Tunnel Formwork Technology

Jumeirah Palm Island Tunnel, Dubai,


United Arab Emirates

PERI Formwork Technology for Tunnel Construction

Technique
References

Edition 04/2010

PERI GmbH
Formwork Scaffolding Engineering
P.O. Box 1264
89259 Weissenhorn / Germany
Phone: +49 (0)7309.950-0
Fax: +49 (0)7309.951-0
info @peri.com
www.peri.com

Without exception, all current safety regula


tions must be observed in those countries
where our products are used.

The photographs in this handbook show situa-


tions on various construction sites taken at a
particular moment. Therefore, safety aspects or
anchor details are not to be taken as a defini
tive guide to the way the equipment is to be
used. Safety instructions and load specifica-
tions are to be strictly observed at all times.

Separate structural calculations are required for


any deviations from the standard design data.

We reserve the right to make technical changes.


Copyright by PERI GmbH

10129900_Peri_Tunnel_001.indd 1 20.03.12 11:35


Content

4 Introduction into Cut-and-cover construction: Cross- Cut-and-cover construction: Cross-


tunnelling technique sections built separately sections built semi-monolithically

7 Cut-and-cover construction 48 Tunnel Zwickau, Bottom plate concreted in advance,


Germany walls and slab cast as a single unit
8 Cross-sections built separately
50 Neu-Ulm 21 railway project, Neu-Ulm, 68 Tunnel Limerick,
10 Cross-sections built semi-monolithically Germany Ireland

14 Cross-sections built monolithically 52 Tunnel Kreuzstrae, Tuttlingen, 70 Neulustheim Tunnel, Munich,


Germany Germany
18 Cover building method
56 Windshear Wind Tunnel, Concord, 72 Istra Tunnel, Boljunsko Polje,
20 Mining construction USA Croatia

22 Deviations from the standard 58 Troja Tunnel, Prague, 74 Laliki road tunnel,
cross-section Czech Republic Poland

24 Transfer point from the tunnel to the 60 Wolfsgruben Tunnel, St. Anton, 78 Reinertshof Tunnel, Fssen,
above-ground area Austria Germany

26 Gallery structures 62 Jumeirah Palm Island Tunnel, Dubai, 80 Green bridge on the A96
United Arab Emirates inGebrazhofen,
Germany
28 PERI systems and experience 66 Underground railway station at
in tunnel construction Mricz Zsigmond Square, Budapest, 82 Environmental protection tunnel
Hungary inStetten,
30 The VARIOKIT Engineering Austria
construction kit
86 DAreuse Motorway Tunnel,
34 The tunnel waler system Switzerland

35 Telescopic steel formwork carriage

36 Proven tunnel construction details


andtechniques

40 Ensuring the durability of the tunnel


Tunnel Diez S 060,
construction
New railway line Cologne Rhine/Main Tunnel Plaunscher Grund, Dresden

44 Process for reducing construction times

10129900_Peri_Tunnel_002-003.indd 1 20.03.12 11:31


88 Railway tunnel in Vranany, Cut-and-cover construction: Mining method
Czech Republic Monolithic construction of the
cross-section 136 Savio railway tunnel, Helsinki,
90 Erstfeld Tunnel, Finland
Gotthard Base Tunnel North Portal, 118 resund Tunnel,
Switzerland Denmark Sweden 138 Losenberg Tunnel, Bigge-Olsberg,
Germany
92 Warnow Crossing, Rostock, 122 Tunnel under Vltava river, Prague,
Germany Czech Republic 140 Detour tunnel, Sotchi,
Russia
96 A100 motorway tunnel, Berlin, 124 Lsslingen Tunnel, Solothurn,
Germany Switzerland 142 Railway tunnel, Penalva,
Portugal
98 Somosierra Pass Tunnel, 126 Tunnel near Zwickau,
Spain Germany 144 Huesca Tunnel,
Spain
100 NDIA Midfield Tunnel, Doha,
Qatar Cover building method 146 Flelen Tunnel,
Switzerland
102 RAV Tunnel, Vancouver, 128 Audi Tunnel, Ingolstadt,
Canada Germany 148 Tunnel Mosty u Jablunkova,
Czech Republic
104 Denkendorf Tunnel, 130 Underground railway extension,
Germany Vienna, Austria 150 Santiago de Chile underground
railway, Chile
106 Sewage canals, 132 Bayview Station, Toronto,
Germany, Spain and South Africa Canada 152 Torcaz railway tunnel,
Subtramo Madrid Zaragoza,
Spain
Bottom plate and walls cast as a sin-
gle unit, slab concreted afterwards 154 Odelouca Tunnel, Serra de Monchique,
Portugal
108 City Tunnel Malm,
Sweden 156 Haiku and Halavawa tunnel project,
Hawaii, USA
110 B311 bypass, Ertingen,
Germany 157 Landfill inspection tunnel Klliken,
Switzerland
112 Eching am Ammersee
noise protection tunnel,
Germany Adresses

114 Schleifenstrasse Tunnel, Augsburg, 158 PERI International


Germany

10129900_Peri_Tunnel_002-003.indd 2 20.03.12 11:31


About this book Introduction into tunnelling technique

This technical book provides an Tunnel construction then and now


overview of different tunnel design
and construction techniques. Ancient civilisations constructed under- traffic routes over the following centuries.
Formwork, scaffolding systems, ground tunnels and defensive structures Tunnels were constructed in those days to
technical aspects and details of thousands of years ago. For example, overcome mountain ranges and straighten
underground construction tech- underground aqueducts were constructed the traffic routes. In the present day, the
niques are illustrated. The second around 2,800 BC in what is now Iran. This requirements also include traffic calming,
part of this book introduces a was later followed by the construction of noise protection and land reclamation.
number of international projects canals and alpine transit tunnels. Thishas extended the definition of tunnel
that have used PERI systems and construction to include green bridges and
engineering services. Mining pro- In the second century AD, especially the portals for ensuring freedom of movement
cedures using sprayed concrete Romans pushed progress in aqueduct and for wild animals.
slabs or prefabricated segments tunnel construction. They created an aque-
(tubbings) are not described here. duct network over large parts of Europe The increasing demands on tunnel struc-
andthe Orient. Examples of this are the tures have also increased the demands
Eifel water supply to Cologne and the water placed on the engineers. The ever present
supply to Side in Turkey, both of which dangers during construction and daily use
werebuilt in the third century AD. New have lead to the development of a number
techniques for open and closed (in those of different construction methods for differ-
times the cladding of mining tunnels) ent construction designs. This has resulted
excavation of tunnels were developed in commercially viable supporting systems
andused even in these early days. that can guarantee safe use of a tunnel for
a calculated service life of over 100 years.
The advent of railway construction in the This includes the required density of the
17th and 18th centuries, and the rapid structure, which greatly influences the con-
development of transportation systems struction method and the type of formwork
demanded constant improvements in the used.

Grotto of Pausilippo near


Naples without formwork
in a stable tuff mountain,
40-86 BC

10129900_Peri_Tunnel_004-045.indb 4 20.03.12 11:27


Tunnel construction techniques

The construction technique is a general


description of the arrangement of the con-
struction elements. In tunnel construction
this depends on the accessibility of the
construction site.

If the tunnel is constructed in an open ditch


that is later covered with soil, then this is
described as an open construction tech-
nique. With cut-and-cover construction, the
tunnel slab is concreted after the excavation
walls have been installed and the tunnel
excavation then progresses underneath this
slab. The mining construction technique
describes the excavation of a tunnel com-
pletely underground.

Neu-Ulm 21 railway project,


Neu-Ulm, Germany

Construction process

The construction process or construction of the tunnel, the amount of material to be is finished or monolithically constructing the
method describes the procedures and work- excavated and the geological conditions over bottom plate and walls and then concreting
ing methods for constructing a tunnel. It the length of the tunnel. the slab after this. Monolithic construction
defines the individual construction steps and ofatunnel means casting the bottom plate,
the components that are separated from each A distinction is made between separate walls and slab formwork as a single unit.
other by concrete seams. casting, semi-monolithic and monolithic
construction.
The definition of the construction process
alsodefines the type of formwork system In the separate casting process the bottom
required. This is a decisive criterion for deter- plate, walls and slab are individually concret-
mining the economic viability of the tunnel ed, one after another. Semi-monolithic con-
construction. The major factors influencing struction means either concreting the walls
theconstruction process are the total length and slab in a single cast after the bottom plate

10129900_Peri_Tunnel_004-045.indb 5 20.03.12 11:27


Introduction into tunnelling technique

Supporting frameworks in tunnel


construction Trough structure

Regardless of the construction process, a


number of different supporting frameworks
can be used depending on the geological
conditions and the future use of the tunnel.
The usual forms are rectangular, round,
ovoidor a special cross-section. Each tunnel
framework can be single-cell or multi-cell.

6.76
0.90 0.90
9.50

Arched tube

0.90
8.68
7.95

10.80
1.00 14.30 1.00

Rectangular cross-section 9.70


0.85
5.71

10129900_Peri_Tunnel_004-045.indb 6 20.03.12 11:27


Cut-and-cover construction and associated construction methods
Economical when good accessibility is available

In the cut-and-cover construction technique The wall formworks used are normally The separate casting method is used for
an open ditch is first excavated and the tun- designed for a fresh concrete pressure of tunnels with minimum waterproofing require-
nel is then constructed in the ditch. After 60 kN/m and the slab formworks are ments and also for short tunnels. The advan-
this the working area is filled and the con- designed for the formwork self-weight and tage of this method lies in the economical
struction isburied. wet concrete load and live load. Depending useof standard formwork and scaffolding
on the manufacturing process used, the systems. The formwork can also be easily
Depending on the manufacturing method cut-and-cover construction method requires adjusted to suit variable tunnel geometries
and formwork used, rectangular cross- a construction ditch at least as large as the (e.g. height and width, curve radius, road
sections with one or more pipes, vaults, tunnel and an appropriately large area for inclination). The major disadvantage is the
galleries, ditches, supporting walls and temporary storage ofthe filling material. relatively large area required in the direction
portals are built, each of which having a ofthe tunnel due to the expansive nature of
continuous bottom plate or a foundation. the construction site.

10129900_Peri_Tunnel_004-045.indb 7 20.03.12 11:28


Cut-and-cover construction cross-sections built separately
Bottom plate, walls and slab sequentially concreted
on top of each other

In this construction method the three main


elements of the tunnel cross-section bot- Guideline values for using the process
tom plate, walls and slab are manufactured n Segment lengths: up to approx. 30 m

separately and sequentially. n Height: approx. 3 to 10 m


n Width: no limits
n Number of segments: maximum of

approx. 10 segments

Fill
Slab
Intermediate segment
Walls
Intermediate segment
Bottom plate
Construction sequence for separate
Ditch manufacture of the cross-section show-
ing the extent of the construction site.

10129900_Peri_Tunnel_004-045.indb 8 20.03.12 11:28


6.33
9.78 9.78

Various different standard systems can be used for con- The tunnel walls can be constructed using mobile wall The tunnel slab can be brought into form using variable
structing the tunnel bottom plate, for example horizon- formwork units. mobile slab formwork carriages.
tally mounted TRIO panels.

Tunnel bottom plate formwork Tunnel wall formwork Tunnel slab formwork
Panel or girder formwork tied on one side Mobile or crane-movable formwork is used Depending on the number of steps and
with light brace frames, or supported for the walls, depending on the length of thecross-section geometry, standard load-
against the lining, can be used for the edge the structure. A decision is made for each bearing systems can be used, which are
stopends. individual project as to whether the number moved as tables in small units, or other
of labour-intensive tie points can be project solutions can use large tables that
reduced. can be hydraulically lowered and relocated.
This also allows for the provision of transit
openings.

Diagram of possible formwork solutions


for the individual tunnel components.

Lateral stopends

Movable slab formwork

One or two intermediate segments

Movable wall formwork

One or two intermediate segments

Bottom plate formwork proceeds ahead of the rest

Alternatively, slab tables on MULTIPROP supporting


towers can be used, which can be moved from segment
to segment with a striking and transportation trolley.

10129900_Peri_Tunnel_004-045.indb 9 20.03.12 11:28


Cut-and-cover construction
cross-sections built semi-monolithically
Bottom plate concreted in advance,
walls and slab cast as a single unit

In this process, after the bottom plate for Construction sequence for semi-monolithic manufacture
of the cross-section (bottom plate first, followed by walls
each segment is finished, the walls and slab and slab) showing the extent of the construction site.
formwork are erected from the inside of the
tunnel using a formwork carriage. The outer
wall formwork is erected using a separate
formwork carriage that can be relocated or
moved from segment to segment using a
crane.

When moving the inner formwork, the wall


formwork must be retracted and the slab
formwork must be lowered. This requires Fill
clearance compensation areas and suitable
Walls and slab
vertical and horizontal adjustment features in
the formwork. The individual formwork units One or two intermediate segments
are moved either hydraulically or manually. Bottom plate
Ditch

The advantage of this formwork process systems allow efficient manufacture of the
is that only one load-bearing system is walls and slab. They are movable and can
needed for the walls and slab. The outer thus be used without cranes. They are not
wall formwork is also the stopend for very labour-intensive.
theslab edge. These types of formwork

The lifting and lowering device allows the slab formwork Inner formwork moved forward for a railway tunnel. After
carriage to be hydraulically lifted into the concreting the reinforcement work is completed the wall formworks
position and then lowered later. are closed using VARIO panels.

10

10129900_Peri_Tunnel_004-045.indb 10 20.03.12 11:28


Diagram of semi-monolithic construction process,
thebottom plate is laid in advance here.

Movable wall and slab


formwork carriage

Bottom plate formwork


proceeds ahead of the rest
Outer formwork is movable or
can be relocated using a crane

One or two intermediate segments

Guideline values for using the process


n Segment lengths: up to approx. 25 m
n Height: approx. 4 to 10 m
n Width: approx. 4 to a maximum of

approx. 20 m per carriage


n Number of segments: minimum of

approx. 10 to a maximum of approx.


60segments

12.80

Formwork in position Retracted


9.65

4%

21.50

Two-tube rectangular cross-section with tied wall formwork. One of the two tie points is in the bottom Vault cross-section, formwork carriage solution
plate area to reduce the danger of water penetration. At the upper tie position, DW32 tie rods securely with tied wall area.
support the heavy load of 360 kN.

11

10129900_Peri_Tunnel_004-045.indb 11 20.03.12 11:28


Cut-and-cover construction
cross-sections built semi-monolithically
Bottom plate and walls cast as a single unit,
slab concreted afterwards

After the bottom plate and outer walls have been con- This formwork machine is moved hydraulically and the An alternative to this is a portal carriage, shown here with
creted, the formwork for the middle wall separating the formwork is also erected and struck hydraulically. The hung VARIO wall formwork panels.
two traffic lanes is erected (if necessary). The slab is wallformwork is fully supported when in the concreting
then erected after this. position.

This process is also known as trough con- In special cases the tunnel sections are After this, as with conventional construction
struction. This is used in groundwater areas manufactured in steps and the wall form- processes, the slab can be brought into
where absolute watertightness is required work is used as a self-supporting structure form using a slab formwork carriage. The
and construction joints are intentionally not over one section length. For the bottom sideways positioning of the slab is done
used. The wall formworks hang on a portal plate and wall components progressing in using additional formwork on scaffolding.
carriage that spans the entire tunnel width advance when using up to six construction The slab formwork is normally supported
and can be moved along the tunnel. The segments, a wall formwork solution is using standard material. If a transit opening
formwork is moved perpendicular to the selected that is erected on steel profiles is required, then a system formwork car-
wall when being erected and stripped. and moved using a crane. For multiple, riage can also be constructed.
repeating segments a portal carriage is
used on which the wall elements are hung.

Construction sequence for semi-monolithic manufac-


ture of the cross-section (bottom plate and walls
first, followed by the slab) showing the extent of the
construction site.

Fill
Slab

Intermediate segment

Bottom plate and walls


Ditch

12

10129900_Peri_Tunnel_004-045.indb 12 20.03.12 11:28


Diagram of the semi-mono-
lithic construction process:
Bottom plate and walls are
concreted at the same time
and slab is then built after-
wards.

Slab formwork carriage with


lateral stopends

One or two intermediate segments

Wall formwork unit at the portal

Variant 1 Bottom plate and wall Variant 2 Bottom plate and wall Guideline values for using the process
Concreting of the trough with tied wall Concreting of the trough with single side n Segment lengths: up to 15 m maximum
formwork. The tie points are usually supported wall formwork. This variant
designed to be watertight, e.g. through does not require the installation and n Height: approx. 4 to 8 m
the use of PERI DK or SK tie systems. sealing of tie points. n Width: approx. 25 m
n Number of segments: minimum of

approx. 10 to a maximum of approx.


60 segments
Formwork removed installed
5.65
7.49

10.80 16.16 In both semi-monolithic construction


processes, the longitudinal extent of the
Use of the portal formwork carriage for Single sided wall formwork on a formwork carriage construction site is less than with the
bottom plate and wall
separate casting process. Adjustments
tocope with geometric changes in the
tunnel can be easily performed in a simi-
lar manner to conventional construction
1.00

processes. The use of formwork carriag-


es becomes economically sensible when
the tunnel requires about ten segments
5.35

or more.
1.00

10.80 0.70 16.16 0.70

Slab formwork in concreting position Slab formwork in concreting position

13

10129900_Peri_Tunnel_004-045.indb 13 20.03.12 11:28


Cut-and-cover construction cross-sections built monolithically
Bottom plate, walls and slab concreted in a single casting

Variant using a launching beam

In the monolithic construction process the Functional sequence of variant using


complete tunnel tube is manufactured in a a launching beam
single casting process this means that the
formwork for the bottom plate, walls and After removing the bulkhead, the launching beams
hanging on the inner formwork are moved, with raised
slab must be erected at the same time. Two launching beam supports, to the next section.
different formwork processes can be used
for constructing monolithic tunnel cross-
sections: one variant using a launching
beam and the other variant using a portal
and trailer.

PERI developed this construction process in


1998 for the construction of the city railway
Fill
tunnel in Ismaning near Munich. Many vari-
ants of this process have been used suc-
Combined cross-section cessfully since then, including a system for
Reinforcement the worlds largest tunnelling machine, used
in the construction of the Oeresund tunnel
Ditch between Denmark and Sweden.

Once the concrete has hardened, the so-


called launching beams, which span two
complete concreting sections, are moved
Construction sequence for monolithic manufacture forward by one section. The launching
ofthe cross-section (bottom plate walls and the slab)
showing the extent of the construction site.
beams are moveable and hang on the inner
formwork. This is supported by the concrete
that has already hardened. Once the rein-
forcement has been built into the bottom
plate, the outer wall formwork is moved into
place using a crossbeam sitting on the
launching beams.

Once the reinforcement for the outer wall


has been installed, the inner formwork
(walls and slab) is moved to the next sec-
tion, supported by the launching beams. All
movements can be performed hydraulically.

14

10129900_Peri_Tunnel_004-045.indb 14 20.03.12 11:28


After the bottom plate is reinforced, the outer formwork The inner formwork moves along the transport beam The entire cross-section is manufactured in a single
is moved using a crossbeam and then aligned. Then the with raised middle supports into the next section. casting process. The middle support is lowered onto
outer walls are reinforced. Oncethe inner formwork has been moved, the middle thefinished concreted bottom plate once this has
wall and then the slab are reinforced. reachedto the required minimum level of hardness.

Guideline values for using the process


n Segment lengths: minimum of

approx. 10 to approx. 24 m
n Height: approx. 3 to approx. 10 m
n Width: maximum of approx. 20 m
n Number of segments: minimum of 50seg-

ments

This variant is used for tunnels that are par-


tially or fully underwater and have more
than50 concreting sections. The normal
segment length lies between 10 m and 24 m.
Savings result from the fact that overlap
joints are not required, which reduces the
amount of reinforcing needed. In addition
tothis, no sealing measures for horizontal
concrete seams are required, which also
saves effort and costs.

15

10129900_Peri_Tunnel_004-045.indb 15 20.03.12 11:28


Cut-and-cover construction
Cross-sections built monolithically

Variant using a portal and trailer

The bottom plate, walls and slab are also


cast as a single unit in the variant using a
portal and trailer.

Once the concrete has set and the front


stopend has been removed, the inner form-
work is lowered / retracted. The inner form-
work is mounted on a carriage. The carriage
hangs on a mobile portal in front of the
concreted tunnel section and moves on the
finished bottom plate at the rear end seen 6.39 6.39

in the working direction of the tunnel.

The outer formwork is also supported by


this portal and is moved perpendicular to
the wall to bring it into the striking position.
After the next bottom plate has been rein- Above: Cross-section with
forced, the portal is moved to the next con- installed and removed frame-
work, with the main beam
creting section, together with the hung
and portal clearly visible.
inner and outer formwork, in a single work-
ing step. All movements can be performed Below: Side view of finished
tunnel tube with the portal
hydraulically.
(front) and support (rear).

Inner formwork on portal


andtrailer

Reinforcing is done one


segment in advance

Outer formwork on the


leading and trailing portal

Functional sequence of variant using a portal The complete cross-section is concreted. The bulkhead The inner formwork is folded away and the outer form-
andtrailer has been removed. The next bottom plate section is work stripped. The two formworks sit on the movable
reinforced. carriage or hang on the portal and are moved over the
reinforced bottom plate. In the next step the inner form-
work is aligned and the walls are reinforced.

16

10129900_Peri_Tunnel_004-045.indb 16 20.03.12 11:28


Guideline values for using the process
n Segment lengths: minimum of

approx. 10 to approx. 20 m
n Height: approx. 4 to approx. 9 m
n Width: maximum of approx. 18 m
n Number of segments: minimum of

25segments

This variant is used for tunnel cross-


sections with only one pipe and of smaller
widths that do not require special provi
sional support. It is economically viable
fortunnels with approx. 25 or more
concreting sections.

