You are on page 1of 38

Divecha Centre for

INDIAN
INSTITUTE OF SCIENCE
Climate Change
Indian Institute of Science

Renewable Energy Systems


Reports

A case study of
3-MW scale
grid-connected solar
photovoltaic power plant
at Kolar, Karnataka
Performance assessment &
recommendations

H. Mitavachan, Anandhi Gokhale


and J. Srinivasan
REPORT IISc-DCCC 11 RE 1 AUGUST 2011
T he Divecha Centre for Climate Change was
established at the Indian Institute of Science in
January 2009 with a generous financial
contribution from Arjun and Diana Divecha and the
Grantham Foundation for the Protection of the
Environment.

The primary goal of this Centre is to understand climate


variability and climate change and its impact on the
environment. The Centre has undertaken outreach activities
to create awareness among people and policy makers about
climate change and its consequences. This has been done
through workshops, lectures and quiz contests. An annual
invited public lecture called the Jeremy Grantham Lecture
on Climate Change has been organized. The Centre has
identified technologies to mitigate climate change in
collaboration with entrepreneurs and different engineering
departments in the Indian Institute of Science. The Centre is
also working with Grantham Institute for Climate Change
at Imperial College, London, on the impact of climate
change on water.
Divecha Centre for
INDIAN
INSTITUTE OF SCIENCE
Climate Change
Indian Institute of Science

Renewable Energy Systems


Reports

A case study of
3-MW scale
grid-connected solar
photovoltaic power plant
at Kolar, Karnataka
Performance assessment &
recommendations
H. Mitavachan, Anandhi Gokhale
and J. Srinivasan

REPORT IISc-DCCC 11 RE 1 AUGUST 2011


Executive Summary
Karnataka Power Corporation Limited (KPCL) has established 3 MWpeak capacity
grid-connected solar photovoltaic power plant near Yalesandra village in Kolar
district of Karnataka, which is the first of its scale in India. After the site
preparations were completed the first segment was installed in 4 months,
followed by the second and third segments in the next two months. The plant
was fully commissioned on 27 December 2009. The Yalesandra plant is one
among 20 such Mega-watt size solar power plants in India, *as on 31st July
2011. India has an ambitious plan to build large grid-connected solar power
plants, with a cumulative installed capacity of 20,000 MWp by 2020, under the
National Solar Mission. Hence, it is essential to document the performance of
the first large-scale grid-connected solar power plant installed in Karnataka. In
this report we discuss the performance of the photovoltaic solar power plant in
Kolar during 2010.

0
The Yalesandra power plant is located at a latitude of 12 53' and a longitude of
0
78 09'. The overall area occupied by photovoltaic modules is 10.3 acres. The
plant has 3 segments with each segment having an installed capacity of 1 MWp.
Each segment has 4 inverters with a capacity of 250 kW each. There are 13,368
modules (557 arrays with 24 modules per array) that contain mono-crystalline
Silicon solar cells. The solar photovoltaic modules are connected such that a
voltage of 415 volts is generated at the output of each inverter. This is stepped up
to 11 kV by a step-up transformer and connected to the existing 11 kV grid.

The total electrical energy generated by the Yaleasandra plant during 2010 was
3.34 million kWh and 3.30 million units were sold to the grid. Although the
performance of the photovoltaic modules was good, there were teething
troubles associated with the inverters, which was the main reason for reduced
energy generation. The impact of temperature variation of modules on their
performance was studied both on daily and yearly basis. It is observed that the
efficiency of the plant is more sensitive to temperature than the solar insolation.
Daily datasets of five minute average data have been used for in-depth analysis.
Some of the maintenance and technical related problems faced by the plant
operators have also been discussed.

*
Ch
ec
k
MN
RE
we
bsi
t
e (
ht
t
p:
/
/ww
w.mn
r
e.go
v
.
i
n/
so
l
ar
-c
o
nc
l
ave
2
01
0
.
ht
m)
fo
rm
or
ed
et
a
il
son
g
r
i
d-
co
n
ne
c
t
ed
so
l
arpow
erp
la
nt
si
nIn
di
a
Contents

