which is either specified in the which is either specified in the
Contract or agreed by both Contract or agreed by both
TAKING OVER Parties) unless and until the Parties) unless and until the
Engineer has issued a Engineer has issued a
Taking-Over Certificate for Taking-Over Certificate for
this part. However, if the this part. However, if the
Employer does use any part of Employer does use any part of
the Works before the Taking- the Works before the Taking-
Over Certificate is issued: Over Certificate is issued:
(a) The part which is used (a) The part which is used
shall be deemed to have shall be deemed to have
been taken over as from the been taken over as from the
date on which it is used, date on which it is used,
(b) The Contractor shall (b) The Contractor shall
cease to be liable for the cease to be liable for the
care of such part as from care of such part as from
this date, when responsibility this date, when responsibility
shall pass to the Employer, shall pass to the Employer,
and and
(c) If requested by the (c) If requested by the
Contractor, the Engineer Contractor, the Engineer
shall issue a Taking-Over shall issue a Taking-Over
Certificate for this part. Certificate for this part.
After the Engineer has issued a After the Engineer has issued a
Taking-Over Certificate for a Taking-Over Certificate for a

27
ISSUE RED (2005) YELLOW (1999) SILVER (1999)

part of the Works, the part of the Works, the
Contractor shall be given the Contractor shall be given the
earliest opportunity to take earliest opportunity to take
such steps as may be necessary such steps as may be necessary
to carry out any outstanding to carry out any outstanding
Tests on Completion. Tests on Completion.
The Contractor shall carry out The Contractor shall carry out
TAKING OVER these Tests on Completion as these Tests on Completion as
soon as practicable before the soon as practicable before the
expiry date of the relevant expiry date of the relevant
Defects Notification Period. Defects Notification Period.
If the Contractor incurs Cost If the Contractor incurs Cost
as a result of the Employer as a result of the Employer
taking over and/or using a taking over and/or using a
part of the Works, other than part of the Works, other than
such use as is specified in the such use as is specified in the
Contract or agreed by the Contract or agreed by the
Contractor, the Contractor Contractor, the Contractor
shall shall
(i) Give notice to the (i) Give notice to the
Engineer; Engineer;
(ii) Be entitled to 20.1 (ii) Be entitled subject to 20.1
[Contractors Claims] to [Contractors Claims] to
payment of any such Cost payment of any such Cost
plus profit, which shall be plus profit, which shall be
included in the Contract included in the Contract
Price. After this notice, the Price. After this notice, the
Engineer (3.5) to agree or Engineer (3.5) to agree or
determine this Cost and profit. determine the Cost and profit.

28
ISSUE RED (2005) YELLOW (1999) SILVER (1999)
CL A I M S 20. 1 Contractors claim 20. 1 Contractors claim 20. 1 Contractors claim
If the Contractor considers If the Contractor considers If the Contractor considers
himself to be entitled to any himself to be entitled to any himself to be entitled to any
EOT EOT EOT
and/or and/or and/or
any additional payment, any additional payment, any additional payment,
under any Clause of these under any Clause of these under any Clause of these
Conditions or otherwise in Conditions or otherwise in Conditions or otherwise in
connection with the Contract, connection with the Contract, connection with the Contract,
the Contractor shall give the Contractor shall give the Contractor shall give
notice to the Engineer, notice to the Engineer, notice to the Employer,
describing the event or describing the event or describing the event or
circumstance giving rise to the circumstance giving rise to the circumstance giving rise to the
claim. The notice shall be claim. The notice shall be claim. The notice shall be
given as soon as practicable, given as soon as practicable, given as soon as practicable,
and not later than 28 days and not later than 28 days and not later than 28 days
after the Contractor became after the Contractor became after the Contractor became
aware, or should have aware, or should have aware, or should have
become aware, of the event become aware, of the event become aware, of the event
or circumstance. or circumstance. or circumstance.
If the Contractor fails to give If the Contractor fails to give If the Contractor fails to give
notice of a claim within such notice of a claim within such notice of a claim within such
period of 28 days, the Time period of 28 days, the Time period of 28 days, the Time
for Completion shall not be for Completion shall not be for Completion shall not be
extended, the Contractor shall extended, the Contractor shall extended, the Contractor shall
not be entitled to additional not be entitled to additional not be entitled to additional
payment, and the Employer payment, and the Employer payment, and the Employer
shall be discharged from all shall be discharged from all shall be discharged from all
29
ISSUE RED (2005) YELLOW (1999) SILVER (1999)