As with the previously described monolithic


process using launching beams, the advan-
tages of this process are a rapid construc-
tion process and cost savings for the rein-
forcing and sealing measures.
The ties are installed after the outer formwork is closed. This is
followed by reinforcing the slab and installing the stopends. Finally,
theentire cross-section is concreted in a single casting process.

17

10129900_Peri_Tunnel_004-045.indb 17 20.03.12 11:28


Cut-and-cover construction
Building the tunnel without impairing the traffic flow

Diagram of the cut-and-cover


construction process

The tunnel slab is concreted after the retaining walls The above-ground area can already be used again at this A single sided formwork is used for the outer tunnel
have hardened and then placed on these. After the tun- stage of construction. The tunnel bottom plate is built walls and the walls are concreted against the piled walls
nel slab has hardened, the soil between the retaining between the walls. or slurry walls.
walls is excavated.

Diagram of the formwork process

Tunnel slab

Slurry wall

Single-sided wall
formwork against
the slurry walls

Bottom plate

18

10129900_Peri_Tunnel_004-045.indb 18 20.03.12 11:28


In the cut-and-cover process, retaining walls The above-ground area can be used for traf- Guideline values for using the process:
in form of piled or slurry walls are first built fic as soon as the tunnel slab has hardened n Segment lengths: up to approx. 30 m

to the left and right of the future tunnel. sufficiently, without impairing the tunnel n Height: up to 12 m maximum

Thetunnel slab is then concreted on top construction work underneath. This con- n Width: no limits

ofthese retaining walls and the soil lying struction process is preferred in inner-city n Number of segments:

between them. Once this slab has hard- areas with heavy traffic in order to reduce 1 or more segments
ened, the construction tunnel under this is the impairment of the traffic flow by the
excavated. construction measures to the minimum
amount of time.
The bottom plate is concreted after the sin-
gle-sided formwork for the tunnel outer wall
has been installed and this is concreted
against the piled or slurry wall. The tunnel
cross-section is usually rectangular.

Variants for wall formwork solutions

Variant 1
Single-sided formwork walls using TRIO panel formwork
and SB brace frames.

Variant 2
Horizontally braced VARIO girder wall formwork
mounted on a movable carriage that allows easy
adjustment for changing cross-section widths.
4.75

4.20 21.08

19

10129900_Peri_Tunnel_004-045.indb 19 20.03.12 11:28


Mining construction
Building tunnels completely underground

The mining process is used when the Diagram of a vaulted formwork carriage.
The formwork for the retaining wall and
depth of the tunnel makes open con- arched slab is installed and they are
struction too expensive, an open ditch is concreted together. The erection and
not possible or the structures above the striking of the formwork can be control-
led hydraulically.
tunnel must remain intact.

The tunnel tube is usually excavated with


explosives or a tunnel boring machine.
Ifnecessary, the tube is then secured
using sprayed concrete and rock anchors.
After application of a sealing foil, the bot-
tom plate is laid first. A horizontal bottom
plate is laid or, if required by the cross-
section geometry, a vaulted bottom plate
formwork is used. After this, the form-
work for the side walls or retaining walls
and the arched slab is installed and these
are concreted, either together or sepa-
rately.

Formwork process for a constant tunnel


cross-section

Vaulted formwork carriages are normally c arriage can be moved from segment to
used in tunnel segments having a constant segment. Steel formwork is often used
tunnel cross-section. The wall and/or arched here due to the high usage numbers and
slab formwork on this carriage can be the heavy formwork pressures.
hydraulically erected and struck and the

Steel formwork ready for use on a self-moving


t ransport carriage. The erection and striking of
theformwork can be hydraulically controlled on
thiscarriage.

20

10129900_Peri_Tunnel_004-045.indb 20 20.03.12 11:28


Formwork process for variable tunnel Arched slab
cross-sections

Separate casting manufacture of the


cross-sections is especially used where the
normal tunnel cross-section changes, e.g.
at passing bays in a road tunnel. This meth-
od can also be used for horizontal, inclined
and vertical shafts.

The tunnel cross-sections are almost


always vaulted in these cases. As with the
combined formwork carriage for walls and
slab used in the open construction method, Retaining wall

the formwork must be able to be retracted


and lowered in order to move the carriage.

In the mining construction method, the


pressures on the formwork are significantly
higher than with the cut-and-cover con-
struction method, especially on the slab.
For this reason, and because the concreting Bottom plate vault
loads are transferred without using tie rods,
the supporting structures are much more
solidly constructed than in the open con-
struction method. The formwork in the wall Diagram of separate casting manufacture in mining
areas is designed to cope with fresh con- tunnel construction

crete pressures of 60 to 100 kN/m and


theslab is designed for pressures of 80 to
120 kN/m.

11.92

18.25

For tunnels with less than about ten concreting sec-


tions, arched slab formworks are usually built with
The formwork for the retaining walls is single-sided. standard falsework components, steel profiles and
The vaulted bottom plate formwork, often mounted With larger tunnel cross-section widths, the formwork wooden formwork skin. System carriages are used for
on a movable carriage, can be easily moved to the next panels are adjusted to suit the geometry and mounted larger numbers of sections. Steel formwork is used for
segment and exactly positioned. In addition to the tun- on braces frames (see wall formwork for cut-and-cover tunnels which have 60 to 70 segments or more. With
nel bottom plate, consoles and/or bases for the next construction). With smaller tunnel widths, the formwork 20concreting segments or more, these are equipped
retaining wall/vault formwork are often constructed can also be cross-braced as long as the space is not with hydraulic systems for erecting / striking the form-
withthis. needed for transit in the tunnel. work and for moving along the tunnel.

21

10129900_Peri_Tunnel_004-045.indb 21 20.03.12 11:28


Deviations from the normal cross-section
Adjusting the formwork to suit different tunnel sections

Transit bays and wider tunnel segments

In addition to the regular tunnel tube, Parking and transit bays are needed over must be constructed so that it can still pass
various geometrical adjustments to the the length of the tunnel. They are wider through the narrower normal cross-section.
cross-section, transfer structures and than the normal tunnel cross-section. The PERI offers many solutions for this usually
auxiliary structures are also needed for formwork carriage must be able to accom- based on standard material.
the tunnel to be used in the planned modate these different cross-sections and
manner. For example, these include
cross-section expansions (bays) and
structures connecting the tunnel to the
above-ground areas. Escape passages
and ventilation shafts are required for
thesafe operation of a tunnel.

PERI offers formwork carriages and


engineering for every type of cross-
section variation, with numerous transfer
structures and auxiliary structures being
implemented inmany different ways.
Thewide range of possibilities can be
demonstrated with a few examples.

22

10129900_Peri_Tunnel_004-045.indb 22 20.03.12 11:28


0.90
Escape and access shafts

Shafts with various different cross-


8.68
7.95

sections are needed for access to tunnel


structures. They provide extra safety in
dangerous situations and provide access
to the tunnel machinery for the operating
personnel.
10.80
1.00 1.00
14.30

In this tunnel, the formwork carriage can


be lowered by over one metre for pass-
ing through the normal cross-section and
the width can be reduced from 14.30 m
to 10.80 m.

0.30
2.50
0.30

0.30 0.30 0.30


3.00 3.00

This sewer canal in South Africa has been formed


with the RKR tunnel formwork system. Due to the
use of pre-assembled units the team at the site was
very fast.

This special mining steel carriage was built for a


supply tunnel. Concreting a 2-day cycle was easily
possible.

23

10129900_Peri_Tunnel_004-045.indb 23 20.03.12 11:28


Transfer point from the tunnel to the above-ground area
Construction of tunnel entrances and portals

8.17

If the entrances are roofed, then this may require spe-


cial forms and high supports for the slab formwork.
Herea variable MULTIFLEX girder slab formwork is
used, with MRK framing connected to towers supported
by MULTIPROP supports carrying the heavy loads.

Transfer structures are used for the area Cyclic movement of large units is usually architect and engineers and also depending
between the mining tubes and the above- done with a crane or a formwork carriage on the manner in which the tunnel is to be
ground roadways or tracks. Different struc- construction. integrated into the landscape. However,
tures are used depending on the height these are usually curved in multiple direc-
differences and other conditions. Retaining All tunnels have portals at the entrances and tions, making the formwork correspondingly
walls of varying form, dimensions and sur- exits, regardless of the chosen construction complicated. The diversity of the PERI sys-
face design are needed for the pre-cutting method and the formwork process used. tems allows formwork and shoring solutions
area. Beam and panel formwork are used The portals are designed differently depend- for the widest possible range of forms.
here depending on the individual conditions. ing on the specifications of the planning

Retaining walls in entrances often require especially


high formwork elements and special supports to accom-
modate the heavy loads resulting from fresh concrete.
Examples of this are SB brace frames or horizontally
positioned MULTIPROP towers.

24

10129900_Peri_Tunnel_004-045.indb 24 20.03.12 11:28


A portal collar formwork using RUNDFLEX circular wall
formwork. The individual elements can be exactly adjusted
to the desired radius via adjustable spindles. The substruc-
ture is built using ST 100 stacking towers.

Longitudinal section and


section of a formwork plan,
seen from above from the
sloping level
3.9
3

10.00 10.00

25

10129900_Peri_Tunnel_004-045.indb 25 20.03.12 11:28


Gallery structures
Semi-open construction

Galleries are used to protect roads and rail-


way tracks from snow, rockfalls and mud-
flows in mountainous regions or they are
used for noise protection in residential
areas. Galleries are similar to tunnels but
have one wall open to the outside. In addi-
tion to the horizontal forces resulting from
falling snow or rocks, the construction must
also be able to deal with the slope force.

Compared to a tunnel, the construction and


especially the upkeep of a gallery are signifi-
cantly cheaper. The open side allows air and This gallery provides noise protection for the neighbour- In this gallery structure, the wall formwork and slab table
ing residential area. A supporting framework construc- were coupled, which allowed the entire unit to be rapidly
light to enter the tunnel, which avoids the tion with integrated supports and beams was erected moved. The wall and slab formwork could be prepared for
need for artificial air inlet and exhaust sys- first and the structure was then later closed using pre- moving with only a few manual steps.
tems and also reduces the amount of artifi- fabricated slab segments.
cial lighting required.

26

10129900_Peri_Tunnel_004-045.indb 26 20.03.12 11:28


A disadvantage of the avalanche gallery is
that it is not fully protected from the weather
with snow and rain penetrating from the
side. This can result in the need to clear
0.90

snow from the inner space in winter. From


an ecological point of view, another disad-
vantage is that, unlike a tunnel, animals do
3.59

not find it easy to cross the track.

Different formwork processes can be used


1.82

for building galleries, such as the separate


casting method. The normal approach,
however, is to use formwork carriage
0.60 0.70
14.72 constructions.
8.30

3.06 - 4.15%

The function of the temporary structure can be clearly Flexible solutions are very important when building
seen. Large cutouts in the wall and slab make the alleries. It is sometimes necessary to implement
g
transfer into the tunnel an experience. differing cross-sections at the ends of the tunnel.

27

10129900_Peri_Tunnel_004-045.indb 27 20.03.12 11:28


PERI systems and experience in tunnel construction
Standard parts devices and engineering
for economically viable solutions

PERI has been a successful partner of many PERI has a wide spectrum of about 4,000
construction companies worldwide for over products developed through productive
40 years. Our solutions have positively teamwork between research and develop-
influenced the construction process and ment specialists, production specialists and
improved the results on the construction site. construction site managers. The products
PERI engineers use modern 3D modelling andsystems are produced to the highest
software and computation processes on a levels of quality in modern plants, with all
daily basis to design efficient construction working steps structured in conformance
processes and make rationalisation reserves tothe criteria of the EN ISO 9001 quality
available. management system. This results in a high

28

10129900_Peri_Tunnel_004-045.indb 28 20.03.12 11:28


level of production quality and safety. These experience gathered through the implemen- that use hydraulics for erecting/striking the
proven standard components flow into the tation of numerous structures. The complex formwork and which can be moved along
individual project planning of the experienced working processes required for using these the tunnel using electric motors.
PERI engineers, which reduces the number efficient formworks are planned in detail and
of custom components and lowers the form- optimised for easy handling and practicality.
work costs. This also reduced the delivery
lead times. The formwork is equipped to suit the spe-
cific requirements of the customer. The
The current state of the PERI tunnel form- spectrum ranges from simple, low-cost
work technology is based on decades of solutions to convenient formwork machines

29

10129900_Peri_Tunnel_004-045.indb 29 20.03.12 11:28


The VARIOKIT construction kit for civil engineering
Tunnel formwork carriage for cut-and-cover construction

VARIOKIT is an engineering construction kit ing limits. The simple installation process
with rentable standardised components istailored to suit building sites and finely
that offer a solution to many different engi- stepped length variations of the core ele-
neering solutions. The number of special ments allow perfect adaptation to suit the
parts has been reduced to an absolute specific requirements of any jobsite.
minimum and the system has only three
core components, the RCS climbing rail, System components having a common
theuniversal SRU steel waler and the SLS function are combined into groups, such
heavy-duty spindle. Together with various asthe construction elements for raising,
accessories (such as scaffolding pipes and lowering or moving. Fundamental details,
couplings) this system allows a diverse such as the scaffolding pipe connection as
range of engineering tasks to be economi- side protection, are accounted for as well
cally solved. as working process technical necessities
(e.g. connections for concrete pumps).
A small number of typical connection ele- Additional components such as the drive
ments offer many advantages, for example mechanism and electrical or hydraulic com-
fewer different connection elements like ponents are also available within the scope
pins and cotter pins. Every type of connec- of the VARIOKIT construction set.
tion can also be assigned standardised load-

The combination of proven systems such as the


VARIOGT 24 and HD 200 with elements from the
VARIOKIT construction set produces economical
formwork carriages.

The modular PERI VARIOKIT system can be used for The diagonal brace (VARIOKIT strut) is installed in the slab
many different solutions perfectly tailored to individual beam using standard connecting elements. The regular
building sites e.g. for slab formwork carriages. matrix of holes in all system components offers many
connection possibilities.

30

10129900_Peri_Tunnel_004-045.indb 30 20.03.12 11:29


Tunnel formwork carriages are always
project-specific solutions. PERI VARIOKIT
allows these to be economically implement-
ed using standardised system components.

Advantages of the VARIOKIT formwork


carriage
n Less ties in the wall area through system

walers up to UU 200.
n Easy adjustment to suit different cross-

sections.
n Optionally available hydraulic assistance

for erecting and striking formwork and


also for raising and lowering.
n Self-moving or movable solutions for

implementing complete units.

All components are optimally adjustable


n The HD 200 heavy duty prop allows
infinitely variable height adjustment and
raster-free length tailoring.
n The RCS rails are available in all necessary

lengths.
n The VARIOKIT strut is infinitely adjustable

from 4.00 to 9.00 m.

In addition to formwork for rectangular cross-sections,


the material can also be used for curved formwork
construction.

31

10129900_Peri_Tunnel_004-045.indb 31 20.03.12 11:29


The VARIOKIT construction kit for civil engineering
Maximum loading capacity for mining tunnels

32

10129900_Peri_Tunnel_004-045.indb 32 20.03.12 11:29


Load optimisation is achieved through the ability to The transport carriage from the RCS system brings the The formwork carriage for the third cycle (arch area) also
install only the parts necessary to support the some- formwork and support units to the next segment. conforms to the construction site requirements.
times large partial forces present.

The extremely high fresh concrete pressure brace frame system is used. With shorter Mining tunnel formwork systems must always
presented to mining tunnel formwork car- tunnels (< 40 cycles) having short section be constructed under conditions that are
riages represent a special challenge for the lengths (< 20 m) and shorter construction sometimes heavily contradictory:
PERI VARIOKIT system. To cope with these times (< 12 months), leasable solutions are
forces while also providing a transit opening significantly more economic than complete n Heavy loads from wet concrete pressure
for the construction site traffic, a combina- project solutions using steel. and concrete weight.
tion of VARIOKIT with tie parts from the SB n Lower individual weights due to restric-

tive available space for installation and


operation.
n Minimum contingency costs from a high

rentable ration and low quantities.


n Few operating elements and optimally

adjusted to suit the construction site


processes.
n Simple operation of large units.

The flexibility of the VARIOKIT system is seen when


solutions must be adapted to suit the special require-
ments and conditions of the structure.

33

10129900_Peri_Tunnel_004-045.indb 33 20.03.12 11:29


The tunnel waler system
Rigid connections for installation-friendly solutions

The tunnel waler system is a modular sys- The universal tunnel waler
system consists of stand-
tem. Standardised walers, braces, spindles ardised beams with head
and movable beams are combined via rigid plates and supplementary
bolted head plates. This allows especially components.
economical adjustments to suit different
cross-sections.

The tunnel waler system allows special


components to be largely replaced with
rentable parts. This greatly reduces the
costof the formwork solution.

Variants for different cross-section forms formwork


built using the tunnel waler system

34

10129900_Peri_Tunnel_004-045.indb 34 20.03.12 11:29


Telescopic steel formwork carriage
The variant for especially high rates of use

A standardised self-supporting steel frame


forms the basis of this formwork carriage
variant. A steel formwork skin is adjusted
tosuit the tunnel cross-section and is then
fastened to the frame.

The frame connections are jointed, which


allows the formwork carriage to be adjusted
to suit the tunnel dimensions. The frame
isequipped with an undercarriage, raising
and lowering units that allow quick and
easyerection and striking of formwork and
moving of the entire unit. The formwork skin is connected to the base
frame via spindles, which allow additional
compensation to suit the tunnel cross-
section. Horizontal and vertical loads are
transferred to the foundation by a special
supporting system above the lower form-
work area.

35

10129900_Peri_Tunnel_004-045.indb 35 20.03.12 11:29


Proven tunnel construction details and techniques
Geometric adjustment of the formwork

Stopends

Cyclic construction of tunnels requires verti- struction equipment. Depending on the must be sealed e.g. with inner and outer
cal stopends at the tunnel head of the indi- forces on the tunnel formwork, it may be water bars. In some cases, thrust-braced
vidual concreting sections, the so-called necessary to support the tunnel wall and/ connections providing continuous reinforce-
bulkhead. To make the system economically or slab formwork on the previously com- ment and ratchet thrust locking must be
viable, it is advantageous when the forces pleted concrete section. installed. The formwork must also have
resulting from concreting are transferred to appropriate mounting points and possibly
the inner tunnel formwork, or distributed The geometric requirements on the manu- also cut-out boxes.
between the inner and outer tunnel form- facture of the bulkhead are usually regarded
work. This should preferably occur without as a special challenge for the formwork con-
additional ties to the structure or the con- structors. For example, the block seams

Bulkhead in the wall and slab area

Bulkhead for the bottom


plate and walls in semi-
Bulkhead on the bottom plate monolithic construction

36

10129900_Peri_Tunnel_004-045.indb 36 20.03.12 11:29


Slab and wall height deviations

Varying cross-sections along the length Example of an increase in wall height: The adjustment to
the changing heights is done by simply stacking and
ofthe tunnel require special construction removing panel formwork elements on the movable portal
measures to allow the formwork to be formwork carriage.
adjusted as construction progresses. This
allows the same devices as the bulkhead
tobe used for transit bays, fan niches or
expansion areas at the end or middle of the
tunnel. In this category are stackable wall
formworks, telescopic slab formworks and
adjustable vaults.

14.38

20.29

Example of the formation of a sloping slab: An appropri- Example of a changeable vault cross-section:
ate adjustment element allows adjustment of the slab Theheight is adjusted simply by using the spindle
formwork. toscrew out the individual walers of the tunnel
walersystem (left). The width is adjusted by
installing yokes and HD 200 heavy duty props.

37

10129900_Peri_Tunnel_004-045.indb 37 20.03.12 11:29


Proven tunnel construction details and techniques
Raising, lowering and moving the formwork carriage

Paths and mechanics of formwork positioning and removal

In the cut-and-cover and mining construction ofthe reinforcement. The values mentioned Among other requirements, a formwork
methods, the formwork must follow a here are for orientation purposes only. angle between 45 and 90 should be aimed
specific striking path when being moved for to prevent the formwork from interlock-
from segment to segment or for cleaning Sensitive edges resulting from the form- ing with the concrete. Special care must be
purposes. The length of this path must be work elements must also be protected. This taken with the formwork direction when
defined in conjunction with the respective is the only way of using such a system with- using dovetailed (tongue and groove) form-
construction process and the installation out requiring time-consuming repairs. work plates.

6.30
9.40

Detail of the positioning and retraction dynamics of The inner wall formwork is folded back for cleaning Cross-section of an underground railway tunnel con-
vaulted formwork. and/or reinforcing work. A suitably large working space structed using the mining process. The steel formwork
must be ensured. can be hydraulically retracted and lowered.

Formwork striking paths based on


experience

Open construction
Slab: >10 cm
Wall: 10 to 50 cm

Mining construction method


Vault (slab and wall): 10 to 50 cm

Inner formwork retracted for the movement process


(left) and positioned ready for concreting.

38

10129900_Peri_Tunnel_004-045.indb 38 20.03.12 11:29


Raising, lowering and drive systems

The lifting, lowering and moving systems do


not normally need to carry forces from the
concreting process. Only the weight of the
formwork must be considered when dimen-
sioning the units. Units equipped with a con-
venient hydraulic system are usually used for
lowering and raising the formwork, depend-
ing on the frequency of this.

Variously equipped formwork carriages are


used for this, depending on the structural
requirements and the special wishes of
thecontractor. These range from simple
constructions that are lowered onto move-
ment wheels via spindles and related using
hoists to hydraulically controlled formwork
machines that are self-moving and can posi-
tion the formwork at the push of a button.

The formwork is raised into position, or lowered onto


the wheels for relocation, by hydraulic cylinders.

Combined lifting and movement devices are also used: Self-moving formwork carriage with hydraulic erection/ Shaft formwork that is manually erected/struck using a
Lifting is done hydraulically and movement occurs with striking for a cross-section with two roadway tubes and spindle and moved using a grip hoist.
an electric motor. a service tunnel between them.