1. Introduction 1

2. Site details 4

2.1 Technical details 5

2.2 Cost details 8

2.3 Plant Maintenance & Operation 8

3. Performance Analysis 9

3.1 Segment-1 and Segment-2 10

3.2 PV Modules Temperature 17

3.3 Performance of Inverter-1 18

3.3.1 Effect of temperature on the efficiency 19

3.3.2 Performance of Inverter-1 on good days Daily plots 20

4. Technical and maintenance related problems 23

5. Conclusion 25

6. References 26

7. Acknowledgments 27
R
e
p
or
tI
I
Sc-
D
CCC
1
1R
E
1 1

1. Introduction

Karnataka's power sector has three main hydro and other renewable energy sources.
utilities namely; Karnataka Power So, to reduce the dependence on fossil fuels
Corporation Ltd. (KPCL) - the Public Sector and increase the share of renewable energy
generation utility, the Karnataka Power sources, KPCL has started investing in wind
Transmission Corporation Ltd. (KPTCL) - and solar energy technologies.
the Public Sector transmission utility, and its
regional distribution utilities - Electricity
Supply Companies (ESCOMs). KPCL is the In early 2009, KPCL started the Arunodaya
main power generator in the state with an scheme to demonstrate, popularize and
installed capacity of 5975.91 MW of hydel, increase the usage of solar energy for
thermal, solar and wind energy, with an electricity generation. Under this scheme,
additional 9500 MW in the pipeline. KPCL came up with a proposal for installing
the country's first 3MWp scale photovoltaic
solar power plant near Yalesandra village in
Till 1985, the state's entire capacity had Kolar district of Karnataka. The intent of the
been hydroelectric, but with 2328 MW of project was to provide power to the farmers
coal based thermal power stations (and a to enable pumping and using of the
few diesel and wind-based plants), the hydro groundwater for irrigation. There are around
share of capacity has dropped to about 61%. 450-500 10-HP pumps in about 14
Further, only about 75% of the hydro surrounding villages and farmers were
capacity is available for utilization; the unable to use these at full capacity because
remaining 25% comprises (a) non-firm of inconsistent power supply. The Kolar
capacity (i.e. a part of the water stored in plant was fully completed and
some hydro-reservoirs is also meant for commissioned on 27 December 2009 (see
irrigation), (b) unforeseen outages Figure1). Later, two more plants with the
(necessitating a spinning reserve), and (c) same capacity were constructed in Belgaum
maintenance protection reserve. Also, in and Raichur (see Table1 and Figure2).
years of poor rainfall, the contribution of
hydel plants to annual electricity generation
decreases further [1]. One of the main India has an ambitious plan to build large
reasons for the power crisis in 2008-09 was grid-connected solar power plants, with a
the failure of the monsoon, which reduced cumulative installed capacity of 20,000 MWP
the reservoir levels in the major hydel by 2020, under the National Solar Mission.
reservoirs (viz., Linganamakki, Supa and Hence, it is essential to document the
Mani) by 26% compared to 2007-08 and this performance of the first large-scale
led to a reduction of 29.51% (2261 MU) in grid-connected solar power plant installed
hydro generation [2]. All of these are leading in Karnataka. This report contains the
to an increased dependence on thermal analysis of the performance of the
plants, whose GHG emissions are high and photovoltaic solar power plant in Kolar
pollute the environment more compared to during 2010.

3
-
MWs
c
al
egr
i
d-
co
n
ne
c
t
ed
so
l
arp
h
ot
o
vol
t
aic
po
w
er
pl
ant
at
Kol
ar
,K
ar
n
at
ak
a
R
e
p
or
tI
I
Sc-
D
CCC
1
1R
E
1 2

Figure 1 : Photovoltaic Solar Power Plant at Yalesandra, Kolar, Karnataka

Table 1 : Mega Watt scale Solar PV Plants in Karnataka State (all are under KPCL)

Place Cost per Mega Watt Total Nominal


(Approximate figures) Capacity (MW) Contractor

Yalesandra Rs. 20 crore Titan Energy Systems Ltd.


Kolar 3
Itnal, Chikkodi
Belgaum Rs. 20 crore 3 Photon Energy Systems Ltd.

Yapaldinni BHEL
Raichur Rs. 14.5 crore 3 (yet to be commissioned)
Shivanasamudra -
Mandya 5
-

3
-
MWs
c
al
egr
i
d-
co
n
ne
c
t
ed
so
l
arp
h
ot
o
vol
t
aic
po
w
er
pl
ant
at
Kol
ar
,K
ar
n
at
ak
a
R
e
p
or
tI
I
Sc-
D
CCC
1
1R
E
1 3

Figure 2 : Karnataka map showing the locations of all the three 3MW Solar PV Power Plants

3
-
MWs
c
al
egr
i
d-
co
n
ne
c
t
ed
so
l
arp
h
ot
o
vol
t
aic
po
w
er
pl
ant
at
Kol
ar
,K
ar
n
at
ak
a
R
e
p
or
tI
I
Sc-
D
CCC
1
1R
E
1 4

2. Site details

The Yalesandra plant installation site has a room, substation and other ancillary
steep slope with a level difference of about structures. The general information
15 m and there are rock outcrops in the site. regarding the climatic conditions of Kolar
The structures for the Power Plant district and description of the Plant are given
comprises Solar Arrays, PCUs, control in the Tables 2 and 3.

Table 2 : General Climatic conditions of Kolar district [3]


Height above sea level 882 m
Maximum: 40oC
Ambient Air Temperature
Minimum: 18oC

Maximum: 99.1% (during monsoon)


Relative Humidity
Minimum: 18.3%

Annual average: 1549 mm


Rainfall
Period: 4 months

Table 3 : General description of Yalesandra PV Plant

Place of Installation Near Yalesandra Village, Kolar, Karnataka,


India
0 0
Latitude & Longitude of the place 12 53 & 78 09
Allotted Land Area 15 acres (10.3 acres effectively used)
Nominal Capacity of the PV Plant 3 MW
Date of Commission 27th December 2009
Owner Karnataka Power Corporation Limited
(KPCL)
Installed by (Contractor) Titan Energy Systems Ltd., Secunderabad
Modules Titan S6-60 series
SCADA for diagnosing and monitoring Yes
PCU (Inverters) 250 kW (12 Nos)
HT Transformer and switchgear for 1.25 MVA for each MW
evacuation

3
-
MWs
c
al
egr
i
d-
co
n
ne
c
t
ed
so
l
arp
h
ot
o
vol
t
aic
po
w
er
pl
ant
at
Kol
ar
,K
ar
n
at
ak
a
R
e
p
or
tI
I
Sc-
D
CCC
1
1R
E
1 5

2.1 Technical details

Segments
The 3 MW Plant is divided into three single Inverter, and each array consists of 24
independent segments of one MW each. modules connected in series. The power
Each segment is equipped with four generated from 3 MWp PV Plant at 0.415 kV
Inverters of 250 kW each and grouped is stepped up to 11 kV with the help of three
together to form one LT panel. Depending on step-up transformers and connected to
the mix of 225 & 240 Wp modules, 45 to 46 existing 11 kV lines. The simple block
PV Arrays are connected in parallel to each diagram of the Plant is shown in Figure 3.

