You are on page 1of 10

aTe 4925

Submarine Pipeline Trenching by Multipass Ploughs


by R.J. Brown and A.C. Palmer, R.J. Brown & Assocs.

Copyright 1985 Offshore Technology Conference

This paper was presented at the 17th Annual OTC in Houston, Texas, May 6-9,1985. The material is subject to correction by the author. Permission to
copy is restricted to an abstract of not more than 300 woras.

ABSTRACT sectors has led to a moderation of


requirements. Authorities are now sometimes
A major development program for large ready to accept that pipelines need not be
ploughs to trench submarine pipelines began trenched, particularly if they are large or
in 1975, and has led to the construction of if it can be demonstrated1t~at they will
13 ploughs, which have been used in many bury themselves naturally ,
parts of the world. Deep trenches are best
cut in a sequence of separate passes. The Until about five years ago, jetting was the
paper describes the development of the first technique almost always used to trench
multi-pass plough, used to trench the submarine pipelines. Since jetting
Gullfaks pipeline in 1984, and the techniques were first developed in the
application of the concept to Arctic 1950s, they have been substantially
pipelines, which may require trenches more modified, but their efficiency is much
than 4 m deep. affected by geotechnical 'conditions on the
sea bed. In medium clay, for instance,
INTRODUCTION jetting cuts a neat rectangular trench, but
in loose sand it leaves a wide and shallow
Many submarine pipelines have to be trench, with side slopes less than 10 0 ,
trenched. A trench protects the pipe against which does little to protect the pipeline.
damage from fishing gear, much reduces In the wrong conditions, jetting is slow an
hydrodynamic forces from waves and currents, expensive. In one notorious instance in the
gives a degree of protection from small Netherlands sector, 13 passes over the same
anchors and from construction vessels' spot were required before the pipeline was
mooring lines, and may be desirable for lowered to the required depth.
security, aesthetic or environmental
reasons. The relative importance of these A creative dissatisfaction with the high
factors naturally varies from project to cost and limited efficiency of jetting led
project. If the trench is backfilled, to a a search for better trenching methods.
protection against fishing gear and waves is There have been two principal lines of
complete, security against other kinds of development, ploughs and mechanical cutting
damage is increased, and heat transfer systems. Each is appropriate in the right
between the pipe and the sea is reduced. conditions. At first, mechanical cutting
systems were plagued by mechanical and
In some areas, regulatory authorities insist electrical faults, and by sensitivity to
on trenching, at least for small-diameter bottom soils and topography. These problem
pipelines. In the early years of North Sea have now been largely overcome, and the
development, for instance, authorities asked Kvaerner-Myren and Heerema systems have bee
for pipelines to be lowered below the used in a number of North Sea projects,
natural sea bed, sometimes to a depth of 2 while in the English Channel good results
or 3 m. It was widely a,rgued that these have been achieved with cutting systems
requirements were excessive, and the designed to trench the cross-channel power
generally excellent ex~erience of more than cables.
15 years operation of an extensive and
growing network of North Sea pipelines, in At the same time, there has been a major
the British, Norwegian, Dutch and Danish development of pipeline trenching ploughs.
Only nine years ago, the idea of ploughing
References and illustrations at 'end of pipeline trenches met a hostile and often
paper. derisive response. Ploughing is now an
283

- - - - - - -- -- -
- - -
2 SUBMARINE PIPELINE TRENCHING BY MULTI-PASS PLOWS OTC4925

accepted and widely used technique, and in attitude alters, so that it cuts less
many conditions is the method of choice. deeply, the heel loses contact with the
Figure I is a plot of the length of trench bottom, the heel reaction falls to
submarine pipeline ploughed each year since zero, and the share reaction pushes the
1977, and the number of distinct projects share downward so that it cuts more deeply.
each year, and shows the growth in the If, on the other hand, the plough cuts too
acceptance of the plough technique since deeply, the heel itself has to cut the soil
1980. and the heel reaction increases and lifts
the share to reduce the cutting depth.