liability in connection with the liability in connection with the liability in connection with the
claim. Otherwise, the claim. Otherwise, the claim. Otherwise, the
CL A I M S following provisions of this following provisions of this following provisions of this
Sub-Clause shall apply. Sub-Clause shall apply. Sub-Clause shall apply.
The Contractor shall also The Contractor shall also The Contractor shall also
submit any other notices submit any other notices submit any other notices
which are required by the which are required by the which are required by the
Contract, and supporting Contract, and supporting Contract, and supporting
particulars for the claim, all as particulars for the claim, all as particulars for the claim, all as
relevant to such event or relevant to such event or relevant to such event or
circumstance. circumstance. circumstance.
The Contractor shall keep The Contractor shall keep The Contractor shall keep
such contemporary records such contemporary records such contemporary records
as may be necessary to as may be necessary to as may be necessary to
substantiate any claim, either substantiate any claim, either substantiate any claim, either
on the Site or at another on the Site or at another on the Site or at another
location acceptable to the location acceptable to the location acceptable to the
Engineer. Engineer. Employer.
Without admitting the Without admitting the Without admitting the
Employers liability, the Employers liability, the Employers liability, the
Engineer may, after receiving Engineer may, after receiving Employer may, after
any notice under this Sub- any notice under this Sub- receiving any notice under this
Clause, monitor the record- Clause, monitor the record- Sub-Clause, monitor the
keeping and/or instruct the keeping and/or instruct the record-keeping and/or
Contractor to keep further Contractor to keep further instruct the
contemporary records. contemporary records. Contractor to keep further
The Contractor shall permit The Contractor shall permit contemporary records.
the Engineer to inspect all the Engineer to inspect all The Contractor shall permit
these records, and shall (if these records, and shall (if the Employer to inspect all

30
instructed) submit copies to instructed) submit copies to these records, and shall (if
the Engineer. the Engineer. instructed) submit copies to
Within 42 days after the Within 42 days after the the Employer.
CL A I M S Contractor became aware Contractor became aware Within 42 days after the
(or should have become (or should have become Contractor became aware
aware) of the event or aware) of the event or (or should have become
circumstance giving rise to the circumstance giving rise to the aware) of the event or
claim, or within such other claim, or within such other circumstance giving rise to the
period as may be proposed by period as may be proposed by claim, or within such other
the Contractor and approved the Contractor and approved period as may be proposed by
by the Engineer, the by the Engineer, the the Contractor and approved
Contractor shall send to the Contractor shall send to the by the Employer, the
Engineer a fully detailed Engineer a fully detailed Contractor shall send to the
claim which includes: claim which includes: Employer a fully detailed
1. Full supporting 3. Full supporting claim which includes:
particulars of the basis of particulars of the basis of d. Full supporting
the claim; the claim; particulars of the basis of
2. The extension of time 4. The extension of time the claim;
and/or additional and/or additional e. The extension of time
payment claimed. payment claimed. and/or additional
If the event or circumstance If the event or circumstance payment claimed.
giving rise to the claim has a giving rise to the claim has a If the event or circumstance
continuing effect: continuing effect: giving rise to the claim has a
a. This fully detailed claim a. This fully detailed claim continuing effect:
shall be considered as shall be considered as a. This fully detailed claim
interim; interim; shall be considered as
b. The Contractor shall b. The Contractor shall interim;
send further interim send further interim b. The Contractor shall
claims at monthly claims at monthly send further interim

