Professional Documents
Culture Documents
METRADO PU
PARTIDA DE CONTROL DESCRIPCION REV 01 Und. DIRECTO (S/.)
8,509,078.02
1,472,096.67
256,220.24
171,484.00
44,602.68
27,820.80
317,016.08
15,282.63
106,190.69
79,117.84
17,810.42
436,551.28
1,053,119.34
211,796.03
120,739.28
42,347.57
332,027.75
91,980.79
198,844.59
14,215.01
28,494.21
12,674.11
703,894.70
210,811.88
66,173.80
22,741.38
307,733.72
70,611.18
25,822.74
992,429.78
149,483.78
96,712.92
33,756.15
404,702.86
105,733.77
148,824.02
13,007.26
33,171.32
7,037.72
1,173,411.72
210,582.27
173,323.50
60,297.13
446,132.38
114,322.52
118,761.62
9,561.28
35,699.99
4,731.03
1,127,063.09
164,179.86
152,486.79
53,048.29
465,927.90
113,417.85
127,744.56
9,108.93
36,029.82
5,119.08
975,478.14
114,963.57
126,601.88
43,120.78
377,026.32
97,967.91
165,744.09
12,366.78
30,772.07
6,914.75
989,534.47
102,341.64
122,850.71
41,843.13
399,284.13
105,950.97
164,197.11
13,495.67
33,310.73
6,260.38
22,050.11
8,684.74
3,855.63
9,509.74
ANALISIS DE PRECIOS UNITARIOS
Rendimiento m3/DIA 200.0000 EQ. 200.0000 Costo unitario directo por : m3 13.64
Cdigo Descripcin Recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.
Mano de Obra
0147010001 CAPATAZ hh 0.1000 0.0040 23.01 0.09
0147010004 PEON hh 4.0000 0.1600 13.02 2.08
2.17
Equipos
0337010001 HERRAMIENTAS MANUALES %MO 0.0300 2.17 0.07
0349060058 EXCAVADORA 330 CL hm 1.0000 0.0400 285.00 11.40
11.47
Rendimiento m3/DIA 55.0000 EQ. 55.0000 Costo unitario directo por : m3 34.34
Cdigo Descripcin Recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.
Mano de Obra
0147010001 CAPATAZ hh 0.3000 0.0436 23.01 1.00
0147010002 OPERARIO hh 1.0000 0.1455 17.31 2.52
0147010004 PEON hh 4.0000 0.5818 13.02 7.58
11.10
Equipos
0337010001 HERRAMIENTAS MANUALES %MO 0.0300 11.10 0.33
0348120094 CAMION CISTERNA 3,500 gl hm 0.2500 0.0364 90.00 3.27
0349040091 MINICARGADOR BOBCAT hm 1.0000 0.1455 75.00 10.91
0349110010 RODILLO LISO VIBRATORIO hm 1.0000 0.1455 60.00 8.73
23.24
Rendimiento m3/DIA 450.0000 EQ. 450.0000 Costo unitario directo por : m3 9.97
Cdigo Descripcin Recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.
Mano de Obra
0147010001 CAPATAZ hh 0.1000 0.0018 23.01 0.04
0147010004 PEON hh 1.0000 0.0178 13.02 0.23
0.27
Equipos
0337010001 HERRAMIENTAS MANUALES %MO 0.0300 0.27 0.01
0348040034 CAMION VOLQUETE 12 m3 hm 3.0000 0.0533 135.00 7.20
0349040009 CARGADOR SOBRE LLANTAS 125 HP 2.5 yd3 hm 1.0000 0.0178 140.00 2.49
9.70
Rendimiento m2/DIA 150.0000 EQ. 150.0000 Costo unitario directo por : m2 26.75
Cdigo Descripcin Recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.
Mano de Obra
0147010001 CAPATAZ hh 0.2000 0.0107 23.01 0.25
0147010002 OPERARIO hh 3.0000 0.1600 17.31 2.77
0147010003 OFICIAL hh 2.0000 0.1067 14.13 1.51
0147010004 PEON hh 12.0000 0.6400 13.02 8.33
12.86
Materiales
0242110001 MADERA TORNILLO p2 3.0000 4.50 13.50
13.50
Equipos
0337010001 HERRAMIENTAS MANUALES %MO 0.0300 12.86 0.39
0.39
Rendimiento m3/DIA 60.0000 EQ. 60.0000 Costo unitario directo por : m3 44.16
Cdigo Descripcin Recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.