PLOUGHS In consequence of the long-beam


configuration, the plough cuts at a uniform
The plough is an ancient device. In depth, and the trench depth does not change
agriculture, its function is not generally if the soil strength changes (unless it
to make a trench, but to turn over and break becomes so weak that it cannot support the
up the upper layer of soil, and to bury heel or the skids). If the heel is indlined
vegetation. Large trenching ploughs are used transversely, so that it is in contact with
in forestry. Ploughs were used to trench the sides of the trench as well as the
pipelines in the UK and the Middle East in bottom, the same principle gives directiona
the 19605. With hindsight, it appears that stability.
the difficulty of designing a good plough
had been underestimated. A plough designed The first trenching plough cut a 1.2 m deep
incorrectly either d~gs too far and becomes trench 2200 m long at Statfjord in 1977. A
anchored, or fails to penetrate and scrapes second plough was designed to trench the
along the surface without making a proper
trench. Moreover, it is sensitive to soil s
shore crossing of the Drake F 7g flowline
system in the Canadian Arctic ' It had to
strength, and cuts at different depths in work in a completely different bottom soil,
different soils. All these troubles a soft marine clay with a shear strength of
occurred, and development was discontinued. 3 kN/m 2
These two ploughs were applied in a
The development described here was pre-trenching mode, to cut a trench into
stimulated by observations during a bottom which a pipeline would afterwards be pulled
tow test in the Norwegian Trench in 1975, Their success prompted investigation of the
which showed that the pull head at the wider pqssibilities of post-trenching, wherE
leading end of the pipeline itself cut a the pipeline is laid first, by a laybarge,
shallow trench in the sea bed, and suggested reel or a tow, and then the trench is cut
that if a plough were added a pipeline could beneath the pipe. Development of
be trenched and towed into position in the post-trenching ploughs began in 1977. One
same operation. The first pipeline trenched concept was for the plough to excavate a
by this method ~a~ a loading line on the trench parallel to the pipeline, and for th
Statfjord field ' As a first application pipe to flex sideways into the trench,
of ploughing, the project was an ambitious rather as it does with the Kvaerner-Myren
one. The trench had to be cut in hard trenching machine. The second concept was
heavily-overconsolidated clay, with a shear for a symmetrical plough, which would cut
strength of 150 kN/m 2 , and the plough was to directly beneath the pipe, and that concept
be pulled by a tug with a bollard pull of has been preferred for all ploughs built to
1.8 MN (180 tonnes). Accurate depth control date, for several reasons, principally its
was essential, since otherwise the specified ability to meet a range of soil types.
trench depth would not be achieved
everyWhere, and the plough might require Model tests on post-trenching were carried
more force than the tug could apply. That out for Shell Expro in 1977, and for Smit
prompted the choice of the long-beam International in 1977-8, and investigated
configuration, shown in Figure 2, which has several aspects of the design, including
been ~dopted in all subsequent pipeline interaction between the plough and the pipe
ploughs. Its outstanding advantage is plough forces in different soils, and
precise and consistent depth control. Skids steering. They confirmed that post-trenchin
or wheels hold the front end of the beam at would be safe and economical, and a full-
a fixed height above the sea bed. The rear scale plough was designed in 1978. Further
end of-the beam carries a share, which cuts model tests followed in 1979.
the soil and lifts it upwards and sideways.
Mouldboards push the spoil outwards, so that Several different plough configurations hav
it does not fall back into the trench. Under been examined. The principal design problem
the share, and fixed to it, there is a rigid is to configure the shares so that they can
heel. In normal operation, the plough runs be placed over the pipeline without risk of
so that the heel is horizontal, and the damage, so that they can close beneath the
plough is in balance under the combined pipe to excavate a trench under it, and so
action of the soil force on the front of the that the plough can be recovered easily at
share, the reaction under the heel, the pull the end of the operation. A separate paper 7
force at the front end of the beam, and its discusses the alternatives. Ploughs designe
own weight (usually small by comparison with by RJBA adopt a "butterfly" configuration:
the other three forces). If the plough twin half-shares are hinged to the rear end
284

