INTERNATIONAL MINING CO. S.A.

GRUPO MINERO LA CHOJLLA


SECCION - PROYECTO

INFORME MEDICION JULIO - 2017


"SECCION MINA"

1.- MEDICION LINEAL Mineral 2.8


N MEDIDO CONTRA AVANCE AREA VOLUMEN TMBH
NIVEL VETA PARAJE LABOR CONTRATISTA CONTRA NUEVA Obs.
Ctto (m) (m) (m) (m2) (m3) Mineral
-120 VETA- 4cc INTERMEDIA s/V-4cc Prep. Horizontal Juan Carrizales M. 6.40 0.00 6.40 1.58 10.12 28 Concluido Med, 03 Agosto 2017 - ORE

-120 VETA - ? PERF. XC- NIV-120 NUEVO Prep. Horizontal Macario Huanca B. 11.70 10.00 1.70 4.10 6.97 20 Concluido Med, 02 Agosto 2017 - Waste
-120 VETA - ? PERF. ENTRANTE # 1 Prep. Horizontal Macario Huanca B. 18.70 5.90 12.80 4.81 61.62 173 18.70m pared izq. Xc recta Med, 02 Agosto 2017 - Waste

-150 VETA - 7ca N PERF. INTERMEDIA V-07ca N Prep. Horizontal Lus Quispe Coronel 25.00 9.00 16.00 1.81 28.93 81 25 m Ceja pared sud Rj 1 Med, 01 Agosto 2017 - ORE

-150 VETA - 7ca N CHIM. CORTA 12 s/CRD 7 Prep. Vertical Hebert Miranda 3.80 0.00 3.80 1.60 6.08 17 Concluido Med, 03 Agosto 2017 - ORE

-150 VETA -8c N CRD V-8cN NIV-150 NORTE Prep. Horizontal Cesar Gutierrez A. 7.00 1.70 5.30 3.50 18.54 52 7m pared norte Pique Med, 01 Agosto 2017 - ORE
-150 VETA -8c N CRD V-8cN NIV-150 SUD Prep. Horizontal Cesar Gutierrez A. 2.30 0.00 2.30 1.84 4.23 12 2.30m pared sud Pique Med, 01 Agosto 2017 - ORE
-150 VETA -7ca N CRD EN CAJA NIV - 150 Rec. Horizontal Cesar Gutierrez A. 3.80 0.00 3.80 3.51 13.36 37 3.80m Tg pared derecha Med, 01 Agosto 2017 - WASTE

52.10 TOTAL 149.84 420

2.- RAJOS SHRINKAGE P.E. Mineral 2.8


N AREA ANCHO FACTOR VOL. TMBH
NIVEL VETA PARAJE LABOR CONTRATISTA Obs.
Ctto (m2) (m) INCLIN. (Total) Mineral

-120 VETA - 4cc Rajo 4- Longitudinal-Shrinkage Explotacin Juan Carrizales 51.32 0.59 90 30.28 84.78 Med, 03 Agosto 2017 - ORE

-150 VETA - 7caN Rajo 3- Longitudinal-Shrinkage Explotacin Hebert Miranda V. 51.36 0.70 90 35.95 100.67 Med, 03 Agosto 2017 - ORE

TOTAL 66.23 185.45

RESUMEN MOVIMIENTO DE CARGA EN


TONELADAS METRICAS
Vol. O/W Mineral Estril Total O+W
216 376 229 605

Chojlla; 03 Agosto de 2017


. .
Ing. Waldo Paita Ing. Daro Ajomado I.
Vo. Bo. GENERENTE MINA CHOJLLA SECCION PROYECTO
Cc.Arch.
Cc.Gerencia Mina