Mano de Obra
0147010001 CAPATAZ hh 0.2000 0.0267 23.01 0.61
0147010002 OPERARIO hh 2.0000 0.2667 17.31 4.62
0147010003 OFICIAL hh 2.0000 0.2667 14.13 3.77
0147010004 PEON hh 8.0000 1.0667 13.02 13.89
22.89
Materiales
0205000033 PIEDRA GRANDE m3 0.3000 52.00 15.60
0229010043 CURADOR ACRILICO gal 0.0400 12.00 0.48
0242110001 MADERA TORNILLO p2 1.0000 4.50 4.50
20.58
Equipos
0337010001 HERRAMIENTAS MANUALES %MO 0.0300 22.89 0.69
0.69
Rendimiento m3/DIA 70.0000 EQ. 70.0000 Costo unitario directo por : m3 31.81
Cdigo Descripcin Recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.
Mano de Obra
0147010001 CAPATAZ hh 0.1000 0.0114 23.01 0.26
0147010002 OPERARIO hh 2.0000 0.2286 17.31 3.96
0147010003 OFICIAL hh 2.0000 0.2286 14.13 3.23
0147010004 PEON hh 8.0000 0.9143 13.02 11.90
19.35
Materiales
0229010043 CURADOR ACRILICO gal 0.0400 12.00 0.48
0242110001 MADERA TORNILLO p2 2.0000 4.50 9.00
9.48
Equipos
0337010001 HERRAMIENTAS MANUALES %MO 0.0300 19.35 0.58
0349070051 VIBRADOR DE CONCRETO hm 2.0000 0.2286 10.50 2.40
0349510094 BOMBA DE CONCRETO 15 m3/h m3 0.0000 25.00 0.00
2.98
Rendimiento kg/DIA 700.0000 EQ. 700.0000 Costo unitario directo por : kg 0.74
Cdigo Descripcin Recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.
Mano de Obra
0147010001 CAPATAZ hh 0.1000 0.0011 23.01 0.03
0147010002 OPERARIO hh 1.0000 0.0114 17.31 0.20
0147010003 OFICIAL hh 1.0000 0.0114 14.13 0.16
0147010004 PEON hh 1.0000 0.0114 13.02 0.15
0.54
Materiales
0202000010 ALAMBRE NEGRO # 16 kg 0.0300 4.50 0.14
0.14
Equipos
0337010001 HERRAMIENTAS MANUALES %MO 0.0300 0.54 0.02
0348960008 CIZALLA ELECTRICA PARA CORTE DE FIERRO hm 0.5000 0.0057 4.00 0.02
0348960009 DOBLADORA PARA FIERRO hm 0.5000 0.0057 4.00 0.02
0.06
Rendimiento m3/DIA 70.0000 EQ. 70.0000 Costo unitario directo por : m3 31.81
Cdigo Descripcin Recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.
Mano de Obra
0147010001 CAPATAZ hh 0.1000 0.0114 23.01 0.26
0147010002 OPERARIO hh 2.0000 0.2286 17.31 3.96
0147010003 OFICIAL hh 2.0000 0.2286 14.13 3.23
0147010004 PEON hh 8.0000 0.9143 13.02 11.90
19.35
Materiales
0229010043 CURADOR ACRILICO gal 0.0400 12.00 0.48
0242110001 MADERA TORNILLO p2 2.0000 4.50 9.00
9.48
Equipos
0337010001 HERRAMIENTAS MANUALES %MO 0.0300 19.35 0.58
0349070051 VIBRADOR DE CONCRETO hm 2.0000 0.2286 10.50 2.40
0349510094 BOMBA DE CONCRETO 15 m3/h m3 0.0000 25.00 0.00
2.98
Rendimiento m2/DIA 12.0000 EQ. 12.0000 Costo unitario directo por : m2 75.49
Cdigo Descripcin Recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.