-
--- - - - -- - ,
--- -
---
- - ~ -----
OTC4925 R.J. BROWN AND A.C. PALMER 3

of the beam, are placed over the pipe in an


open position, and rotate and close under The draft increases rapidly with the depth
the pipe as the plough is pulled forward. of trench. In clay, for geometrically
similar trenches, the draft increases
The first application of a post-trenching rougjhly as the quare of the trench depth,
plough was in the Bass Strait in 1979 to while for trenches of constant width the
trench the 24-inch diameter8s~a~Eer draft increases more than linearly with the
pipeline for Esso Australia " The depth. In sand, the draft increases still
success of that operation helped convince more rapidly with trench depth.
operators of the practicability and economy
of ploughing, and led to wider interest. It follows that any plough that cuts a deep
trench in a single pass will necessarily be
Most of the route of the Snapper line was in both large and heavy, and that it will
sand, but the plough had also encountered require a large pull force. Once the pull
limestone, and had trenched through it. A force exceeds 5 MN (500 tonnes), the
substantial length of the route of the North difficulties multiply. Not only does the
Rankin 40-inch gas pipeline, north-west of structural weight of the plough begin to
Australia, crosses limestone and sandstone become excessive, but friction generated by
sea bed, and has to be trenched for the weight itself begins to make a
protection against high currents, and significant contribution to the draft.
against anchors in shallow water. The Because the plough is so heavy, it becomes
mechanics of ploughing rock are o(course difficult to handle. A large barge is
quite different to those of ploughing soil. required to transport it, and a large crane
Excavation in rock proceeds by a succession to lower it safely onto the pipeline. There
of fracture events, in which the rock breaks has to be a strong link between the pough
into large fragments which are then lifted and whatever is pulling it : even allowing
out of the trench by the share. This was rather small factor of safety of 2 on
studied in a major research program at minimum breaking load, a wire rope some 125
Western Australia Institute of Technology, rom (5 inches) in diameter is needed to pull
designed to investigate fracture mechanisms, 5 MN. Finally, the pulling system must be
plough forces, and interactions when soil anchored. If, the plough is pulled by an
and rock are present together. This effort anchored barge, the problems of relocating
culminated in the design of the largest anchors, finding good holding ground, and
plough ever built (Fi~ijre 3), which trenched balancing and controlling mooring line
the North Rankin line in November and tensions become relatively serious if the
December 1982.Woodside Petroleum have stated pull force exceeds 5 MN, whereas a
that the application of the plough to this reqyuirement to anchor against 1 or 2 MN is
project saved A$40 million. commonplace and easily satisfied, in
deep-water laybarge pipe laying for instance
Table I is a list of pipeline trenching
ploughs. Table 2 is a list of submarine All these factors indicate that a deep
pipelines which have been trenched by trench should not be cut in a single pass,
ploughs, and confirms the extent to which but that it will be better to adopt a
the technique has become accepted. The total multi-pass technique, in which the required
volume of trench excavated by trench~ng depth is reached in two or more cuts.
ploughs is approximately 2,000,000 m
This concept appeared at an early stage ~n
MULTI-PASS PLOUGHS plough development, and model experiments
were carried out in 1977. In the first pass
The dimensions of a plough are primarily the trench was cut to a trapezoidal
determined by the depth and cross-section of cross-section, with a level bottom and side
the trench it has to cut. The structural at 30 0 to the horizontal. The shares were
weight is determined both by the size of the then changed, and in the second pass a
plough and the draft, the pull force deeper triangle was cut from the bottom of
required to advance the plough through the the first-pass trench.
bottom soil. The calculation of draft for a
particular trench design is a complex task, It was ultimately decided not to trench th
and a designer applies a combination of pipeline for which the 1977 tests were
dimensional analysis, theoretical soil conducted, and the development was not
mechanics, results of model tests, and - pursued at the time. Subsequent ploughs wer
most importantly - records from field built for single-pass operation, since the
observations of ploughs in actual projects trenches were relatively shallow and the
and trials. Designers and operators of bottom materials not unusually hard. In
ploughs naturally prefer to keep their 1983, however, a study was made of the
methods and databases proprietary. It can possibility of using a plough to trench a
however be said that in almost all types of pipeline between the Gullfaks and Statfjord
soil a trench 2 m deep, cut in a single fields in the North Sea. Geotechnical
pass, will require a ploughing force between investigation had showed the bottom to be
1 MN and 5 MN (100 and 500 tonnes) and that composed of very hard clay, with an
the corresponding plough will weigh at least undr2ined shear strength of more than 400
1.5 MN (150 tonnes). kN/m in some places, covered with a thin
layer of sand, varying from 0.5 m to a few
285

--- -- - -- - '
--- - - --- - ~ -----
cm. A design study showed that rather than to operation of a load-release system
construct a plough which would achieve the designed to protect the plough and its
design trench depth in a single pass along pulling system against high loads. In one
the entire route, it would be more location, a large boulder brought the plou~
economical to provide for multi-pass to a standstill. The plough was recovered,
operation, as an option so that two passes moved across the boulder, and replaced and
could be used in particularly hard areas. restarted 20 m further along the pipeline.

A multi-pass plough has several design The plough had been tested in the
problems not present in a single-pass second-pass mode, and performed well. In t]
plough. The long-beam principle ensures that actual operation on the Gullfaks pipeline,
the plough cuts a trench whose bottom is at however, the specified trench depth was
a fixed distance below the level of the reached in one pass, and a second pass was
leading end of the beam, whose height is in not necessary.
turn controlled by the skids or wheels which
run on the natural sea bed. In other words, The trials confirm the practicability of
the height of the skids is the reference multi-pass ploughing. They open the way to
level for the trench depth. The first pass plough that can cut trenches to any depth,
leaves the spoil piled along the sides of and will at the same time keep the draft al
the trench. A design choice has to be made, weight to an acceptable level.
of the way to support the leading end of the
beam during the second pass. The choices are AN ARCTIC MULTI-PASS PLOUGH
*
1. to run the skids within the trench, Multi-pass ploughs will of course only be
developed if there is a need for them. In
2. to run the skids outside the spoil left most regions where hydrocarbons are product
by the first pass, offshore, pipeline trenching requirements
have been reduced over the years, as
3. to run the skids on the spoil, or satisfactory experience and continued
research have brought operators and
4. to move the spoil from the first pass regulatory authorities to the opinion that
further away before the skids reach it in deep trenching is unnecessary.
the second pass.
There is a different situation in the
Option 3 is impracticable because the spoil Arctic, where pipelines will need to be
is generally uneve-n and soft. Option 1 has trenched to protect them against ice scour
the advantage that the longitudinal profile (and possibly against strudel scour and ict
of the trench is smoother than the original grounding) . The methods of calculating the
profile of the bottom - a consequence of the expected maximum scour depth are
long-beam principle which can be used controversial, and the required trench
advantageously in span correction - but the depths in different areas even more so.
disadvantage that the skids are too close- There is no intention to engage in that
together and have to be relatively small, controversy here. However, it is generally
since they must run in the trench and at the thought that a cover of 3 or 4 m will be
same time leave room for the pipeline. The required in some areas of the Beaufort Sea
plough may then tend to roll, if one and that where iceberg scour is significant.
half-share is moving hrough harder material as in Davis Strait, there may have to be 6
than the other, or if it strikes an or 7 m cover.
obstruction. Option 2 makes the plough very
wide. Multi-pass ploughing is an attractive and
rapid technique for constructing trenches 7
Model tests of a multi-pass plough were this depth, either in a pre-laying or in a
carried out in a clay pit near Temse in post-laying mode. Design studies indicate
Belgium, in January 1984. Initially, the that a 4 m trench will require 2 to 4
plough was made according to option 2, but passes, and a 6 m trench 4 to 8 passes. Tht
it wasfound that stray fragments of clay decisive factor is the geotechnics of the
spoil from the first pass would collect in sea bedm, and site investigation will have
front of the skids and block the cross-beam. to be careful and detailed, though this is
Angled blades were then added to the front of course equally true for any trenching
of the plough, and moved the spoil outwards, technique. The speed of ploughing depends <
so that a clear path was left for the skids. the power of the pulling system, and the
rate at which anchors can be relocated.
After the model tests, the design of the Maximum speeds of 1000 m/hour have been
prototype multi-pass ploough was finalised, achieved, and average speeds can reach 200
using the lessons learned, and the plough m/hour (4.8 km/day) .Most Arctic pipelines
was built in Holland and tested near Tiel in will not need to have deep trenches over
June 1984. Figures 4 and 5 show the plough long distances, because the most severe ic(
during the tests. The 22 km pipeline was scour occurs over a narrow range of water
successfully trenched in July and August. depths, typically 15 to 30 m, and most oil
Boulders produced some difficulties, and led and gas finds to. date are not far from
shore. Consider a hypothetical 30 km
9QC
OTC 4925 R.J. BROWN AND A.C. PALMER
5

