FEED - Front End Engineering Design

FEED stands for Front End Engineering Design. The FEED is basic engineering which comes after
the Conceptual design or Feasibility study. The FEED design focuses the technical requirements as
well as rough investment cost for the project. The FEED can be divided into seperate packages
covering different portions of the project. The FEED package is used as the basis for bidding the
Execution Phase Contracts (EPC, EPCI, etc) and is used as the design basis.
A good FEED will reflect all the clients project specific requirements and avoid significant changes
during the execution phase. FEED Contracts usually take around 1 year to complete for larger sized
projects. During the FEED phase there is close communication between Project Owners and
Operators and the Engineering Contractor to work up the project specific requirements.

Estimating, Control of Projects and Risk Department Manager, leading a direct team of 14 people. Overlooking and
sponsoring all projects executed in the Spanish Technip operating centers, focused on :
o Project Control: Planning, progress and productivity
o Estimating : TIC 30% and 10% cost estimates
o Cost control: Budgetary control and internal costs follow-up
o Contract Management
o Risk assessment workshops
Project Manager for CEPSA, ACPDM Project - Sulphur Recovery
Units, Huelva - Spain. Responsible for 3 SRU's, sulphur tank and 3
sulphur solidification units:
o Coordination of internal engineering resources
o Direct relation with client, vendors and packages
o Project Control: Planning, progress and productivity
o Scheduling and project control,
o Contract Manager,
o Deputy project manager

Assigned to the Shaw Milton Keynes Technology Projects Group with responsibility for management of a series of
technology feasibility and process study projects in the olefins, refining and petrochemical sectors.
Some key projects are as follows (2010 - 2011):
Front-end engineering design study for a New Cryogenic Ethylene Storage Tank Facility
Management and co-ordination of a technical review of a FEED package for an oil refinery relocation.
Managed a suite of improvement projects for the ISAB refinery in Sicily.

Responsible for the management of the engineering activities during the basic engineering phase. For this particular
project, the client's target ethylene expansion capacity is 113%. Overall responsibilities include implementation of
the Engineering Department's standard work processes, procedures, specifications and quality management
systems
His most recent aSSignment has been the PMC Engineering Manager Process Licensor Coordinator of a major
grassroots Refinery Project in the Sultanate of Oman.

He has assisted in due diligences and business development appraisal of a range of emerging new technologies in
alternative energy (biofuels & GTL) and waste treatment sectors in Europe, Asia and America.

PrinCipal Engineering Manager, assigned as PMC Engineering Manager I licensor Coordinator for the Pre-FEED and
FEED phases of the Duqm Refinery Project in the Sultanate of Oman (August 2012 - Present)
(FEED by Foster Wheeler, Reading). Delivered a number of Client requested feasibility studies to optimise the scope
and capital cost. The role required strong analytical thinking and strategic thinking skills to ensure that all options
and potential risks were fully explored.
Responsible for coordinating the development of engineering specifications for the Duqm refinery, creation of ITT's,
prequalification of bidders, evaluation of bids, preparation of evaluation reports and recommendation to the client
for award of the following:
LlCENSOR(s) Process Design Packages
FEED ENGINEER
HSEIA consultant
ICS vendor
Geotechnical Investigation Consultant
Topographical Survey Consultant.
Site Preparation Consultant
EPCC Pre-Qualification Package

Responsible for all Project management & Engineering aspects of the project. Consultancy duties during
Procurement, Construction and Commissioning.
Project Engineer, revamp project for Confidential Major Nuclear
Company. (2006 - 2007)

Liaison between the lead discipline engineers for the specification and design of pump systems for nuclear sludges.
Process Engineer, revamp project. Responsible for the specification and design of retrofitted jet mixers used for de-
stratification in tank farms such as LNG. (Confidential major oil and gas company.(2006 - 2007)

For the last 12 years, he has worked primarily within a project engineering I management role and has proven
capability of managing FEED, PMC and EPC projects.
These executions have been located in UK, across several sites in Europe and KSA
Responsibilities have included reporting to the Project Engineering Director, with accountability for managing
multidisciplinary engineers across multiple execution centres to deliver a capital expenditure programme. Key
achievements include successful project execution to meet agreed budget, time, quality and HSE requirements.
He has in-depth knowledge of all stages of project execution from concept development through to detailed design,
commissioning and operational qualification within both company and client office environments.
Earlier on in his career as a Process Engineer, he gained an invaluable and varied range of experience within the
speciality chemicals, fine chemicals and pharmaceuticals industry. He has led the process engineering input on a
number of engineering projects, supervising other process engineers and liaising closely with the client and other
engineering technologies.