Mano de Obra
0147010001 CAPATAZ hh 0.1000 0.0667 23.01 1.53
0147010002 OPERARIO hh 1.0000 0.6667 17.31 11.54
0147010003 OFICIAL hh 1.0000 0.6667 14.13 9.42
28.53
Materiales
0202000015 ALAMBRE NEGRO # 8 kg 0.4500 4.50 2.03
0202010005 CLAVOS PARA MADERA CON CABEZA DE 3" kg 0.2000 4.05 0.81
0242110001 MADERA TORNILLO p2 1.5000 4.50 6.75
9.59
Equipos
0337010001 HERRAMIENTAS MANUALES %MO 0.0300 28.53 0.86
0348990001 ENCOFRADO METALICO m2 1.0000 35.00 35.00
37.37
Subpartidas
900305150203 DESENCOFRADO m2 1.0000 7.55 7.55
7.55
Rendimiento kg/DIA 700.0000 EQ. 700.0000 Costo unitario directo por : kg 0.74
Cdigo Descripcin Recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.
Mano de Obra
0147010001 CAPATAZ hh 0.1000 0.0011 23.01 0.03
0147010002 OPERARIO hh 1.0000 0.0114 17.31 0.20
0147010003 OFICIAL hh 1.0000 0.0114 14.13 0.16
0147010004 PEON hh 1.0000 0.0114 13.02 0.15
0.54
Materiales
0202000010 ALAMBRE NEGRO # 16 kg 0.0300 4.50 0.14
0.14
Equipos
0337010001 HERRAMIENTAS MANUALES %MO 0.0300 0.54 0.02
0348960008 CIZALLA ELECTRICA PARA CORTE DE FIERRO hm 0.5000 0.0057 4.00 0.02
0348960009 DOBLADORA PARA FIERRO hm 0.5000 0.0057 4.00 0.02
0.06
Rendimiento m3/DIA 36.0000 EQ. 36.0000 Costo unitario directo por : m3 64.26
Cdigo Descripcin Recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.
Mano de Obra
0147010001 CAPATAZ hh 0.1000 0.0222 23.01 0.51
0147010002 OPERARIO hh 6.0000 1.3333 17.31 23.08
0147010003 OFICIAL hh 2.0000 0.4444 14.13 6.28
0147010004 PEON hh 8.0000 1.7778 13.02 23.15
53.02
Materiales
0229010043 CURADOR ACRILICO gal 0.0400 12.00 0.48
0242110001 MADERA TORNILLO p2 1.0000 4.50 4.50
4.98
Equipos
0337010001 HERRAMIENTAS MANUALES %MO 0.0300 53.02 1.59
0349070051 VIBRADOR DE CONCRETO hm 2.0000 0.4444 10.50 4.67
6.26
Rendimiento m2/DIA 14.0000 EQ. 14.0000 Costo unitario directo por : m2 45.46
Cdigo Descripcin Recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.
Mano de Obra
0147010001 CAPATAZ hh 0.1000 0.0571 23.01 1.31
0147010002 OPERARIO hh 1.0000 0.5714 17.31 9.89
0147010003 OFICIAL hh 1.0000 0.5714 14.13 8.07
23.84
Materiales
0202000015 ALAMBRE NEGRO # 8 kg 0.3000 4.50 1.35
0202010005 CLAVOS PARA MADERA CON CABEZA DE 3" kg 0.1000 4.05 0.41
0242110001 MADERA TORNILLO p2 4.0000 4.50 18.00
20.90
Equipos
0337010001 HERRAMIENTAS MANUALES %MO 0.0300 23.84 0.72
0.72
Subpartidas
900305150201 DESENCOFRADO m2 1.0000 5.71 5.71
5.71
Rendimiento kg/DIA 700.0000 EQ. 700.0000 Costo unitario directo por : kg 0.74
Cdigo Descripcin Recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.