31
ISSUE RED (2005) YELLOW (1999) SILVER (1999)

intervals, giving the intervals, giving the claims at monthly
accumulated delay accumulated delay intervals, giving the
and/or amount claimed, and/or amount claimed, accumulated delay
and such further and such further and/or amount claimed,
CL A I M S particulars as the particulars as the and such further
Engineer may reasonably Engineer may reasonably particulars as the
require; require; Employer may
c. The Contractor shall c. The Contractor shall reasonably require;
send a final claim within send a final claim within c. The Contractor shall
28 days after the end of 28 days after the end of send a final claim within
the effects resulting from the effects resulting from 28 days after the end of
the event or circumstance, the event or circumstance, the effects resulting from
or within such other period or within such other period the event or circumstance,
as may be proposed by the as may be proposed by the or within such other period
Contractor and approved Contractor and approved as may be proposed by the
by the Engineer. by the Engineer. Contractor and approved
Within 42 days after Within 42 days after by the Employer.
receiving a claim or any receiving a claim or any Within 42 days after
further particulars supporting a further particulars supporting a receiving a claim or any
previous claim, or within such previous claim, or within such further particulars supporting a
other period as may be other period as may be previous claim, or within such
proposed by the Engineer and proposed by the Engineer and other period as may be
approved by the Contractor, approved by the Contractor, proposed by the Employer and
the Engineer shall respond the Engineer shall respond approved by the Contractor,
with approval, or with with approval, or with the Employer shall respond
disapproval and detailed disapproval and detailed with approval, or with
comments. He may also comments. He may also disapproval and detailed
request any necessary further request any necessary further comments. He may also
particulars, but shall particulars, but shall request any necessary further

32
nevertheless give his response nevertheless give his response particulars, but shall
on the principles of the claim on the principles of the claim nevertheless give his response
within such time. within such time. on the principles of the claim
As consequence: each Payment As consequence: each Payment within such time.
Certificate shall include such Certificate shall include such As consequence: each interim
CL A I M S amounts for any claim as have amounts for any claim as have Payment shall include such
been reasonably substantiated been reasonably substantiated amounts for any claim as have
as due under the relevant as due under the relevant been reasonably substantiated
provision of the Contract. provision of the Contract. as due under the relevant
However: unless and until the However: unless and until the provision of the Contract.
particulars supplied are particulars supplied are However: unless and until the
sufficient to substantiate the sufficient to substantiate the particulars supplied are
whole of the claim, the whole of the claim, the sufficient to substantiate the
Contractor shall only be Contractor shall only be whole of the claim, the
entitled to payment for such entitled to payment for such Contractor shall only be
part of the claim, as he has part of the claim, as he has entitled to payment for such
been able to substantiate. been able to substantiate. part of the claim, as he has
The Engineer shall proceed in The Engineer shall proceed in been able to substantiate.
accordance with Sub-Clause accordance with Sub-Clause The Employer shall proceed in
3.5 [Determinations] to agree or 3.5 [Determinations] to agree or accordance with Sub-Clause
determine determine 3.5 [Determinations] to agree or
(i) An EOT (i) An EOT determine
and/or and/or (i) An EOT
(ii) An additional payment (ii) An additional payment and/or
(if any) to which the (if any) to which the (ii) An additional payment
Contractor is entitled Contractor is entitled (if any) to which the
under the Contract. under the Contract. Contractor is entitled
If the Contractor fails to If the Contractor fails to under the Contract.
comply with this or another comply with this or another If the Contractor fails to

33
ISSUE RED (2005) YELLOW (1999) SILVER (1999)

Sub- Clause in relation to any Sub- Clause in relation to any comply with this or another
claim, any EOT and/or claim, any EOT and/or Sub- Clause in relation to any
additional payment shall take additional payment shall take claim, any EOT and/or
account of the extent 20. account of the extent 20. additional payment shall take
account of the extent 20.

CL A I M S 20. 2 20. 2 20. 2


DB/DAB Appointment of the DB Appointment of the DB Appointment of the DAB
Disputes shall be referred to a Disputes shall be referred to a Disputes shall be adjudicated
DB for decision in accordance DB for decision in accordance by a DAB in accordance with
with 20.4 [Obtaining DBs with 20.4 [Obtaining DBs 20.4 [Obtaining DBAs Decision].
Decision]. The Parties shall Decision]. The Parties shall The Parties shall jointly
appoint a DB by the date appoint a DB by the date appoint a DAB by the date
stated in the Contract Data. stated in the Contract Data. 28 days after a Party gives
The DB shall comprise, as The DB shall comprise, as notice to the other Party of
stated in the Contract Data, stated in the Contract Data, its intention to refer a
either one or three suitably either one or three suitably dispute to a DAB in
qualified persons (the qualified persons (the accordance 20.4.
members) each of whom members) each of whom The DAB shall comprise, as
shall be fluent in the language shall be fluent in the language stated in the Particular
for communication defined in for communication defined in Conditions, either one or
the Contract and shall be a the Contract and shall be a three
professional experienced in the professional experienced in the suitably qualified persons
type of construction involved type of construction involved (the members).
in the Works and with the in the Works and with the If the number is not so stated
interpretation of contractual interpretation of contractual and the Parties do not agree
documents. documents. otherwise, the DAB shall
If the number is not so If the number is not so comprise three persons.
stated and the Parties do not stated and the Parties do not If the DAB is to comprise

