LTE Flow of Radio Network Planning

www.DigiTrainee.com Company Confidential


Objectives

Participants know the flow of radio network planning

Participants know the key parts of the stages of radio network planning

Participants make the radio network planning be more standard and

controllable

Page 2 www.DigiTrainee.com Company Confidential


Building up Mobile Network

Project Execution

Network
Planning
Network Objective

Network Optimization

www.DigiTrainee.com Company Confidential


Page 3
RNP&O Service

There are four phases during network lifecycle: Pre-Bidding, Bidding,


Implementation, Maintenance.
The RNP&O services are present throughout the network lifecycle,
divided by four parts: Scheme Traction, Radio Network Planning
(including Nominal Planning, Site Selection, Detail Planning), Radio
Networking Optimization (including Initial Tuning, Network Performance
Improvement), On-going

Page 4 www.DigiTrainee.com Company Confidential


Planning Process

Area Types
Propagation Model Coverage Planning
Network Element Capacity Planning Capacity
Network Layout Frequency Planning
Coverage
Approximate Number PCI Planning
Configurations
of Site
Parameter
Interference

www.DigiTrainee.com 5 Company Confidential


Nominal Planning Procedure (bidding)

Page 6 www.DigiTrainee.com Company Confidential


Nominal Planning Procedure (implementation)

Page 7 www.DigiTrainee.com Company Confidential


Nominal Planning Procedure

Page 8 www.DigiTrainee.com Company Confidential


Nominal Planning Procedure
Collects detailed information about the network planning
to meet the requirements of network estimation and
emulation input. It prepares for satisfactory planning result.

Network Planning Information


Related information from the market
Project documents output before the
Output Collection CHECKLIST
network planning is sold
Information about destination area Attention:
Object of network construction Before the project is
Plan of network scale and stage started, be acquainted with
Recent optimization
report
construction related information Carriers network
Available sites and frequencies to Confirm the information configuration information
the carriers
with the users for several Carriers drive test
Digital map
times analysis
MapInfo map
Carriers network traffic
VIP user survey Pay attention to VIPs
analysis
For expansion, move or change, User complaint analysis
the collected information includes Related guide

www.DigiTrainee.com Company Confidential


Page 9
Nominal Planning Procedure

Scheme Output and Risk Analysis (PM focus)

Page 10 www.DigiTrainee.com Company Confidential


CW Test and Model Rectification (Optional)

The Propagation model is the basis of the network planning. Whether the
model is effectual or not affects the planning result, and it also decides
whether we can meet the requirement with economic and proper investment

Attention:
For years development,
Propagation scene the company has a complete
classification model library. It is
Representative test recommended to obtain the
Location selection model from the model library. PROPAGATION MODEL
Preparation of the testing Output
For the needs of the TUNING REPORT
instruments and software market or customers, you
can test the typical area
based on the actual
reconnaissance. Then,
rectify the model based on
the test result.

www.DigiTrainee.com Company Confidential


Page 11
Radio Network Dimensioning

Through the dimensioning, we can perform a quantitative analysis and get the
construction scale for the network. Thus, the construction period, as well as
the cost budget is worked out.

Scenes classification, Attention:


and the Propagation Model If the customer can not Key points:
confirm provide the input
parameters, refer to the
Network input parameters,
The Coverage, Capacity, RND documents and
company planning
Quality for each scenes principle to provide a set of the result.
Traffic model and service recommended values and
model THE RADIO NETWORK
submit to the customer for
Other related parameters confirmation. DIMENSIONING REPORT
Dimensioning tool software For the improper input should be reviewed before
Related references parameters, consult with it is submit to the customer
the customers. Besides,
notify to the project team
and the result need to be
gone through.
.

www.DigiTrainee.com Company Confidential


Page 12
RF Survey (optional)

To have a survey for each candidate site. Collect RNP and environment
Information and confirm whether the site spot meet the requirements or not.

Attention:
For the matching site spots,
record and confirm the
engineering parameters; for Key points to be monitors:
the ones unsuited, give the The following needed to be
Topology map of the
replacing suggestion and reviewed:
network base stations perform the simulation Engineering parameters table
Survey equipments All the site spots which are base station topology, and
failed to be survey by
antenna feeders selection.
customers cause should be
recorded in the survey spot-check the survey resul
memo. .
For co-site RF survey,
enough independence
should be considered.
RF survey factors
.

www.DigiTrainee.com Company Confidential


Page 13
Spectrum Test (Optional)

To make sure that the occupied spectrum is available, we can have a to


spectrum test on site. Generally, the test can be performed during the survey.

Attention:
For large-scale trail
network, spot-check is
acceptable considering
the workload
The test instruments and
Drive Test should be
fittings taken for downlink band
Related reference

www.DigiTrainee.com Company Confidential


Page 14
Simulation

Simulation should be performed after survey based on the survey result. The
simulation is a process keep adjusting the planning configuration to meet the
requirement of the customers.

Attention:
If the sites situation do not
meet the requirements,
Engineering Parameters judgment should be taken
Table to determine whether to
Propagation Model select a new site or not.
Parameters required in If the simulation result Project Network
the simulation does not meet the Simulation Report
requirement. Survey and
Simulation software
simulation should be
Digital map reworked until the target
was fulfilled. Then, we can
output the NETWORK
SIMULATION REPORT.

www.DigiTrainee.com Company Confidential


Page 15
RNP Pre-Planning Report
Integrating the previous information collection, network
dimensioning, RF survey, and simulation, to summarize the
result and output the NETWORK PRE-PLANNING REPORT. .

Template of the network


Attention:
pre-planning report
Import information for the The pre-planning report XXX Project Network
network planning after review needs to be submit Preplanning Report
to the market of the regional W Network Pre-planning
NETWORK DIMENSIONING REPORToffice for improvement. Then, it
RF SURVEY REPORT Input
can be submitted to the
Scheme
SIMULATION REPORT customer. and Report Review
Submit the simulation result Self-Checking
as soon as possible to promote
the progress of the project.

The following needs to be monitored:


Pre-planning result and pre-planning report review
www.DigiTrainee.com Company Confidential
Page 16
Site Selection Procedure

Page 17 www.DigiTrainee.com Company Confidential


Detail Planning Procedure

Page 18 www.DigiTrainee.com Company Confidential


Parameters Design

Set the single cell into a connected network and guide the
later implementation

Network Pre-planning Report


Engineering Parameters
Table
Network Planning
CELL PARAMETER DESIGN
Information Collection Table
REPORT or
Default Parameter Comparison
NETWORK DESIGN REPORT
Table
Related References

The cell parameters include the following:


LAC, RAC/RNC Area, Neighbor Cell List, Frequency Band /PCI,
Power Distribution, Handover

www.DigiTrainee.com Company Confidential


Page 19
Radio Network Planning
Integrate the network pre-planning report and the cell parameter design report, output the
RADIO NETWORK PLANNING PROPOSAL and submit to the regional office and TS for review,
and then have a presentation to the customer .

Attention:
The planning rule of all
parameters must be embodied
Radio Network Pre-Planning Report in the Planning Scheme for the
convenience of other person and
Cell Parameter planning Report or Radio
guide the later network
Network Planning Report optimization. Radio Network Planning Rep
Network Planning Scheme
Radio Network Planning
Communication Report
The following needs to be monitored:
Review the report of the radio network planning
and planning scheme

www.DigiTrainee.com Company Confidential