Project Name: JIGCC Utilities & Common Area - Package 5 Project INSPECTION DATA SHEET PUMP SKIDS' FRAMES
Company Project No.: 02250
& SKID ASSEMBLY + SUF/NSF PREFABRICATION
WORK
Contractor Project No.: 950-2-0151 Company Doc No.:
HOLD
Project Name: JIGCC Utilities & Common Area - Package 5 Project INSPECTION DATA SHEET PUMP SKIDS' FRAMES
Company Project No.: 02250 & SKID ASSEMBLY + SUF/NSF PREFABRICATION
WORK
Contractor Project No.: 950-2-0151 Company Doc No.:
1. SCOPE AND PURPOSE ........................................................................................................................... 4
2. REFERENCE DOCUMENTS ..................................................................................................................... 4
3. DEFINITION & ABBREVIATION ............................................................................................................... 4
4. SURVEILLANCE AND INSPECTION REQUIREMENTS ......................................................................... 4
4.1 GENERAL ........................................................................................................................................... 4
4.2 DEFINITION OF INSPECTION POINTS ..................................................................................................... 5
4.3 QUALITY CONTROL CHART .................................................................................................................. 6
5. CHECKS AND TESTS DESCRIPTION ..................................................................................................... 7
Project Name: JIGCC Utilities & Common Area - Package 5 Project INSPECTION DATA SHEET PUMP SKIDS' FRAMES
Company Project No.: 02250 & SKID ASSEMBLY + SUF/NSF PREFABRICATION
WORK
Contractor Project No.: 950-2-0151 Company Doc No.:
2. REFERENCE DOCUMENTS
Refer to Vendor Document List and manufacturing surveillance instruction & quality control
requirement (02250-00-140-PD-0002 Rev 3) for additional information.
02250-00-140-PD-0002 Rev 3 QA, QC/INSPECTION AND EXPEDITING REQUIREMENTS FOR
VENDORS
4.1 General
SUB-VENDOR is responsible for carrying out, as a minimum, all inspection activities requested in
contractual specification and ITP approved by VENDOR /CONTRACTOR and/or COMPANY.
Such activities shall be performed at SUB-VENDORs premises as specified.
Project Name: JIGCC Utilities & Common Area - Package 5 Project INSPECTION DATA SHEET PUMP SKIDS' FRAMES
Company Project No.: 02250 & SKID ASSEMBLY + SUF/NSF PREFABRICATION
WORK
Contractor Project No.: 950-2-0151 Company Doc No.:
H (Hold Point) An inspection activity that requires the VENDOR /CONTRACTOR /COMPANY
/IA Inspector be notified by the SUB-VENDOR /Manufacturer /Constructor of a
specific time and place for the activity to be witnessed. Vendor is not allowed to
proceed with the test/inspection unless a written release is issued by the
CONTRACTOR.
W (Witness point) An inspection activity that requires the VENDOR /CONTRACTOR /COMPANY
/IA inspector to be notified by the SUB-VENDOR /Manufacturer /Constructor of a
specific time and place for the activity to be witnessed. If CONTRACTOR
/COMPANY inspector is unavailable, Vendor could proceed with the test
/inspection
M (Monitoring point) Quality Surveillance, Verification or Monitoring to be carried out during the
course of manufacture/fabrication to verify whether or not materials, items or
services meet the specified requirements. No advanced notification is required.
These activities may include audit, inspection, witnessing of testing, review of
quality documentation and personnel qualifications, and evaluation of personnel
performance. The VENDOR /CONTRACTOR /COMPANY Authorized Inspector
will use the Sub-Vendors ITP, QC documents and drawings to verify Quality
Control Point was checked and in compliance. The CONTRACTOR /COMPANY
Authorized Inspector shall have the authority to have any such activity performed
again in their presence when the documentation does not appear to reflect the
condition of the product
R (Review) an activity designated by the VENDOR /CONTRACTOR /COMPANY /IA that
requires the review and acceptance of the Sub-Vendor's documentation. No
formal inspection notification is required.
IW (Initial witness) Sub-Vendor is requested to notify VENDOR /CONTRACTOR /COMPANY / IA of
the initial inspection date/time. Sub-Vendor can proceed with the test /inspection
when the VENDOR /CONTRACTOR /COMPANY / IAs inspector is not present
at the notified time. Subsequent test/inspection will not be witnessed unless any
deficiencies are found at the initial inspection.
FI (Full Inspection) Vendor shall perform inspection or test for all quality control activity according to
CONTRACTOR / COMPANY approved procedure. This abbreviation is intended
to be used by Vendor only.
Project Name: JIGCC Utilities & Common Area - Package 5 Project INSPECTION DATA SHEET PUMP SKIDS' FRAMES
Company Project No.: 02250 & SKID ASSEMBLY + SUF/NSF PREFABRICATION
WORK
Contractor Project No.: 950-2-0151 Company Doc No.:
INSPECTION
H/W/M
SUCCESS no
Hold
scope %
extend
yes
SUCCESS
no
Hold 100%
yes
Monitoring
Project Name: JIGCC Utilities & Common Area - Package 5 Project INSPECTION DATA SHEET PUMP SKIDS' FRAMES
Company Project No.: 02250 & SKID ASSEMBLY + SUF/NSF PREFABRICATION
WORK
Contractor Project No.: 950-2-0151 Company Doc No.:
Inspection and Test Plan (approval required before start the manufacturing as per A A
QA,QC/INSPECTION AND EXPEDITINGREQUIREMENTS FOR VENDOR S02250-00-140-PD-0002 )
Special Processes procedures (welding, welding repair, heat treatment, hydro testing, NDTs, alloy
verification (PMI)) , surface preparation and coating, and in general any procedure to be used for the
inspections to be performed during the execution of the work. (approval required before start the A A
manufacturing)
Welding Dossier ( WPS / PQR / Welding Map) (approval required before start the manufacturing) A A
3. BEFORE MANUFACTURING
175-010800 Pipe: Beveled End, Seamless or Welded, Straight Seam, Stainless Steel Pipe *1 *1
Project Name: JIGCC Utilities & Common Area - Package 5 Project INSPECTION DATA SHEET PUMP SKIDS' FRAMES
Company Project No.: 02250 & SKID ASSEMBLY + SUF/NSF PREFABRICATION
WORK
Contractor Project No.: 950-2-0151 Company Doc No.:
5. FINAL INSPECTION
6. RELEASE
7. DOCUMENTION REVIEW
FOR INFO : The above inspection steps amend the SA-175 forms attached.
Project Name: JIGCC Utilities & Common Area - Package 5 Project INSPECTION DATA SHEET PUMP SKIDS' FRAMES
Company Project No.: 02250 & SKID ASSEMBLY + SUF/NSF PREFABRICATION
WORK
Contractor Project No.: 950-2-0151 Company Doc No.: