You are on page 1of 40

14-jun-2017 Pagina: 1 de 36

EDIFICACIONES Y RECONSTRUCCIONES CHIGULERA S.A. DE C.V.


Dependencia: H. AYUNTAMIENTO MUNICIPAL CONSTITUCIONAL
SANTA CRUZ XOXOCOTLAN

No. DE INVITACIN: MSCX/INV/FORTALECE/0701-N/2017 Duracin: 60 das naturales


Obra: CONSTRUCCION DE TECHADO EN LA ESCUELA PRIMARIA SOR JUANA INES DE LA CRUZ CLAVE: 20DPR3454E

Lugar: COLONIA LAS CULTURAS SANTA CRUZ XOXOCOTLAN OAXACA Inicio Obra: 26-jun-2017
Fin Obra: 24-ago-2017
ANLISIS, CLCULO E INTEGRACIN DE LOS PRECIOS UNITARIOS (ANEXO 10)

Cdigo Concepto Unidad Costo Cantidad Importe %


Partida: 1.1 Anlisis No.: 10
Anlisis: CIME:0010 M2 657.78
LIMPIA, TRAZO Y NIVELACION DEL TERRENO (AREA DE EDIFICIOS).
MATERIALES
CALCALHIDRA TON $2,550.00 0.000200 $0.51 6.84%

DUELADUELA DE PINO DE 3a DE 3/4"x3.5"x8.25'' PZA $26.48 0.020000 7.10%


$0.53

MAHILOHILO CAAMO PZA $15.18 0.001000 $0.02 0.27%

3.VARILLA DE 3/8" 9.5 MM KG $14.28 0.020000 $0.29 3.89%

SUBTOTAL: MATERIALES $1.35 18.10%


MANO DE OBRA
1A1PCUADRILLA No 5 (1 ALBAIL+1 PEON) JOR $1,019.04 / 200.000000 68.36%

$5.10
SUBTOTAL: MANO DE OBRA $5.10 68.36%
EQUIPO Y HERRAMIENTA
%MO1HERRAMIENTA MENOR % $5.10 0.030000 2.01%
$0.15

SUBTOTAL: EQUIPO Y HERRAMIENTA $0.15 2.01%


BASICOS
100.CONCRETO DE F'c=100 KG/CM2. HECHO EN M3 $1,712.13 0.000500 11.53%

$0.86
OBRA, T.M.A=19 MM, RESISTENCIA
NORMAL
SUBTOTAL: BASICOS $0.86 11.53%
Costo Directo: $7.46
INDIRECTOS 10.358% $0.77
SUBTOTAL $8.23
FINANCIAMIENTO 2.2356% $0.18
SUBTOTAL $8.41
UTILIDAD 12.9032% $1.09
PRECIO UNITARIO $9.50
(* NUEVE PESOS 50/100 M.N. *)

ADMINISTRADOR UNICO C. DANIEL ORTIZ ALCARAZ


14-jun-2017 Pagina: 2 de 36
EDIFICACIONES Y RECONSTRUCCIONES CHIGULERA S.A. DE C.V.
Dependencia: H. AYUNTAMIENTO MUNICIPAL CONSTITUCIONAL
SANTA CRUZ XOXOCOTLAN

No. DE INVITACIN: MSCX/INV/FORTALECE/0701-N/2017 Duracin: 60 das naturales


Obra: CONSTRUCCION DE TECHADO EN LA ESCUELA PRIMARIA SOR JUANA INES DE LA CRUZ CLAVE: 20DPR3454E

Lugar: COLONIA LAS CULTURAS SANTA CRUZ XOXOCOTLAN OAXACA Inicio Obra: 26-jun-2017
Fin Obra: 24-ago-2017
ANLISIS, CLCULO E INTEGRACIN DE LOS PRECIOS UNITARIOS (ANEXO 10)

Cdigo Concepto Unidad Costo Cantidad Importe %


Partida: 1.1 Anlisis No.: 20
Anlisis: CIM:0021 M3 205.55
EXCAVACION A MANO EN TERRENO TIPO "C", CUALQUIER PROFUNDIDAD, INCLUYE: AFINE TALUDES, FONDO DE EXCAVACION,
ACARREOS DENTRO DE LA OBRA HASTA PRIMERA ESTACION ( 20.00 M ), MANO DE OBRA, HERRAMIENTA Y EQUIPO.
MANO DE OBRA

1PCUADRILLA No 1 (1 PEON) JOR $364.39 / 1.330000 $273.98 97.09%

SUBTOTAL: MANO DE OBRA $273.98 97.09%


EQUIPO Y HERRAMIENTA
%MO1HERRAMIENTA MENOR % $273.98 0.030000 2.91%

$8.22
SUBTOTAL: EQUIPO Y HERRAMIENTA $8.22 2.91%
Costo Directo: $282.20
INDIRECTOS 10.358% $29.23
SUBTOTAL $311.43
FINANCIAMIENTO 2.2356% $6.96
SUBTOTAL $318.39
UTILIDAD 12.9032% $41.08
PRECIO UNITARIO $359.47
(* TRESCIENTOS CINCUENTA Y NUEVE PESOS 47/100 M.N. *)

ADMINISTRADOR UNICO C. DANIEL ORTIZ ALCARAZ


14-jun-2017 Pagina: 3 de 36
EDIFICACIONES Y RECONSTRUCCIONES CHIGULERA S.A. DE C.V.
Dependencia: H. AYUNTAMIENTO MUNICIPAL CONSTITUCIONAL
SANTA CRUZ XOXOCOTLAN

No. DE INVITACIN: MSCX/INV/FORTALECE/0701-N/2017 Duracin: 60 das naturales


Obra: CONSTRUCCION DE TECHADO EN LA ESCUELA PRIMARIA SOR JUANA INES DE LA CRUZ CLAVE: 20DPR3454E

Lugar: COLONIA LAS CULTURAS SANTA CRUZ XOXOCOTLAN OAXACA Inicio Obra: 26-jun-2017
Fin Obra: 24-ago-2017
ANLISIS, CLCULO E INTEGRACIN DE LOS PRECIOS UNITARIOS (ANEXO 10)

Cdigo Concepto Unidad Costo Cantidad Importe %


Partida: 1.1 Anlisis No.: 30
Anlisis: CIME:0035 M2 48.22
PLANTILLA DE CONCRETO HECHO EN OBRA F'C=100 KG/CM2 DE 5 CMS. DE ESPESOR., INCLUYE: ELABORACION DEL CONCRETO,
ACARREO A 2 ESTACIONES DE 20 MTS., HERRAMIENTA, LIMPIEZA Y MANO DE OBRA.
MANO DE OBRA
1A1PCUADRILLA No 5 (1 ALBAIL+1 PEON) JOR $1,019.04 0.050000 36.44%
$50.95

SUBTOTAL: MANO DE OBRA $50.95 36.44%


EQUIPO Y HERRAMIENTA
%MO1HERRAMIENTA MENOR % $50.95 0.030000 $1.53 1.09%

SUBTOTAL: EQUIPO Y HERRAMIENTA $1.53 1.09%


BASICOS
100.CONCRETO DE F'c=100 KG/CM2. HECHO EN M3 $1,712.13 0.051000 $87.32 62.46%

OBRA, T.M.A=19 MM, RESISTENCIA


NORMAL
SUBTOTAL: BASICOS $87.32 62.46%
Costo Directo: $139.80
INDIRECTOS 10.358% $14.48
SUBTOTAL $154.28
FINANCIAMIENTO 2.2356% $3.45
SUBTOTAL $157.73
UTILIDAD 12.9032% $20.35
PRECIO UNITARIO $178.08
(* CIENTO SETENTA Y OCHO PESOS 08/100 M.N. *)

ADMINISTRADOR UNICO C. DANIEL ORTIZ ALCARAZ


14-jun-2017 Pagina: 4 de 36
EDIFICACIONES Y RECONSTRUCCIONES CHIGULERA S.A. DE C.V.
Dependencia: H. AYUNTAMIENTO MUNICIPAL CONSTITUCIONAL
SANTA CRUZ XOXOCOTLAN

No. DE INVITACIN: MSCX/INV/FORTALECE/0701-N/2017 Duracin: 60 das naturales


Obra: CONSTRUCCION DE TECHADO EN LA ESCUELA PRIMARIA SOR JUANA INES DE LA CRUZ CLAVE: 20DPR3454E

Lugar: COLONIA LAS CULTURAS SANTA CRUZ XOXOCOTLAN OAXACA Inicio Obra: 26-jun-2017
Fin Obra: 24-ago-2017
ANLISIS, CLCULO E INTEGRACIN DE LOS PRECIOS UNITARIOS (ANEXO 10)

Cdigo Concepto Unidad Costo Cantidad Importe %


Partida: 1.1 Anlisis No.: 40
Anlisis: CIME:0050 M3 43.7
RELLENO Y COMPACT. D/MAT/P/EXCAV.C/PISON Y AGUA, EN CAPAS DE 20CM. INCLLUYE: ACARREO A UNA ESTACION DE 20 MTS,
TRASPALEO, INCORPORACION DE AGUA, HERRAMIENTA Y MANO DE OBRA
MATERIALES
AGUAAGUA ( MANEJO) M3 $123.60 0.100000 9.40%

$12.36
SUBTOTAL: MATERIALES $12.36 9.40%
MANO DE OBRA
1ACUADRILLA No 3 (1 AYUDANTE GENERAL) JOR $347.04 / 3.000000 $115.68 87.96%

SUBTOTAL: MANO DE OBRA $115.68 87.96%


EQUIPO Y HERRAMIENTA
%MO1HERRAMIENTA MENOR % $115.68 0.030000 2.64%

$3.47
SUBTOTAL: EQUIPO Y HERRAMIENTA $3.47 2.64%
Costo Directo: $131.51
INDIRECTOS 10.358% $13.62
SUBTOTAL $145.13
FINANCIAMIENTO 2.2356% $3.24
SUBTOTAL $148.37
UTILIDAD 12.9032% $19.14
PRECIO UNITARIO $167.51
(* CIENTO SESENTA Y SIETE PESOS 51/100 M.N. *)

ADMINISTRADOR UNICO C. DANIEL ORTIZ ALCARAZ


14-jun-2017 Pagina: 5 de 36
EDIFICACIONES Y RECONSTRUCCIONES CHIGULERA S.A. DE C.V.
Dependencia: H. AYUNTAMIENTO MUNICIPAL CONSTITUCIONAL
SANTA CRUZ XOXOCOTLAN

No. DE INVITACIN: MSCX/INV/FORTALECE/0701-N/2017 Duracin: 60 das naturales


Obra: CONSTRUCCION DE TECHADO EN LA ESCUELA PRIMARIA SOR JUANA INES DE LA CRUZ CLAVE: 20DPR3454E

Lugar: COLONIA LAS CULTURAS SANTA CRUZ XOXOCOTLAN OAXACA Inicio Obra: 26-jun-2017
Fin Obra: 24-ago-2017
ANLISIS, CLCULO E INTEGRACIN DE LOS PRECIOS UNITARIOS (ANEXO 10)

Cdigo Concepto Unidad Costo Cantidad Importe %


Partida: 1.1 Anlisis No.: 50
Anlisis: CIME:0070 M2 195.09
CIMBRA PARA CIMENTACION CON MADERA DE PINO DE 3a.,ACABADO COMUN, INCLUYE CIMBRADO Y DESCIMBRADO.
MATERIALES
DUELADUELA DE PINO DE 3a DE 3/4"x3.5"x8.25'' PZA $26.48 1.000000 $26.48 16.09%

BARROTEBARROTE DE PINO DE 3a DE 1.5"x3.5"x8.25'' PZA $38.38 0.200000 4.67%

$7.68
POLINPOLIN DE PINO DE 3a DE 3.5"x3."x8.25'' PZA $63.54 0.100000 3.86%

$6.35
1.ALAMBRE RECOCIDO KG $22.44 0.200000 $4.49 2.73%

DIESELDIESEL LTO $14.43 0.300000 2.63%

$4.33
CLAVOSCLAVOS DE 2 A 4 " KG $24.48 0.200000 2.98%

$4.90
SUBTOTAL: MATERIALES $54.23 32.96%
MANO DE OBRA
1C1ACUADRILLA No 7 (1 CARP. O.N. + JOR $964.27 / 9.000000 $107.14 65.10%

AYUDANTE)
SUBTOTAL: MANO DE OBRA $107.14 65.10%
EQUIPO Y HERRAMIENTA
%MO1HERRAMIENTA MENOR % $107.14 0.030000 $3.21 1.95%

SUBTOTAL: EQUIPO Y HERRAMIENTA $3.21 1.95%


Costo Directo: $164.58
INDIRECTOS 10.358% $17.05
SUBTOTAL $181.63
FINANCIAMIENTO 2.2356% $4.06
SUBTOTAL $185.69
UTILIDAD 12.9032% $23.96
PRECIO UNITARIO $209.65
(* DOSCIENTOS NUEVE PESOS 65/100 M.N. *)

ADMINISTRADOR UNICO C. DANIEL ORTIZ ALCARAZ


14-jun-2017 Pagina: 6 de 36
EDIFICACIONES Y RECONSTRUCCIONES CHIGULERA S.A. DE C.V.
Dependencia: H. AYUNTAMIENTO MUNICIPAL CONSTITUCIONAL
SANTA CRUZ XOXOCOTLAN