Mano de Obra
0147010001 CAPATAZ hh 0.1000 0.0011 23.01 0.03
0147010002 OPERARIO hh 1.0000 0.0114 17.31 0.20
0147010003 OFICIAL hh 1.0000 0.0114 14.13 0.16
0147010004 PEON hh 1.0000 0.0114 13.02 0.15
0.54
Materiales
0202000010 ALAMBRE NEGRO # 16 kg 0.0300 4.50 0.14
0.14
Equipos
0337010001 HERRAMIENTAS MANUALES %MO 0.0300 0.54 0.02
0348960008 CIZALLA ELECTRICA PARA CORTE DE FIERRO hm 0.5000 0.0057 4.00 0.02
0348960009 DOBLADORA PARA FIERRO hm 0.5000 0.0057 4.00 0.02
0.06
Rendimiento m3/DIA 28.0000 EQ. 28.0000 Costo unitario directo por : m3 74.43
Cdigo Descripcin Recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.
Mano de Obra
0147010001 CAPATAZ hh 0.1000 0.0286 23.01 0.66
0147010002 OPERARIO hh 1.0000 0.2857 17.31 4.95
0147010003 OFICIAL hh 2.0000 0.5714 14.13 8.07
0147010004 PEON hh 10.0000 2.8571 13.02 37.20
50.88
Materiales
0229010043 CURADOR ACRILICO gal 0.0400 12.00 0.48
0242110001 MADERA TORNILLO p2 2.5000 4.50 11.25
11.73
Equipos
0337010001 HERRAMIENTAS MANUALES %MO 0.0300 50.88 1.53
0348090011 ANDAMIO METAL/ALQUILER hm 3.0000 0.8571 5.00 4.29
0349070051 VIBRADOR DE CONCRETO hm 2.0000 0.5714 10.50 6.00
0349510094 BOMBA DE CONCRETO 15 m3/h m3 0.0000 25.00 0.00
11.82
Rendimiento m2/DIA 12.0000 EQ. 12.0000 Costo unitario directo por : m2 97.38
Cdigo Descripcin Recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.
Mano de Obra
0147010001 CAPATAZ hh 0.1000 0.0667 23.01 1.53
0147010002 OPERARIO hh 1.0000 0.6667 17.31 11.54
0147010003 OFICIAL hh 1.0000 0.6667 14.13 9.42
0147010004 PEON hh 1.0000 0.6667 13.02 8.68
43.23
Materiales
0202000015 ALAMBRE NEGRO # 8 kg 0.4000 4.50 1.80
0202010005 CLAVOS PARA MADERA CON CABEZA DE 3" kg 0.1000 4.05 0.41
0242110001 MADERA TORNILLO p2 1.0000 4.50 4.50
6.71
Equipos
0337010001 HERRAMIENTAS MANUALES %MO 0.0300 43.23 1.30
0348990086 ENCOFRADO METALICO COLUMNA m2 1.0000 45.00 45.00
47.44
Subpartidas
900305150201 DESENCOFRADO m2 1.0000 5.71 5.71
900305150205 SOLAQUEO m2 1.0000 7.49 7.49
13.20
Rendimiento kg/DIA 700.0000 EQ. 700.0000 Costo unitario directo por : kg 0.97
Cdigo Descripcin Recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.
Mano de Obra
0147010001 CAPATAZ hh 0.1000 0.0011 23.01 0.03
0147010002 OPERARIO hh 1.0000 0.0114 17.31 0.20
0147010003 OFICIAL hh 1.0000 0.0114 14.13 0.16
0147010004 PEON hh 1.0000 0.0114 13.02 0.15
0.54
Materiales
0202000010 ALAMBRE NEGRO # 16 kg 0.0300 4.50 0.14
0202000015 ALAMBRE NEGRO # 8 kg 0.0500 4.50 0.23
0230140029 EMPALMES MECANICOS Y CONECTORES EN COLUMNAS kg 0.0000 1.66 0.00
0.37
Equipos
0337010001 HERRAMIENTAS MANUALES %MO 0.0300 0.54 0.02
0348960008 CIZALLA ELECTRICA PARA CORTE DE FIERRO hm 0.5000 0.0057 4.00 0.02
0348960009 DOBLADORA PARA FIERRO hm 0.5000 0.0057 4.00 0.02
0.06
Rendimiento m3/DIA 30.0000 EQ. 30.0000 Costo unitario directo por : m3 65.47
Cdigo Descripcin Recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.
