The burner is secured on the boiler with
the flange supplied. Holes are drilled as
shown in the drawing. The flange gasket
can be used as a template.
Mount the flange and its gasket on the
boiler. Check for leaks.
The burner is installed in position 1.
If necessary, it may be installed in
position 2 or 3.
Electrical connection
The electrical setup and the burner
connection must be performed in
compliance with the standards in force.
The burner is supplied with a 7 pin male
connector, to which the single-phase
230V-50Hz power supply with earth and
the thermostat are connected (diagram
opposite).
NB: External connection of an alarm
between S3 and N and an hour meter
between B4 and N.
- Rating of the protective fuse: 6.3A
- Conductor section: 1.5 mm2