PV Arrays PCUs MCBs

z LT PANEL 1
=

z
= TRANSFORMER 1 11 kV HT PANEL

z
=

z 11 kV
= TO SCADA HT
KPTCL lines

METERING
z LT PANEL 2
=
CUBICLE

z TRANSFORMER 2
=

z
=

z TO SCADA
=

z LT PANEL 3 SPARE
=

z TRANSFORMER 3
=

z
=

z TO SCADA
=

Figure 3 : Simple block diagram of the PV Plant

3
-
MWs
c
al
egr
i
d-
co
n
ne
c
t
ed
so
l
arp
h
ot
o
vol
t
aic
po
w
er
pl
ant
at
Kol
ar
,K
ar
n
at
ak
a
R
e
p
or
tI
I
Sc-
D
CCC
1
1R
E
1 6

Tables 4 and 5 give the general technical details and the module specifications of the Plant.

Table 4 : Technical data of Solar PV

Two type of S6 - 60 series modules are used 225 Wp & 240 Wp


Total number of modules 13,368
[10,152 - 225 Wp ; 3216 240 Wp ]
Solar Cell material Mono-Crystalline Silicon
1 Array 24 Modules
No. of Arrays per Inverter (250 kW) 45-46 (Total 557 Arrays with 12 Inverters)
Arrays per MW 1st MW 181
2nd & 3rd MW 188 per MW
Total Solar Cells area 5.4 acre
Inclination of Modules 15 degree

Table 5 : Module Specifications [4]

Type S6- 60 series


Maximum Power, Pmp (W) 225 240
Maximum Power Voltage (Vmp) 28.63 V 29.62 V
Maximum Power Current (Imp) 7.93 A 8.12 A
Open Circuit Voltage (Voc) 37.50 V 37.62 V
Short Circuit Current (Isc) 8.52 A 8.55 A
Module dimensions (mm) 1657 x 987 x 42
Number, type and arrangement of cells 60, Mono-Crystalline, 6 x 10 Matrix
Cell Size 156 x 156 (mm)
NOCT Nominal Operating Cell Temp (C) 45
Weight (Kg) 19
Glass Type and Thickness 3.2mm Thick, Low iron, Tempered

3
-
MWs
c
al
egr
i
d-
co
n
ne
c
t
ed
so
l
arp
h
ot
o
vol
t
aic
po
w
er
pl
ant
at
Kol
ar
,K
ar
n
at
ak
a
R
e
p
or
tI
I
Sc-
D
CCC
1
1R
E
1 7

Power Conditioning Units (PCUs) Transformers


All the twelve PCUs are identical and are The full load rating of the Transformers is
supplied by the single manufacturer 1.25 MVA. All the three oil - cooled
BONFIGLIOLI (VECTRON, RPS 450 type). Transformers are supplied by the
The MPPT device is in-built in the control manufacturer Pan Electro Technic
system which allows operating at constant Enterprises Pvt. Ltd. The efficiency is
voltage. The efficiency of the PCUs is 98.91% at rated voltage and 99.3% at
around 96% at nominal load. The rated maximum flux density.
capacity of the PCU is 250 kW.

Mounting structure

6 x 4 Module Array
Type
(24 modules per Structure)
Material Mild Steel
Overall dimensions (mm) 6780 x 6030

Coating Galvanized

Wind rating 160 km per hour

Tilt angle 150

Foundation PCC
Fixing type Nut Bolts

Timelines
Foundation was laid on 9th January 2009 30th September 2009, 2 MWp on 12th
and the site handed over to TITAN on 28th November and 3 MWp on 27th December
May 2009. 1MWp was completed on 2009.

3
-
MWs
c
al
egr
i
d-
co
n
ne
c
t
ed
so
l
arp
h
ot
o
vol
t
aic
po
w
er
pl
ant
at
Kol
ar
,K
ar
n
at
ak
a
R
e
p
or
tI
I
Sc-
D
CCC
1
1R
E
1 8

2.2 Cost details


The total cost of installing the Power Plant The detailed Cost breakup of 3 MW Kolar PV
including the maintenance charges for first plant is given in Table 6.
three years is approximately Rs. 60 crores.

Table 6 : Cost breakup of 3 MWp Yalesandra PV power plant [3] [5]


Item Cost (in Rupees)
SPV Arrays totaling to 3 MWp 43,50,00,000
PCUs 5,40,00,000
Mounting structures 3,00,00,000
Cables & Hardware 50,00,000
Junction box & distribution boxes 9,00,000
Lightning Arrester, Earthing kit 12,00,000
PVC pipes & accessories 3,00,000
Spares for 3 years 5,00,000
SCADA system 20,00,000
Taxes, CST/KVAT, etc. 1,05,78,000
Design, engineering, quality surveillance,
testing, transportation, insurance coverage, etc. 1,80,99,400
Total Supply of Equipments (for 3 MW) 55,75,77,400
Erection & Commissioning 2,98,00,000
10 kW additional solar PV system with
31,00,000
Battery support
Note: Miscellaneous expenses have not been taken into account

2.3 Plant Maintenance & Operation


In addition to 3 MWp, one more 10 kW PV regularly to meet the water requirements of
plant has been installed on the rooftop of the Plant. The other two pump sets remain
office building to take care of domestic idle most of the time.
lighting and cooling loads of the Plant, Cleaning of PV Modules:
including the load of exhaust fans. At
Generally, the modules are cleaned by
present, the plant is maintained by 13
spraying water with the help of extendable
workers which includes 2 technical persons
hosepipes. Occasionally, wipers are used to
who look after data collection and
remove the accumulated dirt and bird
monitoring.
droppings, say once in a month. On an
Three bore - wells have been installed at average, each module is cleaned once in a
the site with pump-set capacities of 2 HP, week on rotational basis.
5 HP and 10 HP. The 2 HP pump set is used

3
-
MWs
c
al
egr
i
d-
co
n
ne
c
t
ed
so
l
arp
h
ot
o
vol
t
aic
po
w
er
pl
ant
at
Kol
ar
,K
ar
n
at
ak
a
R
e
p
or
tI
I
Sc-
D
CCC
1
1R
E
1 9

3. Performance analysis

The total Energy produced by 3 MWp Plant generation during 2010. Since Segment-3
during the year 2010 was 3,347,480 units. was not performing satisfactorily for a few
Out of this, 3,303,200 units were sold to the months, which is evident from the figure, we
grid. Figure 4 shows the contribution of all will restrict our analysis to the first two
the three Segments in the total power Segments only.

Energy generated by 3 MW Plant - 2010


450000

400000 Segment-3
Segment-2
Monthly Energy Generation (kWh)

350000 Segment-1

300000

250000

200000

150000

100000

50000

0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Month

Figure 4 : Contribution of all the three segments in the total power generation during 2010

3
-
MWs
c
al
egr
i
d-
co
n
ne
c
t
ed
so
l
arp
h
ot
o
vol
t
aic
po
w
er
pl
ant
at
Kol
ar
,K
ar
n
at
ak
a
R
e
p
or
tI
I
Sc-
D
CCC
1
1R
E
1 10

3.1 Segment-1 and Segment-2


The performance of the first two segments mean output of 6655.4 kWh per day. The
and their cumulative production over the capacity factor for this 2 MW plant was
year 2010 is shown in Figures 5 and 6 around 14.52% at the generation end
respectively. The total cumulative Energy (impact of grid-off times and maintenance
generated by both the Segments together down times are not included).
for the year 2010 was 2,429,219.6 kWh with

6000 Segment-1
Segment-2
Energy Generated per day [kWh/day]

5000

4000

3000

2000

1000

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Time [Daily]

Figure 5 : Daily Performance of Segment 1 & 2 during 2010

3
-
MWs
c
al
egr
i
d-
co
n
ne
c
t
ed
so
l
arp
h
ot
o
vol
t
aic
po
w
er
pl
ant
at
Kol
ar
,K
ar
n
at
ak
a
R
e
p
or
tI
I
Sc-
D
CCC
1
1R
E
1 11

The highest power generation achieved was temperature and Plant efficiency of 6663
11812.4 kWh on 5th February 2010, with the Wh/sqm/day, 42oC and 12.24% respectively.
recorded insolation, average module

2500000 2,429,219.6 kWh

2000000
Energy produced [kWh]

1500000

1000000

500000

0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Time [Daily]

Figure 6 : Cumulative Energy Produced by Segment 1 & 2 for the year 2010

3
-
MWs
c
al
egr
i
d-
co
n
ne
c
t
ed
so
l
arp
h
ot
o
vol
t
aic
po
w
er
pl
ant
at
Kol
ar
,K
ar
n
at
ak
a
R
e
p
or
tI
I
Sc-
D
CCC
1
1R
E
1 12

The decline in energy generation during number of cloudy days during that period
August to November period in Figure 7 was (see Figures 8 and 9). The declination can
mainly due to the improper functioning of be seen more clearly in Fig. 11 which shows
four Inverters (two in Segment-1 and the the variation of daily efficiency for the 2 MW
other two in Segment-2), and partially plant during the year 2010.
because of higher plant downtime and more

12000

10000
Energy Produced [kWh]

8000

6000

4000

2000

0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Time [Daily]

Figure 7: Daily energy production of 2MW Plant [Seg.1 & 2]

3
-
MWs
c
al
egr
i
d-
co
n
ne
c
t
ed
so
l
arp
h
ot
o
vol
t
aic
po
w
er
pl
ant
at
Kol
ar
,K
ar
n
at
ak
a
R
e
p
or
tI
I
Sc-
D
CCC
1
1R
E
1 13

Inverter 1 Inverter 2 Inverter 3


1.6M
EnergyGen (wh/day)

1.4M
1.2M
1.0M
800.0k
600.0k
400.0k
200.0k
0.0

Inverter 4 Inverter 5 Inverter 6


Inverter 6
EnergyGen (wh/day)

1.6M
1.4M
1.2M
1.0M
800.0k
600.0k
400.0k
200.0k
0.0
Jan Mar May Jul Sep Nov
Inverter 7 Inverter 8 Date

1.6M
EnergyGen (wh/day)

1.4M
1.2M
1.0M
800.0k
600.0k
400.0k
200.0k
0.0
Jan Mar May Jul Sep Nov Jan Mar May Jul Sep Nov

Date Date

Figure 8: Daily performance of all the 8 inverters

Figure 8 shows the daily performance of all 2, 3, 5 and 7 (which are shown in red) were
the inverters, first four come under malfunctioning during the period August to
Segment-1 and the next four under November, as compared with the remaining
Segment-2. It can be seen that the Inverters four inverters.

3
-
MWs
c
al
egr
i
d-
co
n
ne
c
t
ed
so
l
arp
h
ot
o
vol
t
aic
po
w
er
pl
ant
at
Kol
ar
,K
ar
n
at
ak
a
R
e
p
or
tI
I
Sc-
D
CCC
1
1R
E
1 14

100
Plant Shut Down
Grid-Off Times

80
Downtime (Hours)

60

40

20

0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Month

Figure 9: Monthly Plant down-time in hours-2010

Grid-off times: Figure 9 shows the was observed that the grid-offs occurred
cumulative monthly grid-off times during the mainly during the peak hours (11.30 am
year 2010. Out of the 357 days of the Plant's 2 pm), that is, when the availability of solar
operation, there were 75 days on which the insolation is maximal.
grid was off for less than an hour and 57 days
The Plant was shut down for 8 days during
with grid-offs more than one hour. Totally the
November for repairing the faulty cables and
grid was off for about 201.4 hours. Also, it
Inverters.

