Professional Documents
Culture Documents
This paper was presented at the 17th Annual OTC in Houston, Texas, May 6-9,1985. The material is subject to correction by the author. Permission to
copy is restricted to an abstract of not more than 300 woras.
- - - - - - -- -- -
- - -
2 SUBMARINE PIPELINE TRENCHING BY MULTI-PASS PLOWS OTC4925
accepted and widely used technique, and in attitude alters, so that it cuts less
many conditions is the method of choice. deeply, the heel loses contact with the
Figure I is a plot of the length of trench bottom, the heel reaction falls to
submarine pipeline ploughed each year since zero, and the share reaction pushes the
1977, and the number of distinct projects share downward so that it cuts more deeply.
each year, and shows the growth in the If, on the other hand, the plough cuts too
acceptance of the plough technique since deeply, the heel itself has to cut the soil
1980. and the heel reaction increases and lifts
the share to reduce the cutting depth.
-
--- - - - -- - ,
--- -
---
- - ~ -----
OTC4925 R.J. BROWN AND A.C. PALMER 3
--- -- - -- - '
--- - - --- - ~ -----
cm. A design study showed that rather than to operation of a load-release system
construct a plough which would achieve the designed to protect the plough and its
design trench depth in a single pass along pulling system against high loads. In one
the entire route, it would be more location, a large boulder brought the plou~
economical to provide for multi-pass to a standstill. The plough was recovered,
operation, as an option so that two passes moved across the boulder, and replaced and
could be used in particularly hard areas. restarted 20 m further along the pipeline.
A multi-pass plough has several design The plough had been tested in the
problems not present in a single-pass second-pass mode, and performed well. In t]
plough. The long-beam principle ensures that actual operation on the Gullfaks pipeline,
the plough cuts a trench whose bottom is at however, the specified trench depth was
a fixed distance below the level of the reached in one pass, and a second pass was
leading end of the beam, whose height is in not necessary.
turn controlled by the skids or wheels which
run on the natural sea bed. In other words, The trials confirm the practicability of
the height of the skids is the reference multi-pass ploughing. They open the way to
level for the trench depth. The first pass plough that can cut trenches to any depth,
leaves the spoil piled along the sides of and will at the same time keep the draft al
the trench. A design choice has to be made, weight to an acceptable level.
of the way to support the leading end of the
beam during the second pass. The choices are AN ARCTIC MULTI-PASS PLOUGH
*
1. to run the skids within the trench, Multi-pass ploughs will of course only be
developed if there is a need for them. In
2. to run the skids outside the spoil left most regions where hydrocarbons are product
by the first pass, offshore, pipeline trenching requirements
have been reduced over the years, as
3. to run the skids on the spoil, or satisfactory experience and continued
research have brought operators and
4. to move the spoil from the first pass regulatory authorities to the opinion that
further away before the skids reach it in deep trenching is unnecessary.
the second pass.
There is a different situation in the
Option 3 is impracticable because the spoil Arctic, where pipelines will need to be
is generally uneve-n and soft. Option 1 has trenched to protect them against ice scour
the advantage that the longitudinal profile (and possibly against strudel scour and ict
of the trench is smoother than the original grounding) . The methods of calculating the
profile of the bottom - a consequence of the expected maximum scour depth are
long-beam principle which can be used controversial, and the required trench
advantageously in span correction - but the depths in different areas even more so.
disadvantage that the skids are too close- There is no intention to engage in that
together and have to be relatively small, controversy here. However, it is generally
since they must run in the trench and at the thought that a cover of 3 or 4 m will be
same time leave room for the pipeline. The required in some areas of the Beaufort Sea
plough may then tend to roll, if one and that where iceberg scour is significant.
half-share is moving hrough harder material as in Davis Strait, there may have to be 6
than the other, or if it strikes an or 7 m cover.
obstruction. Option 2 makes the plough very
wide. Multi-pass ploughing is an attractive and
rapid technique for constructing trenches 7
Model tests of a multi-pass plough were this depth, either in a pre-laying or in a
carried out in a clay pit near Temse in post-laying mode. Design studies indicate
Belgium, in January 1984. Initially, the that a 4 m trench will require 2 to 4
plough was made according to option 2, but passes, and a 6 m trench 4 to 8 passes. Tht
it wasfound that stray fragments of clay decisive factor is the geotechnics of the
spoil from the first pass would collect in sea bedm, and site investigation will have
front of the skids and block the cross-beam. to be careful and detailed, though this is
Angled blades were then added to the front of course equally true for any trenching
of the plough, and moved the spoil outwards, technique. The speed of ploughing depends <
so that a clear path was left for the skids. the power of the pulling system, and the
rate at which anchors can be relocated.
After the model tests, the design of the Maximum speeds of 1000 m/hour have been
prototype multi-pass ploough was finalised, achieved, and average speeds can reach 200
using the lessons learned, and the plough m/hour (4.8 km/day) .Most Arctic pipelines
was built in Holland and tested near Tiel in will not need to have deep trenches over
June 1984. Figures 4 and 5 show the plough long distances, because the most severe ic(
during the tests. The 22 km pipeline was scour occurs over a narrow range of water
successfully trenched in July and August. depths, typically 15 to 30 m, and most oil
Boulders produced some difficulties, and led and gas finds to. date are not far from
shore. Consider a hypothetical 30 km
9QC
OTC 4925 R.J. BROWN AND A.C. PALMER
5
REFERENCES
788
-..
.. . ,. . . . . . . -.. -,. . . . . . . . . . . . . . . -. . . . . . . .
Design
Maximum Line Trench
Reference Year of Current trenching bollard Line Operator Location diameter Length depth Year Plough
number construction Designer owner depth pull (inch) (km) (m) (ref table
(m) (tonnes) 1)
3 1980 RJBA/ Land & Marine 1.2 200 Drake F-76 Panarc tic Canada 24 0.3 1.5 1978 2
L&14
Snapper Esso Australia 24 37 0.7 1980 5
4 1978 RJBA Esso Australia 0.8 100
West Sole BP UK sector 20 80 1 1981 3
5 1980 RJBA Esso Australia 1.2 220
Central Shell Sarawak 36 70 1.8 1982 7
6 1979 SMD UDI 0.6 ~Ah Luconia
8 1982 RJBA ETPM 2 400 North Renkin tloodside Australia 40 120 2 1982 8
9 1982 RJBA Esso Japan 1.85 300 Whyslla Santos Australia 12 2.4 0.5 1982 4
10 1984 RJBA Stacoil 1.2 200 Ivaki Esso Japan 12 40 1.85 1983 9
11 1984 SMU Brown & Root 1 200 Northern Leg Britoil UK sector 6 11 0.6 1982 6
13 1984 L&M Land & Marine NA* HA* Statfjord C Mobil Norwegian 12 11 1 1984 11
sector
200
beam
100
7778
El
8081
u 82838485 year t
heel
Fig. lDevelopment of pipeline trenching by ploughs: lengths of bars in- Fig. 2Long-beam plough.
dicate distance ploughed and numbers above bars indicate
projects.
/_&i.