No. DE INVITACIN: MSCX/INV/FORTALECE/0701-N/2017 Duracin: 60 das naturales


Obra: CONSTRUCCION DE TECHADO EN LA ESCUELA PRIMARIA SOR JUANA INES DE LA CRUZ CLAVE: 20DPR3454E

Lugar: COLONIA LAS CULTURAS SANTA CRUZ XOXOCOTLAN OAXACA Inicio Obra: 26-jun-2017
Fin Obra: 24-ago-2017
ANLISIS, CLCULO E INTEGRACIN DE LOS PRECIOS UNITARIOS (ANEXO 10)

Cdigo Concepto Unidad Costo Cantidad Importe %


Partida: 1.1 Anlisis No.: 60
Anlisis: CIME:0080 M3 25.54
CONCRETO F'C=250 KG/CM2 EN CIMENTACION, T.M.A 3/4", HECHO EN OBRA, INCLUYE: COLADO, VIBRADO Y CURADO. ACARREOS A 2
ESTACIONES DE 20 MTS. HERRAMIENTA Y MANO DE OBRA.
MANO DE OBRA
1A5PCUADRILLA No 22 (1 ALBAIL + 5 PEONES) JOR $2,292.31 / 5.000000 $458.46 16.74%

SUBTOTAL: MANO DE OBRA $458.46 16.74%


EQUIPO Y HERRAMIENTA
$30.92

EQVIBVIBRADOR PARA CONCRETO HOR $61.84 0.500000 1.13%


%MO1HERRAMIENTA MENOR % $458.46 0.030000 0.50%
$13.75

SUBTOTAL: EQUIPO Y HERRAMIENTA $44.67 1.63%


BASICOS
250.CONCRETO DE F'c=250 KG/CM2, HECHO EN M3 $2,191.79 1.020000 $2,235.63 81.63%

OBRA, T.M.A.= 19 MM, RESISTENCIA


NORMAL
SUBTOTAL: BASICOS $2,235.63 81.63%
Costo Directo: $2,738.76
INDIRECTOS 10.358% $283.68
SUBTOTAL $3,022.44
FINANCIAMIENTO 2.2356% $67.57
SUBTOTAL $3,090.01
UTILIDAD 12.9032% $398.71
PRECIO UNITARIO $3,488.72
(* TRES MIL CUATROCIENTOS OCHENTA Y OCHO PESOS 72/100
M.N. *)

ADMINISTRADOR UNICO C. DANIEL ORTIZ ALCARAZ


14-jun-2017 Pagina: 7 de 36
EDIFICACIONES Y RECONSTRUCCIONES CHIGULERA S.A. DE C.V.
Dependencia: H. AYUNTAMIENTO MUNICIPAL CONSTITUCIONAL
SANTA CRUZ XOXOCOTLAN

No. DE INVITACIN: MSCX/INV/FORTALECE/0701-N/2017 Duracin: 60 das naturales


Obra: CONSTRUCCION DE TECHADO EN LA ESCUELA PRIMARIA SOR JUANA INES DE LA CRUZ CLAVE: 20DPR3454E

Lugar: COLONIA LAS CULTURAS SANTA CRUZ XOXOCOTLAN OAXACA Inicio Obra: 26-jun-2017
Fin Obra: 24-ago-2017
ANLISIS, CLCULO E INTEGRACIN DE LOS PRECIOS UNITARIOS (ANEXO 10)

Cdigo Concepto Unidad Costo Cantidad Importe %


Partida: 1.1 Anlisis No.: 70
Anlisis: CIME: 0120 KG 934.06
ACERO REFUERZO CIMENT. DIAMETRO #3 F'Y=4200KG/CM2 INCL. SUMINIST.HABILIT.ARMADO, TRASLAPES,SILLETAS,GANCHOS Y
DESPER.
MATERIALES
1.ALAMBRE RECOCIDO KG $22.44 0.500000 35.54%
$11.22

$15.28
3.VARILLA DE 3/8" 9.5 MM KG $14.28 1.070000 48.40%
SUBTOTAL: MATERIALES $26.50 83.94%
MANO DE OBRA
1F1ACUADRILLA No 6 (1 FIERRERO + 1 JOR $934.21 / 190.000000 $4.92 15.58%

AYUDANTE)
SUBTOTAL: MANO DE OBRA $4.92 15.58%
EQUIPO Y HERRAMIENTA
%MO1HERRAMIENTA MENOR % $4.92 0.030000 $0.15 0.48%

SUBTOTAL: EQUIPO Y HERRAMIENTA $0.15 0.48%


Costo Directo: $31.57
INDIRECTOS 10.358% $3.27
SUBTOTAL $34.84
FINANCIAMIENTO 2.2356% $0.78
SUBTOTAL $35.62
UTILIDAD 12.9032% $4.60
PRECIO UNITARIO $40.22
(* CUARENTA PESOS 22/100 M.N. *)

ADMINISTRADOR UNICO C. DANIEL ORTIZ ALCARAZ


14-jun-2017 Pagina: 8 de 36
EDIFICACIONES Y RECONSTRUCCIONES CHIGULERA S.A. DE C.V.
Dependencia: H. AYUNTAMIENTO MUNICIPAL CONSTITUCIONAL
SANTA CRUZ XOXOCOTLAN

No. DE INVITACIN: MSCX/INV/FORTALECE/0701-N/2017 Duracin: 60 das naturales


Obra: CONSTRUCCION DE TECHADO EN LA ESCUELA PRIMARIA SOR JUANA INES DE LA CRUZ CLAVE: 20DPR3454E

Lugar: COLONIA LAS CULTURAS SANTA CRUZ XOXOCOTLAN OAXACA Inicio Obra: 26-jun-2017
Fin Obra: 24-ago-2017
ANLISIS, CLCULO E INTEGRACIN DE LOS PRECIOS UNITARIOS (ANEXO 10)

Cdigo Concepto Unidad Costo Cantidad Importe %


Partida: 1.1 Anlisis No.: 80
Anlisis: CIME: 0121 KG 248.49
ACERO REFUERZO CIMENT. DIAMETRO #4 F'Y=4200KG/CM2 INCL. SUMINIST.HABILIT.ARMADO, TRASLAPES,SILLETAS,GANCHOS Y
DESPER.
MATERIALES
1.ALAMBRE RECOCIDO KG $22.44 0.400000 30.94%
$8.98

$15.28
4.VARILLA DE 1/2" 12.7 MM KG $14.28 1.070000 52.65%
SUBTOTAL: MATERIALES $24.26 83.59%
MANO DE OBRA
1F1ACUADRILLA No 6 (1 FIERRERO + 1 JOR $934.21 / 202.000000 $4.62 15.92%

AYUDANTE)
SUBTOTAL: MANO DE OBRA $4.62 15.92%
EQUIPO Y HERRAMIENTA
%MO1HERRAMIENTA MENOR % $4.62 0.030000 $0.14 0.48%

SUBTOTAL: EQUIPO Y HERRAMIENTA $0.14 0.48%


Costo Directo: $29.02
INDIRECTOS 10.358% $3.01
SUBTOTAL $32.03
FINANCIAMIENTO 2.2356% $0.72
SUBTOTAL $32.75
UTILIDAD 12.9032% $4.23
PRECIO UNITARIO $36.98
(* TREINTA Y SEIS PESOS 98/100 M.N. *)

ADMINISTRADOR UNICO C. DANIEL ORTIZ ALCARAZ


14-jun-2017 Pagina: 9 de 36
EDIFICACIONES Y RECONSTRUCCIONES CHIGULERA S.A. DE C.V.
Dependencia: H. AYUNTAMIENTO MUNICIPAL CONSTITUCIONAL
SANTA CRUZ XOXOCOTLAN

No. DE INVITACIN: MSCX/INV/FORTALECE/0701-N/2017 Duracin: 60 das naturales


Obra: CONSTRUCCION DE TECHADO EN LA ESCUELA PRIMARIA SOR JUANA INES DE LA CRUZ CLAVE: 20DPR3454E

Lugar: COLONIA LAS CULTURAS SANTA CRUZ XOXOCOTLAN OAXACA Inicio Obra: 26-jun-2017
Fin Obra: 24-ago-2017
ANLISIS, CLCULO E INTEGRACIN DE LOS PRECIOS UNITARIOS (ANEXO 10)

Cdigo Concepto Unidad Costo Cantidad Importe %


Partida: 1.1 Anlisis No.: 90
Anlisis: CIME: 0122 KG 628.87
ACERO REFUERZO CIMENT. DIAMETRO #5 F'Y=4200KG/CM2 INCL. SUMINIST.HABILIT.ARMADO, TRASLAPES,SILLETAS,GANCHOS Y
DESPER.
MATERIALES
1.ALAMBRE RECOCIDO KG $22.44 0.350000 28.10%
$7.85

$15.28
5.VARILLA DE 5/8" 15.9 MM KG $14.28 1.070000 54.69%
SUBTOTAL: MATERIALES $23.13 82.79%
MANO DE OBRA
1F1ACUADRILLA No 6 (1 FIERRERO + 1 JOR $934.21 / 200.000000 $4.67 16.71%

AYUDANTE)
SUBTOTAL: MANO DE OBRA $4.67 16.71%
EQUIPO Y HERRAMIENTA
%MO1HERRAMIENTA MENOR % $4.67 0.030000 $0.14 0.50%

SUBTOTAL: EQUIPO Y HERRAMIENTA $0.14 0.50%


Costo Directo: $27.94
INDIRECTOS 10.358% $2.89
SUBTOTAL $30.83
FINANCIAMIENTO 2.2356% $0.69
SUBTOTAL $31.52
UTILIDAD 12.9032% $4.07
PRECIO UNITARIO $35.59
(* TREINTA Y CINCO PESOS 59/100 M.N. *)

ADMINISTRADOR UNICO C. DANIEL ORTIZ ALCARAZ


14-jun-2017 Pagina: 10 de 36
EDIFICACIONES Y RECONSTRUCCIONES CHIGULERA S.A. DE C.V.
Dependencia: H. AYUNTAMIENTO MUNICIPAL CONSTITUCIONAL
SANTA CRUZ XOXOCOTLAN

No. DE INVITACIN: MSCX/INV/FORTALECE/0701-N/2017 Duracin: 60 das naturales


Obra: CONSTRUCCION DE TECHADO EN LA ESCUELA PRIMARIA SOR JUANA INES DE LA CRUZ CLAVE: 20DPR3454E

Lugar: COLONIA LAS CULTURAS SANTA CRUZ XOXOCOTLAN OAXACA Inicio Obra: 26-jun-2017
Fin Obra: 24-ago-2017
ANLISIS, CLCULO E INTEGRACIN DE LOS PRECIOS UNITARIOS (ANEXO 10)

Cdigo Concepto Unidad Costo Cantidad Importe %


Partida: 1.1 Anlisis No.: 100
Anlisis: CIME: 0125 KG 74.4
SUMINISTRO Y COLOCACION DE ANCLAS DE REDONDO LISO DE 5/8" CON UN DESARROLLO DE 1 M CON ROSCA EN UN EXTREMO,
INCLUYE TUERCAS Y RONDANAS, TRAZO, MATERIALES, CORTES, FIJACION, MANO DE OBRA, EQUIPO Y HERRAMIENTA.
MATERIALES
7018SOLDADURA ELECTRODO 7018 KG $34.19 0.050000 4.64%
$1.71

ANCLA8ANCLA DE 5/8" DE DIAM. DE 100 CM. KG $18.09 1.070000 52.55%


$19.36

C/TUERCA
SUBTOTAL: MATERIALES $21.07 57.19%
MANO DE OBRA
1S2ECUADRILLA No 18 (1 SOLDADOR+2 AY.ESP.) JOR $1,494.74 / 100.000000 $14.95 40.58%

SUBTOTAL: MANO DE OBRA $14.95 40.58%


EQUIPO Y HERRAMIENTA
EQPLANPLANTA DE SOLDAR MILLER HOR $7.44 0.050000 $0.37 1.00%

%MO1HERRAMIENTA MENOR % $14.95 0.030000 $0.45 1.22%

SUBTOTAL: EQUIPO Y HERRAMIENTA $0.82 2.22%


Costo Directo: $36.84
INDIRECTOS 10.358% $3.82
SUBTOTAL $40.66
FINANCIAMIENTO 2.2356% $0.91
SUBTOTAL $41.57
UTILIDAD 12.9032% $5.36
PRECIO UNITARIO $46.93
(* CUARENTA Y SEIS PESOS 93/100 M.N. *)

ADMINISTRADOR UNICO C. DANIEL ORTIZ ALCARAZ


14-jun-2017 Pagina: 11 de 36
EDIFICACIONES Y RECONSTRUCCIONES CHIGULERA S.A. DE C.V.
Dependencia: H. AYUNTAMIENTO MUNICIPAL CONSTITUCIONAL
SANTA CRUZ XOXOCOTLAN

