PARTIDA: ESTRUCTURAS
LOSA DE TECHO Y LOSA DE ENTREPISO

Ingeniera Civil Instituto Tecnolgico de Oaxaca (ITO)


[Administracin de la construccin]

CONCRETO
El concreto se cuantificar de acuerdo a la siguiente tabla tomada del manual de ingeniera de
costos en la construccin por el Dr. Enrique Oscar Yescas Nocedal:

Tomaremos el de fc= 250 kg/cm2 de acuerdo al plano y comenzamos a cuantificar:

PRIMER PLANTA
= 41.78 0.10 = .
2

Multiplicamos cada cantidad por nuestro volumen

CEMENTO
= 0.4 4.178 = 1.67123
ARENA
= 0.5 4.178 = 2.089 3
GRAVA
= 0.595 4.178 = 2.48591 3
AGUA
= 0.194 4.178 = 0.810532 3

SEGUNDA PLANTA
= 17.286375 0.10 = .
CEMENTO
= 0.4 1.72873 = 0.6914553
ARENA
= 0.5 1.72873 = 0.3457 3
GRAVA
= 0.595 1.72873 = 0.2057 3
AGUA
= 0.194 1.72873 = 0.0399 3

Ingeniera Civil Instituto Tecnolgico de Oaxaca (ITO)


[Administracin de la construccin]

DESPERDICIO
A cada resultado le aplicaremos el 2% de desperdicio de acuerdo a lo indicado en la siguiente
tabla tomada del manual de ingeniera de costos en la construccin por el Dr. Enrique Oscar
Yescas Nocedal:

PRIMER PLANTA
CEMENTO
= 0.4 4.178 = 1.67123 . = 1.7046 3
ARENA
= 0.5 4.178 = 2.089 3 . = 2.13083
GRAVA
= 0.595 4.178 = 2.48591 3 . = 2.53563
AGUA
= 0.194 4.178 = 0.810532 3 . = 0.82673

Ingeniera Civil Instituto Tecnolgico de Oaxaca (ITO)


[Administracin de la construccin]

SEGUNDA PLANTA

CEMENTO
= 0.4 1.72873 = 0.691455 3 . = 0.7053 3
ARENA
= 0.5 1.72873 = 0.3457 3 . = 0.3526 3
GRAVA
= 0.595 1.72873 = 0.2057 3 . = 0.2098 3
AGUA
= 0.194 1.72873 = 0.0399 3 . = 0.0407 3

Ahora hacemos sumatoria de los materiales de las dos plantas y obtenemos las cantidades de
materiales que se necesitan para elaborar un concreto para la casa habitacin indicada en el
plano anterior.

Nuestros resultados quedan de la siguiente manera:

PRIMER PLANTA + SEGUNDA PLANTA

CEMENTO
1.7046 + 0.7053 = .
ARENA
2.13083 + 0.3526 3 = .
GRAVA
2.53563 + 0.2098 3 = ,
AGUA
0.82673 + 0.0407 3 = .

Ingeniera Civil Instituto Tecnolgico de Oaxaca (ITO)


[Administracin de la construccin]

ACERO DE REFUERZO

Ahora vamos a calcular el acero de refuerzo que se necesita para construir la losa de
techo y la losa de entrepiso con las medidas indicadas en el plano anteriormente visto.

Para poder calcular el acero debemos de tener algunas consideraciones imprescindibles como
es la manera del armado ya sea en un sentido o en dos sentidos, el peso de las varillas y el
clculo de longitud real de las varillas el anlisis fue transcrito y resumido por el Dr. Enrique
Oscar Yescas Nocedal del manual de ingeniera de costos en la construccin.

Ingeniera Civil Instituto Tecnolgico de Oaxaca (ITO)


[Administracin de la construccin]

FORMULAS PARA VARILLAS


Despus de un anlisis el Dr. Propone frmulas para generar la longitud de las varillas
teniendo ciertas consideraciones y restricciones.