39

10129900_Peri_Tunnel_004-045.indb 39 20.03.12 11:29


Ensuring the durability of the tunnel construction
Measures and material for the highest quality

A compressed-air construction vibrator offers high The PERI BPA concrete pump connection matches A pipe cleaner is also available for the BPA concrete
levels of density. thewall formwork systems TRIO, MAXIMO and pump connection.
VARIOGT 24. The filler pipe is shown here.

View of the division of concrete windows

Casting and compressing the fresh concrete

Tunnel construction places especially high Distortion and sagging of the formwork skin pression technology used depends on
demands on the properties of the hardened must lie within an acceptable tolerance theformwork construction. The design
concrete. The casting and compression of range. ofthis should be carefully planned and
the fresh concrete are decisive factors influ- documented.
encing the quality of the hardened concrete. Concreting windows or pressure pipes are
The PERI engineers take this into account provided for filling. It is important to consult
when planning the formwork. concreting experts when designing the
concreting and compression processes.
The pressure of the wet concrete during Compressed-air vibrators with welded or
concreting is a critical factor for the dimen- clamped fastenings should be used in order
sioning and design of the tunnel formwork. to achieve the best results. The type of com-

40

10129900_Peri_Tunnel_004-045.indb 40 20.03.12 11:29


The formwork surface and the design of the concrete surfaces

The decision over the formwork lining to The installation of reinforcement lying on Completely smooth wall and slab surfaces
use depends partially on the geometry but the slab formwork results in increasing with regular seams are seldom required in
primarily on the frequency of use and the damage to the plywood. When using tunnel construction. However, transition and
cost of formlining replacement. Wood or film-coated, multiply glued plywood sheets auxiliary structures, and especially portals,
steel can be used, with the decision based in the slab area, this means an effective place special demands on the surface of
on project-specific comparative calculations. limit of 50 cycles before replacement, the concretes. The use of the appropriate
whereas the same formwork plywood can formwork plywood with the desired surface
Among other factors, it is important to note be used approximately 70 times in the wall allows a wide range of possible surface
that the loading, and the resultant wear, is area. Steel formwork plywood must be designs.
different for the wall and slab formwork. used forhigher levels of usage.

PERI offers plywood in a wide range of dimensions,


The fair-faced concrete of this portal collar was achieved strengths and quality. The correct plywood for the
through exact application of board straps on the plywood. construction side is always available.

The flexible MULTIFLEX girder wall formwork offers


diverse design possibilities and in this case the lower
area of the wall is profiled.

41

10129900_Peri_Tunnel_004-045.indb 41 20.03.12 11:29


Ensuring the durability of the tunnel construction
Measures and material for the highest quality

Post-treatment carriage

The post-treatment process protects the


applied concrete from premature drying.
This ensures proper hardening of the con-
crete surface under construction site condi-
tions. The post-treatment is also important
for the long-term durability of the compo-
nents and the structure as a whole. The
duration and type of post-treatment are pri-
marily dependent on the hardening charac-
teristics of the concrete and the ambient
environmental conditions during hardening.
The measures must be defined based on
the specific conditions.

Appropriate post-treatment carriages are


used in the tunnel, which isolate the
concrete from the environment to protect
itfrom drying too quickly. These carriages
must only be able to support their own
weight. There are a number of different
types of insulation.

Post-treatment trailing carriage with an inner radius


of 5.10 m. The carriage is mounted using the tunnel
walersystem.
Constructing a watertight tensioning point
PERI DK sealing cone system

Cross-section and longitudinal section of a post-treatment Removing the sealing cone using the
carriage. The construction is mounted on series parts from UNIsealing key
the HD 200 heavy duty system.

42

10129900_Peri_Tunnel_004-045.indb 42 20.03.12 11:30


PERI tie technology In both the DK and SK tie systems, the tie
permanent sealing of the tie holes points are sealed using concrete cones and
a two-component glue. Suitable cones and
Based on experience, water impermeable spacing pipes are used depending on the
tensioning points can be expensive and are diameter of the tie rods. The DK system
an important factor in formwork construc- uses two reusable DK cones and one reus-
tion. In the case of damage, the costs of able tie rod. The spacing pipe remains in the
necessary repair work can be many times concrete.
that of the construction costs. In addition
to this, the official testing results of most PERI supplies concrete cones to satisfy all
sealing / waterproofing devices relate only architectural requirements. In the SK sys-
to the individual components and not the tem, two reusable SK cones are connected
entire sealed tensioning point. This means In the pipes of the Oeresund tunnel, which connects to one concreted tie rod. When a spacing
Denmark and Sweden 20 m under the sea, the PERI SK
that the risks are carried entirely by the tie system ensures 20,000 permanently sealed tie
pipe is used, then the tie rod can be
contracting company. points. reused.

For these reasons PERI has developed relia-


ble methods using the structurally tested
DK sealing cones and the SK tie cones that
satisfy all the technical and commercial DK sealing cone
requirements and conform to the legal
requirements.

SK sealing cone

Clean the impression, coat with sealant glue Coat the concrete cone with sealant glue and use the Remove the excess glue done
cone wrench to press the cone into the impression
while lightly turning

PERI tie systems for wall formwork are For more information refer
n water impermeable to the PERI tie technology
n fire resistant productbrochure.
n acoustically damping
n radiation resistant

43

10129900_Peri_Tunnel_004-045.indb 43 20.03.12 11:30


Process for reducing construction times
Gap-concreting

The alternating sequential method can be The leader with double-sided bulkhead is The ability to lease the PERI standard
used equally well for monolithic and semi- decisive for the concreting process. In this device is a big economic plus because the
monolithic cross-sections in both mining construction method, complicated details leasing costs of the additional material are
and open construction methods. With gap- such as the installation of water bars or usually completely amortized by the result-
concreting the first formwork carriage set double-sided stopends with tangential force ing shorter leasing time.
(leader) runs in advance over multiple seg- interlocking must be taken into account.
ments, the second formwork carriage set The amount of material and number of per-
(closer) closes the resulting gaps after- sonnel is doubled by this approach. But this
wards. pays off in many projects due to the shorter
construction time.

Diagram of the alternating sequential


method using PERI formwork carriages.
This tunnel is constructed semi-mono
lithically (bottom plate in advance, walls
and slab cast as a single unit).

Cross-section with inner and outer formwork in concreting The construction of this slab formwork carriage allows
position (left), ties loosened and outer formwork stripped trucks to pass through the formwork in both positions.
for moving (right).
0.85
1.00
8.26

5.71
1.39

1.20 1.20 0.70 0.70


12.31 9.70

44

10129900_Peri_Tunnel_004-045.indb 44 20.03.12 11:30


Faster movement through back proping

This tunnel is gap-concreted and back proping accelerate The so-called back proping reduce the
the movement of the tunnel formwork carriage. A double
time saving!
construction time: The tunnel formwork
carriage is relocated very early, with the
young slab being supported by back
proping. This means that the formwork
carriage is rapidly available for the next
concreting section.

This process accelerates the construction


process with a minimum of extra material
and the solution is also very economical
due to the low effort required for the back
proping.

HD 200 heavy duty supports are used here. The support-


ing structure is connected to a movable carriage allowing
it to be quickly moved forwards from cycle to cycle.

45

10129900_Peri_Tunnel_004-045.indb 45 20.03.12 11:30


Cut-and-cover construction tunnel
Separate casting and semi-monolithic construction
of the cross-section

Rosca-Konscica A1 Motorway Tunnel, Split, Croatia

Cut-and-cover construction is the preferred The main elements of the tunnel bottom
variant for shallow construction depths plate, walls and slab can be constructed
because the technical demands and con- as different variants and in different
struction costs are comparatively low. sequences or can also be concreted mono-
lithically in a single casting process.
To construct the tunnel, a construction
trench is excavated and this is then covered The following sections illustrate projects
with soil after the (usually rectangular) con- where the cross-section is separately cast
crete pipe is finished. or semi-monolithically cast.

46

10129900_Peri_Tunnel_046-067.indb 46 20.03.12 14:40


Horental Tunnel, Switzerland Tunnel in Donzdorf, Germany

Pictograms are used to highlight the tunnel


construction method

Separate casting in open construction:


Bottom plate, walls and slab are concreted
oneaftereach other.

Semi-monolithic construction / Variant 1:


Bottom plate concreted in advance, walls and
slab cast as a single unit afterwards.

Semi-monolithic construction / Variant 2:


Bottom plate and walls cast as a single unit first,
slabconcreted afterwards.

47

10129900_Peri_Tunnel_046-067.indb 47 20.03.12 14:40


Tunnel Zwickau, Germany
Adaptable, easy to handle and quick to move
Weekly cycles in both directions using VARIOKIT

Flexible slab formwork solutions for exact dimensional


accuracy: The VARIOKIT formwork carriage accounts for
a 2.5% lateral slope for the bottom plate and slab as
well as differing longitudinal slopes of up to 3.2% and
variable radii.

48

10129900_Peri_Tunnel_046-067.indb 48 20.03.12 14:40


Cut-and-cover construction separate casting

Contractor
ARGE Tunnel Zwickau Alpine, Hochtief
Field service
PERI Leipzig and PERI Weissenhorn, Germany

A 380 m inner city underpass for the B93 Based on the construction site require-
relieves the residents of noise and exhaust ments, the PERI engineers used the Hans-Jrgen
fumes while also optimising flood protec- VARIOKIT construction set to design tailor- Mlzer
tion. The four-lane expansion also allowed made formwork solutions using rentable Supervisor
the creation of open green areas between standard components from the PERI
the city centre and Mulde river. product range, including HD 200 heavy
dutyprops and RCS walers. The side slab
Starting from construction phase 14, the elements could be moved mechanically
construction crew works in weekly cycles this reduces the width of the formwork The VARIOKIT tunnel formwork
inboth directions using separate casting. carriage while simplifying and accelerating carriage is easy to strike and move.
The bottom plate, walls and slab were the striking and moving operations. Other advantages are the ability to
constructed one after another, with each adjust to differing radii and the transit
concreting section being 10 m long. Four opening for construction site traffic.
VARIOKIT formwork carriages were used
toerect the tunnel slab formwork one for
each tube and direction respectively.

0.70

In the normal tunnel sections, the double tunnel tubes


have a width of 8.75 m and are up to 12.78 m wide in
the expanded sections. To allow the unhindered passage
of construction site traffic, the VARIOKIT slab solution
was constructed with a 3.50 m x 4.00 m transit opening.
5.46
0.82

0.70 0.65 0.70


8.75 12.78 8.75 12.78

Formwork in position Formwork retracted

The tunnel was constructed using separate casting, RCS climbing rails as crossbeams together with HDT
withthe bottom plate, walls and slab being concreted main beams and HD 200 heavy duty props were used
one after another. for a load-optimised slab formwork carriage unit.

49

10129900_Peri_Tunnel_046-067.indb 49 20.03.12 14:41


Neu-Ulm 21 railway project, Neu-Ulm, Germany
Flexible and fast due to rentable system components

a3.6 km stretch through the Neu-Ulm inner


city. The tracks now run about 8 m below
street level through a 1,483 m long trough
structure. This allowed important through-
roads to run over the tracks and made inner-
city areas available for construction and
green belts.

The PERI solution included formwork and


scaffolding for constructing the bottom
plate, the walls and thetunnel sections as
well as two underpasses. The use of VARIO
GT 24 girder wall formwork allowed cost-
effective construction of the 120 cm thick
and up to 8.50 m high concrete walls. The
orientation of the walls and the transfer
ofthe wind loads is achieved using heavy
duty spindles and steel walers on the exist-
ing sheet piling. The tunnel sections with
lengths of 170 and 250 m were constructed
as twin-tube box cross-sections using the
separate casting method, and concreted
with standard cycle lengths of 18 m.
Ineach case, two PERI tunnel formwork
The Stuttgart Munich rail connection is carriages one behind the other and four
animportant part of the European railway carriages next to each other provided opti-
network. A new track path and expansion mal adjustment to the varying track and
tofour tracks was necessary in order to structural radii.
provide a fast, high-capacity transit route
through the city of Neu-Ulm. To achieve
this, the track was sunk underground over

The trough width varies between 21.50 m and 32.60 m.


It has a total length of 1,483 m. The VARIO GT 24 girder
wall formwork used for the up to 8.50 m high reinforced
concrete walls could be moved quickly due to the large
segments. The need for only a few tie points also
reduces costs.

Reinforcement using PERI UP scaffold units, concreting Rentable standard system components resulted in an
of the walls using VARIO and realisation of the cantilev- inexpensive, cost-effective tunnel formwork solution.
ered slab areas for the trough wall using a tunnel form-
work carriage.

50

10129900_Peri_Tunnel_046-067.indb 50 20.03.12 14:41


Cut-and-cover construction separate casting

PERI engineers had to take into considera-


tion the widening of the cross-section with-
in the tunnels which increased the overall
width from 24 to 35 m. For this, GT 24
formwork girders were telescoped as a can-
tilever to the tunnel centre and supported
with MULTIPROP slab props. For the 13 m
and wider cross-sections, an additional
MULTIPROP table in the centre of the
tunnel resulted in a reduction of the filler
areas.

The fact that the tunnel formwork carriages


could also be used as support construction
for the realisation of cantilevered slab areas
for the trough wall brought site crews con-
siderable cost advantages.

Contractor
Ed. Zblin AG, Stuttgart
Field service
PERI Weissenhorn, Germany

Franz Frick
Supervisor

1.20 10.68 0.80 9.92 1.20 With the PERI solution we achieved
an optimal cost-benefit effect. The
0.90

formwork carriages could be easily


adapted to the different tunnel widths
in weekly cycles. For the trough walls,
6.36

we saved on tie points and achieved


fast moving times using the VARIO
1.50

system. The PERI UP reinforcement


1.20 0.80 1.20
16.02 15.98 scaffolds were also quickly moved and
provided safe working conditions.

51

10129900_Peri_Tunnel_046-067.indb 51 20.03.12 14:41


Tunnel Kreuzstrae, Tuttlingen, Germany

52

10129900_Peri_Tunnel_046-067.indb 52 20.03.12 14:41


Cut-and-cover construction separate casting

53

10129900_Peri_Tunnel_046-067.indb 53 20.03.12 14:41


Tunnel Kreuzstrae, Tuttlingen, Germany
The alternating sequential method Rentability made a solution
with two slab formwork carriages cost-effective

Hans Kessler The formwork carriages are easy to


Supervisor andle, they are easy to position both
h
horizontally and vertically, the vaulted
sections are easy to extend and the
bulkhead is easy to install. The entire
system is stable in every way and easy
to operate.

Contractor The raising and lowering system allows the slab form-
ARGE B311 Tuttlingen work carriage to be hydraulically lifted into the concret-
Crossroad tunnel ing position and then lowered later.
Reisch GmbH & Co. KG
SKS Bau GmbH & Co. KG 0.70 9.70 0.70
Heim Tuttlingen
GmbH + Co. KG
0.85

Field service
PERI Weissenhorn, Germany
5.71

5%

5%

The design of the slab formwork carriage allowed


trucks to pass the construction at all times.

The construction of a crossroad tunnel of the system devices made the formwork The cross-sectional shape of the wall form-
greatly alleviated the traffic load in the inner solution especially cost-effective, despite work carriage required a special solution for
city of Tuttlingen. The rectangular cross- the high material use, because the renting load transfer when concreting. Generously
section was constructed using the cut-and- costs for the larger amount of material dimensioned wall walers were tied to the
cover construction method, subdivided into were almost completely amortised by the foundation in the lower wall area and, above
100sections approximately 10 m long. resulting reduction in construction time. the transit passage, the pressure from the
Theouter walls were first concreted on one fresh concrete was transferred via horizon-
side against previously constructed bored The formwork carriage could be optimally tally positioned HD 200 heavy duty props.
piles, with the slab being constructed using adjusted to suit the varying longitudinal and
the Pilger step process to save construction lateral tunnel inclination as well as the cur-
time. A first formwork carriage (the leader) vature of the tunnel. Formwork joints were
progressed in advance across the cycles arranged in the middle of the wall formwork
and a second formwork carriage (the trailer) panels and the vaulted formwork panels on
closed the resulting gaps afterwards. the slab formwork carriage could be moved
horizontally. Spindle and hydraulic units
All three formwork carriages were con- allowed easy adjustment of the polygonal
structed using components from the shape for the roadway.
VARIOKIT construction set. The rentability

54

10129900_Peri_Tunnel_046-067.indb 54 20.03.12 14:41


Cut-and-cover construction separate casting

A drive true of 3 m wide and 4 m high was required


forthe wall formwork carriage for the Tuttlingen tunnel
to ensure that the construction site delivery traffic was
not impaired.

55

10129900_Peri_Tunnel_046-067.indb 55 20.03.12 14:41


Windshear Wind Tunnel, Concord, USA
Cost-effective solution using standard equipment
for an unusual construction task

The unusual construction tasks could be performed


cost-effectively using the project-specific tailor-made
formwork solution.

The Windshear Wind Tunnel has a total surface area


of67 m x 28 m with a diverse range of complex
cross-sections.
11.14
28.19

66.25

23.20

56

10129900_Peri_Tunnel_046-067.indb 56 20.03.12 14:41


Cut-and-cover construction separate casting

Isaiah Wayne, Project Manager


Cecilio Gonzalez, Supervisor

The complicated geometry was a great


challenge for us. PERI was able to help
us with their expertise by supplying us
custom fitted formwork made of stand-
ard equipment. This allowed us to com-
plete the task in a very cost-effective
manner.

The back-leg diffuser, with varying widths and heights, Contractor


could be formed exactly to the required dimensions Wayne Brothers, Inc., Kannapolis
using a raised formwork that was preassembled before Field service
delivery based on rentable PERI standard components. PERI Orlando, USA

The wind tunnel is used as a test bed for tion crew were supported by a PERI super- preassembled before delivery and uses
improving the aerodynamics of racing cars. visor, which allowed especially efficient s ystem components from the VARIOKIT
The vehicles are positioned on a moving implementation on-site. construction set. The adjustment to the
steel floor that rotates at a speed of about changing shape was done using SLS heavy-
290 km/h. A huge fan moves up to 2.85 mil- The major challenges were the unusual duty spindles and MULTIPROP transferred
lion m of air per minute at the same time. geometry and the height of the structure. the loads into the ground from a height of
PERI provided a tailor-made formwork solu- The height and width of the tunnel change 10 m.
tion for constructing the unusual tunnel, continuously in the back-leg diffuser tun-
which used rentable standard components nel area. Especially the angled arched slabs The tapered part of the tunnel is designed
from the PERI hire service. The construc- required special flexibility. The lattice was to function as a jet nozzle and this placed
special demands on the formwork and shor-
ing. A flexible tunnel solution using PERI
system components was also used for
constructing the curved walls and slab.
Heavy-duty MULTIPROP props connected
to MRK frames were used as the load
tower for shoring the slab formwork. This
combination allowed optimum, construction
site specific adjustments to suit the com-
10.49

plex surfaces and heights.


6.82
2.75

5.25

To the left are a longitudinal section and a cross-


section of the tapered tunnel section that serves as
a jet nozzle. To the right is the back-leg diffuser
with a variable cross-section.

57

10129900_Peri_Tunnel_046-067.indb 57 20.03.12 14:41


Troja Tunnel, Prague, Czech Republic
PERI UP Rosett Shoring for heavy loads and large heights

The expansion of the Prague ring road The rectangular, inclined tunnel cross- slabformwork was used for the tunnel slab
includes the Blanka tunnel. The last part section was designed with three construc- with thicknesses of 100 cm to 150 cm. The
ofthis tunnel, which connects Malovanka tion joints. The walls were constructed usual section length for concreting the slab
and Troja, was constructed over a length of afterthe bottom plate. The slab was then was 12 m. The load was transferred using
570 m using the cut-and-cover construction constructed in two steps with a 0.50 m 6.90 m high shoring based on the light-
method. The two complete separate tubes thick concreting joint. weight but very strong PERI UP Rosett
are combined into a single tunnel after pass- modular scaffolding. Guide rollers allowed
ing beneath the Vltava river. The opposing The high side and middle walls were the shoring and slab formwork to be moved
lanes are separated by a dividing wall. The formed using the proven TRIO panel form- to the next concreting section.
traffic returns to the surface at a crossroads work system. MULTIFLEX GT 24 girder
in Troja.

58

10129900_Peri_Tunnel_046-067.indb 58 20.03.12 14:41


Cut-and-cover construction separate casting

The bay sizes used for the PERI UP Rosett shoring were The formwork elements in the areas with single sided
chosen to suit the height of the loads to be transferred. formwork were shored using SKS shoring panels.
1.00
3.90
0.75

0.80 0.80 0.80


10.25 13.75

The PERI UP Rosett modular scaffolding system


rovides light-weight shoring for the slab formwork.
p

Contractor
Metrostav a.s., Division 6, Prague
Field service
PERI Jesenice, Czech Republic

The 80 cm thick walls are 6.50 m high and were formed


using the proven, high pressure TRIO panel wall form-
work system.