No. DE INVITACIN: MSCX/INV/FORTALECE/0701-N/2017 Duracin: 60 das naturales


Obra: CONSTRUCCION DE TECHADO EN LA ESCUELA PRIMARIA SOR JUANA INES DE LA CRUZ CLAVE: 20DPR3454E

Lugar: COLONIA LAS CULTURAS SANTA CRUZ XOXOCOTLAN OAXACA Inicio Obra: 26-jun-2017
Fin Obra: 24-ago-2017
ANLISIS, CLCULO E INTEGRACIN DE LOS PRECIOS UNITARIOS (ANEXO 10)

Cdigo Concepto Unidad Costo Cantidad Importe %


Partida: 1.2 Anlisis No.: 10
Anlisis: ESTR:0210 PZA 10
COLUMNA A BASE DE PERFIL TUBULAR CIRCULAR HUECO OC DE 10" CED. 40 DE 6 M DE ALTURA, CON UNA PLACA DE ACERO DE
45x45CM SOLDADA EN SUS EXTREMOS Y CARTABONES DE REFUERZO EN LA PLACA INFERIOR, INCLUYE: SOLDADURA,
PRIMER,MATERIAL, MANO DE OBRA, EQUIPO Y HERRAMIENTA.
MATERIALES
PTH-OC-204PERFIL TUBULAR REDONDO HUECO DE 10" PZA $11,722.53 1.020000 86.14%
$11,956.98

CED. 40
CO08PRIMARIO ANTICORROSIVO No.2, 89-97 LT $52.76 0.500000 0.19%

$26.38
BLANCO, 98 GRIS CLARO, 96 ROJO OXIDO
SUBTOTAL: MATERIALES $11,983.36 86.33%
MANO DE OBRA
1F1ACUADRILLA No 6 (1 FIERRERO + 1 JOR $934.21 / 0.850000 $1,099.07 7.92%

AYUDANTE)
SUBTOTAL: MANO DE OBRA $1,099.07 7.92%
EQUIPO Y HERRAMIENTA
%MO1HERRAMIENTA MENOR % $1,099.07 0.030000 0.24%

$32.97
%MO2ANDAMIOS % $1,099.07 0.030000 0.24%

$32.97
SUBTOTAL: EQUIPO Y HERRAMIENTA $65.94 0.48%
BASICOS
ESTCARTCartabn para estructura a base de placa de KG $54.29 1.000000 0.39%

$54.29
acero A-36, soldada a columnas y/o postes con
soldadura de electrodo 7018, incluye:
materiales, cortes, soldadura, mano de obra,
equipo y herramienta.
ESA64040Placa base de 3/4" de 45x45 cm. con 4 anclas PZA $677.91 1.000000 $677.91 4.88%

de redondo de 1" con un desarrollo de 90 cm


con rosca en un extremo, incluye: tuercas y
rondanas, trazo, materiales, cortes, soldadura,
fijacin, mano de obra, equipo y herramienta.
SUBTOTAL: BASICOS $732.20 5.27%
Costo Directo: $13,880.57
INDIRECTOS 10.358% $1,437.75
SUBTOTAL $15,318.32
FINANCIAMIENTO 2.2356% $342.46
SUBTOTAL $15,660.78
UTILIDAD 12.9032% $2,020.74
PRECIO UNITARIO $17,681.52
(* DIECISIETE MIL SEISCIENTOS OCHENTA Y UN PESOS 52/100 M.N.
*)
ADMINISTRADOR UNICO C. DANIEL ORTIZ ALCARAZ
14-jun-2017 Pagina: 12 de 36
EDIFICACIONES Y RECONSTRUCCIONES CHIGULERA S.A. DE C.V.
Dependencia: H. AYUNTAMIENTO MUNICIPAL CONSTITUCIONAL
SANTA CRUZ XOXOCOTLAN

No. DE INVITACIN: MSCX/INV/FORTALECE/0701-N/2017 Duracin: 60 das naturales


Obra: CONSTRUCCION DE TECHADO EN LA ESCUELA PRIMARIA SOR JUANA INES DE LA CRUZ CLAVE: 20DPR3454E

Lugar: COLONIA LAS CULTURAS SANTA CRUZ XOXOCOTLAN OAXACA Inicio Obra: 26-jun-2017
Fin Obra: 24-ago-2017
ANLISIS, CLCULO E INTEGRACIN DE LOS PRECIOS UNITARIOS (ANEXO 10)

Cdigo Concepto Unidad Costo Cantidad Importe %


Partida: 1.2 Anlisis No.: 20
Anlisis: HERR:0010 M2 487.21
SUMINISTRO, NIVELACION Y MONTAJE DE CUBIERTA EN ARCO , A BASE DE LAMINA PINTRO ALUM CAL. 26, , INCLUYE: FLETES AL
SITIO,GRUA PARA MONTAJE, MANIOBRAS, ELEVACION, ACARREOS A UNA ESTACION DE 20 MTS., SOLDADURA E-6013 Y E-7018, CORTES,
FIJACION, SELLADO DE ORIFICIOS CON SILICON, HERRAMIENTA, MANO DE OBRA Y LIMPIEZA GENERAL.
MATERIALES
CO08PRIMARIO ANTICORROSIVO No.2, 89-97 LT $52.76 0.604000 $31.87 5.48%

BLANCO, 98 GRIS CLARO, 96 ROJO OXIDO


7018SOLDADURA ELECTRODO 7018 KG $34.19 0.075000 $2.56 0.44%

FB23PERFIL PTR DE 1 1/2" DE 1/8" KG $18.91 1.000000 3.25%

$18.91
SUBTOTAL: MATERIALES $53.34 9.17%
MANO DE OBRA
1F1ACUADRILLA No 6 (1 FIERRERO + 1 JOR $934.21 / 4.000000 $233.55 40.16%

AYUDANTE)
SUBTOTAL: MANO DE OBRA $233.55 40.16%
EQUIPO Y HERRAMIENTA
%MO1HERRAMIENTA MENOR % $233.55 0.030000 $7.01 1.21%

%MO2ANDAMIOS % $233.55 0.030000 $7.01 1.21%

EQPLANPLANTA DE SOLDAR MILLER HOR $7.44 0.500000 $3.72 0.64%

EQGRUAGRUA DE PATIO DE 20. TON HOR $834.18 / 200.000000 $4.17 0.72%

SUBTOTAL: EQUIPO Y HERRAMIENTA $21.91 3.78%


BASICOS
LAR10126Lmina pintro R-101, cal. 26, en cubierta M2 $267.37 1.020000 46.90%

$272.72
metlica, incluye: materiales, acarreos,
elevacin, fijacion, mano de obra, equipo y
herramienta.
SUBTOTAL: BASICOS $272.72 46.90%
Costo Directo: $581.52
INDIRECTOS 10.358% $60.23
SUBTOTAL $641.75
FINANCIAMIENTO 2.2356% $14.35
SUBTOTAL $656.10
UTILIDAD 12.9032% $84.66
PRECIO UNITARIO $740.76
(* SETECIENTOS CUARENTA PESOS 76/100 M.N. *)

ADMINISTRADOR UNICO C. DANIEL ORTIZ ALCARAZ


14-jun-2017 Pagina: 13 de 36
EDIFICACIONES Y RECONSTRUCCIONES CHIGULERA S.A. DE C.V.
Dependencia: H. AYUNTAMIENTO MUNICIPAL CONSTITUCIONAL
SANTA CRUZ XOXOCOTLAN

No. DE INVITACIN: MSCX/INV/FORTALECE/0701-N/2017 Duracin: 60 das naturales


Obra: CONSTRUCCION DE TECHADO EN LA ESCUELA PRIMARIA SOR JUANA INES DE LA CRUZ CLAVE: 20DPR3454E

Lugar: COLONIA LAS CULTURAS SANTA CRUZ XOXOCOTLAN OAXACA Inicio Obra: 26-jun-2017
Fin Obra: 24-ago-2017
ANLISIS, CLCULO E INTEGRACIN DE LOS PRECIOS UNITARIOS (ANEXO 10)

Cdigo Concepto Unidad Costo Cantidad Importe %


Partida: 1.2 Anlisis No.: 30
Anlisis: HERR:0110 ML 53.16
CANALON DE LAMINA GALVANIZADA CAL 26 DE 8" x 4" DE DESARROLLO, APOYADO EN PTR Y LARGUERO, INCLUYE: MATERIALES DE
FIJACION, FLETES, ACARREOS, MANIOBRAS, DESPERDICIOS, ELEVACIONES, ANDAMIOS, MANO DE OBRA, HERRAMIENTA Y EQUIPO.
MATERIALES
7018SOLDADURA ELECTRODO 7018 KG $34.19 0.150000 $5.13 0.83%

CO08PRIMARIO ANTICORROSIVO No.2, 89-97 LT $52.76 0.100000 0.86%

$5.28
BLANCO, 98 GRIS CLARO, 96 ROJO OXIDO
THINNERTHINNER STANDARD LT $45.90 0.500000 3.72%

$22.95
FB001ANGULO DE FIER.1/8" x 3/4" TON $14,498.28 0.005000 11.75%
$72.49

$268.34
FB120LAMINA GALV. ESTRUCT. CAL.24 DE 16'' PZA $813.16 0.330000 43.51%
SUBTOTAL: MATERIALES $374.19 60.67%
MANO DE OBRA
1S2ECUADRILLA No 18 (1 SOLDADOR+2 AY.ESP.) JOR $1,494.74 / 7.000000 $213.53 34.62%

SUBTOTAL: MANO DE OBRA $213.53 34.62%


EQUIPO Y HERRAMIENTA
EQECORTEEQUIPO DE CORTE OXI-ACETILENO HOR $858.31 0.010000 1.39%
$8.58

EQPLANPLANTA DE SOLDAR MILLER HOR $7.44 0.100000 $0.74 0.12%

%MO1HERRAMIENTA MENOR % $213.53 0.040000 1.38%


$8.54

DOBLEZDOBLEZ DE LAMINA PZA $5.57 2.000000 1.81%


$11.14

SUBTOTAL: EQUIPO Y HERRAMIENTA $29.00 4.70%


Costo Directo: $616.72
INDIRECTOS 10.358% $63.88
SUBTOTAL $680.60
FINANCIAMIENTO 2.2356% $15.22
SUBTOTAL $695.82
UTILIDAD 12.9032% $89.78
PRECIO UNITARIO $785.60
(* SETECIENTOS OCHENTA Y CINCO PESOS 60/100 M.N. *)

ADMINISTRADOR UNICO C. DANIEL ORTIZ ALCARAZ


14-jun-2017 Pagina: 14 de 36
EDIFICACIONES Y RECONSTRUCCIONES CHIGULERA S.A. DE C.V.
Dependencia: H. AYUNTAMIENTO MUNICIPAL CONSTITUCIONAL
SANTA CRUZ XOXOCOTLAN

No. DE INVITACIN: MSCX/INV/FORTALECE/0701-N/2017 Duracin: 60 das naturales


Obra: CONSTRUCCION DE TECHADO EN LA ESCUELA PRIMARIA SOR JUANA INES DE LA CRUZ CLAVE: 20DPR3454E

Lugar: COLONIA LAS CULTURAS SANTA CRUZ XOXOCOTLAN OAXACA Inicio Obra: 26-jun-2017
Fin Obra: 24-ago-2017
ANLISIS, CLCULO E INTEGRACIN DE LOS PRECIOS UNITARIOS (ANEXO 10)

Cdigo Concepto Unidad Costo Cantidad Importe %


Partida: 1.2 Anlisis No.: 40
Anlisis: ESTR:0215 PZA 1
CUBIERTA PARA GRADAS DE 15x2.05 M A BASE DE ESTRUCTURA METALICA CON TUBO CED. 40 DE 1 1/2" Y 2" Y POSTES DE 3" AHOGADA
EN MURO DE RESPALDO EN GRADAS, INCLUYE: TECHO DE POLICARBONATO UNIDO MEDIANTE PIJAS CON ARANDELAS Y GOMAS,
MATERIALES, ACARREOS, CORTES, TRAZO, HABILITADO, SOLDADURA, APLICACIN DE PRIMER ANTICORROSIVO, MONTAJE, MANO DE
OBRA, EQUIPO Y HERRAMIENTA.
MATERIALES
PLCRBNTPOLICARBONATO PARA TECHO M2 $225.87 31.030000 $7,008.75 16.83%

D-0107PIJA CABEZA PLANA 10x1 1/2" CTO. $26.98 0.400000 $10.79 0.03%

7018SOLDADURA ELECTRODO 7018 KG $34.19 0.057000 0.00%

$1.95
SUBTOTAL: MATERIALES $7,021.49 16.86%
MANO DE OBRA
1H1ACUADRILLA No 9 (1 HERRERO + AYUDANTE) JOR $994.33 / 0.270000 8.84%
$3,682.70

SUBTOTAL: MANO DE OBRA $3,682.70 8.84%


EQUIPO Y HERRAMIENTA
EQPLANPLANTA DE SOLDAR MILLER HOR $7.44 0.500000 $3.72 0.01%

SUBTOTAL: EQUIPO Y HERRAMIENTA $3.72 0.01%


BASICOS
TUA4075Tubo de acero soldable C-40 sin costura de 75 ML $645.22 16.750000 $10,807.44 25.94%

mm. de dimetro, incluye: materiales, acarreos,


cortes, soldadura, mano de obra, pruebas,
equipo y herramienta.
TUA4050Tubo de acero soldable C-40 sin costura de 50 ML $357.28 9.850000 $3,519.21 8.45%

mm. de dimetro, incluye: materiales, acarreos,


cortes, soldadura, mano de obra, pruebas,
equipo y herramienta.
TUA4038Tubo de acero soldable C-40 sin costura de 38 ML $284.12 58.500000 39.90%

$16,621.02
mm. de dimetro, incluye: materiales, acarreos,
cortes, soldadura, mano de obra, pruebas,
equipo y herramienta.
SUBTOTAL: BASICOS $30,947.67 74.29%
Costo Directo: $41,655.58
INDIRECTOS 10.358% $4,314.68
SUBTOTAL $45,970.26
FINANCIAMIENTO 2.2356% $1,027.71
SUBTOTAL $46,997.97
UTILIDAD 12.9032% $6,064.24
PRECIO UNITARIO $53,062.21
(* CINCUENTA Y TRES MIL SESENTA Y DOS PESOS 21/100 M.N. *)
ADMINISTRADOR UNICO C. DANIEL ORTIZ ALCARAZ
14-jun-2017 Pagina: 15 de 36
EDIFICACIONES Y RECONSTRUCCIONES CHIGULERA S.A. DE C.V.
Dependencia: H. AYUNTAMIENTO MUNICIPAL CONSTITUCIONAL
SANTA CRUZ XOXOCOTLAN

No. DE INVITACIN: MSCX/INV/FORTALECE/0701-N/2017 Duracin: 60 das naturales


Obra: CONSTRUCCION DE TECHADO EN LA ESCUELA PRIMARIA SOR JUANA INES DE LA CRUZ CLAVE: 20DPR3454E

Lugar: COLONIA LAS CULTURAS SANTA CRUZ XOXOCOTLAN OAXACA Inicio Obra: 26-jun-2017
Fin Obra: 24-ago-2017
ANLISIS, CLCULO E INTEGRACIN DE LOS PRECIOS UNITARIOS (ANEXO 10)

Cdigo Concepto Unidad Costo Cantidad Importe %


Partida: 1.2 Anlisis No.: 50
Anlisis: ESTR:0220 KG 1,641.43
ESTRUCTURA METALICA EN ARCO A BASE DE TUBO DE FIERRO ESTRUCTURAL CED. 40 DE 2 1/2" EN CUERDA INFERIOR, SUPERIOR,
MONTANTES Y DIAGONALES SOLDADA EN SUS EXTREMOS A UNA PLACA DE 40X40 CMS. DE 1/2", INCLUYE: MATERIALES, ACARREOS,
CORTES, TRAZO, HABILITADO, SOLDADURA, APLICACIN DE PRIMER ANTICORROSIVO, TAPONES A BASE DE SOLERA DE 1/8",
MONTAJE, MANO DE OBRA, EQUIPO Y HERRAMIENTA.
MATERIALES
FB099PLACA A-36 DE 3 Y 4 DE 3/16" A 1/2" TON $14,498.28 0.000190 $2.75 3.47%

CO08PRIMARIO ANTICORROSIVO No.2, 89-97 LT $52.76 0.067000 4.46%

$3.53
BLANCO, 98 GRIS CLARO, 96 ROJO OXIDO
7018SOLDADURA ELECTRODO 7018 KG $34.19 0.070000 3.02%

$2.39
N105 TUBO NEG SOLD C-40 S/C 64MM KG $26.40 1.050000 $27.72 35.02%

SUBTOTAL: MATERIALES $36.39 45.97%


MANO DE OBRA
1H1ACUADRILLA No 9 (1 HERRERO + AYUDANTE) JOR $994.33 / 220.000000 5.71%

$4.52
1S1ECUADRILLA No 17 (1 SOLDADOR+1 AY.ESP.) JOR $1,114.22 / 45.000000 $24.76 31.28%

SUBTOTAL: MANO DE OBRA $29.28 36.99%


EQUIPO Y HERRAMIENTA
EQPLANPLANTA DE SOLDAR MILLER HOR $7.44 0.500000 $3.72 4.70%

%MO1HERRAMIENTA MENOR % $29.28 0.030000 $0.88 1.11%

%MO2ANDAMIOS % $29.28 0.030000 $0.88 1.11%

EQPLANPLANTA DE SOLDAR MILLER HOR $7.44 0.500000 4.70%


$3.72

EQECORTEEQUIPO DE CORTE OXI-ACETILENO HOR $858.31 0.005000 5.42%


$4.29

SUBTOTAL: EQUIPO Y HERRAMIENTA $13.49 17.04%


Costo Directo: $79.16
INDIRECTOS 10.358% $8.20
SUBTOTAL $87.36
FINANCIAMIENTO 2.2356% $1.95
SUBTOTAL $89.31
UTILIDAD 12.9032% $11.52
PRECIO UNITARIO $100.83
(* CIEN PESOS 83/100 M.N. *)
ADMINISTRADOR UNICO C. DANIEL ORTIZ ALCARAZ
14-jun-2017 Pagina: 16 de 36
EDIFICACIONES Y RECONSTRUCCIONES CHIGULERA S.A. DE C.V.
Dependencia: H. AYUNTAMIENTO MUNICIPAL CONSTITUCIONAL
SANTA CRUZ XOXOCOTLAN

No. DE INVITACIN: MSCX/INV/FORTALECE/0701-N/2017 Duracin: 60 das naturales


Obra: CONSTRUCCION DE TECHADO EN LA ESCUELA PRIMARIA SOR JUANA INES DE LA CRUZ CLAVE: 20DPR3454E

Lugar: COLONIA LAS CULTURAS SANTA CRUZ XOXOCOTLAN OAXACA Inicio Obra: 26-jun-2017
Fin Obra: 24-ago-2017
ANLISIS, CLCULO E INTEGRACIN DE LOS PRECIOS UNITARIOS (ANEXO 10)

Cdigo Concepto Unidad Costo Cantidad Importe %


Partida: 1.2 Anlisis No.: 60
Anlisis: ESTR:0225 KG 2,204.27
ESTRUCTURA METALICA LATERAL A BASE DE PTR DE 2 1/2" CAL. 11 EN CUERDA INFERIOR, SUPERIOR Y DIAGONALES INCLUYE:
MATERIALES, ACARREOS, CORTES, TRAZO, HABILITADO, SOLDADURA, APLICACIN DE PRIMER ANTICORROSIVO, TAPONES A BASE DE
SOLERA DE 1/8", MONTAJE, MANO DE OBRA, EQUIPO Y HERRAMIENTA.
MATERIALES
PTR5003PTR DE 2" x 1/8" KG $25.09 1.070000 $26.85 36.96%

CO08PRIMARIO ANTICORROSIVO No.2, 89-97 LT $52.76 0.075000 $3.96 5.45%

BLANCO, 98 GRIS CLARO, 96 ROJO OXIDO


7018SOLDADURA ELECTRODO 7018 KG $34.19 0.068000 3.19%

$2.32
SUBTOTAL: MATERIALES $33.13 45.60%
MANO DE OBRA

1H1ACUADRILLA No 9 (1 HERRERO + AYUDANTE) JOR $994.33 / 200.000000 $4.97 6.84%

1S1ECUADRILLA No 17 (1 SOLDADOR+1 AY.ESP.) JOR $1,114.22 / 45.000000 34.08%

$24.76
SUBTOTAL: MANO DE OBRA $29.73 40.92%
EQUIPO Y HERRAMIENTA
EQPLANPLANTA DE SOLDAR MILLER HOR $7.44 0.500000 5.12%

$3.72
%MO1HERRAMIENTA MENOR % $29.73 0.030000 $0.89 1.23%

%MO2ANDAMIOS % $29.73 0.030000 $0.89 1.23%

EQECORTEEQUIPO DE CORTE OXI-ACETILENO HOR $858.31 0.005000 5.91%

$4.29
SUBTOTAL: EQUIPO Y HERRAMIENTA $9.79 13.49%
Costo Directo: $72.65
INDIRECTOS 10.358% $7.53
SUBTOTAL $80.18
FINANCIAMIENTO 2.2356% $1.79
SUBTOTAL $81.97
UTILIDAD 12.9032% $10.58
PRECIO UNITARIO $92.55
(* NOVENTA Y DOS PESOS 55/100 M.N. *)

ADMINISTRADOR UNICO C. DANIEL ORTIZ ALCARAZ


14-jun-2017 Pagina: 17 de 36
EDIFICACIONES Y RECONSTRUCCIONES CHIGULERA S.A. DE C.V.
Dependencia: H. AYUNTAMIENTO MUNICIPAL CONSTITUCIONAL
SANTA CRUZ XOXOCOTLAN

No. DE INVITACIN: MSCX/INV/FORTALECE/0701-N/2017 Duracin: 60 das naturales


Obra: CONSTRUCCION DE TECHADO EN LA ESCUELA PRIMARIA SOR JUANA INES DE LA CRUZ CLAVE: 20DPR3454E

Lugar: COLONIA LAS CULTURAS SANTA CRUZ XOXOCOTLAN OAXACA Inicio Obra: 26-jun-2017
Fin Obra: 24-ago-2017
ANLISIS, CLCULO E INTEGRACIN DE LOS PRECIOS UNITARIOS (ANEXO 10)

Cdigo Concepto Unidad Costo Cantidad Importe %


Partida: 1.2 Anlisis No.: 70
Anlisis: ESTR:0230 KG 2,392.32
SUMINISTRO Y COLOCACION DE LARGUEROS A BASE DE CANAL MONTEN DE 6" x 2" CAL. 12, UNIDO A LA CUERDA SUPERIOR DE LAS
ARMADURAS EN ARCO MEDIANTE SOLDADURA, INCLUYE: MATERIALES, ACARREOS, CORTES, TRAZO, HABILITADO, SOLDADURA,
APLICACIN DE PRIMER ANTICORROSIVO, MONTAJE, MANO DE OBRA, EQUIPO Y HERRAMIENTA.
MATERIALES
7018SOLDADURA ELECTRODO 7018 KG $34.19 0.030000 $1.03 3.12%

CO08PRIMARIO ANTICORROSIVO No.2, 89-97 LT $52.76 0.025000 4.00%

$1.32
BLANCO, 98 GRIS CLARO, 96 ROJO OXIDO
$0.69

THINNERTHINNER STANDARD LT $45.90 0.015000 2.09%


FB089MONTEN PINTADO TON $20,253.47 0.001050 $21.27 64.44%

SUBTOTAL: MATERIALES $24.31 73.65%


MANO DE OBRA
1S2ECUADRILLA No 18 (1 SOLDADOR+2 AY.ESP.) JOR $1,494.74 / 180.000000 25.14%

$8.30
SUBTOTAL: MANO DE OBRA $8.30 25.14%
EQUIPO Y HERRAMIENTA
EQPLANPLANTA DE SOLDAR MILLER HOR $7.44 0.010000 $0.07 0.21%

%MO1HERRAMIENTA MENOR % $8.30 0.040000 $0.33 1.00%

SUBTOTAL: EQUIPO Y HERRAMIENTA $0.40 1.21%


Costo Directo: $33.01
INDIRECTOS 10.358% $3.42
SUBTOTAL $36.43
FINANCIAMIENTO 2.2356% $0.81
SUBTOTAL $37.24
UTILIDAD 12.9032% $4.81
PRECIO UNITARIO $42.05
(* CUARENTA Y DOS PESOS 05/100 M.N. *)

ADMINISTRADOR UNICO C. DANIEL ORTIZ ALCARAZ


14-jun-2017 Pagina: 18 de 36
EDIFICACIONES Y RECONSTRUCCIONES CHIGULERA S.A. DE C.V.
Dependencia: H. AYUNTAMIENTO MUNICIPAL CONSTITUCIONAL
SANTA CRUZ XOXOCOTLAN

No. DE INVITACIN: MSCX/INV/FORTALECE/0701-N/2017 Duracin: 60 das naturales


Obra: CONSTRUCCION DE TECHADO EN LA ESCUELA PRIMARIA SOR JUANA INES DE LA CRUZ CLAVE: 20DPR3454E

Lugar: COLONIA LAS CULTURAS SANTA CRUZ XOXOCOTLAN OAXACA Inicio Obra: 26-jun-2017
Fin Obra: 24-ago-2017
ANLISIS, CLCULO E INTEGRACIN DE LOS PRECIOS UNITARIOS (ANEXO 10)

Cdigo Concepto Unidad Costo Cantidad Importe %


Partida: 1.3 Anlisis No.: 10
Anlisis: SALGGC08 SAL 10
SALIDA ELCTRICA APARENTE PARA CONTACTO DUPLEX POLARIZADO CON CONEXION A TIERRA, Y PROTECCION CONTRA FALLA A
TIERRA. CON PLACA Y TAPA CON INSTALACION AL INTEMPERIE.
MATERIALES
TT3342TUBO PVC PESADO 13MM PZA. $12.48 1.400000 $17.47 3.08%