3
-
MWs
c
al
egr
i
d-
co
n
ne
c
t
ed
so
l
arp
h
ot
o
vol
t
aic
po
w
er
pl
ant
at
Kol
ar
,K
ar
n
at
ak
a
R
e
p
or
tI
I
Sc-
D
CCC
1
1R
E
1 15

Solar Insolation
The Plant is equipped with a Pyranometer mid May to mid June, due to some problem
installed at an angle of 15o, equal to the in the Pyranometer. The highest recorded
inclination of the Modules. The Solar daily insolation was 7199 Wh/sqm on 2nd
Insolation recorded at the site is shown in March 2010. The yearly average insolation
Figure 10. The Insolation data is not on the panels was about 4789 Wh/sqm/day.
available for about 44 days, especially from

8000

7000

6000
Insolation [15 Wh/m2]

5000
o

4000

3000

2000

1000

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Time [Daily]

Figure 10: Daily Solar Insolation at the site - 2010 [@15o. inclination]

3
-
MWs
c
al
egr
i
d-
co
n
ne
c
t
ed
so
l
arp
h
ot
o
vol
t
aic
po
w
er
pl
ant
at
Kol
ar
,K
ar
n
at
ak
a
R
e
p
or
tI
I
Sc-
D
CCC
1
1R
E
1 16

Efficiency

The 2-MW plant efficiency is the combined insolation of 2561 Wh/sqm and an average
efficiencies of segments 1 and 2 after the module temperature of 28.630C. The daily
dc-ac conversion by inverters to 415 Volts efficiency of the 2MW plant ranged from 5%
and just before stepping up to 11 kV ac. So, to 13.41% depending on the performance of
this should not to be confused with the arrays, inverters, average module
overall plant efficiency. temperature and the solar insolation. The
yearly average daily efficiency of the plant
Figure 11 shows the efficiency of the 2 MW
was about 10.14%, considering the days
plant, that is combined efficiency of
which have grid-offs for less than half an
segments 1 & 2, over the study period. The
hour or no grid-offs. The abnormal drop in
highest efficiency achieved was 13.41% on
the efficiency during the last few months was
24th July 2010. The total energy generated
mainly due to inverter related problems.
on that day was 4975.8 kWh with solar

16

14

12
Plant Efficiency (%)

10

0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Time [Daily]

Figure 11: Daily Efficiency of 2 MW Plant [Seg.1&2]

3
-
MWs
c
al
egr
i
d-
co
n
ne
c
t
ed
so
l
arp
h
ot
o
vol
t
aic
po
w
er
pl
ant
at
Kol
ar
,K
ar
n
at
ak
a
R
e
p
or
tI
I
Sc-
D
CCC
1
1R
E
1 17

60

50
Temperature [deg. Celsius]

40

30

20

10
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
DATE

Figure 12: Daily average temperature of PV modules (During day time) 2010

3.2 PV Modules Temperature


Figure 12 shows the daily average Although the solar insolation level is more in
temperature of PV modules for the year March compared to January, the efficiency
2010. It ranged from a minimum of 24.650C during March is low. This may be due to
0
(on 6th Dec) to a maximum of 51.9 C (on increase in the daily average temperature of
23rd April). PV modules during that month, as seen from
the Figure. But this is not very clear because
Figure 13 shows the combined plots of plant
of too much noise in the data. To reduce the
efficiency, daily average modules
noise and explore the issue further, we
temperature and daily solar insolation with
decided to analyze a single inverter which
reference to time scale. It appears from the
had performed well during the study period.
figure that the efficiency is more sensitive to
modules temperature than the insolation.

3
-
MWs
c
al
egr
i
d-
co
n
ne
c
t
ed
so
l
arp
h
ot
o
vol
t
aic
po
w
er
pl
ant
at
Kol
ar
,K
ar
n
at
ak
a
R
e
p
or
tI
I
Sc-
D
CCC
1
1R
E
1 18

Figure 13: Daily variation of average modules temperature, insolation (in Wh) and efficiency of the 2MW Plant

3.3 Performance of Inverter-1


As the performance of Inverter-1 is good energy generation by Inverter-1 versus the
compared to other Inverters (see Figure 8), incident solar insolation on that day for the
we chose this Inverter for more in-depth year 2010. The energy generation increases
study. Figure 14 shows the plot of daily linearly with the increase in solar insolation.

3
-
MWs
c
al
egr
i
d-
co
n
ne
c
t
ed
so
l
arp
h
ot
o
vol
t
aic
po
w
er
pl
ant
at
Kol
ar
,K
ar
n
at
ak
a
R
e
p
or
tI
I
Sc-
D
CCC
1
1R
E
1 19

1600

1400
Inverter-1
1200
Energy Generated (kWh)

1000

800

600

400

200

0
0 1000 2000 3000 4000 5000 6000 7000 8000
2
Solar Insolation (Wh/m /day)

Figure 14: Annual plot of daily energy generated by Inverter-1 versus solar insolation