Mano de Obra
0147010001 CAPATAZ hh 0.1000 0.0267 23.01 0.61
0147010002 OPERARIO hh 2.0000 0.5333 17.31 9.23
0147010003 OFICIAL hh 3.0000 0.8000 14.13 11.30
0147010004 PEON hh 8.0000 2.1333 13.02 27.78
48.92
Materiales
0229010043 CURADOR ACRILICO gal 0.0400 12.00 0.48
0242110001 MADERA TORNILLO p2 2.0000 4.50 9.00
9.48
Equipos
0337010001 HERRAMIENTAS MANUALES %MO 0.0300 48.92 1.47
0349070051 VIBRADOR DE CONCRETO hm 2.0000 0.5333 10.50 5.60
0349510094 BOMBA DE CONCRETO 15 m3/h m3 0.0000 25.00 0.00
7.07
Rendimiento m2/DIA 10.0000 EQ. 10.0000 Costo unitario directo por : m2 322.70
Cdigo Descripcin Recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.
Mano de Obra
0147010001 CAPATAZ hh 0.1000 0.0800 23.01 1.84
0147010002 OPERARIO hh 1.0000 0.8000 17.31 13.85
0147010003 OFICIAL hh 1.0000 0.8000 14.13 11.30
0147010004 PEON hh 1.0000 0.8000 13.02 10.42
52.89
Materiales
0202000015 ALAMBRE NEGRO # 8 kg 0.4000 4.50 1.80
0202010005 CLAVOS PARA MADERA CON CABEZA DE 3" kg 0.1000 4.05 0.41
0242110001 MADERA TORNILLO p2 1.0000 4.50 4.50
6.71
Equipos
0337010001 HERRAMIENTAS MANUALES %MO 0.0300 52.89 1.59
0348990087 ENCOFRADO METALICO Y APUNTALAMIENTO m2 1.0000 260.00 260.00
263.10
Subpartidas
900305150202 DESENCOFRADO DE VIGAS m2 1.0000 7.55 7.55
900305150204 SOLAQUEO DE VIGA m2 1.0000 9.44 9.44
16.99
Rendimiento kg/DIA 700.0000 EQ. 700.0000 Costo unitario directo por : kg 0.74
Cdigo Descripcin Recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.
Mano de Obra
0147010001 CAPATAZ hh 0.1000 0.0011 23.01 0.03
0147010002 OPERARIO hh 1.0000 0.0114 17.31 0.20
0147010003 OFICIAL hh 1.0000 0.0114 14.13 0.16
0147010004 PEON hh 1.0000 0.0114 13.02 0.15
0.54
Materiales
0202000010 ALAMBRE NEGRO # 16 kg 0.0300 4.50 0.14
0230140031 EMPALMES MECANICOS EN VIGA kg 0.0000 1.15 0.00
0.14
Equipos
0337010001 HERRAMIENTAS MANUALES %MO 0.0300 0.54 0.02
0348960008 CIZALLA ELECTRICA PARA CORTE DE FIERRO hm 0.5000 0.0057 4.00 0.02
0348960009 DOBLADORA PARA FIERRO hm 0.5000 0.0057 4.00 0.02
0.06
Rendimiento m3/DIA 35.0000 EQ. 35.0000 Costo unitario directo por : m3 73.78
Cdigo Descripcin Recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.
Mano de Obra
0147010001 CAPATAZ hh 0.1000 0.0229 23.01 0.53
0147010002 OPERARIO hh 6.0000 1.3714 17.31 23.74
0147010003 OFICIAL hh 3.0000 0.6857 14.13 9.69
0147010004 PEON hh 8.0000 1.8286 13.02 23.81
57.77
Materiales
0229010043 CURADOR ACRILICO gal 0.0400 12.00 0.48
0242110001 MADERA TORNILLO p2 2.0000 4.50 9.00
9.48
Equipos
0337010001 HERRAMIENTAS MANUALES %MO 0.0300 57.77 1.73
0349070051 VIBRADOR DE CONCRETO hm 2.0000 0.4571 10.50 4.80
0349510094 BOMBA DE CONCRETO 15 m3/h m3 0.0000 25.00 0.00
6.53
Rendimiento m2/DIA 10.0000 EQ. 10.0000 Costo unitario directo por : m2 322.70
Cdigo Descripcin Recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.