TT3343TUBO PVC PESADO 19MM PZA. $15.89 0.700000 1.96%

$11.12
TT3880CAJA CUAD PVC 13MM C/TAPA PZA. $16.73 1.000000 2.95%
$16.73

TT3881CAJA CUAD PVC 19MM C/TAPA PZA. $21.26 1.000000 $21.26 3.74%

TT3883CHALUPA UNIVERS PVC DURALON PZA. $8.71 1.000000 $8.71 1.53%

TT3408CONEC PVC PESADO 13MM PZA. $3.91 2.000000 $7.82 1.38%

TT3409CONEC PVC PESADO 19MM PZA. $5.34 2.000000 1.88%


$10.68

TT3604CODO PVC PESADO 13MM PZA. $4.54 1.000000 0.80%


$4.54

DC2024CABLE THW 12 NEG MTS. $5.49 13.200000 $72.47 12.76%


DC2030CABLE THW 10 NEG MTS. $8.34 4.800000 7.05%

$40.03
AA1281SOCKET BAQ SENC CAFE PZA. $3.65 1.000000 0.64%
$3.65

RD0629INT SENC LUXORY PZA. $24.68 1.000000 $24.68 4.35%

RA1196PLA BAQ LUXORY MARF 1U PZA $20.85 1.000000 $20.85 3.67%

PIJAPIJA PZA $0.60 6.000000 $3.60 0.63%

TAQUETETAQUETE PZA $0.48 6.000000 0.51%

$2.88
SUBTOTAL: MATERIALES $266.49 46.93%
MANO DE OBRA
1E1ECUADRILLA No 19 (1 ELECTRIC.+AY.ESP) JOR $1,024.04 / 3.600000 50.08%
$284.46

SUBTOTAL: MANO DE OBRA $284.46 50.08%


EQUIPO Y HERRAMIENTA
%MO1HERRAMIENTA MENOR % $284.46 0.030000 1.50%
$8.53

%MO2ANDAMIOS % $284.46 0.030000 $8.53 1.50%

SUBTOTAL: EQUIPO Y HERRAMIENTA $17.06 3.00%


Costo Directo: $568.01
INDIRECTOS 10.358% $58.83
SUBTOTAL $626.84
FINANCIAMIENTO 2.2356% $14.01
SUBTOTAL $640.85
UTILIDAD 12.9032% $82.69
PRECIO UNITARIO $723.54
(* SETECIENTOS VEINTITRES PESOS 54/100 M.N. *)
ADMINISTRADOR UNICO C. DANIEL ORTIZ ALCARAZ
14-jun-2017 Pagina: 19 de 36
EDIFICACIONES Y RECONSTRUCCIONES CHIGULERA S.A. DE C.V.
Dependencia: H. AYUNTAMIENTO MUNICIPAL CONSTITUCIONAL
SANTA CRUZ XOXOCOTLAN

No. DE INVITACIN: MSCX/INV/FORTALECE/0701-N/2017 Duracin: 60 das naturales


Obra: CONSTRUCCION DE TECHADO EN LA ESCUELA PRIMARIA SOR JUANA INES DE LA CRUZ CLAVE: 20DPR3454E

Lugar: COLONIA LAS CULTURAS SANTA CRUZ XOXOCOTLAN OAXACA Inicio Obra: 26-jun-2017
Fin Obra: 24-ago-2017
ANLISIS, CLCULO E INTEGRACIN DE LOS PRECIOS UNITARIOS (ANEXO 10)

Cdigo Concepto Unidad Costo Cantidad Importe %


Partida: 1.3 Anlisis No.: 20
Anlisis: TGALP13 ML 130
TUBO CONDUIT APARENTE DE 21 MM. DE DIMETRO, INCLUYE: MATERIALES, ACARREOS, CORTES, DESPERDICIOS, INSTALACIN,
MANO DE OBRA, PRUEBAS, EQUIPO Y HERRAMIENTA.
MATERIALES
TT3343TUBO PVC PESADO 19MM PZA. $15.89 0.350000 $5.56 24.00%

$1.62

360-211-17-34BOTE PEGAMENTO SILER 480 grs PESADO PZA $108.02 0.015000 6.99%
SUBTOTAL: MATERIALES $7.18 30.99%
MANO DE OBRA
1E1ECUADRILLA No 19 (1 ELECTRIC.+AY.ESP) JOR $1,024.04 / 66.000000 66.98%
$15.52

SUBTOTAL: MANO DE OBRA $15.52 66.98%


EQUIPO Y HERRAMIENTA
%MO1HERRAMIENTA MENOR % $15.52 0.030000 $0.47 2.03%

SUBTOTAL: EQUIPO Y HERRAMIENTA $0.47 2.03%


Costo Directo: $23.17
INDIRECTOS 10.358% $2.40
SUBTOTAL $25.57
FINANCIAMIENTO 2.2356% $0.57
SUBTOTAL $26.14
UTILIDAD 12.9032% $3.37
PRECIO UNITARIO $29.51
(* VEINTINUEVE PESOS 51/100 M.N. *)

ADMINISTRADOR UNICO C. DANIEL ORTIZ ALCARAZ


14-jun-2017 Pagina: 20 de 36
EDIFICACIONES Y RECONSTRUCCIONES CHIGULERA S.A. DE C.V.
Dependencia: H. AYUNTAMIENTO MUNICIPAL CONSTITUCIONAL
SANTA CRUZ XOXOCOTLAN

No. DE INVITACIN: MSCX/INV/FORTALECE/0701-N/2017 Duracin: 60 das naturales


Obra: CONSTRUCCION DE TECHADO EN LA ESCUELA PRIMARIA SOR JUANA INES DE LA CRUZ CLAVE: 20DPR3454E

Lugar: COLONIA LAS CULTURAS SANTA CRUZ XOXOCOTLAN OAXACA Inicio Obra: 26-jun-2017
Fin Obra: 24-ago-2017
ANLISIS, CLCULO E INTEGRACIN DE LOS PRECIOS UNITARIOS (ANEXO 10)

Cdigo Concepto Unidad Costo Cantidad Importe %


Partida: 1.3 Anlisis No.: 30
Anlisis: CPVCP51 ML 15
TUBO CONDUIT APARENTE DE 35 MM. DE DIMETRO, INCLUYE: MATERIALES, ACARREOS, CORTES, DESPERDICIOS, INSTALACIN,
MANO DE OBRA, PRUEBAS, EQUIPO Y HERRAMIENTA.
MATERIALES
TT3346TUBO PVC PESADO 38MM PZA. $38.33 0.350000 $13.42 34.74%

$3.24

360-211-17-34BOTE PEGAMENTO SILER 480 grs PESADO PZA $108.02 0.030000 8.39%
SUBTOTAL: MATERIALES $16.66 43.13%
MANO DE OBRA
1E1ECUADRILLA No 19 (1 ELECTRIC.+AY.ESP) JOR $1,024.04 / 48.000000 55.22%
$21.33

SUBTOTAL: MANO DE OBRA $21.33 55.22%


EQUIPO Y HERRAMIENTA
%MO1HERRAMIENTA MENOR % $21.33 0.030000 $0.64 1.66%

SUBTOTAL: EQUIPO Y HERRAMIENTA $0.64 1.66%


Costo Directo: $38.63
INDIRECTOS 10.358% $4.00
SUBTOTAL $42.63
FINANCIAMIENTO 2.2356% $0.95
SUBTOTAL $43.58
UTILIDAD 12.9032% $5.62
PRECIO UNITARIO $49.20
(* CUARENTA Y NUEVE PESOS 20/100 M.N. *)

ADMINISTRADOR UNICO C. DANIEL ORTIZ ALCARAZ


14-jun-2017 Pagina: 21 de 36
EDIFICACIONES Y RECONSTRUCCIONES CHIGULERA S.A. DE C.V.
Dependencia: H. AYUNTAMIENTO MUNICIPAL CONSTITUCIONAL
SANTA CRUZ XOXOCOTLAN

No. DE INVITACIN: MSCX/INV/FORTALECE/0701-N/2017 Duracin: 60 das naturales


Obra: CONSTRUCCION DE TECHADO EN LA ESCUELA PRIMARIA SOR JUANA INES DE LA CRUZ CLAVE: 20DPR3454E

Lugar: COLONIA LAS CULTURAS SANTA CRUZ XOXOCOTLAN OAXACA Inicio Obra: 26-jun-2017
Fin Obra: 24-ago-2017
ANLISIS, CLCULO E INTEGRACIN DE LOS PRECIOS UNITARIOS (ANEXO 10)

Cdigo Concepto Unidad Costo Cantidad Importe %


Partida: 1.3 Anlisis No.: 40
Anlisis: THWC10 ML 320
SUMINISTRO E INSTALACIN DE CABLE AWG CAL. 10, DE LA MARCA CONDUMEX, INCLUYE: MATERIALES, ACARREOS, INSTALACIN,
PUNTAS, PRUEBAS, MANO DE OBRA, EQUIPO Y HERRAMIENTA.
MATERIALES
DC2030CABLE THW 10 NEG MTS. $8.34 1.070000 58.88%

$8.92
DS1493CINTA PLAST 19MM X 18M NEG PZA. $8.98 0.010000 $0.09 0.59%

SUBTOTAL: MATERIALES $9.01 59.47%


MANO DE OBRA
1E1ECUADRILLA No 19 (1 ELECTRIC.+AY.ESP) JOR $1,024.04 / 180.000000 37.56%
$5.69

SUBTOTAL: MANO DE OBRA $5.69 37.56%


EQUIPO Y HERRAMIENTA
%MO1HERRAMIENTA MENOR % $5.69 0.030000 1.12%
$0.17

%MO2ANDAMIOS % $5.69 0.050000 1.85%


$0.28

SUBTOTAL: EQUIPO Y HERRAMIENTA $0.45 2.97%


Costo Directo: $15.15
INDIRECTOS 10.358% $1.57
SUBTOTAL $16.72
FINANCIAMIENTO 2.2356% $0.37
SUBTOTAL $17.09
UTILIDAD 12.9032% $2.21
PRECIO UNITARIO $19.30
(* DIECINUEVE PESOS 30/100 M.N. *)

ADMINISTRADOR UNICO C. DANIEL ORTIZ ALCARAZ


14-jun-2017 Pagina: 22 de 36
EDIFICACIONES Y RECONSTRUCCIONES CHIGULERA S.A. DE C.V.
Dependencia: H. AYUNTAMIENTO MUNICIPAL CONSTITUCIONAL
SANTA CRUZ XOXOCOTLAN

No. DE INVITACIN: MSCX/INV/FORTALECE/0701-N/2017 Duracin: 60 das naturales


Obra: CONSTRUCCION DE TECHADO EN LA ESCUELA PRIMARIA SOR JUANA INES DE LA CRUZ CLAVE: 20DPR3454E

Lugar: COLONIA LAS CULTURAS SANTA CRUZ XOXOCOTLAN OAXACA Inicio Obra: 26-jun-2017
Fin Obra: 24-ago-2017
ANLISIS, CLCULO E INTEGRACIN DE LOS PRECIOS UNITARIOS (ANEXO 10)

Cdigo Concepto Unidad Costo Cantidad Importe %


Partida: 1.3 Anlisis No.: 50
Anlisis: THWC12 ML 160
SUMINISTRO E INSTALACIN DE CABLE AWG CAL. 12, DE LA MARCA CONDUMEX, INCLUYE: MATERIALES, ACARREOS, INSTALACIN,
PUNTAS, PRUEBAS, MANO DE OBRA, EQUIPO Y HERRAMIENTA.
MATERIALES
DC2030CABLE THW 10 NEG MTS. $8.34 1.070000 58.88%

$8.92
DS1493CINTA PLAST 19MM X 18M NEG PZA. $8.98 0.010000 $0.09 0.59%

SUBTOTAL: MATERIALES $9.01 59.47%


MANO DE OBRA
1E1ECUADRILLA No 19 (1 ELECTRIC.+AY.ESP) JOR $1,024.04 / 180.000000 37.56%
$5.69

SUBTOTAL: MANO DE OBRA $5.69 37.56%


EQUIPO Y HERRAMIENTA
%MO1HERRAMIENTA MENOR % $5.69 0.030000 1.12%
$0.17

%MO2ANDAMIOS % $5.69 0.050000 1.85%


$0.28

SUBTOTAL: EQUIPO Y HERRAMIENTA $0.45 2.97%


Costo Directo: $15.15
INDIRECTOS 10.358% $1.57
SUBTOTAL $16.72
FINANCIAMIENTO 2.2356% $0.37
SUBTOTAL $17.09
UTILIDAD 12.9032% $2.21
PRECIO UNITARIO $19.30
(* DIECINUEVE PESOS 30/100 M.N. *)

ADMINISTRADOR UNICO C. DANIEL ORTIZ ALCARAZ


14-jun-2017 Pagina: 23 de 36
EDIFICACIONES Y RECONSTRUCCIONES CHIGULERA S.A. DE C.V.
Dependencia: H. AYUNTAMIENTO MUNICIPAL CONSTITUCIONAL
SANTA CRUZ XOXOCOTLAN

