Id Modo de Nombre de tarea Duracin Comienzo Fin Predecesoras 26 jun '17 03 jul '17 10 jul '17 17 jul '17

tarea L M X J V S D L M X J V S D L M X J V S D L M X J V
0 CALENDARIOBALLONFLUETENTATIVO4 23das mi28/06/1mi19/07/17
1 TRABAJOSPRELIMINARES 11das mi28/06/17sb08/07/17
2 PresentacindeDocumentosdeSeguridad 3das mi28/06/17vie30/06/17
3 Montajedeandamiosyfacilidaes 5das lun03/07/17 sb08/07/17 2FC+3das
4 AprobacindeIPERC 0das vie30/06/17 vie30/06/17 2 30/06
5 ANLISISESTRUCTURAL 16.5das lun03/07/17mar18/07/17
6 TrabajoenCAMPO 9.5das lun03/07/17mar11/07/17
7 Modelamiento3DBallonFlue(Verificacion 5das lun03/07/17 vie07/07/17 Marco Caballero,Raul Narvez
DimensionalenCampo)
8 Comprobacindemodeloconestadoreal 4das sb mar11/07/17 7
(AsBuilt) 08/07/17
9 TrabajoenGABINETE 7das mi12/07/17mar18/07/17
10 Estimacindepeso 2das mi12/07/17jue13/07/17 8
11 AnalisisEstructuralFEM 5das jue13/07/17 mar18/07/17 10
12 InformeEstructural 0das mar18/07/17mar18/07/17 11 18/07
13 ESCANEO3DLASER 11das sb08/07/17mar18/07/17
14 FaseCaliente 9das sb08/07/17lun17/07/17
15 TrabajoenCAMPO 1da sb08/07/17dom09/07/17
16 Escaneoencaliente 1da sb08/07/17dom09/07/17 3
17 TrabajoenGABINETE 8das dom09/07/1lun17/07/17
18 GeneraciondeEscenario 1da dom09/07/1 lun10/07/17 16
19 Generaciondenubedepuntos 1da lun10/07/17 mar11/07/17 18
20 LimpiezadePuntos 4das mar11/07/17vie14/07/17 19
21 GeneracindeMalla 1da vie14/07/17 sb15/07/17 20
22 ComprobacindeMallayModelo 1da sb15/07/17lun17/07/17 21
23 FaseFrio(ISASTOP) 8das mar11/07/17mar18/07/17
24 TrabajoenCAMPO 4das mar11/07/17vie14/07/17
25 Escaneoenfrio 1da mar11/07/17mi12/07/17 19
26 DesmontajedeAndamios 3das mi12/07/17vie14/07/17 25
27 TrabajoenGABINETE 7das mi12/07/17mar18/07/17
28 GeneraciondeEscenario 1da mi12/07/17jue13/07/17 25
29 Generaciondenubedepuntos 1da jue13/07/17 jue13/07/17 28
30 LimpiezadePuntos 3das vie14/07/17 lun17/07/17 29
31 GeneracindeMalla 1da lun17/07/17 lun17/07/17 30
32 ComprobacindeMallayModelo 1da mar18/07/17mar18/07/17 31
33 InformeEscaneo3D 0das mar18/07/17mar18/07/17 32 18/07
34 NDT 6das lun10/07/17sb15/07/17
35 Medicindeespesores 4das lun10/07/17 jue13/07/17 18
36 ReplicasMetalograficas 2das vie14/07/17 sb15/07/17 35
37 InformeNTD 0das sb15/07/17sb15/07/17 36 15/07
38 ENTREGADEINFORMEFINAL. 1da mar18/07/17mi19/07/17 33,12,37 19/07

Tarea Resumen del proyecto Tarea manual solo el comienzo Fecha lmite
Proyecto: CALENDARIO BALLO Divisin Tarea inactiva solo duracin solo fin Progreso
Fecha: mi 28/06/17 Hito Hito inactivo Informe de resumen manual Tareas externas Progreso manual

Resumen Resumen inactivo Resumen manual Hito externo

Pgina 1