Mano de Obra
0147010001 CAPATAZ hh 0.1000 0.0800 23.01 1.84
0147010002 OPERARIO hh 1.0000 0.8000 17.31 13.85
0147010003 OFICIAL hh 1.0000 0.8000 14.13 11.30
0147010004 PEON hh 1.0000 0.8000 13.02 10.42
52.89
Materiales
0202000015 ALAMBRE NEGRO # 8 kg 0.4000 4.50 1.80
0202010005 CLAVOS PARA MADERA CON CABEZA DE 3" kg 0.1000 4.05 0.41
0242110001 MADERA TORNILLO p2 1.0000 4.50 4.50
6.71
Equipos
0337010001 HERRAMIENTAS MANUALES %MO 0.0300 52.89 1.59
0348990087 ENCOFRADO METALICO Y APUNTALAMIENTO m2 1.0000 260.00 260.00
263.10
Subpartidas
900305150202 DESENCOFRADO DE VIGAS m2 1.0000 7.55 7.55
900305150204 SOLAQUEO DE VIGA m2 1.0000 9.44 9.44
16.99
Rendimiento kg/DIA 700.0000 EQ. 700.0000 Costo unitario directo por : kg 0.74
Cdigo Descripcin Recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.
Mano de Obra
0147010001 CAPATAZ hh 0.1000 0.0011 23.01 0.03
0147010002 OPERARIO hh 1.0000 0.0114 17.31 0.20
0147010003 OFICIAL hh 1.0000 0.0114 14.13 0.16
0147010004 PEON hh 1.0000 0.0114 13.02 0.15
0.54
Materiales
0202000010 ALAMBRE NEGRO # 16 kg 0.0300 4.50 0.14
0.14
Equipos
0337010001 HERRAMIENTAS MANUALES %MO 0.0300 0.54 0.02
0348960008 CIZALLA ELECTRICA PARA CORTE DE FIERRO hm 0.5000 0.0057 4.00 0.02
0348960009 DOBLADORA PARA FIERRO hm 0.5000 0.0057 4.00 0.02
0.06
Rendimiento m2/DIA 12.0000 EQ. 12.0000 Costo unitario directo por : m2 52.85
Cdigo Descripcin Recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.
Mano de Obra
0147010001 CAPATAZ hh 0.1000 0.0667 23.01 1.53
0147010002 OPERARIO hh 1.0000 0.6667 17.31 11.54
0147010003 OFICIAL hh 1.0000 0.6667 14.13 9.42
27.06
Materiales
0202000015 ALAMBRE NEGRO # 8 kg 0.4500 4.50 2.03
0202010005 CLAVOS PARA MADERA CON CABEZA DE 3" kg 0.2000 4.05 0.81
0242110001 MADERA TORNILLO p2 2.0000 4.50 9.00
11.84
Equipos
0337010001 HERRAMIENTAS MANUALES %MO 0.0300 27.06 0.81
0348990085 ENCOFRADO METALICO PEDESTAL m2 1.0000 12.00 12.00
13.95
Subpartidas
900305150201 DESENCOFRADO m2 1.0000 5.71 5.71
5.71
PRESUPUESTO
PU
METRADO
ITEM DESCRIPCION REV 01 Und. DIRECTO
(S/.)