No. DE INVITACIN: MSCX/INV/FORTALECE/0701-N/2017 Duracin: 60 das naturales


Obra: CONSTRUCCION DE TECHADO EN LA ESCUELA PRIMARIA SOR JUANA INES DE LA CRUZ CLAVE: 20DPR3454E

Lugar: COLONIA LAS CULTURAS SANTA CRUZ XOXOCOTLAN OAXACA Inicio Obra: 26-jun-2017
Fin Obra: 24-ago-2017
ANLISIS, CLCULO E INTEGRACIN DE LOS PRECIOS UNITARIOS (ANEXO 10)

Cdigo Concepto Unidad Costo Cantidad Importe %


Partida: 1.3 Anlisis No.: 60
Anlisis: INTS3200 PZA 1
TABLERO DE DISTRIBUCION. EN CAJA 1, INCLUYE: CONEXION, PRUEBAS, MANO DE OBRA, EQUIPO Y HERRAMIENTA.
MATERIALES
CI6745INTERIOR NQOD442L225CU PZA. $4,352.57 1.000000 $4,352.57 17.10%

CI6788CAJA MH50M PZA. $395.43 1.000000 1.55%

$395.43
CI6790FTE MHC50 SOB PZA. $1,907.30 1.000000 7.49%

$1,907.30
CI6733KIT INT PRINCIPAL NQODKA PZA. $1,950.71 1.000000 $1,950.71 7.66%

CC6167INT TERMAG KAL 3P 200A PZA. $11,329.00 1.000000 44.51%

$11,329.00
CC6078INT TERMAG QOB 1P 20A PZA. $140.46 16.000000 8.83%

$2,247.36
SUBTOTAL: MATERIALES $22,182.37 87.14%
MANO DE OBRA
1T1ECUADRILLA No 21 (1 TECNICO+ 1 AY.ESP.) JOR $1,234.46 / 0.388943 $3,173.88 12.47%

SUBTOTAL: MANO DE OBRA $3,173.88 12.47%


EQUIPO Y HERRAMIENTA
%MO1HERRAMIENTA MENOR % $3,173.88 0.030000 $95.22 0.37%

SUBTOTAL: EQUIPO Y HERRAMIENTA $95.22 0.37%


Costo Directo: $25,451.47
INDIRECTOS 10.358% $2,636.26
SUBTOTAL $28,087.73
FINANCIAMIENTO 2.2356% $627.93
SUBTOTAL $28,715.66
UTILIDAD 12.9032% $3,705.24
PRECIO UNITARIO $32,420.90
(* TREINTA Y DOS MIL CUATROCIENTOS VEINTE PESOS 90/100 M.N.
*)

ADMINISTRADOR UNICO C. DANIEL ORTIZ ALCARAZ


14-jun-2017 Pagina: 24 de 36
EDIFICACIONES Y RECONSTRUCCIONES CHIGULERA S.A. DE C.V.
Dependencia: H. AYUNTAMIENTO MUNICIPAL CONSTITUCIONAL
SANTA CRUZ XOXOCOTLAN

No. DE INVITACIN: MSCX/INV/FORTALECE/0701-N/2017 Duracin: 60 das naturales


Obra: CONSTRUCCION DE TECHADO EN LA ESCUELA PRIMARIA SOR JUANA INES DE LA CRUZ CLAVE: 20DPR3454E

Lugar: COLONIA LAS CULTURAS SANTA CRUZ XOXOCOTLAN OAXACA Inicio Obra: 26-jun-2017
Fin Obra: 24-ago-2017
ANLISIS, CLCULO E INTEGRACIN DE LOS PRECIOS UNITARIOS (ANEXO 10)

Cdigo Concepto Unidad Costo Cantidad Importe %


Partida: 1.3 Anlisis No.: 70
Anlisis: PRIMAPII PZA 10
LUMINARIA AUTOBALATRADA TIPO CAMPANA, DE 250 W., 220 V; CON LAMPARA DE ADITIVOS METALICOS. H= 7.5 M; MARCA "LJ
ILUMINACION"; MODELO CAMPANA CAT- CIP-250-AM-220-LP-L, CON ACCESORIO LENTE PLANO PROTECTOR CON SINCHO DE
PROTECCION, INCLUYE: MANO DE OBRA, EQUIPO Y HERRAMIENTA.
MATERIALES
LP739-ICCAMPANA LED 150 WATTS COMPACTA A PZA $3,684.38 1.000000 93.14%

$3,684.38
127/220 VOLTS MARCA TECNOLED
SUBTOTAL: MATERIALES $3,684.38 93.14%
MANO DE OBRA
1E1ECUADRILLA No 19 (1 ELECTRIC.+AY.ESP) JOR $1,024.04 / 4.000000 $256.01 6.47%

SUBTOTAL: MANO DE OBRA $256.01 6.47%


EQUIPO Y HERRAMIENTA
%MO1HERRAMIENTA MENOR % $256.01 0.030000 0.19%
$7.68

%MO2ANDAMIOS % $256.01 0.030000 $7.68 0.19%

SUBTOTAL: EQUIPO Y HERRAMIENTA $15.36 0.38%


Costo Directo: $3,955.75
INDIRECTOS 10.358% $409.74
SUBTOTAL $4,365.49
FINANCIAMIENTO 2.2356% $97.59
SUBTOTAL $4,463.08
UTILIDAD 12.9032% $575.88
PRECIO UNITARIO $5,038.96
(* CINCO MIL TREINTA Y OCHO PESOS 96/100 M.N. *)

ADMINISTRADOR UNICO C. DANIEL ORTIZ ALCARAZ


14-jun-2017 Pagina: 25 de 36
EDIFICACIONES Y RECONSTRUCCIONES CHIGULERA S.A. DE C.V.
Dependencia: H. AYUNTAMIENTO MUNICIPAL CONSTITUCIONAL
SANTA CRUZ XOXOCOTLAN

No. DE INVITACIN: MSCX/INV/FORTALECE/0701-N/2017 Duracin: 60 das naturales


Obra: CONSTRUCCION DE TECHADO EN LA ESCUELA PRIMARIA SOR JUANA INES DE LA CRUZ CLAVE: 20DPR3454E

Lugar: COLONIA LAS CULTURAS SANTA CRUZ XOXOCOTLAN OAXACA Inicio Obra: 26-jun-2017
Fin Obra: 24-ago-2017
ANLISIS, CLCULO E INTEGRACIN DE LOS PRECIOS UNITARIOS (ANEXO 10)

Cdigo Concepto Unidad Costo Cantidad Importe %


Partida: 1.4 Anlisis No.: 10
Anlisis: TUS150 ML 13
TUBO DE PVC SANITARIO, DE 102 MM. DE DIMETRO, INCLUYE: MATERIALES, ACARREOS, CORTES, DESPERDICIOS, MANO DE OBRA,
PRUEBAS, EQUIPO Y HERRAMIENTA.
MATERIALES
041-001-15-TUBO PVC E/L 150mm x 1 mto SANIT DU TRM $475.17 0.175000 54.18%

$83.15
96T
SUBTOTAL: MATERIALES $83.15 54.18%
MANO DE OBRA
1P1ECUADRILLA No 20 (1 PLOMERO+ 1 AY.ESP.) JOR $1,024.04 / 15.000000 44.48%

$68.27
SUBTOTAL: MANO DE OBRA $68.27 44.48%
EQUIPO Y HERRAMIENTA
%MO1HERRAMIENTA MENOR % $68.27 0.030000 1.34%

$2.05
SUBTOTAL: EQUIPO Y HERRAMIENTA $2.05 1.34%
Costo Directo: $153.47
INDIRECTOS 10.358% $15.90
SUBTOTAL $169.37
FINANCIAMIENTO 2.2356% $3.79
SUBTOTAL $173.16
UTILIDAD 12.9032% $22.34
PRECIO UNITARIO $195.50
(* CIENTO NOVENTA Y CINCO PESOS 50/100 M.N. *)

ADMINISTRADOR UNICO C. DANIEL ORTIZ ALCARAZ


14-jun-2017 Pagina: 26 de 36
EDIFICACIONES Y RECONSTRUCCIONES CHIGULERA S.A. DE C.V.
Dependencia: H. AYUNTAMIENTO MUNICIPAL CONSTITUCIONAL
SANTA CRUZ XOXOCOTLAN

No. DE INVITACIN: MSCX/INV/FORTALECE/0701-N/2017 Duracin: 60 das naturales


Obra: CONSTRUCCION DE TECHADO EN LA ESCUELA PRIMARIA SOR JUANA INES DE LA CRUZ CLAVE: 20DPR3454E

Lugar: COLONIA LAS CULTURAS SANTA CRUZ XOXOCOTLAN OAXACA Inicio Obra: 26-jun-2017
Fin Obra: 24-ago-2017
ANLISIS, CLCULO E INTEGRACIN DE LOS PRECIOS UNITARIOS (ANEXO 10)

Cdigo Concepto Unidad Costo Cantidad Importe %


Partida: 1.4 Anlisis No.: 20
Anlisis: CS90150 PZA 8
CODO DE PVC SANITARIO DE 45X102 MM., INCLUYE: MATERIALES, ACARREOS, CORTES, DESPERDICIOS, INSTALACIN, MANO DE
OBRA, PRUEBAS, EQUIPO Y HERRAMIENTA.
MATERIALES
042-001-A-1-CODO PVC DUR 45GX 150 mm. SANIT PZA $120.72 1.000000 $120.72 63.13%

4596
360-211-17-40LIMPIADOR SILER 500 ml PZA $36.13 0.060000 $2.17 1.13%

360-211-17-34BOTE PEGAMENTO SILER 480 grs PESADO PZA $108.02 0.090000 5.08%

$9.72
SUBTOTAL: MATERIALES $132.61 69.34%
MANO DE OBRA
1P1ECUADRILLA No 20 (1 PLOMERO+ 1 AY.ESP.) JOR $1,024.04 / 18.000000 29.75%

$56.89
SUBTOTAL: MANO DE OBRA $56.89 29.75%
EQUIPO Y HERRAMIENTA
%MO1HERRAMIENTA MENOR % $56.89 0.030000 $1.71 0.89%

SUBTOTAL: EQUIPO Y HERRAMIENTA $1.71 0.89%


Costo Directo: $191.21
INDIRECTOS 10.358% $19.81
SUBTOTAL $211.02
FINANCIAMIENTO 2.2356% $4.72
SUBTOTAL $215.74
UTILIDAD 12.9032% $27.84
PRECIO UNITARIO $243.58
(* DOSCIENTOS CUARENTA Y TRES PESOS 58/100 M.N. *)

ADMINISTRADOR UNICO C. DANIEL ORTIZ ALCARAZ


14-jun-2017 Pagina: 27 de 36
EDIFICACIONES Y RECONSTRUCCIONES CHIGULERA S.A. DE C.V.
Dependencia: H. AYUNTAMIENTO MUNICIPAL CONSTITUCIONAL
SANTA CRUZ XOXOCOTLAN

No. DE INVITACIN: MSCX/INV/FORTALECE/0701-N/2017 Duracin: 60 das naturales


Obra: CONSTRUCCION DE TECHADO EN LA ESCUELA PRIMARIA SOR JUANA INES DE LA CRUZ CLAVE: 20DPR3454E

Lugar: COLONIA LAS CULTURAS SANTA CRUZ XOXOCOTLAN OAXACA Inicio Obra: 26-jun-2017
Fin Obra: 24-ago-2017
ANLISIS, CLCULO E INTEGRACIN DE LOS PRECIOS UNITARIOS (ANEXO 10)

Cdigo Concepto Unidad Costo Cantidad Importe %


Partida: 1.4 Anlisis No.: 30
Anlisis: CS45150 PZA 2
CODO DE PVC SANITARIO DE 90X102 MM., INCLUYE: MATERIALES, ACARREOS, CORTES, DESPERDICIOS, INSTALACIN, MANO DE
OBRA, PRUEBAS, EQUIPO Y HERRAMIENTA.
MATERIALES
360-211-17-40LIMPIADOR SILER 500 ml PZA $36.13 0.060500 $2.19 1.94%

360-211-17-34BOTE PEGAMENTO SILER 480 grs PESADO PZA $108.02 0.090000 $9.72 8.63%

$42.17
042-001-E-1-CODO PVC SANIT 87.5X160 DUR. CEMENT PZA $42.17 1.000000 37.42%

9096
SUBTOTAL: MATERIALES $54.08 47.99%
MANO DE OBRA
1P1ECUADRILLA No 20 (1 PLOMERO+ 1 AY.ESP.) JOR $1,024.04 / 18.000000 50.49%
$56.89

SUBTOTAL: MANO DE OBRA $56.89 50.49%


EQUIPO Y HERRAMIENTA
%MO1HERRAMIENTA MENOR % $56.89 0.030000 $1.71 1.52%

SUBTOTAL: EQUIPO Y HERRAMIENTA $1.71 1.52%


Costo Directo: $112.68
INDIRECTOS 10.358% $11.67
SUBTOTAL $124.35
FINANCIAMIENTO 2.2356% $2.78
SUBTOTAL $127.13
UTILIDAD 12.9032% $16.40
PRECIO UNITARIO $143.53
(* CIENTO CUARENTA Y TRES PESOS 53/100 M.N. *)

ADMINISTRADOR UNICO C. DANIEL ORTIZ ALCARAZ


14-jun-2017 Pagina: 28 de 36
EDIFICACIONES Y RECONSTRUCCIONES CHIGULERA S.A. DE C.V.
Dependencia: H. AYUNTAMIENTO MUNICIPAL CONSTITUCIONAL
SANTA CRUZ XOXOCOTLAN

