You are on page 1of 3

Membrane System

Model RO, SeaPRO-16,45K,380,TC, AB


Part Number 1267712

Performance Data
_____________________________________________________________
Design Permeate Flow 40 gpm
Feed Flow 114 gpm
Concentrate Feed Flow 74 gpm
Recovery 35 %
Design Temperature 25 C
Design pH 5.5
System Inlet Pressure 30 psi
System Operating Pressure 950 psi
Minimum Inlet Pressure 30 psi

Components
_____________________________________________________________
Cartridge Filtration
Housing Quantity
Housing Model, Manufacturer 40EFCS4-3150
Cartridge Filter Model RO.Zs 05-40,Eden Excel
Filter Quantity 10
TIES of Filter 40
Membrane Element Housings
Membrane Housing Model PRO-8-1200-SP-4
Housing Manufacturer Protec or Equal
Number of Housings 4
Housing length 4
Housing Diameter 8
Banking Arrangements 4, parallel
High-Pressure Pump
Model MSS 2030
Manufacturer Fedco
Quantity 1
Motor Hp and Type 75
Ro Pump Motor Type TEFC
Membrane Elements
Model AD-400
Manufacturer GEWPT
Quantity 16

____________________________________________________________________________________________
Rev: 1.0, Presentation Date: Sep 6,2017 Valid until: Nov 5,2017
GE Confidential and Proprietary Information - The information contained in this document is submitted for evaluation
by Customer only. Customer agrees not to reveal its contents except to those in Customer's organization necessary
for evaluation. Copies of this document may not be made without the prior written consent of GE Management. If the
preceding is not acceptable to Customer, this document shall be returned to GE.
Membrane Type TFC (Polyamide)

Material of Constructions
_____________________________________________________________
Filter Housing FRP
Feedwater Piping Schedule 80, PVC
High-Pressure Piping
Permeate Piping Schedule 80, PVC
Frame Epoxy-coated carbon steel
Membrane Element Housings FRP,
Perm Plumb Schedule 80, PVC
Filter Model RO.Zs 05-40,Eden Excel

Installation and Utility Requirements


_____________________________________________________________
Inlet 3
Permeate 1.5
Concentrate 2
Inlet Water Pressure 30 psi
Drain to be Sized for 114 gpm
Power Hp
Motor Power 380VAC, 3-phase, 50Hz
Control Circuit 220V, 1-phase, 50Hz
Skid (H X W X D)
Shipping Weight Estimate lbs
Membrane Skid Weight 4000 lbs

Controls / Electrical Systems


_____________________________________________________________
Processor A-B Micrologix 1200
Enclosure NEMA 4, 48x36x12 Painted Carbon Steel

____________________________________________________________________________________________
Rev: 1.0, Presentation Date: Sep 6,2017 Valid until: Nov 5,2017
GE Confidential and Proprietary Information - The information contained in this document is submitted for evaluation
by Customer only. Customer agrees not to reveal its contents except to those in Customer's organization necessary
for evaluation. Copies of this document may not be made without the prior written consent of GE Management. If the
preceding is not acceptable to Customer, this document shall be returned to GE.
Instrumentation
_____________________________________________________________
Instrument Manufacturer Location
Flow Meters Signet Permeate, concentrate
Pressure Switch Feed, permeate, concentrate
Pressure Gauge
Conductivity Temp. Thornton Permeate
pH Meter Thornton

Membrane System Alarms


_____________________________________________________________

Features Included
_____________________________________________________________
5-micron pre-filter
Automatic inlet shut-off valve
Low pressure feed flush
Remote machine on/off capability
Thermal motor protection
Pre-filter, post-filter, primary, and final pressure gauges
Flow control center including concentrate and recycle valves
Digital conductivity meter

Note: Please consult with GE Water if the feed water to the RO system has a concentration more than 350 mg/l
of chloride as ion to verify the materials of construction proposed have adequate corrosion resistance. Please
provide minimum, maximum, and average levels of Chloride, Sulphate, pH, and Temperature of the feedwater
solution.

____________________________________________________________________________________________
Rev: 1.0, Presentation Date: Sep 6,2017 Valid until: Nov 5,2017
GE Confidential and Proprietary Information - The information contained in this document is submitted for evaluation
by Customer only. Customer agrees not to reveal its contents except to those in Customer's organization necessary
for evaluation. Copies of this document may not be made without the prior written consent of GE Management. If the
preceding is not acceptable to Customer, this document shall be returned to GE.