3.3.1 Effect of temperature on efficiency


Figure 15 shows the variation in energy This is mainly because of increase in the
generation of solar modules with insolation temperature of modules, which negatively
and the effect of module temperature on impacts the efficiency more during that time
their efficiency. The plots are made using the [see Figure 15(B)]. Figure 16 shows the
5 minutes average values from 10 am to variation in efficiency of the modules with
3 pm on 21st January, 2010. variation in temperature of modules, along
with color mapped values for average solar
Even though the energy generation shows
irradiance. The efficiency of the modules
direct dependency on the incident solar o
decreases from 14.5% at 30 C to 11.5% at
insolation [see Figure 15(A)] and reaches
the maximum during peak insolation hours, 55oC. It is also clear from the Figure that the
the efficiency of the modules decreases and temperature of modules increases with the
reaches the minimum during peak hours. increase in solar insolation and reaches the

3
-
MWs
c
al
egr
i
d-
co
n
ne
c
t
ed
so
l
arp
h
ot
o
vol
t
aic
po
w
er
pl
ant
at
Kol
ar
,K
ar
n
at
ak
a
R
e
p
or
tI
I
Sc-
D
CCC
1
1R
E
1 20

maximum during peak insolation hours, values) for the year 2010. Due to lots of
0
leading to reduced conversion efficiency. noise below 20 C, the temperature values
Thus, the Plant's capacity to produce were binned between 200C and 550C. Then
maximum power is retarded during peak the efficiency values were binned between
insolation hours, when the availability of 10% and 15% choosing only the maximum
incident solar radiation is highest, because points. The plot shows linear decrease in the
of increase in modules temperature. daily efficiency of modules from 14.5% to
Figure 17 shows the annual plot of daily 11.5% with increase in the daily averaged
efficiency of modules in Inverter-1 versus modules temperature from 25 oC to 50oC.
daily averaged module temperature (binned

3.3.2 Performance of Inverter-1 on good days Daily plots


Figure 18 shows the daily performance plots efficiency of Inverter-1 with modules
of Inverter-1 on 24th March, 11th May, 18th temperature. The values of solar insolation,
June, 24th July and 20th September. The modules temperature and efficiency are
plots on the left side show the variation of averaged for every 5 minute interval. The
energy generation with solar insolation and energy generation values are the cumulative
the right side plots show the variation in figures generated for the same time period.

1200 17000
Efficiency
1150 Insolation Temperature
Energy Generated

1100 16000 56

12.8
Energy Generated (Wh)

1050

1000

Temperature ( C)
15000
Efficiency (%)
Insolation (W)

950

900 49
14000 12.0
850

o
800

750 13000

700 42
11.2

650 12000
09:00 10:00 11:00 12:00 13:00 14:00 15:00 09:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00
Time, Jan 21 Time, 21-Jan

Figure A: Insolation and Energy Generation (of Invereter-1) Figure B: Efficiency and Temperature of Modules (of Invereter -1)

Figure15: Plots of insolation, energy generation, efficiency & temperature of


Inverter-1 modules on January 21

3
-
MWs
c
al
egr
i
d-
co
n
ne
c
t
ed
so
l
arp
h
ot
o
vol
t
aic
po
w
er
pl
ant
at
Kol
ar
,K
ar
n
at
ak
a
R
e
p
or
tI
I
Sc-
D
CCC
1
1R
E
1 21

15.0

5 Min Avg. Efficiency SCALE FOR AVG


14.5
SOL IRR (W/m2)

14.0
1000

900.0
13.5 800.0
Efficiency(%)

700.0

13.0 600.0

500.0

400.0
12.5
300.0

200.0
12.0 100.0

20.00

11.5

11.0
25 30 35 40 45 50 55 60
0
Temperature ( C)

Figure 16: Efficiency v/s Temperature of modules of Inverter-1 (5 min average values)
on January 21, 2010 (Color scale : Average Solar Irradiance)

Plot Maximum Efficiency vs Temperature of Modules in Inverter 1


14.5

Maximum Efficiency
14.0 Linear Fit of Maximum Efficiency
Maximum Efficiency (%)

13.5

13.0

12.5

12.0

11.5

11.0
25 30 35 40 45 50 55
0
Temperature ( C)

Figure 17: Plot of daily maximum efficiency versus temperature of modules in Inverter-1 for 2010

3
-
MWs
c
al
egr
i
d-
co
n
ne
c
t
ed
so
l
arp
h
ot
o
vol
t
aic
po
w
er
pl
ant
at
Kol
ar
,K
ar
n
at
ak
a
R
e
p
or
tI
I
Sc-
D
CCC
1
1R
E
1 22

Solar Insolation Energy Generation


Temp Mod Efficiency
Solar Insolation (W/m )
2

1200 18000 70 15

Temp Mod (Deg. C)


Energy Generation (Wh)
1100 16000 14

Efficiency (%)
1000 60 13
14000
900
12
800 12000 50
700 11
10000
600 10
8000 40
500 9
400 6000
30 8
300 4000
200 7
2000
100 20 6
09:36 10:48 12:00 13:12 14:24 15:36 16:48 09:36 10:48 12:00 13:12 14:24 15:36 16:48
Time (March-24) Time (March-24)

Temp Mod (Deg. C)


1200 18000 70 15

Energy Generation (Wh)


Solar Insolation (W/m )

1100
2

16000 14

Efficiency (%)
1000 60
14000 13
900
800 12000 12
50
700 10000 11
600 10
8000 40
500
6000 9
400
300 4000 30 8
200 7
2000
100 20 6
09:36 10:48 12:00 13:12 14:24 15:36 16:48 09:36 10:48 12:00 13:12 14:24 15:36 16:48
Time (May-11) Time (May-11)

1200 18000 70 15
Temp Mod (Deg. C)
Energy Generation (Wh)
Solar Insolation (W/m )
2

1100 16000 14

Efficiency (%)
1000 60
14000 13
900
800 12000 12
50
700 10000 11
600 10
8000 40
500 9
400 6000
300 30 8
4000
200 7
2000
100 20 6
09:36 10:48 12:00 13:12 14:24 15:36 16:48 09:36 10:48 12:00 13:12 14:24 15:36 16:48
Time (June-18) Time (June-18)
Temp Mod (Deg C)

