Subject - Estimating and Costing

Topic - Task work per Day


Task Work
The capacity of doing work by an artesian or skilled labour in the form of quantity of work per day (eight
hours) is known as task work.
Task work per day by different artesian or labourer as per all india schedule of rates
S.No. Items Quantity Per Day
1 Excavation in ordinary soil 3.00 cu m 100.00 cu ft Per coolie
2 Excavation in hard soil 2.00 cu m 75.00 cu ft Per coolie
3 Excavation in rock 1.00 cu m 35.00 cu ft Per coolie
4 Sand filling in plinth 4.00 cu m 140.00 cu ft Per coolie
5 Brickwork in c.m upto plinth 1.25 cu m 45.00 cu ft Per mason
6 .. do. But in superstructure 1.00 cu m 35.00 cu ft Per mason
7 Brickwork in arch in c.m. 0.55 cu m 200.00 cu ft Per mason
8 Brickwork in jack arches in c.m. 0.55 cu m 20.00 cu ft Per mason
9 Half brick wall in partition in c.m. 5.00 sq m 50.00 cu ft Per mason
10 Reinforced brickwork 1.00 cu m 35.00 cu ft Per mason
11 Coursed rubble masonry n c.m. 0.80 cu m 30.00 cu ft Per mason
12 Random rubble masonry in c.m. 1.00 cu m 35.00 cu ft Per mason
13 Ashlar masonry in c.m. 0.40 cu m 15.00 cu ft Per mason
14 Brickbat concrete in foundation 10.00 cu m 350.00 cu ft Per mason
15 Brickbat concrete on terrace 6.00 cu m 200.00 cu ft Per mason
16 Cement concrete 5.00 cu m 175.00 cu ft Per mason
17 Reinforced cement concrete work 3.00 cu m 125.00 cu ft Per mason
18 25 mm thick cement concrete for D.P.C. 12.50 sq m 125.00 sq ft Per mason
6mm thick cement terrazzo flooring over
19 5.00 sq m 50.00 sq ft Per mason
20 mm thick P.C.C (1:2:4)
Precast terrazzo mosaic tiles flooring in
20 5.00 sq m 50.00 sq ft Per mason
c.m. or l.m. bedding of 25 mm thickness.
Precast terrazzo mosaic tiles skirting in 12
21 3.20 sq m 32.00 sq ft Per mason
mm thick c.m.
22 Brick on edge flooring in c.m. 7.00 sq m 70.00 sq ft Per mason
23 25 mm thick cement concrete flooring 12.50 sq m 125.00 sq ft Per mason
24 12 mm thick cement plaster on brickwork 10.00 sq m 100.00 sq ft Per mason
25 6 mm thick cement plaster on R.C.C. 10.00 sq m 100.00 sq ft Per mason
26 Pointing with cement mortar 15.00 sq m 150.00 sq ft Per mason
27 Three coats of whitewash or colourwash 60.00 sq m 600.00 sq ft Per painter
28 One coat of whitewash or colourwash 200.00 sq m 2000.00 sq ft Per painter
29 Snowcem on plaster work 20.00 sq m 200.00 sq ft Per painter
30 Three coats of oil painting 20.00 sq m 200.00 sq ft Per painter
31 Pastic enamel painting 28.00 sq m 28.00 sq ft Per painter
32 Fully paneled wodden doors and windows 0.15 sq m 15.00 sq ft Per carpenter
33 ..do but battened doors and windows 0.80 sq m 80.00 sq ft Per carpenter
34 Timber framing of sag,sal or teak wood 0.07 cu m 2.50 cu ft Per carpenter
35 .do.but country wood 0.15 cu m 5.00 cu ft Per carpenter
36 Galvanized corrugated sheets for roof 10.00 sq m 100.00 sq ft Per carpenter
37 Single manglore tilling 6.00 sq m 60.00 sq ft Per tile layer
38 Double manglore tilling 4.00 sq m 40.00 sq ft Per tile layer
No. of brick laid by amason in brickwork
39 600 bricks Per mason
upto a height of 3 m.
40 Amount of work done by male coolie
(1) Mix 3.00 cu m 100.00 cu ft Per coolie
(2) Deliever brick upto 15 m distance 400 nos. Per coolie
(3) Deliever mortar 5.50 cu m 200.00 cu ft Per coolie
Scaffolding cost for single storey building 0.50 per cu m