to excavate a trench 1.5 m deep and 300 m


pipeline divided into three trenchinq zones, long in 30 minutes. However, that project
as- follows was located in a sheltered bay, in which th
ice was quite smooth, with surface relief.
zone range of design number of ridges and hummocks rarely more than 0.5 m
length water depths trench passes high, and no pressure ridges or large masse
depth of multi-year ice. It was relatively easy t
(km) (m) (m) cut the slot and the hole, and there was
enough depth for the plough to move freely
5 0-1o 2.5 2 under the ice.
15 10 - 30 4.5 4
10 30 - 50 1 1 In the Beaufort Sear ice conditions would
probably be more difficult, with uneven ice
and assume the speed of the plough, and khe pressure ridges, and areas of shallow water
times for deployment and recovery, to be It would then be a harder task to cut a S1O
for the pull cable, though an alternative i
speed ploughing 200 m/hour to select the ice-hole (seal-hole)
speed moving 1000 mlhour technique proposed for ice-based pipeline
deployment 10 hours construction, in which a cable is in ~$;;led
recovery 5 hours under the ice between separate holes
turning in one spot 15 hours problem with all ice-based construction is
that the plough has to be carried across th
The total time depends on the sequence of ice to the starting position, and the ice
trenching. The shortest schedule is 445 has to be strong enough to support the
hours (19 days); plus mechanical and weathe~ plough and its lifting system, and smooth
downtime. Even making a generous allowance enough for the system to move.
for downtime, this is well within the
open-water season in the Beaufort Sea, in Ice-based construction is potentially
any but exceptionally bad ice years, and so attractive, if only because the season of
it would be safe to plan for mobilization strong and stable ice cover is longer and
and completion of trenching in a single more reliable than the open-water season. A
season. choice between ice-based and water-based
construction will depend primarily on the
Any mechanical device that can continuously ice climate.
excavate a trench 4 m deep, on land or at
sear must be large. A plough is no BACKFILLING
exception. Preliminary design estimates are
that the plough would be 45 m long, 25 m When pipeline engineers speak of burial,
broad, and 10 m high, and that it would they generally mean trenching . Trenching
weigh some 3 MN (300 tonnes). This is techniques usually leave the pipeline in an
consistent with the size of major offshore open trench. Ploughing leaves the spoil
equipment, and small by comparison with a neatly piled along the trench sides, rather
cutter-suction dredger or a-mechanical than dispersed into the water. As well as
cutting system able to cut the same trench. eliminating water pollution, this has the
advantage that once trenching is complete- a
There has to be a handling and pulling backfilling device can move along the
system, in addition to the plough itself, trench, to push the spoil back to cover the
and adoption of the multi-pass principle pipeline. In the Arcticr this will protect
keeps down the size of that system. In the the line against ice scour from masses
open-water season, it can be transported by moving along the trench, and from ice
a conventional cargo barge, and handled by z pile-ups and strudel scours over the line.
pull barge which is equipped with a suitabl~
crane. The pull barge is held in position by Model tests have demonstrated that a
mooring lines to anchors, which are backfilled can be constructed on the
progressively relocated byanchor-handling long-beam principle, and that it
tugs . The barge pulls the plough through successfully covers a pipeline.
cables to linear winches. The plough also
carries the monitoring and control system, CONCLUSION
used to follow the operation of the plough
and to control the cutting depth. In the last five years, ploughing has prove
itself as a reliable and economical
An option is to trench in the winter, using technique for trenching pipelines. A
the sea ice as astable working platform. full-scale multi-pass plough has been built
This was the option used in the Drake F-76 and tested. The technology is ready for the
project at Melville Island in 1977, the design and construction of large ploughs to
first and so far only a~p~ication of an cut deep trenches for Arctic offshore
Arctic trenching plough . The plough was pipelines.
lowered through a hole sawed in the sea ice,
which was 2 m thick. A cable was lowered
through a straight slot through the ice
along the pipeline alignment, and a winch or
the ice 1300 m from shore pulled the plough,
j
6 SUBMARINE PIPELINE TRENCHING BY MULTI-PASS PLOWS OTC4925

ACKNOWLEDGEMENT (11) Kaustinen, O.M., Brown, R.J. and


Palmer, A.C. Submarine pipeline
Some of the material presented in this paper crossing of MClure Strait,
formed part of a paper at the 1985 Oil and Proceedings, Seventh International
Gas Pipeline Technology Seminar in Conference on Port and Ocean
Amsterdam. Engineering under Arctic Conditions
[;;;~;nki 1983, VTT Espoo, ~, 289-299
The authors wish to pay tribute to the .
memory of Klaas de Koning, who died in 1984
after a road accident. His energy and
enthusiasm played a major part in the
development of trenching ploughs.

