Uraian Pekerjaan Kuantitas Harga Satuan Jumlah Harga

Uitzet 800.00 5,000.00 4,000,000.00


Galian Tanah 1,249.00 50,000.00 62,450,000.00
Timbunan Tanah 321.00 30,000.00 9,630,000.00
Pemadatan 181.00 40,000.00 7,240,000.00

Mortar 1,878.00 947,098.16 1,778,650,350.11


Plesteran 853.00 60,000.00 51,180,000.00
Penanaman Rumput 111.00 40,000.00 4,440,000.00

Beton Mutu 17.10 1,050,000.00 17,955,000.00


Beton Mutu 0.42 1,150,000.00 483,000.00
Pembesian 53.76 14,500.00 779,520.00
Bekisting 5.20 250,000.00 1,300,000.00
Perancah 1.05 300,000.00 315,000.00
Bongkar Bekisting 5.20 50,000.00 260,000.00

Kistdam 2,400.00 10,000.00 24,000,000.00


Kerangka Kayu 50.00 130,000.00 6,500,000.00

Pintu Sorong Baja 2.00 15,000,000.00 30,000,000.00

Direksi Keet 1.00 7,500,000.00 7,500,000.00


Papan Nama 1.00 467,000.00 467,000.00
Pipa Galvanis 8.60 120,000.00 1,032,000.00
Mobilisasi 1.00 10,000,000.00 10,000,000.00

2,018,181,870.11
201,818,187.01
2,220,000,057.12