59

10129900_Peri_Tunnel_046-067.indb 59 20.03.12 14:41


Wolfsgruben Tunnel, St. Anton, Austria
Time saved by using PERI systems for the slab and walls

The railway line between St. Jakob and river crossing which were adjusted ideally
St.Anton was increased to two tracks to to a fast turnover. The units were pre-
increase the traffic capacity for the 2001 assembled ready for use at heights of 8.40
world skiing championship. The simultane- and 9.00 m, saving valuable site time. The
ous movement of the railway station pro- formwork could be grouped together to
vides more peace and attractiveness in adjust for the different wall heights in the
thetown. subsequent Lions gallery construction
section.
The 1,743 m long Wolfsgruben Tunnel was
constructed using the open construction The PERI suggestion for the slab formwork
method. The width of the tunnel changes and the up to 10 m high shoring resulted
from two to four tracks and the cross- insignificant time savings: The rapid instal-
section changes from a rectangle to a lation of the MULTPROP system and the
trapezoidal shape. The structure has slab simple, flexible adjustments to varying
thicknesses of up to 120 cm and large cross-sections allowed the work to proceed
heights of up to 10,05 m. In addition to the quickly. The construction crew also benefit-
need for transferring heavy loads over large ed from the fact that the entire unit, togeth- 1,200 m VARIO girder wall formwork designed for a
fresh concrete pressure of 80 kN/m filled with 480 m
heights, the slab formwork and shoring er with the slab formwork, could be moved of concrete. Concreting was performed on alternate
needed to be continually adjusted. and brought into concreting position using sides to allow checking for deformation of the falsework.
the hoisting and motion equipment.
VARIO girder wall formwork units were
used for the tunnel walls in the area of the

60

10129900_Peri_Tunnel_046-067.indb 60 20.03.12 14:42


Cut-and-cover construction separate casting

Altering the VARIO GT 24 girder wall formwork in the The light aluminium MULTIPROP towers from the PERI Contractor
area of the polygonal-shaped supporting wall (left) to the renting pool wer quickly installed and securely carried Arge St. Anton Obertage
straight wall (right section) was made by exchanging the the loads of the 10.50 m high and 1.20 m thick tunnel Mayreder, Stuag, Porr Technobau, Rhomberg
articulated couplings with fixed couplings. This avoided slab. Field service
having to modify the entire unit. PERI Vorarlberg and PERI Weissenhorn, Germany

Werner Herzog As the MULTIPROP tables were to be


Site Manager moved in units, we were very fast in
completing the slabs. The system is
extremely flexible and could easily be
adjusted to the changing cross-sections.

6.75 28.51 20.43

The Rosanna crossing is divided in four sections


c omprising the avalanche protection construction,
thecurved supporting walls, the hollow box and
thestraight supporting walls.

61

10129900_Peri_Tunnel_046-067.indb 61 20.03.12 14:42


Jumeirah Palm Island Tunnel,
Dubai, United Arab Emirates

62

10129900_Peri_Tunnel_046-067.indb 62 20.03.12 14:42


Cut-and-cover construction separate casting

63

10129900_Peri_Tunnel_046-067.indb 63 20.03.12 14:42


Jumeirah Palm Island Tunnel, Dubai, United Arab Emirates
Proven systems used in diverse ways

The 2,000 luxury villas and 40 exclusive were constructed using the cut-and-cover ideal basis for all areas. The load-bearing
hotels found at The Palm, Jumeirah, are built construction method. Just pumping out the GT24 formwork girders and the SRZ steel
on sand. More than 100 million cubic excavation pit took one month. walers could also be used very flexibly as
metres of sand and rock were required as slab formwork. The concrete loads during
landfill to create the island in the shape of The cross-section is 38.00 m wide and construction of the tunnel slab were safely
apalm tree. The 12 km long and 5 km diam- 9.16m high, the reinforced concrete bottom transferred into the bottom plate via PD 8
eter crescent-shaped breakwater is con- plate has a thickness ranging from 1.54 m to shoring towers.
structed from rock and has been designed 2.08 m. The slab thickness varies between
to protect the 17 fronds against erosion. 1.50 m and 2.00 m and the outer walls are
1.50 m thick. Forming, reinforcement work
The outer ring with its hotel facilities and a and concreting were carried out using the
gigantic water park is connected to the separate casting method. In 25 m long con-
trunk by a 996 m long tunnel. Including the creting steps and four cycle sequences,
entry and exit ramps, the tunnel construc- thetunnel bottom plate, two wall sections
tion has an overall length of 1.4 km of which respectively and then the slab could be
around 600 m runs underwater up to depths concreted one after the other.
of 25 m. The triple-tubed rectangular cross-
sections with three lanes in each individual PERI system components from the VARIO
tunnel, along with a central supply tunnel, girder wall formwork system provided the

64

10129900_Peri_Tunnel_046-067.indb 64 20.03.12 14:42


Cut-and-cover construction separate casting

Walter Freitag With the PERI systems, we were able to


Site Manager achieve a fast cycle sequence. They are
simple to operate and can be used very
flexibly. In addition, PERI provided us with
the required technical support on the con-
struction site.

Around 200,000 m of concrete was poured for the road Contractor


tunnel in only eleven months. Al Naboodah Engineering Services L.L.C., Dubai
Field service
PERI Dubai, U.A.E.
38.00
0.60 0.60
1.50 15.65 2.50 15.65 1.50

1.50
5.83
1.83

The flexible VARIO GT 24 girder wall formwork was used


for the 60 cm thick middle wall and the 1.50 m thick The 38 m wide tunnel connects the artificial Jumeirah
outer walls. Palm Island with the outer belt.

65

10129900_Peri_Tunnel_046-067.indb 65 20.03.12 14:42


Underground railway station at Mricz Zsigmond Square,
Budapest, Hungary
High loading capacity and flexibility at a height of up to 18 m

The arch formwork and the supporting substructure for


the solid, 80 cm wide reinforced concrete ribs are also
based on rentable system components: GT 24 lattice
girders, SRU steel walers, SLS heavy-duty spindles and
MULTIPROP slab props.

MULTIPROP MP 480 and MP 625 aluminium slab props


were connected to a spatial formwork, vertically via
MPV connectors and horizontally via MRK frames.

TRIO panels used as side formwork for the reinforced


concrete arches leave an orderly joint pattern.

66

10129900_Peri_Tunnel_046-067.indb 66 20.03.12 14:42


Cut-and-cover construction separate casting

Andrs Illinger In the planning and execution phases,


Site Manager thecollaboration work with PERI was
problem-free. The flexibility and load-bear-
ing capacity of the MULTIPROP system
used for shoring the inclined construction
elements was a great advantage.

Raised formwork construction using PERI system Contractor


c omponents, adapted to suit the geometry and static Strabag-MML Kft. HP Dir., Budapest
loading requirements: using UK 70 universal couplings Field service
with rigidly connected SRU steel walers and SLS PERI Budapest, Hungary
heavy-duty spindles.

The first section of the M4, the new fourth high loads to be transferred from great formwork construction of SRU steel walers
line of the Budapest Metro, is 7.3 km long. heights. It also required fair-faced concrete and SLS heavy-duty spindles. The shoring
Itruns under the Danube and is designed for components to be laid in a predefined seam solution installed below this was based on
fully automatic driverless operation at speeds and tie-point pattern. the MULTIPROP system with MULTIPROP
of up to 80 km/h in 90 second intervals. The aluminium slab shoring connected to MRK
Metro station under the Mricz Zsigmond The north and south ends of the Metro frames.
Square is an important public transport junc- station were formed with reinforced con-
tion with many train and bus connections. crete slabs inclined at angles of 48 and 59, With the help of the rentable, modular PERI
which were constructed in three cycles up construction set it was possible to not just
The formwork and scaffolding solutions toa height of 18.70 m. The secure load distri- construct around a previously concreted
designed by the Hungarian PERI engineers bution was achieved using GT 24 formwork cross-beam but also integrate it as a stiffen-
accommodates the static loading and archi- girders and SRU steel walers, with the spa- ing element in the shoring system.
tectural requirements. The project required tial adjustment being provided via a raised

0.
40
17.20

The 40 cm thick concrete components,


inclined at an angle of 48, could be eco-
nomically constructed in 3 cycles using
the modular PERI construction set.
Construction occurred around an existing
1.85 m x 1.30 m reinforced concrete
cross-beam, which was also integrated
into the shoring system as horizontal
stiffening.

67

10129900_Peri_Tunnel_046-067.indb 67 20.03.12 14:42


Tunnel Limerick, Ireland
Tailor-made formwork solutions:
Submerge tunnel in a six-day cycle

The aerial photograph shows the 600 m long and 33 m


wide dry dock used for prefabrication of the five 100 m
long tunnel elements.

Hannes Mauracher
Site Manager

PERI provided us with the best tech-


nical concept and the most cost-effec-
tive solution. The results that we were
able to achieve with the formwork
carriage were more than satisfactory.
It allowed us to concrete each seg-
ment in a weekly cycle. What made
our formwork partner all the more
qualified was the technical support
because we always received an appro-
priate solution to all of our detailed
Foto: DirectRoute Ltd.

questions.

68

10129900_Peri_Tunnel_068-115.indb 68 20.03.12 14:54


Cut-and-cover construction semi-monolithic

Contractor Limerick Southern Ring Road


DirectRoute (Limerick) Construction Ltd.
Strabag AG, John Sisk Son Ltd., Lagan Constr. Ltd.,
Roadbridge Ltd.
BConcreting and shoring work Limerick Tunnel
Strabag International GmbH, Linz, Austria
Field service
PERI Weissenhorn, Germany

The formwork solution for the bulkhead allowed for The 20 m segments could be concreted in a weekly Tunnel formwork carriage based on the VARIOKIT
ratchet thrust locking and two different sealing variants. cycle using the PERI formwork carriage. construction set for the six simultaneously concreted
sections at the south portal.

In position Retracted

The double-tube rectangular cross-section was con-

1.27
structed semi-monolithically. The formwork movement
was accelerated by the hydraulic raising and lowering
equipment and integrated transverse launching units.

6.09
1.15
Five tunnel elements, cost-effectively constructed
watertight and to exact dimensions in five 20 m concret-
ing cycles: The PERI hydraulic system allowed efficient 1.00
10.03
0.70
10.03
1.00
movement of the formwork and easy control of the wall
formwork elements. Integrated transverse launching
units made exact alignment easier.

As part of the M7 motorway development 20,000 tonne reinforced concrete pre-cast


in the south-west of Ireland, the four-lane segments were floated out and then low-
route crosses the Shannon near Limerick, ered, exactly positioned and joined together
afew kilometres before the river flows in a specially prepared channel in the
directly into the Atlantic. The centrepiece Shannon river bed.
ofthe 10 km long Limerick Southern Ring
Road was the required tunnelling, with a At the same time in the area of the south
total length of 915 m. For this, two different portal, an additional tunnel section was
customised PERI formwork solutions were completed in six cycles. This took place
used based on the requirements of the using the cut-and-cover method. Due to the
contractor as well as the construction few concreting sections to be completed
sequence itself. and the consequent short usage time, the
VARIOKIT modular construction system
A customised special formwork carriage was used. The use of mainly rentable
was the most cost-effective solution for standard elements from the construction
the28 concreting sections of the so-called set meant lower overall costs for the
immersed tunnel and the three adjacent contractor.
construction phases in the north which
were cast in-situ. A total of five 100 m tun-
nel elements were completely pre-cast in a
dry dock at the north portal and then sealed
off with bulkheads at the ends. After flood-
ing the dock, the 100 x 25 x 8.50 metre and

69

10129900_Peri_Tunnel_068-115.indb 69 20.03.12 14:54


Neulustheim Tunnel, Munich, Germany
City railway tunnel cost-effectively constructed
in eight cycles using system components

70

10129900_Peri_Tunnel_068-115.indb 70 20.03.12 14:54


Cut-and-cover construction semi-monolithic

The so-called overpass tunnel to the west The short track length and construction in
of the Nymphenburg Palace disentangles only eight 10.70 m concreting cycles made Volkmar Sllner
the track layout of the Munich underground a formwork carriage solution based on the Supervisor
railway network and the regional railway VARIOKIT construction set especially cost-
system since the beginning of 2009. The effective. The use of these flexible and rent-
85.70 m railway tunnel runs in a radius of able standard components with a minimum
200 m and has an inclination to the middle of special parts significantly reduced the
of 0.9% to 0.2%. overall costs.
The VARIOKIT tunnel formwork car-
riage is a mature system. From an
economic and technical point of view,
this was the optimum solution for our
construction site with only eight cycles
In position Retracted and a very tight timeframe.
0.80

Contractor
Hentschke Bau GmbH, Bautzen
8.60
7.75

Field service
PERI Dresden and PERI Weissenhorn, Germany

The rectangular cross-section was constructed semi-


monolithically: bottom plate concreted in advance,
followed by the walls and slab cast as a single unit.

0.80 10.30 0.80

At 8.60 m the Neulustheim tunnel is unusually high. The


sturdy formwork carriage allowed a concreting speed of HD 200 heavy duty props safely transfer the heavy loads
20 to 25 m/h, representing a climbing speed of 1.5 m/h. into the subsurface.

71

10129900_Peri_Tunnel_068-115.indb 71 20.03.12 14:54


Istra Tunnel, Boljunsko Polje, Croatia
Quick formwork movement saves time and construction costs

A green bridge was erected near Boljunsko A supporting structure for the formwork the specified structure geometry. The renta-
Polje to allow wild animals to cross the busy carriage was designed and built using the bility of the components minimised the
country road DC 500 between Uka and PERI UP scaffolding system. The complete material costs of the project. The easy
Vozilii. The 43 m long tunnel was construct- formwork unit was mounted on HEB steel handling of the system reduced the time
ed using the cut-and-cover construction beams and, after being quickly lowered, required for installation and the individual
method. Due to the specified short con- itcould be moved on wheels to the next moving operations.
struction time of only 2 months, the PERI concreting section.
engineers developed a formwork solution
that allowed rapid installation of the tunnel The system components of the PERI UP
formwork carriage and quick movement to scaffolding and the VARIO GT 24 girder wall
each subsequent concreting section. formwork could be easily adjusted to suit

1.10

The PERI UP construction was mounted on several HEB


steel girders which allowed the entire unit to be moved
to each subsequent section.
9.30

1.10 16.20 1.10

The load from the 1.10 m thick tunnel vault is transferred


Thanks to the PERI construction set system, via GT 24 formwork girders, a steel framework of SRU
the 43 m long animal overpass could be con- steel profiles, UK 70 universal couplings, SLS heavy
structed in only 2months. duty spindles and a PERI UP shoring construction.

72

10129900_Peri_Tunnel_068-115.indb 72 20.03.12 14:55


Cut-and-cover construction semi-monolithic

Contractor
Carin d.o.o., Zagreb
Field service
Sinia Ptiar We were convinced by the easy move-
PERI Zagreb, Croatia and Site Manager ment of the PERI solution to the next
PERI Frankfurt, Germany section. This saved us a great deal of
time and money.

73

10129900_Peri_Tunnel_068-115.indb 73 20.03.12 14:55


Laliki road tunnel, Poland

74

10129900_Peri_Tunnel_068-115.indb 74 20.03.12 14:55


Cut-and-cover construction semi-monolithic

PERI supplied several formwork carriages


for the Laliki road tunnel. The designed
solution was very cost effective due to
the low number of individual components
and the flexibility of the VARIOKIT con-
struction set.

75

10129900_Peri_Tunnel_068-115.indb 75 20.03.12 14:55


Laliki road tunnel, Poland
PERI tunnel formwork using ST-A4 heavy duty towers.

A 670 m two-lane tunnel was constructed SLS heavy duty spindles and SKS compres-
using the mining method near to the border sion braces form the horizontal load-bearing
between the Czech Republic and Poland. structure, with these resting on ST-A4
The tunnel vault is 7.74 m high and the heavy duty towers that have an especially
tunnel width is 12.50 m. Steel formwork high loading capacity. PERI supplied the
was used for constructing the tunnel. The preassembled formwork carriage on-site
construction was especially efficient and and the final installation work only took
cost-effective due to the many repeating 3weeks.
identical sections.
Thanks to the good collaboration, the con-
The contractor initially decided to use false- tractor then also commissioned PERI to
work based on the PERI UP Rosett system supply three additional formwork construc-
for constructing the portal area using open tions for an evacuation tunnel: a 12 m long
construction. However, due to a significant formwork for the open construction section
timetable delay, the contractors then and portal area and two smaller 6 m long
decided to use a movable tunnel formwork formworks for the mined section. This
carriage. A construction previously used formwork solution and the necessary rein-
onother construction sites was modified forcement scaffolding were based on the
accordingly. The flexible construction of PERI UP modular scaffolding system.
theexisting formwork carriage allowed it Thesame system was also used for con-
tobequickly and easily adjusted to suit structing the post-treatment carriage for
thecross-section of the Laliki tunnel. themined tunnel.

The PERI GRV articulated waler system


connected by GT 24 formwork girders was
used for the curved forms. The construction
had to be modified for an appropriate load
transfer: A steel framework of RCS rails,

ST-4A heavy duty towers were used for transferring


Side view of the tunnel portal formwork. the vertical loads.

76

10129900_Peri_Tunnel_068-115.indb 76 20.03.12 14:55


Cut-and-cover construction semi-monolithic

Contractor
In position Retracted Doprastav a.s., ilina
Field service
PERI Jesenice and PERI Zln, Czech Republic
0.50

Ing. Martin Valko


Site Manager
7.74

In light of the enormous delays on


the construction site, the entire techni-
cal work performed by PERI and the
final solution were both unbelievably
fast.

0.50 12.50 0.50

77

10129900_Peri_Tunnel_068-115.indb 77 20.03.12 14:55


Reinertshof Tunnel, Fssen, Germany
Alternating sequential concreting rentable tunnel formwork
carriage with VARIOKIT engineering construction kit

78

10129900_Peri_Tunnel_068-115.indb 78 20.03.12 14:55


Cut-and-cover construction semi-monolithic

Contractor
Xaver Lutzenberger, Pfaffenhausen
Field service
PERI Weissenhorn, Germany

The A7 motorway is one of the most impor- working stage with the PERI tunnel form-
Norbert Ritter tant highway connections in Europe. It runs work carriage. The VARIOKIT construction
Site Manager for almost 1,000 km from Denmark to Aus- set with mostly rentable standard compo-
tria and through Germany in a north-south nents was used. Vertical support was
direction. The final gap leading up to the provided by HD 200 heavy duty props. SRU
Austrian border was filled by the construc- steel walers and RCS climbing rails were
tion of the Reinertshof tunnel near Fssen. used very cost-effectively as wall steel
walers and slab beams. VARIOKIT diagonal
PERI provided us with a practical and The 645 m long tunnel with a double-tube bracing functioned as pressure joints.
inexpensive solution as almost only rectangular cross-section was constructed
standard components were used. The using the cut-and-cover construction and The wall formwork could be hydraulically
labour-saving and simple operations alternating sequential method. With two retracted on both sides by 10 cm. The com-
with the hydraulic striking and shutter- formwork sets, the advanced section - plete carriage could also be hydraulically
ing device as well as the drive system which was three cycles ahead - could be lifted into the required concreting position
reduced moving times to a minimum. concreted atthe same time as the remain- and subsequently lowered again using the
It took less than five minutes to move ing gap, each with lengths of 8 m. This raising and lowering equipment. Electric
a formwork carriage to the next accelerated the construction progress and drive units from the VARIOKIT range of
position. reduced the actual site length from the accessories ensured fast movement to the
foundations to the finished tunnel to a next cycle. The fact that only three rows of
maximum of 48 m. Walls and slabs could ties were needed in the walls resulted in
beconstructed semi-monolithically in one anadditional time advantage.

The PERI tunnel formwork


carriage is a modular con-
struction. The formwork
planning also included an
access passageway for
construction site traffic.

8.00 8.00

The electrical drive units The bulkhead formwork of the Optimum construction
and hydraulic operation leading carriage was foldable. progress was achieved
provided fast moving. This allowed it to be moved byusing the alternating
without time-consuming sequential method with
assembly work. two formwork sets.

In position Retracted
0.97
5.71

The standard components


from the VARIOKIT con-
struction set could be
combined into an opti-
mum tunnel formwork 0.80 1.00 0.80
9.50 9.50
solution.

79

10129900_Peri_Tunnel_068-115.indb 79 20.03.12 14:55


Green bridge on the A96 in Gebrazhofen, Germany
One formwork carriage for two cross-sections
Quick and easy adjustment thanks to VARIOKIT

A green bridge was constructed near to formwork carriage could be easily adjusted
Thomas Halder Gebrazhofen as part of the completion of to suit the radius of the single tube by
Supervisor the BAB A96 motorway between Lindau replacing a number of defined filler ele-
and Munich. The motorway is now crossed ments.
by a double-tube vault and the parallel ring
road is crossed by a single-tube vault. Planning and assembly of the control ele-
Asomewhat unusual feature is the round ments was performed by PERI in Weissen-
cross-section with a maximum height of horn. Special 3D components for the com-
The VARIOKIT formwork carriage is over 9 m. plex form of the portal area, where the
very different to our previous systems. walls taper off, were also prefabricated.
Everything worked well there was Both tunnels were concreted using a 9.30 m Concrete pump connectors were integrated
really nothing that could be improved. long formwork carriage using standard ele- into the outer formwork, which made con-
PERI brought all their experience to ments from the VARIOKIT construction set. creting windows unnecessary.
the project. After completion of the double tube, the

Contractor
Ed. Zblin AG,
Friedrichshafen area
Field service
PERI Weissenhorn, Germany

9.53
The construction of the formwork carriage allowed
unhindered delivery traffic.
0.70
13.40 13.40

The concrete was pumped into the formwork via the


The formwork for the complex form of the portal concrete pump connector BPA installed for this purpose.
collarwas supplied prefabricated to the construction The VARIO GT 24 wall formwork elements could be The cleaning slide prevents the residual concrete from
siteby PERI. ptimally adjusted to suit the tunnel cross-section.
o remaining in the concrete pump connection.

80

10129900_Peri_Tunnel_068-115.indb 80 20.03.12 14:55


Cut-and-cover construction semi-monolithic

The double tube above the A96 was constructed using


two formwork carriages built using system components
from the VARIOKIT construction set.

The Gebrazhofen green bridge has a total of three t unnel


tubes. The structure allows unhindered passage for wild
animals across the roads and connects their habitats.

81

10129900_Peri_Tunnel_068-115.indb 81 20.03.12 14:55


Environmental protection tunnel in Stetten, Austria

The so-called Ypsilon, with a total


of51 motorway kilometres was con-
structed to the north of Vienna. The
3km long Stetten environmental pro-
tection tunnel is part of this project.

82

10129900_Peri_Tunnel_068-115.indb 82 20.03.12 14:55


Cut-and-cover construction semi-monolithic

83

10129900_Peri_Tunnel_068-115.indb 83 20.03.12 14:55


Environmental protection tunnel in Stetten, Austria
Rationalised working steps through comprehensive engineering
services and cost-effective system solutions

The S1 Vienna ring expressway was


expanded to meet the needs of increase
traffic capacity. The concept also included
the3,200 m long Stetten tunnel, with the
group of construction firms relying on cost-
effective tunnel formwork solutions and
comprehensive engineering services from
PERI for the construction. The planned
weekly cycle for the 20 m long sections
was easy to maintain thanks to the efficient
movement and optimum working proce-
dures provided by the PERI tunnel form-
work carriage with movable middle and Cost-effective system solutions based on the rentable PERI UP Rosett modular shoring solutions for leg loads
construction set system satisfied a wide range of of up to 40 kN certified, adjustable and easy to install.
outer wall formwork. d ifferent requirements in the construction of the over
3km long environmental protection tunnel.
With a total surface area of almost
100,000m, the environmental protection
tunnel is the largest road tunnel ever built
in cut-and-cover method in Austria. Opti- The solution used a mobile variant to allow
mum construction progress was provided fast, crane-free movement of the outer wall
by twoVARIOKIT formwork carriages for formwork. The PERI engineers were able
the advance middle wall and five VARIOKIT to take advantage of the flexibly usable
tunnel formwork carriages for constructing system elements from the VARIOKIT con-
the slab and outer walls. struction set.

In position Retracted

1.31
5.42

0.65 0.60 0.65


14.62 14.62

The planning of the VARIOKIT tunnel formwork car- In addition to providing hydraulic lowering and folding
riage also included a transit passage for construction of the wall formwork, the VARIOKIT formwork carriage
site traffic. was moved on rails to the next section.

Contractor
Arge Ingenieurbau PPP-Ostregion S1-West
Alpine and Hochtief, Vienna
Field service
PERI Nudorf, Austria

84

10129900_Peri_Tunnel_068-115.indb 84 20.03.12 14:56


Cut-and-cover construction semi-monolithic

The two PERI formwork carriages for


the advance middle wall could be
Ing. Dieter Knig The close collaboration with the PERI moved without cranes.
Project Manager engineers led to the best solutions,
Andreas Lang both technically and economically.
Supervisor Theweekly cycle was easy to maintain
due to the efficient movement process
and optimised working procedures.

85

10129900_Peri_Tunnel_068-115.indb 85 20.03.12 14:56


DAreuse Motorway Tunnel, Switzerland
Self-moving tunnel formwork adjusts hydraulically
to the changing cross-section geometry

The extension of the A5 motorway between The formwork carriages took less than one
Neuchtel and Yverdon required a 481 m minute to travel the 12.00 m to the next Jos Antuns
long tunnel near dAreuse. One feature concreting section. The whole process for Supervisor
ofthe tunnel project is the variable cross- striking, lowering, moving, cleaning and
sections in both rectangular tunnels. repositioning could be carried out by a
three-man crew in only one hour.
Originally planned to be separately con-
structed with five working steps per cycle, The construction process was only limited
this plan was discarded in favour of the by the specified striking times. One section The formwork can be perfectly
solution developed by PERI: Using semi- was completed every two weeks. adjusted to suit the variable cross-
monolithic construction, the walls and slab section from cycle to cycle. Sadly
were concreted in a single pour and, with weonly have to construct 40 stages.
only two working steps, the construction
time could be significantly reduced.

Contractor
F. Bernasconi & Cie. S.A., S. Faccinetti S.A.
Field service
PERI Ohringen, Switzerland

86

10129900_Peri_Tunnel_068-115.indb 86 20.03.12 14:56


Cut-and-cover construction semi-monolithic

The two independently movable formwork carriages


could be easily coupled together in the area without
amiddle wall. This resulted in a uniform ceiling
appearance.

Working direction

12.00
7.02

26.85

The generous space below allowed easy transit through The lateral inclination of the tunnel varied between
the formwork at all times. 2.4% and 4.4%. The carriages are infinitely adjustable
between tunnel widths of 12.25 to 12.80 m.

Only the two VARIO elements on the outer sides of the The tunnel formwork carriages were moved using the The height and width adjustment, lowering and folding
tunnel needed to be moved with a crane. hoist hydraulics with the drive being controlled by were all performed hydraulically.
electric motors.

87

10129900_Peri_Tunnel_068-115.indb 87 20.03.12 14:56


Railway tunnel in Vranany, Czech Republic
The tunnel waler system: Reusable, adaptable, low cost

Contractor
Metrostav a AG, Division 5
Field service
PERI Prague, Czech Republic

In the modernisation of the railway corridor A formwork carriage based on the PERI
Vclav between Prague and Dn, the topographi- tunnel waler system was used for this.
Zkosteleck cal conditions required the construction of Aconstruction set system of combinable,
Site Manager a tunnel near the city of Mlnk. 58 m and standardised components allows the con-
60 m sections had to be constructed with struction of tunnel formwork for almost
cut-and-cover method before and after a anytype of cross-section. The fact that
mined tunnel section secured with sprayed most of the formwork can be rented on a
concrete. job-specific basis is a great advantage.
Since we are not constantly working
on such construction sites, the ability
to rent this tunnel formwork just for
this job was a huge advantage for us.

GT 24 lattice girders and GRV articulated walers provid- serving as the supporting structure. After lowering,
ed exact forming of the required vault form and safely theentire structure could be moved on rails to the
transferred the loads via spindles to the waler system nextcycle.

88

10129900_Peri_Tunnel_068-115.indb 88 20.03.12 14:56


0.60
8.10 Cut-and-cover construction semi-monolithic

12.20

The inner vault radius is 5.50 m and the outer vault


r adius is 6.10 m. The minimum cross-section thickness
at the apex of the vault had to be 60 cm.

The construction crew completed each 10 m concreting The insulation was installed with the help of movable
section in a weekly cycle. PERI UP scaffolding that was optimally adjusted to
suit the cross-section of the mined tunnel section.

The nodes of the PERI UP Rosett system are especially


rigid with a high loading capacity. The wedge of the
horizontal waler falls into the hole in the Rosette when
expanding and latches automatically. The high connec-
After releasing the ties, the outer formwork could be tion rigidity saves the use of diagonal braces and
struck in segments using the crane. increases the loading capacity.

The 11 m wide and 5 m long scaffolding


construction could be moved from cycle
to cycle on six pairs of wheels. Each
respective working position was secured
by lowering the entire unit via spindles.
A total of four working levels with para-
pets provided the best conditions for
safe and productive work. A planned
transit profile 6 m high and 5 m wide
allowed constant traffic within the con-
struction site.

89

10129900_Peri_Tunnel_068-115.indb 89 20.03.12 14:56


Erstfeld Tunnel, Gotthard Base Tunnel North Portal, Switzerland
Tunnel formwork carriage optimally adjustable
to suit a varying cross-section

90

10129900_Peri_Tunnel_068-115.indb 90 20.03.12 14:56


Cut-and-cover construction semi-monolithic

The Erstfeld tunnel forms the north portal of the


57km long Gotthard Base Tunnel. The railway tunnel
should enter operation in 2017 and will be the longest
Sepp Schuler The PERI formwork system is the
tunnel in the world. Supervisor optimum solution for our tunnel
because the formwork carriage can
be easily adjusted to suit the varia-
ble cross-section. The individual
positioning, striking and moving
operations work very well.

Contractor
Strabag AG Ingenieurbau, Erstfeld branch
Field service
PERI Ohringen and
MCE GmbH Eschenz, Switzerland

The northern, 600 m long tunnel section of centre section of the tunnel changes thick- positioning, striking and moving. The polyg-
the Gotthard Base Tunnel near to Erstfeld ness from 1.60 m to 3.80 m at the base of onally installed outer cladding based on the
was openly constructed. The geometrically the wall. VARIO GT 24 wall girder formwork was also
challenging structure has three different easy to adjust to suit the different angles.
tunnel cross-sections 50 m, 240 m and The construction crew built the entire tun- The construction sequence ran in 10 m
316m long respectively. The tunnel changes nel using only one type of PERI formwork stages from north to south.
from a single tube to a hexagonal twin tube carriage so that only the formwork attach-
cross-section. After 290 m, the tunnel ments needed to be replaced for the cross-
changes into two parallel individual tubes section change from a polygonal to a horse-
with a horseshoe profile. The different tun- shoe shape. The carriages were equipped
nel cross-sections are all 8 m high. The with electric drive and hydraulic raising and
middle wall, sloping on both sides, at the lowering units for quick and convenient

The twin tube tunnel cross-section was constructed For the vault cross-section, the PERI formwork carriage
semi-monolithically using the PERI tunnel formwork was simply equipped with modified formwork. This
The northern tunnel section has a polygonal cross- carriage outer walls, middle walls and slab in a allowed concreting of the individual tubes in a regular
section with variable angles. single pour. weekly cycle.

91

10129900_Peri_Tunnel_068-115.indb 91 20.03.12 14:56


Warnow Crossing, Rostock, Germany

The Warnow tunnel connects the two


banks of the river near to Rostock in
Mecklenburg-Vorpommern. The initial
planning goes back to the 1960s. The
structure was finally inaugurated in
2003.

92

10129900_Peri_Tunnel_068-115.indb 92 20.03.12 14:56


Cut-and-cover construction semi-monolithic

93

10129900_Peri_Tunnel_068-115.indb 93 20.03.12 14:56


Warnow Crossing, Rostock, Germany
Convenient tunnel formwork carriages
for smooth construction progress

On the right side: internal and external formwork are


set. Left: struck and internal formwork moved forward
by one concreting section, external formwork is ready
tomove to next cycle.

The contractor, Warnowquerung GmbH & easy to operate because the inner form-
Co. KG, completed the ring road system work could be hydraulically folded, raised Steffen Drgmller
bypassing the Hanseatic city of Rostock and lowered. Supervisor
with this section. The 790 m long tunnel
was formed using six segments. Each The formwork carriage was moved using
segment was 120 m long and pre-cast in grip hoists. The external elements, togeth-
eight concreting sections in special dry er with the top tilt formwork and working
docks. After closing the segment ends with platforms, were moved in a single crane-
steel doors and flooding the docks, the lift, saving considerable time. This allowed The tunnel formwork carriage worked
22,000 tonne elements were floated out. the weekly cycle to be comfortably extremely well so that work on two
achieved. production lines could proceed with-
The individual tunnel elements were con- out any problems.
creted in two cycles: After casting the
bottom plate, the walls and slab were
concreted in one pour, with cycle lengths
between 14.20 m and 15.60 m. The two
PERI formwork carriages supplied were

94

10129900_Peri_Tunnel_068-115.indb 94 20.03.12 14:56


Cut-and-cover construction semi-monolithic

The outer walls have only two tie points, with one of tieposition securely carried the heavy load (360 kN). Building owner
them in the bottom plate. This reduced the danger of Theconsistent use of PERI tie technology permanently Warnowquerung GmbH & Co.KG
water penetration. DW 32 steel tie rods in the upper reduced the risk of leaking tie points. General contractor
Bouygues Travaux Publics S.A.,
Feste Warnowquerung Rostock
In position Retracted Contractor
STRABAG Hoch- und Ingenieurbau AG,
NL Mecklenburg-Vorpommern, Gstrow
Field service
PERI Hamburg and PERI Weissenhorn, Germany

9.65
21.50

The total weight of the two tunnel formwork carriages


was approx. 400 t. The concept took the existing crane dismantled into individual parts of 8 t each, allowing it Water bars in the construction and cycle joints made
capacity into account. The formwork carriage can be to be lifted out of the dry dock before flooding. the structure watertight.

Tunnel construction was carried out using the


floating and sinking method a technology
h ardlyknown in Germany.

The tunnel construction phases


Floating the elements: After two tunnel elements Sinking and positioning: The tunnel pipes made
Construction: Two elements were constructed in were finished, the dry dock was flooded. The pipes ofwaterproof concrete were sealed at the ends for
three sections, with a total of six tunnel segments. were then floated out of the dry dock. fl oating out of the dry dock.

95

10129900_Peri_Tunnel_068-115.indb 95 20.03.12 14:56


A100 motorway tunnel, Berlin, Germany
Formwork carriage infinitely adjustable
to different tunnel widths

The 1,000 m long section for the expansion between 14.50 m in the normal cross- of PERI HD 200 heavy duty props. This
of the southern Berlin ring road in the sub- section up to a maximum of 23.50 m in main beam could be moved from cycle to
urb of Neuklln was built using open con- thewidened area. cycle together with the formwork carriage
struction. Two tunnel pipes provide space using cable winches.
for three lanes each. Two 8.30 m wide The formwork carriage could be adjusted to
exits are integrated into the tunnel. suit the varying tunnel widths via hydraulic Since the tunnel lies in a narrow cutting,
telescoping girders, which avoided time- the PERI formwork carriage was construct-
The foundations were constructed in consuming reconstruction. These were ed with an transit opening 4.00 m high and
advance with the walls and slab then infinitely adjustable for each cycle width wide. This allowed the unhindered passage
becast in a single pour afterwards. The and could be extended up to a distance of of construction site vehicles.
formwork surface for walls and slab was 9.00 m. At extension lengths of 3.50 m or
676 m for each cycle. The width of the more, the telescopic girders were addition-
tunnel in the two main pipes varied ally supported by a main beam composed

96

10129900_Peri_Tunnel_068-115.indb 96 20.03.12 14:56


Cut-and-cover construction semi-monolithic

The two tunnel tubes were designed for


three motorway lanes.
Andreas Katt
Supervisor

15.90

The procedures with the formwork


carriage became easier from section
to section. Everything worked well and
we were able to concrete one section
every ten to twelve days.

7.78

Regular cross section

Contractor
Wolff & Muller RKK, Berlin
24.90
Field service
PERI Berlin, Germany

Widening area

The formwork construction for the regular cross-section ...and extended for the widening area.

97

10129900_Peri_Tunnel_068-115.indb 97 20.03.12 14:56


Somosierra Pass Tunnel, Spain
Alternating sequential concreting accelerates
the construction of the double vault

The Northern Highway the axis from


Madrid to Paris passes over the 1,400 m
high Somosierra pass about 90 km north
ofthe Spanish capital city. The road was
laid underground to protect the traffic
fromsnowstorms in the winter months.
The tunnel could be built using the cut-
and-cover construction method.

The PERI engineers conceived, constructed


and supplied a formwork carriage solution
that allowed quick and efficient construction
of the double vaulted cross-section on-site.
After agreement with the contractors,
adecision was made to concrete in two
phases.

The middle wall and side walls were constructed first


and the vaults were then concreted in sequential alter-
nate cycles. The first formwork carriage progressed
inadvance across the cycles and a second formwork
carriage closed the resulting gaps afterwards. This
greatly accelerated the construction progress.

+8.93
Phase 1
The middle wall of the double tunnel was
formed using VARIO GT 24 girder wall
formwork with curved steel walers and
then concreted. Parallel to this, the outer
walls were positioned and filled using
TRIOformwork.

Phase 2
The formwork for both tunnel vaults was
erected at the same time. The construction
crew used two formwork carriages in an
alternating sequence for each tube, with a
total of four formwork carriages being used.
Special steel formwork was used for the
stopend formwork. +0.00

Concreting was performed in 12 m long


13.20
cycles. A high quality surface appearance of
the concrete was achieved using formwork
composed mainly of standard components. Contractor
A total inventory of 4,400 m of formwork Dragados & Costrucciones, Madrid
The regular cross-section of the vault with inner Field service
was maintained and one cycle could be
formwork carriage and outer formwork. PERI Madrid, Spain
completed each week.

98

10129900_Peri_Tunnel_068-115.indb 98 20.03.12 14:57


Cut-and-cover construction semi-monolithic

The second phase of the concreting section: After con-


struction of the walls on the outer side and between the
two tunnel tubes, the formwork carriages were used for
the double vault.

A special steel construction was used for the stopend


formwork.

A total of four formwork carriages were used for the


section over the Somosierra pass.

99

10129900_Peri_Tunnel_068-115.indb 99 20.03.12 14:57


NDIA Midfield Tunnel, Doha, Qatar
Six-day semi-monolithic cycle implemented

In position Retracted

Each formwork carriage


forthe two tunnel tubes
was 12m long, with the
concreting sections being
8.00

10m long. A 6-day cycle


was achieved for each
block.

42.60

100

10129900_Peri_Tunnel_068-115.indb 100 20.03.12 14:57


Cut-and-cover construction semi-monolithic

The New Doha International Airport A tunnel formwork carriage with fixed wall
(NDIA) is being constructed over an area and slab formwork was used in order to
ofabout nine square kilometres. After implement the tight timetable and reduce
completion of the first construction phase the cycle times to an absolute minimum.
in 2010, in addition to the old airport, an After concreting the bottom plate, the walls
extra 12 million passengers can be han- and slab could be concreted in a single
dled. The capacity will be extended to pour.
60million air passengers by 2020, with
80gates and 11 ramp positions. The chosen solution allowed construction
of the reinforcement, concreting, striking
Among other structures, the Joint Venture and moving of the formwork carriage to
SinoHydro Gamuda WCT constructed thenext concreting section in only 6 days.
the first runways, taxiways and parking The system provided maximum speed with
bays in the outer area and a 650 m long a minimum of personnel.
tunnel. The so-called Midfield Tunnel
runs under the runway and allows unre-
stricted transit of delivery traffic during
normal airport operations. The structure
consists of two 20 m wide rectangular
tunnel pipes with varying wall and slab
GT 24 formwork girders with a high loading capacity and thicknesses.
high rigidity functioned as the longitudinal truss for the
slab formwork

The Midfield Tunnel was constructed semi-monolithical-


ly: The bottom plate was first concreted using standard
elements and the walls and slab were then concreted in
a single pour using two tailor-made formwork carriages.

and for the wall formwork.

Contractor
SinoHydro Gamuda WTC
Joint Venture
Field service
PERI Doha, Qatar

101

10129900_Peri_Tunnel_068-115.indb 101 20.03.12 14:57


RAV Tunnel, Vancouver, Canada
Tailor-made steel formwork carriage for the best tunnel results

The inner view shows the high surface


quality of the concrete. A simple platform
was erected for operating the spindles
Dan Sherin I had never used the PERI system
usedfor positioning and striking. Project Manager before and hesitated somewhat in con-
tracting a completely new supplier for
aproject with such a tight timeframe.
However, once we saw PERIs huge
baseof experience with similar projects
we understood that they were the per-
fect partner for this construction task.

Contractor
CSC Cambie St. Constructors Incl, Vancouver
Field service
PERI Vancouver, Canada

102

10129900_Peri_Tunnel_068-115.indb 102 20.03.12 14:57


Cut-and-cover construction semi-monolithic

A rapid rail connection between the airport, planned with a length of 7 m, which ightweight DOMINO panel formwork was
L
Richmond and city centre (Richmond Air- allowed it to be used for the entire tunnel. used for constructing the walls in this area
port Vancouver = RAV) was constructed and adjustable MULTIFLEX girder formwork
for the 2010 Winter Olympics in Vancouver. The individual sections could be construct- was used for forming the slab. The flexible,
About 6 km of the track runs through a ed in a 3-day cycle. To minimise the distur- easy to handle systems could be easily
tunnel built using the cut-and-cover con- bance in the city centre during construction, adjusted to suit this complicated area.
struction method. the two tunnel tubes were stacked in this
area. Especially exact planning was required
The underground railway is mostly straight, in the transfer area between neighbouring
with curves only present in a few places. and stacked pipes in order to maintain a
The formwork carriage was therefore continuous inclination of about 5%.

0.45 4.65 0.35 4.65 0.45

The tunnel tubes were arranged above each other


0.50

tominimise the excavation work in the city centre.


4.65
0.50

PERI planned, produced and delivered tailor-made steel


formwork for the subsequent construction of a 1 m high During concreting, the formwork carriage Both tunnel pipes are 4.65 m wide and 4.26 m high.
curb. This curb provides service personnel with protected was fastened using a slab tie installed in DW20 ties connected the formwork to the right and left
access during tunnel operation. the previously concreted section. of the 350 mm thick middle wall.

103

10129900_Peri_Tunnel_068-115.indb 103 20.03.12 14:57


Denkendorf Tunnel, Germany
Alternating sequential concreting
a process for keeping to the timetable

Contractor
Arge NBS Nrnberg-Ingolstadt Los Sd
Schaler Bau Berlin GmbH
Berger Bau GmbH, Passau
Field service
PERI Weissenhorn and PERI Berlin, Germany

Quick to move: HD 200 heavy duty props are movably The tunnel was built in a 12 to 20 metre deep construc- Dipl. Ing. Alexander Lenz
mounted on PERI UP Rosett units. They form the tion trench, which was secured by a rear-tied pile
provisional supports and are installed directly after the retaining wall with a stiffening bottom plate and partially
Project Manager
formwork carriage has been moved. by head stiffening. Dipl. Ing. Michael Hackl
Site Manager

The built-in hydraulics allowed our con-


A 675 m long tunnel was constructed in 52 sections were constructed in 12.50 m struction crew to easily lower, move
Denkendorf as part of the new construction concreting cycles, with this being reduced and position the formwork carriages.
of the Nuremberg -Ingolstadt ICE track. to 10.00 m in the entrance and exit areas. We were able to start reinforcement
The structure runs through a heavily built In consultation with the contracting group work on the positioned inner formwork
commercial area and had to be constructed of construction firms, PERI conceived, carriage only one day after striking the
using waterproof concrete. A total of 54 builtand delivered two complete formwork concreted block. We have not regretted
tunnel blocks were constructed. The inner carriage sets. The use of alternating our decision to use the PERI formwork
cross-section remained constant but the sequential concreting with these form- carriage.
wall thicknesses (100 to 120 cm) and slab work carriages allowed two tunnel blocks
thicknesses (105 to 125 cm) varied over the to be completed each week.
length of the tunnel.
1.20
8.26
1.54

1.20 1.20
12.44 12.31 12.50

Longitudinal section of the leader Normal cross-section of the leader


Inner formwork carriage with bulkhead slab formwork in Inner formwork carriage with positioned outer Longitudinal section of the closing (trailing) unit
concreting position. formwork. Outer formwork carriage in concreting position.

104

10129900_Peri_Tunnel_068-115.indb 104 20.03.12 14:57


Cut-and-cover construction semi-monolithic

Inner formwork carriage (trailer) in the concreting posi-


tion. Raised via extension of the hydraulic cylinders and
horizontally aligned via spindle-actuated thrust beams.
Alternating sequential concreting

The leader provides the formwork for


each respective second concreting sec-
tion. The second carriage, the trailer,
closes the resulting section gaps. The
1.00

leader defines the concreting sequence


because time-consuming details such as
the installation of water bars or installa-
8.26

tion of double-sided stopend formwork


with tangential force interlocking must
be taken into account.
1.39

1.20 1.20
12.31

Cross-section of the trailing unit


Left: inner and outer formwork in concreting position;
Right: ties released and outer formwork in transport
position, inner formwork still in concreting position.

105

10129900_Peri_Tunnel_068-115.indb 105 20.03.12 14:57


Sewage canals
Large and small cross-sections formed cost-effectively

Canals of a wide variety of variants and


sizes are required in tunnel construction.
The cross-sections range from small pipe
diameters to connecting canals for large
sewage treatment plants.

Suitable cost-effective formwork solutions


are required that support contractors in sat-
isfying the diverse requirements specified
by the different designs. For larger canals,
water bars in the stopend formwork must
be taken into account when planning the
formwork. To ensure a watertight structure,
it may also be necessary to monolithically
construct the cross-section entirely without
joints.
Sewage canal shaft, Connecting canal between Eching and
Krumbach industrial area Garching for the Munich sewage treat-
The requirement that the shaft walls gener- ment plant
ally run perpendicular to the pipe axis The PERI canal formwork allowed mono
always leads to skew shaft layouts. Light lithic concreting of the cross-section,
systems with small surface areas such as including the middle wall.
PERI HANDSET allow fast forming of such
components. Contractor
Arge Trucksss and Dyckerhoff & Widmann

Contractor
Eco-Einsiedler

Main sewer in Badajos, Spain


The side formwork (TRIO panels) and the
vaulted bottom plate formwork (steel) could
be moved as a single unit to the next con-
creting section. The construction crew
worked with two sets of bottom plate
formwork concreted using the alternating
sequential method. Inthe background,
theinner formwork of the vault cross-
section (built using GT 24 lattice girders
andsteelwalers) is already positioned.

Contractor
Cubiertas M.Z.O.V.

106

10129900_Peri_Tunnel_068-115.indb 106 20.03.12 14:57


Cut-and-cover construction semi-monolithic

Sewage canal Durban, South Africa


Din Naidoo
The Riverhorse Valley near to the city of Owner of
Durban has been developed with 15 individ- AlladinCivils
ual business estates. The intensive building
and generous road system in this area
required suitably dimensioned rainwater
and sewage management to allow for
future development. This included the open The exceptionally fast system has
construction of one-tube and two-tube rein- allowed us to keep to our timetable.
forced concrete canals to accommodate
and protect the steel sewage pipes.

The construction crew used the RKR sys-


tem (box framing) for the 220 m long single
tube cross-section (Culvert 310) and the
460m long double tube (Culvert 308) with The series components (RKR box, GT 24 lattice girders
and formwork coating) were delivered to the construc-
awidth of 7.00 m and a height of 3.10 m. tion site just in time, preassembled and ready to use.
The pre-assembled units supplied allowed
the on-site team to quickly achieve efficient
working times. In peak times, this allows up
to three concreting stages to be completed
each week.

The corner spindle was used to lower the slab formwork


and move the wall formwork horizontally. After unspind
ling the double spindles on the RKR rollers, the entire
unit could be moved to the next section.

Concreting of Culvert 308.


0.30

0.30

General contractor
2.50

2.00

Grinaker-LTA Earthworks (SA) Sivukile JV


Contractor
Alladin Civils, Durban
0.30
0.30

Field service
Wiehahn Formwork and Scaffolding (Pty) Ltd., 0.30 0.30 0.30 0.30 0.30
Durban, South Africa 3.00 3.00 2.00

107

10129900_Peri_Tunnel_068-115.indb 107 20.03.12 14:57


City Tunnel Malm, Sweden
Adjustable tunnel formwork carriage for variable cross-sections

The tunnel section for the railway station at designed VARIO solution for the elliptical rein-
Magnus Malm main station is being built using the forced concrete columns along the tunnel
Jakobsson cut-and-cover construction method. The width centre as well as the two slab formwork
Site Manager E101, and height of two-box rectangular cross-sec- carriages which subsequently followed.
NCC tions vary considerably over the length of the As the bottom plate and external walls were
tunnel. The semi-monolithic method is carried concreted in one working cycle, the form-
out in the so-called trough construction pro- work carriages for the VARIO wall formwork
cedure where the bottom plate and walls are are designed in such a way that moving can
The bottom plate, walls and slabs concreted as a single unitwith the slab com- take place with different heights for the con-
could be constructed in 10-day cycles pleted separately afterwards. crete sub-base at the front and on the bottom
with the PERI tunnel formwork. PERI The comprehensive PERI formwork solution plate at the rear. Generously-sized working
has always provided us with the best for the 12 m concreting sections consisted platforms, PERI UP reinforcement scaffolds
solution. ofthe variable PERI VARIO GT 24 girder wall and scaffold stair access towers allow form-
formwork on two formwork carriages for work operations to be carried out safely along
thecasting section in advance, a specially with an efficient concreting process.

The VARIO girder wall formwork is precisely positioned the same operational speed in 12 m concreting cycles. Continuous adjustment to the different widths in the
using a carriage. Moving takes place via heavy-duty Aformwork carriage is comprised of two support widened areas was performed via telescopic girders.
rollers on the concrete sub-base at the front and on the frames with a hydraulic raising and lowering mechanism Height compensation of up to 2.60 m took place by
bottom plate at the rear. Two separate slab formwork along with a sectional row of HD 200 heavy duty props. means of hydraulic cylinders.
carriages allowed the tunnel slabs to be constructed at
1.07
7.20 - 9.84
1.25

1.00
1.00 17.87 - 20.93 17.87 - 20.93 1.00

108

10129900_Peri_Tunnel_068-115.indb 108 20.03.12 14:57


Cut-and-cover construction semi-monolithic

Contractor 0.70 8.94 0.70


NCC Construction Sverige AB
(Malm C Nedre E101)

0.90

0.65
Arge MCG Malm Citytunnel
(southern entrance area E201):
Bilfinger Berger AG,
Per Aarsleff A/S, E. Pihl & Son A.S.

7.71
7.18
Field service
PERI Halmstad, Sweden
and PERI Weissenhorn, Germany

0.70

0.75
0.95 7.00 0.95

The formwork carriage construction allowed for differing


cross-section dimensions as well as varying wall and
slab thicknesses.

The city tunnel is an 11 km long direct connection


between the Oeresund bridge and the Malm central
railway station, with a new underground railway station
directly at the existing railway station. In a Swedish
German collaboration, for the challenges presented by
the southern entrance and the railway station expansion
in the north, the PERI engineers developed a sensible
combination of a construction site specific formwork
carriage construction and rentable PERI system compo-
nents.

Thomas Ainill
Site Manager E201,
MCG

With the PERI solution we were able Around 1.5 kilometres of the southern The articulated wall elements were
to complete the 48 tunnel sections in entrance area will also be constructed attached to the slab girders and folded by
regular weekly cycles. The work was semi-monolithically by means of the open means of hydraulic cylinders. Internal and
carried out safely despite the tight construction method. The walls and slab external formwork can be continuously
timetable. The support we received were cast together in one unit after the adapted to the different wall heights. The
from the Swedish and German PERI 15m bottom plate was concreted. two formwork carriages were moved to the
engineers was exemplary. next casting section by means of heavy-
For the rectangular cross-sections of the duty rollers positioned on rails.
parallel but separate tunnel structures, with
variable wall and slab thicknesses and varia-
ble heights and widths, the PERI engineers
designed two formwork carriages with a
hydraulic raising and lowering mechanism
as well as integrated stopend formwork
that also accommodates the installation of
water bars.

109

10129900_Peri_Tunnel_068-115.indb 109 20.03.12 14:57


B311 bypass, Ertingen, Germany
Movable wall and slab formwork
for a waterproof road tunnel

Richard Wetzel
Supervisor

We were able to exactly maintain the


concreting cycle and our timetable.
The decision to use the PERI DK
tietechnology was also absolutely
correct. We can recommend using
thissystem.

1 2
9.50

1 Raw pipe
2 DK sealing cone
3 DK concrete cone
0.90 9.50 0.90 9.50

The portal carriage with hung VARIO elements is The head spindles mounted below allow quick All tie points had to satisfy the DIN 1045 requirements
movedfrom cycle to cycle on the previously concreted a djustment of the formwork carriage height for each for watertight walls. The DK tie system developed by
foundations. respective cycle. The slab elements did not need to PERI allows these requirements to be satisfied especially
beremoved for this. safely and at low cost.

The entire tunnel was divided into 39 concreting


1 s ections of 20.00 m each. The height adjustment
5 39
35 ofthewall formwork elements was performed via
10
30 appropriate stacking / unstacking.
15 20 25

780.00

110

10129900_Peri_Tunnel_068-115.indb 110 20.03.12 14:57


Cut-and-cover construction semi-monolithic

To bypass the town of Ertingen, the B311 The wall formwork elements had to be After construction of the bottom plate and
main road passes through a 769 m long adjustable to suit the changing height of the walls, a movable slab formwork carriage
trench and tunnel. The structure was laid walls at the entrance and exit. The inner and was used to form the closing slab. This con-
deeply enough underground so that the outer formwork elements were hung on a sisted of HD 200 heavy duty props with
local stream could remain in its natural portal to allow the bottom plate and walls to GT24 lattice girders and steel walers as a
stream bed and now runs overt the tunnel. be concreted in a single pour. The height of table construction. The formwork carriage
This solution also conformed to the noise the formwork elements could be infinitely was moved from cycle to cycle on heavy-
protection regulations for the nearby houses. adjusted with this construction, thus allow- duty rollers.
ing adaptation to the sloping road.

Contractor
Georg Reisch GmbH & Co. KG, Saulgau-Weingarten
Field service
PERI Weissenhorn, Germany

111

10129900_Peri_Tunnel_068-115.indb 111 20.03.12 14:57


Eching am Ammersee noise protection tunnel, Germany
Variable cross-section and exposed concrete quality achieved
using TRIO and TRIO structure

PERI assembled and delivered the complete formwork


and shoring based on the plans from the PERI branch
inMunich.

Tunnels are being increasingly used to pro-


vide noise protection for existing buildings in
the planning of new motorways. These can
be cut-and-cover constructed and then buried
and planted afterwards. This type of con-
struction process first requires the construc-
tion of a long sloping ramp at both sides of
the tunnel and an architecturally designed
entrance structure before the actual tunnel
begins usually in a trench.

The tunnel cross-section for the Eching noise


protection tunnel seemed very simple at first
but the formwork planning process then
resulted in different concreting sections for
the walls and slab. The formwork planning
was made more difficult by the requirement
to construct the bottom plate and walls as a
single unit.

The tunnel construction was started at two places one


after another due to a road crossing the tunnel path. The
ramp structures were also constructed using the trough
construction method. The design of the noise protection
cladding made construction more difficult.

112

10129900_Peri_Tunnel_068-115.indb 112 20.03.12 14:57


Cut-and-cover construction semi-monolithic

Contractor
Universale-Bau GmbH, Munich
Field service
PERI Munich, Germany

The overview clearly shows the three concreting cycles: The form of both entrances was extremely complex.
After completing the bottom plate and walls in a single Good results were achieved in building this structure
pour, the middle wall and then the slab were concreted. through the use of infinitely adjustable RUNDFLEX
curved formwork and factory installed linings. The
single-sided formwork pressure in the curved sections
was carried by up to 140 push-pull props.

0.80 11.15 0.70 11.15 0.80


75 different formwork applications were
needed to construct the 75 tunnel blocks,
i.e.the formwork systems used had to be
able to adapt to the constantly changing
geometry. In addition to this, exposed
6.32

concrete quality, e.g. with vertical board

6.75
structure, was also required. Gradient 2.9 %
Gradient 2.9 %

These requirements could be satisfied by


using 2.70 m and 3.30 m high TRIO panel
formwork and the TRIO structure variant with
a formwork skin made of pre-treated boards.
Five PD 8 slab tables with provisional sup- 0.80 11.15 0.70 11.15 0.80
ports were used for each tube. These also
had panels with longitudinal ribbing. The Gradient 1.0 % Gradient 2.9 %

chosen formwork solution allowed imple-


mentation of a weekly concreting cycle.

TRIO panel formwork (2.70 m and 3.30 m high) and forthe walls and slab. This solution proved to be
PD8 slab tables were used as the formwork system extremely adaptable.

113

10129900_Peri_Tunnel_068-115.indb 113 20.03.12 14:57


Schleifenstrasse Tunnel, Augsburg, Germany
Hydraulic formwork machine:
Concreting and self-moving in a weekly cycle

The Schleifenstrasse ring road is part of the


southeast bypass of the B17 main road. It
greatly alleviates the traffic in the inner city
of Augsburg and improves the quality of life
of the residents. The last part of this road
runs through a 380 m long tunnel. This was
constructed in cut-and-cover method in a
trench secured by overlapping piles and
retaining walls.

To keep the structure watertight, the tunnel


cross-section was designed as a closed
frame construction using waterproof con-
crete. The bottom plate and walls were
constructed monolithically to avoid a bot-
tom joint.

In cooperation with Zblin, PERI engineers


drafted the detailed performance specifica-
tions for this project and, based on these
requirements, designed an economical
formwork carriage. This was divided into
the following structural components:
launching beam, carriage with internal
formwork, stopends for the base chases
and bulkhead. This allowed the construc-
tion crew to maintain the planned weekly
10 m concreting cycle.

The tailor-made wall formwork steel walers, GT 24


Contractor lattice girders and joint-free formwork skin of the correct
Ed. Zblin AG, Stuttgart branch height for the best concrete surface quality was rigidly
Field service connected to the formwork carriage and could be
PERI Weissenhorn and PERI Stuttgart, Germany hydraulically positioned and retracted.

Thomas Hauser The collaboration between PERI and


Site Manager Zblin in the conception of the formwork
carriage resulted in a functional solution.
After a few concreting cycles, we were
able to maintain the planned weekly
cycle. The working procedures with the
quickly movable carriage worked smooth-
ly. The entire unit could be moved to the
next concreting section in less than half
aday.

114

10129900_Peri_Tunnel_068-115.indb 114 20.03.12 14:57


Cut-and-cover construction semi-monolithic

Working sequence
Moving the formwork carriage from cycle to cycle.

Reinforce- Reinforcement
ment Wall Bottom plate

Concreting section
Fold up supporting legs Longitudinal coupling installed

Formwork struck Longitudinal coupling removed

Retract rear Fold down supporting legs, Retract front


supporting frame underpin with a wedge box supporting frame

Move the launching beam


into the new position

Working direction

Extend the rear Fold up the Extend the front


supporting frame supporting legs supporting frame

Reinforce- Reinforcement
ment Wall Bottom plate

Move the formwork carriage to the


new position, align and position

The formwork carriage construction also integrated the The bulkhead for the walls and bottom plate was con-
formwork for the bottom plate trenches running along structed using different wooden boxes. These held the
both sides of the tunnel. Simple spindling / unspindling water bars in the wall and also a closing water bar in the
was used for positioning and striking the formwork. inner side of the wall.

CE
According to the Trade Supervisory Office of the
Bavarian Ministry for Economic Affairs, Transport
and Technology, these PERI formwork solutions
were subject to the EU Directive 98/37EC for
machinery. This meant that, in addition to satisfy-
ing the many safety and health requirements,
the PERI engineers also had to provide a hazard
analysis, an operating manual and a declaration
of conformity. This resulted in the PERI formwork
carriage receiving the CE symbol of certification.

115

10129900_Peri_Tunnel_068-115.indb 115 20.03.12 14:57


Cut-and-cover construction method
Monolithic construction of the cross-section

Sewage treatment plant in Munich, Germany

In monolithic construction of the tunnel


pipes, the bottom plate, walls and slab are
concreted in a single casting. The formwork
system for this variant is very complex. In
addition to the formwork unit, it requires
either a feeder device or a portal for moving
the formwork machine to the next casting
section.

In the following this pictogram high-


lights the monolithic construction
method.

116

10129900_Peri_Tunnel_116-127.indb 116 20.03.12 16:07


Cover building construction method
A special variant of tunnel construction

Underground railway extension, Vienna, Austria Sheppard underground railway, Bayview Station,
Toronto, Canada

Cover building construction method offers


the great advantage that excavation takes
place under the previously constructed
tunnel slab. This method of construction
minimises the impairment of traffic flow
above the tunnel during construction.

In the following this pictogram high-


lights the cover building construction
method.

117

10129900_Peri_Tunnel_116-127.indb 117 20.03.12 16:07


resund Tunnel, Denmark Sweden
PERI formwork machines used
for the worlds largest monolithictunnel

Since the year 2000, the resund project PERIs extensive experience of constructing
connects Sweden and Denmark with a four- monolithic tunnels enabled the company to
lane motorway and a two-track railway line. beat 15 competing international tenders.
In addition to two bridge approaches, an Theplanning, fabrication, transportation and
elevated bridge and an artificial island, a assembly of the formwork were accom-
4,050 m undersea tunnel was constructed plished in just eight months.
which is the biggest in the world in terms
ofvolume.

118

10129900_Peri_Tunnel_116-127.indb 118 20.03.12 16:07


Cut-and-cover construction monolithic

The photo shows only one of the two production lines whose formwork assemblies weigh 1,150 t each.
The inner formwork has been retracted into the reinforcement cage.

Nils Bjelm
Site Manager NCC
AB, Sweden

The resund tunnel is the worlds


largest monolithically constructed tun-
nel. PERI satisfied all our expectations
in the implementation of this project.
The tight timetable and conformance to
strict manufacturing dimensional toler-
ances were no problem. PERI kept their
promises of performance and technical
ability.

119

10129900_Peri_Tunnel_116-127.indb 119 20.03.12 16:07


resund Tunnel, Denmark Sweden
PERI formwork machines used
for the worlds largest monolithic tunnel

The cantilever launching method used for


bridges since the 1960s was used for the
very first time in the construction of a
tunnel. Two stationary lines produced a total
of twenty 176 m long tunnel elements.
These were cast in eight separate 22.20 m
segments.

The segments were concreted in two


hydraulically operated formwork assem-
blies. Each consisted of one base, two
outside and five tunnel forms, four guide
girders, various temporary foundations and
two stopends. As with cantilever launching
of a bridge, eight segments were concreted
and launched in succession. The base and
outside forms were stationary.

The individual tunnel elements were trans-


ported in a basin similar to a sluice. Each
individual element was lowered to sea
level, equipped with pontoons and towed
tothe tunnel axis where it was positioned
using satellite navigation. Then it was sub-
merged to apreviously excavated trench
onthe sea floor.

1 2
8.50

4
3

42.00

Reliable sealing of the DW 26 tie points: 20,000 tie Cross-section of production line 2 Contractor
points were sealed watertight using the PERI SK OTC-resund Tunnel Contractors:
tiesystem. NCC AB, Sweden
The Laing Group, Great Britain
1 Tie rod concreted in place Boskalis Westminster Dredging B. V., the Netherlands
2 SK tie cone Dumez-GTM, France
3 SK concrete cone E. Pihl & Son A/S, Denmark
4 Raw pipe Field service
PERI Denmark and PERI Weissenhorn, Germany

120

10129900_Peri_Tunnel_116-127.indb 120 20.03.12 16:07


Cut-and-cover construction monolithic

Tunnel element being sealed before flooding of the basin.

Functional sequence

Start position: outer formwork struck, bottom plate formwork in concreting


position, guide girder supported at the front and rear, inner formwork struck
andsupported at the front.

Two 176 m tunnel sections in the flooded basin ready for


towing to their final position.

Completely prefabricated reinforcement cage lifted into the concreting position


viathe guide girder.

Inner formwork extended into the reinforcement cage, bring inner, outer and
bulkhead formwork into position, install box outs and ties.

Concrete tunnel segment (2,700 m), use inner and outer vibrators.

Guide girder hydraulically moved halfway back (for load distribution), tied inner
formwork used as the bearing surface.

Tunnel segment with extended inner formwork and guide girder is moved Transport of a 57,000 t tunnel section across the open sea.
on slideways by one concreting section.

Guide girder brought hydraulically into the starting position.

121

10129900_Peri_Tunnel_116-127.indb 121 20.03.12 16:08


Tunnel under Vltava river, Prague, Czech Republic
Monolithically constructed and positioned
using the submerge method

A somewhat unusual process was used to pushed into the desired position in a pre- portal and trailer was used here. Time-saving
implement his underground railway tunnel pared trench on the floor of the river and tied construction details and a high level of func-
under the Vltava river in Prague: Two 168 m into position. tionality allowed the construction crew to
tunnel tubes were concreted in a dry dock reduce the planned 7-day cycle for construc-
on the river bank. After hermetically sealing PERI planned and supplied a formwork car- tion of each 12 m concreting section by two
the individual tubes, the construction pit was riage that made monolithic concreting of the full days.
flooded so that the entire structure floated. cross-section possible bottom plate, walls
The prefabricated structures were then and slab in a single cast. The variant using a

Contractor
Metrostav, Division 6
Field service
PERI Weissenhorn and
PERI Jesenice,
Czech Republic

6.39
Formwork in position
Inner and outer formwork closed. Cross-section ready Longitudinal section of the outer formwork ready for concreting.
for concreting.
6.48

6.39 12.58
Formwork retracted

To move the formwork carriage, the inner form- Longitudinal section of the outer formwork moved to the
work was retracted and the outer formwork next section.
moved away from the concrete.

The curved tunnel pipe shortly before completion.

122

10129900_Peri_Tunnel_116-127.indb 122 20.03.12 16:08


Cut-and-cover construction monolithic

Dipl.-Ing. During construction, we were able


Petr Vondra toshorten the planned seven-day
Site Manager construction cycle for each 12 m
concreting section by two full days.
Thisgained us valuable time that
wecould then use for the floating
procedure.

123

10129900_Peri_Tunnel_116-127.indb 123 20.03.12 16:08


Lsslingen Tunnel, Solothurn, Switzerland
For the first time in Switzerland
A tunnel cross-section poured in a single casting

The 1,240 m tunnel with two street traffic as erection and striking, adjustments, com-
tubes and a service tunnel between them pensation and moving were performed fully
was monolithically constructed in 10.00 m hydraulically. ACS 100 climbing equipment
sections. The bottom plate, walls and slab from the PERI ACS automatic climbing sys-
were concreted in a single working step. A tem was used for moving the guide girders.
great advantage of this construction method The weekly cycle specified by the group of
was that no horizontal construction joints construction firms could be maintained from
were created. All formwork processes such the very beginning of the project.

124

10129900_Peri_Tunnel_116-127.indb 124 20.03.12 16:08


Cut-and-cover construction monolithic

Ren Cejka The people in my team are enthusiastic


Supervisor about the formwork machine and are
verymotivated in their work. The clearly
defined regular working steps allow us
tosave time from cycle to cycle.

Contractor Entrance ramp and tunnel portal leading to the


Arge Lt S88 Lssling underground site.
Conti, Marti
Meier+Jggi, Stuag
Field service
PERI Ohringen, Switzerland and
PERI Weissenhorn, Germany

The formwork carriage has a total weight of 210 tons,


consisting of two sets of inner formwork for the road
tubes and one formwork set for the service tunnel, both
with guide girder, the outer formwork and the bulkhead
formwork.
0.55 0.40 0.40 0.55
2.00 10.00 2.00 10.00 2.00

27.90

125

10129900_Peri_Tunnel_116-127.indb 125 20.03.12 16:08


Tunnel near Zwickau, Germany
PERI special formwork for monolithic construction

A 450 m long sunken tunnel was constructed The experience in monolithic tunnel and construction of the wall reinforcement much
using the cut-and-cover construction method canal construction shared by PERI and the easier and time-consuming platform scaffold-
for the B93 main road in Mosel near Zwickau. construction company Max Bgl was a major ing was not required.
The entrance and exit ramps had to be con- factor in deciding to use this rational, crane-
structed as open concrete trenches. Due to free formwork machine. The 300 t steel form-
the extremely tight timetable, the tunnel was work was moved entirely hydraulically.
concreted monolithically in 10 m weekly
cycles with the bottom plate, walls and slab The formwork, the bulkhead formwork seg-
being concreted seamlessly in a single cast- mented into groups and the props could
ing. This process saved time and reduced the allbe remotely controlled. The platforms
length of the construction trench. integrated into the guide girders made the

Application technology in brief

Inner and slab formwork


n Movable steel construction on guide gird-

ers with supports at the front and rear,


hydraulic height adjustment and lateral
alignment.
n Formwork component with integrated wall

and slab formwork. Striking bars at the


bottom of the wall formwork. The middle
supports with adjustment rails can be
hydraulically raised by 1 m.

Outer formwork
n Connected with ties to the inner form-
work, stands on the sub-base when
concreting.
n The outer formwork can be moved via

atandem chassis with a lifting system


atthe front and rear. It is guided by the
transport boom on the front supports.

Bulkhead
nAdjusted to suit the normal cross-section
dimensions, can be split for installing
water bars and flexible for conventional
auxiliary formwork.

126

10129900_Peri_Tunnel_116-127.indb 126 20.03.12 16:08


Cut-and-cover construction monolithic

Contractor
Max Bgl, Neumarkt/Oberpfalz
Field service
PERI Weissenhorn, Germany

Functional sequence
1.00
6.32
1.20

0.90 0.80 0.90


13.50 13.50

Moving the outer formwork with the guide girder.


The formwork system is ready for concreting. Ties released, outer formwork struck, front and rear
supports raised.

The walls can be reinforced. The outer formwork


with guide girder is moved and aligned.

The formwork carriage is moved stepwise.

The inner formwork moves to the next section on


the guide girder. The inner formwork is struck via the
guide girder with the middle support lifted.

Peter Brandler
Site Manager

The inner formwork is positioned. Installation of the


ties and closing of the bulkhead. The middle support
remains lifted until the bottom plate is concreted.
As one would expect with PERI, the
formwork carriage functioned perfectly
from the very beginning. This was also Concreting section
10 m
due to the unbureaucratic collaboration
between the construction crew and the
PERI technical office.

The formwork system is ready for concreting.

127

10129900_Peri_Tunnel_116-127.indb 127 20.03.12 16:08


Audi Tunnel, Ingolstadt, Germany
Single-sided wall formwork quickly and accurately concreted
against a concrete slurry wall

The tracks of the new ICE line between


10.80
Nuremberg and Munich run through the
Audi tunnel under part of the factory
premises of the automobile manufacturer.
To avoid disturbing the vibration-sensitive
production plant, a conscious decision was
6.50

made not to use the mining method for


excavating the tunnel tubes. The structure
was built using the cover building method.
After constructing the slurry walls and the
bottom plate underground, the tunnel
outer walls were formed single-sided and
concreted against the retaining walls.
Wall view of two coupled TRIO panel units with waler positions for one concreting
formwork elements and brace frame section (left) and in section (right).
The group of construction firms used TRIO
panel formwork elements and brace frames
for the normal tunnel cross-section. These
were specially built to suit the requirements
of the project. For the concreting cycle
length of 10.20 m, two motion units
designed for a concreting height of 6.48 m
were connected via a compensation plate.
The formwork units were pulled from
cycleto cycle using a grip hoist, initially
separately and then later all together.

Detail of tied brace frame using Plan of brace frame positioning for one concreting cycle length
PERIV tie holders. with bulkhead and tie positions.

The wall height in the south portal area differs from the
normal cross-section. The maximum height of 9.60 m
was concreted in two stages. Brace frames and TRIO
panel formwork elements were used up to a height of
6.55 m and TRIO panels on SKS 180 climbing consoles
were used for the second concreting stage.

Contractor
Arge Tunnel/Einfhrung Ingolstadt:
Walter Bau-AG combined with DYWIDAG,
NL Untertagebau Munich and
Ed. Zblin AG, Munich
Field service
PERI Weissenhorn and PERI Munich, Germany

128

10129900_Peri_Tunnel_128-133.indb 128 20.03.12 16:20


Cover building method

When concreting single-sided against existing walls,


inthis case a slurry wall, the entire fresh concrete pres-
sure on the formwork surface must be transferred to
thefoundations via appropriate ties to the brace frame
construction. Two DW 26 system ties were used for
Quartr
each brace frame in order to safely accommodate the
high loads (additional loading of 2 x 250 kN).

Tertir

PERI V tie holders for efficient installation of ties when The tunnel slab was concreted after the slurry walls
using brace frames. have hardened and then placed on these. The excavation
work began after this, starting with the entrance portal.

129

10129900_Peri_Tunnel_128-133.indb 129 20.03.12 16:20


Underground railway extension, Vienna, Austria
Wall formwork carriage for variable tunnel widths
reduced construction time by five months

In the station area of the U3/19 Gasometer installation or removal of the necessary The type of lateral bracing used allowed
in Vienna, the width of the tunnel changes HDprop segments and spindling the sides theworking and material costs for about
from 12 m to 21 m. For the single-sided of the formwork carriage in or out. 2,000 tie points to be saved.
forming of the facing along the slurry wall,
PERI supplied two horizontal HD 200 main The selected technical solution together
beams that, together with the telescopic with the predefined concreting sequence
formwork carriage, form a movable unit. were responsible for transferring the hori-
zontal load of 162 t generated by the pres-
The HD bearings were preassembled hori- sure of the fresh concrete. Wall 1 was first
zontally, lowered by crane through the load- concreted to half-height, then the complete
ing opening to the underground track and second wall and then wall 1 to the upper
then connected to the formwork carriage. edge as the last step. This solution allowed
Adjustment to the different tunnel widths the construction time to be reduced by five
from cycle to cycle was done by simple months compared to the original planning.

130

10129900_Peri_Tunnel_128-133.indb 130 20.03.12 16:20


Cover building method

Line 3 of the Vienna underground railway Minimum Formwork carriage retracted to minimum
width for single-sided forming of the
has 21 stations over a total length of 13.5 km walls of the single strip track body in the
that must be serviced at about 25 minute transfer area from underground to above-

4.75
intervals. Except for the Erdberg and ground tracks.
Ottakring stations the entire line runs entire-
ly in a tunnel. The Gasometer station was
opened in the year 2000. The old gasworks
used to be here but now only four large 4.20
gasometers remain and these are regarded
as masterpieces of 19th Century industrial
architecture.

6.50

Maximum
7.43
Contractor
ARGE U3/19 Gasometer
STUAG Bau AG, Vienna
NR Bau, Vienna
ERA-Bau, Vienna
Field service
PERI Vienna, Austria

21.08

The grid telescoping formwork carriage combined with HDS 270 props The formwork carriage can be adjusted to
The concrete surfaces are of the fair-faced concrete and HD coupling segments allow exact adjustment to suit the desired suit the variable cross-sections with very
quality. cross-section width. little effort.

131

10129900_Peri_Tunnel_128-133.indb 131 20.03.12 16:20


Bayview Station, Toronto, Canada
Wage costs reduced Single-sided walls
using TRIO and SB brace frames

The MULTIFLEX tables with MULTIPROP


supports for the 600 m slab section could MULTIPROP towers, steel walers and GT 24 lattice The provisional supports using MULTIPROP props and MRK frames
be moved in units from cycle to cycle. girders were used as the surface shoring for the slab. could be quickly installed.

132

10129900_Peri_Tunnel_128-133.indb 132 20.03.12 16:20


Cover building method

Contractor
Walter Construction (Canada) Ltd.
Field service
PERI Toronto, Canada

The Bayview station is one of five stations


Nicolas Dhillon Using the PERI system allowed us on the 6.4 km Sheppard underground rail-
Project Manager toreduce our wage costs. PERI also way line. The 450 m station has two levels
provided us with excellent support and an overpass tunnel.
inthe form of technical advice and
competent engineering services. Walter Construction, general contractor for
the openly constructed station, provided a
positive summary of the PERI formwork
solution after a very short time. Key factors
such as easy handling when erecting
andstriking and the high flexibility of the
system resulted in significant wage cost
savings compared to the previously consid-
ered solutions.
Construction process

1. Concreting of the single- 2. Concreting of the 3. Concreting of the single- 4. Concreting of the main
sided wall below the intermediate slab. sided wall in the upper slab with auxiliary sup-
intermediate slab. level, with MULTIPROP port of the intermediate
towers providing auxilia- slab.
ry support under the
load distribution points.

Striking and moving was done using a TRIO panels stacked to 5.40 m with SB-A and SB-B brace frames Optimised ties allowed fast concreting and
lifting trolley. before concreting. a fresh concrete pressure of 60 kN/m.

133

10129900_Peri_Tunnel_128-133.indb 133 20.03.12 16:20


Tunnels constructed using the mining method

Power station in Livezeni, Romania Islisberg tunnel, Switzerland

With the mining method, the rock is first


broken out using explosives or a tunnel
boring machine. The tunnel created by this
is then lined with concrete.

In addition to the use of sprayed concrete


or lining with tubbings, the bottom plate,
walls and slab can also be concreted using
a wide range of different formwork.

134

10129900_Peri_Tunnel_134-157.indb 134 20.03.12 16:13


Tunnel Luzernerring, Basle, Switzerland Brixlegg tunnel, Austria

In the following this pictogram high-


lights the mining construction method.

135

10129900_Peri_Tunnel_134-157.indb 135 20.03.12 16:13


Savio railway tunnel, Helsinki, Finland
Extreme loads for a mining tunnel

A new railway track was planned to connect


Helsinki harbour in Vusaari in the east to the
rest of the city. About 13.5 km of the 19 km
track runs through the Savio railway tunnel,
which was constructed using the mining
method.

A strait near Myras presented the greatest


challenge for construction: The poor quality
of the rock in this area required reinforce-
ment using a heavily reinforced concrete
structure capable of carrying the loads
fromboth the rock and the groundwater
pressure.

The formwork solution developed by PERI


used the VARIOKIT system. The cross- The wall and slab formwork was designed to allow The construction was additionally braced to prevent
unhindered transit of construction traffic at almost all deformation when moving the slab formwork unit.
section of the watertight construction was times. Deliveries only needed to be interrupted during
built in three stages: The construction crew concreting.
first concreted the bottom plate and side
curb in 30 m cycles. A movable wall form-
work carriage was used to form the tunnel
walls and the arched slab was constructed
after this.

The walls and slab are at least 80 cm thick tosecure the formwork in position. The wall rapid assembly of the system were only
in all areas and were concreted in 15 m and slab formwork were hung or supported two of the reasons for which the construc-
segments. For an even distribution of the on the formwork carriage and could be tion company decided on the PERI solution.
load from the especially high fresh concrete easily retracted away from the concrete.
pressure, the site crew filled the wall form-
work from both sides simultaneously. Addi- After striking, the formwork units were
tional ties between the vertical formwork moved into the next position via a chassis
and the bottom plate side lips were used and heavy-duty rollers. The mobility and

Wall formwork Wall formwork Slab formwork Slab formwork


in position retracted in position retracted
0.80

Contractor
Kalliorakennus-yhtit Oy
8.80

Field service
PERI Suomi Ltd. Oy, Finland
4.55

1.00

0.80 6.90 0.80

136

10129900_Peri_Tunnel_134-157.indb 136 20.03.12 16:13


Mining method

The third tunnel concreting section was the construction


of the arched slab. The poor quality of the rock required
a slab thickness of at least 800 mm in all areas.

137

10129900_Peri_Tunnel_134-157.indb 137 20.03.12 16:13


Losenberg Tunnel, Bigge-Olsberg, Germany
A convincing formwork concept that was quickly ready for use

Andreas Ficht PERI provided us with the most


Site Manager c onvincing technical and cost-effective
formwork concept. The VARIOKIT tun-
nelformwork carriage was planned,
approved, supplied, assembled and
readyfor operation only 3 months after
the contract was awarded. The use of
mostly rentable system components
resulted in massive savings for us.

A movable working platform based on the PERI UP Contractor


Rosett modular scaffolding system was used for the Alfred Kunz
advance reinforcing work. Console extensions allowed Untertagebau GmbH, Munich
optimum adjustment to the complicated tunnel geome- Field service
try and provided maximum working safety. PERI Munich and PERI Weissenhorn, Germany

The 123.50 m Losenberg tunnel is the last


part of a bypass road in Hochsauerland. The
egg-shaped tunnel tubes were constructed
using the mining method with 13 concret-
ing segments, each with a length of 9.50 m.

The most cost-effective solution was the


VARIOKIT tunnel formwork carriage due
tothe small number of units mostly con-
7.62

structed using rentable system compo-


nents. Another advantage was that the
carriage was ready for delivery and use
inavery short time. In combination with
the PERI UP reinforcement carriage, this
resulted in a regular 2-day cycle being
achieved with only five workers, thanks
tothe hydraulic erection and striking
processes.

10.70

Cross-section of the movable tunnel formwork carriage,


built with components from the VARIOKIT construction set.

138

10129900_Peri_Tunnel_134-157.indb 138 20.03.12 16:13


Mining method

The ovoid tunnel cross-section is 11.07 m wide and


7.82m high. It has radii between 250 m and 400 m and
has lateral and longitudinal inclinations of 2% to 5%.

139

10129900_Peri_Tunnel_134-157.indb 139 20.03.12 16:13


Detour tunnel, Sotchi, Russia
Heavy-duty tunnel formwork carriage with flexible construction

A bypass for the city centre is part of the and the entire formwork carriage could be working sequence for this that allowed the
infrastructure measures for the 2014 Winter lowered. This allowed each of the emergen- formwork segments to be hydraulically
Olympics in Sotchi, a health spa on the cy stopping bays to be concreted with six folded away and lowered. The alternating
Black Sea. This required the mining con- 9m concreting sections in a weekly cycle. arrangement of the bays for the right and
struction of a 2.6 km tunnel. The standard left lanes required an additional lateral off-
cross-section is designed for two lanes, The VARIOKIT construction must fit the set of 1.75 m from the tunnel cross-section
with a width of 10.80 m and a height of significantly smaller normal cross-section axis. For this reason, a lateral motion unit
7.95m. Six 54 m long emergency stopping dimensions when being moved from one allowing movement to a second set of
bays required expansions by 3.50 m to emergency stopping bay to the next. This railswas integrated into the hoisting and
14.30 m on alternating sides. required major reduction in the external lowering unit.
dimensions. The width of the formwork
For striking and moving on rails to each sub- carriage had to be reduced from 14.30 m
sequent bay concreting section, the side to10.10 m and the height had to be
formwork of the VARIOKIT tunnel formwork reduced from 8.70 m to 7.60 m. The PERI
carriage could be hydraulically folded back engineers developed an exactly defined

140

10129900_Peri_Tunnel_134-157.indb 140 20.03.12 16:13


Mining method

In addition to the hydraulic control system,


the processes chosen for concreting and Alexey Boldyirew, Deputy Site Manager
compressing the concrete also accelerated Sergey Haladji, Supervisor
the construction process: The use of the
PERI concrete pump connection greatly In the beginning, we were very scepti-
reduced the concreting times and the use cal of the filigree construction. However,
of external vibrators resulted in an especial- our faith in the system grew every day
ly good surface quality. Although all the and now we are truly enthusiastic
equipment was completely new to the aboutit. The PERI formwork carriage
construction crew, striking and moving of isextremely sturdy and has proven its
the formwork could be performed safely worth in practice. It satisfies all our
and quickly. construction requirements.

1.00 14.30 1.00

10.80
0.90

For construction of the emergency stopping bays, the


formwork carriage was constructed with a width of
14.30 m. The external dimensions needed to be reduced
to allow movement to the next passing bay through the
smaller normal cross-section.
8.68

7.95

Contractor
OOO Tonneldorstroy, Sotchi
Field service
PERI St. Petersburg, Russia
Formwork in concreting position Formwork retracted and PERI Weissenhorn, Germany

Steel walers, heavy-duty spindles and GT 24 girders To allow movement through the smaller standard cross-
were the main components of the formwork carriage. section, the formwork carriage construction could be
The VARIOKIT system components could be later hydraulically lowered by over 1 m and folded away to The electric motor provided quick and convenient
reused for subsequent formwork tasks. awidth of about 10 m. forward motion of the formwork carriage.

141

10129900_Peri_Tunnel_134-157.indb 141 20.03.12 16:13


Railway tunnel, Penalva, Portugal
Hydraulic formwork erection, raising and lowering
Especially short construction time with two formwork carriages

The 980 m tunnel near to the city of Penal- designed for the short construction time: exactly the correct dimensions and with
va is part of Portugals north-south railway The first carriage was used to concrete excellent concrete surface quality.
connection. The vault cross-section had to each second subsequent cycle in advance,
be constructed with a radius of 5.70 m and with the second carriage following behind VARIO GT 24 outer formwork was added
40 cm thick walls and slab. Only eight and closing the gaps. This alternating tothe formwork carriages for the cross-
months were available for building the sequential method process allowed a very sections built using cut-and-cover construc-
underground structure. The longest part of short construction time to be achieved. tion method. These were concreted on both
the structure (680 m) ran through mined sides with ahard core of 0.50 m.
tubes, with the rest of the tunnel (300 m) All erection, striking, raising and lowering
built using open construction. movements of both carriages were hydrauli-
cally assisted. This allowed the construction
PERI Portugal conceived and supplied two company to complete the 79 stages to
convenient formwork carriage constructions

The inner formwork ready for use, with the steel form- The formwork carriage in concreting position in the A view of the substructure of the steel inner formwork.
work skin mounted. s econd cycle of the mining area.
0.40

Contractor
Zagope SA, Lisbon
Field service
PERI Portugal
9.27

The formwork carriage in the open con-


0.40 0.40
struction area. The reinforcement is built
11.72 on the leading carriage and the bulkhead
and outer formwork have already been
removed from the trailing carriage. The
rear formwork carriage remains in this
Normal cross-section and longitudinal section in the position until the leading carriage is moved
mining area for a total of 55 concreting sections. to the next position after concreting.

142

10129900_Peri_Tunnel_134-157.indb 142 20.03.12 16:13


Mining method

0.40 0.40
11.72

Normal cross-section in the open construction area. The design of the portal on the formwork carriage The leading carriage with outer formwork in position.
Inner and outer formwork are in the concreting position. rovides enough space for construction site traffic.
p After the reinforcement was built, the bulkhead was
closed and the concrete was poured.

143

10129900_Peri_Tunnel_134-157.indb 143 20.03.12 16:14


Huesca Tunnel, Spain
Four tunnel sections built
using only one system formwork carriage

The Berroy tunnel is 170 m long, with a minimum longi- The formwork segment opened upwards and the The Pedralba tunnel is 2,600 m long. All tunnels were
tudinal curvature of 25 cm. hydraulic cylinder for horizontal motion. constructed in 12 m concreting sections.

Tunnel de Pedralba

The section between the cities of Sabinigo PERI designed a special steel formwork
and Fiscal was newly designed as part of that could be adapted to the differing
the expansion of the Va Pirenaica N-260 forms in a similar manner to an opening
motorway. This motorway section also flower. The formwork was composed of
includes the two tunnels at Berroy and multiple steel segments, which could be
Pedralba, which were both constructed with successively expanded to the correct
differing cross-sections using the mining cross-section via three additional seg-
method. Three different cross-sections ments. The TET-4 standard platform was
were required for the second, longer tunnel equipped with hydraulic units to allow 12.15

structure: one tube for the two-lane motor- efficient, cost-effective cross-section
way and two additional tubes of different changes.
cross-sections for auxiliary roads.

The biggest challenge in designing the


formwork solution was the requirement for
a single formwork carriage capable of
implementing the four geometries needed
for constructing four different vault cross-
sections. In addition to this, the construc-
tion also had to be capable of being used
for all three Pedralba cross-sections without
dismantling the formwork.
9.25

15.65

The drawing shows extracts from the cross-section


adjustment sequence for the tunnel formwork carriage:
Contractor A total of three additional steel segments were
Constructora Pirenaica, S.A. (COPISA) integrated into the structure in order to implement
Field service thegeometry of the Pedralba tunnel.
PERI Catalua, Spain

144

10129900_Peri_Tunnel_134-157.indb 144 20.03.12 16:14


Mining method

I have not previously worked with PERI. Oscar Ortega


But now one year after the contract Site Manager
was awarded and after about 1,000 m of
tunnel cladding I am very happy that we
chose PERI: The company has proven its
quality and reliability and I now have no
worries about the remaining 1,600 m of
tunnel.

The formwork segments were enhanced to allow the


cross-section of the formwork carriage to be adjusted. All
adjustment work could be performed using hydraulic units.

145

10129900_Peri_Tunnel_134-157.indb 145 20.03.12 16:14


Flelen Tunnel, Switzerland
Four tunnel stages completed in only nine days

Felix Bissig
Supervisor JB Bau Altdorf
Hansruedi Walker
Supervisor Zschokke Locher AG

PERI provided us with the most cost-


effective solution. Despite the large
dimensions we can concrete in a single
pour!

The formwork structure consists of a 27 mm 3-S panel,


GT 24 lattice girders as distributor and walings of bent
HEB 160 steel girders.

A 22 m long tunnel vault for the ventilation With the PERI tunnel formwork, the com-
centre runs laterally to the normal tunnel plete cross-section could be concreted
path of the Flelen bypass. So-called cavern instages, with each stage being cast in a
cross-sections of this size are normally built single pour. Since only four stages were
in two to three stages: first the curved wall necessary, an integrated hydraulic system
area in two stages and then the arched was not used for reasons of cost.
slab. However, in order to be able to con-
struct the inner ring of this cross-section in After successful installation in only three
the short time of only one month (including weeks, the site crew constructed the four
installation of the formwork) the TUF group 5.50 m stages in only nine working days.
of construction firms decided on the PERI The short dismounting phase of only seven
solution. working days rounded off the successful
use of the system.

12.80

12.15

Formwork in position Formwork retracted

Contractor The supporting structure could be adjusted to the


Arge Tunnel Flelen bypass (ARGE TUF) required cross-section. The complete formwork unit was
Murer AG, Erstfeld; Prader AG Tunnelbau, Zurich, moved on rails from section to section using a pulling
Zschokke Locher AG, Zurich, device built on-site. For economic reasons, the position-
Rothpletz Lienhard + Cie AG, Aarau, ing and striking of the formwork was done mechanically.
CSC Impresa Costruzioni SA, Lugano
Field service
PERI Ohringen, Switzerland

146

10129900_Peri_Tunnel_134-157.indb 146 20.03.12 16:14


Mining method

147

10129900_Peri_Tunnel_134-157.indb 147 20.03.12 16:14


Mosty u Jablunkova tunnel, Czech Republic
Hydraulically operated steel formwork carriage

The refurbishment of the Mosty u Jablun of the steel structure allowed heavy loads
kova tunnel is part of the expansion of the and a high rate of use while maintaining
320 railway line. The structure is designed excellent concrete surface quality. The car-
for a two-track railway and is 612 m long. riage was designed in such a manner that
564 m of the tunnel at an inclination of horizontal loads could also be transferred
0.2% were constructed using the mining without any additional measures. The rein-
method and open construction was used forcement scaffolding used VARIOKIT
for the portals. system components and was constructed
as 12.50 m long working platforms at three
PERI supplied a tunnel formwork carriage different heights.
with a steel formwork skin and hydraulic
control system, additional formwork material The hydraulically equipped formwork car-
The leading, mobile reinforcement scaffolding was con- for the portal, system formwork for forming riage was a major factor in the rapid con-
structed entirely with PERI standard elements from the
VARIOKIT construction set.
the tunnel bottom plate and mobile rein- struction progress, allowing the formwork
forcement scaffolding. The 7.50 m long steel to be erected, lowered and moved quickly
formwork carriage was equipped with and efficiently. Safety was provided by extra
diverse accessories such as concrete pump integrated access and working platforms.
connector and outer vibrators. The design The tunnel formwork carriage in erected and
struck states. The striking process could be
performed completely hydraulically.

In position Retracted

Tunnel formwork carriage in concreting


position and retracted. Retracting could
be done completely hydraulically.
10.18

The steel formwork carriage was also used for con-


structing the portals. RCS rails, SLS heavy duty spindles
and flexible VARIO GT 24 girder formwork allowed
adjustment to suit the special form.

12.00

The tunnel formwork carriage in use: concreting the All adjustments to the formwork cross-section when
normal cross-section. positioning and striking were hydraulically assisted.

148

10129900_Peri_Tunnel_134-157.indb 148 20.03.12 16:14


Mining method

Contractor
Firesta-Fier, rekonstrukce, stavby a.s., Brnn
Field service
PERI Jesenice, Czech Republic

149

10129900_Peri_Tunnel_134-157.indb 149 20.03.12 16:14


Santiago de Chile underground railway, Chile
10 m in one cycle Hydraulic formwork carriage moved daily

The I.M.S. construction group was respon- in PERIs extensive experience in the con- was required. The PERI solution comprised
sible for the expansion of the number 5 struction of special formwork and the fact two 10 m long formwork carriages that
underground railway line in Santiago de that PERI was represented on location with could be hydraulically controlled. This
Chile, which included a 1,500 m long tunnel the necessary engineering know-how and allowed the moving, positioning, striking
cross-section constructed using the mining support. and lowering of the formwork to be per-
method. PERI developed and supplied the formed quickly and easily.
formwork solution for the underground In order to keep to the specified timetable,
structure. The decisive factors for awarding a formwork allowing the construction of
the contract were the trust that I.M.S. had one complete concreting section per day

In position Retracted
7.70

10.00

Longitudinal section of the formwork carriage construc- For striking the formwork, four hydraulic cylinders are used for the side formwork and another four
tion in position. The filling level during concreting is for raising and lowering. All cylinders could be independently controlled from the hydraulic control
checked from the bulkhead. centre. The formwork carriage was moved using two hydraulic motors on the front cogs.

The two 40 t formwork carriages


were conceived and built in only
1.5months.

150

10129900_Peri_Tunnel_134-157.indb 150 20.03.12 16:14


Mining method

Contractor Formwork solution used Formwork surface area


I.M.S. Ltda.
(Ingecol, Mendes Junior and Sikal)
2 formwork carriages, 10 m long 178.6 m per unit
Field service
PERI Spain, PERI Chile Hydraulics Concrete volume per section
4 lifting cylinders, 4 cylinders 72 m
for the side walls,
2 drive motors, Time required for striking,
1 hydraulic control system moving and positioning
3 hours
Compression equipment
16 pneumatic vibrators Striking commencement
on each formwork carriage 12 hours after concreting

Weight of one formwork carriage Concreting sections


40 tonnes 10 m per day and formwork carriage

151

10129900_Peri_Tunnel_134-157.indb 151 20.03.12 16:14


Torcaz railway tunnel, Subtramo Madrid Zaragoza, Spain
Hydraulically assisted positioning and moving of the formwork
Steel formwork moved daily

Preparation of the last formwork section


at the entrance / exit. The outer vault
0.70

formwork and part of the bulkhead form-


work are already positioned at this time.
9.46

The normal cross-section with inner


In position Retracted
and outer formwork. Left: in position.
Right: with retracted outer formwork
1.20 14.91 1.20 after concreting and the inner form-
work in transport position.

152

10129900_Peri_Tunnel_134-157.indb 152 20.03.12 16:14


Mining method

The Torcaz tunnel is part of the Spanish cycle. The portal-based construction also One12 m tunnel segment was poured each
high-speed railway link (Lav) from Madrid to allowed unhindered construction site traffic day with the steel formwork skin provid-
Zaragoza. 1.00 m thick solid cladding on the along the tunnel axis for material and ing a high quality concrete surface at the
raw tunnel tubes was necessary in order to machines. The vaulted steel formwork same time. Construction wassuccessfully
secure the mined tunnel. transferred the concrete load into the strip completed in only three months using this
foundation. formwork solution.
PERI developed a tailor-made formwork car-
riage concept especially for this project: The steel formwork without ties could be
Amovable support frame was used for hydraulically erected and struck, which
moving the steel formwork from cycle to allowed quick construction progress:

Contractor
Ferrovial
Field service
PERI Madrid, Spain

9.46
14.91
12.10

The longitudinal section shows the formwork carriage The portal design of the supporting structure allowed transit along
construction with the concreting cycle length of 12 m. the tunnel.

The front formwork was designed using a special


steelconstruction mounted on the supporting frame.
The hydraulic system used engine and Asecured working platform provided safe access to
cylinders was designed for heavy loads. thevault area of the formwork.

153

10129900_Peri_Tunnel_134-157.indb 153 20.03.12 16:14


Odelouca Tunnel, Serra de Monchique, Portugal
Hydraulic positioning and striking
with a self-moving full-round formwork

A tunnel at the Odelouca dam in Portugal is


used to regulate the level of water. This
mined 470 m tube with an almost perfectly
circular cross-section had to be clad with
a45 cm thick monolithically constructed
concrete mantle.

PERI Portugal constructed and supplied


aself-supporting, self-moving tunnel
formwork for this task, which could be
hydraulically moved, erected and struck.
This allowed up to three 10 m sections to
be concreted per week. The concreting
work could thus be efficiently completed
in4.5 months.

Ing. Ricardo
Carapinha
Site Manager

PERI provided us with exemplary


support in this project and the techni-
cal solution completely fulfilled our
expectations.
5.08

5.08

5.08

4.30 4.30 4.30

Bottom plate formwork still in position, steel form- Section of the carriage construction with the retracted
Steel formwork in concreting position. work elements hydraulically retracted. bottom plate formwork in the transport position.

154

10129900_Peri_Tunnel_134-157.indb 154 20.03.12 16:14


Mining method

The carriage motion and all formwork positioning and


striking procedures could be hydraulically controlled
from a single place.

Functional sequence

Transport carriage moved


underthe vault formwork,
1stpart of formwork erection.

Transportation to the position


forthe next cycle.

2nd part of formwork


positioning. Transportation
intoposition.

The sturdy carriage construction moved the entire form-


work safely from cycle to cycle.

Closing the gaps


(formwork positioning).

Transport carriage moved


backto accommodate bottom
plate formwork (striking).

Bottom plate formwork in The solid steel formwork always produced good concret-
transport position on the ing results, even after being used many times.
carriage.

Transport through the vault


formwork. Positioning of the
bottom plate formwork.

Contractor
Epos Lda.
Field service
PERI Portugal

155

10129900_Peri_Tunnel_134-157.indb 155 20.03.12 16:14


Haiku and Halavawa tunnel project, Hawaii, USA
High walls and rough surface structure using PERI VARIO

View of the entrance and exit portal.

The rough surface structure helped to integrate the huge Portal of the Haiku tunnel formed with the VARIO GT 24
tunnel portals in the lava rock landscape. The unusual girder wall formwork on KGF 240 scaffolding.
washboard structure was created using extra battens on
the formwork skin.

0.73 1.06

The H3 highway in Hawaii connects Kaneohe Formwork and scaffolding remained con-
and Pearl Harbour. The Haiku and Halavawa nected when moving, which allowed this
tunnel project is part of this highway. tobe performed quickly and easily. The
retracted formwork served as a safety
VARIO GT 24 wall formwork on KGF 240 measure during the subsequent reinforce-
scaffolding was used for forming the two ment work.
tunnel portals. The formwork was connect-
ed to the scaffolding via a carriage and
5.94

could be retracted by a maximum of 75 cm


for cleaning.

Contractor
E.E.Black, Honolulu, Hawaii,
(Haiku Tunnel construction segment)
Hawaiian Dredging & Construction
A section through the self-climbing form- (Halavawa Tunnel construction segment)
work: Left: already retracted for cleaning, Field service
right: still in concreting position. PERI Baltimore, USA

156

10129900_Peri_Tunnel_134-157.indb 156 20.03.12 16:14


Landfill inspection tunnel, Mining method

Klliken, Switzerland
Exact design and highest concrete quality
Special steel tunnel formwork construction

The bulkhead formwork was also easily solved, steel The control system for the vibrators/outer vibrators The tunnel bottom plate was concreted in advance in
walers held the squared timber pieces in the required clearly laid out. 12.30 m sections using the bottom plate formwork.
position. Wooden wedges were used for appropriate Theconstruction could be adjusted to suit the variable
fastening. curve radii of the tunnel.

A pedestrian tunnel was constructed to PERI constructed and delivered two form- Contractor
Walo Bertschinger, Zurich
allow monitoring of a special waste landfill work solutions for this, with lengths of Field service
in the Swiss Canton of Aargau. In order to 12.30 m and 4.00 m. The special formwork PERI Ohringen, Switzerland
clad the tunnel tube with an approximately carriage constructions were equipped with
30 cm thick concrete mantle, the construc- a 6 mm thick steel formwork skin. This con-
tion company needed a tunnel formwork struction allowed consistently high concrete
system that could accommodate two differ- surface quality over the entire construction
ent radii in the 538 m tunnel. time.

The cross-section with the tunnel form-


work in concreting position.

0.25
2.57
0.48

0.33 2.94 0.33

The 12.00 m long tunnel formwork


during pre-installation.

157

10129900_Peri_Tunnel_134-157.indb 157 20.03.12 16:14


PERI International 42

19
20

22 32 44

34
18
38
11
52
6
21
01 PERI GmbH 1
5
Rudolf-Diesel-Strasse
17 46
89264 Weissenhorn
info @ peri.com 2 30
www.peri.com 3 16
13
29
28
9
53
24 48
4
41

61
33 12

02 France 09 Italy 16 Austria 23 Korea 29 Slovania


PERI S.A.S. PERI S.p.A. PERI Ges.mbH PERI (Korea) Ltd. PERI Slowenien
77109 Meaux Cedex 20060 Basiano 3134 Nudorf ob der Traisen Seoul 135-080 2000 Maribor
peri.sas@peri.fr info@peri.it office@peri.at info@perikorea.com peri.slo@triera.net
www.peri.fr www.peri.it www.peri.at www.perikorea.com www.peri.com

03 Switzerland 10 Japan 17 Czech Republic 24 Portugal 30 Slovakia


PERI AG PERI Japan K.K. PERI spol. s r.o. PERIcofragens Lda PERI spol. s r.o.
8472 Ohringen Tokyo 103-0015 252 42 Jesenice u Prahy 2790-326 Queijas 903 01 Senec
info@peri.ch info@perijapan.jp info@peri.cz info@peri.pt info@peri.sk
www.peri.ch www.perijapan.jp www.peri.cz www.peri.pt www.peri.sk

04 Spain 11 United Kingdom/Ireland 18 Denmark 25 Argentina 31 Australia


PERI S.A. PERI Ltd. PERI Danmark A/S PERI S.A. PERI Australia Pty. Ltd.
28110 Algete - Madrid Rugby, CV23 0AN 2670 Greve B1625GPA Escobar Bs. As. Glendenning NSW 2761
info@peri.es info@peri.ltd.uk peri@peri.dk info@peri.com.ar info@periaus.com.au
www.peri.es www.peri.ltd.uk www.peri.dk www.peri.com.ar www.periaus.com.au

05 Belgium/Luxembourg 12 Turkey 19 Finland 26 Brazil 32 Estonia


N.V. PERI S.A. PERI Kalp ve skeleleri PERI Suomi Ltd. Oy PERI Formas e PERI AS
1840 Londerzeel Esenyurt / stanbul 34510 05460 Hyvink Escoramentos Ltda. 76406 Saku vald
info@peri.be info@peri.com.tr info@perisuomi.fi Vargem Grande Paulista Harjumaa
www.peri.be www.peri.com.tr www.perisuomi.fi So Paulo peri@peri.ee
info@peribrasil.com.br www.peri.ee
06 Netherlands 13 Hungary 20 Norway www.peribrasil.com.br
PERI B.V. PERI Kft.. PERI Norge AS 33 Greece
5480 AH-Schijndel 1181 Budapest 3036 Drammen 27 Chile PERI Hellas Ltd.
info@peri.nl info@peri.hu info@peri.no PERI Chile Ltda. 194 00 Koropi
www.peri.nl www.peri.hu www.peri.no Colina, Santiago de Chile info@perihellas.gr
peri.chile@peri.cl www.perihellas.gr
07 USA 14 Malaysia 21 Poland www.peri.cl
PERI Formwork Systems, Inc. PERI Formwork Malaysia PERI Polska Sp. z o.o. 34 Latvia
Elkridge, MD 21075 Sdn. Bhd. 05-860 Pochocin 28 Romania PERI SIA
info@peri-usa.com 43300 Seri Kembangan, info@peri.pl.pl PERI Romnia SRL 2118 Salaspils novads,
www.peri-usa.com Selangor Darul Ehsan www.peri.pl.pl 077015 Baloteti Rigas rajons
info@perimalaysia.com info@peri.ro info@peri-latvija.lv
08 Indonesia www.perimalaysia.com 22 Sweden www.peri.ro www.peri-latvija.lv
PT Beton Perkasa Wijaksana PERIform Sverige AB
Jakarta 10210 15 Singapore 30013 Halmstad 35 United Arab Emirates
bpw@betonperkasa.com PERI ASIA Pte. Ltd peri@periform.se PERI (L.L.C.)
www.peri.com Singapore 387355 www.periform.se Dubai
pha@periasia.com perillc@perime.com
www.periasia.com www.perime.com

158

Fachbuch Tunnel_Export_EN.indb 158 08.03.12 16:45


44
36

43

7 23
50 51 10
37
39 54
40 57
60 56
49 47 59
58 35 55
66

65
63
14
15

62 26 64

27
31
45
25

36 Canada 42 Iceland 49 Mexico 55 India 62 Peru


PERI Formwork Systems, Inc. Armar ehf. PERI Cimbras y Andamios, PERI (India) Pvt Ltd PERI Peruana SAC
Bolton, ON L7E 1K1 220 Hafnarfjrur S.A. de C.V. Mumbai 400064 Villa El Salvador, Lima
info@peri.ca www.armar.is Estado de Mxico, info@peri.in contacto@peri.com.pe
www.peri.ca info@peri.com.mx www.peri.in www.peri.com.pe
43 Kazakhstan www.peri.com.mx
37 Lebanon TOO PERI Kazakhstan 56 Jordan 63 Panama
Lebanon Representative Office 050059 Almaty 50 Azerbaijan PERI GmbH - Jordan PERI Panama Inc.
Jdeideh peri@peri.kz PERI Kalp ve skeleleri 11947 Amman 0832-00155 Panama City
lebanon@peri.de www.peri.kz Baku jordan@peri.com info@peri.com.pa
www.peri.de peribaku@peri.com.tr www.peri.com www.peri.com.pa
44 Russian Federation www.peri.com.tr
38 Lithuania OOO PERI 57 Kuwait 64
Angola
PERI UAB 142407, Noginsk District 51 Turkmenistan PERI Kuwait PERIcofragens, Lda.
02300 Vilnius moscow@peri.ru PERI Kalp ve skeleleri 13011 Kuwait Luanda
info@peri.lt www.peri.ru Agabat kuwait@peri.com renato.portugal@peri.pt
www.peri.lt ahmet.kadioglu@peri.com.tr www.peri.com www.peri.pt
45 South Africa www.peri.com.tr
39 Morocco Wiehahn Formwork and 58 Saudi Arabia 65
Nigeria
PERI S.A. Scaffolding (Pty) Ltd. 52 Belorussia PERI Engineering Heights Access Nigeria Ltd.
Tanger 7600 Stellenbosch PERI Belarus Division of Jamjoom Victoria Island, Lagos
peri25@menara.ma info@wiehahn.co.za 220100 Minsk Consult Saudi Arabia info@heightsaccessng.com
www.peri.com www.wiehahn.co.za info@peri.by 21463 Jeddah www. heightsaccessng.com
www.peri.by info@peri.com.sa
40 Israel 46 Ukraine www.peri.com.sa 66 Oman
PERI Formwork TOW PERI Ukraina 53 Croatia PERI (L.L.C.)
Engineering Ltd 07400 Brovary PERI oplate i skele d.o.o. 59 Qatar Muscat
Petach Tikva, 49002 peri@peri.ua 10 250 Donji Stupnik/ PERI Qatar LLC perimct@perime.com
info@peri.co.il www.peri.ua Zagreb P.O.Box: 31295 - Doha www.perime.com
www.peri.co.il info@peri.com.hr info@periqatar.com
47 Egypt www.peri.com.hr www.periqatar.com
41 Bulgaria Egypt Branch Office
PERI Bulgaria EOOD 11361 Heliopolis / Cairo 54 Iran 60 Algeria
1839 Sofia info@peri.com.eg PERI GmbH Socit PERI S.A.S.
peri.bulgaria@peri.bg www.peri.com.eg Iran Branch Office Kouba - Alger
www.peri.bg Tehran peri.alger@peri.fr
48 Serbia info@peri.ir www.peri.fr
PERI Oplate d.o.o. www.peri.ir
11272 Dobanovci 61 Albania
office@peri.rs PERI Sh.p.k.
www.peri.rs Tirane
erti.hasanaj@peri.com.tr
www.peri.com.tr

159

Fachbuch Tunnel_Export_EN.indb 159 08.03.12 16:45


Formwork
Scaffolding
Engineering

www.peri.com

Successful construction with PERI