34
agree otherwise, the DB shall agree otherwise, the DB shall three persons, each Party shall
comprise three persons, one of comprise three persons, one of nominate one member for the
whom shall serve as chairman. whom shall serve as chairman. approval of the other Party.
If the Parties have not jointly If the Parties have not jointly The Parties shall consult both
appointed the DB 21 days appointed the DB 21 days these members and shall agree
before the date stated in the before the date stated in the upon the third member:
Contract Data and the DB is Contract Data and the DB is chairman.
CL A I M S to comprise three persons, to comprise three persons, However, if a list of potential
DB/DAB each Party shall nominate one each Party shall nominate one members is included in the
member for the approval of member for the approval of Contract, the members shall be
the other Party. the other Party. selected from those on the list,
The first two members shall The first two members shall other than anyone who is
recommend and the Parties recommend and the Parties unable or unwilling to accept
shall agree upon the 3rd shall agree upon the 3rd appointment to the DAB.
member > DB Chairman. member > DB Chairman. The agreement between the
The agreement between the The agreement between the Parties and either the sole
Parties and either the sole Parties and either the sole member (adjudicator) or
member or each of the three member or each of the three each of the three members
members shall incorporate by members shall incorporate by shall incorporate by reference
reference the General reference the General the General Conditions of
Conditions of Dispute Board Conditions of Dispute Board Dispute Adjudication
Agreement contained in the Agreement contained in the Agreement contained in the
Appendix to these General Appendix to these General Appendix to these General
Conditions, with such Conditions, with such Conditions, with such
amendments as are agreed amendments as are agreed amendments as are agreed
between them. between them. between them.
The terms of the The terms of the The terms of the
remuneration of either the remuneration of either the remuneration of either the
sole member or each of the sole member or each of the sole member or each of the

35
ISSUE RED (2005) YELLOW (1999) SILVER (1999)

three members, including the three members, including the three members, shall be
remuneration of any expert remuneration of any expert mutually agreed upon by
whom the DB consults, shall whom the DB consults, shall the Parties when agreeing the
be mutually agreed upon by be mutually agreed upon by terms of appointment.
the Parties when agreeing the the Parties when agreeing the
terms of appointment of the terms of appointment of the
member or such expert (as the member or such expert (as the
case may be). case may be).
CL A I M S Each Party shall be responsible Each Party shall be responsible Each Party shall be responsible
DB/DAB for paying one-half of this for paying one-half of this for paying one-half of this
remuneration. remuneration. remuneration.
If a member declines to act or If a member declines to act or If at any time the Parties so
is unable to act as a result of is unable to act as a result of agree, they may appoint a
death, disability, resignation or death, disability, resignation or suitably qualified person or
termination of appointment, a termination of appointment, a persons to replace any one or
replacement shall be replacement shall be more members of the DAB.
appointed in the same appointed in the same Unless the Parties agree
manner as the replaced manner as the replaced otherwise, the appointment
person was required to have person was required to have will come into effect if a
been nominated or agreed been nominated or agreed member declines to act or is
upon. upon. unable to act as a result of
The appointment of any The appointment of any death, disability, resignation or
member may be terminated by member may be terminated by termination of appointment.
mutual agreement of both mutual agreement of both The replacement shall be
Parties, but not by the Parties, but not by the appointed in the same
Employer or the Contractor Employer or the Contractor manner as the replaced
acting alone. acting alone. person was required to have
Unless otherwise agreed by Unless otherwise agreed by been nominated or agreed.
both Parties, the appointment both Parties, the appointment The appointment of any