REFERENCES

(1) Hulsbergen, C.H. Stirnulat~d


self-burial of submarme pzpelines ,
Proceedings, Sixteenth Annual Offshore
Technology Conference, Houston, ~,
171-178 (1984).

(2) Van Dongen, F.A. Het ingraven van


onderzeese leidingen , Civiele en
;fi~mdige techniek, (7), 22-26
.

(3) Brown, R.J. and Abel, W. Offloading


line made up onshore, towed to site,
Oil and Gas Journal, 76,(47) 67-72
(1978) .

(4) Brownr R.J. Examining new pipeline


burial methods, Offshore (1978).

(5) Palmer, A.C., Baudais, D.J., and


Masterson, D.M. Design and
installation of a submarine flowline in
the Canadian Arctic Islands ,
Proceedingsr Eleventh Annual Offshore
Technology Conference, Houston, ~,
765-772 (1979).

(6) Palmer, A.C., Kenny, J.P., Perera, M.R.


and Reecer A.R. lDesign and operation
of an underwater pipeline trenching
plough, Geotechnique, ~, 305-322
(1979) .

(7) Brown, R.J. and Palmer, A.C. Progress


in pipeline trenching by ploughing
European Seminar on Offshore Oil and
Gas Pipeline Technology, Amsterdam
(1985) .

(8) Brown, R.J. Post-trenching plow


cuts ditch under offshore line Oil and
Gas Journal, 78, (23) 47-51 (1980).

(9) Brown, R.J.ecent advances in pipeline


stabilization and automated connection
European Seminar on Oil and Gas
Pipeline Technology (1981).

(10) Brown, R.J. Here are the latest


advances in pipeline trenching by
plowing, Oil and Gas Journal, Q, (18)
106-111 (1983).

788
-..
.. . ,. . . . . . . -.. -,. . . . . . . . . . . . . . . -. . . . . . . .

TABLE 1 PIPELINE PLOLXHS

Design
Maximum Line Trench
Reference Year of Current trenching bollard Line Operator Location diameter Length depth Year Plough
number construction Designer owner depth pull (inch) (km) (m) (ref table
(m) (tonnes) 1)

1 1977 RJBA Mobil 1.2 300


StatfjorclA Mobil Norwegian 36 2.2 1.2 1977 1
2 1977 RJBA Panarctic 1.5 50 sector

3 1980 RJBA/ Land & Marine 1.2 200 Drake F-76 Panarc tic Canada 24 0.3 1.5 1978 2
L&14
Snapper Esso Australia 24 37 0.7 1980 5
4 1978 RJBA Esso Australia 0.8 100
West Sole BP UK sector 20 80 1 1981 3
5 1980 RJBA Esso Australia 1.2 220
Central Shell Sarawak 36 70 1.8 1982 7
6 1979 SMD UDI 0.6 ~Ah Luconia

7 1982 RJBA McDermott 1.8 200 lfagnus BP UK sector 6 35 0.5 1982 6

8 1982 RJBA ETPM 2 400 North Renkin tloodside Australia 40 120 2 1982 8

9 1982 RJBA Esso Japan 1.85 300 Whyslla Santos Australia 12 2.4 0.5 1982 4

10 1984 RJBA Stacoil 1.2 200 Ivaki Esso Japan 12 40 1.85 1983 9

11 1984 SMU Brown & Root 1 200 Northern Leg Britoil UK sector 6 11 0.6 1982 6

12 1984 RJBA ETPM 1.5 HA* Highlander Texaco UK sector 14 60 NA 1984 6

13 1984 L&M Land & Marine NA* HA* Statfjord C Mobil Norwegian 12 11 1 1984 11
sector

Gullfaks Statoil Norwegian 14 22 1.2 1984 10


This list does not include about 25 model and test ploughs. sector

* Proprietary or not available Heimdal-Brae Elf Norwegian 8 116 0.9 1985 12


sector

Ula-Cod BP Norwegian 10 26 NA 1985 13


sector
km

200
beam

100


7778
El
8081
u 82838485 year t
heel

Fig. lDevelopment of pipeline trenching by ploughs: lengths of bars in- Fig. 2Long-beam plough.
dicate distance ploughed and numbers above bars indicate
projects.

Fig. 3Post-trenching plough for North Ranldn pipeline,


, Fig. 4Post-trenching plough for Gullfaks pipeline.

/_&i.

Fig. 5Post-trenching plough for Gullfaks pipeline.

You might also like