No. DE INVITACIN: MSCX/INV/FORTALECE/0701-N/2017 Duracin: 60 das naturales


Obra: CONSTRUCCION DE TECHADO EN LA ESCUELA PRIMARIA SOR JUANA INES DE LA CRUZ CLAVE: 20DPR3454E

Lugar: COLONIA LAS CULTURAS SANTA CRUZ XOXOCOTLAN OAXACA Inicio Obra: 26-jun-2017
Fin Obra: 24-ago-2017
ANLISIS, CLCULO E INTEGRACIN DE LOS PRECIOS UNITARIOS (ANEXO 10)

Cdigo Concepto Unidad Costo Cantidad Importe %


Partida: 1.4 Anlisis No.: 40
Anlisis: RS6610 PZA 2
REGISTRO DE 0.60X0.60X1.00 M. DE MUROS DE TABIQUE ROJO RECOCIDO, ASENTADO CON MEZCLA CEMENTO ARENA 1:5, CON
APLANADO PULIDO EN EL INTERIOR, CON TAPA DE 8 CM. DE ESPESOR DE CONCRETO DE F'C=150 KG/CM2, CON MARCO Y
CONTRAMARCO A BASE DE ANGULO DE FIERRO DE 3"X3"X1/4, ANCLADA A CADENA PERIMETRAL DE 15X15 CM. ARMADA CON 4
VARILLAS DE 3/8" Y ESTRIBOS DEL NO.2 A CADA 20 CM., PISO DE 10 CM. DE ESPESOR DE CONCRETO DE F'C=150 KG/CM2, INCLUYE:
MATERIALES, ACARREOS, EXCAVACIN, MANO DE OBRA, EQUIPO Y HERRAMIENTA.
MATERIALES
TABIQUETABIQUE ROJO RECOCIDO MIL $4,412.52 0.110000 15.76%
$485.38

FB009ANGULO DE FIER. (3/16" Y 1/4") x 3" TON $14,498.28 0.038000 $550.93 17.89%

7018SOLDADURA ELECTRODO 7018 KG $34.19 0.500000 0.56%

$17.10
3.VARILLA DE 3/8" 9.5 MM KG $14.28 7.000000 $99.96 3.25%

2.ALAMBRON KG $20.40 1.700000 $34.68 1.13%

DUELADUELA DE PINO DE 3a DE 3/4"x3.5"x8.25'' PZA $26.48 1.000000 $26.48 0.86%

CLAVOSCLAVOS DE 2 A 4 " KG $24.48 0.400000 $9.79 0.32%

1.ALAMBRE RECOCIDO KG $22.44 0.500000 0.36%

$11.22
SUBTOTAL: MATERIALES $1,235.54 40.13%
MANO DE OBRA
1A1PCUADRILLA No 5 (1 ALBAIL+1 PEON) JOR $1,019.04 / 1.000000 $1,019.04 33.09%

1S1ECUADRILLA No 17 (1 SOLDADOR+1 AY.ESP.) JOR $1,114.22 / 6.000000 6.03%


$185.70

SUBTOTAL: MANO DE OBRA $1,204.74 39.12%


EQUIPO Y HERRAMIENTA
%MO1HERRAMIENTA MENOR % $1,204.74 0.030000 $36.14 1.17%

SUBTOTAL: EQUIPO Y HERRAMIENTA $36.14 1.17%


BASICOS
1:5MORTERO CEMENTO ARENA 1:5 M3 $1,875.51 0.170000 10.35%
$318.84

150.CONCRETO DE F'c=150 KG/CM2, HECHO EN M3 $1,895.82 0.150000 $284.37 9.23%

OBRA, T.M.A.= 19 MM, RESISTENCIA


NORMAL
SUBTOTAL: BASICOS $603.21 19.58%
Costo Directo: $3,079.63
INDIRECTOS 10.358% $318.99
SUBTOTAL $3,398.62
FINANCIAMIENTO 2.2356% $75.98
SUBTOTAL $3,474.60
UTILIDAD 12.9032% $448.33
PRECIO UNITARIO $3,922.93
(* TRES MIL NOVECIENTOS VEINTIDOS PESOS 93/100 M.N. *)
ADMINISTRADOR UNICO C. DANIEL ORTIZ ALCARAZ
14-jun-2017 Pagina: 29 de 36
EDIFICACIONES Y RECONSTRUCCIONES CHIGULERA S.A. DE C.V.
Dependencia: H. AYUNTAMIENTO MUNICIPAL CONSTITUCIONAL
SANTA CRUZ XOXOCOTLAN

No. DE INVITACIN: MSCX/INV/FORTALECE/0701-N/2017 Duracin: 60 das naturales


Obra: CONSTRUCCION DE TECHADO EN LA ESCUELA PRIMARIA SOR JUANA INES DE LA CRUZ CLAVE: 20DPR3454E

Lugar: COLONIA LAS CULTURAS SANTA CRUZ XOXOCOTLAN OAXACA Inicio Obra: 26-jun-2017
Fin Obra: 24-ago-2017
ANLISIS, CLCULO E INTEGRACIN DE LOS PRECIOS UNITARIOS (ANEXO 10)

Cdigo Concepto Unidad Costo Cantidad Importe %


Partida: 1.5 Anlisis No.: 10
Anlisis: CIME0016 M2 30.83
DEMOLICIN DE PISO DE CONCRETO ARMADO DE 10 CM, DE ESPESOR CON ROMPEDORA ELECTRICA, INCLUYE: EQUIPO DE CORTE,
ROMPEDORA,RETIRO DE ESCOMBRO A TIRO AUTORIZADO, MANO DE OBRA, EQUIPO Y HERRAMIENTA.
MANO DE OBRA
1OMCUADRILLA No 25 (1 OPERADOR DE JOR $376.74 / 11.000000 $34.25 41.58%

MAQ.M.)
SUBTOTAL: MANO DE OBRA $34.25 41.58%
EQUIPO Y HERRAMIENTA
EQROMPEEROMPEDORA ELECTRICA S/OPERADOR HOR $89.80 / 3.000000 36.33%
$29.93

EQECORTEEQUIPO DE CORTE OXI-ACETILENO HOR $858.31 / 50.000000 $17.17 20.84%

%MO1HERRAMIENTA MENOR % $34.25 0.030000 $1.03 1.25%

SUBTOTAL: EQUIPO Y HERRAMIENTA $48.13 58.42%


Costo Directo: $82.38
INDIRECTOS 10.358% $8.53
SUBTOTAL $90.91
FINANCIAMIENTO 2.2356% $2.03
SUBTOTAL $92.94
UTILIDAD 12.9032% $11.99
PRECIO UNITARIO $104.93
(* CIENTO CUATRO PESOS 93/100 M.N. *)

ADMINISTRADOR UNICO C. DANIEL ORTIZ ALCARAZ


14-jun-2017 Pagina: 30 de 36
EDIFICACIONES Y RECONSTRUCCIONES CHIGULERA S.A. DE C.V.
Dependencia: H. AYUNTAMIENTO MUNICIPAL CONSTITUCIONAL
SANTA CRUZ XOXOCOTLAN

No. DE INVITACIN: MSCX/INV/FORTALECE/0701-N/2017 Duracin: 60 das naturales


Obra: CONSTRUCCION DE TECHADO EN LA ESCUELA PRIMARIA SOR JUANA INES DE LA CRUZ CLAVE: 20DPR3454E

Lugar: COLONIA LAS CULTURAS SANTA CRUZ XOXOCOTLAN OAXACA Inicio Obra: 26-jun-2017
Fin Obra: 24-ago-2017
ANLISIS, CLCULO E INTEGRACIN DE LOS PRECIOS UNITARIOS (ANEXO 10)

Cdigo Concepto Unidad Costo Cantidad Importe %


Partida: 1.5 Anlisis No.: 20
Anlisis: CIME0028 PZA 1
DEMOLICION DE REGISTRO ELECTRICO PARA SU POSTERIOR REUBICACION, INCLUYE: RETIRO DE ESCOMBRO A TIRO AUTORIZADO,
MANO DE OBRA, EQUIPO Y HERRAMIENTA
MANO DE OBRA
1OMCUADRILLA No 25 (1 OPERADOR DE JOR $376.74 / 2.000000 $188.37 73.01%

MAQ.M.)
SUBTOTAL: MANO DE OBRA $188.37 73.01%
EQUIPO Y HERRAMIENTA
EQROMPEEROMPEDORA ELECTRICA S/OPERADOR HOR $89.80 / 2.000000 17.40%
$44.90

EQECORTEEQUIPO DE CORTE OXI-ACETILENO HOR $858.31 / 45.000000 $19.07 7.39%

%MO1HERRAMIENTA MENOR % $188.37 0.030000 $5.65 2.19%

SUBTOTAL: EQUIPO Y HERRAMIENTA $69.62 26.98%


Costo Directo: $257.99
INDIRECTOS 10.358% $26.72
SUBTOTAL $284.71
FINANCIAMIENTO 2.2356% $6.36
SUBTOTAL $291.07
UTILIDAD 12.9032% $37.56
PRECIO UNITARIO $328.63
(* TRESCIENTOS VEINTIOCHO PESOS 63/100 M.N. *)

ADMINISTRADOR UNICO C. DANIEL ORTIZ ALCARAZ


14-jun-2017 Pagina: 31 de 36
EDIFICACIONES Y RECONSTRUCCIONES CHIGULERA S.A. DE C.V.
Dependencia: H. AYUNTAMIENTO MUNICIPAL CONSTITUCIONAL
SANTA CRUZ XOXOCOTLAN

No. DE INVITACIN: MSCX/INV/FORTALECE/0701-N/2017 Duracin: 60 das naturales


Obra: CONSTRUCCION DE TECHADO EN LA ESCUELA PRIMARIA SOR JUANA INES DE LA CRUZ CLAVE: 20DPR3454E

Lugar: COLONIA LAS CULTURAS SANTA CRUZ XOXOCOTLAN OAXACA Inicio Obra: 26-jun-2017
Fin Obra: 24-ago-2017
ANLISIS, CLCULO E INTEGRACIN DE LOS PRECIOS UNITARIOS (ANEXO 10)

Cdigo Concepto Unidad Costo Cantidad Importe %


Partida: 1.5 Anlisis No.: 30
Anlisis: CIME: 0145 ML 44.4
CADENA DE 15x30 CM DE CONCRETO HECHO EN OBRA F'C=200 KG/CM2, ACABADO COMUN, CON ARMEX 15x30, INCLUYE: MATERIALES,
ACARREOS, CORTES, DESPERDICIOS, TRASLAPES, AMARRES, CIMBRADO, COLADO, DESCIMBRADO, MANO DE OBRA, EQUIPO Y
HERRAMIENTA.
MATERIALES
DUELADUELA DE PINO DE 3a DE 3/4"x3.5"x8.25'' PZA $26.48 1.000000 $26.48 5.70%

POLINPOLIN DE PINO DE 3a DE 3.5"x3."x8.25'' PZA $63.54 0.200000 2.74%

$12.71
CLAVOSCLAVOS DE 2 A 4 " KG $24.48 0.125000 0.66%

$3.06
1.ALAMBRE RECOCIDO KG $22.44 0.200000 $4.49 0.97%

DIESELDIESEL LTO $14.43 0.200000 $2.89 0.62%

$23.46
2.ALAMBRON KG $20.40 1.150000 5.05%

ARMEX15304ARMEX 15-30-4 M $30.60 1.050000 6.92%

$32.13
SUBTOTAL: MATERIALES $105.22 22.66%
MANO DE OBRA
1A1PCUADRILLA No 5 (1 ALBAIL+1 PEON) JOR $1,019.04 / 4.000000 54.89%

$254.76
SUBTOTAL: MANO DE OBRA $254.76 54.89%
EQUIPO Y HERRAMIENTA
%MO1HERRAMIENTA MENOR % $254.76 0.030000 $7.64 1.65%

SUBTOTAL: EQUIPO Y HERRAMIENTA $7.64 1.65%


BASICOS
200.CONCRETO DE F'c=200 KG/CM2, HECHO EN M3 $2,043.19 0.047250 20.80%

$96.54
OBRA, T.M.A.= 19 MM, RESISTENCIA
NORMAL
SUBTOTAL: BASICOS $96.54 20.80%
Costo Directo: $464.16
INDIRECTOS 10.358% $48.08
SUBTOTAL $512.24
FINANCIAMIENTO 2.2356% $11.45
SUBTOTAL $523.69
UTILIDAD 12.9032% $67.57
PRECIO UNITARIO $591.26
(* QUINIENTOS NOVENTA Y UN PESOS 26/100 M.N. *)

ADMINISTRADOR UNICO C. DANIEL ORTIZ ALCARAZ


14-jun-2017 Pagina: 32 de 36
EDIFICACIONES Y RECONSTRUCCIONES CHIGULERA S.A. DE C.V.
Dependencia: H. AYUNTAMIENTO MUNICIPAL CONSTITUCIONAL
SANTA CRUZ XOXOCOTLAN