36
of the DB shall expire when of the DB shall expire when member may be terminated by
the 14.12 [Discharge] shall have the 14.12 [Discharge] shall have mutual agreement of both
become effective. become effective. Parties, but not by the
20. 3 20. 3 Employer or the Contractor
Failure to appoint the DAB Failure to appoint the DAB acting alone. Unless otherwise
If If agreed by both Parties, the
(a) The Parties fail to agree (a) The Parties fail to agree appointment of the DAB
upon the appointment of the upon the appointment of the (including each member) shall
sole member of the DB by the sole member of the DB by the expire when the DAB has
CL A I M S date stated in the first date stated in the first given its decision on the
DB/DAB paragraph 20.2; paragraph 20.2; dispute referred to it under
20.4, [ObtainingDispute
(b) Either Party fails to (b) Either Party fails to Adjudication Board Decision],
nominate a member (for nominate a member (for unless other disputes have
approval by the other Party) or approval by the other Party) or been referred to the DAB by
fails to approve a member fails to approve a member that time under Sub-Clause
nominated by the other Party, nominated by the other Party, 20.4, in which event the
of a DB of three persons by of a DB of three persons by relevant date shall be when the
such date; such date; DAB has also given decisions
on those disputes.
(c) The Parties fail to agree (c) The Parties fail to agree 20. 3
upon the appointment of the upon the appointment of the Failure to appoint the DAB
third member (chairman) by third member (chairman) by If
such date; such date; (a) The Parties fail to agree
upon the appointment of the
(d) The Parties fail to agree (d) The Parties fail to agree sole member of the DB by the
upon the appointment of a upon the appointment of a date stated in the first
replacement person within 42 replacement person within 42 paragraph 20.2;
days after the date on which days after the date on which (b) Either Party fails to

37
ISSUE RED (2005) YELLOW (1999) SILVER (1999)

the sole member or one of the the sole member or one of the nominate a member (for
three members declines to act three members declines to act approval by the other Party) or
or is unable to act as a result of or is unable to act as a result of fails to approve a member
death, disability, resignation or death, disability, resignation or nominated by the other Party,
termination of appointment, termination of appointment, of a DB of three persons by
such date;
THEN the appointing entity THEN the appointing entity (c) The Parties fail to agree
or official named in the or official named in the upon the appointment of the
Contract Data shall, upon Contract Data shall, upon third member (chairman) by
the request of either or both of the request of either or both of such date;
CL A I M S the Parties and after due the Parties and after due (d) The Parties fail to agree
DB/DAB consultation with both Parties, consultation with both Parties, upon the appointment of a
appoint this member of the appoint this member of the replacement person within 42
DB. This appointment shall be DB. This appointment shall be days after the date on which
final and conclusive. Each final and conclusive. Each the sole member or one of the
Party shall be responsible for Party shall be responsible for three members declines to act
paying one-half of the paying one-half of the or is unable to act as a result of
remuneration of the remuneration of the death, disability, resignation or
appointing entity or official. appointing entity or official. termination of appointment,
THEN the appointing entity
20. 4 Obtaining DB decision 20.4 Obtaining DB decision or official named in the
If a dispute (of any kind If a dispute (of any kind Contract Data shall, upon
whatsoever) arises between the whatsoever) arises between the the request of either or both of
Parties in connection with, or Parties in connection with, or the Parties and after due
arising out of, the Contract or arising out of, the Contract or consultation with both Parties,
the execution of the Works, the execution of the Works, appoint this member of the
including any dispute as to any including any dispute as to any DAB. This appointment shall
certificate, determination, certificate, determination, be final and conclusive. Each
instruction, opinion or instruction, opinion or Party shall be responsible for

