Risk Evaluation Grid

Project Name: Coupon Authentication


Prepared by: Sandeep Kumar Konda
Date: 7/20/2016
Risk
Identified Impact Probability Mitigation
Impact on Project priority
Risk rating of occurring action
number
A B AxB
Attainability of system to Results in the failure of 4 0.9 3.6 Publicity for the program have to be done in a
customers the project diversified manner

Updating the customers Improper offers to the 3 0.3 0.9 Improving the information in the hourly bases
purchases customer and attaining the data to the database

Training the employees Lack of training results in 2 0.2 0.4 Proper training to employees on updated system
the wrong handling of with developers and senior employees
system
Failure to manage end-user Medium 1 0.03 0.03 Work on the updates and look for best
expectations alternative