No. DE INVITACIN: MSCX/INV/FORTALECE/0701-N/2017 Duracin: 60 das naturales


Obra: CONSTRUCCION DE TECHADO EN LA ESCUELA PRIMARIA SOR JUANA INES DE LA CRUZ CLAVE: 20DPR3454E

Lugar: COLONIA LAS CULTURAS SANTA CRUZ XOXOCOTLAN OAXACA Inicio Obra: 26-jun-2017
Fin Obra: 24-ago-2017
ANLISIS, CLCULO E INTEGRACIN DE LOS PRECIOS UNITARIOS (ANEXO 10)

Cdigo Concepto Unidad Costo Cantidad Importe %


Partida: 1.5 Anlisis No.: 40
Anlisis: CIME: 0140 M2 211.07
SUMINISTRO Y COLOCACION DE MALLA ELECTROSOLDAD DE 2.5 M X 6 M ( 15 M2) INCLUYE SUMINIST.HABILIT.ARMADO,
TRASLAPES,SILLETAS,GANCHOS Y DESPER.
MATERIALES
661010MALLA ELECTROSOLDADADA 6x6/10-10 M2 $32.13 1.100000 77.64%
$35.34

$0.56
1.ALAMBRE RECOCIDO KG $22.44 0.025000 1.23%
SUBTOTAL: MATERIALES $35.90 78.87%
MANO DE OBRA
1F1ACUADRILLA No 6 (1 FIERRERO + 1 JOR $934.21 / 100.000000 $9.34 20.52%

AYUDANTE)
SUBTOTAL: MANO DE OBRA $9.34 20.52%
EQUIPO Y HERRAMIENTA
%MO1HERRAMIENTA MENOR % $9.34 0.030000 $0.28 0.62%

SUBTOTAL: EQUIPO Y HERRAMIENTA $0.28 0.62%


Costo Directo: $45.52
INDIRECTOS 10.358% $4.71
SUBTOTAL $50.23
FINANCIAMIENTO 2.2356% $1.12
SUBTOTAL $51.35
UTILIDAD 12.9032% $6.63
PRECIO UNITARIO $57.98
(* CINCUENTA Y SIETE PESOS 98/100 M.N. *)

ADMINISTRADOR UNICO C. DANIEL ORTIZ ALCARAZ


14-jun-2017 Pagina: 33 de 36
EDIFICACIONES Y RECONSTRUCCIONES CHIGULERA S.A. DE C.V.
Dependencia: H. AYUNTAMIENTO MUNICIPAL CONSTITUCIONAL
SANTA CRUZ XOXOCOTLAN

No. DE INVITACIN: MSCX/INV/FORTALECE/0701-N/2017 Duracin: 60 das naturales


Obra: CONSTRUCCION DE TECHADO EN LA ESCUELA PRIMARIA SOR JUANA INES DE LA CRUZ CLAVE: 20DPR3454E

Lugar: COLONIA LAS CULTURAS SANTA CRUZ XOXOCOTLAN OAXACA Inicio Obra: 26-jun-2017
Fin Obra: 24-ago-2017
ANLISIS, CLCULO E INTEGRACIN DE LOS PRECIOS UNITARIOS (ANEXO 10)

Cdigo Concepto Unidad Costo Cantidad Importe %


Partida: 1.5 Anlisis No.: 50
Anlisis: CIME:0075 M2 211.07
PISO DE CONCRETO HIDRAULICO DE ACABADO FINO DE 12 CM. DE ESPESOR DE RESISTENCIA F'C= 250 KG/CM2, INCL. ELABORACION
DE CONCRETO CON REVOLVEDORA, VACIADO, VIBRADO, CURADO, CIMBRADO, Y DESCIMBRADO, ACARREO DEL MATERIAL, CON
CARRETILLA Y BOTES, MATERIALES, EQUIPO, HERRAMIENTA Y MANO DE OBRA.
MATERIALES
DUELADUELA DE PINO DE 3a DE 3/4"x3.5"x8.25'' PZA $26.48 0.180000 $4.77 1.26%

AGUAAGUA ( MANEJO) M3 $123.60 0.010000 0.33%


$1.24

1.ALAMBRE RECOCIDO KG $22.44 0.330000 1.96%

$7.41

3.VARILLA DE 3/8" 9.5 MM KG $14.28 0.006600 $0.09 0.02%


SUBTOTAL: MATERIALES $13.51 3.57%
MANO DE OBRA
1A5PCUADRILLA No 22 (1 ALBAIL + 5 PEONES) JOR $2,292.31 / 27.000000 22.51%

$84.90
SUBTOTAL: MANO DE OBRA $84.90 22.51%
EQUIPO Y HERRAMIENTA
%MO1HERRAMIENTA MENOR % $84.90 0.030000 0.68%

$2.55
SUBTOTAL: EQUIPO Y HERRAMIENTA $2.55 0.68%
BASICOS
250.CONCRETO DE F'c=250 KG/CM2, HECHO EN M3 $2,191.79 0.126000 73.23%
$276.17

OBRA, T.M.A.= 19 MM, RESISTENCIA


NORMAL
SUBTOTAL: BASICOS $276.17 73.23%
Costo Directo: $377.13
INDIRECTOS 10.358% $39.06
SUBTOTAL $416.19
FINANCIAMIENTO 2.2356% $9.30
SUBTOTAL $425.49
UTILIDAD 12.9032% $54.90
PRECIO UNITARIO $480.39
(* CUATROCIENTOS OCHENTA PESOS 39/100 M.N. *)

ADMINISTRADOR UNICO C. DANIEL ORTIZ ALCARAZ


14-jun-2017 Pagina: 34 de 36
EDIFICACIONES Y RECONSTRUCCIONES CHIGULERA S.A. DE C.V.
Dependencia: H. AYUNTAMIENTO MUNICIPAL CONSTITUCIONAL
SANTA CRUZ XOXOCOTLAN

No. DE INVITACIN: MSCX/INV/FORTALECE/0701-N/2017 Duracin: 60 das naturales


Obra: CONSTRUCCION DE TECHADO EN LA ESCUELA PRIMARIA SOR JUANA INES DE LA CRUZ CLAVE: 20DPR3454E

Lugar: COLONIA LAS CULTURAS SANTA CRUZ XOXOCOTLAN OAXACA Inicio Obra: 26-jun-2017
Fin Obra: 24-ago-2017
ANLISIS, CLCULO E INTEGRACIN DE LOS PRECIOS UNITARIOS (ANEXO 10)

Cdigo Concepto Unidad Costo Cantidad Importe %


Partida: 1.5 Anlisis No.: 60
Anlisis: CIME:0036 M2 11.94
PINTURA ACRILICA EN SUPERFICIE, INCLUYENDO UNA MANO DE SELLADOR ACRILICO COMEX O SIMILAR, DOS MANOS DE PINTURA
ACRILICA ULTRAPISOS O SIMILAR. ACARREO MATERIAL PRIMERA ESTACION = 20.00 MTS.
MATERIALES
PIN-535PINTURA ACRILICA ESPECIAL LT $76.50 0.176400 $13.49 26.81%

THINNERTHINNER STANDARD LT $45.90 0.090000 8.21%

$4.13

DUELADUELA DE PINO DE 3a DE 3/4"x3.5"x8.25'' PZA $26.48 0.150000 $3.97 7.89%


AGUAAGUA ( MANEJO) M3 $123.60 0.010000 $1.24 2.46%

SUBTOTAL: MATERIALES $22.83 45.37%


MANO DE OBRA
1P1ACUADRILLA No 8 (1 PINTOR + AYUDANTE) JOR $800.83 / 30.000000 53.04%
$26.69

SUBTOTAL: MANO DE OBRA $26.69 53.04%


EQUIPO Y HERRAMIENTA
%MO1HERRAMIENTA MENOR % $26.69 0.030000 1.59%

$0.80
SUBTOTAL: EQUIPO Y HERRAMIENTA $0.80 1.59%
Costo Directo: $50.32
INDIRECTOS 10.358% $5.21
SUBTOTAL $55.53
FINANCIAMIENTO 2.2356% $1.24
SUBTOTAL $56.77
UTILIDAD 12.9032% $7.33
PRECIO UNITARIO $64.10
(* SESENTA Y CUATRO PESOS 10/100 M.N. *)

ADMINISTRADOR UNICO C. DANIEL ORTIZ ALCARAZ


14-jun-2017 Pagina: 35 de 36
EDIFICACIONES Y RECONSTRUCCIONES CHIGULERA S.A. DE C.V.
Dependencia: H. AYUNTAMIENTO MUNICIPAL CONSTITUCIONAL
SANTA CRUZ XOXOCOTLAN

No. DE INVITACIN: MSCX/INV/FORTALECE/0701-N/2017 Duracin: 60 das naturales


Obra: CONSTRUCCION DE TECHADO EN LA ESCUELA PRIMARIA SOR JUANA INES DE LA CRUZ CLAVE: 20DPR3454E

Lugar: COLONIA LAS CULTURAS SANTA CRUZ XOXOCOTLAN OAXACA Inicio Obra: 26-jun-2017
Fin Obra: 24-ago-2017
ANLISIS, CLCULO E INTEGRACIN DE LOS PRECIOS UNITARIOS (ANEXO 10)

Cdigo Concepto Unidad Costo Cantidad Importe %


Partida: 1.5 Anlisis No.: 70
Anlisis: CIME:0076 JGO 2
SUMINISTRO Y COLOCACION DE CANASTA DE BASQUETBALL Y PORTERIAS, INCLUYE MATERIALES DE FIJACION,TRANSPORTE, Y
POSTURA
MATERIALES
JGO-TAB-CANASTA DE BASQUETBALL CON JGO $22,268.63 1.000000 $22,268.63 99.58%

BSCKTPORTERIAS Y TABLERO DE MICA, ALTURA


AJUSTABLE.
SUBTOTAL: MATERIALES $22,268.63 99.58%
MANO DE OBRA
1PCUADRILLA No 1 (1 PEON) JOR $364.39 / 4.000000 $91.10 0.41%

SUBTOTAL: MANO DE OBRA $91.10 0.41%


EQUIPO Y HERRAMIENTA
%MO1HERRAMIENTA MENOR % $91.10 0.030000 $2.73 0.01%

SUBTOTAL: EQUIPO Y HERRAMIENTA $2.73 0.01%


Costo Directo: $22,362.46
INDIRECTOS 10.358% $2,316.30
SUBTOTAL $24,678.76
FINANCIAMIENTO 2.2356% $551.72
SUBTOTAL $25,230.48
UTILIDAD 12.9032% $3,255.54
PRECIO UNITARIO $28,486.02
(* VEINTIOCHO MIL CUATROCIENTOS OCHENTA Y SEIS PESOS
02/100 M.N. *)

ADMINISTRADOR UNICO C. DANIEL ORTIZ ALCARAZ


14-jun-2017 Pagina: 36 de 36
EDIFICACIONES Y RECONSTRUCCIONES CHIGULERA S.A. DE C.V.
Dependencia: H. AYUNTAMIENTO MUNICIPAL CONSTITUCIONAL
SANTA CRUZ XOXOCOTLAN

No. DE INVITACIN: MSCX/INV/FORTALECE/0701-N/2017 Duracin: 60 das naturales


Obra: CONSTRUCCION DE TECHADO EN LA ESCUELA PRIMARIA SOR JUANA INES DE LA CRUZ CLAVE: 20DPR3454E

Lugar: COLONIA LAS CULTURAS SANTA CRUZ XOXOCOTLAN OAXACA Inicio Obra: 26-jun-2017
Fin Obra: 24-ago-2017
ANLISIS, CLCULO E INTEGRACIN DE LOS PRECIOS UNITARIOS (ANEXO 10)

Cdigo Concepto Unidad Costo Cantidad Importe %


Partida: 1.5 Anlisis No.: 80
Anlisis: CIME: 0141 M2 657.78
LIMPIEZA GENERAL PARA ENTREGA DE OBRA, INCL. DETERGENTE, AGUA NECESARIA, HERRAMIENTA, ACARREOS A 20 M. DE DISTANCIA
DE MATERIAL DE PRODUCTO DE LIMPIEZA EN BOTE ALCOHOLERO, EQUIPO Y MANO DE OBRA.
MATERIALES
%MO3MATERIALES MENORES % $14.46 0.100000 8.87%

$1.45
SUBTOTAL: MATERIALES $1.45 8.87%
MANO DE OBRA
1ACUADRILLA No 3 (1 AYUDANTE GENERAL) JOR $347.04 / 24.000000 $14.46 88.49%

SUBTOTAL: MANO DE OBRA $14.46 88.49%


EQUIPO Y HERRAMIENTA
%MO1HERRAMIENTA MENOR % $14.46 0.030000 2.63%

$0.43
SUBTOTAL: EQUIPO Y HERRAMIENTA $0.43 2.63%
Costo Directo: $16.34
INDIRECTOS 10.358% $1.69
SUBTOTAL $18.03
FINANCIAMIENTO 2.2356% $0.40
SUBTOTAL $18.43
UTILIDAD 12.9032% $2.38
PRECIO UNITARIO $20.81
(* VEINTE PESOS 81/100 M.N. *)

ADMINISTRADOR UNICO C. DANIEL ORTIZ ALCARAZ