38
valuation of the Engineer, valuation of the Engineer, paying one-half of the
either Party may refer the either Party may refer the remuneration of the
dispute in writing to the DB dispute in writing to the DB appointing entity or official.
for its decision, with copies for its decision, with copies
to the other Party and the to the other Party and the 20.4Obtaining DABdecision
Engineer. Engineer. If a dispute (of any kind
For a DB of three persons, the For a DB of three persons, the whatsoever) arises between the
DB shall be deemed to have DB shall be deemed to have Parties in connection with, or
received such reference on the received such reference on the arising out of, the Contract or
date when it is received by the date when it is received by the the execution of the Works,
chairman of the DB. chairman of the DB. including any dispute as to any
CL A I M S Both Parties shall promptly Both Parties shall promptly certificate, determination,
DB/DAB make available to the DB all make available to the DB all instruction, opinion or
such additional information, such additional information, valuation of the Employer,
further access to the Site, and further access to the Site, and then, after a DAB has been
appropriate facilities, as the appropriate facilities, as the appointed pursuant to 20.2
DB may require for the DB may require for the [Appointment of the DBA] and
purposes of making a decision purposes of making a decision 20.3 [Failure to Agree DBA],
on such dispute. The DB on such dispute. The DB either Party may refer the
shall be deemed to be not shall be deemed to be not dispute in writing to the
acting as arbitrator(s). acting as arbitrator(s). DAB for its decision, with a
Within 84 days after receiving Within 84 days after receiving copy to the other Party.
such reference, or within such such reference, or within such Such reference shall state that
other period as may be other period as may be it is given under this Sub-
proposed by the DB and proposed by the DB and Clause.
approved by both Parties, approved by both Parties, For a DAB of three persons,
THE DB SHALL GIVE ITS THE DB SHALL GIVE ITS the DAB shall be deemed to
DECISION, WHICH SHALL BE DECISION, WHICH SHALL BE have received such reference
REASONED AND SHALL STATE REASONED AND SHALL STATE on the date when it is received

39
ISSUE RED (2005) YELLOW (1999) SILVER (1999)

THAT IT IS GIVEN UNDER THAT IT IS GIVEN UNDER by the chairman of the DAB.
THIS SUB-CL A U S E . THIS SUB-CL A U S E . Both Parties shall promptly
The decision shall be The decision shall be make available to the DAB
binding on both Parties, binding on both Parties, all information, access to
who shall promptly give effect who shall promptly give effect the Site, and appropriate
to it unless and until it shall be to it unless and until it shall be facilities, as the DAB may
revised in an amicable revised in an amicable require for the purposes of
settlement or an arbitral award settlement or an arbitral award making a decision on such
as described below. as described below. dispute. The DAB shall be
Unless the Contract has Unless the Contract has deemed to be not acting as
already been abandoned, already been abandoned, arbitrator.
repudiated or terminated, the repudiated or terminated, the Within 84 days after
CL A I M S Contractor shall continue to Contractor shall continue to receiving such reference, [or
DB/DAB proceed with the Works in proceed with the Works in the advance payment referred
accordance with the Contract. accordance with the Contract. to in (Clause 6 of the Appendix -
If either Party is dissatisfied If either Party is dissatisfied General Conditions of Dispute
with the DBs decision, with the DBs decision, Adjudication Agreement),
then EITHER PARTY MAY, then EITHER PARTY MAY, whichever date is later, or
WITHIN 28 DAYS after receiving WITHIN 28 DAYS after receiving within such other period as
the decision, GIVE NOTICE TO the decision, GIVE NOTICE TO may be proposed by the DAB
THE OTHER PARTY OF ITS THE OTHER PARTY OF ITS and approved by both Parties,]
DISSATISFACTION AND DISSATISFACTION AND the DAB shall give its
INTENTION TO COMMENCE INTENTION TO COMMENCE decision, which shall be
ARBITRATION. ARBITRATION. reasoned and shall state that
If the DB fails to give its If the DB fails to give its it is given under this Sub-
decision within the period of decision within the period of Clause.
84 days (or as otherwise 84 days (or as otherwise However, if neither of the
approved) after receiving such approved) after receiving such Parties has paid in full the
reference, then either Party reference, then either Party invoices submitted by each

40
may, within 28 days after this may, within 28 days after this member pursuant to Clause 6
period has expired, give notice period has expired, give notice of the Appendix, the DAB
to the other Party of its to the other Party of its shall not be obliged to give
dissatisfaction and intention to dissatisfaction and intention to its decision until such
commence arbitration. commence arbitration. invoices have been paid in
In either event, this notice of In either event, this notice of full. The decision shall be
dissatisfaction shall state dissatisfaction shall state binding on both Parties,
that it is given under this Sub- that it is given under this Sub- who shall promptly give
Clause, and shall set out the Clause, and shall set out the effect to it unless and until it
matter in dispute and the matter in dispute and the shall be revised in an
reason(s) for dissatisfaction. reason(s) for dissatisfaction. AMICABLE SETTLEMENT or
Except as stated in 20.7 Except as stated in 20.7 AN ARBITRAL AWARD as
[Failure to Comply with Dispute [Failure to Comply with Dispute described below. Unless the
CL A I M S Boards Decision] and 20.8 Boards Decision] and 20.8 Contract has already been
DB/DAB [Expiry of Dispute Boards [Expiry of Dispute Boards abandoned, repudiated or
Appointment], neither Party Appointment], neither Party terminated, the Contractor
shall be entitled to shall be entitled to shall continue to proceed
commence arbitration of a commence arbitration of a with the Works in
dispute unless a notice of dispute unless a notice of accordance with the
dissatisfaction has been given dissatisfaction has been given Contract.
in accordance with this Sub- in accordance with this Sub- If either Party is dissatisfied
Clause. Clause. with the DABs decision, then
If the DB has given its If the DB has given its either Party may, within 28
decision as to a matter in decision as to a matter in days after receiving the
dispute to both Parties, and no dispute to both Parties, and no decision, give notice to the
notice of dissatisfaction has notice of dissatisfaction has other Party of its
been given by either Party been given by either Party dissatisfaction.
within 28 days after it within 28 days after it If the DAB fails to give its
received the DBs decision, received the DBs decision, decision within the period of

41
ISSUE RED (2005) YELLOW (1999) SILVER (1999)

then the decision shall become then the decision shall become 84 days (or as otherwise
final and binding upon both final and binding upon both approved) after receiving such
Parties. Parties. reference or such payment,
20. 7 20. 7 then either Party may,
Failure to comply with the Failure to comply with the within 28 days after this
DBs decision DBs decision period has expired, give
In the event that a Party fails In the event that a Party fails notice to the other Party of
to comply with a DB decision to comply with a DB decision its dissatisfaction.
which has become final and which has become final and Except as stated in Sub-Clause
binding, then the other Party binding, then the other Party 20.7 [Failure to Comply with
may, without prejudice to may, without prejudice to DABs Decision] and 20.8
any other rights it may have, any other rights it may have, [Expiry of DABs Appointment],
refer the failure itself to refer the failure itself to neither Party shall be
arbitration under 20.6 arbitration under 20.6 entitled to commence
CL A I M S [Arbitration] and 20.4 [Obtaining [Arbitration] and 20.4 [Obtaining arbitration of a dispute
DB/DAB Dispute Boards Decision] and Dispute Boards Decision] and unless a notice of
20.5 [Amicable Settlement] shall 20.5 [Amicable Settlement] shall dissatisfaction has been
not apply to this reference. not apply to this reference. given in accordance with this
20. 8 20. 8 Sub-Clause.
Expiry of DAB appointment Expiry of DAB appointment If
If a dispute arises between the If a dispute arises between the - The DAB has given its
Parties in connection with, or Parties in connection with, or decision as to a matter in
arising out of, the Contract or arising out of, the Contract or dispute to both Parties;
the execution of the Works the execution of the Works - No notice of
and there is no DB in place the and there is no DB in place the dissatisfaction has been
dispute may be referred dispute may be referred given by either Party within
directly to arbitration under directly to arbitration under 28 days after it received the
20.6 [Arbitration] 20.6 [Arbitration] DABs decision, then the
decision shall become final

42
and binding upon both
Parties.

20. 7
Failure to comply with the
DABs decision
In the event that a Party fails
to comply with a DAB
decision which has become
final and binding, then the
other Party may, without
prejudice to any other rights
it may have, refer the failure
CL A I M S itself to arbitration under
DB/DAB 20.6 [Arbitration] and 20.4
[Obtaining DBAs Decision] and
the DBAs related decision has
become final and binding and
Parties fail to comply:
then the other Party may,
without prejudice to any other
rights it may have, refer the
failure itself to arbitration
under 20.6 [Arbitration].
20.4[Obtaining DBAs Decision]
and 20.5 [Amicable Settlement]
shall not apply to this

43
ISSUE RED (2005) YELLOW (1999) SILVER (1999)

reference.

20. 8
Expiry of DAB appointment
If a dispute arises between the
Parties in connection with, or
arising out of, the Contract or
the execution of the Works
and there is no DAB in place
the dispute may be referred
directly to arbitration under
20.6 [Arbitration].
20.4[Obtaining DBAs Decision]
and 20.5 [Amicable Settlement]
shall not apply to this
reference.
AM I C A B L E 20. 5 Where notice of 20. 5 Where notice of 20. 5 Where notice of
SE T T L E M E N T dissatisfaction has been given dissatisfaction has been given dissatisfaction has been given
under 20.4 above, both under 20.4 above, both under 20.4 above, both
Parties shall attempt to Parties shall attempt to Parties shall attempt to
settle the dispute amicably settle the dispute amicably settle the dispute amicably
before the commencement before the commencement before the commencement
of arbitration. However, of arbitration. However, of arbitration. However,
unless both Parties agree unless both Parties agree unless both Parties agree
otherwise, arbitration may be otherwise, arbitration may be otherwise, arbitration may be
commenced on or after 56 day commenced on or after 56 day commenced on or after 56 day
after the day on which a notice after the day on which a notice after the day on which a notice
of dissatisfaction and intention of dissatisfaction and intention of dissatisfaction and intention
to commence arbitration was to commence arbitration was to commence arbitration was

44
given, even if no attempt at given, even if no attempt at given, even if no attempt at
amicable settlement has been amicable settlement has been amicable settlement has been
made. made. made.
ISSUE RED (2005) YELLOW (1999) SILVER (1999)
AR B I T R A T I O N - Unless settled amicably; - Unless settled amicably; - Unless settled amicably;
- Unless the DBs decision - Unless the DBs decision - Unless the DABs
has not become final and has not become final and decision has not become
binding: binding: final and binding:
The dispute shall be finally The dispute shall be finally The dispute shall be finally
settled by international settled by international settled by international
arbitration. arbitration. arbitration.
Unless otherwise agreed by Unless otherwise agreed by Unless otherwise agreed by
both Parties: both Parties: both Parties:
A. Arbitration proceedings A. If no arbitration A. If no arbitration
shall be conducted as stated proceedings are so stated, the proceedings are so stated, the
in the Particular Conditions; dispute shall be finally dispute shall be finally
settled by institutional settled by institutional
B. If no arbitration arbitration under the Rules arbitration under the Rules
proceedings are so stated, the of Arbitration of the ICC; of Arbitration of the ICC;
dispute shall be finally
settled by institutional B. The dispute shall be settled B. The dispute shall be settled
arbitration under the Rules by 3 arbitrators; by 3 arbitrators;
of Arbitration of the ICC;
C. The arbitration shall be C. The arbitration shall be
C. The dispute shall be settled conducted in the language for conducted in the language for
by 3 arbitrators; communications defined (1.4) communications defined (1.4)
The arbitrators shall have full The arbitrators shall have full
D. The arbitration shall be power to open up, review and power to open up, review and
conducted in the language revise any certificate, revise any certificate,
45
ISSUE RED (2005) YELLOW (1999) SILVER (1999)

upon 1.4. The arbitrators shall determination, instruction, determination, instruction,
have full power to open up, opinion or valuation of the opinion or valuation of the
review and revise any Engineer, and any decision Engineer, and any decision
AR B I T R A T I O N certificate, determination, of the DB, relevant to the of the DAB, relevant to the
instruction, opinion or dispute. dispute.
valuation of the Engineer, and Nothing shall disqualify the Nothing shall disqualify the
any decision of the DB, Engineer from being called as Engineer from being called as
relevant to the dispute. a witness and giving evidence a witness and giving evidence
Nothing shall disqualify the before the arbitrators on any before the arbitrators on any
Engineer from being called as matter whatsoever relevant to matter whatsoever relevant to
a witness and giving evidence the dispute. the dispute.
before the arbitrators on any Any decision of the DB shall Any decision of the DAB
matter whatsoever relevant to be admissible in evidence in shall be admissible in
the dispute. the arbitration. evidence in the arbitration.
Any decision of the DB shall Arbitration may be Arbitration may be
be admissible in evidence in commenced prior to or after commenced prior to or after
the arbitration. Arbitration completion of the Works. The completion of the Works. The
may be commenced prior to or obligations of the Parties, the obligations of the Parties, the
after completion of the Works. Engineer and the DB shall not Engineer and the DB shall not
The obligations of the Parties, be altered by reason of any be altered by reason of any
the Engineer and the DB shall arbitration being conducted arbitration being conducted
not be altered by reason of any during the Works progress. during the Works progress.
arbitration being conducted
during the Works progress.

46

You might also like