DPTO: 421 INTERCAMBIADOR DE CALOR
1.00 OBRAS PRELIMINARES
1.10 Trazo y replanteo 1.00 Glb.
2.00 MOVIMIENTO DE TIERRAS
2.10 Excavaciones con maquina 18,784.48 m3. 13.64
2.20 Relleno compactado con material propio 12,712.62 m3. 34.34
2.30 Eliminacion de material excedente 17,200.00 m3. 9.97
3.00 CONCRETO SIMPLE
3.10 Solados
3.11 Coloc. de Concreto en solados e=4" 1,667.39 m2. 26.75
3.20 Sub Zapatas
3.21 Coloc. de Concreto para subzapatas 630.00 m3. 44.16
4.00 CONCRETO ARMADO
4.10 Zapatas
4.11 Coloc. de Concreto para zapatas 3,338.28 m3. 31.81
4.12 Encofrado y Desencofrado - Zapatas 289.17 m2. 52.85
4.13 Habilitacion y Colocacion de acero 287,977.19 kg. 0.74
4.20 Vigas de Cimentacin
4.21 Coloc. de Concreto para vigas de cimentacion 559.90
Inci de nci a m3. de 31.81
Costos por R ubros
-
-
256,220.24
436,551.28
171,484.00
-
-
44,602.68
-
27,820.80
-
-
106,190.69
15,282.63
213,103.12
-
a de Costos por17,810.42
R ubros
79,117.84
103,912.96
-
8,684.74
3,855.63
9,509.74
-
297,154.43
858,888.87
1,164,159.02
-
223,300.88
2,732,835.07
699,984.99
-
42,737.07
924,115.99
71,754.94
S/. 8,509,078.02
Comparacin de rendimientos promedio de CAPECO con rendimientos de la
Construccin Real
CAPECO
Item Descripcion Und Rendimiento CUADRILLA
Horario (8H) Cap Oper
1.00 OBRAS PRELIMINARES Glb.
1.10 Trazo y replanteo m2. 500.00 1 1
2.00 MOVIMIENTO DE TIERRAS
2.10 Excavaciones con maquina m3. 450.00 0.1 1
2.20 Relleno compactado con material propio m3. 7.00 0.1
2.30 Eliminacion de material excedente m3. 6.00 0.1
3.00 CONCRETO SIMPLE
3.10 Solados
3.11 Coloc. de Concreto en solados e=4" m2. 80.00 0.2 2
3.20 Sub Zapatas
3.21 Coloc. de Concreto para subzapatas m3.
4.00 CONCRETO ARMADO
4.10 Zapatas
4.11 Coloc. de Concreto para zapatas m3. 25.00 0.2 2
4.12 Encofrado y Desencofrado - Zapatas m2. 14.00 0.2 1
Desencofrado m2. 28.00
4.13 Habilitacion y Colocacion de acero kg. 250.00 0.2 2
4.20 Vigas de Cimentacin
4.21 Coloc. de Concreto para vigas de cimentacion m3. 20.00 0.2 2
4.22 Encofrado y desencofrado m2. 10.00 0.1 1
Desencofrado m2. 35.00
4.23 Habilitacion y Colocacion de acero kg. 250.00 0.2 2
4.30 Losa de Piso
4.31 Coloc. de Concreto para piso m3. 22.00 0.2 2
4.32 Encofrado y desencofrado m2. 15.00 0.1 1
Desencofrado m2. 45.00
4.33 Habilitacion y Colocacion de acero kg. 250.00 0.2 2
4.40 Columnas
4.41 Coloc. de Concreto para columnas m3. 10.00 0.2 2
4.42 Encofrado y desencofrado caravista m2. 10.00 0.1 1
Desencofrado m2. 40.00
4.43 Habilitacion y Colocacion de acero kg. 250.00 0.2 2
4.50 Vigas
4.51 Coloc. de Concreto para vigas m3. 20.00 0.2 2
4.52 Encofrado y desencofrado caravista m2. 9.00 0.1 1
Desencofrado m2. 36.00
4.53 Habilitacion y Colocacion de acero kg. 250.00 0.2 2
4.60 Losas de techo
4.61 Coloc. de Concreto para losas m3. 20.00 0.2 2
4.62 Encofrado y desencofrado caravista m2. 15.00 0.1 1
Desencofrado m2. 45.00
4.63 Habilitacion y Colocacion de acero kg. 250.00 0.2 2
Real
CAPECO EMPRESA N
CUADRILLA Rendimiento CUADRILLA
Ofic Pen Horario (8H) Cap Oper Ofic Pen
2
1
1
2.00 6
2.00 8
1.00
1.00 2
2.00
2.00 8
1.00
1.00 2
2.00
2.00 8
1.00
1.00 2
2.00
2.00 10.00
1.00
1.00 2
2.00
2.00 10.00
1.00
1.00 2
2.00
2.00 10.00
1.00
1.00 2
2.00
EPIC.PO.004
ESTIMACION DE DURACION DE ACTIVIDADES Revisin: 00
Fecha:
NOMBRE DEL PROYECTO: CODIGO: