TABLE FOR PRODUCTIVITY RATES OF VARIOUS TRADES

Activity Description Unit (Man/Machine)Hr./Unit Resource Approx. Output

Blinding Concrete m 0.20 Mason+Helper 80m per day.

Back fill m 0.01 Compactor+Helper 1800m per day.

Anti Termite Protection m 0.11 Mason+Helper 150m per day.

Plinths no. 0.13 Mason+Helper 120blocks per day.

Excavation m 0.11 Excavator+Helper 150m per day

Hor. Waterproofing m 0.89 WP applicator+Torchman 18m per day.

Ver. Waterproofing m 1.00 WP applicator+Torchman 16m per day.

Liquid Waterproofing m 0.89 WP applicator+Torchman 18m per day.

Water Tank Waterproofing m 1.00 WP applicator+Torchman 16m per day.

Rebar Placement kg 0.03 Steel Fixer (1 person) 300 kg per day.

Raft Slab Concreting m 0.33 Mason+Helper( group of 12) 36m per hour.

Formwork for Retaining wall & Vertical Elements m 10 Carpenter (1 person)

Retaining Wall Concreting m 0.22 Mason+Helper( group of 4) 18m per hour.

Vertical Elements Concreting m 0.67 Mason+Helper( group of 4) 6m per hour.

Slab formwork preparation m 2.52 Carpenter+Helper 14m per day.

Floor Slab Concreting m 0.43 Mason+Helper( group of 12) 28m per hour.

Blockwalls m 1.78 Mason+Helper 9m per day.

Additional Blockwalls m 2.29 Mason+Helper 7m per day.

Plastering Horizontal m 1.45 Mason+Helper 11m per day.

Plastering Horizontal (for Hotel) m 1.6 Mason+Helper 10m per day.

Plastering Vertical m 1.14 Mason+Helper 14m per day.

Plastering Vertical (for Hotel) m 1.45 Mason+Helper 11m per day.

Floor Screed m 0.44 Mason+Helper( group of 12) 27m per hour.

Painting Horizontal m 0.57 Painter+Helper 28m per day.

Painting Vertical m 0.53 Painter+Helper 30m per day.

Painting External m 0.50 Painter+Helper 32m per day.

Painting Staircase m 1.60 Painter+Helper 10m per day.

Floor Tiling m 2.00 Tile Fixer+Helper 8m per day.

Wall Tiling m 3.20 Tile Fixer+Helper 5m per day.

Roof cement Tiling m 1.33 Tile Fixer+Helper 12m per day.

False ceiling suspension System m 0.53 Carpenter+Helper 30m per day.

Faade Damp Proofing m 0.27 WP applicator+Torchman 60m per day.

Road marking m 0.53 Painter+Helper 30m per day.

Corner & column Guard pc 1.33 Carpenter+Helper 12 pc per day.

Handrail m 1.00 Welder+Helper 16m per day.

Wall Finishes m 3.20 Mason+Painter 5m per day.

Al Wall Finishes m 0.32 Carpenter+Helper 50m per day.

Granite & Terracota Wall Finishes m 3.20 Mason+Painter 5m per day.

Countertops pc 4.00 Tile Fixer+Helper 4 pc per day.

Curtain glass pc 0.32 Carpenter+Helper 50 pc per day.

Gypsum & Al False ceiling m 0.32 Carpenter+Helper 50m per day.

Sanitary wares pc 3.20 Tile Fixer+Helper 5 pc per day(1 bathroom).

Al doors & windows pc 4.00 Carpenter+Helper 4 pc per day.

Wardrobes pc 2.67 Carpenter+Helper 6 pc per day.

Kitchen units m 0.50 Carpenter+Helper 32m per day(2 kitchen units).

Doors pc 3.20 Carpenter+Helper 5 pc per day.

Steel Frame work & Metal Deck m 0.53 Welder+Helper 30m per day.

NOTE: The above work rates are calculated for 8 hrs. working/day.
TABLE FOR PRODUCTIVITY RATES OF VARIOUS TRADES

Activity Description Unit Skilled Manhours/Unit Unskilled Manhours/Unit Approx. Output

Concrete Pouring:

Blinding m2 0.25 0.50

Concrete For Raft m3 0.50 2.00

Concrete For other members m3


1.00 4.00

Formwork:

Formwork for Retaining Wall m2 3.50

Formwork for Columns m2


3.50

Formwork for Walls m2 4.00

Formwork for Slab (Table type) m2


3.00

Formwork for Beams m2 5.00

Formwork for Ramps,Stairs & Parapets m2


6.00

Steel Reinforcement:

Reinforcement for Raft Tonnes 0.33

Reinforcement for Other members Tonnes 0.55

Finishes:

Block work m2 1.25

Plastering for Walls (with mesh & Scaffolding) m2 3.25

Plastering for Ceilings (with mesh & Scaffolding) m2


3.50

Wall Marble m2 6.00

Floor Marble m2
5.00

Wall Ceramics m2 4.75

Floor Ceramics m2
4.25
NOTE: The above work rates are calculated for 8 hrs. working/day.