1200 18000 70 15
Energy Generation (Wh)
Solar Insolation (W/m )

1100
2

16000 14 Efficiency (%)


1000 60
14000 13
900
800 12000 12
50
700 10000 11
600 10
8000 40
500 9
400 6000
30 8
300 4000
200 7
2000
100 20 6
09:36 10:48 12:00 13:12 14:24 15:36 16:48 09:36 10:48 12:00 13:12 14:24 15:36 16:48
Time (July-24) Time (July-24)
Solar Insolation (W/m )

Energy Generation (Wh)


2

1200 18000
Temp Mod (Deg C)

70
1100 16000 14
Efficiency (%)

1000
14000 60
900
800 12000 12
700 50
10000
600 10
8000
500 40
400 6000
8
300 4000 30
200 2000
100 20 6
09:36 10:48 12:00 13:12 14:24 15:36 16:48 09:36 10:48 12:00 13:12 14:24 15:36 16:48
Time (Sept-20) Time (Sept-20)

Figure 18: (Left) Daily plots showing variation of energy generation with insolation;
(Right) Daily plots showing variation of efficiency with modules temperature

3
-
MWs
c
al
egr
i
d-
co
n
ne
c
t
ed
so
l
arp
h
ot
o
vol
t
aic
po
w
er
pl
ant
at
Kol
ar
,K
ar
n
at
ak
a
R
e
p
or
tI
I
Sc-
D
CCC
1
1R
E
1 23

4. Technical and maintenance related problems

Some of the major technical & maintenance ?


Presently the modules are cleaned by
related problems faced by the plant s p r a y i n g w a t e r. B u t t h e d u s t
operators are as follows: accumulated on the modules turns into
paste form once the modules are water
?
The power of the PV plant cannot be fed sprayed, making it difficult to remove.
to the grid if the power supply from the Also, the height of the modules
grid stops. Due to this, the power from mounting structures (see Figure 19)
the PV Plant is not available when it is makes it impossible to remove the dirt
needed most and the capacity of the completely with wipers while standing
Plant to work effectively has been on the ground. This has led inevitably, to
retarded. the option of cleaning the modules by
?
There is no tracking mechanism to climbing on top of them (and then using
locate the modules if they fail. If a wipers!). This will weaken the strength
module fails, it is very tiresome to of solar modules as well as mounting
identify it because no sensors have structures in the long run and also affect
been installed for this purpose. The only the power production. Hence, it is felt
solution presently available is to wait till that there is a need to address this issue
the peak time to identify the Inverter by developing alternate method/
(from which the output is lower). Then technology for cleaning the PV
the Inverter has to be isolated and all modules.
the 45-46 arrays connected to this ?
Recently, some of the modules have
inverter should be checked. Once the shown change in color (see Figure 20).
faulty array is located, all the connected It is yet to be ascertained whether this
modules need to be checked to identify color change in the modules has any
the faulty one. negative impact on their performance.

Figure 19: Photo of PV Plant showing the modules mounting structures inclined at 150.

3
-
MWs
c
al
egr
i
d-
co
n
ne
c
t
ed
so
l
arp
h
ot
o
vol
t
aic
po
w
er
pl
ant
at
Kol
ar
,K
ar
n
at
ak
a
R
e
p
or
tI
I
Sc-
D
CCC
1
1R
E
1 24

Figure 20: Visual color change of the photovoltaic modules

3
-
MWs
c
al
egr
i
d-
co
n
ne
c
t
ed
so
l
arp
h
ot
o
vol
t
aic
po
w
er
pl
ant
at
Kol
ar
,K
ar
n
at
ak
a
R
e
p
or
tI
I
Sc-
D
CCC
1
1R
E
1 25

5. Conclusion

The performance of the 3 MWp Yalesandra afternoon. The daily efficiency of modules
solar photovoltaic power plant has been varied from 14.5% to 11.5% with the
analyzed for the year 2010. The total variation in the daily averaged modules
o o
electrical energy generated by the temperature from 25 C to 50 C. Hence,
Yalesandra power plant during 2010 was cooling of the solar modules may be
3.34 million kWh and 3.30 million units were desirable to increase the efficiency. There is
sold to the grid. Based on the performance of a need to evaluate if the additional energy
the first two segments we estimate the mean required for cooling the solar modules will be
output to be 6655 kWh per day. This is lower less than the additional energy generated
than expected for a solar power plant and is due to higher efficiency.
on account of teething trouble associated
with inverters and the grid-encountered in
the first year of the operation of the plant. It The daily plots showing the variation of
was found that failure in inverters were the efficiency with modules temperature and the
most frequent incidents. This is mostly variation of energy generation with solar
caused by lack of experience in the initial insolation have been plotted for five different
production stage and some unexplained days of the year. Also, some of the present
inverter failures might be caused by maintenance and technical problems faced
disturbance from the grid and other by plant operators, including the color
interconnected issues [6]. change in PV modules and cleaning issues,
have been discussed.

The impact of temperature variation (of


modules) on the performance of It is also suggested that more measuring
photovoltaic mono-crystalline silicon instruments such as Pyrheliometer, Rain
modules was studied both on daily and Gauge, Thermocouple (Thermometer) for
yearly basis (daily average values). It is measuring ambient temperature, to be
observed that the efficiency of modules is installed in the plant and the existing
more sensitive to temperature than the solar instruments to be calibrated for greater
insolation. The normal daily trend is that the accuracy. This will enable further technical
efficiency of Plant is high during morning analysis of Indias first 3MW scale plant and
hours but low during the middle of the day help KPCL in their future solar power plant
and again starts increasing from late projects.