= + 0.17

= + 0.21


= + 0.4
4


0.15

SENTIDO DEL ARMADO


Para determinar si el armado de la losa ser de un sentido o de dos sentidos lo indicara la
siguiente formula:


< 1.5

O bien


> 1.5

Ingeniera Civil Instituto Tecnolgico de Oaxaca (ITO)


[Administracin de la construccin]

CUANTIFICACIN DE ACERO
Comenzamos a cuantificar de acuerdo a lo visto anteriormente. Para ser referencia
utilizaremos nmeros y ejes para identificar el tramo que se cuantificar:

1 PLANTA

(1)
Ejes (A-C) (1-3)

Lado A-C (3.2 m)


=
4.15 + 0.17 =
4.32 15 = 64.8

= 4.15 + 0.21 = 4.36 15 =


65.4

=
. .
+
4
0.4 = 1.4 30 = 42

Lado 1-3 (4.15 m)


= 3.2 + 0.17 = 3.37 23 = 77.51
= 3.2 + 0.21 = 3.41 23 = 78.43
3.20.15
= ( 4 ) + 0.4 = 1.1625 40 = 53.475

De las longitudes = 381.615m

Ingeniera Civil Instituto Tecnolgico de Oaxaca (ITO)


[Administracin de la construccin]

(2)
Ejes (3-4) (A-D)
.
Lado A-D (5.35 m) en un sentido debido a ( ) > 1.
= 2 + 0.17 21 = 45.57
= 2 + 0.21 = 2.21 21 = 46.41
2.15
= ( 4 ) + 0.4 = 0.8625 42 = 36.225

= .
(3)
Ejes (2-3) (C-D)

Lado 2-3 (1.65 m)


= 2.15 + 0.17 = 2.32 7 = 16.24
= 2.15 + 0.21 = 0.36 7 = 16.52
2.150.15
= ( 4 ) + 0.4 = 0.9 14 = 12.6
Lado C-D (2.15m)
= 1.65 + 0.17 = 1.82 9 = 16.38
= 1.65 + 0.21 = 1.86 9 = 16.74
1.650.15
= ( 4 ) + 0.4 = 0.775 18 = 13.95
= .

(4)
Ejes (2-4) (D-E)

Lado 2-4 (2m + 1.65 = 3.65 m)


= 3.5 + 0.17 = 3.67 15 = 55.05
= 3.5 + 0.21 = 3.71 15 = 55.65
3.50.15
= ( 4 ) + 0.4 = 1.2375 30 = 37.125
Lado D-E (3.5)
= 3.65 + 0.17 = 3.82 15 = 57.3
= 3.65 + 0.21 = 3.86 15 =
57.9
3.650.15
= ( 4 ) + 0.4 = 1.275 30 = 38.25
= .

Ingeniera Civil Instituto Tecnolgico de Oaxaca (ITO)


[Administracin de la construccin]

SEGUNDA PLANTA

(5)
Ejes (2-3) (C-D)

Lado 2-3 (1.65 m)


= 2.15 + 0.17 = 2.32 7 = 16.24
= 2.15 + 0.21 = 0.36 7 = 16.52
2.150.15
= ( 4 ) + 0.4 = 0.9 14 = 12.6
Lado C-D (2.15m)
= 1.65 + 0.17 = 1.82 9 = 16.38
= 1.65 + 0.21 = 1.86 9 = 16.74
1.650.15
= ( 4 ) + 0.4 = 0.775 18 = 13.95
= .

(6)
Ejes (2-4) (D-E)

Lado 2-4 (2m + 1.65 = 3.65 m)


= 3.5 + 0.17 = 3.67 15 = 55.05
= 3.5 + 0.21 = 3.71 15 = 55.65
3.50.15
= ( 4 ) + 0.4 = 1.2375 30 = 37.125
Lado D-E (3.5)
= 3.65 + 0.17 = 3.82 15 = 57.3
= 3.65 + 0.21 = 3.86 15 =
57.9
3.650.15
= ( 4 ) + 0.4 = 1.275 30 = 38.25
= .

Ingeniera Civil Instituto Tecnolgico de Oaxaca (ITO)


[Administracin de la construccin]

3
= . 3 ( ")
8

( )

A continuacin sacaremos el peso de acero por metro cuadrado, para ello necesitamos saber
cunto pesa una varilla comercial del N 3.

3
2 =


1297.23 0.557
2
= 2
= 11.9797 2
60.315
Mas desperdicio:

11.9797 1.07 = .
2

AMARRES (alambre recocido del N 18)


Siguiendo el orden de construccin y colocacin de las varillas cuantificamos los amarres en
cada cruce de varillas; primero se colocan las varillas corridas en ambos sentidos y se amarran
en cada cruce

Ingeniera Civil Instituto Tecnolgico de Oaxaca (ITO)


[Administracin de la construccin]

(1) Varilla corrida: En la seccin de cuantificacin de acero en el claro (1) obtuvimos la


cantidad de 23 varillas en el lado largo por 15 en el corto; 23 * 15 = 345 amarres en
varillas corridas en el claro (1)

Varilla columpiada: Entre cada varilla recta y justo a la mitad omitiendo los extremos
se coloca un columpio en ambos sentidos y se amarran en sus cruces (columpios con
corridas). Se obtuvo la cantidad de 22 varillas a lo largo y 14 en lo corto; 22 * 14 = 308
amarres

Bastones: dado que los bastones van arriba de las varillas corridas se podra decir que
es el doble ya que estn en la parte superior y en la parte inferior. Por lo tanto hay 30
bastones;

Nuestros datos arrojaron que tenemos 23 varillas en el lado largo y 15 en el lado corto,
por lo tanto: 23 * 15 = 345 amarres de varillas columpiadas. As sucesivamente con
todos los claros.
Hay otros autores que les dan un 30% de alambre recocido al total de kg/cm2 de acero
Quedando de la siguiente manera:

12.8182 30% = 16.6637

Ingeniera Civil Instituto Tecnolgico de Oaxaca (ITO)


[Administracin de la construccin]

CIMBRA
Ahora comenzamos a generar la cimbra u obra falsa que lleva para poder colar la losa
Para ello debemos tener las siguientes consideraciones:

Medidas de la duela: 2.5m x .10m x 2.5


Lo que nos interesa es saber el rea de contacto de la duela que es 2.5 x .10 = 0.25

Duela
1ER PLANTA
rea /rea de la duela= piezas de duela
36.0025/0.25= 144.01 pzas de duela
+ Permetro/ longitud de la duela = pzas de duela en permetro
27.25/2.5= 10.9 pzas de duela

2DA PLANTA
rea /rea de la duela= piezas de duela
16.3225/0.25 = 65.29 pzas de duela
+ Permetro/ longitud de la duela = pzas de duela en permetro
19.05/2.5=7.62
Ahora sumamos todas las piezas y obtendremos las piezas comerciales
227.82 pzas de duela comercial

Poln
1ER PLANTA
Los polines se colocan 4 por cada metro cuadrado y la formula es la siguiente
(lado de la loza +1)(lado de la losa+1)=cantidad de piezas de poln comercial

Es decir, si nuestra losa es de 3 * 4, aplicamos la frmula de la siguiente manera

(3+1)*(4+1)= 20 polines

En nuestro caso nuestra losa de la primer planta es 9 *6.3 con vacos, es decir,
(3.2*6.3) + (2.150*1.65) + (3.5*3.65) y a cada claro le aplicamos la formula:
4.2*7.3 30 polines
+ 3.15*2.65 8 polines
+ 4.5*4.65 21 polines
La sumatoria es = 59 polines de la planta de abajo

2DA PLANTA
En nuestro caso nuestra losa de la segunda planta es 5.8*3.8 con vacos, es decir
(2.3*1.8) + (3.5*3.8) y a cada claro aplicamos la formula:
3.3*2.89 polines
4.5*4.8 22 polines
La sumatoria es = 31 polines de la planta de arriba
Ahora sumamos los polines de las dos plantas
59+31=90 pzas de polines comerciales

Ingeniera Civil Instituto Tecnolgico de Oaxaca (ITO)