Responsible for a series of infrastructure projects to support the expansion of Client's processing stream. Projects
involved the design and build of a new chiller facility and the upgrade of the site cooling water system. Duties
included coordination of the civil, mechanical and E&I design teams, equipment procurement I subcontract
management and the ongoing drive of construction activities on site. (2009 - 2010)

Responsible for a series of phased utility projects to centralise and expand the site's hot water, steam, condensate
and compressed air infrastructure. Duties involved managing the M, E & I design and construction services as part
of a site alliance partner for a range of projects totalling circa. 9 million (2006 to 2008).

Bioprocess Project Engineer, directly responsible for the engineering and implementation of all activities related to
a new product introduction at Phase III clinical trials, Centocor, Leiden, The Netherlands. Work included overall
responsibility of design and integration of the process equipment within the Leiden manufacturing facility, which
was achieved through managing the interfaces between the site process development, validation, SHE, QA,
maintenance and production groups. (2004 - 2005)
Site based Project Engineer accountable for an integrated cooling study, GlaxoSmithKline, Irvine, Scotland, UK,
which is primarily aimed at determining the most efficient and cost effective operating strategy for the site towers
and chilled water systems. Key deliverables were provision of hydraulic & thermal simulation models using Fathom
and Aspen Plus, and budget costing for energy saving projects. (2003 - 2004)
Great Lakes, Saudi Arabia. Home office based Lead Process Engineer responsible for the detailed design phase of a
blending facility constructed in AI Jubail, Saudi Arabia. Responsible for all areas of process design associated with
the raw material I product storage, process blending, offloading equipment and utility packages. (2003)
Site based Lead Process Engineer for a 1.2 million plant expansion of two processing streams on a general-
purpose plant facility, GlaxoSmithKline, Utverston. Responsibte for a small team of process engineers in providing
all process deliverables against a fast track programme for the front-end and detailed phases tn a project
engineering capacity, also responsible for delivering several engineering capital projects of values up to 1million.
(2002)
Home office based Lead Process Engineer working on a front-end package for a 8 million utility upgrade project,
BNFL, Sellafield, UK.
Proposal was to upgrade existing site utility systems to withstand a
seismic event. Work involved utility system studies, package specification
and basis of safety analysis. (2002)

Commissioning and validation support for a vacuum pan filter and dry
milling facility. Responsible for writing the associated operational I
performance qualification documents.

During the detailed design phase, project managed a multi-disciplined team of engineers in the provision of a new
350K bulk storage and handling facility for MDI, Gurit Essex, Nuneaton, UK. Other responsibilities included
procurement and subcontractor negotiations (2001).
Site-based Process and Project Group Leader providing basic engineering services for the expansion of an existing
polymer plant, Solvay Interox, Warrington, UK. Overall responsibilities included front-end process design and co-
ordinating the workload and activities of the engineering team members. Role also involved compilation of a
sanction grade estimate for circa 3.5 million for submission to the client. (2000 - 2001)
Site-based Project Engineer for several environmental and improvement projects, GSK. Ulverston. Responsibilities
included process design support and project management of an integrated team of GSK and company personnel.
Typical projects included a 1.6 million environmental I operational expansion of the incinerator plant and a 350k
detection and isolation system on the site drainage system. Other responsibilities included support in procurement
and subcontract management, as well as construction assistance. (1998 - 2000)
Process Engineer supporting a Concept Study for an Active Pharmaceutical Ingredient (API) plant. Work involved
generation of preliminary equipment data sheets, design philosophy documents and utility reviews.
Process Engineer providing design support for the Front-End Engineering Package for a validatable API plant,
Mitchell Cotts Chemicals, Mirfield. (1998)

Process Engineer involved with the detailed design phase of a major upgrade of an API Plant, GlaxoWelicome,
Montrose. Work included line sizing, process equipment and instrumentation specification and P&I D development.
(1997 -1998)
Technical Team Leader accountable for the expansion of a speciality chemical plant, DuPont, Ruabon. Work
included front-end and detailed design, liaison with vendors and other departments, closing -out safety
actions, commissioning and start-up assistance. (1997)
Assigned to the Process Additives Division of FMC to assist in the commissioning and hand over to production of
the RDP Plant - a batch reactor and continuous distillation facility. This assignment involved working a 12-hour shift
roster system. (1996 -1997)
Seconded to the Engineering Division of DuPont UK Ltd; working as a technical team leader on a wide range of
improvements projects. Project responsibilities included both mechanical I process engineering design, estimating,
project planning and management. (1996)