You are on page 1of 5

CALENDARIO DE AVANCE DE OBRA VALORIZADO ACTUALIZADO

L.P. N :009-2010/GR.PIURA-GGC.GRI
OBRA: "AMPLIACION Y MEJORAMIENTO INTEGRAL DE LOS SERVICIOS DE SALUD EN ESTABLECIMIENTO DE SALUD
MARA GORETI DEL DISTRITO DE CASTIILLA - PIURA
CONTRATISTA
: CONSORCIO MARA GORETI
SUPERVISA:ING JIMMY GONZALES BARN
ENTIDAD : GOBIERNO REGIONAL DE PIURA
FECHA : MARZO DE 2011
FECHA DE INICIO CONTRACTUAL : 19/02/2011
FECHA DE TRMINO CONTRACTUAL : 18/07/2011
PLAZO DE EJECUCIN CONTRACTUAL : 150 D.N

ITEM ACTIVIDAD PRESUPUESTO 1 MES 2 MES 3 MES


CONTRATADO 19 FEB.-11 01-31 Mar-11 01-30 Abr.-11
(10 das) (31das) (30das)
I ESTRUCTURAS 598086.88 42716.86 175279.65 224720.09
II ARQUITECTURA 534909.88 0.00 83162.94 176470.74
III INSTALACIONES SANITARIAS 50704.39 119.22 6488.06 15851.13
IV INSTALACIONES ELECTRICAS 397420.22 0.00 39742.01 96043.22
V MEDIA TENSION 64712.22 10785.37 34513.18 19413.57
COSTO DIRECTO 1645833.59 53621.45 339185.84 532498.75
GASTOS GENERALES (12.00%) 197500.03 6434.57 40702.30 63899.85
UTILIDAD (10.00%) 164583.36 5362.15 33918.58 53249.88
EQUIPAMIENTO 975137.14
SUB-TOTAL 2983054.12 65418.17 413806.72 649648.48
I.G.V. (19%) 566780.28 12429.45 78623.28 123433.21
TOTAL 3549834.40 77847.62 492430.00 773081.69
AVANCE MENSUAL (%) 2.19 13.87 21.78
AVANCE ACUMULADO (%) 2.19 16.06 37.84

CALENDARIO ACELERADO VALORIZADO DE AVANCE DE OBRA

L.P. N :009-2010/GR.PIURA-GGC.GRI
OBRA: "AMPLIACION Y MEJORAMIENTO INTEGRAL DE LOS SERVICIOS DE SALUD EN ESTABLECIMIENTO DE SALUD
MARA GORETI DEL DISTRITO DE CASTIILLA - PIURA
CONTRATISTA
: CONSORCIO MARA GORETI
SUPERVISA:ING JIMMY GONZALES BARN
ENTIDAD : GOBIERNO REGIONAL DE PIURA
FECHA : MARZO DE 2011
FECHA DE INICIO CONTRACTUAL : 19/02/2011
FECHA DE TRMINO CONTRACTUAL : 18/07/2011
PLAZO DE EJECUCIN CONTRACTUAL : 150 D.N

ITEM ACTIVIDAD PRESUPUESTO 1 MES 2 MES 3 MES


CONTRATADO 19 FEB.-11 01-31 Mar-11 01-30 Abr.-11
(10 das) (31das) (30das)
I ESTRUCTURAS 598086.88 0.00 217996.51 224720.09
II ARQUITECTURA 534909.88 0.00 83162.94 176470.74
III INSTALACIONES SANITARIAS 50704.39 0.00 6607.28 15851.13
IV INSTALACIONES ELECTRICAS 397420.22 0.00 39742.01 96043.22
V MEDIA TENSION 64712.22 0.00 45298.55 19413.57
COSTO DIRECTO 1645833.59 0.00 392807.29 532498.75
GASTOS GENERALES (12.00%) 197500.03 0.00 47136.87 63899.85
UTILIDAD (10.00%) 164583.36 0.00 39280.73 53249.88
EQUIPAMIENTO 975137.14
SUB-TOTAL 2983054.12 0.00 479224.89 649648.48
I.G.V. (19%) 566780.28 0.00 91052.73 123433.21
TOTAL 3549834.40 0.00 570277.62 773081.69

AVANCE MENSUAL (%) 0.00 16.06 21.78


AVANCE ACUMULADO (%) 0.00 16.06 37.84
ZADO ACTUALIZADO

ECIMIENTO DE SALUD

4 MES 5 MES 6 MES


01-31 May.-11 01-30 Jun.-11 01-18 jul.-11
(31das) (30 das) (18 das)
155370.28 0.00 0.00
147372.69 102012.83 25890.72
16413.13 9303.48 2529.37
102666.89 96043.23 62924.87
0.00 0.00 0.00
421822.99 207359.54 91344.96
50618.76 24883.14 10961.40
42182.30 20735.95 9134.50
975137.14
514624.05 252978.64 1086577.99
97778.57 48065.94 206449.82
612402.62 301044.58 1293027.81
17.25 8.48 36.43
55.09 63.57 100.00

AVANCE DE OBRA

ECIMIENTO DE SALUD
4 MES 5 MES 6 MES
01-31 May.-11 01-30 Jun.-11 01-18 jul.-11
(31das) (30 das) (18 das)
155370.28 0.00 0.00
147372.69 102012.83 25890.72
16413.13 9303.48 2529.37
102666.89 96043.23 62924.87
0.00 0.00 0.00
421822.99 207359.54 91344.96
50618.76 24883.14 10961.40
42182.30 20735.95 9134.50
975137.14
514624.05 252978.64 1086577.99
97778.57 48065.94 206449.82
612402.62 301044.58 1293027.81

17.25 8.48 36.43


55.09 63.57 100.00
21-Mar
10-Jul 12-Aug