3
-
MWs
c
al
egr
i
d-
co
n
ne
c
t
ed
so
l
arp
h
ot
o
vol
t
aic
po
w
er
pl
ant
at
Kol
ar
,K
ar
n
at
ak
a
R
e
p
or
tI
I
Sc-
D
CCC
1
1R
E
1 26

6. References
1
.A
n
to
n
et
t
eD'S
aa
ndK
.V.
Nar
a
si
mhaMur
th
y,
Kar
na
t
ak
a'
sPo
w
er
Se
ct
o
r&S
u
g
ge
s
t
ed
Wa
y
s
F
o
rw
a
rd
,I
nt
er
n
at
i
ona
l
Ener
gy
I
ni
t
iat
i
ve,
di
scu
s
si
onp
ap
er
,
200
2
.

2
.K
.
Jai
r
aj,
Ene
r
gys
c
en
a
r
ioi
nKa
r
n
at
ak
a,
pow
e
r
poi
ntp
r
es
e
nt
a
ti
on,
Ene
r
g
yDe
p
ar
t
men
t
,
G
o
ver
nmen
to
f
Ka
rn
a
ta
k
a.

3
.S
o
la
rP
VP
o
w e
r
Pl
ant
s
,co
nt
r
ac
tag
re
em
en
t
fo
rs
u
pp
ly
of
equ
i
pme
n
t
s,
CE(
EI
&TA
)
/
SPV
,
K
P
CLa
n
dT
i
t
anE
ne
rg
ySy
st
e
msLt
d
.,
Sec
u
nd
e
r
aba
d
.

4
.O
p
er
a
ti
onm
a
n
ua
l
,Ti
t
anE
n
e
rg
y
Sy
s
t
em
sL
t
d
.,
Sec
u
nd
e
r
ab
ad
.

5
.C
o
nt
r
ac
ta
g
re
eme
n
t
fo
rE
r
ec
t
io
n,
t
est
i
nga
n
dc
o
mmi
ssi
oni
ngo
f
3MW
S
o
l
arP
Vp
o
we
r
pl
ant
,
K
P
CL
and
T
it
a
nEn
e
r
gy
Sy
st
e
msL
td.
,
Sec
u
nd
e
r
ab
ad
.

6
.M
o
ha
m e
d A.
El
ta
wi
lan
d Z
h
e
ngm
i
ngZ
ha
o,Gr
i
d-
co
n
ne
cte
d
ph
o
to
vol
t
aicp
o
we
r
sy
st
ems
:
T
e
ch
ni
cal
andp
ot
ent
i
al
pro
b
l
ems
-Ar
e
vi
ew,
Ren
ew
a
bl
ean
dS
u
st
a
in
abl
eEn
e
rg
y
Re
vi
ews
,
1
4
,2
01
0,112
1
29.

3
-
MWs
c
al
egr
i
d-
co
n
ne
c
t
ed
so
l
arp
h
ot
o
vol
t
aic
po
w
er
pl
ant
at
Kol
ar
,K
ar
n
at
ak
a
R
e
p
or
tI
I
Sc-
D
CCC
1
1R
E
1 27

7. Acknowledgements
Wew
isht
o t
ha
nkMr.B.R
.Naga
ra
ju
, Ex
-Chi
efEngi
nee
r
, R
EProj
ect
s,K
arn
ata
kaPower
C
orp
or
at
io
n L
td
.
(
KPCL)f
or
par
t
i
cipa
t
ingi
nth
eproj
ectby
giv
i
nga
ut
hori
zat
i
ont
ocol
l
ect
anduse
d
at
af
ort
hi
sre
se
ar
ch.Wet
ha
nkM r
.
A .
V.V.
Reddy,Exe
cut
i
veE
ngi
neer
,i
n-
cha
rg
e of
Kol
arPV
P
l
ant
f
orgi
vi
ngu
st
heper
f
orma
nc
e d
atao
fth
e p
lan
t.Weal
soap
pr
eci
at
e h
iss
pen
di
ngval
uab
le
t
i
mewi
t
h u
sand
sh
ari
ngh
i
scon
cer
nsab
outt
hepl
antdur
i
ngou
rf
i
el
dvi
si
ts.
W e
als
ot
hankMr.
D.
C
.Kr
i
shn
amur
th
y
,Exe
cut
i
veEn
gi
nee
r
,El
ectr
i
cal
Div
isi
on,
KPCLf
or
hel
pi
ngusi
nge
tt
in
gth
e da
ta
a
ndo
t
heri
nf
or
ma
ti
onr
ela
t
edt
ot
hepl
ant
.

W
e
al
soa
ckn
ow
l
edge
Mr
.M
.K.Na
ga
ra
ja
nd
th
eof
fi
cest
a
ff
atD
i
vec
h
aC
en
t
r
efo
r
Cl
i
m a
t
e
C
h
a
ng
e,f
or
t
he
ir
ki
nds
u
pp
o
rt
du
ri
ngt
h
eco
ur
se
of
t
hi
spr
oj
ect
.

3
-
MWs
c
al
egr
i
d-
co
n
ne
c
t
ed
so
l
arp
h
ot
o
vol
t
aic
po
w
er
pl
ant
at
Kol
ar
,K
ar
n
at
ak
a
Satellite image of the 3-MW scale grid-connected solar photovoltaic power plant at Kolar, Karnataka
REPORT IISc-DCCC 11 RE 1
AUGUST 2011

DIVECHA CENTRE FOR CLIMATE CHANGE


INDIAN INSTITUTE OF SCIENCE
Bangalore

You might also like